Rapid-p0011-scs-qac-itp-3220-0003-itp For Hvac Equipment Installation.pdf

  • Uploaded by: Alif Firdaus
  • 0
  • 0
  • March 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Rapid-p0011-scs-qac-itp-3220-0003-itp For Hvac Equipment Installation.pdf as PDF for free.

More details

  • Words: 3,576
  • Pages: 25
Loading documents preview...
Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAC

ITP

3220

0004

Rev.

Page

0

1/9

INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU

INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION

OWNER Approval: Name: Date (DD-MMM-YY): Signature:

Document Class:

Pages modified under this revision:

0A

1-Nov-17

Re-IFC-Issued For Construction

Alif Firdaus

Ahmad Damanhuri

Ridzuan Zaini

0

20-Oct-17

IFC-Issued For Construction

Alif Firdaus

Ahmad Damanhuri

Ridzuan Zaini

REV.

DATE DD-MMM-YY

STATUS – REVISION MEMO

WRITTEN BY (name &signature)

CHECKED BY (name &signature)

APPROVED BY (name & signature)

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION

PIPES

Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAC

ITP

3220

0004

Rev.

Page

0

2/9

INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU

HOLD’s HOLD No.

REF. §

DESCRIPTION

ACTIONS

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION

PIPES

Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAC

ITP

3220

0004

Rev.

Page

0

3/9

INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU

Table of Contents 1.

PURPOSE ........................................................................................................................................................................ 4

2.

SCOPE .............................................................................................................................................................................. 4

3.

REFERENCE .................................................................................................................................................................. 4

4.

DEFINITION OF INSPECTION POINT ....................................................................................................................... 4

APPENDIX

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION PIPES

Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAC

ITP

3220

0004

Rev.

Page

0

4/9

INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU 1.

PURPOSE This Procedure is prepared for controlling and monitoring Inspection and Test activities of HVAC Refrigeration Pipes for RAPID Package 11 Ethylene Oxide/Ethylene Glycol(EO/EG) PROJECT in ensuring compliance with the project specification and requirements.

2. SCOPE This ITP is applicable to inspection / test activities for HVAC Equipment Installation, which executed by Sub-contractor.

3. REFERENCE  RAPID-FE1-TPX-HVA-DES-0001-0003: Heating, Ventilation And Air Conditioning (HVAC) Design Philosophy  RAPIDFE1 TPX HVA SPN 0001 0001: HVAC Job Specification For Supply  RAPID-P011-SCS-HVA-DWG-3220-00XX: HVAC General Drawings  VENDOR SHOP DRAWINGS

4. DEFINITION OF INSPECTION POINT 4.1 Hold Point (H)

It is an Inspection/test activity on the ITP that requires the presence of the inspecting organizationand/or representative, OWNER. It shall not proceed beyond this point until it has been cleared or waived in writing by Contractor or OWNER. 4.2 Witness Point (W)

This Indicates an inspection/test activity within the ITP that requires the presence of OWNER. It may proceed beyond this point if OWNER has not attended, provided prior and ample notice of the activity has been given to the OWNER.One (1) hour waiting from when the notice is given to Owner is deemed approval to proceed next activities. 4.3 Spot Witness Point(SW)

Spot Witness indicates an Inspection/test activity for ongoing construction processes which will be witnessed on a spot check basis. 4.4 Approval Point (A)

This Indicates a document approval. The CONTRACTOR is allowed to continue work related to the document only after approval of the document by Contractor or OWNER.

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION PIPES

Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAC

ITP

3220

0004

Rev.

Page

0

5/9

INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU 4.5 Review Point (R)

This indicates a document review by Contractor or OWNER. 4.6 Spot Review Point(SR)

Spot Review indicates a document review on a spot check basis. 4.7 Inspection Point (I)

This indicates Inspection, testing and/or generation of certificate, test report as applicable by Subcontractor, and inspection point for Subcontractor shall be 100% inspected by Subcontractor.

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION PIPES

Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAQC

ITP

3220

0003

Rev.

Page

0

6/9

INSPECTION & TEST PLAN FOR HVAC REFRIGERATION PIPES PACKAGE 11 – EOU & EGU

No.

Activity

1.0

MATERIAL RECEIVED

1.1

TRANSPORTATION AND STORAGE

1.1.1

Material Receiving.

Reference

Storage and Preservation.

2.0

FOUNDATION CHECK

2.1

Verify foundation Handover Document

2.2

Center(N/E Coordinates ) & level marking IFC Drawing

Surface Chipping

Frequency

MAR For Equipments

1.1.2

2.5

Acceptance Criteria

IFC Drawing

IFC Drawing

Test Record or Documentation

Participation by Remark Subcon

SC

Owner

Comply with Design & Once for Every Manufacturer’s delivery requirement /No damages

Material Receiving Inspection Report RAPID11-HVACCHK-001 RAPID11-HVACCHK-025

I

W

SW

Comply with Discipline Handover Checklist

Once

Approved Release Notice

R

R

R

Marking on the Foundation

Once

I

W

SW

I

W

Chipped surface shall allow for atleast 25mm of grout under the base plate (Not more than 50mm)

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

RAPID11-HVACCHK-026 Once

SW

Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAQC

ITP

3220

0003

Rev.

Page

0

7/9

INSPECTION & TEST PLAN FOR HVAC REFRIGERATION PIPES PACKAGE 11 – EOU & EGU

Acceptance Criteria

Frequency

2.2

Installation of Air Handling Unit

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

Comply with Design & Manufacturer’s Requirement / No Damages

Installation Complete

2.2

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan Installation of Air Cooled Condensing Unit HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

Comply with Design & Manufacturer’s Requirement / No Damages

2.3

Installation of Split Air Conditioner Unit/FCU

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

2.4

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Installation of Exhaust/ Supply Fan Units Work) HVAC Duct Plan HVAC Duct Enlarged Plan

No.

2.0

Activity

Reference

Test Record or Documentation

Participation by Remark Subcon

SC

Owner

RAPID11-HVACCHK-014

I

W

SW

Installation Complete

RAPID11-HVACCHK-015

I

W

SW

Comply with Design & Manufacturer’s Requirement / No Damages

Installation Complete

RAPID11-HVACCHK-016

I

W

SW

Comply with Design & Manufacturer’s Requirement / No Damages

Installation Complete

RAPID11-HVACCHK-017

I

W

SW

EQUIPMENT INSTALLATION

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAQC

ITP

3220

0003

Rev.

Page

0

8/9

INSPECTION & TEST PLAN FOR HVAC REFRIGERATION PIPES PACKAGE 11 – EOU & EGU

No.

Acceptance Criteria

Frequency

Installation of Gas Tight Damper

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

Comply with Design & Manufacturer’s Requirement / No Damages

Installation Complete

Installation of Fire Damper

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

Comply with Design & Manufacturer’s Requirement / No Damages

Installation of Volume Control Damper/Non-Return Damper/ Pressure Relief Damper/Diffuser and Grilles

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

Installation of Shut Off Damper

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan

Activity

Reference

Test Record or Documentation

Participation by Remark Subcon

SC

Owner

RAPID11-HVACCHK-018

I

W

SW

Installation Complete

RAPID11-HVACCHK-019

I

W

SW

Comply with Design & Manufacturer’s Requirement / No Damages

Installation Complete

RAPID11-HVACCHK-020

I

W

SW

Comply with Design & Manufacturer’s Requirement / No Damages

Installation Complete

RAPID11-HVACCHK-021

I

W

SW

HVAC Piping Plan HVAC Section Shop Drawings

2.5

2.6

2.7

2.8

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

Document Number Project

Package

RAPID

P0011

Originator

SCS

Discipline

Doc. Type

Unit n°

Serial n°

QAQC

ITP

3220

0003

Rev.

Page

0

9/9

INSPECTION & TEST PLAN FOR HVAC REFRIGERATION PIPES PACKAGE 11 – EOU & EGU

No.

Acceptance Criteria

Frequency

Instalation of Blast Valve

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

Comply with Design & Manufacturer’s Requirement / No Damages

Installation Complete

Installation of HVAC Control Panel

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

Comply with Design & Manufacturer’s Requirement / No Damages

Installation of Motor Control Centre

RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

Comply with Design & Manufacturer’s Requirement / No Damages

Activity

Reference

Test Record or Documentation

Participation by Remark Subcon

SC

Owner

RAPID11-HVACCHK-022

I

W

SW

Installation Complete

RAPID11-HVACCHK-023

I

W

SW

Installation Complete

RAPID11-HVACCHK-024

I

W

SW

HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings

2.9

2.10

2.11

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

MATERIAL RECEIVING CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED

INSPECTION ITEM

YES

N/A

REMARKS

NO

 Review Documents for Material Receiving. - IRC (Inspection Release Certificate) - Material Test Reports - Packing list - Approved Vendor List - Catalogue - DWG & Etc  Rotating equipment skid,diver/driven,aux.piping & other component are free from any physical damage  External surface there are no visible damage,deflection and rust.

 Materials shall be stored as per manufacture instruction or project specifications.  Any loose parts and precision parts on the equipment shall be keep properly at site store inside.  Are identification and name plate on the equipment as per data sheet.

 Perform visual inspection of components for compliance with project requirement  Review Documents for Material Receiving. - IRC (Inspection Release Certificate) - Material Test Reports - Packing list - Approved Vendor List - Catalogue - DWG & Etc SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-001

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

STORAGE, HANDLING AND PRESERVATION CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

REMARKS YES

N/A

NO

1) Are identifications and markings intact? 2) Are covers,plugs,and caps intact? 3) Are temporary preservatives and coating intact 4) Any evidence of physical damage 5) Is proper cleanliness being maintained? 6) Are instrument racks energized as specified 7) Evidence of damage to items hit by a fork lift or truck? 8) Any water damage? 9) Is dust and dirt excessive? 10) Are items and materials on cribbing as specified? 11) Any container items broken or leaking? 12) Has storage level been maintained? SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-025

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

FOUNDATION CHECK CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

REMARKS YES

N/A

NO

 Location, orientation, elevation and condition of support foundation conformed to project specification.

 Foundation center (N/E Coordinate) & Level Marking  Top of concrete surface has been roughened by chipping or other mechanical means to exposed sound aggregate.  Concrete surfaces to be grouted shall be cleaned of all laitance, loose particles, grease, curing compound and other foreign matters.

 Enough space to maintain minimum thickness of 25mm to max.50mm for grout.  Top elevation of leveling shims conformed to AFC drawing elevation plan.

 Location, orientation, elevation and condition of support foundation conformed to project specification.  Foundation center (N/E Coordinate) & Level Marking

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-026

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF AIR HANDLING UNIT CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

REMARKS YES

N/A

NO

 Dimensionally check that the Air Handling Section in accordance with latest approved for construction drawings

 Check that all main components are installed in position as shown in the drawing and are correct size / type.



Inspect and ensure access doors properly fitted and operable.



Units internally and externally clean.



Earth bonding completed and correct



Check the secondary drain pan properly fitted and corrected.



Check the tag number and nameplate.



Check no damage to the equipment.

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-014

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF AIR COOLED CONDENSING UNIT CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

YES

N/A

NO

REMARKS

 Dimensionally check that the Air Handling Section in accordance with latest approved for construction drawings.

 Check that all main components are installed in position as shown in the drawing and are correct size / type.

 Inspect and ensure access doors properly fitted and operable..  Units internally and externally clean.  Earth bonding completed and correct  Check the tag number and nameplate.  Check no damage to the equipment.

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-015

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF SPLIT AIR CONDITIONER UNIT/FCU CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

YES

N/A

NO

REMARKS

 Ensure piping insulation and cladding installed as per general HVAC Drawings.

 Indoor Unit Correctly located  Outdoor unit correctly located  Refrigerant Pipe work insulated, secured & covered  Check air filters is cleaned.  Check drain pan is clean  Check the secondary drain pan properly fitted and corrected.  Dimension checked

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-016

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF EXHAUST/ SUPPLY FAN UNITS CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

YES

N/A

NO

REMARKS

 Name plate / Tagging fitted. Details correct to specification and drawings  Installation correct to design and specifications  Impeller rotates freely and clears of impeller housing.  Alignment checked.  Dimension checked  Maintenance access and facilities satisfactory  Exhaust fan to duct connection checked  Exhaust fan clean and in good condition.  Check earth grounding and bonding correct

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-017

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF GAS TIGHT DAMPER CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

YES

N/A

NO

REMARKS

 Name plate / Tagging fitted. Details correct to specification and drawings  Installation correct to design and specifications  Check the air flow direction  Check initial open and close indication of the dampers  Damper blades can be manually open and closed  Damper blade alignment checked  Dimension checked  Maintenance access and facilities satisfactory  Dampers to duct connection checked  Dampers clean and in good condition  Check electrical supply connection into terminal box  Check actuator physical condition SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-018

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF FIRE DAMPER CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

YES

N/A

NO

REMARKS

 Name plate / Tagging fitted. Details correct to specification and drawings  Installation correct to design and specifications  Check the air flow direction  Check initial open and close indication of the dampers  Damper blades can be manually open and closed  Damper blade alignment checked  Dimension checked  Maintenance access and facilities satisfactory  Dampers to duct connection checked  Dampers clean and in good condition  Check pneumatic piping  Check actuator physical condition SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-019

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF VOLUME CONTROL DAMPER/NON-RETURN DAMPER/PRESSURE RELIEF DAMPER/DIFFUSER CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

YES

N/A

NO

REMARKS

 Name plate / Tagging fitted. Details correct to specification and drawings  Installation correct to design and specifications  Check the air flow direction  Check the inlet Damper/Diffuser condition and ensure that it is properly installed.

 Check inlet Damper/Diffuser protection guard.  Test operation of damper by manually opening and closing the damper blade  Dimension checked  Dampers/diffuser to duct connection checked  Dampers/diffuser clean and in good condition

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-020

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF SHUT OFF DAMPER CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

YES

N/A

NO

REMARKS

 Name plate / Tagging fitted. Details correct to specification and drawings  Installation correct to design and specifications  Check the air flow direction  Check initial open and close indication of the dampers.  Damper blades can be manually open and closed  Damper blade alignment checked  Dimension checked  Maintenance access and facilities satisfactory  Dampers to duct connection checked  Dampers clean and in good condition  Check electrical supply connection into terminal box  Check actuator physical condition SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-021

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF BLAST VALVE CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

YES

N/A

NO

REMARKS

 Name plate / Tagging fitted. Details correct to specification and drawings  Installation correct to design and specifications  Check the air flow direction  Check the inlet Blast Valve condition and ensure that it is properly installed.  Dimension checked  Blast Valve s to duct/Wall connection checked  Blast Valve clean and in good condition  Check Louver is fitted on the blast valve

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-022

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF HVAC CONTROL PANEL CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

 Condition – No damage Enclosure, Doors, Panels, Components  Condition – Internal/External Cleanliness  Condition – No missing components/parts  Condition – Gaskets – in place; seals – installed  Condition – Doors fully open not obstructed  Identification – Tag Numbers / Name plate data as per specs/dwgs/datasheet  Support / Mounting – Per Drawings  Support / Mounting – Level/aligned/secure  Support / Mounting – Hardware is correct, lubricated, none missing, tight  Grounding/Earthing/IS Earthing – Continuity / per specs and drawings  Preservation: Lubricated and vapor based inhibitor applied  Preservation – Anti-condensation heaters energized  Mechanical Installation/Operation – MCB, Pushbuttons, etc.  Cable – Clamped and/or secured by correct means / material  Cable – Incoming cable looming is OK  Cable – Bending radius is OK

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

YES

N/A

NO

REMARKS

 Glands – Correct size & type, tight / locknuts tight  Glands – IP washers are installed / Ingress Protection  Conductor – Terminated per drawing with correct size & type terminal lug, crimp and die

 Conductor – Correctly identified  Conductor – Spares terminated and correctly identified  Conductor – Insulation Resistance / Continuity is OK  Blanking Plugs – Fitted to unused cable entries  Test Equipment – Calibration is current

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-023

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG

INSTALLATION OF MOTOR CONTROL CENTR CHECKLIST AREA / LOCATION :

REF. SPEC. / DWG NO. : ITEM

DESCRIPTION

EQUIPMENT NAME MANUFACTURER

INSPECTED INSPECTION ITEM

 Condition – No damage Enclosure, Doors, Panels, Components  Condition – Internal/External Cleanliness  Condition – No missing components/parts  Condition – Gaskets – in place; seals – installed  Condition – Doors fully open not obstructed  Identification – Tag Numbers / Name plate data as per specs/dwgs/datasheet  Support / Mounting – Per Drawings  Support / Mounting – Level/aligned/secure  Support / Mounting – Hardware is correct, lubricated, none missing, tight  Grounding/Earthing – Continuity / per specs and drawings  Preservation: Lubricated and vapor based inhibitor applied  Preservation – Anti-condensation heaters energized  Mechanical Installation/Operation – MCB, Pushbuttons, etc.  Mechanical Installation/Operation – individual lockout devices  Mechanical Installation/Operation – Barriers and Shutters  Bus Bar – Torque Settings per vendor / Specification

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

YES

N/A

NO

REMARKS

 Bus Bar – Ducter test (low Resistance) of all bus-bar joints  Bus Bar – Insulation Resistance Tests  Blanking Plugs – Fitted to unused cable entries  Incoming Transit/Gland Plate sealed (verify again after cable installation is complete)

 Fuses – Type and Size, links are correct & properly installed  Test Equipment – Calibration is current  Service trolleys in place and fully unpacked ready for Static commissioning

SUBCONTRACTOR

CONTRACTOR

COMPANY

SIGNATURE NAME DATE

RAPID 11-HVAC-024

SAMSUNG ENGINEERING CO.,LTD

Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx

Related Documents

Hvac
January 2021 5
Hvac Validation
January 2021 2
Hvac Course
March 2021 0
Hvac Qualification
January 2021 1
Equipment
January 2021 3
Hvac _pq__
January 2021 2

More Documents from "Prem Goel"