VCE Summer Internship Program 2020 Smart Task 04
Project Topic : Project Finance - Modeling and Analysis INSTRUCTIONS
✔ Interns need to prepare a final internship report. The formatting, content and the analysis of the report should be upto corporate standards. ✔ The intern needs to go through the Industry Case Problem Statement and select ONE project from it. That project will be the topic and title of the final report. ✔ Apart from making one report, there is NO other task in this module. Your evaluation of this internship will be done on the report and hence make it in a professional way.
PREPARATION OF CORPORATE STANDARD REPORT
1. The report should be in the A4 page ONLY, prepared on MS Word / Google Docs / WPS. Reports in the form of presentation will NOT be accepted. 2. The report SHOULD be well formatted and MUST have all the features of a good report. Such as Cover Page, Executive Summary, Table of Contents, List of Figures, List of Tables, Footnote, Endnote, Justified Text, Bibliography and References. Please check the Sample Report for reference. 3. Sample Report:- https://drive.google.com/open?id=1pK-UMj3KJGUzkSZ7LRGiNMX_mNM_f2Bw 4. Report SHOULD have pictures, graphs, tables and charts etc showing the analysis done during the project. Having ONLY text in the report is not acceptable. 5. Report SHOULD contain 15-30 pages, including all pages. 6. The content of the report SHOULD have “Introduction” as first chapter and “Conclusion” as last chapter. The middle chapters can be chosen as per the project title and analysis done. 7. In the executive summary, the interns should mention about VCE and the experience about this internship. There is NO need to mention about VCE anywhere else in the report. 8. The content of the report SHOULD be in your words, so that you can take the reference of this report in future. 9. Your quality of report will be the main deciding factor for evaluating your work in this internship. We will provide an internship certificate, letter of recommendation and select the best interns as per the report submitted by the interns. So, focus and prepare it as per the instructions.
https://techvardhan.com/
VCE Summer Internship Program 2020 Smart Task 04
INDUSTRY CASE PROBLEM STATEMENT M/s Vardhan Consulting Engineers “VCE” is a management consulting firm, which provides consultancy to energy and infrastructure developers to raise debt and equity for their projects. In terms of project finance (non-recourse debt) and private equity. For doing this the financial analysts and consultants at VCE prepare financial models of the projects and perform the analysis and figure out the Equity IRR, DSCR for the project. As an intern of VCE, we would like you to help some of our clients by preparing financial model and report on different cases (you need to select ONE case only). Instructions to prepare the Financial Model A. In this task every intern needs to select ONLY ONE case from the list. B. Interns needs to take appropriate assumptions ( What so ever required) to finish the analysis. The details and the results of the analysis should be mentioned in the report submitted by the intern. C. The financial model needs to be prepared in MS Excel. Hence, the .xls file of the financial model is required to be submitted separately. D. Submission in any other format such as PDF or DOC is NOT accepted. The candidate can take reference from the financial model provided in Module 2. E. The financial model should have four sheets, Revenue, Cost, FinFlows and Debt. F. This task should be submitted directly through email to
[email protected] but the report should be submitted through the link.
CASE-01
Project Title : Financial Modeling and Analysis of 10 MW Solar/Wind Power Project in Porbandar, Gujarat IN Techvardhan Power Pvt. Ltd (Any Company) “CLIENT” has signed a PPA for 25 years with GUVNL for a 10 MW Solar PV / Wind Power Plant at a fixed tariff of Rs. 3.50 / kWh. The project location is in Porbandar Gujarat, India. They are expecting a net annual energy production of 18 Million kWh / year with a degradation of 1% per annum. The expected CapEx is Rs. 3 Crore / MW and OpEx is Rs. 30 Lacs / per annum for the whole plant. They are seeking a non-recourse debt (project financing) with 70:30 as D/E ratio from leading commercial banks in India as a 12 years (maximum) term loan. Please prepare a financial model and analyse the cost, revenue and debt repayment along with finflow / cash flow analysis. Calculate equity IRR and DSCR.
https://techvardhan.com/
VCE Summer Internship Program 2020 Smart Task 04
CASE-02
Project Title : Financial Modeling and Analysis of 20 TPD Pyrolysis Project in Pune, Maharashtra IN
Techvardhan Energy Pvt. Ltd (Any Company) “CLIENT” has signed a long term FSA with a large industrial player for supplying refined pyrolysis oil of 10,000 LPD at a rate of Rs. 15 per Litre. They want to set up a 20 TPD pyrolysis plant near Pune MH.
The expected CapEx is Rs. 10 Crore and OpEx is Rs. 2 Crore / per annum for the whole project.
They are seeking a non-recourse debt (project financing) with 70:30 as D/E ratio from leading commercial banks in India as a 12 years term loan.
Please prepare a financial model and analyse the cost, revenue and debt repayment along with finflow / cash flow analysis. Calculate equity IRR and DSCR.
CASE-03
Project Title : Financial Modeling and Analysis of 50 Flats Housing Project in Gurgaon, Haryana IN
Techvardhan Infra Pvt. Ltd (Any Company) “CLIENT” has acquired a piece of land near Gurugram HR and wants to develop it as a residential building having 50 flats of 900 sq. ft each.
They are expecting to sell the flats at a rate of Rs. 4000 / sq.ft. The expected CapEx is Rs. 8 Crore and OpEx is Rs. 50 Lacs / per annum for the whole project.
They are seeking a non-recourse debt (project financing) with 70:30 as D/E ratio from leading commercial banks in India as a 12 years term loan.
Please prepare a financial model and analyse the cost, revenue and debt repayment along with finflow / cash flow analysis. Calculate equity IRR and DSCR.
CASE-04
Project Title : Financial Modeling and Analysis of PPP based Airport Development Project in Ranchi, JH
Techvardhan Infra Pvt. Ltd (Any Company) “CLIENT” has been alloted a project of building and operating (for 20 years) a new commercial airport in Ranchi, JH. They can charge different charges to the airlines through their Schedule of Charges. The charges were eventually paid by the passengers which roughly calculated as Rs. 500 per passenger.
They are expecting to have a passenger traffic of 1 Million with an increase of 5% every year. The expected CapEx is Rs. 100 Crore and OpEx is Rs. 25 Crores / per annum for the whole airport.
https://techvardhan.com/
VCE Summer Internship Program 2020 Smart Task 04
They are seeking a non-recourse debt (project financing) with 70:30 as D/E ratio from leading commercial banks in India as a 12 years term loan.
Please prepare a financial model and analyse the cost, revenue and debt repayment along with finflow / cash flow analysis. Calculate equity IRR and DSCR.
CASE-05
Project Title : Financial Modeling and Analysis of PPP based Expressway Project in Hyderabad, TN
Techvardhan Infra Pvt. Ltd (Any Company) “CLIENT” has been alloted a project of building and operating (for 20 years) a new expressway between Hyderabad and Anantapur AP. They can charge different charges to the vehicles using the expressway through their Schedule of Charges, which is averagely calculated as Rs. 160 per vehicle.
They are expecting to have a vehicle traffic of 10000 vehicles per day with an increase of 5% every year. The expected CapEx is Rs. 200 Crore and OpEx is Rs. 28 Crores / per annum for the whole airport.
They are seeking a non-recourse debt (project financing) with 70:30 as D/E ratio from leading commercial banks in India as a 12 years term loan.
Please prepare a financial model and analyse the cost, revenue and debt repayment along with finflow / cash flow analysis. Calculate equity IRR and DSCR.
CASE-06
Project Title : Lender's Analysis of Project Financial Cash Flows and Risk Assessment of Infrastructure Projects.
Techvardhan Infra Bank Ltd (Any Company) “CLIENT” is a bank who want to provide Non-Recourse Debt as per their policy. They want your help to analyse the financial models, cost break up and revenue realization sheets and make a credit worthiness report on any proposed infrastructure project for project financing. Take the example of any infrastructure project from the above and create a credit worthiness report of the project. Please perform a risk assessment also and advise the bank if it is worthy to fund or not as per the financial model.
*** https://techvardhan.com/