Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAC
ITP
3220
0004
Rev.
Page
0
1/9
INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU
INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION
OWNER Approval: Name: Date (DD-MMM-YY): Signature:
Document Class:
Pages modified under this revision:
0A
1-Nov-17
Re-IFC-Issued For Construction
Alif Firdaus
Ahmad Damanhuri
Ridzuan Zaini
0
20-Oct-17
IFC-Issued For Construction
Alif Firdaus
Ahmad Damanhuri
Ridzuan Zaini
REV.
DATE DD-MMM-YY
STATUS – REVISION MEMO
WRITTEN BY (name &signature)
CHECKED BY (name &signature)
APPROVED BY (name & signature)
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION
PIPES
Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAC
ITP
3220
0004
Rev.
Page
0
2/9
INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU
HOLD’s HOLD No.
REF. §
DESCRIPTION
ACTIONS
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION
PIPES
Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAC
ITP
3220
0004
Rev.
Page
0
3/9
INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU
Table of Contents 1.
PURPOSE ........................................................................................................................................................................ 4
2.
SCOPE .............................................................................................................................................................................. 4
3.
REFERENCE .................................................................................................................................................................. 4
4.
DEFINITION OF INSPECTION POINT ....................................................................................................................... 4
APPENDIX
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION PIPES
Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAC
ITP
3220
0004
Rev.
Page
0
4/9
INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU 1.
PURPOSE This Procedure is prepared for controlling and monitoring Inspection and Test activities of HVAC Refrigeration Pipes for RAPID Package 11 Ethylene Oxide/Ethylene Glycol(EO/EG) PROJECT in ensuring compliance with the project specification and requirements.
2. SCOPE This ITP is applicable to inspection / test activities for HVAC Equipment Installation, which executed by Sub-contractor.
3. REFERENCE RAPID-FE1-TPX-HVA-DES-0001-0003: Heating, Ventilation And Air Conditioning (HVAC) Design Philosophy RAPIDFE1 TPX HVA SPN 0001 0001: HVAC Job Specification For Supply RAPID-P011-SCS-HVA-DWG-3220-00XX: HVAC General Drawings VENDOR SHOP DRAWINGS
4. DEFINITION OF INSPECTION POINT 4.1 Hold Point (H)
It is an Inspection/test activity on the ITP that requires the presence of the inspecting organizationand/or representative, OWNER. It shall not proceed beyond this point until it has been cleared or waived in writing by Contractor or OWNER. 4.2 Witness Point (W)
This Indicates an inspection/test activity within the ITP that requires the presence of OWNER. It may proceed beyond this point if OWNER has not attended, provided prior and ample notice of the activity has been given to the OWNER.One (1) hour waiting from when the notice is given to Owner is deemed approval to proceed next activities. 4.3 Spot Witness Point(SW)
Spot Witness indicates an Inspection/test activity for ongoing construction processes which will be witnessed on a spot check basis. 4.4 Approval Point (A)
This Indicates a document approval. The CONTRACTOR is allowed to continue work related to the document only after approval of the document by Contractor or OWNER.
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION PIPES
Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAC
ITP
3220
0004
Rev.
Page
0
5/9
INSPECTION AND TEST PLAN FOR HVAC EQUIPMENT INSTALLATION PACKAGE 11 – EOU & EGU 4.5 Review Point (R)
This indicates a document review by Contractor or OWNER. 4.6 Spot Review Point(SR)
Spot Review indicates a document review on a spot check basis. 4.7 Inspection Point (I)
This indicates Inspection, testing and/or generation of certificate, test report as applicable by Subcontractor, and inspection point for Subcontractor shall be 100% inspected by Subcontractor.
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docxREFRIGERATION PIPES
Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAQC
ITP
3220
0003
Rev.
Page
0
6/9
INSPECTION & TEST PLAN FOR HVAC REFRIGERATION PIPES PACKAGE 11 – EOU & EGU
No.
Activity
1.0
MATERIAL RECEIVED
1.1
TRANSPORTATION AND STORAGE
1.1.1
Material Receiving.
Reference
Storage and Preservation.
2.0
FOUNDATION CHECK
2.1
Verify foundation Handover Document
2.2
Center(N/E Coordinates ) & level marking IFC Drawing
Surface Chipping
Frequency
MAR For Equipments
1.1.2
2.5
Acceptance Criteria
IFC Drawing
IFC Drawing
Test Record or Documentation
Participation by Remark Subcon
SC
Owner
Comply with Design & Once for Every Manufacturer’s delivery requirement /No damages
Material Receiving Inspection Report RAPID11-HVACCHK-001 RAPID11-HVACCHK-025
I
W
SW
Comply with Discipline Handover Checklist
Once
Approved Release Notice
R
R
R
Marking on the Foundation
Once
I
W
SW
I
W
Chipped surface shall allow for atleast 25mm of grout under the base plate (Not more than 50mm)
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
RAPID11-HVACCHK-026 Once
SW
Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAQC
ITP
3220
0003
Rev.
Page
0
7/9
INSPECTION & TEST PLAN FOR HVAC REFRIGERATION PIPES PACKAGE 11 – EOU & EGU
Acceptance Criteria
Frequency
2.2
Installation of Air Handling Unit
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
Comply with Design & Manufacturer’s Requirement / No Damages
Installation Complete
2.2
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan Installation of Air Cooled Condensing Unit HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
Comply with Design & Manufacturer’s Requirement / No Damages
2.3
Installation of Split Air Conditioner Unit/FCU
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
2.4
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Installation of Exhaust/ Supply Fan Units Work) HVAC Duct Plan HVAC Duct Enlarged Plan
No.
2.0
Activity
Reference
Test Record or Documentation
Participation by Remark Subcon
SC
Owner
RAPID11-HVACCHK-014
I
W
SW
Installation Complete
RAPID11-HVACCHK-015
I
W
SW
Comply with Design & Manufacturer’s Requirement / No Damages
Installation Complete
RAPID11-HVACCHK-016
I
W
SW
Comply with Design & Manufacturer’s Requirement / No Damages
Installation Complete
RAPID11-HVACCHK-017
I
W
SW
EQUIPMENT INSTALLATION
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAQC
ITP
3220
0003
Rev.
Page
0
8/9
INSPECTION & TEST PLAN FOR HVAC REFRIGERATION PIPES PACKAGE 11 – EOU & EGU
No.
Acceptance Criteria
Frequency
Installation of Gas Tight Damper
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
Comply with Design & Manufacturer’s Requirement / No Damages
Installation Complete
Installation of Fire Damper
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
Comply with Design & Manufacturer’s Requirement / No Damages
Installation of Volume Control Damper/Non-Return Damper/ Pressure Relief Damper/Diffuser and Grilles
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
Installation of Shut Off Damper
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan
Activity
Reference
Test Record or Documentation
Participation by Remark Subcon
SC
Owner
RAPID11-HVACCHK-018
I
W
SW
Installation Complete
RAPID11-HVACCHK-019
I
W
SW
Comply with Design & Manufacturer’s Requirement / No Damages
Installation Complete
RAPID11-HVACCHK-020
I
W
SW
Comply with Design & Manufacturer’s Requirement / No Damages
Installation Complete
RAPID11-HVACCHK-021
I
W
SW
HVAC Piping Plan HVAC Section Shop Drawings
2.5
2.6
2.7
2.8
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
Document Number Project
Package
RAPID
P0011
Originator
SCS
Discipline
Doc. Type
Unit n°
Serial n°
QAQC
ITP
3220
0003
Rev.
Page
0
9/9
INSPECTION & TEST PLAN FOR HVAC REFRIGERATION PIPES PACKAGE 11 – EOU & EGU
No.
Acceptance Criteria
Frequency
Instalation of Blast Valve
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
Comply with Design & Manufacturer’s Requirement / No Damages
Installation Complete
Installation of HVAC Control Panel
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
Comply with Design & Manufacturer’s Requirement / No Damages
Installation of Motor Control Centre
RAPID-P0011-0007-HVA-MST3220-00188 (HVAC Equipment Work) HVAC Duct Plan HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
Comply with Design & Manufacturer’s Requirement / No Damages
Activity
Reference
Test Record or Documentation
Participation by Remark Subcon
SC
Owner
RAPID11-HVACCHK-022
I
W
SW
Installation Complete
RAPID11-HVACCHK-023
I
W
SW
Installation Complete
RAPID11-HVACCHK-024
I
W
SW
HVAC Duct Enlarged Plan HVAC Piping Plan HVAC Section Shop Drawings
2.9
2.10
2.11
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
MATERIAL RECEIVING CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED
INSPECTION ITEM
YES
N/A
REMARKS
NO
Review Documents for Material Receiving. - IRC (Inspection Release Certificate) - Material Test Reports - Packing list - Approved Vendor List - Catalogue - DWG & Etc Rotating equipment skid,diver/driven,aux.piping & other component are free from any physical damage External surface there are no visible damage,deflection and rust.
Materials shall be stored as per manufacture instruction or project specifications. Any loose parts and precision parts on the equipment shall be keep properly at site store inside. Are identification and name plate on the equipment as per data sheet.
Perform visual inspection of components for compliance with project requirement Review Documents for Material Receiving. - IRC (Inspection Release Certificate) - Material Test Reports - Packing list - Approved Vendor List - Catalogue - DWG & Etc SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-001
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
STORAGE, HANDLING AND PRESERVATION CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
REMARKS YES
N/A
NO
1) Are identifications and markings intact? 2) Are covers,plugs,and caps intact? 3) Are temporary preservatives and coating intact 4) Any evidence of physical damage 5) Is proper cleanliness being maintained? 6) Are instrument racks energized as specified 7) Evidence of damage to items hit by a fork lift or truck? 8) Any water damage? 9) Is dust and dirt excessive? 10) Are items and materials on cribbing as specified? 11) Any container items broken or leaking? 12) Has storage level been maintained? SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-025
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
FOUNDATION CHECK CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
REMARKS YES
N/A
NO
Location, orientation, elevation and condition of support foundation conformed to project specification.
Foundation center (N/E Coordinate) & Level Marking Top of concrete surface has been roughened by chipping or other mechanical means to exposed sound aggregate. Concrete surfaces to be grouted shall be cleaned of all laitance, loose particles, grease, curing compound and other foreign matters.
Enough space to maintain minimum thickness of 25mm to max.50mm for grout. Top elevation of leveling shims conformed to AFC drawing elevation plan.
Location, orientation, elevation and condition of support foundation conformed to project specification. Foundation center (N/E Coordinate) & Level Marking
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-026
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF AIR HANDLING UNIT CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
REMARKS YES
N/A
NO
Dimensionally check that the Air Handling Section in accordance with latest approved for construction drawings
Check that all main components are installed in position as shown in the drawing and are correct size / type.
Inspect and ensure access doors properly fitted and operable.
Units internally and externally clean.
Earth bonding completed and correct
Check the secondary drain pan properly fitted and corrected.
Check the tag number and nameplate.
Check no damage to the equipment.
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-014
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF AIR COOLED CONDENSING UNIT CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
YES
N/A
NO
REMARKS
Dimensionally check that the Air Handling Section in accordance with latest approved for construction drawings.
Check that all main components are installed in position as shown in the drawing and are correct size / type.
Inspect and ensure access doors properly fitted and operable.. Units internally and externally clean. Earth bonding completed and correct Check the tag number and nameplate. Check no damage to the equipment.
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-015
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF SPLIT AIR CONDITIONER UNIT/FCU CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
YES
N/A
NO
REMARKS
Ensure piping insulation and cladding installed as per general HVAC Drawings.
Indoor Unit Correctly located Outdoor unit correctly located Refrigerant Pipe work insulated, secured & covered Check air filters is cleaned. Check drain pan is clean Check the secondary drain pan properly fitted and corrected. Dimension checked
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-016
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF EXHAUST/ SUPPLY FAN UNITS CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
YES
N/A
NO
REMARKS
Name plate / Tagging fitted. Details correct to specification and drawings Installation correct to design and specifications Impeller rotates freely and clears of impeller housing. Alignment checked. Dimension checked Maintenance access and facilities satisfactory Exhaust fan to duct connection checked Exhaust fan clean and in good condition. Check earth grounding and bonding correct
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-017
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF GAS TIGHT DAMPER CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
YES
N/A
NO
REMARKS
Name plate / Tagging fitted. Details correct to specification and drawings Installation correct to design and specifications Check the air flow direction Check initial open and close indication of the dampers Damper blades can be manually open and closed Damper blade alignment checked Dimension checked Maintenance access and facilities satisfactory Dampers to duct connection checked Dampers clean and in good condition Check electrical supply connection into terminal box Check actuator physical condition SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-018
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF FIRE DAMPER CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
YES
N/A
NO
REMARKS
Name plate / Tagging fitted. Details correct to specification and drawings Installation correct to design and specifications Check the air flow direction Check initial open and close indication of the dampers Damper blades can be manually open and closed Damper blade alignment checked Dimension checked Maintenance access and facilities satisfactory Dampers to duct connection checked Dampers clean and in good condition Check pneumatic piping Check actuator physical condition SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-019
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF VOLUME CONTROL DAMPER/NON-RETURN DAMPER/PRESSURE RELIEF DAMPER/DIFFUSER CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
YES
N/A
NO
REMARKS
Name plate / Tagging fitted. Details correct to specification and drawings Installation correct to design and specifications Check the air flow direction Check the inlet Damper/Diffuser condition and ensure that it is properly installed.
Check inlet Damper/Diffuser protection guard. Test operation of damper by manually opening and closing the damper blade Dimension checked Dampers/diffuser to duct connection checked Dampers/diffuser clean and in good condition
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-020
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF SHUT OFF DAMPER CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
YES
N/A
NO
REMARKS
Name plate / Tagging fitted. Details correct to specification and drawings Installation correct to design and specifications Check the air flow direction Check initial open and close indication of the dampers. Damper blades can be manually open and closed Damper blade alignment checked Dimension checked Maintenance access and facilities satisfactory Dampers to duct connection checked Dampers clean and in good condition Check electrical supply connection into terminal box Check actuator physical condition SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-021
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF BLAST VALVE CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
YES
N/A
NO
REMARKS
Name plate / Tagging fitted. Details correct to specification and drawings Installation correct to design and specifications Check the air flow direction Check the inlet Blast Valve condition and ensure that it is properly installed. Dimension checked Blast Valve s to duct/Wall connection checked Blast Valve clean and in good condition Check Louver is fitted on the blast valve
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-022
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF HVAC CONTROL PANEL CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
Condition – No damage Enclosure, Doors, Panels, Components Condition – Internal/External Cleanliness Condition – No missing components/parts Condition – Gaskets – in place; seals – installed Condition – Doors fully open not obstructed Identification – Tag Numbers / Name plate data as per specs/dwgs/datasheet Support / Mounting – Per Drawings Support / Mounting – Level/aligned/secure Support / Mounting – Hardware is correct, lubricated, none missing, tight Grounding/Earthing/IS Earthing – Continuity / per specs and drawings Preservation: Lubricated and vapor based inhibitor applied Preservation – Anti-condensation heaters energized Mechanical Installation/Operation – MCB, Pushbuttons, etc. Cable – Clamped and/or secured by correct means / material Cable – Incoming cable looming is OK Cable – Bending radius is OK
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
YES
N/A
NO
REMARKS
Glands – Correct size & type, tight / locknuts tight Glands – IP washers are installed / Ingress Protection Conductor – Terminated per drawing with correct size & type terminal lug, crimp and die
Conductor – Correctly identified Conductor – Spares terminated and correctly identified Conductor – Insulation Resistance / Continuity is OK Blanking Plugs – Fitted to unused cable entries Test Equipment – Calibration is current
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-023
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
PETRONAS RAPID PROJECT PACKAGE 11 – EO & EG
INSTALLATION OF MOTOR CONTROL CENTR CHECKLIST AREA / LOCATION :
REF. SPEC. / DWG NO. : ITEM
DESCRIPTION
EQUIPMENT NAME MANUFACTURER
INSPECTED INSPECTION ITEM
Condition – No damage Enclosure, Doors, Panels, Components Condition – Internal/External Cleanliness Condition – No missing components/parts Condition – Gaskets – in place; seals – installed Condition – Doors fully open not obstructed Identification – Tag Numbers / Name plate data as per specs/dwgs/datasheet Support / Mounting – Per Drawings Support / Mounting – Level/aligned/secure Support / Mounting – Hardware is correct, lubricated, none missing, tight Grounding/Earthing – Continuity / per specs and drawings Preservation: Lubricated and vapor based inhibitor applied Preservation – Anti-condensation heaters energized Mechanical Installation/Operation – MCB, Pushbuttons, etc. Mechanical Installation/Operation – individual lockout devices Mechanical Installation/Operation – Barriers and Shutters Bus Bar – Torque Settings per vendor / Specification
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx
YES
N/A
NO
REMARKS
Bus Bar – Ducter test (low Resistance) of all bus-bar joints Bus Bar – Insulation Resistance Tests Blanking Plugs – Fitted to unused cable entries Incoming Transit/Gland Plate sealed (verify again after cable installation is complete)
Fuses – Type and Size, links are correct & properly installed Test Equipment – Calibration is current Service trolleys in place and fully unpacked ready for Static commissioning
SUBCONTRACTOR
CONTRACTOR
COMPANY
SIGNATURE NAME DATE
RAPID 11-HVAC-024
SAMSUNG ENGINEERING CO.,LTD
Electronic Filename: RAPID-P0011-SCS-QAC-ITP-3220-0003-ITP For HVAC Equipment Installation.docx