RAWMILL-1 1ST CHAMBER & LCD PLATES REPLACEMENT WORK ID

Task Name

Duration 18 days

% Complete 38%

1

RAWMILL-1 1ST CHAMBER & LCD PLATES REPLACEMENT WORK

Start Sun 22-06-14

F

S

22 Jun '14 S M T

2

Mill Inlet chute & mill door removal

1 day

100%

Sun 22-06-14

100%

3

Grinding media unloading

1 day

100%

Sun 22-06-14

100%

4

Existing shell liners removal and shifting wor

4 days

90%

Mon 23-06-14

5

New shell liners installation work

8 days

30%

Fri 27-06-14

6

New Rubber plugs fixing work

2 days

0%

Thu 03-07-14

7

Existing LCD grate plates & back side plates removal and shifting work

1.5 days

0%

Sat 05-07-14

8

New LCD grate plates & backside plates installation work

1.5 days

0%

Sun 06-07-14

9

Grinding media loading in both the chamber

1 day

0%

Tue 08-07-14

10

Mill Inlet chute & mill door fixing work

1 day

0%

Wed 09-07-14

Project: COAL FEEDING PROJECT Date: Wed 02-07-14

W

T

F

S

29 Jun '14 S M T 38%

W

T

F

S

06 Jul '14 S M

T

W

90% 30% 0% 0% 0% 0% 0%

Task

Milestone

External Tasks

Split

Summary

External Milestone

Progress

Project Summary

Deadline Page 1