RAWMILL-1 1ST CHAMBER & LCD PLATES REPLACEMENT WORK ID
Task Name
Duration 18 days
% Complete 38%
1
RAWMILL-1 1ST CHAMBER & LCD PLATES REPLACEMENT WORK
Start Sun 22-06-14
F
S
22 Jun '14 S M T
2
Mill Inlet chute & mill door removal
1 day
100%
Sun 22-06-14
100%
3
Grinding media unloading
1 day
100%
Sun 22-06-14
100%
4
Existing shell liners removal and shifting wor
4 days
90%
Mon 23-06-14
5
New shell liners installation work
8 days
30%
Fri 27-06-14
6
New Rubber plugs fixing work
2 days
0%
Thu 03-07-14
7
Existing LCD grate plates & back side plates removal and shifting work
1.5 days
0%
Sat 05-07-14
8
New LCD grate plates & backside plates installation work
1.5 days
0%
Sun 06-07-14
9
Grinding media loading in both the chamber
1 day
0%
Tue 08-07-14
10
Mill Inlet chute & mill door fixing work
1 day
0%
Wed 09-07-14
Project: COAL FEEDING PROJECT Date: Wed 02-07-14
W
T
F
S
29 Jun '14 S M T 38%
W
T
F
S
06 Jul '14 S M
T
W
90% 30% 0% 0% 0% 0% 0%
Task
Milestone
External Tasks
Split
Summary
External Milestone
Progress
Project Summary
Deadline Page 1