Unit Cost Analysis/price Breakdown Lged, Bangladesh

  • Uploaded by: Mohaiminul Karim
  • 0
  • 0
  • January 2021
  • PDF

This document was uploaded by user and they confirmed that they have the permission to share it. If you are author or own the copyright of this book, please report to us by using this DMCA report form. Report DMCA


Overview

Download & View Unit Cost Analysis/price Breakdown Lged, Bangladesh as PDF for free.

More details

  • Words: 674,793
  • Pages: 2,994
Loading documents preview...
Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Chapter - 2 : Earth Works in Road Embankment 2.01.1

C&G: Clearing and grubbing by removal and disposal of everything above ground level including overhanging branches, removing of all foundation stumps, embedded logs, tree roots and other material either to a depth of 0.3m below the proposed surface elevation or to the level as shown on the drawing, disposing of all materials resulting from clearing and grubbing at a safe distance, etc. all complete as per direction of the E-I-C.

sqm

Sardar

0.0010

day

800.00

0.80

Ordinary Labour

0.0200

day

370.00

7.40 8.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9.20

VAT

6% of Total

IT

4% of Total

0.61 0.41 Total:

2.01.2

G&RS: Grubbing by removal of all foundation, stumps, embedded logs, trees, roots and other materials up to a depth of 1m or as per drawing, etc. all complete as per direction of the E-I-C.

2.01.2.

Unknown...

Note : Rates of all items should be inclusive of all supply and carriage.

10.22

LS

Page: 1 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

2.02.1

EFW: Earth filling work by manual labour with specified soil in any type of embankment and bridge approaches including cutting, carrying, filling, and compacting to 85% maximum dry density at optimum moisture content, with reference to laboratory density test AAHSTO standard hammer by throwing earth in layers not more than 150mm in each layer in proper alignment, grade, camber and side slope in all types of soil other than rocky, gravelly and slushy including clod breaking to a maximum size of 100mm, benching not more than 300mm vertical and 600mm horizontal steps along the sides while widening any embankment, etc. all complete as per direction of the E-IC. Earth is to be borrowed from the road side for all lead. Payment will be made on compacted volume. (compaction will be done by the contractor/LCS worker with approved equipment, including all ancillary charges for compaction and testing)

2.02.1.1

Initial lift up to 1.50 m from the toe of embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Sardar

0.0300

day

800.00

24.00

Ordinary Labour

0.2500

day

370.00

92.50 116.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

118.83

10% Profit ( Add 10% on Subtotal-B) :

130.71

VAT

6% of Total

IT

4% of Total

8.71 5.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

145.24

Page: 2 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.02.1.2

Detailed Analysis Brief Description of Item 2 Up to 2.50m lift from the toe of embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Sardar

0.0300

day

800.00

24.00

Ordinary Labour

0.3000

day

370.00

111.00 135.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

137.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

151.47

VAT

6% of Total

10.10

IT

4% of Total

6.73 Total:

Up to 3.50m lift from the toe of embankment

168.30

cum Sardar

0.0300

day

800.00

24.00

Ordinary Labour

0.3500

day

370.00

129.50 153.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

156.57

10% Profit ( Add 10% on Subtotal-B) :

172.23

VAT

6% of Total

IT

4% of Total

11.48 7.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8

cum

Subtotal-A:

2.02.1.3

Amount

191.36

Page: 3 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.02.1.4

Detailed Analysis Brief Description of Item 2 Up to 4.50m lift from the toe of embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Sardar

0.0300

day

800.00

24.00

Ordinary Labour

0.4100

day

370.00

151.70 175.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

179.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

197.14

VAT

6% of Total

13.14

IT

4% of Total

8.76 Total:

Up to 5.50m lift from the toe of embankment

219.04

cum Sardar

0.0300

day

800.00

24.00

Ordinary Labour

0.4800

day

370.00

177.60 201.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

205.63

10% Profit ( Add 10% on Subtotal-B) :

226.20

VAT

6% of Total

IT

4% of Total

15.08 10.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8

cum

Subtotal-A:

2.02.1.5

Amount

251.33

Page: 4 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.02.1.6

Detailed Analysis Brief Description of Item 2 Up to 6.50m lift from the toe of embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Sardar

0.0300

day

800.00

24.00

Ordinary Labour

0.5400

day

370.00

199.80 223.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

228.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

251.10

VAT

6% of Total

16.74

IT

4% of Total

11.16 Total:

Up to 7.50m lift from the toe of embankment

279.00

cum Sardar

0.0300

day

800.00

24.00

Ordinary Labour

0.6100

day

370.00

225.70 249.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

254.69

10% Profit ( Add 10% on Subtotal-B) :

280.16

VAT

6% of Total

IT

4% of Total

18.68 12.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8

cum

Subtotal-A:

2.02.1.7

Amount

311.29

Page: 5 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

2.02.2

EFW(AE): Earth filling work with specified soil in any type of embankment, Earth shall be arranged by the contractor's own cost including royalty, cutting, carrying, filling and compacting to 85%/95%/98% maximum dry density at optimum moisture content, with reference to laboratory density test AAHSTO standard hammer by throwing earth in layers not more than 150mm in each layer in proper alignment, grade, camber and side slope in all types of soil except rocky, gravelly and slushy including benching not more than 300mm in vertical and 600mm in horizontal steps along the sides while widening any embankment with clod breaking to maximum size of 100mm, benching the side slopes, removing roots and stumps of trees of girth upto 200mm, stripping/ ploughing the base of embankment and borrow pit area, dug bailing, clearing jungles, bail out of water, rough dressing including 150mm cambering at the centre of crest with all leads and lifts complete (compaction will be done by the contractor with approved equipment including all ancillary charges for compaction and testing) as per direction of Engineer in charge. Payment will be made on compacted volume.

2.02.2.01

85% Compaction

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Royalty of Earth

1.1200

m3

25.00

28.00

Sardar

0.0040

day

800.00

3.20

Ordinary Labour

0.3500

day

370.00

129.50 160.70

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

163.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

180.31

VAT

6% of Total

12.02

IT

4% of Total

8.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

200.34

Page: 6 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 2.02.2.02

2 95% Compaction

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Royalty of Earth

1.1800

m3

25.00

29.50

Sardar

0.0040

day

800.00

3.20

Ordinary Labour

0.3200

day

370.00

118.40

H.C. of Vibratory Road Roller (8-10 ton)

0.0070

day

3000.00

21.00

Diesel

0.3000

liter

68.00

20.40

Lubricant

0.0150

liter

220.00

3.30 195.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

199.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

219.69

VAT

6% of Total

IT

4% of Total

14.65 9.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

244.10

Page: 7 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 2.02.2.03

2 98% Compaction

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Royalty of Earth

1.2500

m3

25.00

31.25

Sardar

0.0040

day

800.00

3.20

Ordinary Labour

0.3200

day

370.00

118.40

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00

Diesel

0.4000

liter

68.00

27.20

Lubricant

0.0200

liter

220.00

4.40 211.45

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

215.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

237.25

VAT

6% of Total

IT

4% of Total

15.82 10.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

263.61

Page: 8 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

2.02.3

EFW(CE): Earth filling work with specified soil in any type of embankment, Earth shall be carried by truck/boat or any other means, supplied at contractor's own cost including royalty, cutting, carrying, filling and compacting to 85%/95%/98% maximum dry density at optimum moisture content, with reference to laboratory density test AAHSTO standard hammer by throwing earth in layers not more than150mm in proper alignment, grade, camber and side slope in all types of soil except rocky, gravelly and slushy including benching not more than 300mm in vertical and 600mm in horizontal steps along the sides while widening any embankment, with clod breaking to maximum size of 100mm, benching the side slopes, removing roots and stumps of trees of girth upto 200mm, stripping/ ploughing the base of embankment and borrow pit area, dug bailing, clearing jungles, bail out of water, rough dressing including 150mm cambering at the centre of crest with all leads and lifts complete (compaction will be done by the contractor with approved equipment including all ancillary charges for compaction and testing) as per direction of Engineer in charge. Payment will be made on compacted volume. The item is applicable when earth is supplied and arranged by the contractor from a distance beyond 200m from the end of right of way.

2.02.3.01

Outside municipal area, 85% Compaction

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Royalty of Earth (Outside Municipal Area)

1.1200

m3

35.00

39.20

Ordinary Labour

0.3500

day

370.00

129.50

Sardar

0.0040

day

800.00

3.20

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00 211.90

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

216.14

10% Profit ( Add 10% on Subtotal-B) :

237.75

VAT

6% of Total

15.85

IT

4% of Total

10.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

264.17

Page: 9 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.02.3.02

Detailed Analysis Brief Description of Item 2 Outside municipal area, 95% Compaction

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Royalty of Earth (Outside Municipal Area)

1.1800

m3

35.00

41.30

Ordinary Labour

0.3200

day

370.00

118.40

Sardar

0.0040

day

800.00

3.20

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00

Diesel

0.3000

liter

68.00

20.40

Lubricant

0.0150

liter

220.00

3.30

H.C. of Vibratory Road Roller (8-10 ton)

0.0070

day

3000.00

21.00 247.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

252.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

277.81

VAT

6% of Total

IT

4% of Total

18.52 12.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

308.67

Page: 10 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.02.3.03

Detailed Analysis Brief Description of Item 2 Outside municipal area, 98% Compaction

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Royalty of Earth (Outside Municipal Area)

1.2500

m3

35.00

43.75

Ordinary Labour

0.3200

day

370.00

118.40

Sardar

0.0040

day

800.00

3.20

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00

Diesel

0.3500

liter

68.00

23.80

Lubricant

0.0200

liter

220.00

4.40

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00 260.55

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

265.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

292.34

VAT

6% of Total

IT

4% of Total

19.49 12.99 Total:

2.02.3.04

Within municipal area, 85% Compaction

cum Royalty of Earth (Within Municipal Area)

1.1200

m3

50.00

56.00

Ordinary Labour

0.3500

day

370.00

129.50

Sardar

0.0040

day

800.00

3.20

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00 228.70

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

233.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

256.60

VAT

6% of Total

IT

4% of Total

17.11 11.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

324.82

285.11 Page: 11 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.02.3.05

Detailed Analysis Brief Description of Item 2 Within municipal area, 95% Compaction

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Royalty of Earth (Within Municipal Area)

1.1800

m3

50.00

59.00

Ordinary Labour

0.3200

day

370.00

118.40

Sardar

0.0040

day

800.00

3.20

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00

Diesel

0.3000

liter

68.00

20.40

Lubricant

0.0150

liter

220.00

3.30

H.C. of Vibratory Road Roller (8-10 ton)

0.0070

day

3000.00

21.00 265.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

270.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

297.67

VAT

6% of Total

IT

4% of Total

19.84 13.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

330.74

Page: 12 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.02.3.06

Detailed Analysis Brief Description of Item 2 Within municipal area, 98% Compaction

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Royalty of Earth (Within Municipal Area)

1.2500

m3

50.00

62.50

Ordinary Labour

0.3200

day

370.00

118.40

Sardar

0.0040

day

800.00

3.20

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00

Diesel

0.3500

liter

68.00

23.80

Lubricant

0.0200

liter

220.00

4.40

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00 279.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

284.89

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

313.37

VAT

6% of Total

IT

4% of Total

20.89 13.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

348.19

Page: 13 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.02.4

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

EFW(DrS): Earth filling work in any type of embankment/pond/low lands with suitable dredged soil (sandy clay/silty clay/silt but excluding organic material), collected from silt-up river/canal bed by dredging with appropriate local dredger, including carrying through pipe or any other suitable means, loading, unloading and filling gradually at the right place of filling area in an artificial silt up manner at a suitable height and distance, including leveling, dressing and all necessary arrangements to fill-up soil and compacting to 95% minimum dry density at optimum moisture content with reference to laboratory density test AASHTO modified hammer with suitable equipment dressing etc. complete in all respect as per direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, their carriages, hire charges of dredger and all other machines, equipment for filling soil as per specification, fuels, lubricants, wages of operational staff and all incidental charges in this connection, etc. Location of river bed from where earth will be collected and quality of borrow soil must have prior approval from the Engineerin-charge. In no circumstances, earth shall be borrowed from agricultural/homestead land. The borrow earth have to be collected from river bed by avoiding any detrimental impact on the river channel. Payment will be made on compacted volume.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 14 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 2.02.4.01

2 Initial distance within 300m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Dredging & Carrying Cost of Earth

0.0420

hr.

2000.00

84.00

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0110

day

370.00

4.07

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00

Diesel

0.4000

liter

68.00

27.20

Lubricant

0.0200

liter

220.00

4.40 149.37

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

152.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

167.59

VAT

6% of Total

IT

4% of Total

11.17 7.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

186.21

Page: 15 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 2.02.4.02

2 Distance 300m to 600m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Dredging & Carrying Cost of Earth

0.0520

hr.

2000.00

104.00

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0110

day

370.00

4.07

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00

Diesel

0.4000

liter

68.00

27.20

Lubricant

0.0200

liter

220.00

4.40 169.37

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

172.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

190.03

VAT

6% of Total

IT

4% of Total

12.67 8.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

211.15

Page: 16 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 2.02.4.03

2 Distance 600m to 1.0km

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Dredging & Carrying Cost of Earth

0.0700

hr.

2000.00

140.00

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0110

day

370.00

4.07

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00

Diesel

0.4000

liter

68.00

27.20

Lubricant

0.0200

liter

220.00

4.40 205.37

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

209.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

230.43

VAT

6% of Total

IT

4% of Total

15.36 10.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

256.03

Page: 17 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 2.02.4.04

2 Distance 1.0km to 2.0km

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Dredging & Carrying Cost of Earth

0.0900

hr.

2000.00

180.00

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0110

day

370.00

4.07

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00

Diesel

0.4000

liter

68.00

27.20

Lubricant

0.0200

liter

220.00

4.40 245.37

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

250.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

275.31

VAT

6% of Total

IT

4% of Total

18.35 12.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

305.89

Page: 18 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 2.02.4.05

2 Distance 2.0km to 3.0km

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Dredging & Carrying Cost of Earth

0.1100

hr.

2000.00

220.00

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0110

day

370.00

4.07

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00

Diesel

0.4000

liter

68.00

27.20

Lubricant

0.0200

liter

220.00

4.40 285.37

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

291.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

320.19

VAT

6% of Total

IT

4% of Total

21.35 14.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

355.76

Page: 19 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 2.02.4.06

2 Distance 3.0km to 4.0km

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Dredging & Carrying Cost of Earth

0.1300

hr.

2000.00

260.00

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0110

day

370.00

4.07

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00

Diesel

0.4000

liter

68.00

27.20

Lubricant

0.0200

liter

220.00

4.40 325.37

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

331.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

365.07

VAT

6% of Total

IT

4% of Total

24.34 16.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

405.63

Page: 20 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 2.02.4.07

2 Distance 4.0km and above

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Dredging & Carrying Cost of Earth

0.1600

hr.

2000.00

320.00

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0110

day

370.00

4.07

H.C. of Vibratory Road Roller (8-10 ton)

0.0090

day

3000.00

27.00

Diesel

0.4000

liter

68.00

27.20

Lubricant

0.0200

liter

220.00

4.40 385.37

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

393.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

432.39

VAT

6% of Total

IT

4% of Total

28.83 19.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

480.43

Page: 21 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.03.1

Detailed Analysis Brief Description of Item 2 CB: Providing clay blanket/clay cover by carried earth supplied at contractor's own cost including royalty in different thickness over the side slopes or crest of the road embankment with selected soil (clay content minimum 80% and silt content 0-20%) including throwing clay in layers not exceeding 150 mm in thickness, clod breaking, benching the side slopes and compacting to 95% minimum dry density at optimum moisture content with reference to laboratory density test AASHTO standard hammer with suitable equipment dressing etc. complete as per direction of Engineer-in-charge. Composition of specified soil must be confirmed by laboratory test before use. (compaction will be done by the contractor with approved equipment including all ancillary charges for compaction and testing) as per direction of Engineer in charge. Payment will be made on compacted volume.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Royalty of Earth (Outside Municipal Area)

1.1800

m3

35.00

41.30

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00

Sardar

0.0040

day

800.00

3.20

Ordinary Labour

0.3200

day

370.00

118.40

H.C. of Vibratory Road Roller (8-10 ton)

0.0070

day

3000.00

21.00

Diesel

0.3000

liter

68.00

20.40

Lubricant

0.0150

liter

220.00

3.30 247.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

252.55

10% Profit ( Add 10% on Subtotal-B) :

277.81

VAT

6% of Total

IT

4% of Total

18.52 12.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

308.67

Page: 22 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

2.04.1

EWEx(Rd/C/P): Excavation for roadway/canals/ponds, etc. in soil by manual means, including cutting and disposing of all excavated materials at a safe distance designated by the E-I-C, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, leveling, dressing, etc. all complete for an initial excavation depth of 2m and lead upto 20m. including arranging and supplying all necessary tools and equipment at work site, etc. complete as per direction of the E-I-C.

2.04.1.1

Upto 20m lead from center line of the embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Labour

0.2000

day

370.00

74.00

Skilled Labour

0.0040

day

450.00

1.80 75.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

77.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

85.05

VAT

6% of Total

5.67

IT

4% of Total

3.78 Total:

2.04.1.2

Lead more than 20m from center line of the embankment

cum Ordinary Labour

0.2500

day

370.00

92.50

Skilled Labour

0.0040

day

450.00

1.80 94.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

96.19 105.80

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

7.05

IT

4% of Total

4.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

94.50

117.56

Page: 23 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.04.2

Detailed Analysis Brief Description of Item 2 EWEx(C/P/D): Earthwork in excavation of canals, ponds, drains, etc. by excavating earth to the lines, grades and elevation as shown in the drawing, filling baskets, carrying and disposing of all excavated materials at a safe distance designated by the E-I-C in all types of rocky, gravelly, slushy or organic soil, leveling, dressing, etc. all complete for an initial excavation depth of 2m and an initial lead not exceeding 20m, including arranging for and supplying all necessary tools and equipment at work site, etc. complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Labour

0.3000

day

370.00

111.00

Mason

0.0250

day

550.00

13.75 124.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

127.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

139.97

VAT

6% of Total

9.33

IT

4% of Total

6.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

155.52

Page: 24 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.04.3

Detailed Analysis Brief Description of Item 2 EWEx(Dr): Earth work in re-excavation of Beel, River & Beel connectivity (Canal) etc. by small dredging unit according to the lines, grades and elevation as shown in the drawing, fitting of cutter machine, delivery pipe fitting, soil management, filling chamber, village platform and disposing of all excavated materials at a safe distance designated by the E-I-C in all types of clay/slurry/organic soils except rocky, gravelly, slushy soil, levelling, dressing, etc. all complete for an initial soil dumping lead upto 100m including arranging for and supplying all necessary tools and equipment at work site etc. complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

H.C. of Excavator (Medium Size)

0.0040

day

8880.00

35.52

Ordinary Labour

0.0060

day

370.00

2.22

Diesel

0.3700

liter

68.00

25.16

Lubricant

0.0109

liter

220.00

2.40

Operator

0.0030

day

570.00

1.71 67.01

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

68.35

10% Profit ( Add 10% on Subtotal-B) :

75.18

VAT

6% of Total

IT

4% of Total

5.01 3.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

83.54

Page: 25 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.04.4

Detailed Analysis Brief Description of Item 2 EWEx(M): Earth Excavation by Mechanical hydraulic Excavator (Long Boon) in roadway/canals/ponds, etc. with 0.90 cum bucket capacity, including cutting and loading in tippers or disposing of all excavated materials at a safe distance designated by the E-I-C, trimming bottom and side slopes, in accordance with requirements of lines, grades and cross sections, leveling, dressing, etc. all complete for an initial excavation depth of 3m and lead upto 20m. including cost of hire charges of Excavator and all other machines, equipment, fuels, lubricants and wages of operational staff etc. all complete as per the direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

H.C. of Excavator (Medium Size)

0.0030

day

8880.00

26.64

Ordinary Labour

0.0052

day

370.00

1.92

Diesel

0.3700

liter

68.00

25.16

Lubricant

0.0100

liter

220.00

2.20

Operator

0.0030

day

570.00

1.71 57.63

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58.79

10% Profit ( Add 10% on Subtotal-B) :

64.67

VAT

6% of Total

IT

4% of Total

4.31 2.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

71.85

Page: 26 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.05.1

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Leveling and dressing the embankment crown, road flanks, etc. in maintenance work by earth cutting and filling as necessary with maintaining proper slope and camber including compaction etc. all complete as per direction of the E-I-C.

sqm

Quantity 5

Unit

Rate

6

7

Amount 8

Ordinary Labour

0.0200

day

370.00

7.40

Sardar

0.0020

day

800.00

1.60 9.00

Subtotal-A: Subtotal-B:

9.18

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10.10

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

0.67 0.45 Total:

2.06.1

Turfing on embankment top and slope, building compound with good quality turf supplied by the contractor of not less than 225mm square in dimension including placing and watering till grass is fully grown, etc. all complete as per direction of the E-I-C (payment to be made only when grass is fully grown).

sqm

Turf

1.0000

m2

5.00

5.00

Ordinary Labour

0.0450

day

370.00

16.65 21.65

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24.29

VAT

6% of Total

IT

4% of Total

1.62 1.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11.22

26.99

Page: 27 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 2.06.2

Detailed Analysis Brief Description of Item 2 Supplying and planting vertiver (Binna) grass in a bunch of 2 to 3 stem @of 225mm c/c all over the side slope starting from 225mm beyond the edge of the shoulder and watering till the grasses are fully grown etc. all complete as per direction of E-I-C. The stem should be 125mm to 150mm long with roots. (The payment is to be made only when grasses are fully grown)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Ordinary Labour

0.0650

day

370.00

24.05

Vertiver (binna) Grass

1.0000

m2

11.00

11.00 35.05

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

35.75

10% Profit ( Add 10% on Subtotal-B) :

39.33

VAT

6% of Total

2.62

IT

4% of Total

1.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

43.70

Page: 28 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Chapter - 3 : Road Works 3.01.1

BP: Preparation of bed by cutting and filling including watering to bring moisture content ± 2% of OMC & compacting by appropriate mechanical means etc. to obtain design CBR at minimum compaction 98% of MDD etc. all complete as per direction of the E-I-C

sqm

Mason

0.0050

day

550.00

2.75

Ordinary Labour

0.0080

day

370.00

2.96

H.C. of Water Tanker (Towed by Tractor)

0.0004

day

1500.00

0.60

H.C. of Water Pump

0.0004

day

500.00

0.20

H.C. of 3 Wheel Static Road roller (8-10 ton)

0.0008

day

3500.00

2.80

Diesel

0.0060

liter

68.00

0.41

Lubricant

0.0006

liter

220.00

0.13 9.85

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10.05

10% Profit ( Add 10% on Subtotal-B) :

11.05

VAT

6% of Total

IT

4% of Total

0.74 0.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12.28

Page: 29 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.01.2

Detailed Analysis Brief Description of Item 2 BC(150mm): Earth work in box cutting on road crest up to 150mm depth, maintaining proper grade, camber and alignment, super elevation on curves, removing soil to a safe distance, watering, if necessary, spreading the excavated earth on road flanks and slopes uniformly including leveling, dressing, manual compacting, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

sqm

Ordinary Labour

0.0500

18.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18.87

10% Profit ( Add 10% on Subtotal-B) :

20.76

VAT

6% of Total

IT

4% of Total

1.38 0.92 Total:

3.01.3.1

BC(300mm): Earth work in box cutting on road crest up to 300mm depth, maintaining proper grade, camber and alignment, super elevation on curves, removing soil to a safe distance, watering, if necessary, spreading the excavated earth on road flanks and slopes uniformly including leveling, dressing, compacting the sub-grade by manual labour, etc. all complete as per direction of the E-I-C.

23.06

sqm

Mason

0.0050

day

550.00

2.75

Ordinary Labour

0.0950

day

370.00

35.15 37.90

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

38.66

10% Profit ( Add 10% on Subtotal-B) :

42.52

VAT

6% of Total

2.83

IT

4% of Total

1.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18.50

47.25

Page: 30 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.01.3.2

Detailed Analysis Brief Description of Item 2 BC&SGC(300mm): Earth work in box cutting on road crest up to 300mm depth, maintaining proper grade, camber and alignment, super elevation on curves, removing soils to a safe distance or if necessary, spreading the excavated earth on road flanks and slopes uniformly including leveling, dressing, watering to bring moisture content ± 2% of OMC & compacting the sub-grade by appropriate mechanical means to attain design CBR at minimum compaction 98% of MDD (Standard) etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0900

day

370.00

33.30

H.C. of Water Tanker (Towed by Tractor)

0.0005

day

1500.00

0.75

H.C. of Water Pump

0.0005

day

500.00

0.25

H.C. of 3 Wheel Static Road roller (8-10 ton)

0.0009

day

3500.00

3.15

Diesel

0.0090

liter

68.00

0.61

Lubricant

0.0008

liter

220.00

0.18 43.74

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

44.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

49.07

VAT

6% of Total

IT

4% of Total

3.27 2.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

54.53

Page: 31 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.01.3.3

Detailed Analysis Brief Description of Item 2 BC&SGP(300mm): Earth work in box cutting up to 300mm depth & Preparation of sub-grade by excavating road crest up to 300mm depth, removing soils to a safe distance or spreading it on road flanks, slopes. In preparing 300mm sub-grade below the box, excavating top 150mm layer and excavated earth set aside to reuse, then scarifying the bottom 150 mm layer, breaking clods to 40mm maximum in size, leveling, dressing, watering to OMC ± 2% & compacting the 1st layer by appropriate mechanical means to attain design CBR at minimum compaction 98% of Standard proctor, subsequently prepare 2nd layer by spreading aside materials on top of prepared 1st layer, removing all deleterious material breaking clods, leveling, dressing, watering to OMC ± 2% and compacting the layer following the same procedure as 1st layer including maintaining proper grade, camber and alignment, super elevation on curves etc. all complete as per direction of the E-I-C. (When in-situ sub grade materials is suitable but very loose)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Mason

0.0150

day

550.00

8.25

Ordinary Labour

0.1800

day

370.00

66.60

H.C. of Water Tanker (Towed by Tractor)

0.0008

day

1500.00

1.25

H.C. of Water Pump

0.0008

day

500.00

0.42

H.C. of 3 Wheel Static Road roller (8-10 ton)

0.0017

day

3500.00

5.78

Diesel

0.0165

liter

68.00

1.12

Lubricant

0.0016

liter

220.00

0.35 83.76

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

85.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

93.98

VAT

6% of Total

6.27

IT

4% of Total

4.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

104.42

Page: 32 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.01.4.1

Detailed Analysis Brief Description of Item 2 BC(450mm): Earth work in box cutting on road crest up to 450mm depth, maintaining proper grade, camber and alignment, super elevation on curves, removing soil to a safe distance, spreading the excavated earth on road flanks and slopes uniformly including leveling, dressing, watering, compacting the sub-grade by manual labour, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.1340

day

370.00

49.58 55.08

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56.18

10% Profit ( Add 10% on Subtotal-B) :

61.80

VAT

6% of Total

4.12

IT

4% of Total

2.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

68.67

Page: 33 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.01.4.2

Detailed Analysis Brief Description of Item 2 BC&SGC(450mm): Earth work in box cutting on road crest up to 450mm depth, maintaining proper grade, camber and alignment, super elevation on curves, removing soils to a safe distance or if necessary, spreading the excavated earth on road flanks and slopes uniformly including leveling, dressing, watering to bring moisture content ± 2% of OMC & compacting the sub-grade by appropriate mechanical means to attain design CBR at minimum compaction 98% of MDD (Standard) etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.1340

day

370.00

49.58

H.C. of Water Tanker (Towed by Tractor)

0.0005

day

1500.00

0.75

H.C. of Water Pump

0.0005

day

500.00

0.25

H.C. of 3 Wheel Static Road roller (8-10 ton)

0.0009

day

3500.00

3.15

Diesel

0.0090

liter

68.00

0.61

Lubricant

0.0008

liter

220.00

0.18 60.02

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

67.34

VAT

6% of Total

IT

4% of Total

4.49 2.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

74.82

Page: 34 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.01.4.3

Detailed Analysis Brief Description of Item 2 BC&SGP(450mm): Earth work in box cutting up to 450mm depth & Preparation of sub-grade by excavating road crest up to 450mm depth, removing soils to a safe distance or spreading it on road flanks, slopes. In preparing 300mm sub-grade below the box, excavating top 150mm layer and excavated earth set aside to reuse, then scarifying the bottom 150 mm layer, breaking clods to 40mm maximum in size, leveling, dressing, watering to OMC ± 2% & compacting the 1st layer by appropriate mechanical means to attain design CBR at minimum compaction 98% of Standard proctor, subsequently prepare 2nd layer by spreading aside materials on top of prepared 1st layer, removing all deleterious material breaking clods, leveling, dressing, watering to OMC ± 2% and compacting the layer following the same procedure as 1st layer including maintaining proper grade, camber and alignment, super elevation on curves etc. all complete as per direction of the E-I-C. (When in-situ sub grade materials is suitable but very loose)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Mason

0.0200

day

550.00

11.00

Ordinary Labour

0.2200

day

370.00

81.40

H.C. of Water Tanker (Towed by Tractor)

0.0008

day

1500.00

1.25

H.C. of Water Pump

0.0008

day

500.00

0.42

H.C. of 3 Wheel Static Road roller (8-10 ton)

0.0017

day

3500.00

5.78

Diesel

0.0165

liter

68.00

1.12

Lubricant

0.0016

liter

220.00

0.35 101.31

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

103.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

113.67

VAT

6% of Total

7.58

IT

4% of Total

5.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

126.30

Page: 35 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.02.1.1

Detailed Analysis Brief Description of Item 2 Sand (FM 0.50) filling on the road bed in the improved sub-grade with sand free from dust, earth, other vegetable growth and foreign materials including supplying all materials, spreading, watering, compacting by appropriate mechanical means to obtain a minimum Soaked CBR 8% or Design CBR at minimum compaction 98% of MDD (Modified), etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Sand (FM - 0.5)

1.1500

m3

420.00

483.00

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0080

day

3000.00

24.00

Diesel

0.0400

liter

68.00

2.72

Lubricant

0.0035

liter

220.00

0.77 547.49

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

558.44

10% Profit ( Add 10% on Subtotal-B) :

614.28

VAT

6% of Total

IT

4% of Total

40.95 27.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

682.54

Page: 36 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.02.1.2

Detailed Analysis Brief Description of Item 2 Sand (FM 0.80) filling on the road bed in the improved sub-grade with sand free from dust, earth, other vegetable growth and foreign materials including supplying all materials, spreading, watering, compacting by appropriate mechanical means to obtain a minimum Design Soaked CBR but not less than 8% at minimum compaction 98% of MDD (Modified), etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Sand (FM - 0.8)

1.1500

m3

480.00

552.00

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0080

day

3000.00

24.00

Diesel

0.0400

liter

68.00

2.72

Lubricant

0.0035

liter

220.00

0.77 616.49

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

628.82

10% Profit ( Add 10% on Subtotal-B) :

691.70

VAT

6% of Total

IT

4% of Total

46.11 30.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

768.56

Page: 37 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.02.1.3

Detailed Analysis Brief Description of Item 2 Filling the road bed in the improved sub-grade with locally available sand (passing <=15% through #200 sieve) free from dust, earth clod, other vegetable growth and foreign materials including supplying all materials, spreading, watering, compacting by appropriate mechanical means to obtain a minimum Soaked CBR 8% or Design CBR at minimum compaction 98% of MDD (Modified), etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum

Local Sand (Sieve # 200 passing not more than 15%)

1.1500

m3

350.00

402.50

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0080

day

3000.00

24.00

Diesel

0.0400

liter

68.00

2.72

Lubricant

0.0035

liter

220.00

0.77 466.99

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

476.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

523.96

VAT

6% of Total

IT

4% of Total

34.93 23.29 Total:

3.02.2

PiISG: Labour charge for taking out the existing sand from road bed of any thickness and removing the debris including staking the materials at a specified distance, etc. all complete as per direction of the E-I-C.

cum

Ordinary Labour

0.1500

day

370.00

55.50 55.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

62.27

VAT

6% of Total

IT

4% of Total

4.15 2.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

582.18

69.19 Page: 38 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.02.3

Detailed Analysis Brief Description of Item 2 CISG: Labour for spreading & compaction of Improved Subgrade consisting of sand having compacted thickness as per specifications including local handling, hand packing, watering, dry rolling followed by wet rolling in layers of specified loose thickness with 8~10 tonne road roller to achieve Design Soaked CBR but not less than 8% at a degree of compaction to minimum 98% (Modified Proctor ) etc all complete as per direction of the Engineering-in-charge. Thickness of each layer should not be more than 125mm loose and Payment will be made on compacted thickness. (The rate excludes the cost of sand)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

day

370.00

37.00

8

cum

Ordinary Labour

0.1000

H.C. of Vibratory Road Roller (8-10 ton)

0.0080

day

3000.00

24.00

Diesel

0.0400

liter

68.00

2.72

Lubricant

0.0035

liter

220.00

0.77 64.49

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

65.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

72.36

VAT

6% of Total

IT

4% of Total

4.82 3.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

80.40

Page: 39 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.1

Detailed Analysis Brief Description of Item 2 Dis(SB/BC): Dismantling of damaged sub-base and Base course works in flexible paved road of any thickness by appropriate mechanical means and removing the debris to a safe distance, stacking properly including all tools and plants, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

day

370.00

55.50

8

cum

Ordinary Labour

0.1500

H.C. of Excavator (Medium Size)

0.0055

day

8880.00

48.84

Diesel

0.0600

liter

68.00

4.08

Lubricant

0.0070

liter

220.00

1.54 109.96

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

112.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

123.38

VAT

6% of Total

8.23

IT

4% of Total

5.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

137.08

Page: 40 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.2

Detailed Analysis Brief Description of Item 2 S&C(SB): Labour for mixing, spreading & compacting of Sub-base consisting of sand and crusher run aggregate made of well burnt picked 1st class bricks or stone having compacted thickness as per specifications including local handling, hand packing, watering, dry rolling followed by wet rolling in layers of specified loose thickness with 8~10 tonne road roller to achieve Design soaked CBR but not less than 30% at a degree of compaction to minimum 98% (Modified Proctor) etc. all complete as per direction of the Engineering-in-charge. Thickness of each layer should not be more than 100mm loose and Payment will be made on compacted thickness. (The rate excludes the cost of sand, brick/stone aggregates)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Mason

0.0100

day

550.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.2500

day

370.00

92.50

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00

5.50

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20 203.36

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

207.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

228.17

VAT

6% of Total

15.21

IT

4% of Total

10.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

253.52

Page: 41 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.3.1

Detailed Analysis Brief Description of Item 2 SBBC(FM-0.5): Providing compacted aggregate sand sub-base course with 38mm down Crusher run 1st class bricks/picked chips of LAA value not exceeding 40 & sand of minimum FM 0.50 mixed in proportion 1:1 by volume placed in layer(s), mixing properly, watering, compacting with 8~10 tonne road roller to attain minimum soaked CBR 30% or Design CBR at minimum compaction 98% of MDD (modified) including supplying of all materials, labourers, tools and equipment etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class/ Picked Brick chips (40mm down graded)

0.6650

m3

2786.00

1852.69

Sand (FM - 0.5)

0.6650

m3

420.00

279.30

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20 2435.85

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2484.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2733.02

VAT

6% of Total

IT

4% of Total

182.20 121.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3036.69

Page: 42 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.3.2

Detailed Analysis Brief Description of Item 2 SBBC(FM<0.5): Providing compacted aggregate sand sub-base course with 38mm down Crusher run 1st class bricks/picked chips of LAA value not exceeding 40 & locally available sand (Passing <=15% through #200 sieve) mixed in proportion 1:1 by volume placed in layer(s) to give a maximum compacted thickness of 100mm in a single appropriate layer, mixing properly, watering, compacting with 8~10 tonne road roller to attain minimum soaked CBR 30% or Design CBR at minimum compaction 98% of MDD (modified) including supplying of all materials, labourers, tools and equipment etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class/ Picked Brick chips (40mm down graded)

0.6650

m3

2786.00

1852.69

Local Sand (Sieve # 200 passing not more than 15%)

0.6650

m3

350.00

232.75

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00 2389.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2437.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2680.79

VAT

6% of Total

178.72

IT

4% of Total

119.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2978.66

Page: 43 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.3.3

Detailed Analysis Brief Description of Item 2 SBSL(FM-0.5): Providing compacted aggregate sand sub-base course with 38mm down local Crushed stone (Louva) chips mixed with Bholaganj crushed stone chips, as necessary, having LAA value not exceeding 40 & sand of minimum FM 0.50 mixed in proportion 1:1 by volume placed in layer(s), mixing properly, watering, compacting with 8~10 tonne road roller to attain minimum soaked CBR 30% or Design CBR at minimum compaction 98% of MDD (modified) including supplying of all materials, labourers, tools and equipment etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Crushed stone (Louva) chips (38mm down graded)

0.6650

cum

2300.00

1529.50

Sand (FM - 0.5)

0.6650

m3

420.00

279.30

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20 2112.66

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2154.91

10% Profit ( Add 10% on Subtotal-B) :

2370.40

VAT

6% of Total

IT

4% of Total

158.03 105.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2633.78

Page: 44 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.3.4

Detailed Analysis Brief Description of Item 2 SBBC(FM-0.8): Providing compacted aggregate sand sub-base course with 38mm down Crusher run 1st class bricks/picked chips of LAA value not exceeding 40 & sand of minimum FM 0.80 mixed in proportion 1:1 by volume placed in layer(s), mixing properly, watering, compacting with 8~10 tonne road roller to attain minimum soaked CBR 35% or Design CBR at minimum compaction 98% of MDD (modified) including supplying of all materials, labourers, tools and equipment etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class/ Picked Brick chips (40mm down graded)

0.6650

m3

2786.00

1852.69

Sand (FM - 0.8)

0.6650

m3

480.00

319.20

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20 2475.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2525.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2777.79

VAT

6% of Total

IT

4% of Total

185.19 123.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3086.44

Page: 45 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.4.1

Detailed Analysis Brief Description of Item 2 SBBC(70:30): Providing compacted aggregate sand sub-base course with 38mm down brick chips made of 1st class /picked brick (LAA value not exceeding 40) mixed thoroughly with sand of requisite FM (FM not less than 0.8) to obtain a homogeneous mix complying with the specified grading requirement of the relevant item of Road Design standards – 2005, (Suggested mixing ratio Brick Chips 38mm down graded 25% and 20mm down graded 45% with 30% sand) including mixing, carrying, placing and spreading uniformly in appropriate layer to give specified compacted thickness not more than 100mm in a single layer, watering, compacting by 8~10 tonne road roller at OMC±3% to obtain a minimum soaked CBR 50% or Design CBR at minimum compaction 98% of MDD (Modified), including supplying of all materials, their carriage, labourers tools and equipment etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class/ Picked Brick chips (40mm down graded)

0.3300

m3

2786.00

919.38

1st Class Brick Chips (20mm down graded)

0.6000

m3

2940.00

1764.00

Sand (FM - 0.8)

0.4000

m3

480.00

192.00

Ordinary Labour

0.5000

day

370.00

185.00

Skilled Labour

0.2200

day

450.00

99.00

Mason

0.0100

day

550.00

5.50

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00 3225.24

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3289.74

10% Profit ( Add 10% on Subtotal-B) :

3618.72

VAT

6% of Total

IT

4% of Total

241.25 160.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4020.80 Page: 46 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 47 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.4.2

Detailed Analysis Brief Description of Item 2 SBSC(50:50): Providing compacted aggregate sand sub-base course with 38mm down chips made of Crushed Stone (LAA value not exceeding 35) mixed thoroughly with sand of requisite FM (FM not less than 0.8) to obtain a homogeneous mix complying with the specified grading requirement of the relevant item of Road Design standards – 2005, (Suggested mixing ratio Crushed Stone 38mm down graded 25% and 20mm down graded 25% with 50% sand of total mix) including mixing, carrying, placing and spreading uniformly in appropriate layer to give specified compacted thickness not more than 100mm in a single layer, watering, compacting with 8~10 tonne road roller at OMC±3% to obtain a minimum soaked CBR 50% or Design CBR at minimum compaction 98% of MDD (Modified), including supplying of all materials, their carriage, labourers tools and equipment etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Stone Chips (38mm down graded) [LAA≤35]

0.2650

cum

4850.00

1285.25

Stone Chips (20mm down graded) [LAA≤35]

0.4000

cum

4930.00

1972.00

Sand (FM - 0.8)

0.6650

m3

480.00

319.20

Ordinary Labour

0.5000

day

370.00

185.00

Skilled Labour

0.2200

day

450.00

99.00

Mason

0.0100

day

550.00

5.50

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00 3926.31

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4004.84

10% Profit ( Add 10% on Subtotal-B) :

4405.32

VAT

6% of Total

IT

4% of Total

293.69 195.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4894.80 Page: 48 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.5.1

Detailed Analysis Brief Description of Item 2 SBbySM(FM-0.5): Providing compacted aggregate sand sub-base course with 38mm down crusher run 1st class bricks/picked chips from suitable salvage materials and supplying sand of minimum FM 0.50 mixed in proportion of 1:1 by volume placed in layer(s), mixing properly, watering, compacting with 8~10 tonne road roller to attain minimum soaked CBR 30% or Design CBR at minimum compaction 98% of MDD (modified) including supplying of all materials, labourers, tools and equipment etc. all complete as per direction of the E-I-C. (Excluding cost of 0.6650cum brick chips per cum work).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

279.30

cum

Sand (FM - 0.5)

0.6650

m3

420.00

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20 583.16

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

594.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

654.31

VAT

6% of Total

IT

4% of Total

43.62 29.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

727.01

Page: 49 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.03.5.2

Detailed Analysis Brief Description of Item 2 SBbySM(FM-0.8): Providing compacted aggregate sand sub-base course with 38mm down crusher run 1st class bricks/picked chips from suitable salvage materials and supplying sand of minimum FM 0.80 mixed in proportion of 1:1 by volume placed in layer(s), mixing properly, watering, compacting with 8~10 tonne road roller to attain minimum soaked CBR 35% or Design CBR at minimum compaction 98% of MDD (modified) including supplying of all materials, labourers, tools and equipment etc. all complete as per direction of the E-I-C. (Excluding cost of 0.6650cum brick chips per cum work).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

319.20

cum

Sand (FM - 0.8)

0.6650

m3

480.00

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00

H.C. of Water Pump

0.0100

day

500.00

5.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0100

day

3000.00

30.00

Diesel

0.1200

liter

68.00

8.16

Lubricant

0.0100

liter

220.00

2.20 623.06

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

635.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

699.07

VAT

6% of Total

IT

4% of Total

46.60 31.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

776.75

Page: 50 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.04.1.1

Detailed Analysis Brief Description of Item 2 PiEE(75mm): Labour charge for picking up the existing brick on end edging (75mm across) including staking the materials at a specified distance, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

m

Ordinary Labour

0.0140

5.18

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5.28

10% Profit ( Add 10% on Subtotal-B) :

5.81

VAT

6% of Total

IT

4% of Total

0.39 0.26

Subtotal-C:

Total: 3.04.1.2

PiEE(125mm): Labour charge for picking up the existing brick on end edging (125mm across) including staking the materials at a specified distance, etc. all complete as per direction of the E-I-C.

6.46

m

Ordinary Labour

0.0270

day

370.00

9.99 9.99

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11.21

VAT

6% of Total

IT

4% of Total

0.75 0.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5.18

12.45

Page: 51 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.04.2.1

Detailed Analysis Brief Description of Item 2 ReEE(75mm): Labour charge for Resetting the brick on end edging (75mm across) with 1st class/picked bricks, including cutting trenches true to level & grade, removing earth, re-filling & ramming the sides properly, including supplying and filling the gaps with local sand, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Sand (FM - 0.5)

0.0020

m3

420.00

0.84

Mason

0.0030

day

550.00

1.65

Ordinary Labour

0.0200

day

370.00

7.40 9.89

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11.10

VAT

6% of Total

IT

4% of Total

0.74 0.49 Total:

3.04.2.2

ReEE(125mm): Labour charge for Resetting the brick on end edging (125mm across) with 1st class/picked bricks including cutting trenches true to level & grade, removing earth, re-filling & ramming the sides properly, including supplying and filling the gaps with local sand, etc. all complete as per direction of the E-I-C.

m

Sand (FM - 0.5)

0.0050

m3

420.00

2.10

Mason

0.0040

day

550.00

2.20

Ordinary Labour

0.0330

day

370.00

12.21 16.51

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18.52

VAT

6% of Total

IT

4% of Total

1.23 0.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12.33

20.58 Page: 52 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.04.3.1

Detailed Analysis Brief Description of Item 2 EE(75mm): Brick on end edging (75mm across) with 1st class/picked bricks including cutting trenches true to level & grade, removing earth, re-filling & ramming the sides properly, including supplying and filling the gaps with local sand, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

1st Class Brick

8.0000

each

9.00

72.00

Sand (FM - 0.5)

0.0020

m3

420.00

0.84

Mason

0.0030

day

550.00

1.65

Ordinary Labour

0.0150

day

370.00

5.55 80.04

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

81.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

89.80

VAT

6% of Total

5.99

IT

4% of Total

3.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

99.78

Page: 53 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.04.3.2

Detailed Analysis Brief Description of Item 2 EE(125mm): Brick on end edging (125mm across) with 1st class/picked bricks including cutting trenches true to level & grade, removing earth, re-filling & ramming the sides properly, including supplying and filling the gaps with local sand, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

1st Class Brick

14.0000

each

9.00

126.00

Sand (FM - 0.5)

0.0050

m3

420.00

2.10

Mason

0.0040

day

550.00

2.20

Ordinary Labour

0.0300

day

370.00

11.10 141.40

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

144.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

158.65

VAT

6% of Total

10.58

IT

4% of Total

7.05 Total:

3.05.1

Amount

176.28

S&SBC: Supplying and spreading 1st class and picked brick chips (LAA value not exceeding 40) including cost of bricks carrying breaking into specified sizes including screening & specified sizes spreading uniformly on the road surface maintaining grade, camber and super elevation, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 54 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.1.1

2 20mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Skilled Labour

0.7000

day

450.00

315.00

1st Class Brick

300.0000

each

9.00

2700.00 3015.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3075.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3382.83

VAT

6% of Total

225.52

IT

4% of Total

150.35 Total:

3.05.1.2

40mm down graded

cum Skilled Labour

0.6000

day

450.00

270.00

1st Class Brick

294.0000

each

9.00

2646.00 2916.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2974.32

10% Profit ( Add 10% on Subtotal-B) :

3271.75

VAT

6% of Total

IT

4% of Total

218.12 145.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3758.70

3635.28

Page: 55 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.1.3

2 50mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Skilled Labour

0.5000

day

450.00

225.00

1st Class Brick

289.0000

each

9.00

2601.00 2826.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2882.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3170.77

VAT

6% of Total

211.38

IT

4% of Total

140.92 Total:

3.05.1.4

63mm down graded

cum Skilled Labour

0.4500

day

450.00

202.50

1st Class Brick

285.0000

each

9.00

2565.00 2767.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2822.85

10% Profit ( Add 10% on Subtotal-B) :

3105.14

VAT

6% of Total

IT

4% of Total

207.01 138.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3523.08

3450.15

Page: 56 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.1.5

2 80mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Skilled Labour

0.4000

day

450.00

180.00

1st Class Brick

282.0000

each

9.00

2538.00 2718.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2772.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3049.60

VAT

6% of Total

203.31

IT

4% of Total

135.54 Total:

3.05.2

B&SBC: Labour charge for breaking and spreading 1st class & picked brick chips including cost of bricks carrying, breaking into specified sizes including screening & spreading uniformly on the road surface maintaining grade, camber and super elevation, etc. all complete as per direction of the E-I-C.

3.05.2.1

20mm down graded

cum Skilled Labour

0.7500

day

450.00

337.50 337.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

344.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

378.68

VAT

6% of Total

IT

4% of Total

25.25 16.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3388.44

420.75

Page: 57 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.2.2

2 40mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

450.00

270.00

cum Skilled Labour

0.6000

270.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

275.40

10% Profit ( Add 10% on Subtotal-B) :

302.94

VAT

6% of Total

20.20

IT

4% of Total

13.46 Total:

3.05.2.3

50mm down graded

336.60

cum Skilled Labour

0.5000

day

450.00

225.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

229.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

252.45

VAT

6% of Total

IT

4% of Total

16.83 11.22 Total:

3.05.2.4

63mm down graded

280.50

cum Skilled Labour

0.4500

day

450.00

Subtotal-B: Subtotal-C:

202.50 202.50

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

206.55

10% Profit ( Add 10% on Subtotal-B) :

227.21

VAT

6% of Total

IT

4% of Total

15.15 10.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

225.00

252.45 Page: 58 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.2.5

2 80mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

450.00

180.00

cum Skilled Labour

0.4000

180.00

Subtotal-A: Subtotal-B: Subtotal-C:

3.05.3

S&SSC: Supplying and spreading stone chips of LAA value not exceeding 35% [Preferably stone chips from Madhyapara, Dinajpur], to be obtained from boulders including cost of boulders carrying breaking into specified sizes including screening & specified sizes & spreading uniformly on the road surface maintaining grade, camber and super elevation, etc. all complete as per direction of the E-I-C.

3.05.3.1

20mm down graded

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

183.60

10% Profit ( Add 10% on Subtotal-B) :

201.96

VAT

6% of Total

13.46

IT

4% of Total

8.98 Total:

224.40

cum Stone Boulder

0.9500

m3

3700.00

3515.00

Skilled Labour

1.4000

day

450.00

630.00 4145.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4227.90

10% Profit ( Add 10% on Subtotal-B) :

4650.69

VAT

6% of Total

IT

4% of Total

310.05 206.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5167.43

Page: 59 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.3.2

2 40mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Boulder

0.9500

m3

3700.00

3515.00

Skilled Labour

1.2000

day

450.00

540.00 4055.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4136.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4549.71

VAT

6% of Total

303.31

IT

4% of Total

202.21 Total:

3.05.3.3

50mm down graded

cum Stone Boulder

0.9500

m3

3700.00

3515.00

Skilled Labour

1.0000

day

450.00

450.00 3965.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4044.30

10% Profit ( Add 10% on Subtotal-B) :

4448.73

VAT

6% of Total

IT

4% of Total

296.58 197.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5055.23

4943.03

Page: 60 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.3.4

2 63mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Boulder

0.9500

m3

3700.00

3515.00

Skilled Labour

0.7500

day

450.00

337.50 3852.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3929.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4322.51

VAT

6% of Total

288.17

IT

4% of Total

192.11 Total:

3.05.3.5

80mm down graded

cum Stone Boulder

0.9500

m3

3700.00

3515.00

Skilled Labour

0.5000

day

450.00

225.00 3740.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3814.80

10% Profit ( Add 10% on Subtotal-B) :

4196.28

VAT

6% of Total

IT

4% of Total

279.75 186.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4802.78

4662.53

Page: 61 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.05.4.1

Detailed Analysis Brief Description of Item 2 S&SBC(WG): Supplying and spreading 50mm down graded crusher run 1st class and Picked brick chips of LAA value not exceeding 40% including supplying of required amount of 12mm down graded chips made of same quality bricks to fill the voids including cost of materials, spreading uniformly in layers of specified loose thickness on road surface maintaining grade, camber and super elevation, etc. all complete as per direction of the E-I- C. Measurement will be made on loose volume.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class/ Picked Brick chips (50mm down graded)

0.9000

m3

2730.00

2457.00

1st Class Brick Chips (10mm down graded)

0.1000

m3

3049.00

304.90

Skilled Labour

0.0400

day

450.00

18.00

Ordinary Labour

0.2000

day

370.00

74.00 2853.90

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2910.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3202.08

VAT

6% of Total

IT

4% of Total

213.47 142.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3557.86

Page: 62 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.05.4.2

Detailed Analysis Brief Description of Item 2 S&SSC(WG): Supplying and spreading 50mm down graded crusher run stone chips of LAA value not exceeding 35% including supplying of required amount of 12mm down graded chips made of same quality stone to fill the voids including cost of materials, spreading uniformly in layers of specified loose thickness on road surface maintaining grade, camber and super elevation, etc. all complete as per direction of the E-IC. Measurement will be made on loose volume.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Stone Chips (50mm down graded) [LAA≤35]

0.6000

cum

4730.00

2838.00

Stone Chips (12mm down graded) [LAA≤35]

0.4000

cum

4320.00

1728.00

Skilled Labour

0.0400

day

450.00

18.00

Ordinary Labour

0.2000

day

370.00

74.00 4658.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4751.16

10% Profit ( Add 10% on Subtotal-B) :

5226.28

VAT

6% of Total

348.42

IT

4% of Total

232.28 Total:

3.05.5

Amount

5806.97

B&SCS: Labour charge for breaking and spreading the concrete slab into pieces, salvaged from existing RCC pavement, breaking into specified sizes including screening & stacking properly in measurable stacks (max stack height 0.5m) at site, etc. all complete including dismantling existing concrete pavement as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 63 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.5.1

2 20mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

450.00

8

cum Skilled Labour

2.7500

1237.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1262.25

10% Profit ( Add 10% on Subtotal-B) :

1388.48

VAT

6% of Total

92.57

IT

4% of Total

61.71 Total:

3.05.5.2

40mm down graded

1542.75

cum Skilled Labour

2.5000

day

450.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1147.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1262.25

VAT

6% of Total

IT

4% of Total

84.15 56.10 Total:

50mm down graded

1402.50

cum Skilled Labour

2.0000

day

450.00

Subtotal-B: Subtotal-C:

900.00 900.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

918.00 1009.80

10% Profit ( Add 10% on Subtotal-B) :

VAT

67.32 44.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1125.00 1125.00

Subtotal-A:

3.05.5.3

1237.50

1122.00 Page: 64 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.05.5.4

2 63mm down graded

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

450.00

787.50

cum Skilled Labour

1.7500

787.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

803.25

10% Profit ( Add 10% on Subtotal-B) :

883.58

VAT

6% of Total

58.91

IT

4% of Total

39.27 Total:

3.05.5.5

75mm down graded

cum Skilled Labour

1.5000

day

450.00

675.00 675.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

688.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

757.35

VAT

6% of Total

IT

4% of Total

50.49 33.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

981.75

841.50

Page: 65 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.05.6

Detailed Analysis Brief Description of Item 2 CWBM(iSSM): Labour charge for compacted WBM base course with crusher run aggregate made of well burnt picked and 1st class bricks or stone having compacted thickness as per specifications including local handling, hand packing, watering, dry rolling followed by wet rolling in layers of specified loose thickness with 8~10 tonne road roller to attain minimum soaked CBR 80% or Design CBR at minimum degree of compaction 98% of MDD (Modified Proctor) including supplying choking/screening material as filler material @0.012cum/sqm or as required etc. all complete as per direction of the Engineering-in-charge. After adequate dry rolling, spreading of choking/screening material on the surface, sprinkling of water and rolling is to be continued until all the voids are filled, wave of grout/slurry flushes ahead of the roller. Thickness of each layer should not be more than 100mm loose and Payment will be made on compacted thickness. The rate excludes the cost of brick aggregates.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Sand (FM - 0.8)

0.1000

m3

480.00

48.00

Head Mason

0.0010

day

650.00

0.65

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.1800

day

370.00

66.60

H.C. of Vibratory Road Roller (8-10 ton)

0.0220

day

3000.00

66.00

H.C. of Water Tanker (Truck Mounted)

0.0180

day

2500.00

45.00

Diesel

0.1500

liter

68.00

10.20

Lubricant

0.0100

liter

220.00

2.20 243.15

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

248.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

272.81

VAT

6% of Total

IT

4% of Total

18.19 12.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

303.13

Page: 66 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.05.7.1

Detailed Analysis Brief Description of Item 2 WBMBC: Providing compacted brick aggregate base course, including supplying, spreading and compacting 50mm down graded crusher run 1st class and Picked brick chips (LAA value not exceeding 40%) including supplying of required amount of 12mm down graded chips made of same quality bricks, including spreading uniformly in layers of specified loose thickness on road surface maintaining grade, camber and super elevation including local handling, hand packing, booming, watering, dry rolling followed by wet rolling in layers with 8~10 tonne road roller to attain minimum soaked CBR 80% or Design CBR at minimum degree of compaction 98% of MDD (Modified Proctor), including supplying choking/screening material as filler material @0.018cum/sqm or as required including cost of materials, labours etc. all complete as per direction of the E-I-C. After adequate dry rolling spreading of choking/screening material on the surface, sprinkling water and rolling is to be continued until all the voids are filled, wave of grout/slurry flushes ahead of the roller. Thickness of each layer should not be more than 100mm loose and measurement for Payment will be made on compacted thickness.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class/ Picked Brick chips (50mm down graded)

1.0900

m3

2730.00

2975.70

1st Class Brick Chips (10mm down graded) Skilled Labour

0.1400

m3

3049.00

426.86

0.2000

day

450.00

90.00

Ordinary Labour

0.4500

day

370.00

166.50

Sand (FM - 0.5)

0.1200

m3

420.00

50.40

Head Mason

0.0020

day

650.00

1.30

H.C. of Vibratory Road Roller (8-10 ton)

0.0220

day

3000.00

66.00

H.C. of Water Tanker (Truck Mounted)

0.0180

day

2500.00

45.00

Diesel

0.1500

liter

68.00

10.20

Lubricant

0.0100

liter

220.00

2.20 3834.16

Subtotal-A: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3910.84

10% Profit ( Add 10% on Subtotal-B) :

4301.93

6% of Total

286.80 Page: 67 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

8 191.20

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4779.92

Page: 68 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.05.7.2

Detailed Analysis Brief Description of Item 2 WMMBC: Providing compacted brick aggregate WMM base course, including supplying, spreading and compacting 38mm down graded aggregates as specified in the relevant item of LGED road design standard or wet mix macadam specification (LAA value not exceeding 40% ) made of 1st class and Picked bricks, combining brick chips of different sizes to provide requisite grading and premixing the material with water at OMC in mechanical mix plant at stack yard including carriage of mixed material by tipper with proper covering to site, laying in uniform layers of specified loose thickness not more than 100mm with Grader in base course on well prepared surface and compacting with 8~10 tonne Vibratory road roller to attain minimum soaked CBR 80% or Design CBR at a degree of minimum compaction 98% (Modified Proctor) including supplying all materials, carriage, labors, tools & equipment etc. all complete as per direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class/ Picked Brick chips (40mm down graded)

0.4500

m3

2786.00

1253.70

1st Class Picked Brick Chips (20mm down graded)

0.7500

m3

2940.00

2205.00

Sand (FM - 0.5)

0.1500

m3

420.00

63.00

Ordinary Labour

0.3000

day

370.00

111.00

Skilled Labour

0.2000

day

450.00

90.00

Head Mason

0.0050

day

650.00

3.25

H.C. of Mixing Machine for Aggregate

0.0040

day

8000.00

32.00

H.C. of Dump Truck/ Tripping Trucks

0.0300

day

4500.00

135.00

H.C. of Motor Graders (14 tons)

0.0020

day

6000.00

12.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0300

day

3000.00

90.00

H.C. of Water Tanker (Truck Mounted)

0.0020

day

2500.00

5.00

Stackyard Rent

1.0000

m3

6.48

6.48

Diesel

0.8000

liter

68.00

54.40

Lubricant

0.0600

liter

220.00

13.20 4074.03

Subtotal-A: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4155.51 Page: 69 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

6% of Total

IT

4% of Total

304.74 203.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8 4571.06

10% Profit ( Add 10% on Subtotal-B) :

VAT

Amount

5078.96

Page: 70 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.05.8.1

Detailed Analysis Brief Description of Item 2 WBMSC: Providing compacted Stone Aggregate Base Course by supplying, spreading and compacting 50mm down graded crusher run stone chips as specified in the relevant item of LGED road design standard (LAA value not exceeding 35%), including supplying of required amount of 12mm down graded chips made of same quality stone and Sand of minimum FM=0.80, including spreading uniformly in layers of specified loose thickness on road surface maintaining grade, camber and super elevation including local handling, hand packing, booming, watering, dry rolling followed by wet rolling in layers with 8~10 tonne road roller to attain minimum soaked CBR 90% or Design CBR at minimum degree of compaction 98% of MDD (Modified Proctor ), blinding withchoking material as filler material @0.018cum/sqm or as required including cost of materials, labours etc. all complete as per direction of the E-I-C. After adequate dry rolling spreading choking material on the surface, sprinkling water and rolling is to be continued until all the voids are filled, wave of grout/slurry flushes ahead of the roller. Thickness of each layer should not be more than 100mm loose and measurement for Payment will be made on compacted thickness.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Stone Chips (50mm down graded) [LAA≤35]

0.5300

cum

4730.00

2506.90

Stone Chips (12mm down graded) [LAA≤35]

0.4000

cum

4320.00

1728.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4500

day

370.00

166.50

Sand (FM - 0.8)

0.4000

m3

480.00

192.00

Head Mason

0.0020

day

650.00

1.30

H.C. of Vibratory Road Roller (8-10 ton)

0.0220

day

3000.00

66.00

H.C. of Water Tanker (Truck Mounted)

0.0180

day

2500.00

45.00

Diesel

0.1500

liter

68.00

10.20

Lubricant

0.0100

liter

220.00

2.20 4808.10

Subtotal-A: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4904.26

10% Profit ( Add 10% on Subtotal-B) :

5394.69

6% of Total

359.65 Page: 71 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

8 239.76

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5994.10

Page: 72 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.05.8.2

Detailed Analysis Brief Description of Item 2 WMMSC: Providing compacted Stone aggregate base course by supplying, spreading and compacting 38mm down graded stone chips as specified in the relevant item of LGED road design standard or wet mix macadam specification (LAA value not exceeding 35% made of Crushed stone combining aggregates of different sizes to provide required grading and premixing with water at OMC in mechanical mix plant at stack yard including carriage of mixed material by tipper with proper covering to site, laying in uniform layers of specified loose thickness not more than 100mm with Grader in base course on well prepared surface and compacting with 8~10 tonne vibratory road roller to attain minimum soaked CBR 90% or Design CBR at minimum degree of compaction 98% of MDD (Modified Proctor ) including supplying all materials, carriage, labors, tools & equipment etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (38mm down graded) [LAA≤35]

0.4500

cum

4850.00

2182.50

Stone Chips (20mm down graded) [LAA≤35]

0.2500

cum

4930.00

1232.50

Stone Chips (12mm down graded) [LAA≤35]

0.2400

cum

4320.00

1036.80

Sand (FM - 0.8)

0.4000

m3

480.00

192.00

Ordinary Labour

0.3000

day

370.00

111.00

Skilled Labour

0.2000

day

450.00

90.00

Head Mason

0.0050

day

650.00

3.25

H.C. of Mixing Machine for Aggregate

0.0040

day

8000.00

32.00

H.C. of Dump Truck/ Tripping Trucks

0.0300

day

4500.00

135.00

H.C. of Motor Graders (14 tons)

0.0020

day

6000.00

12.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0300

day

3000.00

90.00

H.C. of Water Tanker (Truck Mounted)

0.0020

day

2500.00

5.00

Stackyard Rent

1.0000

m3

6.48

6.48

Diesel

0.8000

liter

68.00

54.40

Lubricant

0.0600

liter

220.00

13.20

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity

5196.13

Page: 73 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5300.05

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5830.06

VAT

6% of Total

IT

4% of Total

388.67 259.11 Total:

3.06.1.1

[email protected]: Providing Prime coat @1.2 liter/sqm with cut back bitumen to be prepared by cutting back 60/70 or 80/100 penetration grade straight run bitumen (conforming to the requirements of ASTM/ AASHTO in the ratio of 100 parts by volume of bitumen to 40-60 parts by volume of kerosene depending on the porosity of the surface and will be decided by field trials, the correct quantity that is completely absorbed within 24 hours including carefully cleaning of the surface of the granular base material to be primed and spraying cut back bitumen at a temperature from 100°C to 120°C by appropriate hand device, etc. complete as per direction of the E-I-C.

sqm

Bitumen [Grade 80/100]

0.8000

kg

49.00

39.20

Kerosene

0.4000

litre

72.00

28.80

Fire wood

0.6400

kg

7.75

4.96

Mason

0.0001

day

550.00

0.06

Skilled Labour

0.0010

day

450.00

0.45

Ordinary Labour

0.0070

day

370.00

2.59 76.06

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

77.58

10% Profit ( Add 10% on Subtotal-B) :

85.33

VAT

6% of Total

IT

4% of Total

5.69 3.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6477.84

94.82

Page: 74 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.1.2

Detailed Analysis Brief Description of Item 2 [email protected]: Providing Prime coat @1.2 liter/sqm with cut back bitumen to be prepared by cutting back 60/70 or 80/100 penetration grade straight run bitumen (conforming to the requirements of ASTM/ AASHTO in the ratio of 100 parts by volume of bitumen to 40-60 parts by volume of kerosene depending on the porosity of the surface and will be decided by field trials, the correct quantity that is completely absorbed within 24 hours including carefully cleaning of the surface of the granular base material to be primed and spraying cut back bitumen at a temperature from 100°C to 120°C by mechanical distributor, etc. complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen [Grade 80/100]

0.8000

kg

49.00

39.20

Fire wood

0.6400

kg

7.75

4.96

Kerosene

0.4000

litre

72.00

28.80

Mason

0.0001

day

550.00

0.06

Skilled Labour

0.0010

day

450.00

0.45

Ordinary Labour

0.0060

day

370.00

2.22

H.C. of Distributor

0.0003

day

3750.00

1.01

Diesel

0.0025

liter

68.00

0.17

Lubricant

0.0003

liter

220.00

0.06 76.92

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

78.46

10% Profit ( Add 10% on Subtotal-B) :

86.31

VAT

6% of Total

IT

4% of Total

5.75 3.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

95.90

Page: 75 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.2.1

Detailed Analysis Brief Description of Item 2 [email protected]: Providing tack coat @0.50kg/sqm with 60/70 or 80/100 penetration grade straight run bitumen complying with the requirements of ASTM/AASHTO applied by appropriate hand device at a temperature between 175°C and 185°C including heating bitumen, surface cleaning, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen [Grade 80/100]

0.5000

kg

49.00

24.50

Fire wood

0.4000

kg

7.75

3.10

Mason

0.0001

day

550.00

0.06

Skilled Labour

0.0010

day

450.00

0.45

Ordinary Labour

0.0070

day

370.00

2.59 30.70

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

31.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

34.44

VAT

6% of Total

2.30

IT

4% of Total

1.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

38.27

Page: 76 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.2.2

Detailed Analysis Brief Description of Item 2 [email protected]: Providing tack coat @0.75kg/sqm with 60/70 or 80/100 penetration grade straight run bitumen complying with the requirements of ASTM/AASHTO applied by appropriate hand device at a temperature between 175°C and 185°C including heating bitumen, surface cleaning, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen [Grade 80/100]

0.7500

kg

49.00

36.75

Fire wood

0.6000

kg

7.75

4.65

Mason

0.0001

day

550.00

0.06

Skilled Labour

0.0010

day

450.00

0.45

Ordinary Labour

0.0070

day

370.00

2.59 44.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

45.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

49.92

VAT

6% of Total

3.33

IT

4% of Total

2.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

55.47

Page: 77 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.2.3

Detailed Analysis Brief Description of Item 2 [email protected]: Providing tack coat @0.50kg/sqm with 60/70 or 80/100 penetration grade straight run bitumen complying with the requirements of ASTM/AASHTO applied by mechanical distributor at a temperature between 175°C and 185°C including heating bitumen, surface cleaning, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen [Grade 80/100]

0.5000

kg

49.00

24.50

Fire wood

0.4000

kg

7.75

3.10

Mason

0.0010

day

550.00

0.55

Skilled Labour

0.0020

day

450.00

0.90

Ordinary Labour

0.0050

day

370.00

1.85

H.C. of Distributor

0.0003

day

3750.00

1.13

Diesel

0.0030

liter

68.00

0.20

Lubricant

0.0003

liter

220.00

0.07 32.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32.94

10% Profit ( Add 10% on Subtotal-B) :

36.23

VAT

6% of Total

2.42

IT

4% of Total

1.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

40.26

Page: 78 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.2.4

Detailed Analysis Brief Description of Item 2 [email protected]: Providing tack coat @0.75kg/sqm with 60/70 or 80/100 penetration grade straight run bitumen complying with the requirements of ASTM/AASHTO applied by mechanical distributor at a temperature between 175°C and 185°C including heating bitumen, surface cleaning, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen [Grade 80/100]

0.7500

kg

49.00

36.75

Fire wood

0.6000

kg

7.75

4.65

Mason

0.0010

day

550.00

0.55

Skilled Labour

0.0020

day

450.00

0.90

Ordinary Labour

0.0050

day

370.00

1.85

H.C. of Distributor

0.0003

day

3750.00

1.13

Diesel

0.0030

liter

68.00

0.20

Lubricant

0.0003

liter

220.00

0.07 46.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

47.02

10% Profit ( Add 10% on Subtotal-B) :

51.72

VAT

6% of Total

3.45

IT

4% of Total

2.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

57.47

Page: 79 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.3

Detailed Analysis Brief Description of Item 2 7mmSC: Providing 7mm thick (minimum) compacted pre-mixed bituminous seal coat to be prepared using 6.33mm down crushed stone chips & stone dust blended together to comply the gradation as specified in the relevant item of Road Design Standards – 2005, mixed with 80/100 or 60/70 (Preferable) penetration grade minimum @5.0% by weight of total mix or as determined by job mix design. The bitumen and chips shall be separately heated to a temperature 140°C – 155°C and 150°C – 170°C respectively. The mixing shall be done at temperature between 140°C – 160°C at a separate place away from the fire. The mixture of bitumen and chips shall be laid uniformly on the road surface in appropriate layer so as to produce the specified compacted thickness, rolling at a temperature not bellow 90°C with appropriate Steel Drum Roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to the desired compaction, including supplying of all materials, their carriage, labourers tools and equipment etc. all complete as per direction of the E-I-C [Excluding the cost of applying Prime/Tack coat].

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Chips (6mm down graded) [LAA≤35]

0.0049

cum

3690.00

18.08

Stone Dust (2.38mm down)

0.0049

cum

1500.00

7.35

Bitumen [Grade 80/100]

0.9210

kg

49.00

45.13

Fire wood

0.9210

kg

7.75

7.14

Mason

0.0008

day

550.00

0.44

Skilled Labour

0.0050

day

450.00

2.25

Ordinary Labour

0.0190

day

370.00

7.03

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0005

day

3000.00

1.50

Diesel

0.0008

liter

68.00

0.05

Lubricant

0.0008

liter

220.00

0.18

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0005

day

3000.00

1.50 90.65

Subtotal-A: Subtotal-B: Subtotal-C: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

92.46 101.71 Page: 80 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

8 6.78 4.52

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

113.01

Page: 81 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.3.1

Detailed Analysis Brief Description of Item 2 Providing 15mm thick (minimum) compacted pre-mixed bituminous surfacing - wearing course to be prepared using 12mm down, 6mm down graded crushed stone chips & Stone Dust to comply the gradation as specified in the relevant item of Road Design Standards – 2005, mixed with 80/100 or 60/70 (Preferable) penetration grade minimum @5.0% by weight of total mix or as determined by job mix design. The bitumen and chips shall be separately heated to a temperature 140°C – 155°C and 150°C – 170°C respectively. The mixing shall be done at temperature between 140°C – 160°C at a separate place away from the fire. The mixture of bitumen and chips shall be laid uniformly on the road surface in appropriate layer so as to produce the specified compacted thickness, rolling at a temperature not bellow 90°C with appropriate Steel Drum Roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to the desired compaction, including supplying of all materials, their carriage, labours, tools and equipment etc. all complete in all respect as per direction of the Engineer-in-charge. [Excluding the cost of applying Prime/Tack coat].

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Chips (12mm down graded) [LAA≤35]

0.0042

cum

4320.00

18.14

Stone Chips (6mm down graded) [LAA≤35]

0.0095

cum

3690.00

35.06

Stone Dust (2.38mm down)

0.0074

cum

1500.00

11.10

Bitumen [Grade 80/100]

1.7625

kg

49.00

86.36

Fire wood

1.7625

kg

7.75

13.66

Mason

0.0011

day

550.00

0.61

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0300

day

370.00

11.10

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0007

day

3000.00

2.10

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0007

day

3000.00

2.10

Diesel

0.0110

liter

68.00

0.75

Lubricant

0.0011

liter

220.00

0.24 183.92

Subtotal-A: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

187.59 Page: 82 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

6% of Total

IT

4% of Total

13.76 9.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8 206.35

10% Profit ( Add 10% on Subtotal-B) :

VAT

Amount

229.28

Page: 83 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.4.1

Detailed Analysis Brief Description of Item 2 25mmBC: Providing 25mm thick (minimum) compacted pre-mixed bituminous carpeting to be prepared using 16mm down graded stonechips (LAA value not exceeding 35%) to comply the gradation as specified, mixed with heated bitumen of 60/70 (Preferable) or 80/100 penetration grade heated straight run bitumen satisfying the requirements of ASTM/AASHTO. The bitumen and stone-chips shall be separately heated to a temperature 140°C – 155°C and 150°C – 170°C respectively before mixing. The mixing shall be done at temperature between 140°C – 160°C at a separate place away from the fire. The bitumen and stone-chips mixture shall be laid uniformly in proper camber, grade and super-elevation, only on the prepared and accepted base or surface in a single appropriate layer to give the specified compacted thickness. The mixture should be rolled with appropriate by Steel Drum Roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to full compaction. The rolling temperature shall be maintained not below 90°C including supplying of all materials, their carriage, labourers, tools and equipment etc. all complete as per direction of the E-I-C. The bitumen in the mix shall be @4.5% to 5.5% by weight of total mix or as determined by job mix design. (In order to achieve the specified grading a blending of nominal maximum size of 16mm, 12mm, 6mm crushed stone chips and stone dust is suggested and proportion will have to determine by the laboratory analysis)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (16mm down graded) [LAA≤35]

0.0068

cum

4720.00

32.10

Stone Chips (12mm down graded) [LAA≤35]

0.0118

cum

4320.00

50.98

Stone Chips (6mm down graded) [LAA≤35]

0.0118

cum

3690.00

43.54

Stone Dust (2.38mm down)

0.0034

cum

1500.00

5.10

Bitumen [Grade 80/100]

2.3128

kg

49.00

113.33

Fire wood

2.3128

kg

7.75

17.92

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0110

day

450.00

4.95

Ordinary Labour

0.0450

day

370.00

16.65

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0010

day

3000.00

3.00

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0010

day

3000.00

3.00

Page: 84 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Diesel

0.0160

liter

68.00

1.09

Lubricant

0.0016

liter

220.00

0.35 293.11

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

298.97

10% Profit ( Add 10% on Subtotal-B) :

328.86

VAT

6% of Total

21.92

IT

4% of Total

14.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

365.40

Page: 85 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.4.2

Detailed Analysis Brief Description of Item 2 25mmDC: Providing 25mm thick (minimum) compacted pre-mixed bituminous surfacing - wearing course with 16mm down graded crushed stone chips complying with the specified grading requirement of the relevant item of Road Design standards – 2005, of LAA value <=35%, water absorption not >2%, flakiness index not >35% mixed with 60/70 (Preferable) or 80/100 penetration grade heated straight run bitumen satisfying the requirements of ASTM/AASHTO. The bitumen and stone-chips shall be separately heated to a temperature 140oC – 155oC and 150oC – 170oC respectively before mixing. The mixing shall be done at temperature between 140oC – 160oC at a separate place away from the fire. The bitumen and stone-chips mixture shall be laid uniformly on the road surface in single appropriate layer to give specified compacted thickness in proper camber, grade and superelevation. The mixture should be rolled at a temperature not below 90oC with Steel Drum Roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to full compaction, including supplying of all materials, their carriage, labourers tools and equipment etc. all complete as per the direction of the E-I-C. The bitumen in the mix shall be between 5.0% by weight of total mix or as determined by job mix design. (In order to achieve the specified grading a blending of nominal maximum size of 16mm, 12mm, 6mm crushed stone chips and stone dust is suggested and proportion will have to determine by the laboratory analysis) .

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (16mm down graded) [LAA≤35]

0.0070

cum

4720.00

33.04

Stone Chips (12mm down graded) [LAA≤35]

0.0105

cum

4320.00

45.36

Stone Chips (6mm down graded) [LAA≤35]

0.0088

cum

3690.00

32.47

Stone Dust (2.38mm down)

0.0088

cum

1500.00

13.20

Bitumen [Grade 80/100]

2.9500

kg

49.00

144.55

Fire wood

2.9500

kg

7.75

22.86

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0120

day

450.00

5.40

Ordinary Labour

0.0500

day

370.00

18.50

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0010

day

3000.00

3.00

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0010

day

3000.00

3.00

Page: 86 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Diesel

0.0160

liter

68.00

1.09

Lubricant

0.0016

liter

220.00

0.35 323.92

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

330.40

10% Profit ( Add 10% on Subtotal-B) :

363.44

VAT

6% of Total

24.23

IT

4% of Total

16.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

403.83

Page: 87 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.5.1

Detailed Analysis Brief Description of Item 2 40mmBC: Providing 40mm thick (minimum) compacted pre-mixed bituminous carpeting to be prepared using 25mm down graded crushed stone chips (LAA value <= 35%) to comply the gradation as specified, mixed with heated bitumen of 60/70 (Preferable) or 80/100 penetration grade heated straight run bitumen satisfying the requirements of ASTM/AASHTO. The bitumen and stone-chips shall be separately heated to a temperature 140°C – 155°C and 150°C – 170°C respectively before mixing. The mixing shall be done at temperature between 140°C – 160°C at a separate place away from the fire. The bitumen and stonechips mixture shall be laid uniformly in proper camber, grade and superelevation only on the prepared and accepted base or surface in a single appropriate layer to give the specified compacted thickness. The mixture should be rolled with appropriate Steel Drum Roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to full compaction. The rolling temperature shall be maintained not below 90°C. including supplying of all materials, their carriage, labourers, tools and equipment etc. all complete as per direction of the E-I-C. The bitumen in the mix shall be @4.5% to 5.5% by weight of total mix or as determined by job mix design. (In order to achieve the specified grading a blending of nominal maximum size of 25mm, 12mm, 6mm crushed stone chips and stone dust is suggested and proportion will have to determine by the laboratory analysis)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (25mm down graded) [LAA≤35]

0.0135

cum

4920.00

66.42

Stone Chips (12mm down graded) [LAA≤35]

0.0162

cum

4320.00

69.98

Stone Chips (6mm down graded) [LAA≤35]

0.0162

cum

3690.00

59.78

Stone Dust (2.38mm down)

0.0081

cum

1500.00

12.15

Bitumen [Grade 80/100]

3.6816

kg

49.00

180.40

Fire wood

3.6816

kg

7.75

28.53

Mason

0.0028

day

550.00

1.54

Skilled Labour

0.0170

day

450.00

7.65

Ordinary Labour

0.0700

day

370.00

25.90

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0016

day

3000.00

4.80

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0016

day

3000.00

4.80

Page: 88 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Diesel

0.0270

liter

68.00

1.84

Lubricant

0.0027

liter

220.00

0.59 464.38

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

473.67

10% Profit ( Add 10% on Subtotal-B) :

521.04

VAT

6% of Total

34.74

IT

4% of Total

23.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

578.93

Page: 89 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.5.2

Detailed Analysis Brief Description of Item 2 40mmDC: Providing 40mm thick (minimum) compacted pre-mixed bituminous surfacing - wearing course with 25mm down graded crushed stone chips (LAA value <= 35%) complying with the specified grading requirement of the relevant item of Road Design standards – 2005, water absorption not >2%, flakiness index not >35% mixed with 60/70 (Preferable) or 80/100 penetration grade heated straight run bitumen satisfying the requirements of ASTM/AASHTO. The bitumen and stone-chips shall be separately heated to a temperature 140oC – 155oC and 150oC – 170oC respectively before mixing. The mixing shall be done at temperature between 140oC – 160oC at separate place away from the fire. The bitumen and stone-chips mixture shall be laid uniformly on the road surface in single appropriate layer to give specified compacted thickness in proper camber, grade and superelevation. The mixture should be rolled at a temperature not below 90oC with appropriate Steel Drum Roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to full compaction, including supplying of all materials, their carriage, labourers tools and equipment etc. all complete as per the direction of the E-I-C. The bitumen in the mix shall be @ 5.0% to 5.5% by weight of total mix or as determined by job mix design. (In order to achieve the specified grading a blending of nominal maximum size of 25mm, 12mm, 6mm crushed stone chips and stone dust is suggested and proportion will have to determine by the laboratory analysis)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (25mm down graded) [LAA≤35]

0.0140

cum

4920.00

68.88

Stone Chips (12mm down graded) [LAA≤35]

0.0140

cum

4320.00

60.48

Stone Chips (6mm down graded) [LAA≤35]

0.0140

cum

3690.00

51.66

Stone Dust (2.38mm down)

0.0140

cum

1500.00

21.00

Bitumen [Grade 80/100]

4.5312

kg

49.00

222.03

Fire wood

4.5312

kg

7.75

35.12

Mason

0.0028

day

550.00

1.54

Skilled Labour

0.0170

day

450.00

7.65

Ordinary Labour

0.0800

day

370.00

29.60

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0016

day

3000.00

4.80

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (3-

0.0016

day

3000.00

4.80

Page: 90 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

5 tons) Diesel

0.0280

liter

68.00

1.90

Lubricant

0.0028

liter

220.00

0.62 510.08

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

520.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

572.30

VAT

6% of Total

IT

4% of Total

38.15 25.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

635.89

Page: 91 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.6

Detailed Analysis Brief Description of Item 2 50mmBC: Providing 50mm thick (minimum) compacted pre-mixed bituminous carpeting to be prepared using 25mm down graded stonechips (LAA value <= 35%) of gradation as specified, mixed with heated bitumen of 60/70 (Preferable) or 80/100 penetration grade heated straight run bitumen satisfying the requirements of ASTM/AASHTO. The bitumen and stone-chips shall be separately heated to a temperature 140°C – 155°C and 150°C – 170°C respectively before mixing. The mixing shall be done at temperature between 140°C – 160°C at a separate place away from the fire. The bitumen and stone-chips mixture shall be laid uniformly in proper camber, grade and super-elevation only on the prepared and accepted base or surface in a single appropriate layer to give the specified compacted thickness. The mixture should be rolled with appropriate Steel Drum Roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to full compaction. The rolling temperature shall be maintained not below 90°C including supplying of all materials, their carriage, labourers, tools and equipment etc. all complete as per direction of the E-I-C. The bitumen in the mix shall be @4.5% to 5.5% by weight of total mix or as determined by job mix design. (In order to achieve the specified grading a blending of nominal maximum size of 25mm, 12mm, 6mm crushed stone chips and stone dust is suggested and proportion will have to determine by the laboratory analysis).

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (25mm down graded) [LAA≤35]

0.0203

cum

4920.00

99.88

Stone Chips (12mm down graded) [LAA≤35]

0.0169

cum

4320.00

73.01

Stone Chips (6mm down graded) [LAA≤35]

0.0169

cum

3690.00

62.36

Stone Dust (2.38mm down)

0.0135

cum

1500.00

20.25

Bitumen [Grade 80/100]

4.6020

kg

49.00

225.50

Fire wood

4.6020

kg

7.75

35.67

Mason

0.0033

day

550.00

1.82

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0020

day

3000.00

6.00

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0020

day

3000.00

6.00

Page: 92 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Diesel

0.0320

liter

68.00

2.18

Lubricant

0.0032

liter

220.00

0.70 579.35

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

590.94

10% Profit ( Add 10% on Subtotal-B) :

650.03

VAT

6% of Total

43.34

IT

4% of Total

28.89 Total:

3.06.7

Amount

722.26

DCPM: Providing and Laying pre-mixed dense bituminous surfacing wearing course with hot mix plant using coarse aggregate, fine aggregate, filler and bituminous binder as per design Job Mix Formula conforming Marshall Method as per specification, LAA value of aggregate should be <=35%, water absorption not >2%, flakiness index not >35% mixed with (60/70 or 80/100) penetration grade straight run bitumen satisfying the requirements of ASTM/AASHTO. including screening, cleaning of chips and preparing a uniform and quality mix in Hot Mix Plant and ensuring a homogenous mix, in which all particles of the mineral aggregates are coated uniformly, carrying the hot premixed materials by means of Dump/tipper truck, spreading the mixed materials at specified laying temperature with a hydrostatic paver finisher with sensor control to the required grade, level and alignment over the prepared surface tamping and finishing the mix at specified compacted thickness, maintaining specified camber, grade, superelevation and cross section, through rolling with appropriate Steel Drum Roller & pneumatic multiple tire roller (8-10 tons) to full compaction, for break down, inter - mediate and finished rolling to achieve the desired density of at least 98% of that of Laboratory Marshall specimen, hand packing and pinning to give an even surface, including cost of all materials, their carriages, hire charges of Hot Mix Plant and all other machines, equipments for construction and quality control as per specification, fuels, lubricants and wages of operational staff etc. all complete as per the direction of the E-I-C

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 93 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.06.7.1

2 [Bitumen Grade 80/100]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Stone Chips (16mm down graded) [LAA≤35]

0.3500

cum

4720.00

1652.00

Stone Chips (12mm down graded) [LAA≤35]

0.3500

cum

4320.00

1512.00

Stone Chips (6mm down graded) [LAA≤35]

0.3500

cum

3690.00

1291.50

0.3500

cum

Stone Dust (2.38mm down)

1500.00

525.00

113.2800

kg

49.00

5550.72

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.2500

day

450.00

112.50

Bitumen [Grade 80/100]

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0600

day

3000.00

180.00

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0600

day

3000.00

180.00

Diesel

5.5000

liter

68.00

374.00

Lubricant

0.6000

liter

220.00

132.00

Foreman

0.0400

day

800.00

32.00

Asphalt Plant

0.0600

day

10000.00

600.00

AC Paver

0.0600

day

6000.00

360.00

H.C. of Dump Truck/ Tripping Trucks

0.1000

day

4500.00

450.00 13187.72

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13451.47

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14796.62

VAT

6% of Total

IT

4% of Total

986.44 657.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16440.69

Page: 94 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.06.7.2

2 [Bitumen Grade 60/70]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Stone Chips (16mm down graded) [LAA≤35]

0.3500

cum

4720.00

1652.00

Stone Chips (12mm down graded) [LAA≤35]

0.3500

cum

4320.00

1512.00

Stone Chips (6mm down graded) [LAA≤35]

0.3500

cum

3690.00

1291.50

0.3500

cum

Stone Dust (2.38mm down)

1500.00

525.00

113.2800

kg

51.00

5777.28

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.2500

day

450.00

112.50

Bitumen [Grade 60/70]

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0600

day

3000.00

180.00

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0600

day

3000.00

180.00

Diesel

5.5000

liter

68.00

374.00

Lubricant

0.6000

liter

220.00

132.00

Foreman

0.0400

day

800.00

32.00

Asphalt Plant

0.0600

day

10000.00

600.00

AC Paver

0.0600

day

6000.00

360.00

H.C. of Dump Truck/ Tripping Trucks

0.1000

day

4500.00

450.00 13414.28

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13682.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15050.82

VAT

6% of Total

IT

4% of Total

1003.39 668.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16723.14

Page: 95 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.8

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

BMPM: Providing and Laying pre-mixed bituminous macadam with hot mix plant using coarse aggregate, fine aggregate, filler and bituminous binder as per design Job Mix Formula conforming Marshall Method as per specification, LAA value of aggregate should be <=35%, water absorption not >2%, flakiness index not >35% mixed with 60/70 penetration grade straight run bitumen satisfying the requirements of ASTM/AASHTO. including screening, cleaning of chips and preparing a uniform and quality mix in Hot Mix Plant and ensuring a homogenous mix, in which all particles of the mineral aggregates are coated uniformly, carrying the hot premixed materials by means of Dump/tipper truck, spreading the mixed materials at specified laying temperature with a hydrostatic paver finisher with sensor control to the required grade, level and alignment over the prepared surface, tamping and finishing the mix at specified compacted thickness, maintaining specified camber, grade, super-elevation and cross section, through rolling with appropriate Steel Drum Roller & pneumatic multiple tire roller (8-10 tons) to full compaction, for break down, inter - mediate and finished rolling to achieve the desired density of at least 98% of that of Laboratory Marshall specimen, hand packing and pinning to give an even surface, including cost of all materials, their carriages, hire charges of Hot Mix Plant and all other machines, equipments for construction and quality control as per specification, fuels, lubricants and wages of operational staff etc. all complete as per the direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 96 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.8.1

Detailed Analysis Brief Description of Item 2 A. For Grading -1, [Bitumen Grade 60/70] (25mm nominal size, 5075mm thick.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Stone Chips (16mm down graded) [LAA≤35]

0.2025

cum

4720.00

Stone Chips (12mm down graded) [LAA≤35]

0.3375

cum

4320.00

1458.00

Stone Chips (6mm down graded) [LAA≤35]

0.3375

cum

3690.00

1245.38

Stone Dust (2.38mm down)

0.1350

cum

1500.00

202.50

92.0400

kg

51.00

4694.04

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.2500

day

450.00

112.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0600

day

3000.00

180.00

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0600

day

3000.00

180.00

Diesel

5.5000

liter

68.00

374.00

Lubricant

0.6000

liter

220.00

132.00

Foreman

0.0400

day

800.00

32.00

Asphalt Plant

0.0600

day

10000.00

600.00

AC Paver

0.0600

day

6000.00

360.00

Bitumen [Grade 60/70]

955.80

H.C. of Dump Truck/ Tripping Trucks

0.1000

day

4500.00

450.00

Stone Chips (25mm down graded) [LAA≤35]

0.3375

cum

4920.00

1660.50 12872.72

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13130.17

10% Profit ( Add 10% on Subtotal-B) :

14443.19

VAT

6% of Total

962.88

IT

4% of Total

641.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16047.98

Page: 97 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.06.8.2

Detailed Analysis Brief Description of Item 2 B. For Grading -2, [Bitumen Grade 60/70] (40mm nominal size, 75100mm thick.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Stone Chips (20mm down graded) [LAA≤35]

0.2700

cum

4930.00

Stone Chips (12mm down graded) [LAA≤35]

0.3375

cum

4320.00

1458.00

Stone Chips (6mm down graded) [LAA≤35]

0.3375

cum

3690.00

1245.38

Stone Dust (2.38mm down)

0.1350

cum

1500.00

202.50

89.6800

kg

51.00

4573.68

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.2500

day

450.00

112.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0600

day

3000.00

180.00

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0600

day

3000.00

180.00

Diesel

5.5000

liter

68.00

374.00

Lubricant

0.6000

liter

220.00

132.00

Foreman

0.0400

day

800.00

32.00

Asphalt Plant

0.0600

day

10000.00

600.00

AC Paver

0.0600

day

6000.00

360.00

Bitumen [Grade 60/70]

1331.10

H.C. of Dump Truck/ Tripping Trucks

0.1000

day

4500.00

450.00

Stone Chips (38mm down graded) [LAA≤35]

0.2700

cum

4850.00

1309.50 12776.66

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13032.19

10% Profit ( Add 10% on Subtotal-B) :

14335.41

VAT

6% of Total

955.69

IT

4% of Total

637.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15928.23

Page: 98 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.1

Detailed Analysis Brief Description of Item 2 PS: Providing and laying polythene sheet (0.18mm thick) on prepared road surface underneath the cement concrete, etc. all complete as per specifications and direction of the Engineering-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

0.18mm thick polythene sheet

1.0000

m2

12.31

12.31

Ordinary Labour

0.0010

day

370.00

0.37 12.68

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14.23

VAT

6% of Total

0.95

IT

4% of Total

0.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15.81

Page: 99 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.2.1

Detailed Analysis Brief Description of Item 2 RCC-17BCCM(RW): Providing and laying reinforced, dowel jointed, cement concrete pavement over a prepared sub-base with picked brick chips and minimum cement contents ralates to nominal mix ratio 1:2:4 and maximum water cement ratio 0.45 having minimum required average strength f'cr = 24 MPa and satisfying specified minimum compressive strength f'c = 17 MPa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, best quality sand [50% quantity of medium sand (FM. 1.2) and 50% quantity of coarse sand of equivalent FM = 2.2] and 25mm down well graded picked brick chips (LAA value & maximum water absorption not exceeding 38 & 15% respectively) conforming ASTM C-33 including breaking chips and screening, making, placing steel shutter in position and maintaining true to the alignment, making shutter water-tight properly, placing reinforcement in position, mixing in a batching and mixing plant as per approved mix design unless other wise approved by the Engineer, transported to site, laid with a fixed form, compacting by vibrator machine and finished in a continuous operation including provision of contraction, expansion and longitudinal joints, joint filler, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing for 28 days, finishing to lines and grades, removing centering-shuttering after specified time approved, as per drawing complete, etc. all complete approved and accepted by the E-I-C. Additional quantity of cement to be added if required to attain the strength at the contractors own cost. (Rate is excluding the cost of all reinforcement and its fabrication, admixtures and joint sealant, etc.)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

25mm down graded Brick Chips

0.8570

cum

2895.00

2481.02

Sand (FM - 2.5)

0.4290

m3

1500.00

643.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0480

bag

430.00

2600.64

Head Mason

0.0800

day

650.00

52.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Page: 100 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Form Work:

( +.75 % on Subtotal-A )

Subtotal-A1:

Subtotal-C:

51.00 6851.66

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6988.69

10% Profit ( Add 10% on Subtotal-B) :

7687.56

VAT

6% of Total

IT

4% of Total

512.50 341.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8 6800.66

Subtotal-A:

Subtotal-B:

Amount

8541.74

Page: 101 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.2.2

Detailed Analysis Brief Description of Item 2 RCC-20BCCM(RW): Providing and laying reinforced, cement concrete pavement over a prepared sub-base with picked brick chips and minimum cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 28.5 Mpa and satisfying a compressive strength f'c = 20 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, with best quality coarse sand (FM. 2.2) and 25mm down well graded picked brick chips (LAA value & maximum water absorption not exceeding 38 & 15% respectively) conforming ASTM C-33 including breaking chips and screening, making, placing steel shutter in position and maintaining true to the alignment, making shutter water-tight properly, placing reinforcement in position, mixing in a batching and mixing plant as per approved mix design unless other wise approved by the Engineer, transported to site, laid with a fixed form, compacting by vibrator machine and finished in a continuous operation including provision of contraction, expansion and longitudinal joints, joint filler, joint sealant, de-bonding strip, dowel bar, tie rod, admixtures as approved, curing for 28 days, finishing to lines and grades, removing centering-shuttering after specified time approved, as per drawing complete, etc. all complete approved and accepted by the E-I-C. Additional quantity of cement to be added if required to attain the specified strength at the contractors own cost. (Rate is excluding the cost of all reinforcement and its fabrication, admixtures and joint sealant, etc.)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

25mm down graded Brick Chips

0.8180

cum

2895.00

2368.11

Sand (FM - 2.5)

0.2460

m3

1500.00

369.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.6970

bag

430.00

3309.71

Head Mason

0.0800

day

650.00

52.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1640

m3

970.00

159.08

Page: 102 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Form Work:

( +.75 % on Subtotal-A )

Subtotal-A1:

Subtotal-C:

54.61 7336.01

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7482.73

10% Profit ( Add 10% on Subtotal-B) :

8231.00

VAT

6% of Total

IT

4% of Total

548.73 365.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8 7281.40

Subtotal-A:

Subtotal-B:

Amount

9145.56

Page: 103 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.3.1

Detailed Analysis Brief Description of Item 2 RCC-20SCBP(RW): Providing and laying reinforced, cement concrete pavement over a prepared sub-base with crushed stone chips and minimum cement content relates to mix ratio 1:2:4 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 28.5 Mpa and satisfying a compressive strength f'c = 20 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), best quality coarse sand [FM: 2.2] and 25mm down well graded crushed stone chips (Preferably stone chips from Madhyapara, Dinajpur), (LAA value not exceeding 35) conforming ASTM C-33 including breaking chips and screening, making, placing steel shutter in position and maintaining true to the alignment, making shutter water-tight properly, placing reinforcement in position, mixing in a batching and mixing plant as per approved mix design unless other wise approved by the Engineer, transported to site, laid with a fixed form, compacting by vibrator machine and finished in a continuous operation including provision of contraction, expansion and longitudinal joints, joint filler, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing for 28 days, finishing to lines and grades, removing centering-shuttering after specified time approved, as per drawing complete, etc. all complete approved and accepted by the E-I-C. Additional quantity of cement to be added if required to attain the specified strength at the contractors own cost. (Rate is excluding the cost of all reinforcement and its fabrication, admixtures and joint sealant, etc.)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (25mm down graded) [LAA≤35]

0.5160

cum

4920.00

2538.72

Stone Chips (12mm down graded) [LAA≤35]

0.3440

cum

4320.00

1486.08

Sand (FM - 2.5)

0.2460

m3

1500.00

369.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0480

bag

430.00

2600.64

Head Mason

0.0800

day

650.00

52.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20

0.0083

day

23000.00

190.90

Page: 104 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum/hour Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Diesel

0.7000

liter

68.00

47.60

Sand (FM - 1.8)

0.1640

m3

970.00

159.08 8686.82

Subtotal-A: Form Work:

( +.75 % on Subtotal-A )

Subtotal-A1:

8751.97

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8927.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9819.71

VAT

6% of Total

IT

4% of Total

654.65 436.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

65.15

10910.79

Page: 105 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.3.2

Detailed Analysis Brief Description of Item 2 RCC-25SCBP(RW): Providing and laying reinforced, cement concrete pavement over a prepared sub-base with crushed stone chips and minimum cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 33.5 Mpa and satisfying a compressive strength f'c = 25 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), best quality coarse sand of equivalent FM = 2.5 and 25mm down well graded crushed stone chips (Preferably stone chips from Madhyapara, Dinajpur), (LAA value not exceeding 30) conforming ASTM C-33 including breaking chips and screening, making, placing steel shutter in position and maintaining true to the alignment, making shutter watertight properly, placing reinforcement in position, mixing in a batching and mixing plant as per approved mix design unless other wise approved by the Engineer, transported to site, laid with a fixed form, compacting by vibrator machine and finished in a continuous operation including provision of contraction, expansion and longitudinal joints, joint filler, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing for 28 days, finishing to lines and grades, removing centering-shuttering after specified time approved, as per drawing complete, etc. all complete approved and accepted by the E-I-C. Additional quantity of cement to be added if required to attain the specified strength at the contractors own cost. (Rate is excluding the cost of all reinforcement and its fabrication, admixtures and joint sealant, etc.)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (25mm down graded)[LAA≤30]

0.4910

cum

5220.00

2563.02

Stone Chips (12mm down graded) [LAA≤30]

0.3270

m3

4470.00

1461.69

Sand (FM - 2.5)

0.4290

m3

1500.00

643.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.6970

bag

430.00

3309.71

Head Mason

0.0800

day

650.00

52.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.5000

day

370.00

555.00

Page: 106 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Diesel

0.7000

liter

68.00

47.60 9511.22

Subtotal-A: Form Work:

( +.75 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

71.33 9582.55

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

9774.21 10751.63

10% Profit ( Add 10% on Subtotal-B) :

VAT

716.78 477.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11946.25

Page: 107 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.3.3

Detailed Analysis Brief Description of Item 2 RCC-30SCBP(RW): Providing and laying reinforced, dowel jointed, cement concrete pavement over a prepared base/sub-base with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 38.5 MPa and satisfying a specified compressive strength, f'c = 30 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C-494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self-compacting concrete), sand of minimum FM 2.50 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C-33 including breaking chips, screening through proper sieves, cleaning, placing steel shutter in position and maintaining true to the alignment, making shutter watertight properly, placing reinforcement in position, mixing in a batching and mixing in mechanized batch mix plant, transported to site, laid with a fixed form (pumping using line pump or boom placer), maintaining allowable slump of 75mm to 100mm, casting in forms, compacting by mechanical vibrator machine and finished in a continuous operation including provision of contraction, expansion and longitudinal joints, joint filler, joint sealant, debonding strip, dowel bar, tie rod, admixtures as approved, curing for 28 days, finishing to lines and grades, removing centering-shuttering after specified time approved, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and its fabrication, placing, binding and, dowel bar and joint sealant etc. is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the required strength at the contractors own cost. The Mix Design has to be approved by the Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (25mm down graded)[LAA≤30]

0.3711

cum

5220.00

1937.14

Stone Chips (12mm down graded) [LAA≤30]

0.3711

m3

4470.00

1658.82

Sand (FM - 2.5)

0.4485

m3

1500.00

672.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

8.7000

bag

430.00

3741.00

Page: 108 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Head Mason

0.0800

day

650.00

52.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Diesel

0.7000

liter

68.00

47.60 9588.01

Subtotal-A: Cost of Form Works/Shuttering, Prop/necessary supports, etc.

( +.75 % on Subtotal-A )

Subtotal-A1:

71.91 9659.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9853.12 10838.43 722.56 481.71

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12042.70

Page: 109 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.4

Detailed Analysis Brief Description of Item 2 KS(RW): Manufacturing, Supplying and Fixing of cement concrete kerb stone with top and bottom thickness 120mm and 150mm respectively, width 380mm and height 550mm as per approved drawing for side of footpath/median/road island etc. using steel shutter, with 6mm downgraded Stone Chips of LAA value ≤35%, sand (FM>=2.2) and minimum cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N content relates to mix ratio 1:2:4 satisfying specified minimum required average strength, f'cr = 28.5 MPa and satisfying a compressive strength f'c = 20 MPa at 28 days on standard cylinders, including grading, washings stone chips, mixing in standard mixture machine, casting in forms, making shutter water-tight properly, compacting by vibrator machine and curing for at least 28 days, including preparation kerb foundation, true to level, maintaining alignment and height, including carrying and placing kerb stone, filling interstices of kerb stone tightly with cement mortar (1:4), raking out joints, cleaning and soaking kerb stone at least for 24 hours before use, curing for requisite period, etc. all complete as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Stone Chips (6mm down graded) [LAA≤35]

0.0643

cum

3690.00

237.27

Sand (FM - 2.5)

0.0210

m3

1500.00

31.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.4740

bag

430.00

203.82

Head Mason

0.0010

day

650.00

0.65

Mason

0.0120

day

550.00

6.60

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0054

day

1200.00

6.48

Hire and running charges of Concrete Vibrator

0.0054

day

400.00

2.16

Sand (FM - 1.8)

0.0140

m3

970.00

13.58 699.56

Subtotal-A: Form Work:

( +2.50 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

17.49 717.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

731.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

804.53 Page: 110 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

8 53.64 35.76

Total: 3.07.5

Amount

893.92

Admixture: Supplying and mixing specified type chemical admixture delivered from an authorized local agent or manufacturer, comply with the ASTM C 494 requirements, confirming the current compliance of the admixture to specification requirements like physical properties, unifomity and equivalence in composition etc., performance (water content, fresh concrete setting time and compressive strength) requirements, delivered in sealed water-tight containers having and confirming plainly marked the proprietary name of the admixture, type under this specification, net weight or volume, manufacturing and expiry date, non aggressiveness to environment, aggregates and metals in concrete etc. and mixing the admixture in non prestressed cement concrete mixture in the field under the strict accordance with manufacturers recommendation and instruction, providing safety provisions in all respects etc. all complete as per instruction and approved by the E-I-C. Dose (quantity in milliliters per 50 kg bag cement) and brand/origin/manufacturer with respect to particular brand of cement and particular stock of aggregates and method of use to be determined by mix design/ trial mix at the cost borne by the Contractor and shall be carried out prior to start the work. Note: The minimum cement specified shall not be reduced on account of the use of admixtures. Use of admixture (Type/Brand/Dosages, etc.) is subject to prior approval of The Engineer supported by appropriate test report from designated Material Testing Laboratory like BUET/CQCL, LGED or equivalent.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 111 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.5.01

Detailed Analysis Brief Description of Item 2 WRCA(T-A): Water Reducing Chemical Admixture in concrete, complying to ASTM C 494 Type - A of approved brand/ origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces quantity of mixing water required to produce concrete of a given consistency.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

130.00

130.00

litre

Water reducing chemical admixture : Type-A

1.0000

liter

130.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.20 135.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

137.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

151.69

VAT

6% of Total

10.11

IT

4% of Total

6.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

168.55

Page: 112 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.5.02

Detailed Analysis Brief Description of Item 2 RCA(T-B): Retarding Chemical Admixture in concrete, complying to ASTM C 494 Type B of approved brand/origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that retards the setting of concrete, there by reducing shrinkage in concrete specially for concrete laid in thick layers and intended delayed construction for improved construction joints, reconcreting etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

125.00

125.00

litre

Retrading chemical admixture : Type-B

1.0000

liter

125.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.00 130.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145.86

VAT

6% of Total

9.72

IT

4% of Total

6.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

162.07

Page: 113 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.5.03

Detailed Analysis Brief Description of Item 2 ACA(T-C): Accelerating Chemical Admixture in concrete, complying to ASTM C 494 Type C of approved brand/origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that accelerates the setting time and early strength developmnet of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

135.00

135.00

litre

Accelerating chemical admixture : Type-C

1.0000

liter

135.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.40 140.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

143.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

157.53

VAT

6% of Total

10.50

IT

4% of Total

7.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

175.03

Page: 114 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.5.04

Detailed Analysis Brief Description of Item 2 WRRCA(T-D): Water-Reducing and Retarding Chemical Admixture in concrete, complying to ASTM C 494 Type D of approved brand/ origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces the quantity of mixing water required to produce concrete of a given consistency i.e. low w/c ratio and retards the setting of concrete specially for layerd, thick laid concrete etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

125.00

125.00

litre

Water-reducing and retrading chemical admixture : Type-D

1.0000

liter

125.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.00 130.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145.86

VAT

6% of Total

9.72

IT

4% of Total

6.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

162.07

Page: 115 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.5.05

Detailed Analysis Brief Description of Item 2 WRACA(T-E): Water-Reducing and Accelerating Chemical Admixture in concrete, complying ASTM C 494 Type E of approved brand/origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces the quantity of mixing water required to produce concrete of a given consistency i.e. low w/c ratio and accelerates setting and early strength development of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

135.00

135.00

litre

Water-reducing and accelerating chemical admixture : Type-E

1.0000

liter

135.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.40 140.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

143.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

157.53

VAT

6% of Total

10.50

IT

4% of Total

7.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

175.03

Page: 116 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.5.06

Detailed Analysis Brief Description of Item 2 WRACA(T-F): Supply and use of water-reducing high range chemical admixture in concrete, complying to ASTM C 494 Type F of approved brand/origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces the quantity of mixing water required to produce concrete of a given consistency by 12 or greater (flowing concrete) and for higher strength of concrete

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

160.00

160.00

litre

Water-reducing high range chemical admixture : Type-F

1.0000

liter

160.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

6.40 166.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

186.70

VAT

6% of Total

12.45

IT

4% of Total

8.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

207.45

Page: 117 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.07.5.07

Detailed Analysis Brief Description of Item 2 WRACA(T-G): Supply and use of water-reducing high range and retarding chemical admixture in concrete, complying to ASTM C 494 Type G of approved brand/ origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces the quantity of mixing water required to produce concrete of a given consistency by 12% or greater (flowing concrete) and retards setting of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

160.00

160.00

litre

Water-reducing high range and retrading chemical admixture : Type-G

1.0000

liter

160.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

6.40

Subtotal-A1:

166.40

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.73

10% Profit ( Add 10% on Subtotal-B) :

186.70

VAT

6% of Total

IT

4% of Total

12.45 8.30 Total:

3.08.1.1

PiBFS: Labour charge for picking up the existing brick flat (BFS) soling and staking the materials at a specified distance, etc. all complete as per direction of the E-I-C.

sqm

Ordinary Labour

0.0330

day

370.00

12.21 12.21

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13.70

VAT

6% of Total

IT

4% of Total

0.91 0.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

207.45

15.22

Page: 118 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.1.2

Detailed Analysis Brief Description of Item 2 PiHBB: Labour charge for picking up the existing HBB and staking the materials at a specified distance, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

sqm

Ordinary Labour

0.0500

18.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18.87

10% Profit ( Add 10% on Subtotal-B) :

20.76

VAT

6% of Total

IT

4% of Total

1.38 0.92 Total:

3.08.2.1

ReBFS(FM-0.50): Labour charge for Resetting of Single layer brick flat soling (BFS) with 1st class or picked bricks, true to level, maintaining camber/super elevation and grade including carrying bricks, supplying and filling the interstices tightly with sand of minimum FM 0.50, etc. all complete as per direction of the E-I-C.

23.06

sqm

Sand (FM - 0.5)

0.0120

m3

420.00

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0500

day

370.00

18.50

Subtotal-B: Subtotal-C:

5.04

29.04

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

29.62

10% Profit ( Add 10% on Subtotal-B) :

32.58

VAT

6% of Total

2.17

IT

4% of Total

1.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18.50

36.20

Page: 119 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.2.2

Detailed Analysis Brief Description of Item 2 ReBFS(FM-0.80): Labour charge for Resetting of Single layer brick flat soling (BFS) with 1st class or picked bricks, true to level, maintaining camber/super elevation and grade including carrying bricks, supplying and filling the interstices tightly with sand of minimum FM 0.80, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 0.8)

0.0120

m3

480.00

5.76

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0500

day

370.00

18.50 29.76

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33.39

VAT

6% of Total

IT

4% of Total

2.23 1.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

37.10

Page: 120 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.2.3

Detailed Analysis Brief Description of Item 2 ReBFS(FM<0.50): Labour charge for Resetting of Single layer brick flat soling (BFS) with 1st class or picked bricks, true to level, maintaining camber/super elevation and grade including carrying bricks, supplying and filling the interstices tightly with locally available sand (passing <=15% through #200 sieve), etc. all complete as per direction of the EI-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Local Sand (Sieve # 200 passing not more than 15%)

0.0120

m3

350.00

4.20

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0500

day

370.00

18.50 28.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

31.64

VAT

6% of Total

2.11

IT

4% of Total

1.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

35.16

Page: 121 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.3.1

Detailed Analysis Brief Description of Item 2 ReHBB(FM-0.50): Labour charge for Resetting of Brick on edge pavement in single layer of Herring Bone Bond (HBB) with 1st class or picked bricks true to level, maintaining camber, super elevation and grade over 25mm thick sand (minimum FM 0.50) cushion including filling the interstices tightly with same type of sand, etc. including supplying sand all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 0.5)

0.0280

m3

420.00

11.76

Mason

0.0300

day

550.00

16.50

Ordinary Labour

0.0850

day

370.00

31.45 59.71

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

60.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

66.99

VAT

6% of Total

4.47

IT

4% of Total

2.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

74.44

Page: 122 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.3.2

Detailed Analysis Brief Description of Item 2 ReHBB(FM-0.80): Labour charge for Resetting of Brick on edge pavement in single layer of Herring Bone Bond (HBB) with 1st class or picked bricks true to level, maintaining camber, super elevation and grade over 25mm thick sand (minimum FM 0.80) cushion including filling the interstices tightly with same type of sand, etc. including supplying sand all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 0.8)

0.0280

m3

480.00

13.44

Mason

0.0300

day

550.00

16.50

Ordinary Labour

0.0850

day

370.00

31.45 61.39

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

68.88

VAT

6% of Total

4.59

IT

4% of Total

3.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

76.53

Page: 123 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.3.3

Detailed Analysis Brief Description of Item 2 ReHBB(FM<0.50): Labour charge for Resetting of Brick on edge pavement in single layer of Herring Bone Bond (HBB) with 1st class or picked bricks true to level, maintaining camber, super elevation and grade over 25mm thick locally available sand (passing<=15% through #200 sieve) cushion including filling the interstices tightly with same type of sand, etc. including supplying sand all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Local Sand (Sieve # 200 passing not more than 15%)

0.0280

m3

350.00

9.80

Mason

0.0300

day

550.00

16.50

Ordinary Labour

0.0850

day

370.00

31.45 57.75

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58.91

10% Profit ( Add 10% on Subtotal-B) :

64.80

VAT

6% of Total

IT

4% of Total

4.32 2.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

72.00

Page: 124 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.4.1

Detailed Analysis Brief Description of Item 2 SBFS(FM-0.50): Providing Single layer brick flat soling (BFS) with 1st class or picked bricks, true to level, maintaining camber/super elevation and grade including carrying bricks, filling the interstices tightly with sand of minimum FM 0.50, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick

31.0000

each

9.00

279.00

Sand (FM - 0.5)

0.0120

m3

420.00

5.04

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0500

day

370.00

18.50 308.04

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

314.20

10% Profit ( Add 10% on Subtotal-B) :

345.62

VAT

6% of Total

IT

4% of Total

23.04 15.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

384.02

Page: 125 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.4.2

Detailed Analysis Brief Description of Item 2 SBFS(FM-0.80): Providing Single layer brick flat soling (BFS) with 1st class or picked bricks, true to level, maintaining camber/super elevation and grade including carrying bricks, filling the interstices tightly with sand of minimum FM 0.80, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick

31.0000

each

9.00

279.00

Sand (FM - 0.8)

0.0120

m3

480.00

5.76

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0500

day

370.00

18.50 308.76

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

314.94

10% Profit ( Add 10% on Subtotal-B) :

346.43

VAT

6% of Total

IT

4% of Total

23.10 15.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

384.92

Page: 126 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.4.3

Detailed Analysis Brief Description of Item 2 SBFS(FM<0.50): Providing Single layer brick flat soling (BFS) with 1st class or picked bricks, true to level, maintaining camber/super elevation and grade including carrying bricks, filling the interstices tightly with locally available sand (passing <=15% through#200 sieve), etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick

31.0000

each

9.00

279.00

Local Sand (Sieve # 200 passing not more than 15%)

0.0120

m3

350.00

4.20

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0500

day

370.00

18.50 307.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

313.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

344.68

VAT

6% of Total

IT

4% of Total

22.98 15.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

382.98

Page: 127 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.5.1

Detailed Analysis Brief Description of Item 2 SHBB(FM-0.50): Providing Brick on edge pavement in single layer of Herring Bone Bond (HBB) with 1st class or picked bricks true to level, maintaining camber, super elevation and grade, including supplying and laying 25mm thick sand (FM 0.50) cushion over the BFS, filling the interstices tightly with same type of sand, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-incharge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick

52.0000

each

9.00

468.00

Sand (FM - 0.5)

0.0280

m3

420.00

11.76

Mason Ordinary Labour

0.0300

day

550.00

16.50

0.0850

day

370.00

31.45 527.71

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

538.26

10% Profit ( Add 10% on Subtotal-B) :

592.09

VAT

6% of Total

39.47

IT

4% of Total

26.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

657.88

Page: 128 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.5.2

Detailed Analysis Brief Description of Item 2 SHBB(FM-0.80): Providing Brick on edge pavement in single layer of Herring Bone Bond (HBB) with 1st class or picked bricks true to level, maintaining camber, super elevation and grade, including supplying and laying 25mm thick sand (FM 0.80) cushion over the BFS, filling the interstices tightly with same type of sand, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-incharge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick

52.0000

each

9.00

468.00

Sand (FM - 0.8)

0.0280

m3

480.00

13.44

Mason Ordinary Labour

0.0300

day

550.00

16.50

0.0850

day

370.00

31.45 529.39

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

539.98

10% Profit ( Add 10% on Subtotal-B) :

593.98

VAT

6% of Total

39.60

IT

4% of Total

26.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

659.97

Page: 129 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.08.5.3

Detailed Analysis Brief Description of Item 2 SHBB(FM<0.50): Providing Brick on edge pavement in single layer of Herring Bone Bond (HBB) with 1st class or picked bricks true to level, maintaining camber, super elevation and grade, including supplying and laying 25mm thick sand (passing<=15% through #200 sieve) cushion over the BFS, filling the interstices tightly with same type of sand, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick

52.0000

each

9.00

468.00

Local Sand (Sieve # 200 passing not more than 15%)

0.0280

m3

350.00

9.80

Mason Ordinary Labour

0.0300

day

550.00

16.50

0.0850

day

370.00

31.45 525.75

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

536.27

10% Profit ( Add 10% on Subtotal-B) :

589.89

VAT

6% of Total

39.33

IT

4% of Total

26.22 Total:

3.09.1.1

PiCCB: Labour charge for picking up the existing CC Block (375mmX100mmX225mm) on End Edging, including staking the materials at a specified distance, etc. all complete as per direction of the E-I-C.

m

Ordinary Labour

0.0670

day

370.00

Subtotal-B: Subtotal-C:

24.79 24.79

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25.29

10% Profit ( Add 10% on Subtotal-B) :

27.81

VAT

6% of Total

IT

4% of Total

1.85 1.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

655.44

30.90

Page: 130 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.1.2

Detailed Analysis Brief Description of Item 2 PiCCB: Labour charge for picking up the existing CC Block L:1000mmXH:500mmXW:(100mm+150mm)] on End Edging, including staking the materials at a specified distance, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

m

Ordinary Labour

0.2000

74.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

75.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

83.03

VAT

6% of Total

5.54

IT

4% of Total

3.69 Total:

3.09.2

PiCCB(cum): Labour charge for picking up the existing CC Block of any sizes on soling or slope of embankment, including staking the materials at a specified distance, etc. all complete as per direction of the E-I-C.

92.25

cum

Ordinary Labour

0.6700

day

370.00

Subtotal-B: Subtotal-C:

247.90 247.90

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

252.86

10% Profit ( Add 10% on Subtotal-B) :

278.14

VAT

6% of Total

18.54

IT

4% of Total

12.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

74.00

309.05

Page: 131 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.3.1

Detailed Analysis Brief Description of Item 2 ReCCB: Labour charge for Resetting the CC Block on End Edging (100mm across) with CC Block (375mmX100mmX225mm), including cutting trenches true to level & grade, removing earth, re-filling & ramming the sides properly, including supplying and filling the gaps with local sand (FM - 0.5), etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Mason

0.0083

day

550.00

4.57

Ordinary Labour

0.0833

day

370.00

30.82

Sand (FM - 0.5)

0.0010

m3

420.00

0.42 35.81

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

36.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

40.17

VAT

6% of Total

2.68

IT

4% of Total

1.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

44.64

Page: 132 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.3.2

Detailed Analysis Brief Description of Item 2 ReCCB: Labour charge for Resetting the CC Block on End Edging (Average 125mm across) with CC Block [L:1000mmXH:500mmXW:(100mm+150mm)], including cutting trenches true to level & grade, removing earth, re-filling & ramming the sides properly, including supplying and filling the gaps with local sand (FM - 0.5), etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Mason

0.0030

day

550.00

1.65

Ordinary Labour

0.3000

day

370.00

111.00

Sand (FM - 0.5)

0.0010

m3

420.00

0.42 113.07

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

115.33

10% Profit ( Add 10% on Subtotal-B) :

126.86

VAT

6% of Total

IT

4% of Total

8.46 5.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

140.96

Page: 133 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.4

Detailed Analysis Brief Description of Item 2 ReCCB(cum): Labour charge for Setting/Resetting of single layer CC Block of different sizes on road top, including preparation base, true to level, maintaining camber, super elevation, grade, watering and ramming the base, including carrying CC blocks, supplying and filling the interstices tightly with sand (FM - 0.5), etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-incharge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Sand (FM - 0.5)

0.0427

m3

420.00

17.93

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.3000

day

450.00

135.00

Ordinary Labour

1.3000

day

370.00

481.00 644.93

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

657.83

10% Profit ( Add 10% on Subtotal-B) :

723.62

VAT

6% of Total

48.24

IT

4% of Total

32.16 Total:

3.09.5

Amount

804.02

CCBSS-PW: Manufacturing and supplying Plain Cement Concrete (PCC) Blocks with cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, using steel shutter, with 40mm down graded Stone Shingles, sand (FM>=1.5) and minimum cement content relates to mix ratio 1:3.6 satisfying specified minimum compressive strength 10.0Mpa at 28 days, including grading, washings shingles, mixing in standard mixture machine, casting in forms, making shutter water-tight properly, compacting by vibrator machine and curing for at least 28 days, including preparation of platform, shuttering and stacking in measurable stacks etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 134 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.5.1

Detailed Analysis Brief Description of Item 2 PCC Block Size: 400mmX200mmX150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0108

m3

3500.00

37.80

Sand (FM - 1.5)

0.0054

m3

795.00

4.29

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0508

bag

430.00

21.84

Mason

0.0010

day

550.00

0.55

Skilled Labour

0.0058

day

450.00

2.61

Ordinary Labour

0.0216

day

370.00

7.99

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0009

day

1200.00

1.08

Hire and running charges of Concrete Vibrator

0.0009

day

400.00

0.36 76.53

Subtotal-A: Form Work:

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1.91 78.44

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

80.01

10% Profit ( Add 10% on Subtotal-B) :

88.01

VAT

6% of Total

IT

4% of Total

5.87 3.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

97.79

Page: 135 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.5.2

Detailed Analysis Brief Description of Item 2 PCC Block Size: 375mmX100mmX225mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0076

m3

3500.00

26.60

Sand (FM - 1.5)

0.0038

m3

795.00

3.02

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0357

bag

430.00

15.35

Mason

0.0010

day

550.00

0.55

Skilled Labour

0.0051

day

450.00

2.30

Ordinary Labour

0.0190

day

370.00

7.03

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0008

day

1200.00

0.96

Hire and running charges of Concrete Vibrator

0.0008

day

400.00

0.32 56.13

Subtotal-A: Form Work:

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1.40 57.53

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58.68

10% Profit ( Add 10% on Subtotal-B) :

64.55

VAT

6% of Total

IT

4% of Total

4.30 2.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

71.72

Page: 136 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.5.3

Detailed Analysis Brief Description of Item 2 PCC Block Size: 1000mmX500mmX(100+150)mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0563

m3

3500.00

197.05

Sand (FM - 1.5)

0.0281

m3

795.00

22.34

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2646

bag

430.00

113.78

Mason

0.0050

day

550.00

2.75

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.1125

day

370.00

41.63

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0045

day

1200.00

5.40

Hire and running charges of Concrete Vibrator

0.0045

day

400.00

1.80 398.24

Subtotal-A: Form Work:

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

9.96 408.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

416.36

10% Profit ( Add 10% on Subtotal-B) :

458.00

VAT

6% of Total

IT

4% of Total

30.53 20.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

508.89

Page: 137 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.6.1

Detailed Analysis Brief Description of Item 2 CCBSS-EE: Providing PCC Block on End Edging (100mm across) of size (375mmX100mmX225mm), including manufacturing and supplying Plain Cement Concrete (PCC) Blocks with cement conforming to BDS EN 1971 : 2003 CEM-II/A-M 42.5N, using steel shutter, with 40mm down graded Stone Shingles, sand (FM>=1.5) and minimum cement content relates to mix ratio 1:3.6 satisfying specified minimum compressive strength 10.0Mpa at 28 days, including cutting trenches true to level & grade, removing earth, re-filling & ramming the sides properly, including supplying and filling the gaps with local sand (FM - 0.5), etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Manufacturing and supplying CC blocks Size 375mmx100mmx225mm…..(3.09.5.2)

2.6500

each

57.53

152.45

Sand (FM - 0.5)

0.0010

m3

420.00

0.42

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.1000

day

370.00

37.00 195.37

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

199.28

10% Profit ( Add 10% on Subtotal-B) :

219.21

VAT

6% of Total

14.61

IT

4% of Total

9.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

243.57

Page: 138 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.6.2

Detailed Analysis Brief Description of Item 2 CCBSS-EE-SR: Providing CC Block on End Edging (average 125mm across) for submersible road of size [L: 1000mmXH: 500mmXW:(100mm+150mm)], including manufacturing and supplying Plain Cement Concrete (PCC) Blocks with cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, using steel shutter, with 40mm down graded Stone Shingles, sand (FM>=1.5) and minimum cement content relates to mix ratio 1:3.6 satisfying specified minimum compressive strength 10.0Mpa at 28 days, including cutting trenches true to level & grade, removing earth, re-filling & ramming the sides properly, including supplying and filling the gaps with local sand (FM - 0.5), etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

408.20

408.20

m

Manufacturing and supplying CC blocks with cement, sand (FM>=1.5) 1000mmx500mmx(100+150)mm …………(3.09.5.3)

1.0000

each

Sand (FM - 0.5)

0.0010

m3

420.00

0.42

Mason

0.0030

day

550.00

1.65

Ordinary Labour

0.3000

day

370.00

111.00 521.27

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

531.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

584.86

VAT

6% of Total

38.99

IT

4% of Total

25.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

649.85

Page: 139 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.7

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

CCBSC-RW: Manufacturing and supplying Plain Cement Concrete (PCC) Blocks with cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, for road pavement works using steel shutter, with 40mm down graded Stone Chips, sand (FM>=1.8) and minimum cement content relates to mix ratio 1:2:4 satisfying specified minimum compressive strength 20.0Mpa at 28 days, including grading, washings stone chips, mixing in standard mixture machine, casting in forms, making shutter water-tight properly, compacting by vibrator machine and curing for at least 28 days, including preparation of platform, shuttering and stacking in measurable stacks etc.all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. [Excluding the cost of labour charge for block setting].

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 140 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.7.1

Detailed Analysis Brief Description of Item 2 PCC Block Size: 375mmX225mmX150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Chips (38mm down graded) [LAA≤35]

0.0076

cum

4850.00

36.86

Stone Chips (16mm down graded) [LAA≤35]

0.0033

cum

4720.00

15.58

Sand (FM - 1.8)

0.0054

m3

970.00

5.24

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0765

bag

430.00

32.90

Mason

0.0010

day

550.00

0.55

Skilled Labour

0.0061

day

450.00

2.75

Ordinary Labour

0.0228

day

370.00

8.44

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0009

day

1200.00

1.08

Hire and running charges of Concrete Vibrator

0.0009

day

400.00

0.36 103.74

Subtotal-A: Form Work:

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2.59 106.33

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

108.46

10% Profit ( Add 10% on Subtotal-B) :

119.31

VAT

6% of Total

IT

4% of Total

7.95 5.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

132.56

Page: 141 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.8

Detailed Analysis Brief Description of Item 2 CCBSC-RW: Providing single layer PCC Block on road top of size (375mmX225mmX150mm), including manufacturing and supplying Plain Cement Concrete (PCC) Blocks with cement conforming to BDS EN 1971 : 2003 CEM-II/A-M 42.5N, using steel shutter, with 40mm down graded Stone Chips, sand (FM>=1.8) and minimum cement content relates to mix ratio 1:2.4 satisfying specified minimum compressive strength 20.0Mpa at 28 days, including preparation of bed by cutting or filling with ramming the filled up earth to the same profile as that of the finished pavement, including carrying and placing PCC blocks, filling the interstices tightly with sand (FM - 0.5), etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-incharge.

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

0.0332

m3

420.00

13.94

11.0000

each

106.33

1169.67

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.2500

day

370.00

92.50

5

8

sqm

Sand (FM - 0.5) Manufacturing and supplying CC Block for road pavement works using steel shutter ….. (Size 375mmX225mmX150mm) ….. (3.09.7.1)

1285.11

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1310.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1441.90

VAT

6% of Total

96.13

IT

4% of Total

64.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1602.11

Page: 142 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.09.9

Detailed Analysis Brief Description of Item 2 LC-CCB: Labour charge for laying single layer CC Block of different sizes for protective wall, including preparation trenches, true to level, maintaining alignment, watering and ramming the base, including carrying and placing CC blocks, filling minimum 65% interstices of CC Block work tightly with cement mortar (1:6), raking out joints, cleaning and soaking Block at least for 24 hours before use, washing of sand, curing for requisite period, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. [Excluding the cost of CC Blocks].

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

0.0752

m3

584.00

43.92

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3538

bag

430.00

152.13

Head Mason

0.0200

day

650.00

13.00

Mason

0.2500

day

550.00

137.50

Skilled Labour

0.8000

day

450.00

360.00

Ordinary Labour

1.5000

day

370.00

555.00

5

8

cum

Sand (FM - 1.2)

1261.55

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1286.78

10% Profit ( Add 10% on Subtotal-B) :

1415.46

VAT

6% of Total

IT

4% of Total

94.36 62.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1572.73

Page: 143 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.01.1

Detailed Analysis Brief Description of Item 2 PPLM: Preparation of Pothole for small patch works (pothole, edge breaking, etc.) by cutting, scarifying and loosening of existing damaged Base/sub- base Course materials up to the depth of 150mm at the pothole areas in order to make regular shape of the pothole including leveling, dressing and compacting manually where mechanical compactors are not suitable to give a smooth surface including brushing, removing & stacking all debris at a safe distance etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Ordinary Labour

0.0300

day

370.00

11.10

Skilled Labour

0.0050

day

450.00

2.25 13.35

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14.98

VAT

6% of Total

1.00

IT

4% of Total

0.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16.64

Page: 144 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.01.2

Detailed Analysis Brief Description of Item 2 HBPMM: Preparation of hard bed by scarifying and loosening of existing top (bituminous) surface, including base/sub-base course materials up to the depth of 75mm (minimum) using mechanical means, breaking dismantled material into specified sizes (less than 40mm), with supplying of extra fresh base course materials of required specification (if required) including spreading, leveling, dressing of loose material uniformly for maintaining camber & grade, watering if needed, rolling with 8 to 10 MT road roller to give compaction to 100% of MDD as obtained by standard proctor test etc. all complete in all respect as per direction of the Engineer-in-charge. (Rate is excluding the cost of additional material supplied)

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

0.0055

day

450.00

2.48

Ordinary Labour

0.0280

day

370.00

10.36

H.C. of Excavator (Medium Size)

0.0006

day

8880.00

5.33

H.C. of 3 Wheel Static Road roller (8-10 ton)

0.0006

day

3500.00

2.10

Diesel

0.0150

liter

68.00

1.02

Lubricant

0.0010

liter

220.00

0.22

5

8

sqm

Skilled Labour

21.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21.93

10% Profit ( Add 10% on Subtotal-B) :

24.13

VAT

6% of Total

IT

4% of Total

1.61 1.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

26.81

Page: 145 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.02

Detailed Analysis Brief Description of Item 2 SB: Providing and applying sand blinding with sand of minimum FM 0.80 @0.005 cum per sqm on prepared road surface, including supplying of all material, their carriage, labours, tools and equipment, etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 0.8)

0.0050

m3

480.00

2.40

Ordinary Labour

0.0030

day

370.00

1.11 3.51

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3.58

10% Profit ( Add 10% on Subtotal-B) :

3.94

VAT

6% of Total

IT

4% of Total

0.26 0.18

Subtotal-C:

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4.38

Page: 146 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.03

Detailed Analysis Brief Description of Item 2 25mmSGSS: Providing 25mm thick (average) grouting with 20mm down graded broken stone shingles metal (LAA value not exceeding 35) and using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, spraying tack coat @ 0.50kg per sqm over the cleaned road surface and laying, spreading stone metal @0.028cum per sqm (loose) on the road surface, maintaining proper camber, level, grade, super elevation and spraying hot bitumen @1.50kg per sqm uniformly, including rolling hard to full compaction with 8 to 10 MT road roller including cleaning the surface & heating bitumen from 140°C to 160°C temperature and spreading crushed stone chips/Sand (FM-1.80) @0.006cum per sqm road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Shingles (20mm down graded)

0.0280

m3

3500.00

98.00

Sand (FM - 1.8)

0.0060

m3

970.00

5.82

Bitumen [Grade 80/100]

2.0000

kg

49.00

98.00

Fire wood

1.5000

kg

7.75

11.63

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0250

day

450.00

11.25

Ordinary Labour

0.0400

day

370.00

14.80

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0200

liter

68.00

1.36

Lubricant

0.0020

liter

220.00

0.44 251.40

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

256.42

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

282.07

VAT

6% of Total

18.80

IT

4% of Total

12.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

313.41

Page: 147 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.04.1

Detailed Analysis Brief Description of Item 2 50mmSGBC: Providing 50mm thick (average) grouting with picked brick chips (LAA value not exceeding 40) and using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, laying and spreading picked brick chips 60mm thick (loose) in two layers, 1st layer of 35mm thick (loose) with 25mm to 16mm size and 2nd layer of 25mm thick (loose) mixing with 80% of 16mm to 12mm size and 20% of 12mm to 8mm size picked brick chips, spraying tack coat @ 0.50kg per sqm over the cleaned road surface, maintaining proper camber, level, grade, super elevation and spraying hot bitumen @1.25kg per sqm uniformly on the 1st layer and @1.50kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller including cleaning the surface & heating bitumen from 140°C to 160°C temperature and spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class/ Picked Brick chips (40mm down graded)

0.0600

m3

2786.00

167.16

Sand (FM - 1.8)

0.0060

m3

970.00

5.82

Bitumen [Grade 80/100]

3.2500

kg

49.00

159.25

Fire wood

2.6000

kg

7.75

20.15

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0600

day

370.00

22.20

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0280

liter

68.00

1.90

Lubricant

0.0028

liter

220.00

0.62 400.70

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

408.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

449.59

VAT

6% of Total

IT

4% of Total

29.97 19.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

499.54 Page: 148 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.04.2

Detailed Analysis Brief Description of Item 2 50mmSGSS: Providing 50mm thick (average) grouting with broken stone shingles (LAA value not exceeding 35) and using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, laying and spreading stone shingles 60mm thick (loose) in two layers, 1st layer of 35mm thick (loose) with 25mm to 16mm size and 2nd layer of 25mm thick (loose) mixing with 80% of 16mm to 12mm size and 20% of 12mm to 8mm size stone shingles, spraying tack coat @ 0.50kg per sqm over the cleaned road surface, maintaining proper camber, level, grade, super elevation and spraying hot bitumen @1.25kg per sqm uniformly on the 1st layer and @1.50kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller including cleaning the surface & heating bitumen from 140°C to 160°C temperature and spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Shingles (20mm down graded)

0.0600

m3

3500.00

210.00

Bitumen [Grade 80/100]

3.2500

kg

49.00

159.25

Fire wood

2.6000

kg

7.75

20.15

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0600

day

370.00

22.20

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0280

liter

68.00

1.90

Lubricant

0.0028

liter

220.00

0.62

Sand (FM - 1.8)

0.0060

m3

970.00

5.82 443.54

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

452.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

497.65

VAT

6% of Total

IT

4% of Total

33.18 22.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

552.95 Page: 149 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.04.3

Detailed Analysis Brief Description of Item 2 50mmSGSC: Providing 50mm thick (average) grouting with broken stone metal (LAA value not exceeding 35) and using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, laying and spreading stone metal 60mm thick (loose) in two layers, 1st layer of 35mm thick (loose) with 25mm to 16mm size and 2nd layer of 25mm thick (loose) mixing with 80% of 16mm to 12mm size and 20% of 12mm to 8mm size stone metal, spraying tack coat @ 0.50kg per sqm over the cleaned road surface, maintaining proper camber, level, grade, super elevation and spraying hot bitumen @1.25kg per sqm uniformly on the 1st layer and @1.50kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller including cleaning the surface & heating bitumen from 140°C to 160°C temperature and spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Boulder

0.0600

m3

3700.00

222.00

Bitumen [Grade 80/100]

3.2500

kg

49.00

159.25

Fire wood

2.6000

kg

7.75

20.15

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0280

liter

68.00

1.90

Lubricant

0.0028

liter

220.00

0.62

Sand (FM - 1.8)

0.0060

m3

970.00

5.82 470.34

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

479.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

527.72

VAT

6% of Total

IT

4% of Total

35.18 23.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

586.36 Page: 150 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.05.1

Detailed Analysis Brief Description of Item 2 75mmSGBC: Providing 75mm thick (average) grouting with picked brick chips (LAA value not exceeding 40) and using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, laying and spreading picked brick chips 100mm thick (loose) in two layers, 1st layer of 60mm thick (loose) with 40mm to 25mm size and 2nd layer of 40mm thick (loose) mixing with 80% of 25mm to 20mm size and 20% of 20mm to 10mm size picked brick chips, maintaining proper camber, level, grade, super elevation and spraying hot bitumen @2.00kg per sqm uniformly on the 1st layer and @2.20kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller including cleaning the surface & heating bitumen from 140°C to 160°C temperature and spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

25mm down graded Brick Chips

0.0400

cum

2895.00

115.80

Sand (FM - 1.8)

0.0060

m3

970.00

5.82

Bitumen [Grade 80/100]

4.2000

kg

49.00

205.80

Fire wood

3.3600

kg

7.75

26.04

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0400

day

450.00

18.00

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0280

liter

68.00

1.90

Lubricant

0.0028

liter

220.00

0.62

1st Class/ Picked Brick chips (40mm down graded)

0.0600

m3

2786.00

167.16 588.24

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

600.00

10% Profit ( Add 10% on Subtotal-B) :

660.01

VAT

6% of Total

IT

4% of Total

44.00 29.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

733.34 Page: 151 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.05.2

Detailed Analysis Brief Description of Item 2 75mmSGSS: Providing 75mm thick (average) grouting with broken stone shingles (LAA value not exceeding 35) and using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, laying and spreading stone shingles 94mm thick (loose) in two layers, 1st layer of 56mm thick (loose) with 40mm to 25mm size and 2nd layer of 38mm thick (loose) mixing with 80% of 25mm to 20mm size and 20% of 20mm to 10mm size stone shingles, maintaining proper camber, level, grade, super elevation and spraying hot bitumen @1.50kg per sqm uniformly on the 1st layer and @2.00kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller including cleaning the surface & heating bitumen from 140°C to 160°C temperature and spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Shingles (20mm down graded)

0.0940

m3

3500.00

329.00

Bitumen [Grade 80/100]

3.5000

kg

49.00

171.50

Fire wood

2.8000

kg

7.75

21.70

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

0.0800

day

370.00

29.60

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0300

liter

68.00

2.04

Lubricant

0.0030

liter

220.00

0.66

Sand (FM - 1.8)

0.0060

m3

970.00

5.82 597.42

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

609.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

670.31

VAT

6% of Total

IT

4% of Total

44.69 29.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

744.78 Page: 152 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.05.3

Detailed Analysis Brief Description of Item 2 75mmSGSC: Providing 75mm thick (average) grouting with Stone metal (LAA value not exceeding 35) and using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, laying and spreading Stone metal 94mm thick (loose) in two layers, 1st layer of 56mm thick (loose) with 40mm to 25mm size and 2nd layer of 38mm thick (loose) mixing with 80% of 25mm to 20mm size and 20% of 20mm to 10mm size stone shingles, maintaining proper camber, level, grade, super elevation and spraying hot bitumen @1.50kg per sqm uniformly on the 1st layer and @2.00kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller including cleaning the surface & heating bitumen from 140°C to 160°C temperature and spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Boulder

0.0940

m3

3700.00

347.80

Sand (FM - 1.8)

0.0060

m3

970.00

5.82

Bitumen [Grade 80/100]

3.5000

kg

49.00

171.50

Fire wood

2.8000

kg

7.75

21.70

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0300

liter

68.00

2.04

Lubricant

0.0030

liter

220.00

0.66 623.62

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

636.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

699.70

VAT

6% of Total

46.65

IT

4% of Total

31.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

777.45

Page: 153 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.06

Detailed Analysis Brief Description of Item 2 100mmSGBC: Providing 100mm thick (average) grouting with picked brick chips (LAA value not exceeding 40) and using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, laying and spreading picked brick chips 130mm thick (loose) in two layers, 1st layer of 80mm thick (loose) with 40mm to 25mm size and 2nd layer of 50mm thick (loose) mixing with 80% of 25mm to 20mm size and 20% of 20mm to 10mm size picked brick chips, maintaining proper camber, level, grade, super elevation and spraying hot bitumen @2.00kg per sqm uniformly on the 1st layer and @3.00kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller including cleaning the surface & heating bitumen from 140°C to 160°C temperature and spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class/ Picked Brick chips (40mm down graded)

0.0800

m3

2786.00

222.88

Sand (FM - 1.2)

0.0060

m3

584.00

3.50

Bitumen [Grade 80/100]

5.0000

kg

49.00

245.00

Fire wood

4.0000

kg

7.75

31.00

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0400

day

450.00

18.00

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0280

liter

68.00

1.90

Lubricant

0.0028

liter

220.00

0.62

25mm down graded Brick Chips

0.0500

cum

2895.00

144.75 714.75

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

729.05

10% Profit ( Add 10% on Subtotal-B) :

801.95

VAT

6% of Total

IT

4% of Total

53.46 35.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

891.06 Page: 154 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.07.1

Detailed Analysis Brief Description of Item 2 50mmSGSS(BE): Providing 50mm thick (average) grouting with broken stone shingles (LAA value not exceeding 35) and using bitumen emulsion of grade k-1-60 conforming to the requirements of ASTM/AASHTO, laying and spreading stone shingles 60mm thick (loose) in two layers, 1st layer of 35mm thick (loose) with 25mm to 16mm size and 2nd layer of 25mm thick (loose) mixing with 80% of 16mm to 12mm size and 20% of 12mm to 8mm size stone shingles, spraying tack coat @ 0.750kg per sqm over the cleaned road surface, maintaining proper camber, level, grade, super elevation and spraying bitumen emulsion @1.75kg per sqm uniformly on the 1st layer and @2.00kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller and cleaning the surface, spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Shingles (20mm down graded)

0.0600

m3

3500.00

210.00

Bitumen Emulsion

4.5000

kg

61.00

274.50

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0500

day

370.00

18.50

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0280

liter

68.00

1.90

Lubricant

0.0028

liter

220.00

0.62

Sand (FM - 1.5)

0.0060

m3

795.00

4.77 533.89

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

544.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

599.02

VAT

6% of Total

IT

4% of Total

39.93 26.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

665.58

Page: 155 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.07.2

Detailed Analysis Brief Description of Item 2 75mmSGSS(BE): Providing 75mm thick (average) grouting with broken stone shingles (LAA value not exceeding 35) and using bitumen emulsion of grade k-1-60 conforming to the requirements of ASTM/AASHTO, laying and spreading stone shingles 94mm thick (loose) in two layers, 1st layer of 56mm thick (loose) with 40mm to 25mm size and 2nd layer of 38mm thick (loose) mixing with 80% of 25mm to 20mm size and 20% of 20mm to 10mm size stone shingles, maintaining proper camber, level, grade, super elevation and spraying bitumen emulsion @2.25kg per sqm uniformly on the 1st layer and @3.00kg per sqm on 2nd layer, including rolling hard to full compaction with 8 to 10 MT road roller and cleaning the surface, spreading crushed stone chips/Sand (FM-1.80) @0.006 cum per sqm on road surface etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Shingles (20mm down graded)

0.0940

m3

3500.00

329.00

Bitumen Emulsion

5.2500

kg

61.00

320.25

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0500

day

370.00

18.50

H.C. of Vibratory Road Roller (8-10 ton)

0.0030

day

3000.00

9.00

Diesel

0.0300

liter

68.00

2.04

Lubricant

0.0030

liter

220.00

0.66

Sand (FM - 1.5)

0.0060

m3

795.00

4.77 698.82

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

712.80

10% Profit ( Add 10% on Subtotal-B) :

784.08

VAT

6% of Total

IT

4% of Total

52.27 34.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

871.20

Page: 156 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.08.1

Detailed Analysis Brief Description of Item 2 [email protected]: Providing a single coat chip sealing over a low cracked road surface, using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, spraying bitumen by mechanical distributor on road surface @ 0.75kg/sqm, after spraying bitumen instantly spreading uniform graded crushed stone aggregates of 6.5mm average size defined as 100% passing through 10mm sieve and retain on 4.75mm sieve LAA value not exceeding 35 @ 0.006cum/sqm over the surface, sweeping the surface and hand packing for identical spreading of aggregate, surface rolling to embed the aggregate with Pneumatic Multiple Tired Roller (7 tires, 6-8 tons), including properly surface cleaning, heating bitumen upto 140°C to 180°C, etc. including cost of all materials, their carriages, hire charges of machineries, equipment for construction and quality control as per specification, fuels, lubricants and wages of operational staff etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Chips (6mm down graded) [LAA≤35]

0.0060

cum

3690.00

22.14

Bitumen [Grade 80/100]

0.7500

kg

49.00

36.75

Fire wood

0.5625

kg

7.75

4.36

Skilled Labour

0.0011

day

450.00

0.50

Ordinary Labour

0.0100

day

370.00

3.70

H.C. of Pneumatic Multiple Tired Roller (7 tires, 6-8 tons)

0.0003

day

3000.00

0.90

H.C. of Distributor

0.0003

day

3750.00

1.13

Diesel

0.0120

liter

68.00

0.82

Lubricant

0.0010

liter

220.00

0.22

Foreman

0.0003

day

800.00

0.24 70.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

72.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

79.38

VAT

6% of Total

IT

4% of Total

5.29 3.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

88.20 Page: 157 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.08.2

Detailed Analysis Brief Description of Item 2 [email protected]: Providing single coat chip sealing over a moderate cracked road surface, using 60/70 or 80/100 penetration grade straight run bitumen conforming to the requirements of ASTM/ AASHTO, spraying bitumen by mechanical distributor on road surface @ 1.00kg/sqm, after spraying bitumen instantly spreading uniform graded crushed stone aggregates of 6.5mm average size defined as 100% passing through 10mm sieve and retain on 4.75mm sieve with LAA value not exceeding 35 @ 0.007cum/sqm over the surface, sweeping the surface and hand packing for identical spreading of aggregate, surface rolling to embed the aggregate with Pneumatic Multiple Tired Roller (7 tires, 6-8 tons), including properly surface cleaning, heating bitumen upto 140°C to 180°C, etc. including cost of all materials, their carriages, hire charges of machineries, equipment for construction and quality control as per specification, fuels, lubricants and wages of operational staff etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Chips (6mm down graded) [LAA≤35]

0.0070

cum

3690.00

25.83

Bitumen [Grade 80/100]

1.0000

kg

49.00

49.00

Fire wood

0.7500

kg

7.75

5.81

Skilled Labour

0.0010

day

450.00

0.45

Ordinary Labour

0.0100

day

370.00

3.70

H.C. of Pneumatic Multiple Tired Roller (7 tires, 6-8 tons)

0.0003

day

3000.00

0.90

H.C. of Distributor

0.0003

day

3750.00

1.13

Diesel

0.0120

liter

68.00

0.82

Lubricant

0.0010

liter

220.00

0.22

Foreman

0.0003

day

800.00

0.24 88.09

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

89.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

98.84

VAT

6% of Total

IT

4% of Total

6.59 4.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

109.82 Page: 158 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.08.3

Detailed Analysis Brief Description of Item 2 [email protected](BE): Providing a single coat chip sealing over a moderate cracked road surface, using bitumen emulsion of grade k-1-60 conforming to the requirements of ASTM/ AASHTO, spraying bitumen emulsion by mechanical distributor on cleaned road surface @ 1.20kg/sqm, after spraying bitumen emulsion instantly spreading uniform graded crushed stone aggregates of 6.5mm average size defined as 100% passing through 10mm sieve and retain on 4.75mm sieve with LAA value not exceeding 35 @ 0.007cum/sqm over the surface, sweeping the surface and hand packing for identical spreading of aggregate, surface rolling to embed the aggregate with Pneumatic Multiple Tired Roller (7 tires, 6-8 tons), including cost of all materials, their carriages, hire charges of machineries, equipment for construction and quality control as per specification, fuels, lubricants and wages of operational staff etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Chips (6mm down graded) [LAA≤35]

0.0070

cum

3690.00

25.83

Bitumen Emulsion

1.2000

kg

61.00

73.20

Foreman

0.0003

day

800.00

0.24

Skilled Labour

0.0011

day

450.00

0.50

Ordinary Labour

0.0100

day

370.00

3.70

H.C. of Pneumatic Multiple Tired Roller (7 tires, 6-8 tons)

0.0003

day

3000.00

0.90

Diesel

0.0120

liter

68.00

0.82

Lubricant

0.0010

liter

220.00

0.22

H.C. of Distributor

0.0003

day

3750.00

1.13 106.53

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

108.66

10% Profit ( Add 10% on Subtotal-B) :

119.52

VAT

6% of Total

7.97

IT

4% of Total

5.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

132.80

Page: 159 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.09

Detailed Analysis Brief Description of Item 2 12mmSC: Providing 12mm thick (minimum) compacted pre-mixed bituminous surfacing - wearing course to be prepared using 10mm down, 6mm down graded crushed stone chips & Stone Dust to comply the gradation as specified in the relevant item of Road Design Standards – 2005, mixed with 60/70 (Preferable) or 80/100 penetration grade minimum @5.0% by weight of total mix or as determined by job mix design. The bitumen and chips shall be separately heated to a temperature 140°C – 155°C and 150°C – 170°C respectively. The mixing shall be done at temperature between 140°C – 160°C at a separate place away from the fire. The mixture of bitumen and chips shall be laid uniformly on the road surface in appropriate layer so as to produce the specified compacted thickness, rolling at a temperature not bellow 90°C with appropriate Steel Drum Roller (3-5 tons) & pneumatic multiple tire roller (8-10 tons) to the desired compaction, including supplying of all materials, their carriage, labours, tools and equipment etc. all complete in all respect as per direction of the Engineer-incharge. [Excluding the cost of applying Prime/Tack coat].

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Chips (12mm down graded) [LAA≤35]

0.0039

cum

4320.00

16.85

Stone Chips (6mm down graded) [LAA≤35]

0.0076

cum

3690.00

28.04

Stone Dust (2.38mm down)

0.0059

cum

1500.00

8.85

Bitumen [Grade 80/100]

1.4100

kg

49.00

69.09

Fire wood

1.4100

kg

7.75

10.93

Mason

0.0011

day

550.00

0.61

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.0300

day

370.00

11.10

H.C. of Pneumatic Multiple Tired Roller (7 tires, 8-10 tons)

0.0007

day

3000.00

2.10

H.C. of Vibratory (Ride On) Roller 2 Steel Drum Compactor (35 tons)

0.0007

day

3000.00

2.10

Diesel

0.0110

liter

68.00

0.75

Lubricant

0.0011

liter

220.00

0.24 153.35

Subtotal-A: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

156.42 Page: 160 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8 172.06

10% Profit ( Add 10% on Subtotal-B) :

Subtotal-C: VAT

6% of Total

IT

4% of Total

11.47 7.65 Total:

3.10.10.1

CP-BB: Supplying, cutting and fitting of 6mm thick Chequer Plate for bailey bridge decking with minimum 6mm thick mild steel chequer plate of unit weight 49.20kg/sqm, including cutting and shaping of required sizes of bridge deck with cleaning, removing rust, etc. including local handling, carriage of the plate to the site with loading & unloading and placing, etc. all complete in all respect as per direction of the Engineerin-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

kg

Chequer Plate (thickness 6mm)

1.0100

sqm

110.00

111.10

Bailey Bridge Mistry

0.0010

day

680.00

0.68

Skilled Labour

0.0020

day

450.00

0.90

Ordinary Labour

0.0020

day

370.00

0.74 113.42

Subtotal-A: Carrying cost to Working Site, etc.

( +1.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1.13 114.55

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

116.85

10% Profit ( Add 10% on Subtotal-B) :

128.53

VAT

6% of Total

8.57

IT

4% of Total

5.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

191.18

142.81

Page: 161 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.10.2

Detailed Analysis Brief Description of Item 2 Welding at the splicing point of mild steel chequer plate with joist of deck at 3 points (each point being 25mm in length) using electrodes, including cleaning, local handling, cost of all materials, labours, tools, equipment, cost of power, etc. all complete as per drawings, specifications and directions of the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

Electrode

0.0200

pkt

810.00

16.20

Welder

0.0025

day

680.00

1.70

Welder Helper

0.0025

day

470.00

1.18

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0025

day

3000.00

7.50 26.58

Subtotal-A: Portable staging, etc.

( +75.00 % on Subtotal-A )

Subtotal-A1:

19.93 46.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

47.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

52.18

VAT

6% of Total

IT

4% of Total

3.48 2.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

57.98

Page: 162 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.10.11.01

Detailed Analysis Brief Description of Item 2 CCRM-30SCCM: Providing and laying 12BWG G.I. wire meshed cement concrete layer over an old RCC/CC pavement with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 38.5 MPa and satisfying a specified compressive strength, f'c = 30 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N/ASTM C150 Type-1, sand of minimum FM 2.50 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C-33 including breaking chips, screening through proper sieves, cleaning, placing shutter in position and maintaining true to the alignment, making shutter water-tight properly, mixing in standard concrete mixture machine, maintaining allowable slump of 50mm to 75mm, including spraying cement grouting/slurry over the cleaned existing road surface, casting in forms, placing 50mm rhombus 12 BWG G.I. wire mesh in position, compacting by mechanical vibrator machine and finished in a continuous operation including provision of contraction, curing for 28 days, finishing to lines and grades, removing centering-shuttering after specified time approved, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of 12 BWG G.I. wire mesh is not included in this unit rate. Additional quantity of cement to be added if required to attain the required strength at the contractors own cost. The Mix Design has to be approved by the Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work. (Unit cost including all materials, cleaning the existing surface shuttering, casting, curing for 28 days, and all other incidental charges, etc.)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.9000

bag

455.00

4049.50

Stone Chips (20mm down graded) [LAA≤30]

0.4547

m3

5320.00

2419.00

Stone Chips (12mm down graded) [LAA≤30]

0.3032

m3

4470.00

1355.30

Sand (FM - 2.5)

0.4260

m3

1500.00

639.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Page: 163 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9919.31

Subtotal-A: Cost of Form Works/Shuttering, necessary supports, etc.

( +.50 % on Subtotal-A )

49.60

Subtotal-A1:

9968.90

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10168.28

10% Profit ( Add 10% on Subtotal-B) :

11185.11

VAT

6% of Total

IT

4% of Total

745.67 497.12 Total:

3.10.12.01

12 BWG (WM): Supplying and laying 50mm rhombus 12 BWG G.I. wire mesh of required size in cement concreting work, placing mesh in the middle of concreting work or as mentioned in the drawing, including cutting and carrying of wire mesh to the site, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. (Rate is inclusive of cost of materials, labour and all incidental charges in this connection).

sqm

GI Wire Net (12 BWG) [Rhombus Size 50mm]

1.0000

sqm

130.00

130.00

Ordinary Labour

0.0050

day

370.00

1.85 131.85

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

134.49

10% Profit ( Add 10% on Subtotal-B) :

147.94

VAT

6% of Total

9.86

IT

4% of Total

6.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12427.90

164.37

Page: 164 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.01

Detailed Analysis Brief Description of Item 2 PCCBC-10: Plain cement concrete work in foundation with minimum compressive strength of 10 Mpa at 28 days (sugessted mix proportion 1:3:6) on standard cylinder as per standard practice of Code AASTHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II /A-M, 42.5 N, best quality sand (FM. 1.2) and 20mm down well graded picked brick chips (LAA value and maximum water absorption not exceeding 38 & 15% respectively) conforming ASTM C-33, including breaking chips and screening, placing shutter in position and maintaining true to the alignment, making shutter water-tight properly, mixing in standard mixture machine, casting in forms, compacting by vibrator machine and curing for 28 days, removing shuttering after specified time approved, etc. all complete approved and accepted by the E-I-C. (Additional quantity of cement to be added if required to attain the strength at the contractors own cost).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Brick Chips (20mm down graded)

0.9000

m3

2940.00

2646.00

Sand (FM - 1.2)

0.4500

m3

584.00

262.80

Head Mason

0.1000

day

650.00

65.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

4.2340

bag

430.00

1820.62

Mason

0.3000

day

550.00

165.00 5679.42

Subtotal-A: Form Work:

( +.50 % on Subtotal-A )

Subtotal-A1:

28.40 5707.82

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5821.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6404.17

VAT

6% of Total

IT

4% of Total

426.94 284.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7115.75 Page: 165 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.02.1

Detailed Analysis Brief Description of Item 2 125mmBW(1:3): 125mm thick brick work with 1st class brick in specified cement mortar (1:3) in foundation with sand of minimum FM 1.20 and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, making bond with connected walls, including necessary scaffolding, raking out joints, cleaning and soaking the bricks at least for 24 hours before use, washing of sand, curing for requisite period, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick

52.0000

each

9.00

468.00

Sand (FM - 1.2)

0.0258

m3

584.00

15.07

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

Head Mason

0.0100

day

650.00

6.50

Mason

0.0500

day

550.00

27.50

Ordinary Labour

0.3500

day

370.00

129.50

Skilled Labour

0.1000

day

450.00

45.00 799.07

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

815.05

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

896.55

VAT

6% of Total

59.77

IT

4% of Total

39.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

996.17

Page: 166 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.02.2

Detailed Analysis Brief Description of Item 2 BW(1:3): Brick works with 1st class bricks in cement mortar (1:3) in foundation and wall with sand of minimum FM 1.20 and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, including filling the interstices tightly with mortar, raking out joints, cleaning and soaking bricks at least for 24 hours before use, washing of sand, curing for requisite period, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Brick

404.0000

Sand (FM - 1.2)

each

9.00

3636.00

584.00

169.01

0.2894

m3

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.7230

bag

430.00

1170.89

Head Mason

0.0600

day

650.00

39.00

Mason

0.4000

day

550.00

220.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 5919.90

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6038.30

10% Profit ( Add 10% on Subtotal-B) :

6642.13

VAT

6% of Total

IT

4% of Total

442.81 295.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7380.14

Page: 167 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.03

Detailed Analysis Brief Description of Item 2 FP(1:2): Flush pointing to brick wall with sand of minimum FM 1.20 and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N morter (1:2), including raking out the joints, and necessary scaffolding, curing for the requisite period etc. all complete in all respect as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 1.2)

0.0030

m3

584.00

1.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0430

bag

430.00

18.49

Head Mason

0.0270

day

650.00

17.55

Mason

0.0540

day

550.00

29.70

Ordinary Labour

0.1080

day

370.00

39.96 107.45

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

109.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

120.56

VAT

6% of Total

8.04

IT

4% of Total

5.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

133.96

Page: 168 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.04

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-20BCCM(PW): Reinforced cement concrete in Protective Works using steel shutter, with picked brick chips and minimum cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 28.5 Mpa and satisfying a compressive strength f'c = 20 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N), with best quality sand [50% quantity of medium sand (FM. 1.2) and 50% quantity of coarse sand of equivalent FM = 2.2] and 25mm down well graded picked brick chips (LAA value & maximum water absorption not exceeding 38 & 15% respectively) conforming ASTM C-33, including breaking chips and screening, making, placing shutter in position and maintaining true to the alignment, making shutter water-tight properly, placing reinforcement in position, mixing in standard mixture machine with hoper fed by standard measuring boxes, casting in forms, compacting by vibrator machine and curing for 28 days, removing centering-shuttering after specified time approved, including cost of water, electricity, additional testing charges of materials and cylinders required by Engineer, other charges etc. all complete approved and accepted by the E-I-C. Additional quantity of cement to be added if required to attain the strength at the contractors own cost. (Rate is excluding the cost of reinforcement and its fabrication, placing and binding etc.)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 169 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 3.11.04.1

2 Pilining Work

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum 1st Class Picked Brick Chips (20mm down graded)

0.8180

m3

2940.00

2404.92

Sand (FM - 1.8)

0.4090

m3

970.00

396.73

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7000

bag

430.00

3311.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7188.15

Subtotal-A: Form Work:

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1078.22 8266.37

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8431.70

10% Profit ( Add 10% on Subtotal-B) :

9274.87

VAT

6% of Total

IT

4% of Total

618.32 412.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10305.41

Page: 170 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.04.2

2 Vertical Wall, Grade Beams, etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum 1st Class Picked Brick Chips (20mm down graded)

0.8180

m3

2940.00

2404.92

Sand (FM - 1.8)

0.4090

m3

970.00

396.73

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7000

bag

430.00

3311.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.7000

day

370.00

629.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7262.15

Subtotal-A: Form Work:

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1815.54 9077.69

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

9259.24 10185.17

10% Profit ( Add 10% on Subtotal-B) :

VAT

679.01 452.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11316.85

Page: 171 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.05

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS ISO 6935-2:2006 (or standard subsequently released from BSTI) for all types of RCC work including straightening, removing ruts, cleaning, cutting, hooking, bending, lapping and/or welding wherever required as directed, placing in position, tieing with 22 BWG black annealed binding wire double fold, cost of binding wire and anchoring to the adjoining members wherever necessary, supplying and placing with proper cover blocks (1:1), supports, chairs, spacers, splices or laps etc. including cost of all materials, cost of labour, cost of equipment & machinery, loading and unloading, transportation, all other incidental charges and work at all leads and lifts etc. to complete the work as per design, drawing, specifications and direction of the E-I-C. Reinforcement shall be measured only in lengths of bars as actually placed in position on standard weight i.e. 7850 kg/m3 (BNBC Table 6.2.1) basis. No separate payment shall be allowed for Chairs of any shape & profile, spacer bar of any shape & profile, lap/ splice, wastages, binding wire, concrete cover blocks etc. as the cost of these is included in the unit rate.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 172 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.05.1

Detailed Analysis Brief Description of Item 2 RB 300: Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield strength, fy (ReH) = 300 MPa, but the actual yield strength based on mill tests does not exceed fy by more than the 125 MPa and the ratio of actual ultimate strength, fu (Re) to actual tensile yield strength (fy) shall be at least 1.25 and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 16% and 2.5% respectively.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78

M.S. Ribbed/ Deformed Bar (Grade 300)

1.0200

kg

54.00

55.08 61.59

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

69.10

VAT

6% of Total

IT

4% of Total

4.61 3.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

76.78

Page: 173 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.05.2

Detailed Analysis Brief Description of Item 2 RB 400 / 400W: Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield stress, fy (ReH) = 400 MPa, but the actual yield strength based on mill tests does not exceed fy by more than the 125 MPa, the ratio of actual ultimate strength, fu (Re) to actual tensile yield strength (fy) shall be at least 1.25 and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 14% and 2.5% respectively.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78

M.S. Ribbed/ Deformed Bar (Grade 400)

1.0200

kg

58.00

59.16 65.67

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

73.68

VAT

6% of Total

IT

4% of Total

4.91 3.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

81.87

Page: 174 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.05.3

Detailed Analysis Brief Description of Item 2 Grade 420 (B420DWR): Ribbed or Deformed bar produced and marked as per ISO 6935-2:2015/ ASTM A706M - 16 with minimum yield strength, fy(ReH) = 420 MPa but fy(ReH) not exceeding 540 MPa, the ratio of ultimate tensile strength, fu(Rm) to actual yield strength, fy(ReH) shall be at least 1.25 and minimum elongation in 200mm shall be at least 14% for bar sizes 10mm through 20mm, at least 12% for bar sizes 22mm through 32mm and at least 10% for bar sizes 40mm and 50mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78

M.S. Ribbed/ Deformed Bar (Grade 420)

1.0200

kg

58.00

59.16 65.67

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.98

10% Profit ( Add 10% on Subtotal-B) :

73.68

VAT

6% of Total

4.91

IT

4% of Total

3.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

81.87

Page: 175 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.06

Detailed Analysis Brief Description of Item 2 Labour for breaking head of hardened cast-in-situ bored pile/ pre-cast piles to the correct lines and levels from the top of the piles to the cutoff level as indicated in the approved drawing and exposing pile reinforcement for embedment in pile cap by any means and disposal of the debris to an unobjectionable place outside the site premises including scrapping and removing concrete from steel/ MS rods, straightening and bending of pile bars, preparation and making of platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, leveling and dressing the site and clearing the river bed, etc. all complete as per direction of the E-I-C. Measurement will be given for the actual pile head volume to be broken.The debris from pile chipping shall be disposed outside the site premises at an environmentally safe place with minimum traffic disruption and procuring entity will not be responsilbe for any irregularities by the party regarding dumping of the debris. (Measurement will be given for the actual pile head volume to be broken).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

9.0000

day

370.00

3330.00 3397.50

Subtotal-A: Repairing of pile head including materials Straightening and bending of pile bars, removing the debris to a safe distance, tools & plant, sundries etc.

( +10.00 % on Subtotal-A ) ( +10.00 % on Subtotal-A )

Subtotal-A1:

339.75 339.75

4077.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4158.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4574.39

VAT

6% of Total

IT

4% of Total

304.96 203.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5082.66

Page: 176 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

3.11.07

Labour charge for driving pre-cast RCC piles with drop hammer type rig in any type of soil, handling and keeping in position and driving with suitable monkey/drop hammer for small pile otherwise suitable mechanical means to the required depth including fitting and fixing steel cap, etc. cost included hire charges of machineries, tools & equipments, wages of operational staff etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

3.11.07.1

Cost of pile driving (Size-150mmx150mm) depth up to 6 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Driving Equipment

0.0400

day

350.00

14.00 171.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

174.42

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

191.86

VAT

6% of Total

IT

4% of Total

12.79 8.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

213.18

Page: 177 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.07.2

Detailed Analysis Brief Description of Item 2 Cost of pile driving (Size-150mm to 200mmx200mm) depth up to 6 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Operator

0.0208

day

570.00

11.86

Skilled Labour

0.0417

day

450.00

18.77

Ordinary Labour

0.1250

day

370.00

46.25

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0208

day

3000.00

62.40

Diesel

0.3000

liter

68.00

20.40 159.67

Subtotal-A: Preparation of Machine Base/Platform

( +75.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

119.75 279.42

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

285.01

10% Profit ( Add 10% on Subtotal-B) :

313.51

VAT

6% of Total

IT

4% of Total

20.90 13.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

348.35

Page: 178 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.07.3

Detailed Analysis Brief Description of Item 2 Cost of pile driving (Size-150mm to 200mmx200mm) depth 6m to 12m and above

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Operator

0.0278

day

570.00

Skilled Labour

0.0556

day

450.00

25.02

Ordinary Labour

0.1944

day

370.00

71.93

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0278

day

3000.00

83.40

Diesel

0.4000

liter

68.00

27.20

15.85

223.39

Subtotal-A: Preparation of Machine Base/Platform

( +75.00 % on Subtotal-A )

Subtotal-A1:

167.55 390.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

398.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

438.63

VAT

6% of Total

IT

4% of Total

29.24 19.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

487.37

Page: 179 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.07.4

Detailed Analysis Brief Description of Item 2 Cost of pile driving (Size-200mm to 250mmx250mm) depth upto 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Operator

0.0238

day

570.00

13.57

Skilled Labour

0.0476

day

450.00

21.42

Ordinary Labour

0.1429

day

370.00

52.87

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0238

day

3000.00

71.40

Diesel

0.3800

liter

68.00

25.84 185.10

Subtotal-A: Preparation of Machine Base/Platform

( +75.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

138.82 323.92

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

330.40

10% Profit ( Add 10% on Subtotal-B) :

363.44

VAT

6% of Total

IT

4% of Total

24.23 16.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

403.82

Page: 180 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.07.5

Detailed Analysis Brief Description of Item 2 Cost of pile driving (Size-200mm to 250mmx250mm) depth 6m to 12m and above

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Operator

0.0417

day

570.00

Skilled Labour

0.0833

day

450.00

37.49

Ordinary Labour

0.2917

day

370.00

107.93

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0417

day

3000.00

125.10

Diesel

0.6700

liter

68.00

45.56

23.77

339.84

Subtotal-A: Preparation of Machine Base/Platform

( +75.00 % on Subtotal-A )

Subtotal-A1:

254.88 594.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

606.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

667.28

VAT

6% of Total

IT

4% of Total

44.49 29.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

741.42

Page: 181 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.07.6

Detailed Analysis Brief Description of Item 2 Cost of pile driving (Size-250mm to 300mmx300mm) depth upto 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Operator

0.0278

day

570.00

15.85

Skilled Labour

0.0556

day

450.00

25.02

Ordinary Labour

0.1944

day

370.00

71.93

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0278

day

3000.00

83.40

Diesel

0.4400

liter

68.00

29.92 226.11

Subtotal-A: Preparation of Machine Base/Platform

( +75.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

169.59 395.70

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

403.61

10% Profit ( Add 10% on Subtotal-B) :

443.97

VAT

6% of Total

IT

4% of Total

29.60 19.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

493.31

Page: 182 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.07.7

Detailed Analysis Brief Description of Item 2 Cost of pile driving (Size-250mm to 300mmx300mm) depth 6m to 12m and above

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Operator

0.0556

day

570.00

Skilled Labour

0.1111

day

450.00

50.00

Ordinary Labour

0.4440

day

370.00

164.28

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0556

day

3000.00

166.80

Diesel

0.8800

liter

68.00

59.84

31.69

472.61

Subtotal-A: Preparation of Machine Base/Platform

( +75.00 % on Subtotal-A )

Subtotal-A1:

354.46 827.06

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

843.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

927.96

VAT

6% of Total

IT

4% of Total

61.86 41.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1031.07

Page: 183 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.07.8

Detailed Analysis Brief Description of Item 2 Cost of pile driving (Size-300mm to 350mmx350mm) depth upto 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Operator

0.0417

day

570.00

23.77

Skilled Labour

0.0833

day

450.00

37.49

Ordinary Labour

0.2917

day

370.00

107.93

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0417

day

3000.00

125.10

Diesel

0.6700

liter

68.00

45.56 339.84

Subtotal-A: Preparation of Machine Base/Platform

( +75.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

254.88 594.73

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

606.62

10% Profit ( Add 10% on Subtotal-B) :

667.28

VAT

6% of Total

IT

4% of Total

44.49 29.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

741.42

Page: 184 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.07.9

Detailed Analysis Brief Description of Item 2 Cost of pile driving (Size-300mm to 350mmx350mm) depth 6m to 12m and above

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Operator

0.0833

day

570.00

Skilled Labour

0.1667

day

450.00

75.02

Ordinary Labour

0.5833

day

370.00

215.82

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0833

day

3000.00

249.90

Diesel

1.3300

liter

68.00

90.44

47.48

678.66

Subtotal-A: Preparation of Machine Base/Platform

( +75.00 % on Subtotal-A )

Subtotal-A1:

508.99 1187.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1211.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1332.54

VAT

6% of Total

IT

4% of Total

88.84 59.22 Total:

3.11.08

Amount

1480.60

CCBSS-10(PW): Manufacturing and supplying Plain Cement Concrete (PCC) Blocks with cement conforming to BDS EN 197-1 : 2003 CEM-II/AM 42.5N, sand of minimum FM 1.5 and 40 mm down well graded shingles to attain a minimum 28 days cylinder strength of 10.00 Mpa (suggested mix proporation 1:3:6), including grading, washings shingles, mixing in standard mixture machine, casting in forms, making shutter water-tight properly, compacting by vibrator machine and curing for at least 28 days, including preparation of platform, shuttering and stacking in measurable stacks, cost of all materials, labour, equiptment and machinery, work at all leads and lifts, loading and unloading, transportation and all other incidental charges etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. Steel shutter shall be used to perform the job.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 185 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.01

2 Size 500mmX500mmX300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0675

m3

3500.00

236.25

Sand (FM - 1.5)

0.0338

m3

795.00

26.87

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3175

bag

430.00

136.53

Mason

0.0060

day

550.00

3.30

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.1125

day

370.00

41.63

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0045

day

1200.00

5.40

Hire and running charges of Concrete Vibrator

0.0045

day

400.00

1.80 465.27

Subtotal-A: Form Work:

( +2.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

9.31 474.58

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

484.07

10% Profit ( Add 10% on Subtotal-B) :

532.47

VAT

6% of Total

IT

4% of Total

35.50 23.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

591.64

Page: 186 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.02

2 Size 400mmX400mmX300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0432

m3

3500.00

151.20

Sand (FM - 1.5)

0.0216

m3

795.00

17.17

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2032

bag

430.00

87.38

Mason

0.0168

day

550.00

9.24

Skilled Labour

0.0192

day

450.00

8.64

Ordinary Labour

0.0720

day

370.00

26.64

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0029

day

1200.00

3.48

Hire and running charges of Concrete Vibrator

0.0029

day

400.00

1.16 304.91

Subtotal-A: Form Work:

( +1.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3.05 307.96

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

314.12

10% Profit ( Add 10% on Subtotal-B) :

345.53

VAT

6% of Total

IT

4% of Total

23.04 15.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

383.92

Page: 187 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.03

2 Size 300mmX300mmX300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0243

m3

3500.00

85.05

Sand (FM - 1.5)

0.0122

m3

795.00

9.70

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1143

bag

430.00

49.15

Mason

0.0113

day

550.00

6.22

Skilled Labour

0.0130

day

450.00

5.85

Ordinary Labour

0.0486

day

370.00

17.98

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0019

day

1200.00

2.28

Hire and running charges of Concrete Vibrator

0.0019

day

400.00

0.76 176.99

Subtotal-A: Form Work:

( +2.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3.54 180.52

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

184.14

10% Profit ( Add 10% on Subtotal-B) :

202.55

VAT

6% of Total

IT

4% of Total

13.50 9.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

225.05

Page: 188 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.04

2 Size 500mmX500mmX200mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0450

m3

3500.00

157.50

Sand (FM - 1.5)

0.0225

m3

795.00

17.89

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2117

bag

430.00

91.03

Mason

0.0175

day

550.00

9.63

Skilled Labour

0.0220

day

450.00

9.90

Ordinary Labour

0.0825

day

370.00

30.53

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0030

day

1200.00

3.60

Hire and running charges of Concrete Vibrator

0.0030

day

400.00

1.20 321.27

Subtotal-A: Form Work:

( +2.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6.43 327.69

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

334.25

10% Profit ( Add 10% on Subtotal-B) :

367.67

VAT

6% of Total

IT

4% of Total

24.51 16.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

408.53

Page: 189 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.05

2 Size 500mmX500mmX150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0338

m3

3500.00

118.30

Sand (FM - 1.5)

0.0169

m3

795.00

13.44

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1588

bag

430.00

68.28

Mason

0.0131

day

550.00

7.21

Skilled Labour

0.0165

day

450.00

7.43

Ordinary Labour

0.0619

day

370.00

22.90

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0025

day

1200.00

3.00

Hire and running charges of Concrete Vibrator

0.0025

day

400.00

1.00 241.55

Subtotal-A: Form Work:

( +2.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.83 246.38

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

251.31

10% Profit ( Add 10% on Subtotal-B) :

276.44

VAT

6% of Total

IT

4% of Total

18.43 12.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

307.16

Page: 190 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.06

2 Size 400mmX400mmX150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0216

m3

3500.00

75.60

Sand (FM - 1.5)

0.0108

m3

795.00

8.59

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1016

bag

430.00

43.69

Mason

0.0084

day

550.00

4.62

Skilled Labour

0.0106

day

450.00

4.77

Ordinary Labour

0.0396

day

370.00

14.65

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0016

day

1200.00

1.92

Hire and running charges of Concrete Vibrator

0.0016

day

400.00

0.64 154.48

Subtotal-A: Form Work:

( +2.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3.09 157.57

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

160.72

10% Profit ( Add 10% on Subtotal-B) :

176.79

VAT

6% of Total

IT

4% of Total

11.79 7.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

196.43

Page: 191 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.07

2 Size 300mmX300mmX150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0122

m3

3500.00

42.70

Sand (FM - 1.5)

0.0061

m3

795.00

4.85

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0572

bag

430.00

24.60

Mason

0.0052

day

550.00

2.86

Skilled Labour

0.0065

day

450.00

2.93

Ordinary Labour

0.0243

day

370.00

8.99

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0010

day

1200.00

1.20

Hire and running charges of Concrete Vibrator

0.0010

day

400.00

0.40 88.52

Subtotal-A: Form Work:

( +2.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1.77 90.29

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

92.10 101.31

10% Profit ( Add 10% on Subtotal-B) :

VAT

6.75 4.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

112.56

Page: 192 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.08

2 Size 250mmX250mmX250mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0141

m3

3500.00

49.35

Sand (FM - 1.5)

0.0070

m3

795.00

5.57

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0662

bag

430.00

28.47

Mason

0.0066

day

550.00

3.63

Skilled Labour

0.0075

day

450.00

3.38

Ordinary Labour

0.0281

day

370.00

10.40

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0011

day

1200.00

1.32

Hire and running charges of Concrete Vibrator

0.0011

day

400.00

0.44 102.54

Subtotal-A: Form Work:

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2.56 105.11

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

107.21

10% Profit ( Add 10% on Subtotal-B) :

117.93

VAT

6% of Total

IT

4% of Total

7.86 5.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

131.03

Page: 193 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.09

2 Size 400mmX400mmX100mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0144

m3

3500.00

50.40

Sand (FM - 1.5)

0.0072

m3

795.00

5.72

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0677

bag

430.00

29.11

Mason

0.0056

day

550.00

3.08

Skilled Labour

0.0077

day

450.00

3.47

Ordinary Labour

0.0288

day

370.00

10.66

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0012

day

1200.00

1.44

Hire and running charges of Concrete Vibrator

0.0012

day

400.00

0.48 104.36

Subtotal-A: Form Work:

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2.61 106.96

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

109.10

10% Profit ( Add 10% on Subtotal-B) :

120.01

VAT

6% of Total

IT

4% of Total

8.00 5.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

133.35

Page: 194 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.11.08.10

2 Size 375mmX225mmX150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0114

m3

3500.00

39.90

Sand (FM - 1.5)

0.0057

m3

795.00

4.53

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0536

bag

430.00

23.05

Mason

0.0044

day

550.00

2.42

Skilled Labour

0.0061

day

450.00

2.75

Ordinary Labour

0.0228

day

370.00

8.44

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0009

day

1200.00

1.08

Hire and running charges of Concrete Vibrator

0.0009

day

400.00

0.36 82.52

Subtotal-A: Form Work:

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2.06 84.58

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

86.28

10% Profit ( Add 10% on Subtotal-B) :

94.90

VAT

6% of Total

IT

4% of Total

6.33 4.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

105.45

Page: 195 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.09

Detailed Analysis Brief Description of Item 2 LC-CCB(PW): Labour charge for laying single layer CC Block of different sizes on slope of embankment, including preparation of slopes by cutting or filling with ramming the filled up earth to the same profile as that of the finished slope level, including carrying CC blocks, supplying and filling the interstices tightly with local sand (FM - 0.5), etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. [Excluding the cost of CC Blocks].

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.3000

day

450.00

135.00

Ordinary Labour

1.3000

day

370.00

481.00 627.00

Subtotal-A: Bamboo Ladder, Jute Rope, Tools, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

62.70 689.70

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

703.49

10% Profit ( Add 10% on Subtotal-B) :

773.84

VAT

6% of Total

51.59

IT

4% of Total

34.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

859.83

Page: 196 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.10

Detailed Analysis Brief Description of Item 2 WMCCBSS-20(PW): Providing and laying cast in place 12 BWG G.I. wire meshed Cement Concrete Blocks (1000mm X 1000mm X 100mm) at bridge approaches/road slopes with cement conforming to BDS EN 1971 : 2003 CEM-II/A-M 42.5N, sand of minimum FM 1.5 and 25 mm down well graded shingles (LAA value not exceeding 35) to attain a minimum 28 days cylinder strength of 20MPa (suggested mix proporation 1:2:4), including grading, washings shingles, shuttering, mixing in satndard concrete mixture machine, casting with supplying and laying 75mm rhombus 12 BWG G.I. wire mesh for required size and length in CC Block, placing mesh in the middle of CC block as it should be, compacting concrete properly, curing for 28 days, including preparation of slopes by cutting or filling with ramming the filled up earth to the same profile as that of the finished slope level, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. (Unit cost including all materials, shuttering, casting, curing for 28 days, and all other incidental charges, etc.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Stone Shingles (20mm down graded)

0.0857

m3

3500.00

Sand (FM - 1.5)

0.0428

m3

795.00

34.03

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.6040

bag

430.00

259.72

GI Wire Net (12 BWG) [Rhombus Size 75mm]

1.0000

m2

100.00

100.00

Mason

0.0050

day

550.00

2.75

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.2000

day

370.00

74.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0010

day

1200.00

1.20

299.95

794.15

Subtotal-A: Form works

( +2.50 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19.85 814.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

830.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

913.31

VAT

6% of Total

IT

4% of Total

60.89 40.59

Page: 197 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 3.11.11

Geo-Textile: Supplying and laying of a geo-textile filter between CC blocks and embankment slopes properly with non-woven needle punched type geo-textile filter of different grades, specification for effective erosion protection in hydraulic structures/river training works including local handling placing in position, providing machine seamed joints (with 100% polypropylene or nylon thread) or 35cm lap in dry condition or minimum 100cm lap under water including protecting the geo-textile material; from UV ray and from any other damages etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. (Geo-textile delivered at site should be clearly labeled with brand name and grade printed at regular intervals across the body of the fabric)

3.11.11.1

Grade-I : Specification of which Mass (minimum) =170 gm/m2, Thickness under pressure 2kpa (minimum)=1.5mm, Strip tensile strength (minimum)=12.0kn/m, Elongation (minimum) =35%, Grab tensile strength (minimum)=700 N, CBR puncture resistance (minimum)=2000 N, Effective opening size (Maximum) = 0.10mm, Permeability vertical under 2 kpa pressure h is 100mm (minimum)=0.003 m/s and Permeability horizontal under 2 kpa pressure (minimum)=0.004 m/s.

sqm

Geo Textile (Grade-I-DF-20-1.5mm thick)

1.0700

m2

60.00

64.20

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.1000

day

370.00

37.00 114.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

116.99

10% Profit ( Add 10% on Subtotal-B) :

128.69

VAT

6% of Total

IT

4% of Total

8.58 5.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1014.79

142.99

Page: 198 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.11.2

Detailed Analysis Brief Description of Item 2 Grade-II : Specification of which Mass (minimum)=190 gm/m2, Thickness under pressure 2kpa (minimum)=1.8mm, Strip tensile strength (minimum)=14.0 kn/m, Elongation (minimum)=35%, Grab tensile strength (minimum)=750 N, CBR puncture resistance (minimum)=2200 N, Effective opening size (Maximum)=0.10mm, Permeability vertical under 2 kpa pressure h is 100mm (minimum)=0.003 m/s and Permeability horizontal under 2 kpa pressure (minimum)=0.004 m/s.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Geo Textile (Grade-II-DF-30-2.0mm thick)

1.0700

m2

60.00

64.20

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.1000

day

370.00

37.00 114.70

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

116.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

128.69

VAT

6% of Total

IT

4% of Total

8.58 5.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

142.99

Page: 199 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.11.3

Detailed Analysis Brief Description of Item 2 Grade-III : Specification of which Mass (minimum)=240 gm/m2, Thickness under pressure 2kpa (minimum)=2.0mm, Strip tensile strength (minimum)=18.0 kn/m, Elongation (minimum)=35%, Grab tensile strength (minimum)=1000 N, CBR puncture resistance (minimum)=2700 N, Effective opening size (Maximum)=0.09mm, Permeability vertical under 2 kpa pressure h is 100mm (minimum)=0.003 m/s and Permeability horizontal under 2 kpa pressure (minimum)=0.004 m/s.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Geo Textile (Grade-III-DF-40-2.3mm thick)

1.0700

m2

65.00

69.55

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.1000

day

370.00

37.00 120.05

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

122.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

134.70

VAT

6% of Total

IT

4% of Total

8.98 5.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

149.66

Page: 200 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.11.4

Detailed Analysis Brief Description of Item 2 Grade-IV : Specification of which Mass (minimum)=310 gm/m2, Thickness under pressure 2kpa (minimum)=2.6mm, Strip tensile strength (minimum)=22.0 kn/m, Elongation (minimum)=40%, Grab tensile strength (minimum)=1300 N, CBR puncture resistance (minimum)=3700 N, Effective opening size (Maximum) = 0.09mm, Permeability vertical under 2 kpa pressure h is100mm (minimum)=0.003 m/s and Permeability horizontal under 2 kpa pressure (minimum)=0.004 m/s.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Geo Textile (Grade-IV-DF-50-2.5mm thick)

1.0700

m2

75.00

80.25

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.1000

day

370.00

37.00 130.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

133.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

146.70

VAT

6% of Total

IT

4% of Total

9.78 6.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

163.00

Page: 201 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.11.5

Detailed Analysis Brief Description of Item 2 Grade-V : Specification of which Mass (minimum)=365 gm/m2, Thickness under pressure 2kpa (minimum)=3.0mm, Strip tensile strength (minimum)=25.0 kn/m, Elongation (minimum)=40%, Grab tensile strength (minimum)=1500 N, CBR puncture resistance (minimum)=4000 N, Effective opening size (Maximum) = 0.08mm, Permeability vertical under 2 kpa pressure h is 100mm (minimum) = 0.003 m/s and Permeability horizontal under 2 kpa pressure (minimum) = 0.004 m/s.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Geo Textile (Grade-V-DF-60-3.0mm thick)

1.0700

m2

90.00

96.30

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.1000

day

370.00

37.00 146.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

149.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

164.71

VAT

6% of Total

IT

4% of Total

10.98 7.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

183.01

Page: 202 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.12

Detailed Analysis Brief Description of Item 2 LC-Geo-Tex: Labour charge for laying of a geo-textile filter between CC blocks and embankment slopes properly with non-woven needle punched type geo- textile filter of different grades for effective erosion protection in hydraulic structures/river training works including local handling, placing in proper position, leveling, dressing, maintaining slope, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0300

day

370.00

11.10 15.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17.50

VAT

6% of Total

IT

4% of Total

1.17 0.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19.45

Page: 203 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.13

Detailed Analysis Brief Description of Item 2 RCC(P+W)BC-PW: Construction and Installing in position palisading work as per standard drawing enumerated in Appendix-6 (type designs for protective works) using Pre-Cast RCC Post & Cast-In-Situ RCC Wall with 02 (two) meter long (size 150mmX150mm) pre-cast RCC (1:1.5:3) post made of 20mm down graded brick chips to be driven by suitable monkey/drop hammer in full length of the post @ 1.0meter c/c into the ground laying on proper alignment, breaking head (150mm length) of all post carefully, scrapping and removing concrete from Steel/MS rod, including in-situ casting of 150mm X 150mm Grade beam and 100mm thick and 1 meter high RCC vertical wall along the protective work using 1st class bricks/ picked 20mm down graded bricks chips, sand (minimum FM 1.80) and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N to attain a minimum 28 days ultimate cylinder crushing 20.00 Mpa (suggested mix proportion 1:1.5:3), supplying, fabricating and binding of M. S. High strength deformed bar of required size, length and spacing by means approved designed including form work, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. (Unit cost including reinforcement, its fabrication, shuttering, casting, curing for 28 days, driving of the post and all other incidental charges, etc.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0450

cum

75.80

3.41

Reinforced cement concrete works (1:1.5:3) Below Plinth Level and in Ground Floor……… (3.11.04.1)

0.0450

cum

8266.37

371.99

Pre-cast pile driving (Size-150mmx150mm) ………… (3.11.07.1)

2.0350

m

171.00

347.99

Labour for breaking head of cast-in-situ bored pile/pre-cast pile……. (3.11.06)

0.0037

cum

7474.50

27.66

Reinforced cement concrete works (1:1.5:3) In foundation beam……. (3.11.04.2)

0.1320

cum

9077.69

1198.25

28.3210

kg

61.59

1744.29

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

3693.58

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3767.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4144.20 Page: 204 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

8 276.28 184.19

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4604.67

Page: 205 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.14

Detailed Analysis Brief Description of Item 2 RCC(P+BW)-PW: Construction and Installing in position palisading work as per standard drawing enumerated in Appendix-6 (type designs for protective works) with 250mm thick Brick Masonry work & pre cast RCC Post of 03 (three) meter long (size 150mmX150mm) pre-cast RCC (1:1.5:3) post made by 20mm down graded brick chips to be driven by suitable monkey/drop hammer in 2/3rd of its total length @ 1 meter c/c into the ground laying on proper alignment, constructing of 250mm thick and 1 meter high vertical wall along the protective work using Brick Masonry work in cement mortar (1:3), filling the interstices tightly with mortar, raking out joints, cleaning and soaking bricks at least for 24 hours before use, washing of sand, including flush pointing at front face of the brick wall with cement mortar (1:2), curing for requisite period, including excavating minimum 300mm depth foundation trenches for brick wall and laying one layer polythene sheet, constructing 50mm thick cement concrete (1:3:6) on it & below the brick work by means approved designed including form work, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. (Unit cost including reinforcement, its fabrication, shuttering, casting, curing for 28 days, driving of the post and all other incidental charges, etc.)

Unit

Sub-Item

3

4

5

Unit

Rate

6

7

Amount 8

m

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.1140

cum

75.80

8.64

Providing single layer polythene sheet (0.18mm thick)……… (3.07.1)

0.3500

sqm

12.68

4.44

Mass concrete in foundation (1:3:6) with cement, sand and brick chips ……….. (3.11.01)

0.0130

cum

5707.82

74.20

First class brick works in cement mortar (1:3)……… (3.11.02.2)

0.2500

cum

5919.90

1479.97

Reinforced cement concrete works (1:1.5:3) Below Plinth Level and in Ground Floor……… (3.11.04.1)

0.0690

cum

8266.37

570.38

Pre-cast pile driving (Size-150mmx150mm) ………… (3.11.07.1)

2.4200

m

171.00

413.82

16.6630

kg

61.59

1026.27

1.0630

sqm

107.45

114.22

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1) Flush pointing to brick wall with cement mortar (1:2) for Ground floor…….. (3.11.03) Note : Rates of all items should be inclusive of all supply and carriage.

Quantity

Page: 206 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3765.79

10% Profit ( Add 10% on Subtotal-B) :

4142.37

VAT

6% of Total

IT

4% of Total

276.16 184.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8 3691.95

Subtotal-A: Subtotal-B:

Amount

4602.63

Page: 207 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.15.1

Detailed Analysis Brief Description of Item 2 RCC(P+SP)-PW: Palisading work with Single pre-cast RCC (1:1.5:3) plate (1050mm X 600mm X 75mm) fitted with RCC (1:1.5:3) post of 150mm x 150mm, 2m long, 0.9m center to center to be driven 2/3rd of the total length (2m) of the post made of 20mm down graded brick chips. Pre-cast plate to be fitted with RCC post fixed necessary nuts and bolts at driving of post supplying all necessary nuts and bolts etc. all complete in all respect as per approved drawing enumerated in Appendix-6, specification and direction of the Engineer-in-charge. Measurement will be made on center to center distance of the post.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Reinforced cement concrete works (1:1.5:3) Below Plinth Level and in Ground Floor……… (3.11.04.1)

0.1020

cum

8266.37

843.17

Pre-cast pile driving (Size-150mmx150mm) ………… (3.11.07.1)

1.9560

m

171.00

334.48

14.1230

kg

61.59

869.84

Nails/ Nut bolts/ Screw/ Spikes

0.4070

kg

65.00

26.46

Ordinary Labour

0.1500

day

370.00

55.50

Skilled Labour

0.1000

day

450.00

45.00

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

2174.44

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2217.93

10% Profit ( Add 10% on Subtotal-B) :

2439.72

VAT

6% of Total

IT

4% of Total

162.65 108.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2710.80

Page: 208 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.15.2

Detailed Analysis Brief Description of Item 2 RCC(P+DP)-PW: Palisading work with Double pre-cast RCC (1:1.5:3) plate (1050mm X 600mm X 75mm) fitted with RCC (1:1.5:3) post of 150mm x 150mm, 3m long, 0.9m center to center to be driven 2/3rd of the total length (3m) of the post made of 20mm down graded brick chips. Pre-cast plate to be fitted with RCC post fixed necessary nuts and bolts at driving of post supplying all necessary nuts and bolts etc..all complete in all respect as per approved drawing (Road Design Standards – 2005, Plate UPR-UNR-EM1-2-1)/enumerated in Appendix-6, specification and direction of the Engineer-in- charge. Measurement will be made on center to center distance of the post.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Reinforced cement concrete works (1:1.5:3) Below Plinth Level and in Ground Floor……… (3.11.04.1)

0.1820

cum

8266.37

1504.48

Pre-cast pile driving (Size-150mmx150mm) ………… (3.11.07.1)

2.4440

m

171.00

417.92

23.2410

kg

61.59

1431.41

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1) Nails/ Nut bolts/ Screw/ Spikes

0.8140

kg

65.00

52.91

Ordinary Labour

0.2000

day

370.00

74.00

Skilled Labour

0.1000

day

450.00

45.00 3525.73

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3596.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3955.87

VAT

6% of Total

IT

4% of Total

263.72 175.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4395.41

Page: 209 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.16.1

Detailed Analysis Brief Description of Item 2 ReSP-PW: Labour charge for Re-setting of existing distorted/collapsed RCC single plate palisading work including pulling out of distorted/collapsed existing RCC post (150mmX150mm, 3m long, 0.9m c/c) and re-driven the post 2/3rd (minimum) of its total length by suitable monkey/drop hammer. Existing RCC plate to be fitted with necessary nuts & bolts at appropriate location of driven RCC post, including supplying required nuts and bolts etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

day

450.00

11.25

8

m

Skilled Labour

0.0250

Ordinary Labour

1.2500

day

370.00

462.50

H.C. of Driving Equipment

0.0500

day

350.00

17.50

Nails/ Nut bolts/ Screw/ Spikes

0.3400

kg

65.00

22.10 513.35

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

523.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

575.98

VAT

6% of Total

IT

4% of Total

38.40 25.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

639.98

Page: 210 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.16.2

Detailed Analysis Brief Description of Item 2 ReDP-PW: Labour charge for Re-setting of existing distorted/collapsed RCC Double plate palisading work including pulling out of distorted/collapsed existing RCC post (150mmX150mm, 3m long, 0.9m c/c) and re-driven the post 2/3rd (minimum) of its total length by suitable monkey/drop hammer. Existing RCC plate to be fitted with necessary nuts & bolts at appropriate location of driven RCC post including supplying required nuts and bolts etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

day

450.00

157.50

m

Skilled Labour

0.3500

Ordinary Labour

1.7500

day

370.00

647.50

H.C. of Driving Equipment

0.0500

day

350.00

17.50

Nails/ Nut bolts/ Screw/ Spikes

0.6700

kg

65.00

43.55 866.05

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

883.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

971.71

VAT

6% of Total

IT

4% of Total

64.78 43.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1079.68

Page: 211 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.17

Detailed Analysis Brief Description of Item 2 BP(Ø75mm): Supplying of straight & strong bamboo posts of minimum 75mm dia (at all sections) and driving the same vertically in the ground upto required depth by any means, all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. The rate is for single pin. (Total length embedded and above ground shall be considered towards payment)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Skilled Labour

0.0001

day

450.00

0.05

Ordinary Labour

0.0300

day

370.00

11.10

Borak Bamboo (75mm dia)

1.0000

m

38.00

38.00 49.15

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

50.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

55.14

VAT

6% of Total

3.68

IT

4% of Total

2.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

61.27

Page: 212 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.18

Detailed Analysis Brief Description of Item 2 CHB-PW(Ø75mm): Closed hole bamboo palisading with matured borak bamboo of minimum diameter of 75mm including driving at least half of its length below G.L. including carrying of all materials, fitting fixing with half split borak bamboo runners @450mm c/c horizontally with iron nails, GI wire etc. with double tarza etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-incharge. (Payment will be made for the work above ground water levels).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Tarza

0.7500

m2

210.00

157.50

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.4000

day

370.00

148.00

18.0000

m

38.00

684.00

Nails/ Nut bolts/ Screw/ Spikes

0.2000

kg

65.00

13.00

GI Wire (22 BWG)

0.1200

kg

90.00

10.80

Borak Bamboo (75mm dia)

1058.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1079.47

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1187.41

VAT

6% of Total

79.16

IT

4% of Total

52.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1319.35

Page: 213 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.19.1

Detailed Analysis Brief Description of Item 2 BDS-PW: Providing Palisading with Bitumen drum sheet walling tied with 20 gauge G.I. wire, fixing the same with already driven bamboo posts with half split Borrak bamboo (75mm to 100mm dia) runners @450mm c/c horizontally with iron nail, G.I wire etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-incharge. (Cost excluded the bamboo posts)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen Drum Sheet

1.0000

m2

269.00

269.00

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.4000

day

370.00

148.00

Borak Bamboo (75mm to 100mm)

1.5000

m

42.00

63.00

GI Wire (22 BWG)

0.1000

kg

90.00

9.00

Nails/ Nut bolts/ Screw/ Spikes

0.1500

kg

65.00

9.75 503.25

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

513.32

10% Profit ( Add 10% on Subtotal-B) :

564.65

VAT

6% of Total

37.64

IT

4% of Total

25.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

627.39

Page: 214 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.19.2

Detailed Analysis Brief Description of Item 2 BDS-PW(Ø150mmGP): Providing Palisading with bitumen drum sheet fitted with gazari post 150mm minimum dia, 0.90m c/c to be driven half of the total length of the post Drum sheet to be fitted with Shisu/Mehagoni wooden batten 50mmx50mm size at 0.60 meter c/c supplying and fixing with 150mm dia gazari post crosses 1.80 meter c/c fixed with necessary nuts and bolts at the slope side of palisading and tied up the palisading work by GI wire No. 10 with gazari post 150mm dia and 1.8 meter c/c driven at the opposite direction up to 1.20 meter depth including supplying all necessary nails and spikes etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.(Payment will be made for the work above ground levels.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen Drum Sheet

1.0000

m2

269.00

269.00

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.4000

day

370.00

148.00

Mehagoni/ Shishu

0.0040

m3

59730.00

238.92

Shal/sundari/gazari Bullah (150mm to 200mm)

2.4000

m

225.00

540.00

Nails/ Nut bolts/ Screw/ Spikes

0.4000

kg

65.00

26.00

GI Wire (22 BWG)

0.1500

kg

90.00

13.50 1239.92

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1264.72

10% Profit ( Add 10% on Subtotal-B) :

1391.19

VAT

6% of Total

IT

4% of Total

92.75 61.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1545.77

Page: 215 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.20

Detailed Analysis Brief Description of Item 2 GBW(1:8)-PW: Providing single layer gunny bag barrier/wall for toe protection with cement (conforming to BDS EN 197-1 : 2003 CEM-II/AM 42.5N) and sand (FM-1.00) mortar 1:8 filled gunny bags [minimum size L: 650mmX W:400mmX H:175mm], including washing of sand, mixing in standard mixture machine, filled & tamping the bags in place, stitching bags by hand sewing machine, curing by sprinkling water over the bags, including preparation of trenches (bed) by cutting or filling with ramming the filled up earth to the same profile as that of the finished toe level, placing the filled gunny bags along the toe line by avoiding vertical joints, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 0.8)

0.3203

m3

480.00

153.74

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.1301

bag

430.00

485.94

Empty Gunny Bag

8.0000

each

30.00

240.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

1.0000

day

370.00

370.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.1000

day

1200.00

120.00 1469.69

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1499.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1648.99

VAT

6% of Total

109.93

IT

4% of Total

73.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1832.21

Page: 216 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.21

Detailed Analysis Brief Description of Item 2 GB(1:8)-SPW: Providing single layer gunny bag on slope of embankment for slope protection with cement (conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N) and sand (FM-1.00) mortar 1:8 filled gunny bags [minimum size L: 650mmX W:400mmX H:175mm], including washing of sand, mixing in standard mixture machine, filled & tamping the bags in place, stitching bags by hand sewing machine, curing by sprinkling water over the bags, including preparation of slope (bed) by cutting or filling with ramming the filled up earth to the same profile as that of the finished slope level, placing the filled gunny bags along the slope by minimum 40% overlapping to the successive previous layer and avoiding vertical joints, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-incharge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 0.8)

0.1820

m3

480.00

87.36

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.6421

bag

430.00

276.10

Empty Gunny Bag

5.0000

each

30.00

150.00

Mason

0.0625

day

550.00

34.38

Skilled Labour

0.0625

day

450.00

28.13

Ordinary Labour

0.6250

day

370.00

231.25

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0625

day

1200.00

75.00 882.21

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

899.86

10% Profit ( Add 10% on Subtotal-B) :

989.84

VAT

6% of Total

IT

4% of Total

65.99 43.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1099.83

Page: 217 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.22

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

DSFGB: Supplying & dumping of soil filled geo-textile bags of different size and capacity (fill volume and weight when filled with dry sand/earth) at the specified locations along the bottom of piles of piers/ toe line properly, including loading, unloading, carrying geo-bags from stack-yard to dumping place by head load and power driven flat top country boat etc. including supplying of geo-textile bags (empty) of different sizes and capacity at project/work site conforming to the following Technical Specifications, filling of empty geo-textile bags of different sizes with suitable soil, stitching the bags by hand sewing machine in accordance with the detailed drawing and technical specifications with plastic thread, protecting the geo-textile bags from UV ray or any other damages and dumping the same in position etc. including higher charge and mobilization of all equipment, materials, labours, taxes, incidental charges etc. complete in all respect as per approved drawing, specification and direction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 218 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.22.01

Detailed Analysis Brief Description of Item 2 Geo-Textile Bag: Empty Size: 800mm x 650mm, Fill Volumn: 0.0520 cum & Weight: 80 Kg, [Geo-Textile Grade: Grade-III-DF-40-2.3mm thick]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Geo Textile (Grade-III-DF-40-2.3mm thick)

1.1900

m2

65.00

77.35

Royalty of Earth

0.0520

m3

25.00

1.30

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.0514

day

370.00

19.02

H.C. of Sewing Machine

0.0029

day

500.00

1.45

H.C. of Cutter (Geo-Textile)

0.0017

day

500.00

0.85 103.12

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

5.16 108.27

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

110.44

10% Profit ( Add 10% on Subtotal-B) :

121.48

VAT

6% of Total

8.10

IT

4% of Total

5.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

134.98

Page: 219 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.22.02

Detailed Analysis Brief Description of Item 2 Geo-Textile Bag: Empty Bag Size: 900mm x 700mm, Fill Volumn: 0.0730 cum & Weight: 110 Kg, [Geo-Textile Grade: Grade-III-DF-402.3mm thick]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Geo Textile (Grade-III-DF-40-2.3mm thick)

1.4250

m2

65.00

92.63

Operator

0.0033

day

570.00

1.88

Helper

0.0017

day

400.00

0.68

Royalty of Earth

0.0730

m3

25.00

1.83

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0600

day

370.00

22.20

H.C. of Sewing Machine

0.0033

day

500.00

1.65

H.C. of Cutter (Geo-Textile)

0.0020

day

500.00

1.00 123.82

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6.19 130.01

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.61

10% Profit ( Add 10% on Subtotal-B) :

145.87

VAT

6% of Total

IT

4% of Total

9.72 6.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

162.08

Page: 220 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.22.03

Detailed Analysis Brief Description of Item 2 Geo-Textile Bag: Empty Bag Size: 950mm x 750mm, Fill Volumn: 0.0840 cum & Weight: 125 Kg, [Geo-Textile Grade: Grade-III-DF-402.3mm thick]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Geo Textile (Grade-III-DF-40-2.3mm thick)

1.6000

m2

65.00

104.00

Operator

0.0033

day

570.00

1.88

Helper

0.0020

day

400.00

0.80

Royalty of Earth

0.0840

m3

25.00

2.10

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0700

day

370.00

25.90

H.C. of Sewing Machine

0.0033

day

500.00

1.65

H.C. of Cutter (Geo-Textile)

0.0017

day

500.00

0.85 139.14

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6.96 146.10

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

149.02

10% Profit ( Add 10% on Subtotal-B) :

163.92

VAT

6% of Total

IT

4% of Total

10.93 7.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

182.14

Page: 221 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.22.04

Detailed Analysis Brief Description of Item 2 Geo-Textile Bag: Empty Bag Size: 1075mm x 850mm, Fill Volumn: 0.1164 cum & Weight: 175 Kg, [Geo-Textile Grade: Grade-V-DF-603.0mm thick]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Geo Textile (Grade-V-DF-60-3.0mm thick)

2.0250

m2

90.00

182.25

Operator

0.0040

day

570.00

2.28

Helper

0.0020

day

400.00

0.80

Royalty of Earth

0.1164

m3

25.00

2.91

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0800

day

370.00

29.60

H.C. of Sewing Machine

0.0040

day

500.00

2.00

H.C. of Cutter (Geo-Textile)

0.0025

day

500.00

1.25 223.05

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11.15 234.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

238.89

10% Profit ( Add 10% on Subtotal-B) :

262.78

VAT

6% of Total

IT

4% of Total

17.52 11.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

291.97

Page: 222 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.22.05

Detailed Analysis Brief Description of Item 2 Geo-Textile Bag: Empty Bag Size: 1100mm x 850mm, Fill Volumn: 0.1333 cum & Weight: 200 Kg, [Geo-Textile Grade: Grade-V-DF-603.0mm thick]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Geo Textile (Grade-V-DF-60-3.0mm thick)

2.0700

m2

90.00

186.30

Operator

0.0040

day

570.00

2.28

Helper

0.0020

day

400.00

0.80

Royalty of Earth

0.1333

m3

25.00

3.33

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0900

day

370.00

33.30

H.C. of Sewing Machine

0.0040

day

500.00

2.00

H.C. of Cutter (Geo-Textile)

0.0025

day

500.00

1.25 231.22

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11.56 242.78

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

247.64

10% Profit ( Add 10% on Subtotal-B) :

272.40

VAT

6% of Total

IT

4% of Total

18.16 12.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

302.67

Page: 223 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.22.06

Detailed Analysis Brief Description of Item 2 Geo-Textile Bag: Empty Bag Size: 1300mm x 1050mm, Fill Volumn: 0.1664 cum & Weight: 250 Kg, [Geo-Textile Grade: Grade-V-DF-603.0mm thick]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Geo Textile (Grade-V-DF-60-3.0mm thick)

2.9700

m2

90.00

267.30

Operator

0.0040

day

570.00

2.28

Helper

0.0020

day

400.00

0.80

Royalty of Earth

0.1664

m3

25.00

4.16

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Sewing Machine

0.0040

day

500.00

2.00

H.C. of Cutter (Geo-Textile)

0.0025

day

500.00

1.25 316.75

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

15.84 332.59

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

339.24

10% Profit ( Add 10% on Subtotal-B) :

373.16

VAT

6% of Total

IT

4% of Total

24.88 16.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

414.63

Page: 224 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.23

Detailed Analysis Brief Description of Item 2 DSFPB: Supplying and Dumping of soil filled Plastic bags at the specified locations bridge approaches/damaged slope areas properly (Each bag shall be 50kg Capacity minimum), including supplying of plastic bags, filling with suitable soil and stitching bags by hand sewing machine properly with plastic thread and dumping the same in position etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. (Unit cost including Plastic Bags, Stitching of bags, Filled with suitable soil, Dumping at specified locations and all other incidental charges, etc.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Empty Plastic Cement/Fertilizer Bag

1.0000

each

10.00

10.00

Royalty of Earth

0.0300

m3

25.00

0.75

Skilled Labour

0.0067

day

450.00

3.02

Ordinary Labour

0.0733

day

370.00

27.12 40.89

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +3.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1.23 42.11

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

42.95

10% Profit ( Add 10% on Subtotal-B) :

47.25

VAT

6% of Total

IT

4% of Total

3.15 2.10 Total:

3.11.24

Amount

52.50

JGT_RBP: Supplying and laying of natural additive treated woven type double warp plain weave jute geo-textile (JGT) conforming to BDS 1909: 2016 for river bank and slope protection work including local handling, unrolling, placing in position, ensuring proper drapability (JGT should touch the ground surface at all points), stapling JGT by 6mm dia. U-shapped pegs/ hooknails or 37mm long mushroom shaped nails at an interval of 300mm with overlaps of 100mm, protecting the JGT from any other damages etc. all complete in all respect as per instructions given in Annexure-B (JGT Installation Guideline for River Bank Protection) of BDS 1909 : 2016 and approval of Engineer-In-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 225 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.24.01

Detailed Analysis Brief Description of Item 2 JGT_RBP-1: Applicable for mild to moderate River River Bank Protection work. This type of treated JGT shall have the following requirements. Ends x Picks /dm ≥ 85 x 32, Width(m) ≥ 1, Mass per unit area (gsm) = 627 ± 15%, Thickness under 2 kPa pressure (mm) = 2.0 ± 20%, AOS (O95) (μm) ≤ 150, Vertical Permeability (m/sec) ≥ 1.0 x10-3, Horizontal Permeability (m/sec) ≥ 6.0 x10-3, Grab Tensile Strength (N) MD x CD ≥ 950 x 230, Grab Tensile Elongation (%) MD x CD ≤ 35 x 45, CBR Puncture Resistance (N) ≥ 2500, Wide Width Tensile Strength (KN/m) MD x CD ≥ 20 x 10, Wide Width Elongation (%) MD x CD ≤ 12 x 10.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Natural Additive Treated Double Warp Plain Weave - 627 gsm

1.0800

sqm

139.00

150.12

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 162.02

Subtotal-A: Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

16.20 178.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

181.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

199.97

VAT

6% of Total

13.33

IT

4% of Total

8.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

222.18

Page: 226 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.25

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

JGT-HSM: Supplying and laying of open mesh Plain Weave jute geotextile (JGT) commonly known as Soil Saver of different grades conforming to BDS 1909: 2016 for Hill Slope Management work including local handling, unrolling, placing in position, unrolling of JGT in the direction of surface run-off, stapling JGT by 6mm dia. U-shapped hooknails at an interval of 300mm with overlaps of 100mm at the sides and 150mm at the ends, anchoring JGT within a trench at the two ends by filling the trench with big bats/gravel or other suitable materials, ensuring proper drapability (JGT must touch the ground surface at all points), filling drain materials immediately after laying of JGT, protecting the JGT from any other damages etc. all complete in all respect as per instructions given in Annexure-C (JGT Installation Guideline for Hill Slope Management) of BDS 1909 : 2016 and approval of Engineer-InCharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 227 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.25.01

Detailed Analysis Brief Description of Item 2 JGT_HSM-1: Applicable for Moderate slope (≤35 degree) & annual rainfall ≤ 2000mm. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 6.5 x 4.5, Width(m) = 1.22, Mass per unit area (gsm) = 500 ± 10%, Thickness under 2 kPa pressure (mm) = 4.5 ± 10%, Water Holding Capacity (% by weight) ≥ 400, Wide Width Tensile Strength (kN/m) MD x CD ≥ 6.5 x 6.0, Wide Width Elongation (%) MD x CD ≤ 14.0 x 14.0.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Open Mesh Plain Weave (Soil Saver) 500 gsm

1.0800

sqm

29.00

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40

Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

31.32

43.22

Subtotal-A:

4.32 47.54

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

48.49

10% Profit ( Add 10% on Subtotal-B) :

53.34

VAT

6% of Total

3.56

IT

4% of Total

2.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

59.27

Page: 228 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.25.02

Detailed Analysis Brief Description of Item 2 JGT_HSM-2: Applicable for Moderate slope (≤35 degree) & annual rainfall ≥ 2000mm and steep stope (>35 degree to ≤ 45 degree) & annual rainfall ≤ 2000mm. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 8 x 7, Width(m) = 1.22, Mass per unit area (gsm) = 600±10%, Thickness under 2 kPa pressure (mm) = 5.5±10%, Water Holding Capacity (% by weight) ≥ 400, Wide Width Tensile Strength (kN/m) MD x CD ≥ 12.0 x 6.0, Wide Width Elongation (%) MD x CD ≤ 14.0 x 14.0.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Open Mesh Plain Weave (Soil Saver) 600 gsm

1.0800

sqm

32.00

34.56

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 46.46

Subtotal-A: Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.65 51.11

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

52.13

10% Profit ( Add 10% on Subtotal-B) :

57.34

VAT

6% of Total

IT

4% of Total

3.82 2.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

63.71

Page: 229 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.25.03

Detailed Analysis Brief Description of Item 2 JGT_HSM-3: Applicable for steep stope (>35 degree to ≤ 45 degree) & annual rainfall > 2000mm. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 8 x 8, Width(m) = 1.22, Mass per unit area (gsm) = 700±10%, Thickness under 2 kPa pressure (mm) = 5.5±10%, Water Holding Capacity (% by weight) ≥ 400, Wide Width Tensile Strength (kN/m) MD x CD ≥ 14.0 x 7.0, Wide Width Elongation (%) MD x CD ≤ 14.0 x 14.0.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Open Mesh Plain Weave (Soil Saver) 700 gsm

1.0800

sqm

35.00

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40

Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

37.80

49.70

Subtotal-A:

4.97 54.67

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55.76

10% Profit ( Add 10% on Subtotal-B) :

61.34

VAT

6% of Total

4.09

IT

4% of Total

2.73 Total:

3.11.26

Amount

68.16

JGT_RRC: Supplying and laying of woven type untreated double warp plain weave jute geo-textile (JGT) of different grades conforming to BDS 1909: 2016 for strengthening subgrade of Road & Bridge approach including local handling, unrolling, placing in position, ensuring proper drapability (JGT should touch the ISG surface at all points), stapling JGT by 6mm dia. U-shapped pegs/ hooknails or 37mm long mushroom shaped nails at an interval of 300mm with overlaps of 100mm, protecting the JGT from any other damages etc. all complete in all respect as per instructions given in Annexure-A (JGT Installation Guideline for Rural Road Construction) of BDS 1909 : 2016 and approval of Engineer-In-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 230 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.26.01

Detailed Analysis Brief Description of Item 2 JGT_RRC-1 : Applicable for Strengthening subgrade of Village Roads. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 85 x 32, Width(m) ≥ 1, Mass per unit area (gsm) = 627 ± 10%, Thickness under 2 kPa pressure (mm) = 2.0 ± 10%, AOS (O95) (μm) ≤ 450, Vertical Permeability (m/sec) ≥ 3.0 x10-3, Horizontal Permeability (m/sec) ≥ 7.0 x10-3, Grab Tensile Strength (N) MD x CD ≥ 850 x 200, Grab Tensile Elongation (%) MD x CD ≤ 30 x 35, CBR Puncture Resistance (N) ≥ 2000, Wide Width Tensile Strength (kN/m) MD x CD ≥ 20 x 10, Wide Width Elongation (%) MD x CD ≤ 12 x 10.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Double Warp Plain Weave - 627 gsm

1.0800

sqm

99.00

106.92

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 118.82

Subtotal-A: Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

11.88 130.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

133.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

146.65

VAT

6% of Total

IT

4% of Total

9.78 6.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

162.94

Page: 231 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.26.02

Detailed Analysis Brief Description of Item 2 JGT_RRC-2 : Applicable for Strengthening subgrade of Union or Higher Roads. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 94 x 39, Width(m) ≥ 1, Mass per unit area (gsm) = 724 ± 10%, Thickness under 2 kPa pressure (mm) = 2.0 ± 10%, AOS (O95) (μm) ≤ 300, Vertical Permeability (m/sec) ≥ 2.0 x10-3, Horizontal Permeability (m/sec) ≥ 6.0 x10-3, Grab Tensile Strength (N) MD x CD ≥ 925 x 425, Grab Tensile Elongation (%) MD x CD ≤ 35 x 40, CBR Puncture Resistance (N) ≥ 2150, Wide Width Tensile Strength (kN/m) MD x CD ≥ 25 x 10, Wide Width Elongation (%) MD x CD ≤ 15 x 12.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Double Warp Plain Weave - 724 gsm

1.0800

sqm

117.00

126.36

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 138.26

Subtotal-A: Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

13.83 152.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

155.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

170.64

VAT

6% of Total

IT

4% of Total

11.38 7.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

189.60

Page: 232 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.27

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

S&DSP: Supplying, delivering, assembling & installing of circular steel pipe conforming to ASTM A 252/ AASHTO M 183 of different diameter (internal) to a depth as shown in approved construction drawings for piling works including lowering & pitching the fabricated pipe in position, driving the pipe below bed level through all types of soils, fixing the pipe in position with necessary lateral bracings (if required) etc. for stability until completion of all works, including cost of gas cutting, bending, welding at fabrication shop & construction site, transporting & unloading safely at working site, driving of pipes, all sorts of labour, materials, hire charges of driving equipment, tools, any other related equipment, fuel, lubricants and wages of operational staff, taxes etc. all complete as per design, drawing, specification & direction of E-I-C. Only length of steel pipe driven as per drawing will be paid, wastage shall not be considered for payment. All longitudinal and transverse welds shall be made with full penetration butt welds and adjacent segments shall be rotated 90 degree relative to each other so that longitudinal welds on the fabricated casing are staggered. The outside (expose) surface of the steel pipe shall receive two coats of anti-corrosion tar type paint which shall be approved by the E-I-C and its application shall follow the manufacturer's instructions. If the handling, transportation, driving arrangement requires a greater thickness to avoid deformation or buckling of pipe, the increase in thickness shall be provided by the contractor at his own expense.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 233 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.11.27.01

Detailed Analysis Brief Description of Item 2 200mm internal diameter and 6mm wall thickness

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 5mm thick 200mm dia MS pipe-6.5mm thick

1.0000

m

3608.00

3608.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0088

day

3000.00

26.40

H.C. of Derrick

0.0175

day

400.00

7.00

H.C. of Welding Machine

0.0175

day

500.00

8.75

Foreman

0.0088

day

800.00

7.04

Operator

0.0088

day

570.00

5.02

Skilled Labour

0.0175

day

450.00

7.88

Diesel

0.5000

liter

68.00

34.00

Lubricant

0.0090

liter

220.00

1.98 3706.06

Subtotal-A: Cost of welding & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

185.30 3891.36

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3969.19

10% Profit ( Add 10% on Subtotal-B) :

4366.11

VAT

6% of Total

IT

4% of Total

291.07 194.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4851.23

Page: 234 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.01.1

Detailed Analysis Brief Description of Item 2 kmPost: Providing, fitting and fixing rectangular Kilometer Post as per standard drawing enumerated in Appendix-6 (type design for Kilometer post) with Reinforced Cement Concrete (1:2:4) Plate with 20mm down well graded brick chips in correct position true to line and level, including cost of providing 4 nos. of 12mm dia M.S. rods in vertical direction of length 1085mm and 7nos. Of 10mm dia M.S. rods in horizontal direction of length 520mm, RCC Plate firmly fixed to the ground by means properly designed foundation as per approved drawing with 1st class bricks work in cement mortar (1:4), filling the interstices tightly with mortar, raking out joints, cleaning and soaking bricks at least for 24 hours before use, washing of sand, including 6mm thick plaster (1:4) in all exposed portion, curing for requisite period, with two coat of painting on the exposed portion of the post with best quality synthetic enamel paint of approved brand of different shades over a coat of priming, including carriage of the post to the site with loading & unloading and printing of letters and numbers, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Unit

Sub-Item

3

4

5

Unit

Rate

6

7

Amount 8

each

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.2450

cum

75.80

18.57

Brick work with 1st class bricks in cement mortar (1:4) in foundation and plinth….(5.04.02)

0.1390

cum

5849.80

813.12

Providing and laying reinforced, cement concrete pavement over a prepared sub-base with picked brick chips and minimum cement content relates to mix ratio 1:2:4 satisfying ……… (3.07.2.1)

0.0510

cum

6851.66

349.43

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

6.0960

kg

61.59

375.45

Minimum 6mm thick cement plaster (1:4) to ceiling RCC columns, beams for Ground Floor……….. (5.12.03.01)

1.9430

sqm

168.65

327.68

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0490

cum

75.80

3.71

Painting with Synthetic Enamel paint………. (3.12.5.1)

1.0670

sqm

166.35

177.49

Subtotal-A: Note : Rates of all items should be inclusive of all supply and carriage.

Quantity

2065.47 Page: 235 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Writing of km post with approved colour

Quantity 5

Unit

Rate

6

7

( +12.00 % on Subtotal-A )

Subtotal-A1:

8 247.86 2313.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2359.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2595.55

VAT

6% of Total

IT

4% of Total

173.04 115.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2883.95

Page: 236 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.01.2

Detailed Analysis Brief Description of Item 2 RNPlate: Providing, fitting and fixing rectangular Road Name Plate as per standard drawing enumerated in Appendix-6 (type design for Road Name Plate) with Reinforced Cement Concrete (1:2:4) Plate with 20mm down well graded brick chips in correct position true to line and level, including cost of providing 7 nos. of 12mm dia M.S. rods in vertical direction of length 1125mm and 8nos. Of 10mm dia M.S. rods in horizontal direction of length 970mm, RCC Plate firmly fixed to the ground by means properly designed foundation as per approved drawing with 1st class bricks work in cement mortar (1:4), filling the interstices tightly with mortar, raking out joints, cleaning and soaking bricks at least for 24 hours before use, washing of sand, including 6mm thick plaster (1:4) in all exposed portion, curing for requisite period, with two coat of painting on the exposed portion of the post with best quality synthetic enamel paint of approved brand of different shades over a coat of priming, including carriage of the post to the site with loading & unloading and printing of letters and numbers, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Unit

Sub-Item

3

4

5

Unit

Rate

6

7

Amount 8

each

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.4890

cum

75.80

37.07

Brick work with 1st class bricks in cement mortar (1:4) in foundation and plinth….(5.04.02)

0.2780

cum

5849.80

1626.24

Providing and laying reinforced, cement concrete pavement over a prepared sub-base with picked brick chips and minimum cement content relates to mix ratio 1:2:4 satisfying ……… (3.07.2.1)

0.0950

cum

6851.66

650.91

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

11.7420

kg

61.59

723.19

Minimum 6mm thick cement plaster (1:4) to ceiling RCC columns, beams for Ground Floor……….. (5.12.03.01)

3.5330

sqm

168.65

595.83

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0980

cum

75.80

7.43

Painting with Synthetic Enamel paint………. (3.12.5.1)

1.7780

sqm

166.35

295.77

Subtotal-A: Note : Rates of all items should be inclusive of all supply and carriage.

Quantity

3936.43 Page: 237 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity

Writing of Road Name Plate post with approved colour

5

Unit

Rate

6

7

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

8 472.37 4408.81

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4496.98

10% Profit ( Add 10% on Subtotal-B) :

4946.68

VAT

6% of Total

IT

4% of Total

329.78 219.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5496.31

Page: 238 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.02

Detailed Analysis Brief Description of Item 2 RCC-Gpost: Prroviding, fitting and fixing 200mm dia round RCC Guide Post 1.70m long as per standard drawing enumerated in Appendix-6 (type design for Guide Post) with Reinforced Cement Concrete (1:2:4) with 20mm down well graded brick chips casting, curing for requisite period, including cost of providing 4nos.of 12mm dia. Rod of length 1.65m as main reinforcement and 12 nos. of round shaped 8mm dia rods used as binders; including two coats of painting with best quality synthetic enamel paint over a prime coat of approved brand of different colour and grade to form 6 nos. horizontal alternate bands in white/yellow and red to 90 cm length standing up above ground, making hole in ground of 800mm depth and 300m minimum dia, fixing the guard posts in the same holes and repacking the earth properly so as to keep the guard posts standing properly erect in correct position true to line and length including carriage of RCC Guide Post with due care to the site including loading into the truck and unloading at site complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0860

cum

75.80

6.52

Providing and laying reinforced, cement concrete pavement over a prepared sub-base with picked brick chips and minimum cement content relates to mix ratio 1:2:4 satisfying ……… (3.07.2.1)

0.0650

cum

6851.66

445.36

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

8.4680

kg

61.59

521.54

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0170

cum

75.80

1.29

Painting with Synthetic Enamel paint………. (3.12.5.1)

0.6280

sqm

166.35

104.47 1079.18

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1100.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1210.83

VAT

6% of Total

IT

4% of Total

80.72 53.81 Page: 239 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 1345.37

Page: 240 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.03

Detailed Analysis Brief Description of Item 2 RS-Plate: Supplying, fitting and fixing of Road Sign plates (Precautionary/Mandatory/Informative/Direction) made of 18 BWG M.S. sheet of equilateral triangle/Circular/Rectangular plates of different sizes as per standard drawing enumerated in Appendix-6 fitted with MS triangular/Rectangular frame of same size as plates by point welding (frames made by thorough welding of 25mmX25mmX3mm MS angle covering all sides of the plates and maximum 150mm center to center in the middle of frames in each vertical & horizontal directions), Plates are fitted with 50mm dia & 2.90mm thick GI pipes by continuous welding, including cutting of MS angle touched with GI pipe and 200mm long 4 nos. 12mm dia anchor bars be fitted at the lower part of the MS pipes by welding, making finishing, grinding and carrying to the working sites, etc. all complete in all respect as per design, specification and direction of the Engineer-in-charge. (Rate excludes the material cost of 50mm dia MS pipes & 4 nos. 12mm dia anchor bar)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

18/20/22 BWG MS Sheet/plate

9.9600

kg

70.00

697.20

MS Angle 25mmx25mmx3mm

14.6360

kg

58.00

848.89

Electrode

0.2300

pkt

810.00

186.30

Foreman

0.0800

day

800.00

64.00

Welder

0.4000

day

680.00

272.00

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

0.6000

day

370.00

222.00

H.C. of Welding Machine

0.3000

day

500.00

150.00

H.C. of Grinding Machine

0.3000

day

100.00

30.00 2537.89

Subtotal-A: Carrying cost to working site, etc.

( +3.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

76.14 2614.02

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2666.31

10% Profit ( Add 10% on Subtotal-B) :

2932.94

VAT

6% of Total

IT

4% of Total

195.53 130.35 Page: 241 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

3.12.04

Amount 8 3258.82

CRS-Plate: Providing and fixing of retro-reflectorized cautionary, mandatory and informatory sign as per standard drawing enumerated in Appendix-6 (type design for Traffic Signs) made of 18 BWG M.S. sheet of equilateral triangle/Circular/Rectangular plates of different sizes as mentioned in the drawing fitted with MS triangular/Rectangular frame of same size as plates by point welding (frames made by thorough welding of 25mmX25mmX3mm MS angle covering all sides of the plates and maximum 150mm center to center in the middle of frames in each vertical & horizontal directions), Plates are fitted with 50mm dia & 2.90mm thick MS pipes by continuous welding, including cutting of MS angle at touched point of MS pipe, including cost of providing 200mm long 4 nos. 12mm dia anchor bars be fitted at the lower part of the GI pipes by welding, making finishing, grinding and carrying to the working sites, the post firmly fixed to the ground by means of properly deigned foundation with cement concrete of minimum cylinder crushing strength of concrete 17.0Mpa at 28 days of curing (Suggested Mix Proportion 1:2:4), 60cm below the ground level, the signs properly erect in correct position, true to line and length, including two coats of painting with best quality synthetic enamel paint of approved brand & printing with retro-reflective paint of different approved colour, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 242 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.04.1

Detailed Analysis Brief Description of Item 2 600mm equilateral triangle with 671mm X 202mm supplementary Plate (For Precautionary Sign)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.3380

cum

75.80

25.62

2.9mm thick MS Pipe (50mm dia)

3.2700

m

440.00

1438.80

Providing single layer polythene sheet (0.18mm thick)……… (3.07.1)

1.4400

sqm

12.68

18.26

Cement concrete work in foundation……….. (4.1.10.01.2)

0.1690

cum

6964.15

1176.94

Supplying, fitting and fixing of Road Sign plates………. (3.12.3)

0.3370

sqm

2614.02

880.93

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

0.7100

kg

61.59

43.73

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0680

cum

75.80

5.15

Painting with Synthetic Enamel paint………. (3.12.5.1)

1.2980

sqm

166.35

215.92 3805.35

Subtotal-A: Writing & Printing of Road Sign with RetroReflective Paint, etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

456.64 4261.99

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4347.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4781.95

VAT

6% of Total

318.80

IT

4% of Total

212.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5313.28

Page: 243 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

3.12.04.2

600mm circular with 600mm X 202mm supplementary Plate (For Compulsory Sign)

each

Quantity 5

Unit

Rate

6

7

8

2.9mm thick MS Pipe (50mm dia)

3.2700

m

440.00

1438.80

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.3380

cum

75.80

25.62

Providing single layer polythene sheet (0.18mm thick)……… (3.07.1)

1.4400

sqm

12.68

18.26

Cement concrete work in foundation……….. (4.1.10.01.2)

0.1690

cum

6964.15

1176.94

Supplying, fitting and fixing of Road Sign plates………. (3.12.3)

0.4040

sqm

2614.02

1056.07

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

0.7100

kg

61.59

43.73

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0680

cum

75.80

5.15

Painting with Synthetic Enamel paint………. (3.12.5.1)

1.4320

sqm

166.35

238.21 4002.78

Subtotal-A: Writing & Printing of Road Sign with TetroReflective Paint, etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

480.33 4483.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4572.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5030.05

VAT

6% of Total

335.34

IT

4% of Total

223.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5588.95

Page: 244 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.04.3

Detailed Analysis Brief Description of Item 2 435mm X 500mm Square with 435mm X 202mm supplementary Plate (For Informative Sign)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.3380

cum

75.80

25.62

2.9mm thick MS Pipe (50mm dia)

3.2200

m

440.00

1416.80

Providing single layer polythene sheet (0.18mm thick)……… (3.07.1)

1.4400

sqm

12.68

18.26

Cement concrete work in foundation……….. (4.1.10.01.2)

0.1690

cum

6964.15

1176.94

Supplying, fitting and fixing of Road Sign plates………. (3.12.3)

0.3050

sqm

2614.02

797.28

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

0.7100

kg

61.59

43.73

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0680

cum

75.80

5.15

Painting with Synthetic Enamel paint………. (3.12.5.1)

1.2230

sqm

166.35

203.44 3687.22

Subtotal-A: Writing & Printing of Road Sign with TetroReflective Paint, etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

442.47 4129.69

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4212.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4633.51

VAT

6% of Total

308.90

IT

4% of Total

205.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5148.35

Page: 245 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.04.4

Detailed Analysis Brief Description of Item 2 810mm X 480mm Rectangular (For Informative Sign)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each 2.9mm thick MS Pipe (50mm dia)

3.0300

m

440.00

1333.20

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.3380

cum

75.80

25.62

Providing single layer polythene sheet (0.18mm thick)……… (3.07.1)

1.4400

sqm

12.68

18.26

Cement concrete work in foundation……….. (4.1.10.01.2)

0.1690

cum

6964.15

1176.94

Supplying, fitting and fixing of Road Sign plates………. (3.12.3)

0.3890

sqm

2614.02

1016.86

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

0.7100

kg

61.59

43.73

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0680

cum

75.80

5.15

Painting with Synthetic Enamel paint………. (3.12.5.1)

1.3850

sqm

166.35

230.39 3850.15

Subtotal-A: Writing & Printing of Road Sign with TetroReflective Paint, etc.

( +11.00 % on Subtotal-A )

Subtotal-A1:

423.52 4273.67

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4359.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4795.05

VAT

6% of Total

319.67

IT

4% of Total

213.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5327.84

Page: 246 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.04.5

Detailed Analysis Brief Description of Item 2 600mm X 605mm Rectangular (For Chevron Sign)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Supplying, fitting and fixing of Road Sign plates………. (3.12.3)

0.3630

sqm

2614.02

948.89

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0300

cum

75.80

2.27

Providing single layer polythene sheet (0.18mm thick)……… (3.07.1)

1.0400

sqm

12.68

13.19

Painting with Synthetic Enamel paint………. (3.12.5.1)

0.7870

sqm

166.35

130.92

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.1510

cum

75.80

11.45

Cement concrete work in foundation……….. (4.1.10.01.2)

0.1040

cum

6964.15

724.27

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

0.6000

kg

61.59

36.95

2.9mm thick MS Pipe (50mm dia)

3.2000

m

440.00

1408.00 3275.94

Subtotal-A: Providing Retro-Reflective Sheeting for Sign

( +15.00 % on Subtotal-A )

Subtotal-A1:

491.39 3767.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3842.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4226.94

VAT

6% of Total

281.80

IT

4% of Total

187.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4696.60

Page: 247 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

3.12.05

Painting the vertical end faces of posts, wheel guard, railing, rail post, parapet wall, kilometer post, road name plate, guide post, traffic signs, etc. in two coats with best quality synthetic enamel paint of approved make and brand of different shades over a coat of priming, applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray, including cleaning and washing the surface, rubbing and mending good damages as necessary and necessary scaffolding, etc. all complete in all respect as direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

3.12.05.1

Two coats over a prime coat for new concrete surface.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Synthetic Enamel Paint

0.1194

litre

260.00

31.04

Synthetic enamel paint primer/ sealer

0.0833

litre

206.00

17.16

Thinner T-6 of Synthetic Enamel Paint

0.0119

liter

130.00

1.55

Plumber/ Electric Mistry/ Painter

0.0945

day

680.00

64.26

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0945

day

470.00

44.42 158.43

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

7.92 166.35

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.67

10% Profit ( Add 10% on Subtotal-B) :

186.64

VAT

6% of Total

IT

4% of Total

12.44 8.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

207.38

Page: 248 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.05.2

Detailed Analysis Brief Description of Item 2 Two coats for old concrete surface and steel surface.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Synthetic Enamel Paint

0.1194

litre

260.00

31.04

Thinner T-6 of Synthetic Enamel Paint

0.0119

liter

130.00

1.55

Plumber/ Electric Mistry/ Painter

0.0540

day

680.00

36.72

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0540

day

470.00

25.38 94.69

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

4.73 99.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

101.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

111.56

VAT

6% of Total

IT

4% of Total

7.44 4.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

123.95

Page: 249 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.06

Detailed Analysis Brief Description of Item 2 Painting and writing on kilometer post, road name plate, traffic signs, etc. in two coats with best quality synthetic enamel paint of approved make and brand of different shades, applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray with cleaning and washing the surface, rubbing and mending good damages as necessary and necessary scaffolding, including printing new letter and figures of any shade with synthetic enamel paint black or any other approved colour to give an even shade etc. all complete in all respect as direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Synthetic Enamel Paint

0.1194

litre

260.00

Thinner T-6 of Synthetic Enamel Paint

0.0119

liter

130.00

1.55

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0540

day

470.00

25.38 125.97

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, printing/writing, etc.

( +100.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

125.97 251.94

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

256.98

10% Profit ( Add 10% on Subtotal-B) :

282.68

VAT

6% of Total

IT

4% of Total

18.85 12.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

31.04

314.09

Page: 250 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

3.12.07

RMP: Providing and applying road marking paint (lines, dashes, arrows, etc.) on road hump, pedestrian crossing, lane line, warning line, barrier line, edge line, zig-zag line, give-way marking, etc. on road/plain surface by brush/roller in two coats with ready mixed road marking paint, including cleaning the surface of all dirt, oils, grease, dust and other contaminants, demarcation at site and traffic control involved. The finished surface to be level, uniform and free from streaks and holes, etc. all complete in all respect as direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour machinery, lighting, guarding, maintenance of diversion and all incidental charges in this connection.

3.12.07.1

Two coats for new surface

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Ready Mixed Road Marking Paint

0.3591

liter

608.75

218.60

Thinner T-4 of Ready Mixed Road Marking Paint

0.0539

liter

212.50

11.45

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 287.56

Subtotal-A: All other remaining costs covering sand paper, putty, tools, etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

14.38 301.93

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

307.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

338.77

VAT

6% of Total

IT

4% of Total

22.58 15.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

376.41

Page: 251 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 3.12.07.2

2 Two coats on old surface

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Ready Mixed Road Marking Paint

0.2873

liter

608.75

174.89

Thinner T-4 of Ready Mixed Road Marking Paint

0.0431

liter

212.50

9.16

Plumber/ Electric Mistry/ Painter

0.0438

day

680.00

29.78

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0438

day

470.00

20.59 234.42

Subtotal-A: All other remaining costs covering sand paper, putty, tools, etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

11.72 246.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

251.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

276.17

VAT

6% of Total

IT

4% of Total

18.41 12.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

306.86

Page: 252 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.08

Detailed Analysis Brief Description of Item 2 RMP(By-TPC): Providing and applying road markings of center line and stop line etc. with 2.5mm thick hot applied thermoplastic compound including reflectorising glass beads @ 250mgs per sqm area by special applicator machine on road/plain surface, including cleaning the surface of all dirt, oils, grease, dust and other contaminants, demarcation at site and traffic control involved, the finished surface to be level, uniform and free from streaks and holes, etc. all complete in all respect as direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour machinery, lighting, guarding, maintenance of diversion and all incidental charges in this connection.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Thermoplastic Compound

5.0000

kg

121.40

607.00

Reflectorising Glass Beads

0.2500

kg

121.40

30.35

H. C. of Thermoplastic Appilicator Machine

0.0286

day

2000.00

57.20

Foreman

0.0286

day

800.00

22.88

Skilled Labour

0.0571

day

450.00

25.70

Ordinary Labour

0.1143

day

370.00

42.29 785.42

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

801.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

881.24

VAT

6% of Total

IT

4% of Total

58.75 39.17 Total:

3.12.09

Maintenance and protection of traffic at all times (at all hours during the day and night) along the existing roads, rivers or canals throughout the working period by maintaining all detours, including additional embankment filling, necessary barricades, warning lights and guide signs as well as other equipment, removal of all temporary constructions on completion of the bridge, etc. all complete as per requirement and instruction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

979.15

LS

Page: 253 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.10

Detailed Analysis Brief Description of Item 2 RRSheeting: Supplying and fixing retro-reflectorised reflective sheeting on cautionary, mandatory and informatory traffic signs with honey comb retro-reflectorised (encapsulated lens type) reflective sheet of approved brand of different colour, including cleaning and washing the surface and necessary scaffolding, etc. including carriage of sheet to the site and fixing, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Retro-Reflecting Sheet

1.0000

sqm

2260.00

2260.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.0500

day

370.00

18.50 2301.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2347.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2581.72

VAT

6% of Total

IT

4% of Total

172.11 114.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2868.58

Page: 254 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 3.12.11

Detailed Analysis Brief Description of Item 2 AR-Paint: Supplying & providing flexible and acrylic type reflectorized traffic painting/ coating on rail post, rail bar, wheel guard, Guide Post, Pier column etc. Including cleaning the surface of all dirt, oils, grease, dust and other contaminants, demarcation at site and traffic control involved. The finished surface to be level, uniform and free from streaks and holes, etc. all complete in all respect as direction of the Engineer-incharge. Rate is inclusive of cost of all materials, labour machinery, lighting, guarding and all incidental charges in this connection.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Reflectorized paint

0.1200

liter

2528.00

303.36

Sealer/Primer (for texture paint)

0.0900

litre

200.00

18.00

Plumber/ Electric Mistry/ Painter

0.1500

day

680.00

102.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 493.86

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

503.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

554.11

VAT

6% of Total

IT

4% of Total

36.94 24.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

615.68

Page: 255 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Chapter - 4 : Bridge Works 4.01.01

Dismantling of existing/ damaged structures like culverts, bridges, retaining walls comprising of masonry, cement concrete, wood work, steel work by manual/ mechanical means and sorting the dismantled material, disposal of unserviceable material and stackting the serviceable material with all lifts and lead up to 1000 meters including scrapping and removing concrete from MS rods, preparation and erection of platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, leveling and dressing the site and clearing the river/canal bed, etc. all complete as per direction of the E-I-C. Cost of conveying, loading, transportation of unserviceable material accumulated during dismantling operation is included in this unit rate. The unserviceable material must be disposed at a safe place outside the site premises with minimum traffic disruption and the procuring entity will not provide any environmentally safe place for disposing the unserviceable materials.

4.01.01.01

RCC works

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 256 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.01.01.01.01

2 Case I: By Manual Means

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Blacksmith

0.2000

day

450.00

90.00

Skilled Labour

0.1200

day

450.00

54.00

Ordinary Labour

2.8000

day

370.00

1036.00

H.C. of Tractor (4 WD)

0.0200

day

2200.00

44.00 1224.00

Scaffolding & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

61.20 1285.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1310.90

10% Profit ( Add 10% on Subtotal-B) :

1441.99

VAT

6% of Total

IT

4% of Total

96.13 64.09 Total:

Case II: By Manual Means submersed in water

8

cum

Subtotal-A:

4.01.01.01.02

Amount

1602.22

Add +50.00% with Item No 4.01.01.01.01

Page: 257 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.01.01.01.03

2 Case III: By Mechanical Means

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Blacksmith

0.2000

day

450.00

90.00

Skilled Labour for Pneumatic breaker

0.5280

day

470.00

248.16

Skilled Labour

0.0400

day

450.00

18.00

Ordinary Labour

0.2000

day

370.00

74.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.1000

day

2500.00

250.00

Hire & running charges of Joint cutting machine with 2-3 blades

0.1000

day

1500.00

150.00

H.C. of Tractor (4 WD)

0.0200

day

2200.00

44.00 874.16

Scaffolding & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.01.01.02

PCC Works

Note : Rates of all items should be inclusive of all supply and carriage.

cum

43.71 917.87

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

936.23 1029.85

10% Profit ( Add 10% on Subtotal-B) :

VAT

68.66 45.77 Total:

Case IV: By Mechanical Means submersed in water

8

cum

Subtotal-A:

4.01.01.01.04

Amount

1144.28

Add +50.00% with Item No 4.01.01.01.03

Page: 258 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.01.01.02.01

2 Case I: By Manual Means

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Skilled Labour

0.0400

day

450.00

18.00

Ordinary Labour

1.0000

day

370.00

370.00

H.C. of Tractor (4 WD)

0.0200

day

2200.00

44.00 432.00

Scaffolding & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

21.60 453.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

462.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

508.94

VAT

6% of Total

IT

4% of Total

33.93 22.62 Total:

Case II: By Manual Means submersed in water

8

cum

Subtotal-A:

4.01.01.02.02

Amount

565.49

Add +50.00% with Item No 4.01.01.02.01

Page: 259 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.01.01.02.03

2 Case III: By Mechanical Means

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Skilled Labour for Pneumatic breaker

0.2000

day

470.00

94.00

Skilled Labour

0.0160

day

450.00

7.20

Ordinary Labour

0.2000

day

370.00

74.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.0667

day

2500.00

166.75

H.C. of Tractor (4 WD)

0.0200

day

2200.00

44.00 385.95

Scaffolding & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.01.01.03

Brick Works

Note : Rates of all items should be inclusive of all supply and carriage.

cum

19.30 405.25

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

413.35

10% Profit ( Add 10% on Subtotal-B) :

454.69

VAT

6% of Total

IT

4% of Total

30.31 20.21 Total:

Case IV: By Mechanical Means submersed in water

8

cum

Subtotal-A:

4.01.01.02.04

Amount

505.21

Add +50.00% with Item No 4.01.01.02.03

Page: 260 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.01.01.03.01

Detailed Analysis Brief Description of Item 2 Case I :By Manual/ Mechanical Means

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.6000

day

370.00

222.00

H.C. of Tractor (4 WD)

0.0200

day

2200.00

44.00 275.00

Equipment staging etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

4.01.01.04

Steel Work in all types of sections upto a height of 10m above plinth level including cutting of rivets.

Note : Rates of all items should be inclusive of all supply and carriage.

cum

13.75 288.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

294.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

323.98

VAT

6% of Total

IT

4% of Total

21.60 14.40 Total:

Case II :By Manual/ Mechanical Means submersed in water

8

cum

Subtotal-A:

4.01.01.03.02

Amount

359.98

Add +50.00% with Item No 4.01.01.03.01

Page: 261 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.01.01.04.01

2 Case I: Including dismembering

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT Blacksmith

1.0000

day

450.00

450.00

Skilled Labour

0.1400

day

450.00

63.00

Ordinary Labour

2.5000

day

370.00

925.00

H.C. of Tractor (4 WD)

0.0250

day

2200.00

55.00 1493.00

Subtotal-A: cost of labour for gas cutting, ropes, pulleys etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

298.60 1791.60

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1827.43

10% Profit ( Add 10% on Subtotal-B) :

2010.18

VAT

6% of Total

IT

4% of Total

134.01 89.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2233.53

Page: 262 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.01.01.04.02

Detailed Analysis Brief Description of Item 2 Case II: Excluding dismembering

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT Blacksmith

0.5000

day

450.00

225.00

Skilled Labour

0.2200

day

450.00

99.00

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Tractor (4 WD)

0.0250

day

2200.00

55.00 1119.00

Subtotal-A: cost of labour for gas cutting, ropes, pulleys etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

223.80 1342.80

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1369.66

10% Profit ( Add 10% on Subtotal-B) :

1506.62

VAT

6% of Total

IT

4% of Total

100.44 66.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1674.02

Page: 263 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.01.01.05

Wood Work wrought framed and fixed in frames of trusses upto a height of 10 m above plinth level

cum

Quantity 5

Unit

Rate

Amount

6

7

8

272.00

Carpenter

0.4000

day

680.00

Skilled Labour

0.0480

day

450.00

21.60

Ordinary Labour

0.8000

day

370.00

296.00

H.C. of Tractor (4 WD)

0.0200

day

2200.00

44.00 633.60

Subtotal-A: Equipment staging etc.

( +5.00 % on Subtotal-A )

31.68

Subtotal-A1:

665.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

678.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

746.44

VAT

6% of Total

49.76

IT

4% of Total

33.18 Total:

4.01.01.06

Dismantling wooden bullah in posts and structs

m Skilled Labour

0.0125

day

450.00

5.63

Ordinary Labour

0.0125

day

370.00

4.63

H.C. of Tractor (4 WD)

0.0006

day

2200.00

1.32 11.57

Subtotal-A: Equipment staging etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

0.58 12.15

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13.63

VAT

6% of Total

IT

4% of Total

0.91 0.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

829.38

15.15 Page: 264 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.01.01.07

Scraping of Bricks dismantled from Brick Work including Stacking

1000 nos.

Quantity 5

Unit

Rate

6

7

Amount 8

Skilled Labour

0.1400

day

450.00

63.00

Ordinary Labour

3.5000

day

370.00

1295.00 1358.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1385.16

10% Profit ( Add 10% on Subtotal-B) :

1523.68

VAT

6% of Total

IT

4% of Total

101.58 67.72 Total:

4.01.01.08

Removing & disposing all types of Pre-cast/ cast-in-situ pipes including Earthwork and Dismantling of Masonry Works.

4.01.01.08.01

Up to 600mm diameter

m Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.5200

day

370.00

192.40 201.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

205.43

10% Profit ( Add 10% on Subtotal-B) :

225.97

VAT

6% of Total

15.06

IT

4% of Total

10.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1692.97

251.08

Page: 265 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.01.01.08.02

2 For 600mm to 900mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.7000

day

370.00

259.00 272.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

277.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

305.75

VAT

6% of Total

20.38

IT

4% of Total

13.59 Total:

4.01.01.08.03

For above 900mm diameter

m Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

1.2000

day

370.00

444.00 466.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

475.83

10% Profit ( Add 10% on Subtotal-B) :

523.41

VAT

6% of Total

IT

4% of Total

34.89 23.26 Total:

4.01.02

Removal of telephone/ Electric poles including excavation and dismantling of foundation concrete and lines under the supervision of concerned department, disposal with all lifts and up to a lead of 1km and stacking the serviceable and unserviceable material separately.

LS

4.01.03

Dismantling of CI water pipe line of various diameter under supervision of concerned department including disposal with all lifts and lead up to 1Km and stacking of serviceable material and unserviceable material separately but excluding earth excavation and dismantling of masonry works.

LS

Note : Rates of all items should be inclusive of all supply and carriage.

339.72

581.57

Page: 266 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.01.04

Removal of cement concrete pipe of sewer gutter 1500 mm dia under the supervision of concerned department including disposal with all lifts and up to a lead of 1Km and stacking of serviceable and unserviceable material separately but excluding earth excavation and dismantling of masonry works.

4.01.05

Providing and maintaining semi pucca site office (Appendix 5) with necessary furniture, sanitary & electrical/ power facilities, water supply arrangement, office and survey equipment for the use of the Engineer and his staff, all complete including removal of structures and restoration of the site on completion of the work. The contractor shall submit the detailed plan and drawing of the site office for approval of the engineer. The site office should be provided with sufficient natural light, heat protecting ceiling, dam proofing etc. as per direction of E-I-C. All materials, equipment and plant, furniture, fittings recovered from dismantling the office and removing access road will be the property of the contractor upon completion of the work. The contractor will responsilbe for maintaining the facilities of site office in good condition throughout the contract period and payment of this item shall be made only with the final bill.

4.01.05.01

Area of field office: 30 sqm

LS

4.01.05.02

Area of field office: 50 sqm

LS

4.01.05.03

Area of field office: 80 sqm

LS

4.01.06

Videography: Providing and carrying out video shoting of roads, bridges, buildings, other programmes by professional videographer including hiring of vehicle, equipment for video shooting, titling, lightening, mixing, lettering, editing including cost of two DVDs of approved makes and quality etc. all complete as per direction of E-I-C. The edition of the video film and the script for narration shall be as approved by the engineer.

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

LS

Page: 267 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.01.06.01

Detailed Analysis Brief Description of Item 2 Within 50 Kilometer from district head quarter for full day

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

day Videographer

1.0000

day

2500.00

2500.00

Subtotal-A: Video Editing, Digital Storage media etc. all complete

( +15.00 % on Subtotal-A )

375.00

Subtotal-A1: Subtotal-B: Subtotal-C:

2875.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2932.50

10% Profit ( Add 10% on Subtotal-B) :

3225.75

VAT

6% of Total

IT

4% of Total

215.05 143.37 Total:

4.01.06.02

Beyond 50 Kilometer from district head quarter for full day

3584.17

day Videographer

1.0000

day

2500.00

Distance beyond 50 KM Video Editing, Digital Storage media etc. all complete

( +10.00 % on Subtotal-A ) ( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2500.00 2500.00

Subtotal-A:

250.00 375.00 3125.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3187.50

10% Profit ( Add 10% on Subtotal-B) :

3506.25

VAT

6% of Total

IT

4% of Total

233.75 155.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2500.00

3895.83

Page: 268 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.01.06.03

2 Work upto 5 hours per day only

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

day Videographer

0.6500

day

2500.00

1625.00

Subtotal-A: Video Editing, Digital Storage media etc. all complete

( +15.00 % on Subtotal-A )

243.75

Subtotal-A1: Subtotal-B: Subtotal-C:

1868.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1906.13

10% Profit ( Add 10% on Subtotal-B) :

2096.74

VAT

6% of Total

IT

4% of Total

139.78 93.19 Total:

4.01.07

Photography: Shooting of still photographs by professinal photographer at outdoor and indoor of construction and other works of building, bridges, roads etc. for recording the progress of works at any distances including hiring of vehicle, equipment for photo shooting, lightening, mixing, lettering, editing including cost of digitized media & min. 10 nos.4R images printed on photo paper etc. all complete as per direction of E-I-C.

2329.71

hour

Photographer

0.2000

day

1200.00

240.00 240.00

Subtotal-A: cost of Image editing, Photo Paper, storage media, printing, transport etc.

( +50.00 % on Subtotal-A )

Subtotal-A1:

120.00 360.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

367.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

403.92

VAT

6% of Total

IT

4% of Total

26.93 17.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1625.00

448.80

Page: 269 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.01.08

Detailed Analysis Brief Description of Item 2 As-Built Drawings: Providing 3 full sets of as-built drawings of the completed works subject to Engineer's approval in AutoCAD software in standard drawing paper. The As-Built Drawing shall clearly show the lines and dimensions of the permanent construction actually made based on the changes to the original design from time to time as ordered by the Engineer or proposed by the Contractor and approved by the Engineer. One set of as-built drawings shall be considered for final measurement and payment. The soft copy of the as-built drawings must be submitted to the Design Unit, LGED for future reference. If the contractor does not supply the as-built drawings by the date stated in the Particular Conditions of Contract (PCC), or they do not receive the Engineer's approval, the Engineer shall withhold the amount stated in the PCC from the payment due to the contractor.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

day

600.00

8

per scheme

CAD Operator

20.0000

cost of Paper, printing, binding etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12000.00 12000.00

Subtotal-A:

1200.00 13200.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13464.00

10% Profit ( Add 10% on Subtotal-B) :

14810.40

VAT

6% of Total

IT

4% of Total

987.36 658.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16456.00

Page: 270 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.01.09

Detailed Analysis Brief Description of Item 2 Project Profile Signboard: Providing and maintenance one project profile signboard as per direction of E-I-C, to be placed at a suitable place of the site including submission of proposals for the materials & size of the signboards (recommended size: 1800mm x 1200 mm with 2 nos. 75mm dia. MS post, outer & inner frames of board shall be 50mm x 50mm x 5mm & 20mm x 25mm x 5 mm respectively ) and text layout to the engineer for approval which will be positioned as directed by the engineer and removing the same on completeion of the works or as instructed by the E-I-C. Sheeting will be made of encapsulated lens with retro-reflective type and messages/ borders will be screen printed. The text shall mention among others the name of the project, name of the implementing agency, cost of the project, completion time, name of the contractor etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

MS Angle, Flat bar, Z bar 75mm dia. MS pipe and wall thickness 4mm 24 SWG GP Sheet Skilled Labour

30.0000

kg

59.00

1770.00

7.3000

m

780.00

5694.00

10.6500

kg

80.00

852.00

1.5300

day

450.00

688.50 9004.50

Subtotal-A: Cost of fabrication, welding, painting, writing, placing in position & PCC (1:2:4) etc.

( +25.00 % on Subtotal-A )

Subtotal-A1:

2251.13 11255.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11480.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12628.81

VAT

6% of Total

841.92

IT

4% of Total

561.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14032.01

Page: 271 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.01.10

Detailed Analysis Brief Description of Item 2 Bench Mark Pillar: Manufacturing, supplying & fixing in position RCC (1:2:4) Bench Mark Pillars of size 150mm x 150mm x 750mm, with 400mm x 400mm x 100mm base having 3 nos. 10mm dia MS bar each way at base, 4 nos. 10mm dia vertical bar and 8 nos. 6mm dia tie, including cost of form works, concreting, reinforcement, plastering at top, inscribing on exposed surface, finishing surface, curing, earth cutting, embedding 450mm below GL., backfilling, ramming etc. complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

RCC-17BCCM: Reinforced cement concrete work with minimum cement content ralates to nominal mix ratio 1:2:4 and maximum water cement ratio 0.45 having minimum required average strength, f'cr = 24 Mpa a.............4.09.01.02

0.0329

cum

7674.21

252.48

Minimum 6mm thick cement plaster including neat cement finishing (1:3) …… 4.06.05.01

0.4725

sqm

181.40

85.71

Earth work in excavation of foundation of structures by mechanical (Hydraulic excavator - Long Boom)/ manual means in all sorts of soil up to specified depth in accordance with requirements of lines, .............4.05.01.01.01

0.0911

cum

124.75

11.36

Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS ISO 6935-2:2006 (or standard subsequently released from BSTI) for all types of RCC work including straightening, rem.............4.11.01.01

4.7015

kg

61.59

289.57

Head Mason

0.0005

day

650.00

0.33

Mason

0.0060

day

550.00

3.30

Skilled Labour

0.0060

day

450.00

2.70

Ordinary Labour

0.1016

day

370.00

37.59 683.04

Subtotal-A: Misc. Sundry etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

68.30 751.34

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

766.37

10% Profit ( Add 10% on Subtotal-B) :

843.01

6% of Total

56.20 Page: 272 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

37.47 Total:

4.01.11

Overall environment management in addition to the clause 27 & 29 of GCC to the entire satisfaction of Engineer-in-charge

4.01.11.01

Improvement of Waste Disposal Facility for temporary camp site. There should be atleast one camp in each site, there should be 1 no of organic waste and 1 no of inorganic waste disposal facility.

936.67

each

Waste Disposal Facility

1.0000

each

10000.00

10000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10200.00

10% Profit ( Add 10% on Subtotal-B) :

11220.00

VAT

6% of Total

748.00

IT

4% of Total

498.67 Total:

4.01.11.02

Dust suppression measures

12466.67

km Dust suppresion measures

1.0000

km

2000.00

2000.00 2000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2040.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2244.00

VAT

6% of Total

IT

4% of Total

149.60 99.73 Total:

4.01.12

10000.00

2493.33

Providing and maintaining adequate portable water supply and sanitation facilities at camp site and work site to the entire satisfaction of Engineer-in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 273 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.01.12.01

Detailed Analysis Brief Description of Item 2 Temporary Toilet: There should be 1 camp in each site. In each camp, there should be 1 no of toilet for women and 1 no of toilet for men

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Temporary Toilet Facility at site

1.0000

each

10000.00

10000.00 10000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10200.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11220.00

VAT

6% of Total

748.00

IT

4% of Total

498.67 Total:

4.02.01

Amount

12466.67

Conducting detailed topographical survey by electronic total station (digital survey equipment) and investigation and collection of hydraulic data (essential design data as per appraisal format for bridges and culvert) regarding catchment area, L-section of road and canal, Xsection of canal at the point of crossing at upstream and down stream as well as making of HFL/OFL, transferring and fixing of pucca bench mark at site, to pin point all salient features such as roads, building, trees, water body, play field, green area, water supply lines, sewer lines, electric/ telephonic lines with poles, wells etc., taking all the boundary measurement, internal angles, North direction, preparation of survey drawing including spot levels/ contours ongrids 5m x 5m and plotting on AutoCAD etc. complete including of all necessary material and labour required for survey work. Contractor shall submit final topographical survey drawings in five copies duly spiral binded along with soft copy.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 274 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.02.01.01

Detailed Analysis Brief Description of Item 2 For catchment area less then 1.25 sq. Km.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Digital Topographical Survey & Collection of Hydraulic Data including equipment & transportation

1.2500

km2

20000.00

25000.00

Subtotal-A: Report Generation and consumables etc.

( +10.00 % on Subtotal-A )

2500.00

Subtotal-A1: Subtotal-B: Subtotal-C:

27500.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28050.00

10% Profit ( Add 10% on Subtotal-B) :

30855.00

VAT

6% of Total

IT

4% of Total

2057.00 1371.33 Total:

4.02.01.02

For catchment area less then 1.25 to 2.50 sq. Km.

34283.33

each Digital Topographical Survey & Collection of Hydraulic Data including equipment & transportation

2.5000

km2

20000.00

Report Generation and consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

50000.00 50000.00

Subtotal-A:

5000.00 55000.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56100.00

10% Profit ( Add 10% on Subtotal-B) :

61710.00

VAT

6% of Total

IT

4% of Total

4114.00 2742.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25000.00

68566.67

Page: 275 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.02.01.03

Detailed Analysis Brief Description of Item 2 For catchment area beyond then 2.50 sq. Km.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Digital Topographical Survey & Collection of Hydraulic Data including equipment & transportation

3.5000

km2

20000.00

Report Generation and consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

70000.00 70000.00

Subtotal-A:

7000.00 77000.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

78540.00

10% Profit ( Add 10% on Subtotal-B) :

86394.00

VAT

6% of Total

IT

4% of Total

5759.60 3839.73 Total:

4.02.02

Amount

95993.33

Survey and investigation and preparation of Report for bridge approach road work with chain and compass, auto level, theodolite or total station including fixing of permanent benchmark and also fixing of bench mark on all the permanent structures, along the alignment, like boundary wall, electrical poles etc. Also marking of locations of boundary wall, electric poles, telephone poles trees etc. in the road boundary, collection and submission of existing inventory of the road all along the alignment conducting survey@20 metre interval for L-section and for single lane Xsection interval will be @ 0.75, 1.25, 1.875, 2.60, 3.75, 4.50, 5.50 and 6.50 metre on both side of centre line for double or other lane interval for x-section shall be as specified by the E-I-C. Data collected as specified above are required to be submitted in both hard and soft copies, L-section, X-section and plan is required to be submitted in the shape of drawing sheets drawn with the help of auto plotter. Preparation of report complete and submission of the same in five copies duly spiral binded.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 276 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.02.02.01

2 For single lane road

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

km Digital Topographical Survey of Single Lane Road Alignment including equipment & transportation

1.0000

km

15000.00

15000.00

Subtotal-A: Report Generation and consumables etc.

( +10.00 % on Subtotal-A )

1500.00

Subtotal-A1: Subtotal-B: Subtotal-C:

16500.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16830.00

10% Profit ( Add 10% on Subtotal-B) :

18513.00

VAT

6% of Total

IT

4% of Total

1234.20 822.80 Total:

4.02.02.02

For double lane road

20570.00

km Digital Topographical Survey of Single Lane Road Alignment including equipment & transportation

1.3000

km

15000.00

Report Generation and consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

19500.00 19500.00

Subtotal-A:

1950.00 21450.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21879.00

10% Profit ( Add 10% on Subtotal-B) :

24066.90

VAT

6% of Total

IT

4% of Total

1604.46 1069.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15000.00

26741.00

Page: 277 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.02.02.03

2 Beyond the double lane

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

km Digital Topographical Survey of Single Lane Road Alignment including equipment & transportation

1.6000

km

15000.00

Report Generation and consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Sub-soil investigation at the actual locations of each abutment and pier positions in accordance with the specifications of ASTM D 1586 and D 1587. The bore holes shall have a minimum diameter of 100mm and shall be lined throughout and shall be minimum 30m to 45m deep or to a depth as specified in the ASTM/ AASHTO or as directed by the E-I-C from the existing GL and taking all cautions and steps to collect the disturbed and undisturbed samples and making the bore holes. The item is inclusive of mobilization & demobilization, proper method of borings, arrangement of boat/barge all cost of materials, labourers, field and laboratory tests including report and records. (The Testing Party will be selected taking prior approval of Procuring Entity)

4.02.03.01

Test on ground surface

LS

4.02.03.02

Test under water

LS

4.02.03.03

Test under water for flashy river with flow velocity > 1m/s

LS

2400.00 26400.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26928.00

10% Profit ( Add 10% on Subtotal-B) :

29620.80

VAT

6% of Total

IT

4% of Total

1974.72 1316.48 Total:

4.02.03

24000.00 24000.00

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

32912.00

Page: 278 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.02.04

Conducting Electronic Cone Penetration Test with pore pressure measurement, dissipation test as per ASTM D 5778 method upto 50m depth to measure friction angle, undrained shear strength, tip resistance,skin friction , Relative density, pore pressure etc. (The Testing Party will be selected taking prior approval of Procuring Entity)

4.02.04.01

Test on ground surface

LS

4.02.04.02

Test under water

LS

4.03.01

Construction of 2m wide temporary bamboo diversion bridge with 100mm average dia pucca borak bamboo in 4 (four) lines of posts longitudinally and required lines of posts 2m c/c transversely with beams and struts and every post with double bracing’s and each post driven to at least 0.75m depth including half split bamboo decking including supplying nuts, bolts, etc. fitting, fixing and supply, carrying and cost of all materials & labour, etc. all complete as per direction of the Engineer.

m

Borak Bamboo (75mm to 100mm)

Quantity 5

Unit

Rate

6

7

8

50.0000

m

42.00

2100.00

Nails/ Nut bolts/ Screw/ Spikes

1.0000

kg

65.00

65.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

0.7600

day

370.00

281.20 2671.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2724.62

10% Profit ( Add 10% on Subtotal-B) :

2997.09

VAT

6% of Total

IT

4% of Total

199.81 133.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3330.10

Page: 279 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.03.02

Detailed Analysis Brief Description of Item 2 Construction of 0.25m width bamboo sanko with 100mm dia pucca borak bamboo posts of required length @2.5m c/c driven at least 1m below ground level of stream with 75mm dia full bamboo decking beams, breaching diagonals with 100mm dia bamboo including fitting, fixing to complete satisfaction including supply of nails, nuts, bolts, etc. all materials, carrying and labour, etc. all complete as per direction of the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Borak Bamboo (75mm to 100mm)

20.0000

m

42.00

840.00

Nails/ Nut bolts/ Screw/ Spikes

0.5000

kg

65.00

32.50

Skilled Labour

0.2500

day

450.00

112.50

Ordinary Labour

0.5000

day

370.00

185.00 1170.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1193.40

10% Profit ( Add 10% on Subtotal-B) :

1312.74

VAT

6% of Total

87.52

IT

4% of Total

58.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1458.60

Page: 280 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.03.03

Detailed Analysis Brief Description of Item 2 MS work in timber bridge or timber structure including the supply, carrying and fitting of specified approved nuts, bolts, hinges, cleats, screws, washer, fish plate of specified and approved size and make, etc. all complete as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

Re-bar Fabricator

0.0030

day

570.00

1.71

Welder

0.0600

day

680.00

40.80

Nails/ Nut bolts/ Screw/ Spikes

1.0000

kg

65.00

65.00 107.51

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

109.66

10% Profit ( Add 10% on Subtotal-B) :

120.63

VAT

6% of Total

IT

4% of Total

8.04 5.36 Total:

4.03.04

Amount

134.03

Wood work with specified timber of different sizes in superstructure of timber bridges i.e. bracing’s, struts, diagonals, beams, cross beams, decking, railings, etc. including supply and carrying of timber, sizing and shaping, fitting, fixing with nut, bolt, nails, screw, washer including providing fish plate, etc. all complete as per design. The wood must be free from rots, knots, sap and shall be seasoned and creosoted with creosote oil, etc. all complete including supply, carrying and cost of all materials and labour, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 281 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.03.04.01

2 Jam (Black Berry/Jarul/Local Korai)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Jam/Jarul

1.0000

m3

65650.00

65650.00

Nails/ Nut bolts/ Screw/ Spikes

3.0000

kg

65.00

195.00

Carpenter

8.0000

day

680.00

5440.00

16.0000

day

450.00

7200.00

Skilled Labour

78485.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

80054.70

10% Profit ( Add 10% on Subtotal-B) :

88060.17

VAT

6% of Total

IT

4% of Total

5870.68 3913.79 Total:

4.03.04.02

Chittagong Silkorai

cum Sil Korai

1.0000

m3

88000.00

88000.00

Nails/ Nut bolts/ Screw/ Spikes

3.0000

kg

65.00

195.00

8.0000

day

680.00

5440.00

16.0000

day

450.00

7200.00

Carpenter Skilled Labour

100835.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102851.70

10% Profit ( Add 10% on Subtotal-B) :

113136.87

VAT

6% of Total

IT

4% of Total

7542.46 5028.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

97844.63

125707.63

Page: 282 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.03.04.03

2 Sundari/ Garjan

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Sundari/ Garzen

1.0000

m3

67580.00

67580.00

Nails/ Nut bolts/ Screw/ Spikes

3.0000

kg

65.00

195.00

Carpenter

8.0000

day

680.00

5440.00

16.0000

day

450.00

7200.00

Skilled Labour

80415.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

82023.30

10% Profit ( Add 10% on Subtotal-B) :

90225.63

VAT

6% of Total

IT

4% of Total

6015.04 4010.03 Total:

4.03.04.04

Shisu/ Mehagoni

cum Mehagoni/ Shishu

1.0000

m3

59730.00

59730.00

Nails/ Nut bolts/ Screw/ Spikes

3.0000

kg

65.00

195.00

8.0000

day

680.00

5440.00

16.0000

day

450.00

7200.00

Carpenter Skilled Labour

72565.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

74016.30

10% Profit ( Add 10% on Subtotal-B) :

81417.93

VAT

6% of Total

IT

4% of Total

5427.86 3618.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

100250.70

90464.37

Page: 283 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.03.04.05

2 Shal

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Shal

1.0000

m3

75000.00

75000.00

Nails/ Nut bolts/ Screw/ Spikes

3.0000

kg

65.00

195.00

Carpenter

8.0000

day

680.00

5440.00

16.0000

day

450.00

7200.00

Skilled Labour

87835.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

89591.70

10% Profit ( Add 10% on Subtotal-B) :

98550.87

VAT

6% of Total

IT

4% of Total

6570.06 4380.04 Total:

4.03.04.06

Babla

cum Babla

1.0000

m3

42000.00

42000.00

Nails/ Nut bolts/ Screw/ Spikes

3.0000

kg

65.00

195.00

8.0000

day

680.00

5440.00

16.0000

day

450.00

7200.00

Carpenter Skilled Labour

54835.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55931.70

10% Profit ( Add 10% on Subtotal-B) :

61524.87

VAT

6% of Total

IT

4% of Total

4101.66 2734.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

109500.97

68360.97

Page: 284 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.03.05

Construction of temporary diversion road of minimum width 4.8m on detour with arranged earth, protected with bamboo palisading if necessary, compacting the earth, keeping provision of drainage facilities with providing RCC pipe of required size, nos. and length, leveling, dressing the road surface for smoothly plying vehicle & maintaining the same till completion of bridges/ culvert construction including all materials labour and removal of the same after construction of bridge/ culvert all complete as per direction of the E-I-C.

4.03.05.01

Road Surface: Earthen

LS

4.03.05.02

Road Surface: 3.7m HBB pavement over BFS & 150mm ISG

LS

4.04.01

Labour charge for erecting and assembling of PSB, fitting, fixing in proper position and providing necessary decking by arrangement of all necessary tools and equipment including local handling of bridge parts and all incidental charges, etc. all complete as per direction of the E-I-C.

4.04.01.01

Single Bailey Bridge or Acrow panel.

Quantity 5

Unit

Rate

6

7

8

m Bailey Bridge Mistry

0.1430

day

680.00

97.24

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

7.2800

day

370.00

2693.60 3240.84

Subtotal-A: H.C. of Lunching equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

Subtotal-A1:

615.76 842.62 4699.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4793.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5272.52

VAT

6% of Total

IT

4% of Total

351.50 234.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5858.36

Page: 285 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.04.01.02

2 Double single Bailey Bridge or Acrow panel.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m Bailey Bridge Mistry

0.1680

day

680.00

114.24

Skilled Labour

1.1740

day

450.00

528.30

Ordinary Labour

8.5500

day

370.00

3163.50 3806.04

Subtotal-A: H.C. of Lunching equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

723.15 989.57

Subtotal-A1:

5518.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5629.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6192.05

VAT

6% of Total

412.80

IT

4% of Total

275.20 Total:

4.04.01.03

Calender Hamilton truss bridge

m Bailey Bridge Mistry

0.7000

day

680.00

476.00

Skilled Labour

4.8700

day

450.00

2191.50

35.0000

day

370.00

12950.00

Ordinary Labour

15617.50

Subtotal-A: H.C. of Lunching equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2967.33 4060.55 22645.38

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23098.28

10% Profit ( Add 10% on Subtotal-B) :

25408.11

VAT

6% of Total

IT

4% of Total

1693.87 1129.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6880.05

28231.23 Page: 286 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.04.01.04

2 Indian quadricon bridge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m Bailey Bridge Mistry

0.5600

day

680.00

380.80

Skilled Labour

3.9200

day

450.00

1764.00

28.5400

day

370.00

10559.80

Ordinary Labour

12704.60

Subtotal-A: H.C. of Lunching equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

2413.87 3303.20

Subtotal-A1:

18421.67

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18790.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20669.11

VAT

6% of Total

1377.94

IT

4% of Total

918.63 Total:

4.04.01.05

UCB and Chinese truss bridge

m Bailey Bridge Mistry

0.8400

day

680.00

571.20

Skilled Labour

5.8300

day

450.00

2623.50

42.4400

day

370.00

15702.80

Ordinary Labour

18897.50

Subtotal-A: H.C. of Lunching equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3590.53 4913.35 27401.38

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

27949.40

10% Profit ( Add 10% on Subtotal-B) :

30744.34

VAT

6% of Total

IT

4% of Total

2049.62 1366.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

22965.68

34160.38 Page: 287 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.04.02

Labour charge for delaunching of PSB with all necessary arrangements including necessary decking by arrangement of all necessary tools and equipment, all incidental charges, etc. all complete as per direction of the E-I-C.

4.04.02.01

Single Bailey Bridge or Acrow panel bridge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bailey Bridge Mistry

0.1000

day

680.00

68.00

Skilled Labour

0.7200

day

450.00

324.00

Ordinary Labour

5.1900

day

370.00

1920.30 2312.30

Subtotal-A: H.C. of De-lunching Equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

Subtotal-A1:

439.34 601.20 3352.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3419.89

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3761.88

VAT

6% of Total

IT

4% of Total

250.79 167.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4179.87

Page: 288 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.04.02.02

2 Double single Bailey Bridge or Acrow panel bridge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Bailey Bridge Mistry

0.1200

day

680.00

81.60

Skilled Labour

0.8640

day

450.00

388.80

Ordinary Labour

6.2300

day

370.00

2305.10 2775.50

Subtotal-A: H.C. of De-lunching Equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

527.35 721.63

Subtotal-A1:

4024.48

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4104.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4515.46

VAT

6% of Total

301.03

IT

4% of Total

200.69 Total:

4.04.02.03

Calender Hamilton truss bridge.

m Bailey Bridge Mistry

0.4940

day

680.00

335.92

Skilled Labour

3.5600

day

450.00

1602.00

25.6400

day

370.00

9486.80

Ordinary Labour

11424.72

Subtotal-A: H.C. of De-lunching Equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2170.70 2970.43 16565.84

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16897.16

10% Profit ( Add 10% on Subtotal-B) :

18586.88

VAT

6% of Total

IT

4% of Total

1239.13 826.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5017.18

20652.09 Page: 289 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.04.02.04

2 Indian quadricon bridge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m Bailey Bridge Mistry

0.4000

day

680.00

272.00

Skilled Labour

2.8700

day

450.00

1291.50

20.6600

day

370.00

7644.20

Ordinary Labour

9207.70

Subtotal-A: H.C. of De-lunching equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

1749.46 2394.00

Subtotal-A1:

13351.17

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13618.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14980.01

VAT

6% of Total

998.67

IT

4% of Total

665.78 Total:

4.04.02.05

UCB and Chinese truss bridge

m Bailey Bridge Mistry

0.5900

day

680.00

401.20

Skilled Labour

4.2400

day

450.00

1908.00

30.5700

day

370.00

11310.90

Ordinary Labour

13620.10

Subtotal-A: H.C. of De-lunching equipment Bullah, Bamboo, Wire, Nylon Rope, Jute, etc.

( +19.00 % on Subtotal-A ) ( +26.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2587.82 3541.23 19749.15

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20144.13

10% Profit ( Add 10% on Subtotal-B) :

22158.54

VAT

6% of Total

IT

4% of Total

1477.24 984.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

16644.45

24620.60 Page: 290 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

4.04.03

Supply and installation of steel pontoon of size 7.20mx4.00mx0.915m with plates (4mm thick), angles, flat bars, etc. shall be of steel of shipbuilding quality, hand capstan, hosting system pulley, bollards, winch, counter weight, manhole, CI roof, deck fittings, ramps, provision of inside inspection and carry out repair work in case of necessity, provision of de-watering, appropriate anchorage, steel fabrication, gas cutting, welding, paints (paints shall be used of BERGER Robbialac marine quality paints. Scrapping the entire steel surface shall be done before painting. Two coats of black bituminous paints to be used inside the pontoon and out side level including ramp) and other required accessories complete as per design, drawings, specifications and direction of the E-I-C. (Rate shall include all materials, labour, tools, equipment, plants, accessories, transportation, all taxes, VATs. charges, profits and maintenance for one year)

LS

4.04.04

Supply and installation of steel pontoon of size 18.00mx8.00mx1.00m with plates (8mm thick), angles, flat bars, etc. shall be of steel of shipbuilding quality, hand capstan, hosting system pulley, bollards, winch, counter weight, manhole, CI roof, deck fittings, ramps, provision of inside inspection and carry out repair work in case of necessity, provision of de-watering, appropriate anchorage, steel fabrication, gas cutting, welding, paints (paints shall be used of BERGER Robbialac marine quality paints. Scrapping the entire steel surface shall be done before painting. Two coats of black bituminous paints to be used inside the pontoon and out side level including ramp) and other required accessories complete as per design, drawings, specifications and direction of the E-I-C. (Rate shall include all materials, labour, tools, equipment, plants, accessories, transportation, all taxes, VATs. charges, profits and maintenance for one year)

LS

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 291 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.04.05

Detailed Analysis Brief Description of Item 2 Labour for erection of E.I. Rail including hoisting and placing in position etc. all complete as per direction of the E/C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Jute Rope

0.4000

kg

120.00

48.00

Ordinary Labour

0.7500

day

370.00

277.50 325.50

Subtotal-A: Subtotal-B: Subtotal-C:

4.04.06

Supplying C.I. Shoe of specified diameter including fitting, fixing etc. all complete as per direction of the E-I-C.

4.04.06.01

For 300mm dia.: Weight of each shoe should be at least 1.0 cwt

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

332.01

10% Profit ( Add 10% on Subtotal-B) :

365.21

VAT

6% of Total

IT

4% of Total

24.35 16.23 Total:

405.79

each CI Shoe (300mm dia)

1.0000

each

1650.00

1650.00

Ordinary Labour

0.2500

day

370.00

92.50 1742.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1777.35

10% Profit ( Add 10% on Subtotal-B) :

1955.09

VAT

6% of Total

130.34

IT

4% of Total

86.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2172.32

Page: 292 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.04.06.02

Detailed Analysis Brief Description of Item 2 For 600mm dia.: Weight of each shoe should be at least 2.0 cwt

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each CI Shoe (600mm dia)

1.0000

each

5200.00

5200.00

Ordinary Labour

0.3000

day

370.00

111.00 5311.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5417.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5958.94

VAT

6% of Total

397.26

IT

4% of Total

264.84 Total:

4.04.06.03

For 750mm dia.: Weight of each shoe should be atleast 3.0 cwt

each CI Shoe (750mm dia)

1.0000

each

6750.00

6750.00

Ordinary Labour

0.4500

day

370.00

166.50 6916.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7054.83

10% Profit ( Add 10% on Subtotal-B) :

7760.31

VAT

6% of Total

IT

4% of Total

517.35 344.90 Total:

4.04.07

6621.05

8622.57

Supplying C.I. Cap of standard size to fit on single/ double E.I. Rail, with necessary fittings etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 293 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.04.07.01

2 CI Cap (Single Headed)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each CI Cap (single headed)

1.0000

each

1650.00

1650.00

Ordinary Labour

0.2500

day

370.00

92.50 1742.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1777.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1955.09

VAT

6% of Total

130.34

IT

4% of Total

86.89 Total:

4.04.07.02

CI Cap (Double Headed)

each CI Cap (double headed)

1.0000

each

1875.00

1875.00

Ordinary Labour

0.3500

day

370.00

129.50 2004.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2044.59

10% Profit ( Add 10% on Subtotal-B) :

2249.05

VAT

6% of Total

IT

4% of Total

149.94 99.96 Total:

4.04.08

2172.32

2498.94

Labour for taking out E.I. Rail post with specified diameter C.I. shoe ( Portion embedded within earth only will be paid ) etc. all complete as per direction of the E/C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 294 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.04.08.01

2 For 300mm dia. CI shoe

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

370.00

m Ordinary Labour

1.0000

370.00

Subtotal-A: Necessary arrangement

( +15.00 % on Subtotal-A )

55.50

Subtotal-A1:

425.50

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

434.01

10% Profit ( Add 10% on Subtotal-B) :

477.41

VAT

6% of Total

IT

4% of Total

31.83 21.22 Total:

4.04.08.02

For 600mm dia. CI shoe

m Ordinary Labour

1.5000

day

370.00

Necessary arrangement

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

555.00 555.00

Subtotal-A:

111.00 666.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

679.32

10% Profit ( Add 10% on Subtotal-B) :

747.25

VAT

6% of Total

IT

4% of Total

49.82 33.21 Total:

4.04.09

530.46

830.28

Labour for driving E.I. Rail post with specified diameter C.I. shoe with all driving arrangements ( only under ground portion with shoe will be considered for measurement) etc. all complete as per direction of the EI-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 295 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.04.09.01

2 For 300mm dia CI shoe

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

510.60

m Ordinary Labour

1.3800

510.60

Subtotal-A: Necessary arrangement

( +18.00 % on Subtotal-A )

91.91

Subtotal-A1:

602.51

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

614.56

10% Profit ( Add 10% on Subtotal-B) :

676.01

VAT

6% of Total

IT

4% of Total

45.07 30.05 Total:

4.04.09.02

For 600mm dia CI shoe

m Ordinary Labour

1.6500

day

370.00

Necessary arrangement

( +22.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

610.50 610.50

Subtotal-A:

134.31 744.81

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

759.71

10% Profit ( Add 10% on Subtotal-B) :

835.68

VAT

6% of Total

IT

4% of Total

55.71 37.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

751.13

928.53

Page: 296 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.04.10

Detailed Analysis Brief Description of Item 2 Supplying double headed EI rail of standard size at site to construction iron bridge including necessary fitting, fixing, drilling the hole and priming a coat of red oxide etc. all complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Double Headed EI Rail

1.0000

m

2558.00

2558.00

Skilled Labour

0.5000

day

450.00

225.00 2783.00

Subtotal-A: All other cost including priming

( +2.00 % on Subtotal-A )

55.66

Subtotal-A1:

2838.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2895.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3184.98

VAT

6% of Total

212.33

IT

4% of Total

141.55 Total:

4.04.11

Supplying RS joist of different sizes at site to construct iron bridge in/c fitting, fixing etc. all complete as per direction of E-I-C.

kg RS Joist

1.0000

kg

75.00

75.00

Skilled Labour

0.0100

day

450.00

4.50 79.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

81.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

89.20

VAT

6% of Total

IT

4% of Total

5.95 3.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3538.86

99.11

Page: 297 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.04.12

Detailed Analysis Brief Description of Item 2 Labour for utilizing RS joist of different sizes of necessary fitting, fixing, drilling hole etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

450.00

8

kg Skilled Labour

0.0200

9.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9.18 10.10

VAT

6% of Total

0.67

IT

4% of Total

0.45 Total:

4.04.13

Supplying utilizing MS Angle, flat bar of different sizes or section in/c fitting, fixing etc. all complete as per direction if E-I-C.

11.22

kg MS Angle, Flat bar, Z bar

1.0000

kg

59.00

59.00

Skilled Labour

0.0250

day

450.00

11.25 70.25

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

71.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

78.82

VAT

6% of Total

IT

4% of Total

5.25 3.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9.00

87.58

Page: 298 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.05.01

Earth work in excavation of foundation of structures by mechanical (Hydraulic excavator - Long Boom)/ manual means in all sorts of soil up to specified depth in accordance with requirements of lines, grades, cross sections and elevation as shown in the drawing including setting out, removal of stumps, logs, boulders and other deleterious materials, providing necessary tools and plants, construction of shoring and bracing, cleaning the excavated materials to a safe distance out of the site premises, cut to a firm surface including pumping/ bailing out water, removal of spoils to a safe distance, dressing of sides and bottom and backfilling of trenches up to original level with approved material etc. all complete as per approval of E-I-C. Contractor shall get acquainted with site conditions, nature of soil and adopt suitable adequate dewatering system as deemed fit for the nature of soil and prevailing water table to get the surface reasonably dry for laying PCC at the time of execution so that execution will not be hampered or delayed. Back-filled materials shall be compacted to a density comparable with the adjacent undisturbed material.

4.05.01.01

Earth work in Ordinary Soil by Manual Means for an initial lead up to 30m

4.05.01.01.01

For depth up to 3m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.3000

day

370.00

111.00 124.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

127.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

139.97

VAT

6% of Total

9.33

IT

4% of Total

6.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

155.52

Page: 299 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.01.02

2 For depth 3m to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.3500

day

370.00

129.50 143.25

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

146.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

160.73

VAT

6% of Total

10.72

IT

4% of Total

7.14 Total:

4.05.01.01.03

For depth above 6m

cum Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.6000

day

370.00

222.00 235.75

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

240.47

10% Profit ( Add 10% on Subtotal-B) :

264.51

VAT

6% of Total

IT

4% of Total

17.63 11.76 Total:

4.05.01.02

178.59

293.90

Earth work in Ordinary Soil by Mechanical Means (Hydaulic Excavator) for an initial lead of 30m

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 300 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.02.01

2 For depth up to 3m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Skilled Labour

0.0030

day

450.00

1.35

Ordinary Labour

0.0182

day

370.00

6.73

Operator

0.0030

day

570.00

1.71

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0061

day

470.00

2.87

H.C. of Excavator (Medium Size)

0.0030

day

8880.00

26.64

Diesel

0.3697

liter

68.00

25.14

Lubricant

0.0109

liter

220.00

2.40 66.84

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

68.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

74.99

VAT

6% of Total

5.00

IT

4% of Total

3.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

83.33

Page: 301 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.02.02

2 For depth 3m to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Skilled Labour

0.0033

day

450.00

1.49

Ordinary Labour

0.0233

day

370.00

8.62

Operator

0.0033

day

570.00

1.88

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0067

day

470.00

3.15

H.C. of Excavator (Medium Size)

0.0033

day

8880.00

29.30

Diesel

0.4067

liter

68.00

27.66

Lubricant

0.0120

liter

220.00

2.64 74.74

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

76.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

83.85

VAT

6% of Total

5.59

IT

4% of Total

3.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

93.17

Page: 302 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.02.03

2 For depth above 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Skilled Labour

0.0037

day

450.00

1.67

Ordinary Labour

0.0296

day

370.00

10.95

Operator

0.0037

day

570.00

2.11

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0074

day

470.00

3.48

H.C. of Excavator (Medium Size)

0.0037

day

8880.00

32.86

Diesel

0.4519

liter

68.00

30.73

Lubricant

0.0133

liter

220.00

2.93 84.72

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

86.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

95.05

VAT

6% of Total

6.34

IT

4% of Total

4.22 Total:

4.05.01.03

Amount

105.61

Earth work in Rocky, gravelly, slushy or organic type Soil by Manual Means for an initial lead of 30m

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 303 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.03.01

2 For depth up to 3m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.4000

day

370.00

148.00 161.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

164.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

181.48

VAT

6% of Total

12.10

IT

4% of Total

8.07 Total:

4.05.01.03.02

For depth 3m to 6m

cum Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.5500

day

370.00

203.50 217.25

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

221.60

10% Profit ( Add 10% on Subtotal-B) :

243.75

VAT

6% of Total

IT

4% of Total

16.25 10.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

201.65

270.84

Page: 304 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.03.03

2 For depth above 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.6500

day

370.00

240.50 254.25

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

259.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

285.27

VAT

6% of Total

19.02

IT

4% of Total

12.68 Total:

4.05.01.04

Amount

316.97

Earth work Rocky, gravelly, slushy or organic type Soil by Mechanical Means (Hydaulic Excavator) for an initial lead of 30m

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 305 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.04.01

2 For depth up to 3m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Skilled Labour

0.0033

day

450.00

1.49

Ordinary Labour

0.0200

day

370.00

7.40

Operator

0.0033

day

570.00

1.88

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0067

day

470.00

3.15

H.C. of Excavator (Medium Size)

0.0033

day

8880.00

29.30

Diesel

0.4067

liter

68.00

27.66

Lubricant

0.0120

liter

220.00

2.64 73.51

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

74.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

82.48

VAT

6% of Total

5.50

IT

4% of Total

3.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

91.65

Page: 306 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.04.02

2 For depth 3m to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Skilled Labour

0.0036

day

450.00

1.62

Ordinary Labour

0.0291

day

370.00

10.77

Operator

0.0036

day

570.00

2.05

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0073

day

470.00

3.43

H.C. of Excavator (Medium Size)

0.0036

day

8880.00

31.97

Diesel

0.4436

liter

68.00

30.16

Lubricant

0.0131

liter

220.00

2.88 82.88

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

93.00

VAT

6% of Total

6.20

IT

4% of Total

4.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

103.33

Page: 307 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.01.04.03

2 For depth above 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0400

day

370.00

14.80

Operator

0.0040

day

570.00

2.28

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0080

day

470.00

3.76

H.C. of Excavator (Medium Size)

0.0040

day

8880.00

35.52

Diesel

0.4880

liter

68.00

33.18

Lubricant

0.0144

liter

220.00

3.17 94.51

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

96.40 106.04

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

7.07

IT

4% of Total

4.71 Total:

4.05.02

Amount

117.82

Disposing surplus excavated soils of all types outside the site premises up to a lead of specified distance including cost of labour, cost of equipment and machinery, loading and unloading at both ends, transportation, all other incidental charges at all leads and lifts etc. complete as per approval of the E-I-C. The surplus excavated material must be dumped in an unobjectionable place outside the site premises with minimum traffic disruption and the procuring entity will not be responsible for any irregularities by the party regarding disposing of the earth.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 308 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.05.02.01

2 Lead up to 500m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Operator

0.0057

day

570.00

3.25

Ordinary Labour

0.0114

day

370.00

4.22

H.C. of Tipper -5 cum capacity

0.0057

day

4500.00

25.65

H.C. of Tipper -5 cum capacity for lead beyond 1 km

0.6000 ton.km

6.00

3.60 36.72

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

37.45

10% Profit ( Add 10% on Subtotal-B) :

41.20

VAT

6% of Total

IT

4% of Total

2.75 1.83 Total:

4.05.02.02

Lead 500m to 1km

cum Operator

0.0057

day

570.00

3.25

Ordinary Labour

0.0114

day

370.00

4.22

H.C. of Tipper -5 cum capacity

0.0057

day

4500.00

25.65

H.C. of Tipper -5 cum capacity for lead beyond 1 km

1.2000 ton.km

6.00

7.20 40.32

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

41.12

10% Profit ( Add 10% on Subtotal-B) :

45.24

VAT

6% of Total

IT

4% of Total

3.02 2.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

45.77

50.26

Page: 309 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.02.03

2 Lead 1km to 2km

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Operator

0.0057

day

570.00

3.25

Ordinary Labour

0.0114

day

370.00

4.22

H.C. of Tipper -5 cum capacity

0.0057

day

4500.00

25.65

H.C. of Tipper -5 cum capacity for lead beyond 1 km

2.4000 ton.km

6.00

14.40 47.52

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

48.47

10% Profit ( Add 10% on Subtotal-B) :

53.31

VAT

6% of Total

IT

4% of Total

3.55 2.37 Total:

4.05.02.04

Lead 2km to 3km

cum Operator

0.0057

day

570.00

3.25

Ordinary Labour

0.0114

day

370.00

4.22

H.C. of Tipper -5 cum capacity

0.0057

day

4500.00

25.65

H.C. of Tipper -5 cum capacity for lead beyond 1 km

3.6000 ton.km

6.00

21.60 54.72

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55.81

10% Profit ( Add 10% on Subtotal-B) :

61.39

VAT

6% of Total

IT

4% of Total

4.09 2.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

59.24

68.21

Page: 310 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.02.05

2 Lead 3km to 4km

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Operator

0.0057

day

570.00

3.25

Ordinary Labour

0.0114

day

370.00

4.22

H.C. of Tipper -5 cum capacity

0.0057

day

4500.00

25.65

H.C. of Tipper -5 cum capacity for lead beyond 1 km

4.8000 ton.km

6.00

28.80 61.92

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

63.16

10% Profit ( Add 10% on Subtotal-B) :

69.47

VAT

6% of Total

IT

4% of Total

4.63 3.09 Total:

4.05.02.06

Lead 4km to 5km

cum Operator

0.0057

day

570.00

3.25

Ordinary Labour

0.0114

day

370.00

4.22

H.C. of Tipper -5 cum capacity

0.0057

day

4500.00

25.65

H.C. of Tipper -5 cum capacity for lead beyond 1 km

6.0000 ton.km

6.00

36.00 69.12

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

70.50

10% Profit ( Add 10% on Subtotal-B) :

77.55

VAT

6% of Total

IT

4% of Total

5.17 3.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

77.19

86.17

Page: 311 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.05.02.07

2 Lead above 5km

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Operator

0.0057

day

570.00

3.25

Ordinary Labour

0.0114

day

370.00

4.22

H.C. of Tipper -5 cum capacity

0.0057

day

4500.00

25.65

H.C. of Tipper -5 cum capacity for lead beyond 1 km

7.2000 ton.km

6.00

43.20 76.32

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

77.84

10% Profit ( Add 10% on Subtotal-B) :

85.63

VAT

6% of Total

IT

4% of Total

5.71 3.81 Total:

4.05.03

P&B: Pumping and bailing out water from the interior of any foundation enclosure of work site with all leads and lifts including supply, operation and maintenance of requisite number of water pumps, arrangements for protection of ringh bund and side slopes of foundation pit against erosion or washout etc. It should be carried out in such a manner as to preclude the possibility of the movement of water through or alongside any concrete being placed, etc. all complete as per direction of E-I-C. No pumping or bailing will be permitted during the placing of concrete.

LS

4.05.04

RB: Making earthen ring/ cross bundh of required height and width to prevent water from entering in the working area for any type of foundation with earth arranged and carried by the contractor including bullah/bamboo palisading and double tarja mat/drum sheets walling as and where necessary, maintaining the same throughout the working period, filling by throwing earth in layers, removal of structure totally on completion of the bridge, etc. all complete as per requirement and instruction of the E-I-C.

LS

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

95.14

Page: 312 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.05.05

AI: Making artificial island in river/channel having standing water suitable for well sinking/ cast-in-situ bored pile with supplying and driving sal-bullah (150mm to 200mm dia) and bamboo posts (75mm to 100mm dia) up to required depth, tarja walling and all other necessary iron fitting, earth arranged and carried by contractor by any means including cost of all materials required for the work and maintaining the same till the completion of the main component of the structure for which the island is made, etc. all complete as per direction of the Engineer-in-Charge. The structures are to be completely removed on completion of the main component of the structure.

4.05.05.01

Beyond 900mm and up to 1500mm of standing water

4.05.05.01.01

For 3000mm x 6000mm wells

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Shal/sundari/gazari Bullah (150mm to 200mm)

140.0000

m

225.00

31500.00

Borak Bamboo (75mm to 100mm)

541.0000

m

42.00

22722.00

56.0000

m2

210.00

11760.00

114.0000

m3

25.00

2850.00

Tarza Royalty of Earth Sardar Ordinary Labour

0.4000

day

800.00

320.00

114.0000

day

370.00

42180.00 111332.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

113558.64

10% Profit ( Add 10% on Subtotal-B) :

124914.50

VAT

6% of Total

8327.63

IT

4% of Total

5551.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

138793.89

Page: 313 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.05.01.02

2 For 3000mm x 7200mm wells

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

Shal/sundari/gazari Bullah (150mm to 200mm)

154.0000

m

225.00

34650.00

Borak Bamboo (75mm to 100mm)

595.0000

m

42.00

24990.00

62.0000

m2

210.00

13020.00

8

each

Tarza Royalty of Earth Sardar Ordinary Labour

125.0000

m3

25.00

3125.00

0.4400

day

800.00

352.00

125.0000

day

370.00

46250.00 122387.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

124834.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

137318.21

VAT

6% of Total

IT

4% of Total

9154.55 6103.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

152575.79

Page: 314 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.05.01.03

2 For 3600mm x 7200mm wells

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

Shal/sundari/gazari Bullah (150mm to 200mm)

156.0000

m

225.00

35100.00

Borak Bamboo (75mm to 100mm)

601.0000

m

42.00

25242.00

63.0000

m2

210.00

13230.00

8

each

Tarza Royalty of Earth Sardar Ordinary Labour

126.0000

m3

25.00

3150.00

0.4500

day

800.00

360.00

126.0000

day

370.00

46620.00 123702.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

126176.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

138793.64

VAT

6% of Total

IT

4% of Total

9252.91 6168.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

154215.16

Page: 315 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.05.01.04

2 For 3000mm x 8100mm wells

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

Shal/sundari/gazari Bullah (150mm to 200mm)

164.0000

m

225.00

36900.00

Borak Bamboo (75mm to 100mm)

631.0000

m

42.00

26502.00

66.0000

m2

210.00

13860.00

8

each

Tarza Royalty of Earth Sardar Ordinary Labour

132.0000

m3

25.00

3300.00

0.4700

day

800.00

376.00

132.0000

day

370.00

48840.00 129778.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132373.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145610.92

VAT

6% of Total

IT

4% of Total

9707.39 6471.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

161789.91

Page: 316 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.05.01.05

2 For 3600mm x 8100mm wells

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

Shal/sundari/gazari Bullah (150mm to 200mm)

167.0000

m

225.00

37575.00

Borak Bamboo (75mm to 100mm)

644.0000

m

42.00

27048.00

67.0000

m2

210.00

14070.00

8

each

Tarza Royalty of Earth Sardar Ordinary Labour

135.0000

m3

25.00

3375.00

0.4800

day

800.00

384.00

135.0000

day

370.00

49950.00 132402.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

135050.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

148555.04

VAT

6% of Total

IT

4% of Total

9903.67 6602.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

165061.16

Page: 317 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.05.01.06

2 For 3300mm x 8400mm wells

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

Shal/sundari/gazari Bullah (150mm to 200mm)

169.0000

m

225.00

38025.00

Borak Bamboo (75mm to 100mm)

650.0000

m

42.00

27300.00

68.0000

m2

210.00

14280.00

8

each

Tarza Royalty of Earth Sardar Ordinary Labour

136.0000

m3

25.00

3400.00

0.4800

day

800.00

384.00

136.0000

day

370.00

50320.00 133709.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

136383.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

150021.50

VAT

6% of Total

IT

4% of Total

10001.43 6667.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

166690.55

Page: 318 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.05.01.07

2 For 3900mm x 7800mm wells

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

Shal/sundari/gazari Bullah (150mm to 200mm)

170.0000

m

225.00

38250.00

Borak Bamboo (75mm to 100mm)

656.0000

m

42.00

27552.00

68.0000

m2

210.00

14280.00

8

each

Tarza Royalty of Earth Sardar Ordinary Labour

137.0000

m3

25.00

3425.00

0.4900

day

800.00

392.00

137.0000

day

370.00

50690.00 134589.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

137280.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

151008.86

VAT

6% of Total

IT

4% of Total

10067.26 6711.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

167787.62

Page: 319 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.05.01.08

2 For 4800mm x 7800mm wells

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

Shal/sundari/gazari Bullah (150mm to 200mm)

172.0000

m

225.00

38700.00

Borak Bamboo (75mm to 100mm)

662.0000

m

42.00

27804.00

69.0000

m2

210.00

14490.00

8

each

Tarza Royalty of Earth Sardar Ordinary Labour

138.0000

m3

25.00

3450.00

0.4900

day

800.00

392.00

138.0000

day

370.00

51060.00 135896.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

138613.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

152475.31

VAT

6% of Total

IT

4% of Total

10165.02 6776.68 Total:

4.05.05.02

Extra for each additional 300mm above 1500mm and upto 3000mm depth of water

4.05.05.02.01

For 3000mm x 6000mm wells

each

Add +8.00% with Item No 4.05.05.01.01

4.05.05.02.02

For 3000mm x 7200mm wells

each

Add +14.00% with Item No 4.05.05.01.02

4.05.05.02.03

For 3600mm x 7200mm wells

each

Add +15.00% with Item No 4.05.05.01.03

4.05.05.02.04

For 3000mm x 8100mm wells

each

Add +15.00% with Item No 4.05.05.01.04

4.05.05.02.05

For 3600mm x 8100mm wells

each

Add +15.00% with Item No 4.05.05.01.05

4.05.05.02.06

For 3300mm x 8400mm wells

each

Add +15.00% with Item No 4.05.05.01.06

4.05.05.02.07

For 3900mm x 7800mm wells

each

Add +15.00% with Item No 4.05.05.01.07

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

169417.01

Page: 320 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.05.05.02.08

For 4800mm x 7800mm wells

4.05.05.03

Extra for each additional 300mm above 3000mm and up to 4500mm depth of water

4.05.05.03.01

Unit

Sub-Item

3

4

each

Add +16.00% with Item No 4.05.05.01.08

For 3000mm x 6000mm wells

each

Add +16.00% with Item No 4.05.05.01.01

4.05.05.03.02

For 3000mm x 7200mm wells

each

Add +17.00% with Item No 4.05.05.01.02

4.05.05.03.03

For 3600mm x 7200mm wells

each

Add +18.00% with Item No 4.05.05.01.03

4.05.05.03.04

For 3000mm x 8100mm wells

each

Add +18.00% with Item No 4.05.05.01.04

4.05.05.03.05

For 3600mm x 8100mm wells

each

Add +19.00% with Item No 4.05.05.01.05

4.05.06

Making temporary artificial island in river/ channel required for cast-insitu bored pile with supplying and driving bamboo posts of 75 to 100mm diameter at specified spacing up to required depth with nails, driving additional gazari/ shalbullah posts of 150 to 175mm diameter at specified spacing up to required depth & half split bullah bracing at top level for longer depth, dram sheet walling & internal cross tie by re-bar with specified diameter & spacing and all other necessary iron fitting, earth arrangement and carried by contractor by any means including cost of all materials required for the work and maintaining the same till the completion of the work for which the island is made. The structures are to be completely removed on completion of the work and the cost is inclusive of this element also.

4.05.06.01

For depth up to 2.0m: Spacing of bamboo posts: 250mm c/c, internal cross ties: 12mm dia re-bar @ 2m c/c

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 321 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.06.01.01

2 Size of Island: 11m x 15m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

Borak Bamboo (75mm to 100mm)

800.0000

m

42.00

33600.00

Bitumen Drum Sheet

117.0000

m2

269.00

31473.00

MS Rod (Plain, 40 Grade)

145.6300

kg

45.00

6553.35

Royalty of Earth

346.5000

m3

25.00

8662.50

1.7500

day

800.00

1400.00

76.0000

day

370.00

28120.00

312.0000

m

42.00

13104.00

10.0000

kg

65.00

650.00

8

each

Sardar Ordinary Labour Borak Bamboo (75mm to 100mm) Nails/ Nut bolts/ Screw/ Spikes

123562.85

Subtotal-A: Lobour charge for removal of island

( +3.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3706.89 127269.74

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

129815.13

10% Profit ( Add 10% on Subtotal-B) :

142796.64

VAT

6% of Total

IT

4% of Total

9519.78 6346.52 Total:

4.05.06.01.02

Size of Island: 11m x 18m

each

Add +12.00% with Item No 4.05.06.01.01

4.05.06.01.03

Size of Island: 11m x 20m

each

Add +21.00% with Item No 4.05.06.01.01

4.05.06.02

For depth above 2.0m: Spacing of bamboo post: close hole, spacing of Gazari/ Shalbullah posts: 1m c/c, internal cross ties: 16mm dia. re-bar at alternate bullah post.

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

158662.94

Page: 322 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.06.02.01

2 Size of Island: 11m x 15m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Borak Bamboo (75mm to 100mm)

2704.0000

m

42.00

113568.00

Shal/sundari/gazari Bullah (150mm to 200mm)

317.2000

m

225.00

71370.00

Bitumen Drum Sheet

195.0000

m2

269.00

52455.00

MS Rod (Plain, 40 Grade)

259.1200

kg

45.00

11660.40

Royalty of Earth

594.0000

m3

25.00

14850.00

5.0000

day

800.00

4000.00

Ordinary Labour

167.0000

day

370.00

61790.00

Borak Bamboo (75mm dia)

884.0000

m

38.00

33592.00

25.0000

kg

65.00

1625.00

Sardar

Nails/ Nut bolts/ Screw/ Spikes

364910.40

Subtotal-A: Labour Charge for removal of Island

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

36491.04 401401.44

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

409429.47

10% Profit ( Add 10% on Subtotal-B) :

450372.42

VAT

6% of Total

IT

4% of Total

30024.83 20016.55 Total:

4.05.06.02.02

Size of Island: 11m x 18m

each

Add +12.00% with Item No 4.05.06.02.01

4.05.06.02.03

Size of Island: 11m x 20m

each

Add +21.00% with Item No 4.05.06.02.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

500413.80

Page: 323 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.05.07

Making arrangement of barge of required size & capacity for construction of cast-in-site bored piles / pre-cast pile at pier locations in river/channel having water depth more than 3.0m. including mobilization and demobilization, setting of piling rigs, fuel, lubricants, other incidental charges etc. all complete as per direction of the engineer. Note: Measurement/ Unit shall be nos. of piers in river with water depth above 3.0m

4.05.07.01

Size: 26.0m x 8.5m, Loaded Draft: 1.8m/1.2m, Carrying capacity: 150 Ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each/ month H.C. of Barge (Size: 26.0m x 8.5m, Loaded Draft: 1.8m/1.2m, Carrying capacity: 150 Ton) including mobilization, demobilization and shifting at site

30.0000

day

6500.00

Mobilization and demobilization etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

195000.00

195000.00

Subtotal-A:

29250.00 224250.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

228735.00

10% Profit ( Add 10% on Subtotal-B) :

251608.50

VAT

6% of Total

16773.90

IT

4% of Total

11182.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

279565.00

Page: 324 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.07.02

Detailed Analysis Brief Description of Item 2 Size: 30.0m x 9.0m, Loaded Draft: 1.8m/1.2m, Carrying capacity: 200 Ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each/ month H.C. of Barge (Size: 30.0m x 9.0m, Loaded Draft: 1.8m/1.2m, Carrying capacity: 200 Ton) including mobilization, demobilization and shifting at site

30.0000

day

9000.00

270000.00

Subtotal-A: Mobilization and demobilization etc.

( +15.00 % on Subtotal-A )

40500.00

Subtotal-A1: Subtotal-B: Subtotal-C:

310500.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

316710.00

10% Profit ( Add 10% on Subtotal-B) :

348381.00

VAT

6% of Total

IT

4% of Total

23225.40 15483.60 Total:

4.05.07.03

Size: 38.0m x 9.0m, Loaded Draft: 2.0m/1.37m, Carrying capacity: 300 Ton

387090.00

each/ month H.C. of Barge (Size: 38.0m x 9.0m, Loaded Draft: 2.0m/1.37m, Carrying capacity: 300 Ton) including mobilization, demobilization and shifting at site

30.0000

day

10500.00

Mobilization and demobilization etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

315000.00

315000.00

Subtotal-A:

47250.00 362250.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

369495.00

10% Profit ( Add 10% on Subtotal-B) :

406444.50

VAT

6% of Total

27096.30

IT

4% of Total

18064.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

270000.00

451605.00

Page: 325 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.07.04

Detailed Analysis Brief Description of Item 2 Size: 36.5m x 12.0m, Loaded Draft: 2.4m/1.8m, Carrying capacity: 400 Ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each/ month H.C. of Barge (Size: 36.5m x 12.0m, Loaded Draft: 2.4m/1.8m, Carrying capacity: 400 Ton) including mobilization, demobilization and shifting at site

30.0000

day

14000.00

420000.00

Subtotal-A: Mobilization and demobilization etc.

( +15.00 % on Subtotal-A )

63000.00

Subtotal-A1: Subtotal-B: Subtotal-C:

483000.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

492660.00

10% Profit ( Add 10% on Subtotal-B) :

541926.00

VAT

6% of Total

IT

4% of Total

36128.40 24085.60 Total:

4.05.07.05

Size: 38.0m x 13.5m, Loaded Draft: 2.4m/1.8m, Carrying capacity: 500 Ton

602140.00

each/ month H.C. of Barge (Size: 38.0m x 13.5m, Loaded Draft: 2.4m/1.8m, Carrying capacity: 500 Ton) including mobilization, demobilization and shifting at site

30.0000

day

16500.00

Mobilization and demobilization etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

495000.00

495000.00

Subtotal-A:

74250.00 569250.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

580635.00

10% Profit ( Add 10% on Subtotal-B) :

638698.50

VAT

6% of Total

42579.90

IT

4% of Total

28386.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

420000.00

709665.00

Page: 326 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.08

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Making arrangement of steel staging for construction of Cast-in-situ pile by driving of double headed EI Rail post up to 4.00 m to 6m with 600/750mm dia C.I Shoe (screw) @ 1.00m c/c in transverse dimension and 4.00m c/c in longitudinal direction povided with double headed C.I cap and RS Joist of required size in both direction . The double headed EI vertical post shall be cross-braced with 3"x3" MS Angle. The RS joist frame shall be covered with MS plate (6mm thick) to make a smooth platform.The work shall be completed including cost of all material, fitting fixing with nut bolt etc,all labour cost and maintaining the same till the completion of the work for which it is made. The structure is to be completely removed on completion of the work and the cost is inclusive of the element also. All work shall be done as per supplied drawing and direction of the Engineer-in- charge. Contractor shall take necessary safety measure for the stage and shall be responsible for any accident. He will prepare the staging design & get it approved by the EI-C. Note: This item shall be selected as per instruction given in the drawing & after getting approval from Design unit, LGED.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 327 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.08.01

Detailed Analysis Brief Description of Item 2 For 5.00m to 9.00m depth of water

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Diesel

2.0500

liter

68.00

139.40

H.C. of Welding Machine

0.0500

day

500.00

25.00

H.C. of Engine Boat

0.0500

day

1000.00

50.00

H.C. of Tripod Stand

0.0500

day

400.00

20.00

H.C. of Chain Pulley (1.5 ton)

0.0500

day

500.00

25.00

H.C. of Vertical Drill Machine

0.0100

day

150.00

1.50

H.C. of Electric Auto Gas Cutter Set

0.0100

day

500.00

5.00

Ordinary Labour

8.6000

day

370.00

3182.00

Skilled Labour

4.8300

day

450.00

2173.50

Foreman

0.0600

day

800.00

48.00

Welder

0.0200

day

680.00

13.60 5683.00

Subtotal-A: H.C for Double Headed EI Rail, RS Joist, MS Double Angle, CI Shoe,CI Cap, Nut bolts, MS Plate, Electrode etc all other elements whice is required

( +63.00 % on Subtotal-A )

Subtotal-A1:

3580.29

9263.29

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9448.56 10393.41

VAT

6% of Total

692.89

IT

4% of Total

461.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11548.23

Page: 328 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.08.02

Detailed Analysis Brief Description of Item 2 For 9.00m to 12.00m depth of water

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Diesel

2.0500

liter

68.00

139.40

H.C. of Welding Machine

0.0500

day

500.00

25.00

H.C. of Engine Boat

0.0500

day

1000.00

50.00

H.C. of Tripod Stand

0.0500

day

400.00

20.00

H.C. of Chain Pulley (1.5 ton)

0.0500

day

500.00

25.00

H.C. of Vertical Drill Machine

0.0100

day

150.00

1.50

H.C. of Electric Auto Gas Cutter Set

0.0100

day

500.00

5.00

Ordinary Labour

9.2200

day

370.00

3411.40

Skilled Labour

5.3400

day

450.00

2403.00

Foreman

0.0600

day

800.00

48.00

Welder

0.0200

day

680.00

13.60 6141.90

Subtotal-A: H.C for Double Headed EI Rail, RS Joist, MS Double Angle, CI Shoe,CI Cap, Nut bolts, MS Plate, Electrode etc all other elements whice is required

( +74.00 % on Subtotal-A )

Subtotal-A1:

4545.01

10686.91

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10900.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11990.71

VAT

6% of Total

799.38

IT

4% of Total

532.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13323.01

Page: 329 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.08.03

Detailed Analysis Brief Description of Item 2 For 12.00m to 15.00m depth of water

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Diesel

2.0500

liter

68.00

139.40

H.C. of Welding Machine

0.0500

day

500.00

25.00

H.C. of Engine Boat

0.0500

day

1000.00

50.00

H.C. of Tripod Stand

0.0500

day

400.00

20.00

H.C. of Chain Pulley (1.5 ton)

0.0500

day

500.00

25.00

H.C. of Vertical Drill Machine

0.0100

day

150.00

1.50

H.C. of Electric Auto Gas Cutter Set

0.0100

day

500.00

5.00

Ordinary Labour

9.8200

day

370.00

3633.40

Skilled Labour

5.4200

day

450.00

2439.00

Foreman

0.0600

day

800.00

48.00

Welder

0.0200

day

680.00

13.60 6399.90

Subtotal-A: H.C for Double Headed EI Rail, RS Joist, MS Double Angle, CI Shoe,CI Cap, Nut bolts, MS Plate, Electrode etc all other elements whice is required

( +77.00 % on Subtotal-A )

Subtotal-A1:

4927.92

11327.82

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11554.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12709.82

VAT

6% of Total

847.32

IT

4% of Total

564.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14122.02

Page: 330 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.08.04

Detailed Analysis Brief Description of Item 2 For 15.00m to 18.00m depth of water

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Diesel

2.0500

liter

68.00

139.40

H.C. of Welding Machine

0.0500

day

500.00

25.00

H.C. of Engine Boat

0.0500

day

1000.00

50.00

H.C. of Tripod Stand

0.0500

day

400.00

20.00

H.C. of Chain Pulley (1.5 ton)

0.0500

day

500.00

25.00

H.C. of Vertical Drill Machine

0.0100

day

150.00

1.50

H.C. of Electric Auto Gas Cutter Set

0.0100

day

500.00

5.00

Ordinary Labour

10.4100

day

370.00

3851.70

Skilled Labour

5.5000

day

450.00

2475.00

Foreman

0.0600

day

800.00

48.00

Welder

0.0200

day

680.00

13.60 6654.20

Subtotal-A: H.C for Double Headed EI Rail, RS Joist, MS Double Angle, CI Shoe,CI Cap, Nut bolts, MS Plate, Electrode etc all other elements whice is required

( +80.00 % on Subtotal-A )

Subtotal-A1:

5323.36

11977.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12217.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13438.82

VAT

6% of Total

895.92

IT

4% of Total

597.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14932.02

Page: 331 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.08.05

Detailed Analysis Brief Description of Item 2 For 18.00m & Above depth of water

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Diesel

2.0500

liter

68.00

139.40

H.C. of Welding Machine

0.0500

day

500.00

25.00

H.C. of Engine Boat

0.0500

day

1000.00

50.00

H.C. of Tripod Stand

0.0500

day

400.00

20.00

H.C. of Chain Pulley (1.5 ton)

0.0500

day

500.00

25.00

H.C. of Vertical Drill Machine

0.0100

day

150.00

1.50

H.C. of Electric Auto Gas Cutter Set

0.0100

day

500.00

5.00

Ordinary Labour

11.0100

day

370.00

4073.70

Skilled Labour

5.5800

day

450.00

2511.00

Foreman

0.0600

day

800.00

48.00

Welder

0.0200

day

680.00

13.60 6912.20

Subtotal-A: H.C for Double Headed EI Rail, RS Joist, MS Double Angle, CI Shoe,CI Cap, Nut bolts, MS Plate, Electrode etc all other elements whice is required

( +83.00 % on Subtotal-A )

Subtotal-A1:

5737.13

12649.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12902.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14192.54

VAT

6% of Total

946.17

IT

4% of Total

630.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15769.49

Page: 332 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.09

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Construction of steel cofferdam with bottom frame with a required number of hole, side frame with necessary nos. of bracings at different level and top platform with provision of adequate access, light and ventilation including cost of MS plate, MS angle, joists, fabrication, welding, grinding, shifting the cofferdam from bank to pier location, lowering of cofferdam to it's design level, bottom plugging of cofferdam by 30MPa Tremie Concrete (underwater concrete) through a tube usually 200 to 250mm pipe, dewater the interior area, breaking head of hardened cast-in-situ bored pile to the cut-off level and exposing pile reinforcement for embedment in pile cap, erection and removal of cofferdam by unifloat (pontoon), monitoring the behavior of the cofferdam and surrounding area, tower crane, generator, gas cutter set etc. all complete in all respect as per direction of Design Unit & concern Engineer-in-Charge. Contractor shall submit the design calculations and methodology which must be compatible with the weather conditions, waves, currents, construction equipment, construction method, internal permanent structures and ground condition. Contractor shall take necessary safety measure for the construction of cofferdam and responsible for all obligations. Note: Measurement will be based on the actual pile cap area. This item shall be selected as per instruction given in the drawing & after getting approval from Design unit, LGED.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 333 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.05.09.01

2 For depth up to 5m from LWL

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm RCC-30SCBP: Reinforced cement concrete work for cast-insitu pile with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required a.............4.07.05

0.3984

cum

MS Plate (3mm)

74.6957

MS Angle, Flat bar, Z bar RS Joist MS Plate (6mm)

10839.17

4318.33

kg

55.00

4108.26

79.0087

kg

59.00

4661.51

36.8348

kg

75.00

2762.61

7.0087

kg

70.00

490.61

H.C. of MS Plate, MS Angle & I-Beam etc.

532.8311

kg

18.00

9590.96

Fabrication cost for MS plate, Angle & I-beam for cofferdam

650.9223

kg

32.00

20829.51

Erection at site, shifting from river bank to pier location including cost of consumable materials (i.e., electrode, LP, Oxygen etc.), welding machine, grinding machine & manpower

628.0474

kg

28.00

17585.33

1.1858

kg

65.00

77.08

448.4585

kg

8.00

3587.67

Nails/ Nut bolts/ Screw/ Spikes Removal of Cofferdam materials after completion of pier shaft above water level H.C. of 150mm dia & 4mm thick MS pipe

11.9526 m/month

65.00

776.92

250.00

1992.10

day

12000.00

284.40

day

1200.00

5502.00

MS pipe driving in river bed and removal

7.9684

m

H. C. of Dredger

0.0237

H.C. of Unifloat/ Pontoon

4.5850

H.C. of Tower Crane

0.4585

day

5000.00

2292.50

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.9170

day

3000.00

2751.00

H.C. of Generator (40 KVA)

0.9170

day

2500.00

2292.50

145.4545

liter

68.00

9890.91

Diesel

93794.19

Subtotal-A: All other Cost including mobilization & Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +3.00 % on Subtotal-A )

2813.83 Page: 334 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

demobilization of equipment Subtotal-A1: Subtotal-B: Subtotal-C:

96608.02 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7226.28 4817.52 Total:

4.05.09.02

For depth 5m to 6m from LWL

sqm

Add +10.00% with Item No 4.05.09.01

4.05.09.03

For depth 6m to 7m from LWL

sqm

Add +20.00% with Item No 4.05.09.01

4.05.09.04

For depth 7m to 8m from LWL

sqm

Add +30.00% with Item No 4.05.09.01

4.05.09.05

For depth 8m to 9m from LWL

sqm

Add +40.00% with Item No 4.05.09.01

4.05.09.06

For depth 9m to 10m from LWL

sqm

Add +50.00% with Item No 4.05.09.01

4.05.09.07

For depth above 10m from LWL

sqm

Add +60.00% with Item No 4.05.09.01

Note : Rates of all items should be inclusive of all supply and carriage.

98540.18 108394.20

120438.00

Page: 335 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.10

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Making arrangement of dewatering system to provide temporary reductions in ground water level for construction of pile caps/ foundation of any other structure which extend to below ground water level including installation of a wellpoint system consists of a closely spaced series of small-diameter shallow wells connected to a common headermain and pumped with a high-efficiency vacuum dewatering pump or installation and operation of series of submersible pumps so as to lower the water table to provide stable and dry conditions to facilitate excavation. For drawdowns in excess of 6m further stages of wellpoints are required, installed at successively lower levels as excavation proceeds. Dewatering system may be used around open cut excavations or in conjunction with shoring or retaining wall used to support the excavation. The choise of pumping system used for dewatering or groundwater systems depends on the amount of drawdown required and the ground conditions. Contractor shall submit the design calculations and methodology which must be compatible with the subsoil & weather condition, construction equipment, construction method, ground water level etc. Contractor shall take necessary safety measure for making arrangement of dewatering system and responsible for all obligations. Note: Measurement will be based on the actual pile cap/ foundation area. This item shall be selected as per instruction given in the drawing & after getting approval from Design unit, LGED.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 336 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.10.01

Detailed Analysis Brief Description of Item 2 Dewatering system for depth up to 3m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Earth filling work in any type of embankment/pond/low lands with suitable dredged soil (sandy clay/silty clay/silt), collected from silt-up river/canal bed by dredging with appropriate local dredger, ………….2.02.4.01

20.6341

cum

149.37

3082.12

H.C. of Generator (40 KVA)

0.0884

day

2500.00

221.00

H.C. of Submersible Pump - 3 HP

0.7070

day

1200.00

848.40

Diesel

7.4231

liter

68.00

504.77

Foreman

0.0442

day

800.00

35.36

Electricians

0.0442

day

600.00

26.52

Asst Electrician

0.0884

day

680.00

60.11

Skilled Labour

0.1767

day

450.00

79.52

Ordinary Labour

0.4419

day

370.00

163.50 5021.30

Subtotal-A: All other Cost including mobilization & demobilization of equipment, regular maintenance of Generator & submersible pumps etc.

( +3.00 % on Subtotal-A )

Subtotal-A1:

150.64

5171.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5275.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5802.91

VAT

6% of Total

386.86

IT

4% of Total

257.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6447.68

Page: 337 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.10.02

Detailed Analysis Brief Description of Item 2 Dewatering system for depth 3m to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Earth filling work in any type of embankment/pond/low lands with suitable dredged soil (sandy clay/silty clay/silt), collected from silt-up river/canal bed by dredging with appropriate local dredger, ………….2.02.4.01

70.5779

cum

149.37

10542.22

H.C. of Generator (100 KVA)

0.1237

day

3500.00

432.95

H.C. of Submersible Pump - 3 HP

1.8558

day

1200.00

2226.96

23.9024

liter

68.00

1625.36

Foreman

0.0619

day

800.00

49.52

Electricians

0.0619

day

600.00

37.14

Asst Electrician

0.1237

day

680.00

84.12

Skilled Labour

0.2474

day

450.00

111.33

Ordinary Labour

0.6186

day

370.00

228.88

Diesel

15338.48

Subtotal-A: All other Cost including mobilization & demobilization of equipment, regular maintenance of Generator & submersible pumps etc.

( +3.00 % on Subtotal-A )

Subtotal-A1:

460.15

15798.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16114.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17726.07

VAT

6% of Total

1181.74

IT

4% of Total

787.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19695.63

Page: 338 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.05.10.03

Detailed Analysis Brief Description of Item 2 Dewatering system for depth 6m to 9m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

179.1868

cum

149.37

26765.13

H.C. of Generator (150 KVA)

0.1767

day

5000.00

883.50

H.C. of Submersible Pump - 3 HP

5.3022

day

1200.00

6362.64

51.1135

liter

68.00

3475.72

Foreman

0.0884

day

800.00

70.72

Electricians

0.0884

day

600.00

53.04

Asst Electrician

0.1767

day

680.00

120.16

Skilled Labour

0.3535

day

450.00

159.08

Ordinary Labour

0.8837

day

370.00

326.97

Diesel

38216.95

Subtotal-A: All other Cost including mobilization & demobilization of equipment, regular maintenance of Generator & submersible pumps etc.

( +3.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

sqm

1146.51

39363.46

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40150.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

44165.80

VAT

6% of Total

2944.39

IT

4% of Total

1962.92 Total:

Dewatering system for depth above 9m

8

sqm Earth filling work in any type of embankment/pond/low lands with suitable dredged soil (sandy clay/silty clay/silt), collected from silt-up river/canal bed by dredging with appropriate local dredger, ………….2.02.4.01

4.05.10.04

Amount

49073.11

Add +25.00% with Item No 4.05.10.03

Page: 339 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.06.01

Sand filling on the prepared foundation bed with sand of specified FM in layers not more than 150mm thick including necessary carriage, leveling, watering and ramming to achieve minimum dry density (MDD) of 95% STD compaction with optimum moisture content (OMC) by ramming each layer up to finished level as per direction of E-I-C.

4.06.01.01

Sand of Minimum FM 0.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Sand (FM - 0.8)

1.2000

m3

480.00

576.00

Ordinary Labour

0.3000

day

370.00

111.00 687.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

700.74

10% Profit ( Add 10% on Subtotal-B) :

770.81

VAT

6% of Total

IT

4% of Total

51.39 34.26 Total:

4.06.01.02

Sand of Minimum FM 1.2

cum Sand (FM - 1.2)

1.2000

m3

584.00

700.80

Ordinary Labour

0.3000

day

370.00

111.00 811.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

828.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

910.84

VAT

6% of Total

60.72

IT

4% of Total

40.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

856.46

1012.04

Page: 340 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.06.01.03

2 Sand of Minimum FM 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Sand (FM - 1.8)

1.2000

m3

970.00

1164.00

Ordinary Labour

0.3000

day

370.00

111.00 1275.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1300.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1430.55

VAT

6% of Total

95.37

IT

4% of Total

63.58 Total:

4.06.01.04

Sand of Minimum FM 2.5

cum Sand (FM - 2.5)

1.2000

m3

1500.00

1800.00

Ordinary Labour

0.3000

day

370.00

111.00 1911.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1949.22

10% Profit ( Add 10% on Subtotal-B) :

2144.14

VAT

6% of Total

IT

4% of Total

142.94 95.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1589.50

2382.38

Page: 341 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.06.02

Detailed Analysis Brief Description of Item 2 Single layer brick flat soling with 1st class or picked kiln burnt bricks in foundation, filling the interstices tightly with sand of minimum FM 0.50, watering, leveling, dressing, etc. all complete as per instruction of the EI-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick

31.0000

each

9.00

279.00

Sand (FM - 0.5)

0.0120

m3

420.00

5.04

Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.1000

day

370.00

37.00 334.79

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

341.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

375.63

VAT

6% of Total

25.04

IT

4% of Total

16.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

417.37

Page: 342 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.06.03

Detailed Analysis Brief Description of Item 2 PCC-10: Plain cement concrete work in foundation with minimum compressive strength of 10 MPa at 28 days (sugessted mix proportion 1:3:6) on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/AL/M/V/W 42.5N, sand of minimum FM 1.8 and 20mm down well graded 1st class/ picked brick chips (LAA value not exceeding 40) comforming to ASTM C 33 including breaking bricks into chips, shuttering, mixing by concrete mixer machine, casting, laying compacting and curing for the requisite period etc. all complete as per direction of the E-I-C. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

4.2400

bag

430.00

1823.20

1st Class Brick Chips (20mm down graded)

0.9000

m3

2940.00

2646.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 6288.20

Subtotal-A: Loading & Unloading and other costs

( +.50 % on Subtotal-A )

Subtotal-A1:

31.44 6319.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6446.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7090.64

VAT

6% of Total

IT

4% of Total

472.71 315.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7878.49

Page: 343 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.06.04

Detailed Analysis Brief Description of Item 2 PCC-17: Plain cement concrete work in foundation with minimum compressive strength of 17 MPa at 28 days (sugessted mix proportion 1:2:4 & maximum w/c ratio 0.45) on standard cylinder as per standard practice of Code AASHTO/ ASTM/ and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 20mm down well graded 1st class/ picked brick chips (LAA value not exceeding 40) comforming to ASTM C 33 including breaking bricks into chips, shuttering, mixing by concrete mixer machine, casting, laying compacting and curing for the requisite period etc. all complete as per direction of the E-I-C. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Brick Chips (20mm down graded)

0.8600

m3

2940.00

2528.40

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 6929.50

Subtotal-A: Loading & Unloading and other costs

( +.50 % on Subtotal-A )

Subtotal-A1:

34.65 6964.15

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7103.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7813.77

VAT

6% of Total

IT

4% of Total

520.92 347.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8681.97

Page: 344 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.06.05

Brick work with 1st class brick in specified cement mortar in foundation with sand of minimum FM 1.20 and cement conforming to BDS EN 1971 : 2003 CEM-II/A-L/M/V/W 42.5N, filling the interstices tightly with mortar, raking out joints, cleaning and soaking bricks at least for 24 hours before use, washing of sand, curing at least for 7 days etc. all complete as per design, specification & direction of the E-I-C.

4.06.05.01

Cement mortar (1:3)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 1st Class Brick Sand (FM - 1.2)

2.8600

bag

430.00

1229.80

406.0000

each

9.00

3654.00

584.00

210.24

0.3600

m3

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 6203.04

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6327.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6959.81

VAT

6% of Total

IT

4% of Total

463.99 309.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7733.12

Page: 345 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.06.05.02

2 Cement mortar (1:4)

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

2.1200

bag

430.00

911.60

406.0000

each

9.00

3654.00

584.00

175.20

5

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 1st Class Brick Sand (FM - 1.2)

0.3000

m3

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 5849.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5966.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6563.48

VAT

6% of Total

IT

4% of Total

437.57 291.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7292.75

Page: 346 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.06.05.03

2 Cement mortar (1:6)

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

1.4000

bag

430.00

602.00

406.0000

each

9.00

3654.00

584.00

164.98

5

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) 1st Class Brick Sand (FM - 1.2)

0.2825

m3

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 5529.98

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5640.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6204.64

VAT

6% of Total

IT

4% of Total

413.64 275.76 Total:

4.06.06

Amount

6894.04

Minimum 6mm thick cement plaster including neat cement finishing over concrete faces with sand of minimum FM 1.20 and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N including washing of sand, cleaning junctiongs of concrete, grouting, dabbing, doing independent double-legged scaffolding, finishing the edges and corners, cleaning of surfaces and curing for requisite period etc. all complete at all leads & lifts as per drawings, specification & direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 347 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.06.06.01

2 Cement mortar (1:3)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0795

bag

430.00

34.19

Sand (FM - 1.2)

0.0068

m3

584.00

3.97

Head Mason

0.0250

day

650.00

16.25

Mason

0.1000

day

550.00

55.00

Ordinary Labour

0.1500

day

370.00

55.50 164.91

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

16.49 181.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185.02

10% Profit ( Add 10% on Subtotal-B) :

203.53

VAT

6% of Total

13.57

IT

4% of Total

9.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

226.14

Page: 348 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.06.06.02

2 Cement mortar (1:4)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0636

bag

430.00

27.35

Sand (FM - 1.2)

0.0054

m3

584.00

3.15

Head Mason

0.0250

day

650.00

16.25

Mason

0.1000

day

550.00

55.00

Ordinary Labour

0.1500

day

370.00

55.50 157.25

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

15.73 172.98

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

176.44

10% Profit ( Add 10% on Subtotal-B) :

194.08

VAT

6% of Total

12.94

IT

4% of Total

8.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

215.64

Page: 349 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.07.01

BCIS: Boring for cast-in-situ piles up to the required depth and specified diameter with driving temporary steel casing (shall be 8mm thick with necessary stiffener bands and sharp edge at bottom and provided up to non-collapsible strata from the existing ground level but not less then 4.0 m) in all types of soils including min. 2-chamber slurry tank, drilling with bentonite circulation (Dry Bentonite powder of liquid limit of minimum 350 shall be mixed with water @ minimum 4% by weight to make the fresh drilling fluid of viscosity between 32-50 seconds and density less than 1.1gm/cc), maintaining fluid level inside casing at all time at least 2 m higher than outside the casings, washing bore hole by air lift cleanup method with fresh bentonite slurry until the slurry from bore hole bottom have density less than 1.15gm/cc and sand content is less than 4%, make the bore hole ready for concreting including disposal/removal of all bored material, hire charge of mechanical winch machine/ skid mounted mechanical table drive rotary/ hydraulic rotary boring equipment, derrick, trimie pipe, cost of fuel, lubricant, mobilization, demobilization, spares, insurance coverage, water, electricity and other charges all complete as per design, drawing, specification and direction of E-I-C. Contractor shall submit the methodology of cast-in-situ pile work including information on boring equipment, sequence of boring & casting, quality control, disposal of spoils, test result of materials to the E-I-C for approval before commencing any boring operation. Boring and excavation for a pile shall not commence until 24 hours after completion of any pile within radius of 6 meters c/c. Cost of collecting, conveying, loading, transportation of spoils/mud accumulated during boring of cast-in-situ pile with all lifts and lead is included in this unit rate. The spoils must be dumped in an unobjectionable place outside the site premises with minimum traffic disruption and the procuring entity will not be responsible for any irregularities by the party regarding dumping of the spoils. Note: Boring method shall be selected as per instruction given in the drawing.

4.07.01.01

BCIS_PM: Boring by PERCUSSION METHOD using Direct Mud Circulation (DMC) or Bailer and Chisel technique by tripod and mechanical winch machine. Tubewell boring machine shall not be used.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 350 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.01.01

2 450mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

7.0000

kg

36.00

252.00

Foreman

0.0500

day

800.00

40.00

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

0.3000

day

370.00

111.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0500

day

3000.00

150.00

H.C. of Derrick

0.0500

day

400.00

20.00

H.C. of Water Pump

0.0500

day

500.00

25.00

H.C. of Tremie Pipe

0.0500

day

500.00

25.00

H.C. of Bailer

0.0500

day

300.00

15.00

H.C. of Cutter

0.0500

day

200.00

10.00

H.C. of Water Sealing Device

0.0500

day

200.00

10.00

H.C. of Welding Machine

0.0200

day

500.00

10.00

Diesel

3.0000

liter

68.00

204.00

Lubricant

0.0300

liter

220.00

6.60

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0083

Day

3000.00

24.90 971.00

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

97.10 1068.10

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1089.46

10% Profit ( Add 10% on Subtotal-B) :

1198.41

VAT

6% of Total

79.89

IT

4% of Total

53.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1331.56

Page: 351 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.01.02

2 500mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

8.7500

kg

36.00

315.00

Foreman

0.0625

day

800.00

50.00

Skilled Labour

0.1875

day

450.00

84.38

Ordinary Labour

0.5000

day

370.00

185.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0600

day

3000.00

180.00

H.C. of Derrick

0.0600

day

400.00

24.00

H.C. of Water Pump

0.0600

day

500.00

30.00

H.C. of Tremie Pipe

0.0600

day

500.00

30.00

H.C. of Bailer

0.0600

day

300.00

18.00

H.C. of Cutter

0.0600

day

200.00

12.00

H.C. of Water Sealing Device

0.0600

day

200.00

12.00

H.C. of Welding Machine

0.0300

day

500.00

15.00

Diesel

3.0000

liter

68.00

204.00

Lubricant

0.0300

liter

220.00

6.60

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0083

Day

3000.00

24.90 1190.88

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

119.09 1309.96

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1336.16

10% Profit ( Add 10% on Subtotal-B) :

1469.78

VAT

6% of Total

97.99

IT

4% of Total

65.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1633.09

Page: 352 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.01.03

2 600mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

12.5000

kg

36.00

450.00

Foreman

0.0750

day

800.00

60.00

Skilled Labour

0.2250

day

450.00

101.25

Ordinary Labour

0.5000

day

370.00

185.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0750

day

3000.00

225.00

H.C. of Derrick

0.0750

day

400.00

30.00

H.C. of Water Pump

0.0750

day

500.00

37.50

H.C. of Tremie Pipe

0.0750

day

500.00

37.50

H.C. of Bailer

0.0750

day

300.00

22.50

H.C. of Cutter

0.0750

day

200.00

15.00

H.C. of Water Sealing Device

0.0750

day

200.00

15.00

H.C. of Welding Machine

0.0400

day

500.00

20.00

Diesel

3.0000

liter

68.00

204.00

Lubricant

0.0300

liter

220.00

6.60

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0083

Day

3000.00

24.90 1434.25

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

143.43 1577.68

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1609.23

10% Profit ( Add 10% on Subtotal-B) :

1770.15

VAT

6% of Total

118.01

IT

4% of Total

78.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1966.83

Page: 353 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.01.04

2 700mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

17.0000

kg

36.00

612.00

Foreman

0.0875

day

800.00

70.00

Skilled Labour

0.2500

day

450.00

112.50

Ordinary Labour

0.5000

day

370.00

185.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0875

day

3000.00

262.50

H.C. of Derrick

0.0875

day

400.00

35.00

H.C. of Water Pump

0.0875

day

500.00

43.75

H.C. of Tremie Pipe

0.0875

day

500.00

43.75

H.C. of Bailer

0.0875

day

300.00

26.25

H.C. of Cutter

0.0875

day

200.00

17.50

H.C. of Water Sealing Device

0.0875

day

200.00

17.50

H.C. of Welding Machine

0.0500

day

500.00

25.00

Diesel

3.0000

liter

68.00

204.00

Lubricant

0.0300

liter

220.00

6.60

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0083

Day

3000.00

24.90 1686.25

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

168.63 1854.88

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1891.97

10% Profit ( Add 10% on Subtotal-B) :

2081.17

VAT

6% of Total

138.74

IT

4% of Total

92.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2312.41

Page: 354 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.01.05

2 800mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

22.0000

kg

36.00

792.00

Foreman

0.0900

day

800.00

72.00

Skilled Labour

0.2500

day

450.00

112.50

Ordinary Labour

0.5000

day

370.00

185.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0900

day

3000.00

270.00

H.C. of Derrick

0.0900

day

400.00

36.00

H.C. of Water Pump

0.0900

day

500.00

45.00

H.C. of Tremie Pipe

0.0900

day

500.00

45.00

H.C. of Bailer

0.0900

day

300.00

27.00

H.C. of Cutter

0.0900

day

200.00

18.00

H.C. of Water Sealing Device

0.0900

day

200.00

18.00

H.C. of Welding Machine

0.0600

day

500.00

30.00

Diesel

3.0000

liter

68.00

204.00

Lubricant

0.0300

liter

220.00

6.60

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0083

Day

3000.00

24.90 1886.00

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

188.60 2074.60

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2116.09

10% Profit ( Add 10% on Subtotal-B) :

2327.70

VAT

6% of Total

155.18

IT

4% of Total

103.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2586.33

Page: 355 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.01.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

BCIS_SMMTD: Boring by Skid Mounted Mechanical Table Drive Rotary Boring/ Spindle Type Rotary Drilling Machine. Tube well boring machine/ Bailer and chisel technique by tripod and mechanical winch machine shall not be used.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 356 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.02.01

2 800mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

22.0000

kg

36.00

792.00

Foreman

0.0093

day

800.00

7.44

Skilled Labour

0.0667

day

450.00

30.02

Ordinary Labour

0.2333

day

370.00

86.32

Hire and running charges of Skid Mounted Mechanical Table Drive Rotary Boring/ Spindle Type Rotary Drilling Machine with power unit including boring attachment and other accessories and shifting at site

0.0467

Day

20000.00

934.00

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0083

Day

3000.00

24.90

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0040

day

4500.00

18.00

Hire and running charges of bentonite pump

0.0500

day

3200.00

160.00

H.C. of Backhoe End Loader (6 tons)

0.0200

day

6000.00

120.00

H.C. of Tipper -5 cum capacity

0.0200

day

4500.00

90.00

H.C. of Tremie Pipe

0.0200

day

500.00

10.00 2272.68

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

227.27 2499.94

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2549.94

10% Profit ( Add 10% on Subtotal-B) :

2804.94

VAT

6% of Total

IT

4% of Total

187.00 124.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3116.60

Page: 357 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.02.02

2 900mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

27.2000

kg

36.00

979.20

Foreman

0.0120

day

800.00

9.60

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.3000

day

370.00

111.00

Hire and running charges of Skid Mounted Mechanical Table Drive Rotary Boring/ Spindle Type Rotary Drilling Machine with power unit including boring attachment and other accessories and shifting at site

0.0556

Day

20000.00

1112.00

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0100

Day

3000.00

30.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0048

day

4500.00

21.60

Hire and running charges of bentonite pump

0.0600

day

3200.00

192.00

H.C. of Backhoe End Loader (6 tons)

0.0280

day

6000.00

168.00

H.C. of Tipper -5 cum capacity

0.0280

day

4500.00

126.00

H.C. of Tremie Pipe

0.0280

day

500.00

14.00 2803.90

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

280.39 3084.29

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3145.98

10% Profit ( Add 10% on Subtotal-B) :

3460.57

VAT

6% of Total

IT

4% of Total

230.70 153.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3845.08

Page: 358 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.01.02.03

2 1000mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

35.0000

kg

36.00

1260.00

Foreman

0.0160

day

800.00

12.80

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.4000

day

370.00

148.00

Hire and running charges of Skid Mounted Mechanical Table Drive Rotary Boring/ Spindle Type Rotary Drilling Machine with power unit including boring attachment and other accessories and shifting at site

0.0690

Day

20000.00

1380.00

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0125

Day

3000.00

37.50

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0060

day

4500.00

27.00

Hire and running charges of bentonite pump

0.0750

day

3200.00

240.00

H.C. of Backhoe End Loader (6 tons)

0.0400

day

6000.00

240.00

H.C. of Tipper -5 cum capacity

0.0400

day

4500.00

180.00

H.C. of Tremie Pipe

0.0400

day

500.00

20.00 3601.55

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

360.16 3961.71

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4040.94

10% Profit ( Add 10% on Subtotal-B) :

4445.03

VAT

6% of Total

IT

4% of Total

296.34 197.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4938.93

Page: 359 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.01.02.04

2 1200mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

42.7778

kg

36.00

1540.00

Foreman

0.0200

day

800.00

16.00

Skilled Labour

0.1667

day

450.00

75.02

Ordinary Labour

0.5000

day

370.00

185.00

Hire and running charges of Skid Mounted Mechanical Table Drive Rotary Boring/ Spindle Type Rotary Drilling Machine with power unit including boring attachment and other accessories and shifting at site

0.0744

Day

20000.00

1488.00

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0139

Day

3000.00

41.70

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0067

day

4500.00

30.15

Hire and running charges of bentonite pump

0.0833

day

3200.00

266.56

H.C. of Backhoe End Loader (6 tons)

0.0556

day

6000.00

333.60

H.C. of Tipper -5 cum capacity

0.0556

day

4500.00

250.20

H.C. of Tremie Pipe

0.0556

day

500.00

27.80 4254.03

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

425.40 4679.43

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4773.02

10% Profit ( Add 10% on Subtotal-B) :

5250.32

VAT

6% of Total

IT

4% of Total

350.02 233.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5833.69

Page: 360 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.01.03

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

BCIS_HRM: Boring by HYDRAULIC ROTARY METHOD using Crawler mounted, telescopic boom hydraulic piling rig. Tube well boring machine/ Bailer and chisel technique by tripod and mechanical winch machine/ Skid Mounted Mechanical Table Drive Rotary Boring/ Spindle Type Rotary Drilling Machine shall not be used.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 361 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.03.01

2 800mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

22.0000

kg

36.00

792.00

Foreman

0.0093

day

800.00

7.44

Skilled Labour

0.0667

day

450.00

30.02

Ordinary Labour

0.2333

day

370.00

86.32

Hire and running charges of hydraulic rotary drilling equipment with power unit including 0.8m to 2.5m dia boring attachment and other accessories and shifting at site

0.0467

day

37000.00

1727.90

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0083

Day

3000.00

24.90

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0040

day

4500.00

18.00

Hire and running charges of bentonite pump

0.0500

day

3200.00

160.00

H.C. of Backhoe End Loader (6 tons)

0.0200

day

6000.00

120.00

H.C. of Tipper -5 cum capacity

0.0200

day

4500.00

90.00

H.C. of Tremie Pipe

0.0200

day

500.00

10.00 3066.58

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1:

306.66 3373.23

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3440.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3784.77

VAT

6% of Total

252.32

IT

4% of Total

168.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4205.30

Page: 362 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.01.03.02

2 900mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

27.2000

kg

36.00

979.20

Foreman

0.0120

day

800.00

9.60

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.3000

day

370.00

111.00

Hire and running charges of hydraulic rotary drilling equipment with power unit including 0.8m to 2.5m dia boring attachment and other accessories and shifting at site

0.0556

day

37000.00

2057.20

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0100

Day

3000.00

30.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0048

day

4500.00

21.60

Hire and running charges of bentonite pump

0.0600

day

3200.00

192.00

H.C. of Backhoe End Loader (6 tons)

0.0280

day

6000.00

168.00

H.C. of Tipper -5 cum capacity

0.0280

day

4500.00

126.00

H.C. of Tremie Pipe

0.0280

day

500.00

14.00 3749.10

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1:

374.91 4124.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4206.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4627.14

VAT

6% of Total

308.48

IT

4% of Total

205.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5141.27

Page: 363 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.01.03.03

2 1000mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

35.0000

kg

36.00

1260.00

Foreman

0.0160

day

800.00

12.80

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.4000

day

370.00

148.00

Hire and running charges of hydraulic rotary drilling equipment with power unit including 0.8m to 2.5m dia boring attachment and other accessories and shifting at site

0.0690

day

37000.00

2553.00

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0125

Day

3000.00

37.50

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0060

day

4500.00

27.00

Hire and running charges of bentonite pump

0.0750

day

3200.00

240.00

H.C. of Backhoe End Loader (6 tons)

0.0400

day

6000.00

240.00

H.C. of Tipper -5 cum capacity

0.0400

day

4500.00

180.00

H.C. of Tremie Pipe

0.0400

day

500.00

20.00 4774.55

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1:

477.46 5252.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5357.05

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5892.75

VAT

6% of Total

392.85

IT

4% of Total

261.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6547.50

Page: 364 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.01.03.04

2 1200mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

42.7778

kg

36.00

1540.00

Foreman

0.0200

day

800.00

16.00

Skilled Labour

0.1667

day

450.00

75.02

Ordinary Labour

0.5000

day

370.00

185.00

Hire and running charges of hydraulic rotary drilling equipment with power unit including 0.8m to 2.5m dia boring attachment and other accessories and shifting at site

0.0744

day

37000.00

2752.80

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0139

Day

3000.00

41.70

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0067

day

4500.00

30.15

Hire and running charges of bentonite pump

0.0833

day

3200.00

266.56

H.C. of Backhoe End Loader (6 tons)

0.0556

day

6000.00

333.60

H.C. of Tipper -5 cum capacity

0.0556

day

4500.00

250.20

H.C. of Tremie Pipe

0.0556

day

500.00

27.80 5518.83

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1:

551.88 6070.71

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6192.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6811.33

VAT

6% of Total

454.09

IT

4% of Total

302.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7568.15

Page: 365 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.01.03.05

2 1500mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

50.0000

kg

36.00

1800.00

Foreman

0.0278

day

800.00

22.24

Skilled Labour

0.2222

day

450.00

99.99

Ordinary Labour

0.5556

day

370.00

205.57

Hire and running charges of hydraulic rotary drilling equipment with power unit including 0.8m to 2.5m dia boring attachment and other accessories and shifting at site

0.0856

day

37000.00

3167.20

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0139

Day

3000.00

41.70

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0111

day

4500.00

49.95

Hire and running charges of bentonite pump

0.1067

day

3200.00

341.44

H.C. of Backhoe End Loader (6 tons)

0.0833

day

6000.00

499.80

H.C. of Tipper -5 cum capacity

0.0833

day

4500.00

374.85

H.C. of Tremie Pipe

0.0833

day

500.00

41.65 6644.39

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1:

664.44 7308.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7455.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8200.51

VAT

6% of Total

546.70

IT

4% of Total

364.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9111.68

Page: 366 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.01.03.06

2 1800mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

63.3333

kg

36.00

2280.00

Foreman

0.0311

day

800.00

24.88

Skilled Labour

0.2778

day

450.00

125.01

Ordinary Labour

0.6667

day

370.00

246.68

Hire and running charges of hydraulic rotary drilling equipment with power unit including 0.8m to 2.5m dia boring attachment and other accessories and shifting at site

0.0967

day

37000.00

3577.90

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0139

Day

3000.00

41.70

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0111

day

4500.00

49.95

Hire and running charges of bentonite pump

0.1111

day

3200.00

355.52

H.C. of Backhoe End Loader (6 tons)

0.1111

day

6000.00

666.60

H.C. of Tipper -5 cum capacity

0.1111

day

4500.00

499.95

H.C. of Tremie Pipe

0.1111

day

500.00

55.55 7923.74

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1:

792.37 8716.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8890.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9779.48

VAT

6% of Total

651.97

IT

4% of Total

434.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10866.09

Page: 367 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.01.03.07

2 2000mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

72.2222

kg

36.00

2600.00

Foreman

0.0333

day

800.00

26.64

Skilled Labour

0.3333

day

450.00

149.99

Ordinary Labour

0.7778

day

370.00

287.79

Hire and running charges of hydraulic rotary drilling equipment with power unit including 0.8m to 2.5m dia boring attachment and other accessories and shifting at site

0.1044

day

37000.00

3862.80

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0139

Day

3000.00

41.70

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0111

day

4500.00

49.95

Hire and running charges of bentonite pump

0.1111

day

3200.00

355.52

H.C. of Backhoe End Loader (6 tons)

0.1222

day

6000.00

733.20

H.C. of Tipper -5 cum capacity

0.1222

day

4500.00

549.90

H.C. of Tremie Pipe

0.1222

day

500.00

61.10 8718.58

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

871.86 9590.44

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9782.25 10760.47

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

717.36

IT

4% of Total

478.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11956.08

Page: 368 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.01.03.08

2 2500mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Bentonite

94.4444

kg

36.00

3400.00

Foreman

0.0389

day

800.00

31.12

Skilled Labour

0.3889

day

450.00

175.01

Ordinary Labour

0.8889

day

370.00

328.89

Hire and running charges of hydraulic rotary drilling equipment with power unit including 0.8m to 2.5m dia boring attachment and other accessories and shifting at site

0.1111

day

37000.00

4110.70

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0139

Day

3000.00

41.70

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0111

day

4500.00

49.95

Hire and running charges of bentonite pump

0.1111

day

3200.00

355.52

H.C. of Backhoe End Loader (6 tons)

0.1333

day

6000.00

799.80

H.C. of Tipper -5 cum capacity

0.1333

day

4500.00

599.85

H.C. of Tremie Pipe

0.1333

day

500.00

66.65 9959.19

Subtotal-A: Bentonite mixing & circulation from slurry Tank

( +10.00 % on Subtotal-A )

Subtotal-A1:

995.92 10955.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11174.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12291.63

VAT

6% of Total

819.44

IT

4% of Total

546.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13657.36

Page: 369 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.07.02

DCIS: Driven Cast-in-Situ vertical R.C.C. pile of specified diameter and length (length to be measured from the bottom of pile cap to the bottom of shoe), to carry safe working load not less than specified, including cost shoe & all other materials and labour for casting, hoisting, driving etc. and also including cost of dummy lengths of pile and of hire charges of all instruments as necessary but excluding concrete & reinforcement etc. all complete as per drawing, specification and direction of Engineer-in-Charge.

4.07.02.01

Pile diameter - 450 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

4.0000

kg

70.00

280.00

M.S. Clamps for Shoe

1.7500

kg

85.00

148.75

Steel Helmet and Cushion block on top of casing head during driving

2.5000

kg

65.00

162.50

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0240

day

40000.00

960.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0030

day

4500.00

13.50

Operator

0.0040

day

570.00

2.28

Skilled Labour

0.1000

day

450.00

45.00 1612.03

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1644.27

10% Profit ( Add 10% on Subtotal-B) :

1808.70

VAT

6% of Total

IT

4% of Total

120.58 80.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2009.66

Page: 370 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.02.02

2 Pile diameter - 500 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

4.0000

kg

70.00

280.00

M.S. Clamps for Shoe

1.7500

kg

85.00

148.75

Steel Helmet and Cushion block on top of casing head during driving

2.5000

kg

65.00

162.50

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0270

day

40000.00

1080.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0030

day

4500.00

13.50

Operator

0.0040

day

570.00

2.28

Skilled Labour

0.1000

day

450.00

45.00 1732.03

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1766.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1943.34

VAT

6% of Total

IT

4% of Total

129.56 86.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2159.26

Page: 371 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.02.03

2 Pile diameter - 600 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

4.0000

kg

70.00

280.00

M.S. Clamps for Shoe

1.7500

kg

85.00

148.75

Steel Helmet and Cushion block on top of casing head during driving

2.5000

kg

65.00

162.50

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0300

day

40000.00

1200.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0030

day

4500.00

13.50

Operator

0.0040

day

570.00

2.28

Skilled Labour

0.1000

day

450.00

45.00 1852.03

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1889.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2077.98

VAT

6% of Total

IT

4% of Total

138.53 92.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2308.86

Page: 372 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.02.04

2 Pile diameter - 700 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

5.3330

kg

70.00

373.31

M.S. Clamps for Shoe

2.3330

kg

85.00

198.31

Steel Helmet and Cushion block on top of casing head during driving

3.3330

kg

65.00

216.65

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0470

day

40000.00

1880.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0040

day

4500.00

18.00

Operator

0.0090

day

570.00

5.13

Skilled Labour

0.2330

day

450.00

104.85 2796.24

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2852.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3137.38

VAT

6% of Total

IT

4% of Total

209.16 139.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3485.98

Page: 373 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.02.05

2 Pile diameter - 800 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

6.4000

kg

70.00

448.00

M.S. Clamps for Shoe

2.8000

kg

85.00

238.00

Steel Helmet and Cushion block on top of casing head during driving

4.0000

kg

65.00

260.00

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0520

day

40000.00

2080.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0060

day

4500.00

27.00

Operator

0.0130

day

570.00

7.41

Skilled Labour

0.3000

day

450.00

135.00 3195.41

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3259.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3585.25

VAT

6% of Total

IT

4% of Total

239.02 159.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3983.61

Page: 374 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.02.06

2 Pile diameter - 900 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

6.4000

kg

70.00

448.00

M.S. Clamps for Shoe

2.8000

kg

85.00

238.00

Steel Helmet and Cushion block on top of casing head during driving

4.0000

kg

65.00

260.00

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0580

day

40000.00

2320.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0060

day

4500.00

27.00

Operator

0.0140

day

570.00

7.98

Skilled Labour

0.3200

day

450.00

144.00 3444.98

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3513.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3865.27

VAT

6% of Total

IT

4% of Total

257.68 171.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4294.74

Page: 375 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.02.07

2 Pile diameter - 1000 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

8.0000

kg

70.00

560.00

M.S. Clamps for Shoe

3.5000

kg

85.00

297.50

Steel Helmet and Cushion block on top of casing head during driving

5.0000

kg

65.00

325.00

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0680

day

40000.00

2720.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0060

day

4500.00

27.00

Operator

0.0160

day

570.00

9.12

Skilled Labour

0.4000

day

450.00

180.00 4118.62

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4200.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4621.09

VAT

6% of Total

IT

4% of Total

308.07 205.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5134.55

Page: 376 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.02.08

2 Pile diameter - 1200 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

8.8890

kg

70.00

622.23

M.S. Clamps for Shoe

3.8890

kg

85.00

330.57

Steel Helmet and Cushion block on top of casing head during driving

5.5560

kg

65.00

361.14

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0740

day

40000.00

2960.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0070

day

4500.00

31.50

Operator

0.0200

day

570.00

11.40

Skilled Labour

0.5000

day

450.00

225.00 4541.84

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4632.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5095.94

VAT

6% of Total

IT

4% of Total

339.73 226.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5662.15

Page: 377 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.02.09

2 Pile diameter - 1500 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m C.I. Shoes for the pile

8.8890

kg

70.00

622.23

M.S. Clamps for Shoe

3.8890

kg

85.00

330.57

Steel Helmet and Cushion block on top of casing head during driving

5.5560

kg

65.00

361.14

Hire and running charges of hydraulic piling rig Including double acting pile driving hammer complete with power unit, accessories and shifting at site

0.0860

day

40000.00

3440.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0110

day

4500.00

49.50

Operator

0.0220

day

570.00

12.54

Skilled Labour

0.5560

day

450.00

250.20 5066.18

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5167.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5684.25

VAT

6% of Total

IT

4% of Total

378.95 252.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6315.83

Page: 378 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.03

Detailed Analysis Brief Description of Item 2 RCC-25SCCM: Reinforced cement concrete work for cast-in-situ pile with minimum cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average compressive strength, f'cr = 33.5 MPa and satisfying a compressive strength f'c = 25 MPa at 28 days on standard cylinders as per standard practice of code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C 33, including breaking chips, screening through proper sieves, placing & maintaining re-bar cage in position, jointing longitudinal bars by welding or re-bar coupling method, placing and removing tripod/ derrick as per requirement, mixing in standard mixture machine with hoper, maintaining allowable slump of 150mm to 200mm, placing a sliding plug or barrier to prevent direct contact between the first charge of concrete in the pipe of the tremie and the water of drilling fluid, pouring the concrete in bore hole with the help of trimie pipe, maintaining the trimie pipe immersed in concrete by at least 1.5m throughout the period of concreting etc. including cost of all materials, labour, equipment and all incidental charges but excluding the cost of reinforcement and its fabrication, welding, coupling and placing etc. all complete as per design, drawing, specifications and direction of the E-IC. The contractor shall maintain a continuous record of the volume of concrete used and the level of the concrete in the pipe. Any deviations from the theoretical, or expected, volume/ level relationship shall be immediately reported to the E-I-C. Additional quantity of cement to be added if required to attain the specified strength to be provided by the contractor at his own cost. Note: Using Concrete Mixer

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

3.8550

liter

160.00

616.80

Foreman

0.1240

day

800.00

99.20

Page: 379 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Fitter Helper

0.1240

day

470.00

Skilled Labour

0.6780

day

450.00

305.10

Ordinary Labour

1.3600

day

370.00

503.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.1240

day

3000.00

372.00

H.C. of Derrick

0.1240

day

400.00

49.60

H.C. of Tremie Pipe

0.1240

day

500.00

62.00

H.C. of Casing

0.1240

day

260.00

32.24

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Subtotal-B: Subtotal-C:

58.28

10182.62

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10386.27

10% Profit ( Add 10% on Subtotal-B) :

11424.90

VAT

6% of Total

761.66

IT

4% of Total

507.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12694.33

Page: 380 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.04

Detailed Analysis Brief Description of Item 2 RCC-25SCBP: Reinforced cement concrete work for cast-in-situ pile with minimum cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average compressive strength, f'cr = 33.5 MPa and satisfying a compressive strength f'c = 25 MPa at 28 days on standard cylinders as per standard practice of code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C 33, including breaking chips, screening through proper sieves, placing & maintaining re-bar cage in position, jointing longitudinal bars by welding or re-bar coupling method, placing and removing tripod/ derrick as per requirement, mixing in mechanized batch mix plant & pumping using line pump or boom placer, maintaining allowable slump of 150mm to 200mm, placing a sliding plug or barrier to prevent direct contact between the first charge of concrete in the pipe of the tremie and the water of drilling fluid, pouring the concrete in bore hole with the help of trimie pipe, maintaining the trimie pipe immersed in concrete by at least 1.5m throughout the period of concreting etc. including cost of all materials, labour, equipment and all incidental charges but excluding the cost of reinforcement and its fabrication, welding, coupling and placing etc. all complete as per design, drawing, specifications and direction of the E-I-C. The contractor shall maintain a continuous record of the volume of concrete used and the level of the concrete in the pipe. Any deviations from the theoretical, or expected, volume/ level relationship shall be immediately reported to the E-I-C. Additional quantity of cement to be added if required to attain the specified strength to be provided by the contractor at his own cost. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

3.8550

liter

160.00

616.80

Foreman

0.1240

day

800.00

99.20

Page: 381 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Fitter Helper

0.1240

day

470.00

Skilled Labour

0.6780

day

450.00

305.10

Ordinary Labour

1.3600

day

370.00

503.20

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0100

day

4500.00

45.00

H.C. of Tremie Pipe

0.1240

day

500.00

62.00

H.C. of Casing

0.1240

day

260.00

32.24

58.28

10170.27

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10373.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11411.04

VAT

6% of Total

IT

4% of Total

760.74 507.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12678.94

Page: 382 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.05

Detailed Analysis Brief Description of Item 2 RCC-30SCBP: Reinforced cement concrete work for cast-in-situ pile with minimum cement content and maximum water cement ratio as specified by the laboratory having minimum required average compressive strength, f'cr = 38.5 MPa and satisfying a specified compressive strength, f'c = 30 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C 33 including breaking chips, screening through proper sieves, placing & maintaining re-bar cage in position, jointing longitudinal bars by welding or re-bar coupling method, placing and removing tripod/ derrick as per requirement, mixing in mechanized batch mix plant & pumping using line pump or boom placer, maintaining allowable slump of 150mm to 200mm, placing a sliding plug or barrier to prevent direct contact between the first charge of concrete in the pipe of the tremie and the water of drilling fluid, pouring the concrete in bore hole with the help of trimie pipe, maintaining the trimie pipe immersed in concrete by at least 1.5m throughout the period of concreting etc. including cost of all materials, labour, equipment and all incidental charges but excluding the cost of reinforcement and its fabrication, welding, coupling and placing etc. all complete as per design, drawing, specifications and direction of the E-IC. The contractor shall maintain a continuous record of the volume of concrete used and the level of the concrete in the pipe. Any deviations from the theoretical, or expected volume/ level relationship shall be immediately reported to the E-I-C. Additional quantity of cement to be added if required to attain the specified strength to be provided by the contractor at his own cost. The Mix Design shall have to be approved by the concerned District Quality Control Laboratory or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Page: 383 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

4.3000

liter

160.00

688.00

Foreman

0.1240

day

800.00

99.20

Fitter Helper

0.1240

day

470.00

58.28

Skilled Labour

0.6780

day

450.00

305.10

Ordinary Labour

1.3600

day

370.00

503.20

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0100

day

4500.00

45.00

H.C. of Tremie Pipe

0.1240

day

500.00

62.00

H.C. of Casing

0.1240

day

260.00

32.24 10839.17

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11055.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12161.55

VAT

6% of Total

IT

4% of Total

810.77 540.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13512.83

Page: 384 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Permanent Casing: Supplying, fabricating and placing in position permanent Steel casing conforming to ASTM A 36/ AASHTO M 183 for RCC bored cast-in-situ piles of specified diameters (internal) to a depth as shown in approved construction drawings including lowering & pitching the fabricated casing in position, driving the casing below bed level through all types of soil/clay/boulders/weathered or fissured or hard rock, fixing the casing in position with necessary lateral bracings (if required) etc. for stability until completion of all deck works, gas cutting, bending, welding at fabrication shop & site, painting with Red Oxide paint, transporting from fabrication shop to site, unloading at site, driving of casing, all sorts of labour, materials, tools, equipment, fuel, taxes etc. all complete as per design, drawing, specification & direction of Engineer-in-charge. Only length of steel casing driven as per drawing will be paid, wastage shall not be paid. All longitudinal and transverse welds shall be made with full penetration butt welds and adjacent segments shall be rotated 90 degree relative to each other so that longitudinal welds on the fabricated casing are staggered. The outside surface of the permanent casing shall receive two coats of anti-corrosion tar type paint which shall be approved by the Engineer-in-charge and it's application shall follow the manufacturer's instructions. If the handling, transportation, driving arrangement require a greater thickness to avoid deformation or buckling of casing, the increase in thickness shall be provided by the contractor at his own expense.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 385 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.01

Detailed Analysis Brief Description of Item 2 400mm diameter and 6mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 6mm Thick MS Casing (400mm dia)

1.0000

m

3900.00

3900.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0125

day

3000.00

37.50

H.C. of Derrick

0.0250

day

400.00

10.00

H.C. of Welding Machine

0.0250

day

500.00

12.50

Foreman

0.0125

day

800.00

10.00

Operator

0.0125

day

570.00

7.13

Skilled Labour

0.0250

day

450.00

11.25

Diesel

0.9100

liter

68.00

61.88

Lubricant

0.0130

liter

220.00

2.86 4053.12

Subtotal-A: Cost of welding & other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

405.31 4458.43

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4547.60

10% Profit ( Add 10% on Subtotal-B) :

5002.35

VAT

6% of Total

IT

4% of Total

333.49 222.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5558.17

Page: 386 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.02

Detailed Analysis Brief Description of Item 2 500mm diameter and 6mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 6mm Thick MS Casing (500mm dia)

1.0000

m

4850.00

4850.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0125

day

3000.00

37.50

H.C. of Derrick

0.0250

day

400.00

10.00

H.C. of Welding Machine

0.0250

day

500.00

12.50

Foreman

0.0125

day

800.00

10.00

Operator

0.0125

day

570.00

7.13

Skilled Labour

0.0250

day

450.00

11.25

Diesel

0.9100

liter

68.00

61.88

Lubricant

0.0130

liter

220.00

2.86 5003.12

Subtotal-A: Cost of welding & other consumables etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

750.47 5753.58

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5868.65

10% Profit ( Add 10% on Subtotal-B) :

6455.52

VAT

6% of Total

IT

4% of Total

430.37 286.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7172.80

Page: 387 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.03

Detailed Analysis Brief Description of Item 2 600mm diameter and 6mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 6mm Thick MS Casing (600mm dia)

1.0000

m

5800.00

5800.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0140

day

3000.00

42.00

H.C. of Derrick

0.0280

day

400.00

11.20

H.C. of Welding Machine

0.0280

day

500.00

14.00

Foreman

0.0140

day

800.00

11.20

Operator

0.0140

day

570.00

7.98

Skilled Labour

0.0280

day

450.00

12.60

Diesel

1.0000

liter

68.00

68.00

Lubricant

0.0140

liter

220.00

3.08 5970.06

Subtotal-A: Cost of welding & other consumables etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

895.51 6865.57

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7002.88

10% Profit ( Add 10% on Subtotal-B) :

7703.17

VAT

6% of Total

IT

4% of Total

513.54 342.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8559.08

Page: 388 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.04

Detailed Analysis Brief Description of Item 2 700mm diameter and 6mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 6mm Thick MS Casing (700mm dia)

1.0000

m

6700.00

6700.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0140

day

3000.00

42.00

H.C. of Derrick

0.0280

day

400.00

11.20

H.C. of Welding Machine

0.0280

day

500.00

14.00

Foreman

0.0140

day

800.00

11.20

Operator

0.0140

day

570.00

7.98

Skilled Labour

0.0280

day

450.00

12.60

Diesel

1.0000

liter

68.00

68.00

Lubricant

0.0140

liter

220.00

3.08 6870.06

Subtotal-A: Cost of welding & other consumables etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1030.51 7900.57

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8058.58

10% Profit ( Add 10% on Subtotal-B) :

8864.44

VAT

6% of Total

IT

4% of Total

590.96 393.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9849.38

Page: 389 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.05

Detailed Analysis Brief Description of Item 2 800mm diameter and 8mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 8mm Thick MS Casing (800mm dia)

1.0000

m

10300.00

10300.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0150

day

3000.00

45.00

H.C. of Derrick

0.0300

day

400.00

12.00

H.C. of Welding Machine

0.0300

day

500.00

15.00

Foreman

0.0150

day

800.00

12.00

Operator

0.0150

day

570.00

8.55

Skilled Labour

0.0300

day

450.00

13.50

Diesel

1.1000

liter

68.00

74.80

Lubricant

0.0150

liter

220.00

3.30 10484.15

Subtotal-A: Cost of welding & other consumables etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1572.62 12056.77

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12297.91

10% Profit ( Add 10% on Subtotal-B) :

13527.70

VAT

6% of Total

IT

4% of Total

901.85 601.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15030.78

Page: 390 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.06

Detailed Analysis Brief Description of Item 2 900mm diameter and 8mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 8mm Thick MS Casing (900mm dia)

1.0000

m

11590.00

11590.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0150

day

3000.00

45.00

H.C. of Derrick

0.0300

day

400.00

12.00

H.C. of Welding Machine

0.0300

day

500.00

15.00

Foreman

0.0150

day

800.00

12.00

Operator

0.0150

day

570.00

8.55

Skilled Labour

0.0300

day

450.00

13.50

Diesel

1.1000

liter

68.00

74.80

Lubricant

0.0150

liter

220.00

3.30 11774.15

Subtotal-A: Cost of welding & other consumables etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1766.12 13540.27

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13811.08

10% Profit ( Add 10% on Subtotal-B) :

15192.19

VAT

6% of Total

IT

4% of Total

1012.81 675.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16880.21

Page: 391 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.07

Detailed Analysis Brief Description of Item 2 1000mm diameter and 10mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 10mm Thick MS Casing (1000mm dia)

1.0000

m

16110.00

16110.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0160

day

3000.00

48.00

H.C. of Derrick

0.0320

day

400.00

12.80

H.C. of Welding Machine

0.0320

day

500.00

16.00

Foreman

0.0160

day

800.00

12.80

Operator

0.0160

day

570.00

9.12

Skilled Labour

0.0320

day

450.00

14.40

Diesel

1.2000

liter

68.00

81.60

Lubricant

0.0160

liter

220.00

3.52 16308.24

Subtotal-A: Cost of welding & other consumables etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2446.24 18754.48

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19129.57

10% Profit ( Add 10% on Subtotal-B) :

21042.52

VAT

6% of Total

IT

4% of Total

1402.83 935.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

23380.58

Page: 392 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.08

Detailed Analysis Brief Description of Item 2 1200mm diameter and 10mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 10mm Thick MS Casing (1200mm dia)

1.0000

m

19320.00

19320.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0170

day

3000.00

51.00

H.C. of Derrick

0.0340

day

400.00

13.60

H.C. of Welding Machine

0.0340

day

500.00

17.00

Foreman

0.0170

day

800.00

13.60

Operator

0.0170

day

570.00

9.69

Skilled Labour

0.0340

day

450.00

15.30

Diesel

1.2000

liter

68.00

81.60

Lubricant

0.0170

liter

220.00

3.74 19525.53

Subtotal-A: Cost of welding & other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1952.55 21478.08

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21907.64

10% Profit ( Add 10% on Subtotal-B) :

24098.41

VAT

6% of Total

IT

4% of Total

1606.56 1071.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

26776.01

Page: 393 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.09

Detailed Analysis Brief Description of Item 2 1500mm diameter and 12mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 12mm Thick MS Casing (1500mm dia)

1.0000

m

28970.00

28970.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0180

day

3000.00

54.00

H.C. of Derrick

0.0360

day

400.00

14.40

H.C. of Welding Machine

0.0360

day

500.00

18.00

Foreman

0.0180

day

800.00

14.40

Operator

0.0180

day

570.00

10.26

Skilled Labour

0.0360

day

450.00

16.20

Diesel

1.3000

liter

68.00

88.40

Lubricant

0.0180

liter

220.00

3.96 29189.62

Subtotal-A: Cost of welding & other consumables etc.

( +7.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2189.22 31378.84

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32006.42

10% Profit ( Add 10% on Subtotal-B) :

35207.06

VAT

6% of Total

IT

4% of Total

2347.14 1564.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

39118.96

Page: 394 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.10

Detailed Analysis Brief Description of Item 2 1800mm diameter and 12mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 12mm Thick MS Casing (1800mm dia)

1.0000

m

34740.00

34740.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0210

day

3000.00

63.00

H.C. of Derrick

0.0420

day

400.00

16.80

H.C. of Welding Machine

0.0420

day

500.00

21.00

Foreman

0.0210

day

800.00

16.80

Operator

0.0210

day

570.00

11.97

Skilled Labour

0.0420

day

450.00

18.90

Diesel

1.4000

liter

68.00

95.20

Lubricant

0.0210

liter

220.00

4.62 34988.29

Subtotal-A: Cost of welding & other consumables etc.

( +7.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2624.12 37612.41

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

38364.66

10% Profit ( Add 10% on Subtotal-B) :

42201.13

VAT

6% of Total

IT

4% of Total

2813.41 1875.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

46890.14

Page: 395 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.11

Detailed Analysis Brief Description of Item 2 2000mm diameter and 16mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 16mm Thick MS Casing (2000mm dia)

1.0000

m

51500.00

51500.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0240

day

3000.00

72.00

H.C. of Derrick

0.0480

day

400.00

19.20

H.C. of Welding Machine

0.0480

day

500.00

24.00

Foreman

0.0240

day

800.00

19.20

Operator

0.0240

day

570.00

13.68

Skilled Labour

0.0480

day

450.00

21.60

Diesel

1.5000

liter

68.00

102.00

Lubricant

0.0240

liter

220.00

5.28 51776.96

Subtotal-A: Cost of welding & other consumables etc.

( +7.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3883.27 55660.23

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56773.44

10% Profit ( Add 10% on Subtotal-B) :

62450.78

VAT

6% of Total

IT

4% of Total

4163.39 2775.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

69389.76

Page: 396 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.06.12

Detailed Analysis Brief Description of Item 2 2500mm diameter and 20mm thick wall

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 20mm Thick MS Casing (2500mm dia)

1.0000

m

80470.00

80470.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0270

day

3000.00

81.00

H.C. of Derrick

0.0540

day

400.00

21.60

H.C. of Welding Machine

0.0540

day

500.00

27.00

Foreman

0.0270

day

800.00

21.60

Operator

0.0270

day

570.00

15.39

Skilled Labour

0.0540

day

450.00

24.30

Diesel

1.6000

liter

68.00

108.80

Lubricant

0.0270

liter

220.00

5.94 80775.63

Subtotal-A: Cost of welding & other consumables etc.

( +7.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6058.17 86833.80

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

88570.48

10% Profit ( Add 10% on Subtotal-B) :

97427.53

VAT

6% of Total

IT

4% of Total

6495.17 4330.11 Total:

4.07.07

Amount

108252.81

Welding: Providing and making specified welding conforming to AWS D1.4 by electric arc welding for construction of cast-in-situ bored pile carefully with highly oxidized electrodes making the points prominent and accepted by the Engineer-in-charge. The cost of all materials, labour, tools and plants, electricity and all equipment is included in this unit rate. Welding shall be carried out under the continuous direction of an experienced and competent superisor.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 397 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.07.07.01

SW: spot/tack welding at contact point of the spirals at reasonalbe intervals with the main vertical reinforcements of re-bar cage to be placed in borehole.

each

Quantity 5

Unit

Rate

6

7

Amount 8

Welder Helper

0.0040

day

470.00

1.88

Electrode

0.0010

pkt

810.00

0.81

H.C. of Welding Machine

0.0010

day

500.00

0.50 3.19

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3.58

VAT

6% of Total

IT

4% of Total

0.24 0.16 Total:

4.07.07.02

LW: Direct type Lap-welded splice over two sides of contact by welding of minimum length not less than 10 times of bar diameter unless otherwise mentioned in the working drawing at the lap of main reinforcement in re-bar cage to be placed in borehole.

meter

Welder

0.1250

day

680.00

85.00

Electrode H.C. of Welding Machine

0.3330

pkt

810.00

269.73

0.0400

day

500.00

20.00 374.73

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

382.22

10% Profit ( Add 10% on Subtotal-B) :

420.45

VAT

6% of Total

IT

4% of Total

28.03 18.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3.98

467.16

Page: 398 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.08

Detailed Analysis Brief Description of Item 2 Labour for breaking head of hardened cast-in-situ bored pile/ pre-cast piles to the correct lines and levels from the top of the piles to the cutoff level as indicated in the approved drawing and exposing pile reinforcement for embedment in pile cap by any means and disposal of the debris to an unobjectionable place outside the site premises including scrapping and removing concrete from steel/ MS rods, straightening and bending of pile bars, preparation and making of platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, leveling and dressing the site and clearing the river bed, etc. all complete as per direction of the E-I-C. Measurement will be given for the actual pile head volume to be broken.The debris from pile chipping shall be disposed outside the site premises at an environmentally safe place with minimum traffic disruption and procuring entity will not be responsilbe for any irregularities by the party regarding dumping of the debris.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

9.0000

day

370.00

3330.00

Mason

0.0100

day

550.00

5.50 3403.00

Subtotal-A: Repairing of pile head including materials

( +10.00 % on Subtotal-A )

340.30

Straightening and bending of pile bars, removing the debris to a safe distance, tools & plant, sundries etc.

( +10.00 % on Subtotal-A )

340.30

Subtotal-A1: Subtotal-B: Subtotal-C:

4083.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4165.27

10% Profit ( Add 10% on Subtotal-B) :

4581.80

VAT

6% of Total

IT

4% of Total

305.45 203.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5090.89

Page: 399 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.09

Detailed Analysis Brief Description of Item 2 RCC-17BCCM: Reinforced cement concrete work for pre-cast pile with minimum cement content relates to nominal mix ratio 1:2:4 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 24 MPa and satisfying a compressive strength f'c = 17 MPa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 20mm down well graded crushed picked brick chips (LAA value & maximum water absorption not exceeding 38 & 15% respectively) conforming to ASTM C 33 including breaking chips, screening through proper sieves, cleaning and washing, centering and shuttering with MS sheet, MS angle, nuts and bolts, chamfering edges, preparation of casting beds, laying polythene, placing reinforcement cages in position, mixing in standard mixture machine with hoper, maintaining allowable slump of 50mm to 100mm, casting, compacting by mechanical vibrators and tapered rods as where necessary, curing for 28 days etc. The cost of reinforcement and it's fabrication, binding, welding and placing is not included in this unit rate. Additional quantity of cement to be added if required to attain the specified strength to be provided by the contractor at his own cost. Note: Using Concrete Mixer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7040.56

Subtotal-A: Formwork/ shuttering and consumables etc. Subtotal-A1: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +9.00 % on Subtotal-A )

633.65 7674.21 Page: 400 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-B: Subtotal-C:

Quantity 5

Unit

Rate

6

7

8

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7827.69

10% Profit ( Add 10% on Subtotal-B) :

8610.46

VAT

6% of Total

IT

4% of Total

574.03 382.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9567.18

Page: 401 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.10

Detailed Analysis Brief Description of Item 2 RCC-25SCCM: Reinforced cement concrete work for pre-cast pile with cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average compressive strength, f'cr = 33.5 MPa and satisfying a compressive strength f'c = 25 MPa at 28 days on standard cylinders as per standard practice of code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, water reducing admixture of complying type A under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C 33, including breaking stone boulders into chips, screening through proper sieves, cleaning and washing, centering and shuttering with MS sheet, MS angle, nuts and bolts, chamfering edges, preparation of casting beds, laying polythene, placing reinforcement cages in position, mixing in standard mixture machine with hoper, maintaining allowable slump of 50mm to 100mm, casting, compacting by mechanical vibrators and tapered rods as where necessary, curing for 28 days etc. The cost of reinforcement and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the specified strength to be provided by the contractor at his own cost. Note: Using Concrete Mixer

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water reducing chemical admixture : Type-A

1.9275

liter

130.00

250.58

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.1000

day

370.00

407.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Page: 402 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Steel formwork and consumables etc.

( +17.00 % on Subtotal-A )

Subtotal-A1:

Subtotal-C:

1606.04 11053.31

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11274.38

10% Profit ( Add 10% on Subtotal-B) :

12401.82

VAT

6% of Total

IT

4% of Total

826.79 551.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8 9447.28

Subtotal-A:

Subtotal-B:

Amount

13779.80

Page: 403 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.11

Detailed Analysis Brief Description of Item 2 RCC-25SCBP: Reinforced cement concrete work for pre-cast pile with cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average compressive strength, f'cr = 33.5 MPa and satisfying a compressive strength f'c = 25 MPa at 28 days on standard cylinders as per standard practice of code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, water reducing admixture of complying type A under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C 33, including breaking stone boulders into chips, screening through proper sieves, cleaning and washing, centering and shuttering with MS sheet, MS angle, nuts and bolts, chamfering edges, preparation of casting beds, laying polythene, placing reinforcement cages in position, mixing in mechanized batch mix plant & pumping using line pump or boom placer, maintaining allowable slump of 50mm to 100mm, casting, compacting by mechanical vibrators and tapered rods as where necessary, curing for 28 days etc. The cost of reinforcement and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the specified strength to be provided by the contractor at his own cost. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water reducing chemical admixture : Type-A

1.9275

liter

130.00

250.58

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Page: 404 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.0000

day

370.00

370.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9662.03

Subtotal-A: Steel Forwork and consumables etc.

( +17.00 % on Subtotal-A )

Subtotal-A1:

1642.54 11304.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11530.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12683.73

VAT

6% of Total

IT

4% of Total

845.58 563.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14093.03

Page: 405 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.12

Detailed Analysis Brief Description of Item 2 RCC-30SCBP: Reinforced cement concrete work for pre-cast pile with minimum cement content and maximum water cement ratio as specified by the laboratory having minimum required average compressive strength, f'cr = 38.5 MPa and satisfying a specified compressive strength, f'c = 30 MPa at 28 days on standard cylinders as per standard practice of code AASHTO/ ASTM and cement conforming to BDS EN 1971 : 2003 CEM-I 52.5N / ASTM C150 Type-1, water reducing admixture of complying type A under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C 33, including breaking stone boulders into chips, screening through proper sieves, cleaning and washing, centering and shuttering with MS sheet, MS angle, nuts and bolts, chamfering edges, preparation of casting beds, laying polythene, placing reinforcement cages in position, mixing in mechanized batch mix plant & pumping using line pump or boom placer, maintaining allowable slump of 50mm to 100mm, casting, compacting by mechanical vibrators and tapered rods as where necessary, curing for 28 days etc. The cost of reinforcement and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the specified strength to be provided by the contractor at his own cost. The Mix Design shall have to be approved by the concerned District Quality Control Laboratory or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water reducing chemical admixture : Type-A

2.1500

liter

130.00

279.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

Page: 406 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.0000

day

370.00

370.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10288.65

Subtotal-A: Steel Formwork and consumables etc.

( +17.00 % on Subtotal-A )

Subtotal-A1:

1749.07 12037.72

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12278.47

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13506.32

VAT

6% of Total

900.42

IT

4% of Total

600.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15007.02

Page: 407 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.13

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Mobilization and demobilization of drop hammer type pre-cast pile driving rig set..

set/site H.C. of Flat Body Truck (3 tons)

Quantity 5

2.0000

Unit

Rate

6

7

day

( +10.00 % on Subtotal-A )

Subtotal-A1:

X-section of pre-cast pile: 225mm X 225mm

Note : Rates of all items should be inclusive of all supply and carriage.

400.00 4400.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4488.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4936.80

VAT

6% of Total

329.12

IT

4% of Total

219.41 Total:

4.07.14.01

4000.00 4000.00

Incidental & Sundries

Driving pre-cast RCC piles with drop hammer type rig in any type of soil to the required depth including fitting and fixing steel cap, handling and keeping in position and maintaining driving log in prescribed format as per design, drawing & direction of the E-I-C. Before commencing driving operation, contractor shall submit the methodology for carrying the driving operation including sequence of driving to the E-I-C. The maximum permitted deviation of the finished pile from the horizontal & vertical shall be 50mm & 25mm respectively. Cutting of a pile not being installed to the planned depth is exclusively subject to the approval of Design Unit, LGED.

8

2000.00

Subtotal-A:

4.07.14

Amount

5485.33

Page: 408 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.14.01.01

2 For height: Up to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

H.C. of pre-cast pile driving complete rig set

0.0256

day

10500.00

268.80

Rig Operator

0.0333

day

600.00

19.98

Skilled Labour

0.0333

day

450.00

14.99

Ordinary Labour

0.2500

day

370.00

92.50 396.27

Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.07.14.02

X-section of pre-cast pile:250mm X 250mm

Note : Rates of all items should be inclusive of all supply and carriage.

m

19.81 416.08

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

424.40

10% Profit ( Add 10% on Subtotal-B) :

466.84

VAT

6% of Total

IT

4% of Total

31.12 20.75 Total:

For height: 6m and above

8

m

Subtotal-A:

4.07.14.01.02

Amount

518.71

Add +15.00% with Item No 4.07.14.01.01

Page: 409 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.14.02.01

2 For height: Up to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

H.C. of pre-cast pile driving complete rig set

0.0278

day

10500.00

291.90

Rig Operator

0.0417

day

600.00

25.02

Skilled Labour

0.0417

day

450.00

18.77

Ordinary Labour

0.3333

day

370.00

123.32 459.01

Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.07.14.03

X-section of pre-cast pile:300mm X 300mm

Note : Rates of all items should be inclusive of all supply and carriage.

m

22.95 481.96

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

491.60

10% Profit ( Add 10% on Subtotal-B) :

540.75

VAT

6% of Total

IT

4% of Total

36.05 24.03 Total:

For height: 6m and above

8

m

Subtotal-A:

4.07.14.02.02

Amount

600.84

Add +15.00% with Item No 4.07.14.02.01

Page: 410 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.14.03.01

2 For height: Up to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

H.C. of pre-cast pile driving complete rig set

0.0303

day

10500.00

318.15

Rig Operator

0.0483

day

600.00

28.98

Skilled Labour

0.0625

day

450.00

28.13

Ordinary Labour

0.4167

day

370.00

154.18 529.43

Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.07.14.04

X-section of pre-cast pile: 350mm X 350mm

Note : Rates of all items should be inclusive of all supply and carriage.

m

26.47 555.91

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

567.02

10% Profit ( Add 10% on Subtotal-B) :

623.73

VAT

6% of Total

IT

4% of Total

41.58 27.72 Total:

For height: 6m and above

8

m

Subtotal-A:

4.07.14.03.02

Amount

693.03

Add +15.00% with Item No 4.07.14.03.01

Page: 411 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.14.04.01

2 For height: Up to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

H.C. of pre-cast pile driving complete rig set

0.0333

day

10500.00

349.65

Rig Operator

0.0556

day

600.00

33.36

Skilled Labour

0.0833

day

450.00

37.49

Ordinary Labour

0.5000

day

370.00

185.00 605.50

Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

m

30.27 635.77

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

648.49

10% Profit ( Add 10% on Subtotal-B) :

713.33

VAT

6% of Total

IT

4% of Total

47.56 31.70 Total:

For height: 6m and above

8

m

Subtotal-A:

4.07.14.04.02

Amount

792.59

Add +15.00% with Item No 4.07.14.04.01

Page: 412 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.15

Detailed Analysis Brief Description of Item 2 Mobilization and demobilization of automatic diesel hammer mounted compete rig set.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

per site H.C. of Crane for lifting & movement of diesel mounted hammer up to site

2.0000

day

50000.00

100000.00

H.C. of Truck for carrying diesel hammer mounted rig

2.0000

day

12000.00

24000.00 124000.00

Subtotal-A: Loading & Unloading and other costs

( +15.00 % on Subtotal-A )

18600.00

Subtotal-A1:

142600.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

145452.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

159997.20

VAT

6% of Total

IT

4% of Total

10666.48 7110.99 Total:

4.07.16

Amount

177774.67

Driving pre-cast RCC piles with automatic diesel hammer mounted rig in any type of soil to the required depth including fitting and fixing steel cap, handling and keeping in position and maintaining driving log in prescribed format as per design, drawing & direction of the E-I-C. Before commencing driving operation, contractor shall submit the methodology for carrying the driving operation including sequence of driving to the E-I-C. The maximum permitted deviation of the finished pile from the horizontal & vertical shall be 50mm & 25mm respectively. Cutting of a pile not being installed to the planned depth is exclusively subject to the approval of Design Unit, LGED.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 413 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.16.01

Detailed Analysis Brief Description of Item 2 X-section of pre-cast pile: 225 mm X 225 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of double acting diesel hammer mounted complete rig set with power unit and accessories

0.0105

day

25000.00

262.50

Diesel

0.5263

liter

68.00

35.79

Lubricant

0.0211

liter

220.00

4.64

Foreman

0.0211

day

800.00

16.88

Rig Operator

0.0105

day

600.00

6.30

Rig Operator Helper

0.0842

day

400.00

33.68

Skilled Labour

0.0526

day

450.00

23.67 383.46

Subtotal-A: Tools & plant, consumables, spares, maintenance, insurance etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

38.35 421.81

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

430.24

10% Profit ( Add 10% on Subtotal-B) :

473.27

VAT

6% of Total

IT

4% of Total

31.55 21.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

525.85

Page: 414 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.16.02

Detailed Analysis Brief Description of Item 2 X-section of pre-cast pile: 250 mm X 250 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of double acting diesel hammer mounted complete rig set with power unit and accessories

0.0133

day

25000.00

332.50

Diesel

0.6667

liter

68.00

45.34

Lubricant

0.0267

liter

220.00

5.87

Foreman

0.0267

day

800.00

21.36

Rig Operator

0.0133

day

600.00

7.98

Rig Operator Helper

0.1067

day

400.00

42.68

Skilled Labour

0.0667

day

450.00

30.02 485.74

Subtotal-A: Tools & plant, consumables, spares, maintenance, insurance etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

48.57 534.32

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

545.01

10% Profit ( Add 10% on Subtotal-B) :

599.51

VAT

6% of Total

IT

4% of Total

39.97 26.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

666.12

Page: 415 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.16.03

Detailed Analysis Brief Description of Item 2 X-section of pre-cast pile: 300 mm X 300 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of double acting diesel hammer mounted complete rig set with power unit and accessories

0.0182

day

25000.00

455.00

Diesel

0.9091

liter

68.00

61.82

Lubricant

0.0364

liter

220.00

8.01

Foreman

0.0364

day

800.00

29.12

Rig Operator

0.0182

day

600.00

10.92

Rig Operator Helper

0.1455

day

400.00

58.20

Skilled Labour

0.0909

day

450.00

40.91 663.97

Subtotal-A: Tools & plant, consumables, spares, maintenance, insurance etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

66.40 730.37

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

744.98

10% Profit ( Add 10% on Subtotal-B) :

819.47

VAT

6% of Total

IT

4% of Total

54.63 36.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

910.53

Page: 416 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.16.04

Detailed Analysis Brief Description of Item 2 X-section of pre-cast pile: 350 mm X 350 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of double acting diesel hammer mounted complete rig set with power unit and accessories

0.0200

day

25000.00

500.00

Diesel

1.0000

liter

68.00

68.00

Lubricant

0.0400

liter

220.00

8.80

Foreman

0.0400

day

800.00

32.00

Rig Operator

0.0200

day

600.00

12.00

Rig Operator Helper

0.1600

day

400.00

64.00

Skilled Labour

0.1000

day

450.00

45.00 729.80

Subtotal-A: Tools & plant, consumables, spares, maintenance, insurance etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

72.98 802.78

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

818.84

10% Profit ( Add 10% on Subtotal-B) :

900.72

VAT

6% of Total

IT

4% of Total

60.05 40.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1000.80

Page: 417 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.16.05

Detailed Analysis Brief Description of Item 2 X-section of pre-cast pile: 400 mm X 400 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of double acting diesel hammer mounted complete rig set with power unit and accessories

0.0222

day

25000.00

555.00

Diesel

1.1111

liter

68.00

75.55

Lubricant

0.0444

liter

220.00

9.77

Foreman

0.0444

day

800.00

35.52

Rig Operator

0.0222

day

600.00

13.32

Rig Operator Helper

0.1778

day

400.00

71.12

Skilled Labour

0.1111

day

450.00

50.00 810.28

Subtotal-A: Tools & plant, consumables, spares, maintenance, insurance etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

81.03 891.31

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

909.13 1000.04

10% Profit ( Add 10% on Subtotal-B) :

VAT

66.67 44.45 Total:

4.07.17

Amount

1111.16

Mobilization and demobilization of Hydraulic Static Pile driver (HSPD) including complete accessories

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 418 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.17.01

Detailed Analysis Brief Description of Item 2 Maximum pile driving force up to 120 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set/site H.C. of Low bed Trailers for carrying Hydraulic static pile driver

1.0000 per trip

140000.00

140000.00

H.C. of high bed Trailers for carrying Long leg, short leg & generator of Hydraulic static pile driver

2.0000

45000.00

90000.00

H.C. of Truck for carrying Counter Weights of Hydraulic static pile driver

2.0000 per trip

20000.00

40000.00

H.C. of Crane for lifting & movement of Hydraulic static pile driver up to site

1.0000

55000.00

55000.00

each

day

325000.00

Subtotal-A: Loading & Unloading and consumables etc.

( +2.50 % on Subtotal-A )

Subtotal-A1:

8125.00 333125.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

339787.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

373766.25

VAT

6% of Total

24917.75

IT

4% of Total

16611.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

415295.83

Page: 419 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.17.02

Detailed Analysis Brief Description of Item 2 Maximum pile driving force 120 to 180 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set/site H.C. of Low bed Trailers for carrying Hydraulic static pile driver

1.0000 per trip

140000.00

140000.00

H.C. of high bed Trailers for carrying Long leg, short leg & generator of Hydraulic static pile driver

2.0000

45000.00

90000.00

H.C. of Truck for carrying Counter Weights of Hydraulic static pile driver

4.0000 per trip

20000.00

80000.00

H.C. of Crane for lifting & movement of Hydraulic static pile driver up to site

1.0000

55000.00

55000.00

each

day

365000.00

Subtotal-A: Loading & Unloading and consumables etc.

( +3.00 % on Subtotal-A )

Subtotal-A1:

10950.00 375950.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

383469.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

421815.90

VAT

6% of Total

28121.06

IT

4% of Total

18747.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

468684.33

Page: 420 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.17.03

Detailed Analysis Brief Description of Item 2 Maximum pile driving force 180 to 260 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set/site H.C. of Low bed Trailers for carrying Hydraulic static pile driver

1.0000 per trip

140000.00

140000.00

H.C. of high bed Trailers for carrying Long leg, short leg & generator of Hydraulic static pile driver

2.0000

45000.00

90000.00

H.C. of Truck for carrying Counter Weights of Hydraulic static pile driver

6.0000 per trip

20000.00

120000.00

H.C. of Crane for lifting & movement of Hydraulic static pile driver up to site

1.0000

55000.00

55000.00

each

day

405000.00

Subtotal-A: Loading & Unloading and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

20250.00 425250.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

433755.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

477130.50

VAT

6% of Total

31808.70

IT

4% of Total

21205.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

530145.00

Page: 421 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.17.04

Detailed Analysis Brief Description of Item 2 Maximum pile driving force 260 to 360 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set/site H.C. of Low bed Trailers for carrying Hydraulic static pile driver

1.0000 per trip

140000.00

140000.00

H.C. of high bed Trailers for carrying Long leg, short leg & generator of Hydraulic static pile driver

2.0000

45000.00

90000.00

H.C. of Truck for carrying Counter Weights of Hydraulic static pile driver

9.0000 per trip

20000.00

180000.00

H.C. of Crane for lifting & movement of Hydraulic static pile driver up to site

1.0000

55000.00

55000.00

each

day

465000.00

Subtotal-A: Loading & Unloading and consumables etc.

( +2.50 % on Subtotal-A )

Subtotal-A1:

11625.00 476625.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

486157.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

534773.25

VAT

6% of Total

35651.55

IT

4% of Total

23767.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

594192.50

Page: 422 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.17.05

Detailed Analysis Brief Description of Item 2 Maximum pile driving force above 360 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set/site H.C. of Low bed Trailers for carrying Hydraulic static pile driver

1.0000 per trip

H.C. of high bed Trailers for carrying Long leg, short leg & generator of Hydraulic static pile driver

2.0000

H.C. of Truck for carrying Counter Weights of Hydraulic static pile driver H.C. of Crane for lifting & movement of Hydraulic static pile driver up to site

each

11.0000 per trip 1.0000

day

140000.00

140000.00

45000.00

90000.00

20000.00

220000.00

55000.00

55000.00 505000.00

Subtotal-A: Loading & Unloading and other consumables etc.

( +2.50 % on Subtotal-A )

Subtotal-A1:

12625.00 517625.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

527977.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

580775.25

VAT

6% of Total

38718.35

IT

4% of Total

25812.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

645305.83

Page: 423 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.18

Detailed Analysis Brief Description of Item 2 Driving pre-cast RCC piles of various sizes (250 mm x 250 mm to 600 mm x 600 mm) in any type of soil using Hydraulic Static pile driver having free of any noise and vibration during driving including handling and installation of pile keeping in position as shown in the drawing, all labours, operators, tools, all equipment charges, power source, piles splicing, site arrangement, keeping all measures to avoid any disturbance to the adjacent structure, keeping driving record & pile capacity Record etc. all complete as per design, drawing, specification & direction of the E-I-C and finally submission of pile driving report in 3(three) copies duly signed by professional engineer. The maximum permitted deviation of the finished pile from the horizontal & vertical shall be 50mm & 25mm respectively. Cutting of a pile not being installed to the planned depth is exclusively subject to the approval of EI-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Hire and running charges of hydraulic static pile driver including complete accessories and shifting at site

0.0025

day

280000.00

700.00

Foreman

0.0025

day

800.00

2.00

Rig Operator

0.0025

day

600.00

1.50

Skilled Labour

0.0100

day

450.00

4.50 708.00

Subtotal-A: Report Generation and consumables etc.

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

17.70 725.70

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

740.21

10% Profit ( Add 10% on Subtotal-B) :

814.24

VAT

6% of Total

IT

4% of Total

54.28 36.19 Total:

4.07.19

Amount

904.71

Driven vertical Steel piles of required shape and length including cost of all materials and labour for hoisting, driving etc. and also including cost of dummy lengths of pile and of hire charges of all instruments as necessary complete as per drawing and & Technical Specification.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 424 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.07.19.01

Steel H-Piles of 400mm x 250mm conforming to requirements of AASHTO M 183.

m

Quantity

Corrosion resistant Structural steel

Unit

Rate

5

6

7

86.3140

kg

8

58.00

5006.21

H.C. of Excavator (Medium Size)

0.0110

day

8880.00

97.68

H.C. of Letourneau Mobile Crane (20 ton)

0.0110

day

6000.00

66.00

Operator

0.0020

day

570.00

1.14

Skilled Labour

0.0430

day

450.00

19.35 5190.38

Subtotal-A: For providing steel helmet during driving, stacking of piles at site, providing anti-corrosion treatment and other imponderables during installation.

( +1.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

51.90

5242.29 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5347.13

10% Profit ( Add 10% on Subtotal-B) :

5881.84

VAT

6% of Total

IT

4% of Total

392.12 261.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6535.38

Page: 425 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.07.19.02

Steel H-Piles of 450mm x 250mm conforming to requirements of AASHTO M 183.

m

Quantity

Corrosion resistant Structural steel

Unit

Rate

5

6

7

97.1330

kg

8

58.00

5633.71

H.C. of Excavator (Medium Size)

0.0130

day

8880.00

115.44

H.C. of Letourneau Mobile Crane (20 ton)

0.0130

day

6000.00

78.00

Operator

0.0020

day

570.00

1.14

Skilled Labour

0.0500

day

450.00

22.50 5850.79

Subtotal-A: For providing steel helmet during driving, stacking of piles at site, providing anti-corrosion treatment and other imponderables during installation.

( +1.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

58.51

5909.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6027.49

10% Profit ( Add 10% on Subtotal-B) :

6630.24

VAT

6% of Total

IT

4% of Total

442.02 294.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7366.93

Page: 426 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.20

Detailed Analysis Brief Description of Item 2 Manufacturing, supplying and fitting fixing MS shoe at RCC pre-cast pile tip with tip area 12mm x 12 mm, butt area 150mm x 150mm and height 250mm, fabricated with 6mm thick 4 nos MS plate (12mm x 150mm x 250mm) at sides and one plate (12mm x 12mm) at tip, having 6mm thick continuous fillet weld at all joints and 20mm dia. 800mm long anchor MS re-bar along with 4 nos. 20mm x 20mm x 3mm MS angle welded to the tip plate including cost of all materials, labour etc. all complete as per design, drawing & direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

LW: Direct type Lap-welded splice over two sides of contact by welding of minimum length not less than 10 times of bar diameter …...(4.07.07.02)

1.0800

meter

374.73

404.71

MS Angle 20mmx20mmx3mm

0.8620

kg

58.00

50.00

M.S. Ribbed/ Deformed Bar (Grade 300)

8.6900

kg

54.00

469.26

MS Plate (6mm thick) in Wt.

4.9200

kg

70.00

344.40

Ordinary Labour

0.0400

day

370.00

14.80 1283.16

Subtotal-A: Cost of grinding. Manufacturing cost for making, fitting and fixing of pile shoe including cutting, shaping, sizing of MS Plate & trasportation from workshop to site

( +5.00 % on Subtotal-A ) ( +25.00 % on Subtotal-A )

Subtotal-A1:

64.16 320.79

1668.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1701.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1871.62

VAT

6% of Total

124.77

IT

4% of Total

83.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2079.58

Page: 427 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.07.21

RCC-30SCCM: Reinforced cement concrete work for pre-cast driven micro pile with minimum cement content and maximum water cement ratio as specified by laboratory having minimum required average compressive strength, f'cr = 38.5 MPa and satisfying a specified compressive strength, f'c = 30 MPa at 28 days on standard cylinders as per standard practice of code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N/ ASTM C150 Type-1, water reducing admixture of complying type A under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C 33, mixing in standard mixture machine with hoper and fed by standard measuring boxes, including all related works like breaking stone boulders into chips, screening through proper sieves, cleaning and washing, centering and shuttering with MS sheet, MS angle, nuts and bolts, chamfering edges, preparation of casting beds, laying polythene, placing reinforcement cages in position, casting in steel forms, compacting by vibrators and tapered rods as where necessary , curing for 28 days, driving the pile upto the design depth as per standard practice or specified method, providing all equipment, labour, materials including carrying etc. all complete as per design, drawing and direction of the E-I-C. The cost of reinforcement and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the specified strength to be provided by the contractor at his own cost. The Mix Design shall have to be approved by the concerned District Quality Control Laboratory or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Concrete Mixer

4.07.21.01

X-section of pre-cast pile: 150mm x 150mm

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 428 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.21.01.01

Detailed Analysis Brief Description of Item 2 Cost of reinforced cement concrete

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Ordinary Portland Cement (CEM I, 52.5N)

0.1935

bag

455.00

88.04

Stone Chips (20mm down graded) [LAA≤30]

0.0110

m3

5320.00

58.52

Stone Chips (12mm down graded) [LAA≤30]

0.0074

m3

4470.00

33.08

Sand (FM - 2.5)

0.0092

m3

1500.00

13.80

Water reducing chemical admixture : Type-A

0.0484

liter

130.00

6.29

Head Mason

0.0030

day

650.00

1.95

Mason

0.0110

day

550.00

6.05

Skilled Labour

0.0160

day

450.00

7.20

Ordinary Labour

0.0200

day

370.00

7.40

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0013

day

1200.00

1.56

Hire and running charges of Concrete Vibrator

0.0013

day

400.00

0.52 224.41

Subtotal-A: Steel Formwork

( +17.00 % on Subtotal-A )

Subtotal-A1:

38.15 262.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

267.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

294.60

VAT

6% of Total

19.64

IT

4% of Total

13.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

327.33

Page: 429 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.21.01.02

2 Cost of driving up to 8.00m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Rig Operator

0.0250

day

600.00

15.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.1563

day

370.00

57.83

H.C. of pre-cast micro pile driving complete rig set

0.0125

day

5000.00

62.50 157.83

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

160.99

10% Profit ( Add 10% on Subtotal-B) :

177.09

VAT

6% of Total

IT

4% of Total

11.81 7.87 Total:

4.07.21.02

Amount

196.76

X-section of pre-cast pile: 200mm x 200mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 430 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.21.02.01

Detailed Analysis Brief Description of Item 2 Cost of reinforced cement concrete

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Ordinary Portland Cement (CEM I, 52.5N)

0.3440

bag

455.00

156.52

Stone Chips (20mm down graded) [LAA≤30]

0.0196

m3

5320.00

104.27

Stone Chips (12mm down graded) [LAA≤30]

0.0132

m3

4470.00

59.00

Sand (FM - 2.5)

0.0164

m3

1500.00

24.60

Water reducing chemical admixture : Type-A

0.0860

liter

130.00

11.18

Head Mason

0.0050

day

650.00

3.25

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.0280

day

450.00

12.60

Ordinary Labour

0.0350

day

370.00

12.95

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0020

day

1200.00

2.40

Hire and running charges of Concrete Vibrator

0.0023

day

400.00

0.92 398.70

Subtotal-A: Steel Formwork

( +17.00 % on Subtotal-A )

Subtotal-A1:

67.78 466.47

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

475.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

523.38

VAT

6% of Total

34.89

IT

4% of Total

23.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

581.54

Page: 431 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.21.02.02

2 Cost of driving up to 8.00m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Rig Operator

0.0313

day

600.00

18.78

Skilled Labour

0.0625

day

450.00

28.13

Ordinary Labour

0.2188

day

370.00

80.96

H.C. of pre-cast micro pile driving complete rig set

0.0156

day

5000.00

78.00 205.86

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

209.98

10% Profit ( Add 10% on Subtotal-B) :

230.98

VAT

6% of Total

IT

4% of Total

15.40 10.27 Total:

4.07.22

Amount

256.64

Supplying, fitting, fixing prefabricated square shaped two steel caps for Pre-cast spliced pile made up by 6mm thick MS plate conforming to ASTM A 36, sides formed by bent in channel shape to have only two line of joinery on faces, having min 50 mm dia hole on its web; capping by min. 12mm thick MS Plate shaping the edges in 45 degree, having min. 40 mm dia hole at centre to pass 25mm MS bar 450 mm in length; jointed at channels root by welding; cap fitted with 2 nos. BDS ISO 6935-2: 2006 RB 400W complied 20mm U-bar 1250mm in length by welding equidistance from centre holes of cap and shall have min 75mm clear from pile faces; and finally, the system be fitted in correct alignments on pile head positions waiting for concreting; both the pile heads fitted with the steel caps be welded together through v-notches in field, while one of the companion segment of piles drived in ground and other one placed over it maintaining true verticality; all complete as per design, drawing, specification & direction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 432 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.22.01

Detailed Analysis Brief Description of Item 2 X-section of pile segment: 300 mm x 300 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each MS Angle, Flat bar, Z bar

18.3400

kg

59.00

1082.06

M.S. Ribbed/ Deformed Bar (Grade 300)

17.2462

kg

54.00

931.29

MS Plate (12mm thick)

16.9560

kg

70.00

1186.92

MS Plate (6mm thick) in Wt.

19.4994

kg

70.00

1364.96

32mm dia GI pipe wall thickness 3.25mm

0.4500

m

380.00

171.00

Skilled Labour

0.1000

day

450.00

45.00 4781.23

Subtotal-A: Cost of Welding, grinding etc. Manufacturing cost including cutting, shaping, sizing of MS Plate & trasportation from workshop to site

( +20.00 % on Subtotal-A ) ( +30.00 % on Subtotal-A )

Subtotal-A1:

956.25 1434.37

7171.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7315.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8046.81

VAT

6% of Total

536.45

IT

4% of Total

357.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8940.91

Page: 433 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.22.02

Detailed Analysis Brief Description of Item 2 X-section of pile segment: 350 mm x 350 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each MS Angle, Flat bar, Z bar

18.3400

kg

59.00

1082.06

M.S. Ribbed/ Deformed Bar (Grade 300)

17.2462

kg

54.00

931.29

MS Plate (12mm thick)

23.0790

kg

70.00

1615.53

MS Plate (6mm thick) in Wt.

22.5609

kg

70.00

1579.26

32mm dia GI pipe wall thickness 3.25mm

0.4500

m

380.00

171.00

Skilled Labour

0.1000

day

450.00

45.00 5424.15

Subtotal-A: Cost of Welding, grinding etc. Manufacturing cost including cutting, shaping, sizing of MS Plate & trasportation from workshop to site

( +20.00 % on Subtotal-A ) ( +30.00 % on Subtotal-A )

Subtotal-A1:

1084.83 1627.24

8136.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8298.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9128.84

VAT

6% of Total

608.59

IT

4% of Total

405.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10143.16

Page: 434 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.22.03

Detailed Analysis Brief Description of Item 2 X-section of pile segment: 400 mm x 400 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each MS Angle, Flat bar, Z bar

18.3400

kg

59.00

1082.06

M.S. Ribbed/ Deformed Bar (Grade 300)

17.2462

kg

54.00

931.29

MS Plate (12mm thick)

30.1440

kg

70.00

2110.08

MS Plate (6mm thick) in Wt.

25.6224

kg

70.00

1793.57

32mm dia GI pipe wall thickness 3.25mm

0.4500

m

380.00

171.00

Skilled Labour

0.1000

day

450.00

45.00 6133.00

Subtotal-A: Cost of Welding, grinding etc. Manufacturing cost including cutting, shaping, sizing of MS Plate & trasportation from workshop to site

( +20.00 % on Subtotal-A ) ( +30.00 % on Subtotal-A )

Subtotal-A1:

1226.60 1839.90

9199.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9383.49 10321.84

VAT

6% of Total

688.12

IT

4% of Total

458.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11468.72

Page: 435 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

SLT: Conducting static load test as per ASTM D 1143 or equivalent standard for the cast in situ/ pre-cast pile providing required scaffolding, bracing, jacks, pressure test gauge, loading unloading, arranging other necessary plants and equipment including staging, mobilization, demobilization, hire charge of gunny bag/ concrete block/ steel sheet, sand and filling sacs/ gunny bags for loading, record readings and preparation of results in standard forms and other incidental charges as per standard practice and procedures including submission of load test report, furnishing all graph and chart etc. complete in all respects approved and accepted by the Engineer (Minimum two cyclic loading; one at service load and another cycle at double the load of service load then to continue loading till failure of the pile). Before commencing load test, Contractor shall submit methodology along with combined calibration report for conducting load test to the E-I-C for approval. The Testing firm will be selected taking prior approval of procuring entity. The methodology of static load test and driving logs/ boring & pouring logs shall be the part of test report. Load Test and Report shall be conducted under the supervision of a professional Geotechnical Engineer registered in the Bangladesh Professional Engineers Registration Board (BPERB), Institute of Engineers Bangladesh (IEB). [Cost of Combined Calibration Test (Hydraulic Jack, pressure gauge & electric/hydraulic pump) has been included in all sub-items.]

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 436 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.23.01

2 Up to 75 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Empty Gunny Bag Sand (FM - 0.5) Foreman Skilled Labour

675.0000

each

30.00

20250.00

19.0000

m3

420.00

7980.00

2.0000

day

800.00

1600.00

6.0000

day

450.00

2700.00

12.0000

day

370.00

4440.00

H.C. of Load Test Equipment and Accessories including Transportation: up to 125 Ton Capacity

1.0000

set

10500.00

10500.00

H.C. of Flat Body Truck (5 tons)

3.0000

day

3000.00

9000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

Ordinary Labour

86470.00

Subtotal-A: Cost of Labour for bag filling, Stitching, loading & unloading Report Generation and consumables etc.

( +30.00 % on Subtotal-A )

25941.00

( +5.00 % on Subtotal-A )

4323.50

Subtotal-A1:

116734.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

119069.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

130976.11

VAT

6% of Total

IT

4% of Total

8731.74 5821.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

145529.01

Page: 437 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.02

Detailed Analysis Brief Description of Item 2 Above 75 ton and up to 125 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Empty Gunny Bag Sand (FM - 0.5) Foreman Skilled Labour

1125.0000

each

30.00

33750.00

32.0000

m3

420.00

13440.00

2.0000

day

800.00

1600.00

6.0000

day

450.00

2700.00

12.0000

day

370.00

4440.00

H.C. of Load Test Equipment and Accessories including Transportation: up to 125 Ton Capacity

1.0000

set

10500.00

10500.00

H.C. of Flat Body Truck (5 tons)

4.0000

day

3000.00

12000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

Ordinary Labour

108430.00

Subtotal-A: Cost of Labour for bag filling, Stitching, loading & unloading Report Generation and consumables etc.

( +30.00 % on Subtotal-A )

32529.00

( +5.00 % on Subtotal-A )

5421.50

Subtotal-A1:

146380.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

149308.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

164238.92

VAT

6% of Total

IT

4% of Total

10949.26 7299.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

182487.69

Page: 438 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.03

Detailed Analysis Brief Description of Item 2 Above 125 ton and up to 175 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Empty Gunny Bag Sand (FM - 0.5) Foreman Skilled Labour

1575.0000

each

30.00

47250.00

45.0000

m3

420.00

18900.00

2.0000

day

800.00

1600.00

8.0000

day

450.00

3600.00

16.0000

day

370.00

5920.00

H.C. of Load Test Equipment and Accessories including Transportation: above 125 Ton capacity

1.0000

set

12500.00

12500.00

H.C. of Flat Body Truck (5 tons)

5.0000

day

3000.00

15000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

Ordinary Labour

134770.00

Subtotal-A: Cost of Labour for bag filling, Stitching, loading & unloading Report Generation and consumables etc.

( +30.00 % on Subtotal-A )

40431.00

( +5.00 % on Subtotal-A )

6738.50

Subtotal-A1:

181939.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185578.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

204136.12

VAT

6% of Total

IT

4% of Total

13609.07 9072.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

226817.91

Page: 439 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.04

Detailed Analysis Brief Description of Item 2 Above 175 ton and up to 225 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Empty Gunny Bag Sand (FM - 0.5) Foreman Skilled Labour

2025.0000

each

30.00

60750.00

57.5000

m3

420.00

24150.00

2.0000

day

800.00

1600.00

8.0000

day

450.00

3600.00

16.0000

day

370.00

5920.00

H.C. of Load Test Equipment and Accessories including Transportation: above 125 Ton capacity

1.0000

set

12500.00

12500.00

H.C. of Flat Body Truck (5 tons)

6.0000

day

3000.00

18000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

Ordinary Labour

156520.00

Subtotal-A: Cost of Labour for bag filling, Stitching, loading & unloading Report Generation and consumables etc.

( +30.00 % on Subtotal-A )

46956.00

( +5.00 % on Subtotal-A )

7826.00

Subtotal-A1:

211302.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

215528.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

237080.84

VAT

6% of Total

IT

4% of Total

15805.39 10536.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

263423.16

Page: 440 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.05

Detailed Analysis Brief Description of Item 2 Above 225 ton and up to 275 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Empty Gunny Bag Sand (FM - 0.5) Foreman Skilled Labour

2475.0000

each

30.00

74250.00

70.0000

m3

420.00

29400.00

2.0000

day

800.00

1600.00

8.0000

day

450.00

3600.00

16.0000

day

370.00

5920.00

H.C. of Load Test Equipment and Accessories including Transportation: above 125 Ton capacity

1.0000

set

12500.00

12500.00

H.C. of Flat Body Truck (5 tons)

7.0000

day

3000.00

21000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

Ordinary Labour

178270.00

Subtotal-A: Cost of Labour for bag filling, Stitching, loading & unloading Report Generation and consumables etc.

( +30.00 % on Subtotal-A )

53481.00

( +5.00 % on Subtotal-A )

8913.50

Subtotal-A1:

240664.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

245477.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

270025.57

VAT

6% of Total

IT

4% of Total

18001.70 12001.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

300028.41

Page: 441 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.06

Detailed Analysis Brief Description of Item 2 Above 275 ton and up to 325 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Empty Gunny Bag Sand (FM - 0.5) Foreman Skilled Labour

2912.5000

each

30.00

87375.00

82.5000

m3

420.00

34650.00

2.0000

day

800.00

1600.00

8.0000

day

450.00

3600.00

20.0000

day

370.00

7400.00

H.C. of Load Test Equipment and Accessories including Transportation: above 125 Ton capacity

1.0000

set

12500.00

12500.00

H.C. of Flat Body Truck (5 tons)

8.0000

day

3000.00

24000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

Ordinary Labour

201125.00

Subtotal-A: Cost of Labour for bag filling, Stitching, loading & unloading Report Generation and consumables etc.

( +30.00 % on Subtotal-A )

60337.50

( +5.00 % on Subtotal-A )

10056.25

Subtotal-A1:

271518.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

276949.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

304644.04

VAT

6% of Total

IT

4% of Total

20309.60 13539.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

338493.38

Page: 442 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.07

Detailed Analysis Brief Description of Item 2 Above 325 ton and up to 375 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Empty Gunny Bag Sand (FM - 0.5) Foreman

3360.0000

each

30.00

100800.00

95.0000

m3

420.00

39900.00

2.0000

day

800.00

1600.00

Skilled Labour

10.0000

day

450.00

4500.00

Ordinary Labour

20.0000

day

370.00

7400.00

H.C. of Load Test Equipment and Accessories including Transportation: above 125 Ton capacity

1.0000

set

12500.00

12500.00

H.C. of Flat Body Truck (5 tons)

9.0000

day

3000.00

27000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00 223700.00

Subtotal-A: Cost of Labour for bag filling, Stitching, loading & unloading Report Generation and consumables etc.

( +30.00 % on Subtotal-A )

67110.00

( +5.00 % on Subtotal-A )

11185.00

Subtotal-A1:

301995.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

308034.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

338838.39

VAT

6% of Total

IT

4% of Total

22589.23 15059.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

376487.10

Page: 443 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.08

Detailed Analysis Brief Description of Item 2 Above 375 ton and up to 500 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each H.C. of Concrete Block (Size: 1.0m x 1.0m x 1.0m)

208.0000each/month

833.00

173264.00

H.C. of Load Test Equipment and Accessories including Transportation: 500 - 1500 Ton Capacity

1.0000

set

100000.00

100000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

H.C. of KATO Mobile Crane (upto 5 ton)

4.0000

day

4000.00

16000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Flat Body Truck (5 tons)

6.0000

day

3000.00

18000.00 342464.00

Subtotal-A: Report Generation and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

17123.20 359587.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

366778.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

403456.84

VAT

6% of Total

IT

4% of Total

26897.12 17931.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

448285.38

Page: 444 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.09

Detailed Analysis Brief Description of Item 2 Above 500 ton and up to 700 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each H.C. of Concrete Block (Size: 1.0m x 1.0m x 1.0m)

292.0000each/month

833.00

243236.00

H.C. of Load Test Equipment and Accessories including Transportation: 500 - 1500 Ton Capacity

1.0000

set

100000.00

100000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

H.C. of KATO Mobile Crane (upto 5 ton)

4.0000

day

4000.00

16000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Flat Body Truck (5 tons)

6.0000

day

3000.00

18000.00 412436.00

Subtotal-A: Report Generation and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

20621.80 433057.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

441718.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

485890.85

VAT

6% of Total

IT

4% of Total

32392.72 21595.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

539878.72

Page: 445 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.10

Detailed Analysis Brief Description of Item 2 Above 700 ton and up to 900 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each H.C. of Concrete Block (Size: 1.0m x 1.0m x 1.0m)

375.0000each/month

833.00

312375.00

H.C. of Load Test Equipment and Accessories including Transportation: 500 - 1500 Ton Capacity

1.0000

set

100000.00

100000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

H.C. of KATO Mobile Crane (upto 5 ton)

4.0000

day

4000.00

16000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Flat Body Truck (5 tons)

6.0000

day

3000.00

18000.00 481575.00

Subtotal-A: Report Generation and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

24078.75 505653.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

515766.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

567343.51

VAT

6% of Total

IT

4% of Total

37822.90 25215.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

630381.68

Page: 446 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.11

Detailed Analysis Brief Description of Item 2 Above 900 ton and up to 1100 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each H.C. of Concrete Block (Size: 1.0m x 1.0m x 1.0m)

458.0000each/month

833.00

381514.00

H.C. of Load Test Equipment and Accessories including Transportation: 500 - 1500 Ton Capacity

1.0000

set

100000.00

100000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

H.C. of KATO Mobile Crane (upto 5 ton)

4.0000

day

4000.00

16000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Flat Body Truck (5 tons)

6.0000

day

3000.00

18000.00 550714.00

Subtotal-A: Report Generation and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

27535.70 578249.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

589814.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

648796.16

VAT

6% of Total

IT

4% of Total

43253.08 28835.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

720884.63

Page: 447 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.23.12

Detailed Analysis Brief Description of Item 2 Above 1100 ton and up to 1300 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each H.C. of Concrete Block (Size: 1.0m x 1.0m x 1.0m)

542.0000each/month

833.00

451486.00

H.C. of Load Test Equipment and Accessories including Transportation: 500 - 1500 Ton Capacity

1.0000

set

100000.00

100000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

H.C. of KATO Mobile Crane (upto 5 ton)

4.0000

day

4000.00

16000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Flat Body Truck (5 tons)

6.0000

day

3000.00

18000.00 620686.00

Subtotal-A: Report Generation and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

31034.30 651720.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

664754.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

731230.18

VAT

6% of Total

IT

4% of Total

48748.68 32499.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

812477.97

Page: 448 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.07.23.13

2 Above 1300 ton and up to 1500 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

625.0000each/month

833.00

520625.00

H.C. of Load Test Equipment and Accessories including Transportation: 500 - 1500 Ton Capacity

1.0000

set

100000.00

100000.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00

H.C. of KATO Mobile Crane (upto 5 ton)

4.0000

day

4000.00

16000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Flat Body Truck (5 tons)

6.0000

day

3000.00

18000.00 689825.00

Subtotal-A: Report Generation and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

34491.25 724316.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

738802.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

812682.83

VAT

6% of Total

IT

4% of Total

54178.86 36119.24 Total:

Above 1500 ton

8

each H.C. of Concrete Block (Size: 1.0m x 1.0m x 1.0m)

4.07.23.14

Amount

902980.93

LS

Page: 449 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.07.24

LLT: Performing Lateral load test for test load of 1.5 times of the working lateral load in accordance with ASTM D 3966 (Standard Test Methods for Deep Foundations under Lateral Load) on working pile including the cost of arranging kenteldge, jacks, platform, reaction frame with required anchorage, island where required, preparing the pile head if necessary, dial gauges, joist and all other necessary arrangement, loading and unloading, submission of the result, removal of all arrangement after completion, cost of all labour, material, carriage, leads and lift etc. complete as per approved drawing, Technical specification and as directed by the Engineer-in-charge. Before commencing load test, Contractor shall submit methodology for conducting load test to the E-I-C for approval. The Testing firm will be selected taking prior approval of procuring entity. The methodology of lateral load test and driving logs/ boring & pouring logs shall be the part of test report. Lateral Load Test and Report shall be conducted under the supervision of a professional Geotechnical Engineer registered in the Bangladesh Professional Engineers Registration Board (BPERB), Institute of Engineers Bangladesh (IEB).

4.07.24.01

LLT_50: Up to 50 ton capacity pile

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Lateral load testing of single pile in accordance with ASTM D 3966 for determining safe allowable lateral load on pile. Upto 50 ton capacity

1.0000 Per Test

25000.00

25000.00

25000.00

Subtotal-A: Report Generation and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

1250.00 26250.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26775.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

29452.50

VAT

6% of Total

1963.50

IT

4% of Total

1309.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

32725.00

Page: 450 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.24.02

Detailed Analysis Brief Description of Item 2 LLT_50+: Above 50 ton capacity pile

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Lateral load testing of single pile in accordance with ASTM D 3966 for determining safe allowable lateral load on pile. Above 50 ton capacity

1.0000 Per Test

38000.00

38000.00

38000.00

Subtotal-A: Report Generation and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

1900.00 39900.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40698.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

44767.80

VAT

6% of Total

IT

4% of Total

2984.52 1989.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

49742.00

Page: 451 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.25

Detailed Analysis Brief Description of Item 2 Conducting initial load test upto three times the design load capacity on single pile including installation of bored cast-in-situ pile to required depth using reinforced cement concrete with minimum compressive strength of 25 MPa at 28 days (suggested mix proportion 1:1.5:3, w/c max. 0.4) on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEMII 42.5N, coarse sand of minimum FM 2.5 and 20mm down well graded crushed stone chips conforming to ASTM C33 (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) including materials, boring/ drilling in all types of strata from ground level to termination depth of pile including providing bentonite slurry (Dry Bentonite powder of liquid limit of minimum 350 shall be mixed with water @ minimum 4% by weight to make the fresh drilling fluid of viscosity between 32-50 seconds and density less than 1.1gm/cc) and/ or casing for stabilization of pile bore, flushing of pile bore, cleaning, providing plasticizer wherever required, breaking pile head to cut off level and exposing pile reinforcement for embedment in pile cap, constructing test pile cap including materials, excavation, all arrangements of loading, unloading, equipments, jacks, recording of results, labour, dismantling the pile cap after test, submission of test report etc complete for the following as per design, drawing, specification and direction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

LS

Page: 452 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.26

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

PIT (Pile Integrity Test): Conducting Low-Strain Impact Integrity Testing on cast-in-situ/ pre-cast piles in accordance with ASTM D 5882 (Standard Test Method for Low Strain Impact Integrity Testing of Deep Foundations) using pile integrity tester containing calibrated measuring devices like highly sensitive accelerometer, a magnification device, an amplification box, a small impact device (hammer) & a computer with ability to convert data from analog to digital form with graphical display on completion of required setting/ driving of piles, preparation of pile top by removing soil, mud, dust & chipping lean concrete lumps etc., mobilizing and demobilizing of equipment, preparation of results in standard forms and compiling final report with recommendations on the tests etc. complete in all respects approved and accepted by the E-I-C. Report should include proper presentable graph of same wave speed (m/sec), impendence reduction, interpretation of results, cross sectional or material changes (if any), length of pile, concrete quality etc. Routine test samples shall be chosen by E-I-C on random basis. Methodology for conducting PIT shall be submitted to the E-I-C for approval and shall be the part of PIT report. All pile integrity tests shall be performed and analyzed under the supervison of a professional geotechnical engineer registered in the Bangladesh Professional Engineers Registration Board (BPERB), Institute of Engineers Bangladesh (IEB).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 453 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.26.01

Detailed Analysis Brief Description of Item 2 PIT on 10 (ten) nos. piles or less of a single bridge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set PIT: Mobilization, demobilization of Pile Integrity Testing Equipment including 10 nos. tests

1.0000

set

15000.00

15000.00

Skilled Technician

1.0000

day

680.00

680.00

Semi Skilled Technician

1.0000

day

570.00

570.00 16250.00

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

812.50

Subtotal-A1:

17062.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17403.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19144.13

VAT

6% of Total

IT

4% of Total

1276.28 850.85 Total:

4.07.26.02

Additional charge on Mobilization & demobilization beyond 100km of Dhaka/ nearby source to site

Per km PIT/ CSL: Beyond 100km from Dhaka

1.0000 per km

35.00

35.00 35.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

35.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

39.27

VAT

6% of Total

2.62

IT

4% of Total

1.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21271.25

43.63

Page: 454 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.26.03

Detailed Analysis Brief Description of Item 2 PIT on each additional pile after 10(ten) piles tested.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each PIT: per PIT after 1st 10 nos. PIT

1.0000

Each

1200.00

1200.00

Skilled Technician

0.0667

day

680.00

45.36

Semi Skilled Technician

0.0667

day

570.00

38.02 1283.38

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

64.17 1347.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1374.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1511.94

VAT

6% of Total

IT

4% of Total

100.80 67.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1679.94

Page: 455 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.07.27

PDA (Pile Driving Analyzer) Test: Performing high-strain dynamic testing on piles in accordance with ASTM D 4945 (Standard Method for HighStrain Dynamic Testing of Deep Foundation) to evaluate integrity of the hardened pile using pile driving analyser by impacting a weight of atleast 1.5% to 2% of required ultimate pile bearing capacity with a fall varying from 1m to 3m including preparing head, providing ply and sheet plates, fixing atleast 2 pairs of strain & acceleration sensors at diametrically opposite sides, experts, labour, mobilization, demobilization, data acquisition, CAPWAP analysis, integrity, interpolation, preparation of results in standard forms etc. complete in all respects approved and accepted by the E-I-C. Routine test samples shall be chosen by E-I-C on random basis. Before commencing PDA test, Contractor shall submit methodology for conducting test to the E-I-C for approval. The report should include true static capacity of the pile at the time of testing, simulated static load test curve, total skin variation along the length of pile, skin friction variation along the length of the pile, compressive and tensile stressses developed in pile during testing, net and total displacement of the pile & pile integrity. The Testing firm will be selected taking prior approval of procuring entity. All PDA testing shall be performed and analyzed under the supervison of a professional geotechnical engineer registered in the Bangladesh Professional Engineers Registration Board (BPERB), Institute of Engineers Bangladesh (IEB).

4.07.27.01

For test load up to 100 MT

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 456 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.01.01

Detailed Analysis Brief Description of Item 2 Only one pile at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

H.C. of KATO Mobile Crane Truck Mounted (20 ton)

1.0000

day

11000.00

11000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

4.0000

day

3000.00

12000.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 56615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

5661.50

( +15.00 % on Subtotal-A )

8492.25

Subtotal-A1:

70768.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

72184.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

79402.54

VAT

6% of Total

IT

4% of Total

5293.50 3529.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

88225.04

Page: 457 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.01.02

Detailed Analysis Brief Description of Item 2 Up to two piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

H.C. of KATO Mobile Crane Truck Mounted (20 ton)

1.0000

day

11000.00

11000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

2.0000

day

3000.00

6000.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 50615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

5061.50

( +15.00 % on Subtotal-A )

7592.25

Subtotal-A1:

63268.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

64534.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

70987.54

VAT

6% of Total

IT

4% of Total

4732.50 3155.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

78875.04

Page: 458 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.01.03

Detailed Analysis Brief Description of Item 2 Up to three piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

H.C. of KATO Mobile Crane Truck Mounted (20 ton)

1.0000

day

11000.00

11000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

1.3333

day

3000.00

3999.90

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 48614.90

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

4861.49

( +15.00 % on Subtotal-A )

7292.24

Subtotal-A1:

60768.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61984.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

68182.40

VAT

6% of Total

IT

4% of Total

4545.49 3030.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

75758.22

Page: 459 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.01.04

Detailed Analysis Brief Description of Item 2 four or above piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

H.C. of KATO Mobile Crane Truck Mounted (20 ton)

1.0000

day

11000.00

11000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

1.0000

day

3000.00

3000.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 47615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

4761.50

( +15.00 % on Subtotal-A )

7142.25

Subtotal-A1:

59518.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

60709.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

66780.04

VAT

6% of Total

IT

4% of Total

4452.00 2968.00 Total:

4.07.27.02

Amount

74200.04

For test load above 100 MT to 300 MT

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 460 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.02.01

Detailed Analysis Brief Description of Item 2 Only one pile at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 50 MT)

1.0000

day

60000.00

60000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

10.0000

day

3000.00

30000.00

1.0000

day

800.00

800.00

Foreman Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 123615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

12361.50

( +15.00 % on Subtotal-A )

18542.25

Subtotal-A1:

154518.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

157609.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

173370.04

VAT

6% of Total

IT

4% of Total

11558.00 7705.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

192633.38

Page: 461 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.02.02

Detailed Analysis Brief Description of Item 2 Up to two piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 50 MT)

1.0000

day

60000.00

60000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

5.0000

day

3000.00

15000.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 108615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

10861.50

( +15.00 % on Subtotal-A )

16292.25

Subtotal-A1:

135768.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

138484.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

152332.54

VAT

6% of Total

IT

4% of Total

10155.50 6770.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

169258.38

Page: 462 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.02.03

Detailed Analysis Brief Description of Item 2 Up to three piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 50 MT)

1.0000

day

60000.00

60000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

3.3333

day

3000.00

9999.90

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 103614.90

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

10361.49

( +15.00 % on Subtotal-A )

15542.24

Subtotal-A1:

129518.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132109.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145319.90

VAT

6% of Total

IT

4% of Total

9687.99 6458.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

161466.55

Page: 463 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.02.04

Detailed Analysis Brief Description of Item 2 four or above piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 50 MT)

1.0000

day

60000.00

60000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

2.5000

day

3000.00

7500.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 101115.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

10111.50

( +15.00 % on Subtotal-A )

15167.25

Subtotal-A1:

126393.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

128921.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

141813.79

VAT

6% of Total

IT

4% of Total

9454.25 6302.84 Total:

4.07.27.03

Amount

157570.88

For test load above 300 MT to 500 MT

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 464 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.03.01

Detailed Analysis Brief Description of Item 2 Only one pile at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 80 MT)

1.0000

day

70000.00

70000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

16.0000

day

3000.00

48000.00

1.0000

day

800.00

800.00

Foreman Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 151615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

15161.50

( +15.00 % on Subtotal-A )

22742.25

Subtotal-A1:

189518.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

193309.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

212640.04

VAT

6% of Total

IT

4% of Total

14176.00 9450.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

236266.71

Page: 465 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.03.02

Detailed Analysis Brief Description of Item 2 Up to two piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 80 MT)

1.0000

day

70000.00

70000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

8.0000

day

3000.00

24000.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 127615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

12761.50

( +15.00 % on Subtotal-A )

19142.25

Subtotal-A1:

159518.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

162709.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

178980.04

VAT

6% of Total

IT

4% of Total

11932.00 7954.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

198866.71

Page: 466 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.03.03

Detailed Analysis Brief Description of Item 2 Up to three piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 80 MT)

1.0000

day

70000.00

70000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

5.3333

day

3000.00

15999.90

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 119614.90

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

11961.49

( +15.00 % on Subtotal-A )

17942.24

Subtotal-A1:

149518.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

152509.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

167759.90

VAT

6% of Total

IT

4% of Total

11183.99 7456.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

186399.89

Page: 467 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.07.27.03.04

2 four or above piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 80 MT)

1.0000

day

70000.00

70000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

4.0000

day

3000.00

12000.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 115615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

11561.50

( +15.00 % on Subtotal-A )

17342.25

Subtotal-A1:

144518.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

147409.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

162150.04

VAT

6% of Total

IT

4% of Total

10810.00 7206.67 Total:

4.07.27.04

Amount

180166.71

For test load above 500 MT

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 468 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.04.01

Detailed Analysis Brief Description of Item 2 Only one pile at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 100 MT)

1.0000

day

80000.00

80000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

21.0000

day

3000.00

63000.00

1.0000

day

800.00

800.00

Foreman Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 176615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

17661.50

( +15.00 % on Subtotal-A )

26492.25

Subtotal-A1:

220768.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

225184.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

247702.54

VAT

6% of Total

IT

4% of Total

16513.50 11009.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

275225.04

Page: 469 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.04.02

Detailed Analysis Brief Description of Item 2 Up to two piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 100 MT)

1.0000

day

80000.00

80000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

10.5000

day

3000.00

31500.00

1.0000

day

800.00

800.00

Foreman Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 145115.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

14511.50

( +15.00 % on Subtotal-A )

21767.25

Subtotal-A1:

181393.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185021.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

203523.79

VAT

6% of Total

IT

4% of Total

13568.25 9045.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

226137.54

Page: 470 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.04.03

Detailed Analysis Brief Description of Item 2 Up to three piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 100 MT)

1.0000

day

80000.00

80000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

7.0000

day

3000.00

21000.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 134615.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

13461.50

( +15.00 % on Subtotal-A )

20192.25

Subtotal-A1:

168268.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

171634.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

188797.54

VAT

6% of Total

IT

4% of Total

12586.50 8391.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

209775.04

Page: 471 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.27.04.04

Detailed Analysis Brief Description of Item 2 four or above piles at a site to test in single run

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Hire and running Charges of Pile Driving Analyzer (PDA) with four (4) Strain transducers and two (2) Piezoelectric accelerometers

1.0000

day

30000.00

30000.00

Hire and running charges of Crane (Capacity 100 MT)

1.0000

day

80000.00

80000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of electric grinding machine

1.0000

day

165.00

165.00

H.C. of Flat Body Truck (5 tons)

5.2500

day

3000.00

15750.00

Foreman

1.0000

day

800.00

800.00

Electricians

1.0000

day

600.00

600.00

Mason

1.0000

day

550.00

550.00

Skilled Labour

3.0000

day

450.00

1350.00 129365.00

Subtotal-A: Hire charges for Hammer, Hammer guide, 50mm thick timber cushion, steel plate cap cover, computer etc. CAPWAP software analysis with reporting charges etc.

( +10.00 % on Subtotal-A )

12936.50

( +15.00 % on Subtotal-A )

19404.75

Subtotal-A1:

161706.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

164940.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

181434.41

VAT

6% of Total

IT

4% of Total

12095.63 8063.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

201593.79

Page: 472 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.28

Detailed Analysis Brief Description of Item 2 CSL Access Tube Installation: Supplying and Installation of 38 to 50mm inside diameter standard weight MS access tubes in each diameter drilled shaft to permit possible inspection by CSL having regular internal diameter, free of defects and obstructions, free from corrosion with clean internal and external faces to ensure a good bond between the concrete and the tubes, fit with a watertight shoe on the bottom and removable cap on the top, extended to within 150mm of the bottom of the drilled shaft to at least 1.0m above the top of the concrete and at least 0.6m but not more than 1.5m above the ground surface including materials, labour, tools and equipment necessary for unobstructed passage of the probes during the CSL Testing.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

407.00

407.00

m

MS Pipe (50mm dia, 2.35mm thick)

1.0000

m

50mm dia end cap

0.0667

each

74.00

4.94

50mm Dia MS Socket

0.1333

Nos.

150.00

20.00

PVC tape

0.1667

each

15.00

2.50

Construction Water

0.0042

KL

500.00

2.10

H.C. of Generator (150 KVA)

0.0042

day

5000.00

21.00

H.C. of Water Tanker (Truck Mounted)

0.0167

day

2500.00

41.75

Diesel

0.4583

liter

68.00

31.16

Foreman

0.0083

day

800.00

6.64

Re-bar Fabricator

0.0167

day

570.00

9.52

Skilled Labour

0.0250

day

450.00

11.25

Ordinary Labour

0.0500

day

370.00

18.50

Pump Operator

0.0042

day

500.00

2.10

Pump Operator Helper

0.0042

day

350.00

1.47 579.92

Subtotal-A: MS pipe Thread 40mm long including Tools & Equipment

( +7.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

43.49 623.42

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

635.89 Page: 473 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

6% of Total

IT

4% of Total

46.63 31.09 Total:

4.07.29

8 699.48

10% Profit ( Add 10% on Subtotal-B) :

VAT

Amount

777.20

CSL (Crosshole Sonic Logging) Test: Conducting ultrasonic crosshole testing for checking homogeneity, structural integrity, location of defects (if any) of concrete in bored pile/ drilled shafts in accordance with ASTM D 6760 (Standard Test Method for Integrity Testing of Concrete Deep Foundation by Ultrasonic Crosshole Testing) providing all equipment, experts, labour, mobilization, demobilization, data acquisition, analysis software, integrity, interpolation, preparation of results in standard forms etc. complete in all respects approved and accepted by the E-I-C. The contractor shall provide a pleliminary report to the E-I-C within 72 hours after the CSL testing has been finished and furnish two copies of the final CSL testing report sealed by the professional Geotechnical Engineer within 10 working days of testing. The final report should include CSL logs with analysis of the initial pulse arrival time versus depth and pulse energy/ amplitude versus depth and summary of the CSL test results which covers bored pile identification, test data, shaft age at time of CSL testing, bored pile diameter, number of CSL tubes tested, test length, average compression velocity & a drecription of defects detected. Before commencing CSL test, Contractor shall submit methodology with resumes of the consulting personnel for conducting test to the E-I-C for approval. All CSL testing shall be performed and analyzed under the supervison of a professional geotechnical engineer registered in the Bangladesh Professional Engineers Registration Board (BPERB), Institute of Engineers Bangladesh (IEB). The Testing firm will be selected taking prior approval of procuring entity.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 474 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.29.01

Detailed Analysis Brief Description of Item 2 Mobilization & demobilization within 100km of Dhaka/ nearby source to site and CSL Testing on 4 (four) nos. access tubes or less of a single bored pile/drilled shafts

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

CSL: Mobilization, demobilization & accomodation including 4 nos. CSL (Crosshole Sonic Logging)

1.0000

set

200000.00

200000.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 201150.00

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

10057.50

Subtotal-A1: Subtotal-B: Subtotal-C:

211207.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

215431.65

10% Profit ( Add 10% on Subtotal-B) :

236974.82

VAT

6% of Total

15798.32

IT

4% of Total

10532.21 Total:

4.07.29.02

Additional charge on Mobilization & demobilization beyond 100km of Dhaka/ nearby source to site

Per Km PIT/ CSL: Beyond 100km from Dhaka

1.0000 per km

35.00

Subtotal-B: Subtotal-C:

35.00 35.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

35.70

10% Profit ( Add 10% on Subtotal-B) :

39.27

VAT

6% of Total

IT

4% of Total

2.62 1.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

263305.35

43.63

Page: 475 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.07.29.03

Detailed Analysis Brief Description of Item 2 CSL Testing on each additional access tube after 4(four) access tubes

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

CSL: per CSL after 1st 4 nos. CSL

1.0000

each

40000.00

40000.00

Plumber/ Electric Mistry/ Painter

0.2500

day

680.00

170.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 40287.50

Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

4.08.01.01

Sinking of 6m external diameter well in Sandy Soil

Note : Rates of all items should be inclusive of all supply and carriage.

2014.38 42301.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

43147.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

47462.70

VAT

6% of Total

IT

4% of Total

3164.18 2109.45 Total:

Sinking of Well as per specification through all types of strata namely sandy soil, clayey soil and rock as shown against each case, including drawing Foundation Wells true to position and plumb with dia under cutting edge as mentioned below, including hire charges of all tools and plants etc. and supplying power, dewatering etc., initial excavation of earth complete as per drawing and technical specifications and direction of the Engineer-in-charge including throwing the spoils clear off the well up to 150m radius (Measurement to be taken in the following stages from the level of the bottom of capping slab on well up to the bottom of cutting edge) through any kind of soil including rocky soil and rock till 25% of cutting edge (linear) comes in contact with rock including testing of bottom plug by dewatering the well upto 5 meters and checking the rise in water level as per Specification. Depth of sinking is reckoned from bed level.

8

each

Subtotal-A:

4.08.01

Amount

52736.34

Page: 476 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.01.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.1200

day

550.00

66.00

Sareng

1.0000

day

570.00

570.00

Khalashi

2.0000

day

390.00

780.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.2500

day

12000.00

3000.00 4416.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

441.60 4857.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4954.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5450.23

VAT

6% of Total

363.35

IT

4% of Total

242.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6055.81

Page: 477 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.01.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.1500

day

550.00

82.50

Sareng

1.2500

day

570.00

712.50

Khalashi

2.5000

day

390.00

975.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.3750

day

12000.00

4500.00 6270.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

627.00 6897.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7034.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7738.43

VAT

6% of Total

515.90

IT

4% of Total

343.93 Total:

4.08.01.01.03

Depth beyond 10.0 m up to 15.0 m

m

Add +16.00% with Item No 4.08.01.01.02

4.08.01.01.04

Depth beyond 15.0 m up to 20.0 m

m

Add +48.00% with Item No 4.08.01.01.02

4.08.01.01.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +145.00% with Item No 4.08.01.01.02

4.08.01.01.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +250.00% with Item No 4.08.01.01.02

4.08.01.01.07

Depth beyond 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +440.00% with Item No 4.08.01.01.02

4.08.01.02

Sinking of 6m external diameter well in Clayey Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8598.26

Page: 478 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.02.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.1500

day

550.00

82.50

Sareng

1.5000

day

570.00

855.00

Khalashi

2.2500

day

390.00

877.50

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.3750

day

12000.00

4500.00 6315.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

631.50 6946.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7085.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7793.97

VAT

6% of Total

519.60

IT

4% of Total

346.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8659.97

Page: 479 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.02.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.3000

day

550.00

165.00

Sareng

3.0000

day

570.00

1710.00

Khalashi

4.5000

day

390.00

1755.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7500

day

12000.00

9000.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.2500

day

2500.00

625.00 13255.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1325.50 14580.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14872.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16359.32

VAT

6% of Total

IT

4% of Total

1090.62 727.08 Total:

4.08.01.02.03

Depth beyond 10.0 m up to 15.0 m

m

Add +20.00% with Item No 4.08.01.02.02

4.08.01.02.04

Depth beyond 15.0 m up to 20.0 m

m

Add +55.00% with Item No 4.08.01.02.02

4.08.01.02.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +160.00% with Item No 4.08.01.02.02

4.08.01.02.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +280.00% with Item No 4.08.01.02.02

4.08.01.02.07

Depth beyond 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +460.00% with Item No 4.08.01.02.02

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

18177.02

Page: 480 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.01.03

Sinking of 6m external diameter well in Soft Rock

4.08.01.03.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

0.9200

day

550.00

506.00

Sareng

3.0000

day

570.00

1710.00

Khalashi

20.0000

day

390.00

7800.00

Operator

0.5000

day

570.00

285.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.5000

day

12000.00

6000.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.4375

day

2500.00

1093.75

5

m Mason

17394.75

Subtotal-A: Consumables in sinking Cost for Dewatering

( +10.00 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1739.48 869.74 20003.96

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20404.04

10% Profit ( Add 10% on Subtotal-B) :

22444.45

VAT

6% of Total

IT

4% of Total

1496.30 997.53 Total:

4.08.01.04

Amount

24938.27

Sinking of 7m external diameter well in Sandy Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 481 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.04.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.1500

day

550.00

82.50

Sareng

1.2500

day

570.00

712.50

Khalashi

2.5000

day

390.00

975.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.4063

day

12000.00

4875.60 6645.60

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

664.56 7310.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7456.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8202.00

VAT

6% of Total

546.80

IT

4% of Total

364.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9113.33

Page: 482 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.04.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.1800

day

550.00

99.00

Sareng

1.5000

day

570.00

855.00

Khalashi

3.0000

day

390.00

1170.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.5625

day

12000.00

6750.00 8874.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

887.40 9761.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9956.63 10952.29

VAT

6% of Total

730.15

IT

4% of Total

486.77 Total:

4.08.01.04.03

Depth beyond 10.0 m up to 15.0 m

m

Add +16.00% with Item No 4.08.01.04.02

4.08.01.04.04

Depth beyond 15.0 m up to 20.0 m

m

Add +48.00% with Item No 4.08.01.04.02

4.08.01.04.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +145.00% with Item No 4.08.01.04.02

4.08.01.04.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +250.00% with Item No 4.08.01.04.02

4.08.01.04.07

Depth beyond 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +440.00% with Item No 4.08.01.04.02

4.08.01.05

Sinking of 7m external diameter well in Clayey Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12169.21

Page: 483 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.05.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.1800

day

550.00

99.00

Sareng

1.5000

day

570.00

855.00

Khalashi

3.0000

day

390.00

1170.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.5625

day

12000.00

6750.00 8874.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

887.40 9761.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9956.63 10952.29

VAT

6% of Total

730.15

IT

4% of Total

486.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12169.21

Page: 484 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.05.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.2600

day

550.00

143.00

Sareng

2.0000

day

570.00

1140.00

Khalashi

4.0000

day

390.00

1560.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7500

day

12000.00

9000.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.4063

day

2500.00

1015.75 12858.75

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1285.88 14144.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14427.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15870.27

VAT

6% of Total

IT

4% of Total

1058.02 705.35 Total:

4.08.01.05.03

Depth beyond 10.0 m up to 15.0 m

m

Add +20.00% with Item No 4.08.01.05.02

4.08.01.05.04

Depth beyond 15.0 m up to 20.0 m

m

Add +55.00% with Item No 4.08.01.05.02

4.08.01.05.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +160.00% with Item No 4.08.01.05.02

4.08.01.05.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +280.00% with Item No 4.08.01.05.02

4.08.01.05.07

Depth beyond 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +460.00% with Item No 4.08.01.05.02

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

17633.63

Page: 485 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.01.06

Sinking of 7m external diameter well in Soft Rock

4.08.01.06.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

0.5800

day

550.00

319.00

Sareng

4.0000

day

570.00

2280.00

Khalashi

10.0000

day

390.00

3900.00

Operator

0.7500

day

570.00

427.50

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.5625

day

12000.00

6750.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.4688

day

2500.00

1172.00

5

m Mason

14848.50

Subtotal-A: Consumables in sinking Cost for Dewatering

( +10.00 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1484.85 742.43 17075.78

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17417.29

10% Profit ( Add 10% on Subtotal-B) :

19159.02

VAT

6% of Total

IT

4% of Total

1277.27 851.51 Total:

4.08.01.07

Amount

21287.80

Sinking of 8m external diameter well in Sandy Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 486 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.07.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.1800

day

550.00

99.00

Sareng

1.5000

day

570.00

855.00

Khalashi

3.0000

day

390.00

1170.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.5000

day

12000.00

6000.00 8124.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

812.40 8936.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9115.13 10026.64

VAT

6% of Total

668.44

IT

4% of Total

445.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11140.71

Page: 487 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.07.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.2500

day

550.00

137.50

Sareng

1.7500

day

570.00

997.50

Khalashi

3.5000

day

390.00

1365.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.6250

day

12000.00

7500.00 10000.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1000.00 11000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11220.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12342.00

VAT

6% of Total

822.80

IT

4% of Total

548.53 Total:

4.08.01.07.03

Depth beyond 10.0 m up to 15.0 m

m

Add +16.00% with Item No 4.08.01.07.02

4.08.01.07.04

Depth beyond 15.0 m up to 20.0 m

m

Add +48.00% with Item No 4.08.01.07.02

4.08.01.07.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +145.00% with Item No 4.08.01.07.02

4.08.01.07.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +250.00% with Item No 4.08.01.07.02

4.08.01.07.07

Depth beyond 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +440.00% with Item No 4.08.01.07.02

4.08.01.08

Sinking of 8m external diameter well in Clayey Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13713.33

Page: 488 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.08.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.2200

day

550.00

121.00

Sareng

2.0000

day

570.00

1140.00

Khalashi

3.5000

day

390.00

1365.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.6875

day

12000.00

8250.00 10876.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1087.60 11963.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12202.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13423.16

VAT

6% of Total

894.88

IT

4% of Total

596.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14914.62

Page: 489 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.08.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.3200

day

550.00

176.00

Sareng

2.5000

day

570.00

1425.00

Khalashi

4.5000

day

390.00

1755.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7500

day

12000.00

9000.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.4063

day

2500.00

1015.75 13371.75

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1337.18 14708.93

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15003.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16503.41

VAT

6% of Total

IT

4% of Total

1100.23 733.49 Total:

4.08.01.08.03

Depth beyond 10.0 m up to 15.0 m [Considering additional cost for Dewatering]

m

Add +20.00% with Item No 4.08.01.08.02

4.08.01.08.04

Depth beyond 15.0 m up to 20.0 m [Considering additional cost for Dewatering]

m

Add +55.00% with Item No 4.08.01.08.02

4.08.01.08.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +160.00% with Item No 4.08.01.08.02

4.08.01.08.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +280.00% with Item No 4.08.01.08.02

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

18337.13

Page: 490 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.01.08.07

Depth beyond 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

4.08.01.09

Sinking of 8m external diameter well in Soft Rock

4.08.01.09.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

m

Quantity 5

Unit

Rate

6

7

8

Add +460.00% with Item No 4.08.01.08.02

m Mason

0.6800

day

550.00

374.00

Sareng

4.0000

day

570.00

2280.00

Khalashi

12.0000

day

390.00

4680.00

Operator

1.0000

day

570.00

570.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.6250

day

12000.00

7500.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.4688

day

2500.00

1172.00 16576.00

Subtotal-A: Consumables in sinking Cost for Dewatering

( +10.00 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

Subtotal-A1:

1657.60 828.80 19062.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19443.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21388.01

VAT

6% of Total

IT

4% of Total

1425.87 950.58 Total:

4.08.01.10

Amount

23764.46

Sinking of 9m external diameter well in Sandy Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 491 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.10.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.1900

day

550.00

104.50

Sareng

1.5000

day

570.00

855.00

Khalashi

3.2500

day

390.00

1267.50

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.5000

day

12000.00

6000.00 8227.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

822.70 9049.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9230.69 10153.76

VAT

6% of Total

676.92

IT

4% of Total

451.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11281.96

Page: 492 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.10.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.2700

day

550.00

148.50

Sareng

1.7500

day

570.00

997.50

Khalashi

4.0000

day

390.00

1560.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.6875

day

12000.00

8250.00 10956.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1095.60 12051.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12292.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13521.90

VAT

6% of Total

901.46

IT

4% of Total

600.97 Total:

4.08.01.10.03

Depth beyond 10.0 m up to 15.0 m

m

Add +16.00% with Item No 4.08.01.10.02

4.08.01.10.04

Depth beyond 15.0 m up to 20.0 m

m

Add +48.00% with Item No 4.08.01.10.02

4.08.01.10.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +145.00% with Item No 4.08.01.10.02

4.08.01.10.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +250.00% with Item No 4.08.01.10.02

4.08.01.10.07

Depth beyond 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +440.00% with Item No 4.08.01.10.02

4.08.01.11

Sinking of 9m external diameter well in Clayey Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15024.33

Page: 493 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.11.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.2400

day

550.00

132.00

Sareng

2.2500

day

570.00

1282.50

Khalashi

3.7500

day

390.00

1462.50

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7188

day

12000.00

8625.60 11502.60

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1150.26 12652.86

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12905.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14196.51

VAT

6% of Total

946.43

IT

4% of Total

630.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15773.90

Page: 494 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.11.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.3400

day

550.00

187.00

Sareng

2.5000

day

570.00

1425.00

Khalashi

5.0000

day

390.00

1950.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.8125

day

12000.00

9750.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.4688

day

2500.00

1172.00 14484.00

Subtotal-A: Consumables in sinking +.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1448.40 15932.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16251.05

10% Profit ( Add 10% on Subtotal-B) :

17876.15

VAT

6% of Total

IT

4% of Total

1191.74 794.50 Total:

4.08.01.11.03

Depth beyond 10.0 m up to 15.0 m [Considering additional cost for Dewatering]

m

Add +20.00% with Item No 4.08.01.11.02

4.08.01.11.04

Depth beyond 15.0 m up to 20.0 m [Considering additional cost for Dewatering]

m

Add +55.00% with Item No 4.08.01.11.02

4.08.01.11.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +160.00% with Item No 4.08.01.11.02

4.08.01.11.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +280.00% with Item No 4.08.01.11.02

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19862.39

Page: 495 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.01.11.07

Depth beyond 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

4.08.01.12

Sinking of 9m external diameter well in Soft Rock

4.08.01.12.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

m

Quantity 5

Unit

Rate

6

7

8

Add +460.00% with Item No 4.08.01.11.02

m Mason

0.7600

day

550.00

418.00

Sareng

4.0000

day

570.00

2280.00

Khalashi

14.0000

day

390.00

5460.00

Operator

1.2000

day

570.00

684.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.8125

day

12000.00

9750.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.5000

day

2500.00

1250.00 19842.00

Subtotal-A: Consumables in sinking Cost for Dewatering

( +10.00 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

Subtotal-A1:

1984.20 992.10 22818.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23274.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25602.13

VAT

6% of Total

IT

4% of Total

1706.81 1137.87 Total:

4.08.01.13

Amount

28446.81

Sinking of 10m external diameter well in Sandy Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 496 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.13.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.2000

day

550.00

110.00

Sareng

1.5000

day

570.00

855.00

Khalashi

3.5000

day

390.00

1365.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.6250

day

12000.00

7500.00 9830.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

983.00 10813.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11029.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12132.19

VAT

6% of Total

808.81

IT

4% of Total

539.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13480.21

Page: 497 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.13.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.3100

day

550.00

170.50

Sareng

2.0000

day

570.00

1140.00

Khalashi

4.2500

day

390.00

1657.50

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7188

day

12000.00

8625.60 11593.60

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1159.36 12752.96

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13008.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14308.82

VAT

6% of Total

953.92

IT

4% of Total

635.95 Total:

4.08.01.13.03

Depth beyond 10.0 m up to 15.0 m

m

Add +16.00% with Item No 4.08.01.13.02

4.08.01.13.04

Depth beyond 15.0 m up to 20.0 m

m

Add +48.00% with Item No 4.08.01.13.02

4.08.01.13.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +145.00% with Item No 4.08.01.13.02

4.08.01.13.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +250.00% with Item No 4.08.01.13.02

4.08.01.13.07

Depth beyond 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +440.00% with Item No 4.08.01.13.02

4.08.01.14

Sinking of 10m external diameter well in Clayey Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15898.69

Page: 498 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.14.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.2500

day

550.00

137.50

Sareng

2.5000

day

570.00

1425.00

Khalashi

5.5000

day

390.00

2145.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7500

day

12000.00

9000.00 12707.50

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1270.75 13978.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14257.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15683.60

VAT

6% of Total

1045.57

IT

4% of Total

697.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

17426.22

Page: 499 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.14.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.4000

day

550.00

220.00

Sareng

3.0000

day

570.00

1710.00

Khalashi

5.5000

day

390.00

2145.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7500

day

12000.00

9000.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.5000

day

2500.00

1250.00 14325.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1432.50 15757.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16072.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17679.92

VAT

6% of Total

IT

4% of Total

1178.66 785.77 Total:

4.08.01.14.03

Depth beyond 10.0 m up to 15.0 m [Considering additional cost for Dewatering]

m

Add +20.00% with Item No 4.08.01.14.02

4.08.01.14.04

Depth beyond 15.0 m up to 20.0 m [Considering additional cost for Dewatering]

m

Add +55.00% with Item No 4.08.01.14.02

4.08.01.14.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +160.00% with Item No 4.08.01.14.02

4.08.01.14.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +280.00% with Item No 4.08.01.14.02

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19644.35

Page: 500 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.01.14.07

Depth beyond 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

4.08.01.15

Sinking of 10m external diameter well in Soft Rock

4.08.01.15.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

m

Quantity 5

Unit

Rate

6

7

8

Add +460.00% with Item No 4.08.01.14.02

m Mason

0.8600

day

550.00

473.00

Sareng

4.0000

day

570.00

2280.00

Khalashi

16.0000

day

390.00

6240.00

Operator

1.4000

day

570.00

798.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.8750

day

12000.00

10500.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.5313

day

2500.00

1328.25 21619.25

Subtotal-A: Consumables in sinking Cost for Dewatering

( +10.00 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

Subtotal-A1:

2161.93 1080.96 24862.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25359.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

27895.32

VAT

6% of Total

IT

4% of Total

1859.69 1239.79 Total:

4.08.01.16

Amount

30994.80

Sinking of 11m external diameter well in Sandy Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 501 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.16.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.4200

day

550.00

231.00

Sareng

3.0000

day

570.00

1710.00

Khalashi

6.6000

day

390.00

2574.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

1.5000

day

12000.00

18000.00 22515.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

2251.50 24766.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25261.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

27788.01

VAT

6% of Total

1852.53

IT

4% of Total

1235.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

30875.57

Page: 502 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.16.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.6400

day

550.00

352.00

Sareng

4.0000

day

570.00

2280.00

Khalashi

9.0000

day

390.00

3510.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

1.0000

day

12000.00

12000.00 18142.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1814.20 19956.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20355.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22390.86

VAT

6% of Total

1492.72

IT

4% of Total

995.15 Total:

4.08.01.16.03

Depth beyond 10.0 m up to 15.0 m

m

Add +16.00% with Item No 4.08.01.16.02

4.08.01.16.04

Depth beyond 15.0 m up to 20.0 m

m

Add +48.00% with Item No 4.08.01.16.02

4.08.01.16.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +145.00% with Item No 4.08.01.16.02

4.08.01.16.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +250.00% with Item No 4.08.01.16.02

4.08.01.16.07

Depth beyond 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +440.00% with Item No 4.08.01.16.02

4.08.01.17

Sinking of 11m external diameter well in Clayey Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

24878.73

Page: 503 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.17.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.5200

day

550.00

286.00

Sareng

5.0000

day

570.00

2850.00

Khalashi

8.0000

day

390.00

3120.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

1.2500

day

12000.00

15000.00 21256.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

2125.60 23381.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23849.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26234.16

VAT

6% of Total

1748.94

IT

4% of Total

1165.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

29149.06

Page: 504 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.17.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.8600

day

550.00

473.00

Sareng

7.0000

day

570.00

3990.00

Khalashi

11.5000

day

390.00

4485.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

1.5000

day

12000.00

18000.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

1.0625

day

2500.00

2656.25 29604.25

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

2960.43 32564.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

33215.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

36537.57

VAT

6% of Total

IT

4% of Total

2435.84 1623.89 Total:

4.08.01.17.03

Depth beyond 10.0 m up to 15.0 m [Considering additional cost for Dewatering]

m

Add +20.00% with Item No 4.08.01.17.02

4.08.01.17.04

Depth beyond 15.0 m up to 20.0 m [Considering additional cost for Dewatering]

m

Add +55.00% with Item No 4.08.01.17.02

4.08.01.17.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +160.00% with Item No 4.08.01.17.02

4.08.01.17.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +280.00% with Item No 4.08.01.17.02

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

40597.29

Page: 505 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.01.17.07

Depth beyond 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

4.08.01.18

Sinking of 11m external diameter well in Soft Rock

4.08.01.18.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

m

Quantity 5

Unit

Rate

6

7

8

Add +460.00% with Item No 4.08.01.17.02

m Mason

1.9000

day

550.00

1045.00

Sareng

8.5000

day

570.00

4845.00

Khalashi

36.0000

day

390.00

14040.00

Operator

3.0000

day

570.00

1710.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

2.0000

day

12000.00

24000.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

1.1250

day

2500.00

2812.50 48452.50

Subtotal-A: Consumables in sinking Cost for Dewatering

( +10.00 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

Subtotal-A1:

4845.25 2422.63 55720.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56834.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

62518.26

VAT

6% of Total

IT

4% of Total

4167.88 2778.59 Total:

4.08.01.19

Amount

69464.73

Sinking of 12m external diameter well in Sandy Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 506 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.19.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.8800

day

550.00

484.00

Sareng

7.0000

day

570.00

3990.00

Khalashi

16.0000

day

390.00

6240.00

3.0000

day

12000.00

36000.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

46714.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

4671.40 51385.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

52413.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

57654.42

VAT

6% of Total

3843.63

IT

4% of Total

2562.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

64060.47

Page: 507 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.19.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

1.4800

day

550.00

814.00

Sareng

10.0000

day

570.00

5700.00

Khalashi

19.0000

day

390.00

7410.00

3.2500

day

12000.00

39000.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

52924.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

5292.40 58216.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

59380.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

65318.80

VAT

6% of Total

4354.59

IT

4% of Total

2903.06 Total:

4.08.01.19.03

Depth beyond 10.0 m up to 15.0 m

m

Add +16.00% with Item No 4.08.01.19.02

4.08.01.19.04

Depth beyond 15.0 m up to 20.0 m

m

Add +48.00% with Item No 4.08.01.19.02

4.08.01.19.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +145.00% with Item No 4.08.01.19.02

4.08.01.19.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +250.00% with Item No 4.08.01.19.02

4.08.01.19.07

Depth beyond 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +440.00% with Item No 4.08.01.19.02

4.08.01.20

Sinking of 12m external diameter well in Clayey Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

72576.45

Page: 508 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.20.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

1.2000

day

550.00

660.00

Sareng

12.0000

day

570.00

6840.00

Khalashi

18.0000

day

390.00

7020.00

3.1250

day

12000.00

37500.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

52020.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

5202.00 57222.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58366.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

64203.08

VAT

6% of Total

4280.21

IT

4% of Total

2853.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

71336.76

Page: 509 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.01.20.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

1.9200

day

550.00

1056.00

Sareng

15.0000

day

570.00

8550.00

Khalashi

24.0000

day

390.00

9360.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

4.1650

day

12000.00

49980.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

2.2500

day

2500.00

5625.00 74571.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

7457.10 82028.10

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

83668.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

92035.53

VAT

6% of Total

IT

4% of Total

6135.70 4090.47 Total:

4.08.01.20.03

Depth beyond 10.0 m up to 15.0 m [Considering additional cost for Dewatering]

m

Add +20.00% with Item No 4.08.01.20.02

4.08.01.20.04

Depth beyond 15.0 m up to 20.0 m [Considering additional cost for Dewatering]

m

Add +55.00% with Item No 4.08.01.20.02

4.08.01.20.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +160.00% with Item No 4.08.01.20.02

4.08.01.20.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +280.00% with Item No 4.08.01.20.02

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

102261.70

Page: 510 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.01.20.07

Depth beyond 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

4.08.01.21

Sinking of 12m external diameter well in Soft Rock

4.08.01.21.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

m

Quantity 5

Unit

Rate

6

7

8

Add +460.00% with Item No 4.08.01.20.02

m Mason

4.2400

day

550.00

2332.00

Sareng

18.0000

day

570.00

10260.00

Khalashi

80.0000

day

390.00

31200.00

Operator

7.0000

day

570.00

3990.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

5.0000

day

12000.00

60000.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

2.3750

day

2500.00

5937.50 113719.50

Subtotal-A: Consumables in sinking Cost for Dewatering

( +10.00 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

11371.95 5685.98

Subtotal-A1:

130777.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

133392.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

146732.27

VAT

6% of Total

IT

4% of Total

9782.15 6521.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

163035.86

Page: 511 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.02

Sinking of Twin D Type Well as per specification through all types of strata namely sandy soil, clayey soil and rock as shown against each case, including drawing Foundation Wells true to position and plumb with dia under cutting edge as mentioned below, including hire charges of all tools and plants etc. and supplying power, dewatering etc., initial excavation of earth complete as per drawing and technical specifications and direction of the Engineer-in-charge including throwing the spoils clear off the well up to 150m radius (Measurement to be taken in the following stages from the level of the bottom of capping slab on well up to the bottom of cutting edge). Depth of sinking is reckoned from bed level.

4.08.02.01

Sinking of 8m external diameter well in Sandy Soil

4.08.02.01.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.2000

day

550.00

110.00

Sareng

1.2500

day

570.00

712.50

Khalashi

3.7500

day

390.00

1462.50

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.6875

day

12000.00

8250.00 10535.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1053.50 11588.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11820.27

10% Profit ( Add 10% on Subtotal-B) :

13002.30

VAT

6% of Total

IT

4% of Total

866.82 577.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14447.00

Page: 512 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.02.01.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.3000

day

550.00

165.00

Sareng

1.5000

day

570.00

855.00

Khalashi

4.0000

day

390.00

1560.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7350

day

12000.00

8820.00 11400.00

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1140.00 12540.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12790.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14069.88

VAT

6% of Total

937.99

IT

4% of Total

625.33 Total:

4.08.02.01.03

Depth beyond 10.0 m up to 15.0 m

m

Add +16.00% with Item No 4.08.02.01.02

4.08.02.01.04

Depth beyond 15.0 m up to 20.0 m

m

Add +48.00% with Item No 4.08.02.01.02

4.08.02.01.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +145.00% with Item No 4.08.02.01.02

4.08.02.01.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +250.00% with Item No 4.08.02.01.02

4.08.02.01.07

Depth beyond 30.0 m [Considering additional cost for Kentledge including supports, loading arrangement and Labour.]

m

Add +440.00% with Item No 4.08.02.01.02

4.08.02.02

Sinking of 8m external diameter well in Clayey Soil

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15633.20

Page: 513 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.02.02.01

Detailed Analysis Brief Description of Item 2 Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Mason

0.2600

day

550.00

143.00

Sareng

2.5000

day

570.00

1425.00

Khalashi

4.0000

day

390.00

1560.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.7813

day

12000.00

9375.60 12503.60

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1250.36 13753.96

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14029.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15431.94

VAT

6% of Total

1028.80

IT

4% of Total

685.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

17146.60

Page: 514 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.02.02.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Depth beyond 3.0 m up to 10.0 m

m

Quantity 5

Unit

Rate

6

7

8

Mason

0.4500

day

550.00

247.50

Sareng

3.2500

day

570.00

1852.50

Khalashi

6.0000

day

390.00

2340.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

0.8338

day

12000.00

10005.60

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.5625

day

2500.00

1406.25 15851.85

Subtotal-A: Consumables in sinking

( +10.00 % on Subtotal-A )

Subtotal-A1:

1585.19 17437.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17785.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19564.35

VAT

6% of Total

IT

4% of Total

1304.29 869.53 Total:

4.08.02.02.03

Depth beyond 10.0 m up to 15.0 m

m

Add +20.00% with Item No 4.08.02.02.02

4.08.02.02.04

Depth beyond 15.0 m up to 20.0 m

m

Add +55.00% with Item No 4.08.02.02.02

4.08.02.02.05

Depth beyond 20.0 m up to 25.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +160.00% with Item No 4.08.02.02.02

4.08.02.02.06

Depth beyond 25.0 m up to 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +280.00% with Item No 4.08.02.02.02

4.08.02.02.07

Depth beyond 30.0 m [Considering additional cost for Dewatering, Kentledge including supports, loading arrangement and Labour.]

m

Add +460.00% with Item No 4.08.02.02.02

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

21738.17

Page: 515 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.08.02.03

Sinking of 8m external diameter well in Soft Rock

4.08.02.03.01

Depth below bed level up to 3.0 m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

0.8600

day

550.00

473.00

Sareng

4.5000

day

570.00

2565.00

Khalashi

15.0000

day

390.00

5850.00

Operator

1.5000

day

570.00

855.00

Hire & running charges of crane with grab bucket of 0.75 cum capacity and accessories.

1.0413

day

12000.00

12495.60

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.7500

day

2500.00

1875.00

5

m Mason

24113.60

Subtotal-A: Consumables in sinking Cost for Dewatering

( +10.00 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2411.36 1205.68 27730.64

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28285.25

10% Profit ( Add 10% on Subtotal-B) :

31113.78

VAT

6% of Total

IT

4% of Total

2074.25 1382.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

34570.86

Page: 516 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.03

Detailed Analysis Brief Description of Item 2 SL: Providing Steel liner 10 mm thick for Curbs and 6 mm thick for Steining of Wells including fabrication and setting out as per detailed drawing, specification and direction of Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT

Corrosion resistant Structural steel

1050.0000

kg

58.00

60900.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2400

day

470.00

582.80

Fitter

6.0000

day

680.00

4080.00

Blacksmith

5.0000

day

450.00

2250.00

Welder Ordinary Labour

5.0000

day

680.00

3400.00

10.0000

day

370.00

3700.00 74912.80

Subtotal-A: Electrodes, gas cutting and other consumables

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3745.64 78658.44

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

80231.61

10% Profit ( Add 10% on Subtotal-B) :

88254.77

VAT

6% of Total

IT

4% of Total

5883.65 3922.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

98060.86

Page: 517 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.08.04

2 SCE: Providing and laying Steel Cutting edge weighing not less than 40 kg per metre for Well foundation including cost & carriage of all materials complete as per drawing, specification and direction of Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Nails/ Nut bolts/ Screw/ Spikes

1050.0000

kg

58.00

20.0000

kg

65.00

1300.00

5.5000

day

680.00

3740.00

Blacksmith

5.5000

day

450.00

2475.00

Welder

5.5000

day

680.00

3740.00

Ordinary Labour

1.3200

day

450.00

594.00

16.5000

day

370.00

6105.00 78854.00

Subtotal-A: Electrodes, gas cutting and other consumables

( +10.00 % on Subtotal-A )

Subtotal-A1:

In well curb

Note : Rates of all items should be inclusive of all supply and carriage.

7885.40 86739.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

88474.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

97321.61

VAT

6% of Total

6488.11

IT

4% of Total

4325.40 Total:

4.08.05.01

60900.00

Fitter

Skilled Labour

PCC/RCC_WF: Plain/ Reinforced Cement Concrete, in Well foundation with coarse aggregates of appropriate nominal size and grading, fine aggregate (sand) conforming to proper grading zone, both of approved quality, cement and water reducing admixtures, as necessary, including labour, cost and carriage of all materials and including preparation of design mix, approval of the same by the Engineer-in-Charge and cost for quality control, sampling, testing etc. all complete as per drawing and technical specification including the cost of necessary form work and staging complete.

8

MT

Corrosion resistant Structural steel

4.08.05

Amount

108135.12

Page: 518 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.01.01

Detailed Analysis Brief Description of Item 2 RCC-17BCCM : Compressive strength, f'c = 17 MPa MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 20mm down well graded crushed picked brick chips (LAA <=38) [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

1.3330

day

370.00

493.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

H.C. of Generator (40 KVA)

0.0600

day

2500.00

150.00 6376.77

Subtotal-A: Formwork

( +20.00 % on Subtotal-A )

Subtotal-A1:

1275.35 7652.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7805.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8585.68

VAT

6% of Total

IT

4% of Total

572.38 381.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9539.65

Page: 519 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.01.02

Detailed Analysis Brief Description of Item 2 RCC-20SCCM : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 2.2 and 20mm down well graded crushed stone chips (LAA <=35), water reducing admixture of complying type A under ASTM C 494 [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 8104.15

Subtotal-A: Formwork

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1620.83 9724.98

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9919.47 10911.42

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

727.43

IT

4% of Total

484.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12123.80

Page: 520 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.01.03

Detailed Analysis Brief Description of Item 2 RCC-20SCBP : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 2.2 and 20mm down well graded crushed stone chips (LAA <=35),, water reducing admixture of complying type A under ASTM C 494 [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 7809.69

Subtotal-A: Formwork

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1561.94 9371.63

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) : 6% of Total

9559.06 10514.97 701.00 Page: 521 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

467.33 Total:

4.08.05.01.04

RCC-25SCCM : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30), high range water reducing admixture of complying type F under ASTM C 494 [Using Concrete Mixture]

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 9079.71

Subtotal-A: Formwork

( +20.00 % on Subtotal-A )

Subtotal-A1:

1815.94 10895.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11113.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12224.92

VAT

6% of Total

IT

4% of Total

814.99 543.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11683.30

13583.24

Page: 522 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.01.05

Detailed Analysis Brief Description of Item 2 RCC-25SCBP : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30), high range water reducing admixture of complying type F under ASTM C 494 [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 8785.25

Subtotal-A: Formwork

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1757.05 10542.30

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10753.15

10% Profit ( Add 10% on Subtotal-B) :

11828.46

VAT

6% of Total

IT

4% of Total

788.56 525.71 Page: 523 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 4.08.05.01.06

RCC-30SCCM : Compressive strength, f'c = 30 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30), high range water reducing admixture of complying type F under ASTM C 494. [Using Concrete Mixture]

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 9713.01

Subtotal-A: Formwork

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1942.60 11655.61

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11888.72

10% Profit ( Add 10% on Subtotal-B) :

13077.59

VAT

6% of Total

IT

4% of Total

871.84 581.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13142.73

14530.66

Page: 524 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.01.07

Detailed Analysis Brief Description of Item 2 RCC-30SCBP : Compressive strength, f'c = 30 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 9418.55

Subtotal-A: Formwork

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1883.71 11302.26

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11528.31

10% Profit ( Add 10% on Subtotal-B) :

12681.14

VAT

6% of Total

IT

4% of Total

845.41 563.61 Page: 525 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 4.08.05.02

In well steining

4.08.05.02.01

RCC-17BCCM : Compressive strength, f'c = 17 MPa MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 20mm down well graded crushed picked brick chips (LAA <=38) [Using Concrete Mixture]

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

1.3330

day

370.00

493.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

H.C. of Generator (40 KVA)

0.0600

day

2500.00

150.00 6376.77

Subtotal-A: Formwork

( +10.00 % on Subtotal-A )

Subtotal-A1:

637.68 7014.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7154.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7870.21

VAT

6% of Total

524.68

IT

4% of Total

349.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14090.15

8744.68

Page: 526 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.02.02

Detailed Analysis Brief Description of Item 2 RCC-20SCCM : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 2.2 and 20mm down well graded crushed stone chips (LAA <=35), water reducing admixture of complying type A under ASTM C 494 [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 8104.15

Subtotal-A: Formwork

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

810.41 8914.56

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9092.85 10002.14

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

666.81

IT

4% of Total

444.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11113.49

Page: 527 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.02.03

Detailed Analysis Brief Description of Item 2 RCC-20SCBP : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 2.2 and 20mm down well graded crushed stone chips (LAA <=35),, water reducing admixture of complying type A under ASTM C 494 [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 7809.69

Subtotal-A: Formwork

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

780.97 8590.66

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8762.47

10% Profit ( Add 10% on Subtotal-B) :

9638.72

6% of Total

642.58 Page: 528 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

428.39 Total:

4.08.05.02.04

RCC-25SCCM : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Concrete Mixture]

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 9079.71

Subtotal-A: Formwork

( +10.00 % on Subtotal-A )

Subtotal-A1:

907.97 9987.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10187.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11206.17

VAT

6% of Total

IT

4% of Total

747.08 498.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10709.69

12451.30

Page: 529 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.02.05

Detailed Analysis Brief Description of Item 2 RCC-25SCBP : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 8785.25

Subtotal-A: Formwork

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

878.53 9663.78

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9857.05 10842.76 722.85 481.90 Page: 530 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 4.08.05.02.06

RCC-30SCCM : Compressive strength, f'c = 30 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Concrete Mixture]

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 9713.01

Subtotal-A: Formwork

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

971.30 10684.31

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10897.99

10% Profit ( Add 10% on Subtotal-B) :

11987.79

VAT

6% of Total

IT

4% of Total

799.19 532.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12047.51

13319.77

Page: 531 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.02.07

Detailed Analysis Brief Description of Item 2 RCC-30SCBP : Compressive strength, f'c = 30 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 9418.55

Subtotal-A: Formwork

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

941.86 10360.41

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10567.61

10% Profit ( Add 10% on Subtotal-B) :

11624.37

VAT

6% of Total

IT

4% of Total

774.96 516.64 Page: 532 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 12915.97

Page: 533 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.02.09

Detailed Analysis Brief Description of Item 2 RCC-35SCBP : Compressive strength, f'c = 35 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.8 and 20mm down well graded crushed stone chips (LAA <=25). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 9915.37

Subtotal-A: Formwork

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

991.54 10906.91

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11125.05

10% Profit ( Add 10% on Subtotal-B) :

12237.55

VAT

6% of Total

IT

4% of Total

815.84 543.89 Page: 534 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.08.05.03

Amount 8 13597.28

In Bottom Plug [Concrete to be placed using tremie pipe, 10% extra cement is included in these unit rates.]

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 535 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.03.01

Detailed Analysis Brief Description of Item 2 PCC-17BCCM : Compressive strength, f'c = 17 MPa MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 40mm down well graded crushed picked brick chips (LAA <=38) [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.6550

bag

430.00

2861.65

1st Class/ Picked Brick chips (40mm down graded)

0.3440

m3

2786.00

958.38

1st Class Picked Brick Chips (20mm down graded)

0.3440

m3

2940.00

1011.36

1st Class Brick Chips (10mm down graded)

0.1720

m3

3049.00

524.43

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Water reducing chemical admixture : Type-A

1.6638

liter

130.00

216.29

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0500

day

4500.00

225.00 6974.54

Subtotal-A: Cost of foming sump, protective bunds, chiselling and making arrangement for under water concreting with tremie pipe.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

348.73

7323.26 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7469.73

10% Profit ( Add 10% on Subtotal-B) :

8216.70

VAT

6% of Total

547.78

IT

4% of Total

365.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9129.67

Page: 536 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.03.02

Detailed Analysis Brief Description of Item 2 PCC-20SCCM : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, water reducing admixture of complying type A under ASTM C 494, sand of minimum FM 2.2 and 38mm down well graded crushed stone chips (LAA <=35). [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.6550

bag

430.00

2861.65

Stone Chips (38mm down graded) [LAA≤35]

0.3440

cum

4850.00

1668.40

Stone Chips (20mm down graded) [LAA≤35]

0.3440

cum

4930.00

1695.92

Stone Chips (12mm down graded) [LAA≤35]

0.1720

cum

4320.00

743.04

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.3310

liter

130.00

173.03

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0500

day

4500.00

225.00 8681.20

Subtotal-A: Cost of foming sump, protective bunds, chiselling and making arrangement for under water concreting with tremie pipe.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

434.06

9115.26 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9297.57 10227.32 681.82 454.55 Page: 537 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 11363.69

Page: 538 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.03.03

Detailed Analysis Brief Description of Item 2 PCC-20SCBP : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, water reducing admixture of complying type A under ASTM C 494, sand of minimum FM 2.2 and 38mm down well graded crushed stone chips (LAA <=35). [Using Batching Plant, Transit Mixer & Crane/ Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.6550

bag

430.00

2861.65

Stone Chips (38mm down graded) [LAA≤35]

0.3440

cum

4850.00

1668.40

Stone Chips (20mm down graded) [LAA≤35]

0.3440

cum

4930.00

1695.92

Stone Chips (12mm down graded) [LAA≤35]

0.1720

cum

4320.00

743.04

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.3310

liter

130.00

173.03

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0073

day

450.00

3.29

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 8160.67

Subtotal-A: Cost of foming sump, protective bunds, chiselling and making arrangement for under water concreting with tremie pipe.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

408.03

8568.70 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8740.07 Page: 539 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

6% of Total

IT

4% of Total

640.94 427.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8 9614.08

10% Profit ( Add 10% on Subtotal-B) :

VAT

Amount

10682.31

Page: 540 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.03.04

Detailed Analysis Brief Description of Item 2 PCC-25SCCM : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 38mm down well graded crushed stone chips (LAA <=30). [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

8.4810

bag

430.00

3646.83

Stone Chips (38mm down graded) [LAA≤30]

0.3280

cum

5230.00

1715.44

Stone Chips (20mm down graded) [LAA≤30]

0.3280

m3

5320.00

1744.96

Stone Chips (12mm down graded) [LAA≤30]

0.1640

m3

4470.00

733.08

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1203

liter

160.00

339.25

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0500

day

4500.00

225.00 9779.88

Subtotal-A: Cost of foming sump, protective bunds, chiselling and making arrangement for under water concreting with tremie pipe.

( +5.00 % on Subtotal-A )

Subtotal-A1:

488.99

10268.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10474.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11521.68

VAT

6% of Total

IT

4% of Total

768.11 512.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12801.86 Page: 541 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.03.05

Detailed Analysis Brief Description of Item 2 PCC-25SCBP : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 38mm down well graded crushed stone chips (LAA <=30). [Using Batching Plant, Transit Mixer & Crane/ Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

8.4810

bag

430.00

3646.83

Stone Chips (38mm down graded) [LAA≤30]

0.3280

cum

5230.00

1715.44

Stone Chips (20mm down graded) [LAA≤30]

0.3280

m3

5320.00

1744.96

Stone Chips (12mm down graded) [LAA≤30]

0.1640

m3

4470.00

733.08

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1203

liter

160.00

339.25

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0073

day

450.00

3.29

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 9259.34

Subtotal-A: Cost of foming sump, protective bunds, chiselling and making arrangement for under water concreting with tremie pipe.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

462.97

9722.31 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

9916.76 10908.43 Page: 542 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

8 727.23 484.82

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12120.48

Page: 543 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.03.06

Detailed Analysis Brief Description of Item 2 RCC-30SCCM : Compressive strength, f'c = 30 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 38mm down well graded crushed stone chips (LAA <=30). [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Portland Cement (CEM I, 52.5N)

9.4600

bag

455.00

4304.30

Stone Chips (38mm down graded) [LAA≤30]

0.3280

cum

5230.00

1715.44

Stone Chips (20mm down graded) [LAA≤30]

0.3280

m3

5320.00

1744.96

Stone Chips (12mm down graded) [LAA≤30]

0.1640

m3

4470.00

733.08

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.3650

liter

160.00

378.40

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0500

day

4500.00

225.00 10475.29

Subtotal-A: Cost of foming sump, protective bunds, chiselling and making arrangement for under water concreting with tremie pipe.

( +5.00 % on Subtotal-A )

Subtotal-A1:

523.76

10999.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11219.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12340.93

VAT

6% of Total

IT

4% of Total

822.73 548.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13712.15 Page: 544 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.03.07

Detailed Analysis Brief Description of Item 2 PCC-30SCBP : Compressive strength, f'c = 35 Mpa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 38mm down well graded crushed stone chips (LAA <=25). [Using Batching Plant, Transit Mixer & Crane/ Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Portland Cement (CEM I, 52.5N)

9.4600

bag

455.00

4304.30

Stone Chips (38mm down graded) [LAA≤30]

0.3280

cum

5230.00

1715.44

Stone Chips (20mm down graded) [LAA≤30]

0.3280

m3

5320.00

1744.96

Stone Chips (12mm down graded) [LAA≤30]

0.1640

m3

4470.00

733.08

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.3650

liter

160.00

378.40

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0073

day

450.00

3.29

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0063

day

10000.00

63.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 9862.97

Subtotal-A: Cost of foming sump, protective bunds, chiselling and making arrangement for under water concreting with tremie pipe.

( +5.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

493.15

10356.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10563.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11619.56 Page: 545 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

8 774.64 516.42

Total: 4.08.05.04

Amount

12910.62

In Intermediate Plug [Concrete to be placed using tremie pipe, 10% extra cement is included in these unit rates.]

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 546 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.04.01

Detailed Analysis Brief Description of Item 2 PCC-17BCCM : Compressive strength, f'c = 17 MPa MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 40mm down well graded crushed picked brick chips (LAA <=38) [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.6550

bag

430.00

2861.65

1st Class/ Picked Brick chips (40mm down graded)

0.3440

m3

2786.00

958.38

1st Class Picked Brick Chips (20mm down graded)

0.3440

m3

2940.00

1011.36

1st Class Brick Chips (10mm down graded)

0.1720

m3

3049.00

524.43

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Water reducing chemical admixture : Type-A

1.6638

liter

130.00

216.29

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0500

day

4500.00

225.00 6974.54

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7114.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7825.43

VAT

6% of Total

521.70

IT

4% of Total

347.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8694.92

Page: 547 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.04.02

Detailed Analysis Brief Description of Item 2 PCC-20SCCM : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, water reducing admixture of complying type A under ASTM C 494, sand of minimum FM 2.2 and 38mm down well graded crushed stone chips (LAA <=35). [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.6550

bag

430.00

2861.65

Stone Chips (38mm down graded) [LAA≤35]

0.3440

cum

4850.00

1668.40

Stone Chips (20mm down graded) [LAA≤35]

0.3440

cum

4930.00

1695.92

Stone Chips (12mm down graded) [LAA≤35]

0.1720

cum

4320.00

743.04

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.3310

liter

130.00

173.03

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0500

day

4500.00

225.00 8681.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8854.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9740.31

VAT

6% of Total

649.35

IT

4% of Total

432.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10822.56

Page: 548 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.04.03

Detailed Analysis Brief Description of Item 2 PCC-20SCBP : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, water reducing admixture of complying type A under ASTM C 494, sand of minimum FM 2.2 and 38mm down well graded crushed stone chips (LAA <=35). [Using Batching Plant, Transit Mixer & Crane/ Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.6550

bag

430.00

2861.65

Stone Chips (38mm down graded) [LAA≤35]

0.3440

cum

4850.00

1668.40

Stone Chips (20mm down graded) [LAA≤35]

0.3440

cum

4930.00

1695.92

Stone Chips (12mm down graded) [LAA≤35]

0.1720

cum

4320.00

743.04

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.3310

liter

130.00

173.03

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0073

day

450.00

3.29

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 8160.67

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8323.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9156.27

VAT

6% of Total

IT

4% of Total

610.42 406.95 Page: 549 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 4.08.05.04.04

PCC-25SCCM : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 38mm down well graded crushed stone chips (LAA <=30). [Using Concrete Mixture]

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

8.4810

bag

430.00

Stone Chips (38mm down graded) [LAA≤30]

0.3280

cum

5230.00

1715.44

Stone Chips (20mm down graded) [LAA≤30]

0.3280

m3

5320.00

1744.96

Stone Chips (12mm down graded) [LAA≤30]

0.1640

m3

4470.00

733.08

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1203

liter

160.00

339.25

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

1.3333

day

370.00

493.32

3646.83

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00

Hire and running charges of light crane for lowering reinforcement cage & operating tremie pipe

0.0500

day

4500.00

225.00 9779.88

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

9975.48 10973.02

10% Profit ( Add 10% on Subtotal-B) :

VAT

731.53 487.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10173.63

12192.25

Page: 550 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.04.05

Detailed Analysis Brief Description of Item 2 PCC-25SCBP : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 38mm down well graded crushed stone chips (LAA <=30). [Using Batching Plant, Transit Mixer & Crane/ Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

8.4810

bag

430.00

3646.83

Stone Chips (38mm down graded) [LAA≤30]

0.3280

cum

5230.00

1715.44

Stone Chips (20mm down graded) [LAA≤30]

0.3280

m3

5320.00

1744.96

Stone Chips (12mm down graded) [LAA≤30]

0.1640

m3

4470.00

733.08

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1203

liter

160.00

339.25

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0073

day

450.00

3.29

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 9259.34

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

9444.53 10388.98

10% Profit ( Add 10% on Subtotal-B) :

VAT

692.60 461.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11543.31 Page: 551 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

4.08.05.05

In Top Plug

4.08.05.05.01

PCC-17BCCM : Compressive strength, f'c = 17 MPa MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 40mm down well graded crushed picked brick chips (LAA <=38) [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class/ Picked Brick chips (40mm down graded)

0.3440

m3

2786.00

958.38

1st Class Picked Brick Chips (20mm down graded)

0.3440

m3

2940.00

1011.36

1st Class Brick Chips (10mm down graded)

0.1720

m3

3049.00

524.43

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 6271.88

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6397.32

10% Profit ( Add 10% on Subtotal-B) :

7037.05

VAT

6% of Total

IT

4% of Total

469.14 312.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7818.94

Page: 552 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.05.02

Detailed Analysis Brief Description of Item 2 PCC-20SCCM : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, water reducing admixture of complying type A under ASTM C 494, sand of minimum FM 2.2 and 38mm down well graded crushed stone chips (LAA <=35). [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (38mm down graded) [LAA≤35]

0.3440

cum

4850.00

1668.40

Stone Chips (20mm down graded) [LAA≤35]

0.3440

cum

4930.00

1695.92

Stone Chips (12mm down graded) [LAA≤35]

0.1720

cum

4320.00

743.04

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 8021.81

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8182.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9000.47

VAT

6% of Total

600.03

IT

4% of Total

400.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10000.52

Page: 553 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.05.03

Detailed Analysis Brief Description of Item 2 PCC-20SCBP : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, water reducing admixture of complying type A under ASTM C 494, sand of minimum FM 2.2 and 38mm down well graded crushed stone chips (LAA <=35). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (38mm down graded) [LAA≤35]

0.3440

cum

4850.00

1668.40

Stone Chips (20mm down graded) [LAA≤35]

0.3440

cum

4930.00

1695.92

Stone Chips (12mm down graded) [LAA≤35]

0.1720

cum

4320.00

743.04

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 7727.35

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7881.90

10% Profit ( Add 10% on Subtotal-B) :

8670.09

VAT

6% of Total

IT

4% of Total

578.01 385.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9633.43 Page: 554 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.05.04

Detailed Analysis Brief Description of Item 2 PCC-25SCCM : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 38mm down well graded crushed stone chips (LAA <=30). [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (38mm down graded) [LAA≤30]

0.3280

cum

5230.00

1715.44

Stone Chips (20mm down graded) [LAA≤30]

0.3280

m3

5320.00

1744.96

Stone Chips (12mm down graded) [LAA≤30]

0.1640

m3

4470.00

733.08

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 9191.29

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9375.11 10312.62

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

687.51

IT

4% of Total

458.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11458.47

Page: 555 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.05.05

Detailed Analysis Brief Description of Item 2 PCC-25SCBP : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 38mm down well graded crushed stone chips (LAA <=30). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (38mm down graded) [LAA≤30]

0.3280

cum

5230.00

1715.44

Stone Chips (20mm down graded) [LAA≤30]

0.3280

m3

5320.00

1744.96

Stone Chips (12mm down graded) [LAA≤30]

0.1640

m3

4470.00

733.08

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 8896.83

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9074.77

10% Profit ( Add 10% on Subtotal-B) :

9982.24

VAT

6% of Total

IT

4% of Total

665.48 443.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11091.38 Page: 556 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

4.08.05.06

In well cap

4.08.05.06.01

RCC-17BCCM : Compressive strength, f'c = 17 MPa MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 20mm down well graded crushed picked brick chips (LAA <=38) [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 6343.17

Subtotal-A: Formwork

( +4.00 % on Subtotal-A )

Subtotal-A1:

253.73 6596.89

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6728.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7401.71

VAT

6% of Total

IT

4% of Total

493.45 328.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8224.13

Page: 557 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.06.02

Detailed Analysis Brief Description of Item 2 RCC-20SCCM : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 2.2 and 20mm down well graded crushed stone chips (LAA <=35), water reducing admixture of complying type A under ASTM C 494 [Using Concrete Mixture]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 8104.15

Subtotal-A: Formwork

( +3.75 % on Subtotal-A )

Subtotal-A1:

303.91 8408.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8576.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9433.83

VAT

6% of Total

628.92

IT

4% of Total

419.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10482.04

Page: 558 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.06.03

Detailed Analysis Brief Description of Item 2 RCC-20SCBP : Compressive strength, f'c = 20 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, sand of minimum FM 2.2 and 20mm down well graded crushed stone chips (LAA <=35),, water reducing admixture of complying type A under ASTM C 494 [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 7809.69

Subtotal-A: Formwork

( +3.75 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

292.86 8102.55

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8264.60

10% Profit ( Add 10% on Subtotal-B) :

9091.06

6% of Total

606.07 Page: 559 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

404.05 Total:

4.08.05.06.04

RCC-25SCCM : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Concrete Mixture]

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 9079.71

Subtotal-A: Formwork

( +3.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

317.79 9397.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9585.45 10543.99 702.93 468.62

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10101.18

11715.54

Page: 560 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.06.05

Detailed Analysis Brief Description of Item 2 RCC-25SCBP : Compressive strength, f'c = 25 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEMII/A-L/M/V/W 42.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 8785.25

Subtotal-A: Formwork

( +3.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

307.48 9092.73

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9274.59 10202.05 680.14 453.42 Page: 561 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 4.08.05.06.06

RCC-30SCCM : Compressive strength, f'c = 30 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Concrete Mixture]

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.0573

day

450.00

25.79

Ordinary Labour

1.3333

day

370.00

493.32

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0500

day

1200.00

60.00

H.C. of Generator (40 KVA)

0.0500

day

2500.00

125.00 9713.01

Subtotal-A: Formwork

( +3.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

291.39 10004.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10204.48

10% Profit ( Add 10% on Subtotal-B) :

11224.93

VAT

6% of Total

IT

4% of Total

748.33 498.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11335.61

12472.15

Page: 562 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.06.07

Detailed Analysis Brief Description of Item 2 RCC-30SCBP : Compressive strength, f'c = 30 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.5 and 20mm down well graded crushed stone chips (LAA <=30). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 9418.55

Subtotal-A: Formwork

( +3.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

282.56 9701.11

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9895.13 10884.64 725.64 483.76 Page: 563 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 12094.05

Page: 564 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.08.05.06.08

Detailed Analysis Brief Description of Item 2 RCC-35SCBP : Compressive strength, f'c = 35 MPa at 28 days on standard cylinders, cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N, high range water reducing admixture of complying type F under ASTM C 494, sand of minimum FM 2.8 and 20mm down well graded crushed stone chips (LAA <=25). [Using Batching Plant, Transit Mixer & Concrete Pump]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0070

day

450.00

3.15

Ordinary Labour

0.1500

day

370.00

55.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0156

day

10000.00

156.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50 9915.37

Subtotal-A: Formwork

( +3.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

297.46 10212.83

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10417.09

10% Profit ( Add 10% on Subtotal-B) :

11458.80

VAT

6% of Total

IT

4% of Total

763.92 509.28 Page: 565 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 4.08.06

Brick work with 1st class brick in specified cement mortar in staining of wells with sand of minimum FM 1.50 and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, cutting bricks to required sizes, cleaning and soaking bricks at least for 24 hours before use, hoisting and keeping in position the MS bond rods and finished with flush pointing joints, watering, etc. complete including cost of all materials but excluding cost of MS bond rods and bottle nuts, etc. all complete as per direction of the E-I-C.

4.08.06.01

Cement mortar (1:3)

cum 1st Class Brick

406.0000

each

9.00

3654.00

Sand (FM - 1.5)

0.3800

m3

795.00

302.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.8600

bag

430.00

1229.80

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 6294.90

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6420.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7062.88

VAT

6% of Total

IT

4% of Total

470.86 313.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12732.00

7847.64

Page: 566 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.08.06.02

2 Cement mortar (1:4)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum 1st Class Brick

406.0000

each

9.00

3654.00

Sand (FM - 1.5)

0.3800

m3

795.00

302.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.1200

bag

430.00

911.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 5976.70

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6096.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6705.86

VAT

6% of Total

IT

4% of Total

447.06 298.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7450.95

Page: 567 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-17BCCM: Reinforced cement concrete work with minimum cement content relates to nominal mix ratio 1:2:4 and maximum water cement ratio 0.45 having minimum required average strength, f'cr = 24 MPa and satisfying a compressive strength f'c = 17 MPa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, sand of minimum FM 1.8 and 20mm down well graded crushed picked brick chips (LAA value & maximum water absorption not exceeding 38 & 15% respectively ) conforming to garadation requirement as per ASTM C 33 including screening chips through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in standard mixture machine with hoper, fed by standard measuring boxes, maintaining allowable slump of 50mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling, placing, binding etc. is not included in this unit rate. Additional quantity of cement to be added if required to attain the specified strength at the contractor's own cost. Note: Using Concrete Mixer

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 568 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.01.01

Detailed Analysis Brief Description of Item 2 For pile caps, abutment base of bridges and bottom slab of box culverts

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7040.56

Subtotal-A: Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

633.65 7674.21

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7827.69

10% Profit ( Add 10% on Subtotal-B) :

8610.46

VAT

6% of Total

IT

4% of Total

574.03 382.69 Total:

4.09.01.02

Amount

9567.18

For diaphragm walls, wing walls, piers, columns, pier caps, abutments of bridges and vertical members of box culverts

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 569 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.01.02.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7040.56

Formwork

( +14.00 % on Subtotal-A )

Subtotal-A1:

4.09.01.03

For solid slab type super-structure including cantilever, side walk, curb, wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

cum

985.68 8026.24

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8186.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9005.44

VAT

6% of Total

IT

4% of Total

600.36 400.24 Total:

For height above 5m

8

cum

Subtotal-A:

4.09.01.02.02

Amount

10006.04

Add +25.00% with Item No 4.09.01.02.01

Page: 570 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.01.03.01

2 For height Up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7040.56

Formwork/ shuttering, prop with necessary supports etc.

( +40.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.09.01.04

For T-girder & slab type super-structure including cross girders, side walk, curb, wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2816.22 9856.78

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10053.92

10% Profit ( Add 10% on Subtotal-B) :

11059.31

VAT

6% of Total

IT

4% of Total

737.29 491.52 Total:

For height above 5m

8

cum

Subtotal-A:

4.09.01.03.02

Amount

12288.12

Add +12.50% with Item No 4.09.01.03.01

Page: 571 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.01.04.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7262.06

Formwork/ shuttering, prop with necessary supports etc.

( +45.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.09.01.05

For top slab including curb and wheel guard of box culvert

Note : Rates of all items should be inclusive of all supply and carriage.

cum

3267.93 10529.99

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10740.59

10% Profit ( Add 10% on Subtotal-B) :

11814.65

VAT

6% of Total

IT

4% of Total

787.64 525.10 Total:

For height above 5m

8

cum

Subtotal-A:

4.09.01.04.02

Amount

13127.38

Add +13.75% with Item No 4.09.01.04.01

Page: 572 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.01.05.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7040.56

Formwork/ shuttering, prop with necessary supports etc.

( +28.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.09.01.06

For cast-in-situ/ pre-cast railing and rail post of bridges and box culverts

Note : Rates of all items should be inclusive of all supply and carriage.

cum

1971.36 9011.92

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

9192.16 10111.37

10% Profit ( Add 10% on Subtotal-B) :

VAT

674.09 449.39 Total:

For height above 5m

8

cum

Subtotal-A:

4.09.01.05.02

Amount

11234.86

Add +6.00% with Item No 4.09.01.05.01

Page: 573 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.01.06.01

2 For pre-cast railing and rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7262.06

Subtotal-A: Formwork/ shuttering, prop with necessary supports etc.

( +29.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2106.00 9368.06

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

9555.42 10510.96

10% Profit ( Add 10% on Subtotal-B) :

VAT

700.73 467.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11678.84

Page: 574 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.01.06.02

Detailed Analysis Brief Description of Item 2 For cast-in-situ railing and rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 7262.06

Subtotal-A: Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1016.69 8278.75

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8444.32

10% Profit ( Add 10% on Subtotal-B) :

9288.76

VAT

6% of Total

IT

4% of Total

619.25 412.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10320.84

Page: 575 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-20SCCM: Reinforced cement concrete work with minimum cement content relates to nominal mix ratio 1:2:4 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 28.5 MPa and satisfying a compressive strength f'c = 20 MPa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.2 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 35) conforming to ASTM C33 including screening chips through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in standard mixture machine with hoper, fed by standard measuring boxes, maintaining allowable slump of 75mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling, placing, binding etc. is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost. Note: Using Concrete Mixer

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 576 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.02.01

Detailed Analysis Brief Description of Item 2 For pile caps, abutment base of bridges and bottom slab of Box Culvert

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤25]

0.3400

cum

4640.00

1577.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8910.34

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

801.93 9712.27

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9906.52 10897.17

VAT

6% of Total

726.48

IT

4% of Total

484.32 Total:

4.09.02.02

Amount

12107.96

For diaphragm walls, wing walls, piers, columns, abutments of bridges and vertical members of box culverts

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 577 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.02.02.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8801.54

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

1232.22 10033.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10234.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11257.87

VAT

6% of Total

750.52

IT

4% of Total

500.35 Total:

4.09.02.02.02

For height above 5m to 10m

cum

Add +25.00% with Item No 4.09.02.02.01

4.09.02.02.03

For height above 10m to 15m

cum

Add +50.00% with Item No 4.09.02.02.01

4.09.02.02.04

For height above 15m to 20m

cum

Add +75.00% with Item No 4.09.02.02.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12508.75

Page: 578 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.09.02.02.05

For height above 20m

4.09.02.03

For solid slab type super-structure including cantilever, side walk, curb, wheel guard of bridges

4.09.02.03.01

For height up to 5m

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

8

Add +80.00% with Item No 4.09.02.02.01

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8801.54

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +40.00 % on Subtotal-A )

Subtotal-A1:

3520.62 12322.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12568.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13825.46

VAT

6% of Total

IT

4% of Total

921.70 614.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15361.62

Page: 579 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.09.02.03.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.02.03.01

4.09.02.03.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.02.03.01

4.09.02.03.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.02.03.01

4.09.02.03.05

For height above 20m

cum

Add +40.00% with Item No 4.09.02.03.01

4.09.02.04

For T-girder & slab type super-structure including cross girders, side walk, curb, wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 580 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.02.04.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9023.04

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +45.00 % on Subtotal-A )

Subtotal-A1:

4060.37 13083.41

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13345.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14679.58

VAT

6% of Total

978.64

IT

4% of Total

652.43 Total:

4.09.02.04.02

For height above 5m to 10m

cum

Add +13.75% with Item No 4.09.02.04.01

4.09.02.04.03

For height above 10m to 15m

cum

Add +27.50% with Item No 4.09.02.04.01

4.09.02.04.04

For height above 15m to 20m

cum

Add +41.25% with Item No 4.09.02.04.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16310.65

Page: 581 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.09.02.04.05

For height above 20m

4.09.02.05

For top slab including curb and wheel guard of box culvert

4.09.02.05.01

For height up to 5m

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8801.54

Steel Formwork/ shuttering, prop with necessary supports etc.

( +28.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2464.43 11265.97

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11491.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12640.42

VAT

6% of Total

842.69

IT

4% of Total

561.80 Total:

For height above 5m

8

Add +44.00% with Item No 4.09.02.04.01

Subtotal-A:

4.09.02.05.02

Amount

14044.91

Add +6.00% with Item No 4.09.02.05.01 Page: 582 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.09.02.06

For cast-in-situ/ pre-cast railing & rail post of bridges and box culverts

4.09.02.06.01

For pre-cast railing & rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (12mm down graded) [LAA≤35]

0.8600

cum

4320.00

3715.20

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8705.84

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +29.00 % on Subtotal-A )

Subtotal-A1:

2524.69 11230.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11455.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12600.66

VAT

6% of Total

IT

4% of Total

840.04 560.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14000.73

Page: 583 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.02.06.02

Detailed Analysis Brief Description of Item 2 For cast-in-situ railing & rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (12mm down graded) [LAA≤35]

0.8600

cum

4320.00

3715.20

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8705.84

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

1218.82 9924.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10123.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11135.47

VAT

6% of Total

742.36

IT

4% of Total

494.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

12372.74

Page: 584 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.03

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-25SCCM: Reinforced cement concrete work with minimum cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 33.5 MPa and satisfying a compressive strength f'c = 25 MPa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C33 including breaking chips, screening through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in standard mixture machine with hoper, maintaining allowable slump of 75mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling, placing, binding etc. is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost. Note: Using Concrete Mixer

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 585 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.03.01

Detailed Analysis Brief Description of Item 2 For pile caps, abutment base, facing elements of Reinforced/ Mechanically Stabilized Earth Structure, bottom slab of Box Culvert etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9777.10

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

879.94 10657.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10870.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11957.20

VAT

6% of Total

IT

4% of Total

797.15 531.43 Total:

4.09.03.02

Amount

13285.78

For diaphragm walls, wing walls, piers, columns, projected pile cap above water level, pier caps, abutments of bridges and vertical members of box culverts

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 586 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.03.02.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9777.10

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

1368.79 11145.89

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11368.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12505.69

VAT

6% of Total

833.71

IT

4% of Total

555.81 Total:

4.09.03.02.02

For height above 5m to 10m

cum

Add +25.00% with Item No 4.09.03.02.01

4.09.03.02.03

For height above 10m to 15m

cum

Add +50.00% with Item No 4.09.03.02.01

4.09.03.02.04

For height above 15m to 20m

cum

Add +75.00% with Item No 4.09.03.02.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13895.21

Page: 587 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.09.03.02.05

For height above 20m

4.09.03.03

For solid slab type super-structure including cantilever, side walk, curb and wheel guard of bridges

4.09.03.03.01

For height up to 5 m

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9777.10

Steel Formwork/ shuttering, prop with necessary supports etc.

( +55.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

5377.41 15154.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15457.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17003.35

VAT

6% of Total

1133.56

IT

4% of Total

755.70 Total:

For height above 5m to 10m

8

Add +80.00% with Item No 4.09.03.02.01

Subtotal-A:

4.09.03.03.02

Amount

18892.62

Add +11.00% with Item No 4.09.03.03.01 Page: 588 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.09.03.03.03

For height above 10m to 15m

cum

Add +22.00% with Item No 4.09.03.03.01

4.09.03.03.04

For height above 15 m to 20 m

cum

Add +33.00% with Item No 4.09.03.03.01

4.09.03.03.05

For height above 20m

cum

Add +44.00% with Item No 4.09.03.03.01

4.09.03.04

For T-girder & slab type super-structure including cross girders, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 589 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.09.03.04.01

2 Height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9998.60

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

5999.16 15997.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16317.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17949.49

VAT

6% of Total

1196.63

IT

4% of Total

797.75 Total:

4.09.03.04.02

For height above 5m to 10m

cum

Add +7.50% with Item No 4.09.03.04.01

4.09.03.04.03

For height above 10m to 15m

cum

Add +15.00% with Item No 4.09.03.04.01

4.09.03.04.04

For height above 15m to 20m

cum

Add +22.50% with Item No 4.09.03.04.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19943.87

Page: 590 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

4.09.03.04.05

For height above 20m

4.09.03.05

For top slab including curb and wheel guard of box culvert

4.09.03.05.01

Height up to 5 m

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9777.10

Steel Formwork/ shuttering, prop with necessary supports etc.

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2933.13 12710.23

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12964.43

10% Profit ( Add 10% on Subtotal-B) :

14260.88

VAT

6% of Total

950.73

IT

4% of Total

633.82 Total:

For height above 5m

8

Add +30.00% with Item No 4.09.03.04.01

Subtotal-A:

4.09.03.05.02

Amount

15845.42

Add +6.00% with Item No 4.09.03.05.01

Page: 591 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.09.03.06

For Arch/ inclined girder of bridges

4.09.03.06.01

For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10163.60

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +65.00 % on Subtotal-A )

Subtotal-A1:

6606.34 16769.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17105.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18815.87

VAT

6% of Total

IT

4% of Total

1254.39 836.26 Total:

4.09.03.06.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.03.06.01

4.09.03.06.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.03.06.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

20906.53

Page: 592 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.09.03.06.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.03.06.01

4.09.03.06.05

For height above 20m

cum

Add +40.00% with Item No 4.09.03.06.01

4.09.03.07

For RCC deck slab/Cross girder/diaphragm supported on PSC Girder using suspended type staging/ centering and shuttering for any height

cum

Quantity 5

Unit

Rate

6

7

8

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9777.10

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

5866.26 15643.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15956.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17551.85

VAT

6% of Total

1170.12

IT

4% of Total

780.08 Total:

4.09.03.08

Amount

19502.06

For cast-in-situ/ pre-cast railing and rail post of bridges & culverts

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 593 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.03.08.01

2 For pre-cast railing and rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (12mm down graded) [LAA≤30]

0.8200

m3

4470.00

3665.40

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9582.10

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +29.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2778.81 12360.91

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12608.13

10% Profit ( Add 10% on Subtotal-B) :

13868.94

VAT

6% of Total

IT

4% of Total

924.60 616.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15409.93

Page: 594 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.03.08.02

Detailed Analysis Brief Description of Item 2 For cast-in-situ railing and rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (12mm down graded) [LAA≤30]

0.8200

m3

4470.00

3665.40

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9582.10

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1341.49 10923.59

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11142.07

10% Profit ( Add 10% on Subtotal-B) :

12256.27

VAT

6% of Total

IT

4% of Total

817.08 544.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13618.08

Page: 595 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.03.09

Detailed Analysis Brief Description of Item 2 For Pre-cast paving slab for bridge footpath

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9777.10

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

879.94 10657.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10870.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11957.20

VAT

6% of Total

797.15

IT

4% of Total

531.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13285.78

Page: 596 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.04

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-25SCBP: Reinforced cement concrete work with minimum cement content relates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 33.5 MPa and satisfying a compressive strength f'c = 25 MPa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C33 including breaking chips, screening through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in mechanized batch mix plant and pumping using line pump or boom placer, maintaining allowable slump of 75mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling, placing, binding etc. is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 597 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.04.01

Detailed Analysis Brief Description of Item 2 For pile caps, abutment base, facing elements of Reinforced/ Mechanically Stabilized Earth Structure, bottom slab of Box Culvert etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9843.85

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

885.95 10729.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10944.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12038.83

VAT

6% of Total

IT

4% of Total

802.59 535.06 Page: 598 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.04.02

Amount 8 13376.48

For diaphragm walls, wing walls, piers, columns, projected pile cap above water level, pier caps, abutments of bridges and vertical members of box culverts

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 599 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.04.02.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9843.85

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1378.14 11221.99

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11446.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12591.07

VAT

6% of Total

IT

4% of Total

839.40 559.60

Page: 600 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.04.02.02

For height above 5m to 10m

cum

Add +25.00% with Item No 4.09.04.02.01

4.09.04.02.03

For height above 10m to 15m

cum

Add +50.00% with Item No 4.09.04.02.01

4.09.04.02.04

For height above 15m to 20m

cum

Add +75.00% with Item No 4.09.04.02.01

4.09.04.02.05

For height above 20m

cum

Add +80.00% with Item No 4.09.04.02.01

4.09.04.03

For solid slab type super-structure including cantilever, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 13990.08

Page: 601 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.04.03.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9843.85

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +55.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5414.12 15257.97

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15563.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17119.44

VAT

6% of Total

IT

4% of Total

1141.30 760.86

Page: 602 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.04.03.02

For height above 5m to 10m

cum

Add +11.00% with Item No 4.09.04.03.01

4.09.04.03.03

For height above 10m to 15m

cum

Add +22.00% with Item No 4.09.04.03.01

4.09.04.03.04

For height above 15m to 20m

cum

Add +33.00% with Item No 4.09.04.03.01

4.09.04.03.05

For height above 20m

cum

Add +44.00% with Item No 4.09.04.03.01

4.09.04.04

For T-girder & slab type super-structure including cross girders, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 19021.60

Page: 603 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.04.04.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10065.35

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6039.21 16104.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16426.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18069.32

VAT

6% of Total

IT

4% of Total

1204.62 803.08

Page: 604 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.04.04.02

For height above 5m to 10m

cum

Add +7.50% with Item No 4.09.04.04.01

4.09.04.04.03

For height above 10m to 15m

cum

Add +15.00% with Item No 4.09.04.04.01

4.09.04.04.04

For height above 15m to 20m

cum

Add +22.50% with Item No 4.09.04.04.01

4.09.04.04.05

For height above 20m

cum

Add +30.00% with Item No 4.09.04.04.01

4.09.04.05

For top slab including curb and wheel guard of box culvert

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 20077.02

Page: 605 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.04.05.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9843.85

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +30.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2953.16 12797.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13052.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14358.24

VAT

6% of Total

IT

4% of Total

957.22 638.14

Page: 606 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.04.05.02

For height above 5m

4.09.04.06

For Arch/ inclined girder of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

cum

Amount 8 15953.60

Add +6.00% with Item No 4.09.04.05.01

Page: 607 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.04.06.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10230.35

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +65.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6649.73 16880.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17217.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18939.45

VAT

6% of Total

IT

4% of Total

1262.63 841.75

Page: 608 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.04.06.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.04.06.01

4.09.04.06.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.04.06.01

4.09.04.06.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.04.06.01

4.09.04.06.05

For height above 20m

cum

Add +40.00% with Item No 4.09.04.06.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 21043.83

Page: 609 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.04.07

Detailed Analysis Brief Description of Item 2 For RCC deck slab/Cross girder/diaphragm supported on PSC Girder using suspended type staging/ centering and shuttering for any height

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9843.85

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5906.31 15750.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16065.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17671.68

VAT

6% of Total

IT

4% of Total

1178.11 785.41 Page: 610 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.04.08

Amount 8 19635.20

For cast-in-situ/ pre-cast railing and rail post of bridges & culverts

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 611 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.04.08.01

2 For pre-cast railing and rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (12mm down graded) [LAA≤30]

0.8200

m3

4470.00

3665.40

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9648.85

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +29.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2798.17 12447.02

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12695.96

10% Profit ( Add 10% on Subtotal-B) :

13965.55

VAT

6% of Total

931.04

IT

4% of Total

620.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

15517.28

Page: 612 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.04.08.02

Detailed Analysis Brief Description of Item 2 For cast-in-situ railing and rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (12mm down graded) [LAA≤30]

0.8200

m3

4470.00

3665.40

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9648.85

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1350.84 10999.69

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11219.68

10% Profit ( Add 10% on Subtotal-B) :

12341.65

VAT

6% of Total

822.78

IT

4% of Total

548.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13712.95

Page: 613 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.04.09

Detailed Analysis Brief Description of Item 2 For Pre-cast paving slab for bridge footpath

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

1.9275

liter

160.00

308.40

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9843.85

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

885.95 10729.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10944.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12038.83

VAT

6% of Total

IT

4% of Total

802.59 535.06

Page: 614 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.05

Amount 8 13376.48

RCC-30SCCM: Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average strength, f'cr = 38.5 MPa and satisfying a compressive strength f'c = 30 MPa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C33 including breaking chips, screening through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in standard mixture machine with hoper, maintaining allowable slump of 100mm to 150mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling, placing, binding etc. is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by the concerned District Quality Control Laboratory or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Concrete Mixer

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 615 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.05.01

Detailed Analysis Brief Description of Item 2 For foundation of Pier & Abutment of Bridges and Box Culverts

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10410.40

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

936.94 11347.34

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11574.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12731.71

VAT

6% of Total

848.78

IT

4% of Total

565.85 Total:

4.09.05.02

Amount

14146.35

For diaphragm walls, wing walls, piers, columns, projected pile cap above water level, pier caps, abutments of bridges and vertical members of box culverts

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 616 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.05.02.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10410.40

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

1457.46 11867.86

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12105.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13315.73

VAT

6% of Total

887.72

IT

4% of Total

591.81 Total:

4.09.05.02.02

For height above 5m to 10m

cum

Add +25.00% with Item No 4.09.05.02.01

4.09.05.02.03

For height above 10m to 15m

cum

Add +50.00% with Item No 4.09.05.02.01

4.09.05.02.04

For height above 15m to 20m

cum

Add +75.00% with Item No 4.09.05.02.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14795.26

Page: 617 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.09.05.02.05

For height above 20m

4.09.05.03

For solid slab type super-structure including cantilever, side walk, curb and wheel guard of bridges

4.09.05.03.01

For height up to 5m

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10410.40

Steel Formwork/ shuttering, prop with necessary supports etc.

( +55.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

5725.72 16136.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16458.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18104.73

VAT

6% of Total

1206.98

IT

4% of Total

804.65 Total:

For height above 5m to 10m

8

Add +80.00% with Item No 4.09.05.02.01

Subtotal-A:

4.09.05.03.02

Amount

20116.36

Add +11.00% with Item No 4.09.05.03.01 Page: 618 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.09.05.03.03

For height above 10m to 15m

cum

Add +22.00% with Item No 4.09.05.03.01

4.09.05.03.04

For height above 15m to 20m

cum

Add +33.00% with Item No 4.09.05.03.01

4.09.05.03.05

For height above 20m

cum

Add +44.00% with Item No 4.09.05.03.01

4.09.05.04

For T-girder & slab type super-structure including cross girders, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 619 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.05.04.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10631.90

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

6379.14 17011.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17351.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19086.39

VAT

6% of Total

1272.43

IT

4% of Total

848.28 Total:

4.09.05.04.02

For height above 5m to 10m

cum

Add +7.50% with Item No 4.09.05.04.01

4.09.05.04.03

For height above 10m to 15m

cum

Add +15.00% with Item No 4.09.05.04.01

4.09.05.04.04

For height above 15m to 20m

cum

Add +22.50% with Item No 4.09.05.04.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

21207.10

Page: 620 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.09.05.04.05

For height above 20m

4.09.05.05

For top slab including curb and wheel guard of box culvert

4.09.05.05.01

For height up to 5m

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10410.40

Steel Formwork/ shuttering, prop with necessary supports etc.

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

3123.12 13533.52

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13804.19

10% Profit ( Add 10% on Subtotal-B) :

15184.61

VAT

6% of Total

1012.31

IT

4% of Total

674.87 Total:

For height above 5m

8

Add +30.00% with Item No 4.09.05.04.01

Subtotal-A:

4.09.05.05.02

Amount

16871.79

Add +6.00% with Item No 4.09.05.05.01

Page: 621 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.09.05.06

For Arch/ inclined girder of bridges

4.09.05.06.01

For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10684.40

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +65.00 % on Subtotal-A )

Subtotal-A1:

6944.86 17629.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17981.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19780.03

VAT

6% of Total

IT

4% of Total

1318.67 879.11 Total:

4.09.05.06.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.05.06.01

4.09.05.06.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.05.06.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

21977.81

Page: 622 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.09.05.06.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.05.06.01

4.09.05.06.05

For height above 20m

cum

Add +40.00% with Item No 4.09.05.06.01

4.09.05.07

For RCC deck slab/Cross girder/diaphragm supported on PSC Girder using suspended type staging/ centering and shuttering for any height

cum

Quantity 5

Unit

Rate

6

7

8

Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10410.40

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

6246.24 16656.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16989.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18688.75

VAT

6% of Total

1245.92

IT

4% of Total

830.61 Total:

4.09.05.08

Amount

20765.28

For cast-in-situ/ pre-cast railing and rail post of bridges & box culverts

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 623 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.05.08.01

2 For pre-cast railing and rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (12mm down graded) [LAA≤30]

0.8200

m3

4470.00

3665.40

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10215.40

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +29.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2962.47 13177.87

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13441.42

10% Profit ( Add 10% on Subtotal-B) :

14785.57

VAT

6% of Total

IT

4% of Total

985.70 657.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16428.41

Page: 624 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.05.08.02

Detailed Analysis Brief Description of Item 2 For cast-in-situ railing and rail post

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (12mm down graded) [LAA≤30]

0.8200

m3

4470.00

3665.40

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.2500

day

370.00

832.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10215.40

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1430.16 11645.56

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11878.47

10% Profit ( Add 10% on Subtotal-B) :

13066.31

VAT

6% of Total

IT

4% of Total

871.09 580.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14518.13

Page: 625 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.05.09

Detailed Analysis Brief Description of Item 2 For Pre-cast paving slab for bridge footpath

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10410.40

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

936.94 11347.34

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11574.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12731.71

VAT

6% of Total

848.78

IT

4% of Total

565.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14146.35

Page: 626 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.06

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-30SCBP: Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 38.5 MPa and satisfying a specified compressive strength, f'c = 30 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.50 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C 33 including breaking chips, screening through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in mechanized batch mix plant, pumping using line pump or boom placer, maintaining allowable slump of 100mm to 150mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, placing, binding etc. is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by the concerned District Quality Control Laboratory or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 627 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.06.01

Detailed Analysis Brief Description of Item 2 For foundation of Pier & Abutment of Bridges and Facing Elements of Reinforced/ Mechanically Stabilized Earth Structure

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10477.15

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

942.94 11420.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11648.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12813.34

VAT

6% of Total

IT

4% of Total

854.22 569.48 Page: 628 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.06.02

Amount 8 14237.05

For diaphragm walls, wing walls, piers, columns, projected pile cap above water level, pier caps, abutments of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 629 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.06.02.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10477.15

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1466.80 11943.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12182.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13401.11

VAT

6% of Total

IT

4% of Total

893.41 595.61

Page: 630 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.06.02.02

For height above 5m to 10m

cum

Add +25.00% with Item No 4.09.06.02.01

4.09.06.02.03

For height above 10m to 15m

cum

Add +50.00% with Item No 4.09.06.02.01

4.09.06.02.04

For height above 15m to 20m

cum

Add +75.00% with Item No 4.09.06.02.01

4.09.06.02.05

For height above 20m

cum

Add +80.00% with Item No 4.09.06.02.01

4.09.06.03

For solid slab type super-structure including cantilever, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 14890.13

Page: 631 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.06.03.01

2 For Height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10477.15

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +55.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5762.43 16239.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16564.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18220.81

VAT

6% of Total

IT

4% of Total

1214.72 809.81

Page: 632 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.06.03.02

For height above 5m to 10m

cum

Add +10.00% with Item No 4.09.06.03.01

4.09.06.03.03

For height above 10m to 15m

cum

Add +20.00% with Item No 4.09.06.03.01

4.09.06.03.04

For height above 15m to 20m

cum

Add +30.00% with Item No 4.09.06.03.01

4.09.06.03.05

For height above 20m

cum

Add +40.00% with Item No 4.09.06.03.01

4.09.06.04

For T-girder & slab type super-structure including cross girders, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 20245.35

Page: 633 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.06.04.01

2 For Height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10698.65

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6419.19 17117.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17460.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19206.22

VAT

6% of Total

IT

4% of Total

1280.41 853.61

Page: 634 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.06.04.02

For height above 5m to 10m

cum

Add +6.50% with Item No 4.09.06.04.01

4.09.06.04.03

For height above 10m to 15m

cum

Add +13.00% with Item No 4.09.06.04.01

4.09.06.04.04

For height above 15m to 20m

cum

Add +19.50% with Item No 4.09.06.04.01

4.09.06.04.05

For height above 20m

cum

Add +26.00% with Item No 4.09.06.04.01

4.09.06.05

For top slab including curb and wheel guard of box culvert

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 21340.24

Page: 635 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.06.05.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10477.15

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +30.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3143.15 13620.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13892.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15281.97

VAT

6% of Total

IT

4% of Total

1018.80 679.20

Page: 636 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.06.05.02

For height above 5m

4.09.06.06

For Arch/ inclined girder of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

cum

Amount 8 16979.97

Add +5.50% with Item No 4.09.06.05.01

Page: 637 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.06.06.01

2 For Height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10863.65

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +62.50 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6789.78 17653.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18006.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19807.15

VAT

6% of Total

IT

4% of Total

1320.48 880.32

Page: 638 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.06.06.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.06.06.01

4.09.06.06.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.06.06.01

4.09.06.06.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.06.06.01

4.09.06.06.05

For height above 20m

cum

Add +40.00% with Item No 4.09.06.06.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 22007.94

Page: 639 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.06.07

Detailed Analysis Brief Description of Item 2 For RCC deck slab/Cross girder/diaphragm supported on PSC Girder using suspended type staging/ centering and shuttering for any height

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10477.15

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6286.29 16763.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17098.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18808.58

VAT

6% of Total

IT

4% of Total

1253.91 835.94 Page: 640 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.06.08

Amount 8 20898.42

For Box Girder and Balanced Cantilever

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 641 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.06.08.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.6000

bag

455.00

3913.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10863.65

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +65.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7061.37 17925.02

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18283.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20111.88

VAT

6% of Total

IT

4% of Total

1340.79 893.86

Page: 642 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.06.08.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.06.08.01

4.09.06.08.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.06.08.01

4.09.06.08.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.06.08.01

4.09.06.08.05

For height above 20m

cum

Add +40.00% with Item No 4.09.06.08.01

4.09.07

RCC-35SCBP: Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 45 MPa and satisfying a specified compressive strength, f'c = 35 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C 33 including breaking chips, screening through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in mechanized batch mix plant, pumping using line pump or boom placer, maintaining allowable slump of 100mm to 150mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, placing, binding etc. is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 22346.53

Page: 643 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.07.01

Detailed Analysis Brief Description of Item 2 For foundation of Pier & Abutment of Bridges and Facing Elements of Reinforced/ Mechanically Stabilized Earth Structure

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10973.97

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

987.66 11961.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12200.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13420.95

VAT

6% of Total

IT

4% of Total

894.73 596.49 Page: 644 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.07.02

Amount 8 14912.16

For diaphragm walls, wing walls, piers, columns, projected pile cap above water level, pier caps, abutments of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 645 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.07.02.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10973.97

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1536.36 12510.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12760.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14036.59

VAT

6% of Total

IT

4% of Total

935.77 623.85

Page: 646 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.07.02.02

For height above 5m to 10m

cum

Add +25.00% with Item No 4.09.07.02.01

4.09.07.02.03

For height above 10m to 15m

cum

Add +50.00% with Item No 4.09.07.02.01

4.09.07.02.04

For height above 15m to 20m

cum

Add +75.00% with Item No 4.09.07.02.01

4.09.07.02.05

For height above 20m

cum

Add +80.00% with Item No 4.09.07.02.01

4.09.07.03

For solid slab type super-structure including cantilever, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 15596.21

Page: 647 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.07.03.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10973.97

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +50.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5486.99 16460.96

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16790.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18469.19

VAT

6% of Total

IT

4% of Total

1231.28 820.85

Page: 648 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.07.03.02

For height above 5m to 10m

cum

Add +9.50% with Item No 4.09.07.03.01

4.09.07.03.03

For height above 10m to 15m

cum

Add +19.00% with Item No 4.09.07.03.01

4.09.07.03.04

For height above 15m to 20m

cum

Add +28.50% with Item No 4.09.07.03.01

4.09.07.03.05

For height above 20m

cum

Add +38.00% with Item No 4.09.07.03.01

4.09.07.04

For T-girder & slab type super-structure including cross girders, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 20521.32

Page: 649 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.07.04.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11195.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +55.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6157.51 17352.98

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17700.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19470.04

VAT

6% of Total

IT

4% of Total

1298.00 865.34

Page: 650 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.07.04.02

For height above 5m to 10m

cum

Add +6.50% with Item No 4.09.07.04.01

4.09.07.04.03

For height above 10m to 15m

cum

Add +13.00% with Item No 4.09.07.04.01

4.09.07.04.04

For height above 15m to 20m

cum

Add +19.50% with Item No 4.09.07.04.01

4.09.07.04.05

For height above 20m

cum

Add +26.00% with Item No 4.09.07.04.01

4.09.07.05

For Arch/ inclined girder of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 21633.38

Page: 651 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.07.05.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11360.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +60.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6816.28 18176.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18540.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20394.32

VAT

6% of Total

IT

4% of Total

1359.62 906.41

Page: 652 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.07.05.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.07.05.01

4.09.07.05.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.07.05.01

4.09.07.05.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.07.05.01

4.09.07.05.05

For height above 20m

cum

Add +40.00% with Item No 4.09.07.05.01

4.09.07.06

For Box Girder, Segmental Construction and Balanced Cantilever

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 22660.35

Page: 653 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.07.06.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11360.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +62.50 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7100.29 18460.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18829.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20712.98

VAT

6% of Total

IT

4% of Total

1380.87 920.58

Page: 654 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.07.06.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.07.06.01

4.09.07.06.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.07.06.01

4.09.07.06.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.07.06.01

4.09.07.06.05

For height above 20m

cum

Add +40.00% with Item No 4.09.07.06.01

4.09.08

RCC-40SCBP: Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 50 MPa and satisfying a specified compressive strength, f'c = 40 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C 33 including breaking chips, screening through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in mechanized batch mix plant, pumping using line pump or boom placer, maintaining allowable slump of 100mm to 150mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, placing, binding etc. is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 23014.42

Page: 655 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.09.08.01

Detailed Analysis Brief Description of Item 2 For foundation of Pier & Abutment of bridges

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.3500

liter

160.00

376.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11171.97

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1005.48 12177.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12421.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13663.10

VAT

6% of Total

IT

4% of Total

910.87 607.25

Page: 656 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.08.02

Amount 8 15181.22

For diaphragm walls, wing walls, piers, columns, projected pile cap above water level, pier caps, abutments of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 657 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.08.02.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.3500

liter

160.00

376.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11171.97

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1564.08 12736.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12990.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14289.84

VAT

6% of Total

IT

4% of Total

952.66 635.10

Page: 658 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.08.02.02

For height above 5m to 10m

cum

Add +25.00% with Item No 4.09.08.02.01

4.09.08.02.03

For height above 10m to 15m

cum

Add +50.00% with Item No 4.09.08.02.01

4.09.08.02.04

For height above 15m to 20m

cum

Add +75.00% with Item No 4.09.08.02.01

4.09.08.02.05

For height above 20m

cum

Add +80.00% with Item No 4.09.08.02.01

4.09.08.03

For solid slab type super-structure including cantilever, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 15877.60

Page: 659 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.08.03.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.3500

liter

160.00

376.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Diesel

1.0730

liter

68.00

72.96 11244.93

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +50.00 % on Subtotal-A )

Subtotal-A1:

5622.47 16867.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17204.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18925.22

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

1261.68 Page: 660 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

For height above 5m to 10m

cum

Add +9.50% with Item No 4.09.08.03.01

4.09.08.03.03

For height above 14m to 15m

cum

Add +19.00% with Item No 4.09.08.03.01

4.09.08.03.04

For height above 19m to 20m

cum

Add +28.50% with Item No 4.09.08.03.01

4.09.08.03.05

For height above 20m

cum

Add +38.00% with Item No 4.09.08.03.01

4.09.08.04

For T-girder & slab type super-structure including cross girders, side walk, curb and wheel guard of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

8 841.12

Total: 4.09.08.03.02

Amount

21028.03

Page: 661 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.08.04.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.3500

liter

160.00

376.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11393.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +55.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6266.41 17659.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18013.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19814.38

VAT

6% of Total

IT

4% of Total

1320.96 880.64

Page: 662 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.08.04.02

For height above 5m to 10m

cum

Add +6.00% with Item No 4.09.08.04.01

4.09.08.04.03

For height above 10m to 15m

cum

Add +12.00% with Item No 4.09.08.04.01

4.09.08.04.04

For height above 15m to 20m

cum

Add +18.00% with Item No 4.09.08.04.01

4.09.08.04.05

For height above 20m

cum

Add +24.00% with Item No 4.09.08.04.01

4.09.08.05

For Arch/ inclined girder of bridges

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 22015.98

Page: 663 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.08.05.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.3500

liter

160.00

376.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11558.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +57.50 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6646.12 18204.59

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18568.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20425.55

VAT

6% of Total

IT

4% of Total

1361.70 907.80

Page: 664 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.08.05.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.08.05.01

4.09.08.05.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.08.05.01

4.09.08.05.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.08.05.01

4.09.08.05.05

For height above 20m

cum

Add +40.00% with Item No 4.09.08.05.01

4.09.08.06

For Box Girder, Segmental Construction and Balanced Cantilever

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 22695.06

Page: 665 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.09.08.06.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.3500

liter

160.00

376.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.7500

day

370.00

647.50

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11558.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +62.50 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7224.04 18782.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19158.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21073.98

VAT

6% of Total

IT

4% of Total

1404.93 936.62

Page: 666 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

4.09.08.06.02

For height above 5m to 10m

cum

Add +12.50% with Item No 4.09.08.06.01

4.09.08.06.03

For height above 10m to 15m

cum

Add +25.00% with Item No 4.09.08.06.01

4.09.08.06.04

For height above 15m to 20m

cum

Add +37.50% with Item No 4.09.08.06.01

4.09.08.06.05

For height above 20m

cum

Add +40.00% with Item No 4.09.08.06.01

4.10.01

PSC-35SCCM: Providing and laying Cement Concrete in Pre-stressed Concrete works with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 45 MPa and satisfying a specified compressive strength, f'c = 35 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C 33 , including breaking stone boulders into chips, screening through proper sieves, making and placing shutter in position, making shutter water-tight properly, placing non prestressing reinforcement, HT Strand, sheath, anchorage in position, mixing in standard mixture machine with hoper, maintaining allowable slump of 75mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing at least for 28 days, removing shutter after specified time period, finishing, launching, shifting & placing in position etc. including cost of water, electricity, other incidental charges etc. all complete as per design, drawing, specification & directionn of E-I-C. The cost of non prestressing reinforcement, HT Strand and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Concrete Mixture

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 23415.53

Page: 667 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.10.01.01

For Solid Slab/ voided slab Super-structure.

4.10.01.01.01

For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

2.7000

liter

160.00

432.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.5000

day

370.00

925.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11225.22

Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +50.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

5612.61

16837.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17174.59

10% Profit ( Add 10% on Subtotal-B) :

18892.05

VAT

6% of Total

IT

4% of Total

1259.47 839.65 Total:

For height above 5 m to 10 m

8

cum

Subtotal-A:

4.10.01.01.02

Amount

20991.16

Add +10.00% with Item No 4.10.01.01.01

Page: 668 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.10.01.01.03

For height above 10 m to 15 m

cum

Add +20.00% with Item No 4.10.01.01.01

4.10.01.01.04

For height above 15 m to 20 m

cum

Add +30.00% with Item No 4.10.01.01.01

4.10.01.01.05

For height above 20 m

cum

Add +40.00% with Item No 4.10.01.01.01

4.10.01.02

For I-Girder/T-Girder including casting of girders on staging at site or launching of precast girders by launching truss.

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 669 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.01.02.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

2.7000

liter

160.00

432.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.5000

day

370.00

925.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11225.22

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +80.00 % on Subtotal-A )

Subtotal-A1:

8980.18

20205.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20609.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22670.45

VAT

6% of Total

IT

4% of Total

1511.36 1007.58 Total:

4.10.01.02.02

For height above 5 m to 10 m

cum

Add +6.00% with Item No 4.10.01.02.01

4.10.01.02.03

For height above 10 m to 15 m

cum

Add +12.00% with Item No 4.10.01.02.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

25189.39

Page: 670 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.10.01.02.04

For height above 15 m to 20 m

cum

Add +18.00% with Item No 4.10.01.02.01

4.10.01.02.05

For height above 20 m

cum

Add +24.00% with Item No 4.10.01.02.01

4.10.01.03

For cast-in-situ box girder, segmental construction and balanced cantilever.

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 671 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.01.03.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

2.7000

liter

160.00

432.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.5000

day

370.00

925.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11225.22

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +100.00 % on Subtotal-A )

Subtotal-A1:

22450.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22899.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25189.39

VAT

6% of Total

IT

4% of Total

1679.29 1119.53 Total:

4.10.01.03.02

For height above 5 m to 10 m

cum

Add +6.50% with Item No 4.10.01.03.01

4.10.01.03.03

For height above 10 m to 15 m

cum

Add +13.00% with Item No 4.10.01.03.01

Note : Rates of all items should be inclusive of all supply and carriage.

11225.22

27988.22

Page: 672 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.10.01.03.04

For height above 15 m to 20 m

cum

Add +19.50% with Item No 4.10.01.03.01

4.10.01.03.05

For height above 20 m

cum

Add +26.00% with Item No 4.10.01.03.01

4.10.02

PSC-35SCBP: Providing and laying Cement Concrete in Pre-stressed Concrete works with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 45 MPa and satisfying a specified compressive strength, f'c = 35 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C 33, including breaking stone boulders into chips, screening through proper sieves, making and placing shutter in position, making shutter water-tight properly, placing non prestressing reinforcement, HT Strand, sheath, anchorage in position, mixing in mechanized batch mix plant & pumping using line pump or boom placer, maintaining allowable slump of 125mm to 150mm, casting in forms, compacting by mechanical vibrator machine, curing at least for 28 days, removing shutter after specified time period, finishing, launching, shifting & placing in position etc. including cost of water, electricity, other incidental charges etc. all complete as per design, drawing, specification & directionn of E-I-C. The cost of non prestressing reinforcement, HT Strand and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by Central Quality Control Laboratory (CQCL), LGED or or any other reputed laboratory approved by the competent authority before execution of the workk. Note: Using Batching Plant, Transit Mixer & Concrete Pump

4.10.02.01

For Solid Slab/voided slab Super-structure.

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 673 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.02.01.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.6000

liter

160.00

576.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11435.97

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +50.00 % on Subtotal-A )

Subtotal-A1:

5717.99

17153.96

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17497.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19246.74

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

1283.12 Page: 674 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

For height above 5 m to 10 m

cum

Add +10.00% with Item No 4.10.02.01.01

4.10.02.01.03

For height above 10 m to 15 m

cum

Add +20.00% with Item No 4.10.02.01.01

4.10.02.01.04

For height above 15 m to 20 m

cum

Add +30.00% with Item No 4.10.02.01.01

4.10.02.01.05

For height above 20 m

cum

Add +40.00% with Item No 4.10.02.01.01

4.10.02.02

For I-Girder/T-Girder including casting of girders on staging at site or launching of precast girders by launching truss.

Note : Rates of all items should be inclusive of all supply and carriage.

8 855.41

Total: 4.10.02.01.02

Amount

21385.26

Page: 675 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.02.02.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.6000

liter

160.00

576.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11435.97

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +80.00 % on Subtotal-A )

Subtotal-A1:

9148.78

20584.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20996.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

23096.09

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

1539.74 Page: 676 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

For height above 5 m to 10 m

cum

Add +6.00% with Item No 4.10.02.02.01

4.10.02.02.03

For height above 10 m to 15 m

cum

Add +12.00% with Item No 4.10.02.02.01

4.10.02.02.04

For height above 15 m to 20 m

cum

Add +18.00% with Item No 4.10.02.02.01

4.10.02.02.05

For height above 20 m

cum

Add +24.00% with Item No 4.10.02.02.01

4.10.02.03

For cast-in-situ box girder, segmental construction and balanced cantilever.

Note : Rates of all items should be inclusive of all supply and carriage.

8 1026.49

Total: 4.10.02.02.02

Amount

25662.32

Page: 677 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.02.03.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.6000

liter

160.00

576.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11435.97

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +100.00 % on Subtotal-A )

Subtotal-A1:

22871.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23329.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25662.32

VAT Note : Rates of all items should be inclusive of all supply and carriage.

11435.97

6% of Total

1710.82 Page: 678 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

For height above 5 m to 10 m

cum

Add +6.50% with Item No 4.10.02.03.01

4.10.02.03.03

For height above 10 m to 15 m

cum

Add +13.00% with Item No 4.10.02.03.01

4.10.02.03.04

For height above 15 m to 20 m

cum

Add +19.50% with Item No 4.10.02.03.01

4.10.02.03.05

For height above 20 m

cum

Add +26.00% with Item No 4.10.02.03.01

Note : Rates of all items should be inclusive of all supply and carriage.

8 1140.55

Total: 4.10.02.03.02

Amount

28513.69

Page: 679 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.10.03

PSC-40SCRDM: Providing and laying Cement Concrete in Pre-stressed Concrete works with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 50 MPa and satisfying a specified compressive strength, f'c = 40 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C 494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C 33 , including breaking stone boulders into chips, screening through proper sieves, making and placing shutter in position, making shutter water-tight properly, placing non prestressing reinforcement, HT Strand, sheath, anchorage in position, mixing in Reversible Drum Mixer/ Batch Mix Plant, maintaining allowable slump of 125mm to 150mm, casting in forms, compacting by mechanical vibrator machine, curing at least for 28 days, removing shutter after specified time period, finishing, launching, shifting & placing in position etc. including cost of water, electricity, other incidental charges etc. all complete as per design, drawing, specification & directionn of E-I-C. The cost of non prestressing reinforcement, HT Strand and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Reversible Drum Mixer/ Batch Mix Plant

4.10.03.01

For Solid Slab/voided slab Super-structure

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 680 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.03.01.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.7600

liter

160.00

601.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Reversible Drum Mixer/ Batch Mix Plant (15 cum/hr)

0.0083

day

15000.00

124.50

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11670.82

Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +50.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

5835.41

17506.23 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17856.35

10% Profit ( Add 10% on Subtotal-B) :

19641.99

VAT

6% of Total

IT

4% of Total

1309.47 872.98 Total:

For height above 5 m to 10 m

8

cum

Subtotal-A:

4.10.03.01.02

Amount

21824.43

Add +10.00% with Item No 4.10.03.01.01 Page: 681 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.10.03.01.03

For height above 10 m to 15 m

cum

Add +20.00% with Item No 4.10.03.01.01

4.10.03.01.04

For height above 15 m to 20 m

cum

Add +30.00% with Item No 4.10.03.01.01

4.10.03.01.05

For height above 20 m

cum

Add +40.00% with Item No 4.10.03.01.01

4.10.03.02

For I-Girder/T-Girder including casting of girders on staging at site or launching of precast girders by launching truss.

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 682 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.03.02.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.7600

liter

160.00

601.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Reversible Drum Mixer/ Batch Mix Plant (15 cum/hr)

0.0083

day

15000.00

124.50

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11670.82

Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +80.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

cum

9336.66

21007.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21427.63

10% Profit ( Add 10% on Subtotal-B) :

23570.39

VAT

6% of Total

IT

4% of Total

1571.36 1047.57 Total:

For height above 5 m to 10 m

8

cum

Subtotal-A:

4.10.03.02.02

Amount

26189.32

Add +6.00% with Item No 4.10.03.02.01 Page: 683 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

4.10.03.02.03

For height above 10 m to 15 m

cum

Add +12.00% with Item No 4.10.03.02.01

4.10.03.02.04

For height above 15 m to 20 m

cum

Add +18.00% with Item No 4.10.03.02.01

4.10.03.02.05

For height above 20 m

cum

Add +24.00% with Item No 4.10.03.02.01

4.10.04

PSC-40SCBP: Providing and laying Cement Concrete in Pre-stressed Concrete works with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive strength, f'cr = 50 MPa and satisfying a specified compressive strength, f'c = 40 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C 33, including breaking stone boulders into chips, screening through proper sieves, making and placing shutter in position, making shutter water-tight properly, placing non prestressing reinforcement, HT Strand, sheath, anchorage in position, mixing in mechanized batch mix plant & pumping using line pump or boom placer, maintaining allowable slump of 100mm to 150mm, casting in forms, compacting by mechanical vibrator machine, curing at least for 28 days, removing shutter after specified time period, finishing, launching, shifting & placing in position etc. including cost of water, electricity, other incidental charges etc. all complete as per design, drawing, specification & directionn of E-I-C. The cost of non prestressing reinforcement, HT Strand and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

4.10.04.01

For Solid Slab/voided slab Super-structure.

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 684 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.04.01.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.7600

liter

160.00

601.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11643.57

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +50.00 % on Subtotal-A )

Subtotal-A1:

5821.79

17465.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17814.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19596.13

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

1306.41 Page: 685 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

For height above 5 m to 10 m

cum

Add +10.00% with Item No 4.10.04.01.01

4.10.04.01.03

For height above 10 m to 15 m

cum

Add +20.00% with Item No 4.10.04.01.01

4.10.04.01.04

For height above 15 m to 20 m

cum

Add +30.00% with Item No 4.10.04.01.01

4.10.04.01.05

For height above 20 m

cum

Add +40.00% with Item No 4.10.04.01.01

4.10.04.02

For I-Girder/T-Girder including casting of girders on staging at site or launching of precast girders by launching truss.

Note : Rates of all items should be inclusive of all supply and carriage.

8 870.94

Total: 4.10.04.01.02

Amount

21773.48

Page: 686 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.04.02.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.7600

liter

160.00

601.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11643.57

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +80.00 % on Subtotal-A )

Subtotal-A1:

9314.86

20958.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21377.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

23515.35

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

1567.69 Page: 687 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

For height above 5 m to 10 m

cum

Add +6.00% with Item No 4.10.04.02.01

4.10.04.02.03

For height above 10 m to 15 m

cum

Add +12.00% with Item No 4.10.04.02.01

4.10.04.02.04

For height above 15 m to 20 m

cum

Add +18.00% with Item No 4.10.04.02.01

4.10.04.02.05

For height above 20 m

cum

Add +24.00% with Item No 4.10.04.02.01

4.10.04.03

For cast-in-situ box girder, segmental construction and balanced cantilever.

Note : Rates of all items should be inclusive of all supply and carriage.

8 1045.13

Total: 4.10.04.02.02

Amount

26128.17

Page: 688 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.04.03.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.4000

bag

455.00

4277.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.7600

liter

160.00

601.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 11643.57

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +100.00 % on Subtotal-A )

Subtotal-A1:

23287.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23752.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26128.17

VAT Note : Rates of all items should be inclusive of all supply and carriage.

11643.57

6% of Total

1741.88 Page: 689 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

4% of Total

For height above 5 m to 10 m

cum

Add +6.50% with Item No 4.10.04.03.01

4.10.04.03.03

For height above 10 m to 15 m

cum

Add +13.00% with Item No 4.10.04.03.01

4.10.04.03.04

For height above 15 m to 20 m

cum

Add +19.50% with Item No 4.10.04.03.01

4.10.04.03.05

For height above 20 m

cum

Add +26.00% with Item No 4.10.04.03.01

Note : Rates of all items should be inclusive of all supply and carriage.

8 1161.25

Total: 4.10.04.03.02

Amount

29031.30

Page: 690 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.10.05

PSC-45SCBP: Providing and laying Cement Concrete in Pre-stressed Concrete workswith minimum cement content and maximum water cement ratio as specified by the laboratory having minimum required average compressive strength, f'cr = 55 MPa and satisfying a specified compressive strength, f'c = 45 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, silica fume conforming to ASTM C 1240, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C 33, including breaking stone boulders into chips, screening through proper sieves, making and placing shutter in position, making shutter water-tight properly, placing non prestressing reinforcement, HT Strand, sheath, anchorage in position, mixing in mechanized batch mix plant & pumping using line pump or boom placer, maintaining allowable slump of 75mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing at least for 28 days, removing shutter after specified time period, finishing, launching, shifting & placing in position etc. including cost of water, electricity, other incidental charges etc. all complete as per design, drawing, specification & directionn of E-I-C. The cost of non prestressing reinforcement, HT Strand and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

4.10.05.01

For cast-in-situ box girder, segmental construction and balanced cantilever.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 691 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.05.01.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.8000

bag

455.00

4459.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.9200

liter

160.00

627.20

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

75.0000

kg

30.00

2250.00

Silica Fume in accordance with ASTM C 1240

14101.17

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +80.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11280.94

25382.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25889.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

28478.72 Page: 692 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

For height above 5 m to 10 m

cum

Add +5.75% with Item No 4.10.05.01.01

4.10.05.01.03

For height above 10 m to 15 m

cum

Add +11.50% with Item No 4.10.05.01.01

4.10.05.01.04

For height above 15 m to 20 m

cum

Add +17.50% with Item No 4.10.05.01.01

4.10.05.01.05

For height above 20 m

cum

Add +23.00% with Item No 4.10.05.01.01

Note : Rates of all items should be inclusive of all supply and carriage.

8 1898.58 1265.72

Total: 4.10.05.01.02

Amount

31643.03

Page: 693 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.10.06

PSC-50SCBP: Providing and laying Cement Concrete in Pre-stressed Concrete workswith minimum cement content and maximum water cement ratio as specified by the laboratory having minimum required average compressive strength, f'cr = 60 MPa and satisfying a specified compressive strength, f'c = 50 MPa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, silica fume conforming to ASTM C 1240, high range water reducing admixture of complying type F/ G under ASTM C 494 (Doses of admixture to be fixed by the mix design) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C 33 , including breaking stone boulders into chips, screening through proper sieves, making and placing shutter in position, making shutter water-tight properly, placing non prestressing reinforcement, HT Strand, sheath, anchorage in position, mixing in mechanized batch mix plant & pumping using line pump or boom placer, maintaining allowable slump of 75mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing at least for 28 days, removing shutter after specified time period, finishing, launching, shifting & placing in position etc. including cost of water, electricity, other incidental charges etc. all complete as per design, drawing, specification & directionn of E-I-C. The cost of non prestressing reinforcement, HT Strand and it's fabrication, binding, welding and placing is not included but the cost of admixture is included in this unit rate. The Mix Design shall have to be approved by Central Quality Control Laboratory (CQCL), LGED or any other reputed laboratory approved by the competent authority before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

4.10.06.01

For cast-in-situ box girder, segmental construction and balanced cantilever.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 694 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.06.01.01

2 For height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.8000

bag

455.00

4459.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range and retrading chemical admixture : Type-G

3.9200

liter

160.00

627.20

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0063

day

23000.00

144.90

H.C. of Generator (100 KVA)

0.0063

day

3500.00

22.05

H.C. of Backhoe End Loader (6 tons)

0.0063

day

6000.00

37.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0063

day

5000.00

31.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

90.0000

kg

30.00

2700.00

Silica Fume in accordance with ASTM C 1240

14551.17

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports, girder shifting/ launching, steel sheath & all necessary equipment etc.

( +80.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11640.94

26192.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26715.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

29387.54 Page: 695 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

For height above 5 m to 10 m

cum

Add +5.75% with Item No 4.10.06.01.01

4.10.06.01.03

For height above 10 m to 15 m

cum

Add +11.50% with Item No 4.10.06.01.01

4.10.06.01.04

For height above 15 m to 20 m

cum

Add +17.25% with Item No 4.10.06.01.01

4.10.06.01.05

For height above 20 m

cum

Add +23.00% with Item No 4.10.06.01.01

Note : Rates of all items should be inclusive of all supply and carriage.

8 1959.17 1306.11

Total: 4.10.06.01.02

Amount

32652.83

Page: 696 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.10.07

Detailed Analysis Brief Description of Item 2 Providing and laying of 7-ply un-coated HT strand conforming to AASHTO M 203/ ASTM A 416 (Grade 1860, low relaxation type) having minimum ultimate tensile strength 1860 MPa of required size as per design including supplying, fabrication, placing in position, providing corrugated galvanized steel sheathing duct of minimum 0.4mm thick and minimum 75mm internal diameter, decoling the strands, cutting to the required lengths, preparing cables of required number strands as per drawings, making dead ends of cables in flowers to achieve rigid ends, spacers & joineries of approved quality, inserting cables within the sheathing, fixind tendon support bars, supervising anti bursting reinforcements, maintaning profile during concreting operations, stressing of cables in sequence as per design to required loads with approved stressing jacks, Blocking with proper pressure, measuring and recording elongation and force, grouting the duct with pumpable, nonbleeeding, high strength non-shrink cementitious grout with nonshrink grout admixture conforming to ASTM C 1107, maintaining the water cement ratio between 0.47 to 0.53, cutting the excess HT strand after satisfactory tensioning & anchorage, providing patch concrete at recess end with epoxy coating, all materials, labors, equipment, tools etc. all complete including leads and lifts as per design, drawing, specification and direction of the E-I-C. [Extra Length required for stressing operation is included in this unit rate]

Unit

Sub-Item

3

4

5

Unit

Rate

6

7

Amount 8

MT

H.T. Strand Corrugated Galvanized Steel Sheathing Duct

1.0500

100000.00

105000.00

m

165.00

18381.99

6.6310

bag

455.00

3017.11

H.C. of Grout pump with agitator & accessories

2.6530

hour

200.00

530.60

H.C. of Generator (40 KVA)

1.1600

day

2500.00

2900.00

H.C. of Stressing Jack with Pump and other accessories

0.8290

Day

1500.00

1243.50

Foreman

0.6900

day

800.00

552.00

Re-bar Fabricator

2.6530

day

570.00

1512.21

Mason

0.6630

day

550.00

364.65

0.6630

day

570.00

377.91

13.2630

day

450.00

5968.35

Skilled Labour

111.4060

MT

Ordinary Portland Cement (CEM I, 52.5N)

Operator

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity

Page: 697 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Grouting, Erection & all other accessories H.C. of all Machines and Equipment

( +25.00 % on Subtotal-A ) ( +25.00 % on Subtotal-A )

Subtotal-A1:

Subtotal-C:

34962.08 34962.08 209772.47

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

213967.92

10% Profit ( Add 10% on Subtotal-B) :

235364.71

VAT

6% of Total

IT

4% of Total

15690.98 10460.65 Total:

4.10.08

8 139848.32

Subtotal-A:

Subtotal-B:

Amount

261516.35

Multi-Strand Steel Anchorage: Supplying, fitting and fixing of best quality international branded (preferably of Freyssinet, Dynamic, Poston or equivalent) post tensioning multi-strand steel anchorage system comprising bearing plate, wedge plate, guide tube and gripping accessories with necessary test certificate from manufacturer for origin, performance and capacity including cost of all materials and accessories, necessary performance and capacity test from BUET, placing properly in position, labour, welding and carrying etc. all complete as design, drawing and direction of the E-I-C. The geometrical size and shape of the anchorage system shall be confirmed as per drawing or manufacturer’s recommendation with necessary test results. One set of extra anchorage will be required for laboratory test and necessary arrangement.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 698 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.08.01

2 Anchorage Type: 4K13/ 4T13

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Anchorage of 4K13/ 4T13 System

1.0000

Set

3000.00

3000.00

Subtotal-A: All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

300.00

Subtotal-A1: Subtotal-B: Subtotal-C:

3300.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3366.00

10% Profit ( Add 10% on Subtotal-B) :

3702.60

VAT

6% of Total

IT

4% of Total

246.84 164.56 Total:

4.10.08.02

Anchorage Type: 7K13/ 7T13

4114.00

set Anchorage of 7K13/ 7T13 System

1.0000

set

3500.00

All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3500.00 3500.00

Subtotal-A:

350.00 3850.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3927.00

10% Profit ( Add 10% on Subtotal-B) :

4319.70

VAT

6% of Total

IT

4% of Total

287.98 191.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3000.00

4799.67

Page: 699 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.08.03

2 Anchorage Type: 12K13/ 12T13

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Anchorage of 12K13/ 12T13 System

1.0000

set

5600.00

5600.00

Subtotal-A: All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

560.00

Subtotal-A1: Subtotal-B: Subtotal-C:

6160.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6283.20

10% Profit ( Add 10% on Subtotal-B) :

6911.52

VAT

6% of Total

IT

4% of Total

460.77 307.18 Total:

4.10.08.04

Anchorage Type: 19K13/ 19T13

7679.47

set Anchorage of 19K13/ 19T13 System

1.0000

set

7000.00

All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

7000.00 7000.00

Subtotal-A:

700.00 7700.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7854.00

10% Profit ( Add 10% on Subtotal-B) :

8639.40

VAT

6% of Total

IT

4% of Total

575.96 383.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5600.00

9599.33

Page: 700 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.08.05

2 Anchorage Type: 27K13/ 27T13

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Anchorage of 27K13/ 27T13 System

1.0000

Set

9000.00

9000.00

Subtotal-A: All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

900.00

Subtotal-A1: Subtotal-B: Subtotal-C:

9900.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10098.00

10% Profit ( Add 10% on Subtotal-B) :

11107.80

VAT

6% of Total

IT

4% of Total

740.52 493.68 Total:

4.10.08.06

Anchorage Type: 37K13/ 37T13

12342.00

set Anchorage of 37K13/ 37T13 System

1.0000

Set

12000.00

All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12000.00 12000.00

Subtotal-A:

1200.00 13200.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13464.00

10% Profit ( Add 10% on Subtotal-B) :

14810.40

VAT

6% of Total

IT

4% of Total

987.36 658.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9000.00

16456.00

Page: 701 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.08.07

2 Anchorage Type: 4K15/ 4T15

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Anchorage of 4K15/ 4T15 System

1.0000

Set

3500.00

3500.00

Subtotal-A: All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

350.00

Subtotal-A1: Subtotal-B: Subtotal-C:

3850.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3927.00

10% Profit ( Add 10% on Subtotal-B) :

4319.70

VAT

6% of Total

IT

4% of Total

287.98 191.99 Total:

4.10.08.08

Anchorage Type: 7K15/ 7T15

4799.67

set Anchorage of 7K15/ 7T15 System

1.0000

set

5000.00

All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

5000.00 5000.00

Subtotal-A:

500.00 5500.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5610.00

10% Profit ( Add 10% on Subtotal-B) :

6171.00

VAT

6% of Total

IT

4% of Total

411.40 274.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3500.00

6856.67

Page: 702 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.08.09

2 Anchorage Type: 12K15/ 12T15

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Anchorage of 12K15/ 12T15 System

1.0000

set

8000.00

8000.00

Subtotal-A: All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

800.00

Subtotal-A1: Subtotal-B: Subtotal-C:

8800.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8976.00

10% Profit ( Add 10% on Subtotal-B) :

9873.60

VAT

6% of Total

IT

4% of Total

658.24 438.83 Total:

4.10.08.10

Anchorage Type: 19K15/ 19T15

10970.67

set Anchorage of 19K15/ 19T15 System

1.0000

set

10000.00

All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

10000.00 10000.00

Subtotal-A:

1000.00 11000.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11220.00

10% Profit ( Add 10% on Subtotal-B) :

12342.00

VAT

6% of Total

IT

4% of Total

822.80 548.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8000.00

13713.33

Page: 703 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.08.11

2 Anchorage Type: 27K15/ 27T15

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Anchorage of 27K15/ 27T15 System

1.0000

Set

11000.00

11000.00

Subtotal-A: All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

1100.00

Subtotal-A1: Subtotal-B: Subtotal-C:

12100.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12342.00

10% Profit ( Add 10% on Subtotal-B) :

13576.20

VAT

6% of Total

IT

4% of Total

905.08 603.39 Total:

4.10.08.12

Anchorage Type: 37K15/ 37T15

15084.67

set Anchorage of 37K15/ 37T15 System

1.0000

Set

12500.00

All other cost & fitting & fixing

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12500.00 12500.00

Subtotal-A:

1250.00 13750.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14025.00

10% Profit ( Add 10% on Subtotal-B) :

15427.50

VAT

6% of Total

IT

4% of Total

1028.50 685.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11000.00

17141.67

Page: 704 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.10.09

Detailed Analysis Brief Description of Item 2 Unbonded Monostrand: Providing and laying of cold-drawn, low relaxation 7-wire coated HT strand conform to ASTM A 416 (Grade 1860, the outer diameter of HDPE sheathing should not be less then 1.27mm) having minimum ultimate tensile strength 1860 MPa of required size as per design including supplying, fabrication, placing in position, support chairs, spacers, joineries of approved quality, properly stage wise tensioning with approved jacks, Blocking with proper pressure, measuring and recording elongation and force, cutting the excess HT strand after satisfactory tensioning & anchorage, providing patch concrete at recess end with epoxy coating, all materials, labors, equipment, tools etc. all complete including leads and lifts as per design, drawing, specification and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT

Unbonded Monostrand

1.0000

MT

150000.00

150000.00

H.C. of Generator (40 KVA)

1.1600

day

2500.00

2900.00

H.C. of Stressing Jack with Pump and other accessories

0.8290

Day

1500.00

1243.50

Foreman

0.5000

day

800.00

400.00

Operator

2.0000

day

570.00

1140.00

Re-bar Fabricator

2.0000

day

570.00

1140.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

3.0000

day

450.00

1350.00

Ordinary Labour

6.0000

day

370.00

2220.00 160668.50

Subtotal-A: H.C. of all Machines and Equipment

( +25.00 % on Subtotal-A )

Subtotal-A1:

40167.13 200835.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

204852.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

225337.57

VAT

6% of Total

IT

4% of Total

15022.50 10015.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

250375.08

Page: 705 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.10.10

Mono Strand Anchorage: Supplying, fitting and fixing of best quality international branded (preferably Freyssinet, Dynamic, Poston, VSL or equivalent) post tensioning monostrand steel anchorage system comprising bearing plate, wedge plate, guide tube and gripping accessories with necessary test certificate from manufacturer for origin, performance and capacity including cost of all materials and accessories, necessary performance and capacity test from BUET, placing properly in position, labour, welding and carrying etc. all complete as design, drawing and direction of the E-I-C. The geometrical size and shape of the anchorage system shall be confirmed as per drawing or manufacturer’s recommendation with necessary test results. One set of extra anchorage will be required for laboratory test and necessary arrangement.

4.10.10.01

MSA: 1K13/ 1T13

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set

850.00

850.00

set Monostrand Steel Anchorage (1K13/ 1T13)

1.0000

850.00

Subtotal-A: All other costs including fitting, fixing, installation, testing, transportation etc.

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

255.00 1105.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1127.10

10% Profit ( Add 10% on Subtotal-B) :

1239.81

VAT

6% of Total

82.65

IT

4% of Total

55.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1377.57

Page: 706 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.10.10.02

2 MSA: 1K15/ 1T15

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

950.00

950.00

set Monostrand Steel Anchorage (1K15/ 1T15)

1.0000

each

950.00

Subtotal-A: All other costs including fitting, fixing, installation, testing, transportation etc.

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Stay Cables: Supplying, fabricating and fixing Stay Cables (preferably VSL, Tensaccial, Freyssinet, BBR or equivalent) in position having a tendon formed from multiple and parallel 15.7mm dia. high tensile 7wire steel low relaxation strands with nominal cross-sectional area of 150 mm2 and a minimum ultimate tensile strengh of 1860 MPa, strands shall be galvanized and corrosion inhibited, a greased or waxed strand with a tightly extruded plastic sheathing, an outer thick-walled plastic stay pipe, factory prefabricated fixed/ adjustable anchorages, elastomeric dampers at the end of the form tube, appropriate saddle system (if required) including cost of equipment, labour etc. complete in all respect as per drawing, specification and direction of Engineer-incharge. [Contractors generally do not have expertise for this item. The job is therefore, got done from specialised/patented firms who have the expertise in the field of stay cables. The prevailing rate in the market is required to be ascertained from the market and added in the cost estimate.]

Note : Rates of all items should be inclusive of all supply and carriage.

285.00 1235.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1259.70

10% Profit ( Add 10% on Subtotal-B) :

1385.67

VAT

6% of Total

IT

4% of Total

92.38 61.59 Total:

4.10.11

Amount

1539.63

LS

Page: 707 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.10.12

Detailed Analysis Brief Description of Item 2 Dummy Cable Duct: Supplying, fabricating and fixing dummy cable duct including end anchor cone, cost of equipment, labour etc. complete as per drawing, specification and direction of Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Corrugated Galvanized Steel Sheathing Duct

1.0500

m

165.00

173.25

Anchorage of 19K15/ 19T15 System

0.0400

set

10000.00

400.00

Non-Shrink Grout

0.1600

Kg

40.00

6.40

Stone Chips (12mm down graded) [LAA≤25]

0.0007

cum

4640.00

3.25

H.C. of Sheating Pipe Machine

0.0075

Day

2500.00

18.75

H.C. of Generator (40 KVA)

0.0075

day

2500.00

18.75

Skilled Technician

0.0075

day

680.00

5.10

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0575

day

470.00

27.03

Carpenter

0.0600

day

680.00

40.80

Mason

0.0200

day

550.00

11.00 704.32

Subtotal-A: Cost of material for Spacers, Insulation Tape, Plywood and Miscellaneous items

( +7.50 % on Subtotal-A )

Subtotal-A1:

52.82 757.15

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

772.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

849.52

VAT

6% of Total

IT

4% of Total

56.63 37.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

943.91

Page: 708 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying and fabrication of Ribbed or deformed bar reinforcement for all types of RCC work including straightening, removing ruts, cleaning, cutting, hooking, bending, lapping and/or welding wherever required as directed, placing in position, tieing with 22 BWG black annealed binding wire (PVC coated in case of FBEC rebar) double fold, cost of binding wire and anchoring to the adjoining members wherever necessary, supplying and placing with proper cover blocks (1:1), supports, chairs, spacers, splices or laps etc. including cost of all materials, cost of labour, cost of equipment & machinery, loading and unloading, transportation, all other incidental charges and work at all leads and lifts etc. to complete the work as per design, drawing, specifications and direction of the E-I-C. Measurement relating to nominal mass, dimensions and tolerances of various types of steel shall conform to relevant BDS/ ASTM codes. Reinforcement shall be measured only in lengths of bar as actually placed in position on standard weight i.e. 7850 kg/m3 (BNBC Table 6.2.1) basis. No separate payment shall be allowed for chairs of any shape & profile, spacer bar of any shape & profile, lap/ splice unless otherwise shown in the drawing, wastages, binding wire, concrete cover blocks etc. as the cost of these is included in the unit rate. Note: Tests for reinforcing bars shall be conducted at LGED/ BUET/ CUET/ KUET/ RUET.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 709 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.01.01

Detailed Analysis Brief Description of Item 2 Grade 300 (RB 300): Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield strength, fy (ReH) = 300 MPa, but the tested yield strength shall not exceed fy by more than the 125 MPa and the ratio of tested ultimate strength, fu (Re) to tested yield strength (fy) shall be at least 1.25 and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 16% and 2.5% respectively.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

M.S. Ribbed/ Deformed Bar (Grade 300)

1.0200

kg

54.00

55.08

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 61.59

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

69.10

VAT

6% of Total

IT

4% of Total

4.61 3.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

76.78

Page: 710 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.01.02

Detailed Analysis Brief Description of Item 2 Grade 400 (RB 400/ 400W): Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield strength, fy (ReH) = 400 MPa, but the tested yield strength shall not exceed fy by more than the 125 MPa and the ratio of tested ultimate strength, fu (Re) to tested yield strength (fy) shall be at least 1.25 and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 14% and 2.5% respectively.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

M.S. Ribbed/ Deformed Bar (Grade 400)

1.0200

kg

58.00

59.16

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 65.67

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

73.68

VAT

6% of Total

IT

4% of Total

4.91 3.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

81.87

Page: 711 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.01.03

Detailed Analysis Brief Description of Item 2 Grade 420 (B420DWR): Ribbed or Deformed bar produced and marked as per ISO 6935-2:2015/ ASTM A706M - 16 with minimum yield strength, fy(ReH) = 420 MPa but fy(ReH) not exceeding 540 MPa, the ratio of ultimate tensile strength, fu(Rm) to actual yield strength, fy(ReH) shall be at least 1.25 and minimum elongation in 200mm shall be at least 14% for bar sizes 10mm through 20mm, at least 12% for bar sizes 22mm through 32mm and at least 10% for bar sizes 40mm and 50mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

M.S. Ribbed/ Deformed Bar (Grade 420)

1.0200

kg

58.00

59.16

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 65.67

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.98

10% Profit ( Add 10% on Subtotal-B) :

73.68

VAT

6% of Total

4.91

IT

4% of Total

3.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

81.87

Page: 712 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.01.04

Detailed Analysis Brief Description of Item 2 Grade 500 (RB 500/ 500W): Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield stress, fy (ReH) = 500 MPa and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 14% and 2.5% respectively. [This reinforcement shall be selected as per instruction given in the drawing & after getting approval from Design unit, LGED.]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

M.S. Ribbed/ Deformed Bar (Grade 500)

1.0200

kg

57.00

58.14

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 64.65

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

65.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

72.54

VAT

6% of Total

IT

4% of Total

4.84 3.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

80.60

Page: 713 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.01.05

Detailed Analysis Brief Description of Item 2 Grade 550: Deformed bar produced and marked as per ASTM A706M 16 with minimum yield strength, fy = 550 MPa but fy not exceeding 675 MPa, minimum ultimate strength, fu = 690 MPa, the ratio of actual ultimate tensile strength, fu to actual yield strength, fy shall be at least 1.25 and minimum elongation in 200mm shall be at least 12% for bar sizes 10mm through 32mm and at least 10% for bar sizes 40mm and 50mm. [This reinforcement shall be selected as per instruction given in the drawing & after getting approval from Design unit, LGED.]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

M.S. Ribbed/ Deformed Bar (Grade 550)

1.0200

kg

59.00

60.18

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 66.69

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

68.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

74.83

VAT

6% of Total

4.99

IT

4% of Total

3.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

83.14

Page: 714 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.11.02

FBECR: Extra over item code: 4.11.01 for providing Fusion Bonded Epoxy Coating (FBEC) to reinforcement bars as per ASTM A775/ BDS ISO 14654: 2013 specification for a coating thickness (after curing) of 175 to 300 microns for 10mm to 16mm and 175 to 400 microns for 20mmm to 50mm re-bars including extra cost on account of careful handling during straightening, cutting, bending & placing, extra cost on account of using PVC coated binding wire instead of G.I. wire, extra cost on account of touch-up material (All cut edges/weld areas and bend locations where coating has been damaged touch up shall be done with same paint, the upper thickness limit shall not apply to repaired areas of damaged coating) supplied by coating agency and repair work, extra cost on account of transportation to and fro from steel yard to plant and plant to work site by trailer (if required), loading, unloading, flexibility & holiday testing, including all taxes, etc. complete to ensure proper resistance of FBE against corrosive environment. [Fusion Bonded Epoxy Coating to be proposed only in Coastal Area/Severe Exposure Condition with prior approval of Design Unit, LGED.]

4.11.02.01

For Re-bar diameter: 8mm to 12mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg Fusion Bonded Epoxy Coating (FBEC) to Reinforcing Bar as per ASTM A775 (Average rate for bars of 8mm to 12mm)

1.0000

kg

10.00

10.00 10.00

Subtotal-A: Extra Cost for Handling, Epoxy Touch Up, PVC coated binding wire etc.

( +5.00 % on Subtotal-A )

0.50

Subtotal-A1:

10.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11.78

VAT

6% of Total

IT

4% of Total

0.79 0.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

13.09

Page: 715 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.02.02

Detailed Analysis Brief Description of Item 2 For Re-bar diameter: 16mm to 50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg Fusion Bonded Epoxy Coating (FBEC) to Reinforcing Bar as per ASTM A775 (Average rate for bars of 16mm to 50mm)

1.0000

kg

8.00

8.00 8.00

Subtotal-A: Extra Cost for Handling, Epoxy Touch Up, PVC coated binding wire etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

0.40 8.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9.42

VAT

6% of Total

IT

4% of Total

0.63 0.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10.47

Page: 716 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.03

Detailed Analysis Brief Description of Item 2 Supplying and fabrication of High Yield strength (500 MPa, Galvanized wire rope) of required size and length for all types of Arch Bridge work including cutting, fitting , securing and placing them in position, etc. including cost of all materials, labour, local handling, laboratory test, incidentals charge to complete the work as per specifications, drawings and direction of the Engineer. Laboratory test for physical property, strength, to be performed as per ASTM

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

High Yield strength wire

1.0000

kg

200.00

200.00

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 205.61

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

209.72

10% Profit ( Add 10% on Subtotal-B) :

230.69

VAT

6% of Total

15.38

IT

4% of Total

10.25 Total:

4.11.04

Amount

256.33

Supplying, fitting and fixing mechanical couplers of various diameter confirming to ACI/ AASHTO having minimum connection strength at least 125% of nominal yield strength, fy of the reinforcing bars including fitting & fixing in proper position as shown in drawing and attach to the reinforcement bars by thread, cold swaging and extrusion or hot forging including cost of all materials, labors, equipment, tools etc. all complete as per design, drawing and direction of the E-I-C. All operations relating to reinforcement coupling shall be done using supplier's petented machine/ equipment and in the presence of the supplier's representative. The contractor shall submit relevant trade literature, mill certificates, certificate of origin and letters of approval for each proposed application. A sample of each type of mechanical coupler shall be submitted for testing and approval prior to the use of any coupler in the works

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 717 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.04.01

Detailed Analysis Brief Description of Item 2 For 25mm diameter rebar Coupler

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Coupler (Min. Outer diameter 45mm & Length 150mm) including wastage 2% & carrying

1.0200

each

160.00

163.20

Pressing Machine

0.0080

day

3000.00

24.00

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0400

day

370.00

14.80 223.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

227.97

10% Profit ( Add 10% on Subtotal-B) :

250.77

VAT

6% of Total

IT

4% of Total

16.72 11.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

278.63

Page: 718 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.04.02

Detailed Analysis Brief Description of Item 2 For 32mm diameter rebar Coupler

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Coupler (Min. Outer diameter 56mm & Length 192mm) including wastage 2% & carrying

1.0200

each

240.00

244.80

Pressing Machine

0.0080

day

3000.00

24.00

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0400

day

370.00

14.80 305.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

311.20

10% Profit ( Add 10% on Subtotal-B) :

342.32

VAT

6% of Total

IT

4% of Total

22.82 15.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

380.36

Page: 719 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.04.03

Detailed Analysis Brief Description of Item 2 For 40mm diameter rebar Coupler

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Coupler (Min. Outer diameter 70mm & Length 240mm) including wastage 2% & carrying

1.0200

each

400.00

408.00

Pressing Machine

0.0080

day

3000.00

24.00

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0400

day

370.00

14.80 468.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

477.67

10% Profit ( Add 10% on Subtotal-B) :

525.43

VAT

6% of Total

IT

4% of Total

35.03 23.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

583.81

Page: 720 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.04.04

Detailed Analysis Brief Description of Item 2 For 50mm diameter rebar Coupler

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coupler (Min. Outer diameter 82mm & Length 300mm) including wastage 2% & carrying

1.0200

each

450.00

459.00

Pressing Machine

0.0080

day

3000.00

24.00

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0400

day

370.00

14.80 519.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

529.69

10% Profit ( Add 10% on Subtotal-B) :

582.65

VAT

6% of Total

IT

4% of Total

38.84 25.90 Total:

4.11.05

Providing nosing with MS angles of different sizes. including cost of all materials, welding, carrying, etc. all complete as per design, drawing and direction of the E-I-C.

kg

MS Angle, Flat bar, Z bar

1.0000

kg

59.00

59.00 59.00

Subtotal-A: Welding, fitting, fixing etc.

( +96.00 % on Subtotal-A )

Subtotal-A1:

56.64 115.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

117.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

129.75

VAT

6% of Total

IT

4% of Total

8.65 5.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

647.39

144.16

Page: 721 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.11.06

Supplying, fitting, fixing & installation of expansion joints as indicated on the drawing and conforming to the following specifications and as directed by the E-I-C.

4.11.06.01

Providing expansion joints between the breast walls (abutment top wall) and girders or in between the girders with steel sheet and filling the gap with sand and bitumen (80/100) as per design, drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

MS Angle, Flat bar, Z bar

1.0000

kg

59.00

59.00

Bitumen [Grade 80/100]

0.0300

kg

49.00

1.47

Sand (FM - 0.8)

0.0070

m3

480.00

3.36 63.83

Subtotal-A: Welding, fitting, fixing etc.

( +100.00 % on Subtotal-A )

Subtotal-A1:

127.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

130.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

143.23

VAT

6% of Total

IT

4% of Total

9.55 6.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

63.83

159.15

Page: 722 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.06.02

Detailed Analysis Brief Description of Item 2 Strip Seal Expansion Joint: Providing and laying of Strip Seal type bridge deck expansion joint catering to maximum horizontal movement up to 80 mm including all materials (edge beams, Strip seal, anchorage, angle, bar, plate etc.), installation in proper position, labour charges, testing, handling, tools, equipment etc. all complete as per approved drawing, specification and direction of the E-I-C. The Installation shall be done by the manufacturer/ supplier or their authorised representative ensuring compliance to the manufacturer's instruction for installation. [The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC Deck.]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Supply of complete assembly of strip seal expansion joint comprising of edge beams, anchorage, strip seal element and complete accessories as per approved specifications and drawings.

1.0000

m

15200.00

15200.00

Mason

0.0042

day

550.00

2.31

Skilled Labour

0.0208

day

450.00

9.36

Ordinary Labour

0.0833

day

370.00

30.82 15242.49

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

762.12 16004.62

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16324.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17957.18

VAT

6% of Total

IT

4% of Total

1197.15 798.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19952.42

Page: 723 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.11.06.03

Modular Strip/ Box Seal Expansion Joint: Providing and laying of modular strip/ Box seal expansion joint catering to maximum horizontal movement beyond 80 mm and up to 240 mm including all materials, installation in proper position, labour charges, testing, handling, tools, equipment etc. all complete as per drawing, specification and direction of the E-I-C. The anchoring bars of the expansion joint assembly shall be welded to the main reinforcement of the deck. The installation shall be done by the manufacturer/ supplier or their authorised representative ensuring compliance to the manufacturer's instruction for installation. [The concreting for joining the expansion joint assembly with the deck has not been included in this analysis as the same is catered in the quantities of RCC Deck.]

4.11.06.03.01

Modular Strip Expansion: beyond 80 mm and up to 160 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Modular strip expansion joint comprising of edge beams, central beam, 2 modules chloroprene seal, anchorage elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer (+80 to 160mm)

1.0000

m

80000.00

Mason

0.0042

day

550.00

2.31

Skilled Labour

0.0333

day

450.00

14.99

Ordinary Labour

0.0833

day

370.00

30.82

80000.00

80048.12

Subtotal-A: Fitting, fixing & Installation Charge

( +5.00 % on Subtotal-A )

Subtotal-A1:

4002.41 84050.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

85731.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

94304.69

VAT

6% of Total

IT

4% of Total

6286.98 4191.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

104782.98

Page: 724 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.06.03.02

Detailed Analysis Brief Description of Item 2 Modular Strip Expansion: beyond 160 mm and up to 240 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Modular strip expansion joint comprising of edge beams, central beam, 2 modules chloroprene seal, anchorage elements, support and control system, all steel sections protected against corrosion and installed by the manufacturer (+160 to 240mm)

1.0000

m

Mason

0.0058

day

550.00

3.19

Skilled Labour

0.0417

day

450.00

18.77

Ordinary Labour

0.1042

day

370.00

38.55

120000.00

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Roller bearing with required numbers of rollers, plate and other fittings

Note : Rates of all items should be inclusive of all supply and carriage.

6003.03 126063.53

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

128584.81

10% Profit ( Add 10% on Subtotal-B) :

141443.29

VAT

6% of Total

IT

4% of Total

9429.55 6286.37 Total:

4.11.07.01

120000.00

120060.51 Steel Formwork/ shuttering, prop with necessary supports etc.

Supplying, fitting and fixing bridge bearings including cost of all materials, labour, welding and carrying etc. complete in all respect as per design, drawing, specification and direction of the E-I-C.

8

m

Subtotal-A:

4.11.07

Amount

157159.21

Page: 725 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.07.01.01

Detailed Analysis Brief Description of Item 2 Each set up to 150 mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg MS Plate (8mm thick)

0.5000

kg

70.00

35.00

Roller Bearing (150mm dia)

0.5000

kg

125.00

62.50

MS Angle, Flat bar, Z bar

0.1700

kg

59.00

10.03

Skilled Labour

0.3100

day

450.00

139.50 247.03

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

251.97

10% Profit ( Add 10% on Subtotal-B) :

277.17

VAT

6% of Total

IT

4% of Total

18.48 12.32 Total:

4.11.07.01.02

Each set beyond 150 mm diameter

kg MS Plate (8mm thick)

0.5000

kg

70.00

35.00

Roller Bearing (beyond 150mm dia)

0.5000

kg

150.00

75.00

MS Angle, Flat bar, Z bar

0.1700

kg

59.00

10.03

Skilled Labour

0.6000

day

450.00

270.00 390.03

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

397.83

10% Profit ( Add 10% on Subtotal-B) :

437.61

VAT

6% of Total

IT

4% of Total

29.17 19.45 Total:

4.11.07.02

307.96

486.24

Hinge plate bearing with lead plates and other fittings

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 726 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.07.02.01

Detailed Analysis Brief Description of Item 2 Each set with plate up to 25 mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

kg Hinge Plate Bearing (25mm dia)

0.6860

kg

275.00

188.65

Lead Sheet

0.1900

kg

350.00

66.50

MS Rod (Plain, 40 Grade)

0.1300

kg

45.00

5.85

MS Angle, Flat bar, Z bar

0.0800

kg

59.00

4.72

Skilled Labour

0.2000

day

450.00

90.00 355.72

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

362.83

10% Profit ( Add 10% on Subtotal-B) :

399.12

VAT

6% of Total

26.61

IT

4% of Total

17.74 Total:

4.11.07.02.02

Each set with plate beyond 25 mm thick

kg Hinge Plate Bearing (beyond 25mm dia)

0.6860

kg

335.00

229.81

Lead Sheet

0.1900

kg

350.00

66.50

MS Rod (Plain, 40 Grade)

0.1300

kg

45.00

5.85

MS Angle, Flat bar, Z bar

0.0800

kg

59.00

4.72

Skilled Labour

0.2000

day

450.00

90.00 396.88

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

404.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

445.30

VAT

6% of Total

IT

4% of Total

29.69 19.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

443.46

494.78

Page: 727 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.11.07.03

Free plate bearing with lead plates and other fittings

4.11.07.03.01

Each set with plate up to 25 mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg MS Plate Bearing (upto 25mm thick)

0.6860

kg

59.40

40.75

Lead Sheet

0.1900

kg

350.00

66.50

MS Rod (Plain, 40 Grade)

0.1300

kg

45.00

5.85

MS Angle, Flat bar, Z bar

0.0800

kg

59.00

4.72

Skilled Labour

0.2000

day

450.00

90.00 207.82

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

211.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

233.17

VAT

6% of Total

15.54

IT

4% of Total

10.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

259.08

Page: 728 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.07.03.02

Detailed Analysis Brief Description of Item 2 Each set with plate beyond 25 mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg MS Plate Bearing (beyond 25mm thick)

0.6860

kg

64.80

44.45

Lead Sheet

0.1900

kg

350.00

66.50

MS Rod (Plain, 40 Grade)

0.1300

kg

45.00

5.85

MS Angle, Flat bar, Z bar

0.0800

kg

59.00

4.72

Skilled Labour

0.2000

day

450.00

90.00 211.52

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

215.75

10% Profit ( Add 10% on Subtotal-B) :

237.33

VAT

6% of Total

15.82

IT

4% of Total

10.55 Total:

4.11.07.04

Hinge plate bearing with lead sheets including fitting & fixing

kg MS Plate (8mm thick)

0.6860

kg

70.00

48.02

Lead Sheet

0.1900

kg

350.00

66.50

MS Rod (Plain, 40 Grade)

0.1300

kg

45.00

5.85

MS Angle, Flat bar, Z bar

0.0800

kg

59.00

4.72

Skilled Labour

0.2000

day

450.00

90.00 215.09

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

219.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

241.33

VAT

6% of Total

IT

4% of Total

16.09 10.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

263.70

268.15

Page: 729 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.08

Detailed Analysis Brief Description of Item 2 SLEB: Supplying, fitting and fixing steel-laminated Elastomeric/ Neoprene bearings (preferably from Mageba, VSL, Tensa, Watson or equivalent) in exact positions as per drawing, specifications and direction of the E-I-C including cost of all materials, labour, carrying etc. The set shall be of 100% virgin Chloroprene Rubber (CR), grades of raw elastomer of proven use in elastomeric bearings, with low crystallization rates and adequate shelf life viz. Neoprene WRT, Neoprene W, Bayprene 110, Bayprene 210, Skyprene B-5, Skyprene B-30, Denka S40V and Denka M-40, shall be used. No reclaimed rubber or Vulcanized wastes or natural rubber shall be used. Use of synthetic rubber-like materials such as Ethyl Propylene Dimonomer (EPDM), Isobutane Isoprene Copolymer (IIR) and Chloro-Isoprene Copolymer (CIIR) shall not be permitted. Laboratory test to be performed from BUET, Dhaka for Elastomer hardness limits determined in accordance with ASTM D 2240 shall be 60 ± 5 duro, minimum tensile strength determined in accordance with ASTM D 412 shall be 17 MPa, ultimate elongation determined in accordance with ASTM D 412 shall be minimum 400%, compression set value after 22 hours at 100 degree centigrade determined in accordance with ASTM D 395 Method B shall be maximum 35%, Elastomeric content determined in accordance with ASTM D 297 shall not be less than 60%, Ash content determined in accordance with ASTM D 297 shall not exceed 5%, Shear modulus of elastomeric bearing determined in accordance with ASTM D 4014 shall neither be less than 0.8 MPa nor greater than 1.2 MPa, the adhesion strength of elastomer to steel plates (Peel Strength) determined in accordance with ASTM D 429 Method B shall not be less than 7kN/m. One set of Elastomeric Bearing must be taken as extra for laboratory test.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cucm

Elastomeric/Neoprene Bearing

1.0000

cm3

1.73

1.73

Foreman

0.0001

day

800.00

0.08

Skilled Labour

0.0001

day

450.00

0.05

Ordinary Labour

0.0002

day

370.00

0.07 1.93

Subtotal-A: Add 15% of cost of bearing assembly for foundation anchorage bolts and comsumables Subtotal-A1: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +15.00 % on Subtotal-A )

0.29 2.22 Page: 730 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

4.11.09

Filling of expansion joints upto a depth of 40 mm with bitumen mixed with coarse sand (FM ≥ 2.5) in concrete works including supply of all materials etc. complete as per specification and direction of E-I-C.

4.11.09.01

25mm wide

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2.49

VAT

6% of Total

IT

4% of Total

0.17 0.11 Total:

2.77

m Sand (FM - 2.5)

0.0010

m3

1500.00

1.50

Bitumen [Grade 80/100]

0.5412

kg

49.00

26.52

Fire wood

0.6560

kg

7.75

5.08

Skilled Labour

0.0246

day

450.00

11.07

Ordinary Labour

0.0492

day

370.00

18.20 62.38

Subtotal-A: Miscellaneous Sundry etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3.12 65.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.81

10% Profit ( Add 10% on Subtotal-B) :

73.49

VAT

6% of Total

IT

4% of Total

4.90 3.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

81.65

Page: 731 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.11.09.02

2 20mm wide

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.0008

m3

1500.00

1.20

Bitumen [Grade 80/100]

0.4330

kg

49.00

21.22

Fire wood

0.5248

kg

7.75

4.07

Skilled Labour

0.0197

day

450.00

8.87

Ordinary Labour

0.0394

day

370.00

14.58 49.93

Subtotal-A: Miscellaneous Sundry etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2.50 52.42

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

53.47

10% Profit ( Add 10% on Subtotal-B) :

58.82

VAT

6% of Total

3.92

IT

4% of Total

2.61 Total:

4.11.10

Amount

65.35

POT Bearing: Supplying, fitting and fixing in position true to line and level free/ fixed/guided POT-PTFE bearing consisting of a metal piston supported by a disc or unreinforced elastomer confined within a metal cylinder, sealing rings, dust seals, PTFE surface sliding against stainless steel mating surface, complete assembly to be of cast steel/fabricated structural steel, metal and elastomer elements to be as per AASHTO Specifications and direction of the E-I-C. One set must be taken as extra for laboratory test which to be performed from BUET.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 732 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.10.01

Detailed Analysis Brief Description of Item 2 PBG: Guided/ Free Type Pot Bearing

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

780.00

780.00

MT Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel mating together with fabricated structural steel assemblies duly painted with all components Guided/ Free Type

1.0000

each

Head Mason

0.0006

day

650.00

0.39

Skilled Labour

0.0034

day

450.00

1.53

Ordinary Labour

0.0103

day

370.00

3.81 785.73

Subtotal-A: Cost of bearing assembly for foundation achorage bolts and comsumables

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

39.29 825.02

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

841.52

10% Profit ( Add 10% on Subtotal-B) :

925.67

VAT

6% of Total

IT

4% of Total

61.71 41.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1028.52

Page: 733 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.11.10.02

2 PBF: Fixed Type Pot Bearing

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT

470.00

470.00

MT Pot type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel mating together with fabricated structural steel assemblies duly painted with all components Fixed Type

1.0000

Head Mason

0.0003

day

650.00

0.20

Skilled Labour

0.0022

day

450.00

0.99

Ordinary Labour

0.0065

day

370.00

2.41 473.59

Subtotal-A: Cost of bearing assembly for foundation achorage bolts and comsumables

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

23.68 497.27

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

507.21

10% Profit ( Add 10% on Subtotal-B) :

557.94

VAT

6% of Total

IT

4% of Total

37.20 24.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

619.93

Page: 734 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.11

Detailed Analysis Brief Description of Item 2 Spherical Bearing: Supplying fitting and fixing in position true to line and level cast steel spherical/ cylindrical type bearing with stainless steel plate with PTFE sliding surface as per AASHTO specification complete with all accessories as per drawing and direction of E-I-C and including cost of all material installation. One set must be taken as extra for laboratory test which to be performed from BUET.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT

825.00

825.00

MT

Spherical type bearing assembly consisting of a metal piston supported by a disc, PTFE pads providing sliding surfaces against stainless steel mating together with fabricated structural steel assemblies duly painted with all components

1.0000

Head Mason

0.0003

day

650.00

0.20

Skilled Labour

0.0017

day

450.00

0.77

Ordinary Labour

0.0050

day

370.00

1.85 827.81

Subtotal-A: Cost of bearing assembly for foundation achorage bolts and comsumables

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

41.39 869.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

886.58

10% Profit ( Add 10% on Subtotal-B) :

975.24

VAT

6% of Total

IT

4% of Total

65.02 43.34 Total:

4.11.12

Amount

1083.60

STU: Providing and fitting in position true to line and level shock transmission unit as per AASHTO specification complete with all accessories as per drawing and direction of Engineer-in-charge and including cost of all material for installation. The installation shall be done by the manufacturer/ supplier or their authorised representative ensuring compliance to the manufacturer's instruction for installation.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 735 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.12.01

Detailed Analysis Brief Description of Item 2 STU_50: Up to 50 MT of Horizontal Load

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT Shock Tramission Unit (For Horizontal Load <= 50 MT)

1.0000

MT

30500.00

30500.00

Head Mason

0.0286

day

650.00

18.59

Mason

0.0286

day

550.00

15.73

Skilled Labour

0.0571

day

450.00

25.70

Ordinary Labour

0.1143

day

370.00

42.29 30602.31

Subtotal-A: Cost of temporary works (staging etc.), Anchorage Bolts, Grout, Concrete and rent of Equipment, Machinery, tools etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

1530.12

32132.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32775.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

36052.58

VAT

6% of Total

2403.51

IT

4% of Total

1602.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

40058.42

Page: 736 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.11.12.02

Detailed Analysis Brief Description of Item 2 STU_50+: Above 50 MT of Horizontal Load

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT Shock Tramission Unit (For Horizontal Load >= 50 MT)

1.0000

MT

23000.00

23000.00

Head Mason

0.0125

day

650.00

8.13

Mason

0.0125

day

550.00

6.88

Skilled Labour

0.0250

day

450.00

11.25

Ordinary Labour

0.0500

day

370.00

18.50 23044.75

Subtotal-A: Cost of temporary works (staging etc.), Anchorage Bolts, Grout, Concrete and rent of Equipment, Machinery, tools etc.

( +3.00 % on Subtotal-A )

Subtotal-A1:

691.34

23736.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24210.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26631.90

VAT

6% of Total

1775.46

IT

4% of Total

1183.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

29591.00

Page: 737 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying and mixing specified type chemical admixture delivered from an authorized local agent or manufacturer, comply with the ASTM C 494 requirements, confirming the current compliance of the admixture to specification requirements like physical properties, unifomity and equivalence in composition etc., performance (water content, fresh concrete setting time and compressive strength) requirements, delivered in sealed water-tight containers having and confirming plainly marked the proprietary name of the admixture, type under this specification, net weight or volume, manufacturing and expiry date, non aggressiveness to environment, aggregates and metals in concrete etc. and mixing the admixture in non prestressed cement concrete mixture in the field under the strict accordance with manufacturers recommendation and instruction, providing safety provisions in all respects etc. all complete as per instruction and approved by the E-I-C. Dose (quantity in milliliters per 50 kg bag cement) and brand/origin/manufacturer with respect to particular brand of cement and particular stock of aggregates and method of use to be determined by mix design/ trial mix at the cost borne by the Contractor and shall be carried out prior to start the work. Note: The minimum cement specified shall not be reduced on account of the use of admixtures. Use of admixture is subject to prior approval of Central Quality Control Laboratory (CQCL), LGED or any specified laboratory approved by the Engineer.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 738 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.01.01

Detailed Analysis Brief Description of Item 2 Supply and use of water reducing chemical admixture in concrete, complying to ASTM C 494 Type - A of approved brand/ origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces quantity of mixing water required to produce concrete of a given consistency.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

130.00

130.00

litre

Water reducing chemical admixture : Type-A

1.0000

liter

130.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.20 135.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

137.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

151.69

VAT

6% of Total

10.11

IT

4% of Total

6.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

168.55

Page: 739 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.01.02

Detailed Analysis Brief Description of Item 2 Supply and use of retarding chemical admixture in concrete, complying to ASTM C 494 Type B of approved brand/origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that retards the setting of concrete, there by reducing shrinkage in concrete specially for concrete laid in thick layers and intended delayed construction for improved construction joints, reconcreting etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

125.00

125.00

litre

Retrading chemical admixture : Type-B

1.0000

liter

125.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.00 130.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145.86

VAT

6% of Total

9.72

IT

4% of Total

6.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

162.07

Page: 740 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.01.03

Detailed Analysis Brief Description of Item 2 Supply and use of accelerating chemical admixture in concrete, complying to ASTM C 494 Type C of approved brand/origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that accelerates the setting time and early strength developmnet of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

135.00

135.00

litre

Accelerating chemical admixture : Type-C

1.0000

liter

135.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.40 140.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

143.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

157.53

VAT

6% of Total

10.50

IT

4% of Total

7.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

175.03

Page: 741 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.01.04

Detailed Analysis Brief Description of Item 2 Supply and use of water-reducing and retarding chemical admixture in concrete, complying to ASTM C 494 Type D of approved brand/ origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces the quantity of mixing water required to produce concrete of a given consistency i.e. low w/c ratio and retards the setting of concrete specially for layerd, thick laid concrete etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

125.00

125.00

litre

Water-reducing and retrading chemical admixture : Type-D

1.0000

liter

125.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.00 130.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145.86

VAT

6% of Total

9.72

IT

4% of Total

6.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

162.07

Page: 742 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.01.05

Detailed Analysis Brief Description of Item 2 Supply and use of water-reducing and accelerating chemical admixture in concrete, complying ASTM C 494 Type E of approved brand/origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces the quantity of mixing water required to produce concrete of a given consistency i.e. low w/c ratio and accelerates setting and early strength development of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

135.00

135.00

litre

Water-reducing and accelerating chemical admixture : Type-E

1.0000

liter

135.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1:

5.40 140.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

143.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

157.53

VAT

6% of Total

10.50

IT

4% of Total

7.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

175.03

Page: 743 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.01.06

Detailed Analysis Brief Description of Item 2 Supply and use of water-reducing high range chemical admixture in concrete, complying to ASTM C 494 Type F of approved brand/origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces the quantity of mixing water required to produce concrete of a given consistency by 12 or greater (flowing concrete) and for higher strength of concrete

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

160.00

160.00

litre

Water-reducing high range chemical admixture : Type-F

1.0000

liter

160.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6.40 166.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.73

10% Profit ( Add 10% on Subtotal-B) :

186.70

VAT

6% of Total

IT

4% of Total

12.45 8.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

207.45

Page: 744 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.01.07

Detailed Analysis Brief Description of Item 2 Supply and use of water-reducing high range and retarding chemical admixture in concrete, complying to ASTM C 494 Type G of approved brand/ origin/ manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin. An admixture that reduces the quantity of mixing water required to produce concrete of a given consistency by 12% or greater (flowing concrete) and retards setting of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

160.00

160.00

litre

Water-reducing high range and retrading chemical admixture : Type-G

1.0000

liter

160.00

Subtotal-A: Carriage, safe storage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6.40 166.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.73

10% Profit ( Add 10% on Subtotal-B) :

186.70

VAT

6% of Total

IT

4% of Total

12.45 8.30 Total:

4.12.02

Amount

207.45

Providing Film Galvanizing Compound having 96% of zinc (purity is 99.99%), corrosion rate shall be less than 0.05mm per year, solid content shall not be more than 40% by volume and relative density shall not more than 2.70 gm/cc and should be complied the international test result like salt spray test, frame test, weathering test and humidity test. Shelf and drying time shall not be more than 25 minuities for the cathodic (galvanic/sacrificial) protection of all steel structure for a specified time against formation of rust and corrosion. All complete as per direction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 745 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.02.01

Detailed Analysis Brief Description of Item 2 20 Micron Film Galvanizing Compound for minimum 5 years protection against rust & corrosion.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Film Galvanizing Compound

0.1650

kg

4550.00

750.75

Water Paper

1.0000

Emery Paper

0.5000

each

22.00

22.00

each

21.00

10.50

Wire Brush

0.1000

each

50.00

5.00

Scrapper

0.1000

each

55.00

5.50

Chissel

0.1000

each

65.00

6.50

Roll Brush

0.0500

each

50.00

2.50

Jute

0.0800

kg

20.00

1.60

Markin cloth

0.0800

m

10.00

0.80

Hand Gloves

0.0300

Pair

130.00

3.90

Galvanize Coating Expert

0.0200

day

800.00

16.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Skilled Technician

0.0500

day

680.00

34.00

Semi Skilled Technician

0.0500

day

570.00

28.50 921.55

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

939.98 1033.98

10% Profit ( Add 10% on Subtotal-B) :

VAT

68.93 45.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1148.87

Page: 746 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.02.02

Detailed Analysis Brief Description of Item 2 40 Micron Film Galvanizing Compound for minimum 10 years protection against rust & corrosion.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Film Galvanizing Compound

0.3300

kg

4550.00

1501.50

Water Paper

1.0000

Emery Paper

0.5000

each

22.00

22.00

each

21.00

10.50

Wire Brush

0.1000

each

50.00

5.00

Scrapper

0.1000

each

55.00

5.50

Chissel

0.1000

each

65.00

6.50

Roll Brush

0.1000

each

50.00

5.00

Jute

0.1000

kg

20.00

2.00

Markin cloth

0.1000

m

10.00

1.00

Hand Gloves

0.0500

Pair

130.00

6.50

Galvanize Coating Expert

0.0400

day

800.00

32.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Skilled Technician

0.1600

day

680.00

108.80

Semi Skilled Technician

1.0000

day

570.00

570.00 2344.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2391.19

10% Profit ( Add 10% on Subtotal-B) :

2630.30

VAT

6% of Total

IT

4% of Total

175.35 116.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2922.56

Page: 747 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.02.03

Detailed Analysis Brief Description of Item 2 40 Micron Film Galvanizing Compound including top coat of Polyurethane combined with micaceous iron oxide (MIO), aluminium and magnesium silicate for minimum 10 years protection against rust & corrosion.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Film Galvanizing Compound

0.3300

kg

4550.00

1501.50

Water Paper

1.0000

Emery Paper

0.5000

each

22.00

22.00

each

21.00

10.50

Wire Brush

0.1000

each

50.00

5.00

Scrapper

0.1000

each

55.00

5.50

Chissel

0.1000

each

65.00

6.50

Roll Brush

0.1000

each

50.00

5.00

Jute

0.1000

kg

20.00

2.00

Markin cloth

0.1000

m

10.00

1.00

Hand Gloves

0.0500

Pair

130.00

6.50

Galvanize Coating Expert

0.0400

day

800.00

32.00

Plumber/ Electric Mistry/ Painter

0.0800

day

680.00

54.40

Skilled Technician

0.1600

day

680.00

108.80

Semi Skilled Technician

1.0000

day

570.00

570.00

Polyurethane with micaceous iron oxide

0.0900

liter

6000.00

540.00

Rust & Paint Removing Solution

0.1000

liter

400.00

40.00

Ditergent Powder

0.0500

kg

180.00

9.00 2919.70

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2978.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3275.90

VAT

6% of Total

IT

4% of Total

218.39 145.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3639.89 Page: 748 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.12.03

Detailed Analysis Brief Description of Item 2 CCC: Supplying and spraying liquid membrane-forming water/resin based concrete curing compounds conforming to ASTM C 309/ AASHTO M 148 on freshly cast concrete or newly exposed concrete surfaces immediately after removal of shuttering or after initial moist curing at a rate of 5.0 m2/L or in accordance with the manufacturer's instructions to form a thin continuous firm barrier/ temporary membrane which will retain sufficient moisture for effective curing to take place during the early-hardening period without disturbing the normal setting action of concrete including labour, equipment, other incidental charges etc. all complete as per specification and direction of E-I-C. The curing compound shall exhibit water loss not more than 0.55 Kg/m2 in 72 hours when tested as per ASTM C 156, shall exhibit a daylight reflectance of not less than 60% when tested as per ASTM E 1347 and shall dry to touch in not more than 4 hours. [This unit rate includes 10% extra curing compound for overlaps and wastage.]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Water based Concrete Curing Compound conforming to ASTM C 309/ AASHTO M 148

0.2200

Liter

400.00

88.00

Skilled Labour

0.0500

day

450.00

22.50 110.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

112.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

123.98

VAT

6% of Total

8.27

IT

4% of Total

5.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

137.76

Page: 749 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.01

Detailed Analysis Brief Description of Item 2 CWC: Providing and laying wearing course on deck slab of bridge with minimum cement content ralates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 33.5 MPa and satisfying a compressive strength f'c = 25 MPa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/AL/M/V/W 42.5N, Coarse sand of minimum FM 2.5 and 6mm down well graded crushed stone chips broken from boulders (preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30), including breaking stone boulders into chips, screening through proper sieves, casting, finishing complete to camber and grade, compacting, curing at least for 28 days, etc. including cost and carriage of all materials, labour, water, electricity, other incidental cost etc. all complete as per design, drawing, specification & directionn of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (6mm down graded) [LAA≤30]

0.8200

m3

3800.00

3116.00

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water reducing chemical admixture : Type-A

1.9275

liter

130.00

250.58

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.1000

day

370.00

407.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8481.38

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8651.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9516.10

VAT

6% of Total

634.41

IT

4% of Total

422.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10573.45

Page: 750 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.13.02

RWDP: Providing & fixing rainwater down pipes including cost of all materials, labours, equipment, transportation, fixtures, accessories etc. at any level as per specification, drawings and direction of the E-I-C.

4.13.02.01

RWDP40GI: 40mm dia GI pipe of 2.90mm wall thickness conforming to BDS 1031/ BS 1387 Light Class

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 40mm dia GI pipe wall thickness 2.90mm

1.0000

m

380.48

380.48

Skilled Labour

0.0800

day

450.00

36.00 416.48

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

424.81

10% Profit ( Add 10% on Subtotal-B) :

467.29

VAT

6% of Total

31.15

IT

4% of Total

20.77 Total:

4.13.02.02

RWDP50GI: 50mm dia GI pipe of 2.90mm wall thickness conforming to BDS 1031/ BS 1387 Light Class

m 50mm dia GI pipe wall thickness 2.90mm

1.0000

m

457.42

457.42

Skilled Labour

0.0900

day

450.00

40.50 497.92

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

507.88

10% Profit ( Add 10% on Subtotal-B) :

558.67

VAT

6% of Total

37.24

IT

4% of Total

24.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

519.21

620.74

Page: 751 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.02.03

Detailed Analysis Brief Description of Item 2 RWDP65GI: 65mm dia GI pipe of 3.25mm wall thickness conforming to BDS 1031/ BS 1387 Light Class

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 65mm dia GI pipe wall thickness 3.25mm

1.0000

m

701.10

701.10

Skilled Labour

0.1000

day

450.00

45.00 746.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

761.02

10% Profit ( Add 10% on Subtotal-B) :

837.12

VAT

6% of Total

IT

4% of Total

55.81 37.21 Total:

4.13.02.04

RWDP80GI: 80mm dia GI pipe of 3.25mm wall thickness conforming to BDS 1031/ BS 1387 Light Class

m 80mm dia GI pipe wall thickness 3.25mm

1.0000

m

784.90

784.90

Skilled Labour

0.1100

day

450.00

49.50 834.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

851.09

10% Profit ( Add 10% on Subtotal-B) :

936.20

VAT

6% of Total

IT

4% of Total

62.41 41.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

930.14

1040.22

Page: 752 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.02.05

Detailed Analysis Brief Description of Item 2 RWDP100GILC: 100mm dia GI pipe of 3.65mm wall thickness conforming to BDS 1031/ BS 1387 Light Class

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 100mm dia GI pipe wall thickness 3.65mm

1.0000

m

1132.88

1132.88

Skilled Labour

0.1100

day

450.00

49.50 1182.38

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1206.03

10% Profit ( Add 10% on Subtotal-B) :

1326.63

VAT

6% of Total

IT

4% of Total

88.44 58.96 Total:

4.13.02.06

RWDP100GIMC: 100mm dia GI pipe of 4.05mm wall thickness conforming to BDS 1031/ BS 1387 Medium Class

m 100mm dia GI pipe wall thickness 4.05mm

1.0000

m

1660.00

1660.00

Skilled Labour

0.1100

day

450.00

49.50 1709.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1743.69

10% Profit ( Add 10% on Subtotal-B) :

1918.06

VAT

6% of Total

IT

4% of Total

127.87 85.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1474.03

2131.18

Page: 753 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.13.02.07

RWDP50PVC: 50mm uPVC Pipe of 2.5mm to 3mm wall thickness conforming to BS 3505

m

Quantity 5

Unit

Rate

6

7

Amount 8

50mm PVC Pipe-2.5mm to 3mm wall thick

1.0000

m

93.00

93.00

Skilled Labour

0.0400

day

450.00

18.00 111.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

113.22

10% Profit ( Add 10% on Subtotal-B) :

124.54

VAT

6% of Total

IT

4% of Total

8.30 5.54 Total:

4.13.02.08

RWDP75PVC: 75mm uPVC Pipe of 2.9mm to 3.4mm wall thickness conforming to BS 3505

m 75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00

Skilled Labour

0.0450

day

450.00

20.25 185.25

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

188.96

10% Profit ( Add 10% on Subtotal-B) :

207.85

VAT

6% of Total

IT

4% of Total

13.86 9.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

138.38

230.95

Page: 754 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.03

Detailed Analysis Brief Description of Item 2 BF: Back filling behind abutments, wing walls and retaining walls with selected granular material (50:50 best quality picked brick chips & sand of min. FM 1.00) of minimum 450 mm width, in layers of 150 mm thickness free from dust, impurities etc. including compaction using plate compactor, watering & dressing, supply & cost of all materials, carrying and labour, hire charge of plate compactor and other tools etc. all complete as per direction of the Engineer-In-Charge. Payment to be made for the compacted volume only for a compaction of 90% of the maximum dry density.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Picked Brick Bats

0.6650

m3

2150.00

1429.75

Sand (FM - 1.0) Ordinary Labour

0.6650

m3

567.00

377.06

0.5000

day

370.00

185.00

H.C. of Plate Compactor (LF-72)

0.0313

day

850.00

26.61

H.C. of Water Tanker (Truck Mounted)

0.0020

day

2500.00

5.00 2023.41

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2063.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2270.27

VAT

6% of Total

151.35

IT

4% of Total

100.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2522.52

Page: 755 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.04

Detailed Analysis Brief Description of Item 2 WH: Providing weep holes in Brick masonry/ Plain/ Reinforced concrete retaining wall, abutment, wing/ return wall, with 50 - 100 mm dia PVC pipe extending through the full width of structure with slope 1V : 20H towards draining face including hand packing of 0.85 cum pervious backfill material (40mm - 63mm sized 1st class/picked brick) wrapped in filter fabric in the back of each weep hole etc. all compete as per direction of the E-I-C. [Cost of PVC pipe is included in this item and shall not be paid separately.]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

1st Class Brick Chips (20mm down graded)

0.0850

m3

2940.00

249.90

75mm PVC Pipe -2.9mm to 3.4mm wall thick

0.6000

m

165.00

99.00

Sand (FM - 0.8)

0.0270

m3

480.00

12.96

Empty Gunny Bag

1.0000

each

30.00

30.00

Skilled Labour

0.1000

day

450.00

45.00 436.86

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

445.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

490.16

VAT

6% of Total

32.68

IT

4% of Total

21.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

544.62

Page: 756 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.05

Detailed Analysis Brief Description of Item 2 DS: Supplying, fitting and fixing in position galvanized drainage spouts for bridge decks made up by minimum 100mm dia. MS pipe of 4.05mm wall thickness conforming to BDS 1031/ BS 1387 Medium Class, grating formed by 262mm x 262mm top rim of 32mm X 28mm ASTM A36 complied MS rectangular bars and 4 nos. 198mm X 12mm X 25mm ASTM A36 complied MS flat bars, square shaped collection pit of 210mm X 210mm made up by 6mm thick ASTM A36 complied MS plate with necessary anchorage and fixing the grating frame by minimum 6 nos. of 10mm dia. bolts and other necessary fittings including all labour, tools, plant, equipment, machinery, leads & lifts, fuel, electric charges etc. complete in all respectas as per drawing, specifications and direction of Engineer-in-Charge. The grating has to carry a spot load of 100 kN. Drainage spouts has to be constructed in such a way so that the gratings can be temporarily fixed to protect against theft. After fabrication, the complete assembly shall be given a hot dipped galvanized coating. [600mm MS Pipe is included in this unit rate, Extra length must be added if necessary]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

LW: Direct type Lap-welded splice over two sides of contact by welding of minimum length not less than 10 times of bar diameter …...(4.07.07.02)

0.9800

meter

374.73

367.24

18.9030

kg

58.00

1096.37

0.6000

m

1300.00

780.00

25.1380

kg

65.00

1633.97

GI bolt 10mm diameter

6.0000

each

20.00

120.00

Nails/ Nut bolts/ Screw/ Spikes

0.5000

kg

65.00

32.50

Mason

0.0100

day

550.00

5.50

Welder

0.0200

day

680.00

13.60

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.2500

day

370.00

92.50

Corrosion resistant Structural steel 100mm dia MS pipe and wall thickness 4mm Hot-dip Galvanizing in accordance with BS EN ISO 1461: 1999 with minimum coat thickness of 85 microns or 610 gm per square meter

4146.18

Subtotal-A: Cost of cutting, sealant, grinding and fabrication Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +10.00 % on Subtotal-A )

414.62 Page: 757 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

etc. Subtotal-A1:

4560.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4652.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5117.21

VAT

6% of Total

IT

4% of Total

341.15 227.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5685.79

Page: 758 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.06

Detailed Analysis Brief Description of Item 2 DG: Supplying, fitting and fixing in position galvanized drainage grating for bridge decks made up by 200mm x 150mm outer frame of 25mm x 25mm x 6mm ASTM A 36 complied MS Angles and 4 nos. 25mm x 6mm ASTM A36 complied MS flat bars, grating fitted with 4 nos. BDS ISO 6935-2: 2006 (Grade 400) complied 12mm dia. anchor bar 100mm in length by welding and other necessary fittings including all labour, tools, plant, equipment, machinery, leads & lifts, fuel, electric charges etc. complete in all respect as per drawing, specifications and direction of Engineer-in-Charge. After fabrication, grating shall be given a hot dipped galvanized coating.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

LW: Direct type Lap-welded splice over two sides of contact by welding of minimum length not less than 10 times of bar diameter …...(4.07.07.02)

0.2000

meter

374.73

74.95

Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS ISO 6935-2:2006 (Grade 400)………….(4.11.01.04)

0.3720

kg

65.67

24.43

Corrosion resistant Structural steel

1.8010

kg

58.00

104.46

Hot-dip Galvanizing in accordance with BS EN ISO 1461: 1999 with minimum coat thickness of 85 microns or 610 gm per square meter

2.1730

kg

65.00

141.25

Mason

0.0100

day

550.00

5.50

Welder

0.0100

day

680.00

6.80

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0500

day

370.00

18.50 380.38

Subtotal-A: Cost of cutting, sealant, grinding and fabrication etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

38.04 418.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

426.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

469.46

VAT

6% of Total

IT

4% of Total

31.30 20.87 Page: 759 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 4.13.07

PS: Providing cork sheet/ polystyrene sheet in expansion joints of concrete works including supply of all materials etc. complete as per direction of E-I-C.

4.13.07.01

PS_25 mm thick sheet

sqm Cork/ Polystyrene Sheet (25mm thick)

1.0000

sqm

160.00

160.00

Skilled Labour

0.1000

day

450.00

45.00 205.00

Subtotal-A: Miscellaneous Sundry etc.

( +1.00 % on Subtotal-A )

Subtotal-A1:

2.05 207.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

211.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

232.31

VAT

6% of Total

IT

4% of Total

15.49 10.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

521.63

258.12

Page: 760 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.13.07.02

2 PS_20 mm thick sheet

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Cork/ Polystyrene Sheet (20mm thick)

1.0000

sqm

550.00

550.00

Skilled Labour

0.1000

day

450.00

45.00 595.00

Subtotal-A: Miscellaneous Sundry etc.

( +1.00 % on Subtotal-A )

Subtotal-A1:

5.95 600.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

612.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

674.27

VAT

6% of Total

44.95

IT

4% of Total

29.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

749.18

Page: 761 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.08

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

MA: Providing and laying mastic asphalt wearing course on top of deck slab excluding prime/tack coat with 10/20 penetration grade bitumen satisfying the requirements of ASTM/AASHTO code, coarse aggregate should be crushed stone chips (LAA value <=30) complying with the specified grading requirement of the relevant item of Road Design Standard - 2005, water absorption not >2%, flakiness index not > 35%, fine aggregate shall be the fraction passing the 2.36mm and retained on the 0.075mm sieve, filler shall be limestone powder passing 75 micron sieve and shall have a calcium carbonate content of not < 80%, prepared by using mastic cooker and laid to required level and slope after cleaning the surface, including hire charges of all tools, plants and machinery, wages of operational staff, cost of fuel & lubricants and all other incidental charges all complete as per design, specification and direction of Engineer-in-Charge. The contractor shall submit to the Engineer for approval at least one month before the start of the work the job mix formula proposed to be used by him for the work. [Excluding the cost of applying Prime/Tack coat] Notes: 1. Where prime/tack coat is required to be provided before laying mastic asphalt, the same is required to be measured and paid separately. The rate for prime/tack coat shall be taken from Road Works. 2. Bituminous wearing course of specified thickness shall be overlaid with this mastic asphalt and the rate for bituminous wearing course shall be taken from Road Works.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 762 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.08.01

Detailed Analysis Brief Description of Item 2 MA_12: 12mm thick mastic asphalt wearing course

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Bitumen (Drum/Bulk) of Penetration Grade 10/20

4.8045

kg

52.00

249.83

Stone Dust (2.38mm down)

0.0092

cum

1500.00

13.80

Limestone Powder

8.4786

kg

12.00

101.74

Stone Chips (6mm down graded) [LAA≤30] Mason

0.0130

m3

3800.00

49.40

0.0115

day

550.00

6.33

Skilled Labour

0.0294

day

450.00

13.23

Ordinary Labour

0.2591

day

370.00

95.87

H.C. of Mechanical Road Sweeper Broom

0.0002

day

1000.00

0.20

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0002

Day

3000.00

0.60

H.C. of Mastic Cooker (1 tonne capacity)

0.0177

day

3000.00

53.10

H.C. of Bitumen Heater & Decanter

0.0177

day

5000.00

88.50

H.C. of Tractor (4 WD)

0.0029

day

2200.00

6.38 678.98

Subtotal-A: Other incidental charges

( +5.00 % on Subtotal-A )

Subtotal-A1:

33.95 712.93

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

727.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

799.91

VAT

6% of Total

53.33

IT

4% of Total

35.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

888.78

Page: 763 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.13.08.02

Detailed Analysis Brief Description of Item 2 MA_25: 25mm thick mastic asphalt wearing course

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Bitumen (Drum/Bulk) of Penetration Grade 10/20

5.8286

kg

52.00

303.09

Stone Dust (2.38mm down)

0.0111

cum

1500.00

16.65

10.2857

kg

12.00

123.43

Stone Chips (12mm down graded) [LAA≤30] Stone Chips (6mm down graded) [LAA≤30]

0.0079

m3

4470.00

35.31

0.0079

m3

3800.00

30.02

Mason

0.0126

day

550.00

6.93

Skilled Labour

0.0286

day

450.00

12.87

Limestone Powder

Ordinary Labour

0.2857

day

370.00

105.71

H.C. of Mechanical Road Sweeper Broom

0.0017

day

1000.00

1.70

Air compressor (screw type) 250 cfm with necessary piping arranagement and accessories.

0.0017

Day

3000.00

5.10

H.C. of Mastic Cooker (1 tonne capacity)

0.0214

day

3000.00

64.20

H.C. of Bitumen Heater & Decanter

0.0214

day

5000.00

107.00

H.C. of Tractor (4 WD)

0.0036

day

2200.00

7.92 819.93

Subtotal-A: Other incidental charges

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

41.00 860.92

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

878.14

10% Profit ( Add 10% on Subtotal-B) :

965.96

VAT

6% of Total

IT

4% of Total

64.40 42.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1073.29

Page: 764 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.14.01

Manufacturing and supplying Plain Cement Concrete (PCC) Blocks with cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, sand of minimum FM 1.5 and 40 mm down well graded shingles to attain a minimum 28 days cylinder strength of 9.00 MPa (suggested mix proporation 1:3:6) including grading, washings shingles, mixing, laying in forms, consolidating, curing for at least 21 days, including preparation of platform, shuttering and stacking in measurable stacks, cost of all materials, labour, equiptment and machinery, work at all leads and lifts, loading and unloading, transportation and all other incidental charges etc. all complete as per drawing, specification & direction of the E-I-C. Steel shutter shall be used to perform the job. [Payment shall be done after laying of PCC Blocks]

4.14.01.01

Size: 400 mm x 400 mm x 150 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0216

m3

3500.00

Sand (FM - 1.5)

0.0100

m3

795.00

7.95

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1016

bag

430.00

43.69

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0180

day

450.00

8.10

75.60

Ordinary Labour

0.0430

day

370.00

15.91

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 154.03

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

157.11

10% Profit ( Add 10% on Subtotal-B) :

172.82

VAT

6% of Total

11.52

IT

4% of Total

7.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

192.02

Page: 765 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.01.02

Detailed Analysis Brief Description of Item 2 Size: 500 mm x 500 mm x 150 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0336

m3

3500.00

117.60

Sand (FM - 1.5)

0.0170

m3

795.00

13.52

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1580

bag

430.00

67.94

Mason

0.0012

day

550.00

0.66

Skilled Labour

0.0280

day

450.00

12.60

Ordinary Labour

0.0675

day

370.00

24.98

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 239.93

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

244.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

269.20

VAT

6% of Total

IT

4% of Total

17.95 11.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

299.11

Page: 766 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.01.03

Detailed Analysis Brief Description of Item 2 Size: 500 mm x 500 mm x 200 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Stone Shingles (20mm down graded)

0.0450

m3

3500.00

157.50

Sand (FM - 1.5)

0.0230

m3

795.00

18.29

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2210

bag

430.00

95.03

Mason

0.0015

day

550.00

0.83

Skilled Labour

0.0350

day

450.00

15.75

Ordinary Labour

0.0675

day

370.00

24.98

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 315.01

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

321.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

353.44

VAT

6% of Total

IT

4% of Total

23.56 15.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

392.71

Page: 767 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.02

Detailed Analysis Brief Description of Item 2 Labour charge for protective works in laying Plain Cement Concret (PCC) blocks of different sizes including preparation, watering and ramming of base, packing the residual space between masonry & other structural members like columns, beams, slabs etc., providing opening as directed and finishing neatly around the same, works at all leads and lifts, loading and unloading, transportaiton and all other incidental charges etc. all complete as per drawing, specification & direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.3000

day

450.00

135.00

Ordinary Labour

1.3000

day

370.00

481.00 627.00

Subtotal-A: H.C for jute & bamboo

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

62.70 689.70

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

703.49

10% Profit ( Add 10% on Subtotal-B) :

773.84

VAT

6% of Total

51.59

IT

4% of Total

34.39 Total:

4.14.03

Amount

859.83

Providing brick mattressing in bridge approaches as protective work with required layer soling of 1st class/ picked bricks encased in 12 BWG galvanised wire 100mm square mesh wire net over a 25mm thick filter bed of sand (minimum FM 2.50) & brick chips (20mm down graded) mixed with proportion 1:1 including necessary earth cutting and fitting, fixing with 750mm long bamboo peg @ 1m c/c, dressing, leveling, compacting, etc. all complete in all respect as per approved design, specification and direction of E-I-C. Rate is inclusive of cost of materials, labour, equiptment & machinery, work at all leads and lifts, loading & unloading, transportation and all incidental charges in this connection.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 768 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.03.01

Detailed Analysis Brief Description of Item 2 Single Layer Soling of 1st Class/ picked bricks

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1st Class Brick

31.0000

each

9.00

279.00

Sand (FM - 2.5)

0.0180

m3

1500.00

27.00

1st Class Brick Chips (20mm down graded)

0.0180

m3

2940.00

52.92

Borak Bamboo (50mm dia)

1.5000

m

30.00

45.00

GI Wire Net (12 BWG) [Rhombus Size 75mm]

2.0000

m2

100.00

200.00

Skilled Labour

0.0310

day

450.00

13.95

Ordinary Labour

0.1820

day

370.00

67.34 685.21

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

698.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

768.81

VAT

6% of Total

IT

4% of Total

51.25 34.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

854.23

Page: 769 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.03.02

Detailed Analysis Brief Description of Item 2 Double Layer Soling of 1st Class/ picked bricks

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1st Class Brick

62.0000

each

9.00

558.00

Sand (FM - 2.5)

0.0180

m3

1500.00

27.00

1st Class Brick Chips (20mm down graded)

0.0180

m3

2940.00

52.92

Borak Bamboo (50mm dia)

1.5000

m

30.00

45.00

GI Wire Net (12 BWG) [Rhombus Size 75mm]

2.0000

m2

100.00

200.00

Skilled Labour

0.0620

day

450.00

27.90

Ordinary Labour

0.2820

day

370.00

104.34 1015.16

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1035.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1139.01

VAT

6% of Total

IT

4% of Total

75.93 50.62 Total:

4.14.04

Amount

1265.57

Supplying and placing of required layers of gunny bagged Riprap filled with cement (BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N) and Sand (minimum FM 1.00) mortar (1:8) along slopes of abutments, piers, banks of river/ khal including washing of sand, mixing in standard mixture machine, filled & tamping the bags in place, stitching bags by hand sewing machine, curing by sprinkling water over the bags including preparation of slope (bed) by cutting or filling with ramming the filled up earth to the same profile as that of the finished slope level, placing the filled gunny bags along the slope, etc. all complete in all respect as per approved design, specification and direction of the E-I-C. Rate is inclusive of cost of all materials, labour and all incidental charges in this connection.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 770 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.04.01

Detailed Analysis Brief Description of Item 2 Single layer of Gunny Bagged Riprap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sand (FM - 1.0)

0.1100

m3

567.00

62.37

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3800

bag

430.00

163.40

Empty Gunny Bag

5.0000

each

30.00

150.00

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.4000

day

370.00

148.00 529.27

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

539.86

10% Profit ( Add 10% on Subtotal-B) :

593.84

VAT

6% of Total

39.59

IT

4% of Total

26.39 Total:

4.14.04.02

Two layers of Gunny Bagged Riprap

sqm Sand (FM - 1.0)

0.2200

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

m3

567.00

124.74

0.7800

bag

430.00

335.40

10.0000

each

30.00

300.00

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.7100

day

370.00

262.70

Empty Gunny Bag

1028.34

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1048.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1153.80

VAT

6% of Total

IT

4% of Total

76.92 51.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

659.82

1282.00

Page: 771 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.14.05

Supplying best quality sal/ sundari/ gazari/ sonali/ tetul/ Jam etc. bullah piles free from rots, knots, sap and uniform in size at work site including carrying, stacking, etc. all complete as per direction of the Engineer-inCharge. Before any piling work is commenced the contractor shall submit to the engineer full details of the pile driving equipment and the method he intends to use in carrying out the work. Diameter of bullah pile to be measured at a distance of 1.5m from the thicker end.

4.14.05.01

Bullah piles of 150mm to 200mm diameter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m Shal/sundari/gazari Bullah (150mm to 200mm)

1.0000

m

225.00

225.00

Ordinary Labour

0.0200

day

370.00

7.40 232.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

237.05

10% Profit ( Add 10% on Subtotal-B) :

260.75

VAT

6% of Total

17.38

IT

4% of Total

11.59 Total:

4.14.05.02

Bullah piles of 200mm to 250mm diameter

m Shal/sundari/gazari Bullah (200mm to 250mm)

1.0000

m

426.40

426.40

Ordinary Labour

0.0200

day

370.00

7.40 433.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

442.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

486.72

VAT

6% of Total

32.45

IT

4% of Total

21.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

289.73

540.80

Page: 772 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.14.06

Labour for driving best quality bullah piles up to required depth by monkey/ power winch in all sorts of soil including hoisting and placing piles in position, protecting the pile head with iron ring and cutting and shaping heads before and after driving and including hire and labour for necessary driving appliances etc. complete in all respect as per direction of the Engineer-in-Charge. Pamyment to be made on the length driven into the ground.

4.14.06.01

Bullah piles of 150mm to 200mm diameter

4.14.06.01.01

For driving from ground with staging

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Driving Equipment

0.0500

day

350.00

17.50 174.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

177.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

195.79

VAT

6% of Total

IT

4% of Total

13.05 8.70 Total:

4.14.06.01.02

For driving from pontoon or boats with staging

m

Add +4.00% with Item No 4.14.06.01.01

4.14.06.01.03

For driving from pontoon or boats with heavy staging

m

Add +7.00% with Item No 4.14.06.01.01

4.14.06.02

Bullah piles of 200mm to 250mm diameter

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

217.54

Page: 773 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.06.02.01

Detailed Analysis Brief Description of Item 2 For driving from ground with staging

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.6000

day

370.00

222.00

H.C. of Driving Equipment

0.0500

day

350.00

17.50 253.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

258.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

283.87

VAT

6% of Total

IT

4% of Total

18.92 12.62 Total:

4.14.06.02.02

For driving from pontoon or boats with staging

m

Add +4.00% with Item No 4.14.06.02.01

4.14.06.02.03

For driving from pontoon or boats with heavy staging

m

Add +7.00% with Item No 4.14.06.02.01

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

315.41

Page: 774 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.07

Detailed Analysis Brief Description of Item 2 Providing & Installtion of 100mm x 200mm x 8mm steel joist or any other required steel sections of 7.62m length @ 200mm c/c for Shore protection work during excavation in foundation trenches to protect the adjacent property including rent, conveyance, labour, material for cutting to required size & for driving the same upto required depth including cost of all fittings etc. complete as per direction of the E-I-C. The contractor will remove the joists after completing the work without any extra payment & the contractor will be the owner of these joists. Note: Measurement shall be based on lengths of protection work in horizontal direction.

Unit

Sub-Item

3

4

Quantity

Unit

Rate

5

6

7

982.1900

kg

18.00

17679.42

Skilled Labour

2.5000

day

450.00

1125.00

Ordinary Labour

7.0000

day

370.00

2590.00

H.C. of Driving Equipment

1.0000

day

350.00

350.00

8

m

H.C. of MS Plate, MS Angle & I-Beam etc.

21744.42

Subtotal-A: All other costs & consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1087.22 22831.64

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23288.27

10% Profit ( Add 10% on Subtotal-B) :

25617.10

VAT

6% of Total

IT

4% of Total

1707.81 1138.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

28463.45

Page: 775 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.08

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying & dumping of soil filled geo-textile bags of different size and capacity (fill volumn and weight when filled with dry sand/earth) at the specified locations along the bottom of piles of piers/ toe line properly including supply of geo-textile fabric as per following grading, sewing in accordance with the detailed drawing and technical specifications, protecting the geo-textile bags from UV ray or any other damages, filling with suitable soil/ sand and stitching bags by hand sewing machine properly with plastic thread and dumping the same in position etc. including cost of all materials, labours, taxes, incidental charges etc. complete in all respect as per approved drawing, specification and direction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 776 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.08.01

Detailed Analysis Brief Description of Item 2 Geo-Textile Bag: Empty Size: 800mm x 650mm, Fill Volumn: 0.0520 cum & Weight: 80 Kg Geo-Textile Grade: Grade-III-DF-40-2.3mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Geo Textile (Grade-III-DF-40-2.3mm thick)

1.1900

m2

65.00

77.35

Operator

0.0029

day

570.00

1.65

Helper

0.0014

day

400.00

0.56

Royalty of Earth

0.0520

m3

25.00

1.30

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0500

day

370.00

18.50

H.C. of Sewing Machine

0.0029

day

500.00

1.45

H.C. of Cutter (Geo-Textile)

0.0017

day

500.00

0.85 103.62

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

5.18 108.80

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

110.98

10% Profit ( Add 10% on Subtotal-B) :

122.08

VAT

6% of Total

IT

4% of Total

8.14 5.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

135.64

Page: 777 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.14.08.02

Geo-Textile Bag: Empty Bag Size: 900mm x 700mm, Fill Volumn: 0.0730 cum & Weight: 110 Kg Geo-Textile Grade: Grade-III-DF-40-2.3mm thick

bag

Quantity 5

Unit

Rate

6

7

8

Geo Textile (Grade-III-DF-40-2.3mm thick)

1.4250

m2

65.00

92.63

Operator

0.0033

day

570.00

1.88

Helper

0.0017

day

400.00

0.68

Royalty of Earth

0.0730

m3

25.00

1.83

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0600

day

370.00

22.20

H.C. of Sewing Machine

0.0033

day

500.00

1.65

H.C. of Cutter (Geo-Textile)

0.0020

day

500.00

1.00 123.82

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6.19 130.01

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.61

10% Profit ( Add 10% on Subtotal-B) :

145.87

VAT

6% of Total

IT

4% of Total

9.72 6.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

162.08

Page: 778 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.14.08.03

Geo-Textile Bag: Empty Bag Size: 950mm x 750mm, Fill Volumn: 0.0840 cum & Weight: 125 Kg Geo-Textile Grade: Grade-III-DF-40-2.3mm thick

bag

Quantity 5

Unit

Rate

6

7

8

Geo Textile (Grade-III-DF-40-2.3mm thick)

1.6000

m2

65.00

104.00

Operator

0.0033

day

570.00

1.88

Helper

0.0020

day

400.00

0.80

Royalty of Earth

0.0840

m3

25.00

2.10

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0700

day

370.00

25.90

H.C. of Sewing Machine

0.0033

day

500.00

1.65

H.C. of Cutter (Geo-Textile)

0.0017

day

500.00

0.85 139.14

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6.96 146.10

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

149.02

10% Profit ( Add 10% on Subtotal-B) :

163.92

VAT

6% of Total

IT

4% of Total

10.93 7.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

182.14

Page: 779 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.14.08.04

Geo-Textile Bag: Empty Bag Size: 1075mm x 850mm, Fill Volumn: 0.1164 cum & Weight: 175 Kg Geo-Textile Grade: Grade-V-DF-60-3.0mm thick

bag

Quantity 5

Unit

Rate

6

7

8

Geo Textile (Grade-V-DF-60-3.0mm thick)

2.0250

m2

90.00

182.25

Operator

0.0040

day

570.00

2.28

Helper

0.0020

day

400.00

0.80

Royalty of Earth

0.1164

m3

25.00

2.91

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0800

day

370.00

29.60

H.C. of Sewing Machine

0.0040

day

500.00

2.00

H.C. of Cutter (Geo-Textile)

0.0025

day

500.00

1.25 223.05

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11.15 234.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

238.89

10% Profit ( Add 10% on Subtotal-B) :

262.78

VAT

6% of Total

IT

4% of Total

17.52 11.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

291.97

Page: 780 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.14.08.05

Geo-Textile Bag: Empty Bag Size: 1100mm x 850mm, Fill Volumn: 0.1333 cum & Weight: 200 Kg Geo-Textile Grade: Grade-V-DF-60-3.0mm thick

bag

Quantity 5

Unit

Rate

6

7

8

Geo Textile (Grade-V-DF-60-3.0mm thick)

2.0700

m2

90.00

186.30

Operator

0.0040

day

570.00

2.28

Helper

0.0020

day

400.00

0.80

Royalty of Earth

0.1333

m3

25.00

3.33

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.0900

day

370.00

33.30

H.C. of Sewing Machine

0.0040

day

500.00

2.00

H.C. of Cutter (Geo-Textile)

0.0025

day

500.00

1.25 231.22

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11.56 242.78

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

247.64

10% Profit ( Add 10% on Subtotal-B) :

272.40

VAT

6% of Total

IT

4% of Total

18.16 12.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

302.67

Page: 781 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.08.06

Detailed Analysis Brief Description of Item 2 Geo-Textile Bag: Empty Bag Size: 1300mm x 1050mm, Fill Volumn: 0.1664 cum & Weight: 250 Kg Geo-Textile Grade: Grade-V-DF-60-3.0mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

bag

Geo Textile (Grade-V-DF-60-3.0mm thick)

2.9700

m2

90.00

267.30

Operator

0.0040

day

570.00

2.28

Helper

0.0020

day

400.00

0.80

Royalty of Earth

0.1664

m3

25.00

4.16

Foreman

0.0002

day

800.00

0.16

Skilled Labour

0.0040

day

450.00

1.80

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Sewing Machine

0.0040

day

500.00

2.00

H.C. of Cutter (Geo-Textile)

0.0025

day

500.00

1.25 316.75

Subtotal-A: Cost of Polyproplene/ Nylon thread & other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

15.84 332.59

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

339.24

10% Profit ( Add 10% on Subtotal-B) :

373.16

VAT

6% of Total

IT

4% of Total

24.88 16.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

414.63

Page: 782 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.09

Detailed Analysis Brief Description of Item 2 Providing, preparing and laying of geogrid crated apron 1 m x 5 m, 600 mm thick including excavation and backfilling with baffles at 1 m interval, made with geogrids having , joining sides with connectors/ring staples, top corners to be tie tensioned, placing of suitable cross interval ties in layers of 300 mm connecting opposite side with lateral braces and tied with polymer braids to avoid bulging, filled with stone with minimum size of 200 mm and specific gravity not less than 2.65, packed with stone spalls, keyed to the foundation recess in case of sloping ground and laid over a layer of geotextile to prevent migration of fines, all as per approved design and direction of E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Synthetic Geogrids as per approved design and specifications

7.0000

sqm

180.00

1260.00

Stone Boulder

1.3000

m3

3700.00

4810.00

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.5000

day

370.00

185.00 6356.00

Subtotal-A: Cost of material for miscellaneous items Connectors, Staples, Polymer braids, etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1271.20 7627.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7779.74

10% Profit ( Add 10% on Subtotal-B) :

8557.72

VAT

6% of Total

IT

4% of Total

570.51 380.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9508.58

Page: 783 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.14.10

Construction of single/ double row bamboo spur, with full length borak bamboo of specified dia. & length, at 0.3m c/c, two rows at 1.5m apart (not applicable for single row spur) and stays with bamboo at 3 m apart on the D/S side of the spur, single/ double (for length > 6m) row runner with half split bamboo on both sides and also with double layer cross tie at 3.0m interval, including 2.4m to 3.0m driving of bamboo pins by monkey hammer, necessary staging etc. complete with supply of all materials including local carriage within 150m and as per drawing and direction of E-I-C.

4.14.10.01

Single bamboo spur: dia. = 75mm, Length = 6.0m to 7.5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Borak Bamboo (75mm dia)

32.6000

m

38.00

1238.80

Nails/ Nut bolts/ Screw/ Spikes

0.0990

kg

65.00

6.44

GI Wire (22 BWG)

0.0260

kg

90.00

2.34

H.C. of Driving Equipment

0.0328

day

350.00

11.48

H.C. of Engine Boat

0.0328

day

1000.00

32.80

Ordinary Labour

0.8770

day

370.00

324.49 1616.35

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

80.82 1697.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1731.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1904.22

VAT

6% of Total

IT

4% of Total

126.95 84.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2115.80

Page: 784 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.14.10.02

Double row bamboo spur: dia. = 75mm, Length = 3.0m to 4.5m

m Borak Bamboo (75mm dia)

Quantity 5

Unit

Rate

6

7

8

29.7200

m

38.00

1129.36

Nails/ Nut bolts/ Screw/ Spikes

0.2000

kg

65.00

13.00

GI Wire (22 BWG)

0.0450

kg

90.00

4.05

H.C. of Driving Equipment

0.0100

day

350.00

3.50

H.C. of Engine Boat

0.0100

day

1000.00

10.00

Ordinary Labour

1.0000

day

370.00

370.00 1529.91

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

76.50 1606.41

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1638.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1802.39

VAT

6% of Total

IT

4% of Total

120.16 80.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2002.65

Page: 785 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.14.10.03

Double row bamboo spur: dia. = 75mm, Length = 4.5m to 6.0m

m Borak Bamboo (75mm dia)

Quantity 5

Unit

Rate

6

7

8

44.4000

m

38.00

1687.20

Nails/ Nut bolts/ Screw/ Spikes

0.2500

kg

65.00

16.25

GI Wire (22 BWG)

0.0520

kg

90.00

4.68

H.C. of Driving Equipment

0.0650

day

350.00

22.75

H.C. of Engine Boat

0.1300

day

1000.00

130.00

Ordinary Labour

1.8600

day

370.00

688.20 2549.08

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

127.45 2676.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2730.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3003.07

VAT

6% of Total

IT

4% of Total

200.20 133.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3336.75

Page: 786 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.10.04

Detailed Analysis Brief Description of Item 2 Double row bamboo spur: dia. = 100mm, Length = 7.5m to 11.0m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Borak Bamboo (75mm to 100mm)

80.1000

m

42.00

3364.20

Nails/ Nut bolts/ Screw/ Spikes

0.3100

kg

65.00

20.15

GI Wire (22 BWG)

0.0520

kg

90.00

4.68

H.C. of Driving Equipment

0.0328

day

350.00

11.48

H.C. of Engine Boat

0.1312

day

1000.00

131.20

Ordinary Labour

2.0330

day

370.00

752.21 4283.92

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

214.20 4498.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4588.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5046.89

VAT

6% of Total

IT

4% of Total

336.46 224.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5607.65

Page: 787 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.11

Detailed Analysis Brief Description of Item 2 Construction of a narrow filter sub- surface drain consisting of porous or perforated pipe laid in narrow trench surrounded by a geotextile filter fabric, with a minimum of 450 mm overlap of fabric and installed including excavation and backfilling.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

120.00

120.00

m

Perforated geosynthetic pipe 150 mm dia

1.0000

Geo Textile (Grade-V-DF-60-3.0mm thick)

1.0000

m2

90.00

90.00

Mason

0.0400

day

550.00

22.00

Skilled Labour

0.2500

day

450.00

112.50

Ordinary Labour

0.5000

day

370.00

185.00 529.50

Subtotal-A: Cost of material for miscellaneous items like synthetic cord

( +5.00 % on Subtotal-A )

Subtotal-A1:

26.48 555.98

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

567.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

623.80

VAT

6% of Total

41.59

IT

4% of Total

27.72 Total:

4.14.12

Amount

693.12

JGT_RRC: Supplying and laying of woven type untreated double warp plain weave jute geo-textile (JGT) of different grades conforming to BDS 1909: 2016 for strengthening subgrade of Road & Bridge approach including local handling, unrolling, placing in position, ensuring proper drapability (JGT should touch the ISG surface at all points), stapling JGT by 6mm dia. U-shapped pegs/ hooknails or 37mm long mushroom shaped nails at an interval of 300mm with overlaps of 100mm, protecting the JGT from any other damages etc. all complete in all respect as per instructions given in Annexure-A (JGT Installation Guideline for Rural Road Construction) of BDS 1909 : 2016 and approval of Engineer-In-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 788 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.12.01

Detailed Analysis Brief Description of Item 2 JGT_RRC-1 : Applicable for Strengthening subgrade of Village Roads. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 85 x 32, Width(m) ≥ 1, Mass per unit area (gsm) = 627 ± 10%, Thickness under 2 kPa pressure (mm) = 2.0 ± 10%, AOS (O95) (μm) ≤ 450, Vertical Permeability (m/sec) ≥ 3.0 x10-3, Horizontal Permeability (m/sec) ≥ 7.0 x10-3, Grab Tensile Strength (N) MD x CD ≥ 850 x 200, Grab Tensile Elongation (%) MD x CD ≤ 30 x 35, CBR Puncture Resistance (N) ≥ 2000, Wide Width Tensile Strength (kN/m) MD x CD ≥ 20 x 10, Wide Width Elongation (%) MD x CD ≤ 12 x 10.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Double Warp Plain Weave - 627 gsm

1.0800

sqm

99.00

106.92

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 118.82

Subtotal-A: Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

11.88 130.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

133.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

146.65

VAT

6% of Total

IT

4% of Total

9.78 6.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

162.94

Page: 789 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.12.02

Detailed Analysis Brief Description of Item 2 JGT_RRC-2 : Applicable for Strengthening subgrade of Union or Higher Roads. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 94 x 39, Width(m) ≥ 1, Mass per unit area (gsm) = 724 ± 10%, Thickness under 2 kPa pressure (mm) = 2.0 ± 10%, AOS (O95) (μm) ≤ 300, Vertical Permeability (m/sec) ≥ 2.0 x10-3, Horizontal Permeability (m/sec) ≥ 6.0 x10-3, Grab Tensile Strength (N) MD x CD ≥ 925 x 425, Grab Tensile Elongation (%) MD x CD ≤ 35 x 40, CBR Puncture Resistance (N) ≥ 2150, Wide Width Tensile Strength (kN/m) MD x CD ≥ 25 x 10, Wide Width Elongation (%) MD x CD ≤ 15 x 12.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Double Warp Plain Weave - 724 gsm

1.0800

sqm

117.00

126.36

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 138.26

Subtotal-A: Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

13.83 152.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

155.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

170.64

VAT

6% of Total

IT

4% of Total

11.38 7.58 Total:

4.14.13

Amount

189.60

JGT_RBP: Supplying and laying of natural additive treated woven type double warp plain weave jute geo-textile (JGT) conforming to BDS 1909: 2016 for river bank and slope protection work including local handling, unrolling, placing in position, ensuring proper drapability (JGT should touch the ground surface at all points), stapling JGT by 6mm dia. U-shapped pegs/ hooknails or 37mm long mushroom shaped nails at an interval of 300mm with overlaps of 100mm, protecting the JGT from any other damages etc. all complete in all respect as per instructions given in Annexure-B (JGT Installation Guideline for River Bank Protection) of BDS 1909 : 2016 and approval of Engineer-In-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 790 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.13.01

Detailed Analysis Brief Description of Item 2 JGT_RBP-1: Applicable for mild to moderate River River Bank Protection work. This type of treated JGT shall have the following requirements. Ends x Picks /dm ≥ 85 x 32, Width(m) ≥ 1, Mass per unit area (gsm) = 627 ± 15%, Thickness under 2 kPa pressure (mm) = 2.0 ± 20%, AOS (O95) (μm) ≤ 150, Vertical Permeability (m/sec) ≥ 1.0 x10-3, Horizontal Permeability (m/sec) ≥ 6.0 x10-3, Grab Tensile Strength (N) MD x CD ≥ 950 x 230, Grab Tensile Elongation (%) MD x CD ≤ 35 x 45, CBR Puncture Resistance (N) ≥ 2500, Wide Width Tensile Strength (KN/m) MD x CD ≥ 20 x 10, Wide Width Elongation (%) MD x CD ≤ 12 x 10.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Natural Additive Treated Double Warp Plain Weave - 627 gsm

1.0800

sqm

139.00

150.12

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 162.02

Subtotal-A: Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

16.20 178.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

181.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

199.97

VAT

6% of Total

13.33

IT

4% of Total

8.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

222.18

Page: 791 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.14

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

JGT-HSM: Supplying and laying of open mesh Plain Weave jute geotextile (JGT) commonly known as Soil Saver of different grades conforming to BDS 1909: 2016 for Hill Slope Management work including local handling, unrolling, placing in position, unrolling of JGT in the direction of surface run-off, stapling JGT by 6mm dia. U-shapped hooknails at an interval of 300mm with overlaps of 100mm at the sides and 150mm at the ends, anchoring JGT within a trench at the two ends by filling the trench with big bats/gravel or other suitable materials, ensuring proper drapability (JGT must touch the ground surface at all points), filling drain materials immediately after laying of JGT, protecting the JGT from any other damages etc. all complete in all respect as per instructions given in Annexure-C (JGT Installation Guideline for Hill Slope Management) of BDS 1909 : 2016 and approval of Engineer-InCharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 792 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.14.01

Detailed Analysis Brief Description of Item 2 JGT_HSM-1: Applicable for Moderate slope (≤35 degree) & annual rainfall ≤ 2000mm. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 6.5 x 4.5, Width(m) = 1.22, Mass per unit area (gsm) = 500 ± 10%, Thickness under 2 kPa pressure (mm) = 4.5 ± 10%, Water Holding Capacity (% by weight) ≥ 400, Wide Width Tensile Strength (kN/m) MD x CD ≥ 6.5 x 6.0, Wide Width Elongation (%) MD x CD ≤ 14.0 x 14.0.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Open Mesh Plain Weave (Soil Saver) 500 gsm

1.0800

sqm

29.00

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40

Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

31.32

43.22

Subtotal-A:

4.32 47.54

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

48.49

10% Profit ( Add 10% on Subtotal-B) :

53.34

VAT

6% of Total

3.56

IT

4% of Total

2.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

59.27

Page: 793 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.14.02

Detailed Analysis Brief Description of Item 2 JGT_HSM-2: Applicable for Moderate slope (≤35 degree) & annual rainfall ≥ 2000mm and steep stope (>35 degree to ≤ 45 degree) & annual rainfall ≤ 2000mm. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 8 x 7, Width(m) = 1.22, Mass per unit area (gsm) = 600±10%, Thickness under 2 kPa pressure (mm) = 5.5±10%, Water Holding Capacity (% by weight) ≥ 400, Wide Width Tensile Strength (kN/m) MD x CD ≥ 12.0 x 6.0, Wide Width Elongation (%) MD x CD ≤ 14.0 x 14.0.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Jute Geo-Textile (JGT): Open Mesh Plain Weave (Soil Saver) 600 gsm

1.0800

sqm

32.00

34.56

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 46.46

Subtotal-A: Cost of U-shaped peg, mashroom nails etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4.65 51.11

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

52.13

10% Profit ( Add 10% on Subtotal-B) :

57.34

VAT

6% of Total

IT

4% of Total

3.82 2.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

63.71

Page: 794 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.14.03

Detailed Analysis Brief Description of Item 2 JGT_HSM-3: Applicable for steep stope (>35 degree to ≤ 45 degree) & annual rainfall > 2000mm. This type of JGT shall have the following requirements. Ends x Picks /dm ≥ 8 x 8, Width(m) = 1.22, Mass per unit area (gsm) = 700±10%, Thickness under 2 kPa pressure (mm) = 5.5±10%, Water Holding Capacity (% by weight) ≥ 400, Wide Width Tensile Strength (kN/m) MD x CD ≥ 14.0 x 7.0, Wide Width Elongation (%) MD x CD ≤ 14.0 x 14.0.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Jute Geo-Textile (JGT): Open Mesh Plain Weave (Soil Saver) 700 gsm

1.0800

sqm

35.00

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

MS pipe of 100mm diameter & 4mm wall thickness

Note : Rates of all items should be inclusive of all supply and carriage.

4.97 54.67

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55.76

10% Profit ( Add 10% on Subtotal-B) :

61.34

VAT

6% of Total

4.09

IT

4% of Total

2.73 Total:

4.14.15.01

37.80

49.70 Cost of U-shaped peg, mashroom nails etc.

Supplying best quality MS pipes of different diameter at work site including, carrying, stacking, handling etc. all complete as per direction of the E-I-C.

8

sqm

Subtotal-A:

4.14.15

Amount

68.16

Page: 795 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.15.01.01

Detailed Analysis Brief Description of Item 2 For permanent use, cost of MS pipe is included in this unit rate.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 100mm dia MS pipe and wall thickness 4mm

1.0000

m

1300.00

1300.00

Subtotal-A: Stacking, Handling & other consumables

( +5.00 % on Subtotal-A )

65.00

Subtotal-A1: Subtotal-B: Subtotal-C:

1365.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1392.30

10% Profit ( Add 10% on Subtotal-B) :

1531.53

VAT

6% of Total

IT

4% of Total

102.10 68.07 Total:

4.14.15.01.02

For temporary use, rent of MS pipe is included in this unit rate.

1701.70

m H.C. of 100mm dia & 4mm thick MS pipe

1.0000 m/month

45.00

Stacking, Handling & other consumables

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

45.00 45.00

Subtotal-A:

2.25 47.25

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

48.20

10% Profit ( Add 10% on Subtotal-B) :

53.01

VAT

6% of Total

IT

4% of Total

3.53 2.36 Total:

4.14.15.02

1300.00

58.91

MS pipe of 150mm diameter & 4mm wall thickness

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 796 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.15.02.01

Detailed Analysis Brief Description of Item 2 For permanent use, cost of MS pipe is included in this unit rate.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 150mm dia. MS pipe and wall thickness 4mm

1.0000

m

1950.00

1950.00

Subtotal-A: Stacking, Handling & other consumables

( +5.00 % on Subtotal-A )

97.50

Subtotal-A1: Subtotal-B: Subtotal-C:

2047.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2088.45

10% Profit ( Add 10% on Subtotal-B) :

2297.30

VAT

6% of Total

IT

4% of Total

153.15 102.10 Total:

4.14.15.02.02

For temporary use, rent of MS pipe is included in this unit rate.

2552.55

m H.C. of 150mm dia & 4mm thick MS pipe

1.0000 m/month

65.00

Stacking, Handling & other consumables

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

65.00 65.00

Subtotal-A:

3.25 68.25

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

69.62

10% Profit ( Add 10% on Subtotal-B) :

76.58

VAT

6% of Total

IT

4% of Total

5.11 3.40 Total:

4.14.15.03

1950.00

85.09

MS pipe of 200mm diameter & 6.5mm wall thickness

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 797 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.15.03.01

Detailed Analysis Brief Description of Item 2 For permanent use, cost of MS pipe is included in this unit rate.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 200mm dia. MS pipe and wall thickness 6.5mm

1.0000

m

3510.00

3510.00

Subtotal-A: Stacking, Handling & other consumables

( +5.00 % on Subtotal-A )

175.50

Subtotal-A1: Subtotal-B: Subtotal-C:

3685.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3759.21

10% Profit ( Add 10% on Subtotal-B) :

4135.13

VAT

6% of Total

IT

4% of Total

275.68 183.78 Total:

4.14.15.03.02

For temporary use, rent of MS pipe is included in this unit rate.

4594.59

m H.C. of 200mm dia & 6.5mm thick MS pipe

1.0000 m/month

115.00

Stacking, Handling & other consumables

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

115.00 115.00

Subtotal-A:

5.75 120.75

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

123.17

10% Profit ( Add 10% on Subtotal-B) :

135.48

VAT

6% of Total

IT

4% of Total

9.03 6.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3510.00

150.54

Page: 798 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.16

Detailed Analysis Brief Description of Item 2 Labour for driving MS steel pipes of any size up to required depth with monkey, power winch etc. including all necessary tools, equipment and accessories and hoisting piles in true & vertical position etc. all complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

day

450.00

8

m

Skilled Labour

0.0500

22.50

Ordinary Labour

0.2000

day

370.00

74.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0500

day

3000.00

150.00

H.C. of Derrick

0.0500

day

400.00

20.00

Diesel

0.2500

liter

68.00

17.00

Lubricant

0.0100

liter

220.00

2.20 285.70

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

14.29 299.99

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

305.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

336.58

VAT

6% of Total

22.44

IT

4% of Total

14.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

373.98

Page: 799 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.14.17

Detailed Analysis Brief Description of Item 2 Labour for extraction of MS steel/ micro pipes of any size with monkey, power winch etc. including all necessary tools, equipment and accessories all complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.2000

day

370.00

74.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0300

day

3000.00

90.00

H.C. of Derrick

0.0300

day

400.00

12.00

Diesel

0.2500

liter

68.00

17.00

Lubricant

0.0100

liter

220.00

2.20 217.70

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

10.89 228.59

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

233.16

10% Profit ( Add 10% on Subtotal-B) :

256.47

VAT

6% of Total

IT

4% of Total

17.10 11.40 Total:

4.14.18

Amount

284.97

Labour charge for taking out bullah from river bed (measurement for the driven portion to be taken only); or cross ties walling pieces, including cutting and opening out bolts and nuts; or old bamboo pieces and struts from river bed and stacking the materials on the bank as per direction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 800 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.14.18.01

2 Bullah

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

m Ordinary Labour

0.0950

35.15

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

1.76

Subtotal-A1:

36.91

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

37.65

10% Profit ( Add 10% on Subtotal-B) :

41.41

VAT

6% of Total

IT

4% of Total

2.76 1.84 Total:

4.14.18.02

Cross ties walling pieces

46.01

m Ordinary Labour

0.0250

day

370.00

Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

9.25 9.25

Subtotal-A:

0.46 9.71

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

9.91 10.90

10% Profit ( Add 10% on Subtotal-B) :

VAT

0.73 0.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35.15

12.11

Page: 801 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.14.18.03

2 Old bamboo pieces and struts

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

day

370.00

8

m Ordinary Labour

0.0200

Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B:

7.40 7.40

Subtotal-A:

0.37 7.77

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7.93

10% Profit ( Add 10% on Subtotal-B) :

8.72

VAT

6% of Total

IT

4% of Total

0.58 0.39

Subtotal-C:

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9.69

Page: 802 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.01

Detailed Analysis Brief Description of Item 2 Providing and erecting a "W" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal beam rail, 70 cm above road/ground level, fixed on channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m high, 1.10 m below ground/road level, all steel parts and fittings to be galvanised by hot dip process (zinc coated, 550 gsm, minimum single spot), all fittings to conform to AASHTO M 180, metal beam rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 330 mm long etc. all complete as per specification & direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

kg

150.00

1373.67

8

m

Corrugated sheet,3 mm thick, "W" beam section railing Channel post 150 x 75 x 5 mm,1.8 long

9.1578 19.6800

kg

120.00

2361.60

Spacer 150 x 75 x 5 mm channel 0.33 m long,

3.6089

kg

120.00

433.07

Nails/ Nut bolts/ Screw/ Spikes

4.4444

kg

65.00

288.89

Foreman

0.0133

day

800.00

10.64

Welder

0.1111

day

680.00

75.55

Skilled Labour

0.2222

day

450.00

99.99

H.C. of Flat Body Truck (3 tons)

0.0028

day

2000.00

5.60 4649.00

Subtotal-A: Cost of material for fabrication, nuts, bolts and washers etc.

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1162.25 5811.25

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5927.48

10% Profit ( Add 10% on Subtotal-B) :

6520.23

VAT

6% of Total

IT

4% of Total

434.68 289.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7244.69

Page: 803 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.02

Detailed Analysis Brief Description of Item 2 Providing and erecting a "Thrie" metal beam crash barrier comprising of 3 mm thick corrugated sheet metal rail, 70 cm above road/ground level, fixed on channel vertical post, 150 x 75 x 5 mm spaced 2 m centre to centre, 1.8 m high with 1.15 m below ground level, all steel parts and fitments to be galvanised by hot dip process (zinc coated, 550 gsm, minimum single spot), all fittings to conform to AASHTO M 180, metal rail to be fixed on the vertical post with a spacer of channel section 150 x 75 x 5 mm, 546 mm long etc. all complete as per specification & direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

kg

150.00

2431.34

8

m

Corrugated sheet,3 mm thick, "W" beam section railing

16.2089

Channel post 150 x 75 x 5 mm,1.8 long

21.8667

kg

120.00

2624.00

Spacer 150 x 75 x 5 mm channel 0.33 m long,

5.9689

kg

120.00

716.27

Nails/ Nut bolts/ Screw/ Spikes

6.6667

kg

65.00

433.34

Foreman

0.0133

day

800.00

10.64

Welder

0.1111

day

680.00

75.55

Skilled Labour

0.2222

day

450.00

99.99

H.C. of Flat Body Truck (3 tons)

0.0028

day

2000.00

5.60 6396.72

Subtotal-A: Cost of material for fabrication, nuts, bolts and washers etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

959.51 7356.23

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7503.35

10% Profit ( Add 10% on Subtotal-B) :

8253.69

VAT

6% of Total

IT

4% of Total

550.25 366.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9170.76

Page: 804 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.15.03

Supplying fitting and fixing railing & rail post made of various dia MS pipes of standard thickness for normal, ornamental Bridge or any other structure including required ms plate, nutbolt, cutting, welding, painting with anticorrosive paint, laying in position etc. all complete as per design, drawing, spacification & the direction of the E-I-C.

4.15.03.01

50mm dia. and wall thickness 4mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 50mm dia. MS pipe and wall thickness 4mm

1.0000

m

640.00

640.00

Skilled Labour

0.1500

day

450.00

67.50 707.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1:

176.88 884.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

902.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

992.27

VAT

6% of Total

IT

4% of Total

66.15 44.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1102.52

Page: 805 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.03.02

Detailed Analysis Brief Description of Item 2 75mm dia. and wall thickness 4mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 75mm dia. MS pipe and wall thickness 4mm

1.0000

m

780.00

780.00

Skilled Labour

0.1500

day

450.00

67.50 847.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

211.88

Subtotal-A1: Subtotal-B: Subtotal-C:

1059.38 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1080.56

10% Profit ( Add 10% on Subtotal-B) :

1188.62

VAT

6% of Total

IT

4% of Total

79.24 52.83 Total:

4.15.03.03

100mm dia. and wall thickness 4mm

m 100mm dia MS pipe and wall thickness 4mm

1.0000

m

1300.00

1300.00

Skilled Labour

0.1500

day

450.00

67.50 1367.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1:

341.88 1709.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1743.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1917.92

VAT

6% of Total

IT

4% of Total

127.86 85.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1320.69

2131.02

Page: 806 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.03.04

Detailed Analysis Brief Description of Item 2 150mm dia. and wall thickness 4mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 150mm dia. MS pipe and wall thickness 4mm

1.0000

m

1950.00

1950.00

Skilled Labour

0.1500

day

450.00

67.50 2017.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

504.38

Subtotal-A1: Subtotal-B: Subtotal-C:

2521.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2572.31

10% Profit ( Add 10% on Subtotal-B) :

2829.54

VAT

6% of Total

IT

4% of Total

188.64 125.76 Total:

4.15.03.05

200mm dia. and wall thickness 6.5mm

m 200mm dia. MS pipe and wall thickness 6.5mm

1.0000

m

3510.00

3510.00

Skilled Labour

0.1500

day

450.00

67.50 3577.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1:

894.38 4471.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4561.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5017.44

VAT

6% of Total

IT

4% of Total

334.50 223.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3143.94

5574.94

Page: 807 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.15.04

Supplying fitting and fixing railing & rail post made of various size MS Square Box of standard thickness for normal & ornamental Bridge or any other structure, including required ms plate, nut-bolt, cutting, welding, painting with anticorrosive paint, laying in position, etc. all complete as per design, drawing, spacification & the direction of the E-IC.

4.15.04.01

Size: 25mm x 25mm MS box and wall thickness 4mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 25mm x 25mm MS box and wall thickness 4mm

1.0000

m

350.00

350.00

Skilled Labour

0.1500

day

450.00

67.50 417.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

104.38 521.88

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

532.31

10% Profit ( Add 10% on Subtotal-B) :

585.54

VAT

6% of Total

39.04

IT

4% of Total

26.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

650.60

Page: 808 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.04.02

Detailed Analysis Brief Description of Item 2 Size: 40mm x 40mm MS box and wall thickness 4mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 40mm x 40mm MS box and wall thickness 4mm

1.0000

m

475.00

475.00

Skilled Labour

0.1500

day

450.00

67.50 542.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

135.63

Subtotal-A1: Subtotal-B: Subtotal-C:

678.13 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

691.69

10% Profit ( Add 10% on Subtotal-B) :

760.86

VAT

6% of Total

IT

4% of Total

50.72 33.82 Total:

4.15.04.03

Size: 50mm x 50mm MS box and wall thickness 6mm

m 50mm x 50mm MS box and wall thickness 6mm

1.0000

m

870.00

870.00

Skilled Labour

0.1500

day

450.00

67.50 937.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1:

234.38 1171.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1195.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1314.84

VAT

6% of Total

IT

4% of Total

87.66 58.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

845.40

1460.94

Page: 809 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.04.04

Detailed Analysis Brief Description of Item 2 Size: 62.5mm x 62.5mm MS box and wall thickness 6mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 62.5mm x 62.5mm MS box and wall thickness 6mm

1.0000

m

1050.00

1050.00

Skilled Labour

0.1500

day

450.00

67.50 1117.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

279.38

Subtotal-A1: Subtotal-B: Subtotal-C:

1396.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1424.81

10% Profit ( Add 10% on Subtotal-B) :

1567.29

VAT

6% of Total

IT

4% of Total

104.49 69.66 Total:

4.15.04.05

Size: 75mm x 75mm MS box and wall thickness 8mm

m 75mm x 75mm MS box and wall thickness 8mm

1.0000

m

1720.00

1720.00

Skilled Labour

0.1500

day

450.00

67.50 1787.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1:

446.88 2234.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2279.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2506.97

VAT

6% of Total

IT

4% of Total

167.13 111.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1741.44

2785.52

Page: 810 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.04.06

Detailed Analysis Brief Description of Item 2 Size: 100mm x 100mm MS box and wall thickness 8mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 100mm x 100mm MS box and wall thickness 8mm

1.0000

m

2225.00

2225.00

Skilled Labour

0.1500

day

450.00

67.50 2292.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

573.13

Subtotal-A1: Subtotal-B: Subtotal-C:

2865.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2922.94

10% Profit ( Add 10% on Subtotal-B) :

3215.23

VAT

6% of Total

IT

4% of Total

214.35 142.90 Total:

4.15.04.07

Size: 125mm x 125mm MS box and wall thickness 8mm

m 125mm x 125mm MS box and wall thickness 8mm

1.0000

m

2750.00

2750.00

Skilled Labour

0.1500

day

450.00

67.50 2817.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1:

704.38 3521.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3592.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3951.54

VAT

6% of Total

IT

4% of Total

263.44 175.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3572.48

4390.60

Page: 811 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.04.08

Detailed Analysis Brief Description of Item 2 Size: 125mm x 125mm MS box and wall thickness 10mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 125mm x 125mm MS box and wall thickness 10mm

1.0000

m

3350.00

3350.00

Skilled Labour

0.1500

day

450.00

67.50 3417.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

854.38

Subtotal-A1: Subtotal-B: Subtotal-C:

4271.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4357.31

10% Profit ( Add 10% on Subtotal-B) :

4793.04

VAT

6% of Total

IT

4% of Total

319.54 213.02 Total:

4.15.04.09

Size: 150mm x 150mm MS box and wall thickness 8mm

m 150mm x 150mm MS box and wall thickness 8mm

1.0000

m

3220.00

3220.00

Skilled Labour

0.1500

day

450.00

67.50 3287.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1:

821.88 4109.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4191.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4610.72

VAT

6% of Total

IT

4% of Total

307.38 204.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5325.60

5123.02

Page: 812 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.04.10

Detailed Analysis Brief Description of Item 2 Size: 150mm x 150mm MS box and wall thickness 10mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 150mm x 150mm MS box and wall thickness 10mm

1.0000

m

3950.00

3950.00

Skilled Labour

0.1500

day

450.00

67.50 4017.50

Subtotal-A: Workshop Charges, Anti corrosive paint & other costing

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1004.38 5021.88

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5122.31

10% Profit ( Add 10% on Subtotal-B) :

5634.54

VAT

6% of Total

IT

4% of Total

375.64 250.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6260.60

Page: 813 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.05

Detailed Analysis Brief Description of Item 2 Supplying & providing flexible and acrylic type reflectorized traffic painting/ coating on rail post, rail bar, wheel guard, Pier column etc. including surface preparation, applying paint, all materials, labour charges, tools, equipment etc. all complete as per specification & direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Reflectorized paint

0.1200

liter

2528.00

303.36

Sealer/Primer (for texture paint)

0.0900

litre

200.00

18.00

Plumber/ Electric Mistry/ Painter

0.1500

day

680.00

102.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 493.86

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

503.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

554.11

VAT

6% of Total

36.94

IT

4% of Total

24.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

615.68

Page: 814 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.06

Detailed Analysis Brief Description of Item 2 Lighting on Bridges: Supplying and Installation of mild steel hollow bent light pole of overall length 8.9m having 150mm dia. at bottom & 75mm dia. at top & wall thickness 4mm with base plate 275 x 27 5x 16mm thick, providing 32mm dia MS/GI pipe for incoming and outgoing cable connection to jucntion box, 20 m apart and fitted with pole light fitting, sodium vapour lamp, circuit breaker, bending of steel poles, two coats of silver white aluminium paint over steel pole, steel reducers for changing diameter from 150mm to 75mm, scaffolding, holes at top of the pole for fixing ring type GI braket/ pole light fitting, suitable precautions for ensuring prevention of water ingress etc. all complete in all respect as per design, specification and direction of E-I-C. The cost of pole light fitting, sodium vapour lamp, circuit breaker and cable is not included in this unit rate. Note: Length of pole: 8.9m ( Straight portion = 4m of 150mm dia. & bent portion = 4.9m of 75mm dia.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

150mm dia. MS pipe and wall thickness 4mm

4.0000

m

1950.00

7800.00

75mm dia. MS pipe and wall thickness 4mm

4.9000

m

780.00

3822.00

MS Plate (16mm)

9.4985

kg

80.00

759.88

MS Plate (6mm)

2.1195

kg

70.00

148.37

Nails/ Nut bolts/ Screw/ Spikes

6.1654

kg

65.00

400.75

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.4000

day

370.00

148.00 13088.00

Subtotal-A: Cost of pipe bending, reducer, scaffolding etc.

( +25.00 % on Subtotal-A )

3272.00

Cost of two coats of alluminium paint over steel circular hollow pipe

( +2.50 % on Subtotal-A )

327.20

Subtotal-A1:

16687.19

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17020.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18723.03

VAT

6% of Total

IT

4% of Total

1248.20 832.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

20803.37 Page: 815 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.07

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Lighting on Bridge Approaches: Supplying and Installation of mild steel hollow bent light pole of specifiedlength having 150mm dia. at bottom & 75mm dia. at top & wall thickness 4mm with base plate 275 x 275 x 16mm thick, providing 32mm dia MS/GI pipe for incoming and outgoing cable connection to jucntion box, 20 m apart and fitted with pole light fitting, sodium vapour lamp, circuit breaker, bending of steel poles, two coats of silver white aluminium paint over steel pole, steel reducers for changing diameter from 150mm to 75mm, laying 500 x 500 x 1200 mm cement concrete block in the ratio 1:3:6 and block be continued up to 300mm above the ground level i.e. 900mm below ground level including excavation, centering, shuttering and refilling, providing props for pole, holes at top of the pole for fixing ring type GI braket/ pole light fitting etc. all complete in all respect as per design, specification and direction of E-IC. The cost of pole light fitting, sodium vapour lamp, circuit breaker and cable is not included in this unit rate.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 816 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.07.01

Detailed Analysis Brief Description of Item 2 Pole with double arm if fixed in the median Note: Length of pole: 12.9m ( Straight portion = 5.0m of 150mm dia. & bent portion on both sides = 7.9m of 75mm dia.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

150mm dia. MS pipe and wall thickness 4mm

5.0000

m

1950.00

9750.00

75mm dia. MS pipe and wall thickness 4mm

7.9000

m

780.00

6162.00

MS Plate (16mm)

9.4985

kg

80.00

759.88

MS Plate (6mm)

2.1195

kg

70.00

148.37

Nails/ Nut bolts/ Screw/ Spikes

6.1654

kg

65.00

400.75

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.5000

day

370.00

185.00 17419.50

Subtotal-A: Cost of Excavation, concreting, pipe bending, reducer, scaffolding etc. Cost of two coats of alluminium paint over steel circular hollow pipe

( +25.00 % on Subtotal-A )

4354.87

( +2.50 % on Subtotal-A )

435.49

Subtotal-A1: Subtotal-B: Subtotal-C:

22209.86 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22654.05

10% Profit ( Add 10% on Subtotal-B) :

24919.46

VAT

6% of Total

IT

4% of Total

1661.30 1107.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

27688.29

Page: 817 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.07.02

Detailed Analysis Brief Description of Item 2 Pole with single arm if fixed on the footpath Note: Length of pole: 9.9m ( Straight portion = 5.0m of 150mm dia. & bent portion = 4.9m of 75mm dia.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

150mm dia. MS pipe and wall thickness 4mm

5.0000

m

1950.00

9750.00

75mm dia. MS pipe and wall thickness 4mm

4.9000

m

780.00

3822.00

MS Plate (16mm)

9.4985

kg

80.00

759.88

MS Plate (6mm)

2.1195

kg

70.00

148.37

Nails/ Nut bolts/ Screw/ Spikes

6.1654

kg

65.00

400.75

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.5000

day

370.00

185.00 15079.50

Subtotal-A: Cost of Excavation, concreting, pipe bending, reducer, scaffolding etc. Cost of two coats of alluminium paint over steel circular hollow pipe

( +25.00 % on Subtotal-A )

3769.87

( +2.50 % on Subtotal-A )

376.99

Subtotal-A1: Subtotal-B: Subtotal-C:

19226.36 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19610.88

10% Profit ( Add 10% on Subtotal-B) :

21571.97

VAT

6% of Total

IT

4% of Total

1438.13 958.75 Total:

4.15.08

Amount

23968.86

Construction of pre-cast/ Cast-in-situ RCC Railing of specified strength having aggregate size not exceeding 12mm, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 1500mm, leaving adequate space between vertical post for expansion, complete as per Bridge Design Standard For LGED- June 2012, approved drawings, technical specification and approval of E-I-C. The cost of reinforcement and it's fabrication, binding, welding and placing is included in this unit rate.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 818 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.08.01

Detailed Analysis Brief Description of Item 2 Pre-cast RCC Railing of 25 MPa concrete

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m RCC-25SCCM: Reinforced cement concrete work with minimum cement content ralates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 33.5 Mpa and sa.............4.09.03.06.01

0.0889

cum

Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS ISO 6935-2:2006 (Grade 400)………….(4.11.01.04)

19.7191

kg

12360.91

1098.88

65.67

1294.95

2393.84

Subtotal-A: Cost for form work for casting in casting yard

( +5.00 % on Subtotal-A )

119.69

Cost for handling and fixing of precast panels in position

( +5.00 % on Subtotal-A )

119.69

Subtotal-A1:

2633.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2685.89

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2954.47

VAT

6% of Total

IT

4% of Total

196.96 131.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3282.75

Page: 819 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.08.02

Detailed Analysis Brief Description of Item 2 Cast-in-Situ RCC Railing of 25 MPa concrete

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS ISO 6935-2:2006 (Grade 400)………….(4.11.01.04)

19.7191

kg

RCC-25SCCM: Reinforced cement concrete work with minimum cement content ralates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 33.5 Mpa and sa.............4.09.03.06.02

0.0889

cum

65.67

1294.95

10923.59

971.11

2266.06

Subtotal-A: Cost of formwork

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

113.30 2379.36

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2426.95

10% Profit ( Add 10% on Subtotal-B) :

2669.65

VAT

6% of Total

177.98

IT

4% of Total

118.65 Total:

4.15.09

Amount

2966.27

Supplying fitting and fixing railing & rail post made of various dia Stainless Steel (SS) pipes of standard thickness for normal , ornamental Bridge or any other structure including required SS plate, nutbolt, cutting, welding, laying in position etc. all complete as per design, drawing,spacification & the direction of the Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 820 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.09.01

Detailed Analysis Brief Description of Item 2 25mm dia. and wall thickness 1.5mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 25mm dia. Stainless Steel pipe and wall thickness 2.00mm

1.0000

m

335.00

335.00

Skilled Labour

0.1500

day

450.00

67.50 402.50

Subtotal-A: Workshop Charges, & other consumables.

( +25.00 % on Subtotal-A )

100.63

Subtotal-A1:

503.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

513.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

564.51

VAT

6% of Total

37.63

IT

4% of Total

25.09 Total:

4.15.09.02

38mm dia. and wall thickness 2.5mm

m 38mm dia. Stainless Steel pipe and wall thickness 2.50mm

1.0000

m

710.00

710.00

Skilled Labour

0.1500

day

450.00

67.50 777.50

Subtotal-A: Workshop Charges, & other consumables.

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

194.38 971.88

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

991.31 1090.44 72.70 48.46

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

627.23

1211.60

Page: 821 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.09.03

Detailed Analysis Brief Description of Item 2 50mm dia. and wall thickness 2.50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 50mm dia. Stainless Steel pipe and wall thickness 2.50mm

1.0000

m

960.00

960.00

Skilled Labour

0.1500

day

450.00

67.50 1027.50

Subtotal-A: Workshop Charges, & other consumables.

( +25.00 % on Subtotal-A )

256.88

Subtotal-A1:

1284.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1310.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1441.07

VAT

6% of Total

96.07

IT

4% of Total

64.05 Total:

4.15.09.04

62.50mm dia. and wall thickness 3.00mm

m 62.5mm dia. Stainless Steel pipe and wall thickness 3.00mm

1.0000

m

1450.00

1450.00

Skilled Labour

0.1500

day

450.00

67.50 1517.50

Subtotal-A: Workshop Charges, & other consumables.

( +25.00 % on Subtotal-A )

Subtotal-A1:

379.38 1896.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1934.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2128.29

VAT

6% of Total

IT

4% of Total

141.89 94.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1601.19

2364.77

Page: 822 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.09.05

Detailed Analysis Brief Description of Item 2 75mm dia. and wall thickness 3.00mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 75mm dia. Stainless Steel pipe and wall thickness 3.00mm

1.0000

m

1700.00

1700.00

Skilled Labour

0.1500

day

450.00

67.50 1767.50

Subtotal-A: Workshop Charges, & other consumables.

( +25.00 % on Subtotal-A )

441.88

Subtotal-A1:

2209.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2253.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2478.92

VAT

6% of Total

165.26

IT

4% of Total

110.17 Total:

4.15.09.06

100mm dia. and wall thickness 3.00mm

m 100mm dia. Stainless Steel pipe and wall thickness 3.00mm

1.0000

m

2450.00

2450.00

Skilled Labour

0.1500

day

450.00

67.50 2517.50

Subtotal-A: Workshop Charges, & other consumables.

( +25.00 % on Subtotal-A )

Subtotal-A1:

629.38 3146.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3209.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3530.79

VAT

6% of Total

IT

4% of Total

235.39 156.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2754.35

3923.10

Page: 823 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.09.07

Detailed Analysis Brief Description of Item 2 125mm dia. and wall thickness 3.00mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 125mm dia. Stainless Steel pipe and wall thickness 3.00mm

1.0000

m

3200.00

3200.00

Skilled Labour

0.1500

day

450.00

67.50 3267.50

Subtotal-A: Workshop Charges, & other consumables.

( +25.00 % on Subtotal-A )

Subtotal-A1:

816.88 4084.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4166.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4582.67

VAT

6% of Total

305.51

IT

4% of Total

203.67 Total:

4.15.10

Amount

5091.85

Supplying fitting and fixing railing & rail post made of various size Stainless Steel (SS) Square/Rectangular Box of standard thickness for normal & ornamental Bridge or any other structure, including required SS plate, nutbolt, cutting, welding, laying in position, etc. all complete as per design, drawing, spacification & the direction of the Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 824 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.10.01

Detailed Analysis Brief Description of Item 2 Size: 25mm x 25mm Stainless Steel box and wall thickness 2.00mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 25mm x 25mm Stainless Steel box and wall thickness 2.00mm

1.0000

m

570.00

570.00

Skilled Labour

0.1500

day

450.00

67.50 637.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

159.38

Subtotal-A1: Subtotal-B: Subtotal-C:

796.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

812.81

10% Profit ( Add 10% on Subtotal-B) :

894.09

VAT

6% of Total

IT

4% of Total

59.61 39.74 Total:

4.15.10.02

Size: 32mm x 32mm Stainless Steel box and wall thickness 1.50mm

m 32mm x 32mm Stainless Steel box and wall thickness 1.50mm

1.0000

m

555.00

555.00

Skilled Labour

0.1500

day

450.00

67.50 622.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

Subtotal-A1:

155.63 778.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

793.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

873.06

VAT

6% of Total

IT

4% of Total

58.20 38.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

993.44

970.06

Page: 825 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.10.03

Detailed Analysis Brief Description of Item 2 Size: 38mm x 38mm Stainless Steel box and wall thickness 2.50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 38mm x 38mm Stainless Steel box and wall thickness 2.50mm

1.0000

m

915.00

915.00

Skilled Labour

0.1500

day

450.00

67.50 982.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

245.63

Subtotal-A1: Subtotal-B: Subtotal-C:

1228.13 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1252.69

10% Profit ( Add 10% on Subtotal-B) :

1377.96

VAT

6% of Total

IT

4% of Total

91.86 61.24 Total:

4.15.10.04

Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

m 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

1.0000

m

1150.00

1150.00

Skilled Labour

0.1500

day

450.00

67.50 1217.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

Subtotal-A1:

304.38 1521.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1552.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1707.54

VAT

6% of Total

IT

4% of Total

113.84 75.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1531.06

1897.27

Page: 826 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.10.05

Detailed Analysis Brief Description of Item 2 Size: 62.5mm x 62.5mm Stainless Steel box and wall thickness 2.00mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 62.5mm x 62.5mm Stainless Steel box and wall thickness 2.00mm

1.0000

m

1495.00

1495.00

Skilled Labour

0.1500

day

450.00

67.50 1562.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

390.63

Subtotal-A1:

1953.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1992.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2191.41

VAT

6% of Total

IT

4% of Total

146.09 97.40 Total:

4.15.10.06

Size: 50mm x 25mm Stainless Steel box and wall thickness 1.50mm

m 50mm x 25mm Stainless Steel box and wall thickness 1.50mm

1.0000

m

680.00

680.00

Skilled Labour

0.1500

day

450.00

67.50 747.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

186.88 934.38

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

953.06 1048.37

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

69.89

IT

4% of Total

46.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2434.90

1164.85

Page: 827 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.10.07

Detailed Analysis Brief Description of Item 2 Size: 75mm x 25mm Stainless Steel box and wall thickness 1.50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 75mm x 25mm Stainless Steel box and wall thickness 1.50mm

1.0000

m

910.00

910.00

Skilled Labour

0.1500

day

450.00

67.50 977.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

244.38

Subtotal-A1: Subtotal-B: Subtotal-C:

1221.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1246.31

10% Profit ( Add 10% on Subtotal-B) :

1370.94

VAT

6% of Total

IT

4% of Total

91.40 60.93 Total:

4.15.10.08

Size: 75mm x 50mm Stainless Steel box and wall thickness 2.00mm

m 75mm x 50mm Stainless Steel box and wall thickness 2.00mm

1.0000

m

1405.00

1405.00

Skilled Labour

0.1500

day

450.00

67.50 1472.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

Subtotal-A1:

368.13 1840.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1877.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2065.18

VAT

6% of Total

IT

4% of Total

137.68 91.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1523.27

2294.65

Page: 828 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.10.09

Detailed Analysis Brief Description of Item 2 Size: 100mm x 50mm Stainless Steel box and wall thickness 2.00mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m 100mm x 50mm Stainless Steel box and wall thickness 2.00mm

1.0000

m

1765.00

1765.00

Skilled Labour

0.1500

day

450.00

67.50 1832.50

Subtotal-A: Size: 50mm x 50mm Stainless Steel box and wall thickness 2.00mm

( +25.00 % on Subtotal-A )

Subtotal-A1:

458.13 2290.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2336.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2570.08

VAT

6% of Total

IT

4% of Total

171.34 114.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2855.65

Page: 829 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.15.11

Detailed Analysis Brief Description of Item 2 Painting on Concrete Surface: Providing and applying 2 coats of water based cement paint to unplastered concrete surface after cleaning the surface of dirt, dust, oil, grease, efflorescence and applying paint @ 1 litre for 2 sqm including cost of all materialas, labour etc. complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Cement Paint

0.5000

kg

80.00

40.00

Plumber/ Electric Mistry/ Painter

0.0010

day

680.00

0.68

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0250

day

470.00

11.75

Skilled Labour

0.0250

day

450.00

11.25 63.68

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

64.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

71.45

VAT

6% of Total

4.76

IT

4% of Total

3.18 Total:

4.16.01

Amount

79.39

Lifting of Super-Structure of Bridge for resetting if required/ refixing of new bearing including removal of old bearings and including all higher and runing expenses of all plants, jacks, machines and equipment, temporary supports, required for keeping the super-structure in lifted position for completing the operation, lowering of super-structure on bearings and without causing any detrimental effect to any part of the bridge structure, diversion of traffic if necessary etc. all complete as per design, drawing, specification & direction of E-I-C. The cost of replaced bearings has not been included in this rate. The work entails replacement of all the bearings on one side of the span.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 830 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.16.01.01

2 Span up to 20 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

per end Foreman

0.5000

day

800.00

400.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

3.0000

day

370.00

1110.00

H.C. of Jack for Lifting 50 ton lifting capacity

3.0000

day

1250.00

3750.00 5710.00

Subtotal-A: Wooden packing, Scaffolding Works etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1142.00 6852.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6989.04

10% Profit ( Add 10% on Subtotal-B) :

7687.94

VAT

6% of Total

IT

4% of Total

512.53 341.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8542.16

Page: 831 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.01.02

Detailed Analysis Brief Description of Item 2 Span beyond 20 m and upto 30 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

per end Foreman

0.5000

day

800.00

400.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

3.0000

day

370.00

1110.00

H.C. of Jack for Lifting 50 ton lifting capacity

4.0000

day

1250.00

5000.00 6960.00

Subtotal-A: Wooden packing, Scaffolding Works etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1392.00 8352.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8519.04

10% Profit ( Add 10% on Subtotal-B) :

9370.94

VAT

6% of Total

IT

4% of Total

624.73 416.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10412.16

Page: 832 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.16.01.03

2 Span beyond 30 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

per end Foreman

0.5000

day

800.00

400.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

3.0000

day

370.00

1110.00

H.C. of Jack for Lifting 50 ton lifting capacity

8.0000

day

1250.00

10000.00 11960.00

Subtotal-A: Wooden packing, Scaffolding Works etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2392.00 14352.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14639.04

10% Profit ( Add 10% on Subtotal-B) :

16102.94

VAT

6% of Total

IT

4% of Total

1073.53 715.69 Total:

4.16.02

Amount

17892.16

Removal of existing cement concrete/ bituminous wearing course over existing bridge deck including its disposal as per direction of E-I-C without causing any detrimental effect to any part of the bridge structure and removal of dismantled material with all lifts and lead upto 1 km. The dismantled materials must be dumped in an unobjectionable place outside the site premises with minimum traffic disruption and the procuring entity will not be responsible for any irregularities by the party regarding dumping of the materials.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 833 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.02.01

Detailed Analysis Brief Description of Item 2 Cement concrete wearing course of avg. 75mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.5000

day

370.00

185.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.0200

day

2500.00

50.00

H.C. of Tractor (2 WD)

0.0100

day

2200.00

22.00 279.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

285.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

313.60

VAT

6% of Total

20.91

IT

4% of Total

13.94 Total:

4.16.02.02

Bituminous wearing course of avg. 50mm thick asphaltic concrete laid over 12 mm thick mastic asphalt

sqm Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.4000

day

370.00

148.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.0200

day

2500.00

50.00

H.C. of Tractor (2 WD)

0.0100

day

2200.00

22.00 242.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

247.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

272.09

VAT

6% of Total

IT

4% of Total

18.14 12.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

348.44

302.32

Page: 834 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

4.16.03

Sealing of cracks/ porous concrete by injecting grout through nipples including cleaning the affected area by wire brush, compressed air, 15mm dia and 150 to 200mm deep holes along the length of the cracks at a spacing of 500mm may be drilled by wet drilling using rotary percussion drills and nipples, inerterd in these holes. Only non-shrink grout admixture conforming to ASTM C 1107 has been included in this unit rate. Where necessary and approved by the Engineer, admixutures to protland cement grout mixtures may be added for delaying the setting time, increasing flow ability, minimising segregation and shrinkage, not being added to the analysis.

4.16.03.01

Cement Grout

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg Ordinary Portland Cement (CEM I, 52.5N)

0.0220

bag

455.00

Non-Shrink Grout Admixture conforming to ASTM C 1107

0.0100

Kg

400.00

4.00

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.2500

day

370.00

92.50

Carriage, safe storage, mixing, cleaning, H.C. of Injecting equipment & sundries etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

10.01

162.76

Subtotal-A:

32.55 195.31

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

199.22

10% Profit ( Add 10% on Subtotal-B) :

219.14

VAT

6% of Total

14.61

IT

4% of Total

9.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

243.49

Page: 835 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.16.03.02

2 Cement Mortar (1:1) Grout

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg Ordinary Portland Cement (CEM I, 52.5N)

0.0110

bag

455.00

5.01

Sand (FM - 1.8)

0.0100

m3

970.00

9.70

Non-Shrink Grout Admixture conforming to ASTM C 1107

0.0100

Kg

400.00

4.00

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.2500

day

370.00

92.50 167.46

Subtotal-A: Carriage, safe storage, mixing, cleaning, H.C. of Injecting equipment & sundries etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

33.49 200.95

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

204.96

10% Profit ( Add 10% on Subtotal-B) :

225.46

VAT

6% of Total

IT

4% of Total

15.03 10.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

250.51

Page: 836 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.04

Detailed Analysis Brief Description of Item 2 Sealing of cracks/ porous concrete by injection of epoxy resin through nipples including cleaning the affected surfaces adjacent to cracks or other areas of application from dirt, grease, oil efflorescence or other foreign matter by brushing/ water jetting/ sand blasting. Just before use, the two components i.e. resin and hardeer, shall be thoroughly mixed in the ratios specified by the manufacturer. Acids and corrosives shall not be permitted for cleaning. Epoxy adhesive injection shall be performed until crakcs are complely filled. The Contractor shall furnish detailed methodology of construction including source of supply of material, tools, equipment and appliances to be used on work, details of personel and supervision and take approval from Design Unit, LGED.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

550.00

kg

Epoxy compound with accessories for preparing epoxy mortar

1.1000

kg

500.00

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.2500

day

370.00

92.50 698.75

Subtotal-A: H.C. of Epoxy Injection Gun, Carriage, safe storage, mixing, cleaning & sundries etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

139.75 838.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

855.27

10% Profit ( Add 10% on Subtotal-B) :

940.80

VAT

6% of Total

IT

4% of Total

62.72 41.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1045.33

Page: 837 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.05

Detailed Analysis Brief Description of Item 2 Shotcrete/ guniting concrete surface with 40mm thick (avg.) cement mortar comprising of cement, graded sand conforming to ASTM C 33, coarse aggregate (20 to 40% of total aggregate for thick sections if adequate guniting equptment is available), water and quick setting compound conforming to ASTM C 1141 in the proportion as per guidence of Central Quality Control Laboratory (CQCL), LGED or any approved laboratory instructed by Engineer-in-Charge, water cement ratio ranging from 0.35 to 0.5, density of shotcrete/ gunite not less than 2000kg/cum, strength not less than 25 MPa, applied with compressed air under pressure after cleaning removing old guniting/ part of defective concrete, cleaning the surface and exposed reinforcement thoroughly by sand blasting, spraying with epoxy conforming to ASTM C 881 @ 67 kg/sqm including cost of wire mesh fabrics 50mm x 50mm x 10 BWG in first layer of guniting complete as per drawings & direction of E-I-C. Wherever the reinforcement have been corroded, the same shall be removed and replaced by additional reinforcement.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

145.60

sqm

Ordinary Portland Cement (CEM I, 52.5N)

0.3200

bag

455.00

Sand (FM - 2.5)

0.0400

m3

1500.00

60.00

Epoxy resin-hardner mix for prime/seal coat conforming to ASTM C 881/ AASHTO M 235

0.6700

kg

785.00

525.95

Quick Setting Compound

0.6400

Kg

160.00

102.40

10 BWG wire reinforcement

2.0000

kg

90.00

180.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.2000

day

370.00

74.00

Air Compressor 250 cfm with pneumatic breaker/ jack hammer along with accessories.

0.0125

day

2500.00

31.25

H.C. of Shotcreting equipment

0.1000

hour

500.00

50.00

H.C. of Water Tanker (Towed by Tractor)

0.0100

day

1500.00

15.00 1295.45

Subtotal-A: Misellaneous consumables like nozzles, wire brush, cotton waste etc.

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +5.00 % on Subtotal-A )

64.77

Page: 838 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-A1:

1360.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1387.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1526.17

VAT

6% of Total

IT

4% of Total

101.74 67.83 Total:

4.16.06

Patching of damages concrete surface with 25mm thick (avg.) polymer concrete and curing compounds, initiator and promoter, available in present formulations, to be applied as per instruction of manufacturer and as approved by the E-I-C. This item is a proprietory item available in market as pre-packed plymer concrete and is required to be applied as per instructions of the manufacturer.

sqm

Acrylic Polymer Bonding Agent

0.1400

liter

160.00

22.40

Pre-packed cement based polymer mortar of strength 45 Mpa at 28 days

3.1500

kg

100.00

315.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.0000

day

370.00

370.00

H.C. of Grout pump with agitator & accessories

1.0000

hour

200.00

200.00 1187.40

Subtotal-A: Misellaneous consumables like wire brush, cotton waste etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

237.48 1424.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1453.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1598.72

VAT

6% of Total

IT

4% of Total

106.58 71.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1695.74

1776.35

Page: 839 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.07

Detailed Analysis Brief Description of Item 2 Providing and applying 10mm thick (avg.) pre-packed cement based polymer mortar of strength 45 MPa at 28 days by trowels & float over the spalled concrete for bridge deck, pier cap etc. including scaffolding, shuttering, supplying required material including polymer etc. complete as per the specification & as directed by E-I-C. Primer coat by Nylon brush must be applied on the spalled out concrete location before applying polymer mortar.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Acrylic Polymer Bonding Agent

0.1400

liter

160.00

22.40

Pre-packed cement based polymer mortar of strength 45 Mpa at 28 days

1.2000

kg

100.00

120.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00 435.40

Subtotal-A: Misellaneous consumables like wire brush, cotton waste, wastage of chemical etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

21.77 457.17

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

466.31

10% Profit ( Add 10% on Subtotal-B) :

512.94

VAT

6% of Total

IT

4% of Total

34.20 22.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

569.94

Page: 840 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.08

Detailed Analysis Brief Description of Item 2 EBA: Providing & applying epoxy bonding agent conforming to ASTM C 881/ AASHTO M 235 to exposed old concrete surfaces for bonding of freshly mixed concrete to hardened concrete at the rate of 0.80 Kg/sqm or as per manufacturer's recommendation with pot life not less than 6090 minutes at normal temperature including cost of materials, storage, labour, tools, lead lifts, preparation of surface, cleaning the surface, tackles etc. complete as per manufacturer's specification and as directed & instructed by Engineer-In-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Epoxy resin-hardner mix for prime/seal coat conforming to ASTM C 881/ AASHTO M 235

0.8000

kg

785.00

628.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.2500

day

370.00

92.50 831.75

Subtotal-A: Carriage, safe storage, wastage, mixing & sundries etc.

( +4.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

33.27 865.02

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

882.32

10% Profit ( Add 10% on Subtotal-B) :

970.55

VAT

6% of Total

64.70

IT

4% of Total

43.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1078.39

Page: 841 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.09

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Applying epoxy mortar over leached, honey combed and spalled concrete surface and exposed steel reinforcement complete as per direction of E-I-C. Thickness of epoxy mortar shall not be less than 10mm

sqm

Quantity 5

Unit

Rate

6

7

8

Epoxy resin-hardner mix for prime/seal coat conforming to ASTM C 881/ AASHTO M 235

0.2500

kg

785.00

196.25

Epoxy mortar

0.2200

kg

275.00

60.50

Epoxy resin-hardner mix for prime/seal coat conforming to ASTM C 881/ AASHTO M 235

0.2000

kg

785.00

157.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.2500

day

370.00

92.50 617.50

Subtotal-A: Carriage, safe storage, wastage, mixing & sundries etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

30.88 648.38

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

661.34

10% Profit ( Add 10% on Subtotal-B) :

727.48

VAT

6% of Total

48.50

IT

4% of Total

32.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

808.31

Page: 842 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.10

Detailed Analysis Brief Description of Item 2 Replacement of Expansion Joints including removal and replacement of 300 mm wide portion of a existing deck slab to accommodate expansion joint, cleaning by blower, fabrication of additional reinforcement (if required), applying epoxy bonding agent for old to new concrete conforming to ASTM C 881, concreting with 35 MPa concrete after fixing the expansion joint complete as per manufacture specifications & direction of E-I-C. The cost of admixture & epoxy required for this work has been included in this analysis. The rate for the installation of new exapansion joints may be taken from the chapter 11 on Bridge Works.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Epoxy resin-hardner mix for prime/seal coat conforming to ASTM C 881/ AASHTO M 235

0.8000

kg

785.00

628.00

Stone Chips (20mm down graded) [LAA≤30]

0.0700

m3

5320.00

372.40

Sand (FM - 2.5)

0.0350

m3

1500.00

52.50

Ordinary Portland Cement (CEM I, 52.5N)

0.8000

bag

455.00

364.00

Water-reducing high range chemical admixture : Type-F

0.2500

liter

160.00

40.00

Head Mason

0.0150

day

650.00

9.75

Mason

0.1500

day

550.00

82.50

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0300

day

1200.00

36.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 2574.15

Subtotal-A: Labour for epoxy application etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

128.71 2702.86

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2756.91

10% Profit ( Add 10% on Subtotal-B) :

3032.61

VAT

6% of Total

IT

4% of Total

202.17 134.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3369.56 Page: 843 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.11

Detailed Analysis Brief Description of Item 2 Clearing slab/ box/ pipe culverts including cleaning and reshapping of both upstream and down stream faces of existing culvert with in right of way by removing deposited debris, silt, soil and any other foreign material. The job includes safe disposal of excess material recovered from site including vegetation outside ROW with all leads and lifts complete in all respect as per direction of Engineer In-Charge. Frequency of cleaning will be one time in a year i.e. before start of monsoon.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Skilled Labour

0.0333

day

450.00

14.99

Ordinary Labour

0.1667

day

370.00

61.68

H.C. of Tractor (2 WD)

0.0042

day

2200.00

9.24 85.90

Subtotal-A: Cost of Hand Tools etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

4.30 90.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

92.00 101.20 6.75 4.50

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

112.45

Page: 844 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.12

Detailed Analysis Brief Description of Item 2 Carrying out proper cleaning of carriageways, footpaths, verges, expansion joints (for free movement), drainage spouts of bridge including removal and disposal of trash, plastic, vegetation etc. from site outside ROW complete as per direction of E-I-C. Frequency of cleaning will be two times in a year i.e. before and after the monsoon.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

rm of bridge

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0400

day

370.00

14.80 19.30

Subtotal-A: Cost of Hand Tools etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

0.97 20.27

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22.74

VAT

6% of Total

1.52

IT

4% of Total

1.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

25.26

Page: 845 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.13

Detailed Analysis Brief Description of Item 2 Replacement of Damaged RCC Railing of 25 MPa strength having aggregate size not exceeding 12mm, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre to centre spacing between vertical post not to exceed 1500mm, leaving adequate space between vertical post for expansion, complete as per Bridge Design Standard For LGED- June 2012, approved drawings, technical specification and approval of E-I-C. The cost of reinforcement and it's fabrication, binding, welding and placing is included in this unit rate.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Construction of pre-cast/ Cast-in-situ RCC Railing of specified strength having aggregate size not exceeding 12mm, true to line and grade, tolerance of vertical RCC post not to exceed 1 in 500, centre.............4.15.08.02

1.0000

m

2379.36

2379.36

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.5000

day

370.00

185.00

H.C. of Tractor (2 WD)

0.0125

day

2200.00

27.50 2600.86

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2652.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2918.17

VAT

6% of Total

IT

4% of Total

194.54 129.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3242.41

Page: 846 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.14

Detailed Analysis Brief Description of Item 2 Carrying out repair of RCC railing of 25 MPa concrete to bring it to the original shape including dismantling and trimming the surface to a regular shape and removal of damaged material as per Bridge Design Standard for LGED, 2012 and direction of E-I-C. [Note: It is assumed that damage is to the extent of 10%]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

RCC-25SCCM: Reinforced cement concrete work with minimum cement content ralates to mix ratio 1:1.5:3 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 33.5 Mpa and sa.............4.09.03.06.02

0.0100

cum

10923.59

109.24

Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS ISO 6935-2:2006 (Grade 400)………….(4.11.01.04)

1.3000

kg

65.67

85.37

Skilled Labour

0.0016

day

450.00

0.72

Ordinary Labour

0.0200

day

370.00

7.40 202.73

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

206.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

227.46

VAT

6% of Total

15.16

IT

4% of Total

10.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

252.73

Page: 847 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.15

Detailed Analysis Brief Description of Item 2 Micro Concrete Work: Providing and laying in position Micro concrete having minimum compressive strength 50 MPa after 28 days (as per ASTM C 109), tensile strength 2 MPa after 28 days (as per ASTM C 307) and flexular strength 5 MPa after 28 days (as per ASTM C 580), cement based prepacked single component, chloride free, non shrink, free flow, self compacting, ready to use after mixing water in specified proportion obtained from approved manufacture including water tight shuttering and scaffolding etc. complete as per specification and as per direction of Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Micro Concrete (25 kg )

50.5122

bag

1850.00

93447.57

Stone Chips (12mm down graded) [LAA≤25]

0.8301

cum

4640.00

3851.66

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.3532

day

1200.00

423.84

Head Mason

0.3532

day

650.00

229.58

Mason

0.7065

day

550.00

388.58

Skilled Labour

1.4129

day

450.00

635.81

Ordinary Labour

5.6517

day

370.00

2091.13 101068.16

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +2.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2021.36 103089.53

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

105151.32

10% Profit ( Add 10% on Subtotal-B) :

115666.45

VAT

6% of Total

IT

4% of Total

7711.10 5140.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

128518.28

Page: 848 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.16.16

Chemically Bonded Anchor: Providing and fixing reinforcing bars by drilling holes up to specified depth and fixing required diameter anchor rods at every specified spacing on the surfaces of the slabs, columns, beams as the case may be, clean the same using water and make sure that there are no fine particles present in the hole, mix the base and hardener of the polyester resin with the spatula thoroughly, fill the drilled and cleaned holes to a maximum depth of 2/3rd of the hole with the prepared polyester resin, make sure that the resin has reached till the end of the hole. At this stage push the shear connector gently in to the hole and finish the excess resin which comes out of the hole and allow the shear connectors not to be disturbed for minimum 20 minutes, complete in all respect and direction of E-I-C. The cost of reinforcement is not included in this unit rate.

4.16.16.01

CBA_8: Diameter of Rebar = 8mm, minimum drilling diameter = 14mm, minimum drilling depth = 80mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each Epoxy resin based anchoring mortar for fixing heavy loads

0.0159 Cartridge

2700.00

42.93

H.C. of Vertical Drill Machine

0.0053

day

150.00

0.80

Operator

0.0053

day

570.00

3.02

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0053

day

470.00

2.49

Mason

0.0053

day

550.00

2.92

Skilled Labour

0.0106

day

450.00

4.77 56.92

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

63.87

VAT

6% of Total

IT

4% of Total

4.26 2.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

70.96

Page: 849 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.16.16.02

CBA_10: Diameter of Rebar = 10mm, minimum drilling diameter = 14mm, minimum drilling depth = 90mm

each Epoxy resin based anchoring mortar for fixing heavy loads

Quantity 5

Unit

Rate

6

7

0.0238 Cartridge

8

2700.00

64.26

H.C. of Vertical Drill Machine

0.0079

day

150.00

1.19

Operator

0.0079

day

570.00

4.50

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0079

day

470.00

3.71

Mason

0.0079

day

550.00

4.35

Skilled Labour

0.0159

day

450.00

7.16 85.16

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

86.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

95.55

VAT

6% of Total

6.37

IT

4% of Total

4.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

106.17

Page: 850 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.16.16.03

CBA_12: Diameter of Rebar = 12mm, minimum drilling diameter = 16mm, minimum drilling depth = 110mm

each Epoxy resin based anchoring mortar for fixing heavy loads

Quantity 5

Unit

Rate

6

7

0.0345 Cartridge

8

2700.00

93.15

H.C. of Vertical Drill Machine

0.0115

day

150.00

1.73

Operator

0.0115

day

570.00

6.56

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0115

day

470.00

5.41

Mason

0.0115

day

550.00

6.33

Skilled Labour

0.0230

day

450.00

10.35 123.51

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

125.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

138.58

VAT

6% of Total

9.24

IT

4% of Total

6.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

153.98

Page: 851 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.16.16.04

CBA_16: Diameter of Rebar = 16mm, minimum drilling diameter = 20mm, minimum drilling depth = 125mm

each Epoxy resin based anchoring mortar for fixing heavy loads

Quantity 5

Unit

Rate

6

7

0.0625 Cartridge

8

2700.00

168.75

H.C. of Vertical Drill Machine

0.0208

day

150.00

3.12

Operator

0.0208

day

570.00

11.86

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0208

day

470.00

9.78

Mason

0.0208

day

550.00

11.44

Skilled Labour

0.0417

day

450.00

18.77 223.71

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

228.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

251.00

VAT

6% of Total

16.73

IT

4% of Total

11.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

278.89

Page: 852 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.16.16.05

CBA_20: Diameter of Rebar = 20mm, minimum drilling diameter = 25mm, minimum drilling depth = 170mm

each Epoxy resin based anchoring mortar for fixing heavy loads

Quantity 5

Unit

Rate

6

7

0.1250 Cartridge

8

2700.00

337.50

H.C. of Vertical Drill Machine

0.0417

day

150.00

6.26

Operator

0.0417

day

570.00

23.77

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0417

day

470.00

19.60

Mason

0.0417

day

550.00

22.94

Skilled Labour

0.0833

day

450.00

37.49 447.54

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

456.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

502.14

VAT

6% of Total

33.48

IT

4% of Total

22.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

557.94

Page: 853 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.16.16.06

CBA_25: Diameter of Rebar = 25mm, minimum drilling diameter = 32mm, minimum drilling depth = 250mm

each Epoxy resin based anchoring mortar for fixing heavy loads

Quantity 5

Unit

Rate

6

7

0.3333 Cartridge

8

2700.00

899.91

H.C. of Vertical Drill Machine

0.1111

day

150.00

16.67

Operator

0.1111

day

570.00

63.33

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1111

day

470.00

52.22

Mason

0.1111

day

550.00

61.11

Skilled Labour

0.2222

day

450.00

99.99 1193.21

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1217.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1338.79

VAT

6% of Total

89.25

IT

4% of Total

59.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1487.54

Page: 854 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

4.16.16.07

CBA_32: Diameter of Rebar = 32mm, minimum drilling diameter = 40mm, minimum drilling depth = 300mm

each Epoxy resin based anchoring mortar for fixing heavy loads

Quantity 5

Unit

Rate

6

7

0.5000 Cartridge

8

2700.00

1350.00

H.C. of Vertical Drill Machine

0.1667

day

150.00

25.01

Operator

0.1667

day

570.00

95.02

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1667

day

470.00

78.35

Mason

0.1667

day

550.00

91.69

Skilled Labour

0.3333

day

450.00

149.99 1790.04

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1825.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2008.43

VAT

6% of Total

133.90

IT

4% of Total

89.26 Total:

4.16.17

Amount

2231.59

EP: Providing external prestressing with high tensile steel wires/strands including drilling for passage of prestessing steel, all accessories for stressing and stressing operation and grouting complete as per drawing and Technical specification. [This item shall be selected as per instruction given in the drawing & after getting approval from Desing Unit, LGED.]

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 855 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.17.01

Detailed Analysis Brief Description of Item 2 EP_25m: Span assumed: 25 m (12.7mm dia. Strand in 12T13/12K13 system. Weight-9.42 kg/m of cable.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT H.T. Strand

1.0500

75mm diameter HDPE Sheathing Duct

112.0000

Corrosion resistant Structural steel

MT

100000.00

105000.00

m

160.00

17920.00

bag

455.00

3640.00

2100.0000

kg

58.00

121800.00

8.0000

kg

500.00

4000.00

Ordinary Portland Cement (CEM I, 52.5N)

8.0000

Epoxy compound with accessories for preparing epoxy mortar Foreman

0.2600

day

800.00

208.00

Mason

1.3800

day

550.00

759.00

Fitter

0.7000

day

680.00

476.00

Re-bar Fabricator

3.0000

day

570.00

1710.00

Skilled Labour

3.0000

day

450.00

1350.00

16.3000

day

370.00

6031.00

H.C. of Stressing Jack with Pump and other accessories

0.5000

Day

1500.00

750.00

H.C. of Grout pump with agitator & accessories

1.3500

hour

200.00

270.00

Ordinary Labour

263914.00

Subtotal-A: Cost of achorage set, bearing plate, permanent wedges, lead sheet, sleeves, deviator fixtures etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

52782.80 316696.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

323030.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

355333.81

VAT

6% of Total

IT

4% of Total

23688.92 15792.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

394815.34

Page: 856 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.16.17.02

Detailed Analysis Brief Description of Item 2 EP_50m: Span assumed: 50 m (12.7mm dia. Strand in 19T13/19K13 system. Weight-14.73 kg/m of cable.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

MT H.T. Strand

3.1000

90mm diameter HDPE Sheathing Duct

Corrosion resistant Structural steel

MT

100000.00

310000.00

224.0000

m

170.00

38080.00

20.2000

bag

455.00

9191.00

7000.0000

kg

58.00

406000.00

10.0000

kg

500.00

5000.00

Ordinary Portland Cement (CEM I, 52.5N)

Epoxy compound with accessories for preparing epoxy mortar Foreman

0.4600

day

800.00

368.00

Mason

2.8600

day

550.00

1573.00

Fitter

1.0000

day

680.00

680.00

Re-bar Fabricator

7.0000

day

570.00

3990.00

Skilled Labour

8.0000

day

450.00

3600.00

42.0000

day

370.00

15540.00

H.C. of Stressing Jack with Pump and other accessories

0.8750

Day

1500.00

1312.50

H.C. of Grout pump with agitator & accessories

3.0000

hour

200.00

600.00

Ordinary Labour

795934.50

Subtotal-A: Cost of achorage set, bearing plate, permanent wedges, lead sheet, sleeves, deviator fixtures etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

159186.90 955121.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

974223.83 1071646.21 71443.08 47628.72

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1190718.01

Page: 857 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.17.01

Supplying and laying machine made pre-cast RCC pipes with collars of different diameter, length & thickness including screening, grading and washing aggregates with clear water, mixing, laying in steel forms, placing re-bars in position, consolidating, curing for at least 14 days including the cost of formwork, lifting, loading and unloading from factory/ yard, laying in position etc including tools, plants, testing etc. all complete as per direction of the E-I-C. The collars shall be of 200mm wide made by RCC and having the same strength as the pipes to be jointed. The spirals shall end in a complete ring/ turn at both the ends of pipes and collars. The cost of reinforcement and it's fabrication, welding, coupling, placing, binding etc. is included in this unit rate.

4.17.01.01

For Light/ Medium Traffic: Cross drains/ culverts/ outlet and any other works carrying light traffic in leanest mix 1:1.5:3 with cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, 20mm down well graded picked brick chips, sand of minimum FM 2.5 to attain a minimum 28 days cylinder strength of 20 MPa.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 858 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.01.01

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

300mm internal dia, wall thickness not less than 50mm, Re-bar for pipe:- circumferential: 10 turns - 6mmΦ and longitudinal: 8 nos. 6mmΦ , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

m

Quantity

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

5

0.4740

Unit

Rate

6

7

8

bag

430.00

203.82

Sand (FM - 2.5)

0.0252

m3

1500.00

37.80

1st Class Brick Chips (10mm down graded)

0.0503

m3

3049.00

153.36

M.S. Ribbed/ Deformed Bar (Grade 300)

5.1304

kg

54.00

277.04

Mason

0.0678

day

550.00

37.29

Operator

0.0250

day

570.00

14.25

Re-bar Fabricator

0.0250

day

570.00

14.25

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00

Skilled Labour

0.1285

day

450.00

57.83

Ordinary Labour

0.3412

day

370.00

126.24

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0250

day

1200.00

30.00

Diesel

0.0363

liter

68.00

2.47

Lubricant

0.0073

liter

220.00

1.61 1002.96

Subtotal-A: H.C. of Pipe manufacturing plant, Steel Formwork Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

200.59

1203.55

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1227.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1350.38

VAT

6% of Total

IT

4% of Total

90.03 60.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1500.43 Page: 859 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.01.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

400mm internal dia, wall thickness not less than 75mm, Re-bar for pipe:- circumferential: 14 turns - 6mmΦ and longitudinal: 8 nos. 6mmΦ , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

m

Quantity

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

5

0.9680

Unit

Rate

6

7

8

bag

430.00

416.24

Sand (FM - 2.5)

0.0514

m3

1500.00

77.10

1st Class Brick Chips (20mm down graded)

0.1028

m3

2940.00

302.23

M.S. Ribbed/ Deformed Bar (Grade 300)

7.4198

kg

54.00

400.67

Mason

0.0856

day

550.00

47.08

Operator

0.0286

day

570.00

16.30

Re-bar Fabricator

0.0286

day

570.00

16.30

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1072

day

470.00

50.38

Skilled Labour

0.1543

day

450.00

69.44

Ordinary Labour

0.7028

day

370.00

260.04

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0286

day

1200.00

34.32

Diesel

0.0363

liter

68.00

2.47

Lubricant

0.0073

liter

220.00

1.61 1694.17

Subtotal-A: H.C. of Pipe manufacturing plant, Steel Formwork Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

338.83

2033.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2073.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2281.04

VAT

6% of Total

IT

4% of Total

152.07 101.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2534.49 Page: 860 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.01.03

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

500mm internal dia, wall thickness not less than 75mm, Re-bar for pipe:- circumferential: 16 turns - 6mmΦ and longitudinal: 8 nos. 6mmΦ , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

m

Quantity

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

5

1.1850

Unit

Rate

6

7

8

bag

430.00

509.55

Sand (FM - 2.5)

0.0629

m3

1500.00

94.35

1st Class Brick Chips (20mm down graded)

0.1258

m3

2940.00

369.85

M.S. Ribbed/ Deformed Bar (Grade 300)

9.3332

kg

54.00

503.99

Mason

0.0856

day

550.00

47.08

Operator

0.0286

day

570.00

16.30

Re-bar Fabricator

0.0286

day

570.00

16.30

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1072

day

470.00

50.38

Skilled Labour

0.1543

day

450.00

69.44

Ordinary Labour

0.7028

day

370.00

260.04

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0286

day

1200.00

34.32

Diesel

0.0444

liter

68.00

3.02

Lubricant

0.0089

liter

220.00

1.96 1976.58

Subtotal-A: H.C. of Pipe manufacturing plant, Steel Formwork Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

395.32

2371.90

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2419.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2661.27

VAT

6% of Total

IT

4% of Total

177.42 118.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2956.97 Page: 861 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.01.04

Detailed Analysis Brief Description of Item 2 600mm internal dia, wall thickness not less than 85mm, Re-bar for pipe:- circumferential: 10 turns - 6mmΦ for inner cage & 8 turns 6mmΦ for outer cage and longitudinal: 6 nos. - 6mmΦ for inner cage & 6 nos. - 6mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.5738

bag

430.00

676.73

Sand (FM - 2.5)

0.0835

m3

1500.00

125.25

1st Class Brick Chips (20mm down graded)

0.1671

m3

2940.00

491.27

M.S. Ribbed/ Deformed Bar (Grade 300)

13.1686

kg

54.00

711.10

Mason

0.0856

day

550.00

47.08

Operator

0.0286

day

570.00

16.30

Re-bar Fabricator

0.0286

day

570.00

16.30

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1072

day

470.00

50.38

Skilled Labour

0.1543

day

450.00

69.44

Ordinary Labour

0.7028

day

370.00

260.04

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0286

day

1200.00

34.32

Diesel

0.0577

liter

68.00

3.92

Lubricant

0.0115

liter

220.00

2.53 2504.68

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

500.94

3005.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3065.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3372.29

VAT

6% of Total

IT

4% of Total

224.82 149.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3746.99 Page: 862 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 863 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.01.05

Detailed Analysis Brief Description of Item 2 700mm internal dia, wall thickness not less than 85mm, Re-bar for pipe:- circumferential: 13 turns - 6mmΦ for inner cage & 10 turns 6mmΦ for outer cage and longitudinal: 6 nos. - 6mmΦ for inner cage & 6 nos. - 6mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.8230

bag

430.00

783.89

Sand (FM - 2.5)

0.0968

m3

1500.00

145.20

1st Class Brick Chips (20mm down graded)

0.1936

m3

2940.00

569.18

M.S. Ribbed/ Deformed Bar (Grade 300)

17.3356

kg

54.00

936.12

Mason

0.0856

day

550.00

47.08

Operator

0.0368

day

570.00

20.98

Re-bar Fabricator

0.0368

day

570.00

20.98

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1472

day

470.00

69.18

Skilled Labour

0.1543

day

450.00

69.44

Ordinary Labour

0.7028

day

370.00

260.04

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0368

day

1200.00

44.16

Diesel

0.0837

liter

68.00

5.69

Lubricant

0.0167

liter

220.00

3.67 2975.61

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

595.12

3570.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3642.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4006.36

VAT

6% of Total

IT

4% of Total

267.09 178.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4451.51 Page: 864 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 865 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.01.06

Detailed Analysis Brief Description of Item 2 800mm internal dia, wall thickness not less than 95mm, Re-bar for pipe:- circumferential: 15 turns - 6mmΦ for inner cage & 11 turns 6mmΦ for outer cage and longitudinal: 7 nos. - 6mmΦ for inner cage & 7 nos. - 6mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.3194

bag

430.00

997.34

Sand (FM - 2.5)

0.1231

m3

1500.00

184.65

1st Class Brick Chips (20mm down graded)

0.2463

m3

2940.00

724.12

M.S. Ribbed/ Deformed Bar (Grade 300)

21.6004

kg

54.00

1166.42

Mason

0.1000

day

550.00

55.00

Operator

0.0470

day

570.00

26.79

Re-bar Fabricator

0.0470

day

570.00

26.79

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1879

day

470.00

88.31

Skilled Labour

0.1800

day

450.00

81.00

Ordinary Labour

0.8200

day

370.00

303.40

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0470

day

1200.00

56.40

Diesel

0.1069

liter

68.00

7.27

Lubricant

0.0214

liter

220.00

4.71 3722.21

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

744.44

4466.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4555.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5011.58

VAT

6% of Total

IT

4% of Total

334.11 222.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5568.42 Page: 866 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 867 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.01.07

Detailed Analysis Brief Description of Item 2 900mm internal dia, wall thickness not less than 100mm, Re-bar for pipe:- circumferential: 18 turns - 6mmΦ for inner cage & 14 turns 6mmΦ for outer cage and longitudinal: 7 nos. - 6mmΦ for inner cage & 7 nos. - 6mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 12 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.7387

bag

430.00

1177.64

Sand (FM - 2.5)

0.1454

m3

1500.00

218.10

1st Class Brick Chips (20mm down graded)

0.2908

m3

2940.00

854.95

M.S. Ribbed/ Deformed Bar (Grade 300)

28.0370

kg

54.00

1514.00

Mason

0.1142

day

550.00

62.81

Operator

0.0572

day

570.00

32.60

Re-bar Fabricator

0.0572

day

570.00

32.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0572

day

1200.00

68.64

Diesel

0.1300

liter

68.00

8.84

Lubricant

0.0260

liter

220.00

5.72 4522.60

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

904.52

5427.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5535.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6089.23

VAT

6% of Total

IT

4% of Total

405.95 270.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6765.81 Page: 868 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

For Heavy Traffic: Cross drains/ culverts/ outlet and any other works carrying heavy traffic in leanest mix 1:1.25:2.5 with cement conforming to BDS EN 197-1 : 2003 BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, 20mm down well graded stone chips broken from boulder (LAA not exceeding 30), sand of minimum FM 2.5 and water reducing admixture conforming to ASTM C 494 Type -A @ 1.75 liter per cubic meter of concrete to attain a minimum 28 days cylinder strength of 30 MPa.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 869 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.01

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

300mm internal dia, wall thickness not less than 50mm, Re-bar for pipe:- circumferential: 14 turns - 6mmΦ and longitudinal: 8 nos. 6mmΦ , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

m

Quantity

Ordinary Portland Cement (CEM I, 52.5N)

5

0.5488

Unit

Rate

6

7

8

455.00

249.70

bag

Sand (FM - 2.5)

0.0243

m3

1500.00

36.45

Stone Chips (12mm down graded) [LAA≤30]

0.0486

m3

4470.00

217.24

M.S. Ribbed/ Deformed Bar (Grade 300)

6.0285

kg

54.00

325.54

Water reducing chemical admixture : Type-A

0.1207

liter

130.00

15.69

Mason

0.0678

day

550.00

37.29

Operator

0.0250

day

570.00

14.25

Re-bar Fabricator

0.0250

day

570.00

14.25

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00

Skilled Labour

0.1285

day

450.00

57.83

Ordinary Labour

0.3412

day

370.00

126.24

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0250

day

1200.00

30.00

Diesel

0.0363

liter

68.00

2.47

Lubricant

0.0073

liter

220.00

1.61 1175.56

Subtotal-A: H.C. of Pipe manufacturing plant, Steel Formwork Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

235.11

1410.67 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1438.88

10% Profit ( Add 10% on Subtotal-B) :

1582.77

VAT

6% of Total

IT

4% of Total

105.52 70.35 Page: 870 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 1758.64

Page: 871 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

400mm internal dia, wall thickness not less than 75mm, Re-bar for pipe:- circumferential: 14 turns - 6mmΦ and longitudinal: 8 nos. 6mmΦ , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

m

Quantity

Ordinary Portland Cement (CEM I, 52.5N)

5

1.1209

Unit

Rate

6

7

8

455.00

510.01

bag

Sand (FM - 2.5)

0.0496

m3

1500.00

74.40

Stone Chips (12mm down graded) [LAA≤30]

0.0992

m3

4470.00

443.42

M.S. Ribbed/ Deformed Bar (Grade 300)

7.4198

kg

54.00

400.67

Water reducing chemical admixture : Type-A

0.2466

liter

130.00

32.06

Mason

0.0856

day

550.00

47.08

Operator

0.0286

day

570.00

16.30

Re-bar Fabricator

0.0286

day

570.00

16.30

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1072

day

470.00

50.38

Skilled Labour

0.1543

day

450.00

69.44

Ordinary Labour

0.7028

day

370.00

260.04

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0286

day

1200.00

34.32

Diesel

0.0363

liter

68.00

2.47

Lubricant

0.0073

liter

220.00

1.61 1958.49

Subtotal-A: H.C. of Pipe manufacturing plant, Steel Formwork Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

391.70

2350.19 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2397.20

10% Profit ( Add 10% on Subtotal-B) :

2636.92

VAT

6% of Total

IT

4% of Total

175.79 117.20 Page: 872 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 2929.91

Page: 873 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.03

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

500mm internal dia, wall thickness not less than 75mm, Re-bar for pipe:- circumferential: 19 turns - 6mmΦ and longitudinal: 8 nos. 6mmΦ , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

m

Quantity

Ordinary Portland Cement (CEM I, 52.5N)

5

1.3721

Unit

Rate

6

7

8

455.00

624.31

bag

Sand (FM - 2.5)

0.0607

m3

1500.00

91.05

Stone Chips (12mm down graded) [LAA≤30]

0.1214

m3

4470.00

542.66

10.4251

kg

54.00

562.96

Water reducing chemical admixture : Type-A

0.3019

liter

130.00

39.25

Mason

0.0856

day

550.00

47.08

Operator

0.0286

day

570.00

16.30

Re-bar Fabricator

0.0286

day

570.00

16.30

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1072

day

470.00

50.38

Skilled Labour

0.1543

day

450.00

69.44

M.S. Ribbed/ Deformed Bar (Grade 300)

Ordinary Labour

0.7028

day

370.00

260.04

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0286

day

1200.00

34.32

Diesel

0.0444

liter

68.00

3.02

Lubricant

0.0089

liter

220.00

1.96 2359.05

Subtotal-A: H.C. of Pipe manufacturing plant, Steel Formwork Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

471.81

2830.86 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2887.48

10% Profit ( Add 10% on Subtotal-B) :

3176.23

VAT

6% of Total

IT

4% of Total

211.75 141.17 Page: 874 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 3529.14

Page: 875 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.04

Detailed Analysis Brief Description of Item 2 600mm internal dia, wall thickness not less than 85mm, Re-bar for pipe:- circumferential: 19 turns - 6mmΦ for inner cage & 14 turns 6mmΦ for outer cage and longitudinal: 6 nos. - 6mmΦ for inner cage & 6 nos. - 6mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

1.8223

bag

455.00

829.15

Sand (FM - 2.5)

0.0806

m3

1500.00

120.90

Stone Chips (12mm down graded) [LAA≤30]

0.1612

m3

4470.00

720.56

M.S. Ribbed/ Deformed Bar (Grade 300)

20.2307

kg

54.00

1092.46

Water reducing chemical admixture : Type-A

0.4009

liter

130.00

52.12

Mason

0.0856

day

550.00

47.08

Operator

0.0286

day

570.00

16.30

Re-bar Fabricator

0.0286

day

570.00

16.30

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1072

day

470.00

50.38

Skilled Labour

0.1543

day

450.00

69.44

Ordinary Labour

0.7028

day

370.00

260.04

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0286

day

1200.00

34.32

Diesel

0.0577

liter

68.00

3.92

Lubricant

0.0115

liter

220.00

2.53 3315.50

Subtotal-A: H.C. of Pipe manufacturing plant, Steel Formwork Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

663.10

3978.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4058.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4463.99

VAT

6% of Total

IT

4% of Total

297.60 198.40 Page: 876 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 4959.98

Page: 877 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.05

Detailed Analysis Brief Description of Item 2 700mm internal dia, wall thickness not less than 85mm, Re-bar for pipe:- circumferential: 19 turns - 6mmΦ for inner cage & 14 turns 6mmΦ for outer cage and longitudinal: 8 nos. - 6mmΦ for inner cage & 8 nos. - 6mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

2.1109

bag

455.00

960.46

Sand (FM - 2.5)

0.0934

m3

1500.00

140.10

Stone Chips (12mm down graded) [LAA≤30]

0.1868

m3

4470.00

835.00

M.S. Ribbed/ Deformed Bar (Grade 300)

23.6199

kg

54.00

1275.47

Water reducing chemical admixture : Type-A

0.4644

liter

130.00

60.37

Mason

0.0856

day

550.00

47.08

Operator

0.0368

day

570.00

20.98

Re-bar Fabricator

0.0368

day

570.00

20.98

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1472

day

470.00

69.18

Skilled Labour

0.1543

day

450.00

69.44

Ordinary Labour

0.7028

day

370.00

260.04

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0368

day

1200.00

44.16

Diesel

0.0837

liter

68.00

5.69

Lubricant

0.0167

liter

220.00

3.67 3812.61

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

762.52

4575.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4666.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5133.30

VAT

6% of Total

IT

4% of Total

342.22 228.15 Page: 878 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 5703.67

Page: 879 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.06

Detailed Analysis Brief Description of Item 2 800mm internal dia, wall thickness not less than 95mm, Re-bar for pipe:- circumferential: 22 turns - 6mmΦ for inner cage & 17 turns 6mmΦ for outer cage and longitudinal: 8 nos. - 6mmΦ for inner cage & 8 nos. - 6mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 8 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

2.6856

bag

455.00

1221.95

Sand (FM - 2.5)

0.1188

m3

1500.00

178.20

Stone Chips (12mm down graded) [LAA≤30]

0.2376

m3

4470.00

1062.07

M.S. Ribbed/ Deformed Bar (Grade 300)

30.1117

kg

54.00

1626.03

Water reducing chemical admixture : Type-A

0.5908

liter

130.00

76.80

Mason

0.1000

day

550.00

55.00

Operator

0.0470

day

570.00

26.79

Re-bar Fabricator

0.0470

day

570.00

26.79

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1879

day

470.00

88.31

Skilled Labour

0.1800

day

450.00

81.00

Ordinary Labour

0.8200

day

370.00

303.40

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0470

day

1200.00

56.40

Diesel

0.1069

liter

68.00

7.27

Lubricant

0.0214

liter

220.00

4.71 4814.73

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

962.95

5777.67

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5893.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6482.55

VAT

6% of Total

IT

4% of Total

432.17 288.11 Page: 880 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 7202.83

Page: 881 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.07

Detailed Analysis Brief Description of Item 2 900mm internal dia, wall thickness not less than 100mm, Re-bar for pipe:- circumferential: 14 turns - 8mmΦ for inner cage & 11 turns 8mmΦ for outer cage and longitudinal: 8 nos. - 6mmΦ for inner cage & 8 nos. - 6mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 6mmΦ and longitudinal: 12 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

3.1711

bag

455.00

1442.85

Sand (FM - 2.5)

0.1403

m3

1500.00

210.45

Stone Chips (12mm down graded) [LAA≤30]

0.2806

m3

4470.00

1254.28

M.S. Ribbed/ Deformed Bar (Grade 300)

37.1018

kg

54.00

2003.50

Water reducing chemical admixture : Type-A

0.6976

liter

130.00

90.69

Mason

0.1142

day

550.00

62.81

Operator

0.0572

day

570.00

32.60

Re-bar Fabricator

0.0572

day

570.00

32.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0572

day

1200.00

68.64

Diesel

0.1300

liter

68.00

8.84

Lubricant

0.0260

liter

220.00

5.72 5759.67

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1151.93

6911.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7049.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7754.83

VAT

6% of Total

IT

4% of Total

516.99 344.66 Page: 882 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 8616.47

Page: 883 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.08

Detailed Analysis Brief Description of Item 2 1000mm internal dia, wall thickness not less than 115mm, Re-bar for pipe:- circumferential: 17 turns - 8mmΦ for inner cage & 13 turns 8mmΦ for outer cage and longitudinal: 8 nos. - 8mmΦ for inner cage & 8 nos. - 8mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 8mmΦ and longitudinal: 12 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

4.0411

bag

455.00

1838.70

Sand (FM - 2.5)

0.1788

m3

1500.00

268.20

Stone Chips (12mm down graded) [LAA≤30]

0.3575

m3

4470.00

1598.03

M.S. Ribbed/ Deformed Bar (Grade 300)

52.5381

kg

54.00

2837.06

Water reducing chemical admixture : Type-A

0.8890

liter

130.00

115.57

Mason

0.1142

day

550.00

62.81

Operator

0.0572

day

570.00

32.60

Re-bar Fabricator

0.0572

day

570.00

32.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0572

day

1200.00

68.64

Diesel

0.1500

liter

68.00

10.20

Lubricant

0.0300

liter

220.00

6.60 7417.70

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1483.54

8901.24

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9079.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9987.19

VAT

6% of Total

IT

4% of Total

665.81 443.88 Page: 884 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 11096.88

Page: 885 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.09

Detailed Analysis Brief Description of Item 2 1100mm internal dia, wall thickness not less than 115mm, Re-bar for pipe:- circumferential: 19 turns - 8mmΦ for inner cage & 14 turns 8mmΦ for outer cage and longitudinal: 8 nos. - 8mmΦ for inner cage & 8 nos. - 8mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 8mmΦ and longitudinal: 12 nos. - 6mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

4.4390

bag

455.00

2019.75

Sand (FM - 2.5)

0.1964

m3

1500.00

294.60

Stone Chips (12mm down graded) [LAA≤30]

0.3928

m3

4470.00

1755.82

M.S. Ribbed/ Deformed Bar (Grade 300)

61.0518

kg

54.00

3296.80

Water reducing chemical admixture : Type-A

0.9766

liter

130.00

126.96

Mason

0.1142

day

550.00

62.81

Operator

0.0715

day

570.00

40.76

Re-bar Fabricator

0.0715

day

570.00

40.76

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0715

day

1200.00

85.80

Diesel

0.1650

liter

68.00

11.22

Lubricant

0.0330

liter

220.00

7.26 8289.21

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1657.84

9947.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10145.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11160.59

VAT

6% of Total

IT

4% of Total

744.04 496.03 Page: 886 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 12400.65

Page: 887 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.10

Detailed Analysis Brief Description of Item 2 1200mm internal dia, wall thickness not less than 120mm, Re-bar for pipe:- circumferential: 21 turns - 8mmΦ for inner cage & 16 turns 8mmΦ for outer cage and longitudinal: 8 nos. - 8mmΦ for inner cage & 8 nos. - 8mmΦ for outer cage , Re-bar for Collar:- circumferential: 3 turns - 8mmΦ and longitudinal: 12 nos. - 8mmΦ

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

5.0933

bag

455.00

2317.45

Sand (FM - 2.5)

0.2253

m3

1500.00

337.95

Stone Chips (12mm down graded) [LAA≤30]

0.4506

m3

4470.00

2014.18

M.S. Ribbed/ Deformed Bar (Grade 300)

72.5811

kg

54.00

3919.38

Water reducing chemical admixture : Type-A

1.1205

liter

130.00

145.67

Mason

0.1142

day

550.00

62.81

Operator

0.0858

day

570.00

48.91

Re-bar Fabricator

0.0858

day

570.00

48.91

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0858

day

1200.00

102.96

Diesel

0.1793

liter

68.00

12.19

Lubricant

0.0360

liter

220.00

7.92 9565.01

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1913.00

11478.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11707.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12878.33

VAT

6% of Total

IT

4% of Total

858.56 572.37 Page: 888 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount 8 14309.26

Page: 889 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.11

Detailed Analysis Brief Description of Item 2 1400mm internal dia, wall thickness not less than 135mm, Re-bar for pipe:- circumferential: 17 turns - 10mmΦ for inner cage & 13 turns 10mmΦ for outer cage and longitudinal: 12 nos. - 8mmΦ for inner cage & 12 nos. - 8mmΦ for outer cage , Re-bar for Collar:circumferential: 3 turns - 8mmΦ for inner cage & 3 turns - 8mmΦ for outer cage and longitudinal: 8 nos. - 8mmΦ for inner cage & 8 nos. 8mmΦ for outer cage

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

6.6109

bag

455.00

3007.96

Sand (FM - 2.5)

0.2925

m3

1500.00

438.75

0.5849

m3

4470.00

2614.50

112.0797

kg

54.00

6052.30

Stone Chips (12mm down graded) [LAA≤30] M.S. Ribbed/ Deformed Bar (Grade 300) Water reducing chemical admixture : Type-A

1.4544

liter

130.00

189.07

Mason

0.1142

day

550.00

62.81

Operator

0.0858

day

570.00

48.91

Re-bar Fabricator

0.0858

day

570.00

48.91

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0858

day

1200.00

102.96

Diesel

0.2324

liter

68.00

15.80

Lubricant

0.0464

liter

220.00

10.21 13138.87

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2627.77

15766.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16081.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17690.18 Page: 890 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

8 1179.35 786.23

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19655.75

Page: 891 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.12

Detailed Analysis Brief Description of Item 2 1600mm internal dia, wall thickness not less than 140mm, Re-bar for pipe:- circumferential: 21 turns - 10mmΦ for inner cage & 16 turns 10mmΦ for outer cage and longitudinal: 12 nos. - 8mmΦ for inner cage & 12 nos. - 8mmΦ for outer cage , Re-bar for Collar:circumferential: 3 turns - 8mmΦ for inner cage & 3 turns - 8mmΦ for outer cage and longitudinal: 8 nos. - 8mmΦ for inner cage & 8 nos. 8mmΦ for outer cage

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

7.8418

bag

455.00

3568.02

Sand (FM - 2.5)

0.3469

m3

1500.00

520.35

0.6938

m3

4470.00

3101.29

148.9871

kg

54.00

8045.30

Stone Chips (12mm down graded) [LAA≤30] M.S. Ribbed/ Deformed Bar (Grade 300) Water reducing chemical admixture : Type-A

1.7252

liter

130.00

224.28

Mason

0.1142

day

550.00

62.81

Operator

0.0858

day

570.00

48.91

Re-bar Fabricator

0.0858

day

570.00

48.91

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0858

day

1200.00

102.96

Diesel

0.2324

liter

68.00

15.80

Lubricant

0.0464

liter

220.00

10.21 16295.52

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3259.10

19554.62

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19945.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21940.28 Page: 892 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

8 1462.69 975.12

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

24378.09

Page: 893 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.13

Detailed Analysis Brief Description of Item 2 1800mm internal dia, wall thickness not less than 150mm, Re-bar for pipe:- circumferential: 22 turns - 10mmΦ for inner cage & 22 turns 10mmΦ for outer cage and longitudinal: 14 nos. - 10mmΦ for inner cage & 14 nos. - 10mmΦ for outer cage , Re-bar for Collar:circumferential: 3 turns - 8mmΦ for inner cage & 3 turns - 8mmΦ for outer cage and longitudinal: 12 nos. - 8mmΦ for inner cage & 12 nos. 8mmΦ for outer cage

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N)

9.4541

bag

455.00

4301.62

Sand (FM - 2.5)

0.4182

m3

1500.00

627.30

0.8365

m3

4470.00

3739.16

201.3434

kg

54.00

10872.54

Stone Chips (12mm down graded) [LAA≤30] M.S. Ribbed/ Deformed Bar (Grade 300) Water reducing chemical admixture : Type-A

2.0799

liter

130.00

270.39

Mason

0.1142

day

550.00

62.81

Operator

0.0858

day

570.00

48.91

Re-bar Fabricator

0.0858

day

570.00

48.91

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0858

day

1200.00

102.96

Diesel

0.2324

liter

68.00

15.80

Lubricant

0.0464

liter

220.00

10.21 20647.28

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4129.46

24776.74

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25272.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

27799.50 Page: 894 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

8 1853.30 1235.53

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

30888.34

Page: 895 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.17.01.02.14

Detailed Analysis Brief Description of Item 2 2000mm internal dia, wall thickness not less than 170mm, Re-bar for pipe:- circumferential: 22 turns - 10mmΦ for inner cage & 22 turns 10mmΦ for outer cage and longitudinal: 14 nos. - 10mmΦ for inner cage & 14 nos. - 10mmΦ for outer cage , Re-bar for Collar:circumferential: 3 turns - 8mmΦ for inner cage & 3 turns - 8mmΦ for outer cage and longitudinal: 12 nos. - 8mmΦ for inner cage & 12 nos. 8mmΦ for outer cage

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Ordinary Portland Cement (CEM I, 52.5N) Sand (FM - 2.5) Stone Chips (12mm down graded) [LAA≤30] M.S. Ribbed/ Deformed Bar (Grade 300)

11.8754

bag

455.00

5403.31

0.5254

m3

1500.00

788.10

1.0507

m3

4470.00

4696.63

221.9522

kg

54.00

11985.42

Water reducing chemical admixture : Type-A

2.6126

liter

130.00

339.64

Mason

0.1142

day

550.00

62.81

Operator

0.0858

day

570.00

48.91

Re-bar Fabricator

0.0858

day

570.00

48.91

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2286

day

470.00

107.44

Skilled Labour

0.2056

day

450.00

92.52

Ordinary Labour

0.9371

day

370.00

346.73

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0858

day

1200.00

102.96

Diesel

0.2324

liter

68.00

15.80

Lubricant

0.0464

liter

220.00

10.21 24049.38

Subtotal-A: H.C. of Pipe manufacturing plant and cost of Steel Formwork, Earth oil, Power consumption & other Consumables etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4809.88

28859.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

29436.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

32380.08 Page: 896 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

Amount 8 2158.67 1439.11

Total: 4.18.01

RHT (Rebound/ Schmidt Hammer Test): Conducting rebound hammer test to assess quality of the concrete on built structure in accordance with ASTM C 805 (Standard Test Method for Rebound Number of Hardened Concrete) including preparing the surface of RCC structural members such as beams, columns, slabs etc. by chipping the plastered surface/ finishing/ cladding to expose the concrete, smoothening the area using carborndum stone all as directed by E-I-C, preparation of separate report for each structure with observations and recommendations for remedial measures if any. Before commencing RHT, Contractor shall submit methodology with resumes of the consulting personnel for conducting test to the E-I-C for approval.

4.18.01.01

Mobilization & demobilization within 100km of Dhaka/ nearby source to site and RHT on 10 (ten) nos. spots or less of a single structure

set RHT: Mobilization, demobilization & accomodation including 10 nos. RHT (Rebound Hammer Test)

1.0000 ithin 100k

Foreman

1.0000

Ordinary Labour

1.0000

10000.00

10000.00

day

800.00

800.00

day

370.00

370.00 11170.00

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

558.50 11728.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11963.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13159.38

VAT

6% of Total

877.29

IT

4% of Total

584.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35977.87

14621.53

Page: 897 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.18.01.02

Detailed Analysis Brief Description of Item 2 Additional charge on Mobilization & demobilization beyond 100km of dhaka/ nearby source to site

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

per km RHT/UPV: Beyond 100km from Dhaka

1.0000 per km

25.00

25.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

28.05

VAT

6% of Total

1.87

IT

4% of Total

1.25 Total:

4.18.01.03

RHT on each additional spot after 10(ten) spots tested.

31.17

each RHT: per impact after 1st 10 RHT

1.0000

each

1000.00

1000.00

Foreman

0.1000

day

800.00

80.00

Ordinary Labour

0.1000

day

370.00

37.00 1117.00

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

55.85 1172.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1196.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1315.94

VAT

6% of Total

87.73

IT

4% of Total

58.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25.00

1462.15

Page: 898 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.18.02

UPV (Ultrasonic Pulse Velocity) Test: Conducting Ultrasonic Pulse Velocity test to assess uniformity, homogeneity and quality of the concrete, in terms of cracks, voids, flaws, honeycombing etc. and other inperfections in accordance with ASTM C 597 (Standard Test Method for Pulse Velocity Through Concrete) including preparing the surface of RCC structural members such as beams, columns, slabs etc. by chipping the plastered surface/ finishing/ cladding to expose the concrete, smoothening the area using carborndum stone all as directed by E-I-C, preparation of separate report for each structure with observations and recommendations for remedial measures if any. Before commencing UPV, Contractor shall submit methodology with resumes of the consulting personnel for conducting test to the E-I-C for approval.

4.18.02.01

Mobilization & demobilization within 100km of Dhaka/ nearby source to site and UPV on 10 (ten) nos. spots or less of a single structure

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set UPV: Mobilization, demobilization & accomodation including 10 nos. UPV (Ultrasonic Pulse Velocity) Test

1.0000 ithin 100k

Foreman

1.0000

Ordinary Labour

1.0000

15000.00

15000.00

day

800.00

800.00

day

370.00

370.00 16170.00

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

808.50 16978.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17318.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19049.88

VAT

6% of Total

IT

4% of Total

1269.99 846.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

21166.53

Page: 899 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.18.02.02

Detailed Analysis Brief Description of Item 2 Additional charge on Mobilization & demobilization beyond 100km of dhaka/ nearby source to site

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

per km RHT/UPV: Beyond 100km from Dhaka

1.0000 per km

25.00

25.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

28.05

VAT

6% of Total

1.87

IT

4% of Total

1.25 Total:

4.18.02.03

UPV on each additional spot after 10(ten) spots tested.

31.17

each UPV: per test after 1st 10 UPV

1.0000

each

1500.00

1500.00

Foreman

0.1000

day

800.00

80.00

Ordinary Labour

0.1000

day

370.00

37.00 1617.00

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

80.85 1697.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1731.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1904.99

VAT

6% of Total

127.00

IT

4% of Total

84.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25.00

2116.65

Page: 900 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.18.03

Core Cutter: Obtaining, preparing and testing in-situ cylindrical core specimens of specified diameter drilled from hardened concrete including core location determination by rebar locator/ scanning and preparing the structural members as directed to expose the concrete, cleaning the area with blower/ wire brush and taking out the comcrete sample with cutter and testing as per standard specification. The procedure for drilling, examination, measurement and testing for comprehensive strength shall be in accordance with ASTM C 42 (Standard Test Method for obtaining and testing drilled cores and sawed beams of concrete). Before commencing Core cutting, contractor shall submit methodology with resumes of the consulting personnel for conducting test to the E-I-C for approval. The cost of cutting the core with necessary laboratory test fees is included in this unit rate.

4.18.03.01

Mobilization & demobilization within 100km of Dhaka/ nearby source to site and in-situ core cutting on 3 (three) nos. spots or less of a single structure

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set

Mobilization, demobilization & accomodation including 3 nos. in-situ core cutting & testing

1.0000 ithin 100k

Foreman

1.0000

Ordinary Labour

1.0000

16000.00

16000.00

day

800.00

800.00

day

370.00

370.00 17170.00

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

858.50 18028.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18389.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20227.98

VAT

6% of Total

IT

4% of Total

1348.53 899.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

22475.53

Page: 901 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.18.03.02

Detailed Analysis Brief Description of Item 2 Additional charge on Mobilization & demobilization beyond 100km of Dhaka/ nearby source to site

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

per km Core Cutter: Beyond 100km from Dhaka

1.0000 per km

35.00

35.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

35.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

39.27

VAT

6% of Total

2.62

IT

4% of Total

1.75 Total:

4.18.03.03

In-situ core cutting on each additional nos. after 3(three) spots

43.63

each Core Cutter: per core after 1st 3 cores

1.0000

each

4200.00

4200.00

Foreman

0.2500

day

800.00

200.00

Ordinary Labour

0.2500

day

370.00

92.50 4492.50

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

224.63 4717.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4811.47

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5292.61

VAT

6% of Total

352.84

IT

4% of Total

235.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35.00

5880.68

Page: 902 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.19.01

Sand Compaction Pile: Execution of sand compaction pile through displacement method by using tripod rig, mechanical winch, special type drop hammer (weighing minimum 1.00 ton) and casing pipe of inner diameter 200mm to 300mm upto a maximum depth of 10.0m, compacting the sand with desired sand volume and FM value of sand upto desired relative density (60% to 65%), to attain the desired SPT value between sand piles etc. complete including the cost of compacted sand as per design, specification and direction of Engineer in charge.

4.19.01.01

Pile diameter: 200mm

4.19.01.01.01

Sand Volumn 0.075 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

m3

795.00

8

m Sand (FM - 1.5)

0.0750

59.63

H.C. of Casing

0.0077

day

260.00

2.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0077

day

3000.00

23.10

H.C. of Driving Equipment

0.0077

day

350.00

2.70

Operator

0.0077

day

570.00

4.39

Foreman

0.0062

day

800.00

4.96

Skilled Labour

0.0246

day

450.00

11.07

Ordinary Labour

0.0215

day

370.00

7.96

Diesel

0.4892

liter

68.00

33.27

Lubricant

0.0061

liter

220.00

1.34 150.40

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

153.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

168.75

VAT

6% of Total

11.25

IT

4% of Total

7.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

187.50

Page: 903 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.01.02

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.075 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.0750

m3

970.00

72.75

H.C. of Casing

0.0077

day

260.00

2.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0077

day

3000.00

23.10

H.C. of Driving Equipment

0.0077

day

350.00

2.70

Operator

0.0077

day

570.00

4.39

Foreman

0.0062

day

800.00

4.96

Skilled Labour

0.0246

day

450.00

11.07

Ordinary Labour

0.0215

day

370.00

7.96

Diesel

0.4892

liter

68.00

33.27

Lubricant

0.0061

liter

220.00

1.34 163.53

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

166.80

10% Profit ( Add 10% on Subtotal-B) :

183.48

VAT

6% of Total

IT

4% of Total

12.23 8.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

203.87

Page: 904 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.01.03

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.075 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.0750

m3

1500.00

112.50

H.C. of Casing

0.0077

day

260.00

2.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0077

day

3000.00

23.10

H.C. of Driving Equipment

0.0077

day

350.00

2.70

Operator

0.0077

day

570.00

4.39

Foreman

0.0062

day

800.00

4.96

Skilled Labour

0.0246

day

450.00

11.07

Ordinary Labour

0.0215

day

370.00

7.96

Diesel

0.4892

liter

68.00

33.27

Lubricant

0.0061

liter

220.00

1.34 203.28

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

207.34

10% Profit ( Add 10% on Subtotal-B) :

228.08

VAT

6% of Total

IT

4% of Total

15.21 10.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

253.42

Page: 905 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.01.04

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.1 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.1000

m3

795.00

79.50

H.C. of Casing

0.0091

day

260.00

2.37

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0091

day

3000.00

27.30

H.C. of Driving Equipment

0.0091

day

350.00

3.19

Operator

0.0091

day

570.00

5.19

Foreman

0.0073

day

800.00

5.84

Skilled Labour

0.0291

day

450.00

13.10

Ordinary Labour

0.0255

day

370.00

9.44

Diesel

0.5782

liter

68.00

39.32

Lubricant

0.0072

liter

220.00

1.58 186.81

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

190.55

10% Profit ( Add 10% on Subtotal-B) :

209.60

VAT

6% of Total

IT

4% of Total

13.97 9.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

232.89

Page: 906 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.01.05

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.1 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.1000

m3

970.00

97.00

H.C. of Casing

0.0091

day

260.00

2.37

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0091

day

3000.00

27.30

H.C. of Driving Equipment

0.0091

day

350.00

3.19

Operator

0.0091

day

570.00

5.19

Foreman

0.0073

day

800.00

5.84

Skilled Labour

0.0291

day

450.00

13.10

Ordinary Labour

0.0255

day

370.00

9.44

Diesel

0.5782

liter

68.00

39.32

Lubricant

0.0072

liter

220.00

1.58 204.31

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

208.40

10% Profit ( Add 10% on Subtotal-B) :

229.24

VAT

6% of Total

IT

4% of Total

15.28 10.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

254.71

Page: 907 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.01.06

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.1 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.1000

m3

1500.00

150.00

H.C. of Casing

0.0091

day

260.00

2.37

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0091

day

3000.00

27.30

H.C. of Driving Equipment

0.0091

day

350.00

3.19

Operator

0.0091

day

570.00

5.19

Foreman

0.0073

day

800.00

5.84

Skilled Labour

0.0291

day

450.00

13.10

Ordinary Labour

0.0255

day

370.00

9.44

Diesel

0.5782

liter

68.00

39.32

Lubricant

0.0072

liter

220.00

1.58 257.31

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

262.46

10% Profit ( Add 10% on Subtotal-B) :

288.70

VAT

6% of Total

IT

4% of Total

19.25 12.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

320.78

Page: 908 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.01.07

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.15 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.1500

m3

795.00

119.25

H.C. of Casing

0.0133

day

260.00

3.46

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0133

day

3000.00

39.90

H.C. of Driving Equipment

0.0133

day

350.00

4.66

Operator

0.0133

day

570.00

7.58

Foreman

0.0107

day

800.00

8.56

Skilled Labour

0.0427

day

450.00

19.22

Ordinary Labour

0.0373

day

370.00

13.80

Diesel

0.8480

liter

68.00

57.66

Lubricant

0.0106

liter

220.00

2.33 276.42

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

281.94

10% Profit ( Add 10% on Subtotal-B) :

310.14

VAT

6% of Total

IT

4% of Total

20.68 13.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

344.60

Page: 909 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.01.08

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.15 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.1500

m3

970.00

145.50

H.C. of Casing

0.0133

day

260.00

3.46

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0133

day

3000.00

39.90

H.C. of Driving Equipment

0.0133

day

350.00

4.66

Operator

0.0133

day

570.00

7.58

Foreman

0.0107

day

800.00

8.56

Skilled Labour

0.0427

day

450.00

19.22

Ordinary Labour

0.0373

day

370.00

13.80

Diesel

0.8480

liter

68.00

57.66

Lubricant

0.0106

liter

220.00

2.33 302.67

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

308.72

10% Profit ( Add 10% on Subtotal-B) :

339.59

VAT

6% of Total

IT

4% of Total

22.64 15.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

377.32

Page: 910 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.19.01.01.09

2 Sand Volumn 0.15 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.1500

m3

1500.00

225.00

H.C. of Casing

0.0133

day

260.00

3.46

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0133

day

3000.00

39.90

H.C. of Driving Equipment

0.0133

day

350.00

4.66

Operator

0.0133

day

570.00

7.58

Foreman

0.0107

day

800.00

8.56

Skilled Labour

0.0427

day

450.00

19.22

Ordinary Labour

0.0373

day

370.00

13.80

Diesel

0.8480

liter

68.00

57.66

Lubricant

0.0106

liter

220.00

2.33 382.17

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

389.81

10% Profit ( Add 10% on Subtotal-B) :

428.79

VAT

6% of Total

IT

4% of Total

28.59 19.06 Total:

4.19.01.02

Amount

476.43

Pile diameter: 250mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 911 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.01

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.1 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.1000

m3

795.00

79.50

H.C. of Casing

0.0095

day

260.00

2.47

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0095

day

3000.00

28.50

H.C. of Driving Equipment

0.0095

day

350.00

3.33

Operator

0.0095

day

570.00

5.42

Foreman

0.0076

day

800.00

6.08

Skilled Labour

0.0305

day

450.00

13.73

Ordinary Labour

0.0267

day

370.00

9.88

Diesel

0.6057

liter

68.00

41.19

Lubricant

0.0076

liter

220.00

1.67 191.75

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

195.59

10% Profit ( Add 10% on Subtotal-B) :

215.15

VAT

6% of Total

IT

4% of Total

14.34 9.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

239.05

Page: 912 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.02

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.1 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.1000

m3

970.00

97.00

H.C. of Casing

0.0095

day

260.00

2.47

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0095

day

3000.00

28.50

H.C. of Driving Equipment

0.0095

day

350.00

3.33

Operator

0.0095

day

570.00

5.42

Foreman

0.0076

day

800.00

6.08

Skilled Labour

0.0305

day

450.00

13.73

Ordinary Labour

0.0267

day

370.00

9.88

Diesel

0.6057

liter

68.00

41.19

Lubricant

0.0076

liter

220.00

1.67 209.25

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

213.44

10% Profit ( Add 10% on Subtotal-B) :

234.78

VAT

6% of Total

IT

4% of Total

15.65 10.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

260.87

Page: 913 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.03

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.1 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.1000

m3

1500.00

150.00

H.C. of Casing

0.0095

day

260.00

2.47

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0095

day

3000.00

28.50

H.C. of Driving Equipment

0.0095

day

350.00

3.33

Operator

0.0095

day

570.00

5.42

Foreman

0.0076

day

800.00

6.08

Skilled Labour

0.0305

day

450.00

13.73

Ordinary Labour

0.0267

day

370.00

9.88

Diesel

0.6057

liter

68.00

41.19

Lubricant

0.0076

liter

220.00

1.67 262.25

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

267.50

10% Profit ( Add 10% on Subtotal-B) :

294.25

VAT

6% of Total

IT

4% of Total

19.62 13.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

326.94

Page: 914 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.04

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.15 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.1500

m3

795.00

119.25

H.C. of Casing

0.0143

day

260.00

3.72

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0143

day

3000.00

42.90

H.C. of Driving Equipment

0.0143

day

350.00

5.01

Operator

0.0143

day

570.00

8.15

Foreman

0.0114

day

800.00

9.12

Skilled Labour

0.0457

day

450.00

20.57

Ordinary Labour

0.0400

day

370.00

14.80

Diesel

0.9086

liter

68.00

61.78

Lubricant

0.0114

liter

220.00

2.51 287.80

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

293.56

10% Profit ( Add 10% on Subtotal-B) :

322.91

VAT

6% of Total

IT

4% of Total

21.53 14.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

358.79

Page: 915 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.05

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.15 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.1500

m3

970.00

145.50

H.C. of Casing

0.0143

day

260.00

3.72

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0143

day

3000.00

42.90

H.C. of Driving Equipment

0.0143

day

350.00

5.01

Operator

0.0143

day

570.00

8.15

Foreman

0.0114

day

800.00

9.12

Skilled Labour

0.0457

day

450.00

20.57

Ordinary Labour

0.0400

day

370.00

14.80

Diesel

0.9086

liter

68.00

61.78

Lubricant

0.0114

liter

220.00

2.51 314.05

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

320.33

10% Profit ( Add 10% on Subtotal-B) :

352.37

VAT

6% of Total

IT

4% of Total

23.49 15.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

391.52

Page: 916 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.06

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.15 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.1500

m3

1500.00

225.00

H.C. of Casing

0.0143

day

260.00

3.72

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0143

day

3000.00

42.90

H.C. of Driving Equipment

0.0143

day

350.00

5.01

Operator

0.0143

day

570.00

8.15

Foreman

0.0114

day

800.00

9.12

Skilled Labour

0.0457

day

450.00

20.57

Ordinary Labour

0.0400

day

370.00

14.80

Diesel

0.9086

liter

68.00

61.78

Lubricant

0.0114

liter

220.00

2.51 393.55

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

401.42

10% Profit ( Add 10% on Subtotal-B) :

441.57

VAT

6% of Total

IT

4% of Total

29.44 19.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

490.63

Page: 917 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.07

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.20 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.2000

m3

795.00

159.00

H.C. of Casing

0.0182

day

260.00

4.73

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0182

day

3000.00

54.60

H.C. of Driving Equipment

0.0182

day

350.00

6.37

Operator

0.0182

day

570.00

10.37

Foreman

0.0145

day

800.00

11.60

Skilled Labour

0.0582

day

450.00

26.19

Ordinary Labour

0.0509

day

370.00

18.83

Diesel

1.1564

liter

68.00

78.64

Lubricant

0.0145

liter

220.00

3.19 373.52

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

380.99

10% Profit ( Add 10% on Subtotal-B) :

419.09

VAT

6% of Total

IT

4% of Total

27.94 18.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

465.66

Page: 918 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.08

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.20 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.2000

m3

970.00

194.00

H.C. of Casing

0.0182

day

260.00

4.73

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0182

day

3000.00

54.60

H.C. of Driving Equipment

0.0182

day

350.00

6.37

Operator

0.0182

day

570.00

10.37

Foreman

0.0145

day

800.00

11.60

Skilled Labour

0.0582

day

450.00

26.19

Ordinary Labour

0.0509

day

370.00

18.83

Diesel

1.1564

liter

68.00

78.64

Lubricant

0.0145

liter

220.00

3.19 408.52

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

416.69

10% Profit ( Add 10% on Subtotal-B) :

458.36

VAT

6% of Total

IT

4% of Total

30.56 20.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

509.29

Page: 919 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.09

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.20 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.2000

m3

1500.00

300.00

H.C. of Casing

0.0182

day

260.00

4.73

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0182

day

3000.00

54.60

H.C. of Driving Equipment

0.0182

day

350.00

6.37

Operator

0.0182

day

570.00

10.37

Foreman

0.0145

day

800.00

11.60

Skilled Labour

0.0582

day

450.00

26.19

Ordinary Labour

0.0509

day

370.00

18.83

Diesel

1.1564

liter

68.00

78.64

Lubricant

0.0145

liter

220.00

3.19 514.52

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

524.81

10% Profit ( Add 10% on Subtotal-B) :

577.30

VAT

6% of Total

IT

4% of Total

38.49 25.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

641.44

Page: 920 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.10

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.25 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.2500

m3

795.00

198.75

H.C. of Casing

0.0222

day

260.00

5.77

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0222

day

3000.00

66.60

H.C. of Driving Equipment

0.0222

day

350.00

7.77

Operator

0.0222

day

570.00

12.65

Foreman

0.0178

day

800.00

14.24

Skilled Labour

0.0711

day

450.00

32.00

Ordinary Labour

0.0622

day

370.00

23.01

Diesel

1.4133

liter

68.00

96.10

Lubricant

0.0177

liter

220.00

3.89 460.79

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

470.01

10% Profit ( Add 10% on Subtotal-B) :

517.01

VAT

6% of Total

IT

4% of Total

34.47 22.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

574.46

Page: 921 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.02.11

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.25 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.2500

m3

970.00

242.50

H.C. of Casing

0.0222

day

260.00

5.77

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0222

day

3000.00

66.60

H.C. of Driving Equipment

0.0222

day

350.00

7.77

Operator

0.0222

day

570.00

12.65

Foreman

0.0178

day

800.00

14.24

Skilled Labour

0.0711

day

450.00

32.00

Ordinary Labour

0.0622

day

370.00

23.01

Diesel

1.4133

liter

68.00

96.10

Lubricant

0.0177

liter

220.00

3.89 504.54

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

514.63

10% Profit ( Add 10% on Subtotal-B) :

566.10

VAT

6% of Total

IT

4% of Total

37.74 25.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

629.00

Page: 922 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.19.01.02.12

2 Sand Volumn 0.25 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.2500

m3

1500.00

375.00

H.C. of Casing

0.0222

day

260.00

5.77

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0222

day

3000.00

66.60

H.C. of Driving Equipment

0.0222

day

350.00

7.77

Operator

0.0222

day

570.00

12.65

Foreman

0.0178

day

800.00

14.24

Skilled Labour

0.0711

day

450.00

32.00

Ordinary Labour

0.0622

day

370.00

23.01

Diesel

1.4133

liter

68.00

96.10

Lubricant

0.0177

liter

220.00

3.89 637.04

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

649.78

10% Profit ( Add 10% on Subtotal-B) :

714.76

VAT

6% of Total

IT

4% of Total

47.65 31.77 Total:

4.19.01.03

Amount

794.18

Pile diameter: 300mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 923 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.01

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.15 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.1500

m3

795.00

119.25

H.C. of Casing

0.0150

day

260.00

3.90

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0150

day

3000.00

45.00

H.C. of Driving Equipment

0.0150

day

350.00

5.25

Operator

0.0150

day

570.00

8.55

Foreman

0.0120

day

800.00

9.60

Skilled Labour

0.0480

day

450.00

21.60

Ordinary Labour

0.0420

day

370.00

15.54

Diesel

0.9540

liter

68.00

64.87

Lubricant

0.0119

liter

220.00

2.62 296.18

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

302.10

10% Profit ( Add 10% on Subtotal-B) :

332.31

VAT

6% of Total

IT

4% of Total

22.15 14.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

369.24

Page: 924 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.02

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.15 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.1500

m3

970.00

145.50

H.C. of Casing

0.0150

day

260.00

3.90

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0150

day

3000.00

45.00

H.C. of Driving Equipment

0.0150

day

350.00

5.25

Operator

0.0150

day

570.00

8.55

Foreman

0.0120

day

800.00

9.60

Skilled Labour

0.0480

day

450.00

21.60

Ordinary Labour

0.0420

day

370.00

15.54

Diesel

0.9540

liter

68.00

64.87

Lubricant

0.0119

liter

220.00

2.62 322.43

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

328.88

10% Profit ( Add 10% on Subtotal-B) :

361.77

VAT

6% of Total

IT

4% of Total

24.12 16.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

401.96

Page: 925 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.03

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.15 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.1500

m3

1500.00

225.00

H.C. of Casing

0.0150

day

260.00

3.90

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0150

day

3000.00

45.00

H.C. of Driving Equipment

0.0150

day

350.00

5.25

Operator

0.0150

day

570.00

8.55

Foreman

0.0120

day

800.00

9.60

Skilled Labour

0.0480

day

450.00

21.60

Ordinary Labour

0.0420

day

370.00

15.54

Diesel

0.9540

liter

68.00

64.87

Lubricant

0.0119

liter

220.00

2.62 401.93

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

409.97

10% Profit ( Add 10% on Subtotal-B) :

450.97

VAT

6% of Total

IT

4% of Total

30.06 20.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

501.07

Page: 926 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.04

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.20 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.2000

m3

795.00

159.00

H.C. of Casing

0.0200

day

260.00

5.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0200

day

3000.00

60.00

H.C. of Driving Equipment

0.0200

day

350.00

7.00

Operator

0.0200

day

570.00

11.40

Foreman

0.0160

day

800.00

12.80

Skilled Labour

0.0640

day

450.00

28.80

Ordinary Labour

0.0560

day

370.00

20.72

Diesel

1.2720

liter

68.00

86.50

Lubricant

0.0159

liter

220.00

3.50 394.91

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

402.81

10% Profit ( Add 10% on Subtotal-B) :

443.09

VAT

6% of Total

IT

4% of Total

29.54 19.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

492.33

Page: 927 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.05

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.20 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.2000

m3

970.00

194.00

H.C. of Casing

0.0200

day

260.00

5.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0200

day

3000.00

60.00

H.C. of Driving Equipment

0.0200

day

350.00

7.00

Operator

0.0200

day

570.00

11.40

Foreman

0.0160

day

800.00

12.80

Skilled Labour

0.0640

day

450.00

28.80

Ordinary Labour

0.0560

day

370.00

20.72

Diesel

1.2720

liter

68.00

86.50

Lubricant

0.0159

liter

220.00

3.50 429.91

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

438.51

10% Profit ( Add 10% on Subtotal-B) :

482.36

VAT

6% of Total

IT

4% of Total

32.16 21.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

535.96

Page: 928 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.06

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.20 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.2000

m3

1500.00

300.00

H.C. of Casing

0.0200

day

260.00

5.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0200

day

3000.00

60.00

H.C. of Driving Equipment

0.0200

day

350.00

7.00

Operator

0.0200

day

570.00

11.40

Foreman

0.0160

day

800.00

12.80

Skilled Labour

0.0640

day

450.00

28.80

Ordinary Labour

0.0560

day

370.00

20.72

Diesel

1.2720

liter

68.00

86.50

Lubricant

0.0159

liter

220.00

3.50 535.91

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

546.63

10% Profit ( Add 10% on Subtotal-B) :

601.30

VAT

6% of Total

IT

4% of Total

40.09 26.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

668.11

Page: 929 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.07

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.25 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.2500

m3

795.00

198.75

H.C. of Casing

0.0250

day

260.00

6.50

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0250

day

3000.00

75.00

H.C. of Driving Equipment

0.0250

day

350.00

8.75

Operator

0.0250

day

570.00

14.25

Foreman

0.0200

day

800.00

16.00

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.0700

day

370.00

25.90

Diesel

1.5900

liter

68.00

108.12

Lubricant

0.0199

liter

220.00

4.38 493.65

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

503.52

10% Profit ( Add 10% on Subtotal-B) :

553.87

VAT

6% of Total

IT

4% of Total

36.92 24.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

615.41

Page: 930 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.08

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.25 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.2500

m3

970.00

242.50

H.C. of Casing

0.0250

day

260.00

6.50

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0250

day

3000.00

75.00

H.C. of Driving Equipment

0.0250

day

350.00

8.75

Operator

0.0250

day

570.00

14.25

Foreman

0.0200

day

800.00

16.00

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.0700

day

370.00

25.90

Diesel

1.5900

liter

68.00

108.12

Lubricant

0.0199

liter

220.00

4.38 537.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

548.15

10% Profit ( Add 10% on Subtotal-B) :

602.96

VAT

6% of Total

IT

4% of Total

40.20 26.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

669.96

Page: 931 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.09

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.25 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.2500

m3

1500.00

375.00

H.C. of Casing

0.0250

day

260.00

6.50

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0250

day

3000.00

75.00

H.C. of Driving Equipment

0.0250

day

350.00

8.75

Operator

0.0250

day

570.00

14.25

Foreman

0.0200

day

800.00

16.00

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.0700

day

370.00

25.90

Diesel

1.5900

liter

68.00

108.12

Lubricant

0.0199

liter

220.00

4.38 669.90

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

683.30

10% Profit ( Add 10% on Subtotal-B) :

751.63

VAT

6% of Total

IT

4% of Total

50.11 33.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

835.14

Page: 932 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.10

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.30 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.3000

m3

795.00

238.50

H.C. of Casing

0.0300

day

260.00

7.80

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0300

day

3000.00

90.00

H.C. of Driving Equipment

0.0300

day

350.00

10.50

Operator

0.0300

day

570.00

17.10

Foreman

0.0240

day

800.00

19.20

Skilled Labour

0.0960

day

450.00

43.20

Ordinary Labour

0.0840

day

370.00

31.08

Diesel

1.9080

liter

68.00

129.74

Lubricant

0.0239

liter

220.00

5.26 592.38

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

604.23

10% Profit ( Add 10% on Subtotal-B) :

664.65

VAT

6% of Total

IT

4% of Total

44.31 29.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

738.50

Page: 933 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.11

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.30 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.3000

m3

970.00

291.00

H.C. of Casing

0.0300

day

260.00

7.80

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0300

day

3000.00

90.00

H.C. of Driving Equipment

0.0300

day

350.00

10.50

Operator

0.0300

day

570.00

17.10

Foreman

0.0240

day

800.00

19.20

Skilled Labour

0.0960

day

450.00

43.20

Ordinary Labour

0.0840

day

370.00

31.08

Diesel

1.9080

liter

68.00

129.74

Lubricant

0.0239

liter

220.00

5.26 644.88

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

657.78

10% Profit ( Add 10% on Subtotal-B) :

723.56

VAT

6% of Total

IT

4% of Total

48.24 32.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

803.95

Page: 934 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.12

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.30 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.3000

m3

1500.00

450.00

H.C. of Casing

0.0300

day

260.00

7.80

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0300

day

3000.00

90.00

H.C. of Driving Equipment

0.0300

day

350.00

10.50

Operator

0.0300

day

570.00

17.10

Foreman

0.0240

day

800.00

19.20

Skilled Labour

0.0960

day

450.00

43.20

Ordinary Labour

0.0840

day

370.00

31.08

Diesel

1.9080

liter

68.00

129.74

Lubricant

0.0239

liter

220.00

5.26 803.88

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

819.96

10% Profit ( Add 10% on Subtotal-B) :

901.96

VAT

6% of Total

IT

4% of Total

60.13 40.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1002.17

Page: 935 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.13

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.35 cum/m, minimum FM = 1.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.5)

0.3500

m3

795.00

278.25

H.C. of Casing

0.0350

day

260.00

9.10

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0350

day

3000.00

105.00

H.C. of Driving Equipment

0.0350

day

350.00

12.25

Operator

0.0350

day

570.00

19.95

Foreman

0.0280

day

800.00

22.40

Skilled Labour

0.1120

day

450.00

50.40

Ordinary Labour

0.0980

day

370.00

36.26

Diesel

2.2260

liter

68.00

151.37

Lubricant

0.0278

liter

220.00

6.12 691.09

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

704.92

10% Profit ( Add 10% on Subtotal-B) :

775.41

VAT

6% of Total

IT

4% of Total

51.69 34.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

861.56

Page: 936 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.14

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.35 cum/m, minimum FM = 1.8

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 1.8)

0.3500

m3

970.00

339.50

H.C. of Casing

0.0350

day

260.00

9.10

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0350

day

3000.00

105.00

H.C. of Driving Equipment

0.0350

day

350.00

12.25

Operator

0.0350

day

570.00

19.95

Foreman

0.0280

day

800.00

22.40

Skilled Labour

0.1120

day

450.00

50.40

Ordinary Labour

0.0980

day

370.00

36.26

Diesel

2.2260

liter

68.00

151.37

Lubricant

0.0278

liter

220.00

6.12 752.34

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

767.39

10% Profit ( Add 10% on Subtotal-B) :

844.13

VAT

6% of Total

IT

4% of Total

56.28 37.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

937.92

Page: 937 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.01.03.15

Detailed Analysis Brief Description of Item 2 Sand Volumn 0.35 cum/m, minimum FM = 2.5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Sand (FM - 2.5)

0.3500

m3

1500.00

525.00

H.C. of Casing

0.0350

day

260.00

9.10

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0350

day

3000.00

105.00

H.C. of Driving Equipment

0.0350

day

350.00

12.25

Operator

0.0350

day

570.00

19.95

Foreman

0.0280

day

800.00

22.40

Skilled Labour

0.1120

day

450.00

50.40

Ordinary Labour

0.0980

day

370.00

36.26

Diesel

2.2260

liter

68.00

151.37

Lubricant

0.0278

liter

220.00

6.12 937.84

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

956.60 1052.26

10% Profit ( Add 10% on Subtotal-B) :

VAT

70.15 46.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1169.18

Page: 938 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.19.02

Stone Column: Providing and installing cast-in-situ compaction stone column of speicified diameter and length to increase bearing capacity and reduce the settlement of construction by driving of suitable MS casing pipe (removable) having a detachable M.S.shoe (flat/conical) at the bottom and filling inside the casing pipe in layers of 1m using 1(sand; minimum FM 2.5) : 2(Shingles; Shingles shall be 50mm down graded) and each layer be well compacted by dynamic compaction method (before compaction lift the casing for 800mm from bottom and then the backfill shall be throughly compacted. This procedure shall be repeated for every layer till the ground level is reached) for ground improvement including all materials, labour etc complete as per specification, drawings and as directed by the E-I-C.

4.19.02.01

For 300mm diameter:

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 939 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.19.02.01.01

2 Fill Volumn 0.2 cum/m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Stone Shingles (20mm down graded)

0.1333

m3

3500.00

466.55

Sand (FM - 2.5)

0.0667

m3

1500.00

100.05

H.C. of Casing

0.0250

day

260.00

6.50

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0250

day

3000.00

75.00

H.C. of Driving Equipment

0.0250

day

350.00

8.75

Operator

0.0250

day

570.00

14.25

Foreman

0.0200

day

800.00

16.00

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.0700

day

370.00

25.90

Diesel

1.5900

liter

68.00

108.12

Lubricant

0.0199

liter

220.00

4.38 861.50

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

43.07 904.57

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

922.66 1014.93

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

67.66

IT

4% of Total

45.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1127.70

Page: 940 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.19.02.01.02

2 Fill Volumn 0.3 cum/m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Stone Shingles (20mm down graded)

0.2000

m3

3500.00

700.00

Sand (FM - 2.5)

0.1000

m3

1500.00

150.00

H.C. of Casing

0.0300

day

260.00

7.80

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0300

day

3000.00

90.00

H.C. of Driving Equipment

0.0300

day

350.00

10.50

Operator

0.0300

day

570.00

17.10

Foreman

0.0240

day

800.00

19.20

Skilled Labour

0.0960

day

450.00

43.20

Ordinary Labour

0.0840

day

370.00

31.08

Diesel

1.9080

liter

68.00

129.74

Lubricant

0.0239

liter

220.00

5.26 1203.88

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

60.19 1264.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1289.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1418.29

VAT

6% of Total

94.55

IT

4% of Total

63.04 Total:

4.19.02.02

Amount

1575.88

For 500mm diameter:

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 941 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.19.02.02.01

2 Fill Volumn 0.6 cum/m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Stone Shingles (20mm down graded)

0.4000

m3

3500.00

1400.00

Sand (FM - 2.5)

0.2000

m3

1500.00

300.00

H.C. of Casing

0.0300

day

260.00

7.80

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0300

day

3000.00

90.00

H.C. of Driving Equipment

0.0300

day

350.00

10.50

Operator

0.0300

day

570.00

17.10

Foreman

0.0240

day

800.00

19.20

Skilled Labour

0.0960

day

450.00

43.20

Ordinary Labour

0.0840

day

370.00

31.08

Diesel

1.9080

liter

68.00

129.74

Lubricant

0.0239

liter

220.00

5.26 2053.88

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

102.69 2156.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2199.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2419.68

VAT

6% of Total

161.31

IT

4% of Total

107.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2688.53

Page: 942 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.19.02.02.02

2 Fill Volumn 0.8 cum/m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Stone Shingles (20mm down graded)

0.5333

m3

3500.00

1866.55

Sand (FM - 2.5)

0.2667

m3

1500.00

400.05

H.C. of Casing

0.0350

day

260.00

9.10

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0350

day

3000.00

105.00

H.C. of Driving Equipment

0.0350

day

350.00

12.25

Operator

0.0350

day

570.00

19.95

Foreman

0.0280

day

800.00

22.40

Skilled Labour

0.1120

day

450.00

50.40

Ordinary Labour

0.0980

day

370.00

36.26

Diesel

2.2260

liter

68.00

151.37

Lubricant

0.0278

liter

220.00

6.12 2679.44

Subtotal-A: Other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

133.97 2813.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2869.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3156.65

VAT

6% of Total

210.44

IT

4% of Total

140.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

3507.39

Page: 943 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.03

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Prefabricated Vertical Drain (PVD)/ Wick Drain: Supply & Installation of prefabricated virtical drains/ wick drains to reduce the preload time & to accelerate settlement of embankments for bridge approach or roadways including unrolling the wick drain roll, changing & splicing wick drain roll, pushing hollow mandrel carrying into the ground carring the wick drain inside to protect it from tear, cuts and abrasion, providing anchor plate/ rod at the bottom of the mandrel to prevent soil from entering the mandrel during installation, maintain the mandrel in a vertical position, providing a minimum of 30 ton of static push force when setting on firm ground, installing by specialized wick drain installation equipment mounted on hydraulic excavator or crane, withdrawn the mandrel after the installtion of the drain, cost of furnishing all tools, materials, labour, equipment and all other costs necessary to complete the work as per design, specification & direction of the E-I-C. Hydraulic jetting shall not be permitted for installtion of the drains. The locations and depth of wick drain, sequene of installation will be as directed by the Engineer and specifications in conjuction with all drawings and logs. All drains will go to maximum allowable/ anchorable depth or until refusal as directed in the specification and logs. Note: Prior to installation of PVD the Contractor shall demonstrate that the equipment, method, and materials produce a satisfactory installation in accordance with the specifications. For this purpose, the Contractor will be required to install 2 trial drains at locations designated by the Engineer. Trial drains will be paid at the contract unit price unless the drain is improperly installed. 5% wastage is considered in this unit rate.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 944 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.03.01

Detailed Analysis Brief Description of Item 2 SPVD: Prefabricated Vertical Synthetic Drains shall consist of a continuous plastic drainage core wrapped in a non-woven polypropylene/polyester geotexile material having discharge capacity at 240 kPa and Hydraulic Gradient of 1 should be greater than 500 m3/yr and shall meet the following specifications. Composite Drain Properties: Weight (g/m) > 75± 10%, Width(mm) ≥ 100 ± 2, Thickness (mm) > 3.0, Tensile Strength (kN) > 2.2, Elongation at 2.0 kN (%) > 25, Strength at 10% Elongation (kN) > 1.3 Filter Fabric Properties: CBR Puncture Resistance (N) > 150, Trapezoidal Tear Strength (N) > 200, Grab Tensile Strength (N) > 550, Apparent opening size(AOS, O95) (micron) ≤ 90, Permeability/ Permittivity (cm/s) > 200 x 100

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

136.50

m

Prefabricated Vertical Synthetic Drains (SPVD)- Non-woven polypropylene/ polyester geotextile

1.0500

m

130.00

Skilled Labour

0.0030

day

450.00

1.35

Ordinary Labour

0.0182

day

370.00

6.73

Operator

0.0040

day

570.00

2.28

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0080

day

470.00

3.76

H.C. of Excavator (Medium Size)

0.0020

day

8880.00

17.76

Diesel

0.2030

liter

68.00

13.80

Lubricant

0.0025

liter

220.00

0.55 182.74

Subtotal-A: Anchor Plates, Staplers, Stapler Pins and other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

9.14 191.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

195.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

215.28

VAT

6% of Total

IT

4% of Total

14.35 9.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

239.20 Page: 945 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.03.02

Detailed Analysis Brief Description of Item 2 PVJD: Prefabricated Vertical Jute Drains (PVJD) shall consist of an outer sheath (jacket) made of woven jute geotextile (JGT) with 4-coir wicks separated by stitched compartments having discharge capacity at 7 days (200 kPa at hydraulic gradient of 1.0) shall be greater than 500 m3/yr and shall meet the following specifications. Composite Drain Properties: Width (mm) ≥ 90 ± 10%, Thickness (mm) > 5, Grab Tensile Strength (N), MD X CD > 350 X 350, Trapezoidal Tear Strength (N), MD X CD > 100 X 100, Puncture Resistance (N) > 100, Burst Strength (N) > 900, Apparent Opening size (AOS, O95) (micron) ≤ 90. Filter Fabric Properties: Equivalent Diameter (mm) > 50.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Prefabricated Vertical Jute Drain (PVJD) - Jute sheath with coir wick

1.0500

m

110.00

115.50

Skilled Labour

0.0030

day

450.00

1.35

Ordinary Labour

0.0182

day

370.00

6.73

Operator

0.0040

day

570.00

2.28

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0080

day

470.00

3.76

H.C. of Excavator (Medium Size)

0.0020

day

8880.00

17.76

Diesel

0.2030

liter

68.00

13.80

Lubricant

0.0025

liter

220.00

0.55 161.74

Subtotal-A: Anchor Plates, Staplers, Stapler Pins and other consumables etc.

( +5.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

8.09 169.82

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

173.22

10% Profit ( Add 10% on Subtotal-B) :

190.54

VAT

6% of Total

IT

4% of Total

12.70 8.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

211.72 Page: 946 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

4.19.04

Khoa Consolidation: 50mm down graded picked jhama Khoa Consolidation in foundation trenches by mixing in mixture machine with local sand of min. FM 1.2 incluing/ excluding cement to achieve minimum dry density of 90% with optimum mositure content (Modified Proctor Test) including breaking and screening chips, laying and spreading in 150mm layers uniformly and compacting etc. all complete and accepted by the E-I-C.

4.19.04.01

Khoa: Sand = 2: 1

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum 1st Class Picked Brick Chips (20mm down graded)

0.9000

m3

2940.00

2646.00

Sand (FM - 1.2)

0.4500

m3

584.00

262.80

Head Mason

0.0883

day

650.00

57.40

Mason

0.2650

day

550.00

145.75

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

0.7500

day

370.00

277.50 3726.95

Subtotal-A: Other consumables etc.

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

93.17 3820.12

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3896.52

10% Profit ( Add 10% on Subtotal-B) :

4286.17

VAT

6% of Total

IT

4% of Total

285.74 190.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4762.41

Page: 947 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 4.19.04.02

2 Cement: Sand: Khoa: = 1:6:12

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.0080

bag

430.00

863.44

1st Class Picked Brick Chips (20mm down graded)

0.8526

m3

2940.00

2506.64

Sand (FM - 1.2)

0.4263

m3

584.00

248.96

Head Mason

0.0883

day

650.00

57.40

Mason

0.2650

day

550.00

145.75

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

0.7500

day

370.00

277.50 4437.19

Subtotal-A: Other consumables etc.

( +2.50 % on Subtotal-A )

Subtotal-A1:

110.93 4548.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4639.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5102.99

VAT

6% of Total

IT

4% of Total

340.20 226.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5669.99

Page: 948 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

MSE: Construction of Mechanically Stabilized/Reinforced Earth retaining walls, viaduct access ramps, road widening and bridge abutments with pre-cast Facia panels, reinforcing element, foundation beam, caping beam including excavation for foundation, concreting the foundation with appropriate groove seating for facing elements, placement of facing elements, assembling, joining with facing elements, laying of the reinforcing elements, earth filling with granular material etc. as per design, drawing, specification and direction of Engineer-in-charge. Contractor shall submit the methodology of reinforced earth work to the Engineer-in-Charge for approval before commencing the work. Notes: i) Drainage arrangement including filter media shall be made as per approved design & drawings and calculated separately. ii) The rates for excavation and foundation concrete shall be taken from section 5 & 9 of Bridge Works. iii) The earth fill to be retained is not included in this analysis which is to be worked out and provide separately. iv) Capping beam is to be priced separately as per approved design. The rate for cement concrete shall be taken from the section 7 of bridge works.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 949 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05.01

Detailed Analysis Brief Description of Item 2 MSE_FP: Providing, hoisting and placing of pre-cast RCC Facia Panels of minimum 0.80 sqm area and 180mm thickness, made with minimum 35 MPa concrete inclusive of reinforcement, shuttering, casting in yard, curing, storing, transporting, lifting, placing in position, erection with all necessary accessories i.e., rubber pad, universal hook, anchor block, nut, washer, joint fillers, fasteners etc. complete in all respect as per approved drawing, specification and direction of Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

RCC-35SCBP: Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by the laboratory through mix design having minimum required average compressive str.............4.09.06.01

0.1800

cum

11961.63

2153.09

Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS ISO 6935-2:2006 (Grade 500)………….(4.11.01.04)

5.0000

kg

64.65

323.25

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.0400

day

370.00

14.80

H.C. of KATO Mobile Crane (upto 5 ton)

0.0600

day

4000.00

240.00 2745.64

Subtotal-A: For all necessary temporary form work, scaffolding and provision of loops/lugs for lifting of pannels and joining the reinforcing elements

( +30.00 % on Subtotal-A )

Subtotal-A1:

823.69

3569.34

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3640.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4004.79

VAT

6% of Total

IT

4% of Total

266.99 177.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4449.77

Page: 950 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.19.05.02

Reinforcing Elements: Providing, assembling, joining with facing elements and laying of reinforcing elements (metal strip/geotextile/steel etc.) in the form of grid or strip or strap or combination of metallic or synthetic or any other proprietary material as per approved drawing, specification and direction of Engineer-in-Charge. The packaging of reinforcing elements shall clearly indicate the name of the manufacturer/ supplier and brand name, date of production, expiry, if any and batch identification number along with the manufacturers test certificates.

4.19.05.02.01

MSE_MSR_GCS: With reinforcing elements of Galvanised carbon steel strips of 60mm wide and 5mm thick with minimum bearing and shear strength of 490 MPa conforming to BS EN 10025, Grade S 355 JR. The fabricated element shall be galvanized and the minimum zinc coating weight shall not be less than 1000gm/sqm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

800.00

880.00

m

Reinforcement strips 60 mm wide 5 mm thick Galvanised carbon steel strips

1.1000

m

Foreman

0.0020

day

800.00

1.60

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 893.50

Subtotal-A: Cost of accessories for joining reinforcing elements with the facia panels, overlaps, heat bonding or extension.

( +10.00 % on Subtotal-A )

Subtotal-A1:

89.35

982.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1002.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1102.76

VAT

6% of Total

IT

4% of Total

73.52 49.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1225.29

Page: 951 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05.02.02

Detailed Analysis Brief Description of Item 2 MSE_MSR_Cu: With reinforcing element of Copper Strips of 60mm wide and 5mm thick conforming to BS 2870 quality C 101 or C 102 in the 1/2H condition and shall have 0.2 percent proof stress of not less than 180 MPa.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

800.00

880.00

m

Reinforcement strips 60 mm wide 5 mm thick Copper Strips

1.1000

m

Foreman

0.0020

day

800.00

1.60

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 893.50

Subtotal-A: Cost of accessories for joining reinforcing elements with the facia panels, overlaps, heat bonding or extension.

( +10.00 % on Subtotal-A )

Subtotal-A1:

89.35

982.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1002.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1102.76

VAT

6% of Total

IT

4% of Total

73.52 49.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1225.29

Page: 952 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05.02.03

Detailed Analysis Brief Description of Item 2 MSE_MSR_Al: With reinforcing elements of Aluminium Strips of 60mm wide and 5mm thick conforming to Bs 1470 quality 5454 in H 24 condition.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Reinforcement strips 60 mm wide 5 mm thick Aluminium strips

1.1000

m

400.00

440.00

Foreman

0.0020

day

800.00

1.60

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 453.50

Subtotal-A: Cost of accessories for joining reinforcing elements with the facia panels, overlaps, heat bonding or extension.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

45.35

498.85 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

508.83

10% Profit ( Add 10% on Subtotal-B) :

559.71

VAT

6% of Total

IT

4% of Total

37.31 24.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

621.90

Page: 953 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05.02.04

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

MSE_MSR_SS: With reinforcing element of Stainless steel strips of 60mm wide and 5mm thick.

m

Quantity 5

Unit

Rate

6

7

8

Reinforcement strips 60 mm wide 5 mm thick Stainless steel strips

1.1000

m

400.00

440.00

Foreman

0.0020

day

800.00

1.60

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 453.50

Subtotal-A: Cost of accessories for joining reinforcing elements with the facia panels, overlaps, heat bonding or extension.

( +10.00 % on Subtotal-A )

Subtotal-A1:

45.35

498.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

508.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

559.71

VAT

6% of Total

IT

4% of Total

37.31 24.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

621.90

Page: 954 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05.02.05

Detailed Analysis Brief Description of Item 2 MSE_MSR_FRP: with reinforcing element of Glass reinforced polymer/ fibre reinforced polymer/ polymeric strips of 60mm wide and 5mm thick.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Reinforcement strips 60 mm wide 5 mm thick Glass reinforced polymer/ fibre reinforced polymer/ polymeric strips

1.1000

m

800.00

880.00

Foreman

0.0020

day

800.00

1.60

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 893.50

Subtotal-A: Cost of accessories for joining reinforcing elements with the facia panels, overlaps, heat bonding or extension.

( +10.00 % on Subtotal-A )

Subtotal-A1:

89.35

982.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1002.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1102.76

VAT

6% of Total

IT

4% of Total

73.52 49.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1225.29

Page: 955 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05.02.06

Detailed Analysis Brief Description of Item 2 MSE_GTR: With reinforcing elements of synthetic geogrids.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm Synthetic Geogrids as per approved design and specifications

1.1000

sqm

180.00

198.00

Foreman

0.0020

day

800.00

1.60

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40 211.50

Subtotal-A: Cost of accessories for joining reinforcing elements with the facia panels, overlaps and other protective elements for synthetic geogrids.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

21.15

232.65 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

237.30

10% Profit ( Add 10% on Subtotal-B) :

261.03

VAT

6% of Total

IT

4% of Total

17.40 11.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

290.04

Page: 956 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05.02.07

Detailed Analysis Brief Description of Item 2 MSE_HDGSR: With reinforcing elements of high yield ribbed/ deformed steel reinforcement complying with BDS ISO 6935-2: 2006 and fully hotdip Galvanized to BS EN ISO 1461: 1999 with minimum coat thickness of 85 microns or 610 gm per meter squre surface.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

kg

Foreman

0.0020

day

800.00

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0200

day

370.00

7.40

M.S. Ribbed/ Deformed Bar (Grade 500)

1.1000

kg

57.00

62.70

Hot-dip Galvanizing in accordance with BS EN ISO 1461: 1999 with minimum coat thickness of 85 microns or 610 gm per square meter

1.1000

kg

65.00

71.50

Subtotal-B: Subtotal-C:

1.60

147.70

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

150.65

10% Profit ( Add 10% on Subtotal-B) :

165.72

VAT

6% of Total

IT

4% of Total

11.05 7.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

184.13

Page: 957 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.05.03

Detailed Analysis Brief Description of Item 2 MSE_BF: Backfill with selected granular material in layers in approaches of work over metal strip/synthetic geogrid/steel which is to be retained by mechanically stabilized/ reinforced earth wall including grading, placement and compaction complete as per drawing, Technical specification and as directed by the Engineer-in-charge. The backfill material shall be clean, free draining, granular with high friction and low cohesion having particle size not more than 100mm and angle of internal friction not less than 34 degree, plasticity index shall not exceed 6 as determined by AASHTO T 90, non-corrosive, coarse grained with not 10 per cent of particles passing 75 micron sieve, free of shale or other soft, poor durability particles, any deleterious matter, chlorides, salts, acids, alkalies, mineral oil, fungus and microbes and pH shall be between 5.0 to 10.0 as determined by AASHTO T 289. The backfill material shall be compacted for AASHTO T 236 to 95 percent of the maximum density determined according to AASHTO T 99 method C or D and corrected for oversized material according to AASHTO T 99, Note 9.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Picked Brick Bats

0.6650

m3

2150.00

1429.75

Sand (FM - 1.0) Ordinary Labour

0.6650

m3

567.00

377.06

0.5000

day

370.00

185.00

H.C. of Plate Compactor (LF-72)

0.0313

day

850.00

26.61

H.C. of Water Tanker (Towed by Tractor)

0.0020

day

1500.00

3.00 2021.41

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2061.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2268.02

VAT

6% of Total

IT

4% of Total

151.20 100.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2520.02

Page: 958 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.06

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Jet Grouting: Execution of Jet grouted pile including mobilization & demobilization of Jet Grouting Machine, cost of furnishing all materials, labour and equipment necessary to complete the work, cost of trial columns, coring, testing and disposal of waste materials. Every completed jet grouted column/s shall be supported with Jet Grout Pile Data. No separate payment shall be made for drilling holes, washing/cleaning of holes, placing grout, labor, equipment, processing, mixing, hooking-up to the hole, injecting grout, hole closures, clearing up, cost of furnishing samples of grouting materials, providing assistance for sampling including verification testing, all of which shall be considered part of the Work of jet grouting.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 959 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.06.01

Detailed Analysis Brief Description of Item 2 JGC_600: Diameter of Jet grouted column = 600mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of Jet Grout Machine with power unit including High-Pressure Jet Grout Pump, Air compressor, mixing plant and other accessories and shifting at site

0.0130

Day

20000.00

260.00

Ordinary Portland Cement (CEM I, 52.5N)

3.9600

bag

455.00

1801.80

Skilled Labour

0.0270

day

450.00

12.15

Foreman

0.0130

day

800.00

10.40

Operator

0.0130

day

570.00

7.41

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0270

day

470.00

12.69

Skilled Labour

0.0130

day

450.00

5.85

Ordinary Labour

0.1330

day

370.00

49.21 2159.51

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

215.95 2375.46

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2422.97

10% Profit ( Add 10% on Subtotal-B) :

2665.27

VAT

6% of Total

IT

4% of Total

177.68 118.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

2961.41

Page: 960 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.06.02

Detailed Analysis Brief Description of Item 2 JGC_800: Diameter of Jet grouted column = 800 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of Jet Grout Machine with power unit including High-Pressure Jet Grout Pump, Air compressor, mixing plant and other accessories and shifting at site

0.0240

Day

20000.00

480.00

Ordinary Portland Cement (CEM I, 52.5N)

7.0400

bag

455.00

3203.20

Skilled Labour

0.0470

day

450.00

21.15

Foreman

0.0240

day

800.00

19.20

Operator

0.0240

day

570.00

13.68

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0470

day

470.00

22.09

Skilled Labour

0.0240

day

450.00

10.80

Ordinary Labour

0.2370

day

370.00

87.69 3857.81

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

385.78 4243.59

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4328.46

10% Profit ( Add 10% on Subtotal-B) :

4761.31

VAT

6% of Total

IT

4% of Total

317.42 211.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

5290.34

Page: 961 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.06.03

Detailed Analysis Brief Description of Item 2 JGC_1000: Diameter of Jet grouted column = 1000 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of Jet Grout Machine with power unit including High-Pressure Jet Grout Pump, Air compressor, mixing plant and other accessories and shifting at site Ordinary Portland Cement (CEM I, 52.5N)

0.0370

Day

20000.00

740.00

11.0000

bag

455.00

5005.00

Skilled Labour

0.0740

day

450.00

33.30

Foreman

0.0370

day

800.00

29.60

Operator

0.0370

day

570.00

21.09

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0740

day

470.00

34.78

Skilled Labour

0.0370

day

450.00

16.65

Ordinary Labour

0.3700

day

370.00

136.90 6017.32

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

601.73 6619.05

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6751.43

10% Profit ( Add 10% on Subtotal-B) :

7426.58

VAT

6% of Total

IT

4% of Total

495.11 330.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8251.75

Page: 962 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.06.04

Detailed Analysis Brief Description of Item 2 JGC_1200: Diameter of Jet grouted column = 1200 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges of Jet Grout Machine with power unit including High-Pressure Jet Grout Pump, Air compressor, mixing plant and other accessories and shifting at site Ordinary Portland Cement (CEM I, 52.5N)

0.0530

Day

20000.00

1060.00

15.8400

bag

455.00

7207.20

Skilled Labour

0.1070

day

450.00

48.15

Foreman

0.0530

day

800.00

42.40

Operator

0.0530

day

570.00

30.21

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1070

day

470.00

50.29

Skilled Labour

0.0530

day

450.00

23.85

Ordinary Labour

0.5330

day

370.00

197.21 8659.31

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

865.93 9525.24

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 6% of Total

IT

4% of Total

9715.75 10687.32

10% Profit ( Add 10% on Subtotal-B) :

VAT

712.49 474.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

11874.80

Page: 963 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.07

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Soil Nailing: Supply and installation of soil nail of specified diameter, spacing and length as shown in drawings including setting-up, drilling in soil or rock, galvanized re-bar, centralizers, grout injection (30 MPa Concrete) as specified in specification. Works also include supply and fix nail head and all necessary works for proper completion including UPVC pipe as casing required for soil nailing work. The constractor shall submit the Methodology for the installtion of Soil Nail to the Engineer-in-charge for prior written approval (at least 7 days) before the commencement of works. The constractor shall keep records for each soil nail installation and submit one signed copy to the Engineer not later than next working day after the soil nails have been installed. The record for each soil nail shall include soil nail reference number, date/time of commencement and completion of drilling and grouting, names of supervisor and operators, the necessary drilling and grouting details etc. Only dry type drilling equipment shall be used to minimize slope disturbance.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 964 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.07.01

Detailed Analysis Brief Description of Item 2 Diameter of Drill Hole: 100 mm, Diameter of Re-bar = 25mm (Grade 500, conforming to BDS ISO 6935-2:2006)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges for horizontal/inclined rock drilling machine (Diameter of Drill Hole = 125mm)

0.0110

day

20000.00

220.00

H.C. of Grout pump with agitator & accessories

0.0440

hour

200.00

8.80

H.C. of Generator (40 KVA)

0.0060

day

2500.00

15.00

Ordinary Portland Cement (CEM I, 52.5N)

0.1110

bag

455.00

50.51

M.S. Ribbed/ Deformed Bar (Grade 500)

4.3330

kg

57.00

246.98

Hot-dip Galvanizing in accordance with BS EN ISO 1461: 1999 with minimum coat thickness of 85 microns or 610 gm per square meter

4.3330

kg

65.00

281.65

Nails/ Nut bolts/ Screw/ Spikes

0.5560

kg

65.00

36.14

PVC Centralizers for Soil Nails

0.3330

each

50.00

16.65

Skilled Labour

0.0440

day

450.00

19.80

Foreman

0.0110

day

800.00

8.80

Operator

0.0110

day

570.00

6.27

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0220

day

470.00

10.34

Ordinary Labour

0.0670

day

370.00

24.79 945.72

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

94.57 1040.29

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1061.10

10% Profit ( Add 10% on Subtotal-B) :

1167.21

VAT

6% of Total

77.81

IT

4% of Total

51.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1296.90

Page: 965 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.19.08

Conducting pull out test for soil nail to 1.5 × Working Load or as specified by E-I-C providing all necessary resources including all torque wrenhches, jacks, gauges, reaction frame, pump, load cell, bearing plates, and other equipment required to carry out the pull-out test of the soil nails as specified in Engineer's specification. The complete jacking system including hydraulic jack, pump and pressure gauge should be calibrated as single unit before use to an accuracy of not less than 5% of the applied load.

4.19.09

Anchor Bar: Fixing anchor bars upto 28mm. dia to the founding level at rock strata as per approved design including cost, conveyance & all taxes of all materials and T&P required for the work but excluding cost of TS rod & labour charges for bending, binding, tying the grills & placing in position as per specification & direction of Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

LS

Page: 966 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 4.19.09.01

2 With G.I/MS pipe

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

nos MS Pipe (50mm dia, 2.35mm thick)

1.0000

m

407.00

407.00

50mm dia end cap

0.0667

each

74.00

4.94

50mm Dia MS Socket

0.1333

Nos.

150.00

20.00

PVC tape

0.1667

each

15.00

2.50

Construction Water

0.0042

KL

500.00

2.10

H.C. of Generator (150 KVA)

0.0042

day

5000.00

21.00

H.C. of Water Tanker (Truck Mounted)

0.0167

day

2500.00

41.75

Diesel

0.4583

liter

68.00

31.16

Foreman

0.0083

day

800.00

6.64

Re-bar Fabricator

0.0167

day

570.00

9.52

Skilled Labour

0.0250

day

450.00

11.25

Ordinary Labour

0.0500

day

370.00

18.50

Pump Operator

0.0042

day

500.00

2.10

Pump Operator Helper

0.0042

day

350.00

1.47 579.92

Subtotal-A: MS pipe Thread 40mm long including Tools & Equipment

( +7.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

43.49 623.42

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

635.89

10% Profit ( Add 10% on Subtotal-B) :

699.48

VAT

6% of Total

46.63

IT

4% of Total

31.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

777.20

Page: 967 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

4.19.10

Rock Drilling: Drilling hole of specified length and diameter (more than 150mm diameter) below foundation bed at weathered rock/rock strata in flat/slopping ground by special drilling equipment with diamond drill bit including mobilization & demobilization of drilling equipment, settingup, drilling in rock as per drawing, specification & direction of Engineerin-Charge. The constractor shall submit the Methodology for the drilling holes in rock to the Engineer-in-charge for prior written approval (at least 7 days) before the commencement of works.

4.19.10.01

RD_250: Diameter of Drill Hole: 250 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges for rock drilling machine (Diameter of Drill Hole = 250 - 300mm)

0.1250

day

46000.00

5750.00

H.C. of Generator (40 KVA)

0.0630

day

2500.00

157.50

Skilled Labour

0.2500

day

450.00

112.50

Foreman

0.1250

day

800.00

100.00

Operator

0.1250

day

570.00

71.25

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50

Ordinary Labour

0.7500

day

370.00

277.50 6586.25

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

658.63 7244.88

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7389.77

10% Profit ( Add 10% on Subtotal-B) :

8128.75

VAT

6% of Total

IT

4% of Total

541.92 361.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

9031.94

Page: 968 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 4.19.10.02

Detailed Analysis Brief Description of Item 2 RD_300: Diameter of Drill Hole: 300 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m Hire and running charges for rock drilling machine (Diameter of Drill Hole = 250 - 300mm)

0.1430

day

46000.00

6578.00

H.C. of Generator (40 KVA)

0.0710

day

2500.00

177.50

Skilled Labour

0.2860

day

450.00

128.70

Foreman

0.1430

day

800.00

114.40

Operator

0.1430

day

570.00

81.51

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2860

day

470.00

134.42

Ordinary Labour

0.8570

day

370.00

317.09 7531.62

Subtotal-A: Other consumables etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

753.16 8284.78

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8450.48

10% Profit ( Add 10% on Subtotal-B) :

9295.53

VAT

6% of Total

IT

4% of Total

619.70 413.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

10328.36

Page: 969 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Chapter - 5 : Building Works 5.01.01

Providing Layout and carry over Bench Mark (BM) at site from nearby BM pillar, demarcating property lines, existing ground level (EGL), formation ground level (FGL), highest flood level (HFL), plinth level (PL). Setting and marking all pillars, markers, pegs etc. showing and maintaining reduced levels (RLs) including locating, establishing, protecting all public utilities within the premise of work and finally all to be presented in black and white etc. all complete as per direction of the E-I-C.

sqm

Surveyor

0.0022

day

1400.00

3.08

Surveyor Helper

0.0022

day

800.00

1.76

H. C. of Level/Theodolite

0.0022

day

600.00

1.32

Ordinary Labour

0.0044

day

370.00

1.63 7.79

Subtotal-A: Construction & Protect bench-mark, test pit,toolsplants, etc

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

9.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9.53 10.49 0.70 0.47

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1.56

11.65

Page: 970 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.01

Detailed Analysis Brief Description of Item 2 Earthwork in excavation of foundation trenches, including layout, by excavating earth to the lines, grades and elevation as shown in the drawing providing center lines, local bench mark pillars, fixing bamboo spikes and marking layout with chalk powder filling baskets, carrying and disposing of all excavated materials at a safe distance designated by the E-I-C in all types of soils except rocky, gravelly, slushy or organic soil, leveling, ramming, dressing and preparing the base, etc. all complete for an initial excavation depth of 2m and an initial lead not exceeding 20m, including arranging all necessary tools and equipment at work site, etc. complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Labour

0.3000

day

370.00

111.00

Mason

0.0250

day

550.00

13.75 124.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

127.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

139.97

VAT

6% of Total

IT

4% of Total

9.33 6.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

155.52

Page: 971 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.02

Detailed Analysis Brief Description of Item 2 Sand filling in foundation trenches and inside plinth with sand (minimum FM 0.50) in 150mm layers in/c leveling, watering and consolidating each layer up to finished level etc. all complete as per direction of the E-I-C. Dry density after compaction shall not be less than 95% of MDD (STD).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum

Sand (FM - 0.5)

1.1500

m3

420.00

483.00

Ordinary Labour

0.3000

day

370.00

111.00 594.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

605.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

666.47

VAT

6% of Total

44.43

IT

4% of Total

29.62 Total:

5.02.03

Sand filling in foundation trenches and inside plinth with sand (minimum FM 0.80) in 150mm layers in/c leveling, watering and consolidating each layer up to finished level etc. all complete as per direction of the E-I-C. Dry density after compaction shall not be less than 95% of MDD (STD).

cum

Sand (FM - 0.8)

1.1500

m3

480.00

552.00

Ordinary Labour

0.3000

day

370.00

111.00 663.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

676.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

743.89

VAT

6% of Total

IT

4% of Total

49.59 33.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

740.52

826.54

Page: 972 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.04

Detailed Analysis Brief Description of Item 2 Sand filling in foundation trenches and inside plinth with sand (minimum FM 1.20) in 150mm layers in/c leveling, watering and consolidating each layer up to finished level, etc. all complete as per direction of the E-I-C. (to be used only if required by the design). Dry density after compaction shall not be less than 95% of MDD (STD).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum

Sand (FM - 1.2)

1.1500

m3

584.00

671.60

Ordinary Labour

0.3000

day

370.00

111.00 782.60

Subtotal-A:

5.02.05

Sand filling in foundation trenches and inside plinth with sand (minimum FM 2.50) in 150mm layers in/c leveling, watering and consolidating each layer up to finished level etc. all complete as per direction of the E-I-C. (to be used only required by the design). Dry density after compaction shall not be less than 95% of MDD (STD).

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

798.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

878.08

VAT

6% of Total

58.54

IT

4% of Total

39.03 Total:

975.64

cum

Sand (FM - 2.5)

1.1500

m3

1500.00

1725.00

Ordinary Labour

0.3000

day

370.00

111.00 1836.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1872.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2059.99

VAT

6% of Total

IT

4% of Total

137.33 91.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2288.88

Page: 973 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.06

Detailed Analysis Brief Description of Item 2 Earth filling inside plinth in 150mm layers with earth available within 90m of the building site, watering, leveling and consolidating each layer up to finished level, etc. all complete as per direction of the E-I-C.. Dry density after compaction shall not be less than 90% of MDD (STD).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Sardar

0.0040

day

800.00

3.20

Ordinary Labour

0.8600

day

370.00

318.20 321.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

327.83

10% Profit ( Add 10% on Subtotal-B) :

360.61

VAT

6% of Total

IT

4% of Total

24.04 16.03 Total:

5.02.07

Amount

400.68

Site improvement/earth filling in foundation trenches and plinth with specified soil in/c supplying, carrying, filling by throwing earth in 150mm layers with carted earth carried by truck or any other means to be supplied at the contractor’s own cost etc. all complete as per direction of the E-I-C. (Carried from a distance beyond 200m).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 974 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.02.07.1

2 Municipal Area.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Ordinary Labour

0.5000

day

370.00

185.00

Sardar

0.0040

day

800.00

3.20

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00

Royalty of Earth (Within Municipal Area)

1.2000

m3

50.00

60.00 288.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

293.96

10% Profit ( Add 10% on Subtotal-B) :

323.36

VAT

6% of Total

IT

4% of Total

21.56 14.37 Total:

5.02.07.2

Outside municipal area.

cum Ordinary Labour

0.5000

day

370.00

185.00

Sardar

0.0040

day

800.00

3.20

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00

Royalty of Earth (Outside Municipal Area)

1.2000

m3

35.00

42.00 270.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

275.60

10% Profit ( Add 10% on Subtotal-B) :

303.16

VAT

6% of Total

IT

4% of Total

20.21 13.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

359.29

336.85

Page: 975 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.08

Detailed Analysis Brief Description of Item 2 Manual compaction of earth in 150mm thick compacted layers by breaking clods to a maximum size of 25mm using wooden drag or ladder and compacting using concrete drop hammer (Durmus), watering or drying to obtain optimum moisture content if necessary including supplying of wooden drag, ladder, bamboo hammer, steel/concrete hammer and other requisite tools, etc. all complete as per direction of the E-I-C. 85% compaction of the maximum dry density is to be obtained by the standard compaction test (Rate is for each layer of 150mm thick)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

day

370.00

8

cum

Ordinary Labour

0.0800

29.60 29.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33.21

VAT

6% of Total

IT

4% of Total

2.21 1.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

36.90

Page: 976 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.09

Detailed Analysis Brief Description of Item 2 Mechanical compaction of earthworks in 150mm thick compacted layers by breaking clods to a maximum size of 25mm using wooden drag or ladder and compacting using mechanical equipment, watering or drying to obtain optimum moisture content watering if necessary including the equipment and other tools required to work site, etc. all complete as per direction of the E-I-C. 98% compaction of the maximum dry density is to be obtained by the standard compaction test (Rate is for each layer of 150mm thick).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Ordinary Labour

0.0250

day

370.00

9.25

H.C. of Vibratory Road Roller (8-10 ton)

0.0070

day

3000.00

21.00

Diesel

0.0300

liter

68.00

2.04

Lubricant

0.0025

liter

220.00

0.55 32.84

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

33.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

36.85

VAT

6% of Total

IT

4% of Total

2.46 1.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

40.94

Page: 977 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.10

Detailed Analysis Brief Description of Item 2 Supplying of straight and strong borrak bamboo posts of having minimum 75 mm diameter although and driving the same vertically in the ground up to required depth by any means shaping the top of the post, all complete and as directed by the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Borak Bamboo (75mm dia)

1.0000

m

38.00

38.00 38.00

Subtotal-A: Driving and carriage cost

( +33.00 % on Subtotal-A )

Subtotal-A1:

12.54 50.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

51.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

56.71

VAT

6% of Total

IT

4% of Total

3.78 2.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

63.01

Page: 978 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.11

Detailed Analysis Brief Description of Item 2 Supplying wooden ballah having an average diameter not less then 150 mm (without barks) at one third distance from large end with a minimum end diameter of 100 mm for retaining purpose and driving to a depth as per design drawing by any method including all arrangement for staging. hoisting, carrying etc. complete and as directed by the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Shal/sundari/gazari Bullah (150mm to 200mm)

1.0000

m

225.00

225.00

Skilled Labour

0.1640

day

450.00

73.80

Ordinary Labour

0.5000

day

370.00

185.00 483.80

Subtotal-A: Removing of skin, sizinf and coaltaring i/c hire charge of monkey with driving arrangement.

( +6.80 % on Subtotal-A )

Subtotal-A1:

32.90 516.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

527.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

579.74

VAT

6% of Total

38.65

IT

4% of Total

25.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

644.15

Page: 979 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.12

Detailed Analysis Brief Description of Item 2 Palisading work by Supplying bitumen drum sheet walling tied with 20 BWG G. I wire fixing the same with alredy driven borrak bamboo posts with half split borrak bamboo runners @ 450mm c/c horizontally with iron nails. G.I wire etc. all complete and as directed by the E-I-C.. (Rate is excluding the cost of bamboo post)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Borak Bamboo (75mm dia)

1.3100

m

38.00

49.78

Bitumen Drum Sheet

1.4500

m2

269.00

390.05

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

0.2200

day

370.00

81.40 588.73

Subtotal-A: Nails, gozzal and wire, local cariage, etc

( +16.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

94.20 682.93

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

696.59

10% Profit ( Add 10% on Subtotal-B) :

766.24

VAT

6% of Total

51.08

IT

4% of Total

34.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

851.38

Page: 980 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.13

Detailed Analysis Brief Description of Item 2 Supplying and fitting – fixing horizontal barcing in palisading with ½ split wooden ballah having an average diameter not less then 150 mm with a minimum end diameter of 100 mm @ 450 mm c/c including supply of iron nails, gazals etc. complete as directed approved and accepted by the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Shal/sundari/gazari Bullah (150mm to 200mm)

1.0000

m

225.00

225.00

Skilled Labour

0.0420

day

450.00

18.90

Ordinary Labour

0.0420

day

370.00

15.54 259.44

Subtotal-A: Gajals,nails and wires, etc.

( +6.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

15.57 275.01

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

280.51

10% Profit ( Add 10% on Subtotal-B) :

308.56

VAT

6% of Total

IT

4% of Total

20.57 13.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

342.84

Page: 981 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.14

Detailed Analysis Brief Description of Item 2 Shore protection work during excavation in foundation trenches up to 1.5 m depth, to protect loose soil due to damage of property by supplying Bitumen drum sheet walling tied with 20 gauge G. I wire, fixing the same with already driven bamboo posts with half split Borrak bamboo runners @450mm c/c horizontally with iron nail, G.I wire etc. all complete as plan and direction of E-I-C. (the rate is including cost of vertical posts)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen Drum Sheet

1.0000

m2

269.00

269.00

Borak Bamboo (50mm dia)

1.5000

m

30.00

45.00

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

0.2200

day

370.00

81.40

Nails/ Nut bolts/ Screw/ Spikes

0.0500

kg

65.00

3.25

GI Wire (22 BWG)

0.1000

kg

90.00

9.00 475.15

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

484.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

533.12

VAT

6% of Total

35.54

IT

4% of Total

23.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

592.35

Page: 982 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.02.15

Detailed Analysis Brief Description of Item 2 Shore protection work during excavation in foundation trenches to protect loose soil due to damage of property with bitumen drum sheet fitted with gazari post 150mm minimum dia, 0.90m c/c to be driven half of the total length of the post Drum sheet to be fitted with Garzan wooden batten 50mmx50mm size at 0.60 meter c/c supplying and fixing with 150mm dia gazari post crosses 1.80 meter c/c fixed with necessary nuts and bolts at the slope side of palisading and tied up the palisading work by GI wire No. 10 with gazari past 150mm dia and 1.8 meter c/c driven at the opposite direction up to 1.20 meter depth including supplying all necessary nails and spikes etc. complete as per direction of E-I-C. (Payment will be made for the work above ground levels.).(the rate is including cost of vertical posts)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Bitumen Drum Sheet

1.0000

m2

269.00

269.00

Shal/sundari/gazari Bullah (150mm to 200mm)

2.4700

m

225.00

555.75

Sundari/ Garzen

0.0010

m3

67580.00

67.58

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.0600

day

370.00

22.20

Nails/ Nut bolts/ Screw/ Spikes

0.3600

kg

65.00

23.40

GI Wire (22 BWG)

0.2000

kg

90.00

18.00 1000.93

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1020.95

10% Profit ( Add 10% on Subtotal-B) :

1123.04

VAT

6% of Total

IT

4% of Total

74.87 49.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

1247.83

Page: 983 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.01.01

Detailed Analysis Brief Description of Item 2 Single layer brick flat soling with 1st class or picked bricks, true to level, camber/super elevation and grade including carrying bricks, filling the interstices tightly with sand of minimum FM 0.80, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 0.8)

0.0120

m3

480.00

5.76

Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.1000

day

370.00

37.00

31.0000

each

9.00

279.00

1st Class Brick

335.51

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

342.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

376.44

VAT

6% of Total

25.10

IT

4% of Total

16.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

418.27

Page: 984 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.01.02

Detailed Analysis Brief Description of Item 2 SCBFS (FM-0.80) Providing Single Layer Solid Concrete Block Flat Soling (SCBFS) with Solid Concrete Blocks having minimum compressive strength of 20 Mpa, true to level, maintaining camber/super elevation and grade including filling the interstices tightly with sand of minimum FM 0.80, etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charg. Solid Concrete Block Size (240mmx110mmx70mm to (215mmx100mmx70mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

651.16

651.16

sqm

Solid Concrete Bricks of Size (240x110x70)mm to (215x100x70)mm

1.0000

sqm

Sand (FM - 0.8)

0.0120

m3

480.00

5.76

Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.1000

day

370.00

37.00 707.67

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

721.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

794.01

VAT

6% of Total

52.93

IT

4% of Total

35.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

882.23

Page: 985 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.02

Detailed Analysis Brief Description of Item 2 Brick on edge pavement in single layer of Herring Bone Bond with 1st class or picked bricks true to level, camber, super elevation and grade over 25mm thick sand (minimum FM 0.80) cushion including filling the interstices tightly with same type of sand, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Sand (FM - 0.8)

0.0280

m3

480.00

13.44

Mason

0.0500

day

550.00

27.50

Ordinary Labour

0.1700

day

370.00

62.90

52.0000

each

9.00

468.00

1st Class Brick

571.84

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

583.28

10% Profit ( Add 10% on Subtotal-B) :

641.60

VAT

6% of Total

IT

4% of Total

42.77 28.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

712.89

Page: 986 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.03

Detailed Analysis Brief Description of Item 2 Brick on end edging (75mm across) with 1st class/picked bricks including cutting trenches true to level & grade including removing earth, re-filling & ramming the sides properly & filling the gaps with local sand, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Sand (FM - 0.5)

0.0030

m3

420.00

Mason

0.0080

day

550.00

4.40

Ordinary Labour

0.0300

day

370.00

11.10

1st Class Brick

8.0000

each

9.00

72.00

1.26

88.76

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

90.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

99.59

VAT

6% of Total

6.64

IT

4% of Total

4.43 Total:

5.03.04

Amount

110.65

Mass concrete work in foundation or floor with Portland Composite Cement (CEM II/AM, 42.5N), sand (minimum FM 1.20) and 20mm down well graded 1st class/picked brick chips (LAA value not exceeding 38), including shuttering, mixing by concrete mixer machine, casting, laying compacting with mechanical vibrator machine and curing for the requisite period breaking bricks into chips etc. all complete as per direction of the E-I-C. Cylinder crushing strength of concrete should not be less than 10.5Mpa at 28 days of curing (suggested mix proportion 1:3:6). Additional quantity of cement to be added if required to attain the strength at the contractors own cost.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 987 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.04.01

Detailed Analysis Brief Description of Item 2 Mass concrete in foundation (1:3:6) with Portland Composite Cement (CEM II/AM, 42.5N), sand (minimum FM 1.20) and 20mm down well graded 1st class/picked brick chips.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Brick Chips (20mm down graded)

0.9000

m3

2940.00

2646.00

Sand (FM - 1.2)

0.4500

m3

584.00

262.80

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

4.2400

bag

430.00

1823.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 6114.50

Subtotal-A: Other costs (form work etc.)

( +.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

30.57 6145.07

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6267.97

10% Profit ( Add 10% on Subtotal-B) :

6894.77

VAT

6% of Total

IT

4% of Total

459.65 306.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7660.86

Page: 988 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.04.02

Detailed Analysis Brief Description of Item 2 Mass concrete in floor (1:3:6) with Portland Composite Cement (CEM II/AM, 42.5N), sand (minimum FM 1.20) and 20mm down well graded 1st class/picked brick chips..

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Brick Chips (20mm down graded)

0.9000

m3

2940.00

2646.00

Sand (FM - 1.2)

0.4500

m3

584.00

262.80

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

4.2400

bag

430.00

1823.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.7700

day

550.00

423.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 6307.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6433.14

10% Profit ( Add 10% on Subtotal-B) :

7076.45

VAT

6% of Total

IT

4% of Total

471.76 314.51 Total:

5.03.05

Amount

7862.73

Mass concrete work in foundation or floor with Portland Composite Cement (CEM II/AM, 42.5N), sand (minimum FM 1.20) and 20mm down well graded 1st class/picked brick chips (LAA value not exceeding 38), including shuttering, mixing by concrete mixer machine, casting, laying compacting with mechanical vibrator machine and curing for the requisite period breaking bricks into chips etc. all complete as per direction of the E-I-C. Cylinder crushing strength of concrete should not be less than 17Mpa at 28 days of curing (suggested mix proportion 1:2:4). Additional quantity of cement to be added if required to attain the strength at the contractors own cost.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 989 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.05.01

Detailed Analysis Brief Description of Item 2 Mass concrete in foundation (1:2:4) with Portland Composite Cement (CEM II/AM, 42.5N), sand (minimum FM 1.20) and 20mm down well graded 1st class/picked brick chips.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Brick Chips (20mm down graded)

0.8600

m3

2940.00

2528.40

Sand (FM - 1.2)

0.4300

m3

584.00

251.12

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0540

bag

430.00

2603.22

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 6765.24

Subtotal-A: Other cost (from work etc)

( +.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

33.83 6799.07

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6935.05

10% Profit ( Add 10% on Subtotal-B) :

7628.55

VAT

6% of Total

IT

4% of Total

508.57 339.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8476.17

Page: 990 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.05.02

Detailed Analysis Brief Description of Item 2 Mass concrete in floor (1:2:4) with Portland Composite Cement (CEM II/AM, 42.5N), sand (minimum FM 1.20) and 20mm down well graded 1st class/picked brick chips.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Brick Chips (20mm down graded)

0.8600

m3

2940.00

2528.40

Sand (FM - 1.2)

0.4300

m3

584.00

251.12

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0540

bag

430.00

2603.22

Head Mason

0.0800

day

650.00

52.00

Mason

0.7700

day

550.00

423.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 6957.74

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7096.89

10% Profit ( Add 10% on Subtotal-B) :

7806.58

VAT

6% of Total

IT

4% of Total

520.44 346.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

8673.98

Page: 991 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.06

Detailed Analysis Brief Description of Item 2 75mm thick lean cement concrete (1:3:6) in floor and wherever needed with Portland Composite Cement (CEM II/AM, 42.5N), best quality coarse sand (minimum FM1.2) and 20mm down well graded picked brick chips (LAA value not exceeding 38), in/c breaking bricks into chips screening, mixing by concrete mixer machine, laying, compacting, washing of sand, curing for requisite period, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Picked Brick Chips (20mm down graded)

0.0700

m3

2940.00

205.80

Sand (FM - 1.2)

0.0340

m3

584.00

19.86

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3230

bag

430.00

138.89

Head Mason

0.0070

day

650.00

4.55

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

0.1300

day

370.00

48.10

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0044

day

1200.00

5.28 460.48

Subtotal-A: Form Work

( +.04 % on Subtotal-A )

Subtotal-A1:

0.18 460.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

469.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

516.86

VAT

6% of Total

34.46

IT

4% of Total

22.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

574.29

Page: 992 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.07

Detailed Analysis Brief Description of Item 2 25mm thick Damp Proof Course (DPC) with cement concrete (1:2:4) in Portland Composite Cement (CEM II/AM, 42.5N), sand (minimum FM 1.80) and 10mm down well graded 1st class/picked brick chips (LAA value not exceeding 38), in/c casting by concrete mixture machine, compacting, curing for requisite period, coal tar/bitumen painting, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick Chips (10mm down graded)

0.0220

m3

3049.00

67.08

Sand (FM - 1.8)

0.0110

m3

970.00

10.67

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1540

bag

430.00

66.22

Head Mason

0.0200

day

650.00

13.00

Mason

0.0700

day

550.00

38.50

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.0900

day

370.00

33.30

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0015

day

1200.00

1.80 271.07

Subtotal-A: Others costs (Tar/Bitumen/Painting etc.)

( +1.00 % on Subtotal-A )

Subtotal-A1:

2.71 273.78

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

279.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

307.18

VAT

6% of Total

20.48

IT

4% of Total

13.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

341.31

Page: 993 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.08

Detailed Analysis Brief Description of Item 2 38mm thick Damp Proof Course (DPC) with cement concrete (1:1.5:3) in Portland Composite Cement (CEM II/AM, 42.5N), sand (minimum FM 1.80) and 10mm down well graded 1st class/picked brick chips (LAA value not exceeding 38), in/c casting by concrete mixture machine, compacting, curing for requisite period, coal tar/bitumen painting, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick Chips (10mm down graded)

0.0310

m3

3049.00

94.52

Sand (FM - 1.8)

0.0160

m3

970.00

15.52

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2930

bag

430.00

125.99

Head Mason

0.0200

day

650.00

13.00

Mason

0.0700

day

550.00

38.50

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.0900

day

370.00

33.30

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 363.97

Subtotal-A: Others costs

( +1.00 % on Subtotal-A )

Subtotal-A1:

3.64 367.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

374.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

412.46

VAT

6% of Total

27.50

IT

4% of Total

18.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

458.29

Page: 994 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.09

Detailed Analysis Brief Description of Item 2 Providing single layer polythene sheet (0.18mm thick) weighing one kilogram per 6.5 square meter in floor or any where in ground floor underneath the cement concrete, etc. all complete as per specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

0.18mm thick polythene sheet

1.0000

m2

12.31

12.31

Ordinary Labour

0.0100

day

370.00

3.70 16.01

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16.33

10% Profit ( Add 10% on Subtotal-B) :

17.96

VAT

6% of Total

IT

4% of Total

1.20 0.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

19.96

Page: 995 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.03.10

Detailed Analysis Brief Description of Item 2 Dismantling of existing/damaged cement concrete work in foundation or floor works on any type of works manualy or any other means without any damage in structure and sorting the dismantled materials disposal of unserviceable materials and stacking the serviceable materials properly for measurment for all floors, Cost of conveying, loading, transportation of unserviceable material accumulated during dismantling operation is included in this unit rate. The unserviceable material must be disposed at a safe place outside the site premises with minimum traffic disruption and the procuring entity will not provide any environmentally safe place for disposing the unserviceable materials.etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

day

370.00

555.00

cum

Ordinary Labour

1.5000

555.00

Subtotal-A: Cost of carriage, tools, plants & other remaining cost etc.

( +5.00 % on Subtotal-A )

Subtotal-A1:

27.75 582.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

594.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

653.85

VAT

6% of Total

IT

4% of Total

43.59 29.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

726.50

Page: 996 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.04.01

Detailed Analysis Brief Description of Item 2 Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2), filling the interstices tightly with mortar, raking out joints, cleaning and soaking bricks at least for 24 hours before use, washing of sand, curing for requisite period, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Brick

9.00

3654.00

Sand (FM - 1.2)

406.0000 0.3600

each m3

584.00

210.24

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.4000

bag

430.00

602.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 5575.24

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5686.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6255.42

VAT

6% of Total

IT

4% of Total

417.03 278.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6950.47

Page: 997 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.04.02

Detailed Analysis Brief Description of Item 2 Brick work with 1st class bricks in cement mortar (1:4) in foundation and plinth with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2), filling the interstices tightly with mortar, raking out joints, cleaning and soaking bricks at least for 24 hours before use, washing of sand, curing for requisite period, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

1st Class Brick

9.00

3654.00

Sand (FM - 1.2)

406.0000 0.3000

each m3

584.00

175.20

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.1200

bag

430.00

911.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 5849.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5966.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6563.48

VAT

6% of Total

IT

4% of Total

437.57 291.71 Total:

5.04.03

Amount

7292.75

Brick work of 1st class bricks in cement mortar (1:6) in superstructure with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) with uniform width and depth joints, true to vertical and horizontal lines, in/c raking out joints, filling interstices tightly with mortar, cleaning and soaking bricks at least for 24 hours before use, washing of sand, necessary scaffolding, curing for requisite period, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 998 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.04.03.01

2 Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum 1st Class Brick

406.0000

each

9.00

3654.00

Sand (FM - 1.2)

0.3600

m3

584.00

210.24

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.4000

bag

430.00

602.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.5200

day

370.00

562.40 5767.64

Subtotal-A: Scaffolding

( +1.50 % on Subtotal-A )

Subtotal-A1:

86.51 5854.15

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5971.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6568.36

VAT

6% of Total

IT

4% of Total

437.89 291.93 Total:

5.04.03.02

Add for each additional floor up to 5th floor

cum

Add +1.20% with Item No 5.04.03.01

5.04.03.03

Add for each additional floor from 6th floor up to 9th floor

cum

Add +1.50% with Item No 5.04.03.01

5.04.03.04

Add for each additional floor for 10th floor and above

cum

Add +2.00% with Item No 5.04.03.01

5.04.04

Brick work with 1st class bricks in cement mortar (1:4) in exterior walls with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) with uniform width and depth joints, true to vertical and horizontal lines, in/c filling the interstices tightly with mortar, racking out joints, cleaning and soaking bricks at least for 24 hours before use, washing of sand, necessary scaffolding, curing for requisite period, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

7298.18

Page: 999 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.04.04.01

2 Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Brick

406.0000

each

9.00

3654.00

Sand (FM - 1.2)

0.3000

m3

584.00

175.20

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.1200

bag

430.00

911.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.5200

day

370.00

562.40 6042.20

Subtotal-A: Scaffolding

( +1.50 % on Subtotal-A )

90.63

Subtotal-A1:

6132.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6255.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6881.04

VAT

6% of Total

IT

4% of Total

458.74 305.82 Total:

5.04.04.02

Add for each additional floor up to 5th floor

cum

Add +1.10% with Item No 5.04.04.01

5.04.04.03

Add for each additional floor from 6th floor up to 9th floor

cum

Add +1.40% with Item No 5.04.04.01

5.04.04.04

Add for each additional floor for 10th floor and above

cum

Add +1.80% with Item No 5.04.04.01

Note : Rates of all items should be inclusive of all supply and carriage.

7645.60

Page: 1000 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.04.05

Exposed brick work (for exterior wall without outside plaster) with special quality sorted out 1st class bricks, very carefully laid in cement mortar (1:4) in superstructure with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) with uniform width and depth joints, true to vertical and horizontal lines in/c racking out joints, scaffolding, soaking the bricks at least for 24 hours before use, washing of sand, curing for requisite period and high class flush pointing with cement mortar (1:1) , etc. all complete as per direction of the E-I-C.

5.04.05.01

Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Brick

9.00

3654.00

Sand (FM - 1.2)

406.0000 0.4000

each m3

584.00

233.60

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.2800

bag

430.00

980.40

Head Mason

0.0900

day

650.00

58.50

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.3100

day

370.00

484.70 6111.20

Subtotal-A: Scaffolding

( +1.50 % on Subtotal-A )

91.67

Subtotal-A1:

6202.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6326.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6959.62

VAT

6% of Total

463.97

IT

4% of Total

309.32 Total:

5.04.05.02

Add for each additional floor up to 5th floor

cum

Add +1.00% with Item No 5.04.05.01

5.04.05.03

Add for each additional floor from 6th floor up to 9th floor

cum

Add +1.16% with Item No 5.04.05.01

Note : Rates of all items should be inclusive of all supply and carriage.

7732.91

Page: 1001 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.04.05.04

Add for each additional floor for 10th floor and above

5.04.06

Brick work with 10 holes machine made bricks of approved size having uniform colour, carefully laid in cement mortar (1:4) in superstructure with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) with uniform width and depth joints, true to vertical and horizontal lines in/c raking out joints, filling the interstices with mortar, cleaning and soaking the bricks at least for 24 hours before use, washing of sand, necessary scaffolding, curing for requisite period and pointing with cement mortar (1:2), etc. all complete as per direction of the E-I-C.

5.04.06.01

Ground Floor

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Add +1.54% with Item No 5.04.05.01

cum 10 holes machine made bricks

each

18.90

7673.40

0.4000

m3

584.00

233.60

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.3000

bag

430.00

989.00

Head Mason

0.0900

day

650.00

58.50

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.3100

day

370.00

484.70

Sand (FM - 1.2)

406.0000

10139.20

Subtotal-A: Scaffolding

( +1.00 % on Subtotal-A )

101.39

Subtotal-A1: Subtotal-B: Subtotal-C:

10240.59 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10445.40

10% Profit ( Add 10% on Subtotal-B) :

11489.94

VAT

6% of Total

IT

4% of Total

766.00 510.66 Total:

5.04.06.02

Add for each additional floor up to 5th floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

12766.60

Add +.80% with Item No 5.04.06.01

Page: 1002 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.04.06.03

Add for each additional floor from 6th floor up to 9th floor

cum

Add +1.00% with Item No 5.04.06.01

5.04.06.04

Add for each additional floor for 10th floor and above

cum

Add +1.30% with Item No 5.04.06.01

5.04.07

Extra rate over the rate of Ground Floor (or any floor as the case may be) for each additional meter height of brick wall in Auditorium, Godown, Overhead water tank, etc. where free height of the structure exceeds beyond 4.00 meter up to 11 meter. The description of the item is same as in item nos. 5.04.03, 5.04.04, 5.04.05 and 5.04.06 above. (For each additional meter of extra height beyond 4.00 meter)

cum

Quantity 5

Unit

Rate

6

7

Amount 8

(For extra height the total height of the wall from the floor should be measured and then 4.00 meter to be deducted. The maximum rate thus calculated on the top height of the wall shall be admissible for the whole volume of brick work above 4.00 meter. Extra payment shall be admissible only when both sides of the wall is uninterruptedly free beyond 4.00 meter) Head Mason

0.0200

day

650.00

13.00

Mason

0.0400

day

550.00

22.00

Skilled Labour

0.0400

day

450.00

18.00

Ordinary Labour

0.0600

day

370.00

22.20 75.20

Subtotal-A: Scaffolding

( +29.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

97.01 98.95

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

108.84

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

7.26

IT

4% of Total

4.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21.81

120.94

Page: 1003 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.04.08

5.04.08.01 5.04.08.01.01

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Providing brick work in facing in super structure with 200mmx100mmx50mm machine made ceramic hard pressed bricks of approved quality in cement mortar (1:4) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2), in/c raking out joints, cutting the bricks to required size wherever necessary in/c high class recessed pointing, cleaning and soaking the bricks at least for 24 hours before use, washing of sand, necessary scaffolding, curing for requisite period, etc. all complete as per direction of the E-I-C . 200mmx100mmx50mm machine made ceramic hard pressed bricks Ground floor

sqm Ceramic Bricks (200x100x50mm)

50.0000

each

18.50

925.00

0.0300

m3

584.00

17.52

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3800

bag

430.00

163.40

Head Mason

0.0300

day

650.00

19.50

Mason

0.3200

day

550.00

176.00

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.4000

day

370.00

148.00

Sand (FM - 1.2)

1498.92

Subtotal-A: Scaffolding and other

( +1.30 % on Subtotal-A )

19.49

Subtotal-A1: Subtotal-B: Subtotal-C:

1518.41 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1548.77

10% Profit ( Add 10% on Subtotal-B) :

1703.65

VAT

6% of Total

IT

4% of Total

113.58 75.72 Total:

5.04.08.01.02

Add for each additional floor up to 5th Floor

Note : Rates of all items should be inclusive of all supply and carriage.

sqm

1892.95

Add +1.00% with Item No 5.04.08.01.01

Page: 1004 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.04.08.01.03

Add for each additional floor from 6th up to 9th Floor

sqm

Add +1.16% with Item No 5.04.08.01.01

5.04.08.01.04

Add for each additional floor for 10th Floor and above

sqm

Add +1.54% with Item No 5.04.08.01.01

5.04.08.02 5.04.08.02.01

Quantity 5

Unit

Rate

6

7

Amount 8

200mmx62mmx16.51mm machine made ceramic hard pressed bricks Ground Floor

sqm Ceramic Bricks (200x62x16.51mm)

76.0000

each

18.00

1368.00

0.0300

m3

584.00

17.52

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3800

bag

430.00

163.40

Head Mason

0.0300

day

650.00

19.50

Mason

0.3200

day

550.00

176.00

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.4000

day

370.00

148.00

Sand (FM - 1.2)

1941.92

Subtotal-A: Scaffolding and others

( +1.30 % on Subtotal-A )

25.24

Subtotal-A1: Subtotal-B: Subtotal-C:

1967.16 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2006.51

10% Profit ( Add 10% on Subtotal-B) :

2207.16

VAT

6% of Total

IT

4% of Total

147.14 98.10 Total:

5.04.08.02.02

Add for each additional floor up to 5th Floor

sqm

Add +1.00% with Item No 5.04.08.02.01

5.04.08.02.03

Add for each additional floor from 6th up to 9th Floor

sqm

Add +1.16% with Item No 5.04.08.02.01

5.04.08.02.04

Add for each additional floor for 10th Floor and above

sqm

Add +1.54% with Item No 5.04.08.02.01

Note : Rates of all items should be inclusive of all supply and carriage.

2452.40

Page: 1005 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.04.09

125mm brick work with 1st class bricks in cement mortar (1:6) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) and making bond with connected walls with uniform width and depth joints, true to vertical and horizontal lines in/c necessary scaffolding, raking out joints, cleaning and soaking the bricks at least for 24 hours before use, washing of sand, curing for requisite period, etc. all complete as per direction of the E-I-C.

5.04.09.01

Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 1st Class Brick

52.0000

each

9.00

468.00

Sand (FM - 1.2)

0.0600

m3

584.00

35.04

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1900

bag

430.00

81.70

Head Mason

0.0100

day

650.00

6.50

Mason

0.0500

day

550.00

27.50

Ordinary Labour

0.4300

day

370.00

159.10 777.84

Subtotal-A: Scaffolding

( +5.00 % on Subtotal-A )

38.89

Subtotal-A1: Subtotal-B: Subtotal-C:

816.73 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

833.07

10% Profit ( Add 10% on Subtotal-B) :

916.37

VAT

6% of Total

IT

4% of Total

61.09 40.73 Total:

5.04.09.02

Add for each additional floor up to 5th floor

sqm

Add +1.30% with Item No 5.04.09.01

5.04.09.03

Add for each additional floor from 6th floor up to 9th floor

sqm

Add +1.60% with Item No 5.04.09.01

5.04.09.04

Add for each additional floor for 10th floor and above

sqm

Add +2.30% with Item No 5.04.09.01

Note : Rates of all items should be inclusive of all supply and carriage.

1018.19

Page: 1006 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.04.10

125mm brick work with 1st class bricks in cement mortar (1:4) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) and making bond with connected walls with uniform width and depth joints, true to vertical and horizontal lines in/c necessary scaffolding, raking out joints, cleaning and soaking the bricks at least for 24 hours before use, washing of sand, curing for requisite period, etc. all complete as per direction of the E-I-C.

5.04.10.01

Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 1st Class Brick

52.0000

each

9.00

468.00

Sand (FM - 1.2)

0.0500

m3

584.00

29.20

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2800

bag

430.00

120.40

Head Mason

0.0100

day

650.00

6.50

Mason

0.0500

day

550.00

27.50

Ordinary Labour

0.4300

day

370.00

159.10 810.70

Subtotal-A: Scaffolding

( +3.00 % on Subtotal-A )

24.32

Subtotal-A1: Subtotal-B: Subtotal-C:

835.02 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

851.72

10% Profit ( Add 10% on Subtotal-B) :

936.89

VAT

6% of Total

IT

4% of Total

62.46 41.64 Total:

5.04.10.02

Add for each additional floor up to 5th floor

sqm

Add +1.30% with Item No 5.04.10.01

5.04.10.03

Add for each additional floor from 6th floor up to 9th floor

sqm

Add +1.60% with Item No 5.04.10.01

5.04.10.04

Add for each additional floor for 10th floor and above

sqm

Add +2.30% with Item No 5.04.10.01

Note : Rates of all items should be inclusive of all supply and carriage.

1040.99

Page: 1007 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.04.11

125mm thick partition wall brick work with 10 holes machine made ceramic bricks of approved size having uniform colour, carefully laid in cement mortar (1:4) in superstructure with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) with uniform width and depth joints, true to vertical and horizontal lines in/c raking out joints, filling the interstices with mortar, cleaning and soaking the bricks at least for 24 hours before use, washing of sand, necessary scaffolding, curing for requisite period and pointing with cement mortar (1:2), etc. all complete as per direction of the E-I-C.

5.04.11.01

Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 10 holes machine made bricks

52.0000

each

18.90

982.80

Sand (FM - 1.2)

0.0500

m3

584.00

29.20

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2800

bag

430.00

120.40

Head Mason

0.0100

day

650.00

6.50

Mason

0.0500

day

550.00

27.50

Ordinary Labour

0.4300

day

370.00

159.10 1325.50

Subtotal-A: Scaffolding

( +2.40 % on Subtotal-A )

31.81

Subtotal-A1:

1357.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1384.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1522.90

VAT

6% of Total

IT

4% of Total

101.53 67.68 Total:

5.04.11.02

Add for each additional floor up to 5th floor

sqm

Add +1.00% with Item No 5.04.11.01

5.04.11.03

Add for each additional floor from 6th floor up to 9th floor

sqm

Add +1.20% with Item No 5.04.11.01

5.04.11.04

Add for each additional floor for 10th floor and above

sqm

Add +1.70% with Item No 5.04.11.01

Note : Rates of all items should be inclusive of all supply and carriage.

1692.12

Page: 1008 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.04.12

Detailed Analysis Brief Description of Item 2 125mm thick Jaffrey brick work with 1st class bricks and cement sand mortar (1:4) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) in/c raking out joints, filling the interstices with mortar, cleaning and soaking the bricks at least for 24 hours before use, washing of sand, necessary scaffolding, curing for requisite period etc. all complete as per direction of the E-I-C. .

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick

30.0000

each

9.00

270.00

Sand (FM - 1.2)

0.0070

m3

584.00

4.09

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0500

bag

430.00

21.50

Mason

0.1500

day

550.00

82.50

Ordinary Labour

0.2240

day

370.00

82.88 460.97

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

470.19

10% Profit ( Add 10% on Subtotal-B) :

517.21

VAT

6% of Total

IT

4% of Total

34.48 22.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

574.67

Page: 1009 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.04.13

Detailed Analysis Brief Description of Item 2 75mm thick cornice of brick masonry in cement mortar (1:4) having minimum 12mm thick cement plaster (1:6) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2), in/c scaffolding and curing for requisite period in all floors, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Exposed brick work for ground floor (for exterior wall without outside plaster)….(5.04.05.01)

0.0060

cum

6202.87

37.22

12mm thick cement plaster (1:6) to wall for ground floor…..(5.12.02.01)

0.2400

sqm

184.48

44.27

Ordinary Labour

0.3300

day

370.00

122.10 203.59

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

207.66

10% Profit ( Add 10% on Subtotal-B) :

228.43

VAT

6% of Total

15.23

IT

4% of Total

10.15 Total:

5.04.14

Fancy screen (Ornamental Screen) work with different size machine made design blocks with uniform colour, carefully laid in coloured cement mortar (1:3) in all floors in wall with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) with uniform mortar joints, true to vertical and horizontal line including racking out joints, cleaning and soaking the blocks for minimum 24 hours before use including washing and screening of sand, scaffolding, curing for requisite period etc. complete in all respect including supply of all necessary materials including cost of water, electricity and other charges etc. all complete as per direction of the E-I-C.

5.04.14.01

Block Size :110mmx110mmx110mm (MCW-Design No.3 or equivalent volume & design)

Note : Rates of all items should be inclusive of all supply and carriage.

253.81

Page: 1010 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.04.14.01.1

2 Ground floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Fancy screen Block 110x110x110mm (MCW-Design No.3) or equivalent

83.0000

each

26.00

2158.00

Sand (FM - 1.2)

0.0120

m3

584.00

7.01

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1100

bag

430.00

47.30

Colour Pigment

0.0500

kg

120.00

6.00

Head Mason

0.1100

day

650.00

71.50

Mason

0.2400

day

550.00

132.00

Skilled Labour

0.2700

day

450.00

121.50

Ordinary Labour

0.3100

day

370.00

114.70 2658.01

Subtotal-A: Scaffolding

( +1.30 % on Subtotal-A )

34.55

Subtotal-A1:

2692.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2746.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3021.05

VAT

6% of Total

201.40

IT

4% of Total

134.27 Total:

5.04.14.01.2

Add for each additional floor up to 5th Floor

sqm

Add +1.00% with Item No 5.04.14.01.1

5.04.14.01.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +1.16% with Item No 5.04.14.01.1

5.04.14.01.4

Add for each additional floor for 10th Floor and above

sqm

Add +1.54% with Item No 5.04.14.01.1

5.04.14.02

Block Size : 140mmx140mmx100mm (MCW-Design No.1 or equivalent volume & design)

Note : Rates of all items should be inclusive of all supply and carriage.

3356.73

Page: 1011 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.04.14.02.1

2 Ground floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Fancy screen Block: 140x140x100mm (MCW-Design No.1) or equivalent

52.0000

each

32.00

1664.00

Sand (FM - 1.2)

0.0120

m3

584.00

7.01

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1100

bag

430.00

47.30

Colour Pigment

0.0500

kg

120.00

6.00

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.2200

day

450.00

99.00

Ordinary Labour

0.2600

day

370.00

96.20 2112.01

Subtotal-A: Scaffolding

( +1.30 % on Subtotal-A )

27.46

Subtotal-A1:

2139.46

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2182.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2400.48

VAT

6% of Total

160.03

IT

4% of Total

106.69 Total:

5.04.14.02.2

Add for each additional floor up to 5th Floor

sqm

Add +1.00% with Item No 5.04.14.02.1

5.04.14.02.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +1.16% with Item No 5.04.14.02.1

5.04.14.02.4

Add for each additional floor for 10th Floor and above

sqm

Add +1.54% with Item No 5.04.14.02.1

5.04.14.03

Block Size : 150mmx160mmx100mm (MCW-Design No.20/27 or equivalent volume & design)

Note : Rates of all items should be inclusive of all supply and carriage.

2667.20

Page: 1012 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.04.14.03.1

2 Ground floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Fancy screen Block: 150x160x100mm (MCW-Design No.27) or equivalent

42.0000

each

35.00

1470.00

Sand (FM - 1.2)

0.0120

m3

584.00

7.01

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1100

bag

430.00

47.30

Colour Pigment

0.0500

kg

120.00

6.00

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.2200

day

450.00

99.00

Ordinary Labour

0.2600

day

370.00

96.20 1918.01

Subtotal-A: Scaffolding

( +1.30 % on Subtotal-A )

24.93

Subtotal-A1:

1942.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1981.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2179.98

VAT

6% of Total

145.33

IT

4% of Total

96.89 Total:

5.04.14.03.2

Add for each additional floor up to 5th Floor

sqm

Add +1.00% with Item No 5.04.14.03.1

5.04.14.03.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +1.16% with Item No 5.04.14.03.1

5.04.14.03.4

Add for each additional floor for 10th Floor and above

sqm

Add +1.54% with Item No 5.04.14.03.1

Note : Rates of all items should be inclusive of all supply and carriage.

2422.20

Page: 1013 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.04.15

Exposed brick work (for exterior wall without outside plaster) with automatic machine made 1st class bricks, very carefully laid in cement mortar (1:4) in superstructure with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) with uniform width and depth joints, true to vertical and horizontal lines in/c racking out joints, scaffolding, soaking the bricks at least for 24 hours before use, washing of sand, curing for requisite period and high class flush pointing with cement mortar (1:1) , etc. all complete as per direction of the E-I-C.

5.04.15.01

Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Automatic machine made 1st class bricks

406.0000

no

9.00

3654.00

Sand (FM - 1.2)

0.4000

m3

584.00

233.60

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.2800

bag

430.00

980.40

Head Mason

0.0900

day

650.00

58.50

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.3100

day

370.00

484.70 6111.20

Subtotal-A: Scaffolding

( +1.50 % on Subtotal-A )

91.67

Subtotal-A1:

6202.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6326.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6959.62

VAT

6% of Total

463.97

IT

4% of Total

309.32 Total:

5.04.15.02

Add for each additional floor up to 5th Floor

cum

Add +1.00% with Item No 5.04.15.01

5.04.15.03

Add for each additional floor from 6th up to 9th Floor

cum

Add +1.16% with Item No 5.04.15.01

Note : Rates of all items should be inclusive of all supply and carriage.

7732.91

Page: 1014 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.04.15.04

Add for each additional floor for 10th Floor and above

cum

5.04.16

Dismantling of existing/damaged brick work in sub-structure or superstructure works of any type manualy or any other means without any damage in structure and sorting the dismantled materials disposal of unserviceable materials and stacking the serviceable materials properly for measurment for all floors, Cost of conveying, loading, transportation of unserviceable material accumulated during dismantling operation is included in this unit rate. The unserviceable material must be disposed at a safe place outside the site premises with minimum traffic disruption and the procuring entity will not provide any environmentally safe place for disposing the unserviceable materials.etc. all complete as per direction of the E-I-C.

cum

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

377.40

Add +1.54% with Item No 5.04.15.01

Ordinary Labour

1.0200

377.40

Subtotal-A: Cost of carriage, tools, plants & other remaining cost etc.

( +5.00 % on Subtotal-A )

18.87

Subtotal-A1: Subtotal-B: Subtotal-C:

396.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

404.20

10% Profit ( Add 10% on Subtotal-B) :

444.61

VAT

6% of Total

IT

4% of Total

29.64 19.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

494.02

Page: 1015 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC:1:2:4, 17MPa, Brick Chips (BC): Reinforced cement concrete works with minimum cement content relates to mix ratio (tentative 1:2:4) and maximum water cement ratio 0.45 having minimum required average strength, f'cr = 24 Mpa and satisfied a specified compressive strength f'c = 17 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and Portland Composite Cement conforming to BDS EN 197-1 : 2003 CEM-II 42.5N sand of minimum FM 1.8 and 20mm down well graded picked brick chips (LAA value and maximum water absorption not exceeding 38 and 15% respectively) conforming to ASTM C 33 or Aggregate Grading Appendix-3 LGED Schedule of Rates or any other International recognized envelop in/c breaking chips and screening through proper sieves, centering, shuttering in position, making shuttering fully leak proof & shuttering with plain 16 BWG steel sheet fitted over 38mm thick wooden plank panels and Standard size Bamboo Props suitably braced, placing of reinforcement in position, mixing the aggregates with standard mixer machine with hoper, fed by standard measuring boxes, maintaining allowable slump of 50mm (without plasticizer) & 75mm to 100mm (when plasticizer use), pouring, casting, compacting by mechanical vibrator machine and curing at least for 28 days, removing centering-shuttering after approved specified time period, i/c cost of additional testing charges of materials and cylinders required. Excluding the cost of reinforcement and its fabrication, welding, coupling, placing, binding etc. Additional quantity of cement and Plasticizer i.e. Water reducing chemical admixture of complying type A under ASTM C 494 to reduce mixing water required for normal workability and to maintain low water-cement (W/C) ratio (Doses of admixture to be fixed by the mix design from approved laboratory instruction by the Engineer) Additional quantity of cement to be added if required to attain the strength at the contractor's own cost) etc. all complete as per direction and approval of the Engineer in charge. Note : Using Concrete Mixer.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1016 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.01.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7044.86

Subtotal-A: Wooden form work & all other remaining costs

( +8.50 % on Subtotal-A )

598.81

Subtotal-A1: Subtotal-B: Subtotal-C:

7643.67 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7796.55

10% Profit ( Add 10% on Subtotal-B) :

8576.20

VAT

6% of Total

IT

4% of Total

571.75 381.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1528.80

9529.11

Page: 1017 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.01.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7044.86

Subtotal-A: Wooden form work & all other remaining costs

( +20.00 % on Subtotal-A )

Subtotal-A1:

8453.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8622.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9485.20

VAT

6% of Total

IT

4% of Total

632.35 421.56 Total:

5.05.01.03

1408.97

10539.11

In pedestal, column, capital lift wall and wall :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1018 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.01.03.1

2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7044.86

Subtotal-A: Wooden form work & all other remaining costs

( +56.00 % on Subtotal-A )

Subtotal-A1:

10989.98

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11209.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12330.76

VAT

6% of Total

IT

4% of Total

822.05 548.03 Total:

5.05.01.03.2

Add for each additional floor up to 5th Floor

cum

Add +.36% with Item No 5.05.01.03.1

5.05.01.03.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.66% with Item No 5.05.01.03.1

5.05.01.03.4

Add for each additional floor for 10th floor and above

cum

Add +.87% with Item No 5.05.01.03.1

5.05.01.04

In Tie Beam and Lintel :

Note : Rates of all items should be inclusive of all supply and carriage.

3945.12

13700.84

Page: 1019 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.01.04.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7044.86

Subtotal-A: Wooden form work & all other remaining costs

( +35.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

9510.56 9700.77

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10670.85

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

711.39 474.26 Total:

5.05.01.04.2

Add for each additional floor up to 5th Floor

cum

Add +.43% with Item No 5.05.01.04.1

5.05.01.04.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.78% with Item No 5.05.01.04.1

5.05.01.04.4

Add for each additional floor for 10th floor and above

cum

Add +1.03% with Item No 5.05.01.04.1

5.05.01.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

Note : Rates of all items should be inclusive of all supply and carriage.

2465.70

11856.50

Page: 1020 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.01.05.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7044.86

Subtotal-A: Wooden form work & all other remaining costs

( +42.00 % on Subtotal-A )

Subtotal-A1:

10003.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10203.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11224.15

VAT

6% of Total

IT

4% of Total

748.28 498.85 Total:

5.05.01.05.2

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.01.05.1

5.05.01.05.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.71% with Item No 5.05.01.05.1

5.05.01.05.4

Add for each additional floor for 10th floor and above

cum

Add +.95% with Item No 5.05.01.05.1

5.05.01.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

Note : Rates of all items should be inclusive of all supply and carriage.

2958.84

12471.28

Page: 1021 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.01.06.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7044.86

Subtotal-A: Wooden form work & all other remaining costs

( +40.00 % on Subtotal-A )

Subtotal-A1:

9862.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10060.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11066.07

VAT

6% of Total

IT

4% of Total

737.74 491.83 Total:

5.05.01.06.2

Add for each additional floor up to 5th Floor

cum

Add +.41% with Item No 5.05.01.06.1

5.05.01.06.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.74% with Item No 5.05.01.06.1

5.05.01.06.4

Add for each additional floor for 10th floor and above

cum

Add +.99% with Item No 5.05.01.06.1

5.05.01.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick)

Note : Rates of all items should be inclusive of all supply and carriage.

2817.94

12295.63

Page: 1022 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.01.07.1

2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7020.86

Subtotal-A: Wooden Form work & all other remaining costs

( +85.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12988.59 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13248.36

10% Profit ( Add 10% on Subtotal-B) :

14573.20

VAT

6% of Total

IT

4% of Total

971.55 647.70 Total:

5.05.01.07.2

Add for each additional floor up to 5th Floor

cum

Add +.98% with Item No 5.05.01.07.1

5.05.01.07.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +1.80% with Item No 5.05.01.07.1

5.05.01.07.4

Add for each additional floor for 10th floor and above

cum

Add +2.46% with Item No 5.05.01.07.1

5.05.01.08

In Stair case slab and step

Note : Rates of all items should be inclusive of all supply and carriage.

5967.73

16192.44

Page: 1023 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.01.08.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7044.86

Subtotal-A: Wooden form work & all other remaining costs

( +43.00 % on Subtotal-A )

Subtotal-A1:

10074.15

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10275.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11303.20

VAT

6% of Total

IT

4% of Total

753.55 502.36 Total:

5.05.01.08.2

Add for each additional floor up to 5th Floor

cum

Add +.42% with Item No 5.05.01.08.1

5.05.01.08.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.75% with Item No 5.05.01.08.1

5.05.01.08.4

Add for each additional floor for 10th floor and above

cum

Add +1.00% with Item No 5.05.01.08.1

5.05.01.09

In Waffle or Ribbed floor/roof slab

Note : Rates of all items should be inclusive of all supply and carriage.

3029.29

12559.11

Page: 1024 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.01.09.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 7044.86

Subtotal-A: Wooden form work & all other remaining costs

( +120.00 % on Subtotal-A )

Subtotal-A1:

15498.69

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15808.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17389.53

VAT

6% of Total

IT

4% of Total

1159.30 772.87 Total:

5.05.01.09.2

Add for each additional floor up to 5th Floor

cum

Add +.27% with Item No 5.05.01.09.1

5.05.01.09.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.48% with Item No 5.05.01.09.1

5.05.01.09.4

Add for each additional floor for 10th floor and above

cum

Add +.63% with Item No 5.05.01.09.1

Note : Rates of all items should be inclusive of all supply and carriage.

8453.83

19321.70

Page: 1025 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC:1:2:4, 20MPa, Stone Chips (SC): Reinforced cement concrete works with minimum cement content relates to mix ratio (tentative 1:2:4) and maximum water cement ratio 0.40 having minimum required average strength, f'cr = 26 Mpa and satisfying a specified compressive strength f'c = 20 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and Portland Composite Cement conforming to BDS EN 197-1 : 2003 CEM-II 42.5N, best quality sand of minimum FM 2.2, 20mm down well graded crushed stone chips (Preferably stone chips from Madhyapara, Dinajpur) (LAA value not exceeding 35) conforming to ASTM C 33 or Aggregate Grading Appendix-3 LGED Schedule of Rates or any other International recognized envelop and Water reducing chemical admixture of complying type A under ASTM C 494, in/c cost of breaking chips, screening through proper sieves, cleaning and washing thoroughly, centering, shuttering in position, with plain 16 BWG steel sheet fitted over 38mm thick wooden plank panels suitably braced and Standard size Bamboo Props making shuttering fully leak proof, placing of reinforcement cage in position, mixing the aggregates with standard mixer machine with hoper, fed by standard measuring boxes, maintaining allowable slump of 75mm to 100mm casting in steel forms, compacting by Mechanical vibrators and tapered rods and curing at least for 28 days, removing centering-shuttering after approved specified time period, i/c cost of additional testing charges of materials and cylinders required. Excluding the cost of reinforcement and its fabrication, welding, coupling, placing, binding etc. additional quantity of Plasticizer i.e. Water reducing chemical admixture of complying type A under ASTM C 494 to reduce mixing water required for normal workability and to maintain low water-cement (W/C) ratio (Doses of admixture to be fixed by the mix design from approved laboratory instruction by the Engineer) Additional quantity of cement to be added if required to attain the strength at the contractor's own cost etc. all complete as per direction and approval of the Engineer in charge. Note : Using Concrete Mixer.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1026 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.02.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80 8805.84

Subtotal-A: Wooden form work & all other remaining costs

( +7.00 % on Subtotal-A )

616.41

Subtotal-A1: Subtotal-B: Subtotal-C:

9422.25 9610.69

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10571.76

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

704.78

IT

4% of Total

469.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2563.60

11746.40

Page: 1027 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.02.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80 8805.84

Subtotal-A: Wooden form work & all other remaining costs

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

10390.89 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10598.71

10% Profit ( Add 10% on Subtotal-B) :

11658.58

VAT

6% of Total

IT

4% of Total

777.24 518.16 Total:

5.05.02.03

1585.05

12953.98

In pedestal, column, capital lift wall and wall :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1028 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.02.03.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80 8805.84

Subtotal-A: Wooden form work & all other remaining costs

( +54.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

13560.99 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13832.21

10% Profit ( Add 10% on Subtotal-B) :

15215.43

VAT

6% of Total

IT

4% of Total

1014.36 676.24 Total:

5.05.02.03.2

Add for each additional floor up to 5th Floor

cum

Add +.35% with Item No 5.05.02.03.1

5.05.02.03.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.63% with Item No 5.05.02.03.1

5.05.02.03.4

Add for each additional floor for 10th floor and above

cum

Add +.85% with Item No 5.05.02.03.1

Note : Rates of all items should be inclusive of all supply and carriage.

4755.15

16906.04

Page: 1029 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

5.05.02.04

In Tie Beam and Lintel :

5.05.02.04.1

Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80 8805.84

Subtotal-A: Form work & all other remaining costs

( +30.00 % on Subtotal-A )

Subtotal-A1:

2641.75 11447.59

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11676.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12844.20

VAT

6% of Total

IT

4% of Total

856.28 570.85 Total:

5.05.02.04.2

Add for each additional floor up to 5th Floor

cum

Add +.41% with Item No 5.05.02.04.1

5.05.02.04.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.75% with Item No 5.05.02.04.1

Note : Rates of all items should be inclusive of all supply and carriage.

2563.60

14271.33

Page: 1030 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.05.02.04.4

Add for each additional floor for 10th floor and above

5.05.02.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

5.05.02.05.1

Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Add +1.00% with Item No 5.05.02.04.1

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Stone Chips (12mm down graded) [LAA≤35]

0.4300

cum

4320.00

1857.60 9194.64

Subtotal-A: Wooden form work & all other remaining costs

( +28.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11769.14 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12004.52

10% Profit ( Add 10% on Subtotal-B) :

13204.97

VAT

6% of Total

IT

4% of Total

880.33 586.89 Total:

5.05.02.05.2

Add for each additional floor up to 5th Floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2574.50

14672.19

Add +.39% with Item No 5.05.02.05.1 Page: 1031 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.02.05.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.69% with Item No 5.05.02.05.1

5.05.02.05.4

Add for each additional floor for 10th floor and above

cum

Add +.92% with Item No 5.05.02.05.1

5.05.02.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

5.05.02.06.1

Below Plinth Level and in Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80 8805.84

Subtotal-A: Wooden form work & all other remaining costs

( +33.00 % on Subtotal-A )

Subtotal-A1:

2905.93 11711.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11946.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13140.60

VAT

6% of Total

IT

4% of Total

876.04 584.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2563.60

14600.67

Page: 1032 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.02.06.2

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.02.06.1

5.05.02.06.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.72% with Item No 5.05.02.06.1

5.05.02.06.4

Add for each additional floor for 10th floor and above

cum

Add +.96% with Item No 5.05.02.06.1

5.05.02.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick)

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1033 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.02.07.1

2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80 8781.84

Subtotal-A: Wooden form work & all other remaining costs

( +82.00 % on Subtotal-A )

Subtotal-A1:

15982.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16302.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17932.87

VAT

6% of Total

1195.52

IT

4% of Total

797.02 Total:

5.05.02.07.2

Add for each additional floor up to 5th Floor

cum

Add +.95% with Item No 5.05.02.07.1

5.05.02.07.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +1.75% with Item No 5.05.02.07.1

5.05.02.07.4

Add for each additional floor for 10th floor and above

cum

Add +2.38% with Item No 5.05.02.07.1

5.05.02.08

In Stair case slab and step

Note : Rates of all items should be inclusive of all supply and carriage.

7201.11

19925.41

Page: 1034 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.02.08.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80 8805.84

Subtotal-A: Wooden form work & all other remaining costs

( +38.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12152.06 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12395.10

10% Profit ( Add 10% on Subtotal-B) :

13634.61

VAT

6% of Total

IT

4% of Total

908.97 605.98 Total:

5.05.02.08.2

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.02.08.1

5.05.02.08.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.72% with Item No 5.05.02.08.1

5.05.02.08.4

Add for each additional floor for 10th floor and above

cum

Add +.96% with Item No 5.05.02.08.1

Note : Rates of all items should be inclusive of all supply and carriage.

3346.22

15149.57

Page: 1035 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.05.02.09

In Waffle or Ribbed floor/roof slab

5.05.02.09.1

Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80 8805.84

Subtotal-A: Wooden form work & all other remaining costs

( +110.00 % on Subtotal-A )

Subtotal-A1:

9686.42 18492.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18862.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20748.32

VAT

6% of Total

IT

4% of Total

1383.22 922.15 Total:

5.05.02.09.2

Add for each additional floor up to 5th Floor

cum

Add +.26% with Item No 5.05.02.09.1

5.05.02.09.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.46% with Item No 5.05.02.09.1

Note : Rates of all items should be inclusive of all supply and carriage.

2563.60

23053.69

Page: 1036 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.05.02.09.4

Add for each additional floor for 10th floor and above

5.05.03

RCC:1:1.5:3, 20MPa, Brick Chips (BC): Reinforced cement concrete works with minimum cement content relates to mix ratio (tentative 1:1.5:3) and maximum water cement ratio 0.40 having minimum required average strength, f'cr = 26 Mpa and satisfying a specified compressive strength f'c = 20 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and Portland Composite Cement conforming to BDS EN 197-1 : 2003 CEM-II 42.5N, sand of minimum FM 2.20, 20mm down well graded picked brick chips (LAA value and maximum water absorption not exceeding 38 and 15% respectively) conforming to ASTM C 33 or Aggregate Grading Appendix3 LGED Schedule of Rates or any other International recognized envelop and Water reducing chemical admixture of complying type A under ASTM C 494, in/c breaking chips and screening through proper sieves, centering, shuttering in position, making shuttering fully leak proof & shuttering with plain 16 BWG steel sheet fitted over 38mm thick wooden plank panels and Standard size Bamboo Props suitably braced, placing of reinforcement in position, mixing the aggregates with standard mixer machine with hoper, fed by standard measuring boxes, maintaining allowable slump of 75mm to 100mm, pouring, casting, compacting by mechanical vibrator machine's and tampered rod and curing at least for 28 days, removing centering-shuttering after approved specified time period, i/c cost of additional testing charges of materials and cylinders required. Excluding the cost of reinforcement and its fabrication, welding, coupling, placing, binding etc. additional quantity of Plasticizer i.e. Water reducing chemical admixture of complying type A under ASTM C 494 to reduce mixing water required for normal workability and to maintain low water-cement (W/C) ratio (Doses of admixture to be fixed by the mix design from approved laboratory instruction by the Engineer) and additional quantity of Portland Composite Cement to be added if required to attain the strength at the contractor's own cost. Etc. all complete as per direction and approval of the Engineer in charge. Note : Using Concrete Mixer.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Add +.62% with Item No 5.05.02.09.1

Page: 1037 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.03.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8048.40

Subtotal-A: Wooden form work & all other remaining costs

( +8.00 % on Subtotal-A )

643.87

Subtotal-A1:

8692.27

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8866.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9752.73

VAT

6% of Total

650.18

IT

4% of Total

433.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1528.80

10836.37

Page: 1038 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.03.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8048.40

Subtotal-A: Wooden form work & all other remaining costs

( +19.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

9577.60 9769.15

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10746.06

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

716.40 477.60 Total:

5.05.03.03

1529.20

11940.07

In pedestal, column, capital lift wall and wall :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1039 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.03.03.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floo

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8048.40

Subtotal-A: Wooden form work & all other remaining costs

( +55.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12475.02 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12724.52

10% Profit ( Add 10% on Subtotal-B) :

13996.97

VAT

6% of Total

IT

4% of Total

933.13 622.09 Total:

5.05.03.03.2

Add for each additional floor upto 5th floor

cum

Add +.36% with Item No 5.05.03.03.1

5.05.03.03.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.65% with Item No 5.05.03.03.1

5.05.03.03.4

Add for each additional floor for 10th floor and above.

cum

Add +.86% with Item No 5.05.03.03.1

Note : Rates of all items should be inclusive of all supply and carriage.

4426.62

15552.19

Page: 1040 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

5.05.03.04

In Tie Beam and Lintel :

5.05.03.04.1

Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8048.40

Subtotal-A: Wooden form work & all other remaining costs

( +33.00 % on Subtotal-A )

Subtotal-A1:

2655.97 10704.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10918.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12010.31

VAT

6% of Total

IT

4% of Total

800.69 533.79 Total:

5.05.03.04.2

Add for each additional floor upto 5th floor

cum

Add +.42% with Item No 5.05.03.04.1

5.05.03.04.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.76% with Item No 5.05.03.04.1

Note : Rates of all items should be inclusive of all supply and carriage.

1528.80

13344.78

Page: 1041 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.05.03.04.4

Add for each additional floor for 10th floor and above.

5.05.03.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

5.05.03.05.1

Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Add +1.01% with Item No 5.05.03.04.1

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8048.40

Subtotal-A: Wooden form work & all other remaining costs

( +41.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11348.24 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11575.21

10% Profit ( Add 10% on Subtotal-B) :

12732.73

VAT

6% of Total

IT

4% of Total

848.85 565.90 Total:

5.05.03.05.2

Add for each additional floor upto 5th floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

3299.84

14147.48

Add +.38% with Item No 5.05.03.05.1 Page: 1042 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.03.05.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.70% with Item No 5.05.03.05.1

5.05.03.05.4

Add for each additional floor for 10th floor and above.

cum

Add +.93% with Item No 5.05.03.05.1

5.05.03.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

5.05.03.06.1

Below Plinth Level and in Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8048.40

Subtotal-A: Wooden form work & all other remaining costs

( +38.00 % on Subtotal-A )

Subtotal-A1:

3058.39 11106.79

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11328.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12461.82

VAT

6% of Total

IT

4% of Total

830.79 553.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1528.80

13846.47

Page: 1043 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.03.06.2

Add for each additional floor upto 5th floor

cum

Add +.41% with Item No 5.05.03.06.1

5.05.03.06.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.73% with Item No 5.05.03.06.1

5.05.03.06.4

Add for each additional floor for 10th floor and above.

cum

Add +.97% with Item No 5.05.03.06.1

5.05.03.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick)

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1044 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.03.07.1

2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8024.40

Subtotal-A: Wooden form work & all other remaining costs

( +83.00 % on Subtotal-A )

Subtotal-A1:

14684.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14978.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16476.18

VAT

6% of Total

1098.41

IT

4% of Total

732.27 Total:

5.05.03.07.2

Add for each additional floor upto 5th floor

cum

Add +.97% with Item No 5.05.03.07.1

5.05.03.07.3

Add for each additional floor from 6th floor upto 9th

cum

Add +1.78% with Item No 5.05.03.07.1

5.05.03.07.4

Add for each additional floor for 10th floor and above.

cum

Add +2.42% with Item No 5.05.03.07.1

5.05.03.08

In Stair case slab and step

Note : Rates of all items should be inclusive of all supply and carriage.

6660.25

18306.87

Page: 1045 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.03.08.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

1528.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8048.40

Subtotal-A: Wooden form work & all other remaining costs

( +40.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11267.76 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11493.12

10% Profit ( Add 10% on Subtotal-B) :

12642.43

VAT

6% of Total

IT

4% of Total

842.83 561.89 Total:

5.05.03.08.2

Add for each additional floor upto 5th floor

cum

Add +.42% with Item No 5.05.03.08.1

5.05.03.08.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.75% with Item No 5.05.03.08.1

5.05.03.08.4

Add for each additional floor for 10th floor and above.

cum

Add +.98% with Item No 5.05.03.08.1

Note : Rates of all items should be inclusive of all supply and carriage.

3219.36

14047.14

Page: 1046 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.05.03.09

In Waffle or Ribbed floor/roof slab

5.05.03.09.1

Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum 1st Class Picked Brick Chips (20mm down graded)

0.5200

m3

2940.00

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

1st Class Brick Chips (10mm down graded)

0.3400

m3

3049.00

1036.66 8048.40

Subtotal-A: Wooden form work & all other remaining costs

( +115.00 % on Subtotal-A )

Subtotal-A1:

9255.66 17304.06

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17650.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19415.16

VAT

6% of Total

IT

4% of Total

1294.34 862.90 Total:

5.05.03.09.2

Add for each additional floor upto 5th floor

cum

Add +.27% with Item No 5.05.03.09.1

5.05.03.09.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.47% with Item No 5.05.03.09.1

Note : Rates of all items should be inclusive of all supply and carriage.

1528.80

21572.39

Page: 1047 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.03.09.4

Detailed Analysis Brief Description of Item 2 Add for each additional floor for 10th floor and above.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Add +.63% with Item No 5.05.03.09.1

Page: 1048 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC: Mix Design 20MPa, Stone Chips (SC):, Batching Plant (BP): Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by specified Laboratory through mix design having minimum required average compressive strength, f'cr = 26 Mpa and satisfying a specified compressive strength, f'c = 20 Mpa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and Portland Composite Cement conforming to BDS EN 197-1 : 2003 CEM-II 42.5N, high range water reducing chemical admixture of complying type F under ASTM C494 which is required to produce concrete of consistency by 12% or greater (flowing concrete) and for higher strength and intend to retard setting time of concrete. (Doses of admixture to be fixed by the mix design from approved laboratory instruction by the Engineer) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.20 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur) (LAA value not exceeding 35) conforming to ASTM C33 or Aggregate Grading Appendix-3 LGED Schedule of Rates or any other International recognized envelop, in/c cost of breaking chips, screening through proper sieves, cleaning and washing thoroughly, centering, shuttering in position, making shuttering fully leak proof & shuttering with plain 16 BWG steel sheet fitted over 38mm thick wooden plank panels and Standard size Bamboo Props suitably braced, placing of reinforcement in position, mixing in mechanized a batching and mixing plant and pumping using line pump or boom placer, maintaining allowable slump of 100mm to 150mm casting in steel forms, compacting by Mechanical vibrators and tapered rods and curing at least for 28 days, removing centering-shuttering after approved specified time period i/c cost of additional testing charges of materials and cylinders required etc all complete as per direction of the Engineer in charge. (Excluding the cost of reinforcements and its fabrication welding, coupling, placing, binding etc. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost) etc. all complete as per direction and approval of the Engineer The Mix Design shall have to be approved by the District Quality Control Laboratory, LGED or approved laboratory instruction by the Engineer before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1049 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8876.61

Subtotal-A: Wooden form work & all other remaining costs

( +8.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

710.13 9586.74

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) : 10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9778.47 10756.32 717.09 478.06 Page: 1050 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11951.47

Page: 1051 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.04.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8876.61

Subtotal-A: Wooden form work & all other remaining costs

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

1597.79 10474.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10683.89

10% Profit ( Add 10% on Subtotal-B) :

11752.28

VAT

6% of Total

IT

4% of Total

783.49 522.32 Page: 1052 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.04.03

13058.09

In pedestal, column, capital lift wall and wall :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1053 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04.03.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8876.61

Subtotal-A: Wooden form work & all other remaining costs

( +54.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

4793.37 13669.98

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13943.38

10% Profit ( Add 10% on Subtotal-B) :

15337.72

VAT

6% of Total

IT

4% of Total

1022.51 681.68 Page: 1054 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.04.03.2

Add for each additional floor upto 5th floor

cum

Add +.35% with Item No 5.05.04.03.1

5.05.04.03.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.63% with Item No 5.05.04.03.1

5.05.04.03.4

Add for each additional floor for 10th floor and above.

cum

Add +.85% with Item No 5.05.04.03.1

5.05.04.04

In Tie Beam and Lintel :

Note : Rates of all items should be inclusive of all supply and carriage.

17041.91

Page: 1055 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04.04.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8876.61

Subtotal-A: Wooden form work & all other remaining costs

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

2662.98 11539.59

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11770.38

10% Profit ( Add 10% on Subtotal-B) :

12947.42

VAT

6% of Total

IT

4% of Total

863.16 575.44 Page: 1056 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.04.04.2

Add for each additional floor upto 5th floor

cum

Add +.41% with Item No 5.05.04.04.1

5.05.04.04.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.75% with Item No 5.05.04.04.1

5.05.04.04.4

Add for each additional floor for 10th floor and above.

cum

Add +1.00% with Item No 5.05.04.04.1

5.05.04.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

Note : Rates of all items should be inclusive of all supply and carriage.

14386.03

Page: 1057 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04.05.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8876.61

Subtotal-A: Wooden form work & all other remaining costs

( +38.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

3373.11 12249.72

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12494.72

10% Profit ( Add 10% on Subtotal-B) :

13744.19

VAT

6% of Total

IT

4% of Total

916.28 610.85 Page: 1058 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.04.05.2

Add for each additional floor upto 5th floor

cum

Add +.38% with Item No 5.05.04.05.1

5.05.04.05.4

Add for each additional floor from 6th floor upto 9th

cum

Add +.69% with Item No 5.05.04.05.1

5.05.04.05.5

Add for each additional floor for 10th floor and above.

cum

Add +.92% with Item No 5.05.04.05.1

5.05.04.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

Note : Rates of all items should be inclusive of all supply and carriage.

15271.32

Page: 1059 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04.06.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8876.61

Subtotal-A: Wooden form work & all other remaining costs

( +33.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

2929.28 11805.89

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12042.01

10% Profit ( Add 10% on Subtotal-B) :

13246.21

VAT

6% of Total

IT

4% of Total

883.08 588.72 Page: 1060 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.04.06.2

Add for each additional floor upto 5th floor

cum

Add +.40% with Item No 5.05.04.06.1

5.05.04.06.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.72% with Item No 5.05.04.06.1

5.05.04.06.4

Add for each additional floor for 10th floor and above.

cum

Add +.96% with Item No 5.05.04.06.1

5.05.04.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick)

Note : Rates of all items should be inclusive of all supply and carriage.

14718.01

Page: 1061 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04.07.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8852.61

Subtotal-A: Wooden form work & all other remaining costs

( +85.00 % on Subtotal-A )

Subtotal-A1:

16377.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16704.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18375.36

VAT

6% of Total

IT

4% of Total

1225.02 816.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7524.72

20417.07

Page: 1062 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.05.04.07.2

Add for each additional floor upto 5th floor

cum

Add +.95% with Item No 5.05.04.07.1

5.05.04.07.3

Add for each additional floor from 6th floor upto 9th

cum

Add +1.75% with Item No 5.05.04.07.1

5.05.04.07.4

Add for each additional floor for 10th floor and above.

cum

Add +2.40% with Item No 5.05.04.07.1

5.05.04.08

In Stair case slab and step

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1063 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04.08.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8876.61

Subtotal-A: Wooden form work & all other remaining costs

( +40.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

3550.64 12427.25

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12675.80

10% Profit ( Add 10% on Subtotal-B) :

13943.38

VAT

6% of Total

IT

4% of Total

929.56 619.71 Page: 1064 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.04.08.2

Add for each additional floor upto 5th floor

cum

Add +.40% with Item No 5.05.04.08.1

5.05.04.08.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.72% with Item No 5.05.04.08.1

5.05.04.08.4

Add for each additional floor for 10th floor and above.

cum

Add +.96% with Item No 5.05.04.08.1

5.05.04.09

In Waffle or Ribbed floor/roof slab

Note : Rates of all items should be inclusive of all supply and carriage.

15492.64

Page: 1065 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.04.09.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0600

bag

430.00

2605.80

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84

Stone Chips (12mm down graded) [LAA≤35]

0.3400

cum

4320.00

1468.80

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 8876.61

Subtotal-A: Form work & all other remaining costs

( +112.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

9941.80 18818.41

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19194.78

10% Profit ( Add 10% on Subtotal-B) :

21114.26

VAT

6% of Total

IT

4% of Total

1407.62 938.41 Page: 1066 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.04.09.2

Add for each additional floor upto 5th floor

cum

Add +.26% with Item No 5.05.04.09.1

5.05.04.09.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.46% with Item No 5.05.04.09.1

5.05.04.09.4

Add for each additional floor for 10th floor and above.

cum

Add +.62% with Item No 5.05.04.09.1

Note : Rates of all items should be inclusive of all supply and carriage.

23460.29

Page: 1067 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.05

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC:1:1.5:3, 25MPa, Stone Chips (SC): Reinforced cement concrete works with minimum cement content relates to mix ratio (tentative 1:1.5:3) and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 33.5 Mpa and satisfying a specified compressive strength f'c = 25 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and Portland Composite Cement conforming to BDS EN 197-1 : 2003 CEM-II 42.5N, best quality sand of minimum FM 2.50, 20mm down well graded crushed stone chips broken from boulder (Preferably stone chips from Madhyapara, Dinajpur) (LAA value not exceeding 30) conforming to ASTM C33 or Aggregate Grading Appendix-3 LGED Schedule of Rates or any other International recognized envelop, Water reducing chemical admixture of complying type A under ASTM C 494, in/c cost of breaking chips, screening through proper sieves, cleaning and washing thoroughly, centering, shuttering in position, with fully leak proof & shuttering with plain 16 BWG steel sheet fitted over 38mmx38mmx5mm MS angle and 25mmx5mm FI bar frame and 38mm/50mm steel or GI pipe props suitably braced and 12 BWG steel sheet plate box of proper size where required, i/c cost of nuts, bolts, J-hooks etc, placing of reinforcement in position, mixing in standard mixer machine with hoper or mixing in mechanized batching and mixing plant and pumping using line pump or boom placer as per approved mix design unless otherwise approved by the Engineer, fed by standard measuring boxes, maintaining allowable slump of 75mm to 100mm, casting in steel forms, compacting by Mechanical vibrators and tapered rods and curing at least for 28 days, removing centering-shuttering after approved specified time period, i/c cost of additional testing charges of materials and cylinders required. Excluding the cost of reinforcement and its fabrication, welding, coupling, placing, binding etc. Water reducing chemical admixture of complying type A under ASTM C 494 to reduce mixing water required for normal workability and to maintain low water-cement (W/C) ratio (Doses of admixture to be fixed by the mix design from approved laboratory instruction by the Engineer) Additional quantity of cement to be added if required to attain the strength at the contractor's own cost) etc. all complete as per direction and approval of the Engineer in charge. Note : Using Concrete Mixer.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1068 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.05.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9421.71

Subtotal-A: Steel form work & all other remaining costs

( +6.00 % on Subtotal-A )

565.30

Subtotal-A1: Subtotal-B: Subtotal-C:

9987.01 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10186.75

10% Profit ( Add 10% on Subtotal-B) :

11205.43

VAT

6% of Total

IT

4% of Total

747.03 498.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2606.80

12450.48

Page: 1069 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.05.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9421.71

Subtotal-A: Steel form work & all other remaining costs

( +14.00 % on Subtotal-A )

Subtotal-A1:

10740.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10955.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12051.12

VAT

6% of Total

803.41

IT

4% of Total

535.61 Total:

5.05.05.03

1319.04

13390.13

In pedestal, column, capital lift wall and wall :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1070 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.05.03.1

2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9421.71

Subtotal-A: Steel form work & all other remaining costs

( +50.00 % on Subtotal-A )

Subtotal-A1:

14132.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14415.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15856.74

VAT

6% of Total

1057.12

IT

4% of Total

704.74 Total:

5.05.05.03.2

Add for each additional floor up to 5th Floor

cum

Add +.35% with Item No 5.05.05.03.1

5.05.05.03.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.63% with Item No 5.05.05.03.1

5.05.05.03.4

Add for each additional floor for 10th floor and above

cum

Add +.85% with Item No 5.05.05.03.1

5.05.05.04

In Tie Beam and Lintel :

Note : Rates of all items should be inclusive of all supply and carriage.

4710.86

17618.60

Page: 1071 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.05.04.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9421.71

Subtotal-A: Steel form work & all other remaining costs

( +32.00 % on Subtotal-A )

Subtotal-A1:

12436.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12685.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13953.93

VAT

6% of Total

930.26

IT

4% of Total

620.17 Total:

5.05.05.04.2

Add for each additional floor upto 5th floor

cum

Add +.41% with Item No 5.05.05.04.1

5.05.05.04.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.75% with Item No 5.05.05.04.1

5.05.05.04.4

Add for each additional floor for 10th floor and above.

cum

Add +1.00% with Item No 5.05.05.04.1

Note : Rates of all items should be inclusive of all supply and carriage.

3014.95

15504.37

Page: 1072 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.05.05.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

5.05.05.05.1

Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9421.71

Subtotal-A: Steel form work & all other remaining costs

( +35.00 % on Subtotal-A )

Subtotal-A1:

12719.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12973.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14271.06

VAT

6% of Total

IT

4% of Total

951.40 634.27 Total:

5.05.05.05.2

Add for each additional floor upto 5th floor

cum

Add +.38% with Item No 5.05.05.05.1

5.05.05.05.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.69% with Item No 5.05.05.05.1

Note : Rates of all items should be inclusive of all supply and carriage.

3297.60

15856.74

Page: 1073 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.05.05.05.4

Add for each additional floor for 10th floor and above.

5.05.05.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

5.05.05.06.1

Ground Floor

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Add +.92% with Item No 5.05.05.05.1

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9421.71

Subtotal-A: Steel form work & all other remaining costs

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12248.22 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12493.19

10% Profit ( Add 10% on Subtotal-B) :

13742.51

VAT

6% of Total

IT

4% of Total

916.17 610.78 Total:

5.05.05.06.2

Add for each additional floor upto 5th floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2826.51

15269.45

Add +.40% with Item No 5.05.05.06.1

Page: 1074 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.05.05.06.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.72% with Item No 5.05.05.06.1

5.05.05.06.4

Add for each additional floor for 10th floor and above.

cum

Add +.96% with Item No 5.05.05.06.1

5.05.05.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick)

5.05.05.07.1

Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

1.5000

day

370.00

555.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9397.71

Subtotal-A: Steel form work & all other remaining costs

( +82.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Add for each additional floor upto 5th floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

7706.12 17103.83

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17445.91

10% Profit ( Add 10% on Subtotal-B) :

19190.50

VAT

6% of Total

1279.37

IT

4% of Total

852.91 Total:

5.05.05.07.2

2606.80

21322.78

Add +.95% with Item No 5.05.05.07.1

Page: 1075 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.05.05.07.3

Add for each additional floor from 6th floor upto 9th

cum

Add +1.75% with Item No 5.05.05.07.1

5.05.05.07.4

Add for each additional floor for 10th floor and above.

cum

Add +2.38% with Item No 5.05.05.07.1

5.05.05.08

In Stair case slab and step

5.05.05.08.1

Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9719.21

Subtotal-A: Steel form work & all other remaining costs

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12634.97 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12887.67

10% Profit ( Add 10% on Subtotal-B) :

14176.44

VAT

6% of Total

IT

4% of Total

945.10 630.06 Total:

5.05.05.08.2

Add for each additional floor upto 5th floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2915.76

15751.60

Add +.40% with Item No 5.05.05.08.1 Page: 1076 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.05.05.08.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.72% with Item No 5.05.05.08.1

5.05.05.08.4

Add for each additional floor for 10th floor and above.

cum

Add +.96% with Item No 5.05.05.08.1

5.05.05.09

In Waffle or Ribbed floor/roof slab

5.05.05.09.1

Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Water reducing chemical admixture : Type-A

1.9270

liter

130.00

250.51 9719.21

Subtotal-A: Steel form work & all other remaining costs

( +94.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

18855.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19232.37

10% Profit ( Add 10% on Subtotal-B) :

21155.61

VAT

6% of Total

IT

4% of Total

1410.37 940.25 Total:

5.05.05.09.2

Add for each additional floor upto 5th floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

9136.06

23506.23

Add +.26% with Item No 5.05.05.09.1 Page: 1077 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.05.09.3

Add for each additional floor from 6th floor upto 9th

cum

Add +.46% with Item No 5.05.05.09.1

5.05.05.09.4

Add for each additional floor for 10th floor and above.

cum

Add +.62% with Item No 5.05.05.09.1

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1078 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.06

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC: Mix Design 25MPa, Stone Chips (SC), Batching Plant (BP): Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by Laboratory through mix design having minimum required average compressive strength, f'cr = 33.5 Mpa and satisfying a specified compressive strength, f'c = 25 Mpa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and Portland Composite Cement conforming to BDS EN 197-1 : 2003 CEM-II 42.5N, high range water reducing chemical admixture of complying type F/G under ASTM C494 which is required to produce concrete of consistency by 12% or greater (flowing concrete) and for higher strength and intend to retard setting time of concrete. (Doses of admixture to be fixed by the mix design from approved laboratory instruction by the Engineer) for smart dynamic concrete (i.e. Low fines self-compacting concrete), sand of minimum FM 2.50 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur) (LAA value not exceeding 30) conforming to ASTM C33 and Aggregate Grading Appendix-3 LGED Schedule of Rates or any other International recognized envelop in/c cost of breaking chips, screening through proper sieves, cleaning and washing thoroughly, centering, shuttering in position with plain 16 BWG steel sheet fitted over 38mmx38mmx5mm MS angle and 25mmx5mm FI bar frame and 38mm/50mm steel or GI pipe props suitably braced and 12 BWG steel sheet plate box of proper size where required i/c cost of nuts, bolts, J-hooks etc, placing of reinforcement in position, mixing in mechanized a batching and mixing plant and pumping using line pump or boom placer, maintaining allowable slump of 100mm to 150mm casting in steel forms, compacting by Mechanical vibrators and tapered rods and curing at least for 28 days removing centering-shuttering after approved specified time period i/c cost of additional testing charges of materials and cylinders required (Excluding the cost of reinforcements and its fabrication welding, coupling, placing, binding etc. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost) etc. all complete as per direction and approval of the Engineer in charge. The Mix Design shall have to be approved by the District Quality Control Laboratory, LGED or approved laboratory instruction by the Engineer before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1079 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.06.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9696.77

Subtotal-A: Steel form work & all other remaining costs

( +6.00 % on Subtotal-A )

581.81

Subtotal-A1: Subtotal-B: Subtotal-C:

10278.58 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10484.15

10% Profit ( Add 10% on Subtotal-B) :

11532.56

VAT

6% of Total

IT

4% of Total

768.84 512.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2606.80

12813.96

Page: 1080 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.06.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9696.77

Subtotal-A: Steel form work & all other remaining costs

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11054.32 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11275.40

10% Profit ( Add 10% on Subtotal-B) :

12402.94

VAT

6% of Total

IT

4% of Total

826.86 551.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1357.55

13781.05

Page: 1081 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.06.03

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

In pedestal, column, column capitals, lift wall and walls

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1082 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.06.03.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9696.77

Subtotal-A: Steel form work & all other remaining costs

( +48.00 % on Subtotal-A )

Subtotal-A1:

14351.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14638.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16102.07

VAT

6% of Total

IT

4% of Total

1073.47 715.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4654.45

17891.19

Page: 1083 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.05.06.03.2

Add for each additional floor up to 5th Floor

cum

Add +.35% with Item No 5.05.06.03.1

5.05.06.03.3

Add for each additional floor from 6th floor up to 9th floor

cum

Add +.63% with Item No 5.05.06.03.1

5.05.06.03.4

Add for each additional floor for 10th floor & above

cum

Add +.85% with Item No 5.05.06.03.1

5.05.06.04

In Tie Beam and lintel :

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1084 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.06.04.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9696.77

Subtotal-A: Steel form work & all other remaining costs

( +31.00 % on Subtotal-A )

Subtotal-A1:

12702.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12956.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14252.51

VAT

6% of Total

IT

4% of Total

950.17 633.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3006.00

15836.12

Page: 1085 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.06.04.2

Add for each additional floor up to 5th Floor

cum

Add +.41% with Item No 5.05.06.04.1

5.05.06.04.3

Add for each additional floor from 6th floor up to 9th floor

cum

Add +.75% with Item No 5.05.06.04.1

5.05.06.04.4

Add for each additional floor for 10th floor & above

cum

Add +1.00% with Item No 5.05.06.04.1

5.05.06.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1086 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.05.06.05.1

2 Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9696.77

Subtotal-A: Steel form work & all other remaining costs

( +34.00 % on Subtotal-A )

Subtotal-A1:

12993.67

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13253.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14578.90

VAT

6% of Total

IT

4% of Total

971.93 647.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3296.90

16198.78

Page: 1087 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.06.05.2

Add for each additional floor up to 5th Floor

cum

Add +.38% with Item No 5.05.06.05.1

5.05.06.05.3

Add for each additional floor from 6th floor up to 9th floor

cum

Add +.69% with Item No 5.05.06.05.1

5.05.06.05.4

Add for each additional floor for 10th floor & above

cum

Add +.92% with Item No 5.05.06.05.1

5.05.06.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1088 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.05.06.06.1

2 Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9696.77

Subtotal-A: Steel form work & all other remaining costs

( +28.00 % on Subtotal-A )

Subtotal-A1:

12411.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12660.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13926.11

VAT

6% of Total

IT

4% of Total

928.41 618.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2715.10

15473.46

Page: 1089 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.06.06.2

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.06.06.1

5.05.06.06.3

Add for each additional floor from 6th floor up to 9th floor

cum

Add +.72% with Item No 5.05.06.06.1

5.05.06.06.4

Add for each additional floor for 10th floor & above

cum

Add +.96% with Item No 5.05.06.06.1

5.05.06.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick).

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1090 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.05.06.07.1

2 Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9672.77

Subtotal-A: Steel form work & all other remaining costs

( +82.00 % on Subtotal-A )

Subtotal-A1:

17604.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17956.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19752.18

VAT

6% of Total

1316.81

IT

4% of Total

877.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7931.67

21946.87

Page: 1091 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.05.06.07.2

Add for each additional floor upto 5th floor

cum

Add +.95% with Item No 5.05.06.07.1

5.05.06.07.3

Add for each additional floor from 6th floor upto 9th

cum

Add +1.75% with Item No 5.05.06.07.1

5.05.06.07.4

Add for each additional floor for 10th floor and above.

cum

Add +2.38% with Item No 5.05.06.07.1

5.05.06.08

In Stair case slab and step

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1092 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.05.06.08.1

2 Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9696.77

Subtotal-A: Steel form work & all other remaining costs

( +33.00 % on Subtotal-A )

Subtotal-A1:

12896.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13154.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14470.10

VAT

6% of Total

IT

4% of Total

964.67 643.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3199.93

16077.89

Page: 1093 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.06.08.2

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.06.08.1

5.05.06.08.3

Add for each additional floor from 6th floor up to 9th floor

cum

Add +.72% with Item No 5.05.06.08.1

5.05.06.08.4

Add for each additional floor for 10th floor & above

cum

Add +.96% with Item No 5.05.06.08.1

5.05.06.09

In Waffle or Ribbed floor/roof slab

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1094 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.05.06.09.1

2 Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water-reducing high range chemical admixture : Type-F

1.9270

liter

160.00

308.32

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Head Mason

0.0800

day

650.00

52.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.4000

day

450.00

180.00

Ordinary Labour

1.2000

day

370.00

444.00 9696.77

Subtotal-A: Steel form work & all other remaining costs

( +98.00 % on Subtotal-A )

Subtotal-A1:

19199.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19583.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21541.96

VAT

6% of Total

IT

4% of Total

1436.13 957.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9502.83

23935.51

Page: 1095 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.06.09.2

Add for each additional floor up to 5th Floor

cum

Add +.26% with Item No 5.05.06.09.1

5.05.06.09.3

Add for each additional floor from 6th floor up to 9th floor

cum

Add +.46% with Item No 5.05.06.09.1

5.05.06.09.4

Add for each additional floor for 10th floor & above

cum

Add +.62% with Item No 5.05.06.09.1

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1096 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.07

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC:1:1.25:2.5, 30MPa, Stone Chips (SC): Reinforced cement concrete works using steel shutter with minimum cement content relates to mix ratio tentative 1:1.25:2.5 and maximum water cement ratio 0.4 having minimum cylinder crushing strength f’cr = 40 Mpa and satisfied a specified compressive strength f’c = 30 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and Ordinary Portland cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N/ASTM C150 Type-1 and adding approved high range water reducing chemical admixture of complying specific type (generally be Type-F) under ASTM-C 494 which is required to produce concrete of consistency by 12% or greater (flowing concrete) and for higher strength and intend to retard setting time of concrete. (Doses of admixture to be fixed by the mix design and used only instruction of Central Quality Control Laboratory of LGED or approved laboratory instruction by the Engineer), best quality sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulder (LAA value not exceeding 30) conforming to ASTM C33 and Aggregate Grading Appendix-3 LGED Schedule of Rates in/c cost of breaking chips, screening, centering, shuttering in position with plain 16 BWG steel sheet fitted over 38mmx38mmx5mm MS angle and 25mmx5mm FI bar frame and 38mm/50mm steel or GI pipe props suitably braced and 12 BWG steel sheet plate box of proper size where required i/c cost of nuts, bolts, J-hooks etc, making shuttering fully leak proof placing of reinforcement in position, mixing in a standard mixer machine with hoper or batching and mixing plant and pumping using line pump or boom placer as per approved mix design unless other wise approved by the Engineer, fed by standard measuring boxes, maintaining allowable slump of 75mm to 100mm pouring, casting, compacting by Mechanical vibrator machine and curing at least for 28 days removing centeringshuttering after approved specified time period i/c cost of additional testing charges of materials and cylinders required. Excluding the cost of reinforcement and its fabrication, welding, coupling, placing, binding etc. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost etc. all complete as per direction and approval of the Engineer in charge. The Mix Design shall be got approved by the District Quality Control Laboratory, LGED or approved laboratory instruction by the Engineer before execution of the work. Note : Using Concrete Mixer.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1097 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.07.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

Sand (FM - 2.5) Ordinary Portland Cement (CEM I, 52.5N)

0.4000

m3

1500.00

600.00

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 10541.91

Subtotal-A: Steel form work & all other remaining costs

( +5.00 % on Subtotal-A )

527.10

Subtotal-A1: Subtotal-B: Subtotal-C:

11069.01 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11290.39

10% Profit ( Add 10% on Subtotal-B) :

12419.42

VAT

6% of Total

IT

4% of Total

827.96 551.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2606.80

13799.36

Page: 1098 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.07.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3900

m3

4470.00

1743.30 10810.11

Subtotal-A: Steel form work & all other remaining costs

( +13.00 % on Subtotal-A )

Subtotal-A1:

12215.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12459.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13705.71

VAT

6% of Total

913.71

IT

4% of Total

609.14 Total:

5.05.07.03

1405.31

15228.56

In pedestal, column, capital lift wall and wall :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1099 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.07.03.1

2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 10541.91

Subtotal-A: Steel form work & all other remaining costs

( +46.00 % on Subtotal-A )

Subtotal-A1:

15391.19

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15699.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17268.91

VAT

6% of Total

1151.26

IT

4% of Total

767.51 Total:

5.05.07.03.2

Add for each additional floor up to 5th Floor

cum

Add +.35% with Item No 5.05.07.03.1

5.05.07.03.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.63% with Item No 5.05.07.03.1

5.05.07.03.4

Add for each additional floor for 10th floor and above

cum

Add +.85% with Item No 5.05.07.03.1

5.05.07.04

In Tie Beam and Lintel :

Note : Rates of all items should be inclusive of all supply and carriage.

4849.28

19187.68

Page: 1100 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.07.04.1

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 10541.91

Subtotal-A: Steel form work & all other remaining costs

( +30.00 % on Subtotal-A )

Subtotal-A1:

13704.48

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13978.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15376.43

VAT

6% of Total

1025.10

IT

4% of Total

683.40 Total:

5.05.07.04.2

Add for each additional floor up to 5th Floor

cum

Add +.41% with Item No 5.05.07.04.1

5.05.07.04.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.75% with Item No 5.05.07.04.1

5.05.07.04.4

Add for each additional floor for 10th floor and above

cum

Add +1.00% with Item No 5.05.07.04.1

Note : Rates of all items should be inclusive of all supply and carriage.

3162.57

17084.92

Page: 1101 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.05.07.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

5.05.07.05.1

Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 10541.91

Subtotal-A: Steel form work & all other remaining costs

( +34.00 % on Subtotal-A )

Subtotal-A1:

14126.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14408.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15849.55

VAT

6% of Total

IT

4% of Total

1056.64 704.42 Total:

5.05.07.05.2

Add for each additional floor up to 5th Floor

cum

Add +.38% with Item No 5.05.07.05.1

5.05.07.05.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.69% with Item No 5.05.07.05.1

Note : Rates of all items should be inclusive of all supply and carriage.

3584.25

17610.61

Page: 1102 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.05.07.05.4

Add for each additional floor for 10th floor and above

5.05.07.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

5.05.07.06.1

Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Add +.92% with Item No 5.05.07.05.1

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 10558.41

Subtotal-A: Steel form work & all other remaining costs

( +28.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

13514.76 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13785.06

10% Profit ( Add 10% on Subtotal-B) :

15163.57

VAT

6% of Total

IT

4% of Total

1010.90 673.94 Total:

5.05.07.06.2

Add for each additional floor up to 5th Floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2956.35

16848.41

Add +.40% with Item No 5.05.07.06.1

Page: 1103 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.07.06.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.72% with Item No 5.05.07.06.1

5.05.07.06.4

Add for each additional floor for 10th floor and above

cum

Add +.96% with Item No 5.05.07.06.1

5.05.07.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick)

5.05.07.07.1

Below Plinth Level and in Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

Sand (FM - 2.5) Ordinary Portland Cement (CEM I, 52.5N)

0.4000

m3

1500.00

600.00

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Water-reducing high range and retrading chemical admixture : Type-G

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 10517.91

Subtotal-A: Steel form work & all other remaining costs

( +81.00 % on Subtotal-A )

Subtotal-A1:

Add for each additional floor up to 5th Floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

8519.51 19037.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19418.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21359.98

VAT

6% of Total

IT

4% of Total

1424.00 949.33 Total:

5.05.07.07.2

2606.80

23733.31

Add +.95% with Item No 5.05.07.07.1 Page: 1104 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.05.07.07.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +1.75% with Item No 5.05.07.07.1

5.05.07.07.4

Add for each additional floor for 10th floor and above

cum

Add +2.38% with Item No 5.05.07.07.1

5.05.07.08

In Stair case slab and step

5.05.07.08.1

Below Plinth Level and in Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 10541.91

Subtotal-A: Steel form work & all other remaining costs

( +31.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

13809.90 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14086.10

10% Profit ( Add 10% on Subtotal-B) :

15494.71

VAT

6% of Total

IT

4% of Total

1032.98 688.65 Total:

5.05.07.08.2

Add for each additional floor up to 5th Floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

3267.99

17216.34

Add +.40% with Item No 5.05.07.08.1 Page: 1105 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.07.08.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.72% with Item No 5.05.07.08.1

5.05.07.08.4

Add for each additional floor for 10th floor and above

cum

Add +.96% with Item No 5.05.07.08.1

5.05.07.09

In Waffle or Ribbed floor/roof slab

5.05.07.09.1

Below Plinth Level and in Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 10541.91

Subtotal-A: Steel form work & all other remaining costs

( +96.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

20662.14 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21075.39

10% Profit ( Add 10% on Subtotal-B) :

23182.93

VAT

6% of Total

IT

4% of Total

1545.53 1030.35 Total:

5.05.07.09.2

Add for each additional floor up to 5th Floor

Note : Rates of all items should be inclusive of all supply and carriage.

cum

10120.23

25758.81

Add +.26% with Item No 5.05.07.09.1 Page: 1106 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.05.07.09.3

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.46% with Item No 5.05.07.09.1

5.05.07.09.4

Add for each additional floor for 10th floor and above

cum

Add +.62% with Item No 5.05.07.09.1

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1107 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-30MPa, Stone Chips (SC), Batching Plant (BP): Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by Quality Control Laboratory, LGED or approved laboratory instruction by the Engineer before execution of the work. Having minimum required average compressive strength, f'cr = 38.5 Mpa and satisfying a specified compressive strength, f'c = 30 Mpa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design from approved laboratory instruction by the Engineer) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.50 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C33 and Aggregate Grading Appendix-3 LGED Schedule of Rates or any other International recognized envelop in/c cost of breaking chips, screening through proper sieves, cleaning and washing thoroughly, centering, shuttering in position with plain 16 BWG steel sheet fitted over 38mmx38mmx5mm MS angle and 25mmx5mm FI bar frame and 38mm/50mm steel or GI pipe props suitably braced and 12 BWG steel sheet plate box of proper size where required i/c cost of nuts, bolts, Jhooks etc, placing of reinforcement in position, mixing in mechanized a batching and mixing plant and pumping using line pump or boom placer, maintaining allowable slump of 100mm to150mm casting in steel forms, compacting by Mechanical vibrators and tapered rods and curing at least for 28 days removing centering-shuttering after approved specified time period i/c cost of additional testing charges of materials and cylinders required (Excluding the cost of reinforcements and its fabrication welding, coupling, placing, binding etc. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost) etc. all complete as per approval of the Engineer in charge. The Mix Design shall have to approved by the Central Quality Control Laboratory (CQCL), LGED or approved laboratory instruction by the Engineer before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1108 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Diesel

1.0730

liter

68.00

72.96 11025.62

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +6.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

661.54 11687.16

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11920.90

10% Profit ( Add 10% on Subtotal-B) :

13113.00

6% of Total

874.20 Page: 1109 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

582.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14569.99

Page: 1110 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.08.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10952.66

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

1533.37 12486.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12735.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14009.33

VAT

6% of Total

IT

4% of Total

933.96 622.64

Page: 1111 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.08.03

15565.92

In pedestal, column, capital lift wall and wall :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1112 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08.03.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10952.66

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +48.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

5257.28 16209.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16534.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18187.55

VAT

6% of Total

IT

4% of Total

1212.50 808.34

Page: 1113 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.08.03.02

Add for each additional floor up to 5th Floor

cum

Add +.35% with Item No 5.05.08.03.01

5.05.08.03.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.63% with Item No 5.05.08.03.01

5.05.08.03.04

Add for each additional floor for 10th floor and above

cum

Add +.85% with Item No 5.05.08.03.01

5.05.08.04

In Tie Beam and Lintel :

Note : Rates of all items should be inclusive of all supply and carriage.

20208.39

Page: 1114 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08.04.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10952.66

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +31.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

3395.32 14347.98

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14634.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16098.44

VAT

6% of Total

IT

4% of Total

1073.23 715.49

Page: 1115 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.08.04.02

Add for each additional floor up to 5th Floor

cum

Add +.41% with Item No 5.05.08.04.01

5.05.08.04.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.75% with Item No 5.05.08.04.01

5.05.08.04.04

Add for each additional floor for 10th floor and above

cum

Add +1.00% with Item No 5.05.08.04.01

5.05.08.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

Note : Rates of all items should be inclusive of all supply and carriage.

17887.15

Page: 1116 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08.05.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10952.66

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +34.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

3723.90 14676.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14970.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16467.11

VAT

6% of Total

IT

4% of Total

1097.81 731.87

Page: 1117 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.08.05.02

Add for each additional floor up to 5th Floor

cum

Add +.38% with Item No 5.05.08.05.01

5.05.08.05.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.69% with Item No 5.05.08.05.01

5.05.08.05.04

Add for each additional floor for 10th floor and above

cum

Add +.92% with Item No 5.05.08.05.01

5.05.08.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

Note : Rates of all items should be inclusive of all supply and carriage.

18296.78

Page: 1118 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08.06.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10952.66

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +28.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

3066.74 14019.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14299.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15729.77

VAT

6% of Total

IT

4% of Total

1048.65 699.10

Page: 1119 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.08.06.02

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.08.06.01

5.05.08.06.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.72% with Item No 5.05.08.06.01

5.05.08.06.04

Add for each additional floor for 10th floor and above

cum

Add +.96% with Item No 5.05.08.06.01

5.05.08.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick)

Note : Rates of all items should be inclusive of all supply and carriage.

17477.52

Page: 1120 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08.07.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10952.66

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +82.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

8981.18 19933.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20332.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22365.77

VAT

6% of Total

IT

4% of Total

1491.05 994.03

Page: 1121 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.08.07.02

Add for each additional floor up to 5th Floor

cum

Add +.95% with Item No 5.05.08.07.01

5.05.08.07.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +1.75% with Item No 5.05.08.07.01

5.05.08.07.04

Add for each additional floor for 10th floor and above

cum

Add +2.38% with Item No 5.05.08.07.01

5.05.08.08

In Stair case slab and step

Note : Rates of all items should be inclusive of all supply and carriage.

24850.86

Page: 1122 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08.08.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10952.66

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +33.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

3614.38 14567.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14858.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16344.22

VAT

6% of Total

IT

4% of Total

1089.61 726.41

Page: 1123 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.08.08.02

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.08.08.01

5.05.08.08.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.72% with Item No 5.05.08.08.01

5.05.08.08.04

Add for each additional floor for 10th floor and above

cum

Add +.96% with Item No 5.05.08.08.01

5.05.08.09

In Waffle or Ribbed floor/roof slab

Note : Rates of all items should be inclusive of all supply and carriage.

18160.24

Page: 1124 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.08.09.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

8.9220

bag

455.00

4059.51

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4000

m3

1500.00

600.00

Water-reducing high range chemical admixture : Type-F

2.1500

liter

160.00

344.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.5000

day

370.00

555.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 10952.66

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +98.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

10733.61 21686.27

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22119.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24331.99

VAT

6% of Total

IT

4% of Total

1622.13 1081.42

Page: 1125 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.08.09.02

Add for each additional floor up to 5th Floor

cum

Add +.26% with Item No 5.05.08.09.01

5.05.08.09.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.46% with Item No 5.05.08.09.01

5.05.08.09.04

Add for each additional floor for 10th floor and above

cum

Add +.62% with Item No 5.05.08.09.01

Note : Rates of all items should be inclusive of all supply and carriage.

27035.55

Page: 1126 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-35 Mpa, Stone Chips (SC), Batching Plant (BP): Reinforced cement concrete work with minimum cement content and maximum water cement ratio as specified by CQCL, LGED having minimum required average compressive strength, f'cr = 45 Mpa and satisfying a specified compressive strength, f'c = 35 Mpa at 28 days on standard cylinder as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-I 52.5N / ASTM C150 Type-1, high range water reducing admixture of complying type F/ G under ASTM C494 (Doses of admixture to be fixed by the mix design from approved laboratory instruction by the Engineer) for smart dynamic concrete (i.e. Low fines self compacting concrete), sand of minimum FM 2.80 and 20mm down well graded crushed stone chips broken from boulders (LAA value not exceeding 25) conforming to ASTM C33 and Aggregate Grading Appendix-3 LGED Schedule of Rates or any other International recognized envelop, in/c cost of breaking chips, screening through proper sieves, cleaning and washing thoroughly, centering, shuttering in position with plain 16 BWG steel sheet fitted over 38mmx38mmx5mm MS angle and 25mmx5mm FI bar frame and 38mm/50mm steel or GI pipe props suitably braced and 12 BWG steel sheet plate box of proper size where required, i/c cost of nuts, bolts, J-hooks etc, placing of reinforcement in position, mixing in mechanized a batching and mixing plant and pumping using line pump or boom placer, maintaining allowable slump of 100mm to 150mm casting in steel forms, compacting by Mechanical vibrators and tapered rods and curing at least for 28 days, removing centering-shuttering after approved specified time period, i/c cost of additional testing charges of materials and cylinders required (Excluding the cost of reinforcements and its fabrication welding, coupling, placing, binding etc. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost), etc. all complete as per approval of the Engineer in charge. The Mix Design shall have to approved by the Central Quality Control Laboratory (CQCL), LGED or approved laboratory instruction by the Engineer before execution of the work. Note: Using Batching Plant, Transit Mixer & Concrete Pump

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1127 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09.01

Detailed Analysis Brief Description of Item 2 In individual and continuous footing of column, raft and floor slab at plinth level

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 12050.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +6.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

723.03 12773.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13028.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14331.86

VAT

6% of Total

IT

4% of Total

955.46 636.97 Page: 1128 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15924.29

Page: 1129 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.05.09.02

2 In foundation beam

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 12050.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

1687.07 13737.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14012.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15413.52

VAT

6% of Total

IT

4% of Total

1027.57 685.05

Page: 1130 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.09.03

17126.13

In pedestal, column, capital lift wall and wall :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1131 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09.03.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 12050.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +48.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

5784.23 17834.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18191.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20010.53

VAT

6% of Total

IT

4% of Total

1334.04 889.36

Page: 1132 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.09.03.02

Add for each additional floor up to 5th Floor

cum

Add +.35% with Item No 5.05.09.03.01

5.05.09.03.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.63% with Item No 5.05.09.03.01

5.05.09.03.04

Add for each additional floor for 10th floor and above

cum

Add +.85% with Item No 5.05.09.03.01

5.05.09.04

In Tie Beam and Lintel :

Note : Rates of all items should be inclusive of all supply and carriage.

22233.92

Page: 1133 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09.04.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 12050.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +31.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

3735.65 15786.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16101.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17712.02

VAT

6% of Total

IT

4% of Total

1180.80 787.20

Page: 1134 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.09.04.02

Add for each additional floor up to 5th Floor

cum

Add +.41% with Item No 5.05.09.04.01

5.05.09.04.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.75% with Item No 5.05.09.04.01

5.05.09.04.04

Add for each additional floor for 10th floor and above

cum

Add +1.00% with Item No 5.05.09.04.01

5.05.09.05

In Tee Beam, Ell Beam, Rectangular Beam etc. (exposed breadth and width of ribs to be measured only).

Note : Rates of all items should be inclusive of all supply and carriage.

19680.02

Page: 1135 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09.05.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 12050.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +34.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

4097.16 16147.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16470.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18117.64

VAT

6% of Total

IT

4% of Total

1207.84 805.23

Page: 1136 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.09.05.02

Add for each additional floor up to 5th Floor

cum

Add +.38% with Item No 5.05.09.05.01

5.05.09.05.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.69% with Item No 5.05.09.05.01

5.05.09.05.04

Add for each additional floor for 10th floor and above

cum

Add +.92% with Item No 5.05.09.05.01

5.05.09.06

In roof slab of all types, cantilever slab and drop panels (excluding floor slab of ground floor at plinth level).

Note : Rates of all items should be inclusive of all supply and carriage.

20130.71

Page: 1137 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09.06.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 12050.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +28.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

3374.13 15424.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15733.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17306.40

VAT

6% of Total

IT

4% of Total

1153.76 769.17

Page: 1138 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.09.06.02

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.09.06.01

5.05.09.06.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.72% with Item No 5.05.09.06.01

5.05.09.06.04

Add for each additional floor for 10th floor and above

cum

Add +.96% with Item No 5.05.09.06.01

5.05.09.07

In sunshade, cornice, railing, drop wall, louver and fins (Average 62mm to 87mm thick)

Note : Rates of all items should be inclusive of all supply and carriage.

19229.34

Page: 1139 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09.07.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Diesel

1.0730

liter

68.00

72.96 12123.43

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +82.00 % on Subtotal-A )

Subtotal-A1:

22064.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22505.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24756.54

VAT Note : Rates of all items should be inclusive of all supply and carriage.

9941.22

6% of Total

1650.44 Page: 1140 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

1100.29 Total:

5.05.09.07.02

Add for each additional floor up to 5th Floor

cum

Add +.95% with Item No 5.05.09.07.01

5.05.09.07.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +1.75% with Item No 5.05.09.07.01

5.05.09.07.04

Add for each additional floor for 10th floor and above

cum

Add +2.38% with Item No 5.05.09.07.01

5.05.09.08

In Stair case slab and step

Note : Rates of all items should be inclusive of all supply and carriage.

27507.26

Page: 1141 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09.08.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 12050.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +33.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

3976.66 16027.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16347.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17982.43

VAT

6% of Total

IT

4% of Total

1198.83 799.22

Page: 1142 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.09.08.02

Add for each additional floor up to 5th Floor

cum

Add +.40% with Item No 5.05.09.08.01

5.05.09.08.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.72% with Item No 5.05.09.08.01

5.05.09.08.04

Add for each additional floor for 10th floor and above

cum

Add +.96% with Item No 5.05.09.08.01

5.05.09.09

In Waffle or Ribbed floor/roof slab

Note : Rates of all items should be inclusive of all supply and carriage.

19980.48

Page: 1143 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.09.09.01

Detailed Analysis Brief Description of Item 2 Below Plinth Level and in Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Ordinary Portland Cement (CEM I, 52.5N)

9.0000

bag

455.00

4095.00

Stone Chips (20mm down graded) [LAA≤25]

0.4900

cum

5730.00

2807.70

Stone Chips (12mm down graded) [LAA≤25]

0.3300

cum

4640.00

1531.20

Sand (FM - 2.8)

0.4100

m3

1602.00

656.82

Water-reducing high range chemical admixture : Type-F

2.2500

liter

160.00

360.00

Head Mason

0.0800

day

650.00

52.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

2.5000

day

370.00

925.00

Hire and running charges of Batching and Mixing Plant @ 20 cum/hour

0.0083

day

23000.00

190.90

H.C. of Generator (100 KVA)

0.0083

day

3500.00

29.05

H.C. of Backhoe End Loader (6 tons)

0.0083

day

6000.00

49.80

H.C. of Transit Mixer 4.0/4.5 cum capacity including fuel & other related cost

0.0200

day

10000.00

200.00

Hire and running charges of Concrete Pump (30 & 45 cum capacity)

0.0083

day

5000.00

41.50

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 12050.47

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +98.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

11809.46 23859.93

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24337.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26770.84

VAT

6% of Total

IT

4% of Total

1784.72 1189.82

Page: 1144 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.05.09.09.02

Add for each additional floor up to 5th Floor

cum

Add +.26% with Item No 5.05.09.09.01

5.05.09.09.03

Add for each additional floor from 6th floor upto 9th floor

cum

Add +.46% with Item No 5.05.09.09.01

5.05.09.09.04

Add for each additional floor for 10th floor and above

cum

Add +.62% with Item No 5.05.09.09.01

5.05.10

Extra rate over the rate of corresponding items of Ground floor (or any other floor as the case may be) for each additional each meter height of Auditorium, Godown, Overhead water tank etc. where free height of the structure exceeds 4m or a remain up to 11m casting of column, capital lift wall, wall, Tee beam, Ell beam, rectangular beam, roof slab, cantilever slab and drop panel that executed after said height. The description of the item will be same as corresponding item Nos. 05.01.03/5.05.01.04/5.05.01.05/5.05.01.06 /5.05.01.07 / 5.05.05.03/5.05.05.04/5.05.05.05/5.05.05.06/5.05.05.03/ 5.05.05.04/ 5.05.05.05 /5.05.05.06/5.05.06.03/5.05.06.04/ 5.05.06.05/ 5.05.06.06 For each additional meter of height beyond 4 m up to 11m height

Note : Rates of all items should be inclusive of all supply and carriage.

29745.38

Page: 1145 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.10.01

Detailed Analysis Brief Description of Item 2 In column, capitals, lift wall & walls where the free height of the structure exceeds 4 m (rate is considered for each additional meter height)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Head Mason

0.0500

day

650.00

32.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.5000

day

370.00

185.00 317.50

Subtotal-A: All other remaining costs

( +214.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

996.95 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1016.89

10% Profit ( Add 10% on Subtotal-B) :

1118.58

VAT

6% of Total

IT

4% of Total

74.57 49.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

679.45

1242.86

Page: 1146 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.10.02

Detailed Analysis Brief Description of Item 2 In Tee beams, Ell beams and Rectangular beams where the free height of the structure exceeds 4 m (rate is considered for each additional meter height)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Head Mason

0.0500

day

650.00

32.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.5000

day

370.00

185.00

( +700.00 % on Subtotal-A )

2222.50

317.50

Subtotal-A: All other remaining costs Subtotal-A1: Subtotal-B: Subtotal-C:

2540.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2590.80

10% Profit ( Add 10% on Subtotal-B) :

2849.88

VAT

6% of Total

IT

4% of Total

189.99 126.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3166.53

Page: 1147 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.10.03

Detailed Analysis Brief Description of Item 2 In floor/roof slab, cantilever slab, waffle slab and drop panels where the free height of the structure exceeds 4m (rate is considered for each additional meter height)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Head Mason

0.0500

day

650.00

32.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.5000

day

370.00

185.00

( +858.00 % on Subtotal-A )

2724.15

317.50

Subtotal-A: All other remaining costs Subtotal-A1: Subtotal-B: Subtotal-C:

3041.65 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3102.48

10% Profit ( Add 10% on Subtotal-B) :

3412.73

VAT

6% of Total

IT

4% of Total

227.52 151.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3791.92

Page: 1148 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.05.11

Detailed Analysis Brief Description of Item 2 Dismantling of existing/damaged RCC work in sub-structure or superstructure works of any type manualy or any other means without any damage in structure and sorting the dismantled materials disposal of unserviceable materials and stacking the serviceable materials properly for measurment for all floors, Cost of conveying, loading, transportation of unserviceable material accumulated during dismantling operation is included in this unit rate. The unserviceable material must be disposed at a safe place outside the site premises with minimum traffic disruption and the procuring entity will not provide any environmentally safe place for disposing the unserviceable materials.etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

962.00

cum

Ordinary Labour

2.6000

962.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

981.24 1079.36 71.96 47.97

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1199.29

Page: 1149 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying and fabrication of Ribbed or deformed bar reinforcement for all types of RCC work including straightening, removing ruts, cleaning, cutting, hooking, bending, lapping and/or welding wherever required as directed, placing in position, tieing with 22 BWG black annealed binding wire (PVC coated in case of FBEC rebar) double fold, cost of binding wire and anchoring to the adjoining members wherever necessary, supplying and placing with proper cover blocks (1:1), supports, chairs, spacers, splices or laps etc. including cost of all materials, cost of labour, cost of equipment & machinery, loading and unloading, transportation, all other incidental charges and work at all leads and lifts etc. to complete the work as per design, drawing, specifications and direction of the E-I-C. Measurement relating to nominal mass, dimensions and tolerances of various types of steel shall conform to relevant BDS/ ASTM codes. Reinforcement shall be measured only in lengths of bar as actually placed in position on standard weight i.e. 7850 kg/m3 (BNBC Table 6.2.1) basis. No separate payment shall be allowed for Chairs of any shape & profile, spacer bar of any shape & profile, lap/ splice unless otherwise shown in the drawing, wastages, binding wire, concrete cover blocks etc. as the cost of these is included in the unit rate. Note: Tests for reinforcing bars shall be conducted at LGED/ BUET/ CUET/ KUET/ RUET.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1150 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.01.01

Detailed Analysis Brief Description of Item 2 Grade 300 (RB 300): Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield strength, fy (ReH) = 300 MPa, but the tested yield strength shall not exceed fy by more than the 125 MPa and the ratio of tested ultimate strength, fu (Re) to tested yield strength (fy) shall be at least 1.25 and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 16% and 2.5% respectively.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78

M.S. Ribbed/ Deformed Bar (Grade 300)

1.0200

kg

54.00

55.08 61.59

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

69.10

VAT

6% of Total

IT

4% of Total

4.61 3.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

76.78

Page: 1151 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.01.02

Detailed Analysis Brief Description of Item 2 Grade 400 (RB 400/ 400W): Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield strength, fy (ReH) = 400 MPa, but the tested yield strength shall not exceed fy by more than the 125 MPa and the ratio of tested ultimate strength, fu (Re) to tested yield strength (fy) shall be at least 1.25 and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 14% and 2.5% respectively.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78

M.S. Ribbed/ Deformed Bar (Grade 400)

1.0200

kg

58.00

59.16 65.67

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

73.68

VAT

6% of Total

IT

4% of Total

4.91 3.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

81.87

Page: 1152 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.01.03

Detailed Analysis Brief Description of Item 2 Grade 420 (B420DWR): Ribbed or Deformed bar produced and marked as per ISO 6935-2:2015/ ASTM A706M - 16 with minimum yield strength, fy(ReH) = 420 MPa but fy(ReH) not exceeding 540 MPa, the ratio of ultimate tensile strength, fu(Rm) to actual yield strength, fy(ReH) shall be at least 1.25 and minimum elongation in 200mm shall be at least 14% for bar sizes 10mm through 20mm, at least 12% for bar sizes 22mm through 32mm and at least 10% for bar sizes 40mm and 50mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

M.S. Ribbed/ Deformed Bar (Grade 420)

1.0200

kg

58.00

59.16

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 65.67

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.98

10% Profit ( Add 10% on Subtotal-B) :

73.68

VAT

6% of Total

4.91

IT

4% of Total

3.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

81.87

Page: 1153 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.01.04

Detailed Analysis Brief Description of Item 2 Grade 500 (RB 500/ 500W): Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield stress, fy (ReH) = 500 Mpa and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 14% and 2.5% respectively. This reinforcement shall be selected as per instruction given in the drawing & after getting approval from Design unit, LGED.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

M.S. Ribbed/ Deformed Bar (Grade 500)

1.0200

kg

57.00

58.14

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 64.65

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

65.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

72.54

VAT

6% of Total

IT

4% of Total

4.84 3.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

80.60

Page: 1154 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.01.05

Detailed Analysis Brief Description of Item 2 Grade 550: Deformed bar produced and marked as per ASTM A706M 16 with minimum yield strength, fy = 550 Mpa but fy not exceeding 675 Mpa, minimum ultimate strength, fu = 690 Mpa, the ratio of actual ultimate tensile strength, fu to actual yield strength, fy shall be at least 1.25 and minimum elongation in 200mm shall be at least 12% for bar sizes 10mm through 32mm and at least 10% for bar sizes 40mm and 50mm. This reinforcement shall be selected as per instruction given in the drawing & after getting approval from Design unit, LGED.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

M.S. Ribbed/ Deformed Bar (Grade 550)

1.0200

kg

59.00

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 66.69

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

68.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

74.83

VAT

6% of Total

4.99

IT

4% of Total

3.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

60.18

83.14

Page: 1155 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.06.02

FBECR: Extra over item code: 5.06.01 for providing Fusion Bonded Epoxy Coating (FBEC) to reinforcement bars as per ASTM A775/ BDS ISO 14654: 2013 specification for a coating thickness (after curing) of 175 to 300 microns for 10mm to 16mm and 175 to 400 microns for 20mmm to 50mm re-bars including extra cost on account of careful handling during straightening, cutting, bending & placing, extra cost on account of using PVC coated binding wire instead of G.I. wire, extra cost on account of touch-up material (All cut edges/weld areas and bend locations where coating has been damaged touch up shall be done with same paint, the upper thickness limit shall not apply to repaired areas of damaged coating) supplied by coating agency and repair work, extra cost on account of transportation to and fro from steel yard to plant and plant to work site by trailer (if required), loading, unloading, flexibility & holiday testing, including all taxes, etc. complete to ensure proper resistance of FBE against corrosive environment. [Fusion Bonded Epoxy Coating to be proposed only in Coastal Area/Severe Exposure Condition with prior approval of Design Unit, LGED.]

5.06.02.01

8mm to 12mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg Fusion Bonded Epoxy Coating (FBEC) to Reinforcing Bar as per ASTM A775 (Average rate for bars of 8mm to 12mm)

1.0000

kg

10.00

10.00

Subtotal-A: Extra cost for careful handling, bending, Epoxy Touch Up, PVC coated binding wire etc.

( +5.00 % on Subtotal-A )

0.50

Subtotal-A1: Subtotal-B: Subtotal-C:

10.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10.71

10% Profit ( Add 10% on Subtotal-B) :

11.78

VAT

6% of Total

IT

4% of Total

0.79 0.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10.00

13.09

Page: 1156 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.06.02.02

2 16mm to 50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg Fusion Bonded Epoxy Coating (FBEC) to Reinforcing Bar as per ASTM A775 (Average rate for bars of 16mm to 50mm)

1.0000

kg

8.00

8.00

Subtotal-A: Extra cost for careful handling, bending, Epoxy Touch Up, PVC coated binding wire etc.

( +5.00 % on Subtotal-A )

0.40

Subtotal-A1:

8.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9.42

VAT

6% of Total

IT

4% of Total

0.63 0.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8.00

10.47

Page: 1157 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.03

Detailed Analysis Brief Description of Item 2 Supplying and fabrication of High Yield strength (500 MPa, Galvanized wire rope) of required size and length for all types of Arch type structure work including cutting, fitting , securing and placing them in position, etc. including cost of all materials, labour, local handling, laboratory test, incidentals charge to complete the work as per specifications, drawings and direction of the Engineer. Laboratory test for physical property, strength, to be performed as per ASTM

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

kg

High Yield strength wire

1.0000

kg

200.00

200.00

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 205.61

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

209.72

10% Profit ( Add 10% on Subtotal-B) :

230.69

VAT

6% of Total

15.38

IT

4% of Total

10.25 Total:

5.06.04

256.33

Supplying, fitting and fixing mechanical couplers of various diameter confirming to ACI/ AASHTO having minimum connection strength at least 125% of nominal yield strength, fy of the reinforcing bars including fitting & fixing in proper position as shown in drawing and attach to the reinforcement bars by thread, cold swaging and extrusion or hot forging including cost of all materials, labors, equipment, tools etc. all complete as per design, drawing and direction of the E-I-C. All operations relating to reinforcement coupling shall be done using supplier's petented machine/ equipment and in the presence of the supplier's representative. The contractor shall submit relevant trade literature, mill certificates, certificate of origin and letters of approval for each proposed application. A sample of each type of mechanical coupler shall be submitted for testing and approval prior to the use of any coupler in the works

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1158 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.04.01

Detailed Analysis Brief Description of Item 2 For 25mm diameter rebar Coupler

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coupler (Min. Outer diameter 45mm & Length 150mm) including wastage 2% & carrying

1.0200

each

160.00

163.20

Pressing Machine

0.0080

day

3000.00

24.00

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0400

day

370.00

14.80 223.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

227.97

10% Profit ( Add 10% on Subtotal-B) :

250.77

VAT

6% of Total

IT

4% of Total

16.72 11.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

278.63

Page: 1159 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.04.02

Detailed Analysis Brief Description of Item 2 For 32mm diameter rebar Coupler

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coupler (Min. Outer diameter 56mm & Length 192mm) including wastage 2% & carrying

1.0200

each

240.00

244.80

Pressing Machine

0.0080

day

3000.00

24.00

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0400

day

370.00

14.80 305.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

311.20

10% Profit ( Add 10% on Subtotal-B) :

342.32

VAT

6% of Total

IT

4% of Total

22.82 15.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

380.36

Page: 1160 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.04.03

Detailed Analysis Brief Description of Item 2 For 40mm diameter rebar Coupler

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coupler (Min. Outer diameter 70mm & Length 240mm) including wastage 2% & carrying

1.0200

each

400.00

408.00

Pressing Machine

0.0080

day

3000.00

24.00

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0400

day

370.00

14.80 468.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

477.67

10% Profit ( Add 10% on Subtotal-B) :

525.43

VAT

6% of Total

IT

4% of Total

35.03 23.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

583.81

Page: 1161 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.04.04

Detailed Analysis Brief Description of Item 2 For 50mm diameter rebar Coupler

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coupler (Min. Outer diameter 82mm & Length 300mm) including wastage 2% & carrying

1.0200

each

450.00

459.00

Pressing Machine

0.0080

day

3000.00

24.00

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0300

day

450.00

13.50

Ordinary Labour

0.0400

day

370.00

14.80 519.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

529.69

10% Profit ( Add 10% on Subtotal-B) :

582.65

VAT

6% of Total

IT

4% of Total

38.84 25.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

647.39

Page: 1162 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.05

Detailed Analysis Brief Description of Item 2 Supplying and fabrication of mild steel of any sections as I, Circular, Tube, Tee, Angle of Mild steel Grade -250 with minimum fy = 250 MPa work in roof truss or any other member as per design, hoisting, fitting and fixing in position with bolts and nuts or rivets or welded and providing two coats of anticorrosive paint over a prime coat of red oxide paint etc. all complete as per direction of the E-I-C (Measurement be given for solid steel section only).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

MS Angle, Flat bar, Z bar

1.0200

kg

59.00

60.18

Subtotal-A: Fabrication, fitting, fixing, reverting, hosting,

( +42.00 % on Subtotal-A )

Supplying fan hook of 16mm dia MS rod (RB 300) (one meter long) having rounded hook at the middle of bar in proper size i/c. fabrication and fixing in position in all floors etc. all complete as per direction of the E-I-C.

85.46

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

87.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

95.88

VAT

6% of Total

6.39

IT

4% of Total

4.26 106.53

each

MS Rod (Plain, 40 Grade)

0.9100

kg

45.00

40.95

Ordinary Labour

0.1200

day

370.00

44.40 85.35

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

87.06

10% Profit ( Add 10% on Subtotal-B) :

95.76

VAT

6% of Total

IT

4% of Total

6.38 4.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25.28

Subtotal-A1:

Total: 5.06.06

60.18

106.40

Page: 1163 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.07

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing MS flat bar clamp (175mmx38mmx6mm) with bifurcated ends to door and window frames with necessary screws and encasing inside the wall with cement concrete (1:2:4) with curing, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.0030

cum

6799.07

20.40

MS flat bar clamp(175x38x6mm)

0.4400

kg

59.00

25.96

Skilled Labour

0.1000

day

450.00

45.00 91.36

Subtotal-A: Subtotal-B: Subtotal-C:

93.18

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102.50

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6.83 4.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

113.89

Page: 1164 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.08

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing MS flat bar clamp (150mmx38mmx6mm) with bifurcated ends to door and window frames with rowel plug, necessary screws etc. with the help of electric drill/hammer drill in/c. cutting groove in chowkat if necessary etc. complete in all respect as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS flat bar clamp(150x38x6mm)

0.3200

kg

59.00

18.88

Rowel plug

4.0000

each

0.25

1.00

50mm Screw (Iron)

4.0000

each

1.10

4.40

40mm screw (Iron)

2.0000

each

0.40

0.80

Skilled Labour

0.1000

day

450.00

45.00 70.08

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

71.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

78.63

VAT

6% of Total

5.24

IT

4% of Total

3.49 Total:

5.06.09

87.37

Constructing expansion joints 25mm/38mm gap in RCC floor or roof slab or beam provided with “V” folded copper/aluminium water stop sheet with loop, notch and inserted 75mm concrete shoulders, the gap being filled up with mixture of hot applied bituminous sealing compound etc. all complete as per direction of the E-I-C. (Excluding the cost of floor shoulders and floor finishes).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1165 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.06.09.01

2 With copper sheet

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m Copper folded water stop sheet

0.2200

m2

891.00

196.02

Mastic or bituminous sealing

1.0000

m

91.80

91.80

Skilled Labour

0.6700

day

450.00

301.50 589.32

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

601.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

661.22

VAT

6% of Total

IT

4% of Total

44.08 29.39 Total:

5.06.09.02

With Aluminum sheet

m Aluminium V-folded water stop sheet

0.2200

m2

640.00

140.80

Mastic or bituminous sealing

1.0000

m

91.80

91.80

Skilled Labour

0.6700

day

450.00

301.50 534.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

544.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

599.26

VAT

6% of Total

39.95

IT

4% of Total

26.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

734.69

665.84

Page: 1166 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.06.09.03

Detailed Analysis Brief Description of Item 2 With Aluminum sheet & 6mmx75mm size MS plate.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m Aluminium V-folded water stop sheet

0.2200

m2

640.00

140.80

MS plate (6mm thick) in sqm

0.0800

m2

3297.00

263.76

Mastic or bituminous sealing

1.0000

m

91.80

91.80

Skilled Labour

0.6700

day

450.00

301.50 797.86

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

813.82

10% Profit ( Add 10% on Subtotal-B) :

895.20

VAT

6% of Total

IT

4% of Total

59.68 39.79 Total:

5.06.10

Providing bearing joints fixed or free with 250mmx375mmx10mm MS shoe plate fitted in the truss angles with 16mm dia MS rod counter sunk, rivets and anchored to 250mmx375mmx10mm MS shoe plate by two Nos. 19mm dia MS ‘U’ rod embedded in the bed of the lintel around the reinforcement, cleaning and greasing the joints for all floors etc. all complete as per direction of the E-I-C.

each

MS Shoe Plate (250x375x10mm) MS Rod (Plain, 40 Grade) Counter sunk rivets Skilled Labour

14.5000

kg

80.00

1160.00

5.5000

kg

45.00

247.50

10.0000

each

5.94

59.40

3.0000

day

450.00

1350.00 2816.90

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2873.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3160.56

VAT

6% of Total

IT

4% of Total

210.70 140.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

994.67

3511.74

Page: 1167 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.07.01

Supplying and making door and window frames with seasoned wood of required size in/c painting two coats of coal tar to the surface in contact with wall, fitted and fixed in position and mending good any damage (All sizes of wood are finished) for all floors etc. all complete as per direction of the E-I-C.

5.07.01.01

Garjan wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Sundari/ Garzen

1.0500

m3

67580.00

70959.00

Carpenter

17.0000

day

680.00

11560.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

23.0000

day

470.00

10810.00 93329.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

4666.45

Subtotal-A1: Subtotal-B: Subtotal-C:

97995.45 99955.36

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

109950.89

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7330.06 4886.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

122167.66

Page: 1168 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.07.01.02

2 Jarul & local Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Jam/Jarul

1.0500

m3

65650.00

68932.50

Carpenter

17.0000

day

680.00

11560.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

23.0000

day

470.00

10810.00 91302.50

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

4565.13

Subtotal-A1: Subtotal-B: Subtotal-C:

95867.63 97784.98

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

107563.48

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7170.90 4780.60 Total:

5.07.01.03

Silkarai/Chikrashi wood

cum Sil Korai

1.0500

m3

88000.00

92400.00

Carpenter

17.0000

day

680.00

11560.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

23.0000

day

470.00

10810.00 114770.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

5738.50

Subtotal-A1: Subtotal-B: Subtotal-C:

120508.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

122918.67

10% Profit ( Add 10% on Subtotal-B) :

135210.54

VAT

6% of Total

IT

4% of Total

9014.04 6009.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

119514.97

150233.93

Page: 1169 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.07.01.04

2 Telsu wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Telsu

1.0500

m3

65000.00

68250.00

Carpenter

17.0000

day

680.00

11560.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

23.0000

day

470.00

10810.00 90620.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

4531.00

Subtotal-A1: Subtotal-B: Subtotal-C:

95151.00 97054.02

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

106759.42

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7117.29 4744.86 Total:

5.07.01.05

Teak Chambol wood

cum Teak chambol

1.0500

m3

110000.00

115500.00

Carpenter

17.0000

day

680.00

11560.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

23.0000

day

470.00

10810.00 137870.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

6893.50

Subtotal-A1: Subtotal-B: Subtotal-C:

144763.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

147658.77

10% Profit ( Add 10% on Subtotal-B) :

162424.65

VAT

6% of Total

IT

4% of Total

10828.31 7218.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

118621.58

180471.83

Page: 1170 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.07.01.06

2 Mehagoni/Shishu wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Mehagoni/ Shishu

1.0500

m3

59730.00

62716.50

Carpenter

17.0000

day

680.00

11560.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

23.0000

day

470.00

10810.00 85086.50

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

4254.33

Subtotal-A1: Subtotal-B: Subtotal-C:

89340.83 91127.64

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100240.41

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6682.69 4455.13 Total:

5.07.01.07

Jack Wood

cum Jack Wood

1.0500

m3

80540.00

84567.00

Carpenter

17.0000

day

680.00

11560.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

23.0000

day

470.00

10810.00 106937.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

5346.85

Subtotal-A1: Subtotal-B: Subtotal-C:

112283.85 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

114529.53

10% Profit ( Add 10% on Subtotal-B) :

125982.48

VAT

6% of Total

IT

4% of Total

8398.83 5599.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

111378.23

139980.53

Page: 1171 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.07.02

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing door frame with MS angle (38mmx 38mmx 6mm), fixing 250mm long 6 nos. of iron clamps of same size (one end bifurcated) with vertical members of the frame, fixing the frame in wall with cement concrete (1:2:4) in Portland Composite cement CEM II/AM, 42.5N), best quality sand (minimum FM1.8) and 20mm down well graded 1st class brick chips, mending good damages, fixing 6 nos. of 100mm size iron hinges with the vertical members of the frame for double leaf shutter, painting all iron faces in 2 coats over a coat of priming with enamel paint of approved colour and quality in/c cutting, sizing, welding for all floors, etc. all complete as per plan and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Mass concrete in floor (1:2:4) with cement, sand and brick chips ……….. (5.03.05.02)

0.0028

cum

6957.74

19.48

Painting of gauge on the body of structure with synthetic enamel paint as per specification etc…(6.011.01)

0.1600

sqm

85.70

13.71

MS Angle, Flat bar, Z bar

4.1600

kg

59.00

245.44

Steel hinge (100mm)

1.0900

each

120.00

130.80

Skilled Labour

0.1600

day

450.00

72.00 481.43

Subtotal-A: All other remaining costs like fabrication, welding

( +50.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

722.15 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

736.59

10% Profit ( Add 10% on Subtotal-B) :

810.25

VAT

6% of Total

54.02

IT

4% of Total

36.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

240.72

900.28

Page: 1172 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.07.03

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing door frame with MS angle (38mmx38mmx6mm), fixing, 250mm long 6 nos. of iron clamps of same size (one end bifurcated) with vertical members of the frame, fixing the frame in wall with cement concrete (1:2:4) in Portland Composite cement CEM II/AM, 42.5N), best quality sand (minimum FM1.8) and 20mm down well graded 1st class brick chips, mending good damages, fixing 3 nos. of 100mm size iron hinges with the vertical members of the frame for single leaf shutter, painting all iron faces in 2 coats over a coat of priming with enamel paint of approved colour and quality, in/c cutting, sizing, welding for all floors, etc. all complete as per plan and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Mass concrete in floor (1:2:4) with cement, sand and brick chips ……….. (5.03.05.02)

0.0028

cum

6957.74

19.48

Painting of gauge on the body of structure with synthetic enamel paint as per specification etc…(6.011.01)

0.1500

sqm

85.70

12.86

MS Angle, Flat bar, Z bar

4.1600

kg

59.00

245.44

Steel hinge (100mm)

1.0900

each

120.00

130.80

Skilled Labour

0.1600

day

450.00

72.00 480.58

Subtotal-A: All other remaining costs like fabrication, welding

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

624.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

637.24

10% Profit ( Add 10% on Subtotal-B) :

700.97

VAT

6% of Total

46.73

IT

4% of Total

31.15 Total:

5.07.04

144.17

778.85

Supplying and making well matured natural seasoned solid wood works in frames of roof truss of required length and size with wall plates as per design in/c supplying, fabricating, hoisting, scaffolding, fitting and fixing in position with bolts and nuts for all floors etc. all complete as per direction of the E-I-C. (All sizes of wood are finished).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1173 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.07.04.01

2 Garjan wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Sundari/ Garzen

1.0200

m3

67580.00

68931.60

35.0000

kg

65.00

2275.00

Carpenter

9.0000

day

680.00

6120.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

9.0000

day

470.00

4230.00

Nails/ Nut bolts/ Screw/ Spikes

81556.60

Subtotal-A: All other remaining costs

( +1.50 % on Subtotal-A )

1223.35

Subtotal-A1:

82779.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84435.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

92879.10

VAT

6% of Total

6191.94

IT

4% of Total

4127.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

103199.00

Page: 1174 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.07.04.02

2 jarul & Local Sal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Shal

1.0200

m3

75000.00

76500.00

35.0000

kg

65.00

2275.00

Carpenter

9.0000

day

680.00

6120.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

9.0000

day

470.00

4230.00

Nails/ Nut bolts/ Screw/ Spikes

89125.00

Subtotal-A: All other remaining costs

( +1.50 % on Subtotal-A )

1336.88

Subtotal-A1:

90461.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

92271.11 101498.22

VAT

6% of Total

6766.55

IT

4% of Total

4511.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

112775.80

Page: 1175 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.07.04.03

2 Silkaral (Ctg)/Chikrashi wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Sil Korai

1.0200

m3

88000.00

89760.00

35.0000

kg

65.00

2275.00

Carpenter

9.0000

day

680.00

6120.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

9.0000

day

470.00

4230.00

Nails/ Nut bolts/ Screw/ Spikes

102385.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1023.85

Subtotal-A1:

103408.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

105477.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

116024.73

VAT

6% of Total

7734.98

IT

4% of Total

5156.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

128916.37

Page: 1176 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.07.04.04

2 Telsu wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Telsu

1.0200

m3

65000.00

66300.00

35.0000

kg

65.00

2275.00

Carpenter

9.0000

day

680.00

6120.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

9.0000

day

470.00

4230.00

Nails/ Nut bolts/ Screw/ Spikes

78925.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

789.25

Subtotal-A1:

79714.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

81308.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

89439.39

VAT

6% of Total

5962.63

IT

4% of Total

3975.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

99377.10

Page: 1177 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.07.04.05

2 Mehagoni/Shishu wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Mehagoni/ Shishu

1.0200

m3

59730.00

60924.60

Carpenter

9.0000

day

680.00

6120.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

9.0000

day

470.00

4230.00

35.0000

kg

65.00

2275.00

Nails/ Nut bolts/ Screw/ Spikes

73549.60

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

735.50

Subtotal-A1:

74285.10

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

75770.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

83347.88

VAT

6% of Total

5556.53

IT

4% of Total

3704.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

92608.75

Page: 1178 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.07.04.06

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Jack Wood

1.0200

m3

80540.00

82150.80

Carpenter

9.0000

day

680.00

6120.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

9.0000

day

470.00

4230.00

35.0000

kg

65.00

2275.00

Nails/ Nut bolts/ Screw/ Spikes

94775.80

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

947.76

Subtotal-A1:

95723.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

97638.03 107401.83

VAT

6% of Total

7160.12

IT

4% of Total

4773.41 Total:

5.07.05

119335.37

Supplying and making well matured natural seasoned solid wooden hand rail of stair case or any where required length and size etc. in/c necessary moulding as per design, fitted and fixed in position with nut, bolts, screw etc for all floors etc. all complete as per direction of the E-IC.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1179 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.07.05.01

2 Silkarai/Chikrashi wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Sil Korai

1.0200

m3

88000.00

89760.00

Carpenter

27.0000

day

680.00

18360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

18.0000

day

470.00

8460.00 116580.00

Subtotal-A: All other remaining costs

( +.53 % on Subtotal-A )

617.87

Subtotal-A1:

117197.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

119541.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

131496.01

VAT

6% of Total

IT

4% of Total

8766.40 5844.27 Total:

5.07.05.02

Chittagong Teak wood

cum Chittagong Teak

1.0200

m3

140000.00

142800.00

Carpenter

27.0000

day

680.00

18360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

18.0000

day

470.00

8460.00 169620.00

Subtotal-A: All other remaining costs

( +.53 % on Subtotal-A )

898.99

Subtotal-A1: Subtotal-B: Subtotal-C:

170518.99 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

173929.37

10% Profit ( Add 10% on Subtotal-B) :

191322.30

VAT

6% of Total

IT

4% of Total

12754.82 8503.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

146106.68

212580.34

Page: 1180 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.07.05.03

2 Jarul Local Sal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Jam/Jarul

1.0200

m3

65650.00

66963.00

Carpenter

27.0000

day

680.00

18360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

18.0000

day

470.00

8460.00 93783.00

Subtotal-A: All other remaining costs

( +.53 % on Subtotal-A )

497.05

Subtotal-A1: Subtotal-B: Subtotal-C:

94280.05 96165.65

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

105782.22

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7052.15 4701.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

117535.80

Page: 1181 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.07.06

Detailed Analysis Brief Description of Item 2 Dismantling of existing/damaged steel structure and steel works of building or any structural works of any type manualy or any other means without any damages in structure for reuse (as possible) and sorting the dismantled materials disposal of unserviceable materials and stacking the serviceable materials properly for measurment for all floors, Cost of conveying, loading, transportation of unserviceable material accumulated during dismantling operation is included in this unit rate. The unserviceable material must be disposed at a safe place outside the site premises with minimum traffic disruption and the procuring entity will not provide any environmentally safe place for disposing the unserviceable materials.etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

MT

Skilled Labour

3.0300

day

450.00

1363.50

Ordinary Labour

5.0000

day

370.00

1850.00 3213.50

Subtotal-A: Cost of carriage, tools, plants & other remaining cost etc.

( +2.00 % on Subtotal-A )

64.27

Subtotal-A1:

3277.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3343.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3677.66

VAT

6% of Total

IT

4% of Total

245.18 163.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4086.29

Page: 1182 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.07.07

Detailed Analysis Brief Description of Item 2 Dismantling of existing/damaged timber structure and timber works of building or structural works of any type manualy or any other means without any damages in structure for reuse (as possible) and sorting the dismantled materials disposal of unserviceable materials and stacking the serviceable materials properly for measurment for all floors, Cost of conveying, loading, transportation of unserviceable material accumulated during dismantling operation is included in this unit rate. The unserviceable material must be disposed at a safe place outside the site premises with minimum traffic disruption and the procuring entity will not provide any environmentally safe place for disposing the unserviceable materials.etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Carpenter

2.0000

day

680.00

1360.00

Ordinary Labour

5.0000

day

370.00

1850.00 3210.00

Subtotal-A: Cost of carriage, tools, plants & other remaining cost etc.

( +2.00 % on Subtotal-A )

64.20

Subtotal-A1:

3274.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3339.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3673.65

VAT

6% of Total

IT

4% of Total

244.91 163.27 Total:

5.08.01

4081.84

Supplying, fitting and fixing 38mm thick well matured natural seasoned solid wooden door shutter (minimum 250mm wide plank) having top rail style of sections (100mmx38mm) lock rail (125mmx38mm) and bottom rail (225mmx38mm), closed joints and provided with best quality 4 nos. 100mm iron hinges, 2 nos. best quality 12mm dia 300mm and 225mm long iron tower and socket bolts, 2 nos. heavy type nickel plated handle, hinge cleats, buffer blocks and finished with sand papering for all floors etc. all complete as per direction of the E-I-C. (Single leaf door. All sizes of wood are finished).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1183 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.01.01

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0500

m3

80540.00

4027.00

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.6300

day

470.00

1236.10 6337.50

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +6.00 % on Subtotal-A )

380.25

Subtotal-A1:

6717.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6852.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7537.32

VAT

6% of Total

IT

4% of Total

502.49 334.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8374.80

Page: 1184 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.01.02

2 Gamari/Chapalish wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Gamari

0.0500

m3

55240.00

2762.00

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.6300

day

470.00

1236.10 5072.50

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +6.00 % on Subtotal-A )

304.35

Subtotal-A1:

5376.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5484.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6032.83

VAT

6% of Total

IT

4% of Total

402.19 268.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6703.14

Page: 1185 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.01.03

2 Teak Chambal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Teak chambol

0.0500

m3

110000.00

5500.00

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.6300

day

470.00

1236.10 7810.50

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +6.00 % on Subtotal-A )

468.63

Subtotal-A1:

8279.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8444.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9289.18

VAT

6% of Total

IT

4% of Total

619.28 412.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10321.32

Page: 1186 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.01.04

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0500

m3

140000.00

7000.00

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.6300

day

470.00

1236.10 9310.50

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.00 % on Subtotal-A )

465.53

Subtotal-A1:

9776.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9971.55 10968.70 731.25 487.50

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12187.44

Page: 1187 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.01.05

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0500

m3

59730.00

2986.50

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.6300

day

470.00

1236.10 5297.00

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.00 % on Subtotal-A )

264.85

Subtotal-A1:

5561.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5673.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6240.40

VAT

6% of Total

IT

4% of Total

416.03 277.35 Total:

5.08.02

6933.77

Supplying, fitting and fixing 38mm thick well matured natural seasoned wooden flush door shutters (minimum 250mm wide plank) having a frame of top, lock and bottom rail of sections (100mmx12mm) styles (100mmx38mm) covered with (100mmx12mm) plank, screwed to each face and provided with best quality 4 nos. 100mm iron hinges, 2 nos. heavy type nickel plated handles, hinge cleats, buffer blocks and finished with sand papering for all floors etc. all complete as per direction of the E-I-C. (Single leaf door. All sizes of wood are finished).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1188 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.02.01

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0420

m3

80540.00

3382.68

Carpenter

1.0500

day

680.00

714.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00 5083.68

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +7.00 % on Subtotal-A )

355.86

Subtotal-A1:

5439.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5548.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6103.16

VAT

6% of Total

IT

4% of Total

406.88 271.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6781.29

Page: 1189 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.02.02

2 Gamari & Chapalish wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Gamari

0.0420

m3

55240.00

2320.08

Carpenter

1.0500

day

680.00

714.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00 4021.08

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +7.00 % on Subtotal-A )

281.48

Subtotal-A1:

4302.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4388.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4827.47

VAT

6% of Total

IT

4% of Total

321.83 214.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5363.85

Page: 1190 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.02.03

2 Teak Chambal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Teak chambol

0.0420

m3

110000.00

4620.00

Carpenter

1.0500

day

680.00

714.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00 6321.00

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +6.00 % on Subtotal-A )

379.26

Subtotal-A1:

6700.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6834.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7517.69

VAT

6% of Total

IT

4% of Total

501.18 334.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8352.99

Page: 1191 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.02.04

2 Ctg. Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0420

m3

140000.00

5880.00

Carpenter

1.0500

day

680.00

714.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00 7581.00

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.00 % on Subtotal-A )

379.05

Subtotal-A1:

7960.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8119.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8931.18

VAT

6% of Total

IT

4% of Total

595.41 396.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9923.53

Page: 1192 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.02.05

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0420

m3

59730.00

2508.66

Carpenter

1.0500

day

680.00

714.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00 4209.66

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.00 % on Subtotal-A )

210.48

Subtotal-A1:

4420.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4508.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4959.40

VAT

6% of Total

IT

4% of Total

330.63 220.42 Total:

5.08.03

5510.44

Supplying, fitting and fixing 38mm thick well matured natural seasoned wooden panel door shutters (minimum 250mm wide plank), top, rail and styles of sections (100mmx38mm), lock rail (125mmx38mm) and bottom rail (225mmx38mm) paneling 38mm thick both sides raised, provided with best quality 6 nos. 100mm iron hinges, 2 nos. best quality 12mm dia 300mm and 225mm long iron tower and socket bolts 2 nos. heavy type nickel plated handle, hinge cleats, buffer blocks and finished with sand papering for all floors etc. all complete as per direction of the E-I-C. (Single/Double leaf. All sizes of wood are finished).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1193 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.03.01

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0540

m3

80540.00

4349.16

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 6952.36

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.00 % on Subtotal-A )

347.62

Subtotal-A1:

7299.98

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7445.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8190.58

VAT

6% of Total

IT

4% of Total

546.04 364.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9100.64

Page: 1194 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.03.02

2 Gamari/Chapalish wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Gamari

0.0540

m3

55240.00

2982.96

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 5586.16

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.50 % on Subtotal-A )

307.24

Subtotal-A1:

5893.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6011.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6612.39

VAT

6% of Total

IT

4% of Total

440.83 293.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7347.10

Page: 1195 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.03.03

2 Teak Chambal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Teak chambol

0.0540

m3

110000.00

5940.00

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 8543.20

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +4.80 % on Subtotal-A )

410.07

Subtotal-A1:

8953.27

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9132.34 10045.57 669.70 446.47

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11161.75

Page: 1196 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.03.04

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0540

m3

140000.00

7560.00

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 10163.20

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +3.60 % on Subtotal-A )

365.88

Subtotal-A1:

10529.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10739.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11813.62

VAT

6% of Total

IT

4% of Total

787.57 525.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13126.25

Page: 1197 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.03.05

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0540

m3

59730.00

3225.42

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 5828.62

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +3.60 % on Subtotal-A )

209.83

Subtotal-A1:

6038.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6159.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6775.14

VAT

6% of Total

IT

4% of Total

451.68 301.12 Total:

5.08.04

7527.93

Supplying, fitting and fixing 38mm thick well matured natural seasoned wooden panel door shutters (minimum 250mm wide plank) top rail and styles of sections (100mmx38mm) lock rail, (125mmx38mm) and bottom rail (225mmx38mm), paneling 25mm thick one side raised provided with best quality 6 nos. 100mm iron hinges, 2 nos. best quality 12mm dia 300mm and 225mm long iron tower and socket bolts 2 nos. heavy type nickel plated handles, hinge cleats, buffer blocks and finished with sand papering for all floors etc. all complete as per direction of the E-I-C. (Single/Double leaf. All sizes of wood are finished).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1198 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.04.01

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0460

m3

80540.00

3704.84

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 6308.04

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +6.00 % on Subtotal-A )

378.48

Subtotal-A1:

6686.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6820.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7502.28

VAT

6% of Total

IT

4% of Total

500.15 333.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8335.86

Page: 1199 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.04.02

2 Gamar/Chapalish wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Gamari

0.0460

m3

55240.00

2541.04

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 5144.24

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +6.30 % on Subtotal-A )

324.09

Subtotal-A1:

5468.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5577.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6135.46

VAT

6% of Total

IT

4% of Total

409.03 272.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6817.18

Page: 1200 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.04.03

2 Teak Chambal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Teak chambol

0.0460

m3

110000.00

5060.00

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 7663.20

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.50 % on Subtotal-A )

421.48

Subtotal-A1:

8084.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8246.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9071.01

VAT

6% of Total

IT

4% of Total

604.73 403.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10078.90

Page: 1201 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.04.04

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0460

m3

140000.00

6440.00

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 9043.20

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +4.20 % on Subtotal-A )

379.81

Subtotal-A1:

9423.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9611.47 10572.62 704.84 469.89

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11747.36

Page: 1202 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.04.05

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0460

m3

59730.00

2747.58

Carpenter

1.3400

day

680.00

911.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.6000

day

470.00

1692.00 5350.78

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +4.20 % on Subtotal-A )

224.73

Subtotal-A1:

5575.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5687.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6255.73

VAT

6% of Total

IT

4% of Total

417.05 278.03 Total:

5.08.05

6950.81

Supplying, fitting and fixing 38mm (finished) thick well matured natural seasoned wooden grooved panel flash door shutters (minimum 250mm wide plank) with top and middle rail (100mmx38mm), bottom rail (225mmx38mm) and style (100mmx38mm) size having vertical panels (100mmx38mm) in/c keeping (6mmx12mm) uniform groove all around and minimum 12mm grooved lap to each panel, providing 4 nos. best quality 100mm iron hinges, 12mm dia best quality 225mm and 300mm iron socket and tower bolts, 2 nos. heavy type best quality nickel plated handle, hinge cleats, wooden buffer blocks in/c supplying necessary nails and screws, preparing surface by sand papering for all floors etc. complete in all respect as per drawing and direction of the E-I-C. (Single leaf. All sizes of wood are finished).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1203 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.05.01

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0560

m3

80540.00

4510.24

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.4200

day

470.00

1607.40 7192.04

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.00 % on Subtotal-A )

359.60

Subtotal-A1:

7551.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7702.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8472.94

VAT

6% of Total

IT

4% of Total

564.86 376.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9414.38

Page: 1204 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.05.02

2 Gamari/Chapalish wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Gamari

0.0560

m3

55240.00

3093.44

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.4200

day

470.00

1607.40 5775.24

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +5.30 % on Subtotal-A )

306.09

Subtotal-A1:

6081.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6202.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6823.25

VAT

6% of Total

IT

4% of Total

454.88 303.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7581.39

Page: 1205 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.05.03

2 For Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0560

m3

140000.00

7840.00

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.4200

day

470.00

1607.40 10521.80

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +3.50 % on Subtotal-A )

368.26

Subtotal-A1:

10890.06

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11107.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12218.65

VAT

6% of Total

IT

4% of Total

814.58 543.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13576.28

Page: 1206 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.05.04

2 For Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0560

m3

59730.00

3344.88

Carpenter

1.5800

day

680.00

1074.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

3.4200

day

470.00

1607.40 6026.68

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +3.50 % on Subtotal-A )

210.93

Subtotal-A1:

6237.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6362.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6998.60

VAT

6% of Total

IT

4% of Total

466.57 311.05 Total:

5.08.06

7776.23

Supplying, fitting & fixing of flash door for internal use made of 36mm thick & 400 Kg/m3 density solid particle board with a solid well matured Garjan wooden frame (min. 250mm wide plank) having finished size (36mmx50mm) all around upon which 1.4mm thick veneer (total 2 nos. of veneers, one of 0.7mm horizontally and another of 0.7mm vertically) are pasted on each side by mechanized process and provided with best quality 4 nos. 100mm iron hinges, 2 nos. best quality 12mm dia 300mm and 225mm long iron tower and socket bolts, 2 nos. heavy type nickel plated handles, hinge cleats, buffer blocks for all floors etc. all complete as per direction of E-I-C (Single leaf door).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1207 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.06.01

2 Burma Teak Veneered

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Burma Teak veneered

1.0200

m2

1025.00

1045.50

Carpenter

0.1400

day

680.00

95.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2700

day

470.00

126.90 1267.60

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +7.00 % on Subtotal-A )

88.73

Subtotal-A1:

1356.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1383.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1521.80

VAT

6% of Total

IT

4% of Total

101.45 67.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1690.89

Page: 1208 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.06.02

2 Champa Veneered

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Champa veneered

1.0200

m2

608.00

620.16

Carpenter

0.1400

day

680.00

95.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2700

day

470.00

126.90 842.26

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +9.50 % on Subtotal-A )

80.01

Subtotal-A1:

922.27

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

940.72 1034.79 68.99 45.99

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1149.77

Page: 1209 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.06.03

2 Chapalish Veneered

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Chaplish veneered

1.0200

m2

910.00

928.20

Carpenter

0.1400

day

680.00

95.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2700

day

470.00

126.90 1150.30

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +9.80 % on Subtotal-A )

112.73

Subtotal-A1:

1263.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1288.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1417.12

VAT

6% of Total

IT

4% of Total

94.47 62.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1574.58

Page: 1210 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.06.04

2 Garjan Veneered

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Garjan veneered

1.0200

m2

757.00

772.14

Carpenter

0.1400

day

680.00

95.20

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2700

day

470.00

126.90 994.24

Subtotal-A: All other remaining costs covering all fittings like tower bolt, socket bolt, hatch bolt, hinges, handle, screws etc.

( +10.80 % on Subtotal-A )

Subtotal-A1:

1101.62

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1123.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1236.02

VAT

6% of Total

IT

4% of Total

82.40 54.93 Total:

5.08.07

107.38

1373.35

Manufacturing and supplying fitting fixing well matured natural seasoned wooden fixed louver shutters (min 250mm wide plank) having frame (62mmx125mm) and inner horizontal wooden louver (150mmx20mm) spaced @75mm c/c fixed with frame in grooves in/c cost of screws, nails, wooden bit, preparing the surface by sand papering for all floors etc complete in all respect as per drawing and direction of the E-I-C (All sizes of wood are finished).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1211 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.07.01

2 Chapallish & Gammari wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chaplish Wood

0.1030

m3

84500.00

8703.50

Nails/ Nut bolts/ Screw/ Spikes

1.2200

kg

65.00

79.30

Carpenter

1.2200

day

680.00

829.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 10185.80

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

101.86

Subtotal-A1:

10287.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10493.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11542.75

VAT

6% of Total

769.52

IT

4% of Total

513.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12825.28

Page: 1212 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.07.02

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.1030

m3

140000.00

14420.00

Nails/ Nut bolts/ Screw/ Spikes

1.2200

kg

65.00

79.30

Carpenter

1.2200

day

680.00

829.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 15902.30

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

159.02

Subtotal-A1:

16061.32

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16382.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18020.80

VAT

6% of Total

1201.39

IT

4% of Total

800.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

20023.12

Page: 1213 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.07.03

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.1030

m3

59730.00

6152.19

Nails/ Nut bolts/ Screw/ Spikes

1.2200

kg

65.00

79.30

Carpenter

1.2200

day

680.00

829.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 7634.49

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

76.34

Subtotal-A1:

7710.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7865.05

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8651.56

VAT

6% of Total

576.77

IT

4% of Total

384.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9612.84

Page: 1214 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.07.04

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.1030

m3

80540.00

8295.62

Nails/ Nut bolts/ Screw/ Spikes

1.2200

kg

65.00

79.30

Carpenter

1.2200

day

680.00

829.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 9777.92

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

97.78

Subtotal-A1:

9875.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10073.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11080.53

VAT

6% of Total

738.70

IT

4% of Total

492.47 Total:

5.08.08

12311.71

Supplying, fitting and fixing well matured natural seasoned wooden glazed ventilator louver shutters (min 250mm wide plunk) having wooden outer frame of finished section (62mmx125mm) vertical divider and inner horizontal glazed louver (local) of size (150mmx6mm) fixed in frame @112mm c/c by cutting groves in the frame in/c cost of screw, wooden bit, sand papering, cutting glass to required size for all floors, etc. all complete as per design drawing and direction of the E-I-C and as per standard practice (All sizes of wood are finished)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1215 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.08.01

2 Chapalish & Gammari wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chaplish Wood

0.0420

m3

84500.00

3549.00

5mm thick glass

1.1700

m2

700.00

819.00

Carpenter

0.8100

day

680.00

550.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 5492.20

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

54.92

Subtotal-A1:

5547.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5658.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6223.87

VAT

6% of Total

414.92

IT

4% of Total

276.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6915.41

Page: 1216 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.08.02

2 Teak Chambal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Teak chambol

0.0420

m3

110000.00

4620.00

5mm thick glass

1.1700

m2

700.00

819.00

Carpenter

0.8100

day

680.00

550.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 6563.20

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

65.63

Subtotal-A1:

6628.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6761.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7437.55

VAT

6% of Total

495.84

IT

4% of Total

330.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8263.94

Page: 1217 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.08.03

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0420

m3

140000.00

5880.00

5mm thick glass

1.1700

m2

700.00

819.00

Carpenter

0.8100

day

680.00

550.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 7823.20

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

78.23

Subtotal-A1:

7901.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8059.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8865.41

VAT

6% of Total

591.03

IT

4% of Total

394.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9850.45

Page: 1218 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.08.04

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0420

m3

59730.00

2508.66

5mm thick glass

1.1700

m2

700.00

819.00

Carpenter

0.8100

day

680.00

550.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 4451.86

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

44.52

Subtotal-A1:

4496.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4586.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5044.94

VAT

6% of Total

336.33

IT

4% of Total

224.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5605.49

Page: 1219 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.08.05

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0420

m3

80540.00

3382.68

5mm thick glass

1.1700

m2

700.00

819.00

Carpenter

0.8100

day

680.00

550.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.2200

day

470.00

573.40 5325.88

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

53.26

Subtotal-A1:

5379.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5486.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6035.39

VAT

6% of Total

402.36

IT

4% of Total

268.24 Total:

5.08.09

6705.99

Supply, fitting and fixing 38mm thick well matured wooden glazed door shutters (min 250mm wide plunk) having styles and rails of section (150mmx38mm) and 5mm thick glass panes fitted and fixed with wooden batten, putty and nails in/c supplying, fitting and fixing 50mm dia best quality round door lock, 12mm dia 300mm long iron tower bolt and 4 nos. 100mm long iron hinges to each shutters hinged cleats, buffer blocks, finished with necessary sand papering and putty works for all floors etc. all complete as per direction of the E-I-C and standard practice. (All sizes of wood are finished)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1220 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.09.01

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0270

m3

140000.00

3780.00

5mm thick glass

0.8200

m2

700.00

574.00

Carpenter

1.8200

day

680.00

1237.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.8200

day

470.00

855.40

Skilled Labour

0.6100

day

450.00

274.50 6721.50

Subtotal-A: All other remaining costs covering fittings like lock, tower bolt, hinges, handle, screws etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

7528.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7678.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8446.51

VAT

6% of Total

563.10

IT

4% of Total

375.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

806.58

9385.01

Page: 1221 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.09.02

2 Silkara wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sil Korai

0.0270

m3

88000.00

2376.00

5mm thick glass

0.8200

m2

700.00

574.00

Carpenter

1.8200

day

680.00

1237.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.8200

day

470.00

855.40

Skilled Labour

0.6100

day

450.00

274.50 5317.50

Subtotal-A: All other remaining costs covering fittings like lock, tower bolt, hinges, handle, screws etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

6061.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6183.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6801.51

VAT

6% of Total

453.43

IT

4% of Total

302.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

744.45

7557.23

Page: 1222 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.09.03

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0270

m3

59730.00

1612.71

5mm thick glass

0.8200

m2

700.00

574.00

Carpenter

1.8200

day

680.00

1237.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.8200

day

470.00

855.40

Skilled Labour

0.6100

day

450.00

274.50 4554.21

Subtotal-A: All other remaining costs covering fittings like lock, tower bolt, hinges, handle, screws etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

5191.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5295.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5825.20

VAT

6% of Total

388.35

IT

4% of Total

258.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

637.59

6472.44

Page: 1223 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.09.04

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0270

m3

80540.00

2174.58

5mm thick glass

0.8200

m2

700.00

574.00

Carpenter

1.8200

day

680.00

1237.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.8200

day

470.00

855.40

Skilled Labour

0.6100

day

450.00

274.50 5116.08

Subtotal-A: All other remaining costs covering fittings like lock, tower bolt, hinges, handle, screws etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

5832.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5948.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6543.88

VAT

6% of Total

436.26

IT

4% of Total

290.84 Total:

5.08.10

716.25

7270.97

Supplying, fitting and fixing 38mm thick well matured natural seasoned wooden glazed window shutters (min 250mm wide plank) having horizontal and vertical sections (87mmx38mm) and sash bar (38mmx38mm) fitted with 3mm thick glass panes with putty, nails and provided with best quality 4 nos. 75mm long iron hinges, 2 nos. best quality 12mm dia 250mm and 150mm long iron tower and socket bolts, nickel plated handles, 225mm long catch hooks or hinges cleats, buffer blocks and finished with sand papering for all floors etc. all complete as per direction of the E-I-C. (All sizes of wood are finished)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1224 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.10.01

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0350

m3

80540.00

2818.90

3mm thick glass

0.6200

m2

380.00

235.60

Carpenter

1.3700

day

680.00

931.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.9600

day

470.00

921.20

Skilled Labour

0.5000

day

450.00

225.00 5132.30

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handles, catch hocks, screws etc.

( +6.00 % on Subtotal-A )

307.94

Subtotal-A1: Subtotal-B: Subtotal-C:

5440.24 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5549.04

10% Profit ( Add 10% on Subtotal-B) :

6103.95

VAT

6% of Total

IT

4% of Total

406.93 271.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6782.16

Page: 1225 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.10.02

2 Gamari & Chappalish wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Gamari

0.0350

m3

55240.00

1933.40

3mm thick glass

0.6200

m2

380.00

235.60

Carpenter

1.3700

day

680.00

931.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.9600

day

470.00

921.20

Skilled Labour

0.5000

day

450.00

225.00 4246.80

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handles, catch hocks, screws etc.

( +6.00 % on Subtotal-A )

254.81

Subtotal-A1: Subtotal-B: Subtotal-C:

4501.61 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4591.64

10% Profit ( Add 10% on Subtotal-B) :

5050.80

VAT

6% of Total

IT

4% of Total

336.72 224.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5612.00

Page: 1226 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.10.03

2 Teak Chambal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Teak chambol

0.0350

m3

110000.00

3850.00

3mm thick glass

0.6200

m2

380.00

235.60

Carpenter

1.3700

day

680.00

931.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.9600

day

470.00

921.20

Skilled Labour

0.5000

day

450.00

225.00 6163.40

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handles, catch hocks, screws etc.

( +6.00 % on Subtotal-A )

369.80

Subtotal-A1: Subtotal-B: Subtotal-C:

6533.20 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6663.87

10% Profit ( Add 10% on Subtotal-B) :

7330.25

VAT

6% of Total

IT

4% of Total

488.68 325.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8144.73

Page: 1227 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.10.04

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0350

m3

140000.00

4900.00

3mm thick glass

0.6200

m2

380.00

235.60

Carpenter

1.3700

day

680.00

931.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.9600

day

470.00

921.20

Skilled Labour

0.5000

day

450.00

225.00 7213.40

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handles, catch hocks, screws etc.

( +6.00 % on Subtotal-A )

432.80

Subtotal-A1: Subtotal-B: Subtotal-C:

7646.20 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7799.13

10% Profit ( Add 10% on Subtotal-B) :

8579.04

VAT

6% of Total

IT

4% of Total

571.94 381.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9532.27

Page: 1228 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.10.05

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0350

m3

59730.00

2090.55

3mm thick glass

0.6200

m2

380.00

235.60

Carpenter

1.3700

day

680.00

931.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.9600

day

470.00

921.20

Skilled Labour

0.5000

day

450.00

225.00 4403.95

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handle, catch hooks, screws etc.

( +6.00 % on Subtotal-A )

264.24

Subtotal-A1: Subtotal-B: Subtotal-C:

4668.19 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4761.55

10% Profit ( Add 10% on Subtotal-B) :

5237.71

VAT

6% of Total

IT

4% of Total

349.18 232.79 Total:

5.08.11

5819.67

Supplying, fitting and fixing 38mm thick well matured wooden window shutter (min 250mm wide plank) one third glazed and 38mm thick two third both sides raised paneling having horizontal and vertical sections (87mmx38mm) and sash bars (38mmx38mm) fitted with 3mm thick glass panes with putty and nails and provided with best quality 4 nos. 75mm long iron hinges, 2 nos. best quality 12mm dia 250mm and 150mm long iron tower and socket bolts, nickel plated handles, 225mm long catch hooks or hinged cleats, buffer blocks and with sand papering for all floors etc. all complete as per direction of the E-I-C. (All sizes of wood are finished)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1229 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.11.01

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0630

m3

80540.00

5074.02

3mm thick glass

0.3400

m2

380.00

129.20

Carpenter

1.4700

day

680.00

999.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00

Skilled Labour

0.2000

day

450.00

90.00 7279.82

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handles, catch hocks, screws etc.

( +4.00 % on Subtotal-A )

291.19

Subtotal-A1: Subtotal-B: Subtotal-C:

7571.01 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7722.43

10% Profit ( Add 10% on Subtotal-B) :

8494.68

VAT

6% of Total

IT

4% of Total

566.31 377.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9438.53

Page: 1230 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.11.02

2 Gammari & Chappalish wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Gamari

0.0630

m3

55240.00

3480.12

3mm thick glass

0.3400

m2

380.00

129.20

Carpenter

1.4700

day

680.00

999.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00

Skilled Labour

0.2000

day

450.00

90.00 5685.92

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handles, catch hocks, screws etc.

( +4.00 % on Subtotal-A )

227.44

Subtotal-A1: Subtotal-B: Subtotal-C:

5913.36 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6031.62

10% Profit ( Add 10% on Subtotal-B) :

6634.79

VAT

6% of Total

IT

4% of Total

442.32 294.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7371.98

Page: 1231 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.11.03

2 Teak Chambal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Teak chambol

0.0630

m3

110000.00

6930.00

3mm thick glass

0.3400

m2

380.00

129.20

Carpenter

1.4700

day

680.00

999.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00

Skilled Labour

0.2000

day

450.00

90.00 9135.80

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handles, catch hocks, screws etc.

( +3.50 % on Subtotal-A )

319.75

Subtotal-A1: Subtotal-B: Subtotal-C:

9455.55 9644.66

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10609.13

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

707.28 471.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11787.92

Page: 1232 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.11.04

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0630

m3

140000.00

8820.00

3mm thick glass

0.3400

m2

380.00

129.20

Carpenter

1.4700

day

680.00

999.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00

Skilled Labour

0.2000

day

450.00

90.00 11025.80

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handles, catch hocks, screws etc.

( +3.00 % on Subtotal-A )

330.77

Subtotal-A1: Subtotal-B: Subtotal-C:

11356.57 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11583.71

10% Profit ( Add 10% on Subtotal-B) :

12742.08

VAT

6% of Total

IT

4% of Total

849.47 566.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14157.86

Page: 1233 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.11.05

2 Mehagoni wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Mehagoni/ Shishu

0.0630

m3

59730.00

3762.99

3mm thick glass

0.3400

m2

380.00

129.20

Carpenter

1.4700

day

680.00

999.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.1000

day

470.00

987.00

Skilled Labour

0.2000

day

450.00

90.00 5968.79

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, handle, catch hooks, screws etc.

( +3.00 % on Subtotal-A )

179.06

Subtotal-A1: Subtotal-B: Subtotal-C:

6147.85 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6270.81

10% Profit ( Add 10% on Subtotal-B) :

6897.89

VAT

6% of Total

IT

4% of Total

459.86 306.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7664.32

Page: 1234 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.12.01

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing steel glazed window shutter with frames as per design having angle section (25mmx25mmx5mm) for chowkat and shutters and ‘T’ section (50mmx25mmx5mm) used for vertical member and F.I. bar (26mmx5mm) for making box (two angle combining) and ‘T’ (25mmx19mmx5mm) used for glass divider etc. in/c all cost of charges by welding, reverting, etc. supplying all essential fittings like iron hinges, plate handle, pin-stopper, adjustable cleat and clamps fitting and fixing the frame in/c supplying, fitting, fixing 3mm thick glass panes by pucca putty and painting the window with two coats of synthetic enamel paint over a coat of anticorrosive priming, making necessary holes in walls and RCC works and necessary filling with Cement Concrete (1:2:4) and mending good the damages in/c all cost of carriage and labour for fittings, fixing for all floors, etc. all complete as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

44.0000

kg

59.00

2596.00

3mm thick glass

1.0000

m2

380.00

380.00

Re-bar Fabricator

0.5000

day

570.00

285.00

Skilled Labour

0.7700

day

450.00

346.50 3607.50

Subtotal-A: All other remaining costs covering fittings like handles, cleats, hinges, lock, all workshop charges, synthetic enamel painting, etc.

( +35.00 % on Subtotal-A )

Subtotal-A1:

4870.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4967.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5464.28

VAT

6% of Total

364.29

IT

4% of Total

242.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1262.63

6071.42

Page: 1235 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.12.02

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing combined steel window shutter, frames and grill welded together as per drawing & design having requisite Nos. of vertical and horizontal standard MS (19mmx19mmx3mm) ‘Z’ section for shutter and MS flat bar all around (25mmx4.5mm) and (19mmx3mm), 10mm square bar as grill welded horizontally @ 100mm c/c, only catch locking handle position gap should 125mm, at inner face of window frame with F.I. clamp 75mmx3mm duly embedded with Cement Concrete (1:2:4:) and mending good the damages in/c all cost of charges for fabrication and manufacture by welding, riveting, etc. supplying all essential fittings like stopper, handle, 3 nos catch hook 300mm long adjustable iron cleat, 50mm long pin hinge in/c supplying, fitting, fixing 18 BWG M.S. sheet in position welded to steel shutter with Tee stiffener (2 nos.) made with 25mm and 19mm flat bars fitted to shutter frame in Two equal part and upper part should be provided with 5mm clear glass, vertically in each shutter panel and putty and painting the window with two coats of synthetic enamel paint over a coat of anticorrosive priming, , etc for all floors. all complete as per direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

18.0000

kg

59.00

MS Square bar 10 mm X 10 mm

6.8580

kg

52.00

356.62

Re-bar Fabricator

0.4500

day

570.00

256.50

Skilled Labour

0.2500

day

450.00

112.50

18/20/22 BWG MS Sheet/plate

4.5800

kg

70.00

320.60

5mm thick glass

0.2090

m2

700.00

146.30 2254.52

Subtotal-A: All other cost covering workshop etc.

( +22.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

495.99 2750.51

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2805.52

10% Profit ( Add 10% on Subtotal-B) :

3086.07

VAT

6% of Total

IT

4% of Total

205.74 137.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1062.00

3428.97

Page: 1236 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.13

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing steel glazed window shutter with frames as per design having ‘Z’ section (19mmx19mmx19mmx3mm) in frame and ‘T’ section (19mmx19mmx3mm) for horizontal dividers of shutters and F.I. bar (25mmx3mm) for middle vertical members of frame in/c all cost of charges for fabrication and manufacture by welding, riveting, etc. supplying all essential fittings like stopper, handle, 300mm long adjustable iron cleats, 50mm long pin hinges, 150mm long clamps for fitting frame in/c supplying, fitting, fixing 3mm thick glass panes by putty and painting the window with two coats of synthetic enamel paint over a coat of anticorrosive priming, making necessary holes in wall and RCC work as necessary, filling with Cement Concrete (1:2:4:) and mending good the damages for all floors, etc. all complete as per direction of the E-I-C and as per drawing and design.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

22.0000

kg

59.00

1298.00

3mm thick glass

1.0000

m2

380.00

380.00

Re-bar Fabricator

0.3000

day

570.00

171.00

Skilled Labour

0.5800

day

450.00

261.00 2110.00

Subtotal-A: All other remaining costs covering fittings like handles, cleats, hinges, lock, all workshop charges, synthetic enamel painting, etc.

( +51.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3186.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3249.82

10% Profit ( Add 10% on Subtotal-B) :

3574.80

VAT

6% of Total

IT

4% of Total

238.32 158.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1076.10

3972.00

Page: 1237 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.14.01

Detailed Analysis Brief Description of Item 2 Manufacturing, supplying, fitting and fixing of fixed glazed frame with outer member of ‘Z’ section (19mmx19mmx19mmx3mm) and vertical and horizontal dividers ‘T’ section (19mmx19mmx3mm) in/c all cost of fabrication and welding, supplying and fixing of 150mm long angle clamps with one end bifurcated (19mmx19mmx3mm) of required nos. with the frame fixing the frame in wall with cement concrete (1:2:4) on making necessary grooves, supplying and fixing of 3mm thick glass panes with putty, mending good all damages, painting iron faces with two coats of synthetic enamel paint of approved colour and quality over a coat of anti-corrosive priming for all floors, etc. all complete as per plan and direction of the E-I-C. (the item is meant for stair case and over partition wall etc.).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

11.0000

kg

59.00

649.00

3mm thick glass

1.0000

m2

380.00

380.00

Re-bar Fabricator

0.4000

day

570.00

228.00

Skilled Labour

0.2500

day

450.00

112.50 1369.50

Subtotal-A: All other remaining costs covering workshop charges, synthetic enamel painting, CC (1:2:4) etc.

( +65.00 % on Subtotal-A )

Subtotal-A1:

2259.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2304.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2535.36

VAT

6% of Total

IT

4% of Total

169.02 112.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

890.18

2817.06

Page: 1238 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.14.02

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing steel glazed sky light frame (Stair Back fixed Window) at stairs as per design having ‘T’ section made with flat bar 25mmx3mm as base and 19mmx3mm flat bar as perpendicular at mid of base flat bar welded 200mm c/c grid and Outer frame having 25mmx25mmx3mm MS angle in/c all cost of charges for fabrication and manufacture by welding, riveting, etc. supplying all essential fittings like 150mm long clamps for fitting frame in/c supplying, fitting, fixing 5mm thick glass panes at grid opening by putty and painting the sky light with two coats of synthetic enamel paint over a coat of anticorrosive priming, making necessary holes in wall and RCC work as necessary, filling with CC (1:2:4:) and mending good the damages for all floors, etc. all complete as per direction of the E-I-C and as per drawing and design.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

10.9510

kg

59.00

646.11

5mm thick glass

1.0000

m2

700.00

700.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00 1848.61

Subtotal-A: All other Cost Covering Bends etc.

( +.00 % on Subtotal-A ) ( +21.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2236.82 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2281.55

10% Profit ( Add 10% on Subtotal-B) :

2509.71

VAT

6% of Total

IT

4% of Total

167.31 111.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

0.00 388.21

2788.57

Page: 1239 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.15

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing steel window shutter with frames & grill as per drawing & design having requisite Nos. of vertical and horizontal standard MS angle (19mmx19mmx3mm) and ‘Z’ section (19mmx19mmx19mmx 3mm) for shutter and MS flat bar (25mmx4.5mm) and (19mmx3mm) and 10mmx10mm square bar welded horizontally @ 125mm at inside face of frame of window shutter with F.I. clamp 75mmx3mm duly embedded in Cement Concrete (1:2:4:) and mending good the damages in/c finishing the intersecting points by filling with all cost of charges for fabrication and manufacture by welding, riveting, etc. supplying all essential fittings like stopper, handle, 3 nos catch hooks, 300mm long adjustable iron cleats, 50mm long pin hinges, 150mm long clamps for fitting frame in/c supplying, fitting, fixing 22 BWG M.S. sheet in position welded to steel shutter with (19mmx3mm) MS flat bar stiffener and putty and painting the window with two coats of synthetic enamel paint over a coat of anticorrosive priming, , etc for all floors. all complete as per direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

11.0000

MS Square bar 10 mm X 10 mm

kg

59.00

13.6300

kg

52.00

708.76

Re-bar Fabricator

0.4500

day

570.00

256.50

Skilled Labour

0.2500

day

450.00

112.50

18/20/22 BWG MS Sheet/plate

6.1900

kg

70.00

433.30 2160.06

Subtotal-A: Workshop charges with 18gauge sheet, synthetic enamel painting, welding, incidental charges and overhead, etc.

( +22.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

475.21

2635.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2687.98

10% Profit ( Add 10% on Subtotal-B) :

2956.78

VAT

6% of Total

IT

4% of Total

197.12 131.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

649.00

3285.31

Page: 1240 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.16

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing steel window shutter with frames & grill as per drawing & design having requisite Nos. of vertical and horizontal standard MS angle (19mmx19mmx3mm) and ‘Z’ section (19mmx19mmx19mmx 3mm) for shutter and MS flat bar (25mmx4.5mm) and (19mmx3mm) and 10mmx10mm square bar welded horizontally @ 125mm at inside face of frame of window shutter with F.I. clamp 75mmx3mm duly embedded in Cement Concrete (1:2:4:) and mending good the damages in/c finishing the intersecting points by filling with all cost of charges for fabrication and manufacture by welding, riveting, etc. supplying all essential fittings like stopper, handle, 3 nos catch hooks, 300mm long adjustable iron cleats, 50mm long pin hinges, 150mm long clamps for fitting frame in/c fitting, fixing provision of 3mm clear glass panes in position with putty to steel shutter and painting the window with two coats of synthetic enamel paint over a coat of anticorrosive priming, , etc for all floors. all complete as per direction of the E-I-C (Rate is excluding cost of glass panes)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

11.0000

kg

59.00

649.00

MS Square bar 10 mm X 10 mm

13.6000

kg

52.00

707.20

Re-bar Fabricator

0.4500

day

570.00

256.50

Skilled Labour

0.2500

day

450.00

112.50 1725.20

Subtotal-A: Workshop charges with putty, synthetic enamel painting, welding, incidental charges and overhead, etc.

( +22.00 % on Subtotal-A )

Subtotal-A1:

2104.74

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2146.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2361.52

VAT

6% of Total

IT

4% of Total

157.43 104.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

379.54

2623.91

Page: 1241 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.17

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing distortion free 3mm thick clear glass of approved quality in steel windows in/c cost of fitting, fixing all necessary accessories and putty for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

3mm thick glass

1.0000

m2

380.00

380.00

Skilled Labour

0.6200

day

450.00

279.00 659.00

Subtotal-A: All other remaining costs covering as putty etc.

( +2.00 % on Subtotal-A )

13.18

Subtotal-A1: Subtotal-B: Subtotal-C:

672.18 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

685.62

10% Profit ( Add 10% on Subtotal-B) :

754.19

VAT

6% of Total

IT

4% of Total

50.28 33.52 Total:

5.08.18

837.98

Supplying, fitting and fixing 25mm thick wooden fly proof wire netting window shutter with vertical and horizontal style (75mmx25mm) and sash bar (38mmx25mm) provided with 24 BWG GI wire netting of 20 mesh, fitted and fixed with shutter by 12mmx12mm wooden bit, screws, nails etc. in/c supply of all necessary fittings such as 2 nos. 150mm long brass tower and socket bolt of best quality, 4 nos. 75mm long brass hinges, heavy type 2 nos. 150mm long catch hook and 2 nos. 100mm long brass handle in/c fitting and fixing the same in position with frame with supply of necessary screws and nails etc. all complete as per direction of E-I-C. (Double leaf. All sizes of wood are finished)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1242 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.18.01

2 Jack wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Jack Wood

0.0230

m3

80540.00

1852.42

20 Mesh 24 BWG GI wire net

0.6800

m2

144.46

98.23

Carpenter

1.7500

day

680.00

1190.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4600

day

470.00

216.20 3356.85

Subtotal-A: All other remaining costs covering fittings like tower and sockets bolts, hinges, handles, catch hocks, etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4028.22 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4108.79

10% Profit ( Add 10% on Subtotal-B) :

4519.67

VAT

6% of Total

IT

4% of Total

301.31 200.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

671.37

5021.85

Page: 1243 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.18.02

2 Teak Chambal wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Teak chambol

0.0230

m3

110000.00

2530.00

20 Mesh 24 BWG GI wire net

0.6800

m2

144.46

98.23

Carpenter

1.7500

day

680.00

1190.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4600

day

470.00

216.20 4034.43

Subtotal-A: All other remaining costs covering fittings like tower and sockets bolts, hinges, handles, catch hocks, etc.

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4760.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4855.84

10% Profit ( Add 10% on Subtotal-B) :

5341.43

VAT

6% of Total

IT

4% of Total

356.10 237.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

726.20

5934.92

Page: 1244 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.08.18.03

2 Chittagong Teak wood

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Chittagong Teak

0.0230

m3

140000.00

3220.00

20 Mesh 24 BWG GI wire net

0.6800

m2

144.46

98.23

Carpenter

1.7500

day

680.00

1190.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4600

day

470.00

216.20 4724.43

Subtotal-A: All other remaining costs covering fittings like tower and sockets bolts, hinges, handles, catch hocks, etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

5433.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5541.76

10% Profit ( Add 10% on Subtotal-B) :

6095.94

VAT

6% of Total

IT

4% of Total

406.40 270.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

708.66

6773.26

Page: 1245 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.19

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 25mm thick well matured Jack wood door and window shutters (min 250mm wide plunk) having ‘Z’ battens (75mmx25mm) provided with best quality 3 nos. 100mm long iron hinges, 2 nos. best quality 12mm dia 300mm and 225mm long iron tower and socket bolts, hinged cleats, buffer blocks and finished with sand papering for all floors etc. all complete as per direction of the E-IC. (All sizes of wood are finished).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Jack Wood

0.0420

m3

80540.00

3382.68

Carpenter

1.1200

day

680.00

761.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.5600

day

470.00

733.20 4877.48

Subtotal-A: All other remaining costs covering fittings like tower and socket bolt, hinges, rings, screws etc.

( +5.00 % on Subtotal-A )

243.87

Subtotal-A1:

5121.35

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5223.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5746.16

VAT

6% of Total

383.08

IT

4% of Total

255.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6384.62

Page: 1246 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.08.20

2 Supplying fitting and fixing steel door shutter with 18 BWG MS sheet/plain plate hinged to RCC columns reinforcement with 38mmx38mmx5mm MS Angle and 25mmx6mm flat bar stiffener etc. all complete as per drawing and direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

18/20/22 BWG MS Sheet/plate MS Angle, Flat bar, Z bar

9.9500

kg

70.00

696.50

25.0000

kg

59.00

1475.00

19mm dia 300mm long brass hasp bolt

1.0000

each

150.00

150.00

254mm long Tower Bolt (Iron)

1.0000

each

35.00

35.00

Red Oxide

0.0920

kg

197.00

18.12

Mason

0.6000

day

550.00

330.00

Skilled Labour

0.6000

day

450.00

270.00

Electrode

0.2000

pkt

810.00

162.00

H.C. of Welding Machine

0.0100

day

500.00

5.00 3141.62

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3204.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3524.90

VAT

6% of Total

IT

4% of Total

234.99 156.66 Total:

5.08.21

Extra cost for using brass or Stainless Steel fittings in place of iron fittings in doors and windows for all floors

5.08.21.1

For Doors

sqm

5.08.21.2

For Windows

sqm

Note : Rates of all items should be inclusive of all supply and carriage.

3916.56

Page: 1247 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.24

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing best quality foreign made hydraulic door closer (big size) including all necessary tools and accessories etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Hydraulic door closer (big size) (king brand

1.0000

each

1700.00

1700.00

Carpenter

0.2000

day

680.00

136.00 1836.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

18.36

Subtotal-A1:

1854.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1891.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2080.59

VAT

6% of Total

138.71

IT

4% of Total

92.47 Total:

5.08.25

Supplying, fitting and fixing best quality heavy type 19mm dia 300mm long brass hasp bolt in/c cutting grooves in door shutter and frames etc. all complete as per direction of the E-I-C.

each

19mm dia 300mm long brass hasp bolt

1.0000

each

150.00

150.00

Carpenter

0.0700

day

680.00

47.60 197.60

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.98

Subtotal-A1:

199.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

203.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

223.92

VAT

6% of Total

14.93

IT

4% of Total

9.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2311.77

248.80

Page: 1248 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.08.26

Supplying fitting, fixing of UPVC hollow or solid plastic door shutter having specific gravity 1.35-1.45, thickness 1.7 mm - 2.2 mm and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacturer standards or ASTM, BS/ISO/IS standards of different sizes fitted fixed with uPVC plastic door frame weighing 5.82 kg/m2 with at least 3 Nos Stainless Steel hinges fitted with min 64 Nos of 3.17 mm - 3.97 mm dia 12.7 mm long rivets, 12 Nos 25.4 mm Stainless Steel screws. 9.38 mm dia, 150 mm long Stainless Steel tower bolts 2 Nos, 146 mm long Stainless Steel handle fitted with rivet, fitted with 2 Nos of G.I inner joint 234.95 mm x 127 mm clamp, 76.2 mm x 57.15 mm, 25 mm dia 1 no Stainless Steel haspbolt, special type round rack, carrying the same to site and local carriage etc. all complete as per direction of the E-I-C.

5.08.26.01

760mmx1980mm uPVC plastic shutter (hollow)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Hollow shutter

1.4000

sqm

767.00

1073.80

MS Rod (Plain, 40 Grade)

2.7200

kg

45.00

122.40

Rivet (for aluminium works)

36.0000

each

0.30

10.80

SS Screw (40 mm long)

24.0000

each

4.50

108.00

SS Tower bolt

2.0000

each

120.00

240.00

SS handle

2.0000

each

75.00

150.00

Lock and Key

1.0000

set

150.00

150.00

Carpenter

0.6000

day

680.00

408.00 2263.00

Subtotal-A: Carrying, fitting, fixing, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2489.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2539.09

10% Profit ( Add 10% on Subtotal-B) :

2792.99

VAT

6% of Total

IT

4% of Total

186.20 124.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

226.30

3103.33

Page: 1249 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.26.02

Detailed Analysis Brief Description of Item 2 760mmx2130mm uPVC plastic shutter (solid)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Solid shutter

1.4700

sqm

767.00

1127.49

MS Rod (Plain, 40 Grade)

2.9000

kg

45.00

130.50

Rivet (for aluminium works)

36.0000

each

0.30

10.80

SS Screw (40 mm long)

24.0000

each

4.50

108.00

SS Tower bolt

2.0000

each

120.00

240.00

SS handle

1.0000

each

75.00

75.00

Lock and Key

1.0000

set

150.00

150.00

Carpenter

0.5000

day

680.00

340.00 2181.79

Subtotal-A: Carrying, fitting, fixing, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2399.97 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2447.97

10% Profit ( Add 10% on Subtotal-B) :

2692.77

VAT

6% of Total

IT

4% of Total

179.52 119.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

218.18

2991.96

Page: 1250 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.26.03

Detailed Analysis Brief Description of Item 2 910mmx2130mm uPVC plastic shutter (hollow)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Hollow shutter

1.6400

sqm

767.00

1257.88

MS Rod (Plain, 40 Grade)

2.3900

kg

45.00

107.55

Rivet (for aluminium works)

36.0000

each

0.30

10.80

SS Screw (40 mm long)

24.0000

each

4.50

108.00

SS Tower bolt

2.0000

each

120.00

240.00

SS handle

1.0000

each

75.00

75.00

Lock and Key

1.0000

set

150.00

150.00

Carpenter

0.5000

day

680.00

340.00 2289.23

Subtotal-A: Carrying, fitting, fixing, etc.

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2563.94 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2615.22

10% Profit ( Add 10% on Subtotal-B) :

2876.74

VAT

6% of Total

IT

4% of Total

191.78 127.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

274.71

3196.38

Page: 1251 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.26.04

Detailed Analysis Brief Description of Item 2 990mmx2130mm uPVC plastic shutter (solid)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Solid shutter

1.8000

sqm

767.00

1380.60

MS Rod (Plain, 40 Grade)

3.2000

kg

45.00

144.00

Rivet (for aluminium works)

36.0000

each

0.30

10.80

SS Screw (40 mm long)

24.0000

each

4.50

108.00

SS Tower bolt

2.0000

each

120.00

240.00

SS handle

1.0000

each

75.00

75.00

Lock and Key

1.0000

set

150.00

150.00

Carpenter

0.6000

day

680.00

408.00 2516.40

Subtotal-A: Carrying, fitting, fixing, etc.

( +13.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2843.53 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2900.40

10% Profit ( Add 10% on Subtotal-B) :

3190.44

VAT

6% of Total

IT

4% of Total

212.70 141.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

327.13

3544.94

Page: 1252 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.08.27

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing best quality magnetic door shock absorber in position with screw etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Magnetic door shock absorber

1.0000

each

200.00

200.00

Carpenter

0.1500

day

680.00

102.00 302.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

3.02

Subtotal-A1: Subtotal-B: Subtotal-C:

305.02 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

311.12

10% Profit ( Add 10% on Subtotal-B) :

342.23

VAT

6% of Total

IT

4% of Total

22.82 15.21 Total:

5.08.28

Supplying, fitting & fixing MORTICE door lock & key heavy duty of approved and accepted color and type i/c making hole in thick wooden door shutter made in USA/Korea/Japan or equivalent best quality etc. all complete as per direction of the E-I-C.

each

Mortice door lock and key

1.0000

each

500.00

500.00

Carpenter

0.2000

day

680.00

136.00 636.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

6.36

Subtotal-A1:

642.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

655.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

720.73

VAT

6% of Total

48.05

IT

4% of Total

32.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

380.26

800.81

Page: 1253 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.08.29

Taking off old door and window frames and shutter without any damages of structure including selecting, storing and stacking properly in measurable stacks after carrying those to a safe distance or preselected place, etc. all complete as per direction of the E-I-C.

5.08.29.1

Doors

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

680.00

340.00

each Carpenter

0.5000

340.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

346.80

10% Profit ( Add 10% on Subtotal-B) :

381.48

VAT

6% of Total

25.43

IT

4% of Total

16.95 Total:

5.08.29.2

Windows

each Carpenter

0.4000

day

680.00

272.00 272.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

277.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

305.18

VAT

6% of Total

IT

4% of Total

20.35 13.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

423.87

339.09

Page: 1254 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.09.01.01

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 0.46mm (26 SWG) thick galvanized iron corrugated sheet (Bangladesh made)having minimum weight 63-65 kg per bundle (2'-6" width 70 – 72 rft long) roofing fitted and fixed on MS sections with ‘J’ hook or wooden purlins with screws, limpet washers, bitumen washers and putty etc. all complete as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

0.46mm thick galvanized CI sheet

0.0700

bundle

8000.00

560.00

Subtotal-A: All other remaining costs like scaffolding, screws, etc.

( +8.00 % on Subtotal-A )

44.80

Subtotal-A1:

604.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

616.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

678.59

VAT

6% of Total

IT

4% of Total

45.24 30.16 Total:

5.09.01.02

0.46mm (26 SWG) thick galvanized iron plain sheet ridging with 300mm lap on either side fitted and fixed with galvanized bolts and nuts etc. all complete as per direction of the E-I-C.

753.98

m

0.46mm thick galvanized plain iron ridging

1.0200

m

165.00

All other remaining costs like screws, labour cost, etc.

( +8.00 % on Subtotal-A )

13.46

Subtotal-A1: Subtotal-B: Subtotal-C:

168.30 168.30

Subtotal-A:

181.76 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185.40

10% Profit ( Add 10% on Subtotal-B) :

203.94

VAT

6% of Total

IT

4% of Total

13.60 9.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

560.00

226.60

Page: 1255 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.09.02.01

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 0.46mm (26 SWG) thick galvanized color iron corrugated sheet (Bangladesh made) having minimum weight 6365 kg per bundle (2'-6" width 70 – 72 rft long) roofing fitted and fixed on MS sections with ‘J’ hook or wooden purlins with screws, limpet washers, bitumen washers and putty etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

0.46mm thick galvanized color CI sheet

0.0700

bundle

8200.00

574.00

Subtotal-A: All other remaining costs like scaffolding, screws, etc.

( +8.00 % on Subtotal-A )

45.92

Subtotal-A1:

619.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

632.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

695.55

VAT

6% of Total

IT

4% of Total

46.37 30.91 Total:

5.09.02.02

0.46mm (26 SWG) thick color iron plain sheet ridging with 300mm lap on either side fitted and fixed with galvanized bolts and nuts etc. all complete as per direction of the E-I-C.

772.83

m

0.46mm thick color plain iron ridging

1.0200

m

270.00

All other remaining costs like screws, labour cost, etc.

( +8.00 % on Subtotal-A )

22.03

Subtotal-A1: Subtotal-B: Subtotal-C:

275.40 275.40

Subtotal-A:

297.43 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

303.38

10% Profit ( Add 10% on Subtotal-B) :

333.72

VAT

6% of Total

IT

4% of Total

22.25 14.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

574.00

370.80

Page: 1256 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.09.03.01

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 1.5 mm thick fiber glass corrugated sheet roofing fitted and fixed on M.S. sections with 'J' hook or wooden purlin with screws, limpet washers and putty etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

592.00

680.80

sqm

1.5mm thick Fiber glass sheet

1.1500

sqm

680.80

Subtotal-A: All other remaining costs like scaffolding, j-hook, screw

( +8.00 % on Subtotal-A )

54.46

Subtotal-A1:

735.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

749.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

824.97

VAT

6% of Total

IT

4% of Total

55.00 36.67 Total:

5.09.03.02

Supplying, fitting and fixing 1.5 mm thick plain fiber glass sheet ridging with 300 mm lap on either side fitted and fixed with galvanized bolts and nuts etc. all complete as per direction of the E-I-C.

m

1.5 mm thick plain fiber glass ridging

1.0000

m

246.00

Subtotal-B: Subtotal-C:

246.00 246.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

250.92

10% Profit ( Add 10% on Subtotal-B) :

276.01

VAT

6% of Total

IT

4% of Total

18.40 12.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

916.63

306.68

Page: 1257 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.09.04

Detailed Analysis Brief Description of Item 2 Taking off CI sheet or fiber glass roofing of building without any damages of structure by any means, including selecting, storing and stacking properly in measurable stacks after carrying those to a safe distance or preselected place, etc. all complete as per direction of the EI-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

680.00

340.00

sqm

Carpenter

0.5000

340.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

346.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

381.48

VAT

6% of Total

IT

4% of Total

25.43 16.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

423.87

Page: 1258 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.09.05

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing temporary safety canopy around the construction work place where public safety is possible be endangered due to constructional activities, which will be made of aligning truss system of steel sections at 1800mm c/c as maximum and making flooring system by corrugated galvanized iron sheets of approximate 0.46mm thick. Placed on steel sections aligned perpendicular to truss at 900mm c/c or as per drawing and design including covering or hanging nylone net above and bellow the safety canopy up to construction working level which protect from drop down construction materials or any other materials . All fitted, fixed in position providing necessary anchors, cables, wires, ties etc. by standard anchoring & welding, nutbolts etc. all complete and certified for safety and accepted for all floor as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

0.46mm thick galvanized CI sheet

0.0500

bundle

8000.00

400.00

12.0000

kg

59.00

708.00

Mason

0.0500

day

550.00

27.50

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

0.1500

day

370.00

55.50

MS Angle, Flat bar, Z bar

1258.50

Subtotal-A: All other cost covering as anchors, cables, wires, ties, welding, nut-bolts etc

( +6.00 % on Subtotal-A )

75.51

Subtotal-A1:

1334.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1360.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1496.76

VAT

6% of Total

99.78

IT

4% of Total

66.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1663.07

Page: 1259 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.01

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing window grills or any where directed made of 16mm dia MS rod @100mm c/c fitted with 3 (three) nos horizontal MS flat bar (40mmx6mm) @ 450mm c/c maximum, in/c. fabricating, welding of each point, riveting, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member and painting with two coats of synthetic enamel paint over a coat of anticorrosive priming for all floors etc. all complete as per direction of the E-I-C. (Total weight per sqm should be approx. 18.00 kg and add or deduct @ Tk. 35.00 for each kg excess or less respectively as the case may be)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

4.7000

kg

59.00

277.30

MS Rod (Plain, 40 Grade)

13.6000

kg

45.00

612.00

25mm screws (Iron)

2.0500

dzn

5.50

11.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1532.58

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +21.00 % on Subtotal-A )

Subtotal-A1:

1854.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1891.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2080.65

VAT

6% of Total

138.71

IT

4% of Total

92.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

321.84

2311.84

Page: 1260 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.02

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing window grills or any where directed of any design made of mild steel F.I bar inner section (20mmx3mm) with outer frame of F.I. bar (25mmx6mm), fabricating, welding of each point, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member painting with two coats of synthetic enamel paint over a coat of anticorrosive priming for all floors etc. all complete as per direction of the E-I-C. (Total wt. per m2 should be 11.00 kg. For each kg excess or less add or deduct, as the case may be, @Tk. 140.00 per kg)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

11.5500

kg

59.00

25mm screws (Iron)

2.0500

dzn

5.50

11.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1324.73

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +21.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

278.19 1602.92

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1634.98

10% Profit ( Add 10% on Subtotal-B) :

1798.47

VAT

6% of Total

IT

4% of Total

119.90 79.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

681.45

1998.30

Page: 1261 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.03

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing window grills of any design made of mild steel F.I bar inner section (20mmx5mm) with outer frame of F.I. bar (25mmx6mm), fabricating, welding of each point, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member painting with two coats of synthetic enamel paint over a coat of anticorrosive priming for all floors etc. all complete as per direction of the E-I-C. (Total wt. per m2 should be 14.00 kg. For each kg excess or less add or deduct, as the case may be, @Tk.125.00 per kg)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

14.3400

kg

59.00

25mm screws (Iron)

2.0500

dzn

5.50

11.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1489.34

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

372.33 1861.67

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1898.90

10% Profit ( Add 10% on Subtotal-B) :

2088.79

VAT

6% of Total

IT

4% of Total

139.25 92.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

846.06

2320.88

Page: 1262 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.04

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing window grills or any where directed of any design made with F.I. bar (20mmx5mm) as inner and outer section; in/c fabricating, welding of each point, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C. (Total wt. per m2 should be 12.00 kg. For each kg excess or less add or deduct, as the case may be, @Tk. 136.00 per kg)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

12.9100

kg

59.00

761.69

25mm screws (Iron)

2.0500

dzn

5.50

11.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1404.97

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +27.00 % on Subtotal-A )

Subtotal-A1:

1784.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1819.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2001.99

VAT

6% of Total

133.47

IT

4% of Total

88.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

379.34

2224.43

Page: 1263 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.05

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing window grills or any where directed of any design made with F.I. bar (20mmx5mm) as inner member but no outer frame; in/c fabricating, welding of each point, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolts in walls/RCC member painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C. (Total wt. per m2 should be 10.00 kg. For each kg excess or less add or deduct, as the case may be, @Tk.152.00 per kg)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

11.5000

kg

59.00

25mm screws (Iron)

2.0500

dzn

5.50

11.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1321.78

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +29.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

383.31 1705.09

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1739.19

10% Profit ( Add 10% on Subtotal-B) :

1913.11

VAT

6% of Total

IT

4% of Total

127.54 85.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

678.50

2125.68

Page: 1264 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.06

Detailed Analysis Brief Description of Item 2 Supplying, fitting, fixing window grills or any where directed of any design made with F.I. bar (25mmx6mm) as both outer and inner section in/c fabricating, welding of each point, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C. (Total wt. per m2 should be 21.00 kg. For each kg excess or less add or deduct, as the case may be, @Tk. 113.00 per kg)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

22.6000

kg

59.00

25mm screws (Iron)

2.0500

dzn

5.50

11.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1976.68

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +19.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

375.57 2352.24

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2399.29

10% Profit ( Add 10% on Subtotal-B) :

2639.22

VAT

6% of Total

IT

4% of Total

175.95 117.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1333.40

2932.46

Page: 1265 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

5.10.07

Supplying, fitting and fixing window grills or any where directed of any design made with F.I. bar (25mmx6mm) as inner member but no outer frame; in/c fabricating, welding of each point, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C. (Total wt. per m2 should be 18.00 kg. For each kg excess or less add or deduct, as the case may be, @Tk.108.00 per kg)

5.10.07.01

25mmx6mm Flat Iron Bar

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle, Flat bar, Z bar

19.3600

kg

59.00

1142.24

25mm screws (Iron)

2.0500

dzn

5.50

11.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1785.52

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +21.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2160.47 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2203.68

10% Profit ( Add 10% on Subtotal-B) :

2424.05

VAT

6% of Total

IT

4% of Total

161.60 107.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

374.96

2693.39

Page: 1266 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.07.02

Detailed Analysis Brief Description of Item 2 25mmx6mm FI Bar or approved size (The measurement and weight should be taken before fixing in position)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg MS Angle, Flat bar, Z bar

1.0000

kg

59.00

25mm screws (Iron)

0.1100

dzn

5.50

0.61

Welder

0.0350

day

680.00

23.80

Welder Helper

0.0350

day

470.00

16.45

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0350

day

370.00

12.95 122.81

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +21.00 % on Subtotal-A )

Subtotal-A1:

25.79 148.59

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

151.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

166.72

VAT

6% of Total

IT

4% of Total

11.11 7.41 Total:

5.10.08

59.00

185.25

Supply, fitting and fixing window grill or any where directed by made of 12mm x 12mm hollow M.S. box made of minimum 16 BWG M.S. sheet @ 4” c/c with outer frame of 38mmx6mm F.I. bar etc. in/c fabricating, welding of each point, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member. Painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1267 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.08.01

Detailed Analysis Brief Description of Item 2 MS Hollow box 12mmx12mmx16 BWG

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Hollow box 12mmx12mm (thickness 16 gauge)

27.0500

m

56.00

1514.80

MS Angle, Flat bar, Z bar

7.2000

kg

59.00

424.80

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2571.60

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +13.00 % on Subtotal-A )

Subtotal-A1:

2905.91

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2964.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3260.43

VAT

6% of Total

IT

4% of Total

217.36 144.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

334.31

3622.70

Page: 1268 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.08.02

Detailed Analysis Brief Description of Item 2 MS Hollow box 12mmx12mmx16 BWG (The measurement and weight should be taken before fixing in position) .

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg MS Hollow box 12mmx12mm (thickness 16 gauge)

0.0630

m

56.00

MS Angle, Flat bar, Z bar

0.4000

kg

59.00

23.60

Welder

0.0350

day

680.00

23.80

Welder Helper

0.0350

day

470.00

16.45

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0350

day

370.00

12.95 90.33

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +13.00 % on Subtotal-A )

Subtotal-A1:

11.74 102.07

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

104.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

114.52

VAT

6% of Total

IT

4% of Total

7.63 5.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3.53

127.25

Page: 1269 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.09

Detailed Analysis Brief Description of Item 2 Supplying, fitting, fixing MS grills made of 10mm dia MS rod @100mm c/c both ways, fitted with MS angles (25mmx25mmx6mm) outer frame in/c fabricating, welding of each point, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member. Painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Flat Iron Bar Clamp

1.5800

kg

70.00

110.60

MS Angle, Flat bar, Z bar

5.7200

kg

59.00

337.48

MS Rod (Plain, 40 Grade)

10.8200

kg

45.00

486.90

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1566.98

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1849.04 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1886.02

10% Profit ( Add 10% on Subtotal-B) :

2074.62

VAT

6% of Total

IT

4% of Total

138.31 92.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

282.06

2305.13

Page: 1270 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.10

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing verandah grill or any where directed made of 10mm dia MS rods provided 75mm c/c in any position both ways as per design with outside MS angle frame (25mmx25mmx6mm) in/c fabricating, welding, cost of electricity, workshop charge, carriage, fixing with M.S. clamps or steel royal bolt in walls/RCC member. Painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Flat Iron Bar Clamp

1.5800

kg

70.00

110.60

MS Angle, Flat bar, Z bar

5.7200

kg

59.00

337.48

MS Rod (Plain, 40 Grade)

14.6900

kg

45.00

661.05

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1741.13

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2054.53 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2095.62

10% Profit ( Add 10% on Subtotal-B) :

2305.19

VAT

6% of Total

IT

4% of Total

153.68 102.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

313.40

2561.32

Page: 1271 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.10.11

Supplying, fitting and fixing window grill, high window grill, ventilation grill, sky window grill or anywhere as directed by the Engineer; making the grill with 20mm or 12 mm or 10mm M.S. square solid bar @ 600mm c/c vertically, fitted with M.S. flat bar series of 20mmx5mm FI bar @ 100mm c/c horizontally; having outer frame of 25mmx5mm F.l. bar fixing the grill with M.S. clamp or Steel royal bolt in walls/RCC member as per approved design and drawing for all floors in/c fabricating, welding, cost of electricity, workshop charge, carriage, Painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C.

5.10.11.01

M.S. flat bar series of 20mmx5mm FI bar @ 100mm c/c horizontally with M.S. square solid bar 25mm x 25 mm @ 600mm c/c vertically

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle, Flat bar, Z bar

8.8200

kg

59.00

520.38

10.7500

kg

50.00

537.50

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50

MS Square bar 25mmx25mm/20mmx20mm

1689.88

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +21.00 % on Subtotal-A )

Subtotal-A1:

2044.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2085.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2294.21

VAT

6% of Total

IT

4% of Total

152.95 101.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

354.87

2549.13

Page: 1272 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.11.02

Detailed Analysis Brief Description of Item 2 M.S. flat bar series of 20mmx5mm FI bar @ 100mm c/c horizontally with M.S. square solid bar 20mm x 20 mm @ 600mm c/c vertically

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle, Flat bar, Z bar

8.8200

kg

59.00

MS Square bar 25mmx25mm/20mmx20mm

6.8600

kg

50.00

343.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1495.38

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +25.00 % on Subtotal-A )

Subtotal-A1:

373.85 1869.23

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1906.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2097.27

VAT

6% of Total

IT

4% of Total

139.82 93.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

520.38

2330.30

Page: 1273 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.11.03

Detailed Analysis Brief Description of Item 2 M.S. flat bar series of 20mmx5mm FI bar @ 100mm c/c horizontally with M.S. square solid bar 12mm x 12 mm @ 600mm c/c vertically

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle, Flat bar, Z bar

8.8200

kg

59.00

MS Square bar 12 mm X 12 mm

2.4700

kg

52.00

128.44

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1280.82

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +29.00 % on Subtotal-A )

Subtotal-A1:

371.44 1652.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1685.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1853.83

VAT

6% of Total

IT

4% of Total

123.59 82.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

520.38

2059.81

Page: 1274 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.11.04

Detailed Analysis Brief Description of Item 2 M.S. flat bar series of 20mmx5mm FI bar @ 100mm c/c horizontally with M.S. square solid bar 10mm x 10 mm @ 600mm c/c vertically

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle, Flat bar, Z bar

8.8200

kg

59.00

MS Square bar 10 mm X 10 mm

1.7200

kg

52.00

89.44

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1241.82

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +30.00 % on Subtotal-A )

Subtotal-A1:

372.55 1614.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1646.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1811.32

VAT

6% of Total

IT

4% of Total

120.75 80.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

520.38

2012.58

Page: 1275 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.11.05

Detailed Analysis Brief Description of Item 2 M.S. flat bar series of 20mmx5mm FI bar @ 100mm c/c horizontally with M.S. square hollow box 20mmx20mmx16 gauge @ 600mm c/c vertically

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

8.8200

kg

59.00

520.38

MS Hollow box 20mmx20mm of thickness 16 gauge

6.8600

m

94.00

644.84

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1797.22

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1833.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2016.48

VAT

6% of Total

IT

4% of Total

134.43 89.62 Total:

5.10.12

Supplying, fitting and fixing window grill, high window grill, ventilation grill, sky window grill or anywhere as directed by the Engineer; making the grill with 20mm or 12 mm or 10mm M.S. square solid bar series @ 150mm, 100mm and 50mm c/c respectively horizontally and stiffener of 20mm M.S. square solid bar vertically, fitted with M.S. flat bar 25mmx5mm outer frame fixing the grill with M.S. clamp or Steel royal bolt in walls/RCC member as per approved design and drawing for all floors in/c fabricating, welding, cost of electricity, workshop charge, carriage, Painting with two coats of synthetic enamel paint over a coat of anticorrosive priming etc. all complete for all floor as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

2240.53

sqm

Page: 1276 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.12.01

Detailed Analysis Brief Description of Item 2 M.S. square solid bar series 20mm x 20 mm @ 150mm c/c horizontally with M.S. flat bar 25mmx5mm outer frame

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Square bar 25mmx25mm/20mmx20mm

20.5900

kg

50.00

MS Angle, Flat bar, Z bar

5.9200

kg

59.00

349.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2010.78

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +17.00 % on Subtotal-A )

Subtotal-A1:

341.83 2352.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2399.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2639.63

VAT

6% of Total

IT

4% of Total

175.98 117.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1029.50

2932.92

Page: 1277 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.12.02

Detailed Analysis Brief Description of Item 2 M.S. square solid bar series 12mm x12 mm @ 100mm c/c horizontally with M.S. flat bar 25mmx5mm outer frame

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Square bar 12 mm X 12 mm

10.9800

kg

52.00

MS Angle, Flat bar, Z bar

5.9200

kg

59.00

349.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1552.24

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +23.00 % on Subtotal-A )

Subtotal-A1:

357.02 1909.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1947.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2142.18

VAT

6% of Total

IT

4% of Total

142.81 95.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

570.96

2380.20

Page: 1278 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.12.03

Detailed Analysis Brief Description of Item 2 M.S. square solid bar series 10mm x10 mm @ 50mm c/c horizontally with M.S. flat bar 25mmx5mm outer frame

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Square bar 10 mm X 10 mm

15.2600

kg

52.00

MS Angle, Flat bar, Z bar

5.9200

kg

59.00

349.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1774.80

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

354.96 2129.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2172.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2389.59

VAT

6% of Total

IT

4% of Total

159.31 106.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

793.52

2655.10

Page: 1279 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.12.04

Detailed Analysis Brief Description of Item 2 M.S. square solid bar series 10mm x10 mm @ 25mm c/c horizontally with M.S. flat bar 25mmx5mm outer frame

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Square bar 10 mm X 10 mm

27.5000

kg

52.00

MS Angle, Flat bar, Z bar

5.9200

kg

59.00

349.28

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2411.28

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +15.00 % on Subtotal-A )

Subtotal-A1:

361.69 2772.97

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2828.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3111.27

VAT

6% of Total

IT

4% of Total

207.42 138.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1430.00

3456.97

Page: 1280 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.13

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing verandah drop or ventilation Grill or anywhere as directed made of 10mmx10mm MS square box series having minimum wall thickness 16 gauge @35mm c/c horizontal and 50mmx50mm MS square box of minimum wall thickness 3mm at top and sides and 75mmx75mm square box of minimum wall thickness 3mm at bottom as per design and drawing fixed with vertical stiffener 20mmx20mm MS square box of minimum wall thickness 16 gauge @ 700mm c/c clamped in RCC or brick work by 40mmx40mm MS square box of minimum wall thickness 3mm i/c cost of fabricating, cutting, welding, painting 2 coats of synthetic enamel paint over a coat of anticorrosive priming in/c. cutting grooves in the R.C.C. or brick work, mending good the damages with Cement Concrete (1:2.4) for all floors etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

MS Hollow box 75mmx75mm of 3mm thick

1.8350

m

275.00

504.63

MS Hollow box 50mmx50mm of 3mm thick

2.7840

m

230.00

640.32

MS Hollow box 40mmx40mm of 3mm thick

0.2800

m

140.00

39.20

MS Hollow box 20mmx20mm of thickness 16 gauge

0.7000

m

94.00

65.80

MS Hollow box 12mmx12mm (thickness 16 gauge)

13.1900

m

56.00

738.64

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2620.59

Subtotal-A: All other remaining costs covering all workshop charges, enamel painting etc.

( +13.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

340.68 2961.26

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3020.49

10% Profit ( Add 10% on Subtotal-B) :

3322.53

VAT

6% of Total

IT

4% of Total

221.50 147.67 Page: 1281 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.10.14

Supplying, fitting and fixing verandah drop or ventilation Grill or anywhere as directed made of 10mmX10mm MS square bar series welded to outer frame made of MS flat bar of size 25mmx3mm having anchoring Clamps of 25mmx25mmx3mm MS Angle @750mm c/c to be embaded in RCC or Brick work i/c cost of fabricating, cutting, welding, painting 2 coats of synthetic enamel paint over a coat of anticorrosive priming in/c. cutting grooves in the R.C.C. or brick work, mending good the damages with Cement Concrete (1:2.4) for all floors etc. all complete as per design and direction of the E-I-C.

sqm

MS Angle, Flat bar, Z bar Welder

31.6420

kg

59.00

1866.88

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2498.88

Subtotal-A: All other cost covering bends etc

( +13.00 % on Subtotal-A )

Subtotal-A1:

324.85 2823.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2880.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3168.23

VAT

6% of Total

IT

4% of Total

211.22 140.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3691.71

3520.25

Page: 1282 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.15

Detailed Analysis Brief Description of Item 2 Manufacturing, Supplying, fitting, fixing of ordinary type M.S. folding gate with 12mm x12mm MS square solid bar and 25 mm x 25mm x 6 mm MS Angle box frame with MS Angle 40mmx40mmx6mm size box including fabrication, welding, cost of electricity, workshop charges, carriage, cutting grooves, mending good the damages, finishing, curing etc. including fabrication, riveting, welding as and where necessary, etc. all complete as per drawing, design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle 40mmx40mmx6mm

5.6400

kg

58.00

327.12

MS Angle 25mmx25mmx6mm

17.8800

kg

58.00

1037.04

MS Square bar 12 mm X 12 mm

11.0500

kg

52.00

574.60

Welder

1.0000

day

680.00

680.00

Welder Helper

0.1000

day

470.00

47.00

Ordinary Labour

0.1000

day

370.00

37.00

Electrode

3.0000

pkt

810.00

2430.00 5132.76

Subtotal-A: All other remaining cost as 3''hinge, 6''clamp, locking arrangement, workshop charge, making holes, CC casting, fitting, fixing etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

6159.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6282.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6910.75

VAT

6% of Total

460.72

IT

4% of Total

307.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1026.55

7678.61

Page: 1283 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.10.16

Detailed Analysis Brief Description of Item 2 Taking off steel or iron grill or gate of any type without any damages of structure by any means, including selecting, storing and stacking properly in measurable stacks after carrying those to a safe distance or preselected place, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Ordinary Labour

0.5000

day

370.00

185.00

Skilled Labour

0.2500

day

450.00

112.50 297.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

303.45

10% Profit ( Add 10% on Subtotal-B) :

333.80

VAT

6% of Total

IT

4% of Total

22.25 14.84 Total:

5.11.01

370.88

Supplying, fitting and fixing of aluminium swing doors as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.8mm thick wall frame (size:101.60mm, 44.45mm, 83.21mm), 2.33mm thick shutter side (size:54mm, 46mm), 0.99mm thick door glass bit (size:16.54mm, 15.49mm), 2.5mm thick closure section (size:101.60mm, 42.93mm), 1.5mm thick closure cover (size:101.60mm), 4mm thick floor bottom (size:101.60mm, 12.70mm), 2.3mm thick shutter bottom (size:82.6mm, 43.99mm), 2.3mm thick shutter top (size:51mm, 43.99mm) and 2.3mm to 4mm thick handle (size:101.60mm, 38.10mm, 25.40mm). Sections of all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories like handle, locks (Japan), auto-closure stopper (USA/Japan), flash bolt, weather seal etc. keeping provision for fitting 5mm thick glass in/c neoprene, sealant for all floors etc. all complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1284 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.01.01

2 Bronze colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.8mm thick bronze colour aluminium wall frame (101.6mm ,44.45mm,83,21mm)

1.8800

m

432.44

812.99

2.3mm thick Bronze colour aluminium shutter side(54mm ,46mm)

1.8800

m

430.15

808.68

0.99mm thick bronze colour aluminium door glass bit (16.54mm,15.49mm)

5.6200

m

46.05

258.80

2.5mm thick bronze colour aluminium closure section (101.6mm,42.93mm)

0.0920

m

409.53

37.68

1.5mm thick bronze colour aluminium closure cover(101.6mm)

0.0920

m

156.35

14.38

4mm thick bronze colour aluminium floor bottom (101.6mm, 12.7mm)

0.0920

m

438.90

40.38

2.3mm thick bronze colour aluminium shutter top (51mm ,43.99mm)

0.0920

m

428.59

39.43

2.3mm thick bronze colour aluminium shutter bottom (82.6mm ,43.99mm)

0.0920

m

523.39

48.15

2.3mm-4mm thick bronze colour aluminium handle (101.6mm,38.1mm ,25.4mm)

0.0460

m

578.22

26.60

Swing Door Closure

0.4400

set

2500.00

1100.00

Swing Door Lock

0.4400

set

650.00

286.00

Swing Door Mohiar

1.8800

m

4.00

7.52

Fixed Neoprene

5.6200

m

4.75

26.70

Skilled Technician

1.3200

day

680.00

897.60

Semi Skilled Technician

1.3200

day

570.00

752.40

Mason

0.2200

day

550.00

121.00

Ordinary Labour

0.4400

day

370.00

162.80 5441.11

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc. Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +6.00 % on Subtotal-A )

326.47 Page: 1285 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-A1:

5767.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5882.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6471.22

VAT

6% of Total

IT

4% of Total

431.41 287.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7190.24

Page: 1286 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.01.02

2 Silver colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.8mm Thick Silver Colour Aluminium Wall Frame(101.6mm,44.45mm,83.21mm)

1.8800

m

419.68

789.00

2.3mm Thick Silver colour Aluminium shutter side (54mm,46mm)

1.8800

m

417.19

784.32

0.99mm Thick Silver Colour Aluminium door glass bit (16.54mm,15.49mm)

5.6200

m

45.01

252.96

2.5mm Thick Silver Colour Aluminium Closure section (101.6mm,42.43mm)

0.0920

m

397.19

36.54

1.5mm Thick Silver Colour Aluminium Closure Cover (101.6mm)

0.0920

m

151.82

13.97

4mm Thick Silver Colour Aluminium floor bottom (101.6mm,12.7mm)

0.0920

m

425.62

39.16

2.3mm Thick Silver Colour Aluminium shutter top (51mm,43.99mm)

0.0920

m

415.78

38.25

2.3mm Thick Silver Colour Aluminium Shutter Bottom (82.6mm,43.99mm)

0.0920

m

507.46

46.69

2.3mm - 4mm Thick Silver Colour Aluminium handle (101.6mm ,38.1mm, 25.4mm)

0.0460

m

560.88

25.80

Swing Door Closure

0.4400

set

2500.00

1100.00

Swing Door Lock

0.4400

set

650.00

286.00

Swing Door Mohiar

1.8800

m

4.00

7.52

Fixed Neoprene

5.6200

m

4.75

26.70

Skilled Technician

1.3200

day

680.00

897.60

Semi Skilled Technician

1.3200

day

570.00

752.40

Mason

0.2200

day

550.00

121.00

Ordinary Labour

0.4400

day

370.00

162.80 5380.69

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc. Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +6.00 % on Subtotal-A )

322.84 Page: 1287 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-A1:

5703.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5817.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6399.36

VAT

6% of Total

IT

4% of Total

426.62 284.42 Total:

5.11.02

7110.40

Supplying, fitting and fixing of aluminium composite swing doors with fixed partition as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.8mm thick wall frame (size:101.60mm, 44.45mm, 83.21mm), 2.33m thick shutter side (size:54mm, 46mm), 0.99mm thick door glass bit (size:16.54mm, 15.49mm) 2.5mm thick closure section (size:101.60mm, 42.93mm), 1.5mm thick closure cover (size:101.60mm, 4mm) thick floor bottom (size:101.60mm, 12.70mm), 2.3mm thick shutter bottom (size:82.6mm, 43.99mm) 2.3mm thick shutter top (size:51mm, 43.99m) 2.3mm to 4mm thick handle (short) (size:101.60mm, 38.10mm, 25.40mm) 1.8mm thick top and side (size:101.60mm, 44.45mm), 1.80mm thick bottom (size:101.35mm, 44.45mm), 1.50mm thick bottom cover (size:44.32mm, 19.61mm), 1.50mm thick groove cover (size:83.21mm, 16.00mm), 1.00mm thick fixed glass protector bit (size:15.75mm, 14.81mm) section of all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories like handle, locks (Japan), auto-closure (USA), stopper, flush bolt, weather seal etc. keeping provision for fitting 5mm thick glass in/c neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1288 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.02.01

2 Bronze colour

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.8mm thick bronze colour aluminium wall frame (101.6mm ,44.45mm,83,21mm)

0.4400

m

432.44

190.27

2.3mm thick Bronze colour aluminium shutter side(54mm ,46mm)

0.6100

m

430.15

262.39

0.99mm thick bronze colour aluminium door glass bit (16.54mm,15.49mm)

1.8400

m

46.05

84.73

2.5mm thick bronze colour aluminium closure section (101.6mm,42.93mm)

0.1600

m

409.53

65.52

1.5mm thick bronze colour aluminium closure cover(101.6mm)

0.1600

m

156.35

25.02

4mm thick bronze colour aluminium floor bottom (101.6mm, 12.7mm)

0.1600

m

438.90

70.22

2.3mm thick bronze colour aluminium shutter top (51mm ,43.99mm)

0.1600

m

428.59

68.57

2.3mm thick bronze colour aluminium shutter bottom (82.6mm ,43.99mm)

0.1600

m

523.39

83.74

2.3mm-4mm thick bronze colour aluminium handle (101.6mm,38.1mm ,25.4mm)

0.0700

m

578.22

40.48

1.8mm Thick Bronze Colour Aluminium top and side (101.60mm,44.45mm)

0.8300

m

545.84

453.05

1.8mm Thick Bronze Colour Aluminium bottom (101.35mm,44.45mm)

0.3500

m

461.14

161.40

1.5mm Thick Bronze Colour Aluminium bottom cover (44.32mm,19.6mm)

0.3500

m

153.43

53.70

1.5mm Thick Bronze Colour Aluminium groove cover (83.21mm, 16mm)

0.6800

m

221.29

150.48

1.00mm Thick Bronze Colour Aluminium fixed glass protector (39.09mm,14.81mm)

0.2900

m

71.85

20.84

1.00mm Thick Bronze Colour Aluminium fixed glass protector BIT (15.75mm,14.81mm)

0.2900

m

53.10

15.40

Page: 1289 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Swing Door Closure

0.1500

set

2500.00

375.00

Swing Door Lock

0.0700

set

650.00

45.50

Swing Door Mohiar

0.4600

m

4.00

1.84

Fixed Neoprene

6.1200

m

4.75

29.07

Flush Bolt

0.1500

set

260.00

39.00

Skilled Technician

0.8600

day

680.00

584.80

Semi Skilled Technician

1.2200

day

570.00

695.40

Mason

0.0700

day

550.00

38.50

Ordinary Labour

0.1100

day

370.00

40.70 3595.62

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +2.50 % on Subtotal-A )

89.89

Subtotal-A1:

3685.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3759.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4135.15

VAT

6% of Total

IT

4% of Total

275.68 183.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4594.61

Page: 1290 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.02.02

2 Silver colour

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.8mm Thick Silver Colour Aluminium Wall Frame(101.6mm,44.45mm,83.21mm)

0.4400

m

419.68

184.66

2.3mm Thick Silver colour Aluminium shutter side (54mm,46mm)

0.6100

m

417.19

254.49

0.99mm Thick Silver Colour Aluminium door glass bit (16.54mm,15.49mm)

1.8400

m

45.01

82.82

2.5mm Thick Silver Colour Aluminium Closure section (101.6mm,42.43mm)

0.1600

m

397.19

63.55

1.5mm Thick Silver Colour Aluminium Closure Cover (101.6mm)

0.1600

m

151.82

24.29

4mm Thick Silver Colour Aluminium floor bottom (101.6mm,12.7mm)

0.1600

m

425.62

68.10

2.3mm Thick Silver Colour Aluminium shutter top (51mm,43.99mm)

0.1600

m

415.78

66.52

2.3mm Thick Silver Colour Aluminium Shutter Bottom (82.6mm,43.99mm)

0.1600

m

507.46

81.19

2.3mm - 4mm Thick Silver Colour Aluminium handle (101.6mm ,38.1mm, 25.4mm)

0.0700

m

560.88

39.26

1.8mm Thick Silver Colour Aluminium top and side (101.60mm,44,45mm)

0.8300

m

594.99

493.84

1.8mm Thick Silver Colour Aluminium bottom (101.35mm,44.45mm)

0.3500

m

447.39

156.59

1.5mm Thick Silver Colour Aluminium bottom cover (44.32mm, 19.6mm)

0.3500

m

106.37

37.23

1.5mm Thick Silver Colour Aluminium groove cover (83.21mm, 16mm)

0.6800

m

214.93

146.15

1.00mm Thick Silver Colour Aluminium fixed glass protector (39.09mm,14.81mm)

0.2900

m

69.66

20.20

1.00mm Thick Silver Colour Aluminium fixed glass protector BIT (15.75mm,14.81mm)

0.2900

m

51.54

14.95

Page: 1291 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Swing Door Closure

0.1500

set

2500.00

375.00

Swing Door Lock

0.0700

set

650.00

45.50

Swing Door Mohiar

0.4600

m

4.00

1.84

Fixed Neoprene

6.1200

m

4.75

29.07

Flush Bolt

0.1500

set

260.00

39.00

Skilled Technician

0.8600

day

680.00

584.80

Semi Skilled Technician

1.2200

day

570.00

695.40

Mason

0.0700

day

550.00

38.50

Ordinary Labour

0.1100

day

370.00

40.70 3583.65

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +2.50 % on Subtotal-A )

89.59

Subtotal-A1:

3673.24

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3746.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4121.38

VAT

6% of Total

IT

4% of Total

274.76 183.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4579.31

Page: 1292 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.11.03

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, fitting and fixing of aluminium sliding doors as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.5mm thick outer bottom (size:75.50mm, 17.79mm), 1.5mm thick outer top (size:75.50mm, 26.80mm), 1.5mm thick shutter top (size:33mm, 26.80mm, 22mm) 1.5mm thick shutter bottom (size:60mm, 24.4mm), 1.5mm thick outer side (size:75.50mm, 19.90mm), 1.5mm thick shutter lock (size:49.20mm, 26.0mm), 1.5mm thick interlock (size:34.40mm, 32.10mm) and 1.5mm thick shutter divider (size:31.75,22mm). Sections all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories like handle, locks (Japan), roller, stopper etc. keeping provision for fitting 5mm thick glass in/c neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C. Size: 2100mmx2100mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1293 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.03.01

2 Bronze colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium outer bottom (75.5mm,17.79mm)

0.4700

m

236.07

110.95

1.5mm Thick Bronze Colour Aluminium outer top (75.5mm,26.8mm)

0.4700

m

352.73

165.78

1.5mm Thick Bronze Colour shutter top (33, 26.8, 22mm)

0.4700

m

210.81

99.08

1.5mm Thick Bronze Colour shutter bottom (60, 24.4mm)

0.4700

m

316.99

148.99

1.5mm Thick Bronze Colour Aluminium outer side (75.5mm,19.9mm)

0.9400

m

238.64

224.32

1.5mm Thick Bronze Colour Shutter Lock (49.2,26.0mm)

0.9400

m

250.67

235.63

1.5mm Thick Bronze Colour Aluminium Inter lock (34.40,32.1mm)

0.9400

m

251.87

236.76

1.5mm Thick Bronze colour Aluminium shutter divider (31.75mm,22mm)

0.4700

m

188.99

88.83

Sliding Door Key Lock

0.4400

set

90.00

39.60

Sliding Door Wheel

0.8800

each

45.00

39.60

Sliding Door Mohiar

6.6800

m

3.60

24.05

Skilled Technician

0.6600

day

680.00

448.80

Semi Skilled Technician

0.6600

day

570.00

376.20

Mason

0.1100

day

550.00

60.50

Ordinary Labour

0.2200

day

370.00

81.40 2380.48

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +6.00 % on Subtotal-A )

Subtotal-A1:

142.83 2523.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2573.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2831.16

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

188.74 Page: 1294 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

125.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3145.73

Page: 1295 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.03.02

2 Silver colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium outer bottom (75.5,17.79mm)

0.4700

m

229.54

107.88

1.5mm Thick Silver Colour Aluminium outer top (75.5,26.8mm)

0.4700

m

342.59

161.02

1.5mm Thick Silver Colour Aluminium shutter top (35,26.8mm)

0.4700

m

204.63

96.18

1.5mm Thick Silver Colour Aluminium shutter bottom (60,24.4mm)

0.4700

m

307.37

144.46

1.5mm Thick Silver Colour Aluminium outer side (75.5,19.9mm)

0.9400

m

231.77

217.86

1.5mm Thick Silver Colour Aluminium shutter lock (49.2,26.0mm)

0.9400

m

243.28

228.68

1.5mm Thick Silver Colour Aluminium Inter Lock (34.4, 32.1mm)

0.9400

m

244.83

230.14

1.5mm Thick Silver Colour Aluminium shutter divider (31.75mm,22.00mm)

0.4700

m

201.49

94.70

Sliding Door Key Lock

0.4400

set

90.00

39.60

Sliding Door Wheel

0.8800

each

45.00

39.60

Sliding Door Mohiar

6.6800

m

3.60

24.05

Skilled Technician

0.6600

day

680.00

448.80

Semi Skilled Technician

0.6600

day

570.00

376.20

Mason

0.1100

day

550.00

60.50

Ordinary Labour

0.2200

day

370.00

81.40 2351.08

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +6.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

141.06 2492.14

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2541.98 Page: 1296 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

Amount 8 2796.18

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

186.41 124.27 Total:

5.11.04

3106.87

Supplying, fitting and fixing of aluminium sliding doors as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.5mm thick outer bottom (size:75.50mm, 17.79mm), 1.5mm thick outer top (size:75.50mm, 26.80mm), 1.5mm thick shutter top (size:33mm, 26.80mm, 22mm), 1.5mm thick shutter bottom (size:60mm, 24.4mm), 1.5mm thick outer side (size:75.50mm, 19.90mm), 1.5mm thick sliding fixed side (size:31mm, 26mm), 1.5mm thick shutter lock (size:49.20mm, 26.0mm), 1.5mm thick interlock (size:34.40mm, 32.10mm) 1.5mm thick shutter divider (size:31.75,22mm) and 1.4mm to 1.5mm thick spandrel (size:152.4,7.14mm). Sections all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories like handle, looks (Japan), roller, stopper etc. keeping provision for fitting 5mm thick glass in/c neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C. Size:1800mmx2100mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1297 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.04.01

2 Bronze colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium outer bottom (75.5mm,17.79mm)

0.4700

m

236.07

110.95

1.5mm Thick Bronze Colour Aluminium outer top (75.5mm,26.8mm)

0.4700

m

352.73

165.78

1.5mm Thick Bronze Colour shutter top (33, 26.8, 22mm)

0.4500

m

210.81

94.86

1.5mm Thick Bronze Colour shutter bottom (60, 24.4mm)

0.4500

m

316.99

142.65

1.5mm Thick Bronze Colour Aluminium outer side (75.5mm,19.9mm)

1.0900

m

238.64

260.12

1.5mm Thick Bronze Colour Aluminium sliding fixed side (31mm,26mm)

0.5500

m

157.21

86.47

1.5mm Thick Bronze Colour Shutter Lock (49.2,26.0mm)

0.5500

m

250.67

137.87

1.5mm Thick Bronze Colour Aluminium Inter lock (34.40,32.1mm)

1.0900

m

251.87

274.54

1.5mm Thick Bronze colour Aluminium shutter divider (31.75mm,22mm)

0.4500

m

188.99

85.05

1.4 - 1.5mm Thick Bronze Colour Aluminium spandrel (152.4,7.14mm)

2.3500

m

250.50

588.68

Sliding Door Key Lock

0.3000

set

90.00

27.00

Sliding Door Wheel

0.3000

each

45.00

13.50

Sliding Door Mohiar

3.6000

m

3.60

12.96

Sliding Neoprene

4.0700

m

8.20

33.37

Skilled Technician

0.4500

day

680.00

306.00

Semi Skilled Technician

0.4500

day

570.00

256.50

Mason

0.1300

day

550.00

71.50

Ordinary Labour

0.2600

day

370.00

96.20 2763.99

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc. Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +3.50 % on Subtotal-A )

96.74

Page: 1298 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-A1:

2860.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2917.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3209.74

VAT

6% of Total

IT

4% of Total

213.98 142.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3566.38

Page: 1299 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.04.02

2 Silver colour

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium outer bottom (75.5,17.79mm)

0.4700

m

229.54

107.88

1.5mm Thick Silver Colour Aluminium outer top (75.5,26.8mm)

0.4700

m

342.59

161.02

1.5mm Thick Silver Colour Aluminium shutter top (35,26.8mm)

0.4500

m

204.63

92.08

1.5mm Thick Silver Colour Aluminium shutter bottom (60,24.4mm)

0.4500

m

307.37

138.32

1.5mm Thick Silver Colour Aluminium outer side (75.5,19.9mm)

1.0900

m

231.77

252.63

1.5mm Thick Silver Colour Aluminium sliding fixed side (31,26mm)

0.5500

m

152.57

83.91

1.5mm Thick Silver Colour Aluminium shutter lock (49.2,26.0mm)

0.5500

m

243.28

133.80

1.5mm Thick Silver Colour Aluminium Inter Lock (34.4, 32.1mm)

1.0900

m

244.83

266.86

1.5mm Thick Silver Colour Aluminium shutter divider (31.75mm,22.00mm)

0.4500

m

201.49

90.67

1.4 - 1.5mm Thick Silver Colour Aluminium spandrel (152.4,7.14mm)

2.3500

m

242.94

570.91

Sliding Door Key Lock

0.3000

set

90.00

27.00

Sliding Door Wheel

0.3000

each

45.00

13.50

Sliding Door Mohiar

3.6000

m

3.60

12.96

Sliding Neoprene

4.0700

m

8.20

33.37

Skilled Technician

0.4500

day

680.00

306.00

Semi Skilled Technician

0.4500

day

570.00

256.50

Mason

0.1300

day

550.00

71.50

Ordinary Labour

0.2600

day

370.00

96.20

Page: 1300 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8 2715.13

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +3.50 % on Subtotal-A )

95.03

Subtotal-A1:

2810.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2866.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3152.99

VAT

6% of Total

IT

4% of Total

210.20 140.13 Total:

5.11.05

3503.33

Supplying, fitting and fixing of aluminium sliding window as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.5mm thick outer bottom (size:75.50mm, 17.79mm), 1.5mm thick outer top (size:75.50mm, 26.80mm) 1.5mm thick shutter top (size:33mm, 26.80mm, 22mm), 1.5mm thick shutter bottom (size:60mm, 24.40mm), 1.5mm thick outer side (size:75.50mm, 19.90mm), 1.5mm thick sliding fixed side (size:31mm, 26mm), 1.5mm thick shutter lock (size:49.20mm, 26.0mm) and 1.5mm thick interlock (size:34.40mm, 32.10mm). Sections all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories like handle, locks (Japan), roller, stopper etc. keeping provision for fitting 5mm thick glass in/c neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1301 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.05.01

Detailed Analysis Brief Description of Item 2 Bronze colour[Size : 1500mmx1400mm]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium outer bottom (75.5mm,17.79mm)

0.7300

m

236.07

172.33

1.5mm Thick Bronze Colour Aluminium outer top (75.5mm,26.8mm)

0.7300

m

352.73

257.49

1.5mm Thick Bronze Colour shutter top (33, 26.8, 22mm)

0.6900

m

210.81

145.46

1.5mm Thick Bronze Colour shutter bottom (60, 24.4mm)

0.6900

m

316.99

218.72

1.5mm Thick Bronze Colour Aluminium outer side (75.5mm,19.9mm)

1.3100

m

238.64

312.62

1.5mm Thick Bronze Colour Aluminium sliding fixed side (31mm,26mm)

0.6600

m

157.21

103.76

1.5mm Thick Bronze Colour Shutter Lock (49.2,26.0mm)

0.6600

m

250.67

165.44

1.5mm Thick Bronze Colour Aluminium Inter lock (34.40,32.1mm)

1.3100

m

251.87

329.95

Sliding Door Key Lock

0.4800

set

90.00

43.20

Sliding Door Wheel

0.9600

each

45.00

43.20

Sliding Door Mohiar

4.8200

m

3.60

17.35

Sliding Neoprene

4.0800

m

8.20

33.46

Skilled Technician

0.4800

day

680.00

326.40

Semi Skilled Technician

0.4800

day

570.00

273.60

Mason

0.2400

day

550.00

132.00

Ordinary Labour

0.2400

day

370.00

88.80 2663.78

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +7.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

186.46 2850.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2907.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3197.98 Page: 1302 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

Amount 8 213.20 142.13

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3553.31

Page: 1303 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.05.02

Detailed Analysis Brief Description of Item 2 Silver colour[Size : 1500mmx1400mm]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium outer bottom (75.5,17.79mm)

0.7300

m

229.54

167.56

1.5mm Thick Silver Colour Aluminium outer top (75.5,26.8mm)

0.7300

m

342.59

250.09

1.5mm Thick Silver Colour Aluminium shutter top (35,26.8mm)

0.6900

m

204.63

141.19

1.5mm Thick Silver Colour Aluminium shutter bottom (60,24.4mm)

0.6900

m

307.37

212.09

1.5mm Thick Silver Colour Aluminium outer side (75.5,19.9mm)

1.3100

m

231.77

303.62

1.5mm Thick Bronze Colour Aluminium sliding fixed side (31mm,26mm)

0.6600

m

157.21

103.76

1.5mm Thick Silver Colour Aluminium shutter lock (49.2,26.0mm)

0.6600

m

243.28

160.56

1.5mm Thick Silver Colour Aluminium Inter Lock (34.4, 32.1mm)

1.3100

m

244.83

320.73

Sliding Door Key Lock

0.4800

set

90.00

43.20

Sliding Door Wheel

0.9600

each

45.00

43.20

Sliding Door Mohiar

4.8200

m

3.60

17.35

Sliding Neoprene

4.0800

m

8.20

33.46

Skilled Technician

0.4800

day

680.00

326.40

Semi Skilled Technician

0.4800

day

570.00

273.60

Mason

0.2400

day

550.00

132.00

Ordinary Labour

0.2400

day

370.00

88.80 2617.61

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc. Subtotal-A1: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +7.00 % on Subtotal-A )

183.23 2800.85 Page: 1304 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2856.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3142.55

VAT

6% of Total

IT

4% of Total

209.50 139.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3491.72

Page: 1305 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.05.03

Detailed Analysis Brief Description of Item 2 Bronze colour[Size : 900mmx1400mm]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium outer bottom (75.5mm,17.79mm)

0.7300

m

236.07

172.33

1.5mm Thick Bronze Colour Aluminium outer top (75.5mm,26.8mm)

0.6700

m

352.73

236.33

1.5mm Thick Bronze Colour shutter top (33, 26.8, 22mm)

0.6700

m

210.81

141.24

1.5mm Thick Bronze Colour shutter bottom (60, 24.4mm)

0.7300

m

316.99

231.40

1.5mm Thick Bronze Colour Aluminium outer side (75.5mm,19.9mm)

2.2000

m

238.64

525.01

1.5mm Thick Bronze Colour Aluminium sliding fixed side (31mm,26mm)

1.1100

m

157.21

174.50

1.5mm Thick Bronze Colour Shutter Lock (49.2,26.0mm)

1.1100

m

250.67

278.24

1.5mm Thick Bronze Colour Aluminium Inter lock (34.40,32.1mm)

2.2000

m

251.87

554.11

Sliding Door Key Lock

0.8000

set

90.00

72.00

Sliding Door Wheel

1.6000

each

45.00

72.00

Sliding Door Mohiar

6.5900

m

3.60

23.72

Sliding Neoprene

5.8500

m

8.20

47.97

Skilled Technician

0.8000

day

680.00

544.00

Semi Skilled Technician

0.8000

day

570.00

456.00

Mason

0.4000

day

550.00

220.00

Ordinary Labour

0.4000

day

370.00

148.00 3896.87

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +7.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

272.78 4169.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4253.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4678.35 Page: 1306 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

Amount 8 311.89 207.93

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5198.16

Page: 1307 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.05.04

Detailed Analysis Brief Description of Item 2 Silver colour[Size : 900mmx1400mm]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium outer bottom (75.5,17.79mm)

0.7300

m

229.54

167.56

1.5mm Thick Silver Colour Aluminium outer top (75.5,26.8mm)

0.6700

m

342.59

229.54

1.5mm Thick Silver Colour Aluminium shutter top (35,26.8mm)

0.6700

m

204.63

137.10

1.5mm Thick Silver Colour Aluminium shutter bottom (60,24.4mm)

0.7300

m

307.37

224.38

1.5mm Thick Silver Colour Aluminium outer side (75.5,19.9mm)

2.2000

m

231.77

509.89

1.5mm Thick Silver Colour Aluminium sliding fixed side (31,26mm)

1.1100

m

152.57

169.35

1.5mm Thick Silver Colour Aluminium shutter lock (49.2,26.0mm)

1.1100

m

243.28

270.04

1.5mm Thick Silver Colour Aluminium Inter Lock (34.4, 32.1mm)

2.2000

m

244.83

538.63

Sliding Door Key Lock

0.8000

set

90.00

72.00

Sliding Door Wheel

1.6000

each

45.00

72.00

Sliding Door Mohiar

6.5900

m

3.60

23.72

Sliding Neoprene

5.8500

m

8.20

47.97

Skilled Technician

0.8000

day

680.00

544.00

Semi Skilled Technician

0.8000

day

570.00

456.00

Mason

0.4000

day

550.00

220.00

Ordinary Labour

0.4000

day

370.00

148.00 3830.19

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc. Subtotal-A1: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +7.00 % on Subtotal-A )

268.11 4098.30 Page: 1308 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4180.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4598.30

VAT

6% of Total

IT

4% of Total

306.55 204.37 Total:

5.11.06

5109.22

Supplying, fitting and fixing of aluminium sliding and fixed composite window as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.5mm thick outer bottom (size:75.50mm, 17.79mm), 1.5mm thick outer top (size:75.50mm, 26.80mm), 1.5mm thick shutter top (size:33mm, 26.80mm, 22mm), 1.5mm thick shutter bottom (size:60mm, 24.40mm), 1.5mm thick outer side (size:75.50mm, 19.90mm), 1.5mm thick sliding fixed side (size:31mm, 26mm), 1.5mm thick shutter lock (size:49.20mm, 26.0mm) 1.5mm thick interlock (size:34.40mm, 32.10mm), 1.5mm thick bottom cover (size:37.78mm, 31.78mm), 1.8mm thick bottom (size:76.20mm, 38.10mm, 57.15mm), 1.5mm thick groove cover (size:57.15mm, 15.88mm) and 1.8mm thick top and side (size:76.20mm, 38.10mm, 57.15mm). Sections all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories like handle, locks (Japan), roller, stopper etc. keeping provision for fitting 5mm thick glass in/c neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1309 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.06.01

2 Bronze colour

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium outer bottom (75.5mm,17.79mm)

0.4700

m

236.07

110.95

1.5mm Thick Bronze Colour Aluminium outer top (75.5mm,26.8mm)

0.4700

m

352.73

165.78

1.5mm Thick Bronze Colour shutter top (33, 26.8, 22mm)

0.4500

m

210.81

94.86

1.5mm Thick Bronze Colour shutter bottom (60, 24.4mm)

0.4500

m

316.99

142.65

1.5mm Thick Bronze Colour Aluminium outer side (75.5mm,19.9mm)

0.8400

m

238.64

200.46

1.5mm Thick Bronze Colour Aluminium sliding fixed side (31mm,26mm)

0.4200

m

157.21

66.03

1.5mm Thick Bronze Colour Shutter Lock (49.2,26.0mm)

0.4200

m

250.67

105.28

1.5mm Thick Bronze Colour Aluminium Inter lock (34.40,32.1mm)

0.8400

m

251.87

211.57

1.5mm Thick Bronze Colour Aluminium bottom cover (37.78,31.78mm)

0.4700

m

153.43

72.11

1.8mm Thick Bronze Colour Aluminium bottom (76.2,38.1,57.15mm)

0.4700

m

382.44

179.75

1.5mm Thick Bronze Colour Aluminium groove cover (57.15,15.88mm)

0.6600

m

146.19

96.49

1.8mm Thick Bronze Colour Aluminium top and side (76.2,38.1mm)

1.1700

m

482.96

565.06

Sliding Door Key Lock

0.3100

set

90.00

27.90

Sliding Door Wheel

0.6200

each

45.00

27.90

Sliding Door Mohiar

3.0900

m

3.60

11.12

Sliding Neoprene

2.6200

m

8.20

21.48

Neoprene

3.7500

m

8.20

30.75

Skilled Technician

0.4600

day

680.00

312.80

Semi Skilled Technician

0.4600

day

570.00

262.20

Page: 1310 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Mason

0.1600

day

550.00

88.00

Ordinary Labour

0.1600

day

370.00

59.20 2852.35

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +8.00 % on Subtotal-A )

228.19

Subtotal-A1:

3080.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3142.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3456.36

VAT

6% of Total

IT

4% of Total

230.42 153.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3840.40

Page: 1311 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.06.02

2 Silver colour

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium outer bottom (75.5,17.79mm)

0.4700

m

229.54

107.88

1.5mm Thick Silver Colour Aluminium outer top (75.5,26.8mm)

0.4700

m

342.59

161.02

1.5mm Thick Silver Colour Aluminium shutter top (35,26.8mm)

0.4500

m

204.63

92.08

1.5mm Thick Silver Colour Aluminium shutter bottom (60,24.4mm)

0.4500

m

307.37

138.32

1.5mm Thick Silver Colour Aluminium outer side (75.5,19.9mm)

0.8400

m

231.77

194.69

1.5mm Thick Silver Colour Aluminium sliding fixed side (31,26mm)

0.4200

m

152.57

64.08

1.5mm Thick Silver Colour Aluminium shutter lock (49.2,26.0mm)

0.4200

m

243.28

102.18

1.5mm Thick Silver Colour Aluminium Inter Lock (34.4, 32.1mm)

0.8400

m

244.83

205.66

1.5mm Thick Silver Colour Aluminium bottom cover (37.78,31,78mm)

0.4700

m

106.37

49.99

1.8mm Thick Silver Colour Aluminium bottom (76.2,38.1,57.15mm)

0.4700

m

370.77

174.26

1.5mm Thick Silver Colour Aluminium groove cover (57.15,15.88m)

0.6600

m

157.44

103.91

1.8mm Thick Silver Colour Aluminium top and side (76.2, 38.1mm)

1.1700

m

468.87

548.58

Sliding Door Key Lock

0.3100

set

90.00

27.90

Sliding Door Wheel

0.6200

each

45.00

27.90

Sliding Door Mohiar

3.0900

m

3.60

11.12

Sliding Neoprene

2.6200

m

8.20

21.48

Neoprene

3.7500

m

8.20

30.75

Page: 1312 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Skilled Technician

0.4600

day

680.00

312.80

Semi Skilled Technician

0.4600

day

570.00

262.20

Mason

0.1600

day

550.00

88.00

Ordinary Labour

0.1600

day

370.00

59.20 2784.00

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +8.00 % on Subtotal-A )

222.72

Subtotal-A1:

3006.72

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3066.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3373.54

VAT

6% of Total

224.90

IT

4% of Total

149.94 Total:

5.11.07

3748.38

Supplying, fitting and fixing of aluminium top hung/casement windows as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.5mm thick casement outer (size:38.86mm, 36.63mm), 1.5mm thick casement outer (size:38.86mm, 36.63mm), 1.5mm thick casement shutter (size:47.62mm, 28.57mm, 40.82mm) and 1.245mm thick shutter glass clip (size:15.87mm, 27mm). Sections of all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories keeping provision for fitting 5mm thick glass in/c neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1313 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.07.01

2 Bronze colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium Casement outer (38.86, 38.86,36.63mm)

3.8200

m

159.27

608.41

1.5mm Thick Bronze Colour Aluminium Casement shutter (47.62,28.57,40.82mm)

6.0100

m

277.82

1669.70

1.245mm Thick Bronze Colour Aluminium shutter glass clip(15.87,27mm)

6.0100

m

61.23

367.99

25x25mm Bronze Colour Aluminium Pipe

1.0900

m

56.53

61.62

4-Bar Hinge

3.4800

each

135.00

469.80

Casement Handle

1.7900

each

189.00

338.31

Skilled Technician

1.8000

day

680.00

1224.00

Semi Skilled Technician

1.8000

day

570.00

1026.00

Mason

0.2300

day

550.00

126.50

Ordinary Labour

0.2300

day

370.00

85.10 5977.43

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6814.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6950.56

10% Profit ( Add 10% on Subtotal-B) :

7645.61

VAT

6% of Total

IT

4% of Total

509.71 339.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

836.84

8495.12

Page: 1314 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.07.02

2 Silver colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium casement outer (38.86, 36.63mm)

3.8200

m

153.94

588.05

1.5mm Thick Silver Colour Aluminium casement shutter (47.62,28.57,40.82mm)

6.0100

m

269.74

1621.14

1.245mm Thick Silver Colour Aluminium shutter glass clip (15.87,27mm)

6.0100

m

61.00

366.61

25x25mm Silver Colour Aluminium Pipe

1.0900

m

54.64

59.56

4-Bar Hinge

3.4800

each

135.00

469.80

Casement Handle

1.7900

each

189.00

338.31

Skilled Technician

1.8000

day

680.00

1224.00

Semi Skilled Technician

1.8000

day

570.00

1026.00

Mason

0.2300

day

550.00

126.50

Ordinary Labour

0.2300

day

370.00

85.10 5905.07

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6731.77 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6866.41

10% Profit ( Add 10% on Subtotal-B) :

7553.05

VAT

6% of Total

IT

4% of Total

503.54 335.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

826.71

8392.28

Page: 1315 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.08

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, fitting and fixing of aluminium corrugated curtain wall as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.5mm thick bottom cover (size:37.78mm, 31.78mm), 1.5mm thick bottom (size:76.20mm, 38.10mm, 57.15mm), 1.8mm thick groove cover (size:57.15mm, 15.88mm), 1.5mm thick top and side (size:76.2mm, 38.10mm, 57.15mm) and 1.10mm thick spandrel (size:106,6.20mm) sections of all Aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories, neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1316 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.08.01

Detailed Analysis Brief Description of Item 2 Bronze colour[Size : 3000mmx2100mm]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium bottom cover (37.78,31.78mm)

1.4100

m

153.43

216.34

1.5mm Thick Bronze Colour Aluminium bottom (76.2,38.1,57.15mm)

1.4100

m

329.36

464.40

1.8mm Thick Bronze Colour Aluminium Groove Cover (57.15,15.88mm)

0.6600

m

201.17

132.77

1.5mm Thick Bronze Colour Aluminium top and side (76.2,38.1,57.15mm)

1.7800

m

405.47

721.74

1.10mm Thick Bronze Colour Aluminium spandrel (106.00,6.20mm)

7.8700

m

204.80

1611.78

15.3600

each

0.30

4.61

Rivet (for aluminium works) Screw (for aluminium works)

2.1500

each

1.00

2.15

31.3400

m

8.20

256.99

Skilled Technician

0.4600

day

680.00

312.80

Semi Skilled Technician

0.4600

day

570.00

262.20

Mason

0.1600

day

550.00

88.00

Ordinary Labour

0.1600

day

370.00

59.20

Neoprene

4132.96

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +7.00 % on Subtotal-A )

289.31

Subtotal-A1: Subtotal-B: Subtotal-C:

4422.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4510.72

10% Profit ( Add 10% on Subtotal-B) :

4961.79

VAT

6% of Total

IT

4% of Total

330.79 220.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5513.10

Page: 1317 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.08.02

Detailed Analysis Brief Description of Item 2 Silver colour[Size : 3000mmx2100mm]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium bottom cover (37.78,31,78mm)

1.4100

m

106.37

149.98

1.5mm Thick Silver Colour Aluminium bottom (76.2,38.1,57.15mm)

1.4100

m

319.57

450.59

1.8mm Thick Silver Colour Aluminium groove cover (57.15,15.88mm)

0.6600

m

157.44

103.91

1.5mm Thick Silver Colour Aluminium top and side (76.2,38.1,57.15mm)

1.7800

m

394.30

701.85

1.10mm Thick Silver Colour Spandrel (106.00,6.20mm)

7.8700

m

200.67

1579.27

Rivet (for aluminium works)

15.3600

each

0.30

4.61

Screw (for aluminium works)

2.1500

each

1.00

2.15

31.3400

m

8.20

256.99

Neoprene Skilled Technician

0.4600

day

680.00

312.80

Semi Skilled Technician

0.4600

day

570.00

262.20

Mason

0.1600

day

550.00

88.00

Ordinary Labour

0.1600

day

370.00

59.20 3971.56

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +7.00 % on Subtotal-A )

278.01

Subtotal-A1:

4249.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4334.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4768.02

VAT

6% of Total

IT

4% of Total

317.87 211.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5297.79

Page: 1318 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.08.03

Detailed Analysis Brief Description of Item 2 Bronze colour[Size : 3000mmx750mm]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium bottom cover (37.78,31.78mm)

1.3100

m

153.43

200.99

1.5mm Thick Bronze Colour Aluminium bottom (76.2,38.1,57.15mm)

1.3100

m

329.36

431.46

1.8mm Thick Bronze Colour Aluminium Groove Cover (57.15,15.88mm)

0.6600

m

201.17

132.77

1.5mm Thick Bronze Colour Aluminium top and side (76.2,38.1,57.15mm)

2.6200

m

405.47

1062.33

1.10mm Thick Bronze Colour Aluminium spandrel (106.00,6.20mm)

7.8700

m

204.80

1611.78

29.2500

each

0.30

8.78

Screw (for aluminium works)

8.6000

each

1.00

8.60

Neoprene

9.1800

m

8.20

75.28

Skilled Technician

0.6600

day

680.00

448.80

Semi Skilled Technician

0.6600

day

570.00

376.20

Mason

0.2200

day

550.00

121.00

Ordinary Labour

0.2200

day

370.00

81.40

Rivet (for aluminium works)

4559.39

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +7.00 % on Subtotal-A )

319.16

Subtotal-A1: Subtotal-B: Subtotal-C:

4878.54 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4976.11

10% Profit ( Add 10% on Subtotal-B) :

5473.72

VAT

6% of Total

IT

4% of Total

364.91 243.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6081.92

Page: 1319 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.08.04

Detailed Analysis Brief Description of Item 2 Silver colour[Size : 3000mmx750mm]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium bottom cover (37.78,31,78mm)

1.3100

m

106.37

139.34

1.5mm Thick Silver Colour Aluminium bottom (76.2,38.1,57.15mm)

1.3100

m

319.57

418.64

1.8mm Thick Silver Colour Aluminium groove cover (57.15,15.88mm)

0.6600

m

157.44

103.91

1.5mm Thick Silver Colour Aluminium top and side (76.2,38.1,57.15mm)

2.6200

m

394.30

1033.07

1.10mm Thick Silver Colour Spandrel (106.00,6.20mm)

7.8700

m

200.67

1579.27

Rivet (for aluminium works)

29.2500

each

0.30

8.78

Screw (for aluminium works)

8.6000

each

1.00

8.60

Neoprene

9.1800

m

8.20

75.28

Skilled Technician

0.6600

day

680.00

448.80

Semi Skilled Technician

0.6600

day

570.00

376.20

Mason

0.2200

day

550.00

121.00

Ordinary Labour

0.2200

day

370.00

81.40 4394.28

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +7.00 % on Subtotal-A )

307.60

Subtotal-A1:

4701.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4795.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5275.51

VAT

6% of Total

IT

4% of Total

351.70 234.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5861.68

Page: 1320 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.09

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, fitting and fixing of aluminium fixed fan light as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.5mm thick bottom cover (17.40mmx31.78mm), 1.5mm thick bottom (76.20mmx38.10mm) sections of all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories, neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1321 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.09.01

2 Bronze colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Bronze Colour Aluminium bottom cover (31.78,17.4mm)

1.4600

m

153.43

224.01

1.5mm Thick Bronze Colour Aluminium bottom (76.2,38.1,57.15mm)

1.4600

m

329.36

480.87

1.8mm Thick Bronze Colour Aluminium Groove Cover (57.15,15.88mm)

0.6600

m

201.17

132.77

1.5mm Thick Bronze Colour Aluminium top and side (76.2,38.1,57.15mm)

3.4200

m

405.47

1386.71

Neoprene

11.6600

m

8.20

95.61

Skilled Technician

0.4800

day

680.00

326.40

Semi Skilled Technician

0.4800

day

570.00

273.60

Mason

0.2400

day

550.00

132.00

Ordinary Labour

0.2400

day

370.00

88.80 3140.77

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +15.00 % on Subtotal-A )

Subtotal-A1:

3611.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3684.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4052.53

VAT

6% of Total

IT

4% of Total

270.17 180.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

471.11

4502.81

Page: 1322 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.09.02

2 Silver colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 1.5mm Thick Silver Colour Aluminium bottom Cover (31.78,17.4mm)

1.4600

m

106.37

155.30

1.5mm Thick Silver Colour Aluminium bottom (76.2,38.1,57.15mm)

1.4600

m

319.57

466.57

1.8mm Thick Silver Colour Aluminium groove cover (57.15,15.88mm)

0.6600

m

157.44

103.91

1.5mm Thick Silver Colour Aluminium top and side (76.2,38.1,57.15mm)

3.4200

m

394.30

1348.51

Neoprene

11.6600

m

8.20

95.61

Skilled Technician

0.4800

day

680.00

326.40

Semi Skilled Technician

0.4800

day

570.00

273.60

Mason

0.2400

day

550.00

132.00

Ordinary Labour

0.2400

day

370.00

88.80 2990.70

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +15.00 % on Subtotal-A )

Subtotal-A1:

3439.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3508.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3858.90

VAT

6% of Total

IT

4% of Total

257.26 171.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

448.61

4287.67

Page: 1323 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.11.10

Supplying fitting and fixing of aluminium fixed louver as per the U.S. Architectural Aluminium Manufacturer’s Association (AAMA) standard specification having 1.5mm thick wall frame (size:76.20mm, 38.10mm), 1.25mm thick louver section (size:55.02mm, 37.39mm) and 1.5mm thick louver outer section (size:39.67mm, 15.06mm) and inner inclined aluminium louver section fixed with above mentioned frames and all aluminium members will be anodized to aluminium bronze/silver colour with a coat not less than 15 microns in thickness and density of 4mg/cm2 etc. in/c all accessories neoprene, sealant for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

5.11.10.01

Bronze colour

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

4.5000

m

298.43

1342.94

26.2300

m

128.28

3364.78

1.5mm Thick Bronze Colour Aluminium lover outer section (39.67,15.06mm)

1.6400

m

124.73

204.56

Skilled Technician

0.6000

day

680.00

408.00

Semi Skilled Technician

0.6000

day

570.00

342.00

5

Amount 8

sqm 1.5mm Thick Bronze Colour Aluminium wall frame(76.2,38.1mm) 1.25mm Thick Bronze Colour Aluminium Lover Section (55.02,37.39mm)

5662.28

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

6341.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6468.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7115.44

VAT

6% of Total

474.36

IT

4% of Total

316.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

679.47

7906.05

Page: 1324 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.10.02

2 Silver colour

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

4.5000

m

289.16

1301.22

26.2300

m

124.91

3276.39

1.6400

m

120.95

198.36

5

Amount 8

sqm 1.5mm Thick Silver Colour Aluminium wall frame (76.2,38.1mm) 1.5mm Thick Silver Colour Aluminium lover section (55.02,37.39mm) 1.5mm Thick Silver Colour Aluminium lover outer section (39.57,15.06mm) Skilled Technician

0.6000

day

680.00

408.00

Semi Skilled Technician

0.6000

day

570.00

342.00 5525.97

Subtotal-A: All other remaining costs covering bolts, screws, machine charges, electricity, wastages, etc.

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6189.08 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6312.87

10% Profit ( Add 10% on Subtotal-B) :

6944.15

VAT

6% of Total

IT

4% of Total

462.94 308.63 Total:

5.11.11

663.12

7715.72

Supplying, fitting and fixing distortion free 5mm thick tinted glass of approved quality and shade in aluminium door frames, partitions /windows in/c cost of fitting, fixing all necessary accessories for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1325 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.11.11.01

2 Bronze colour

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 5mm Thick tinted glass

1.0500

m2

810.00

850.50

Skilled Labour

0.6200

day

450.00

279.00 1129.50

Subtotal-A: Cost of neoprene/rubber gasket,carriage, & other remaining cost etc.

( +9.00 % on Subtotal-A )

101.66

Subtotal-A1: Subtotal-B: Subtotal-C:

1231.16 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1255.78

10% Profit ( Add 10% on Subtotal-B) :

1381.36

VAT

6% of Total

IT

4% of Total

92.09 61.39 Total:

5.11.11.02

Silver colour

sqm 5mm Thick tinted glass

1.0500

m2

810.00

850.50

Skilled Labour

0.6200

day

450.00

279.00 1129.50

Subtotal-A: Cost of neoprene/rubber gasket,carriage, & other remaining cost etc.

( +9.00 % on Subtotal-A )

101.66

Subtotal-A1:

1231.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1255.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1381.36

VAT

6% of Total

IT

4% of Total

92.09 61.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1534.84

1534.84

Page: 1326 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.12

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of approved colour (4mm thick) Aluminum composite panel (Alucobond/ Alcopanel/ Alpolic) as per US Architectural Aluminum Manufacturer’s Association (AAMA)in column, beam and wall surface providing with 44x44x1.5 mm aluminum section including supply of necessary hardwares, consumbales, scaffolding etc. fitted with necessary accessories like, rivet, screw, rowel bolt for all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Aluminium box 44 mm X 44 mm

1.1800

m

280.93

331.50

Aluminium angle 25 mm X 25 mm

5.0800

m

72.85

370.08

Aluminium composite panel

1.0500

sqm

1560.00

1638.00 2339.58

Subtotal-A: Supply of necessary fitting angles,accessoriesrivet, SS screw, fitting technicians,scaffolding, local carriages,etc.including cost and charges etc.

( +16.00 % on Subtotal-A )

Subtotal-A1:

2713.91

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2768.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3045.00

VAT

6% of Total

203.00

IT

4% of Total

135.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

374.33

3383.34

Page: 1327 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.13

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of Aluminum curtain wall and Aluminum top hung / basement windows as per the US Architectural Aluminum Manufacturer’s Association (AAMA)Standard Specification having 100mmx50mmx2mm curtain wall sub - mullim outer and inner frame,15 mm thick casement outer frame (size38mmx36mm),1.9 mm thick casement shutter (size 47mmx28mm)1.2 mm thick shutter glass strips, all Aluminum member will be powder coated with coal not less than 1.5 micron in thickness including all accessories 4 bar hinge casement handle,50m x 50mm x 6m Aluminum angle ,steel rowel bolt, screws, rivets norton tape masking tape ,structural sealant, gum bracket rod for all floors etc. all complete in all respect as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Aluminium curtain wall sub mullium (100 mm X 50 mm X 2.0 mm)

2.9200

m

1120.28

3271.22

Aluminium casement outer frame (29 mm X 20 mm X 1.2 mm)

0.9700

m

131.19

127.25

Aluminium casement outer section (52 mm X 22 mm X 1.5 mm)

0.9700

m

485.00

470.45

Aluminium angle (50 mm X 50 mm X 6.2 mm)

0.1100

m

636.48

70.01

Aluminium cover (50 mm X 6 mm X 1.5 mm)

0.2400

m

115.28

27.67

Aluminium angle (50 mm X 6 mm X 1.5 mm) for casement shutter

0.0800

m

175.00

14.00 3980.60

Subtotal-A: Supply and charge of hardware accessories, like steel rowel bolt, 2 inch SS screw, rivets(big), rivets(normal), norton tap, masking tape, structural

( +64.00 % on Subtotal-A )

Subtotal-A1:

6528.19

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6658.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7324.63

VAT

6% of Total

IT

4% of Total

488.31 325.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2547.59

8138.47

Page: 1328 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.14

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of Aluminum curtain wall and Aluminum top hung / basement windows as per the US Architectural Aluminum Manufacturer’s Association (AAMA)Standard Specification having 50mmx50mmx2mm curtain wall sub - mullim outer and inner frame,15 mm thick casement outer frame (size38mmx36mm),1.9 mm thick casement shutter (size 47mmx28mm)1.2 mm thick shutter glass strips, all Aluminum member will be powder coated with coal not less than 1.5 micron in thickness including all accessories 4 bar hinge casement handle,50m x 50mm x 6m Aluminum angle ,steel rowel bolt, screws, rivets norton tape masking tape ,structural sealant, gum bracket rod for all floors etc. all complete in all respect as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Aluminium curtain wall sub mullium (50 mm X 50 mm X 2.0 mm)

2.9200

m

997.53

2912.79

Aluminium casement outer frame (29 mm X 20 mm X 1.2 mm)

0.9700

m

131.19

127.25

Aluminium casement outer section (52 mm X 22 mm X 1.5 mm)

0.9700

m

485.00

470.45

Aluminium angle (50 mm X 50 mm X 6.2 mm)

0.1100

m

636.48

70.01

Aluminium cover (50 mm X 6 mm X 1.5 mm)

0.2400

m

115.28

27.67

Aluminium angle (50 mm X 6 mm X 1.5 mm) for casement shutter

0.0800

m

175.00

14.00 3622.17

Subtotal-A: Supply and charge of hardware accessories, like steel rowel bolt, 2 inch SS screw, rivets(big), rivets(normal), norton tap, masking tape, structural

( +88.00 % on Subtotal-A )

Subtotal-A1:

6809.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6945.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7640.46

VAT

6% of Total

IT

4% of Total

509.36 339.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3187.51

8489.41

Page: 1329 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.15

Detailed Analysis Brief Description of Item 2 Supplying, fitting, fixing of Aluminum sliding fly proof Netting shutter as per the U. S. Architectural Aluminum Manufacturer’s Association (AAMA) standard specification having 1mm thick 38mm x18mm Aluminum outer frame ,1mm thick 38mm x 12mm mosquito net shutter frame (mesh section). All Aluminum members (total weight 12.79 kg) will be anodized to Aluminum SS / bronze / silver colour with a coat not less then 15 micron in thickness and density of 4 mg per square cm etc. including all accessories like wheel, sealent, rubber, bolts and nuts keeping provision for fitting fiber mesh including labour charge for fitting of accessories, making grooves and mending good damages, carriage, and erecting complete for all floors in all respect as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Aluminium frame 38 mmX 38 mm X 1.5 mm thickness(wall box)

2.8600

m

126.00

360.36

Aluminium frame 38 mmX 12 mm X 1.5 mm thickness(netting shutter)

4.3600

m

200.33

873.44

Mosquito net (plastic)

1.0500

sqm

140.00

147.00 1380.80

Subtotal-A: fitting and fixing accessories-wheel, sealant, rubber, bolt, screws, technician, tools, etc.

( +26.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1739.81 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1774.60

10% Profit ( Add 10% on Subtotal-B) :

1952.06

VAT

6% of Total

IT

4% of Total

130.14 86.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

359.01

2168.96

Page: 1330 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.16

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing verandah drop or ventilation Grill or anywhere directed made of 100mm Aluminum Z-louver series of minimum wall thickness 1mm @ 90mm c/c horizontally in inclined of Bronze color and fitted with Aluminum Z-louver outer section and stiffener 60mmx18mm size of 1.2mm thick fixed by Aluminum fitting angle of 30mmx30mm of 3mm thick with RCC work or brick work by SS screw in/c. drilling holes for all floors etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Aluminum Z-lover 100mm, 1mm thick Bronze colour

10.6400

m

232.10

2469.54

Aluminum Z-lover outer section 60mmx18mm, 1.2mm thick Bronze colour

3.7030

m

189.62

702.16

Aluminum fitting angle 30mmx30mm, 3mm thick

1.5750

m

265.06

417.47

Skilled Technician

0.6000

day

680.00

408.00

Semi Skilled Technician

0.6000

day

570.00

342.00 4339.18

Subtotal-A: fitting and fixing accessoriesl, sealant, rubber, bolt, screws, tools, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

4773.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4868.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5355.41

VAT

6% of Total

357.03

IT

4% of Total

238.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

433.92

5950.46

Page: 1331 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.17

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing verandah drop or ventilation Grill or anywhere directed made of 100mmx25mm Aluminum rectangular box louver series of minimum wall thickness 1mm @100mm c/c horizontally in inclined of Bronze color and fitted with Aluminum outer section and stiffener of 100mmx25mm size of 1mm thick fixed by Aluminum fitting angle of 30mmx30mm of 3mm thick with RCC work or brick work by SS screw in/c. drilling holes for all floors etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Aluminum rectangular box lover 25mmx100mm, 1mm thick Bronze colour

7.3300

m

366.42

2685.86

Aluminum rectangular outer section 25mmx100mm, 1mm thick Bronze colour

2.1080

m

366.42

772.41

Aluminum fitting angle 30mmx30mm, 3mm thick

1.1900

m

265.06

315.42

Skilled Technician

0.6000

day

680.00

408.00

Semi Skilled Technician

0.6000

day

570.00

342.00 4523.69

Subtotal-A: fitting and fixing accessoriesl, sealant, rubber, bolt, screws, tools, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4976.06 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5075.58

10% Profit ( Add 10% on Subtotal-B) :

5583.14

VAT

6% of Total

IT

4% of Total

372.21 248.14 Total:

5.11.18

452.37

6203.49

Supplying, fitting and fixing in Aluminum door frames, window, partitions and curtain wall distortion free glass of approved quality and shade including cost of fitting fixing all necessary accessories all floors etc. complete in all respect as per drawing and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1332 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.11.18.01

2 5mm thick clear glass

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 5mm thick glass

1.0500

m2

700.00

735.00

Skilled Labour

0.6200

day

450.00

279.00 1014.00

Subtotal-A: Cost of neoprene/rubber gasket,carriage, & other remaining cost etc.

( +9.00 % on Subtotal-A )

91.26

Subtotal-A1: Subtotal-B: Subtotal-C:

1105.26 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1127.37

10% Profit ( Add 10% on Subtotal-B) :

1240.10

VAT

6% of Total

IT

4% of Total

82.67 55.12 Total:

5.11.18.02

5 mm thick tinted glass

sqm 5mm Thick tinted glass

1.0500

m2

810.00

850.50

Skilled Labour

0.6200

day

450.00

279.00 1129.50

Subtotal-A: Cost of neoprene/rubber gasket,carriage, & other remaining cost etc.

( +9.00 % on Subtotal-A )

101.66

Subtotal-A1:

1231.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1255.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1381.36

VAT

6% of Total

IT

4% of Total

92.09 61.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1377.89

1534.84

Page: 1333 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.11.18.03

2 5 mm thick ambushed/frosted glass

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 5 mm thick ambushed/frosted glass

1.0500

sqm

700.00

735.00

Skilled Labour

0.6200

day

450.00

279.00 1014.00

Subtotal-A: Cost of neoprene/rubber gasket,carriage, & other remaining cost etc.

( +9.00 % on Subtotal-A )

91.26

Subtotal-A1: Subtotal-B: Subtotal-C:

1105.26 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1127.37

10% Profit ( Add 10% on Subtotal-B) :

1240.10

VAT

6% of Total

IT

4% of Total

82.67 55.12 Total:

5.11.18.04

6 mm thick reflecting glass

sqm 6 mm thick reflecting glass

1.0500

sqm

915.00

960.75

Skilled Labour

0.6200

day

450.00

279.00 1239.75

Subtotal-A: Cost of neoprene/rubber gasket,carriage, & other remaining cost etc.

( +9.00 % on Subtotal-A )

111.58

Subtotal-A1:

1351.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1378.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1516.19

VAT

6% of Total

IT

4% of Total

101.08 67.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1377.89

1684.65

Page: 1334 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.19

Detailed Analysis Brief Description of Item 2 Supplying fitting and fixing 10 mm thick clear tempered glass swing door including all accessories 1 set floor mounted auto closer special quality, 2 nos. top & bottom clamping device, 1 set locking device with heavy duty lock & key, top hinge (pivot) and handle for all floor etc. complete in all respect as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10 mm thick tempered glass

1.0300

sqm

2421.00

2493.63

Subtotal-A: Cost of floor mounted auto closure(Taiwan origin), clamping device top and bottom, locking device,top hinge(pivot), handle, labour cost, scaffolding

( +54.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1346.56

3840.19 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3916.99

10% Profit ( Add 10% on Subtotal-B) :

4308.69

VAT

6% of Total

IT

4% of Total

287.25 191.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2493.63

4787.44

Page: 1335 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.20

Detailed Analysis Brief Description of Item 2 Supplying fitting and fixing 10 mm thick clear glass partition with 44 mm x 44 mm x 1.5 mm aluminum box, protector bit (single) as necessary protector bit (double) in/c all accessories for all floors etc. all complete and as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10 mm thick clear glass

1.0300

sqm

Aluminium frame 44 mmX 44 mm X 1.5 mm thickness(box)

0.5000

m

1452.00

1495.56

94.79

47.40 1542.96

Subtotal-A: Cost of protector bit- single & double,SS screw, silicon, rowel plug, rivet, labour, carriage, etc

( +45.00 % on Subtotal-A )

Subtotal-A1:

2237.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2282.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2510.23

VAT

6% of Total

167.35

IT

4% of Total

111.57 Total:

5.11.21

Taking off any type of Aluminum door and window frames & shutter i/c fixed partitions sections and glass without any damages for reuse (as per possible) by any means including selecting, storing and stacking properly in measurable stacks after carrying those to a safe distance or preselected place, etc. all complete as per direction of the E-I-C.

2789.15

sqm

Skilled Technician

0.0700

day

680.00

47.60

Semi Skilled Technician

0.0700

day

570.00

39.90 87.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

89.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

98.18

VAT

6% of Total

6.55

IT

4% of Total

4.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

694.33

109.08

Page: 1336 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.22

Detailed Analysis Brief Description of Item 2 Re-fixing work of Aluminum partition by the existing same partition materials as per requirement and proper alignment in/c cutting in proper size and cost of supply of new neoprene, sealant for all floor etc. complete in all respect as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Neoprene

3.7500

m

8.20

Skilled Technician

0.2500

day

680.00

170.00

Semi Skilled Technician

0.2500

day

570.00

142.50 343.25

Subtotal-A: All other remaining costs covering bolts, screws, machine charge, electricity, etc.

( +8.00 % on Subtotal-A )

27.46

Subtotal-A1: Subtotal-B: Subtotal-C:

370.71 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

378.12

10% Profit ( Add 10% on Subtotal-B) :

415.94

VAT

6% of Total

IT

4% of Total

27.73 18.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

30.75

462.15

Page: 1337 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.23

Detailed Analysis Brief Description of Item 2 Supplying, fitting & fixing door lock & key heavy duty for Aluminum swing door shutter i/c necessary accessories best quality etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Swing door lock for aluminum shutter

1.0000

each

650.00

650.00

Skilled Technician

0.2000

day

680.00

136.00 786.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

7.86

Subtotal-A1:

793.86

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

809.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

890.71

VAT

6% of Total

59.38

IT

4% of Total

39.59 Total:

5.11.24

Supplying, fitting & fixing swing door bottom lock & key heavy duty for tempered glass swing door shutter i/c necessary accessories best quality etc. all complete as per direction of the E-I-C.

each

Swing door bottom lock of tempered glass

1.0000

each

700.00

700.00

Skilled Technician

0.2000

day

680.00

136.00 836.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

8.36

Subtotal-A1:

844.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

861.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

947.37

VAT

6% of Total

63.16

IT

4% of Total

42.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

989.68

1052.64

Page: 1338 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.25

Detailed Analysis Brief Description of Item 2 Supplying, fitting & fixing door closer heavy duty for Aluminum swing door shutter i/c necessary accessories best quality etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Swing door closer for aluminum shutter

1.0000

each

3000.00

3000.00

Skilled Technician

0.4000

day

680.00

272.00 3272.00

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

65.44

Subtotal-A1:

3337.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3404.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3744.61

VAT

6% of Total

249.64

IT

4% of Total

166.43 Total:

5.11.26

Supplying, fitting & fixing door lock with key for Aluminum sliding door shutter of heavy duty best quality etc. all complete as per direction of the E-I-C.

each

Sliding door lock for aluminum shutter

1.0000

each

90.00

90.00

Skilled Technician

0.1000

day

680.00

68.00 158.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.58

Subtotal-A1:

159.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

162.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

179.05

VAT

6% of Total

11.94

IT

4% of Total

7.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4160.68

198.94

Page: 1339 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.11.27

Detailed Analysis Brief Description of Item 2 Supplying, fitting & fixing Aluminum sliding window lock of heavy duty of best quality etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Sliding window lock for aluminum shutter

1.0000

each

45.00

45.00

Skilled Technician

0.1000

day

680.00

68.00 113.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.13

Subtotal-A1: Subtotal-B: Subtotal-C:

114.13 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

116.41

10% Profit ( Add 10% on Subtotal-B) :

128.05

VAT

6% of Total

IT

4% of Total

8.54 5.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

142.28

Page: 1340 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.01

Detailed Analysis Brief Description of Item 2 Minimum 12mm thick cement plaster (1:4) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) to dado, plinth wall up to 150mm below ground level, water tank or any where directed with neat cement finishing in/c washing of sand, racking out joint and picking up cement morter i/c finishing the edges and corners and curing for the requisite period etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Sand (FM - 1.2)

0.0150

m3

584.00

8.76

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1620

bag

430.00

69.66

Head Mason

0.0270

day

650.00

17.55

Mason

0.1080

day

550.00

59.40

Ordinary Labour

0.1080

day

370.00

39.96 195.33

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

214.86 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

219.16

10% Profit ( Add 10% on Subtotal-B) :

241.08

VAT

6% of Total

IT

4% of Total

16.07 10.71 Total:

5.12.02

19.53

267.86

Minimum 12mm thick cement plaster (1:6) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) to wall both inner and outer surface, finishing the corner and edges in/c washing of sand cleaning the surface, scaffolding and curing for the requisite period etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1341 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.12.02.01

2 Ground floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sand (FM - 1.2)

0.0180

m3

584.00

10.51

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0800

bag

430.00

34.40

Head Mason

0.0270

day

650.00

17.55

Mason

0.1080

day

550.00

59.40

Ordinary Labour

0.1080

day

370.00

39.96 161.82

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

184.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

188.17

10% Profit ( Add 10% on Subtotal-B) :

206.98

VAT

6% of Total

IT

4% of Total

13.80 9.20 Total:

5.12.02.02

Add for each additional floor for 5th floor

sqm

Add +2.00% with Item No 5.12.02.01

5.12.02.03

Add for each additional floor for 6th floor and above

sqm

Add +4.00% with Item No 5.12.02.01

5.12.03

Minimum 6mm thick cement plaster (1:4) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) to ceiling RCC columns, beams, surface of stair case, sunshades, cornices, railings, drop wall, louvers, fins and finishing the corners and edges in/c washing of sand cleaning the surface, scaffolding and curing for the requisite period etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

22.66

229.98

Page: 1342 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.12.03.01

2 Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sand (FM - 1.2)

0.0090

m3

584.00

5.26

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0540

bag

430.00

23.22

Head Mason

0.0270

day

650.00

17.55

Mason

0.1080

day

550.00

59.40

Ordinary Labour

0.1080

day

370.00

39.96 145.39

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +16.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

168.65 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

172.02

10% Profit ( Add 10% on Subtotal-B) :

189.22

VAT

6% of Total

IT

4% of Total

12.61 8.41 Total:

5.12.03.02

Add for each additional floor upto 5th floor

sqm

Add +3.57% with Item No 5.12.03.01

5.12.03.03

Add for each additional floor for 6th floor and above

sqm

Add +5.36% with Item No 5.12.03.01

Note : Rates of all items should be inclusive of all supply and carriage.

23.26

210.25

Page: 1343 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.04

Detailed Analysis Brief Description of Item 2 Taking off defective cement plaster from walls, ceilings, beams, floors or wherever required in/c taking out joints cleaning the surface and removing the debris to a pre-selected place etc. all completed as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Ordinary Labour

0.2000

day

370.00

74.00

Skilled Labour

0.0120

day

450.00

5.40 79.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

80.99

10% Profit ( Add 10% on Subtotal-B) :

89.09

VAT

6% of Total

IT

4% of Total

5.94 3.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

98.99

Page: 1344 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.05

Detailed Analysis Brief Description of Item 2 Providing black board (3.66mx1.22m/2.44mmx1.22mm or directed size) made of 12mm thick cement sand plaster of proportion (1:3) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) on walls finished smooth with cement grouting mixed with black oxide board paint over the cement finishing etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1614

bag

430.00

69.40

Sand (FM - 1.2)

0.0143

m3

584.00

8.35

Head Mason

0.0269

day

650.00

17.49

Mason

0.1345

day

550.00

73.98

Ordinary Labour

0.1345

day

370.00

49.77 218.98

Subtotal-A: All other remaining costs covering washing of sand, scaffolding, black oxide powder, curing, sundries etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

262.77 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

268.03

10% Profit ( Add 10% on Subtotal-B) :

294.83

VAT

6% of Total

19.66

IT

4% of Total

13.10 Total:

5.12.06

43.80

327.59

Flush pointing to brick wall with cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) in/c raking out the joints and necessary scaffolding, curing for the requisite period etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1345 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.12.06.01

2 Ground floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sand (FM - 1.2)

0.0030

m3

584.00

1.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0430

bag

430.00

18.49

Head Mason

0.0270

day

650.00

17.55

Mason

0.0540

day

550.00

29.70

Ordinary Labour

0.1080

day

370.00

39.96 107.45

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

122.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

124.95

10% Profit ( Add 10% on Subtotal-B) :

137.44

VAT

6% of Total

IT

4% of Total

9.16 6.11 Total:

5.12.06.02

Add for each additional floor up to 5th floor

sqm

Add +5.00% with Item No 5.12.06.01

5.12.06.03

Add for 6th floor and above

sqm

Add +7.70% with Item No 5.12.06.01

Note : Rates of all items should be inclusive of all supply and carriage.

15.04

152.71

Page: 1346 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.07

Detailed Analysis Brief Description of Item 2 Flush pointing to CC Block laying for Pavement works with cement concrete mortar (1:2:4) ) with Portland Composite cement (CEM II/AM, 42.5N, best quality sand (minimum FM1.2) and 10mm down well graded picked brick chips in/c raking out the joints and curing for the requisite period etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick Chips (10mm down graded)

0.0054

m3

3049.00

16.46

Sand (FM - 1.2)

0.0027

m3

584.00

1.58

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0380

bag

430.00

16.34

Mason

0.0125

day

550.00

6.88

Skilled Labour

0.0225

day

450.00

10.13

Ordinary Labour

0.0500

day

370.00

18.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0005

day

1200.00

0.60 70.48

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

71.89

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

79.08

VAT

6% of Total

IT

4% of Total

5.27 3.51 Total:

5.12.08

87.87

Rule pointing to brick wall with cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) and raking out the joints, scaffolding, curing for the requisite period etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1347 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.12.08.01

2 Ground floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sand (FM - 1.2)

0.0050

m3

584.00

2.92

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0540

bag

430.00

23.22

Head Mason

0.0270

day

650.00

17.55

Mason

0.1080

day

550.00

59.40

Ordinary Labour

0.1080

day

370.00

39.96 143.05

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

157.36 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

160.50

10% Profit ( Add 10% on Subtotal-B) :

176.55

VAT

6% of Total

IT

4% of Total

11.77 7.85 Total:

5.12.08.02

Add for each additional floor upto 5th floor

sqm

Add +4.00% with Item No 5.12.08.01

5.12.08.03

Add for 6th floor and above

sqm

Add +6.00% with Item No 5.12.08.01

5.12.09

Raised/tack pointing to brick wall with cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) with minimum size (12mmx20mm) in/c raking out the joints, necessary scaffolding, curing at least for 7 days, cleaning each and every brick, cutting the bricks with pumice stone where necessary etc. all complete in all floors as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

14.31

196.17

Page: 1348 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.12.09.01

2 Ground floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sand (FM - 1.2)

0.0090

m3

584.00

5.26

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1080

bag

430.00

46.44

Head Mason

0.0540

day

650.00

35.10

Mason

0.2150

day

550.00

118.25

Ordinary Labour

0.2150

day

370.00

79.55 284.60

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +8.00 % on Subtotal-A )

22.77

Subtotal-A1: Subtotal-B: Subtotal-C:

307.36 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

313.51

10% Profit ( Add 10% on Subtotal-B) :

344.86

VAT

6% of Total

IT

4% of Total

22.99 15.33 Total:

5.12.09.02

Add for each additional floor up to 5th floor

sqm

Add +1.70% with Item No 5.12.09.01

5.12.09.03

Add for 6th floor and above

sqm

Add +2.50% with Item No 5.12.09.01

Note : Rates of all items should be inclusive of all supply and carriage.

383.18

Page: 1349 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.10

Detailed Analysis Brief Description of Item 2 Providing drip course/nosing/throating at the edge of sunshade or cornice with cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) in/c. scaffolding, curing at least for 7 days etc. all complete for all floors as per direction of the E-I-C .

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Sand (FM - 1.2)

0.0020

m3

584.00

1.17

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0110

bag

430.00

4.73

Mason

0.1300

day

550.00

71.50

Ordinary Labour

0.0660

day

370.00

24.42 101.82

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +3.00 % on Subtotal-A )

3.05

Subtotal-A1:

104.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

106.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

117.67

VAT

6% of Total

IT

4% of Total

7.84 5.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

130.74

Page: 1350 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.11

Detailed Analysis Brief Description of Item 2 Pre-cast ventilators (25mm thick) of any design with cement mortar (1:4) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2), fitted and fixed in position, finished with cement plaster (1:6) in/c necessary scaffolding and curing for requisite period in all floors, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.9000

bag

430.00

387.00

Sand (FM - 1.2)

0.1600

m3

584.00

93.44

Mason

1.3000

day

550.00

715.00

Ordinary Labour

0.9000

day

370.00

333.00 1528.44

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1559.01

10% Profit ( Add 10% on Subtotal-B) :

1714.91

VAT

6% of Total

IT

4% of Total

114.33 76.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1905.46

Page: 1351 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.12

Detailed Analysis Brief Description of Item 2 Average 100mm thick finished lime terracing with 20mm down well graded 1st class brick chips (LAA value not exceeding 38), surki from 1st class bricks and slaked lime in the proportion 7:2:2 (brick chips:surki:lime) in/c preparation of the mix on the ground by making a suitable platform under proper cover, cutting the mix twice daily with lime water (1:10) at least for 7 days until the mix attains desirable consistency, laying the mix in proper slope, beating the same with standard ‘koppa’ for minimum 7 days to gain maximum consolidation, making ghoondy, neat finishing with lime mortar (1:2) (lime:surki), curing for 21 days and cleaning etc. all complete as per direction of the E-I-C (Stone lime to be brought at site and to be slaked in presence of Engineer in-charge and to be measured in volume three days after slaking for using in the mix).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick

290.0000

each

9.00

2610.00

Slacked Lime

191.0000

kg

27.00

5157.00

Surki

0.3500

m3

1200.00

420.00

Mason

0.7100

day

550.00

390.50

14.0000

day

370.00

5180.00

Ordinary Labour

13757.50

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

687.88

Subtotal-A1: Subtotal-B: Subtotal-C:

14445.38 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14734.28

10% Profit ( Add 10% on Subtotal-B) :

16207.71

VAT

6% of Total

IT

4% of Total

1080.51 720.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18008.57

Page: 1352 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.12.13

Supplying, fitting, fixing approved best quality locally made roof tiles & ridge of various size or any other appropriate factory size laid on 20mm thick cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2), over inclined RCC roof slab racking out joints and filling with same mortar, cleaning, laying the tiles properly, finishing with care, necessary scaffolding, curing etc. all complete as per drawing, direction of the E-I-C. (Padlo is also be used in mortar)

5.12.13.01

200mmx100mm size (channel-C, MCWDesign No-21 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 200mmx100mm size (channel-C, MCWDesign No-21 or equivalent best quality)

47.0000

each

30.00

1410.00

0.3900

kg

120.00

46.80

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10

Padlo

2047.68

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2088.63

10% Profit ( Add 10% on Subtotal-B) :

2297.50

VAT

6% of Total

153.17

IT

4% of Total

102.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2552.77

Page: 1353 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.13.02

Detailed Analysis Brief Description of Item 2 125x170mm size of Red colour (Taylor-MCW Design No-19 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Roof Tiles: 125x170mm (Round-MCW-Design No.19 or equivalent)

47.0000

each

30.00

1410.00

Padlo

0.3900

kg

120.00

46.80

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 2047.68

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2088.63

10% Profit ( Add 10% on Subtotal-B) :

2297.50

VAT

6% of Total

IT

4% of Total

153.17 102.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2552.77

Page: 1354 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.13.03

Detailed Analysis Brief Description of Item 2 200x100mm size of Red colour (Round-MCW Design No-24 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Roof Tiles: 200x100mm (Round-MCW-Design No.24 or equivalent)

50.0000

each

49.00

2450.00

Padlo

0.3900

kg

120.00

46.80

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 3087.68

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3149.43

10% Profit ( Add 10% on Subtotal-B) :

3464.38

VAT

6% of Total

IT

4% of Total

230.96 153.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3849.31

Page: 1355 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.13.04

Detailed Analysis Brief Description of Item 2 200mmx100mm size Roof Tiles-Ridge of Red colour (MCW Design No23 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 200mmx100mm size Roof Tiles-Ridge

17.2200

each

33.00

Padlo

0.3900

kg

120.00

46.80

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1205.94

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1230.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1353.06

VAT

6% of Total

IT

4% of Total

90.20 60.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

568.26

1503.41

Page: 1356 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.14

Detailed Analysis Brief Description of Item 2 20 mm thick water-proofing work in masonry or on concrete surface with sand (FM - 1.2) and Portland Composite Cement (CEM-II/AL/M/V/W 42.5N) mortar mixed with specified admixture (supplied from authorized local agent or from manufacturer comply with ASTM/BS/IS requirements, confirming current compliance of the admixture to specification requirements like physical properties, uniformity and equivalence in composition, performance requirements, delivered in sealed containers having and confirming plainly marked the proprietary name of the admixture type under this specification, net weight and or volume, manufacturing and expiry date, shelve life, non aggressiveness to environment and metals in concrete etc.) under the strict accordance with manufacturer recommendations / instructions and providing safety provisions in all respect etc. on sound, firm surfaces all complete including cleaning the surface from dust, loose particles, remains of oil, grease etc. all complete approved and accepted by the Engineer. {Portland Composite Cement (CEM II/A-M, 42.5N)}

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

0.0200

m3

584.00

11.68

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3250

bag

430.00

139.75

Admixture

0.4500

kg

130.00

58.50

Head Mason

0.0500

day

650.00

32.50

Mason

0.2000

day

550.00

110.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1000

day

370.00

37.00

5

Amount 8

sqm

Sand (FM - 1.2)

479.43

Subtotal-A: All other remaining costs, tools and plants, safety provisions, scaffolding, sundriesetc.

( +3.00 % on Subtotal-A )

14.38

Subtotal-A1: Subtotal-B: Subtotal-C:

493.81 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

503.69

10% Profit ( Add 10% on Subtotal-B) :

554.06

VAT

6% of Total

IT

4% of Total

36.94 24.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

615.62

Page: 1357 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.15

Detailed Analysis Brief Description of Item 2 38mm thick on an average roof top cement concrete screed in proportion (1:1.5:3) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.8) and 10mm down graded crushed 1st class brick chips/picked chips, (LAA value not exceeding 38), including Cement grouting, mixing concrete, laying with neat cement finishing on the following day of roof slab casting, cost of all materials, labour and transportation to the site, finishing the edges and corners, curing for the requisite period etc. all complete as per drawing, specification and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick Chips (10mm down graded)

0.0340

m3

3049.00

Sand (FM - 1.8)

0.0170

m3

970.00

16.49

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3200

bag

430.00

137.60

Head Mason

0.0080

day

650.00

5.20

Mason

0.0500

day

550.00

27.50

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.2500

day

370.00

92.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 426.10

Subtotal-A: All other remaining costs covering scaffolding, surface cleaning, Cement grouting etc.

( +8.50 % on Subtotal-A )

36.22

Subtotal-A1: Subtotal-B: Subtotal-C:

462.31 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

471.56

10% Profit ( Add 10% on Subtotal-B) :

518.72

VAT

6% of Total

IT

4% of Total

34.58 23.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

103.67

576.35

Page: 1358 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.16

Detailed Analysis Brief Description of Item 2 38mm thick on an average roof top cement concrete screed in proportion (1:1.5:3) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.8) and 6mm down well graded crushed stone chips broken from boulder ( LAA value not exceeding 30), including Cement grouting, mixing concrete, laying with neat cement finishing on the following day of roof slab casting, cost of all materials, labour and transportation to the site, finishing the edges and corners, curing for the requisite period etc. all complete as per drawing, specification and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (6mm down graded) [LAA≤30]

0.0340

m3

3800.00

Sand (FM - 1.8)

0.0170

m3

970.00

16.49

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3200

bag

430.00

137.60

Head Mason

0.0080

day

650.00

5.20

Mason

0.0500

day

550.00

27.50

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.2500

day

370.00

92.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 451.63

Subtotal-A: All other remaining costs covering scaffolding, surface cleaning, Cement grouting etc.

( +8.50 % on Subtotal-A )

38.39

Subtotal-A1: Subtotal-B: Subtotal-C:

490.02 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

499.82

10% Profit ( Add 10% on Subtotal-B) :

549.80

VAT

6% of Total

IT

4% of Total

36.65 24.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

129.20

610.89

Page: 1359 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.17

Detailed Analysis Brief Description of Item 2 44mm thick on an average roof top cement concrete screed in proportion (1:1.5:3) with 10mm down graded crushed 1st class brick chips/picked chips, (LAA value not exceeding 38), cement and sand (minimum FM 1.8) including Cement grouting, mixing concrete, laying with neat cement finishing on the following day of roof slab casting, cost of all materials, labour and transportation to the site, finishing the edges and corners, curing for the requisite period etc. all complete as per drawing, specification and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick Chips (10mm down graded)

0.0390

m3

3049.00

118.91

Sand (FM - 1.8)

0.0190

m3

970.00

18.43

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3400

bag

430.00

146.20

Head Mason

0.0100

day

650.00

6.50

Mason

0.0500

day

550.00

27.50

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.2500

day

370.00

92.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 453.18

Subtotal-A: All other remaining costs covering scaffolding, surface cleaning, Cement grouting etc.

( +8.50 % on Subtotal-A )

38.52

Subtotal-A1:

491.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

501.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

551.69

VAT

6% of Total

IT

4% of Total

36.78 24.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

612.99

Page: 1360 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.18

Detailed Analysis Brief Description of Item 2 44mm thick on an average roof top cement concrete screed in proportion (1:1.5:3) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM 2.5) and 12mm down well graded crushed stone chips broken from boulder ( LAA value not exceeding 33), including Cement grouting, mixing concrete, laying with neat cement finishing on the following day of roof slab casting, cost of all materials, labour and transportation to the site, finishing the edges and corners, curing for the requisite period etc. all complete as per drawing, specification and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (12mm down graded) [LAA≤30]

0.0390

m3

4470.00

Sand (FM - 2.5) Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0190

m3

1500.00

28.50

0.3400

bag

430.00

146.20

Head Mason

0.0100

day

650.00

6.50

Mason

0.0500

day

550.00

27.50

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.2500

day

370.00

92.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 518.67

Subtotal-A: All other remaining costs covering scaffolding, surface cleaning, Cement grouting etc.

( +8.50 % on Subtotal-A )

44.09

Subtotal-A1: Subtotal-B: Subtotal-C:

562.76 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

574.01

10% Profit ( Add 10% on Subtotal-B) :

631.41

VAT

6% of Total

IT

4% of Total

42.09 28.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

174.33

701.57

Page: 1361 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.19

Detailed Analysis Brief Description of Item 2 50mm thick on an average roof top cement concrete screed in proportion (1:1.5:3) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM 1.8) and 10mm down graded crushed 1st class brick chips/picked chips, (LAA value not exceeding 38), including Cement grouting, mixing concrete, laying with neat cement finishing on the following day of roof slab casting, cost of all materials, labour and transportation to the site, finishing the edges and corners, curing for the requisite period etc. all complete as per drawing, specification and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick Chips (10mm down graded)

0.0450

m3

3049.00

Sand (FM - 1.8)

0.0210

m3

970.00

20.37

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3800

bag

430.00

163.40

Head Mason

0.0080

day

650.00

5.20

Mason

0.0500

day

550.00

27.50

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.2500

day

370.00

92.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 489.32

Subtotal-A: All other remaining costs covering scaffolding, surface cleaning, Cement grouting etc.

( +8.50 % on Subtotal-A )

41.59

Subtotal-A1: Subtotal-B: Subtotal-C:

530.91 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

541.52

10% Profit ( Add 10% on Subtotal-B) :

595.68

VAT

6% of Total

IT

4% of Total

39.71 26.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

137.21

661.86

Page: 1362 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.20

Detailed Analysis Brief Description of Item 2 50mm thick on an average roof top cement concrete screed in proportion (1:1.5:3) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM 2.5) and 12mm down well graded crushed stone chips broken from boulder ( LAA value not exceeding 30), including Cement grouting, mixing concrete, laying with neat cement finishing on the following day of roof slab casting, cost of all materials, labour and transportation to the site, finishing the edges and corners, curing for the requisite period etc. all complete as per drawing, specification and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (12mm down graded) [LAA≤30]

0.0450

m3

4470.00

Sand (FM - 2.5) Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0210

m3

1500.00

31.50

0.3800

bag

430.00

163.40

Head Mason

0.0080

day

650.00

5.20

Mason

0.0500

day

550.00

27.50

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.2500

day

370.00

92.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 564.39

Subtotal-A: All other remaining costs covering scaffolding, surface cleaning, Cement grouting etc.

( +8.50 % on Subtotal-A )

47.97

Subtotal-A1: Subtotal-B: Subtotal-C:

612.36 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

624.61

10% Profit ( Add 10% on Subtotal-B) :

687.07

VAT

6% of Total

IT

4% of Total

45.80 30.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

201.15

763.41

Page: 1363 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.12.21

Supplying and laying of approved colour and size of best quality locally made ceramic wall tiles of various size or any other appropriate factory size laid on 20mm thick cement mortar (1:3) with Portland Composite cement (CEM II/AM, 42.5N), best quality sand (minimum FM1.2) on wall and racking out joints and filling with same mortar, cleaning, laying the tiles properly, finishing with care, necessary scaffolding, curing etc. all complete as per drawing, direction of the E-I-C.

5.12.21.01

200mmx62mmx16mm size Wall Tiles Red colour (MCW Design No-CT-5, SL-7 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 200mmx62mmx16mm size Wall Tiles Red colour

75.0000

each

18.00

1350.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1910.78

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1949.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2143.90

VAT

6% of Total

IT

4% of Total

142.93 95.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2382.11

Page: 1364 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.21.02

Detailed Analysis Brief Description of Item 2 200mmx62mmx12mm size Wall Tiles Peach colour (MCW Design No-DT5, SL-7 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 200mmx62mmx12mm size Wall Tiles Peach colour

75.0000

each

34.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 3110.78

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3173.00

10% Profit ( Add 10% on Subtotal-B) :

3490.30

VAT

6% of Total

232.69

IT

4% of Total

155.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2550.00

3878.11

Page: 1365 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.21.03

Detailed Analysis Brief Description of Item 2 200mmx62mmx12mm size Wall Tiles Beige colour (MCW Design No-DT5, SL-7 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 200mmx62mmx12mm size Wall Tiles Beige colour

75.0000

each

20.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 2098.28

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2140.25

10% Profit ( Add 10% on Subtotal-B) :

2354.27

VAT

6% of Total

156.95

IT

4% of Total

104.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1537.50

2615.86

Page: 1366 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.21.04

Detailed Analysis Brief Description of Item 2 231mmx69mmx12mm size Wall Tiles Red colour (MCW Design No-DT16, SL-7 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 231mmx69mmx12mm size Wall Tiles Red colour

59.0000

each

22.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1888.28

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1926.05

10% Profit ( Add 10% on Subtotal-B) :

2118.65

VAT

6% of Total

141.24

IT

4% of Total

94.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1327.50

2354.06

Page: 1367 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.21.05

Detailed Analysis Brief Description of Item 2 231mmx69mmx12mm size Wall Tiles Peach colour (MCW Design No-DT16, SL-7 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 231mmx69mmx12mm size Wall Tiles Peach colour

59.0000

each

35.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 2655.28

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2708.39

10% Profit ( Add 10% on Subtotal-B) :

2979.22

VAT

6% of Total

198.61

IT

4% of Total

132.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2094.50

3310.25

Page: 1368 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.21.06

Detailed Analysis Brief Description of Item 2 231mmx69mmx12mm size Wall Tiles Beige colour (MCW Design No-DT16, SL-7 or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 231mmx69mmx12mm size Wall Tiles Beige colour

59.0000

each

27.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 2183.28

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2226.95

10% Profit ( Add 10% on Subtotal-B) :

2449.64

VAT

6% of Total

163.31

IT

4% of Total

108.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1622.50

2721.82

Page: 1369 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.21.07

Detailed Analysis Brief Description of Item 2 200mmx62mmx16mm size Wall Tiles Red colour (MCW Design No-DT-5, SL-07B or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 200mmx62mmx16mm size Wall Tiles Red colour

75.0000

each

18.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1910.78

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1949.00

10% Profit ( Add 10% on Subtotal-B) :

2143.90

VAT

6% of Total

142.93

IT

4% of Total

95.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1350.00

2382.11

Page: 1370 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.21.08

Detailed Analysis Brief Description of Item 2 225mmx100mmx16mm size Wall Tiles Red colour (MCW Design No-DT5, SL-07B or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 225mmx100mmx16mm size Wall Tiles Red colour

45.0000

each

27.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1798.28

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1834.25

10% Profit ( Add 10% on Subtotal-B) :

2017.67

VAT

6% of Total

134.51

IT

4% of Total

89.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1237.50

2241.86

Page: 1371 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.22

Detailed Analysis Brief Description of Item 2 Plaster rule pointing works 250mmx75mm size as brick shape by 10mmx10mm grove on outside wall over minimum 12mm thick cement plaster (1:6) with Portland Composite cement (CEM II/AM, 42.5N), best quality sand (minimum FM1.2), finishing the corners and edges including washing of sand, cleaning the surface, scaffolding and curing for requisite period etc. all complete as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0800

bag

430.00

34.40

Sand (FM - 1.2)

0.0180

m3

584.00

10.51

Head Mason

0.0400

day

650.00

26.00

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.1600

day

450.00

72.00 230.91

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

235.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

259.08

VAT

6% of Total

IT

4% of Total

17.27 11.51 Total:

5.12.23

287.87

Making groove in plaster on outside wall of various wide and depth i/c finishing the corners and edges including washing of sand, cleaning the surface, scaffolding and curing for requisite period etc. all complete as per drawing and direction of the E-I-C (excluding the cost of cement plaster).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1372 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.23.01

Detailed Analysis Brief Description of Item 2 Groove in plaster 50mm X 6mm size

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Mason

0.0210

day

550.00

11.55

Skilled Labour

0.0210

day

450.00

9.45 21.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21.42

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

23.56

VAT

6% of Total

1.57

IT

4% of Total

1.05 Total:

5.12.23.02

Groove in plaster 40mm X 6mm size

m Mason

0.0250

day

550.00

13.75

Skilled Labour

0.0250

day

450.00

11.25 25.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25.50

10% Profit ( Add 10% on Subtotal-B) :

28.05

VAT

6% of Total

IT

4% of Total

1.87 1.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

26.18

31.17

Page: 1373 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.12.23.03

Detailed Analysis Brief Description of Item 2 Groove in plaster 25mm X 6mm size

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Mason

0.0230

day

550.00

12.65

Skilled Labour

0.0230

day

450.00

10.35 23.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25.81

VAT

6% of Total

1.72

IT

4% of Total

1.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

28.67

Page: 1374 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.13.01

Detailed Analysis Brief Description of Item 2 25mm thick artificial patent stone floor (1:2:4) with Portland Composite cement (CEM II/AM, 42.5N), best quality coarse sand (minimum FM1.8) and 10mm down well graded picked brick chips (LAA value not exceeding 38) in/c breaking graded picked chips, screening, mixing, laying the concrete in alternate panels, compacting and finishing the top with neat cement, curing, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick Chips (10mm down graded)

0.0230

m3

3049.00

70.13

Sand (FM - 1.8)

0.0060

m3

970.00

5.82

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1620

bag

430.00

69.66

Head Mason

0.0020

day

650.00

1.30

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.1100

day

370.00

40.70

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0015

day

1200.00

1.80 282.91

Subtotal-A: Form Work

( +.01 % on Subtotal-A )

0.03

Subtotal-A1:

282.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

288.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

317.45

VAT

6% of Total

21.16

IT

4% of Total

14.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

352.73

Page: 1375 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.13.02

Detailed Analysis Brief Description of Item 2 38mm thick artificial patent stone floor (1:2:4) with Portland Composite cement (CEM II/AM, 42.5N), best quality coarse sand (minimum FM1.8) and 10mm down graded picked brick chips (LAA value not exceeding 38) in/c breaking chips, screening, mixing, laying the concrete in alternate panels, compacting and finishing the top with neat cement, curing for requisite period, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick Chips (10mm down graded)

0.0300

m3

3049.00

91.47

Sand (FM - 1.8)

0.0080

m3

970.00

7.76

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2420

bag

430.00

104.06

Head Mason

0.0020

day

650.00

1.30

Mason

0.1200

day

550.00

66.00

Skilled Labour

0.1700

day

450.00

76.50

Ordinary Labour

0.1700

day

370.00

62.90

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 412.63

Subtotal-A: Form Work

( +.01 % on Subtotal-A )

0.05

Subtotal-A1:

412.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

420.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

463.03

VAT

6% of Total

30.87

IT

4% of Total

20.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

514.48

Page: 1376 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.13.03

Detailed Analysis Brief Description of Item 2 25mm thick patent stone floor (1:2:4) with Portland Composite cement (CEM II/AM, 42.5N), best quality coarse sand (minimum FM1.8) and 10mm down well graded crushed stone chips (Preferably stone chips from Madhyapara, Dinajpur) (LAA value not exceeding 35), in/c chips screening, mixing, laying the concrete in alternate panels, compacting and finishing the top with neat cement, curing for requisite period, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (12mm down graded) [LAA≤35]

0.0230

cum

4320.00

99.36

Sand (FM - 1.8)

0.0060

m3

970.00

5.82

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1620

bag

430.00

69.66

Head Mason

0.0020

day

650.00

1.30

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.1100

day

370.00

40.70

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0015

day

1200.00

1.80 312.14

Subtotal-A: Form Work

( +.01 % on Subtotal-A )

0.03

Subtotal-A1:

312.17

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

318.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

350.26

VAT

6% of Total

23.35

IT

4% of Total

15.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

389.17

Page: 1377 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.13.04

Detailed Analysis Brief Description of Item 2 38mm thick patent stone floor (1:2:4) with Portland Composite cement (CEM II/AM, 42.5N), best quality coarse sand (minimum FM1.8) and 10mm down well graded crushed stone chips (Preferably stone chips from Madhyapara, Dinajpur) (LAA value not exceeding 35), in/c chips screening, mixing, laying the concrete in alternate panels, compacting and finishing the top with neat cement, curing for requisite period, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Stone Chips (12mm down graded) [LAA≤35]

0.0300

cum

4320.00

129.60

Sand (FM - 1.8)

0.0080

m3

970.00

7.76

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2420

bag

430.00

104.06

Head Mason

0.0020

day

650.00

1.30

Mason

0.1200

day

550.00

66.00

Skilled Labour

0.1700

day

450.00

76.50

Ordinary Labour

0.1700

day

370.00

62.90

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0022

day

1200.00

2.64 450.76

Subtotal-A: Form Work

( +.01 % on Subtotal-A )

0.06

Subtotal-A1:

450.82

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

459.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

505.82

VAT

6% of Total

33.72

IT

4% of Total

22.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

562.02

Page: 1378 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Finished cast-in-situ mosaic work with one part of 10mm machine crushed well graded dust free and properly washed Pakistani origin marble chips and one part of mixture containing best quality white cement and Portland Composite gray cement (CEM II/AM, 42.5N) in proportion 9:1 in/c preparation of mixture and laying the same over minimum 25mm thick artificial patent stone floor in proportion (1:2:4) with other specifications stated under Item No. 5.13.03 in/c making suitable panel, compacting, curing at least 7 days, cutting by mosaic cutter machine with pumice stone (No. 40, No. 80, No. 120) and finishing with Minar stone, auxalic acid etc. in/c breaking chips, screening, washing mosaic chips, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1379 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.01.01

Detailed Analysis Brief Description of Item 2 10mm thick finished and laying thickness 12.50mm in floor with panel by 5mm thick and 20mm deep glass dividers (Excluding the cost of artificial patent stone floor)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble chips (Pakistani)

13.0000

kg

18.00

234.00

Minar Stone

0.0400

each

350.00

14.00

5mm thick glass

0.0800

m2

700.00

56.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

10.0000

kg

25.00

250.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0220

bag

430.00

9.46

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 992.76

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1012.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1113.88

VAT

6% of Total

74.26

IT

4% of Total

49.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1237.64

Page: 1380 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.01.02

Detailed Analysis Brief Description of Item 2 12mm thick finished and laying thickness 14.50mm in floor with panel by 5mm thick and 20mm deep glass dividers (Excluding the cost of artificial patent stone floor)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble chips (Pakistani)

15.5000

kg

18.00

279.00

Minar Stone

0.0400

each

350.00

14.00

5mm thick glass

0.0800

m2

700.00

56.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

12.1000

kg

25.00

302.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0270

bag

430.00

11.61

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 1092.41

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1114.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1225.68

VAT

6% of Total

81.71

IT

4% of Total

54.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1361.87

Page: 1381 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.01.03

Detailed Analysis Brief Description of Item 2 10mm thick finished and laying thickness 12.50mm on wall laying on 12mm thick cement plaster (1:4) with other specifications stated under Item No. 5.12.01 instead of artificial patent stone floor. (Excluding the cost of cement plaster).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble chips (Pakistani)

12.9000

kg

18.00

232.20

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.2700

each

140.00

37.80

White Cement

9.6800

kg

25.00

242.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0220

bag

430.00

9.46

Head Mason

0.1100

day

650.00

71.50

Skilled Labour

1.1600

day

450.00

522.00

Ordinary Labour

0.2200

day

370.00

81.40 1210.36

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1234.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1358.02

VAT

6% of Total

IT

4% of Total

90.53 60.36 Total:

5.14.02

1508.92

Finished cast-in-situ mosaic work with one part of 10mm machine crushed well graded dust free and properly washed Indian origin marble chips and one part of mixture containing best quality white cement and Portland Composite grey Cement (CEM II/A-M, 42.5N) in proportion 9:1 in/c preparation of mixture and laying the same over minimum 25mm thick artificial patent stone floor in proportion (1:2:4) with other specifications stated under Item No. 5.13.03 in/c making suitable panel, compacting, curing at least 7 days, cutting by mosaic cutter machine with pumice stone (No. 40, No. 80, No. 120) and finishing with Minar stone, auxalic acid etc. in/c breaking chips, screening, washing mosaic chips, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1382 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.02.01

Detailed Analysis Brief Description of Item 2 10mm thick finished and laying thickness 12.50mm in floor with panel by 5mm thick and 20mm deep glass dividers (Excluding the cost of artificial patent stone floor)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble Chips (Indian)

13.0000

kg

13.00

169.00

Minar Stone

0.0400

each

350.00

14.00

5mm thick glass

0.0800

m2

700.00

56.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

10.0000

kg

25.00

250.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0220

bag

430.00

9.46

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 927.76

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

946.32 1040.95

VAT

6% of Total

69.40

IT

4% of Total

46.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1156.61

Page: 1383 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.02.02

Detailed Analysis Brief Description of Item 2 12mm thick finished and laying thickness 12.50mm in floor with panel by 5mm thick and 20mm deep glass dividers (Excluding the cost of artificial patent stone floor)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble Chips (Indian)

15.5000

kg

13.00

201.50

Minar Stone

0.0400

each

350.00

14.00

5mm thick glass

0.0800

m2

700.00

56.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

12.1000

kg

25.00

302.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0270

bag

430.00

11.61

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 1014.91

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1035.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1138.73

VAT

6% of Total

75.92

IT

4% of Total

50.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1265.25

Page: 1384 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.02.03

Detailed Analysis Brief Description of Item 2 10mm thick on wall laying on 12mm thick cement plaster (1:4) with other specifications stated under Item No. 5.12.01 instead of artificial patent stone floor. (Excluding the cost of cement plaster).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble Chips (Indian)

12.9000

kg

13.00

167.70

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.2700

each

140.00

37.80

White Cement

9.6800

kg

25.00

242.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0220

bag

430.00

9.46

Head Mason

0.1100

day

650.00

71.50

Skilled Labour

1.1600

day

450.00

522.00

Ordinary Labour

0.2200

day

370.00

81.40 1145.86

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1168.78

10% Profit ( Add 10% on Subtotal-B) :

1285.65

VAT

6% of Total

IT

4% of Total

85.71 57.14 Total:

5.14.03

1428.51

Finished cast-in-situ mosaic work with one part of 10mm machine crushed well graded dust free and properly washed Pakistani origin marble chips and one part of mixture containing best quality white cement and Portland Composite grey Cement (CEM II/A-M, 42.5N) in proportion 9:1 in/c preparation of mixture and laying the same over minimum 25mm thick artificial patent stone floor in proportion (1:2:4) with other specifications stated under Item No. 5.13.03 in/c making suitable panel, compacting, curing at least 7 days, cutting by mosaic cutter machine with pumice stone (No. 40, No. 80, No. 120) and finishing with Minar stone, auxalic acid etc. in/c breaking chips, screening, washing mosaic chips, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1385 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.03.01

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

10mm thick finished and laying thickness 12.50mm in floor without glass divider (Excluding the cost of artificial patent stone floor)

sqm 10mm well graded Marble chips (Pakistani)

Quantity 5

Unit

Rate

6

7

Amount 8

13.0000

kg

18.00

234.00

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

10.0000

kg

25.00

250.00

0.0220

bag

430.00

9.46

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 936.76

Subtotal-A: Subtotal-B: Subtotal-C:

955.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1051.04

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

70.07 46.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1167.83

Page: 1386 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.03.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

12mm thick finished and laying thickness 14.50mm in floor without glass divider (Excluding the cost of artificial patent stone floor)

sqm 10mm well graded Marble chips (Pakistani)

Quantity 5

Unit

Rate

6

7

Amount 8

15.5000

kg

18.00

279.00

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

12.1000

kg

25.00

302.50

0.0270

bag

430.00

11.61

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 1036.41

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1057.14

10% Profit ( Add 10% on Subtotal-B) :

1162.85

VAT

6% of Total

IT

4% of Total

77.52 51.68 Total:

5.14.04

1292.06

Finished cast-in-situ mosaic work with one part of 10mm machine crushed well graded dust free and properly washed Indian origin marble chips and one part of mixture containing best quality white cement and Portland Composite grey Cement (CEM II/A-M, 42.5N) in proportion 9:1 in/c preparation of mixture and laying the same over minimum 25mm thick artificial patent stone floor in proportion (1:2:4) with other specifications stated under Item No. 5.13.03 in/c making suitable panel, compacting, curing at least 7 days, cutting by mosaic cutter machine with pumice stone (No. 40, No. 80, No. 120) and finishing with Minar stone, auxalic acid etc. in/c breaking chips, screening, washing mosaic chips, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1387 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.04.01

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

10mm thick finished and laying thickness 12.50mm in floor without glass divider (Excluding the cost of artificial patent stone floor)

sqm 10mm well graded Marble Chips (Indian)

Quantity 5

Unit

Rate

6

7

Amount 8

13.0000

kg

13.00

169.00

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

10.0000

kg

25.00

250.00

0.0220

bag

430.00

9.46

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 871.76

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

889.20

10% Profit ( Add 10% on Subtotal-B) :

978.11

VAT

6% of Total

IT

4% of Total

65.21 43.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1086.79

Page: 1388 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.04.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

12mm thick finished and laying thickness 14.50mm in floor without glass divider (Excluding the cost of artificial patent stone floor)

sqm 10mm well graded Marble Chips (Indian)

Quantity 5

Unit

Rate

6

7

Amount 8

15.5000

kg

13.00

201.50

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

12.1000

kg

25.00

302.50

0.0270

bag

430.00

11.61

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 958.91

Subtotal-A: Subtotal-B: Subtotal-C:

978.09

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1075.90

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

71.73 47.82 Total:

5.14.05

1195.44

Finished silver gray situ mosaic works with one part of 10mm machine crushed well graded, dust free and properly washed Pakistani origin marble chips and one part of mixture containing white cement (Malaysia/Thailand/ India) and Portland Composite grey Cement (CEM II/A-M, 42.5N) in proportion 1:1 in/c preparation of mix and laying the same over 25mm thick artificial patent stone floor in proportion (1:2:4) with other specifications stated under Item No. 5.13.03 in/c making suitable panel, compacting, curing at least 7 days, cutting by mosaic cutter machine with pumice stone (#40, #80, #120) in/c finishing with Minar stone, auxalic acid etc. in/c breaking brick chips, screening, washing mosaic chips, etc. all complete in all respects and as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1389 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.05.01

Detailed Analysis Brief Description of Item 2 10mm thick finished and laying thickness 12.50mm in floor with panel by 5mm thick and 20mm deep glass dividers (Excluding the cost of artificial patent stone floor)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble chips (Pakistani)

12.9000

kg

18.00

232.20

Minar Stone

0.0400

each

350.00

14.00

5mm thick glass

0.0800

m2

700.00

56.00

White Cement

5.3800

kg

25.00

134.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1100

bag

430.00

47.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00

Pumice Stone

0.3200

each

140.00

44.80 913.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

931.57 1024.72

VAT

6% of Total

68.31

IT

4% of Total

45.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1138.58

Page: 1390 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.05.02

Detailed Analysis Brief Description of Item 2 12mm thick finished and laying thickness 14.50mm in floor with panel by 5mm thick and 20mm deep glass dividers (Excluding the cost of artificial patent stone floor)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble chips (Pakistani)

15.5000

kg

18.00

279.00

Minar Stone

0.0400

each

350.00

14.00

5mm thick glass

0.0800

m2

700.00

56.00

White Cement

6.7200

kg

25.00

168.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1350

bag

430.00

58.05

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00

Pumice Stone

0.3200

each

140.00

44.80 1004.35

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1024.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1126.88

VAT

6% of Total

75.13

IT

4% of Total

50.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1252.09

Page: 1391 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.05.03

Detailed Analysis Brief Description of Item 2 10mm thick finished and laying thickness 12.50mm on wall laying on 12mm thick cement plaster (1:4) with other specifications stated under Item No. 5.12.01 instead of artificial patent stone floor. (Excluding the cost of cement plaster).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble chips (Pakistani)

12.9000

kg

18.00

232.20

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.2700

each

140.00

37.80

White Cement

5.3800

kg

25.00

134.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1100

bag

430.00

47.30

Head Mason

0.1100

day

650.00

71.50

Skilled Labour

1.1600

day

450.00

522.00

Ordinary Labour

0.2200

day

370.00

81.40 1140.70

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1163.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1279.87

VAT

6% of Total

IT

4% of Total

85.32 56.88 Total:

5.14.06

1422.07

Finished silver gray situ mosaic works with one part of 10mm machine crushed well graded, dust free and properly washed Indian origin marble chips and one part of mixture containing white cement (Malaysia/ Thailand/India) and Portland Composite grey Cement (CEM II/A-M, 42.5N) in proportion 1:1 in/c preparation of mix and laying the same over 25mm thick artificial patent stone floor in proportion (1:2:4) with other specifications stated under Item No. 5.13.03 in/c making suitable panel, compacting, curing at least 7 days, cutting by mosaic cutter machine with pumice stone (# 40, # 80, # 120) in/c finishing with Minar stone, auxalic acid etc. in/c breaking brick chips, screening, washing mosaic chips, etc. all complete in all respects and as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1392 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.06.01

Detailed Analysis Brief Description of Item 2 10mm thick finished and laying thickness 12.50mm in floor with panel by 5mm thick and 20mm deep glass dividers (Excluding the cost of artificial patent stone floor)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble Chips (Indian)

12.9000

kg

13.00

167.70

Minar Stone

0.0400

each

350.00

14.00

5mm thick glass

0.0800

m2

700.00

56.00

White Cement

5.3800

kg

25.00

134.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1100

bag

430.00

47.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 804.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

820.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

902.09

VAT

6% of Total

60.14

IT

4% of Total

40.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1002.32

Page: 1393 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.06.02

Detailed Analysis Brief Description of Item 2 12mm thick finished and laying thickness 1450mm in floor with panel by 5mm thick and 20mm deep glass dividers (Excluding the cost of artificial patent stone floor)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble Chips (Indian)

15.5000

kg

13.00

201.50

Minar Stone

0.0400

each

350.00

14.00

5mm thick glass

0.0800

m2

700.00

56.00

White Cement

6.7200

kg

25.00

168.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1350

bag

430.00

58.05

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 882.05

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

899.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

989.66

VAT

6% of Total

65.98

IT

4% of Total

43.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1099.62

Page: 1394 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.14.06.03

Detailed Analysis Brief Description of Item 2 10mm thick finished and laying thickness 12.50mm on wall laying on 12mm thick cement plaster (1:4) with other specifications stated under Item No. 5.12.01 instead of artificial patent stone floor. (Excluding the cost of cement plaster).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

10mm well graded Marble Chips (Indian)

12.9000

kg

13.00

167.70

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.2700

each

140.00

37.80

White Cement

5.3800

kg

25.00

134.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1100

bag

430.00

47.30

Head Mason

0.1100

day

650.00

71.50

Skilled Labour

1.1600

day

450.00

522.00

Ordinary Labour

0.2200

day

370.00

81.40 1076.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1097.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1207.50

VAT

6% of Total

IT

4% of Total

80.50 53.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1341.66

Page: 1395 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

200mmx200mmx20mm mosaic terrazzo tiles flooring having 10mm thick finished mosaic top with one part of 10mm machine crushed well graded, dust free and properly washed marble chips and one part of mixture containing white cement (made in Malaysia/ Thailand/India or equivalent best quality) and Portland Composite grey Cement (CEM II/AM, 42.5N) in proportion 9:1 in/c preparation of mix, machine pressed on 12mm thick cement mortar base (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) in/c preparing the base, setting the tiles on 40mm thick cement slurry and lime and surki in proportion of (1:3), compacting, cutting with pumice stone (No. 40, No. 80, No. 120)and finishing with Minar stone, auxalic acid etc. in/c screening, washing mosaic chips and supply of all necessary materials, etc. complete in all respect and as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1396 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.15.01.01

2 With Indian origin marble chips

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 10mm well graded Marble Chips (Indian)

12.9000

kg

13.00

167.70

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

9.6800

kg

25.00

242.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2100

bag

430.00

90.30

Slacked Lime

8.6000

kg

27.00

232.20

Surki

0.0440

m3

1200.00

52.80

Sand (FM - 1.2)

0.0100

m3

584.00

5.84

Mosaic head mistry

0.1600

day

680.00

108.80

Mosaic mistry

0.1100

day

570.00

62.70

Skilled Labour

0.3200

day

450.00

144.00

Ordinary Labour

0.4800

day

370.00

177.60

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 1397.74

Subtotal-A: Charges for tiles making and other remaining cost

( +8.00 % on Subtotal-A )

111.82

Subtotal-A1: Subtotal-B: Subtotal-C:

1509.56 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1539.75

10% Profit ( Add 10% on Subtotal-B) :

1693.73

VAT

6% of Total

112.92

IT

4% of Total

75.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1881.92

Page: 1397 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.01.02

Detailed Analysis Brief Description of Item 2 With Pakistani origin marble chips

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 10mm well graded Marble chips (Pakistani)

12.9000

kg

18.00

232.20

Minar Stone

0.0400

each

350.00

14.00

Pumice Stone

0.3200

each

140.00

44.80

White Cement

9.6800

kg

25.00

242.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2100

bag

430.00

90.30

Slacked Lime

8.6000

kg

27.00

232.20

Surki

0.0440

m3

1200.00

52.80

Sand (FM - 1.2)

0.0100

m3

584.00

5.84

Mosaic head mistry

0.1600

day

680.00

108.80

Mosaic mistry

0.1100

day

570.00

62.70

Skilled Labour

0.3200

day

450.00

144.00

Ordinary Labour

0.4800

day

370.00

177.60

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 1462.24

Subtotal-A: Charges for tiles making and other remaining cost

( +8.00 % on Subtotal-A )

116.98

Subtotal-A1: Subtotal-B: Subtotal-C:

1579.22 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1610.80

10% Profit ( Add 10% on Subtotal-B) :

1771.88

VAT

6% of Total

118.13

IT

4% of Total

78.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1968.76

Page: 1398 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.15.02

Supplying, fitting and fixing glazed wall tiles of different size irrespective of colour or design (country made Prior approved best quality) on 20mm thick cement mortar (1:3) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) base, raking out the joints and filling with white cement in/c cleaning the existing surface, cutting, shaping and laying the tiles in proper way, level and finishing with care, etc. all complete as per direction of the E-I-C.

5.15.02.01

Glazed wall tiles tiles less than or equivalent to 250mmx330mm in size of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Glazed wall tiles less than or equivalent to 250mmx330mm in size

1.0000

m2

451.92

451.92

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1022.45

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1042.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1147.19

VAT

6% of Total

IT

4% of Total

76.48 50.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1274.65

Page: 1399 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.02.02

Detailed Analysis Brief Description of Item 2 Glazed wall tiles more than 250mmx330mm and less than 250mmx400mm in size or equivalent of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Glazed wall tiles more than 250mmx330mm and less than 250mmx400mm in size or equivalent

1.0000

m2

559.52

559.52

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1130.05

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1152.65

10% Profit ( Add 10% on Subtotal-B) :

1267.92

VAT

6% of Total

IT

4% of Total

84.53 56.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1408.80

Page: 1400 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.02.03

Detailed Analysis Brief Description of Item 2 Glazed wall tiles more than 250mmx400mm and less than 300mmx450mm in size or equivalent of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Glazed wall tiles more than 250mmx400mm and less than 300mmx450mm in size or equivalent

1.0000

m2

624.08

624.08

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1194.61

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1218.50

10% Profit ( Add 10% on Subtotal-B) :

1340.35

VAT

6% of Total

IT

4% of Total

89.36 59.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1489.28

Page: 1401 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.02.04

Detailed Analysis Brief Description of Item 2 Glazed wall tiles more than 300mmx450mm and less than 300mmx500mm in size or equivalent of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Glazed wall tiles more than 300mmx450mm and less than 300mmx500mm in size or equivalent

1.0000

sqm

645.60

645.60

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1246.23

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1271.15

10% Profit ( Add 10% on Subtotal-B) :

1398.27

VAT

6% of Total

IT

4% of Total

93.22 62.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1553.63

Page: 1402 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.02.05

Detailed Analysis Brief Description of Item 2 Glazed wall tiles more than 300mmx500mm size or equivalent of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

817.76

817.76

sqm Glazed wall tiles more than 300mmx500mm size or equivalent

1.0000

sqm

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.2200

day

370.00

81.40 1377.69

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1405.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1545.77

VAT

6% of Total

IT

4% of Total

103.05 68.70 Total:

5.15.03

1717.52

Supplying, fitting and fixing GP (Homogeneous) glazed floor tiles irrespective of colour or design (country made of Prior approved best quality) on 20mm thick cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) base, raking out the joints and filling with white cement in/c cleaning the existing surface, cutting, shaping and laying the tiles in proper way, level and finishing with care, etc. all complete as per direction of the E-IC.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1403 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

5.15.03.01

GP (Homogeneous) 300mmx300mm size glazed floor tiles of Prior approved best quality.

sqm

Quantity 5

Unit

Rate

Amount

6

7

8

GP (Homogeneous) 300x300 mm size glazed floor tiles (FuWang, RAK, GreatWall or Prior approved quality)

1.0000

m2

645.60

645.60

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1246.23

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

24.92

Subtotal-A1: Subtotal-B: Subtotal-C:

1271.15 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1296.58

10% Profit ( Add 10% on Subtotal-B) :

1426.24

VAT

6% of Total

IT

4% of Total

95.08 63.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1584.71

Page: 1404 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

5.15.03.02

GP (Homogeneous) 400mmx400mm size glazed floor tiles of Prior approved best quality.

sqm

Quantity 5

Unit

Rate

Amount

6

7

8

GP (Homogeneous) 400x400 mm size glazed floor tiles (FuWang, RAK, GreatWall or Prior approved quality)

1.0000

m2

720.92

720.92

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1291.45

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

25.83

Subtotal-A1: Subtotal-B: Subtotal-C:

1317.28 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1343.62

10% Profit ( Add 10% on Subtotal-B) :

1477.99

VAT

6% of Total

IT

4% of Total

98.53 65.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1642.21

Page: 1405 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

5.15.03.03

GP (Homogeneous) 600mmx600mm size glazed floor tiles of Prior approved best quality.

sqm

Quantity 5

Unit

Rate

6

7

sqm

Amount 8

GP (Homogeneous) 600x600 mm size glazed floor tiles

1.0000

1011.44

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1612.07

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

32.24

Subtotal-A1:

1644.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1677.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1844.92

VAT

6% of Total

IT

4% of Total

122.99 82.00 Total:

5.15.04

1011.44

2049.91

Supplying, fitting and fixing GP (Homogeneous) unglazed floor tiles irrespective of colour or design (country made of Prior approved best quality) on 20mm thick cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) base, raking out the joints and filling with white cement in/c cleaning the existing surface, cutting, shaping and laying the tiles in proper way, level and finishing with care, etc. all complete as per direction of the E-IC.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1406 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.04.01

Detailed Analysis Brief Description of Item 2 GP (Homogeneous) 300mmx300mm size unglazed floor tiles of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Homogeneous) 300x300 mm size unglazed floor tiles ( RAK, GreatWall or Prior approved quality)

1.0000

m2

634.84

634.84

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1235.47

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1260.18

10% Profit ( Add 10% on Subtotal-B) :

1386.20

VAT

6% of Total

IT

4% of Total

92.41 61.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1540.22

Page: 1407 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.04.02

Detailed Analysis Brief Description of Item 2 GP (Homogeneous) 400mx400mm size unglazed floor tiles of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Homogeneous) 400x400 mm size unglazed floor tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

699.40

699.40

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1300.03

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1326.03

10% Profit ( Add 10% on Subtotal-B) :

1458.63

VAT

6% of Total

IT

4% of Total

97.24 64.83 Total:

5.15.05

1620.70

Supplying, fitting and fixing GP mirror polished floor tiles (Country made of Prior approved best quality) on 20mm thick cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) base, raking out the joints and filling with white cement in/c cleaning the existing surface, cutting, shaping and laying the tiles in proper way, level and finishing with care, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1408 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.05.01

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) 300mmx300mm size floor tiles of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Mirror Polished) 300x300 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

645.60

645.60

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1317.73

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1344.08

10% Profit ( Add 10% on Subtotal-B) :

1478.49

VAT

6% of Total

IT

4% of Total

98.57 65.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1642.77

Page: 1409 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.05.02

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) 400mmx400mm size floor tiles of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Mirror Polished) 400x400 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

850.04

850.04

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1522.17

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1552.61

10% Profit ( Add 10% on Subtotal-B) :

1707.87

VAT

6% of Total

IT

4% of Total

113.86 75.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1897.64

Page: 1410 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.05.03

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) 600mmx600mm size floor tiles of Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm GP (Mirror Polished) 600x600 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

1097.52

1097.52

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1769.65

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1805.04

10% Profit ( Add 10% on Subtotal-B) :

1985.55

VAT

6% of Total

IT

4% of Total

132.37 88.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2206.16

Page: 1411 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.06

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 305mmx305mm size floor (stair step) tiles of Prior approved best quality on 20mm thick cement mortar (1:2) with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) base, raking out the joints and filling with white cement in/c cleaning the existing surface, cutting, shaping and laying the tiles in proper way, level and finishing with care, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

GP 305x305 mm size floor (stair step) tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

699.40

699.40

White Cement

0.3900

kg

25.00

9.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.1100

day

650.00

71.50

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1300.03

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1326.03

10% Profit ( Add 10% on Subtotal-B) :

1458.63

VAT

6% of Total

IT

4% of Total

97.24 64.83 Total:

5.15.07

1620.70

Supplying, fitting and fixing country made floor tiles/skirting of GP Homogenous, GP glazed Homogenous or GP un-glazed Homogenous or GP Mirror Polished or Prior approved best quality irrespective of colour or design, with adhesives of approved best quality in full thickness of tiles, filler/tiles grout of approved best quality in/c cutting, shaping and laying the tiles in proper way, level and finishing with care, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1412 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

5.15.07.01

GP glazed (Homogenous) 300mmx300mm size floor tiles of Prior approved best quality

sqm

Quantity 5

Unit

Rate

Amount

6

7

8

GP (Homogeneous) 300x300 mm size glazed floor tiles (FuWang, RAK, GreatWall or Prior approved quality)

1.0000

m2

645.60

645.60

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.1600

day

450.00

72.00

Ordinary Labour

0.1600

day

370.00

59.20 1016.08

Subtotal-A: Other costs

( +2.00 % on Subtotal-A )

20.32

Subtotal-A1:

1036.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1057.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1162.84

VAT

6% of Total

IT

4% of Total

77.52 51.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1292.05

Page: 1413 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.02

Detailed Analysis Brief Description of Item 2 GP (Homogenous) 300mm x 300 mm glazed tiles on skirting of Prior approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Homogeneous) 300x300 mm size glazed floor tiles (FuWang, RAK, GreatWall or Prior approved quality)

1.0500

m2

645.60

677.88

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.1000

day

650.00

65.00

Mason

0.2000

day

550.00

110.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1600

day

370.00

59.20 1101.36

Subtotal-A: Other costs

( +2.00 % on Subtotal-A )

22.03

Subtotal-A1:

1123.39

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1145.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1260.44

VAT

6% of Total

IT

4% of Total

84.03 56.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1400.49

Page: 1414 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

5.15.07.03

GP glazed (Homogenous) floor tiles (400mm x 400 mm) of Prior approved best quality

sqm

Quantity 5

Unit

Rate

Amount

6

7

8

GP (Homogeneous) 400x400 mm size glazed floor tiles (FuWang, RAK, GreatWall or Prior approved quality)

1.0000

m2

720.92

720.92

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.1600

day

450.00

72.00

Ordinary Labour

0.1600

day

370.00

59.20 1091.40

Subtotal-A: Other costs

( +2.00 % on Subtotal-A )

21.83

Subtotal-A1:

1113.23

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1135.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1249.04

VAT

6% of Total

IT

4% of Total

83.27 55.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1387.82

Page: 1415 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.04

Detailed Analysis Brief Description of Item 2 GP (Homogenous) 400mm x 400 mm glazed tiles on skirting of Prior approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Homogeneous) 400x400 mm size glazed floor tiles (FuWang, RAK, GreatWall or Prior approved quality)

1.0500

m2

720.92

756.97

Pasting tiles adhesives

5.8000

kg

16.00

92.80

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.1000

day

650.00

65.00

Mason

0.2000

day

550.00

110.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1600

day

370.00

59.20 1187.17

Subtotal-A: Others Costs

( +2.00 % on Subtotal-A )

23.74

Subtotal-A1:

1210.91

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1235.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1358.64

VAT

6% of Total

IT

4% of Total

90.58 60.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1509.60

Page: 1416 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.05

Detailed Analysis Brief Description of Item 2 GP un-glazed (Homogenous) floor tiles (300mm x 300 mm) of Prior approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Homogeneous) 300x300 mm size unglazed floor tiles ( RAK, GreatWall or Prior approved quality)

1.0000

m2

634.84

634.84

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.1600

day

450.00

72.00

Ordinary Labour

0.1600

day

370.00

59.20 1005.32

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

20.11

Subtotal-A1:

1025.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1045.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1150.53

VAT

6% of Total

IT

4% of Total

76.70 51.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1278.36

Page: 1417 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.06

Detailed Analysis Brief Description of Item 2 GP un-glazed (Homogenous) 300mm x 300 mm tiles on skirtingof Prior approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Homogeneous) 300x300 mm size unglazed floor tiles ( RAK, GreatWall or Prior approved quality)

1.0500

m2

634.84

666.58

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.1000

day

650.00

65.00

Mason

0.2000

day

550.00

110.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1600

day

370.00

59.20 1090.06

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

21.80

Subtotal-A1:

1111.86

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1134.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1247.51

VAT

6% of Total

IT

4% of Total

83.17 55.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1386.12

Page: 1418 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.07

Detailed Analysis Brief Description of Item 2 GP un-glazed (Homogenous) floor tiles (400mm x 400 mm) of Prior approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Homogeneous) 400x400 mm size unglazed floor tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

699.40

699.40

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.1600

day

450.00

72.00

Ordinary Labour

0.1600

day

370.00

59.20 1069.88

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

21.40

Subtotal-A1:

1091.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1113.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1224.41

VAT

6% of Total

IT

4% of Total

81.63 54.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1360.46

Page: 1419 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.08

Detailed Analysis Brief Description of Item 2 GP un-glazed (Homogenous) 400mm x 400 mm tiles on skirting of Prior approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Homogeneous) 400x400 mm size unglazed floor tiles (RAK, GreatWall or Prior approved quality)

1.0500

m2

699.40

734.37

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.2000

day

550.00

110.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1600

day

370.00

59.20 1144.85

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

22.90

Subtotal-A1:

1167.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1191.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1310.21

VAT

6% of Total

IT

4% of Total

87.35 58.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1455.79

Page: 1420 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.09

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) floor tiles (300mm x 300 mm) of Prior approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Mirror Polished) 300x300 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

645.60

645.60

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.1600

day

450.00

72.00

Ordinary Labour

0.1600

day

370.00

59.20 1016.08

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

20.32

Subtotal-A1:

1036.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1057.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1162.84

VAT

6% of Total

IT

4% of Total

77.52 51.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1292.05

Page: 1421 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.10

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) 300mm x 300 mm tiles on skirting

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Mirror Polished) 300x300 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0500

m2

645.60

677.88

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.2000

day

550.00

110.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1600

day

370.00

59.20 1088.36

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

21.77

Subtotal-A1:

1110.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1132.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1245.56

VAT

6% of Total

83.04

IT

4% of Total

55.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1383.96

Page: 1422 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.11

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) floor tiles (400mm x 400 mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Mirror Polished) 400x400 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

850.04

850.04

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.1600

day

450.00

72.00

Ordinary Labour

0.1600

day

370.00

59.20 1220.52

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

24.41

Subtotal-A1:

1244.93

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1269.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1396.81

VAT

6% of Total

93.12

IT

4% of Total

62.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1552.01

Page: 1423 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.12

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) 400mm x 400 mm tiles on skirting

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm GP (Mirror Polished) 400x400 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0500

m2

850.04

892.54

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.2000

day

550.00

110.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1600

day

370.00

59.20 1303.02

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

26.06

Subtotal-A1:

1329.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1355.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1491.23

VAT

6% of Total

99.42

IT

4% of Total

66.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1656.92

Page: 1424 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.13

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) floor tiles (600mm x 600 mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm GP (Mirror Polished) 600x600 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0000

m2

1097.52

1097.52

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.1600

day

550.00

88.00

Skilled Labour

0.1600

day

450.00

72.00

Ordinary Labour

0.1600

day

370.00

59.20 1468.00

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

29.36

Subtotal-A1:

1497.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1527.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1680.04

VAT

6% of Total

112.00

IT

4% of Total

74.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1866.71

Page: 1425 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.07.14

Detailed Analysis Brief Description of Item 2 GP (Mirror Polished) 600mm x 600 mm tiles on skirting

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm GP (Mirror Polished) 600x600 mm size floor tiles (RAK, GreatWall or Prior approved quality)

1.0500

m2

1097.52

1152.40

Pasting tiles adhesives

5.3800

kg

16.00

86.08

Tiles grout/Joint filler

0.1100

kg

120.00

13.20

Head Mason

0.0800

day

650.00

52.00

Mason

0.2000

day

550.00

110.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1600

day

370.00

59.20 1562.88

Subtotal-A: Others costs

( +2.00 % on Subtotal-A )

31.26

Subtotal-A1:

1594.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1626.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1788.62

VAT

6% of Total

119.24

IT

4% of Total

79.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1987.35

Page: 1426 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.15.08

Detailed Analysis Brief Description of Item 2 Picking-up old tiles, marble, mosaic, facing bricks etc. with cement mortar or cement plaster works in floor & walls without any damages the structure in/c. cleaning and removing the debris's to a safe distance etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Ordinary Labour

0.3000

day

370.00

111.00

Skilled Labour

0.0200

day

450.00

9.00 120.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

122.40

10% Profit ( Add 10% on Subtotal-B) :

134.64

VAT

6% of Total

IT

4% of Total

8.98 5.98 Total:

5.15.09

149.60

Labour Cost for making moulding in marble stone as per Architectural drawing including cutting, grinding, finishing, supplying necessary equipment etc. complete in all respect as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1427 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.15.09.01

2 18 mm thick marble stone

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m Head Mason

0.1700

day

650.00

110.50

Ordinary Labour

0.1700

day

370.00

62.90

Disk

0.1000

each

660.00

66.00

Water proofing paper (12 size)

0.7000

each

16.20

11.34

Water proofing paper (320 size)

0.7000

each

19.80

13.86

H.C. of electric grinding machine

0.1700

day

165.00

28.05

Acid stone

0.1000

each

310.00

31.00 323.65

Subtotal-A: All other remaining costs, tools, plants, sundries etc

( +1.00 % on Subtotal-A )

3.24

Subtotal-A1:

326.89

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

333.42

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

366.77

VAT

6% of Total

IT

4% of Total

24.45 16.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

407.52

Page: 1428 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.15.09.02

2 16 mm thick marble stone

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m Head Mason

0.1700

day

650.00

110.50

Ordinary Labour

0.1700

day

370.00

62.90

Disk

0.1000

each

660.00

66.00

Water proofing paper (12 size)

0.6000

each

16.20

9.72

Water proofing paper (320 size)

0.6000

each

19.80

11.88

H.C. of electric grinding machine

0.1700

day

165.00

28.05

Acid stone

0.1000

each

310.00

31.00 320.05

Subtotal-A: All other remaining costs, tools, plants, sundries etc

( +1.00 % on Subtotal-A )

3.20

Subtotal-A1:

323.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

329.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

362.69

VAT

6% of Total

IT

4% of Total

24.18 16.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

402.99

Page: 1429 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.15.09.03

2 12 mm thick marble stone

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Head Mason

0.1200

day

650.00

78.00

Ordinary Labour

0.1200

day

370.00

44.40

Disk

0.1000

each

660.00

66.00

Water proofing paper (12 size)

0.5000

each

16.20

8.10

Water proofing paper (320 size)

0.5000

each

19.80

9.90

H.C. of electric grinding machine

0.1700

day

165.00

28.05

Acid stone

0.1000

each

310.00

31.00 265.45

Subtotal-A: All other remaining costs, tools, plants, sundries etc

( +1.00 % on Subtotal-A )

2.65

Subtotal-A1:

268.10

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

273.47

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

300.81

VAT

6% of Total

IT

4% of Total

20.05 13.37 Total:

5.15.10

334.24

Marble stone flooring with Italian (CARRARA) or equivalent Europian country best quality black /white marble stone of approved quality, texture and size fixed over 25mm thick cement sand mortar (1:2) on floor with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) or over 12mm thick cement sand mortar (1:2) in wall with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) including placing cement slurry below the stone, cutting the marble stone to desired size, grinding and finishing the edges , setting in position in proper level filling the gaps with white cement and colouring pigments including supplying all necessary equipments / materials and finishing and polishing the top by pumic stone and necessary auxiliary materials and water, electricity and other charges complete in all respect as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1430 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.15.10.01

18 mm thick Marble stone flooring (Italian -CARRARA) or equivalent Europian country best quality

5.15.10.01.1

For Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 18 mm thick Marble stone (Italian- CARRARA)

1.0000

sqm

4842.00

4842.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 5045.23

Subtotal-A: Polishing with all materials, cost of cutting, shaping, laying, tools, plants etc. all remaining cost

( +25.00 % on Subtotal-A )

Subtotal-A1:

6306.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6432.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7075.93

VAT

6% of Total

IT

4% of Total

471.73 314.49 Total:

5.15.10.01.2

Add for each additional floor up to 5 th floor

sqm

Add +5.00% with Item No 5.15.10.01.1

5.15.10.01.3

Add for each additional floor for 6th floor to 9th floor

sqm

Add +10.00% with Item No 5.15.10.01.1

5.15.10.01.4

Add for each additional floor for 10th floor and above

sqm

Add +14.00% with Item No 5.15.10.01.1

5.15.10.02

16 mm thick Marble stone flooring (Italian -CARRARA) or equivalent Europian country best quality

Note : Rates of all items should be inclusive of all supply and carriage.

1261.31

7862.15

Page: 1431 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.15.10.02.1

2 For Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 16 mm thick Marble stone (Italian- CARRARA)

1.0000

sqm

4519.00

4519.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 4722.23

Subtotal-A: Polishing with all materials, cost of cutting, shaping, laying, tools, plants etc. all remaining cost

( +25.00 % on Subtotal-A )

Subtotal-A1:

5902.79

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6020.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6622.92

VAT

6% of Total

IT

4% of Total

441.53 294.35 Total:

5.15.10.02.2

Add for each addl. floor up to 5 th floor

sqm

Add +5.00% with Item No 5.15.10.02.1

5.15.10.02.3

Add for each addl. floor for 6th floor to 9th floor

sqm

Add +10.00% with Item No 5.15.10.02.1

5.15.10.02.4

Add for each addl. floor for 10th floor and above

sqm

Add +14.00% with Item No 5.15.10.02.1

5.15.10.03

14 mm thick Marble stone flooring (Italian -CARRARA) or equivalent Europian country best quality

Note : Rates of all items should be inclusive of all supply and carriage.

1180.56

7358.81

Page: 1432 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.15.10.03.1

2 For Ground floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 14 mm thick Marble stone (Italian- CARRARA)

1.0000

sqm

4519.00

4519.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 4722.23

Subtotal-A: Polishing with all materials, cost of cutting, shaping, laying, tools, plants etc. all remaining cost

( +25.00 % on Subtotal-A )

Subtotal-A1:

5902.79

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6020.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6622.92

VAT

6% of Total

IT

4% of Total

441.53 294.35 Total:

5.15.10.03.2

Add for each addl. floor up to 5 th floor

sqm

Add +5.00% with Item No 5.15.10.03.1

5.15.10.03.3

Add for each addl. floor for 6th floor to 9th floor

sqm

Add +10.00% with Item No 5.15.10.03.1

5.15.10.03.4

Add for each addl. floor for 10th floor and above

sqm

Add +14.00% with Item No 5.15.10.03.1

5.15.10.04

12 mm thick Marble stone walling (Italian -CARRARA) or equivalent Europian country best quality

Note : Rates of all items should be inclusive of all supply and carriage.

1180.56

7358.81

Page: 1433 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.15.10.04.1

2 For Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 12 mm thick Marble stone (Italian- CARRARA)

1.0000

sqm

4304.00

4304.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 4507.23

Subtotal-A: Polishing with all materials, cost of cutting, shaping, laying, tools, plants etc. all remaining cost

( +25.00 % on Subtotal-A )

Subtotal-A1:

5634.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5746.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6321.39

VAT

6% of Total

IT

4% of Total

421.43 280.95 Total:

5.15.10.04.2

Add for each addl. Floor up to 5 th floor

sqm

Add +5.00% with Item No 5.15.10.04.1

5.15.10.04.3

Add for each addl. floor for 6th floor to 9th floor

sqm

Add +10.00% with Item No 5.15.10.04.1

5.15.10.04.4

Add for each addl. floor for 10th floor and above

sqm

Add +14.00% with Item No 5.15.10.04.1

Note : Rates of all items should be inclusive of all supply and carriage.

1126.81

7023.76

Page: 1434 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.15.11

Marble stone flooring with Indian or equivalent Asian country best quality black /white marble stone of approved quality, texture and size fixed over 25mm thick cement sand mortar (1:2) on floor with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) or over 12mm thick cement sand mortar (1:2) in wall with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) including placing cement slurry below the stone, cutting the marble stone to desired size, grinding and finishing the edges, setting in position in proper level filling the gaps with white cement and colouring pigments including supplying all necessary equipments / materials and finishing, polishing the top by pumic stone and necessary auxiliary materials and water, electricity and other charges complete in all respect as per direction of the E-I-C.

5.15.11.01

18 mm thick Marble stone flooring (Indian) or equivalent Asian country best quality

5.15.11.01.1

For Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 18mm thick Marble stone (Indian)

1.0000

sqm

3825.00

3825.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 4028.23

Subtotal-A: polising with all materials, etc. Labour cost for laying cost of cutting, shaping, tools, plants, etc.

( +9.10 % on Subtotal-A ) ( +6.40 % on Subtotal-A ) ( +8.50 % on Subtotal-A )

366.57 257.81 342.40

Subtotal-A1: Subtotal-B: Subtotal-C:

4995.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5094.90

10% Profit ( Add 10% on Subtotal-B) :

5604.39

VAT

6% of Total

IT

4% of Total

373.63 249.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6227.10

Page: 1435 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.15.11.01.2

Add for each additional floor up to 5th Floor

sqm

Add +5.00% with Item No 5.15.11.01.1

5.15.11.01.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +10.00% with Item No 5.15.11.01.1

5.15.11.01.4

Add for each additional floor for 10th Floor and above

sqm

Add +14.00% with Item No 5.15.11.01.1

5.15.11.02

16 mm thick Marble stone flooring (Indian) or equivalent Asian country best quality

5.15.11.02.1

For Ground Floor

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 16mm thick Marble stone (Indian)

1.0000

sqm

3450.00

3450.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 3653.23

Subtotal-A: polising with all materials, etc. Labour cost for laying cost of cutting, shaping, tools, plants, etc.

( +9.10 % on Subtotal-A ) ( +5.80 % on Subtotal-A ) ( +8.50 % on Subtotal-A )

332.44 211.89 310.52

Subtotal-A1: Subtotal-B: Subtotal-C:

4508.08 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4598.25

10% Profit ( Add 10% on Subtotal-B) :

5058.07

VAT

6% of Total

IT

4% of Total

337.20 224.80 Total:

5.15.11.02.2

Add for each additional floor up to 5th Floor

sqm

Add +5.00% with Item No 5.15.11.02.1

5.15.11.02.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +10.00% with Item No 5.15.11.02.1

5.15.11.02.4

Add for each additional floor for 10th Floor and above

sqm

Add +14.00% with Item No 5.15.11.02.1

Note : Rates of all items should be inclusive of all supply and carriage.

5620.08

Page: 1436 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.15.11.03

14 mm thick Marble stone flooring (Indian) or equivalent Asian country best quality

5.15.11.03.1

For Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 14mm thick Marble stone (Indian)

1.0000

sqm

3240.00

3240.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 3443.23

Subtotal-A: polising with all materials, etc. Labour cost for laying cost of cutting, shaping, tools, plants, etc.

( +9.50 % on Subtotal-A ) ( +7.00 % on Subtotal-A ) ( +9.00 % on Subtotal-A )

327.11 241.03 309.89

Subtotal-A1:

4321.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4407.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4848.44

VAT

6% of Total

IT

4% of Total

323.23 215.49 Total:

5.15.11.03.2

Add for each additional floor up to 5th Floor

sqm

Add +5.00% with Item No 5.15.11.03.1

5.15.11.03.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +10.00% with Item No 5.15.11.03.1

5.15.11.03.4

Add for each additional floor for 10th Floor and above

sqm

Add +14.00% with Item No 5.15.11.03.1

5.15.11.04

12 mm thick Marble stone walling (Indian) or equivalent Asian country best quality

Note : Rates of all items should be inclusive of all supply and carriage.

5387.16

Page: 1437 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.15.11.04.1

2 For Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 12mm thick Marble stone (Indian)

1.0000

sqm

3060.00

3060.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 3263.23

Subtotal-A: polising with all materials, etc. Labour cost for laying cost of cutting, shaping, tools, plants, etc.

( +12.00 % on Subtotal-A ) ( +8.00 % on Subtotal-A ) ( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4242.20 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4327.04

10% Profit ( Add 10% on Subtotal-B) :

4759.74

VAT

6% of Total

IT

4% of Total

317.32 211.54 Total:

5.15.11.04.2

Add for each additional floor up to 5th Floor

sqm

Add +5.00% with Item No 5.15.11.04.1

5.15.11.04.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +10.00% with Item No 5.15.11.04.1

5.15.11.04.4

Add for each additional floor for 10th Floor and above

sqm

Add +15.00% with Item No 5.15.11.04.1

Note : Rates of all items should be inclusive of all supply and carriage.

391.59 261.06 326.32

5288.60

Page: 1438 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.15.12

Supplying, fitting, fixing and Installation of Black Granite or approved colour on floor with Italian (CARRARA) or equivalent Europian country best quality Polished granite of approved quality, texture and size fixed over size fixed over 25mm thick cement sand mortar (1:2) on floor with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) including placing cement slurry below the stone, cutting the marble stone to desired size, grinding and finishing the edges , setting in position in proper level filling the gaps with white cement and colouring pigments including supplying all necessary equipments / materials and finishing polishing the top by pumic stone and necessary auxiliary materials and water, electricity and other charges complete in all respect as per direction of the E-I-C.

5.15.12.01

18 mm thick black or approved colour polished granite flooring (Italian CARRARA) or equivalent Europian country best quality

5.15.12.01.1

For Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 18 mm thick black or approved colour polished granite (Italian -CARRARA)

1.0000

sqm

5380.00

5380.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 5583.23

Subtotal-A: cost of cutting, shaping, laying, tools, plants etc. all remaining cost

( +25.00 % on Subtotal-A )

Subtotal-A1:

6979.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7118.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7830.48

VAT

6% of Total

IT

4% of Total

522.03 348.02 Total:

5.15.12.01.2

Add for each additional floor up to 5th Floor

Note : Rates of all items should be inclusive of all supply and carriage.

sqm

1395.81

8700.53

Add +5.00% with Item No 5.15.12.01.1 Page: 1439 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.15.12.01.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +10.00% with Item No 5.15.12.01.1

5.15.12.01.4

Add for each additional floor for 10th Floor and above

sqm

Add +14.00% with Item No 5.15.12.01.1

5.15.13

Supplying, fitting, fixing and Installation of Black Granite or approved colour on wall with Italian (CARRARA) or equivalent Europian country best quality Polished granite of approved quality, texture and size fixed over size fixed over 12mm thick cement sand mortar (1:2) in wall with Portland Composite cement (CEM II/AM, 42.5N) and best quality sand (minimum FM1.2) including placing cement slurry below the stone, cutting the marble stone to desired size, grinding and finishing the edges , setting in position in proper level filling the gaps with white cement and colouring pigments including supplying all necessary equipments / materials and finishing polishing the top by pumic stone and necessary auxiliary materials and water, electricity and other charges complete in all respect as per direction of the E-I-C.

5.15.13.01

18 mm thick black or approved colour polished granite flooring (Italian CARRARA) or equivalent Europian country best quality

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1440 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.15.13.01.1

2 For Ground Floor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 18 mm thick black or approved colour polished granite (Italian -CARRARA)

1.0000

sqm

5380.00

5380.00

White Cement

0.4400

kg

25.00

11.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3900

bag

430.00

167.70

Sand (FM - 1.2)

0.0420

m3

584.00

24.53 5583.23

Subtotal-A: cost of cutting, shaping, laying, tools, plants etc. all remaining cost

( +15.00 % on Subtotal-A )

Subtotal-A1:

6420.71

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6549.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7204.04

VAT

6% of Total

IT

4% of Total

480.27 320.18 Total:

5.15.13.01.2

Add for each additional floor up to 5th Floor

sqm

Add +5.00% with Item No 5.15.13.01.1

5.15.13.01.3

Add for each additional floor from 6th up to 9th Floor

sqm

Add +10.00% with Item No 5.15.13.01.1

5.15.13.01.4

Add for each additional floor for 10th Floor and above

sqm

Add +14.00% with Item No 5.15.13.01.1

Note : Rates of all items should be inclusive of all supply and carriage.

837.48

8004.49

Page: 1441 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.01.01

Detailed Analysis Brief Description of Item 2 White washing three coats over a coat of priming with slacked stone lime mixed with gums, blue. Lime mix prepared at least 12 hours before use, in/c removing the floating materials from the mixture, surface cleaning to free all foreign materials before application of each coat. Applying one vertical and one horizontal wash for each coat and successive coat is to be applied after drying up of previous coat i/c cost of hair brush, providing necessary scaffolding and necessary cleaning the plinth, floors, doors, windows, partions and ventilators by washing, rubbing as if necessary before and after the wash, polishing the surface with sand paper etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Slacked Lime

0.2000

kg

27.00

Gum

3.2300

gm

0.17

0.55

Blue

2.1500

gm

0.12

0.26

Mason

0.0160

day

550.00

8.80

Ordinary Labour

0.0100

day

370.00

3.70 18.71

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +8.00 % on Subtotal-A )

1.50

Subtotal-A1:

20.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22.67

VAT

6% of Total

IT

4% of Total

1.51 1.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5.40

25.19

Page: 1442 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.01.02

Detailed Analysis Brief Description of Item 2 White washing two coats with slacked stone lime mixed with gums, blue. Lime mix prepared at least 12 hours before use in/c removing the floating materials from the mixture, surface cleaning to free from all foreign materials before application of each coat. Applying one vertical and one horizontal wash for each coat and successive coat is to be applied after drying up of previous coat i/c cost of hair brush, providing necessary scaffolding and necessary cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary before and after the wash, polishing the surface with sand paper etc. all complete for all floors i/c cost of all materials as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Slacked Lime

0.1300

kg

27.00

Gum

2.1500

gm

0.17

0.37

Blue

1.4300

gm

0.12

0.17

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0100

day

370.00

3.70 13.25

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +8.00 % on Subtotal-A )

1.06

Subtotal-A1:

14.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16.05

VAT

6% of Total

IT

4% of Total

1.07 0.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3.51

17.84

Page: 1443 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.01.03

Detailed Analysis Brief Description of Item 2 White washing one coats with slacked stone lime mixed with gums, blue. Lime mix prepared at least 12 hours before use in/c removing the floating materials from the mixture, surface cleaning to free from all foreign materials before application of each coat. Applying one vertical and one horizontal wash for each coat and successive coat is to be applied after drying up of previous coat i/c cost of hair brush, providing necessary scaffolding and necessary cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary before and after the wash, polishing the surface with sand paper etc. all complete for all floors i/c cost of all materials as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Slacked Lime

0.0650

kg

27.00

Gum

1.0800

gm

0.17

0.18

Blue

0.7150

gm

0.12

0.09

Mason

0.0050

day

550.00

2.75

Ordinary Labour

0.0050

day

370.00

1.85 6.62

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +8.00 % on Subtotal-A )

0.53

Subtotal-A1:

7.15

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8.03

VAT

6% of Total

0.54

IT

4% of Total

0.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1.76

8.92

Page: 1444 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.02.01

Detailed Analysis Brief Description of Item 2 Colour wash with yellow orchre in two coats over a prime coat of white wash. Lime mix prepared at least 12 hours before use in/c removing the floating materials from the mixture, surface cleaning to free from all foreign materials before application of each coat. Applying one vertical and one horizontal wash for each coat and successive coat is to be applied after drying up of previous coat i/c cost of hair brush, providing necessary scaffolding and necessary cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary before and after the wash, polishing the surface with sand paper etc. all complete for all floors i/c cost of all materials as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Slacked Lime

0.2000

kg

27.00

Gum

3.2300

gm

0.17

0.55

Blue

2.1500

gm

0.12

0.26

Colour Pigment

0.0100

kg

120.00

1.20

Mason

0.0160

day

550.00

8.80

Ordinary Labour

0.0100

day

370.00

3.70 19.91

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +6.00 % on Subtotal-A )

1.19

Subtotal-A1: Subtotal-B: Subtotal-C:

21.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21.52

10% Profit ( Add 10% on Subtotal-B) :

23.68

VAT

6% of Total

IT

4% of Total

1.58 1.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5.40

26.31

Page: 1445 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.02.02

Detailed Analysis Brief Description of Item 2 Colour wash with yellow orchre in one coats . Lime mix prepared at least 12 hours before use in/c removing the floating materials from the mixture, surface cleaning to free from all foreign materials before application of each coat. Applying one vertical and one horizontal wash for each coat and successive coat is to be applied after drying up of previous coat i/c cost of hair brush, providing necessary scaffolding and necessary cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary before and after the wash, polishing the surface with sand paper etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Slacked Lime

0.2000

kg

27.00

5.40

Gum

3.2300

gm

0.17

0.55

Blue

2.1500

gm

0.12

0.26

Colour Pigment

0.0100

kg

120.00

1.20

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.0100

day

370.00

3.70 16.61

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +6.00 % on Subtotal-A )

1.00

Subtotal-A1:

17.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19.75

VAT

6% of Total

IT

4% of Total

1.32 0.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21.95

Page: 1446 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.03.01

Detailed Analysis Brief Description of Item 2 Cement paint of approved quality and colour (Bangladesh made) from authorized manufacturer in a seal container, having highly water resistant, high bond ability, flexible in two coats over a coat of priming. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Cement Paint

0.3230

kg

80.00

25.84

Mason

0.0540

day

550.00

29.70

Ordinary Labour

0.0540

day

370.00

19.98 75.52

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +4.50 % on Subtotal-A )

3.40

Subtotal-A1:

78.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

80.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

88.55

VAT

6% of Total

IT

4% of Total

5.90 3.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

98.38

Page: 1447 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.03.02

Detailed Analysis Brief Description of Item 2 Cement paint of approved quality and colour (Bangladesh made) from authorized manufacturer in a seal container, having highly water resistant, high bond ability, flexible in two coats. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Cement Paint

0.2200

kg

80.00

17.60

Mason

0.0400

day

550.00

22.00

Ordinary Labour

0.0400

day

370.00

14.80 54.40

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +4.50 % on Subtotal-A )

2.45

Subtotal-A1:

56.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

57.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

63.78

VAT

6% of Total

IT

4% of Total

4.25 2.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

70.87

Page: 1448 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.03.03

Detailed Analysis Brief Description of Item 2 Cement paint of approved quality and colour (Bangladesh made) from authorized manufacturer in a seal container, having highly water resistant, high bond ability, flexible in one coats. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Cement Paint

0.1100

kg

80.00

8.80

Mason

0.0200

day

550.00

11.00

Ordinary Labour

0.0200

day

370.00

7.40 27.20

Subtotal-A: All other remaining costs covering scaffolding, curing etc.

( +4.50 % on Subtotal-A )

1.22

Subtotal-A1:

28.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

31.89

VAT

6% of Total

IT

4% of Total

2.13 1.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35.44

Page: 1449 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.04.01

Detailed Analysis Brief Description of Item 2 Distempering with ready mixed synthetic polyvinyl distemper from authorized manufacturer in a seal container, to wall and ceiling in two coats over a coat of primer/sealer. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Synthetic Polyvinyl Distemper

0.1000

litre

117.50

11.75

Distemper Primer/sealer

0.0900

litre

204.00

18.36

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 154.31

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +5.00 % on Subtotal-A )

7.72

Subtotal-A1: Subtotal-B: Subtotal-C:

162.03 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

165.27

10% Profit ( Add 10% on Subtotal-B) :

181.79

VAT

6% of Total

12.12

IT

4% of Total

8.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

201.99

Page: 1450 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.04.02

Detailed Analysis Brief Description of Item 2 Distempering with ready mixed synthetic polyvinyl distemper from authorized manufacturer in a seal container, to wall and ceiling in two coats. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Synthetic Polyvinyl Distemper

0.1000

litre

117.50

Plumber/ Electric Mistry/ Painter

0.0540

day

680.00

36.72

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0540

day

470.00

25.38 73.85

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +5.00 % on Subtotal-A )

3.69

Subtotal-A1: Subtotal-B: Subtotal-C:

77.54 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

79.09

10% Profit ( Add 10% on Subtotal-B) :

87.00

VAT

6% of Total

IT

4% of Total

5.80 3.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11.75

96.67

Page: 1451 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.04.03

Detailed Analysis Brief Description of Item 2 Distempering with ready mixed synthetic polyvinyl distemper from authorized manufacturer in a seal container, to wall and ceiling in one coats. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Synthetic Polyvinyl Distemper

0.0500

litre

117.50

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 40.38

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +5.00 % on Subtotal-A )

2.02

Subtotal-A1: Subtotal-B: Subtotal-C:

42.39 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

43.24

10% Profit ( Add 10% on Subtotal-B) :

47.57

VAT

6% of Total

IT

4% of Total

3.17 2.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5.88

52.85

Page: 1452 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.05.01

Detailed Analysis Brief Description of Item 2 Painting with plastic emulsion paint of best quality and approved colour in a seal container from authorized manufacturer. Applying each coat and successive coat is to be applied as per manufacturer special procedure, to wall and ceiling in two coats over a coat of priming coat of water sealer and ready mixed putty of approved brand. It applied on sand papered and cleaned surface and after drying applied sealer coat, 2 coats of ready mixed wall putty of approved brand, each coat dried and smoothened by sand papering. Applying plastic emulsion paint one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Plastic Emulsion paint

0.1350

litre

235.00

31.73

Plastic Emulsion paint sealer/ Primer

0.0900

litre

193.00

17.37

Ready mixed wall Putty

0.0900

kg

76.00

6.84

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 180.14

Subtotal-A: All other remaining costs covering scaffolding, site mix or ready mix putty, sand papering etc.

( +8.00 % on Subtotal-A )

14.41

Subtotal-A1:

194.55

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

198.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

218.28

VAT

6% of Total

14.55

IT

4% of Total

9.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

242.53

Page: 1453 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.05.02

Detailed Analysis Brief Description of Item 2 Painting with plastic emulsion paint of best quality and approved colour in a seal container from authorized manufacturer special procedure, to wall and ceiling in two coats. Applying plastic emulsion paint one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Plastic Emulsion paint

0.1350

litre

235.00

31.73

Plumber/ Electric Mistry/ Painter

0.0540

day

680.00

36.72

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0540

day

470.00

25.38 93.83

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +4.00 % on Subtotal-A )

3.75

Subtotal-A1: Subtotal-B: Subtotal-C:

97.58 99.53

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

109.48

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

7.30

IT

4% of Total

4.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

121.65

Page: 1454 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.05.03

Detailed Analysis Brief Description of Item 2 Painting with plastic emulsion paint of best quality and approved colour from authorized manufacturer in a seal container special procedure, to wall and ceiling in one coats Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Plastic Emulsion paint

0.0700

litre

235.00

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 50.95

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +4.00 % on Subtotal-A )

2.04

Subtotal-A1: Subtotal-B: Subtotal-C:

52.99 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

54.05

10% Profit ( Add 10% on Subtotal-B) :

59.45

VAT

6% of Total

IT

4% of Total

3.96 2.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

16.45

66.06

Page: 1455 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.06

Detailed Analysis Brief Description of Item 2 Painting with acrylic emulsion paint (silky finish) of best quality and approved colour from authorized manufacturer in a seal container, to wall and ceiling in two coats over a coat of acrylic sealer Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. curing for the requisite period etc. all complete for all floors i/c cost of all materials as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Acrylic Emulsion paint

0.1350

litre

210.00

28.35

Acrylic sealer/ primer

0.1350

litre

163.00

22.01

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 174.56

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +3.00 % on Subtotal-A )

5.24

Subtotal-A1:

179.79

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

183.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

201.73

VAT

6% of Total

IT

4% of Total

13.45 8.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

224.14

Page: 1456 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.07

Detailed Analysis Brief Description of Item 2 Painting with Jensolin chlorinated rubber paint of best quality and approved colour from authorized manufacturer in a seal container, to walls in three coats in/c finishing with sand paper, cleaning the old surface with soap water/caustic soda or sand paper as per requirement before application etc. complete in all respects as per direction of the EI-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Jensolin Chlorinated rubber paint

0.2690

litre

522.50

140.55

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 264.75

Subtotal-A: All other remaining costs covering scaffolding, etc.

( +3.00 % on Subtotal-A )

7.94

Subtotal-A1: Subtotal-B: Subtotal-C:

272.70 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

278.15

10% Profit ( Add 10% on Subtotal-B) :

305.96

VAT

6% of Total

IT

4% of Total

20.40 13.60 Total:

5.16.09

339.96

On exterior surface applying as per manufacturer instruction specific coat of weather coat of approved quality and colour delivered from authorized local agent of the manufacturer in a sealed container. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning, washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1457 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.16.09.01

2 3 coat

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Weather coat

0.1650

liter

321.94

53.12

Sealer/Primer (for texture paint)

0.0950

litre

200.00

19.00

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1100

day

470.00

51.70 198.62

Subtotal-A: Cleaning, sand papering, sacffolding, etc.

( +4.00 % on Subtotal-A )

7.94

Subtotal-A1:

206.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

210.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

231.77

VAT

6% of Total

15.45

IT

4% of Total

10.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

257.52

Page: 1458 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.16.09.02

2 2 coat

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Weather coat

0.1100

liter

321.94

35.41

Sealer/Primer (for texture paint)

0.0600

litre

200.00

12.00

Plumber/ Electric Mistry/ Painter

0.0700

day

680.00

47.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90 127.91

Subtotal-A: Cleaning, sand papering, scaffolding, etc.

( +3.00 % on Subtotal-A )

3.84

Subtotal-A1:

131.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

134.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

147.82

VAT

6% of Total

9.85

IT

4% of Total

6.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

164.25

Page: 1459 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.10.01

Detailed Analysis Brief Description of Item 2 Painting to door and window frames, shutters and any type of MS rod, FI bar, MS box, MS angle grill, gate etc. in two coats with synthetic enamel paint of best quality and approved colour over a coat of priming. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning, washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Synthetic Enamel Paint

0.1200

litre

260.00

31.20

Synthetic enamel paint primer/ sealer

0.0900

litre

206.00

18.54

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 173.94

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, etc.

( +7.00 % on Subtotal-A )

12.18

Subtotal-A1: Subtotal-B: Subtotal-C:

186.12 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

189.84

10% Profit ( Add 10% on Subtotal-B) :

208.82

VAT

6% of Total

13.92

IT

4% of Total

9.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

232.02

Page: 1460 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.10.02

Detailed Analysis Brief Description of Item 2 Painting to door and window frames, shutters and any type of MS rod, FI bar, MS box, MS angle grill, gate etc. in two coats with synthetic enamel paint of best quality and approved colour. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning, washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Synthetic Enamel Paint

0.1200

litre

260.00

31.20

Plumber/ Electric Mistry/ Painter

0.0540

day

680.00

36.72

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0540

day

470.00

25.38 93.30

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, etc.

( +7.00 % on Subtotal-A )

6.53

Subtotal-A1: Subtotal-B: Subtotal-C:

99.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

101.83

10% Profit ( Add 10% on Subtotal-B) :

112.01

VAT

6% of Total

IT

4% of Total

7.47 4.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

124.46

Page: 1461 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.10.03

Detailed Analysis Brief Description of Item 2 Painting to door and window frames, shutters and any type of MS rod, FI bar, MS box, MS angle grill, gate etc. in one coats with synthetic enamel paint of best quality and approved colour. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning, washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Synthetic Enamel Paint

0.0600

litre

260.00

15.60

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 50.10

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, etc.

( +7.00 % on Subtotal-A )

3.51

Subtotal-A1: Subtotal-B: Subtotal-C:

53.61 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

54.68

10% Profit ( Add 10% on Subtotal-B) :

60.15

VAT

6% of Total

IT

4% of Total

4.01 2.67 Total:

5.16.11

66.83

Wood varnishing to door and window frames, shutters or any type of wood works in three coats with ready for use wood care varnishes applied with brush. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat in/c cleaning, washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1462 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.16.11.01

2 Varnish (Yacht)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Varnish (yacht)

0.2020

litre

250.00

50.50

G.P thinner

0.0220

litre

130.00

2.86

Sand Paper

0.4300

each

8.00

3.44

Markin cloth

0.0500

m

10.00

0.50

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 181.50

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, etc.

( +3.00 % on Subtotal-A )

5.45

Subtotal-A1:

186.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

190.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

209.75

VAT

6% of Total

IT

4% of Total

13.98 9.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

233.06

Page: 1463 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.16.11.02

2 Varnish (Egg shell)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Varnish (Egg shell)

0.2020

litre

250.00

50.50

G.P thinner

0.0220

litre

130.00

2.86

Sand Paper

0.4300

each

8.00

3.44

Markin cloth

0.0500

m

10.00

0.50

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 181.50

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, etc.

( +3.00 % on Subtotal-A )

5.45

Subtotal-A1:

186.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

190.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

209.75

VAT

6% of Total

IT

4% of Total

13.98 9.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

233.06

Page: 1464 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.16.11.03

2 Varnish (Matt)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Varnish (Matt)

0.2020

litre

280.00

56.56

G.P thinner

0.0220

litre

130.00

2.86

Sand Paper

0.4300

each

8.00

3.44

Markin cloth

0.0500

m

10.00

0.50

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 187.56

Subtotal-A: All other remaining costs covering sand paper, putty, scaffolding, etc.

( +3.00 % on Subtotal-A )

5.63

Subtotal-A1:

193.19

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

197.05

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

216.76

VAT

6% of Total

IT

4% of Total

14.45 9.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

240.84

Page: 1465 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.12.01

Detailed Analysis Brief Description of Item 2 French polishing to door and window frames, shutters or any type of wood works in three coats over a coat of priming. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat in/c cleaning, washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Spirit

0.4300

lb

100.00

43.00

Gala

0.2200

chatak

87.50

19.25

Mostaki

0.0180

seer

365.00

6.57

Karpa

0.1080

chatak

37.50

4.05

Sand Paper

0.4300

each

8.00

3.44

Markin cloth

0.0500

m

10.00

0.50

Plumber/ Electric Mistry/ Painter

0.1080

day

680.00

73.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1080

day

470.00

50.76 201.01

Subtotal-A: All other cost covering cleaning, scraping, etc.

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

237.19 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

241.94

10% Profit ( Add 10% on Subtotal-B) :

266.13

VAT

6% of Total

IT

4% of Total

17.74 11.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

36.18

295.70

Page: 1466 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.12.02

Detailed Analysis Brief Description of Item 2 French polishing to door and window frames, shutters or any type of wood works in two coats. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat in/c cleaning, washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Spirit

0.2900

lb

100.00

29.00

Gala

0.1500

chatak

87.50

13.13

Mostaki

0.0120

seer

365.00

4.38

Karpa

0.0720

chatak

37.50

2.70

Sand Paper

0.2900

each

8.00

2.32

Markin cloth

0.0330

m

10.00

0.33

Plumber/ Electric Mistry/ Painter

0.0720

day

680.00

48.96

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0720

day

470.00

33.84 134.66

Subtotal-A: All other cost covering cleaning, scraping, etc.

( +15.00 % on Subtotal-A )

Subtotal-A1:

154.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

157.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

173.75

VAT

6% of Total

11.58

IT

4% of Total

7.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

20.20

193.05

Page: 1467 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.12.03

Detailed Analysis Brief Description of Item 2 French polishing to door and window frames, shutters or any type of wood works in one coats. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat in/c cleaning, washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Spirit

0.1400

lb

100.00

14.00

Gala

0.0750

chatak

87.50

6.56

Mostaki

0.0060

seer

365.00

2.19

Karpa

0.0360

chatak

37.50

1.35

Sand Paper

0.1450

each

8.00

1.16

Markin cloth

0.0160

m

10.00

0.16

Plumber/ Electric Mistry/ Painter

0.0360

day

680.00

24.48

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0360

day

470.00

16.92 66.82

Subtotal-A: All other cost covering cleaning, scraping, etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

74.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

76.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

83.97

VAT

6% of Total

5.60

IT

4% of Total

3.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8.02

93.30

Page: 1468 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.13

Detailed Analysis Brief Description of Item 2 Painting with textured paint of best quality and approved colour from authorized manufacturer in a seal container, to internal and external surfaces in three layer system consisting of one coat sealer, one coat texture and two coats of top coat (glossy finishing) applied as per standard method/practice Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding, etc. surface smoothing by putty etc. all complete for all floors i/c cost of all materials as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Sealer/Primer (for texture paint)

0.1080

litre

200.00

Texture Paint

2.1500

litre

215.00

462.25

Paint for glossy finishing (Top coat)

0.3840

litre

671.25

257.76

Operator

0.0540

day

570.00

30.78

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0540

day

470.00

25.38 797.77

Subtotal-A: All other remaining costs covering scaffolding, machinery, electricity, etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

111.69 909.46 927.65

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1020.41

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

68.03

IT

4% of Total

45.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21.60

1133.79

Page: 1469 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.14

Detailed Analysis Brief Description of Item 2 Scrapping out old polishing or varnishing to wooden door & window frames & shutter properly without any damages the surface by any means including cleaning the existing surface properly for polishing or vernishing and cost of sand paper and all other materials and labour etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1400

day

470.00

65.80

Sand Paper

0.5000

each

8.00

4.00 76.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

78.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

85.95

VAT

6% of Total

5.73

IT

4% of Total

3.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

95.49

Page: 1470 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.16

Detailed Analysis Brief Description of Item 2 Providing lime chalk powder coating (three coats) to non plastered cement surfaces of ceiling, beams or wherever directed. Chalk powder mixed with Arabian gum properly, mixing applied as per standard method/ practice. Applying one vertical and one horizontal coat for each coat and successive coat is to be applied after drying up of previous coat by brush/roller/spray in/c cleaning the plinth, floors, doors, windows, portions and ventilators by washing, rubbing, as necessary and sand papering the surface and necessary scaffolding etc. all complete as per directions of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Chalk Powder

0.4000

kg

25.00

10.00

Arabian Gum

0.0050

Skilled Labour

0.0200

kg

330.00

1.65

day

450.00

9.00

Ordinary Labour

0.0500

day

370.00

18.50 39.15

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.39

Subtotal-A1:

39.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

44.37

VAT

6% of Total

2.96

IT

4% of Total

1.97 Total:

5.16.17.01

Providing two coats of ASTEC#9 having elongation break 683%, tensile strength 792 psi (made in USA), white or any other color, with thickness 250-300 microns to any type of concrete roof/side walls/metal/ asbestos/ fibre glass roof in/c removing all loose, defective, peeling, perished coating to a sound substance by hand scraping, use of mechanical grinders or if mildew or biological growth is present, it shall be removed by scrubbing with a commercial mildew wash formulated for this purpose or by any other approved method etc. all complete as per specification & directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

49.30

sqm

Page: 1471 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

5.16.17.02

Providing two coats of ASTEC#9 having elongation break 683%, tensile strength 792 psi (made in USA), white or any other color, with thickness 250-300 microns to any type of water proofing surface in/c cleaning the surface and drying at the time of coating is applied and also removing unsound existing coating or other loose particle, etc. all complete as per specification & directions of the E-I-C. One layer of liquid to be applied on the roof putting wide strip of pole force cloth on all joint and seams. Second coat to be applied after minimum 2 hours of drying of first coat. (Coverage of two coats @74-80 ft2/gallon).

sqm

5.16.17.03

Providing two coats of ASTEC#100/# 900 having elongation break 683%, tensile strength 792 psi (made in USA), white or any other color, with thickness 250-300 microns to any type of Radiation control surface in/c cleaning the surface and drying at the time of coating are applied and also removing unsound existing coating or other loose particle, washing all surfaces with mild detergent etc. all complete as per specification & directions of the E-I-C. One layer of ceramic coating ASTEC to be applied on all the surfaces on the roof putting wide strip of pole force cloth on all joints and seams. A second coat to be applied after 4 hours of minimum drying of the first coat. (Coverage of 2 coats @74-80 ft2/gallon).

sqm

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1472 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.18

Detailed Analysis Brief Description of Item 2 Cleaning, polishing & shining of brass post, plate & tub properly with cleaning agent liquid brass cleaner. After cleaning the surface to give polishing and shining using chalk powder and cut piece cloth manually without any damages etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Liquid Brass Cleaner

0.1000

each

117.00

Chalk Powder

0.0500

kg

25.00

1.25

Ordinary Labour

0.2000

day

370.00

74.00

Skilled Labour

0.1000

day

450.00

45.00 131.95

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

134.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

148.05

VAT

6% of Total

9.87

IT

4% of Total

6.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11.70

164.50

Page: 1473 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.19

Detailed Analysis Brief Description of Item 2 Cleaning & polishing of mosaic work by mosaic cutter machine with pumice stone no. 80, 120, 320, yellow & jhama stone, white jute mat, spread white cement & oxalic acid using several step as follows: 1st step- cutting the existing mosaic surface using mosaic cutter machine with pumice stone no. 80 and spread white cement slury or grouting this surface after cleaning the surface, curing at least three days. 2nd step- cutting the existing mosaic surface using mosaic cutter machine with pumice stone no. 120 and spread white cement slury or grouting this surface after cleaning the surface, curing at least three days. 3rd step- cutting the existing mosaic surface using mosaic cutter machine with pumice stone no. 320, yellow & jhama stone and spread oxalic acid this surface after cleaning the surface, Finally use Solvent Paste Wax mixed with GP thinner and polishing by white jute mat in/c. supply of materials & labour as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Pumice Stone

0.1100

each

140.00

15.40

Yellow & Jhama Stone

0.1300

each

350.00

45.50

White Cement

0.1100

kg

25.00

2.75

Oxalic Acid

0.0400

kg

250.00

10.00

Solvent Paste Wax

0.0400

pkt

272.00

10.88

G.P thinner

0.0200

litre

130.00

2.60

White Jute Mat

0.1100

m

64.80

7.13

Emery Paper

0.0800

each

21.00

1.68

Head Mason

0.0800

day

650.00

52.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of mosaic cutter machine

0.1100

day

500.00

55.00 484.94

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

494.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

544.10 Page: 1474 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

Amount 8 36.27 24.18

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

604.56

Page: 1475 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.16.20

Detailed Analysis Brief Description of Item 2 Cleaning & polishing of marble floor work by mosaic or marble cutter machine with pumice stone no. 80, 120, 320, yellow & jhama stone, white jute mat, spread white cement & oxalic acid using several step as follows: 1st step- cutting the existing marble surface using marble cutter machine with pumice stone no. 80 and spread white cement slury or grouting this surface after cleaning the surface, curing at least three days. 2nd step- cutting the existing marble surface using marble cutter machine with pumice stone no. 120 and spread white cement slury or grouting this surface after cleaning the surface, curing at least three days. 3rd step- cutting the existing marble surface using marble cutter machine with pumice stone no. 320, yellow & jhama stone and spread oxalic acid this surface after cleaning the surface, Finally use Solvent Paste Wax mixed with GP thinner and polishing by white jute mat in/c. supply of materials & labour as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Pumice Stone

0.1100

each

140.00

15.40

Yellow & Jhama Stone

0.1300

each

350.00

45.50

White Cement

0.0600

kg

25.00

1.50

Oxalic Acid

0.0400

kg

250.00

10.00

Solvent Paste Wax

0.0500

pkt

272.00

13.60

G.P thinner

0.0200

litre

130.00

2.60

White Jute Mat

0.1100

m

64.80

7.13

Emery Paper

0.0800

each

21.00

1.68

Head Mason

0.1200

day

650.00

78.00

Mason

0.1200

day

550.00

66.00

Skilled Labour

0.3000

day

450.00

135.00

Ordinary Labour

0.6000

day

370.00

222.00

H.C. of mosaic cutter machine

0.1600

day

500.00

80.00 678.41

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

691.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

761.17 Page: 1476 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

5.17.01

Supplying, fitting and fixing 12mm thick plain particle board in ceiling with best quality and well seasoned Garjan wood frame of section 75mmx38mm at 600mmx600mm in grid, suspended from ceiling/ roof or beam by 12 SWG double ply GI wire fixed to the ceiling by rowel plug, screws, hooks, nails etc. maintaining straight lines and desired finished level at bottom face with vertical strut as required in/c cutting holes in slabs or beams by electric drill machine and mending good the damages, if any, during execution of the work, installation, scaffolding, screws, nails etc. in/c, painting 2 coats over a coat of priming with synthetic enamel paint of best quality and approved colour etc, all complete as per drawing, design and direction of the E-I-C. (All sizes of wood are finished).

5.17.01.01

For Ceiling height upto 4m

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

Amount 8 50.74 33.83

Total:

845.75

sqm Sundari/ Garzen

0.0120

m3

67580.00

810.96

12mm thick Plain Particle board

1.0500

m2

350.00

367.50

Carpenter

0.5600

day

680.00

380.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5600

day

470.00

263.20 1822.46

Subtotal-A: All other remaining costs covering wire, rowel plug, nails, screws, paintings, etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

2077.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2119.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2331.07

VAT

6% of Total

IT

4% of Total

155.40 103.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

255.14

2590.08

Page: 1477 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.17.01.02

Detailed Analysis Brief Description of Item 2 For Auditorium and other type of all structures beyond 4m up to 8m.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sundari/ Garzen

0.0120

m3

67580.00

810.96

12mm thick Plain Particle board

1.0500

m2

350.00

367.50

Carpenter

0.5800

day

680.00

394.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5800

day

470.00

272.60 1845.46

Subtotal-A: All other remaining costs covering scaffolding, wire, rowel plug, nails, screws, paintings, etc.

( +23.00 % on Subtotal-A )

Subtotal-A1:

2269.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2315.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2546.85

VAT

6% of Total

IT

4% of Total

169.79 113.19 Total:

5.17.02

424.46

2829.83

Supplying, fitting and fixing 12mm thick gypsum/veneered board laminated by mechanical hot press with a milk white PVC membrane with aluminium ‘T’ bar frame in natural anodized finish at 600mmx600mm in grid, suspended from ceiling by 12 SWG double ply GI wire fixed to the ceiling by rowel plug, screws, hooks, nails etc. maintaining straight lines and desired finished level at bottom face with vertical strut as required in/c making holes in slabs, or beams by electric drill machine and mending good the damages, if any, during execution of the work in/c scaffoldings, installation, screws, nails etc. all complete as per drawing, design and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1478 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.17.02.01

2 For 12mm thick Gypsum board.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Aluminium 'T' bar frame/section

1.0000

m2

269.00

269.00

12mm thick gypsum board

1.0500

m2

215.00

225.75

Skilled Technician

0.5000

day

680.00

340.00

Semi Skilled Technician

0.5000

day

570.00

285.00

Ordinary Labour

0.5000

day

370.00

185.00 1304.75

Subtotal-A: All other remaining costs covering bolts, machine charge, scaffolding, etc.

( +17.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1526.56 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1557.09

10% Profit ( Add 10% on Subtotal-B) :

1712.80

VAT

6% of Total

IT

4% of Total

114.19 76.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

221.81

1903.11

Page: 1479 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.17.02.02

Detailed Analysis Brief Description of Item 2 For 12mm thick Veneered board

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm Aluminium 'T' bar frame/section

1.0000

m2

269.00

269.00

12mm thick Veneered board

1.0500

m2

470.75

494.29

Skilled Technician

0.5000

day

680.00

340.00

Semi Skilled Technician

0.5000

day

570.00

285.00

Ordinary Labour

0.5000

day

370.00

185.00 1573.29

Subtotal-A: All other remaining costs covering bolts, machine charges, scaffolding, etc.

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1856.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1893.61

10% Profit ( Add 10% on Subtotal-B) :

2082.97

VAT

6% of Total

IT

4% of Total

138.86 92.58 Total:

5.17.03

283.19

2314.41

Supplying, fitting and fixing 12mm thick Burma Teak Veneered/Particle board in walling with best quality, well seasoned Garjan wood frame of section 75mmx38mm at 600mmx600mm in grid, fitted and fixed to wall by plugs, nails, screws etc. in/c, treatment of inner surface with termite & damp proofing agent, maintaining leveled and finished exposed faces in/c, making holes in wall and mending good the damages, if any, during execution of the work in/c installation, scaffolding, screws, nails etc. in/c. French polishing 3 coats over a coat of priming etc. all complete as per design, approved sample and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1480 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.17.03.01

Detailed Analysis Brief Description of Item 2 For 12mm thick Burma Teak Veneered board

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sundari/ Garzen

0.0120

m3

67580.00

810.96

Burma Teak veneered

1.0500

m2

1025.00

1076.25

Carpenter

0.5600

day

680.00

380.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5600

day

470.00

263.20 2531.21

Subtotal-A: All other remaining costs covering clamps, screws, nails, French polishing, etc.

( +7.00 % on Subtotal-A )

177.18

Subtotal-A1:

2708.39

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2762.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3038.82

VAT

6% of Total

IT

4% of Total

202.59 135.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3376.47

Page: 1481 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.17.03.02

2 For 12mm thick particle board

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Sundari/ Garzen

0.0120

m3

67580.00

810.96

12mm thick Plain Particle board

1.0500

m2

350.00

367.50

Carpenter

0.5600

day

680.00

380.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5600

day

470.00

263.20 1822.46

Subtotal-A: All other remaining costs covering clamps, screws, nails, painting, etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

2077.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2119.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2331.07

VAT

6% of Total

IT

4% of Total

155.40 103.60 Total:

5.17.04

255.14

2590.08

Supplying, fitting and fixing of false ceiling (600mmx600mm or 600mmx 1200mm grid/ section devided as per perior approval with cross Tee) with 8 mm thick melamine board laminated by mechanical hot press with a milk white PVC membrane with aluminum frame suspended from ceiling, beam etc. by double ply 12 SWG GI twisted wire maintaining straight lines and desired finished level at bottom face in/c cutting holes in slabs or beams by electric drill machine and mending good the damages, if any, during execution of the work, installation, scaffolding, screws, nails etc. i/c cost of aluminum frame, royal plug, etc. all complete as per drawing, design and direction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1482 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.17.04.01

2 600mmx600mm grid/section

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

625.00

625.00

sqm Malamine board (8mm thick) (8'x4' size)

1.0000

sqm

Main tee- 25mm

1.3120

m

Cross tee- 25mm

1.3120

m

L- section- 25mm

1.3120

m

Skilled Technician

0.5000

day

680.00

340.00

Semi Skilled Technician

0.5000

day

570.00

285.00 1250.00

Subtotal-A: All other remaining costs, revit, G.I. Wire, 1.5"screw, rowel plug, wall bit, scaffolding, sundries etc.

( +15.00 % on Subtotal-A )

Subtotal-A1:

1437.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1466.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1612.88

VAT

6% of Total

IT

4% of Total

107.53 71.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

187.50

1792.08

Page: 1483 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.17.04.02

2 600mmx1200mm grid/section

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

625.00

625.00

sqm Malamine board (8mm thick) (8'x4' size)

1.0000

sqm

Main tee- 25mm

1.3120

m

Cross tee- 25mm

0.6150

m

L- section- 25mm

1.3120

m

Skilled Technician

0.4500

day

680.00

306.00

Semi Skilled Technician

0.4500

day

570.00

256.50 1187.50

Subtotal-A: All other remaining costs, revit, G.I. Wire, 1.5"screw, rowel plug, wall bit, scaffolding, sundries etc.

( +13.00 % on Subtotal-A )

Subtotal-A1:

1341.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1368.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1505.58

VAT

6% of Total

IT

4% of Total

100.37 66.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

154.38

1672.87

Page: 1484 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.17.05

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of 9 mm thick perforated gypsum board false ceiling with aluminum T bar frame in natural anodized frame at 600 mm x 600 mm grid suspended from ceiling, beam etc. by double ply 12 SWG GI twisted wire maintaining straight lines and desired finished level at bottom face in/c cutting holes in slabs or beams by electric drill machine and mending good the damages, if any, during execution of the work, installation, scaffolding, screws, nails etc. i/c cost of aluminum frame, royal plug, etc. all complete as per drawing, design and direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

205.00

205.00

sqm

Perforated gypsum board 9mm thick

1.0000

sqm

Main tee- 25mm

1.3120

m

Cross tee- 25mm

1.3120

m

L- section- 25mm

1.3120

m

Skilled Technician

0.5000

day

680.00

340.00

Semi Skilled Technician

0.5000

day

570.00

285.00 830.00

Subtotal-A: All other remaining costs, revit, G.I. Wire, 1.5"screw, rowel plug, wall bit, scaffolding, sundries etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

954.50 973.59

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1070.95

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

71.40

IT

4% of Total

47.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

124.50

1189.94

Page: 1485 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

5.17.06

Supplying, fitting, fixing false ceiling with 6 mm thick plastic wood sheet, weighing 0.358 kg/sft fitted with aluminum T bar frame in natural anodized at 600mmx600mm/600mmx1200mm grid as per perior approval suspended from ceiling, beam etc. by double ply 12 SWG GI twisted wire maintaining straight lines and desired finished level at bottom face in/c cutting holes in slabs or beams by electric drill machine and mending good the damages, if any, during execution of the work, installation, scaffolding, screws, nails etc. i/c cost of aluminum frame, royal plug, etc. all complete as per drawing, design and direction of E-IC.

5.17.06.01

600mmx600mm grid

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

325.00

325.00

sqm Plastic wood (3mm thick sheet)

1.0000

sqm

Main tee- 25mm

1.3120

m

Cross tee- 25mm

1.3120

m

L- section- 25mm

1.3120

m

Skilled Technician

0.5000

day

680.00

340.00

Semi Skilled Technician

0.5000

day

570.00

285.00 950.00

Subtotal-A: All other remaining costs, revit, G.I. Wire, 1.5"screw, rowel plug, wall bit, scaffolding, sundries etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1092.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1114.35

10% Profit ( Add 10% on Subtotal-B) :

1225.79

VAT

6% of Total

81.72

IT

4% of Total

54.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

142.50

1361.98

Page: 1486 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.17.06.02

2 600mmx1200mm grid

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

325.00

325.00

sqm Plastic wood (3mm thick sheet)

1.0000

sqm

Main tee- 25mm

1.3120

m

Cross tee- 25mm

0.6150

m

L- section- 25mm

1.3120

m

Skilled Technician

0.4500

day

680.00

306.00

Semi Skilled Technician

0.4500

day

570.00

256.50 887.50

Subtotal-A: All other remaining costs, revit, G.I. Wire, 1.5"screw, rowel plug, wall bit, scaffolding, sundries etc.

( +13.00 % on Subtotal-A )

Subtotal-A1:

1002.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1022.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1125.23

VAT

6% of Total

IT

4% of Total

75.02 50.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

115.38

1250.25

Page: 1487 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.17.07

Detailed Analysis Brief Description of Item 2 Supplying fitting and fixing of plastic wall paneling with 3 mm thick plstic wood of best quality sheet, weighing 0.188 kg/sft fitted with vertical post of partition frame and mending good the damages, carriage to the site including 5mm thick glass head, partition frame, rubber, 5 mm thick clear glass fitted and fixed with screws, steel clamp accepted and etc. all complete as per direction of the E-I-C.(excluding the cost of glass)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Plastic wood (3mm thick sheet)

1.0000

sqm

325.00

325.00

Carpenter

0.4300

day

680.00

292.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4300

day

470.00

202.10 819.50

Subtotal-A: All other remaining costs, wall bit, 2"screw,super bit, sunstar glue, cloth, terpin, super glue, sundries etc.

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

967.01 986.35

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1084.99

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

72.33 48.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

147.51

1205.54

Page: 1488 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.17.08

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing approved quality and size of approx. 190 mm x 190 mm size glass bricks of best quality fitted with white cement, filling the joints carefully in stair wall or any where directed I/c cost of scaffolding, all materials and labour etc. all complete in all respect as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Glass bricks

29.0000

each

White Cement

17.2160

kg

25.00

430.40

Head Mason

0.1000

day

650.00

65.00

Mason

0.6000

day

550.00

330.00

Skilled Labour

0.6000

day

450.00

270.00

Ordinary Labour

1.0000

day

370.00

370.00 1465.40

Subtotal-A: All other remaining costs,1/4" dia MS rod, scaffolding, sundries etc.

( +6.00 % on Subtotal-A )

87.92

Subtotal-A1:

1553.32

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1584.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1742.83

VAT

6% of Total

IT

4% of Total

116.19 77.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1936.48

Page: 1489 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Manufacturing, supplying, fitting and fixing collapsible gate made of 20mmx20mmx3mm/25mmx25mmx3mm MS angle placed @112mm c/c vertically and connecting the same with each other with 20mmx3mm/25mmx3mm MS flat bar scissors 525mm/600mm long provided in three rows in/c cutting the different MS members to required sizes, fabricating, welding, riveting with required size rivets, providing required size wheels, pulling handles on both sides, suitable looking arrangement and finally placing the same in position in between two nos. 50mmx50mmx6mm MS Tee rail made by welding two nos. 50mmx6mm MS flat bar fitted and fixed at top and bottom with R.C.C. lintel/roof slab, floors and side wall with required nos. 150mm to 225mm long 38mmx6mm MS flat bar clamps one end welded with the gate member and the other end bifurcated and embedded in Cement Concrete (1:2:4) in/c cutting holes and mending good the damages, painting two coats with approved synthetic enamel paint over a coat of anticorrosive painting etc. all complete as per drawing and design and direction of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1490 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.01.01

Detailed Analysis Brief Description of Item 2 Collapsible gate made of 20mm x 20mm x 3mm M.S. angle as vertical member and 20mm x 3mm F.I bar as scissors.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle 20mmx20mmx3mm

18.0000

kg

58.00

MS F.I bar 20mmx3mm

6.6100

kg

58.00

383.38

MS F.I bar Tee 50mmx6mm

4.9000

kg

58.00

284.20

Welder

0.6000

day

680.00

408.00

Welder Helper

0.6000

day

470.00

282.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.6000

day

370.00

222.00 2723.58

Subtotal-A: All other costs for FI bar handle, rivets and washer, 1.5'' dia MS wheel, MS clamp, locking arrangement, welding, electrodes, greesing, carrying, Making grooves, CC work, cement plaster, Synthetic enamel painting with anticorrosive painting, etc

( +16.00 % on Subtotal-A )

435.77

( +6.00 % on Subtotal-A )

163.41

Subtotal-A1:

3322.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3389.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3728.15

VAT

6% of Total

248.54

IT

4% of Total

165.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1044.00

4142.38

Page: 1491 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.01.02

Detailed Analysis Brief Description of Item 2 Collapsible gate made of 25mm x 25mm x 3mm M.S. angle as vertical member and 25mm x 3mm F.I bar as scissors.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle 25mmx25mmx3mm

24.5000

kg

58.00

MS F.I bar 25mmx3mm

8.8800

kg

58.00

515.04

MS F.I bar Tee 50mmx6mm

4.9000

kg

58.00

284.20

Welder

0.6000

day

680.00

408.00

Welder Helper

0.6000

day

470.00

282.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.6000

day

370.00

222.00 3232.24

Subtotal-A: All other costs for FI bar handle, rivets and washer, 1.5'' dia MS wheel, MS clamp, locking arrangement, welding, electrodes, greesing, carrying, Making grooves, CC work, cement plaster, Synthetic enamel painting with anticorrosive painting, etc

( +16.00 % on Subtotal-A )

517.16

( +6.00 % on Subtotal-A )

193.93

Subtotal-A1:

3943.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4022.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4424.42

VAT

6% of Total

294.96

IT

4% of Total

196.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1421.00

4916.02

Page: 1492 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.02

Detailed Analysis Brief Description of Item 2 Supplying, fitting, fixing and installation of ordinary type MS gate (double leaf) with 38mmx38mmx6mm MS angle outer frame having 16mm dia MS rod placed vertically @75mm c/c. at bottom part and top part (arrows) and also placed horizontally at bottom for interconnection of 16mm dia MS rod placed vertically as per design, the top part covered with 18 BWG MS sheet and fixed with four nos. 38mmx6mm F.I. bars placed diagonally and four nos. 38mmx6mm F.I. bars placed horizontally and vertically all passing through the centre, providing locking arrangements on 3mm thick MS plate one for main gate and one for minimum 300mmx1025mm pocket gate with 38mmx38mmx6mm MS angle and 16mm dia MS rod placed vertically @75mm c/c. providing 38mmx38mmx6mm MS angle clamps fitted and fixed with the outer frame of the main gate, the clamp being embedded in R.C.C. or masonry pillars with Cement Concrete (1:2:4) in/c. cutting holes and mending good the damages etc. in/c. riveting, welding as and where necessary, painting two coats with approved quality of synthetic enamel paint over a coat of priming of anti-corrosive paint etc. all complete as per drawing, design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

15.9400

MS Rod (Plain, 40 Grade)

kg

59.00

19.2000

kg

45.00

864.00

MS Plate (3mm)

5.3700

kg

55.00

295.35

MS Rail

2.0000

kg

55.00

110.00

Welder

0.6000

day

680.00

408.00

Welder Helper

0.6000

day

470.00

282.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.6000

day

370.00

222.00 3221.81

Subtotal-A: All other remaining costs covering fabrication, welding, lock, wheel, painting, CC (1:2:4) etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

940.46

644.36 3866.17

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3943.50 Page: 1493 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

Amount 8 4337.84

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

289.19 192.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4819.83

Page: 1494 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.03

Detailed Analysis Brief Description of Item 2 Supplying, fitting, fixing and installation of ordinary type MS gate (double leaf) with 38mmx38mmx6mm MS angle frame, top and bottom parts provided with 25mmx6mm F.I. bar placed vertically @150mm c/c and the middle part covered with 18 BWG MS sheet and fixed with four nos. 38mmx6mm F.I. bar placed diagonally and four nos. 38mmx6mm F.I. bars placed horizontally and vertically, all passing through the center as design in/c locking arrangement on 3mm thick MS plate providing 38mmx38mmx6mm MS angle clamps fitting and fixed with the outer frame of the gate, the clamp be embedded in the R.C.C. or masonry pillars with Cement Concrete (1:2:4) in/c. cutting holes and mending good the damages in/c. riveting, welding as and where necessary, painting two coats of synthetic enamel paint over a coat of anti-corrosive paint etc. all complete as per drawing, design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

13.4400

kg

59.00

792.96

MS Angle, Flat bar, Z bar

8.6000

kg

59.00

507.40

MS Plate (3mm)

6.2100

kg

55.00

341.55

MS Rail

2.0500

kg

55.00

112.75

Welder

0.6000

day

680.00

408.00

Welder Helper

0.6000

day

470.00

282.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.6000

day

370.00

222.00 2766.66

Subtotal-A: All other remaining costs covering fabrication, welding, lock, wheel, painting, CC (1:2:4) etc.

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

553.33 3319.99

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3386.39

10% Profit ( Add 10% on Subtotal-B) :

3725.03

VAT

6% of Total

IT

4% of Total

248.34 165.56 Page: 1495 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4138.92

Page: 1496 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.04

Detailed Analysis Brief Description of Item 2 Manufacturing, supplying, fitting and fixing GI pipe gate having 38mm dia of 2.9mm wall thickness GI pipe outer frame and 19~20mm dia of 2.35~2.3mm wall thickness GI pipe vertical member placed @75mm c/c by welding at top and bottom of GI pipe frame, cutting the pipes in proper shape and size in/c making semicircular band at corners of the outer frame without damaging the pipe, providing six nos. huskle dummy with R.C.C. or brick pillar with Cement Concrete (1:2:4) in/c making provision for minimum 0.61mx1.4m pocket gate having its outer frame and inner vertical members made with 19~20mm dia of 2.35~2.3mm wall thickness GI pipe in/c necessary locking arrangements, painting the gate with two coats of synthetic enamel paint over a coat of anti-corrosive priming, welding as and where necessary in/c necessary locking arrangement and providing two nos. 16mm MS socket bolts etc. all complete as per design and drawing and as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

40mm dia GI pipe of 2.9mm wall thick

3.4400

m

380.48

1308.85

18/20/22 BWG MS Sheet/plate

5.2300

kg

70.00

366.10

19mm dia GI Pipe (2mm thick)

13.8700

m

173.00

2399.51

Huskel dummy

0.8100

each

26.00

21.06

Steel hinge (125mm)

0.3300

each

180.00

59.40

16mm MS Socket

0.3300

esch

13.00

4.29

Welder

0.6000

day

680.00

408.00

Welder Helper

0.6000

day

470.00

282.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.6000

day

370.00

222.00 5171.21

Subtotal-A: All other remaining costs covering lock, welding, painting, CC (1:2:4) etc.

( +16.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

827.39 5998.60

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6118.58 Page: 1497 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

Amount 8 6730.43

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

448.70 299.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7478.26

Page: 1498 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.05

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of rolling shutter made of 24 SWG G.P. sheet unit minimum 69mm width having 10mm & 12mm dia circular folding at ends, rolled in machine, locked together properly to form rolling shutter, top of the shutter to be fitted with circular spring box made of 22 BWG sheet, containing best quality spring made in China, nutted with 38mm GI pipe at one end and the other end nutted to shutter in/c fitting the GI pipe again with 375mmx300mmx6mm punkha at ends with side guide channel (side channel consist of 50mmx100mmx6mm MS plate with 2x19mmx3mm F.I. bar, middle channel consist of 2x150mmx6mm MS plate with 2x19mmx6mm) fixed to wall or column with MS clamps (minimum 3x25mmx6mm), mending the damages, bottom end of shutter fitted to folded G.P. sheet (minimum 125mm width, two layer) which is again fitted to 25mmx25mmx3mm angle, providing handle both sides, (with F.I. bar 25mmx6mm riveted) and locking arrangement both sides, painting two coats with approved colour and brand of synthetic enamel paint over a coat of priming etc. complete in all respect as per drawing, design and as per direction of the E-I-C. (Rolling shutter must be riveted at sides with G.P. sheet and patty).

Unit

Sub-Item

3

4

5

Unit

Rate

6

7

Amount 8

sqm

24 SWG GP Sheet

16.3900

kg

80.00

1311.20

26 SWG GP Sheet

1.6600

kg

80.00

132.80

40mm dia GI pipe of 2.9mm wall thick

0.3500

m

380.48

133.17

MS Angle, Flat bar, Z bar

0.3900

kg

59.00

23.01

16.4400

kg

70.00

1150.80

3.1100

kg

59.00

183.49

MS Plate (6mm) MS Angle, Flat bar, Z bar

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity

Spring (China)

1.8000

m

62.00

111.60

Spring Box

0.5400

each

140.00

75.60

Welder

0.6000

day

680.00

408.00

Welder Helper

0.6000

day

470.00

282.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.6000

day

370.00

222.00

Page: 1499 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8 4133.67

Subtotal-A: All other remaining costs covering nuts, bolts, reverting, lubricant, painting, CC (1:2:4) etc.

( +16.00 % on Subtotal-A )

Subtotal-A1:

4795.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4890.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5380.05

VAT

6% of Total

IT

4% of Total

358.67 239.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

661.39

5977.84

Page: 1500 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.06

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing boundary wall grill or anywhere directed made of 12mmx12mm MS square bar horizontally @ 50mm c/c fixing with outer four side 25mmx25mm MS square box and inside 12mmx12mm MS square bar vertically @ 450mm c/c fixed with boundary column and RCC Lintel by 25mmx25mmx150mm MS Box clamp (minimum 7 nos) i/c cost of all materials and labour, fabricating, cutting, bending, welding, painting 2 coats of synthetic enamel paint over a coat of anticorrosive priming in/c. cutting grooves in the R.C.C. or brick work, mending good the damages with cement concrete (1:2.4) for all floors etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

5.2900

m

350.00

1851.50

17.4200

kg

52.00

905.84

0.3500

day

680.00

238.00

5

Amount 8

sqm

25mm x 25mm MS box and wall thickness 4mm MS Square bar 12 mm X 12 mm Welder Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 3389.34

Subtotal-A: All other remaining costs covering cutting, welding, painting, Cement Concrete (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

3796.06

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3871.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4259.18

VAT

6% of Total

IT

4% of Total

283.95 189.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

406.72

4732.42

Page: 1501 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.18.07

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing two part (double leaf) heavy type Main entrance gate (Swing type) in boundary wall or anywhere directed made of 12mmx12mm MS square solid bar series horizontally @ 50mm c/c (1/3rd of total height as per drawing) fixing with outer frame of 50mmx50mmx5mm MS Angle (2nos welded) box and 1no in horizontally in bottom 1/3rd height in top and 40mmx20mmx5mm MS angle box vertically fixed with outer angle box and horizontal solid bar. In-between 1/3rd total height gap of solid bar series and bottom 1/3rd covered with stainless steel sheet (minimum 1.63mm thick) horizontally in both side with 12mmx12mm MS square solid bar as per drawing i/c locking arrangement on 3mm thick MS plate providing 50mmx50mmx5mm angle clamp fitting and fixed with outer angle box frame of the gate and embedded in the RCC or masonry pillar (minimum 6 nos) i/c cost of all materials and labour, fabricating, cutting, bending, welding, painting 2 coats of synthetic enamel paint over a coat of anticorrosive priming of approved brand in/c. cutting grooves in the R.C.C. or brick work, mending good the damages with cement concrete (1:2.4) etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

25.8600

MS Square bar 12 mm X 12 mm

kg

59.00

17.0400

kg

52.00

886.08

18 SWG Steel Sheet Metal

8.6200

kg

217.00

1870.54

Welder

1.2000

day

680.00

816.00

Welder Helper

1.2000

day

470.00

564.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.6000

day

370.00

222.00 5984.36

Subtotal-A: All other remaining costs covering cutting, bending, welding, painting, roller, wheel, rail, Cement Concrete (1:2:4) etc.

( +16.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

1525.74

957.50

6941.86

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7080.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7788.76 Page: 1502 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

Amount 8 519.25 346.17

Total: 5.19.01

8654.18

Manufacturing, supplying, fitting and fixing stair railing of any standard height with square box (vertically two nos. in each tread) made by thorough welding of two nos. 19mmx19mmx3mm MS angle in/c. providing wooden hand rail of 9675 sq.mm finished section, engraving each box 150mm in the concrete by 50mmx50mmx6mm anchor plate at base welding 38mmx6mm F.I. bar in inclined plain with the top of the box to fit in the grooved wooden rail by necessary screws in/c cutting grooves in concrete, mending good the damages with Cement Concrete (1:2:4) applying 1st class polish to hand rail, two coats of synthetic enamel paint of approved quality over a prime coat etc. finished in all respect for all floors as per direction of the E-I-C. (Exposed area of railing will be considered for measurement).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1503 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.01.01

Detailed Analysis Brief Description of Item 2 With Chittagong Teak wooden hand rail

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle, Flat bar, Z bar

12.5900

kg

59.00

742.81

MS Angle, Flat bar, Z bar

0.9800

kg

59.00

57.82

MS Angle, Flat bar, Z bar

2.1200

kg

59.00

125.08

Chittagong Teak

0.0120

m3

140000.00

1680.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50

Carpenter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 3812.71

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4270.24 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4355.64

10% Profit ( Add 10% on Subtotal-B) :

4791.20

VAT

6% of Total

319.41

IT

4% of Total

212.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

457.53

5323.56

Page: 1504 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.19.01.02

2 With Silkarai wooden hand rail

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm MS Angle, Flat bar, Z bar

12.5900

kg

59.00

742.81

MS Angle, Flat bar, Z bar

0.9800

kg

59.00

57.82

MS Angle, Flat bar, Z bar

2.1200

kg

59.00

125.08

Sil Korai

0.0120

m3

88000.00

1056.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2613.71

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +16.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3031.90 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3092.54

10% Profit ( Add 10% on Subtotal-B) :

3401.80

VAT

6% of Total

IT

4% of Total

226.79 151.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

418.19

3779.77

Page: 1505 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.02

Detailed Analysis Brief Description of Item 2 Manufacturing, supplying, fitting and fixing stair railing of standard height with square box (vertically 1 no. in each tread) made by thorough welding of 2 nos. 25mmx25mmx50mm MS angle in/c. providing wooden hand rail of 9375m2 finished section, engraving each box 150mm in the concrete by 50mmx50mmx6mm anchor plate as base, welding 50mmx6mm F.I. bar in inclined plain with the top of the box fit in the grooved wooden rail and two nos. 225mmx25mm finished section of wooden (Chittagong Teak) strip fitted and fixed at mid height of railing at both side of MS angle box in inclined, plain parallel to the hand rail etc. fitted and fixed by necessary screws, nails, in/c. cutting grooves in concrete mending good the damages with Cement Concrete (1:2:4) applying best quality French polish to wooden hand rail and inclined wooden strip and painting to F.I. bar and square box with two coats of synthetic enamel paint of approved quality over a prime coat etc. complete in all respect for all floors as per direction of the E-I-C. (Exposed area of railing to be considered for measurement). With Chittagong Teak wooden hand rail

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

11.8400

kg

59.00

698.56

MS Angle, Flat bar, Z bar

0.4800

kg

59.00

28.32

MS Angle, Flat bar, Z bar

2.8200

kg

59.00

166.38

Chittagong Teak

0.0280

m3

140000.00

3920.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 5445.26

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

653.43 6098.69

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6220.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6842.73 Page: 1506 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 VAT

6% of Total

IT

4% of Total

Quantity 5

Unit

Rate

6

7

Amount 8 456.18 304.12

Total: 5.19.03

7603.04

Supplying, fitting and fixing 12~15mm dia of 2.35~2.3mm wall thickness GI pipe stair railing of any standard height with 50mmx50mmx6mm MS plate at the base of 12~15mm dia of 2.35~2.3mm wall thickness dia GI pipe and fitted and fixed by welding, placing the pipes vertically @125mm c/c (2 nos. in each steps) 150mm embedded into the R.C.C. step of stair case after cutting grooves and mending good the damages with Cement Concrete (1:2:4) and providing 38mmx6mm F.I. bar on the top of GI pipe in/c providing wooden/GI pipe hand rail of any design in/c polishing/painting etc. all complete as per direction of the E-I-C. (Exposed area of railing to be considered for measurement).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1507 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.03.01

Detailed Analysis Brief Description of Item 2 With Chittagong Teak wood handrail (150mmx62mm) finished

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 12mm dia GI Pipe (2mm thick)

8.2400

m

131.00

MS Angle, Flat bar, Z bar

0.9700

kg

59.00

57.23

MS Angle, Flat bar, Z bar

2.1200

kg

59.00

125.08

Chittagong Teak

0.0120

m3

140000.00

1680.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50

Carpenter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 3803.75

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

456.45 4260.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4345.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4779.94

VAT

6% of Total

318.66

IT

4% of Total

212.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1079.44

5311.05

Page: 1508 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.03.02

Detailed Analysis Brief Description of Item 2 With Silkarai wood handrail (150mmx62mm) finished

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 12mm dia GI Pipe (2mm thick)

8.2400

m

131.00

1079.44

MS Angle, Flat bar, Z bar

0.9700

kg

59.00

57.23

MS Angle, Flat bar, Z bar

2.1200

kg

59.00

125.08

Sil Korai

0.0120

m3

88000.00

1056.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50

Carpenter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 3179.75

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3561.32 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3632.55

10% Profit ( Add 10% on Subtotal-B) :

3995.80

VAT

6% of Total

266.39

IT

4% of Total

177.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

381.57

4439.78

Page: 1509 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.03.03

Detailed Analysis Brief Description of Item 2 With Chittagong Teak wood handrail (112mmx62mm) finished

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 12mm dia GI Pipe (2mm thick)

8.2400

m

131.00

MS Angle, Flat bar, Z bar

0.9700

kg

59.00

57.23

MS Angle, Flat bar, Z bar

2.1200

kg

59.00

125.08

Chittagong Teak

0.0090

m3

140000.00

1260.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50

Carpenter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 3383.75

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

406.05 3789.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3865.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4252.16

VAT

6% of Total

283.48

IT

4% of Total

188.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1079.44

4724.62

Page: 1510 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.03.04

Detailed Analysis Brief Description of Item 2 With Silkarai wood (112mmx62mm) finished

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 12mm dia GI Pipe (2mm thick)

8.2400

m

131.00

1079.44

MS Angle, Flat bar, Z bar

0.9700

kg

59.00

57.23

MS Angle, Flat bar, Z bar

2.1800

kg

59.00

128.62

Sil Korai

0.0090

m3

88000.00

792.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50

Carpenter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2919.29

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3269.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3335.00

10% Profit ( Add 10% on Subtotal-B) :

3668.50

VAT

6% of Total

244.57

IT

4% of Total

163.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

350.31

4076.11

Page: 1511 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.04

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing stair railing or any where directed made of 50mm dia GI pipe of minimum wall thickness 2.90mm hand rail on top and 20mm dia GI pipe series of minimum wall thickness 2.1mm-2.2mm provided 50mm c/c parallel to hand rail as per drawing (top and bottom gap 125mm) fixed with vertical 40mm dia GI pipe post minimum wall thickness 2.65mm @ 900mm c/c which fixed in 6mm thick MS plate angle cleat (top 75mmx75mm and vertical 75mmx100mm) welded to vertical post fixed to stair concrete with 12mm dia MS royal bolt (4 nos) i/c cost of fabricating, cutting, bending, welding, painting 2 coats of synthetic enamel paint over a coat of anticorrosive priming in/c. cutting grooves in the R.C.C. or brick work, mending good the damages with C.C. (1:2.4) for all floors etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

50mm dia GI pipe wall thickness 2.90mm

1.3460

m

457.42

615.69

40mm dia GI pipe wall thickness 2.65mm

1.3160

m

410.00

539.56

20mm dia GI pipe wall thickness 2.10mm

6.5600

m

174.00

1141.44

MS Plate (8mm thick)

1.1360

kg

70.00

79.52

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 3008.21

Subtotal-A: All other costs covering, rowel bolts, cutting, welding GI pipe (with electrode), fabrication, bending, painting, carrying, labour, etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

451.23

3459.44 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3528.63

10% Profit ( Add 10% on Subtotal-B) :

3881.49

VAT

6% of Total

IT

4% of Total

258.77 172.51 Page: 1512 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.19.05

Supplying, fitting and fixing stainless steel (SS) stair railing of standard height with 1mm thick 50mm diameter stainless steel (SS) pipe for handrail fitted on railing top and vertical post used both end of flight, 1mm thick 40mm diameter stainless steel (SS) pipe used 2 nos as middle post (in between 50mm diameter stainless steel vertical pipes at end) of every flight vertically fitted in floor or trade with end cap and stainless steel (SS) screw and 1mm thick 25mm diameter stainless steel (SS) pipe for 5 nos in every flight placed parallel to 1mm thick 50mm diameter stainless steel (SS) rail pipe in each flight as per drawing for all floor and etc. including cost of all materials and labour all complete as per design and direction of the E-I-C.

sqm

SS pipe 50 mm dia

1.6260

m

549.40

893.32

SS pipe 40 mm dia

0.6730

m

332.10

223.50

SS pipe 25 mm dia

5.4670

m

223.04

1219.36

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2968.19

Subtotal-A: All other costs covering bends, sockets, flat bar, rowel bolts, welding rod(electrode), fabrication, welding, carrying, polishing, labour, ect.

( +25.00 % on Subtotal-A )

Subtotal-A1:

742.05

3710.23

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3784.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4162.88

VAT

6% of Total

IT

4% of Total

277.53 185.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4312.77

4625.43

Page: 1513 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.06

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

m

131.00

1172.45

8

Providing verandah railing or any where directed with 40mm or 50mm dia 2.9mm wall thickness GI pipe hand rail welded with 12~15mm dia of 2.35~2.3mm wall thickness GI pipe post fixed vertically @125mm c/c. 75mm of the bottom of the pipes to be embedded in floor with 50mmx50mmx6mm MS base plate welded at bottom, all complete in/c making necessary grooves in floor, packing the post with cement concrete (1:2:4), mending good all damages, finishing etc. all complete as per plan and direction of E-I-C. (Exposed area of railing will considered towards measurement)

5.19.06.01

For 40mm dia of 2.9mm wall thickness GI pipe hand rail

sqm 12mm dia GI Pipe (2mm thick)

8.9500

40mm dia GI pipe of 2.9mm wall thick

1.1200

m

380.48

426.14

MS Angle, Flat bar, Z bar

1.1200

kg

59.00

66.08

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2296.67

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2572.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2623.71

10% Profit ( Add 10% on Subtotal-B) :

2886.08

VAT

6% of Total

IT

4% of Total

192.41 128.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

275.60

3206.76

Page: 1514 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.06.02

Detailed Analysis Brief Description of Item 2 For 50mm dia of 2.9mm wall thickness GI pipe hand rail

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 12mm dia GI Pipe (2mm thick)

8.9500

m

131.00

1172.45

50mm dia GI pipe of 2.9mm wall thick

1.1200

m

457.42

512.31

MS Angle, Flat bar, Z bar

1.1200

kg

59.00

66.08

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2382.84

Subtotal-A: All other remaining costs covering welding, screws, painting, CC (1:2:4) etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

2668.78

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2722.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2994.37

VAT

6% of Total

IT

4% of Total

199.62 133.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

285.94

3327.08

Page: 1515 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.07

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing verandah railing or any where directed with 2mm thick 50 mm diameter stainless steel pipe placed on top horizontally and 1mm thick 40mm diameter stainless steel pipes placed vertically @ maximum 1200mm c/c welded to top rail of that 50mm diameter SS pipe and bottom fixed in floor with end cap and SS screw and 1mm thick 20 mm diameter stainless steel pipes placed horizontally @ maximum 125mm c/c welded with verticals i/c welding, bending, finishing, polishing, with supply of all required materials etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

881.50

963.48

sqm

SS pipe 50mm dia (2mm thick)

1.0930

SS pipe 40 mm dia

1.2300

m

332.10

408.48

SS pipe 20mm dia (1mm thick)

6.5600

m

165.64

1086.60

SS Screw (40 mm long)

4.0000

each

4.50

18.00

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 3108.56

Subtotal-A: All other costs covering bends, sockets, flat bar, rowel bolts,MS pla welding rod(electrode), fabrication, welding, carrying, polishing, labour, ect.

( +15.00 % on Subtotal-A )

Subtotal-A1:

3574.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3646.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4010.98

VAT

6% of Total

IT

4% of Total

267.40 178.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

466.28

4456.64

Page: 1516 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.08

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing verandah railing or any where as directed made of 20mm dia GI pipe of minimum wall thickness 2.1mm-2.2mm @ 100mm c/c and 50mm dia GI pipe of minimum wall thickness 2.65mm top in horizontal ways (top and bottom gap 125mm) as per design and drawing fixed with vertical 800mmx100mmx6mm H type MS plate post @ 900mm c/c which fixed in middle portion 20mm dia GI pipe post in between 50mmx25mmx5mm FI bar) with provision of 20mm GI pipe of minimum wall thickness 2.1mm-2.2mm passing hole in/c making hole in MS plate and FI bars in required diameter. All post fixing in floor by 100mmx150mm x 6mm MS base plate with 12mm dia MS royal bolt i/c cost of fabricating, cutting, welding, painting 2 coats of synthetic enamel paint over a coat of anticorrosive priming in/c. cutting grooves in the R.C.C. or brick work, mending good the damages with C.C. (1:2.4) for all floors etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

50mm dia GI pipe wall thickness 2.90mm

1.0930

m

457.42

499.96

20mm dia GI pipe wall thickness 2.35mm

7.7240

m

171.00

1320.80

MS Plate (8mm thick)

6.6580

kg

70.00

466.06

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 2918.82

Subtotal-A: All other costs covering, rowel bolts, cutting, welding pipe(with electrode), fabrication, carrying, labour, etc.

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

437.82

3356.65 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3423.78

10% Profit ( Add 10% on Subtotal-B) :

3766.16

VAT

6% of Total

IT

4% of Total

251.08 167.38 Page: 1517 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4184.62

Page: 1518 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.09

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing verandah railing or anywhere as directed made of 20mm square box of minimum wall thickness 16 gauge @ 100mm c/c and 50mm square box of minimum wall thickness 3mm in bottom of horizontal ways and side of vertical way and 75mm square box of minimum wall thickness 3mm in top of horizontal way as per design and drawing fixed with vertical 20mm square box of minimum wall thickness 16 gauge post @ 700mm c/c which fixed in 20mm square box of minimum wall thickness 16 gauge i/c cost of fabricating, cutting, welding, painting 2 coats of synthetic enamel paint over a coat of anticorrosive priming in/c. cutting grooves in the R.C.C. or brick work, mending good the damages with cement concrete. (1:2.4) for all floors etc. all complete as per design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

MS Hollow box 75mmx75mm of 3mm thick

0.5800

m

275.00

159.50

MS Hollow box 50mmx50mm of 3mm thick

0.8100

m

230.00

186.30

MS Hollow box 40mmx40mm of 3mm thick

0.0900

m

140.00

12.60

MS Hollow box 20mmx20mm of thickness 16 gauge

3.5600

m

94.00

334.64

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1325.04

Subtotal-A: All other costs covering, rowel bolts, cutting, welding box(with electrode), fabrication, carrying, labour, etc.

( +25.00 % on Subtotal-A )

Subtotal-A1:

1656.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1689.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1858.37

VAT

6% of Total

IT

4% of Total

123.89 82.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

331.26

2064.85

Page: 1519 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.19.10

Providing MS or Corrugated Brass angle to the nosing of steps of stair case or any where directed in/c supplying 75mm long 12mmx3mm F.I. bar clamp with bifurcated ends @ 600mm c/c in each steps in/c fitting and fixing with angle by welding after cutting grooves in R.C.C.work without any damages, finishing and fixing the same with Cement Concrete (1:2:4) etc. all complete as per direction of the E-I-C.

5.19.10.01

For 38mmx38mmx6mm M.S. Angle

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.0004

cum

6799.07

2.72

MS Angle, Flat bar, Z bar

3.6600

kg

59.00

215.94

MS flat bar clamp(175x38x6mm)

0.0700

kg

59.00

4.13

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.2200

day

370.00

81.40 337.69

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

3.38

Subtotal-A1: Subtotal-B: Subtotal-C:

341.07 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

347.89

10% Profit ( Add 10% on Subtotal-B) :

382.68

VAT

6% of Total

25.51

IT

4% of Total

17.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

425.20

Page: 1520 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.10.02

Detailed Analysis Brief Description of Item 2 For 32mmx32mmx6mm M.S. Angle

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.0004

cum

6799.07

2.72

MS Angle, Flat bar, Z bar

2.9800

kg

59.00

175.82

MS flat bar clamp(175x38x6mm)

0.1000

kg

59.00

5.90

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.2200

day

370.00

81.40 299.34

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.99

Subtotal-A1: Subtotal-B: Subtotal-C:

302.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

308.38

10% Profit ( Add 10% on Subtotal-B) :

339.22

VAT

6% of Total

IT

4% of Total

22.61 15.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

376.91

Page: 1521 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.10.03

Detailed Analysis Brief Description of Item 2 For 25mmx25mmx6mm M.S. Angle

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.0004

cum

6799.07

2.72

MS Angle, Flat bar, Z bar

2.3300

kg

59.00

137.47

MS flat bar clamp(175x38x6mm)

0.1000

kg

59.00

5.90

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.2200

day

370.00

81.40 260.99

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.61

Subtotal-A1: Subtotal-B: Subtotal-C:

263.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

268.87

10% Profit ( Add 10% on Subtotal-B) :

295.76

VAT

6% of Total

IT

4% of Total

19.72 13.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

328.62

Page: 1522 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.19.10.04

Detailed Analysis Brief Description of Item 2 For 38mmx38mmx6mm Corrugated Brass Angle

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.0004

cum

6799.07

2.72

Corrugated brass angle

2.3300

kg

259.20

603.94

MS flat bar clamp(175x38x6mm)

0.1000

kg

59.00

5.90

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.2200

day

370.00

81.40 727.46

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

7.27

Subtotal-A1: Subtotal-B: Subtotal-C:

734.73 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

749.42

10% Profit ( Add 10% on Subtotal-B) :

824.37

VAT

6% of Total

IT

4% of Total

54.96 36.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

915.96

Page: 1523 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.01

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing steel grill fencing in boundary wall with 31mmx6mm F.I. bar @150mm c/c placed vertically after cutting as per required measurement, welding the F.I. bar with 2 Nos. horizontal 31mmx6mm F.I. bar placed one at top and another at bottom in/c. embedding the horizontal F.I. bar in position after cutting grooves in wall upto 150mm depth and mending good the damages with Cement Concrete (1:2:4), finished with two coats of painting with synthetic enamel paint over a coat of anti-corrosive paint etc. all complete as per drawing and design and as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

14.4700

kg

59.00

853.73

Welder

0.3500

day

680.00

238.00

Welder Helper

0.3500

day

470.00

164.50

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.3500

day

370.00

129.50 1485.73

Subtotal-A: All other remaining costs covering painting, CC (1:2:4) etc.

( +25.00 % on Subtotal-A )

Subtotal-A1:

1857.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1894.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2083.74

VAT

6% of Total

138.92

IT

4% of Total

92.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

371.43

2315.26

Page: 1524 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.02

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing steel grill fencing made with 20mmx20mmx3mm angle box with top MS cone (made with 2 nos. 20mmx20mmx3mm angle by welding) placed vertically @150mm c/c and welding the said vertical boxes with two nos. horizontal 25mmx25mmx5mm angle box (made with 2 nos. 25mmx25mmx5mm angle by welding), placing one at bottom and another at top and again fitted and fixed by welding the said horizontal box with vertical 38mmx38mmx6mm angle box post with top same MS box cone (made with 2 nos. 38mmx38mmx6mm angle by welding) provided 1800mm c/c in/c embedding the box post in brick/R.C.C. pillar upto 375mm depth after cutting grooves in wall/pillar in/c. mending good the damages with Cement Concrete (1:2:4) and finishing with 3 coats of anti-corrosive paint etc. all complete as per design, drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar Welder

29.9700

kg

59.00

1768.23

1.0000

day

680.00

680.00

Welder Helper

1.0000

day

470.00

470.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

1.0000

day

370.00

370.00 3388.23

Subtotal-A: All other remaining costs covering Febricating, cutting, MS cone, welding, painting, CC (1:2:4) etc.

( +30.00 % on Subtotal-A )

Subtotal-A1:

4404.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4492.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4942.07

VAT

6% of Total

329.47

IT

4% of Total

219.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1016.47

5491.19

Page: 1525 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.03

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing Boundary grill made with 25mmx25mmx4mm square box @ 150mm c/c set vertically with top MS cone welded at top the said Vertical box welded with 2 nos Horizontal MS box of 40mmx40mmx4mm embeded end up to 75mm in Brick/ RCC piller including cutting grooves in wall/ piller, mending good the damages with cement concrete (1:2:4) , finishing with 3 coats of synthetic enamel paint over a coat of anticorrosive priming coat, including febricating, cutting , welding, work shop charge, carrying etc all complete as per design, drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS square box 40mmx40mmx4mm size

28.2080

kg

84.00

MS square box 25mmx25mmx4mm size

8.1690

kg

84.00

686.20

Welder

1.0000

day

680.00

680.00

Welder Helper

1.0000

day

470.00

470.00

Mason

0.1000

day

550.00

55.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

1.0000

day

370.00

370.00 4675.67

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4769.18

10% Profit ( Add 10% on Subtotal-B) :

5246.10

VAT

6% of Total

IT

4% of Total

349.74 233.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2369.47

5829.00

Page: 1526 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.04

Detailed Analysis Brief Description of Item 2 Manufacturing, supplying, fitting and fixing MS angle box post (bottom end bifurcated) made by thorough welding of two nos. 38mmx38mmx6mm MS angle and vertically placing the post into C.C/R.C.C. foundation in/c. cutting angle to required shape and size in/c covering the top of the post with 6mm thick MS plate etc. all complete as per drawing and as per direction of the E-I-C. (Excluding the cost of C.C./R.C.C. foundation).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

MS Angle, Flat bar, Z bar

7.3300

kg

59.00

432.47

MS Angle, Flat bar, Z bar

0.0800

kg

59.00

4.72

Welder

0.3000

day

680.00

204.00

Welder Helper

0.3000

day

470.00

141.00

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.3000

day

370.00

111.00 973.19

Subtotal-A: All other remaining costs

( +.80 % on Subtotal-A )

7.79

Subtotal-A1: Subtotal-B: Subtotal-C:

980.98 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1000.60

10% Profit ( Add 10% on Subtotal-B) :

1100.65

VAT

6% of Total

73.38

IT

4% of Total

48.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1222.95

Page: 1527 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.05

Detailed Analysis Brief Description of Item 2 Providing barbed wire fencing with R.C.C (1:2:4) posts @2.43m c/c and of section 100mmx100mm at top and 150mmx150mm at bottom of 2.13m total height (1.37m above G.L. and 0.76m below G.I) in/c 150mm thick, 450mm square spread footings (posts reinforced with 4 nos. 10mm dia main rod and 6mm dia stirrups @150mm c/c. footing reinforced with 5 nos. 10mm dia rod both ways) supplying, fitting and fixing 8 lines of barbed wire horizontally (fixed with the post through 6mm dia. rods embedded into the post) and 2 lines diagonally from post to post with 12 BWG 2 ply barbed wire with 4 points barbs @minimum 112mm c/c in/c 6mm thick cement plaster (1:4) up to 1500mm length of the posts etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0700

cum

75.80

5.31

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.0300

cum

6799.07

203.97

12mm thick cement plaster (1:6) to wall for ground floor…..(5.12.02.01)

0.3400

sqm

184.48

62.72

M.S. Ribbed/ Deformed Bar (Grade 300)

4.3200

kg

54.00

233.28

12 BWG 2Ply 4 point barbed wire

1.7500

kg

50.00

87.50

Skilled Labour

0.1000

day

450.00

45.00 637.78

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

650.54

10% Profit ( Add 10% on Subtotal-B) :

715.59

VAT

6% of Total

IT

4% of Total

47.71 31.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

795.10

Page: 1528 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.06

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 12 BWG barbed wire (2 ply, 4 points) in fencing work @150mm c/c in both horizontally and vertically supported by 38mmx38mmx6mm MS angle post (300mm embedded in R.C.C. or in brick work. 600mm vertical and 450mm inclined or as per requirement) @2.4m c/c in/c straightening, tightening, bidding the joints with 18 BWG wire making holes in the angle etc. all complete in all respect as per direction of the E-I-C. (Excluding the post of R.C.C/Brick work).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

12 BWG 2Ply 4 point barbed wire

2.3400

kg

50.00

117.00

GI Wire (22 BWG)

0.0900

kg

90.00

8.10

MS Angle, Flat bar, Z bar

1.9300

kg

59.00

113.87

Skilled Labour

0.5100

day

450.00

229.50 468.47

Subtotal-A: All other remaining costs

( +4.00 % on Subtotal-A )

18.74

Subtotal-A1: Subtotal-B: Subtotal-C:

487.21 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

496.95

10% Profit ( Add 10% on Subtotal-B) :

546.65

VAT

6% of Total

IT

4% of Total

36.44 24.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

607.39

Page: 1529 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.07

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 12mmx12mm (base x height) triangular wooden bit instead of putty for fixing glass panes with wooden frame by nails or by any other approved method in/c the cost of necessary wood, painting/polishing, nails etc. all complete as per direction of the E-I-C. (Excluding the cost of wooden frame and glass panes)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Sundari/ Garzen

0.0002

m3

67580.00

13.52

Carpenter

0.0700

day

680.00

47.60 61.12

Subtotal-A: All other remaining costs

( +6.00 % on Subtotal-A )

3.67

Subtotal-A1:

64.78

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

72.69

VAT

6% of Total

4.85

IT

4% of Total

3.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

80.76

Page: 1530 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.08

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing foreign made aluminium curtain rail for door and window in/c cutting, fitting and fixing as per required measurement and supplying necessary screws by electric drill and rowel plug etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Aluminium Curtain rail

1.1000

m

20.00

Carpenter

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90 88.90

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.89

Subtotal-A1: Subtotal-B: Subtotal-C:

89.79 91.58

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100.74

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6.72 4.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

22.00

111.94

Page: 1531 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.09

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of Chittagong Teak wood strip (62mmx25mmx 20mm) for fixing of aluminium curtain rails as per design and drawing, fitted and fixed in position in/c. supply of screws, nails and two coats of French polishing over a coat of priming etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Chittagong Teak

0.0017

m3

140000.00

238.00

Carpenter

0.1100

day

680.00

74.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4100

day

470.00

192.70 505.50

Subtotal-A: All other remaining costs covering screws, polishing, etc.

( +22.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

616.71 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

629.04

10% Profit ( Add 10% on Subtotal-B) :

691.95

VAT

6% of Total

IT

4% of Total

46.13 30.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

111.21

768.83

Page: 1532 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.10

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing vertical Venetian Blinds made with glass fibre fabrics (foreign made) with supply of all materials (foreign made) such as head rail (Aluminium) end capset, Rod till, sigger (stopper), runner, spacer (link), handling cord, ball chain, link chain, cord weight, weight plate, plastic washer, glass fibre fabrics and head capset etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Aluminium head rail

0.5500

m

23.76

13.07

End cap set

0.2300

each

31.32

7.20

Rod till

0.5500

m

9.40

5.17

Sigger (Stopper)

0.2300

each

7.67

1.76

Runner

5.3800

each

6.37

34.27

Spacer (Link)

5.3800

each

2.38

12.80

Handling cord

0.8200

m

5.83

4.78

Ball chain

1.0900

m

11.88

12.95

Link Chain

0.5500

m

18.36

10.10

Cord weight

0.2300

each

23.22

5.34

Weight plate

0.6900

each

11.34

7.82

Plastic washer

1.7900

each

1.13

2.02

Head cap set

0.2300

each

35.64

8.20

Brackets

0.4600

each

5.83

2.68

Glass fiber fabric

9.0000

m

167.00

1503.00 1631.18

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

Subtotal-A1:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

16.31 1647.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1680.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1848.48

VAT

6% of Total

IT

4% of Total

123.23 82.15 Page: 1533 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2053.87

Page: 1534 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.20.11

Detailed Analysis Brief Description of Item 2 Supplying, fitting & fixing horizontal Venetian Blinds 25mm width made with aluminium foils/strips (foreign made) with supply of all materials (foreign made) such as head rail, bottom rail, rod till, head cap, bottom cap, gear box, stick, support end cap cord drum & support, bracket, cord lock, cord equalizer, top holder, ladder cord, handling cord and aluminium foils etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

Aluminium head rail

0.4700

m

23.76

11.17

Aluminium bottom rail

0.4700

m

24.84

11.67

Rod till

0.4700

m

9.40

4.42

Head cap set

0.7700

each

35.64

27.44

Bottom cap

0.7700

each

41.04

31.60

Gear box

0.7700

each

37.26

28.69

Stick

0.7700

each

59.40

45.74

Support end cap

0.7700

each

48.60

37.42

Support and cord cap

0.7700

each

35.64

27.44

Brackets

1.5400

each

5.83

8.98

Cord lock

0.7700

each

22.68

17.46

Cord equalizer

0.7700

each

18.36

14.14

Top holder

0.7700

each

23.22

17.88

Ladder cord

3.2800

m

11.34

37.20

Handling cord

3.6600

m

5.83

21.34

Aluminium foil

22.5100

m

58.32

1312.78 1655.37

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

Subtotal-A1:

16.55 1671.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1705.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1875.90

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

125.06 Page: 1535 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

83.37 Total:

5.21.01

80mm thick Concrete Hollow Block work with Concrete Hollow Block (Size:400mmx200mmx80mm or any other equivalent size or quality) in cement mortar (1:4) with Portland Composite cement CEM II/AM, 42.5N), best quality sand (minimum FM1.2), making bond with connecting walls in/c necessary scaffolding and curing for requisite period etc. all complete as per direction of the E-I-C. Thickness of individual hollow block wall should not be less than 16mm and void volume should not exceed 33% of the block gross volume. Minimum compressive strength of block should be 8.5 Mpa

sqm

80mm thick concrete hollow block of minimum compressive strength is 8.5 Mpa (400mmx200mmx80mm)

12.1500

each

32.00

388.80

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0910

bag

430.00

39.13

Sand (FM - 1.2)

0.0140

m3

584.00

8.18 436.11

Subtotal-A: Labour & other remaining costs

( +17.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

74.14 510.24

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

520.45

10% Profit ( Add 10% on Subtotal-B) :

572.49

VAT

6% of Total

IT

4% of Total

38.17 25.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2084.33

636.10

Page: 1536 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.02

Detailed Analysis Brief Description of Item 2 100mm thick Concrete Hollow Block work with Concrete Hollow Block (Size:400mmx200mmx100mm or any other equivalent size or quality) in cement mortar (1:4) with Portland Composite cement CEM II/AM, 42.5N), best quality sand (minimum FM1.2), making bond with connecting walls in/c necessary scaffolding and curing for requisite period etc. all complete as per direction of the E-I-C. Thickness of individual hollow block wall should not be less than 20mm and void volume should not exceed 33% of the block gross volume. Minimum compressive strength of block should be 8.5 Mpa

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

100mm thick concrete hollow block of minimum compressive strength is 8.5 MPa (400mmx200mmx100mm)

12.1500

each

36.00

437.40

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1240

bag

430.00

53.32

Sand (FM - 1.2)

0.0170

m3

584.00

9.93 500.65

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

575.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

587.26

10% Profit ( Add 10% on Subtotal-B) :

645.99

VAT

6% of Total

IT

4% of Total

43.07 28.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

75.10

717.76

Page: 1537 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.03

Detailed Analysis Brief Description of Item 2 150mm thick Concrete Hollow Block work with Concrete Hollow Block (Size:400mmx200mmx150mm or any other equivalent size or quality) in cement mortar (1:4) with Portland Composite cement CEM II/AM, 42.5N), best quality sand (minimum FM1.2), making bond with connecting walls in/c necessary scaffolding and curing for requisite period etc. all complete as per direction of the E-I-C. Thickness of individual hollow block wall should not be less than 30mm and void volume should not exceed 33% of the block gross volume. Minimum compressive strength of block should be 10MPa

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

150mm thick concrete hollow block of minimum compressive strength is 10 MPa (400mmx200mmx150mm)

12.1500

each

48.00

583.20

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1880

bag

430.00

80.84

Sand (FM - 1.2)

0.0260

m3

584.00

15.18 679.22

Subtotal-A: Labour & other remaining costs

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

774.32 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

789.80

10% Profit ( Add 10% on Subtotal-B) :

868.78

VAT

6% of Total

IT

4% of Total

57.92 38.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

95.09

965.31

Page: 1538 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.04

Detailed Analysis Brief Description of Item 2 190mm thick Concrete Split Block work with Split Hollow Block (Size:400mmx200mmx80mm or any other equivalent size or quality) as per approved texture and colour in cement mortar (1:4) with Portland Composite cement CEM II/AM, 42.5N), best quality sand (minimum FM1.2), making bond with connecting walls in/c necessary scaffolding and curing for requisite period etc. all complete as per direction of the EI-C. Thickness of individual block wall should not be less than 30mm and void volume should not exceed 33% of the block gross volume. Minimum compressive strength of block should be 12MPa.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

190mm thick concrete hollow block of minimum compressive strength is 12 Mpa (400mmx200mmx190mm)

12.1500

each

59.00

716.85

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1880

bag

430.00

80.84

Sand (FM - 1.2)

0.0260

m3

584.00

15.18 812.87

Subtotal-A: Labour & other remaining costs

( +9.00 % on Subtotal-A )

73.16

Subtotal-A1: Subtotal-B: Subtotal-C:

886.03 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

903.75

10% Profit ( Add 10% on Subtotal-B) :

994.13

VAT

6% of Total

IT

4% of Total

66.28 44.18 Total:

5.21.05

1104.59

Supplying and laying of Concrete paving stone high load bearing pavers of approved size, shape and colour for Car Park over on 20mm thick Portland Composite Cement (CEM II/AM, 42.5N) mortar (1:2) base, raking out the joints and filling with same mortar in/c cleaning the existing surface, cutting, shaping and laying the paving stone in proper way, level and finishing with care, etc. all complete as per direction of the E-I-C. (Sand of minimum FM 1.2 to be used).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1539 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.05.01

Detailed Analysis Brief Description of Item 2 150mmx150mmx20mm high load bearing pavers in red colour (MCW Design No CT-3, or equivalent best quality)sqm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 150mmx150mmx20mm high load bearing pavers

43.0000

each

23.00

989.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1651.38

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1684.41

10% Profit ( Add 10% on Subtotal-B) :

1852.85

VAT

6% of Total

123.52

IT

4% of Total

82.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2058.72

Page: 1540 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.05.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

230mmx80mmx20mm high load bearing pavers in red colour(MCW Design No CT-10, or equivalent best quality)

sqm 230mmx80mmx20mm high load bearing pavers

Quantity 5

Unit

Rate

6

7

Amount 8

53.0000

each

19.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.2000

m3

584.00

116.80

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1774.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1809.99

10% Profit ( Add 10% on Subtotal-B) :

1990.99

VAT

6% of Total

132.73

IT

4% of Total

88.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1007.00

2212.21

Page: 1541 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.05.03

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

150mmx80mmx20mm high load bearing pavers in red colour(MCW Design No CT-10, or equivalent best quality)

sqm 150mmx80mmx20mm high load bearing pavers

Quantity 5

Unit

Rate

6

7

Amount 8

80.0000

each

19.00

1520.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 2182.38

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2226.03

10% Profit ( Add 10% on Subtotal-B) :

2448.63

VAT

6% of Total

163.24

IT

4% of Total

108.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2720.70

Page: 1542 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.05.04

Detailed Analysis Brief Description of Item 2 300mmx210mmx25mm high load bearing pavers in red colour(MCW Design No CT-12, or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 300mmx210mmx25mm high load bearing pavers

16.0000

each

40.00

640.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1302.38

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1328.43

10% Profit ( Add 10% on Subtotal-B) :

1461.27

VAT

6% of Total

97.42

IT

4% of Total

64.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1623.63

Page: 1543 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.05.05

Detailed Analysis Brief Description of Item 2 300mmx300mmx25mm high load bearing parking Tiles best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm 300mmx300mmx25mm high load bearing parking Tiles

1.0000

sqm

452.00

452.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1114.38

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1136.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1250.33

VAT

6% of Total

IT

4% of Total

83.36 55.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1389.26

Page: 1544 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.07

Detailed Analysis Brief Description of Item 2 Supplying and Laying of Concrete paving stone 100mm thick uniblock of approved size, shape and colour having minimum compressive strength of 35 Mpa over 40mm thick sand (FM 0.80) cushioning etc. all complete as per direction of E-I-C. Gray Colour of Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

100mm thick uni block of approve size (minimum compressive strength 35 MPa) Gray Colour.

1.0000

sqm

1310.40

1310.40

Sand (FM - 0.8)

0.0600

m3

480.00

28.80 1339.20

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1:

1540.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1570.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1727.97

VAT

6% of Total

IT

4% of Total

115.20 76.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

200.88

1919.97

Page: 1545 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.08

Detailed Analysis Brief Description of Item 2 "Supplying and Laying of Concrete paving stone 100mm thick uniblock of approved size, shape and colour having minimum compressive strength of 35 Mpa over 40mm thick sand (FM 0.80) cushioning etc. all complete as per direction of E-I-C. B) Red/ Black/ or any other approved lour of Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

100mm thick uni block of approve size (minimum compressive strength 35 MPa) Red/ Black/ or any other approved colour.

1.0000

sqm

1597.00

1597.00

Sand (FM - 0.8)

0.0600

m3

480.00

28.80 1625.80

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1869.67 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1907.06

10% Profit ( Add 10% on Subtotal-B) :

2097.77

VAT

6% of Total

IT

4% of Total

139.85 93.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

243.87

2330.86

Page: 1546 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.09

Detailed Analysis Brief Description of Item 2 Supplying and Laying of Concrete paving stone 80mm thick uniblock of approved size, shape and colour having minimum compressive strength of 30 Mpa over 40mm thick sand (FM 0.80) cushioning etc. all complete as per direction of E-I-C. Gray Colourof Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

80mm thick uni block of approve size (minimum compressive strength 30 MPa) Gray Colour.

1.0000

sqm

901.00

901.00

Sand (FM - 1.2)

0.0600

m3

584.00

35.04 936.04

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1:

1076.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1097.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1207.77

VAT

6% of Total

IT

4% of Total

80.52 53.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

140.41

1341.97

Page: 1547 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.10

Detailed Analysis Brief Description of Item 2 "Supplying and Laying of Concrete paving stone 80mm thick uniblock of approved size, shape and colour having minimum compressive strength of 30 Mpa over 40mm thick sand (FM 0.80) cushioning etc. all complete as per direction of E-I-C. Red/ Black/ or any other approved colour of Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

80mm thick uni block of approve size (minimum compressive strength 30 MPa) Red/ Black/ or any other approved colour.

1.0000

sqm

1105.65

1105.65

Sand (FM - 0.8)

0.0600

m3

480.00

28.80 1134.45

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1304.62 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1330.71

10% Profit ( Add 10% on Subtotal-B) :

1463.78

VAT

6% of Total

IT

4% of Total

97.59 65.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

170.17

1626.42

Page: 1548 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.11

Detailed Analysis Brief Description of Item 2 Supplying and Laying of Concrete paving stone 80mm thick uniblock of approved size, shape and colour having minimum compressive strength of 35 MPa over 40mm thick sand (FM 0.80) cushioning etc. all complete as per direction of E-I-C. Gray Colourof Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

80mm thick uni block of approve size (minimum compressive strength 35 MPa) Gray Colour.

1.0000

sqm

941.65

941.65

Sand (FM - 0.8)

0.0600

m3

480.00

28.80 970.45

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1:

1116.02

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1138.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1252.17

VAT

6% of Total

IT

4% of Total

83.48 55.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

145.57

1391.30

Page: 1549 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.12

Detailed Analysis Brief Description of Item 2 Supplying and Laying of Concrete paving stone 80mm thick uniblock of approved size, shape and colour having minimum compressive strength of 35 MPa over 40mm thick sand (FM 0.80) cushioning etc. all complete as per direction of E-I-C. Red/ Black/ or any other approved colourof Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

80mm thick uni block of approve size (minimum compressive strength 35 MPa) Red/ Black/ or any other approved colour.

1.0000

sqm

1146.60

1146.60

Sand (FM - 0.8)

0.0600

m3

480.00

28.80 1175.40

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1351.71 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1378.74

10% Profit ( Add 10% on Subtotal-B) :

1516.62

VAT

6% of Total

IT

4% of Total

101.11 67.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

176.31

1685.13

Page: 1550 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.13

Detailed Analysis Brief Description of Item 2 Supplying and Laying of Concrete paving stone 60mm thick uniblock of approved size, shape and colour having minimum compressive strength of 15 Mpa over 40mm thick sand (FM 0.80) cushioning etc. all complete as per direction of E-I-C. Gray Colour of Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

60mm thick uni block of approve size (minimum compressive strength 15 MPa) Gray Colour.

1.0000

sqm

614.25

614.25

Sand (FM - 1.2)

0.0600

m3

584.00

35.04 649.29

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1:

746.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

761.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

837.78

VAT

6% of Total

IT

4% of Total

55.85 37.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

97.39

930.87

Page: 1551 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.14

Detailed Analysis Brief Description of Item 2 "Supplying and Laying of Concrete paving stone 60mm thick uniblock of approved size, shape and colour for Road Pavement having minimum compressive strength of 15 Mpa over 40mm thick sand (FM 0.80) cushioning etc. all complete as per direction of E-I-C. Red/ Black/ or any other approved colour of Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

60mm thick uni block of approve size (minimum compressive strength 15 MPa) Red/ Black/ or any other approved colour.

1.0000

sqm

819.00

819.00

Sand (FM - 0.8)

0.0600

m3

480.00

28.80 847.80

Subtotal-A: Labour & other remaining costs

( +15.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

974.97 994.47

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1093.92

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

72.93 48.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

127.17

1215.46

Page: 1552 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.15

Detailed Analysis Brief Description of Item 2 KS(RW): Manufacturing, Supplying and Fixing of cement concrete Pre Cast kerb stone of any size as per approved drawing for side of footpath/median/road island etc. using steel shutter, with 20mm downgraded Stone Chips of LAA value ≤30%, sand (FM>=2.5) and minimum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N) content relates to mix ratio 1:1.5:3 satisfying specified minimum required average strength, f'cr = 28.5 MPa and satisfying a compressive strength f'c = 20 MPa at 28 days on standard cylinders, including grading, washings stone chips, mixing in standard mixture machine, casting in forms, making shutter water-tight properly, compacting by vibrator machine and curing for at least 28 days, including preparation kerb foundation, true to level, maintaining alignment and height, including carrying and placing kerb stone, filling interstices of kerb stone tightly with cement mortar (1:4), raking out joints, cleaning and soaking kerb stone at least for 24 hours before use, curing for requisite period, etc. all complete as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

cum

Stone Chips (20mm down graded) [LAA≤30]

0.8180

m3

5320.00

4351.76

Sand (FM - 2.5)

0.4090

m3

1500.00

613.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.6970

bag

430.00

3309.71

Head Mason

0.1200

day

650.00

78.00

Mason

0.3800

day

550.00

209.00

Skilled Labour

0.4500

day

450.00

202.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9526.47

Subtotal-A: Steel form work & all other remaining costs

( +8.00 % on Subtotal-A )

Subtotal-A1:

762.12 10288.59

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10494.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11543.80

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

769.59 Page: 1553 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

513.06 Total:

5.21.16

Supplying and placing of Engraved cement concrete tiles (250mm x 250mm) in size having minimum thickness 24 mm over 12 mm sand cement mortar (4:1) each at a distance of 6 mm apart and filling the joints with cement sand mortar (1:4) including raking out joints and cutting the tiles to required sizes wherever necessary with high class recessed pointing, cleaning and washing of sand, curing for min 3 (three) days on mortar joints by jute /brush in wet, followed by impervious /wet covering for another 4 (four) days etc. all complete and accepted by the Engineer. Gray coloured of Concord/Mir or equivalent Prior approved best quality.

sqm

Engraved cement concrete tiles (250 x 250 x 24mm) Gray coloured

1.0000

sqm

480.00

480.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1142.38

Subtotal-A: Labour & other remaining costs

( +5.00 % on Subtotal-A )

57.12

Subtotal-A1:

1199.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1223.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1345.84

VAT

6% of Total

89.72

IT

4% of Total

59.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12826.44

1495.38

Page: 1554 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.17

Detailed Analysis Brief Description of Item 2 Supplying and placing of Engraved cement concrete tiles (250mm x 250mm) in size having minimum thickness 24 mm over 12 mm sand cement mortar (4:1) each at a distance of 6 mm apart and filling the joints with cement sand mortar (1:4) including raking out joints and cutting the tiles to required sizes wherever necessary with high class recessed pointing, cleaning and washing of sand, curing for min 3 (three) days on mortar joints by jute /brush in wet, followed by impervious /wet covering for another 4 (four) days etc. all complete and accepted by the Engineer. Red/Black/or any other approaved coloured of Concord/Mir or equivalent Prior approved best quality.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Engraved cement concrete tiles (250 x 250 x 24mm) Coloured

1.0000

sqm

560.00

560.00

Sand (FM - 1.2)

0.0200

m3

584.00

11.68

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2700

bag

430.00

116.10

Head Mason

0.2200

day

650.00

143.00

Mason

0.2200

day

550.00

121.00

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.3300

day

370.00

122.10 1222.38

Subtotal-A: Labour & other remaining costs

( +5.00 % on Subtotal-A )

61.12

Subtotal-A1: Subtotal-B: Subtotal-C:

1283.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1309.17

10% Profit ( Add 10% on Subtotal-B) :

1440.09

VAT

6% of Total

IT

4% of Total

96.01 64.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1600.10

Page: 1555 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.21.18

Manufacturing and supplying Plain Cement Concrete (PCC) Blocks with cement conforming to BDS EN 197-1 : 2003 CEM-II/A-M 42.5N, using steel shutter, with 40mm down graded Stone Shingles, sand (FM>=1.5) and minimum cement content relates to mix ratio 1:3.6 satisfying specified minimum compressive strength 10.0Mpa at 28 days, including grading, washings shingles, mixing in standard mixture machine, casting in forms, making shutter water-tight properly, compacting by vibrator machine and curing for at least 28 days, including preparation of platform, shuttering and stacking in measurable stacks etc. all complete in all respect as per approved drawing, specification and direction of the Engineer-in-charge.

5.21.18.01

PCC Block Size : 500mmx500mmx300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0675

m3

3500.00

236.25

Sand (FM - 1.5)

0.0338

m3

795.00

26.83

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3175

bag

430.00

136.53

Mason

0.0063

day

550.00

3.44

Skilled Labour

0.0363

day

450.00

16.31

Ordinary Labour

0.1350

day

370.00

49.95

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0056

day

1200.00

6.72

Hire and running charges of Concrete Vibrator

0.0056

day

400.00

2.24 478.27

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

4.78

Subtotal-A1: Subtotal-B: Subtotal-C:

483.05 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

492.71

10% Profit ( Add 10% on Subtotal-B) :

541.98

VAT

6% of Total

IT

4% of Total

36.13 24.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

602.20

Page: 1556 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.02

Detailed Analysis Brief Description of Item 2 PCC Block Size : 500mmx500mmx200mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0450

m3

3500.00

157.50

Sand (FM - 1.5)

0.0225

m3

795.00

17.89

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2117

bag

430.00

91.03

Mason

0.0042

day

550.00

2.29

Skilled Labour

0.0242

day

450.00

10.88

Ordinary Labour

0.0900

day

370.00

33.30

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0038

day

1200.00

4.50

Hire and running charges of Concrete Vibrator

0.0038

day

400.00

1.50 318.89

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

3.19

Subtotal-A1: Subtotal-B: Subtotal-C:

322.08 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

328.52

10% Profit ( Add 10% on Subtotal-B) :

361.37

VAT

6% of Total

IT

4% of Total

24.09 16.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

401.52

Page: 1557 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.03

Detailed Analysis Brief Description of Item 2 PCC Block Size : 500mmx500mmx150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Sand (FM - 1.5)

0.0169

m3

795.00

13.41

Stone Shingles (20mm down graded)

0.0375

m3

3500.00

131.25

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1587

bag

430.00

68.24

Mason

0.0031

day

550.00

1.72

Skilled Labour

0.0181

day

450.00

8.15

Ordinary Labour

0.0675

day

370.00

24.98

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0028

day

1200.00

3.36

Hire and running charges of Concrete Vibrator

0.0028

day

400.00

1.12 252.22

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

2.52

Subtotal-A1: Subtotal-B: Subtotal-C:

254.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

259.84

10% Profit ( Add 10% on Subtotal-B) :

285.83

VAT

6% of Total

IT

4% of Total

19.06 12.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

317.58

Page: 1558 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.04

Detailed Analysis Brief Description of Item 2 PCC Block Size : 400mmx400mmx300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0432

m3

3500.00

151.20

Sand (FM - 1.5)

0.0216

m3

795.00

17.17

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2032

bag

430.00

87.38

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0232

day

450.00

10.44

Ordinary Labour

0.0864

day

370.00

31.97

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0036

day

1200.00

4.32

Hire and running charges of Concrete Vibrator

0.0036

day

400.00

1.44 306.12

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

3.06

Subtotal-A1: Subtotal-B: Subtotal-C:

309.18 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

315.36

10% Profit ( Add 10% on Subtotal-B) :

346.90

VAT

6% of Total

IT

4% of Total

23.13 15.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

385.44

Page: 1559 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.05

Detailed Analysis Brief Description of Item 2 PCC Block Size : 400mmx400mmx200mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0288

m3

3500.00

100.80

Sand (FM - 1.5)

0.0144

m3

795.00

11.45

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1355

bag

430.00

58.25

Mason

0.0027

day

550.00

1.47

Skilled Labour

0.0155

day

450.00

6.96

Ordinary Labour

0.0576

day

370.00

21.31

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0024

day

1200.00

2.88

Hire and running charges of Concrete Vibrator

0.0024

day

400.00

0.96 204.08

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

2.04

Subtotal-A1: Subtotal-B: Subtotal-C:

206.12 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

210.24

10% Profit ( Add 10% on Subtotal-B) :

231.27

VAT

6% of Total

IT

4% of Total

15.42 10.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

256.96

Page: 1560 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.06

Detailed Analysis Brief Description of Item 2 PCC Block Size : 400mmx400mmx150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0216

m3

3500.00

75.60

Sand (FM - 1.5)

0.0108

m3

795.00

8.59

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1016

bag

430.00

43.69

Mason

0.0020

day

550.00

1.10

Skilled Labour

0.0116

day

450.00

5.22

Ordinary Labour

0.0432

day

370.00

15.98

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0018

day

1200.00

2.16

Hire and running charges of Concrete Vibrator

0.0018

day

400.00

0.72 153.06

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

1.53

Subtotal-A1: Subtotal-B: Subtotal-C:

154.59 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

157.68

10% Profit ( Add 10% on Subtotal-B) :

173.45

VAT

6% of Total

IT

4% of Total

11.56 7.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

192.72

Page: 1561 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.07

Detailed Analysis Brief Description of Item 2 PCC Block Size : 400mmx400mmx100mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0144

m3

3500.00

50.40

Sand (FM - 1.5)

0.0072

m3

795.00

5.72

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0677

bag

430.00

29.11

Mason

0.0013

day

550.00

0.72

Skilled Labour

0.0077

day

450.00

3.47

Ordinary Labour

0.0288

day

370.00

10.66

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0012

day

1200.00

1.44

Hire and running charges of Concrete Vibrator

0.0012

day

400.00

0.48 101.99

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

1.02

Subtotal-A1: Subtotal-B: Subtotal-C:

103.01 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

105.07

10% Profit ( Add 10% on Subtotal-B) :

115.58

VAT

6% of Total

IT

4% of Total

7.71 5.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

128.42

Page: 1562 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.08

Detailed Analysis Brief Description of Item 2 PCC Block Size : 300mmx300mmx300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0243

m3

3500.00

85.05

Sand (FM - 1.5)

0.0122

m3

795.00

9.66

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1143

bag

430.00

49.15

Mason

0.0023

day

550.00

1.24

Skilled Labour

0.0131

day

450.00

5.87

Ordinary Labour

0.0486

day

370.00

17.98

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0020

day

1200.00

2.44

Hire and running charges of Concrete Vibrator

0.0020

day

400.00

0.81 172.20

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

1.72

Subtotal-A1: Subtotal-B: Subtotal-C:

173.92 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

177.40

10% Profit ( Add 10% on Subtotal-B) :

195.14

VAT

6% of Total

IT

4% of Total

13.01 8.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

216.82

Page: 1563 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.09

Detailed Analysis Brief Description of Item 2 PCC Block Size : 300mmx300mmx200mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0162

m3

3500.00

56.70

Sand (FM - 1.5)

0.0081

m3

795.00

6.44

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0762

bag

430.00

32.77

Mason

0.0015

day

550.00

0.83

Skilled Labour

0.0087

day

450.00

3.92

Ordinary Labour

0.0324

day

370.00

11.99

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.62

Hire and running charges of Concrete Vibrator

0.0014

day

400.00

0.54 114.79

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

1.15

Subtotal-A1: Subtotal-B: Subtotal-C:

115.94 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

118.26

10% Profit ( Add 10% on Subtotal-B) :

130.09

VAT

6% of Total

IT

4% of Total

8.67 5.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

144.54

Page: 1564 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.10

Detailed Analysis Brief Description of Item 2 PCC Block Size : 300mmx300mmx150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0122

m3

3500.00

42.53

Sand (FM - 1.5)

0.0061

m3

795.00

4.83

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0572

bag

430.00

24.57

Mason

0.0011

day

550.00

0.62

Skilled Labour

0.0065

day

450.00

2.94

Ordinary Labour

0.0243

day

370.00

8.99

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0010

day

1200.00

1.21

Hire and running charges of Concrete Vibrator

0.0010

day

400.00

0.40 86.10

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

0.86

Subtotal-A1: Subtotal-B: Subtotal-C:

86.96 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

88.70

10% Profit ( Add 10% on Subtotal-B) :

97.57

VAT

6% of Total

IT

4% of Total

6.50 4.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

108.41

Page: 1565 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.11

Detailed Analysis Brief Description of Item 2 PCC Block Size : 300mmx300mmx100mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0081

m3

3500.00

28.35

Sand (FM - 1.5)

0.0041

m3

795.00

3.22

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0381

bag

430.00

16.38

Mason

0.0008

day

550.00

0.41

Skilled Labour

0.0044

day

450.00

1.96

Ordinary Labour

0.0162

day

370.00

5.99

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0007

day

1200.00

0.82

Hire and running charges of Concrete Vibrator

0.0007

day

400.00

0.27 57.40

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

0.57

Subtotal-A1: Subtotal-B: Subtotal-C:

57.98 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

59.14

10% Profit ( Add 10% on Subtotal-B) :

65.05

VAT

6% of Total

IT

4% of Total

4.34 2.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

72.28

Page: 1566 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.12

Detailed Analysis Brief Description of Item 2 PCC Block Size : 250mmx250mmx250mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0141

m3

3500.00

49.22

Sand (FM - 1.5)

0.0070

m3

795.00

5.59

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0661

bag

430.00

28.44

Mason

0.0013

day

550.00

0.72

Skilled Labour

0.0076

day

450.00

3.40

Ordinary Labour

0.0281

day

370.00

10.40

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0012

day

1200.00

1.40

Hire and running charges of Concrete Vibrator

0.0012

day

400.00

0.47 99.63

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

1.00

Subtotal-A1: Subtotal-B: Subtotal-C:

100.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102.64

10% Profit ( Add 10% on Subtotal-B) :

112.90

VAT

6% of Total

IT

4% of Total

7.53 5.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

125.45

Page: 1567 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.18.13

Detailed Analysis Brief Description of Item 2 PCC Block Size : 250mmx250mmx150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0084

m3

3500.00

29.53

Sand (FM - 1.5)

0.0042

m3

795.00

3.35

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0397

bag

430.00

17.07

Mason

0.0008

day

550.00

0.43

Skilled Labour

0.0045

day

450.00

2.04

Ordinary Labour

0.0169

day

370.00

6.25

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0007

day

1200.00

0.84

Hire and running charges of Concrete Vibrator

0.0007

day

400.00

0.28 59.79

Subtotal-A: Steel form work & all other remaining costs

( +1.00 % on Subtotal-A )

0.60

Subtotal-A1: Subtotal-B: Subtotal-C:

60.39 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61.60

10% Profit ( Add 10% on Subtotal-B) :

67.76

VAT

6% of Total

IT

4% of Total

4.52 3.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

75.29

Page: 1568 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.19

Detailed Analysis Brief Description of Item 2 "Cleaning of Drain: Taking out of silted sludge from the bottom of drain and disposal quickly in safe places with necessary materials including cost of all materials and labour etc. all complete as per direction of Engineer in Charge. For open drain"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

444.00

cum

Ordinary Labour

1.2000

444.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

452.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

498.17

VAT

6% of Total

IT

4% of Total

33.21 22.14 Total:

5.21.20

"Cleaning of Drain: Taking out of silted sludge from the bottom of cover/pipe drain and disposal quickly in safe places with necessary materials etc. all complete as per direction of Engineer in Charge. For Cover/ Pipe drain"

cum

Ordinary Labour

2.0000

day

370.00

Subtotal-B: Subtotal-C:

740.00 740.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

754.80

10% Profit ( Add 10% on Subtotal-B) :

830.28

VAT

6% of Total

IT

4% of Total

55.35 36.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

553.52

922.53

Page: 1569 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.21

Detailed Analysis Brief Description of Item 2 Construction of Boundary Wall of 1.83m height with concrete hollow block (Size:400mmx200mmx80mm or any other equivalent size or quality) in cement mortar (1:4)with Portland Composite cement CEM II/AM, 42.5N), best quality sand (minimum FM1.2) with 6mm thick plastering (1:6) with Portland Composite cement CEM II/AM, 42.5N), best quality sand (minimum FM1.2) on both sides, laying of footing, grade beam and column made of special hollow blocks, paving stone below footing, topping over boundary wall in/c reinforcement, necessary scaffolding, curing for the requisite period etc. all complete as per direction of E-I-C. Thickness of individual block wall should not be less than 12mm and void volume should not exceed 33% of block gross volume. Minimum compressive strength of block should be 7N/mm2.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.3060

cum

75.80

23.19

80mm thick concrete hollow block of minimum compressive strength is 8.5 Mpa (400mmx200mmx80mm)

0.3020

each

32.00

9.66

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0700

cum

7643.67

535.06

RCC works (1:2:4) with brick chips for foundation beam….(5.05.01.02)

0.0380

cum

8453.83

321.25

RCC works (1:2:4) with brick chips for pedestal, column, capital, lift wall in ground floor….(5.05.02.01)

0.0750

cum

9422.25

706.67

Fancy Screen

0.5550

m2

300.00

166.50

12mm thick cement plaster (1:6) to wall for ground floor…..(5.12.02.01)

2.4400

sqm

184.48

450.12

MS Rod (Plain, 40 Grade)

4.8800

kg

45.00

219.60

75mm thick brick masonry cement mortar (1:4)….(5.04.13)

1.1100

m

203.59

225.99 2658.04

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2711.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2982.32

VAT

6% of Total

IT

4% of Total

198.82 132.55 Page: 1570 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 5.21.22

Construction of Boundary Wall of 1.83m height with concrete hollow block (Size:400mmx200mmx80mm or any other equivalent size or quality) in cement mortar (1:4) of minimum sand F.M. 1.2 but without any plastering on any side, laying of concrete footing, grade beam and column made of special hollow blocks, paving stone below footing, copping over boundary wall in/c reinforcement, necessary scaffolding, curing for the requisite period etc. all complete as per direction of E-I-C. Thickness of individual block wall should not be less than 12mm and void volume should not exceed 33% of block gross volume. Minimum compressive strength of block should be 7N/mm2.

m

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.3060

cum

75.80

23.19

80mm thick concrete hollow block of minimum compressive strength is 8.5 Mpa (400mmx200mmx80mm)

0.3020

each

32.00

9.66

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0700

cum

7643.67

535.06

RCC works (1:2:4) with brick chips for foundation beam….(5.05.01.02)

0.0380

cum

8453.83

321.25

RCC works (1:2:4) with brick chips for pedestal, column, capital, lift wall in ground floor….(5.05.02.01)

0.0750

cum

9422.25

706.67

Fancy Screen

0.5550

m2

300.00

166.50

MS Rod (Plain, 40 Grade)

4.8800

kg

45.00

219.60

75mm thick brick masonry cement mortar (1:4)….(5.04.13)

1.1100

m

203.59

225.99 2207.92

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2252.08

10% Profit ( Add 10% on Subtotal-B) :

2477.28

VAT

6% of Total

IT

4% of Total

165.15 110.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3313.69

2752.54

Page: 1571 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.23

Detailed Analysis Brief Description of Item 2 Construction of Boundary Wall of 2.44m height with concrete hollow block (Size:400mmx200mmx80mm or any other equivalent size or quality) in cement mortar (1:4) with 6mm thick plastering (1:6) of minimum sand F.M. 1.2 on both sides, laying of concrete footing, grade beam and column made of special hollow blocks, paving stone below footing, topping over boundary wall in/c reinforcement, necessary scaffolding, curing for the requisite period etc. all complete as per direction of E-I-C. Thickness of individual block wall should not be less than 12mm and void volume should not exceed 33% of block gross volume. Minimum compressive strength of block should be 7N/mm2.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.5100

cum

75.80

38.66

80mm thick concrete hollow block of minimum compressive strength is 8.5 Mpa (400mmx200mmx80mm)

0.5400

each

32.00

17.28

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.1230

cum

7643.67

940.17

RCC works (1:2:4) with brick chips for foundation beam….(5.05.01.02)

0.0380

cum

8453.83

321.25

RCC works (1:2:4) with brick chips for pedestal, column, capital, lift wall in ground floor….(5.05.02.01)

0.0920

cum

9422.25

866.85

Fancy Screen

1.4700

m2

300.00

441.00

MS Rod (Plain, 40 Grade)

5.7000

kg

45.00

256.50

75mm thick brick masonry cement mortar (1:4)….(5.04.13)

1.4830

m

203.59

301.93

12mm thick cement plaster (1:6) to wall for ground floor…..(5.12.02.01)

3.2600

sqm

184.48

601.40 3785.02

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3860.72

10% Profit ( Add 10% on Subtotal-B) :

4246.80

VAT

6% of Total

IT

4% of Total

283.12 188.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4718.66

Page: 1572 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.24

Detailed Analysis Brief Description of Item 2 Construction of Boundary Wall of 2.44m height with concrete hollow block (Size:400mmx200mmx80mm or any other equivalent size or quality) in cement mortar (1:4) with Portland Composite cement (CEM II/AM, 42.5N), best quality sand (minimum FM1.2) but without any plastering on any side, laying of concrete footing, grade beam and column made of special hollow blocks, paving stone below footing, topping over boundary wall in/c reinforcement, necessary scaffolding, curing for the requisite period etc. all complete as per direction of E-I-C. Thickness of individual block wall should not be less than 12mm and void volume should not exceed 33% of block gross volume. Minimum compressive strength of block should be 7N/mm2.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.5100

cum

75.80

38.66

80mm thick concrete hollow block of minimum compressive strength is 8.5 Mpa (400mmx200mmx80mm)

0.5400

each

32.00

17.28

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.1230

cum

7643.67

940.17

RCC works (1:2:4) with brick chips for foundation beam….(5.05.01.02)

0.0380

cum

8453.83

321.25

RCC works (1:2:4) with brick chips for pedestal, column, capital, lift wall in ground floor….(5.05.02.01)

0.0920

cum

9422.25

866.85

Fancy Screen

1.4700

m2

300.00

441.00

MS Rod (Plain, 40 Grade)

5.7000

kg

45.00

256.50

75mm thick brick masonry cement mortar (1:4)….(5.04.13)

1.4830

m

203.59

301.93 3183.63

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3247.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3572.03

VAT

6% of Total

IT

4% of Total

238.14 158.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3968.92

Page: 1573 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.21.25

Providing and installation of PVC water grade pipe (Lira brand or equivalent) embedded in R.C.C. roof and other R.C.C. members at all levels complete for electric and telephone wiring with all accessories such as circular box, pull box, bends, sockets in/c No. 12 SWG GI pull wire for drawing of cables in/c tying the pipe with reinforcement with the help of GI binding wires at 400mm intervals where required etc. all complete as per drawing and design (if provided) and as per direction of the E-I-C. (Prior approval from the Executive E-I-C shall have to be taken regarding quality of pipes and accessories).

5.21.25.01

Minimum inner dia 16mm and minimum wall thickness 1.54mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1.54mm thick 16mm inner dia PVC pipe

1.0000

m

29.52

29.52

Plumber/ Electric Mistry/ Painter

0.0330

day

680.00

22.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1640

day

470.00

77.08 129.04

Subtotal-A: All other remaining costs covering water proof paste, wire, polythene etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

141.94 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

144.78

10% Profit ( Add 10% on Subtotal-B) :

159.26

VAT

6% of Total

IT

4% of Total

10.62 7.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12.90

176.96

Page: 1574 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.25.02

Detailed Analysis Brief Description of Item 2 Minimum inner dia 20mm and minimum wall thickness 1.54mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1.54mm thick 20mm inner dia PVC pipe

1.0000

m

40.67

40.67

Plumber/ Electric Mistry/ Painter

0.0330

day

680.00

22.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1640

day

470.00

77.08 140.19

Subtotal-A: All other remaining costs covering water proof paste, wire, polythene etc.

( +6.00 % on Subtotal-A )

8.41

Subtotal-A1: Subtotal-B: Subtotal-C:

148.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

151.57

10% Profit ( Add 10% on Subtotal-B) :

166.73

VAT

6% of Total

11.12

IT

4% of Total

7.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

185.26

Page: 1575 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.21.25.03

Detailed Analysis Brief Description of Item 2 Minimum inner dia 25mm and minimum wall thickness 1.54mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1.54mm thick 20mm inner dia PVC pipe

1.0000

m

40.67

40.67

Plumber/ Electric Mistry/ Painter

0.0330

day

680.00

22.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1640

day

470.00

77.08 140.19

Subtotal-A: All other remaining costs covering water proof paste, wire, polythene etc.

( +8.00 % on Subtotal-A )

11.22

Subtotal-A1: Subtotal-B: Subtotal-C:

151.41 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

154.43

10% Profit ( Add 10% on Subtotal-B) :

169.88

VAT

6% of Total

11.33

IT

4% of Total

7.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

188.75

Page: 1576 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.22.01

Detailed Analysis Brief Description of Item 2 Constructing surface drain of 300 mm clear width and depth up to 300 mm in brick masonry with 125 mm thick check wall in cement sand mortar (1:6) over average 75 mm thick cement concrete base (1:3:6) with Portland Composite cement (CEM II/AM, 42.5N), best quality sand (minimum FM1.2) and 20mm down well graded 1st class/picked brick chips (LAA value not exceeding 40) over one layer of 1st class brick flat soling including breaking chips. The surface having minimum 12 mm thick cement sand plaster (1:3) with Portland Composite cement (CEM II/AM, 42.5N), best quality sand (minimum FM1.2) and neat cement finishing, curing at least for 7 days including excavation in all kinds of soil, back filling with fine sand (F.M. 0.8), consolidating and dressing, cost of water, electricity, other charges etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

m

1st Class Brick

41.0000

each

9.00

369.00

1st Class Brick Chips (20mm down graded)

0.0360

m3

2940.00

105.84

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.4663

bag

430.00

200.51

Sand (FM - 1.2)

0.0450

m3

584.00

26.28

Sand (FM - 0.8)

0.0067

m3

480.00

3.22

Head Mason

0.0410

day

650.00

26.65

Mason

0.1916

day

550.00

105.38

Skilled Labour

0.0320

day

450.00

14.40

Ordinary Labour

0.5250

day

370.00

194.25

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0026

day

1200.00

3.12

Hire and running charges of Concrete Vibrator

0.0026

day

400.00

1.04 1049.69

Subtotal-A: All other costs form work etc.

( +1.00 % on Subtotal-A )

Subtotal-A1:

10.50 1060.18

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1081.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1189.52

VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

6% of Total

79.30 Page: 1577 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

52.87 Total:

5.22.02

Providing apron with 50 mm thick cement concrete (1:2:4) with Portland Composite cement (CEM II/AM, 42.5N), best quality sand (minimum FM1.2) and 20mm down well graded 1st class/picked brick chips (LAA value not exceeding 40) including breaking chips and one layer 1st class brick flat soling at bottom' including cutting earth for preparation of bed and filling the interstices with local sand (F.M. 0.8) including finishing, dressing, curing at least for 7 days etc. all complete, including cost of water, and all other charges etc. all complete as per direction of the E-I-C.

sqm

1st Class Brick

31.0000

each

9.00

279.00

1st Class Brick Chips (20mm down graded)

0.0460

m3

2940.00

135.24

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3750

bag

430.00

161.25

Sand (FM - 1.2)

0.0230

m3

584.00

13.43

Sand (FM - 0.8)

0.0120

m3

480.00

5.76

Head Mason

0.0041

day

650.00

2.67

Mason

0.1032

day

550.00

56.76

Skilled Labour

0.0380

day

450.00

17.10

Ordinary Labour

0.3380

day

370.00

125.06 796.27

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

812.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

893.41

VAT

6% of Total

IT

4% of Total

59.56 39.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1321.69

992.68

Page: 1578 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Pre-cast driven RCC Micro compaction pile (150mmx150mm) with reinforced cement concrete having minimum cylinder crushing strength of 25 Mpa at 28 days (suggested mix proportion 1:1.5:3) with best quality Portland Composite cement (CEM II/AM, 42.5N), best quality coarse sand (minimum FM 2.50) and best quality 20mm down well graded crushed stone chips (LAA value not exceeding 30) (Preferably stone chips from Madhyapara, Dinajpur), screening through proper sieves, cleaning and washing thoroughly, centering and shuttering with MS sheet and steel form, placing of reinforcement cage in position, mixing the aggregates with mixer machine, casting in steel forms, using concrete or similar suitable chemicals, compacting by mechanical vibrators and tapered rods and curing for 28 days etc. all complete as per design & drawing fitting and fixing the pile cap, driving the pile upto the design depth with winch machine or specified method, providing all equipment, labour, materials including carrying etc. all complete as per design, drawing and direction of the E-I-C. (Excluding the cost of reinforcement and its fabrication)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1579 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.01.01

Detailed Analysis Brief Description of Item 2 Cost of cement concrete (Size-150mmx150mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Stone Chips (20mm down graded) [LAA≤30]

0.0100

m3

5320.00

53.20

Sand (FM - 2.5)

0.0100

m3

1500.00

15.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Head Mason

0.0030

day

650.00

1.95

Mason

0.0110

day

550.00

6.05

Skilled Labour

0.0160

day

450.00

7.20

Ordinary Labour

0.0200

day

370.00

7.40

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0013

day

1200.00

1.56

Hire and running charges of Concrete Vibrator

0.0013

day

400.00

0.52

Stone Chips (12mm down graded) [LAA≤30]

0.0100

m3

4470.00

44.70 223.58

Subtotal-A: All other cost covering, form work, sundries etc.

( +17.00 % on Subtotal-A )

Subtotal-A1:

261.59

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

266.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

293.50

VAT

6% of Total

IT

4% of Total

19.57 13.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

38.01

326.11

Page: 1580 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.01.02

Detailed Analysis Brief Description of Item 2 Cost of driving with winch machine up to 7.5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0500

day

3000.00

150.00

H.C. of Driving Equipment

0.0110

day

350.00

3.85

Diesel

0.2200

liter

68.00

14.96

Lubricant

0.0200

liter

220.00

4.40 219.21

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

223.59

10% Profit ( Add 10% on Subtotal-B) :

245.95

VAT

6% of Total

IT

4% of Total

16.40 10.93 Total:

5.23.01.03

Cost of driving manually up to 6 m

m Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Driving Equipment

0.0500

day

350.00

17.50 174.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

177.99

10% Profit ( Add 10% on Subtotal-B) :

195.79

VAT

6% of Total

IT

4% of Total

13.05 8.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

273.28

217.54

Page: 1581 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Pre-cast driven RCC Micro compaction pile (150mmx150mm) with reinforced cement concrete having minimum cylinder crushing strength of 20 Mpa at 28 days (suggested mix proportion 1:1.5:3) with best quality Portland Composite cement (CEM II/AM, 42.5N), best quality coarse sand (minimum FM 2.2) and best quality 20mm down well graded crushed 1st class bricks/picked chips (LAA value not exceeding 38), screening through proper sieves, cleaning and washing thoroughly, centering and shuttering with MS sheet and steel form, placing of reinforcement cage in position, mixing the aggregates with mixer machine, casting in steel forms, compacting by mechanical vibrators and tapered rods and curing for 28 days etc. all complete as per design & drawing fitting and fixing the pile cap, driving the pile upto the design depth with winch machine or specified method, providing all equipment, labour, materials including carrying etc. all complete as per design, drawing and direction of the E-I-C. (Excluding the cost of reinforcement and its fabrication)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1582 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.02.01

Detailed Analysis Brief Description of Item 2 Cost of cement concrete (Size-150mmx150mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (20mm down graded)

0.0120

m3

2940.00

35.28

Sand (FM - 2.5)

0.0060

m3

1500.00

9.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Head Mason

0.0030

day

650.00

1.95

Mason

0.0110

day

550.00

6.05

Skilled Labour

0.0160

day

450.00

7.20

Ordinary Labour

0.0200

day

370.00

7.40

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0013

day

1200.00

1.56

Hire and running charges of Concrete Vibrator

0.0013

day

400.00

0.52

Sand (FM - 1.8)

0.0040

m3

970.00

3.88

1st Class Brick Chips (10mm down graded)

0.0080

m3

3049.00

24.39 183.23

Subtotal-A: All other costs covering form work, sundries etc.

( +17.00 % on Subtotal-A )

Subtotal-A1:

214.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

218.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

240.54

VAT

6% of Total

16.04

IT

4% of Total

10.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

31.15

267.26

Page: 1583 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.02.02

Detailed Analysis Brief Description of Item 2 Cost of driving with winch machine up to 7.5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.1000

day

370.00

37.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0500

day

3000.00

150.00

H.C. of Driving Equipment

0.0110

day

350.00

3.85

Diesel

0.2200

liter

68.00

14.96

Lubricant

0.0200

liter

220.00

4.40 219.21

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

223.59

10% Profit ( Add 10% on Subtotal-B) :

245.95

VAT

6% of Total

IT

4% of Total

16.40 10.93 Total:

5.23.02.03

Cost of driving manually up to 6 m

m Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Driving Equipment

0.0500

day

350.00

17.50 174.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

177.99

10% Profit ( Add 10% on Subtotal-B) :

195.79

VAT

6% of Total

IT

4% of Total

13.05 8.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

273.28

217.54

Page: 1584 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.23.02.04

Construction of Sand compaction pile up to required depth and diameter with temporary steel casing in specified type of soil including Derrick/winch machine & Drop hammer (weight minimum 1 ton). The rate shall contribute the full compensation of furnishing all materials like sand (minimum F.M-0.8), driving pile holes, boring casing pipe, placing of materials & other compaction. SPT or any other method & tests for determining the improvement in the bearing capacity (N-value minimum 8), arranging all equipment and machinery, labour, tools and incidentals necessary to complete the work as per requirements described under this item of work as shown on the drawings and direction of the E-I-C. (excluding the cost of SPT)

5.23.02.04.1

Cost of sand compaction pile (size 200mm dia)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Sand (FM - 0.8)

0.0471

m3

480.00

22.61

Foreman

0.0110

day

800.00

8.80

Skilled Labour

0.0400

day

450.00

18.00

Operator

0.0110

day

570.00

6.27

Ordinary Labour

0.0880

day

370.00

32.56

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0110

day

3000.00

33.00

H.C. of Driving Equipment

0.0110

day

350.00

3.85

H.C. of Casing

0.0110

day

260.00

2.86

Diesel

0.2200

liter

68.00

14.96

Lubricant

0.0200

liter

220.00

4.40 147.31

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

150.25

10% Profit ( Add 10% on Subtotal-B) :

165.28

VAT

6% of Total

IT

4% of Total

11.02 7.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

183.64

Page: 1585 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.02.04.2

Detailed Analysis Brief Description of Item 2 Cost of sand compaction pile (size 250mm dia)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Sand (FM - 0.8)

0.0740

m3

480.00

35.52

Foreman

0.0140

day

800.00

11.20

Skilled Labour

0.0550

day

450.00

24.75

Operator

0.0140

day

570.00

7.98

Ordinary Labour

0.1100

day

370.00

40.70

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0140

day

3000.00

42.00

H.C. of Driving Equipment

0.0140

day

350.00

4.90

H.C. of Casing

0.0140

day

260.00

3.64

Diesel

0.2770

liter

68.00

18.84

Lubricant

0.0277

liter

220.00

6.09 195.62

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

199.53

10% Profit ( Add 10% on Subtotal-B) :

219.49

VAT

6% of Total

IT

4% of Total

14.63 9.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

243.87

Page: 1586 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.02.04.3

Detailed Analysis Brief Description of Item 2 Cost of sand compaction pile (size 300mm dia)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Sand (FM - 0.8)

0.1060

m3

480.00

50.88

Foreman

0.0160

day

800.00

12.80

Skilled Labour

0.0660

day

450.00

29.70

Operator

0.0160

day

570.00

9.12

Ordinary Labour

0.1330

day

370.00

49.21

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0160

day

3000.00

48.00

H.C. of Driving Equipment

0.0160

day

350.00

5.60

H.C. of Casing

0.0160

day

260.00

4.16

Diesel

0.3330

liter

68.00

22.64

Lubricant

0.0330

liter

220.00

7.26 239.37

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

244.16

10% Profit ( Add 10% on Subtotal-B) :

268.58

VAT

6% of Total

IT

4% of Total

17.91 11.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

298.42

Page: 1587 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.23.03

Boring and casting of RCC cast-in-situ piles up to the required depth and diameter with temporary steel casing in all types of soils including 2chamber slurry tank, drilling"Boring and casting of RCC cast-in-situ piles up to the required depth and diameter with temporary steel casing in all types of soils including 2-chamber slurry tank, drilling with bentonite circulation (Dry Bentonite powder of liquid limit of minimum 350 shall be mixed with water @ minimum 4% by weight to make the fresh drilling fluid of viscosity between 32-50 seconds and density less than 1.1gm/cc). Washing bore hole with bentonite fresh slurry (until the slurry from bore hole bottom have density less than 1.15gm/cc and sand less than 4%) placing of reinforcement and placing concrete by tremie pipe with best quality Portland Composite Cement (CEM-II/AL/M/V/W 42.5N), sand (minimum FM 2.50) and 20mm down well graded crushed stone chips (LAA value not exceeding 30) to result minimum ultimate cylinder crushing strength of 25MPa at 28 days (suggested minimum mix proportion 1:1.5:3) with allowable slump of 150mm to 200mm (using necessary admixture : ASTM C494/C494M and additional cement) including cost of all materials, labour, equipment and all incidental charges but excluding the cost of reinforcement and its fabrication, etc. all complete as per design, drawing, specifications and direction of the Engineer. Additional quantity of cement be added, if required to attain the afore-mentioned concrete strength, by the contractor at his own costs.(Boring method shall be selected as set in the drawing).

5.23.03.01

BORING PERCUSSION METHOD: Direct Mud Circulation (DMC)

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1588 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.23.03.01.1

2 450mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Bentonite

7.0000

kg

36.00

252.00

Foreman

0.0500

day

800.00

40.00

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

0.3000

day

370.00

111.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0500

day

3000.00

150.00

H.C. of Derrick

0.0500

day

400.00

20.00

H.C. of Water Pump

0.0500

day

500.00

25.00

H.C. of Tremie Pipe

0.0500

day

500.00

25.00

H.C. of Bailer

0.0500

day

300.00

15.00

H.C. of Cutter

0.0500

day

200.00

10.00

H.C. of Water Sealing Device

0.0500

day

200.00

10.00

H.C. of Welding Machine

0.0200

day

500.00

10.00

Diesel

3.0000

liter

68.00

204.00

Lubricant

0.0300

liter

220.00

6.60 946.10

Subtotal-A: Slurry Tank

( +26.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1192.09 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1215.93

10% Profit ( Add 10% on Subtotal-B) :

1337.52

VAT

6% of Total

89.17

IT

4% of Total

59.45 Total:

5.23.03.01.2

500mm dia

Note : Rates of all items should be inclusive of all supply and carriage.

m

245.99

1486.13

Add +25.00% with Item No 5.23.03.01.1

Page: 1589 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.23.03.01.3

600mm dia

m

Add +50.00% with Item No 5.23.03.01.1

5.23.03.01.4

700mm dia

m

Add +75.00% with Item No 5.23.03.01.1

5.23.03.01.5

800mm dia

m

Add +100.00% with Item No 5.23.03.01.1

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1590 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.03.02

Detailed Analysis Brief Description of Item 2 Concreting (with water reducing Admixture)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Water Reducing Admixture

2.3300

liter

130.00

302.90

Foreman

0.1240

day

800.00

99.20

Fitter Helper

0.1240

day

470.00

58.28

Skilled Labour

0.6780

day

450.00

305.10

Ordinary Labour

1.3600

day

370.00

503.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.1240

day

3000.00

372.00

H.C. of Derrick

0.1240

day

400.00

49.60

H.C. of Tremie Pipe

0.1240

day

500.00

62.00

H.C. of Casing

0.1240

day

260.00

32.24

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Diesel

1.0000

liter

68.00

68.00

Lubricant

0.0100

liter

220.00

2.20

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 9938.92

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10137.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11151.47

VAT

6% of Total

IT

4% of Total

743.43 495.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12390.52

Page: 1591 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.03.03

Detailed Analysis Brief Description of Item 2 Concreting (without water reducing Admixture)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Foreman

0.1240

day

800.00

99.20

Fitter Helper

0.1240

day

470.00

58.28

Skilled Labour

0.6780

day

450.00

305.10

Ordinary Labour

1.3600

day

370.00

503.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.1240

day

3000.00

372.00

H.C. of Derrick

0.1240

day

400.00

49.60

H.C. of Tremie Pipe

0.1240

day

500.00

62.00

H.C. of Casing

0.1240

day

260.00

32.24

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Diesel

1.0000

liter

68.00

68.00

Lubricant

0.0100

liter

220.00

2.20

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 9636.02

Subtotal-A: Subtotal-B: Subtotal-C:

9828.74

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10811.61

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

720.77

IT

4% of Total

480.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12012.90

Page: 1592 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.04

Detailed Analysis Brief Description of Item 2 Labour for breaking head of cast-in-situ bored pile/pre-cast pile up to required length by any means and removing the dismantled materials, such as, concrete to a safe distance including scrapping and removing concrete from steel/MS rods, preparation and making of platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, leveling and dressing the site and clearing the river bed, etc. all complete as per direction of the E-I-C. (Measurement will be given for the actual pile head volume to be broken).

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

5.0000

day

450.00

2250.00

10.0000

day

370.00

3700.00

5

Amount 8

cum

Skilled Labour Ordinary Labour

5950.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6069.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6675.90

VAT

6% of Total

445.06

IT

4% of Total

296.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7417.67

Page: 1593 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

5.23.05

Conducting static load test as per ASTM D1143 or equivalent standard for the cast in situ/ precast pile providing required scaffolding, bracing, jacks, pressure test gauge, loading unloading, arranging other necessary plants and equipment including staging, mobilization. Conducting static load test as per ASTM D1143 or equivalent standard for the cast in situ/ precast pile providing required scaffolding, bracing, jacks, pressure test gauge, loading unloading, arranging other necessary plants and equipment including staging, mobilization, demobilization, hire charge, gunny bags, sand and filling sacs/gunny bags for loading / concrete Block or equivalent, record readings and preparation of results in standard forms and other incidental charges as per standard practice and procedures including submission of load test report, furnishing all graph and chart etc. complete in all respects approved and accepted by the Engineer (Minimum two cyclic loading). Before commencing load test, Contractor shall submit method statement for conducting load test to the Engineer for approval. However, Engineer’s approval shall not relieve the Contractor of his responsibilities and obligations under Contract. Load Test and Report shall be conducted under the supervision of a professional Engineer. Boring and pouring logs / Driving logs of piles and Method statement shall be the part of load test report . [Cost of combined Calibration Test (Hydraulic jack, Pressure gauge and electric pump) is included in all items]

5.23.05.01

using sand filled gunny bag

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1594 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.23.05.01.1

2 up to 75 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Empty Gunny Bag

675.0000

each

30.00

20250.00

Sand (FM - 0.5)

19.0000

m3

420.00

7980.00

Ordinary Labour

12.0000

day

370.00

4440.00

1.0000

set

10500.00

10500.00

H.C. of Load Test Equipment and Accessories including Transportation: up to 125 Ton Capacity H.C. of Flat Body Truck (5 tons)

3.0000

day

3000.00

9000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

6.0000

day

450.00

2700.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00 86470.00

Subtotal-A: Calibration of pressure gauge/calibration of jack, preparation of result, other incidental charge etc. Labour for bag filling, stitching, loading & unloading etc.

( +5.00 % on Subtotal-A )

4323.50

( +30.00 % on Subtotal-A )

25941.00

Subtotal-A1: Subtotal-B: Subtotal-C:

116734.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

119069.19

10% Profit ( Add 10% on Subtotal-B) :

130976.11

VAT

6% of Total

IT

4% of Total

8731.74 5821.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

145529.01

Page: 1595 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.23.05.01.2

2 Above 75 ton and up to 125 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Empty Gunny Bag

1125.0000

each

30.00

33750.00

Sand (FM - 0.5)

45.0000

m3

420.00

18900.00

Ordinary Labour

12.0000

day

370.00

4440.00

1.0000

set

10500.00

10500.00

H.C. of Load Test Equipment and Accessories including Transportation: up to 125 Ton Capacity H.C. of Flat Body Truck (5 tons)

4.0000

day

3000.00

12000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

6.0000

day

450.00

2700.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00 113890.00

Subtotal-A: Calibration of pressure gauge/calibration of jack, preparation of result, other incidental charge etc. Labour for bag filling, stitching, loading & unloading etc.

( +5.00 % on Subtotal-A )

5694.50

( +30.00 % on Subtotal-A )

34167.00

Subtotal-A1: Subtotal-B: Subtotal-C:

153751.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

156826.53

10% Profit ( Add 10% on Subtotal-B) :

172509.18

VAT

6% of Total

IT

4% of Total

11500.61 7667.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

191676.87

Page: 1596 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.05.01.3

Detailed Analysis Brief Description of Item 2 Above 125 ton and up to 175 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Empty Gunny Bag

1575.0000

each

30.00

47250.00

Sand (FM - 0.5)

45.0000

m3

420.00

18900.00

Ordinary Labour

16.0000

day

370.00

5920.00

1.0000

set

12500.00

12500.00

H.C. of Load Test Equipment and Accessories including Transportation: above 125 Ton capacity H.C. of Flat Body Truck (5 tons)

5.0000

day

3000.00

15000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

8.0000

day

450.00

3600.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00 134770.00

Subtotal-A: Calibration of pressure gauge/calibration of jack, preparation of result, other incidental charge etc. Labour for bag filling, stitching, loading & unloading etc.

( +5.00 % on Subtotal-A )

6738.50

( +30.00 % on Subtotal-A )

40431.00

Subtotal-A1: Subtotal-B: Subtotal-C:

181939.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185578.29

10% Profit ( Add 10% on Subtotal-B) :

204136.12

VAT

6% of Total

IT

4% of Total

13609.07 9072.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

226817.91

Page: 1597 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.05.01.4

Detailed Analysis Brief Description of Item 2 Above 175 ton and up to 225 ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Empty Gunny Bag

2025.0000

each

30.00

60750.00

Sand (FM - 0.5)

57.5000

m3

420.00

24150.00

Ordinary Labour

16.0000

day

370.00

5920.00

1.0000

set

12500.00

12500.00

H.C. of Load Test Equipment and Accessories including Transportation: above 125 Ton capacity H.C. of Flat Body Truck (5 tons)

6.0000

day

3000.00

18000.00

Foreman

2.0000

day

800.00

1600.00

Skilled Labour

8.0000

day

450.00

3600.00

Calibration of Hydraulic Jack

1.0000

set

30000.00

30000.00 156520.00

Subtotal-A: Calibration of pressure gauge/calibration of jack, preparation of result, other incidental charge etc. Labour for bag filling, stitching, loading & unloading etc.

( +5.00 % on Subtotal-A )

7826.00

( +30.00 % on Subtotal-A )

46956.00

Subtotal-A1: Subtotal-B: Subtotal-C:

211302.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

215528.04

10% Profit ( Add 10% on Subtotal-B) :

237080.84

VAT

6% of Total

IT

4% of Total

15805.39 10536.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

263423.16

Page: 1598 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.23.06

PIT (Pile Integrity test) of cast-in-situ/pre-cast pile by a qualified and approved PIT expert, preparing the pile heads and placing a small accelerometer on the top of a pile while hitting the pile head with a small hammer. The shock wave traveling through the pile propagate with the velocity of sound in concrete which is 3000-3500 m/s approximately and data acquisition and analysis, preparation of results in standard forms and compiling final report with recommendation on the tests or as decided by the Engineer, as per approved method {Report shall contain driving log/Boring and pouring logs, graphs & statement on “Calibration pile” (pile that tested for its capacity and PIT done earlier on it, at a place of Known soil profiles), soil investigation report (Calibration pile shall be made and tested first)} Method statement for conducting PIT shall be submitted the Engineer for approval, and shall be the part of PIT report.

5.23.06.01

PIT on 10 (ten) nos. piles or less

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set PIT: Mobilization, demobilization of Pile Integrity Testing Equipment including 10 nos. tests

1.0000

set

15000.00

15000.00

Skilled Technician

1.0000

day

680.00

680.00

Semi Skilled Technician

1.0000

day

570.00

570.00 16250.00

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

812.50

Subtotal-A1: Subtotal-B: Subtotal-C:

17062.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17403.75

10% Profit ( Add 10% on Subtotal-B) :

19144.13

VAT

6% of Total

IT

4% of Total

1276.28 850.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21271.25

Page: 1599 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.06.02

Detailed Analysis Brief Description of Item 2 PIT on each additional pile after 10(ten) piles tested.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PIT: per PIT after 1st 10 nos. PIT

1.0000

Each

1200.00

1200.00

Skilled Technician

0.0667

day

680.00

45.36

Semi Skilled Technician

0.0667

day

570.00

38.02 1283.38

Subtotal-A: Reporting charges and consumables etc.

( +5.00 % on Subtotal-A )

64.17

Subtotal-A1:

1347.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1374.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1511.94

VAT

6% of Total

IT

4% of Total

100.80 67.20 Total:

5.23.07

Mobilization for pre-cast RCC test piles for driving with pile driving set, winch (if required, with followers), etc. up to the desired and required depth and length, etc. to determine the length of the services piles, etc, complete as per direction of the E-I-C. (The driving cost will be paid as per service piles).

Note : Rates of all items should be inclusive of all supply and carriage.

1679.94

LS

Page: 1600 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.08

Detailed Analysis Brief Description of Item 2 Reinforced cement concrete in bands of well staining with Portland Composite cement (CEM II/AM, 42.5N), best quality coarse sand (minimum FM 1.8) and 20mm down well graded picked brick chips (LAA value not exceeding 38) to be obtained from best quality Picked chips,admixture with proper dodge, including cost of all other materials shuttering, casting, curing for 28 days, labour charges for breaking bricks into chips and all incidental charges, etc. all complete as per direction of the E-I-C ( excluding the cost of reinforcement and its febrication). Cylinder crushing strength of the concrete should not be less than 17MPa at 28 days of curing (suggested mix proportion 1:2:4). Additional quantity of cement to be added if required to attain the strength at the contractor’s own costs.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (20mm down graded)

0.5400

m3

2940.00

1587.60

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.0570

day

450.00

25.65

Ordinary Labour

0.4650

day

370.00

172.05

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3600

m3

3049.00

1097.64 6299.94

Subtotal-A: All other remaining csts covering form work etc

( +9.00 % on Subtotal-A )

566.99

Subtotal-A1:

6866.93

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7004.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7704.70

VAT

6% of Total

IT

4% of Total

513.65 342.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8560.78

Page: 1601 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.09.01

Detailed Analysis Brief Description of Item 2 First class brick works in cement mortar (1:4) in staining of wells with Portland Composite cement (CEM II/AM, 42.5N) and best quality coarse sand (minimum FM 1.5) cutting bricks to required sizes, hoisting and keeping in position the MS bond rods and finished with flush pointing joints, watering, etc. complete including cost of all materials but excluding cost of MS bond rods and bottle nuts, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick

406.0000

Sand (FM - 1.5)

each

9.00

3654.00

795.00

302.10

0.3800

m3

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.1200

bag

430.00

911.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 5976.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6096.23

10% Profit ( Add 10% on Subtotal-B) :

6705.86

VAT

6% of Total

IT

4% of Total

447.06 298.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7450.95

Page: 1602 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.09.02

Detailed Analysis Brief Description of Item 2 First class brick works in cement mortar (1:3) in staining of wells with Portland Composite cement (CEM II/AM, 42.5N) and best quality coarse sand (minimum FM 1.5), cutting bricks to required sizes, hoisting and keeping in position the MS bond rods and finished with flush pointing joints, watering, etc. complete including cost of all materials but excluding cost of MS bond rods and bottle nuts, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick

406.0000

Sand (FM - 1.5)

each

9.00

3654.00

795.00

302.10

0.3800

m3

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.8600

bag

430.00

1229.80

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 6294.90

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6420.80

10% Profit ( Add 10% on Subtotal-B) :

7062.88

VAT

6% of Total

IT

4% of Total

470.86 313.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7847.64

Page: 1603 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.10

Detailed Analysis Brief Description of Item 2 Reinforced cement concrete in well curb with Portland Composite Cement (CEM II/A-M, 42.5N), sand (minimum FM 1.5), 20mm down well graded Picked brick chips (LAA value not exceeding 38), and admixture with proper doge, having cylinder crushing strength of 17MPa at 28 days as per design (suggested mix proportion 1:2:4) , excluding cost of reinforcement and its fabrication but including cost of MS angle and all other materials, shuttering, casting curing, labour charge for breaking Picked bricks into chips and all other incidental charges, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (20mm down graded)

0.5400

m3

2940.00

1587.60

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.3600

bag

430.00

2734.80

Sand (FM - 1.5)

0.4500

m3

795.00

357.75

Head Mason

0.0600

day

650.00

39.00

Mason

0.3000

day

550.00

165.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

1st Class Brick Chips (10mm down graded)

0.3600

m3

3049.00

1097.64 7155.29

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7298.40

10% Profit ( Add 10% on Subtotal-B) :

8028.24

VAT

6% of Total

IT

4% of Total

535.22 356.81 Total:

5.23.11

8920.26

Labour for sinking composite wells in all sorts of soils by dredging etc. true to drawing, design, plumbing and all other incidental charges (depth of sinking will be measured from bottom of well cap to the bottom of well curb), etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1604 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.23.11.01

2000mmx2000mm wells size

5.23.11.01.1

0m to 6m depth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Wire Rope

0.6500

m

16.40

Jam/Jarul Empty Gunny Bag

0.0001

m3

65650.00

6.57

0.8100

each

30.00

24.30

Sareng

0.8100

day

570.00

461.70

Khalashi

4.0700

day

390.00

1587.30

Skilled Labour

6.1100

day

450.00

2749.50

Ordinary Labour

3.2600

day

370.00

1206.20

H.C. of Derrick

0.0135

day

400.00

5.40

H.C. of Pulley

0.0135

day

250.00

3.38

H.C. of Garb

0.0002

day

500.00

0.10

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.4100

day

3000.00

1230.00 7285.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7430.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8173.88

VAT

6% of Total

IT

4% of Total

544.93 363.28 Total:

5.23.11.01.2

6m to 12m depth

5.23.11.02

2000mmx2500mm wells size

5.23.11.02.1

0m to 6m depth

Note : Rates of all items should be inclusive of all supply and carriage.

10.66

m

Add +12.50% with Item No 5.23.11.01.1

m

Add +16.00% with Item No 5.23.11.01.1

9082.09

Page: 1605 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

5.23.11.02.2

6m to 12m depth

5.23.11.03

2000mmx3000mm wells size

5.23.11.03.1

Unit

Sub-Item

3

4

m

Add +37.00% with Item No 5.23.11.01.1

0m to 6m depth

m

Add +30.00% with Item No 5.23.11.01.1

5.23.11.03.2

6m to 12m depth

m

Add +70.00% with Item No 5.23.11.01.1

5.23.11.04

2500mmx3000mm wells size

5.23.11.04.1

0m to 6m depth

m

Add +37.00% with Item No 5.23.11.01.1

5.23.11.04.2

6m to 12m depth

m

Add +90.00% with Item No 5.23.11.01.1

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1606 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.12

Detailed Analysis Brief Description of Item 2 Plugging the bottom of wells on being sunk to its final position with cement concrete in proportion 1:2:4 laid by “Tremie Pipe” method with Portland Composite Cement (CEM II/A-M, 42.5N), sand (minimum FM 1.50) and best quality 20mm down well graded Picked brick chips (LAA value not exceeding 38) including cost of all materials, labour for breaking bricks into chips and all other incidental charges, etc. complete as per direction of the E-I-C (10% excess cement is to be used). Concrete as laid should not be disturbed for at least 14 days.(excluding cost of reinforcement and its fabrication)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (20mm down graded)

0.5400

m3

2940.00

Sand (FM - 1.5)

0.4500

m3

795.00

357.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.9900

bag

430.00

3005.70

Mason

0.1000

day

550.00

55.00

Ordinary Labour

2.8000

day

370.00

1036.00

1st Class Brick Chips (10mm down graded)

0.3600

m3

3049.00

1097.64 7139.69

Subtotal-A: H.C. of equipments etc

( +2.00 % on Subtotal-A )

142.79

Subtotal-A1: Subtotal-B: Subtotal-C:

7282.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7428.13

10% Profit ( Add 10% on Subtotal-B) :

8170.95

VAT

6% of Total

IT

4% of Total

544.73 363.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1587.60

9078.83

Page: 1607 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.23.13

Detailed Analysis Brief Description of Item 2 Plugging the top of wells with cement concrete (1:2:4) with Portland Composite Cement (CEM II/A-M, 42.5N), sand (minimum FM 1.50) and best quality 20mm down well graded Picked brick chips (LAA value not exceeding 38) including cost of all materials, labour for breaking Picked bricks into chips and all other incidental charges, etc. complete in all respects as per direction of the E-I-C (excluding cost of reinforcement and its fabrication).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (20mm down graded)

0.5400

m3

2940.00

1587.60

Sand (FM - 1.5)

0.4500

m3

795.00

357.75

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.3600

bag

430.00

2734.80

Mason

0.1000

day

550.00

55.00

Ordinary Labour

2.8000

day

370.00

1036.00

1st Class Brick Chips (10mm down graded)

0.3600

m3

3049.00

1097.64 6868.79

Subtotal-A: H.C. of equipments etc

( +2.00 % on Subtotal-A )

137.38

Subtotal-A1:

7006.17

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7146.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7860.92

VAT

6% of Total

IT

4% of Total

524.06 349.37 Total:

5.23.14

8734.35

Driving pre-cast RCC piles with drop hammer type rig in any type of soil to the required depth including mobilization, demobilization, fitting and fixing steel cap, handling and keeping in position and maintaining driving log in prescribed format as per design, drawing & direction of the E-I-C. Before commencing driving operation, contractor shall submit the methodology for carrying the driving operation including sequence of driving to the E-I-C. The maximum permitted deviation of the finished pile from the horizontal & vertical shall be 50mm & 25mm respectively. Cutting of a pile not being installed to the planned depth is exclusively subject to the approval of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1608 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.23.14.01 5.23.14.01.1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

X-section of pre-cast pile: 200mmx200mm 0m to 6m depth

m H.C. of pre-cast pile driving complete rig set

0.0202

day

10500.00

212.10

Rig Operator

0.0175

Skilled Labour

0.0215

day

600.00

10.50

day

450.00

9.68

Ordinary Labour

0.0285

day

370.00

10.55 242.82

Subtotal-A: Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

12.14

Subtotal-A1:

254.96

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

260.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

286.07

VAT

6% of Total

IT

4% of Total

19.07 12.71 Total:

5.23.14.01.2

6m and above depth

5.23.14.02

X-section of pre-cast pile: 225mmx225mm

Note : Rates of all items should be inclusive of all supply and carriage.

m

317.85

Add +15.00% with Item No 5.23.14.01.1

Page: 1609 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.23.14.02.1

2 0m to 6m depth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m H.C. of pre-cast pile driving complete rig set

0.0256

day

10500.00

268.80

Rig Operator

0.0333

day

600.00

19.98

Skilled Labour

0.0333

day

450.00

14.99

Ordinary Labour

0.0250

day

370.00

9.25 313.02

Subtotal-A: Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

15.65

Subtotal-A1: Subtotal-B: Subtotal-C:

328.67 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

335.24

10% Profit ( Add 10% on Subtotal-B) :

368.76

VAT

6% of Total

IT

4% of Total

24.58 16.39 Total:

5.23.14.02.2

6m and above depth

5.23.14.03

X-section of pre-cast pile: 250mmx250mm

Note : Rates of all items should be inclusive of all supply and carriage.

m

409.74

Add +15.00% with Item No 5.23.14.02.1

Page: 1610 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.23.14.03.1

2 0m to 6m depth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m H.C. of pre-cast pile driving complete rig set

0.0278

day

10500.00

291.90

Rig Operator

0.0417

day

600.00

25.02

Skilled Labour

0.0417

day

450.00

18.77

Ordinary Labour

0.3333

day

370.00

123.32 459.01

Subtotal-A: Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

22.95

Subtotal-A1: Subtotal-B: Subtotal-C:

481.96 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

491.60

10% Profit ( Add 10% on Subtotal-B) :

540.75

VAT

6% of Total

IT

4% of Total

36.05 24.03 Total:

5.23.14.03.2 5.23.14.04

6m and above depth

m

600.84

Add +15.00% with Item No 5.23.14.03.1

X-section of pre-cast pile: 300mmx300mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1611 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.23.14.04.1

2 0m to 6m depth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m H.C. of pre-cast pile driving complete rig set

0.0303

day

10500.00

318.15

Rig Operator

0.0483

day

600.00

28.98

Skilled Labour

0.0625

day

450.00

28.13

Ordinary Labour

0.4167

day

370.00

154.18 529.43

Subtotal-A: Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

26.47

Subtotal-A1: Subtotal-B: Subtotal-C:

555.91 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

567.02

10% Profit ( Add 10% on Subtotal-B) :

623.73

VAT

6% of Total

IT

4% of Total

41.58 27.72 Total:

5.23.14.04.2 5.23.14.05

6m and above depth

m

693.03

Add +15.00% with Item No 5.23.14.04.1

X-section of pre-cast pile: 350mmx350mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1612 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 5.23.14.05.1

2 0m to 6m depth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m H.C. of pre-cast pile driving complete rig set

0.0333

day

10500.00

349.65

Rig Operator

0.0556

day

600.00

33.36

Skilled Labour

0.0833

day

450.00

37.49

Ordinary Labour

0.5000

day

370.00

185.00 605.50

Subtotal-A: Preparation of Driving Log & Other Charges

( +5.00 % on Subtotal-A )

30.27

Subtotal-A1: Subtotal-B: Subtotal-C:

635.77 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

648.49

10% Profit ( Add 10% on Subtotal-B) :

713.33

VAT

6% of Total

IT

4% of Total

47.56 31.70 Total:

5.23.14.05.2

6m and above depth

5.24.01

Sub-soil InvestigationExcept in special cases as deemed by the authority sub-soil exploration and testing to be executed only by the agencies having experience in the relevant field. Numbers and depth of Bore hole including necessary tests to be carried out as per advice of E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

m

792.59

Add +15.00% with Item No 5.23.14.05.1

Page: 1613 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.24.01.01

Detailed Analysis Brief Description of Item 2 Mobilization and demobilization of boring equipment such as drilling rig, drilling pipes, drop hammer, tripod, pulley, chain, Wrench, sample collection devices tool and plants, tripod for temporary camp, other accessories and manpower at work site etc. all complete and accepted by the Engineer (with flat body truck for mounting Rig equipment).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

site

H.C. of Flat Body Truck (5 tons)

1.0000

day

3000.00

3000.00

Foreman

1.0000

day

800.00

800.00

Rig Operator

1.0000

day

600.00

600.00

Rig Operator Helper

6.0000

day

400.00

2400.00 6800.00

Subtotal-A: Camp Ofice, conveyance, etc.

( +45.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

9860.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10057.20

10% Profit ( Add 10% on Subtotal-B) :

11062.92

VAT

6% of Total

737.53

IT

4% of Total

491.69 Total:

5.24.01.02

Field visit and inspection of sampling and samples by the Geo-tech. Expert/ Engineer

12292.13

site Geo-tech Expert/Engineer

1.0000

day

1800.00

Subtotal-B: Subtotal-C:

1800.00 1800.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1836.00

10% Profit ( Add 10% on Subtotal-B) :

2019.60

VAT

6% of Total

134.64

IT

4% of Total

89.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3060.00

2244.00

Page: 1614 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

5.24.01.03

Erection and Placement of Boring equipment at site as acceptable to the Engineer.

5.24.01.03.1

On dry ground or a site with 0-0.75m depth of water

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

point Foreman

0.2500

day

800.00

200.00

Rig Operator

0.2500

day

600.00

150.00

Rig Operator Helper

1.5000

day

400.00

600.00 950.00

Subtotal-A: Consumable item etc.

( +110.00 % on Subtotal-A )

Subtotal-A1:

1995.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2034.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2238.39

VAT

6% of Total

IT

4% of Total

149.23 99.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1045.00

2487.10

Page: 1615 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.24.01.03.2

Detailed Analysis Brief Description of Item 2 A site with water depth between 0.75m and 3m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

point Foreman

0.2500

day

800.00

200.00

Rig Operator

0.2500

day

600.00

150.00

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

0.5000

day

370.00

185.00

H.C. of Engine Boat

1.0000

day

1000.00

1000.00

Jute Rope

2.0000

kg

120.00

240.00

14.1700

m

42.00

595.14

Borak Bamboo (75mm to 100mm)

3045.14

Subtotal-A: Wooden plank, T&P, consumable materials, etc.

( +50.00 % on Subtotal-A )

Subtotal-A1:

4567.71

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4659.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5124.97

VAT

6% of Total

IT

4% of Total

341.66 227.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1522.57

5694.41

Page: 1616 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.24.01.03.3

Detailed Analysis Brief Description of Item 2 A site with water depth above 3m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

point Foreman

0.2500

day

800.00

200.00

Rig Operator

0.2500

day

600.00

150.00

Skilled Labour

1.5000

day

450.00

675.00

Ordinary Labour

0.5000

day

370.00

185.00

H.C. of Engine Boat

1.0000

day

1000.00

1000.00

Jute Rope

5.0000

kg

120.00

600.00

13.7500

m

42.00

577.50

0.0625

each

300.00

18.75

Borak Bamboo (75mm to 100mm) Empty Bitumen Drum

3406.25

Subtotal-A: Wooden plank, T&P, consumable materials, etc.

( +40.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

4768.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4864.13

10% Profit ( Add 10% on Subtotal-B) :

5350.54

VAT

6% of Total

IT

4% of Total

356.70 237.80 Total:

5.24.01.04

1362.50

5945.04

Drilling 100mm dia bore-hole by wash boring method in connection with conducting standard penetration test (SPT) as directed and accepted by the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1617 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.24.01.04.1

2 Depth 0 to 9 meter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m H.C. of Rig

0.0440

day

8580.00

377.52

Foreman

0.0220

day

800.00

17.60

Rig Operator

0.0220

day

600.00

13.20

Rig Operator Helper

0.1330

day

400.00

53.20 461.52

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

470.75

10% Profit ( Add 10% on Subtotal-B) :

517.83

VAT

6% of Total

IT

4% of Total

34.52 23.01 Total:

5.24.01.04.2

Depth 9 to 18 meter

m H.C. of Rig

0.0480

day

8580.00

411.84

Foreman

0.0240

day

800.00

19.20

Rig Operator

0.0240

day

600.00

14.40

Rig Operator Helper

0.1470

day

400.00

58.80 504.24

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

514.32

10% Profit ( Add 10% on Subtotal-B) :

565.76

VAT

6% of Total

IT

4% of Total

37.72 25.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

575.36

628.62

Page: 1618 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.24.01.04.3

2 Depth 18 to 27 meter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m H.C. of Rig

0.0530

day

8580.00

454.74

Foreman

0.0300

day

800.00

24.00

Rig Operator

0.0300

day

600.00

18.00

Rig Operator Helper

0.1600

day

400.00

64.00 560.74

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

571.95

10% Profit ( Add 10% on Subtotal-B) :

629.15

VAT

6% of Total

IT

4% of Total

41.94 27.96 Total:

5.24.01.04.4

Depth 27 to 36 meter

m H.C. of Rig

0.0580

day

8580.00

497.64

Foreman

0.0400

day

800.00

32.00

Rig Operator

0.0400

day

600.00

24.00

Rig Operator Helper

0.1770

day

400.00

70.80 624.44

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

636.93

10% Profit ( Add 10% on Subtotal-B) :

700.62

VAT

6% of Total

IT

4% of Total

46.71 31.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

699.06

778.47

Page: 1619 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.24.01.04.5

2 Depth 36 to 45 meter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m H.C. of Rig

0.0640

day

8580.00

549.12

Foreman

0.0320

day

800.00

25.60

Rig Operator

0.0320

day

600.00

19.20

Rig Operator Helper

0.1930

day

400.00

77.20 671.12

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

684.54

10% Profit ( Add 10% on Subtotal-B) :

753.00

VAT

6% of Total

IT

4% of Total

50.20 33.47 Total:

5.24.01.04.6

Depth above 45 meter

m H.C. of Rig

0.0710

day

8580.00

609.18

Foreman

0.0350

day

800.00

28.00

Rig Operator

0.0350

day

600.00

21.00

Rig Operator Helper

0.2200

day

400.00

88.00 746.18

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

761.10

10% Profit ( Add 10% on Subtotal-B) :

837.21

VAT

6% of Total

IT

4% of Total

55.81 37.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

836.66

930.24

Page: 1620 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

5.24.01.05

Execution of SPT at 1500mm interval with Standard Automatic Hammer (ASTM D-1586-84, hammer: (140 ± 2 lbs)/(63.5 ± 1 Kg), height of fall: (30˝ ± 1˝)/ (760mm ± 25mm) including withdrawn of drilling pipe from the bore-hole and fixing the steel cap with drilling pipe and replacing the drilling pipe with cap into the bore hole up to the layer of interest approved and accepted by the Engineer.

5.24.01.05.1

Depth 0 to 9 meter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Foreman

0.0130

day

800.00

10.40

Rig Operator

0.0130

day

600.00

7.80

Rig Operator Helper

0.0800

day

400.00

32.00 50.20

Subtotal-A: All other remaining cost

( +7.00 % on Subtotal-A ) ( +7.00 % on Subtotal-A )

3.51 3.51

Subtotal-A1: Subtotal-B: Subtotal-C:

57.23 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58.37

10% Profit ( Add 10% on Subtotal-B) :

64.21

VAT

6% of Total

IT

4% of Total

4.28 2.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

71.34

Page: 1621 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.24.01.05.2

2 Depth 9 to 18 meter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Foreman

0.0140

day

800.00

11.20

Rig Operator

0.0140

day

600.00

8.40

Rig Operator Helper

0.0870

day

400.00

34.80 54.40

Subtotal-A: All other remaining cost

( +9.00 % on Subtotal-A )

4.90

Subtotal-A1:

59.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

60.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

66.53

VAT

6% of Total

IT

4% of Total

4.44 2.96 Total:

5.24.01.05.3

Depth 18 to 27 meter

m Foreman

0.0150

day

800.00

12.00

Rig Operator

0.0150

day

600.00

9.00

Rig Operator Helper

0.0950

day

400.00

38.00 59.00

Subtotal-A: All other remaining cost

( +9.00 % on Subtotal-A )

5.31

Subtotal-A1: Subtotal-B: Subtotal-C:

64.31 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

65.60

10% Profit ( Add 10% on Subtotal-B) :

72.16

VAT

6% of Total

IT

4% of Total

4.81 3.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

73.92

80.17

Page: 1622 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.24.01.05.4

2 Depth 27 to 36 meter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Foreman

0.0210

day

800.00

16.80

Rig Operator

0.0210

day

600.00

12.60

Rig Operator Helper

0.1230

day

400.00

49.20 78.60

Subtotal-A: All other remaining cost

( +7.00 % on Subtotal-A )

5.50

Subtotal-A1:

84.10

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

85.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

94.36

VAT

6% of Total

IT

4% of Total

6.29 4.19 Total:

5.24.01.05.5

Depth 36 to 45 meter

m Foreman

0.0250

day

800.00

20.00

Rig Operator

0.0250

day

600.00

15.00

Rig Operator Helper

0.1500

day

400.00

60.00 95.00

Subtotal-A: All other remaining cost

( +5.00 % on Subtotal-A )

4.75

Subtotal-A1: Subtotal-B: Subtotal-C:

99.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

101.75

10% Profit ( Add 10% on Subtotal-B) :

111.92

VAT

6% of Total

IT

4% of Total

7.46 4.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

104.85

124.36

Page: 1623 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 5.24.01.05.6

2 Depth above 45 meter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Foreman

0.0270

day

800.00

21.60

Rig Operator

0.0270

day

600.00

16.20

Rig Operator Helper

0.1670

day

400.00

66.80 104.60

Subtotal-A: All other remaining cost

( +5.00 % on Subtotal-A )

5.23

Subtotal-A1:

109.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

112.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

123.23

VAT

6% of Total

IT

4% of Total

8.22 5.48 Total:

5.24.01.06

Collection of undisturbed soil samples in 75mm tubes from cohesive layer including preservation, transportation to the laboratory and testing as directed and accepted by the Engineer. (ASTM D-1587-83)

sample

Lab Assistant

0.2700

day

1000.00

270.00 270.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

275.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

302.94

VAT

6% of Total

20.20

IT

4% of Total

13.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

136.92

336.60

Page: 1624 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

5.24.01.07

Collection of disturbed soil samples in 38mm tubes including preservation, and transportation to the laboratory and testing as directed and accepted by the Engineer. (ASTM D-1586-83)

sample

Lab Assistant

Quantity 5

0.1300

Unit

Rate

6

7

day

Amount 8

1000.00

130.00

Subtotal-A: Subtotal-B: Subtotal-C:

5.24.01.08

Preparation, writing and submission of report on sub-soil investigation containing all parameters, bearing capacities, sections of boreholes on two or more sets of data given or assumed, citing reference (Bench mark and GPS location) etc. and all complete as per satisfaction and direction of Engineer-in-charge.

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.60

10% Profit ( Add 10% on Subtotal-B) :

145.86

VAT

6% of Total

IT

4% of Total

9.72 6.48 Total:

162.07

site

Foundation Engineer

1.0000

day

1800.00

1800.00

Computer Operator

1.0000

day

570.00

570.00 2370.00

Subtotal-A: Paper, spiral binding, consumable articals and submission of report, etc.

( +70.00 % on Subtotal-A )

Subtotal-A1:

1659.00 4029.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4109.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4520.54

VAT

6% of Total

IT

4% of Total

301.37 200.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

130.00

5022.82

Page: 1625 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

5.24.02

Conducting Electronic Cone Penetration Test with pore pressure measurement, dissipation test as per ASTM D 5778 method upto 50m depth to measure friction angle, undrained shear strength, tipresistance,skin friction , Relative density, pore pressure etc. (The Testing Party will be selected taking prior approval of Procuring Entity)

5.24.02.01

Test on ground surface

nos

5.24.02.02

Test under water

nos

5.24.03

Sub-soil investigation at the actual locations of each building foundation positions in accordance with the specifications of ASTM D 1586 and D 1587. The bore holes shall have a minimum diameter of 100mm and shall be lined throughout and shall be minimum 30m to 45m deep or to a depth as specified in the ASTM/AASHTO or as directed by the E-I-C from the existing GL and taking all cautions and steps to collect the disturbed and undisturbed samples and making the bore holes. The item is inclusive of mobilization & demobilization, proper method of borings, arrangement of boat/barge all cost of materials, labourers, field and laboratory tests including report and records. (The Testing Party will be selected taking prior approval of Procuring Entity)

5.24.03.01

Test on ground surface

nos

5.24.03.02

Test under water

nos

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1626 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying and mixing specified type chemical admixture delivered from an authorized local agent or manufacturer, comply with the ASTM C-494 requirements, confirming the current compliance of the admixture to specification requirements like physical properties, uniformity and equivalence in composition etc., performance (water content, fresh concrete setting time and compressive strength) requirements, delivered in sealed water-tight containers having and confirming plainly marked the proprietary name of the admixture type under this specification, net weight and /or volume, manufacturing and expiry date, non aggressiveness to environment, aggregates and metals in concrete etc. and mixing the admixture in non pre-stressed cement concrete mixture in the field under the strict accordance with manufacturers recommendation and instruction, providing safety provisions in all respects etc. all complete as per instruction and approved by the E-I-C. Dose (quantity in milliliters per 50 kg bag cement) and brand/origin/ manufacturer with respect to particular brand of cement and particular stock of aggregates and method of use to be determined by mix design / trial mix at the cost borne by the Contractor and approved by the E-I-C. (Use of admixture is subject to prior approval of Design unit of LGED)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1627 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.01.01

Detailed Analysis Brief Description of Item 2 Supply and use of water reducing chemical admixture in concrete, complying ASTM C-494 Type - A of approved brand / origin / manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin : The admixture is to reduce quantity of mixing water required for normal workability and to maintain low water-cement (W/C) ratio, for improved concrete quality ensuarance.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

130.00

130.00

litre

Water reducing chemical admixture : Type-A

1.0000

liter

130.00

Subtotal-A: All other cost with mixing & sundrise etc.

( +4.00 % on Subtotal-A )

5.20

Subtotal-A1: Subtotal-B: Subtotal-C:

135.20 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

137.90

10% Profit ( Add 10% on Subtotal-B) :

151.69

VAT

6% of Total

IT

4% of Total

10.11 6.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

168.55

Page: 1628 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.01.02

Detailed Analysis Brief Description of Item 2 Supply and use of retarding chemical admixture in concrete, complying ASTM C-494 Type - B of approved brand/origin/manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin :The admixture for retarding setting time of concrete, there by reducing shrinkage in concrete specially for concrete laid in thick layers and intended delayed construction for improved construction joints, reconcreting etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

125.00

125.00

litre

Retrading chemical admixture : Type-B

1.0000

liter

125.00

Subtotal-A: All other cost with mixing & sundrise etc.

( +4.00 % on Subtotal-A )

5.00

Subtotal-A1:

130.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145.86

VAT

6% of Total

9.72

IT

4% of Total

6.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

162.07

Page: 1629 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.01.03

Detailed Analysis Brief Description of Item 2 Supply and use of accelerating chemical admixture in concrete, complying ASTM C-494 Type - C of approved brand/origin/manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin : An admixture that is to accelerate the setting time and early strength gain of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

135.00

135.00

litre

Accelerating chemical admixture : Type-C

1.0000

liter

135.00

Subtotal-A: All other cost with mixing & sundrise etc.

( +4.00 % on Subtotal-A )

5.40

Subtotal-A1:

140.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

143.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

157.53

VAT

6% of Total

10.50

IT

4% of Total

7.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

175.03

Page: 1630 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.01.04

Detailed Analysis Brief Description of Item 2 Supply and use of water-reducing and retarding chemical admixture in concrete, complying ASTM C-494 Type - D of approved brand / origin / manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin : The admixture to reduce the quantity of mixing water required to produce concrete of given consistency, i.e. low water-cement (W/C) ratio and intend to retard setting time of concrete, specially for layered, thick laid concrete etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

125.00

125.00

litre

Water-reducing and retrading chemical admixture : Type-D

1.0000

liter

125.00

Subtotal-A: All other cost with mixing & sundrise etc.

( +4.00 % on Subtotal-A )

5.00

Subtotal-A1:

130.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145.86

VAT

6% of Total

9.72

IT

4% of Total

6.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

162.07

Page: 1631 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.01.05

Detailed Analysis Brief Description of Item 2 Supply and use of water-reducing and accelerating chemical admixture in concrete, complying ASTM C-494 Type - E of approved brand / origin / manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin : The admixture to reduce the quantity of mixing water required to produce concrete of given consistency, i.e. low water-cement (W/C) ratio and intend to accelerate setting time of concrete, and early strength gain in concrete etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

135.00

135.00

litre

Water-reducing and accelerating chemical admixture : Type-E

1.0000

liter

135.00

Subtotal-A: All other cost with mixing & sundrise etc.

( +4.00 % on Subtotal-A )

5.40

Subtotal-A1:

140.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

143.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

157.53

VAT

6% of Total

10.50

IT

4% of Total

7.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

175.03

Page: 1632 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.01.06

Detailed Analysis Brief Description of Item 2 Supply and use of water-reducing high range chemical admixture in concrete, complying ASTM C-494 Type - F of approved brand / origin / manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin : The admixture required to produce concrete of consistency by 12% or greater (flowing concrete) and for higher strength of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

160.00

160.00

litre

Water-reducing high range chemical admixture : Type-F

1.0000

liter

160.00

Subtotal-A: All other cost with mixing & sundrise etc.

( +4.00 % on Subtotal-A )

6.40

Subtotal-A1: Subtotal-B: Subtotal-C:

166.40 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.73

10% Profit ( Add 10% on Subtotal-B) :

186.70

VAT

6% of Total

IT

4% of Total

12.45 8.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

207.45

Page: 1633 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.01.07

Detailed Analysis Brief Description of Item 2 Supply and use of water-reducing high range and retarding chemical admixture in concrete, complying ASTM C-494 Type - G of approved brand / origin/manufacturer and supplied by only manufacturer's authorised dealer with certificate of origin :The admixture required to produce concrete of consistency by 12% or greater (flowing concrete) and for higher strength of concrete and intend to retard setting time of concrete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

160.00

160.00

litre

Water-reducing high range and retrading chemical admixture : Type-G

1.0000

liter

160.00

Subtotal-A: All other cost with mixing & sundrise etc.

( +4.00 % on Subtotal-A )

6.40

Subtotal-A1: Subtotal-B: Subtotal-C:

166.40 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.73

10% Profit ( Add 10% on Subtotal-B) :

186.70

VAT

6% of Total

IT

4% of Total

12.45 8.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

207.45

Page: 1634 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, best quality pliable, cold applied pre-formed self adhesive rubberized/ bituminous water proofing membrane of approved brand / origin / manufacturer from an authorized local agent or manufacturer having minimum thickness 1.5 mm, lined with 2 ply cross laminated high density polyethylene film performances and properties all conforming to ASTM standards and laying, placing, fixing on made up firm and dry surfaces free from hollows, sharp protrusions, contaminates etc. laid over-lap by at least 75 mm along the edges and 125 mm at ends ensuring good initial bond with the surfaces all complete under the strict accordance with the manufacturer recommendations and instructions providing all safety provisions in all respects and accepted by the E-I-C. (supplied by only manufacturer's authorised dealer with certificate of origin ) under following specification: Backing (HDPE) thickness : minimum 0.10mm Membrane thickness : minimum 1.40mm Total thickness : minimum 1.50mm Cold flexibility greater than (-)200C : ASTM D146 Pilability : “No crack” tested in ASTM D146 Tensile strength (film only) : min 3.50MPa (35000KN/m2) testing in ASTM D882 Tensile strength (composite) : at least 2.40 MPa or N/mm2 Elongation (composite) : min 300% Cycling Ove Crack at (-)320C : No effect 100 cycles ASTM C836-89a. Puncture Resistance greater than 240N ASTME 154-88 Resistance to hydrostatic Head at least 50m ASTM D5385 Tear resistance min 4.0 MPa (N/mm2) Adhesion to primed concrete min 4.0N/mm: ASTM D1000 Water vapor Transmission less than 0.10g/m2 per hour : ASTM E96 Water absorption in 24 hour |less than 33% ASTM D570 Heat stability (+)900C Environmental Compliance to conform : ASTM D543

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1635 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.02.01

Detailed Analysis Brief Description of Item 2 Water-proofing membrane on external surface of primed vertical or inclined wall /on plastered and primed back-wall and concrete cast against membrane.(Excluding cost of back fill/brick wall on back/plaster when membrane laid on back-wall and concrete cast against membrane which to be paid as per corresponding items in this schedule)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Primer for bonding

0.1000

liter

450.00

45.00

Water proofing membrane

1.1000

sqm

485.00

533.50

Foreman

0.0500

day

800.00

40.00

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.1000

day

370.00

37.00 678.00

Subtotal-A: All other remaining costs, tools, plants, sundries etc

( +1.80 % on Subtotal-A )

12.20

Subtotal-A1:

690.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

704.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

774.41

VAT

6% of Total

IT

4% of Total

51.63 34.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

860.45

Page: 1636 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.02.02

Detailed Analysis Brief Description of Item 2 Water-proofing membrane on made up surface below the floor or below the horizontal surfaces with temporary protective cover using polysterene/1.5" thick sand-cement mortar in 4:1 /or by equally effective alternative. (Rate is excluding the cost of protective cover which to be paid as per corresponding items in this schedule)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Water proofing membrane

1.1000

sqm

485.00

533.50

Foreman

0.0250

day

800.00

20.00

Skilled Labour

0.0250

day

450.00

11.25

Ordinary Labour

0.0500

day

370.00

18.50 583.25

Subtotal-A: All other remaining costs, tools, plants, sundries etc

( +1.70 % on Subtotal-A )

9.92

Subtotal-A1: Subtotal-B: Subtotal-C:

593.17 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

605.03

10% Profit ( Add 10% on Subtotal-B) :

665.53

VAT

6% of Total

44.37

IT

4% of Total

29.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

739.48

Page: 1637 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.02.03

Detailed Analysis Brief Description of Item 2 Water-proofing membrane on the floor or on the horizontal surfaces with permanent protective cover & wearing coarse. (Rate is excluding the cost of protective cover and wearing coarse which to be paid as per corresponding items in this schedule)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Water proofing membrane

1.1500

sqm

485.00

557.75

Foreman

0.0250

day

800.00

20.00

Skilled Labour

0.0250

day

450.00

11.25

Ordinary Labour

0.0500

day

370.00

18.50 607.50

Subtotal-A: All other remaining costs, tools, plants, sundries etc

( +1.70 % on Subtotal-A )

10.33

Subtotal-A1:

617.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

630.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

693.20

VAT

6% of Total

46.21

IT

4% of Total

30.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

770.22

Page: 1638 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.03.01

Detailed Analysis Brief Description of Item 2 Anti-Salinity and Damp Profooing Admixture for 12mm thick cement Plastering Work in proportion (1:6) on new surface: Supplying and applying specified type of chemicals such as Desalt-S01 and Foam-Lub or equivalent admixture, confirming the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. for treatment of anti-salinity, water & damp proofing, getting high work-abilities, better compatibility, vibration tolerance, void & porosity reducing, partially auto curing, etc. at inside, outside brick wall and concrete faces. Prepare a mixture with the proportion of 1 liter Desalt-S01, 10 liter Water and 25ml or 1 div Catalyst. Cleaning the surface properly and apply one coat of Desalt-S01 mixture with a jute brush or spray over the exposed concrete or brick surface (before plaster). Use the mixture within 2 hours of preparation. After that, prepare sand-cement mortar for plastering work using admixture as Foam-lub 250ml with 50kg cement. Initially 250ml Foam-lub for 1bag cement is to be mixed with required amount of water which will be used in preparation of sand cement mortar or doges mentioned in the manufacturer’s brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. all complete as per direction of the E-I-C. (Excluding cost of Plastering Work).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Desalt-S01

0.0358

liter

370.00

13.25

Foam Lub

0.0182

liter

245.00

4.46

Skilled Labour

0.0100

day

450.00

4.50 22.21

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24.91

VAT

6% of Total

1.66

IT

4% of Total

1.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

27.68

Page: 1639 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.03.02

Detailed Analysis Brief Description of Item 2 Anti-Salinity and Damp Profooing Admixture for 12mm thick cement Plastering Work in proportion (1:4) on new surface: Supplying and applying specified type of chemicals such as Desalt-S01 and Foam-Lub or equivalent admixture, confirming the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. for treatment of anti-salinity, water & damp proofing, getting high work-abilities, better compatibility, vibration tolerance, void & porosity reducing, partially auto curing, etc. at inside, outside brick wall and concrete faces. Prepare a mixture with the proportion of 1 liter Desalt-S01, 10 liter Water and 25ml or 1 div Catalyst. Cleaning the surface properly and apply one coat of Desalt-S01 mixture with a jute brush or spray over the exposed concrete or brick surface (before plaster). Use the mixture within 2 hours of preparation. After that, prepare sand-cement mortar for plastering work using admixture as Foam-lub 250ml with 50kg cement. Initially 250ml Foam-lub for 1bag cement is to be mixed with required amount of water which will be used in preparation of sand cement mortar or doges mentioned in the manufacturer’s brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. all complete as per direction of the E-I-C. (Excluding cost of Plastering Work).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Desalt-S01

0.0358

liter

370.00

13.25

Foam Lub

0.0245

liter

245.00

6.00

Skilled Labour

0.0100

day

450.00

4.50 23.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26.65

VAT

6% of Total

1.78

IT

4% of Total

1.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

29.61

Page: 1640 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.03.03

Detailed Analysis Brief Description of Item 2 Anti-Salinity and Damp Profooing Admixture for 6mm thick cement Plastering Work in proportion (1:4) on new surface: Supplying and applying specified type of chemicals such as Desalt-S01 and Foam-Lub or equivalent admixture, confirming the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. for treatment of anti-salinity, water & damp proofing, getting high work-abilities, better compatibility, vibration tolerance, void & porosity reducing, partially auto curing, etc. at inside, outside brick wall and concrete faces. Prepare a mixture with proportion of 1 liter Desalt-S01, 10 liter Water and 25ml or 1 div Catalyst. Cleaning the surface properly and apply one coat of Desalt-S01 mixture with a jute brush or spray over the exposed concrete or brick surface (before plaster). Use the mixture within 2 hours of preparation. After that, prepare sand-cement mortar for plastering work using admixture as Foam-lub 250ml with 50kg cement. Initially 250ml Foam-lub for 1bag cement is to be mixed with required amount of water which will be used in preparation of sand cement mortar or doges mentioned in the manufacturer’s brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. all complete as per direction of the E-I-C. (Excluding cost of Plastering Work).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Desalt-S01

0.0358

liter

370.00

13.25

Foam Lub

0.0127

liter

245.00

3.11

Skilled Labour

0.0100

day

450.00

4.50 20.86

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

23.40

VAT

6% of Total

1.56

IT

4% of Total

1.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

26.00

Page: 1641 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.03.04

Detailed Analysis Brief Description of Item 2 Anti-Salinity and Damp Profooing Admixture for Rule Pointing Work in proportion (1:2) on new surface: Supplying and applying specified type of chemicals such as Desalt-S01 and Foam-Lub or equivalent admixture, confirming the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. for treatment of anti-salinity, water & damp proofing, getting high work-abilities, better compatibility, vibration tolerance, void & porosity reducing, partially auto curing, etc. at inside and outside brick wall. Prepare a mixture with the proportion of 1 liter Desalt-S01, 10 liter Water and 25ml or 1 div Catalyst. Cleaning the surface properly and apply one coat of Desalt-S01 mixture with a jute brush or spray over the exposed concrete or brick surface (before pointing work). Use the mixture within 2 hours of preparation. After that, prepare sand-cement mortar for pointing work using admixture as Foam-lub 250ml with 50kg cement. Initially 250ml Foam-lub for 1bag cement is to be mixed with required amount of water which will be used in preparation of sand cement mortar or doges mentioned in the manufacturer’s brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. all complete as per direction of the E-I-C. (Excluding cost of Pointing Work).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Desalt-S01

0.0358

liter

370.00

13.25

Foam Lub

0.0135

liter

245.00

3.31

Skilled Labour

0.0100

day

450.00

4.50 21.05

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21.47

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

23.62

VAT

6% of Total

1.57

IT

4% of Total

1.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

26.25

Page: 1642 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.03.05

Detailed Analysis Brief Description of Item 2 Chemical for fair Face Treatment on sand, stones, ceramics & ordinary brick works: Supplying and applying specified type of chemicals such as Desalt-S01 and Hydro-Seal, Ef-34 or equivalent chemical, confirming the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. to prevent salinity, water absorption, growth of algae etc. on normal exposed fair face brick, ceramics and sand stone surface. First of all prepare a mixture with the proportion of 1 liter Desalt-S01, 10 liter Water and 25ml or 1 div Catalyst. Cleaning the surface properly and apply one coat of Desalt-S01 mixture with a jute brush or spray over the surface. Use the mixture within 2 hours of preparation. After 12 hours of application of desaltS01 mixture, cleaning the surface with soft brush and water and wait minimum 4 days for drying the surface. On dried up surface, applying first coat of Hydro-Seal, Ef-34 mixture with jute brush, preparing the mixture with the proportion of 1 liter Hydro-Seal Ef-34, 6 liter water and 25 ml or 1 div mark T. catalyst. Applying second coat of Hydro-Seal, Ef34 mixture after 01 day of first coat with jute brush on the same dried surface, preparing the mixture with the proportion of 1 liter Hydro-Seal Ef-34, 5 liter water and 25 ml or 1 div mark T. catalyst. Finally, applying third coat of Hydro-Seal, Ef-34 mixture after 01 day of second coat with jute brush on the same dried surface following same mixing proportion of second coat or doges mentioned in the manufacturer’s brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Desalt-S01

0.0358

liter

370.00

13.25

Hydro-Seal Ef-34

0.0718

liter

518.00

37.19

Skilled Labour

0.1076

day

450.00

48.42 98.86

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

110.92

VAT

6% of Total

IT

4% of Total

7.39 4.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

123.24

Page: 1643 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.03.06

Detailed Analysis Brief Description of Item 2 Water Profooing & Heat Reducing Admixture for Concrete Screeding over Roof Slab : Supplying and applying specified type of chemicals such as Desalt-S01 and Foam-Lub (Meta) or equivalent admixture, confirming the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. for treatment of water & damp proofing, heat reducing, shrinkage factor controlling of heat of hydration and other thermal affecting factors, thermal insulation, controlling setting time, getting high work-abilities, better compatibility, vibration tolerance, void & porosity reducing, partially auto curing, etc. at roof top of building. First of all prepare a mixture with the proportion of 1 liter Desalt-S01, 10 liter Water and 25ml or 1 div Catalyst. Cleaning the surface properly and apply one coat of Desalt-S01 mixture with a jute brush or spray over the roof surface. Use the mixture within 2 hours of preparation. Secondly, prepare another mixture of curdy-dense grout and apply it before applying patent stone with the proportion of 2 liters Foam-Lub (Meta), 40 liters Water and 1 bag or 50 kg cement. Apply one coat of prepared curdy-dense grout with a broom on all over the roof surface. Finally prepare patent stone concrete/concrete screeding using 500ml Foam-lub (Meta) with 50kg cement. Initially 500ml Foam-lub (meta) for 1bag cement is to be mixed with required amount of water which will be used in preparation of patent stone concrete or doges mentioned in the manufacturer’s brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. all complete as per direction of the E-I-C. (Excluding cost of 38mm thick Concrete Screeding (1:1.5:3)).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Desalt-S01

0.0358

liter

370.00

13.25

Foam Lub (Meta)

0.2185

liter

245.00

53.53

Ordinary Portland Cement (CEM I, 52.5N)

0.0358

bag

455.00

16.29

Skilled Labour

0.0240

day

450.00

10.80 93.87

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

95.74 105.32 7.02 4.68

Total: Note : Rates of all items should be inclusive of all supply and carriage.

117.02

Page: 1644 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1645 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.03.07

Detailed Analysis Brief Description of Item 2 Anti Salinity and damp proofing Plaster treatment : Supplying and applying specified type of chemicals such as Desalt-S01 and Foam-Lub or equivalent Chemicals, confirming to the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. for treatment of anti-salinity, water & damp proofing, getting high work-abilities, vibration tolerance, void & porosity reducing, partially auto curing etc. at inside & outside brick wall and concrete faces. Prepare a mixture in proportion of 1 liter of Desalt-S01 or equivalent Chemicals, 10 liter water and 25 ml or 1 div catalyst. Apply one coat of the mixture within 2 hours of preparation on exposed concrete surface/brick walls with a jute brush. Prepare a mixture of Curdy-Dense Foam-Lub or equivalent Cement Grout in proportion of 2 liters Foam-Lub or equivalent, 35 liters of water and 50 kgs cement. Apply 3 coats of prepared Cement Grout with a jute brush on the brick walls/concrete surfaces at an interval of 6 hours. Sand- Cement plaster work will be started before drying of 3rd coat of curdy-dense Foam-Lub or equivalent cement grout. Prepare sand-cement mortar for plastering work using admixture as Foam-Lub or equivalent 500 ml with 50 kg cement following procedure as 500 ml of Foam-Lub or equivalent is to be mixed with required amount of water to be used for 1 bag Cement. This mixture will be used in preparation of sand cement mortar or doges mentioned in the manufacturer's brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. All complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Desalt-S01

0.0358

liter

370.00

13.25

Foam Lub (Meta)

0.1829

liter

245.00

44.81

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0538

bag

430.00

23.13

Skilled Labour

0.0753

day

450.00

33.89 115.08

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

117.38

10% Profit ( Add 10% on Subtotal-B) :

129.11

VAT

6% of Total

IT

4% of Total

8.61 5.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

143.46

Page: 1646 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.25.03.08

Detailed Analysis Brief Description of Item 2 Chemical for Water & Damp Proofing Basement Floor or Ground Floor or Retaining walls or Water Reservoirs or Water Tank or ETP or WETP or Drain Concreting etc where required incleding supplying and applying specified type of chemicals such as Foam-Lub or equivalent, confirming the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. for the treatment of Water & Damp Proofing treatment, vibration tolerance, decreases the permeability of concrete, better compatibility, void & porosity reducing, shrinkage factor controlling of heat of hydration etc. Prepare concrete screening using 500 ml Foam-Lub with 50kg cement. Initially 500 ml Foam-Lub for 1 bag cement is to be mixed with required amount of water which will be used in preparation of concrete or doges mentioned in the manufacturer's brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc.all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

liter

Foam Lub

1.0000

liter

245.00

245.00

Skilled Labour

0.0100

day

450.00

4.50 249.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

254.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

279.94

VAT

6% of Total

18.66

IT

4% of Total

12.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

311.04

Page: 1647 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.01

Detailed Analysis Brief Description of Item 2 Preparation of pit by earth work in excavation of 600 x 600 x 450 mm size pit for plantation, applying cow dung mixing with loamy silty soil and excavated earth, planting the plants, tightened with 1800 mm long borrak bamboo post by jute rope including supply of tools and plants etc.all complete as per direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Cow dung

0.0300

cum

630.00

18.90

Silty Soil

0.0350

cum

235.00

8.23

Borak Bamboo (75mm to 100mm)

0.9500

m

42.00

39.90

Ordinary Labour

0.0700

day

370.00

25.90 92.93

Subtotal-A: All other remaining cost

( +5.00 % on Subtotal-A )

4.65

Subtotal-A1: Subtotal-B: Subtotal-C:

97.57 99.52

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

109.47

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

7.30

IT

4% of Total

4.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

121.64

Page: 1648 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.02

Detailed Analysis Brief Description of Item 2 Plantation bed Preparation by spading the ground in to a depth of 150 mm to 250 mm beyond 50 mm thick scrapped ground , breaking earth clods to powder by wooden hammers or by any other means, picking up all sorts of rubbish, grasses by required tools, carrying, spreading, levelling and dressing earth all the surface area including cost of tools and plants etc. all complete and accepted by the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

sqm

Ordinary Labour

0.0400

14.80

Subtotal-A: All other remaining costs covering tools, plants etc

( +5.00 % on Subtotal-A )

0.74

Subtotal-A1:

15.54

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15.85

10% Profit ( Add 10% on Subtotal-B) :

17.44

VAT

6% of Total

IT

4% of Total

1.16 0.77 Total:

5.26.03

Lawn surface preparation by scraping out up to 50 mm thick by suitable tool with picking up all sorts of bricks bats, rubbish etc by required tools and cleaning-removinga and stacking the same to preselected safe distance including cost of tools and plants etc. all complete and accepted by the Engineer.

19.37

sqm

Ordinary Labour

0.0200

day

370.00

7.40 7.40

Subtotal-A: All other remaining costs covering tools, plants etc

( +5.00 % on Subtotal-A )

0.37

Subtotal-A1:

7.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8.72

VAT

6% of Total

IT

4% of Total

0.58 0.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14.80

9.69

Page: 1649 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.04

Detailed Analysis Brief Description of Item 2 lawn area Preparation with leveling and dressing to proper slope and grade by spading the earth up to 150 mm thickness including cost tools and plants etc. all complete and accepted by the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

sqm

Ordinary Labour

0.0130

4.81

Subtotal-A: All other remaining costs covering tools, plants etc

( +10.00 % on Subtotal-A )

Subtotal-A1: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5.40

10% Profit ( Add 10% on Subtotal-B) :

5.94

VAT

6% of Total

IT

4% of Total

0.40 0.26

Subtotal-C:

Total: Alluvial loamy silty soil supplying cost by any means of approved local best quality including cost of labour for loading, unloading at both ends with properly stacking at site with cost of tools and plants etc. all complete and accepted by the Engineer.

6.60

cum

Silty Soil

1.0000

cum

235.00

235.00

Ordinary Labour

0.2000

day

370.00

74.00 309.00

Subtotal-A: All other remaining cost

( +5.00 % on Subtotal-A )

15.45

Subtotal-A1:

324.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

330.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

364.03

VAT

6% of Total

24.27

IT

4% of Total

16.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

0.48 5.29

Subtotal-B:

5.26.05

4.81

404.48

Page: 1650 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.06

Detailed Analysis Brief Description of Item 2 Spreading the alluvial loamy silty soil from the stacks at site on the lawn surface including cost labour for carring, spreading, leveling, dressing the same etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

122.10

cum

Ordinary Labour

0.3300

122.10

Subtotal-A: All other remaining cost

( +2.00 % on Subtotal-A )

2.44

Subtotal-A1:

124.54

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

127.03

10% Profit ( Add 10% on Subtotal-B) :

139.74

VAT

6% of Total

IT

4% of Total

9.32 6.21 Total:

5.26.07

Well decomposed cow dung supplying, including cost of carring by trucks or any other means with loading, unloading at both ends, stacking the same at the site in preselected place and cost of tools and plants etc. all complete and accepted by the Engineer.

cum

Cow dung

1.0000

cum

630.00

630.00

Ordinary Labour

0.2000

day

370.00

74.00 704.00

Subtotal-A: All other remaining charges

( +5.00 % on Subtotal-A )

35.20

Subtotal-A1:

739.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

753.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

829.38

VAT

6% of Total

55.29

IT

4% of Total

36.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

155.26

921.54

Page: 1651 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.08

Detailed Analysis Brief Description of Item 2 Mixing well decomposed cow dung with alluvial loamy silty soil including cost of labour for earth excavation, carring, mixing and removing the excess earth to safe distance with cost of tools and plants etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

114.70

cum

Ordinary Labour

0.3100

114.70

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

2.29

Subtotal-A1:

116.99

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

119.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

131.27

VAT

6% of Total

IT

4% of Total

8.75 5.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

145.85

Page: 1652 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.09

Detailed Analysis Brief Description of Item 2 Lawn grass supplying by truck or any other means of approved best quality and size including sorting the grass to proper size and quality with washing the grass, dibbling the grass @ 10 mm to 50 mm distance in both ways, water spreading the lawn area till the grass grown at least for two months after plantation, weeding the undesirable grass, mowing the lawn grass by lawn mower up to two months after plantation, applying urea fertilizer on the lawn surface @ 1 kg per 9.29 sqm including cost of tools and plants etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Lawn grass

1.0000

sqm

2.50

Urea Fertilizer

0.1020

kg

25.00

2.55

Ordinary Labour

0.1000

day

370.00

37.00 42.05

Subtotal-A: All other remaining costs

( +3.00 % on Subtotal-A )

1.26

Subtotal-A1: Subtotal-B: Subtotal-C:

43.31 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

44.18

10% Profit ( Add 10% on Subtotal-B) :

48.60

VAT

6% of Total

IT

4% of Total

3.24 2.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2.50

54.00

Page: 1653 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.10

Detailed Analysis Brief Description of Item 2 Flower bed preparation for Spading in pits up to 600 mm depth, remolding, picking up and placing and removing the spaded earth to a safe distance in pre-selected place including mixing well decomposed cow dung @ 1 cft per 6 cft of cutted earth and 20% loamy silty soil and 6 cft excavated soil and fill back the pit with cost of tools and plants etc.all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Cow dung

0.2500

cum

630.00

157.50

Silty Soil

0.2800

cum

235.00

65.80

Ordinary Labour

0.0700

day

370.00

25.90 249.20

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

12.46

Subtotal-A1:

261.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

266.89

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

293.58

VAT

6% of Total

IT

4% of Total

19.57 13.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

326.20

Page: 1654 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.11

Detailed Analysis Brief Description of Item 2 Hedge beds preparation by excavation of earth up to 300 mm depth, filling up the bed by a mixture of cow dung, loamy silty soil, cutted earth @ 1 cft cow dung manure per 6 cft of cutted earth and 20% loamy silty soil including cost of tools and plant etc.all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Cow dung

0.1000

cum

630.00

63.00

Silty Soil

0.1100

cum

235.00

25.85

Ordinary Labour

0.2000

day

370.00

74.00 162.85

Subtotal-A: All other remaining cost

( +2.00 % on Subtotal-A )

3.26

Subtotal-A1: Subtotal-B: Subtotal-C:

166.11 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.43

10% Profit ( Add 10% on Subtotal-B) :

186.37

VAT

6% of Total

IT

4% of Total

12.42 8.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

207.08

Page: 1655 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.12

Detailed Analysis Brief Description of Item 2 Borrak bamboo of 12.20 m long and 100 mm dia supply and carrying at site including loading and unloading at both end stacking the same at site in pre-selected place with cost of tools and plants etc.all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Borak Bamboo (75mm to 100mm)

1.0000

m

42.00

42.00

Subtotal-A: All other remaining cost

( +2.00 % on Subtotal-A )

0.84

Subtotal-A1:

42.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

43.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

48.07

VAT

6% of Total

IT

4% of Total

3.20 2.14 Total:

5.26.13

Muli bamboo of 7.62 m long and 50 mm to 62.5 mm dia supply and carrying at site including loading and unloading at both end, stacking the same at site in pre-selected place with cost of tools and plants etc.all complete as per direction of the E-I-C.

53.41

each

Muli Bamboo

1.0000

each

80.00

All other remaining cost

( +5.00 % on Subtotal-A )

4.00

Subtotal-A1: Subtotal-B: Subtotal-C:

80.00 80.00

Subtotal-A:

84.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

85.68

10% Profit ( Add 10% on Subtotal-B) :

94.25

VAT

6% of Total

IT

4% of Total

6.28 4.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

42.00

104.72

Page: 1656 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.14

Detailed Analysis Brief Description of Item 2 Providing Muli bamboo tree guard by 1200 mm long and 500 mm dia of best quality muli bamboo including supplying , preparation, fitting and fixing Muli bamboo split 2 mm in size having 75 mm x 75 mm a square holes with 2 mm wide bamboo splits strengthen with 4 Nos. 2 mm wide bamboo split in both sides tightened with G.I wire fitted with 3 Nos. 63 mm dia borrak bamboo post of 1800 mm long of which 600 mm will be driven into earth by digging hole followed by fill back including cost of tools and plants etc.all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Muli Bamboo

1.7000

each

80.00

136.00

Borak Bamboo (75mm to 100mm)

5.5000

m

42.00

231.00

GI Wire (22 BWG)

0.1000

kg

90.00

9.00

Skilled Labour

0.2000

day

450.00

90.00 466.00

Subtotal-A: All other remaining cost

( +5.00 % on Subtotal-A )

23.30

Subtotal-A1: Subtotal-B: Subtotal-C:

489.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

499.09

10% Profit ( Add 10% on Subtotal-B) :

548.99

VAT

6% of Total

IT

4% of Total

36.60 24.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

609.99

Page: 1657 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.15

Detailed Analysis Brief Description of Item 2 Providing, Bamboo jafry fencing by best quality muli bamboo including supplying, fitting, fixing split 2 mm in size having 75 mm x 75 mm mesh placed horizontally and diagonally doing 25 mm framing a square shape in both ways and both sides tightened with G.I wire fitted with Borrak bamboo post of 100 mm dia and placed firmly in position at 1800 mm apart including cost of tools and plants, digging hole and filling back etc.all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Muli Bamboo

1.5000

each

80.00

120.00

Borak Bamboo (75mm to 100mm)

2.3000

m

42.00

96.60

GI Wire (22 BWG)

0.1800

kg

90.00

16.20

Skilled Labour

0.2500

day

450.00

112.50 345.30

Subtotal-A: All other remaining cost

( +2.00 % on Subtotal-A )

6.91

Subtotal-A1:

352.21

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

359.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

395.18

VAT

6% of Total

26.35

IT

4% of Total

17.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

439.08

Page: 1658 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.16

Detailed Analysis Brief Description of Item 2 Rubbish carrying cost including taking up all sorts of bricks, brick-bats and rubbish, gravel chips, loading and unloading at both ends with cost of tools and plants etc.all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

130.61

cum

Ordinary Labour

0.3530

130.61

Subtotal-A: All other remaining cost

( +5.00 % on Subtotal-A )

6.53

Subtotal-A1:

137.14

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

139.88

10% Profit ( Add 10% on Subtotal-B) :

153.87

VAT

6% of Total

IT

4% of Total

10.26 6.84 Total:

5.26.17

Outdoor flower plants (Vogen blush, Tagar, Alamonda or any other species) without tub of local best quality for plantation in prepared bed etc. all complete as per direction of the E-I-C.

each

Outdoor flower plants

1.0000

each

60.00

60.00

Ordinary Labour

0.0500

day

370.00

18.50 78.50

Subtotal-A: All other remaining cost

( +5.00 % on Subtotal-A )

3.93

Subtotal-A1: Subtotal-B: Subtotal-C:

82.43 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84.07

10% Profit ( Add 10% on Subtotal-B) :

92.48

VAT

6% of Total

6.17

IT

4% of Total

4.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

170.97

102.76

Page: 1659 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 5.26.18

Detailed Analysis Brief Description of Item 2 Indoor Plants (Erica Palm, dracaena or any other species of normal size) with burned clay 200mm to 250mm size tub of local best quality etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Indoor flower plants

1.0000

each

50.00

50.00

Burned clay tub 200mm-250mm size

1.0000

each

35.00

35.00

Ordinary Labour

0.0500

day

370.00

18.50 103.50

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

5.18

Subtotal-A1:

108.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

110.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

121.93

VAT

6% of Total

IT

4% of Total

8.13 5.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

135.48

Page: 1660 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Chapter - 6 : Small Scale Water Resources Development Works 6.01.01

Earthwork in excavation of canals/Khals, ponds, drains etc. by excavating earth to lines, grades and elevation in all types of soils exceprt rocky, gravelly, slushy or organic soil as shown in the drawings, filling buskets, carrying and disposing all excavated materials at a safe distance including levelling, dressing etc all complete all for an initial exavation depth of 2m and lead not exceeding 20m including arranging for and supplying all necessary tools and equipments etc., all complete as per direction of the Engineer-in-Charge.

cum

Sardar

0.0170

day

800.00

13.60

Ordinary Labour

0.4000

day

370.00

148.00 161.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

164.83

10% Profit ( Add 10% on Subtotal-B) :

181.32

VAT

6% of Total

12.09

IT

4% of Total

8.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

201.46

Page: 1661 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.02

Detailed Analysis Brief Description of Item 2 Earthwork in excavation of canals/Khals, ponds, drains etc. by excavating earth to the lines, grades and elevation as shown in the drawings, filling baskets, carrying & disposing of all excavated materials at a safe distance designated by the Engineer-in-Charge in all types of soil except rocky, gravelly, slushy or organic soil, levelling, dressing etc all complete for an initial excavation depth of 1m or part thereof beyond the initial 2m depth and an initial lead not exceeding 20m including arranging for & supplying all necessary tools & equipment at work site etc., all complete as per direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

cum

Ordinary Labour

0.0550

20.35

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22.83

VAT

6% of Total

IT

4% of Total

1.52 1.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

20.35

25.37

Page: 1662 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.03

Detailed Analysis Brief Description of Item 2 Earthwork in excavation of canals/khals, ponds, drains, etc. by excavating earth to the lines, grades and elevation as shown in the drawing, filling baskets, carrying and disposing of all excavated materials at a safe distance designated by the E-I-C in all types of rocky, gravelly, slushy or organic soil, leveling, dressing, etc. all complete for an initial excavation depth of 2m and an initial lead not exceeding 20m, including arranging for and supplying all necessary tools and equipment at work site, etc. complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum

Sardar

0.4200

day

800.00

336.00

Mason

0.0250

day

550.00

13.75 349.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

356.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

392.42

VAT

6% of Total

26.16

IT

4% of Total

17.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

436.02

Page: 1663 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.04

Detailed Analysis Brief Description of Item 2 Earthwork in excavation of canals/Khals, ponds, drains etc. by excavating earth to the lines, grades and elevation as shown in the drawings, filling baskets, carrying & disposing of all excavated materials at a safe distance designated by the Engineer-in-Charge in all types of rocky, gravelly, slushy or organic soil, levelling, dressing etc all complete for an initial excavation depth of 1m or part thereof beyond the initial 2m depth and an initial lead not exceeding 20m, including arranging for & supplying all necessary tools & equipment at work site etc., all complete as per direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

cum

Ordinary Labour

0.0850

31.45

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

35.29

VAT

6% of Total

IT

4% of Total

2.35 1.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

31.45

39.21

Page: 1664 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.05

Detailed Analysis Brief Description of Item 2 Earth Work in excavation in foundation trenches for hydraulic structures in all sorts of soil except rocky, gravelly, slushy or organic type, up to a depth of 2m to the lines, grades and elevation as shown on the drawings, removing boulders, logs and other objectionable materials, clearing all loose materials, disposing of all excavated materials to a safe distance designated by the Engineer-in-Charge for an initial lead of 20m, and cut to a firm surface etc. all complete as per requirement and direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum

Sardar

0.3000

day

800.00

240.00

Mason

0.0250

day

550.00

13.75 253.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

258.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

284.71

VAT

6% of Total

18.98

IT

4% of Total

12.65 Total:

6.01.06

316.34

Earth Work in excavation in foundation trenches for hydraulic structures in all sorts of soil except of rocky, gravelly, slushy or organic type, for each additional depth beyond 2m to the lines, grades and elevation as shown on the drawings, removing boulders, logs and other objectionable materials, clearing all loose materials, disposing of all excavated materials to a safe distance designated by the Engineer-inCharge for an initial lead of 20m, and cut to a firm surface, etc. all complete as per requirement and instruction of the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1665 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.01.06.01

2 1st 1m and part thereof

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Ordinary Labour

0.3500

day

370.00

129.50

Sardar

0.0250

day

800.00

20.00 149.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

152.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

167.74

VAT

6% of Total

11.18

IT

4% of Total

7.46 Total:

6.01.06.02

2nd 1m and part thereof

cum Ordinary Labour

0.4000

day

370.00

148.00

Sardar

0.0250

day

800.00

20.00 168.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

171.36

10% Profit ( Add 10% on Subtotal-B) :

188.50

VAT

6% of Total

IT

4% of Total

12.57 8.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

186.38

209.44

Page: 1666 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.01.06.03

2 3rd 1m and part thereof

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Ordinary Labour

0.4500

day

370.00

166.50

Sardar

0.0250

day

800.00

20.00 186.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

190.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

209.25

VAT

6% of Total

13.95

IT

4% of Total

9.30 Total:

6.01.06.04

4th 1m and part thereof

cum Ordinary Labour

0.5000

day

370.00

185.00

Sardar

0.0250

day

800.00

20.00 205.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

209.10

10% Profit ( Add 10% on Subtotal-B) :

230.01

VAT

6% of Total

IT

4% of Total

15.33 10.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

232.50

255.57

Page: 1667 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.01.06.05

2 5th 1m and part thereof

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Ordinary Labour

0.5500

day

370.00

203.50

Sardar

0.0250

day

800.00

20.00 223.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

227.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

250.77

VAT

6% of Total

16.72

IT

4% of Total

11.15 Total:

6.01.06.06

6th 1m and part thereof

cum Ordinary Labour

0.6000

day

370.00

222.00

Sardar

0.0250

day

800.00

20.00 242.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

246.84

10% Profit ( Add 10% on Subtotal-B) :

271.52

VAT

6% of Total

IT

4% of Total

18.10 12.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

278.63

301.69

Page: 1668 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.07

Detailed Analysis Brief Description of Item 2 Earth work in excavation in foundation trenches for hydraulic structures in all sorts of rocky, gravelly, slushy or organic type, up to a depth of 2m to the lines, grades and elevation as shown on the drawing, removing boulders, logs and other objectionable materials, clearing all loose materials, disposing of all excavated materials to a safe distance designated by the E-I-C for an initial lead of 20m, and cut to a firm surface, removal of spoil to a safe distance, etc. all complete as per requirement and instruction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum

Sardar

0.4200

day

800.00

336.00

Mason

0.0250

day

550.00

13.75 349.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

356.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

392.42

VAT

6% of Total

26.16

IT

4% of Total

17.44 Total:

6.01.08

436.02

Earth Work in excavation of foundation trenches for hydraulic structures in all sorts of rocky, gravelly, slushy or organic type, for each additional depth beyond 2m to the lines, grades and elevation as shown on the drawings, removing boulders, logs and other objectionable materials, clearing all loose materials, disposing of all excavated materials to a safe distance designated by the Engineer-in-Charge for an initial lead of 20m, and cut to a firm surface, etc. all complete as per requirement and instruction of the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1669 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.01.08.01

2 1st 1m and part thereof

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Ordinary Labour

0.4700

day

370.00

173.90

Sardar

0.0250

day

800.00

20.00 193.90

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

197.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

217.56

VAT

6% of Total

14.50

IT

4% of Total

9.67 Total:

6.01.08.02

2nd 1m and part thereof

cum Ordinary Labour

0.5200

day

370.00

192.40

Sardar

0.0250

day

800.00

20.00 212.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

216.65

10% Profit ( Add 10% on Subtotal-B) :

238.31

VAT

6% of Total

IT

4% of Total

15.89 10.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

241.73

264.79

Page: 1670 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.01.08.03

2 3rd 1m and part thereof

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Ordinary Labour

0.5700

day

370.00

210.90

Sardar

0.0250

day

800.00

20.00 230.90

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

235.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

259.07

VAT

6% of Total

17.27

IT

4% of Total

11.51 Total:

6.01.08.04

4th 1m and part thereof

cum Ordinary Labour

0.6200

day

370.00

229.40

Sardar

0.0250

day

800.00

20.00 249.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

254.39

10% Profit ( Add 10% on Subtotal-B) :

279.83

VAT

6% of Total

IT

4% of Total

18.66 12.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

287.86

310.92

Page: 1671 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.01.08.05

2 5th 1m and part thereof

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum Ordinary Labour

0.6700

day

370.00

247.90

Sardar

0.0250

day

800.00

20.00 267.90

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

273.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

300.58

VAT

6% of Total

20.04

IT

4% of Total

13.36 Total:

6.01.08.06

6th 1m and part thereof

cum Ordinary Labour

0.7200

day

370.00

266.40

Sardar

0.0250

day

800.00

20.00 286.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

292.13

10% Profit ( Add 10% on Subtotal-B) :

321.34

VAT

6% of Total

IT

4% of Total

21.42 14.28 Total:

6.01.09

333.98

357.05

Earth filling work with specified soil in any type of dykes/ embankment including cutting, carrying, filling by throwing earth in layers not more than 150mm in each layer in proper alignment, grade, cambering and side slope in all types of soil except rocky, gravelly and slushy including benching not more than 30cm in vertical and 60cm in horizontal steps along the sides while widening any embankment, etc. all complete as per the direction of E-I-C. Payment will be made on compacted volume.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1672 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.09.01

Detailed Analysis Brief Description of Item 2 Initial lift upto 1.50 m from the toe of embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Royalty of Earth

1.2000

m3

25.00

30.00

Ordinary Labour

0.1080

day

370.00

39.96

Sardar

0.0040

day

800.00

3.20 73.16

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

74.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

82.09

VAT

6% of Total

IT

4% of Total

5.47 3.65 Total:

6.01.09.02

Upto 2.50m lift from the toe of embankment

cum Royalty of Earth

1.2000

m3

25.00

30.00

Ordinary Labour

0.1800

day

370.00

66.60

Sardar

0.0040

day

800.00

3.20 99.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

101.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

111.98

VAT

6% of Total

7.47

IT

4% of Total

4.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

91.21

124.42

Page: 1673 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.09.03

Detailed Analysis Brief Description of Item 2 Upto 3.50m lift from the toe of embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Royalty of Earth

1.2000

m3

25.00

30.00

Ordinary Labour

0.2520

day

370.00

93.24

Sardar

0.0040

day

800.00

3.20 126.44

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

128.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

141.87

VAT

6% of Total

IT

4% of Total

9.46 6.31 Total:

6.01.09.04

Upto 4.50m lift from the toe of embankment

cum Royalty of Earth

1.2000

m3

25.00

30.00

Ordinary Labour

0.3240

day

370.00

119.88

Sardar

0.0040

day

800.00

3.20 153.08

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

156.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

171.76

VAT

6% of Total

11.45

IT

4% of Total

7.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

157.63

190.84

Page: 1674 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.09.05

Detailed Analysis Brief Description of Item 2 Upto 5.50m lift from the toe of embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Royalty of Earth

1.2000

m3

25.00

30.00

Ordinary Labour

0.3960

day

370.00

146.52

Sardar

0.0040

day

800.00

3.20 179.72

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

183.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

201.65

VAT

6% of Total

IT

4% of Total

13.44 8.96 Total:

6.01.09.06

Upto 6.50m lift from the toe of embankment

cum Royalty of Earth

1.2000

m3

25.00

30.00

Ordinary Labour

0.4680

day

370.00

173.16

Sardar

0.0040

day

800.00

3.20 206.36

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

210.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

231.54

VAT

6% of Total

15.44

IT

4% of Total

10.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

224.05

257.26

Page: 1675 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.09.07

Detailed Analysis Brief Description of Item 2 Upto 7.50m lift from the toe of embankment

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Royalty of Earth

1.2000

m3

25.00

30.00

Ordinary Labour

0.5400

day

370.00

199.80

Sardar

0.0040

day

800.00

3.20 233.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

237.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

261.43

VAT

6% of Total

IT

4% of Total

17.43 11.62 Total:

6.01.10

Extra rate over Item No.6.01.09 for each additional lead of 20m or part thereof beyond the initial lead of 20m

cum Ordinary Labour

0.0250

day

370.00

Subtotal-B: Subtotal-C:

9.25 9.25

Subtotal-A:

9.44

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10.38

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

0.69 0.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

290.47

11.53

Page: 1676 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.11

Detailed Analysis Brief Description of Item 2 Earth filling work by Carried earth with specified soil in any type of embankment including supplying, carrying, filling by throwing earth in layers not more than 150mm in proper alignment, grade, camber and side slope in all types of soil except rocky, and slushy including benching not more than 30cm in vertical and 60cm in horizontal steps along the sides while widening any embankment , etc. all complete as per the direction of E-I-C. Earth shall be arranged by the LCS from a distance beyond 200m from the end of right of the way. (Payment will be made on compacted volume).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Royalty of Earth (Within Municipal Area)

1.2000

m3

50.00

60.00

Ordinary Labour

0.5000

day

370.00

185.00

H.C. of Flat Body Truck (3 tons)

0.0200

day

2000.00

40.00 285.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

290.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

319.77

VAT

6% of Total

IT

4% of Total

21.32 14.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

355.30

Page: 1677 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.12

Detailed Analysis Brief Description of Item 2 Earth filling work with specified soil in any type of dykes/ embankment including cutting, carrying, filling by throwing earth in layers not more than 150mm in each layer in proper alignment, grade, cambering and side slope in all types of soil except rocky, gravelly and slushy including benching not more than 30cm in vertical and 60cm in horizontal steps along the sides while widening any embankment, etc. all complete as per the direction of E-I-C. Earth shall be arranged by the contractor at his own cost and it will include all necessary lead & lift. Payment will be made on compacted volume.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Royalty of Earth

1.2000

m3

25.00

30.00

Ordinary Labour

0.2520

day

370.00

93.24

Sardar

0.0040

day

800.00

3.20 126.44

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

128.97

10% Profit ( Add 10% on Subtotal-B) :

141.87

VAT

6% of Total

9.46

IT

4% of Total

6.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

157.63

Page: 1678 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.13

Detailed Analysis Brief Description of Item 2 Manual compaction of earth in 150mm thick compacted layers by breaking clods to a maximum size of 50mm using wooden drag or ladder and compacting using concrete drop hammer (durmus), watering or drying to obtain optimum moisture content if necessary including supplying of wooden drag, ladder, bamboo hammer, steel/concrete hammer & other requisite tools, etc. all complete as per direction of the Engineer-in-Charge. 85% compaction of the maximum dry density is to be obtained by the standard compaction test.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

day

370.00

8

cum

Ordinary Labour

0.1000

37.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

37.74

10% Profit ( Add 10% on Subtotal-B) :

41.51

VAT

6% of Total

2.77

IT

4% of Total

1.85 Total:

6.01.14

Leveling & dressing the approach embankment crown, road flanks, building compound etc. in maintenance work by earth cutting and filling as necessary in proper slope and cambering including compaction etc. all complete as per direction of the Engineer-in- Charge.

46.13

sqm

Ordinary Labour

0.0350

day

370.00

12.95

Sardar

0.0100

day

800.00

8.00 20.95

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21.37

10% Profit ( Add 10% on Subtotal-B) :

23.51

VAT

6% of Total

IT

4% of Total

1.57 1.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

37.00

26.12

Page: 1679 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.01.15

Detailed Analysis Brief Description of Item 2 Turfing on approach embankment Top & slope, building compound with good quality turf supplied by the contractor of not less than 225 mm x 225 mm in dimension including leveling, dressing, placing, anchoring turf with pegs, and watering till grass is fully grown, etc. all complete as per direction of the Engineer-in-Charge. (Payment to be made only when grass is fully grown)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Turf

1.0000

m2

5.00

5.00

Ordinary Labour

0.0300

day

370.00

11.10 16.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16.42

10% Profit ( Add 10% on Subtotal-B) :

18.06

VAT

6% of Total

1.20

IT

4% of Total

0.80 Total:

6.01.16

Preparation of durmus (Size:150mm dia & 200mm height) by casting C.C.(1:2:4) with 75mm dia bamboo of 1.2m length including fitting & fixing which to be used for compaction of earth in proper way.

LS

6.01.17

Clearing by removal and disposal at a safe distance of everything above ground level which shall include trees, stumps, logs, bush, undergrowth grass, crops, loose vegetable, structures, etc. all complete as per instruction of the E-I-C.

LS

6.01.18

Supplying Sign Board at site of 1.5mx1.0m size in plain CI sheet; painting, writing, erecting & fixing with bamboo including all complete as per direction of Engineer-in-Charge.

LS

Note : Rates of all items should be inclusive of all supply and carriage.

20.07

Page: 1680 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.02.01

Detailed Analysis Brief Description of Item 2 Supplying and spreading/laying 1st class /picked brick chips (AIV less than 32 or LAA value not exceeding 38) including cost of brick carrying, breaking into specified sizes including screening and spreading uniformly in road surfaces maintaining grade, cambering, and super elevation and laying in bedding/ filter layer to CC brick block, including preparation of surfaces, ramming, compacting ,leveling etc., all complete as per design, drawing, specification and direction of the Engineer-in-Charge. (Measurement will be made on loose volume only.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick

300.0000

each

9.00

2700.00

Skilled Labour

1.6000

day

450.00

720.00 3420.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3488.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3837.24

VAT

6% of Total

255.82

IT

4% of Total

170.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4263.60

Page: 1681 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.02.02

Detailed Analysis Brief Description of Item 2 First class brick work in cement mortar (1:4) in toe walls/ guide walls with sand (minimum FM 1.5) and cement, cutting bricks to required sizes, hoisting and watering, etc. complete including cost of all materials all complete as per direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick

406.0000

each

9.00

3654.00

Sand (FM - 1.5)

0.3800

m3

795.00

302.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

2.1200

bag

430.00

911.60

Head Mason

0.0600

day

650.00

39.00

Mason

0.7000

day

550.00

385.00

Skilled Labour

0.7000

day

450.00

315.00

Ordinary Labour

1.0000

day

370.00

370.00 5976.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6096.23

10% Profit ( Add 10% on Subtotal-B) :

6705.86

VAT

6% of Total

447.06

IT

4% of Total

298.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7450.95

Page: 1682 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.02.03

Detailed Analysis Brief Description of Item 2 Single layer brick flat soling with 1st class or picked bricks, true to level, cambering/super elevation and grade including carrying bricks, filling the interstices tightly with sand of minimum FM 0.80, etc. all complete as per direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Sand (FM - 0.8)

0.0120

m3

480.00

5.76

Mason

0.0250

day

550.00

13.75

Ordinary Labour

0.1000

day

370.00

37.00

31.0000

each

9.00

279.00

1st Class Brick

335.51

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

342.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

376.44

VAT

6% of Total

25.10

IT

4% of Total

16.73 Total:

6.02.04

Supplying and laying local coarse sand (minimum FM 1.5 ) in bedding/filter layers below CC/brick blocks in bed and slopes including preparation of surfaces, ramming, compacting, leveling etc., all complete as per design and direction of the Engineer-in-Charge. (Payment will be made for compacted volume only.)

cum

Sand (FM - 1.5)

1.3000

m3

795.00

1033.50

Ordinary Labour

0.5000

day

370.00

185.00 1218.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1242.87

10% Profit ( Add 10% on Subtotal-B) :

1367.16

VAT

6% of Total

IT

4% of Total

91.14 60.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

418.27

1519.06

Page: 1683 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.02.05

Detailed Analysis Brief Description of Item 2 Sand filling on the prepared foundation bed with sand of minimum FM 0.80 in difficult areas with 150mm in thickness each layer including supplying, placing in conformity with the profile and level as per design including watering, compaction etc. all complete as per instruction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

cum

Sand (FM - 0.8)

1.3000

m3

480.00

624.00

Skilled Labour

0.5000

day

450.00

225.00 849.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

865.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

952.58

VAT

6% of Total

63.51

IT

4% of Total

42.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1058.42

Page: 1684 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.01

Detailed Analysis Brief Description of Item 2 Cement Concrete (C.C) work in foundation/blinding layer of hydraulic structures with Portland cement, sand (minimum FM 1.80) and 1st class/picked brick chips 20mm downgraded (LAA value not exceeding 38), including shuttering, mixing by concrete mixer machine, casting, laying, compacting and curing for the requisite period, breaking of bricks into chips etc. all complete as per direction of the Engineer-in-Charge. Cylinder crushing strength of concrete should not be less than 105 Kg/Cm2 at 28 days of curing (Suggested mix proportion 1:3:6). Additional quantity of cement to be added if required to attain the strength

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (20mm down graded)

0.9000

m3

2940.00

2646.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Head Mason

0.0800

day

650.00

52.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

4.2400

bag

430.00

1823.20

Mason

0.4200

day

550.00

231.00 6288.20

Subtotal-A: Form Work

( +.50 % on Subtotal-A )

31.44

Subtotal-A1: Subtotal-B: Subtotal-C:

6319.64 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6446.03

10% Profit ( Add 10% on Subtotal-B) :

7090.64

VAT

6% of Total

IT

4% of Total

472.71 315.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7878.49

Page: 1685 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.02

Detailed Analysis Brief Description of Item 2 Cement Concrete work (1:4:8) in blinding/ centering layer below RCC works, RCC pipes, pipe collar joint, pump house and bottom of sump well in connection with Rubber Dam construction with Portland cement, sand (minimum FM1.8) and 20mm down graded gravel (LAA value not exceeding 35) including mixing by concrete mixer machine, laying, casting, compacting by concrete vibrator, curing for the requisite period etc. all complete as per direction of the Engineer in charge. Cylinder crushing strength of concrete should be as specified in the design.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Shingles (20mm down graded)

0.8600

m3

3500.00

3010.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

3.3300

bag

430.00

1431.90

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 6021.90

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

301.10

Subtotal-A1: Subtotal-B: Subtotal-C:

6323.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6449.45

10% Profit ( Add 10% on Subtotal-B) :

7094.40

VAT

6% of Total

IT

4% of Total

472.96 315.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7882.67

Page: 1686 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.02.01

Detailed Analysis Brief Description of Item 2 Cement concrete (C.C) work in foundation with Portland Composite Cement (CEM II/AM, 42.5N), sand (F.M= 1.8)) and 20mm down graded Shingles (LAA value not exceeding 40) to attain a minimum 28 days cylinder strength of 17.0 Mpa ( Suggested mixing proportion 1:2:4), including grading, washing shingles, mixing, laying in forms, consolidating, curing for at least 21 days, including cutting trench,preparation of bed, shuttering and casting concrete all complete as per direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Shingles (20mm down graded)

0.8600

m3

3500.00

3010.00

Sand (FM - 1.8)

0.4300

m3

970.00

417.10

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Mason

0.0800

day

550.00

44.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

1.8000

day

370.00

666.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0590

day

1200.00

70.80 7146.90

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7289.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8018.82

VAT

6% of Total

IT

4% of Total

534.59 356.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8909.80

Page: 1687 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.03

Detailed Analysis Brief Description of Item 2 Minimum 6mm thick cement plaster (1:4) to rail bar and rail post with neat cement finishing including washing of sand, finishing the edges and corners and curing for requisite period etc. all complete as per direction of the Engineer-in-Charge. (Sand FM 1.2 be used)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

bag

430.00

8

sqm

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0540

Head Mason

0.0270

day

650.00

17.55

Mason

0.1080

day

550.00

59.40

Ordinary Labour

0.1080

day

370.00

39.96

Sand (FM - 1.2)

0.0090

m3

584.00

5.26 145.39

Subtotal-A: Form Work

( +16.00 % on Subtotal-A )

Subtotal-A1:

23.26 168.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

172.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

189.22

VAT

6% of Total

IT

4% of Total

12.61 8.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23.22

210.25

Page: 1688 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.04

Detailed Analysis Brief Description of Item 2 Minimum 12mm thick cement plaster (1:4) to dado and plinth wall upto 150mm below ground level with neat cement finishing including washing of sand, finishing the edges and corners and curing for the requisite period etc. all complete as per direction of the Engineer-inCharge. (Sand minimum FM. 1.2 to be used)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Sand (FM - 1.2)

0.0150

m3

584.00

8.76

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1620

bag

430.00

69.66

Head Mason

0.0270

day

650.00

17.55

Mason

0.1080

day

550.00

59.40

Ordinary Labour

0.1080

day

370.00

39.96 195.33

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

199.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

219.16

VAT

6% of Total

14.61

IT

4% of Total

9.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

243.51

Page: 1689 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.05

Detailed Analysis Brief Description of Item 2 Erection of 200mm wide water level gauge on 6mm thick plastering with Portland Composite Cement (CEM II/A-M, 42.5N) and sand (minimum FM 1.2) in proportion (1:4) on the body of hydraulic structure on both country side and river side including preparing the surface, curing including cutting the gauge marks including marking the value in English & Bengali upto centimeter in small division BWDB's RL value with respect to PWD datum and painting with synthetic enamel paint etc. all complete as per specification and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Sand (FM - 1.2)

0.0090

m3

584.00

5.26

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0540

bag

430.00

23.22

Synthetic Enamel Paint

0.2250

litre

260.00

58.50

Head Mason

0.0270

day

650.00

17.55

Mason

0.1080

day

550.00

59.40

Plumber/ Electric Mistry/ Painter

0.0400

day

680.00

27.20

Ordinary Labour

0.1080

day

370.00

39.96 231.09

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

235.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

259.28

VAT

6% of Total

IT

4% of Total

17.29 11.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

288.09

Page: 1690 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.06

Detailed Analysis Brief Description of Item 2 Epoxy paint 2 coats of approved colour and specification over a priming coat to gate, hoisting device and embedded metal parts including scraper, steel wire brush & emery paper etc. complete in all respect as per direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Red Oxide

0.0920

kg

197.00

18.12

Coal Tar

0.1680

kg

12.00

2.02

Emery Paper

0.3200

each

21.00

6.72

Plumber/ Electric Mistry/ Painter

0.3200

day

680.00

217.60

Skilled Labour

0.2400

day

450.00

108.00

Ordinary Labour

0.0320

day

370.00

11.84 364.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

371.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

408.74

VAT

6% of Total

IT

4% of Total

27.25 18.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

454.16

Page: 1691 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.07

Detailed Analysis Brief Description of Item 2 Painting of steel sheet piles, 2 coats of bitumen paint, including preparation of surface with sand paper, brush etc. including the cost of all materials and labour etc. complete as per direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Bitumen [Grade 80/100]

2.6840

kg

49.00

131.52

Fire wood

0.5386

kg

7.75

4.17

Brush

0.2365

each

35.64

8.43

Mason

0.0090

day

550.00

4.95

Ordinary Labour

0.1345

day

370.00

49.77 198.83

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

202.81

10% Profit ( Add 10% on Subtotal-B) :

223.09

VAT

6% of Total

14.87

IT

4% of Total

9.92 Total:

6.03.08

Painting of gauge on the body of structure with synthetic enamel paint etc. all complete as per specification & direction of E-I-C.

sqm Synthetic Enamel Paint

0.2250

litre

260.00

58.50

Plumber/ Electric Mistry/ Painter

0.0400

day

680.00

27.20 85.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

87.41

10% Profit ( Add 10% on Subtotal-B) :

96.16

VAT

6% of Total

6.41

IT

4% of Total

4.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

247.88

106.84

Page: 1692 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.09

Detailed Analysis Brief Description of Item 2 Providing 50mm average thick wearing course (1:1.5:3) on deck slab of hydraulic structures with cement, sand (minimum FM ≥ 1.8) and 6mm downgraded boulder chips, mixing concrete, laying, cost of all materials, labour and transportation to the site, etc. all complete as per specification and direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (12mm down graded) [LAA≤30]

0.8600

m3

4470.00

3844.20

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Ordinary Portland Cement (CEM I, 52.5N)

7.7700

bag

455.00

3535.35

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.1000

day

370.00

407.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0300

day

1200.00

36.00

Hire and running charges of Concrete Vibrator

0.0300

day

400.00

12.00 8952.55

Subtotal-A: Subtotal-B: Subtotal-C:

9131.60

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10044.76

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

669.65 446.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11160.85

Page: 1693 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.03.10

Detailed Analysis Brief Description of Item 2 Minimum 19mm thick cement plaster (1:4) to dado and plinth wall upto 150mm below ground level with neat cement finishing including washing of sand, finishing the edges and corners and curing for the requisite period etc. all complete as per direction of the engineer - in charge.(sand FM 1.2 be used)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2200

bag

430.00

94.60

Head Mason

0.0300

day

650.00

19.50

Mason

0.1130

day

550.00

62.15

Ordinary Labour

0.1500

day

370.00

55.50

Sand (FM - 1.2)

0.0250

m3

584.00

14.60 246.35

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

251.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

276.40

VAT

6% of Total

18.43

IT

4% of Total

12.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

307.12

Page: 1694 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.04.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-20SCCM: Reinforced cement concrete work with minimum cement content relates to nominal mix ratio 1:2:4 and maximum water cement ratio 0.4 having minimum required average strength, f'cr = 28.5 Mpa and satisfying a compressive strength f'c = 20 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and cement conforming to BDS EN 197-1 : 2003 CEM-II/A-L/M/V/W 42.5N, high range water reducing admixture of complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.2 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 35) conforming to ASTM C33 including screening chips through proper sieves, cleaning, placing shutter in position, making shutter water-tight properly, placing reinforcement in position, mixing in standard mixture machine with hoper, fed by standard measuring boxes, maintaining allowable slump of 75mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling, placing, binding etc. is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost. Note: Using Concrete Mixer

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1695 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.04.01.01

Detailed Analysis Brief Description of Item 2 For bottom and approach slab of box culvert, regulator/ pipe sluice/ Rubber Dam/ WRS of any height

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤35]

0.5200

cum

4930.00

2563.60

Stone Chips (12mm down graded) [LAA≤25]

0.3400

cum

4640.00

1577.60

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.2500

day

370.00

462.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84 8693.84

Subtotal-A: form work

( +3.00 % on Subtotal-A )

260.82

Subtotal-A1: Subtotal-B: Subtotal-C:

8954.66 9133.75

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10047.12

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

669.81

IT

4% of Total

446.54 Total:

6.04.01.02

11163.47

For top slab, side walk, curb, wheel guard etc. of box culvert, regulator/ pipe sluice/ Rubber Dam/ WRS

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1696 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.04.01.02.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤30]

0.5200

m3

5320.00

2766.40

Stone Chips (12mm down graded) [LAA≤30]

0.3400

m3

4470.00

1519.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.2500

day

370.00

462.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84 8838.84

Subtotal-A: Formwork

( +26.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11136.94 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11359.68

10% Profit ( Add 10% on Subtotal-B) :

12495.64

VAT

6% of Total

IT

4% of Total

833.04 555.36 Total:

6.04.01.02.02

For each additional height 300mm beyond 5m

6.04.01.03

For diaphragm walls, wing walls, pier columns, abutments and other vertical members of hydraulic structure

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2298.10

13884.05

Add +1.90% with Item No 6.04.01.02.01

Page: 1697 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.04.01.03.01

2 For Height Up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (20mm down graded) [LAA≤30]

0.5200

m3

5320.00

2766.40

Stone Chips (12mm down graded) [LAA≤30]

0.3400

m3

4470.00

1519.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Sand (FM - 1.8)

0.1720

m3

970.00

166.84 9055.34

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

10323.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10529.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11582.50

VAT

6% of Total

772.17

IT

4% of Total

514.78 Total:

6.04.01.03.02

For each additional height 300mm beyond 5m

Note : Rates of all items should be inclusive of all supply and carriage.

cum

1267.75

12869.45

Add +1.90% with Item No 6.04.01.03.01

Page: 1698 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

6.04.01.04

For cast-in-situ/ pre-cast railing & rail post of hydraulic structures

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

6.0500

bag

430.00

2601.50

Stone Chips (12mm down graded) [LAA≤30]

0.3400

m3

4470.00

1519.80

Sand (FM - 2.5)

0.2580

m3

1500.00

387.00

Water reducing chemical admixture : Type-A

1.2100

liter

130.00

157.30

Head Mason

0.1800

day

650.00

117.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

2.0000

day

450.00

900.00

Ordinary Labour

2.7500

day

370.00

1017.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (20mm down graded) [LAA≤30]

0.5200

m3

5320.00

2766.40

Sand (FM - 1.8)

0.1720

m3

970.00

166.84 10141.84

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +29.00 % on Subtotal-A )

Subtotal-A1:

13082.97

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13344.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14679.10

VAT

6% of Total

978.61

IT

4% of Total

652.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2941.13

16310.11

Page: 1699 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.04.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RCC-25SCCM: Reinforced cement concrete work with minimum cement content ralated to nominal mix ratio 1:1.5:3 and maximum water cement ratio 0.4 achieving minimum required average strength, f'cr = 33.5 Mpa and satisfying a compressive strength, f'c = 25 Mpa at 28 days on standard cylinders as per standard practice of Code AASHTO/ ASTM and using cement conforming to BDS EN 197-1 : 2003 CEM-II 42.5N / ASTM C150 Type-1, with high range water reducing admixture complying type A or F under ASTM C 494 (Doses of admixture to be fixed by the mix design), sand of minimum FM 2.5 and 20mm down well graded crushed stone chips broken from boulders (Preferably stone chips from Madhyapara, Dinajpur, LAA value not exceeding 30) conforming to ASTM C33 including breaking chips, screening through proper sieves, cleaning, placing shutters in position, making shutters water-tight properly, placing reinforcement in position, mixing in standard mixture machine with hoper, maintaining allowable slump of 50mm to 100mm, casting in forms, compacting by mechanical vibrator machine, curing for 28 days, removing centering-shuttering after approved specified time period, other incidental charges, etc. all complete as per drawing, specification & direction of the E-I-C. The cost of reinforcement and it's fabrication, welding, coupling, placing, binding etc. is not included but the cost of admixture is included in this unit rate. Additional quantity of cement to be added if required to attain the strength at the contractor's own cost. Note: Using Concrete Mixer

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1700 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.04.02.01

Detailed Analysis Brief Description of Item 2 For bottom and approach slab of box culvert, regulator/ pipe sluice/ Rubber Dam/ WRS of any height

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water reducing chemical admixture : Type-A

2.3130

liter

130.00

300.69

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9769.39

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +9.00 % on Subtotal-A )

879.25

Subtotal-A1:

10648.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10861.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11947.77

VAT

6% of Total

IT

4% of Total

796.52 531.01 Total:

6.04.02.02

13275.30

For top slab, side walk, curb, wheel guard etc. of box culvert, regulator/ pipe sluice/ Rubber Dam/ WRS

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1701 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.04.02.02.01

2 For height up to 5m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water reducing chemical admixture : Type-A

2.3130

liter

130.00

300.69

Head Mason

0.0600

day

650.00

39.00

Mason

0.4500

day

550.00

247.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9885.39

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +28.00 % on Subtotal-A )

Subtotal-A1:

12653.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12906.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14197.00

VAT

6% of Total

946.47

IT

4% of Total

630.98 Total:

6.04.02.02.02

For each additional height 300mm beyond 5m

6.04.02.03

For diaphragm walls, wing walls, pier columns, abutments and other vertical members of hydraulic structure

Note : Rates of all items should be inclusive of all supply and carriage.

cum

2767.91

15774.45

Add +1.90% with Item No 6.04.02.02.01

Page: 1702 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.04.02.03.01

2 Height up to 5 m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water reducing chemical admixture : Type-A

2.3130

liter

130.00

300.69

Head Mason

0.0800

day

650.00

52.00

Mason

0.4200

day

550.00

231.00

Skilled Labour

0.7500

day

450.00

337.50

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 9769.39

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

11137.10

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11359.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12495.83

VAT

6% of Total

833.06

IT

4% of Total

555.37 Total:

6.04.02.03.02

For each additional height 300mm beyond 5m

Note : Rates of all items should be inclusive of all supply and carriage.

cum

1367.71

13884.26

Add +1.90% with Item No 6.04.02.03.01

Page: 1703 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

6.04.02.04

For cast-in-situ/ pre-cast railing and rail post of Hydraulic Structure

cum

Quantity 5

Unit

Rate

6

7

Amount 8

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Water reducing chemical admixture : Type-A

2.3130

liter

130.00

300.69

Head Mason

0.1800

day

650.00

117.00

Mason

0.7500

day

550.00

412.50

Skilled Labour

2.0000

day

450.00

900.00

Ordinary Labour

2.7500

day

370.00

1017.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80 10855.89

Subtotal-A: Steel Formwork/ shuttering, prop with necessary supports etc.

( +29.00 % on Subtotal-A )

Subtotal-A1:

14004.10

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14284.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15712.60

VAT

6% of Total

1047.51

IT

4% of Total

698.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3148.21

17458.44

Page: 1704 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.04.03

Detailed Analysis Brief Description of Item 2 113mm thick brick bond concrete floor (1:2:4) with Portland cement, best quality coarse sand (minimum FM 1.8) and 10mm downgraded crushed picked brick chips (LAA value not exceeding 38) screening, mixing and laying the concrete between brick gaps (38mm) and 38mm thick over brick flat soling with compacting, and finishing the top with neat cement , curing for required period etc. all complete as per direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

1st Class Brick

42.0000

each

0.0300

m3

Ordinary Portland Cement (CEM I, 52.5N)

0.5000

Mason

0.1000

Skilled Labour

0.4400

Sand (FM - 1.8)

9.00

378.00

970.00

29.10

bag

455.00

227.50

day

550.00

55.00

day

450.00

198.00 887.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

905.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

995.89

VAT

6% of Total

IT

4% of Total

66.39 44.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1106.54

Page: 1705 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.05.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying and fabrication of Ribbed or deformed bar reinforcement conforming to BDS ISO 6935-2:2006 (or standard subsequently released from BSTI) for all types of RCC work including straightening, removing ruts, cleaning, cutting, hooking, bending, lapping and/or welding wherever required as directed, placing in position, tieing with 22 BWG black annealed binding wire double fold, cost of binding wire and anchoring to the adjoining members wherever necessary, supplying and placing with proper cover blocks (1:1), supports, chairs, spacers, splices or laps etc. including cost of all materials, cost of labour, cost of equipment & machinery, loading and unloading, transportation, all other incidental charges and work at all leads and lifts etc. to complete the work as per design, drawing, specifications and direction of the E-I-C. Reinforcement shall be measured only in lengths of bars as actually placed in position on standard weight i.e. 7850 kg/m3 (BNBC Table 6.2.1) basis. No separate payment shall be allowed for Chairs of any shape & profile, spacer bar of any shape & profile, lap/ splice, wastages, binding wire, concrete cover blocks etc. as the cost of these is included in the unit rate.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1706 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.05.01.01

Detailed Analysis Brief Description of Item 2 RB 300: Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield strength, fy (ReH) = 300 MPa, but the actual yield strength based on mill tests does not exceed fy by more than the 125 MPa and the ratio of actual ultimate strength, fu (Re) to actual tensile yield strength (fy) shall be at least 1.25 and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 16% and 2.5% respectively.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

M.S. Ribbed/ Deformed Bar (Grade 300)

1.0200

kg

54.00

55.08

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 61.59

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

69.10

VAT

6% of Total

IT

4% of Total

4.61 3.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

76.78

Page: 1707 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.05.01.02

Detailed Analysis Brief Description of Item 2 RB 400 / 400W: Ribbed or Deformed bar produced and marked as per BDS ISO 6935-2:2006 with minimum yield stress, fy (ReH) = 400 MPa, but the actual yield strength based on mill tests does not exceed fy by more than the 125 MPa, the ratio of actual ultimate strength, fu (Re) to actual tensile yield strength (fy) shall be at least 1.25 and minimum elongation after fracture (A5.65) & minimum total elongation at maximum force (Agt) is 14% and 2.5% respectively.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

M.S. Ribbed/ Deformed Bar (Grade 400)

1.0200

kg

58.00

59.16

GI Wire (22 BWG)

0.0100

kg

90.00

0.90

Re-bar Fabricator

0.0030

day

570.00

1.71

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.0075

day

370.00

2.78 65.67

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

73.68

VAT

6% of Total

IT

4% of Total

4.91 3.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

81.87

Page: 1708 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.05.02

Detailed Analysis Brief Description of Item 2 Supply of MS work in plates, angles, channels, flat bars, Tees etc. including fabricating, machining, cutting, bending, welding, forging drilling, riveting, embedding anchor bars, staging and fitting, fixing, local handling etc including energy consumption etc. all complete as per design, specification and direction of the Engineer-In-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

MS Angle, Flat bar, Z bar

0.6320

kg

59.00

37.29

MS Angle, Flat bar, Z bar

0.1760

kg

59.00

10.38

MS Plate (8mm thick)

0.1920

kg

70.00

13.44

Foreman

0.0050

day

800.00

4.00

Welder

0.0100

day

680.00

6.80

Skilled Labour

0.0300

day

450.00

13.50

H.C. of Electric Auto Gas Cutter Set

0.0030

day

500.00

1.50

H.C. of Vertical Drill Machine

0.0020

day

150.00

0.30

H.C. of Welding Machine

0.0100

day

500.00

5.00

H.C. of Grinding Machine

0.0100

day

100.00

1.00 93.21

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

95.08 104.58

VAT

6% of Total

6.97

IT

4% of Total

4.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

116.20

Page: 1709 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.05.03

Detailed Analysis Brief Description of Item 2 Manufacturing supplying and installation of M.S embedded parts for flap/vertical lift gate including fabricating, bending, welding, forging, drilling holes, welding anchor bars, fitting, fixing etc. all complete with a prime coat of red oxide where necessary as per design, specification and direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

MS Plate (9mm thick)

0.1680

kg

70.00

11.76

MS Angle, Flat bar, Z bar

0.6180

kg

59.00

36.46

MS Rod (Plain, 40 Grade)

0.2150

kg

45.00

9.68

Red Oxide

0.0050

kg

197.00

0.99

Fitter

0.0100

day

680.00

6.80

Foreman

0.0050

day

800.00

4.00

Plumber/ Electric Mistry/ Painter

0.0030

day

680.00

2.04

Welder

0.0200

day

680.00

13.60

Skilled Labour

0.0400

day

450.00

18.00

H.C. of Electric Auto Gas Cutter Set

0.0050

day

500.00

2.50

H.C. of Welding Machine

0.0200

day

500.00

10.00

H.C. of Grinding Machine

0.0200

day

100.00

2.00 117.82

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

120.18

10% Profit ( Add 10% on Subtotal-B) :

132.20

VAT

6% of Total

IT

4% of Total

8.81 5.88 Total:

6.05.04

146.88

Supplying, fitting and fixing in position MS plates , nuts, bolts , MS clamps u-straps etc. complete as per drawings specifications and directions of the Engineer-in-charge

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1710 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.05.04.01

Detailed Analysis Brief Description of Item 2 100mm x 25mm x 6mm M.S Clamp twisted with four holes for fixing

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Clamp (250x38x6mm)

1.0000

each

55.00

55.00

Skilled Labour

0.0200

day

450.00

9.00 64.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

65.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

71.81

VAT

6% of Total

4.79

IT

4% of Total

3.19 Total:

6.05.04.02

350mm x 25mm x 6mm M.S Clamp twisted with four holes for fixing

each Clamp (250x38x6mm)

1.0000

each

55.00

55.00

Skilled Labour

0.0200

day

450.00

9.00 64.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

65.28

10% Profit ( Add 10% on Subtotal-B) :

71.81

VAT

6% of Total

IT

4% of Total

4.79 3.19 Total:

6.06.01

79.79

79.79

Manufacturing and supplying CC blocks with Portland Composite Cement (CEM II/A-M, 42.5N), sand (FM ≥ 1.5) and shingles (40mm down graded) to attain a minimum 28 days cylinder strength of 9.0 MPa (suggested mix proportion 1:3:6), including grading, washings shingles, mixing, laying in forms, consolidating, curing for at least 21 days, including preparation of platform, shuttering and stacking in measurable stacks etc. all complete as per direction of the Engineer in charge (Steel shutter to be used)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1711 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.01.01

Detailed Analysis Brief Description of Item 2 Size: 500mm x 500mm x 300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0650

m3

3500.00

227.50

Sand (FM - 1.5)

0.0320

m3

795.00

25.44

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3200

bag

430.00

137.60

Mason

0.0060

day

550.00

3.30

Skilled Labour

0.0560

day

450.00

25.20

Ordinary Labour

0.1350

day

370.00

49.95

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0044

day

1200.00

5.28 474.27

Subtotal-A: Form Work

( +1.00 % on Subtotal-A )

4.74

Subtotal-A1:

479.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

488.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

537.45

VAT

6% of Total

IT

4% of Total

35.83 23.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

597.17

Page: 1712 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.01.02

Detailed Analysis Brief Description of Item 2 Size: 400mm x 400mm x 300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0410

m3

3500.00

143.50

Sand (FM - 1.5)

0.0220

m3

795.00

17.49

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0360

day

450.00

16.20

Ordinary Labour

0.0860

day

370.00

31.82

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0028

day

1200.00

3.36 300.57

Subtotal-A: Form Work

( +1.00 % on Subtotal-A )

3.01

Subtotal-A1:

303.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

309.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

340.61

VAT

6% of Total

IT

4% of Total

22.71 15.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

378.46

Page: 1713 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.01.03

Detailed Analysis Brief Description of Item 2 Size: 300mm x 300mm x 300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0230

m3

3500.00

80.50

Sand (FM - 1.5)

0.0120

m3

795.00

9.54

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1200

bag

430.00

51.60

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.0500

day

370.00

18.50

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0016

day

1200.00

1.92 173.26

Subtotal-A: Centering

( +1.00 % on Subtotal-A )

1.73

Subtotal-A1:

174.99

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

178.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

196.34

VAT

6% of Total

IT

4% of Total

13.09 8.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

218.16

Page: 1714 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.01.04

Detailed Analysis Brief Description of Item 2 Size: 300mm x 300mm x 150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0120

m3

3500.00

42.00

Sand (FM - 1.5)

0.0060

m3

795.00

4.77

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0570

bag

430.00

24.51

Mason

0.0010

day

550.00

0.55

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0240

day

370.00

8.88

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0008

day

1200.00

0.96 86.17

Subtotal-A: Form Work

( +1.00 % on Subtotal-A )

0.86

Subtotal-A1:

87.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

88.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

97.65

VAT

6% of Total

IT

4% of Total

6.51 4.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

108.50

Page: 1715 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.01.05

Detailed Analysis Brief Description of Item 2 Size: 250mm x 250mm x 250mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0130

m3

3500.00

45.50

Sand (FM - 1.5)

0.0070

m3

795.00

5.57

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0660

bag

430.00

28.38

Mason

0.0010

day

550.00

0.55

Skilled Labour

0.0180

day

450.00

8.10

Ordinary Labour

0.0280

day

370.00

10.36

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0009

day

1200.00

1.08 99.54

Subtotal-A: Form Work

( +1.00 % on Subtotal-A )

1.00

Subtotal-A1:

100.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

112.80

VAT

6% of Total

IT

4% of Total

7.52 5.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

125.33

Page: 1716 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.01.06

Detailed Analysis Brief Description of Item 2 Size: 400mm x 400mm x 100mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0137

m3

3500.00

47.95

Sand (FM - 1.5)

0.0073

m3

795.00

5.80

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0667

bag

430.00

28.68

Mason

0.0013

day

550.00

0.72

Skilled Labour

0.0120

day

450.00

5.40

Ordinary Labour

0.0287

day

370.00

10.62

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0010

day

1200.00

1.20 100.37

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

112.61

VAT

6% of Total

IT

4% of Total

7.51 5.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

125.13

Page: 1717 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.01.07

Detailed Analysis Brief Description of Item 2 Size: 375mm x 225mm x 150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Chips (20mm down graded) [LAA≤30]

0.0104

m3

5320.00

55.33

Sand (FM - 1.5)

0.0052

m3

795.00

4.13

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0730

bag

430.00

31.39

Mason

0.0010

day

550.00

0.55

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0024

day

370.00

0.89

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0010

day

1200.00

1.20 97.99

Subtotal-A: Form Works

( +2.50 % on Subtotal-A )

2.45

Subtotal-A1:

100.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

112.69

VAT

6% of Total

IT

4% of Total

7.51 5.01 Total:

6.06.02

125.21

Manufacturing and supplying Sand Cement blocks of different sizes with Portland Composite Cement (CEM II/A-M, 42.5N) and sand ( FM>=1.5) in 1:6 proportion, to attain a 28 day minimum strength of 2.5 N/mm2 including screening and washing sand, mixing, laying in forms, compacting, curing for at least 14 days including preparation of platform, shuttering (steel shutter to be used) etc. all complete as per specification & direction of the Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1718 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.01

Detailed Analysis Brief Description of Item 2 Size: 300mm x 300mm x 300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Sand (FM - 1.5)

0.0350

m3

795.00

27.83

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1400

bag

430.00

60.20

Head Mason

0.0020

day

650.00

1.30

Mason

0.0070

day

550.00

3.85

Skilled Labour

0.0190

day

450.00

8.55

Ordinary Labour

0.0190

day

370.00

7.03 108.76

Subtotal-A: Form Work

( +1.00 % on Subtotal-A )

1.09

Subtotal-A1:

109.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

112.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

123.24

VAT

6% of Total

IT

4% of Total

8.22 5.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

136.94

Page: 1719 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.02

Detailed Analysis Brief Description of Item 2 Size: 400mm x 400mm x 300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Sand (FM - 1.5)

0.0600

m3

795.00

47.70

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2400

bag

430.00

103.20

Head Mason

0.0030

day

650.00

1.95

Mason

0.0120

day

550.00

6.60

Skilled Labour

0.0330

day

450.00

14.85

Ordinary Labour

0.0330

day

370.00

12.21 186.51

Subtotal-A: Form Work

( +1.00 % on Subtotal-A )

1.87

Subtotal-A1:

188.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

192.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

211.36

VAT

6% of Total

IT

4% of Total

14.09 9.39 Total:

6.06.02.11

234.84

Manufacturing and supplying of hollow Cement Concrete Block of dimension 450 mm x 450 mm with Portland Composit Cement (CEMII/AM 42.5N), Sand (F.M> 1.5) and Shingles (20mm down graded, LAA value not exeeding 40) to attain a minimum 28 days cylinder strength of 17.00 Mpa (suggested mix 1:2:4), including grading, washing shingles, mixing, laying in forms, consolidating, curing for a at least 28 days, including preparation of platform, shuttering and staking in measurable stacks, cost of all materials, labour, equipments and machinery, work at all leads and lifts, loading & unloading, transportation and all other incidental charges etc. all complete as per drawing, specification & direction of the E-I-C. Steel frame to be used for performing job.(Payment should be made after setting the blocks at site properly)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1720 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.11.01

Detailed Analysis Brief Description of Item 2 Size: 450 mm x 450 mm x 75 mm; Hole dia : 150 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0120

m3

3500.00

42.00

Sand (FM - 1.5)

0.0060

m3

795.00

4.77

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0850

bag

430.00

36.55

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0120

day

450.00

5.40

Ordinary Labour

0.0330

day

370.00

12.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 104.81

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

5.24

Subtotal-A1:

110.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

112.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

123.48

VAT

6% of Total

IT

4% of Total

8.23 5.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

137.20

Page: 1721 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.11.02

Detailed Analysis Brief Description of Item 2 Size: 450 mm x 450 mm x 75 mm; Hole dia : 100 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0125

m3

3500.00

43.75

Sand (FM - 1.5)

0.0063

m3

795.00

5.01

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0884

bag

430.00

38.01

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0120

day

450.00

5.40

Ordinary Labour

0.0330

day

370.00

12.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 108.26

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

5.41

Subtotal-A1:

113.67

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

115.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

127.54

VAT

6% of Total

IT

4% of Total

8.50 5.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

141.71

Page: 1722 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.11.03

Detailed Analysis Brief Description of Item 2 Size: 450 mm x 450 mm x 100mm; Hole dia: 150 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0158

m3

3500.00

55.30

Sand (FM - 1.5)

0.0079

m3

795.00

6.28

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1120

bag

430.00

48.16

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0120

day

450.00

5.40

Ordinary Labour

0.0330

day

370.00

12.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 131.23

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

6.56

Subtotal-A1:

137.79

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

140.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

154.60

VAT

6% of Total

IT

4% of Total

10.31 6.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

171.78

Page: 1723 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.11.04

Detailed Analysis Brief Description of Item 2 Size: 450 mm x 450 mm x 100mm; Hole dia: 100 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0167

m3

3500.00

58.45

Sand (FM - 1.5)

0.0083

m3

795.00

6.63

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0118

bag

430.00

5.07

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0120

day

450.00

5.40

Ordinary Labour

0.0330

day

370.00

12.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 91.64

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

4.58

Subtotal-A1:

96.23

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

98.15 107.97 7.20 4.80

Total: 6.06.02.12

Manufacturing and supplying of Hollow Cement Concrete Blocks with necessary inter locking arrangement as per design of dimension 450 mm x 450 mm with Portland Composit Cement (CEM-II/AM 42.5N), sand (F.M> 1.5) and Shingles (20mm down graded, LAA value not exceeding 40) to attain a minimum 28 days cylinder strength of 17.00 Mpa (suggested mix 1:2:4), including grading, washing shingles, mixing, laying in forms, consolidating, curing for a at least 28 days, including preparation of platform, shuttering and staking in measurable stacks, cost of all materials, labour, equipments and machinery, work at all leads and lifts, loading & unloading, transportation and all other incidental charges etc. all complete as per drawing, specification & direction of the E-I-C. Steel frame to be used for performing job.(Payment should be made after setting the blocks at site properly)

Note : Rates of all items should be inclusive of all supply and carriage.

119.96

each

Page: 1724 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.12.01

Detailed Analysis Brief Description of Item 2 Size: 450 mm x 450 mm x 75 mm; Hole dia: 150 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0120

m3

3500.00

42.00

Sand (FM - 1.5)

0.0060

m3

795.00

4.77

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0850

bag

430.00

36.55

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.0330

day

370.00

12.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 108.41

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

5.42

Subtotal-A1:

113.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

116.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

127.72

VAT

6% of Total

IT

4% of Total

8.51 5.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

141.91

Page: 1725 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.12.02

Detailed Analysis Brief Description of Item 2 Size: 450 mm x 450 mm x 75 mm; Hole dia: 100 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0125

m3

3500.00

43.75

Sand (FM - 1.5)

0.0063

m3

795.00

5.01

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0884

bag

430.00

38.01

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.0330

day

370.00

12.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 111.86

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

5.59

Subtotal-A1:

117.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

119.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

131.78

VAT

6% of Total

IT

4% of Total

8.79 5.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

146.43

Page: 1726 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.12.03

Detailed Analysis Brief Description of Item 2 Size: 450 mm x 450 mm x 75 mm; Hole dia: 150 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0158

m3

3500.00

55.30

Sand (FM - 1.5)

0.0079

m3

795.00

6.28

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1120

bag

430.00

48.16

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.0330

day

370.00

12.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 134.83

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

6.74

Subtotal-A1:

141.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

144.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

158.84

VAT

6% of Total

IT

4% of Total

10.59 7.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

176.49

Page: 1727 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.02.12.04

Detailed Analysis Brief Description of Item 2 Size: 450 mm x 450 mm x 75 mm; Hole dia: 100 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Stone Shingles (20mm down graded)

0.0167

m3

3500.00

58.45

Sand (FM - 1.5)

0.0083

m3

795.00

6.60

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.1180

bag

430.00

50.74

Mason

0.0040

day

550.00

2.20

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.0330

day

370.00

12.21

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0014

day

1200.00

1.68 140.88

Subtotal-A: Form Work

( +5.00 % on Subtotal-A )

7.04

Subtotal-A1:

147.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

150.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

165.97

VAT

6% of Total

IT

4% of Total

11.06 7.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

184.41

Page: 1728 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.03

Detailed Analysis Brief Description of Item 2 Supplying brick block of size 380mmx380mmx300mm with 1st class brick in cement mortar (1:6) including curing for 28 days, etc. complete as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1st Class Brick

16.0000

each

9.00

144.00

Sand (FM - 1.5)

0.1900

m3

795.00

151.05

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0740

bag

430.00

31.82

Mason

0.0140

day

550.00

7.70

Skilled Labour

0.1400

day

450.00

63.00

Ordinary Labour

0.0200

day

370.00

7.40

Head Mason

0.0080

day

650.00

5.20 410.17

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

418.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

460.21

VAT

6% of Total

IT

4% of Total

30.68 20.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

511.35

Page: 1729 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.04

Detailed Analysis Brief Description of Item 2 Manufacturing cast-in-situ brick blocks of size 625mmx625mmx300mm with 1st class brick in cement mortar (1:6) including curing for 28 days etc. complete as per drawing and direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1st Class Brick

46.0000

each

9.00

414.00

Sand (FM - 1.5)

0.5200

m3

795.00

413.40

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2000

bag

430.00

86.00

Head Mason

0.0060

day

650.00

3.90

Mason

0.0400

day

550.00

22.00

Skilled Labour

0.0400

day

450.00

18.00

Ordinary Labour

0.1000

day

370.00

37.00 994.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1014.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1115.60

VAT

6% of Total

IT

4% of Total

74.37 49.58 Total:

6.06.05

Labour for laying of brick blocks of size 380mmx380mmx300mm in position including carriage and placing in arrangement, level, grade etc. all complete as per drawing and direction of the E-I-C.

hundre d Head Mason

0.0020

day

650.00

1.30

Skilled Labour

5.0000

day

450.00

2250.00 2251.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2296.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2525.96

VAT

6% of Total

IT

4% of Total

168.40 112.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1239.56

2806.62

Page: 1730 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.06

Detailed Analysis Brief Description of Item 2 Labour charge for protective works in laying C.C blocks of different sizes including preparation, watering and ramming of base etc. all complete as per drawing & direction of the Engineer in charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Mason

0.0200

day

550.00

11.00

Skilled Labour

0.3000

day

450.00

135.00

Ordinary Labour

1.3000

day

370.00

481.00 627.00

Subtotal-A: Bamboo Ladder, Jute Rope, Tools, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

689.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

703.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

773.84

VAT

6% of Total

IT

4% of Total

51.59 34.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

62.70

859.83

Page: 1731 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.07

Detailed Analysis Brief Description of Item 2 Labour charge for dumping in position of Stone Boulders/CC blocks/Brick blocks/ Sand Cement blocks of different sizes on river bed/ slope beyond 1m depth of water etc. all complete as per drawing and direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Mason

0.0200

day

550.00

Skilled Labour

0.3000

day

450.00

135.00

Ordinary Labour

2.0000

day

370.00

740.00

H.C. of Engine Boat

0.0180

day

1000.00

18.00 904.00

Subtotal-A: Bamboo Lader, Jute Rope, Tools, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

90.40 994.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1014.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1115.72

VAT

6% of Total

74.38

IT

4% of Total

49.59 Total:

6.06.08

11.00

1239.69

Labour for laying in position of different size of blocks by any means from store yards to the place of dumping with initial lead of 300m including laying in position.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1732 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.08.01

Detailed Analysis Brief Description of Item 2 Size: 300mm x 300mm x 300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

hundre d Head Mason

0.0020

day

650.00

1.30

Skilled Labour

5.0000

day

450.00

2250.00 2251.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2296.33

10% Profit ( Add 10% on Subtotal-B) :

2525.96

VAT

6% of Total

IT

4% of Total

168.40 112.26 Total:

6.06.08.02

Size: 400mm x 400mm x 300mm

hundre d Head Mason

0.0020

day

650.00

1.30

Skilled Labour

8.0000

day

450.00

3600.00 3601.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3673.33

10% Profit ( Add 10% on Subtotal-B) :

4040.66

VAT

6% of Total

IT

4% of Total

269.38 179.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2806.62

4489.62

Page: 1733 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.09

Detailed Analysis Brief Description of Item 2 Supplying and placing of single layer of gunny bagged Riprap filled with mixture of sand (minimum FM 1.00) and Portland Composite Cement (CEM II/A-M, 42.5N) (8:1) along slopes of abutments, piers banks of river/khal, tamping the bags in place, curing by sprinkling water over the bags including the cost of all materials, labour and incidentals necessary to complete the works as per specification and direction by the Engineer-In-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Sand (FM - 1.0)

0.1100

m3

567.00

62.37

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3800

bag

430.00

163.40

Empty Gunny Bag

5.0000

each

30.00

150.00

Mason

0.0100

day

550.00

5.50

Skilled Labour

0.4000

day

450.00

180.00 561.27

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

572.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

629.74

VAT

6% of Total

IT

4% of Total

41.98 27.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

699.72

Page: 1734 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.10

Detailed Analysis Brief Description of Item 2 Supplying and placing of two layers of gunny bagged Riprap filled with mixture of sand (minimum FM 1.00) and Portland Composite Cement (CEM II/A-M, 42.5N) (8:1) along slopes of abutments, piers banks of river/khal, tamping the bags in place, curing by sprinkling water over the bags including the cost of all materials, labour and incidentals as necessary to complete the work as per specification and direction by the Engineer-In- Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Sand (FM - 1.0)

0.2200

m3

567.00

124.74

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.7800

bag

430.00

335.40

Empty Gunny Bag

10.0000

each

30.00

300.00

Mason

0.0100

day

550.00

5.50

Ordinary Labour

0.7100

day

370.00

262.70 1028.34

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1048.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1153.80

VAT

6% of Total

IT

4% of Total

76.92 51.28 Total:

6.06.11

1282.00

Labour for filling empty gunny bags (75kg capacity) with caked cement/brick bats/earth/sand including supply of gunny bags, filling with material, sewing the mouth of bags with coir string and dumping the same in position, struts etc. all complete as per direction of the Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1735 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.06.11.01

2 Earth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

bag Empty Gunny Bag

1.0000

each

30.00

30.00

Royalty of Earth

0.0300

m3

25.00

0.75

Ordinary Labour

0.1000

day

370.00

37.00 67.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

69.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

76.02

VAT

6% of Total

IT

4% of Total

5.07 3.38 Total:

6.06.11.02

Sand (F.M 0.50)

bag Empty Gunny Bag

1.0000

each

30.00

30.00

Sand (FM - 0.5)

0.0300

m3

420.00

12.60

Ordinary Labour

0.0500

day

370.00

18.50 61.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

68.55

VAT

6% of Total

4.57

IT

4% of Total

3.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

84.46

76.17

Page: 1736 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.06.11.03

2 Caked cement/Brick bats

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

bag Empty Gunny Bag

1.0000

each

30.00

30.00

Caked Cement

0.0300

m3

1620.00

48.60

Ordinary Labour

0.1000

day

370.00

37.00 115.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

117.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

129.70

VAT

6% of Total

IT

4% of Total

8.65 5.76 Total:

6.06.12

144.11

Supplying and placing including embedment along the toe line/under the PVC water stopper properly, non-woven needle punched type geotextile filter of different grades, specifications for effective erosion protection/inverted filter in hydraulic structures/river training works including local handling and placing in position, providing machine made joints (with 100% nylon or polypropylene thread) or 35 cm lap in dry condition or minimum 100 cm lap under water including protecting the geo-textile materials; from UV ray and from any other damages etc. complete as per drawing and direction of Engineer-in-Charge. Geotextile delivered at site should be clearly labeled with brand name and printed at regular intervals across the body of the fabric)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1737 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.12.01

Detailed Analysis Brief Description of Item 2 Grade-I: Specification of which Mass (minimum) = 170 gm/m2, thickness under pressure 2 KPa (minimum)=1.5mm, Strip tensile strength (minimum)=12KN/m, elongation (minimum)=35%, Grab tensile strength (minimum)=700N, CBR puncture resistance (minimum)=2000N, effective opening size (maximum)=0.10mm, permeability vertical under 2 Kpa pressure h is 100m (minimum)=0.003m/s and permeability horizontal under 2 Kpa pressure (minimum)=0.004m/s

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Geo Textile (Grade-I-DF-20-1.5mm thick)

1.0700

m2

60.00

64.20

Skilled Labour

0.0420

day

450.00

18.90

Ordinary Labour

0.1350

day

370.00

49.95 133.05

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

135.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

149.28

VAT

6% of Total

IT

4% of Total

9.95 6.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

165.87

Page: 1738 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.12.02

Detailed Analysis Brief Description of Item 2 Grade-V: Specification of which Mass (minimum) = 365 gm/m2, thickness under pressure 2 KPa (minimum)=3.0mm, Strip tensile strength (minimum)=25KN/m, elongation (minimum)=40%, Grab tensile strength (minimum)=1500N, CBR puncture resistance (minimum)=4000N, effective opening size (maximum)=0.80mm, permeability vertical under 2 Kpa pressure h is 100m (minimum)=0.003m/s and permeability horizontal under 2 Kpa pressure (minimum)=0.004m/s

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Geo Textile (Grade-V-DF-60-3.0mm thick)

1.0700

m2

90.00

96.30

Skilled Labour

0.0420

day

450.00

18.90

Ordinary Labour

0.1350

day

370.00

49.95 165.15

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

168.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

185.30

VAT

6% of Total

IT

4% of Total

12.35 8.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

205.89

Page: 1739 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.06.13

Detailed Analysis Brief Description of Item 2 Manufacturing and Supplying of 25mm thick pre-cast ferro cement sheet made of Portland Composite Cement (CEM II/A-M, 42.5N) with sand of FM=1.5 in proportion of 1:2 and wire mesh of 18 BWG wire net double layer as per detail specification given in the design/drawing including cost of all materials, formwork, curring for 28 days with clean water and fitting, fixing & laying in position with Polythene sheet in the bottom and slopes of irrigation canal (as per design) keeping provision of joint and casting the joint in-situ, of specified length and width with mastic filler etc as per direction of engineering in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

bag

430.00

161.25

sqm

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3750

Sand (FM - 1.5)

0.0292

m3

795.00

23.21

0.18mm thick polythene sheet

1.8600

m2

12.31

22.90

18 BWG GI Wire Net

2.2050

sqm

144.46

318.53

Skilled Labour

0.3181

day

450.00

143.15

Ordinary Labour

0.3268

day

370.00

120.92

Mason

0.2259

day

550.00

124.25

Head Mason

0.0084

day

650.00

5.46 919.66

Subtotal-A: Other costs including Form Works

( +12.00 % on Subtotal-A )

Subtotal-A1:

1030.02

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1050.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1155.68

VAT

6% of Total

77.05

IT

4% of Total

51.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

110.36

1284.09

Page: 1740 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.01

Detailed Analysis Brief Description of Item 2 Supplying of U-Type Hot rolled Steel Sheet piles as per approved design drawings and specifications (sections, thickness, lengths & Mechanical properties). Before using the sheet pile supplied by the contractor a written approval from Project Director must be taken. If contactor's bid price is higher than the departmental supply rate, then the departmental supply rate will be applicable. (Contractor's supply will be applicable when departmental Supply is not possible. If material is supplied by the Department then the contract cost of this item shall be deducted from the contractor's bill. But the VAT & IT shall be deducted the departmental supply rates of steel sheet piles)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

kg

Steel Sheet Pile

1.0000

kg

103.40

103.40

Welder

0.0050

day

680.00

3.40 106.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

108.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

119.83

VAT

6% of Total

IT

4% of Total

7.99 5.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

133.14

Page: 1741 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.02

Detailed Analysis Brief Description of Item 2 Driving U-type steel sheet pile of various sections and weights in any type of soil by monkey hammer including handling and placing in position, staging and supplying of all equipment like monkey hammer, pulley, rope, bamboo, bullah etc. including correcting leaning beyond tolerance & other defects etc. complete as per drawing and direction of the Engineer in charge (Measurement will be taken on projected "width x driven depth" from lowest ground level) up to 4.5m depth.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Jute Rope

0.3000

kg

120.00

36.00

Borak Bamboo (75mm to 100mm)

0.6000

m

42.00

25.20

Shal/sundari/gazari Bullah (150mm to 200mm)

0.3200

m

225.00

72.00

Sundari/ Garzen

0.0020

m3

67580.00

135.16

Nails/ Nut bolts/ Screw/ Spikes

0.0400

kg

65.00

2.60

Foreman

0.1400

day

800.00

112.00

Skilled Labour

0.1760

day

450.00

79.20

Ordinary Labour

0.7920

day

370.00

293.04

H.C. of Driving Equipment

0.1400

day

350.00

49.00 804.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

820.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

902.31

VAT

6% of Total

60.15

IT

4% of Total

40.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1002.57

Page: 1742 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.03

Detailed Analysis Brief Description of Item 2 Taking out u-type steel sheet piles of various sections and weights from any type of soil by mechanical device including handling and placing in stacks etc. complete (measurement will be taken on projected "width x embeded depth" including arranging all equipment etc. all complete as per direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Jute Rope

0.4000

kg

120.00

48.00

Sundari/ Garzen

0.0200

m3

67580.00

1351.60

Foreman

0.0770

day

800.00

61.60

Skilled Labour

0.5000

day

450.00

225.00

Ordinary Labour

0.3300

day

370.00

122.10

H.C. of KATO Mobile Crane (upto 5 ton)

0.0630

day

4000.00

252.00

H.C. of Rig

0.0630

day

8580.00

540.54 2600.84

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2652.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2918.14

VAT

6% of Total

IT

4% of Total

194.54 129.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3242.38

Page: 1743 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.04

Detailed Analysis Brief Description of Item 2 Carrying steel sheet piles of specified sections & length from LGED stack yard as specified by appropriate means to the construction site and stacking at proper place including loading, unloading, local handling as per design, drawing and specifications etc. all complete as per direction of the E-I-C. (a) LGED stack-yard,Gazipur

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

tonnekm

H.C. of Flat Body Truck (5 tons)

0.0010

day

3000.00

3.00

Skilled Labour

0.0120

day

450.00

5.40 8.40

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8.57

10% Profit ( Add 10% on Subtotal-B) :

9.42

VAT

6% of Total

0.63

IT

4% of Total

0.42

Subtotal-C:

Total: 6.07.05

Cutting charge of U-type Hot rolled steel sheet piles as per specification (thickness, length and mechanical properties) and instruction by all complete as per direction of the E-I-C.

each

H.C. of Electric Auto Gas Cutter Set

0.0900

day

500.00

45.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.1500

day

370.00

55.50 190.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

194.31

10% Profit ( Add 10% on Subtotal-B) :

213.74

VAT

6% of Total

IT

4% of Total

14.25 9.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10.47

237.49

Page: 1744 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.06

Detailed Analysis Brief Description of Item 2 Supplying and driving of 100mm thick RCC sheet piles with strength of 20.7 N/mm2 on 28days (suggested mix proportion 1:1.5:3), Portland Composite Cement (CEM II/A-M, 42.5N), coarse sand (FM>=1.8) and 20mm downgraded 1st class/picked brick khoa including watertight shuttering, mixing with mixer machine, casting, comp acting with vibrator, curing etc. all complete, including breaking of khoa fabricating steel face plates with interlocking bars/angles as per drawings, specification and direction of the E-I-C. (Strength of concrete shall be as specified for RCC piles in the drawings and technical specification.) If the working mix proportion, to be determined by trial mix prior to starting work, give required strength richer than the normal mix proportion, additional cement as required by the strength requirement shall be provided by the contractor at his own cost. Form work/shuttering shall be as per specification and shall produce smooth and even concrete surface (no plastering is allowed), etc. all complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

sqm

1st Class Brick Chips (20mm down graded)

0.0900

m3

2940.00

Sand (FM - 1.8)

0.0450

m3

970.00

43.65

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.7770

bag

430.00

334.11

M.S. Ribbed/ Deformed Bar (Grade 400)

0.4760

kg

58.00

27.61

Head Mason

0.0500

day

650.00

32.50

Mason

0.1200

day

550.00

66.00

Skilled Labour

0.8300

day

450.00

373.50

Ordinary Labour

2.1400

day

370.00

791.80

Welder

1.9000

day

680.00

1292.00

Re-bar Fabricator

0.1200

day

570.00

68.40

H.C. of Rig

0.0500

day

8580.00

429.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0060

day

1200.00

7.20

Hire and running charges of Concrete Vibrator

0.0060

day

400.00

2.40

264.60

3732.77

Subtotal-A: Form work/shuttering, etc Note : Rates of all items should be inclusive of all supply and carriage.

Amount

( +5.00 % on Subtotal-A )

186.64 Page: 1745 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-A1:

3919.41

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3997.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4397.57

VAT

6% of Total

IT

4% of Total

293.17 195.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4886.19

Page: 1746 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.07

Detailed Analysis Brief Description of Item 2 Reinforced cement concrete work in pre-cast RCC piles and pile heads with Portland Composite Cement (CEM II/A-M, 42.5N), sand (minimum FM 2.50) and 20mm down well graded crushed stone chips (Preferably stone chips from Madhyapara, Dinajpur), (LAA value not exceeding 30), including shuttering, mixing by concrete mixer machine, casting, laying compacting, curing for the requisite period etc. all complete as per design, drawing, specification and direction of the E-I-C but excluding the cost of reinforcement. Strength of concrete should not be less than 25 MPa (suggested mix proportion 1:1.5:3). Additional quantity of cement to be added if required to attain at his own cost.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Head Mason

0.0600

day

650.00

39.00

Mason

0.3500

day

550.00

192.50

Skilled Labour

1.0000

day

450.00

450.00

Ordinary Labour

1.1000

day

370.00

407.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 9196.70

Subtotal-A: Form Work

( +17.00 % on Subtotal-A )

Subtotal-A1:

10760.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10975.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12072.88

VAT

6% of Total

804.86

IT

4% of Total

536.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1563.44

13414.31

Page: 1747 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.07.08

2 Supplying metal shoes (150mmx150mm) of approved design for RCC piles with cost of iron or steel plate welded to proper size and shape with necessary arrangement and embedding in concrete piles including cost of all materials and labour, etc. all complete as per Specification and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS Plate (8mm thick)

2.5000

kg

70.00

175.00

M.S. Ribbed/ Deformed Bar (Grade 300)

2.0000

kg

54.00

108.00

Skilled Labour

0.1600

day

450.00

72.00 355.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

362.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

398.31

VAT

6% of Total

IT

4% of Total

26.55 17.70 Total:

6.07.09

Labour for driving pre-cast RCC piles in any type of soil, handling and keeping in position and driving with suitable monkey to the required depth including fitting and fixing steel cap, etc, all complete as per direction of E-I-C.

6.07.09.01

225mm x 225mm

Note : Rates of all items should be inclusive of all supply and carriage.

442.57

Page: 1748 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.09.01.01

2 From 0m to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Operator

0.0370

day

570.00

21.09

Skilled Labour

0.0370

day

450.00

16.65

Ordinary Labour

0.3000

day

370.00

111.00 148.74

Subtotal-A: H.C. of Driving Equipment

( +390.00 % on Subtotal-A )

Subtotal-A1:

728.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

743.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

817.74

VAT

6% of Total

IT

4% of Total

54.52 36.34 Total:

6.07.09.01.02

From 6m to 12m and above

908.60

m Operator

0.0430

day

570.00

24.51

Skilled Labour

0.0430

day

450.00

19.35

Ordinary Labour

0.3500

day

370.00

129.50 173.36

Subtotal-A: H.C. of Driving Equipment

( +460.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

797.46 970.82 990.23

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1089.26

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

72.62 48.41 Total:

6.07.09.02

580.09

1210.28

250mm x 250mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1749 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.09.02.01

2 From 0m to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Operator

0.0410

day

570.00

23.37

Skilled Labour

0.0410

day

450.00

18.45

Ordinary Labour

0.3360

day

370.00

124.32 166.14

Subtotal-A: H.C. of Driving Equipment

( +470.00 % on Subtotal-A )

Subtotal-A1:

947.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

965.94 1062.53 70.84 47.22

Total: 6.07.09.02.02

From 6m to 12m and above

1180.59

m Operator

0.0480

day

570.00

27.36

Skilled Labour

0.0480

day

450.00

21.60

Ordinary Labour

0.3900

day

370.00

144.30 193.26

Subtotal-A: H.C. of Driving Equipment

( +460.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

889.00 1082.26

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1103.90

10% Profit ( Add 10% on Subtotal-B) :

1214.29

VAT

6% of Total

IT

4% of Total

80.95 53.97 Total:

6.07.09.03

780.86

1349.21

300mm x 300mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1750 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.09.03.01

2 From 0m to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Operator

0.0460

day

570.00

26.22

Skilled Labour

0.0460

day

450.00

20.70

Ordinary Labour

0.3770

day

370.00

139.49 186.41

Subtotal-A: H.C. of Driving Equipment

( +440.00 % on Subtotal-A )

Subtotal-A1:

1006.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1026.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1129.42

VAT

6% of Total

IT

4% of Total

75.29 50.20 Total:

6.07.09.03.02

From 6m to 12m and above

1254.91

m Operator

0.0520

day

570.00

29.64

Skilled Labour

0.0520

day

450.00

23.40

Ordinary Labour

0.4250

day

370.00

157.25 210.29

Subtotal-A: H.C. of Driving Equipment

( +470.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

988.36 1198.65

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1222.63

10% Profit ( Add 10% on Subtotal-B) :

1344.89

VAT

6% of Total

IT

4% of Total

89.66 59.77 Total:

6.07.09.04

820.20

1494.32

350mm x 350mm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1751 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.09.04.01

2 From 0m to 6m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Operator

0.0540

day

570.00

30.78

Skilled Labour

0.0540

day

450.00

24.30

Ordinary Labour

0.4400

day

370.00

162.80 217.88

Subtotal-A: H.C. of Driving Equipment

( +470.00 % on Subtotal-A )

Subtotal-A1:

1241.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1266.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1393.43

VAT

6% of Total

IT

4% of Total

92.90 61.93 Total:

6.07.09.04.02

From 6m to 12m and above

1548.26

m Operator

0.0570

day

570.00

32.49

Skilled Labour

0.0570

day

450.00

25.65

Ordinary Labour

0.4650

day

370.00

172.05 230.19

Subtotal-A: H.C. of Driving Equipment

( +465.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1070.38 1300.57

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1326.58

10% Profit ( Add 10% on Subtotal-B) :

1459.24

VAT

6% of Total

IT

4% of Total

97.28 64.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1024.04

1621.38

Page: 1752 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.10

2 Labour for breaking head of cast-in-situ bored pile/pre-cast pile up to required length by any means and removing the dismantled materials, such as, concrete to a safe distance including scrapping and removing concrete from steel/MS rods, preparation and making of platform where necessary, carrying, all sorts of handling, stacking the same properly after clearing, leveling and dressing the site and clearing the river bed, etc. all complete as per direction of the E-I-C. (Measurement will be given for the actual pile head volume to be broken)

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

5.0000

day

450.00

2250.00

10.0000

day

370.00

3700.00

5

Amount 8

cum

Skilled Labour Ordinary Labour

5950.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6069.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6675.90

VAT

6% of Total

445.06

IT

4% of Total

296.71 Total:

6.07.11

Boring and casting of RCC cast-in-situ piles up to the required depth and dia with temporary steel casing in all types of soils including staging, drilling, driving, bentonite circulation, placing of reinforcement and placing concrete by termite casting method with concrete with Portland Composite Cement (CEM II/A-M, 42.5N), sand (minimum FM 2.50) and 20mm down graded crushed stone chips (Preferably stone chips from Madhhyapara, Dinajpur), (LAA value not exceeding 30) to result minimum ultimate cylinder crushing strength of 25MPa at 28 days (suggested mix proportion 1:1.5:3) with allowable slump of 100mm to 150mm including cost of all materials, labour, equipment and all incidental charges but excluding the cost of reinforcement and its fabrication, etc. all complete as per design, drawing, specifications and of the Engineer-in-Charge. Additional quantity of cement be added, if required to attain the afore-mentioned concrete strength, by the contractor at his own costs.

6.07.11.01

Boring

Note : Rates of all items should be inclusive of all supply and carriage.

7417.67

Page: 1753 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.11.01.01

2 450mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Bentonite

1.1700

kg

36.00

42.12

Foreman

0.0500

day

800.00

40.00

Skilled Labour

0.1500

day

450.00

67.50

Ordinary Labour

0.3000

day

370.00

111.00

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.0500

day

3000.00

150.00

H.C. of Derrick

0.0500

day

400.00

20.00

H.C. of Water Pump

0.0500

day

500.00

25.00

H.C. of Tremie Pipe

0.0500

day

500.00

25.00

H.C. of Bailer

0.0500

day

300.00

15.00

H.C. of Cutter

0.0500

day

200.00

10.00

H.C. of Water Sealing Device

0.0500

day

200.00

10.00

H.C. of Welding Machine

0.0200

day

500.00

10.00 525.62

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

536.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

589.75

VAT

6% of Total

IT

4% of Total

39.32 26.21 Total:

6.07.11.01.02

500mm dia

m

Add +25.00% with Item No 6.07.11.01.01

6.07.11.01.03

600mm dia

m

Add +50.00% with Item No 6.07.11.01.01

6.07.11.02

Concreting

Note : Rates of all items should be inclusive of all supply and carriage.

655.27

Page: 1754 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.11.02.01

2 450mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Foreman

0.1240

day

800.00

99.20

Fitter Helper

0.1240

day

470.00

58.28

Skilled Labour

0.6780

day

450.00

305.10

Ordinary Labour

1.3600

day

370.00

503.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.1240

day

3000.00

372.00

H.C. of Derrick

0.1240

day

400.00

49.60

H.C. of Tremie Pipe

0.1240

day

500.00

62.00

H.C. of Casing

0.1240

day

260.00

32.24

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 9493.82

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9683.70 10652.07 710.14 473.43

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11835.63

Page: 1755 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.11.02.02

2 500mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Foreman

0.1240

day

800.00

99.20

Fitter Helper

0.1240

day

470.00

58.28

Skilled Labour

0.6780

day

450.00

305.10

Ordinary Labour

1.3600

day

370.00

503.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.1240

day

3000.00

372.00

H.C. of Derrick

0.1240

day

400.00

49.60

H.C. of Tremie Pipe

0.1240

day

500.00

62.00

H.C. of Casing

0.1240

day

260.00

32.24

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 9493.82

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9683.70 10652.07 710.14 473.43

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11835.63

Page: 1756 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.07.11.02.03

2 600mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum Stone Chips (20mm down graded) [LAA≤30]

0.4900

m3

5320.00

2606.80

Sand (FM - 2.5)

0.4100

m3

1500.00

615.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7100

bag

430.00

3315.30

Foreman

0.1240

day

800.00

99.20

Fitter Helper

0.1240

day

470.00

58.28

Skilled Labour

0.6780

day

450.00

305.10

Ordinary Labour

1.3600

day

370.00

503.20

H.C. of Tripod and Mechanical Winch Machine complete with power unit and accessories

0.1240

day

3000.00

372.00

H.C. of Derrick

0.1240

day

400.00

49.60

H.C. of Tremie Pipe

0.1240

day

500.00

62.00

H.C. of Casing

0.1240

day

260.00

32.24

Stone Chips (12mm down graded) [LAA≤30]

0.3300

m3

4470.00

1475.10 9493.82

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9683.70 10652.07 710.14 473.43

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11835.63

Page: 1757 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.12

Detailed Analysis Brief Description of Item 2 Supplying, sizing,placing & driving in position of 75mm to 100mm dia Borak bamboo post or pins of 4.5m to 6.0m long etc. complete as direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Borak Bamboo (75mm to 100mm)

1.0000

m

42.00

42.00

Ordinary Labour

0.1000

day

370.00

37.00 79.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

80.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

88.64

VAT

6% of Total

5.91

IT

4% of Total

3.94 Total:

6.07.13

Driving 75mm to 100mm dia or other means in dry land etc. all complete as per direction of the Engineer in charge.

m Ordinary Labour

0.1000

day

370.00

Subtotal-B: Subtotal-C:

37.00 37.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

37.74

10% Profit ( Add 10% on Subtotal-B) :

41.51

VAT

6% of Total

IT

4% of Total

2.77 1.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

98.49

46.13

Page: 1758 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.14

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Driving 75mm to 100mm dia or other means under water etc. all complete as per direction of the Engineer in charge.

m Ordinary Labour

Quantity 5

0.1000

Unit

Rate

Amount

6

7

day

370.00

8

37.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

37.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

41.51

VAT

6% of Total

2.77

IT

4% of Total

1.85 Total:

6.07.15

Supplying & laying in position packed straw bundles of 1m dia and 1.25m long with struts etc. all complete as per direction of the Engineer in charge.

46.13

bundle

Straw Bundle

1.0000

each

70.00

70.00

Borak Bamboo (75mm to 100mm)

2.0000

m

42.00

84.00

Ordinary Labour

0.0750

day

370.00

27.75 181.75

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

203.92

VAT

6% of Total

13.59

IT

4% of Total

9.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

37.00

226.58

Page: 1759 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.16

Detailed Analysis Brief Description of Item 2 Supplying & dumping brush wood in position compacted in bundles of 450mm dia including cross bamboo as directed including fitting fixing struts etc. all complete as per direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

bundle

Brush Wood Bundle

1.0000

each

61.78

61.78

Borak Bamboo (75mm to 100mm)

3.0000

m

42.00

126.00

Ordinary Labour

0.0750

day

370.00

27.75 215.53

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

219.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

241.82

VAT

6% of Total

IT

4% of Total

16.12 10.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

268.69

Page: 1760 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.17

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 6 ply Nylon net (12mm opening) in position with burnt clay weight (length 4 inch dia 2 inch solid/hollow/cylindrical) and fitting fixing 10mm dia to 12mm dia Polyvinyl / Nylon rope in position as per design, drawings, specifications and directions of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

6 ply Nylon Net

1.0000

sqm

54.00

54.00

Clay

0.0020

cum

1080.00

2.16

Nylon Rope

1.0000

kg

140.00

140.00

Fire wood

1.0000

kg

7.75

7.75

Ordinary Labour

0.1600

day

370.00

59.20 263.11

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

268.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

295.21

VAT

6% of Total

19.68

IT

4% of Total

13.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

328.01

Page: 1761 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.18

Detailed Analysis Brief Description of Item 2 Supplying and placing of 20mm Hessian cloth soaked with bitumen on top of sheet piles as per drawing, specification and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Hessian Cloth

8.0000

sqm

9.72

77.76

Bitumen [Grade 80/100]

1.5000

kg

49.00

73.50

Fire wood

1.2500

kg

7.75

9.69

Skilled Labour

0.3130

day

450.00

140.85

Ordinary Labour

0.0250

day

370.00

9.25 311.05

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

317.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

349.00

VAT

6% of Total

IT

4% of Total

23.27 15.51 Total:

6.07.19

Supplying, fitting and fixing 400mm dia and 500mm long drum with both end closed in position as per design drawings specifications and directions of the E-I-C.

each

Bitumen Drum Sheet

1.0000

m2

269.00

269.00

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.1250

day

370.00

46.25 371.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

378.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

416.82

VAT

6% of Total

27.79

IT

4% of Total

18.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

387.77

463.14

Page: 1762 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

6.07.20

Shoring for slope protection of foundation trench, canal, embankment, road, pond etc, as per design slopes, grades including removal of spoils to a safe distance as per direction of E-I-C.

6.07.20.01

By bamboo post of 6.0m length, 60mm to 80mm dia, 250mm c/c and 2m drive with diagonally woven tarja walling and average 70mm dia half split bamboo batten @ 2.0m c/c fixed with nails etc.all complete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Borak Bamboo (75mm dia)

1.1500

m

38.00

43.70

Tarza

1.0000

m2

210.00

210.00

Nails/ Nut bolts/ Screw/ Spikes

0.1500

kg

65.00

9.75

Head Mason

0.0100

day

650.00

6.50

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.2500

day

370.00

92.50 363.58

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

370.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

407.93

VAT

6% of Total

IT

4% of Total

27.20 18.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

453.26

Page: 1763 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.20.02

Detailed Analysis Brief Description of Item 2 By bamboo post of 6.0m length, 60mm to 80mm dia, 200mm c/c, driven 2.0m below ground, with drum shet walling and average 70mm dia half split bamboo batten @ 2.0m c/c fixed with nails etc.all complete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Borak Bamboo (75mm dia)

1.3000

m

38.00

49.40

Bitumen Drum Sheet

1.0000

m2

269.00

269.00

Nails/ Nut bolts/ Screw/ Spikes

0.1500

kg

65.00

9.75

Head Mason

0.0100

day

650.00

6.50

Skilled Labour

0.0025

day

450.00

1.13

Ordinary Labour

0.2500

day

370.00

92.50 428.28

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

436.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

480.52

VAT

6% of Total

IT

4% of Total

32.03 21.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

533.92

Page: 1764 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.20.03

Detailed Analysis Brief Description of Item 2 By local hard wood ballah post of 6.0m length, 125mm dia, 1.0m c/c, and 2.0m driven with 6.0m long bamboo of agarage 75mm dia, @ 1.0, c/c and 2.0m dia drive with drum sheet walling and average 70mm dia half split bamboo betten @ 2.0m c/c fixed with nails etc.all complete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Borak Bamboo (75mm dia)

0.3200

m

38.00

Shal/sundari/gazari Bullah (150mm to 200mm)

1.5000

m

225.00

337.50

Bitumen Drum Sheet

1.0000

m2

269.00

269.00

Nails/ Nut bolts/ Screw/ Spikes

0.1000

kg

65.00

6.50

Head Mason

0.0100

day

650.00

6.50

Skilled Labour

0.0035

day

450.00

1.58

Ordinary Labour

0.3500

day

370.00

129.50 762.74

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

777.99

10% Profit ( Add 10% on Subtotal-B) :

855.79

VAT

6% of Total

57.05

IT

4% of Total

38.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12.16

950.88

Page: 1765 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.21

Detailed Analysis Brief Description of Item 2 Construction of double row bamboo spur, with full length barrack bamboo, 60mm to 75mm dia and 3.0m to 4.5, long, 0.30m c/c, 1.5m apart and single row runner with half split bamboo on both sides, of each row, fixing with country nails, and 1.5, apart, double layers cross tie at 3.0m interval and 1.5m apart, including 2.4m to 3.0m driving of bamboo pins by monkey hummer, necessary staging etc. complete with supply of all materials and as per drawing and direction of Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

GI Wire (22 BWG)

0.2500

kg

90.00

22.50

Borak Bamboo (75mm dia)

4.9533

m

38.00

188.23

Nails/ Nut bolts/ Screw/ Spikes

0.2000

kg

65.00

13.00

H.C. of Driving Equipment

0.2500

day

350.00

87.50

Skilled Labour

1.0000

day

450.00

450.00 761.23

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

776.45

10% Profit ( Add 10% on Subtotal-B) :

854.09

VAT

6% of Total

56.94

IT

4% of Total

37.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

948.99

Page: 1766 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.22

Detailed Analysis Brief Description of Item 2 Construction of double row bamboo spur, with full length barrack bamboo of average 60mm to 75mm dia and 4.5m to 6.0m long, at 0.30m c/c, two rows at 1.5m apart and stays with bamboo at 3.0m apart on D/S side of spur and single row runner with half split bamboo on both sides of each row and double layers cross tie at 3.0m interval, including 2.4m to 3.0, driving of bamboo pins by monkey hammer, necessary staging etc. complete with supply of all materials including local carriage within 150m and as per drawing and direction of Engineer in Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

GI Wire (22 BWG)

0.3500

kg

90.00

31.50

Borak Bamboo (75mm dia) Nails/ Nut bolts/ Screw/ Spikes

7.4066

m

38.00

281.45

0.2500

kg

65.00

16.25

H.C. of Driving Equipment

0.2500

day

350.00

87.50

H.C. of Engine Boat

0.1300

day

1000.00

130.00

Skilled Labour

1.8600

day

450.00

837.00 1383.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1411.37

10% Profit ( Add 10% on Subtotal-B) :

1552.51

VAT

6% of Total

IT

4% of Total

103.50 69.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1725.01

Page: 1767 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.23

Detailed Analysis Brief Description of Item 2 Construction of double row bamboo spur, with full length barrack bamboo of average 75mm to 100mm dia, 7.5m to 11.0m long, at 0.3m c/c, two rows at 1.5m apart and stays with bamboo at 3.0m apart on the D/S side of the spur and double row runner with half split bamboo on both sides of each row, double layer cross tie at 3.0m interval, including 2.4m to 3.0m, driving of bamboo pins by monkey hammer, necessary staging etc. complete with supply of all materials including local carriage with 150m and as per drawing and direction of Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

GI Wire (22 BWG) Borak Bamboo (75mm dia)

0.4500

kg

90.00

40.50

13.9487

m

38.00

530.05

Nails/ Nut bolts/ Screw/ Spikes

0.3833

kg

65.00

24.91

H.C. of Driving Equipment

0.3500

day

350.00

122.50

H.C. of Engine Boat

0.2600

day

1000.00

260.00

Skilled Labour

4.1533

day

450.00

1868.99 2846.95

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2903.89

10% Profit ( Add 10% on Subtotal-B) :

3194.28

VAT

6% of Total

IT

4% of Total

212.95 141.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3549.20

Page: 1768 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.24

Detailed Analysis Brief Description of Item 2 Supplying of brush wood compacted in bundle not more than 75cm dia and 180cm in length tied securely with coir string and dumping the same in position etc. complete with supply of all materials and as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Brush Wood Bundle

1.0000

each

61.78

GI Wire (22 BWG)

0.5332

kg

90.00

47.99

Ordinary Labour

0.6667

day

370.00

246.68 356.45

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

363.58

10% Profit ( Add 10% on Subtotal-B) :

399.93

VAT

6% of Total

IT

4% of Total

26.66 17.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

61.78

444.37

Page: 1769 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.07.25

Detailed Analysis Brief Description of Item 2 Providing barbed wire fencing with R.C.C. (1:2:4) posts @2.43m c/c and of section 100mmx100mm at top and 150mmx150mm at bottom of 2.13m total height (1.37m above G.L.. and 0.76m below GI) in/c 150mm thick, 450mm square Spread footings (posts reinforced with 4 nos. 10mm dia main rod and 6mm dia stirrups @150mm c/c. footing reinforced with 5 nos. 10mm dia rod both ways) supplying, fitting and fixing 8 lines of barbed wire horizontally (fixed with the post through 6mm dia. Rods embedded into the post) and 2 lines diagonally from post to post with 12 BWG 2 ply barbed wire with 4 points barbs @minimum 112mm c/c in/c 6mm thick cement plaster (1:4) up to 1500mm length of the posts etc. all complete as per direction of the Engineer In Charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.0700

cum

75.80

5.31

12mm thick cement plaster (1:6) to wall for ground floor…..(5.12.02.01)

0.3400

sqm

184.48

62.72

M.S. Ribbed/ Deformed Bar (Grade 300)

4.3200

kg

54.00

233.28

12 BWG 2Ply 4 point barbed wire

1.7500

kg

50.00

87.50

Skilled Labour

0.1000

day

450.00

45.00 433.81

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

442.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

486.73

VAT

6% of Total

IT

4% of Total

32.45 21.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

540.81

Page: 1770 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.08.01

Detailed Analysis Brief Description of Item 2 Manufacturing, supplying and installation of pedestal type lifting device for slide gate with 63mm dia threaded steel shaft, 146mm outer dia bronze nut, thrust bearing, steel bevel gear etc. as per approved design including supply of all components, labour with a prime coat of red oxide where necessary etc. all complete as per specification and direction of the Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Threaded Shaft (D=63mm, L=6m)

1.0000

each

13825.00

13825.00

Bronze Lift nut (D=146mm, L=200mm)

1.0000

each

10667.00

10667.00

Bevel Gear (315 BHN Steel, D=306mm)

1.0000

each

5050.00

5050.00

Thrust Bearing out (D=184, BHN=625)

1.0000

each

4477.00

4477.00

MS Hex. Stop Nut (D=63mm)

1.0000

each

1057.00

1057.00

MS Bevel Pinion & Shaft (D=75mm, 15T)

1.0000

each

2610.00

2610.00

CI Spur Pinion (D=300mm, 60T)

1.0000

each

3567.00

3567.00

MS Spur Pinion ((D=300mm, 15T)

1.0000

each

1413.00

1413.00

CI Gear Cover (D=381mm, H=63mm)

1.0000

each

1956.00

1956.00

CI Bowl (D=419mm)

1.0000

each

9493.00

9493.00

Bronze Lock Washer (D=73mm, T=3mm)

1.0000

each

200.00

200.00

MS Crank

1.0000

each

1240.00

1240.00

MS Pedestal (D=200/250mm, L=760mm)

1.0000

each

7718.00

7718.00

CI Wall Bracket

1.0000

each

2360.00

2360.00

Mason

0.5000

day

550.00

275.00

Welder

1.0000

day

680.00

680.00

Fitter

5.0000

day

680.00

3400.00

Plumber/ Electric Mistry/ Painter

0.0670

day

680.00

45.56

Ordinary Labour

5.0000

day

370.00

1850.00

Welder Helper

1.0000

day

470.00

470.00

Fitter Helper

6.0000

day

470.00

2820.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/

0.0540

day

470.00

25.38

Page: 1771 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Operator 75198.94

Subtotal-A: Other necessary accessories and material

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

85726.79 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

87441.33

10% Profit ( Add 10% on Subtotal-B) :

96185.46

VAT

6% of Total

IT

4% of Total

6412.36 4274.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10527.85

106872.73

Page: 1772 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.08.02

Detailed Analysis Brief Description of Item 2 Manufacturing, supplying and installation of hand-wheel type lifting device for slide gate with 63mm dia steel shaft, 108mm outer dia bronze nut taper roller bearing SKF-50216 etc. as per approved design including supply of all components, labours with a prime coat of red oxide etc. all complete as per specification and direction of the Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Threaded Shaft (D=63mm, L=6m)

1.0000

each

13825.00

13825.00

CI Hand Wheel out (D=760mm)

1.0000

each

9700.00

9700.00

CIB Cover Top (D=190, T=21, H=106mm)

1.0000

each

5473.00

5473.00

Bronze Lift Nut (D=105mm, H=222mm)

1.0000

each

8000.00

8000.00

MS Lift Screw (D=18, L=1825mm)

1.0000

each

3150.00

3150.00

MS Pedestal Welded (D=140mm, L=680mm, T=6mm)

1.0000

each

2500.00

2500.00

CI Bearing Plate (D=267mm, T=20mm)

1.0000

each

1427.00

1427.00

Tapered Roller Bearing (SKF No-50216)

2.0000

each

1553.00

3106.00

Welder

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

0.0670

day

680.00

45.56

Fitter

3.0000

day

680.00

2040.00

Welder Helper

1.0000

day

470.00

470.00

Fitter Helper

5.0000

day

470.00

2350.00

Ordinary Labour

3.0000

day

370.00

1110.00 53876.56

Subtotal-A: Other necessary accessories and material

( +1.00 % on Subtotal-A )

538.77

Subtotal-A1: Subtotal-B: Subtotal-C:

54415.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55503.63

10% Profit ( Add 10% on Subtotal-B) :

61054.00

VAT

6% of Total

IT

4% of Total

4070.27 2713.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

67837.77

Page: 1773 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.08.03

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Manufacturing, supplying of M.S Vertical lift gate shutter of 8mm thick M.S skin plate and stiffener with minimum 75mmx75mmx10mm M.S angle as frame, horizontal & vertical beam, 75mmx25mmx12mm P-type rubber seal, fixed with 10mm diax63.5mm M.S counter shank bolts with nuts and 40mmx10mm M.S strip as clamp drilled space @150mm c/c, stem attachment with proper thread, nut cotter pin and washer as per approved design including the cost of all materials of proper grade and brand new with a prime coat of red oxide where necessary as per specifications including fitting, fixing etc. all complete as per drawing, specification and direction of the Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1774 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.03.01

2 Size: 1.05m x 0.975m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

4.4000

m

820.00

3608.00

40.0000

kg

59.00

2360.00

1.0000

each

1643.00

1643.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm) MS Angle, Flat bar, Z bar Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm) MS Plate (8mm thick)

85.0000

kg

70.00

5950.00

Fitter

2.0000

day

680.00

1360.00

Foreman

0.5000

day

800.00

400.00

Plumber/ Electric Mistry/ Painter

0.2020

day

680.00

137.36

Welder

2.0000

day

680.00

1360.00

Skilled Labour

8.0000

day

450.00

3600.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1650

day

470.00

77.55

H.C. of Electric Auto Gas Cutter Set

2.0000

day

500.00

1000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

1.0000

day

1000.00

1000.00

H.C. of Welding Machine

2.0000

day

500.00

1000.00

H.C. of Grinding Machine

2.0000

day

100.00

200.00 24845.91

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1:

27827.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28383.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

31222.36

VAT

6% of Total

IT

4% of Total

2081.49 1387.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2981.51

34691.52

Page: 1775 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.03.02

2 Size: 1.35m x 1.275m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

5.8000

m

820.00

4756.00

65.0000

kg

59.00

3835.00

1.0000

each

1643.00

1643.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm) MS Angle, Flat bar, Z bar Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm) MS Plate (8mm thick)

142.0000

kg

70.00

9940.00

Fitter

3.0000

day

680.00

2040.00

Foreman

1.0000

day

800.00

800.00

Plumber/ Electric Mistry/ Painter

0.3130

day

680.00

212.84

Welder

3.0000

day

680.00

2040.00

10.0000

day

450.00

4500.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50

H.C. of Electric Auto Gas Cutter Set

3.0000

day

500.00

1500.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

1.0000

day

1000.00

1000.00

H.C. of Welding Machine

3.0000

day

500.00

1500.00

H.C. of Grinding Machine

3.0000

day

100.00

300.00

Skilled Labour

35334.34

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1:

39574.46

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40365.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

44402.55

VAT

6% of Total

IT

4% of Total

2960.17 1973.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4240.12

49336.16

Page: 1776 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.03.03

2 Size: 1.35m x 1.575m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

5.8000

m

820.00

4756.00

65.0000

kg

59.00

3835.00

1.0000

each

1643.00

1643.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm) MS Angle, Flat bar, Z bar Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm) MS Plate (8mm thick)

142.0000

kg

70.00

9940.00

Fitter

1.0000

day

680.00

680.00

Foreman

0.3130

day

800.00

250.40

Plumber/ Electric Mistry/ Painter

3.0000

day

680.00

2040.00

Welder

10.0000

day

680.00

6800.00

Skilled Labour

0.2500

day

450.00

112.50

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

H.C. of Electric Auto Gas Cutter Set

3.0000

day

500.00

1500.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

1.0000

day

1000.00

1000.00

H.C. of Welding Machine

3.0000

day

500.00

1500.00

H.C. of Grinding Machine

3.0000

day

100.00

300.00 35976.90

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1:

40294.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

41100.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

45210.01

VAT

6% of Total

IT

4% of Total

3014.00 2009.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4317.23

50233.35

Page: 1777 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.03.04

2 Size: 1.65m x 1.575m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

7.0000

m

820.00

5740.00

85.0000

kg

59.00

5015.00

1.0000

each

1643.00

1643.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm) MS Angle, Flat bar, Z bar Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm) MS Plate (8mm thick)

245.0000

kg

70.00

17150.00

Fitter

2.0000

day

680.00

1360.00

Foreman

0.4220

day

800.00

337.60

Plumber/ Electric Mistry/ Painter

4.0000

day

680.00

2720.00

Welder

12.0000

day

680.00

8160.00

Skilled Labour

0.3270

day

450.00

147.15

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

H.C. of Electric Auto Gas Cutter Set

4.0000

day

500.00

2000.00

H.C. of Vertical Drill Machine

2.0000

day

150.00

300.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

2.0000

day

1000.00

2000.00

H.C. of Welding Machine

4.0000

day

500.00

2000.00

H.C. of Grinding Machine

4.0000

day

100.00

400.00 50442.75

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1:

56495.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

57625.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

63388.38

VAT

6% of Total

IT

4% of Total

4225.89 2817.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6053.13

70431.53

Page: 1778 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.03.05

2 Size: 1.65m x 1.875m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

7.6000

m

820.00

6232.00

117.5000

kg

59.00

6932.50

1643.00

1643.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm) MS Angle, Flat bar, Z bar Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm) MS Plate (8mm thick)

1.0000

each

266.0000

kg

70.00

18620.00

Fitter

2.0000

day

680.00

1360.00

Foreman

0.5000

day

800.00

400.00

Plumber/ Electric Mistry/ Painter

4.0000

day

680.00

2720.00

Welder

12.0000

day

680.00

8160.00

Skilled Labour

0.4000

day

450.00

180.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

H.C. of Electric Auto Gas Cutter Set

4.0000

day

500.00

2000.00

H.C. of Vertical Drill Machine

2.0000

day

150.00

300.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

2.0000

day

1000.00

2000.00

H.C. of Welding Machine

4.0000

day

500.00

2000.00

H.C. of Grinding Machine

4.0000

day

100.00

400.00 54417.50

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1:

60947.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62166.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

68383.21

VAT

6% of Total

IT

4% of Total

4558.88 3039.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6530.10

75981.34

Page: 1779 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.03.06

2 Size: 1.65m x 2.075m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8.4120

m

820.00

6897.84

130.0400

kg

59.00

7672.36

1643.00

1643.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm) MS Angle, Flat bar, Z bar Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm) MS Plate (8mm thick)

1.0000

each

294.3800

kg

70.00

20606.60

Fitter

2.2000

day

680.00

1496.00

Foreman

0.5500

day

800.00

440.00

Plumber/ Electric Mistry/ Painter

4.4300

day

680.00

3012.40

Welder

13.2000

day

680.00

8976.00

Skilled Labour

0.4500

day

450.00

202.50

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.1500

day

470.00

540.50

H.C. of Electric Auto Gas Cutter Set

4.4500

day

500.00

2225.00

H.C. of Vertical Drill Machine

2.2100

day

150.00

331.50

H.C. of Shaper Machine

1.1000

day

1000.00

1100.00

H.C. of Lathe Machine

2.2100

day

1000.00

2210.00

H.C. of Welding Machine

4.4500

day

500.00

2225.00

H.C. of Grinding Machine

4.4500

day

100.00

445.00 60023.70

Subtotal-A: Form work

( +14.00 % on Subtotal-A )

Subtotal-A1:

68427.02

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

69795.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

76775.11

VAT

6% of Total

IT

4% of Total

5118.34 3412.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8403.32

85305.68

Page: 1780 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.08.04

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Manufacturing and supplying of M.S Flap gate shutter of 8mm thick M.S skin plate and stiffener with minimum 75mmx75mmx10mm M.S angle as frame, horizontal & vertical beams,100mmx45mmx16mm p-type rubber seal, fixed with 10mm dia x63.5mm M.S counter sink and hex nuts & bolts and 40mmx10mm M.S strip as clamp drilled spaces @150mm c/c hinge assembled with gate and wall bracket, link arm of 19mm thick M.S plate, 4 nos. 25mm diax150mm stainless steel hinge pin with proper thread, and nut, cotter pin and washer as per approved design with a prime coat of red oxide where necessary etc. all complete as per drawing specification and direction of the Engineer in charge

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1781 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.04.01

2 Size: 1.05m x 0.975m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

4.4000

m

820.00

3608.00

MS Angle, Flat bar, Z bar

90.3600

kg

59.00

5331.24

MS Angle, Flat bar, Z bar

10.1700

kg

59.00

600.03

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm)

Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm)

4.0000

each

1643.00

6572.00

MS Plate (20mm thick)

18.0000

kg

70.00

1260.00

MS Plate (8mm thick)

77.5000

kg

70.00

5425.00

Fitter

2.0000

day

680.00

1360.00

Foreman

0.5000

day

800.00

400.00

Plumber/ Electric Mistry/ Painter

0.2020

day

680.00

137.36

Welder

2.0000

day

680.00

1360.00

Skilled Labour

8.0000

day

450.00

3600.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1620

day

470.00

76.14

H.C. of Electric Auto Gas Cutter Set

2.0000

day

500.00

1000.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

1.0000

day

1000.00

1000.00

H.C. of Welding Machine

2.0000

day

500.00

1000.00

H.C. of Grinding Machine

2.0000

day

100.00

200.00 34079.77

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

4089.57 38169.34

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

38932.73

10% Profit ( Add 10% on Subtotal-B) :

42826.00

6% of Total

2855.07 Page: 1782 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

1903.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

47584.45

Page: 1783 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.04.02

2 Size: 1.35m x 1.275m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

5.8000

m

820.00

4756.00

MS Angle, Flat bar, Z bar

100.0000

kg

59.00

5900.00

MS Angle, Flat bar, Z bar

14.0000

kg

59.00

826.00

Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm)

4.0000

each

1643.00

6572.00

MS Plate (20mm thick)

8.0000

kg

70.00

560.00

122.0000

kg

70.00

8540.00

Fitter

3.0000

day

680.00

2040.00

Foreman

1.0000

day

800.00

800.00

Plumber/ Electric Mistry/ Painter

0.3126

day

680.00

212.57

Welder

3.0000

day

680.00

2040.00

10.0000

day

450.00

4500.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50

H.C. of Electric Auto Gas Cutter Set

3.0000

day

500.00

1500.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

1.0000

day

1000.00

1000.00

H.C. of Welding Machine

3.0000

day

500.00

1500.00

H.C. of Grinding Machine

3.0000

day

100.00

300.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm)

MS Plate (8mm thick)

Skilled Labour

42314.07

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

5077.69 47391.76

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

48339.59

10% Profit ( Add 10% on Subtotal-B) :

53173.55

6% of Total

3544.90 Page: 1784 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

2363.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

59081.72

Page: 1785 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.04.03

2 Size: 1.35m x 1.675m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

5.8000

m

820.00

4756.00

MS Angle, Flat bar, Z bar

100.0000

kg

59.00

5900.00

MS Angle, Flat bar, Z bar

14.0000

kg

59.00

826.00

Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm)

4.0000

each

1643.00

6572.00

MS Plate (20mm thick)

8.0000

kg

70.00

560.00

122.0000

kg

70.00

8540.00

Fitter

3.0000

day

680.00

2040.00

Foreman

1.0000

day

800.00

800.00

Plumber/ Electric Mistry/ Painter

0.3130

day

680.00

212.84

Welder

3.0000

day

680.00

2040.00

10.0000

day

450.00

4500.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50

H.C. of Electric Auto Gas Cutter Set

3.0000

day

500.00

1500.00

H.C. of Vertical Drill Machine

1.0000

day

150.00

150.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

1.0000

day

1000.00

1000.00

H.C. of Welding Machine

3.0000

day

500.00

1500.00

H.C. of Grinding Machine

3.0000

day

100.00

300.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm)

MS Plate (8mm thick)

Skilled Labour

42314.34

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

5077.72 47392.06

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

48339.90

10% Profit ( Add 10% on Subtotal-B) :

53173.89

6% of Total

3544.93 Page: 1786 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

2363.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

59082.10

Page: 1787 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.04.04

2 Size: 1.65m x 1.575m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

7.0000

m

820.00

5740.00

MS Angle, Flat bar, Z bar

125.0000

kg

59.00

7375.00

MS Angle, Flat bar, Z bar

14.0000

kg

59.00

826.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm)

Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm)

4.0000

each

1643.00

6572.00

MS Plate (20mm thick)

24.0000

kg

70.00

1680.00

MS Plate (8mm thick)

197.0000

kg

70.00

13790.00

Fitter

4.0000

day

680.00

2720.00

Foreman

2.0000

day

800.00

1600.00

Plumber/ Electric Mistry/ Painter

0.4220

day

680.00

286.96

Welder

4.0000

day

680.00

2720.00

12.0000

day

450.00

5400.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.3370

day

470.00

158.39

H.C. of Electric Auto Gas Cutter Set

4.0000

day

500.00

2000.00

H.C. of Vertical Drill Machine

2.0000

day

150.00

300.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

2.0000

day

1000.00

2000.00

H.C. of Welding Machine

4.0000

day

500.00

2000.00

H.C. of Grinding Machine

4.0000

day

100.00

400.00

Skilled Labour

56568.35

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

6788.20 63356.55

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

64623.68

10% Profit ( Add 10% on Subtotal-B) :

71086.05

6% of Total

4739.07 Page: 1788 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

3159.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

78984.50

Page: 1789 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.04.05

2 Size: 1.65m x 1.875m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

7.6000

m

820.00

6232.00

MS Angle, Flat bar, Z bar

180.0000

kg

59.00

10620.00

MS Angle, Flat bar, Z bar

21.0000

kg

59.00

1239.00

5

Amount 8

each Rubber Seal (W=75mm, T=12mm, B=25mm)

Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm)

4.0000

each

1643.00

6572.00

MS Plate (20mm thick)

24.0000

kg

70.00

1680.00

MS Plate (8mm thick)

218.0000

kg

70.00

15260.00

Fitter

4.0000

day

680.00

2720.00

Foreman

2.0000

day

800.00

1600.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Welder

4.0000

day

680.00

2720.00

16.0000

day

450.00

7200.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4000

day

470.00

188.00

H.C. of Electric Auto Gas Cutter Set

4.0000

day

500.00

2000.00

H.C. of Vertical Drill Machine

2.0000

day

150.00

300.00

H.C. of Shaper Machine

1.0000

day

1000.00

1000.00

H.C. of Lathe Machine

2.0000

day

1000.00

2000.00

H.C. of Welding Machine

4.0000

day

500.00

2000.00

H.C. of Grinding Machine

4.0000

day

100.00

400.00

Skilled Labour

64071.00

Subtotal-A: Other necessary accessories and material

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

7688.52 71759.52

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

73194.71

10% Profit ( Add 10% on Subtotal-B) :

80514.18

6% of Total

5367.61 Page: 1790 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

3578.41 Total:

6.08.05

Labour charge for fitting and fixing of M.S vertical lift gate/flap gate shutters of different size including making holes in concrete for hooking arrangements with supply of necessary materials, tools and other accessories required for fitting the same to regulator/sluice and mending the damages with C.C (1:2:4), removing the spoils etc. all complete as per direction of the Engineer in charge.

6.08.05.01

Size: 1.05m x 0.975m

each Jute Rope

1.5000

kg

120.00

180.00

Nylon Rope

2.0000

kg

140.00

280.00

Borak Bamboo (75mm to 100mm)

22.5000

m

42.00

945.00

Fitter

2.0000

day

680.00

1360.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Chain Hoist (3 tons)

2.0000

day

1000.00

2000.00

H.C. of Tripod Stand

2.0000

day

400.00

800.00 9165.00

Subtotal-A: Subtotal-B: Subtotal-C:

9348.30

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10283.13

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

685.54 457.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

89460.20

11425.70

Page: 1791 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.05.02

2 Size: 1.35m x 1.275m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Jute Rope

1.5000

kg

120.00

180.00

Nylon Rope

2.0000

kg

140.00

280.00

22.5000

m

42.00

945.00

Borak Bamboo (75mm to 100mm) Fitter

2.0000

day

680.00

1360.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Chain Hoist (3 tons)

2.0000

day

1000.00

2000.00

H.C. of Tripod Stand

2.0000

day

400.00

800.00 9165.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9348.30 10283.13 685.54 457.03

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11425.70

Page: 1792 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.05.03

2 Size: 1.35m x 1.675m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Jute Rope

1.5000

kg

120.00

180.00

Nylon Rope

2.0000

kg

140.00

280.00

22.5000

m

42.00

945.00

Borak Bamboo (75mm to 100mm) Fitter

2.0000

day

680.00

1360.00

Skilled Labour

8.0000

day

450.00

3600.00

H.C. of Chain Hoist (3 tons)

2.0000

day

1000.00

2000.00

H.C. of Tripod Stand

2.0000

day

400.00

800.00 9165.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9348.30 10283.13 685.54 457.03

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11425.70

Page: 1793 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.05.04

2 Size: 1.65m x 1.575m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Jute Rope

2.0000

kg

120.00

240.00

Nylon Rope

3.0000

kg

140.00

420.00

30.0000

m

42.00

1260.00

Borak Bamboo (75mm to 100mm) Fitter

2.0000

day

680.00

1360.00

10.0000

day

450.00

4500.00

H.C. of Chain Hoist (3 tons)

2.0000

day

1000.00

2000.00

H.C. of Tripod Stand

2.0000

day

400.00

800.00

Skilled Labour

10580.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10791.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11870.76

VAT

6% of Total

IT

4% of Total

791.38 527.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13189.73

Page: 1794 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.05.05

2 Size: 1.65m x 1.875m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Jute Rope

2.0000

kg

120.00

240.00

Nylon Rope

3.0000

kg

140.00

420.00

30.0000

m

42.00

1260.00

Borak Bamboo (75mm to 100mm) Fitter

2.0000

day

680.00

1360.00

10.0000

day

450.00

4500.00

H.C. of Chain Hoist (3 tons)

2.0000

day

1000.00

2000.00

H.C. of Tripod Stand

2.0000

day

400.00

800.00

Skilled Labour

10580.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10791.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11870.76

VAT

6% of Total

IT

4% of Total

791.38 527.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13189.73

Page: 1795 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.05.06

2 Size 1.65mx2.075m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Jute Rope

2.2100

kg

120.00

265.20

Nylon Rope

3.3200

kg

140.00

464.80

33.2000

m

42.00

1394.40

Borak Bamboo (75mm to 100mm) Fitter

2.2100

day

680.00

1502.80

11.0670

day

450.00

4980.15

H.C. of Chain Hoist (3 tons)

2.2100

day

1000.00

2210.00

H.C. of Tripod Stand

2.2200

day

400.00

888.00

Skilled Labour

11705.35

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11939.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13133.40

VAT

6% of Total

IT

4% of Total

875.56 583.71 Total:

6.08.06

14592.67

Labour charge for removal of M.S Gates and Hoists from all types of structures with all leads and lifts including hire charge of boat, chain pulley, bamboo ropes, etc. and re-fixing the same in original level, line and grade after painting (excluding the cost of painting) etc. all complete as direction of the Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1796 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.06.01

2 Size 1.05m x 0.975m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

1.6500

kg

140.00

231.00

18.0000

m

42.00

756.00

Fitter

0.4100

day

680.00

278.80

Skilled Labour

0.9900

day

450.00

445.50

Ordinary Labour

0.6600

day

370.00

244.20

H.C. of Chain Pulley (1.5 ton)

0.4100

day

500.00

205.00

H.C. of Engine Boat

0.1280

day

1000.00

128.00

5

Amount

each Nylon Rope Borak Bamboo (75mm to 100mm)

2288.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2334.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2567.70

VAT

6% of Total

IT

4% of Total

171.18 114.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2853.00

Page: 1797 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.06.02

2 Size 1.35m x 1.275m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

1.6500

kg

140.00

231.00

18.0000

m

42.00

756.00

Fitter

0.4100

day

680.00

278.80

Skilled Labour

0.9900

day

450.00

445.50

Ordinary Labour

0.6600

day

370.00

244.20

H.C. of Chain Pulley (1.5 ton)

0.4100

day

500.00

205.00

H.C. of Engine Boat

0.1280

day

1000.00

128.00

5

Amount

each Nylon Rope Borak Bamboo (75mm to 100mm)

2288.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2334.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2567.70

VAT

6% of Total

IT

4% of Total

171.18 114.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2853.00

Page: 1798 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.06.03

2 Size 1.35m x 1.675m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

1.6500

kg

140.00

231.00

18.0000

m

42.00

756.00

Fitter

0.4100

day

680.00

278.80

Skilled Labour

0.9900

day

450.00

445.50

Ordinary Labour

0.6600

day

370.00

244.20

H.C. of Chain Pulley (1.5 ton)

0.4100

day

500.00

205.00

H.C. of Engine Boat

0.1280

day

1000.00

128.00

5

Amount

each Nylon Rope Borak Bamboo (75mm to 100mm)

2288.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2334.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2567.70

VAT

6% of Total

IT

4% of Total

171.18 114.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2853.00

Page: 1799 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.06.04

2 Size 1.65m x 1.575m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

2.0000

kg

140.00

280.00

18.0000

m

42.00

756.00

Fitter

0.5000

day

680.00

340.00

Skilled Labour

1.2000

day

450.00

540.00

Ordinary Labour

0.8000

day

370.00

296.00

H.C. of Chain Pulley (1.5 ton)

0.5000

day

500.00

250.00

H.C. of Engine Boat

0.1560

day

1000.00

156.00

5

Amount

each Nylon Rope Borak Bamboo (75mm to 100mm)

2618.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2670.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2937.40

VAT

6% of Total

IT

4% of Total

195.83 130.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3263.77

Page: 1800 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.08.06.05

2 Size 1.65m x 1.875m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

8

2.0000

kg

140.00

280.00

18.0000

m

42.00

756.00

Fitter

0.5000

day

680.00

340.00

Skilled Labour

1.2000

day

450.00

540.00

Ordinary Labour

0.8000

day

370.00

296.00

H.C. of Chain Pulley (1.5 ton)

0.5000

day

500.00

250.00

H.C. of Engine Boat

0.1562

day

1000.00

156.20

5

Amount

each Nylon Rope Borak Bamboo (75mm to 100mm)

2618.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2670.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2937.62

VAT

6% of Total

IT

4% of Total

195.84 130.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3264.02

Page: 1801 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.08.07

2 Supplying fitting, fixing fall boards of different dimensions of pressure treated Garjon or Sundari timber for Regulators, Sluices, Water Retention Structures and similar hydraulic structures including fixing, lifting hooks in position, making water tight, filling grooves, testing etc. complete as per drawing and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Sundari/ Garzen

1.0200

m3

67580.00

68931.60

MS Rod (Plain, 40 Grade)

35.0000

kg

45.00

1575.00

Carpenter

16.0000

day

680.00

10880.00

Skilled Labour

18.0000

day

450.00

8100.00 89486.60

Subtotal-A: Subtotal-B: Subtotal-C:

91276.33

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100403.97

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6693.60 4462.40 Total:

6.08.08

Supply of Chain Pulley

6.08.08.1

1.5 tons Capacity

LS

6.08.08.2

3.0 tons Capacity

LS

6.08.08.3

5.0 tons Capacity

LS

Note : Rates of all items should be inclusive of all supply and carriage.

111559.96

Page: 1802 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.08.09

Detailed Analysis Brief Description of Item 2 Supplying fitting fixing of best quality P-type Rubber seal (W=75mm,T=12mm, B=25mm) for M.S Vertical Lift gate/ M.S Flap gate with nut bolt including the cost of all materials where necessary as per specification etc, all complete and direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

Rubber Seal (W=75mm, T=12mm, B=25mm)

1.0200

m

820.00

836.40

Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm)

0.0800

each

1643.00

131.44

Skilled Labour

0.0400

day

450.00

18.00 985.84

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1005.56

10% Profit ( Add 10% on Subtotal-B) :

1106.11

VAT

6% of Total

IT

4% of Total

73.74 49.16 Total:

6.08.10

Supplying fitting fixing of best quality U-type Rubber seal to provide bottom seal of M.S Vertical Lift gate with nut bolt including the cost of all materials where necessary as per specification etc, all complete and direction of E-I-C.

m

Rubber Seal (W=75mm, T=12mm, B=25mm)

1.0200

m

820.00

836.40

Nuts & Hinge Pin Hex. Head (ss, 25mmx150mm)

0.0900

each

1643.00

147.87

Skilled Labour

0.0600

day

450.00

27.00 1011.27

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1031.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1134.64

VAT

6% of Total

75.64

IT

4% of Total

50.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1229.01

1260.72

Page: 1803 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

6.09.01

Supplying MS pipes of standard thickness including painting with anticorrosive paint, laying in position and true to alignment, fitting, fixing, joining by continuous welding etc. all complete as per specifications in the drawings and as per direction of the Engineer in charge.

6.09.01.1

Internal diameter: 150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 4mm thick 150mm dia MS pipe-5mm thick

1.0000

m

2624.00

Red Oxide

0.0460

kg

197.00

9.06

Welder

0.1600

day

680.00

108.80

Welder Helper

0.0500

day

470.00

23.50

Ordinary Labour

0.1500

day

370.00

55.50

H.C. of Welding Machine

0.0200

day

500.00

10.00 2830.86

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2887.48

10% Profit ( Add 10% on Subtotal-B) :

3176.23

VAT

6% of Total

IT

4% of Total

211.75 141.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2624.00

3529.14

Page: 1804 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.01.2

2 Internal diameter: 200mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m MS Pipe (200mm dia)

1.0000

m

3615.00

3615.00

Red Oxide

0.0620

kg

197.00

12.21

Welder

0.2100

day

680.00

142.80

Welder Helper

0.0660

day

470.00

31.02

Ordinary Labour

0.2000

day

370.00

74.00

H.C. of Welding Machine

0.0300

day

500.00

15.00 3890.03

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3967.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4364.62

VAT

6% of Total

IT

4% of Total

290.97 193.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4849.58

Page: 1805 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.01.3

2 Internal diameter: 300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m MS Pipe (300mm dia)

1.0000

m

5400.00

5400.00

Red Oxide

0.0460

kg

197.00

9.06

Welder

0.1600

day

680.00

108.80

Welder Helper

0.0500

day

470.00

23.50

Ordinary Labour

0.1800

day

370.00

66.60

H.C. of Welding Machine

0.0400

day

500.00

20.00 5627.96

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5740.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6314.57

VAT

6% of Total

IT

4% of Total

420.97 280.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7016.19

Page: 1806 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.01.4

Detailed Analysis Brief Description of Item 2 Internal Diameter: 400mm (wall thickness 6mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m MS Pipe (400mm internal dia with 6mm wall thickness)

1.0000

m

6800.00

6800.00

Red Oxide

0.3600

kg

197.00

70.92

Welder

0.1500

day

680.00

102.00

Welder Helper

0.0600

day

470.00

28.20

Ordinary Labour

0.1800

day

370.00

66.60

H.C. of Welding Machine

0.0200

day

500.00

10.00 7077.72

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7219.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7941.20

VAT

6% of Total

IT

4% of Total

529.41 352.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8823.56

Page: 1807 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.01.5

Detailed Analysis Brief Description of Item 2 Internal Diameter: 450mm(wall thickness 6mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m MS Pipe (450mm internal dia. with 6mm wall thickness)

1.0000

m

9350.00

9350.00

Red Oxide

0.4140

kg

197.00

81.56

Welder

0.2000

day

680.00

136.00

Welder Helper

0.0700

day

470.00

32.90

Ordinary Labour

0.2000

day

370.00

74.00

H.C. of Welding Machine

0.0200

day

500.00

10.00 9684.46

Subtotal-A: Subtotal-B: Subtotal-C:

9878.15

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10865.96

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

724.40 482.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12073.29

Page: 1808 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.01.6

2 Internal Diameter: 600mm(wall thickness 7mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m MS Pipe (600mm internal dia. With 7mm wall thickness)

1.0000

m

12500.00

12500.00

Red Oxide

0.7360

kg

197.00

144.99

Welder

0.2500

day

680.00

170.00

Welder Helper

0.1000

day

470.00

47.00

Ordinary Labour

0.2400

day

370.00

88.80

H.C. of Welding Machine

0.0300

day

500.00

15.00 12965.79

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13225.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14547.62

VAT

6% of Total

IT

4% of Total

969.84 646.56 Total:

6.09.02

Providing GI Pipe including placing in position as per drawing & including cost of all materials , their carrying & labour etc. all complete as per direction of the Engineering -in-Charge.

6.09.02.1

38mm dia GI Pipe

m 40mm dia GI pipe of 2.9mm wall thick

1.0000

m

380.48

380.48

Skilled Labour

0.0800

day

450.00

36.00 416.48

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

424.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

467.29

VAT

6% of Total

IT

4% of Total

31.15 20.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

16164.02

519.21

Page: 1809 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.02.2

2 50mm dia GI Pipe

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 50mm dia GI pipe of 2.9mm wall thick

1.0000

m

457.42

457.42

Skilled Labour

0.0800

day

450.00

36.00 493.42

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

503.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

553.62

VAT

6% of Total

36.91

IT

4% of Total

24.61 Total:

6.09.03

Supplying, fitting and fixing silt extractor pipe of 100mm dia. 600mm long GI pipe and supply , fitting and fixing of 600mm dia brass stop cork with GI pipe etc. as per drawing and direction of Engineer-in-charge.

each

100mm dia GI pipe with socket(3.65mm Thick)

0.6000

m

1421.00

20mm dia brass stop cock

1.0000

each

650.00

650.00

Head Mason

0.5000

day

650.00

325.00

852.60

1827.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1864.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2050.57

VAT

6% of Total

136.70

IT

4% of Total

91.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

615.13

2278.41

Page: 1810 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.04

Detailed Analysis Brief Description of Item 2 Welding at the splicing point/at the joint of GI Pipe using electrodes including the cost of all materials , labours, tools & equipments, the cost of power etc. complete as per drawing , Specifications and direction of the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Electrode

0.0200

pkt

810.00

16.20

Welder

0.0025

day

680.00

1.70

H.C. of Welding Machine

0.0025

day

500.00

1.25 19.15

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19.53

10% Profit ( Add 10% on Subtotal-B) :

21.49

VAT

6% of Total

IT

4% of Total

1.43 0.95 Total:

6.09.05

23.87

Supplying pre-cast RCC Pipes including colors of different dia manufactured as per design manual including casting, curing, laying in position, from finished type by steel form works as per the design manual schedule all complete as per direction of the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1811 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.05.1

2 600mm dia, 75mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (20mm down graded)

0.1200

m3

2940.00

352.80

Sand (FM - 1.5)

0.0600

m3

795.00

47.70

Ordinary Portland Cement (CEM I, 52.5N)

1.0600

bag

455.00

482.30

MS Rod (Plain, 40 Grade)

12.7200

kg

45.00

572.40

Mason

0.0580

day

550.00

31.90

Ordinary Labour

0.2800

day

370.00

103.60

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0090

day

1200.00

10.80 1601.50

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1:

1817.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1854.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2039.46

VAT

6% of Total

IT

4% of Total

135.96 90.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

216.20

2266.07

Page: 1812 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.05.2

2 900mm dia, 100mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (20mm down graded)

0.2400

m3

2940.00

705.60

Sand (FM - 1.5)

0.1200

m3

795.00

95.40

Ordinary Portland Cement (CEM I, 52.5N)

2.1600

bag

455.00

982.80

MS Rod (Plain, 40 Grade)

18.8200

kg

45.00

846.90

Mason

0.0580

day

550.00

31.90

Ordinary Labour

0.2800

day

370.00

103.60

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0130

day

1200.00

15.60 2781.80

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1:

3157.34

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3220.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3542.54

VAT

6% of Total

IT

4% of Total

236.17 157.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

375.54

3936.15

Page: 1813 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.05.3

2 1200mm dia, 100mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (20mm down graded)

0.3200

m3

2940.00

940.80

Sand (FM - 1.5)

0.1600

m3

795.00

127.20

Ordinary Portland Cement (CEM I, 52.5N)

2.9000

bag

455.00

1319.50

MS Rod (Plain, 40 Grade)

23.6800

kg

45.00

1065.60

Mason

0.0580

day

550.00

31.90

Ordinary Labour

0.2800

day

370.00

103.60

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0130

day

1200.00

15.60 3604.20

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1:

4090.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4172.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4589.84

VAT

6% of Total

IT

4% of Total

305.99 203.99 Total:

6.09.06

486.57

5099.82

Supplying pre-cast RCC Pipes of different dia manufactured with 12mm down graded dust free 1st class brick chips (1:2:4), curing, laying in position, from finished type by steel form works as per the design specifications all complete as per direction of the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1814 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.01

Detailed Analysis Brief Description of Item 2 300mm internal dia, 50mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.0480

m3

3049.00

146.35

Sand (FM - 1.5)

0.0240

m3

795.00

19.08

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3390

bag

430.00

145.77

M.S. Ribbed/ Deformed Bar (Grade 300)

2.4000

kg

54.00

129.60

Head Mason

0.0480

day

650.00

31.20

Skilled Labour

0.2300

day

450.00

103.50

Ordinary Labour

0.3500

day

370.00

129.50

H.C. of Lister Engine

0.0140

day

10000.00

140.00 845.00

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

959.08 978.26

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1076.08

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

71.74 47.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

114.08

1195.65

Page: 1815 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.02

Detailed Analysis Brief Description of Item 2 350mm internal dia, 50mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.0549

m3

3049.00

167.39

Sand (FM - 1.5)

0.0275

m3

795.00

21.86

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.3880

bag

430.00

166.84

M.S. Ribbed/ Deformed Bar (Grade 300)

2.6600

kg

54.00

143.64

Head Mason

0.0550

day

650.00

35.75

Skilled Labour

0.2500

day

450.00

112.50

Ordinary Labour

0.3800

day

370.00

140.60

H.C. of Lister Engine

0.0150

day

10000.00

150.00 938.58

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1065.29 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1086.60

10% Profit ( Add 10% on Subtotal-B) :

1195.26

VAT

6% of Total

IT

4% of Total

79.68 53.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

126.71

1328.06

Page: 1816 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.03

Detailed Analysis Brief Description of Item 2 400mm internal dia, 50mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.0618

m3

3049.00

188.43

Sand (FM - 1.5)

0.0309

m3

795.00

24.57

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.4363

bag

430.00

187.61

M.S. Ribbed/ Deformed Bar (Grade 300)

2.8900

kg

54.00

156.06

Head Mason

0.0600

day

650.00

39.00

Skilled Labour

0.2500

day

450.00

112.50

Ordinary Labour

0.4000

day

370.00

148.00

H.C. of Lister Engine

0.0150

day

10000.00

150.00 1006.16

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1141.99 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1164.83

10% Profit ( Add 10% on Subtotal-B) :

1281.32

VAT

6% of Total

IT

4% of Total

85.42 56.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

135.83

1423.69

Page: 1817 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.04

Detailed Analysis Brief Description of Item 2 450mm internal dia, 50mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.0686

m3

3049.00

209.16

Sand (FM - 1.5)

0.0343

m3

795.00

27.27

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.4848

bag

430.00

208.46

M.S. Ribbed/ Deformed Bar (Grade 300)

3.0300

kg

54.00

163.62

Head Mason

0.0630

day

650.00

40.95

Skilled Labour

0.2700

day

450.00

121.50

Ordinary Labour

0.4100

day

370.00

151.70

H.C. of Lister Engine

0.0160

day

10000.00

160.00 1082.66

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1228.82 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1253.40

10% Profit ( Add 10% on Subtotal-B) :

1378.74

VAT

6% of Total

IT

4% of Total

91.92 61.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

146.16

1531.93

Page: 1818 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.05

Detailed Analysis Brief Description of Item 2 500mm internal dia, 50mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.0755

m3

3049.00

230.20

Sand (FM - 1.5)

0.0378

m3

795.00

30.05

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.5333

bag

430.00

229.32

M.S. Ribbed/ Deformed Bar (Grade 300)

3.2500

kg

54.00

175.50

Head Mason

0.0680

day

650.00

44.20

Skilled Labour

0.2700

day

450.00

121.50

Ordinary Labour

0.4200

day

370.00

155.40

H.C. of Lister Engine

0.0160

day

10000.00

160.00 1146.17

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1300.90 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1326.92

10% Profit ( Add 10% on Subtotal-B) :

1459.61

VAT

6% of Total

IT

4% of Total

97.31 64.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

154.73

1621.79

Page: 1819 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.06

Detailed Analysis Brief Description of Item 2 550mm internal dia, 75mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.1287

m3

3049.00

392.41

Sand (FM - 1.5)

0.0643

m3

795.00

51.12

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.9090

bag

430.00

390.87

M.S. Ribbed/ Deformed Bar (Grade 300)

3.8000

kg

54.00

205.20

Head Mason

0.0700

day

650.00

45.50

Skilled Labour

0.3000

day

450.00

135.00

Ordinary Labour

0.4400

day

370.00

162.80

H.C. of Lister Engine

0.0160

day

10000.00

160.00 1542.89

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1751.19 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1786.21

10% Profit ( Add 10% on Subtotal-B) :

1964.83

VAT

6% of Total

IT

4% of Total

130.99 87.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

208.29

2183.14

Page: 1820 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.07

Detailed Analysis Brief Description of Item 2 600mm internal dia, 75mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.1390

m3

3049.00

423.81

Sand (FM - 1.5)

0.0695

m3

795.00

55.25

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.9818

bag

430.00

422.17

M.S. Ribbed/ Deformed Bar (Grade 300)

4.4900

kg

54.00

242.46

Head Mason

0.0720

day

650.00

46.80

Skilled Labour

0.3000

day

450.00

135.00

Ordinary Labour

0.4500

day

370.00

166.50

H.C. of Lister Engine

0.0170

day

10000.00

170.00 1662.00

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1886.37 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1924.09

10% Profit ( Add 10% on Subtotal-B) :

2116.50

VAT

6% of Total

IT

4% of Total

141.10 94.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

224.37

2351.67

Page: 1821 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.08

Detailed Analysis Brief Description of Item 2 650mm internal dia, 75mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.1493

m3

3049.00

455.22

Sand (FM - 1.5)

0.0746

m3

795.00

59.31

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.0545

bag

430.00

453.44

M.S. Ribbed/ Deformed Bar (Grade 300)

4.7400

kg

54.00

255.96

Head Mason

0.0750

day

650.00

48.75

Skilled Labour

0.3200

day

450.00

144.00

Ordinary Labour

0.4600

day

370.00

170.20

H.C. of Lister Engine

0.0170

day

10000.00

170.00 1756.87

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1994.04 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2033.93

10% Profit ( Add 10% on Subtotal-B) :

2237.32

VAT

6% of Total

IT

4% of Total

149.15 99.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

237.18

2485.91

Page: 1822 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.09

Detailed Analysis Brief Description of Item 2 700mm internal dia, 75mm thick

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1st Class Brick Chips (10mm down graded)

0.1596

m3

3049.00

486.62

Sand (FM - 1.5)

0.0798

m3

795.00

63.44

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.1272

bag

430.00

484.70

M.S. Ribbed/ Deformed Bar (Grade 300)

5.0300

kg

54.00

271.62

Head Mason

0.0760

day

650.00

49.40

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.4800

day

370.00

177.60

H.C. of Lister Engine

0.0180

day

10000.00

180.00 1861.88

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2113.23 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2155.50

10% Profit ( Add 10% on Subtotal-B) :

2371.05

VAT

6% of Total

IT

4% of Total

158.07 105.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

251.35

2634.49

Page: 1823 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.10

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

750mm internal dia, 100mm thick

m

Quantity 5

Unit

Rate

6

7

Amount 8

1st Class Brick Chips (10mm down graded)

0.2471

m3

3049.00

753.41

Sand (FM - 1.5)

0.1235

m3

795.00

98.18

Ordinary Portland Cement (CEM I, 52.5N)

1.7454

bag

455.00

794.16

M.S. Ribbed/ Deformed Bar (Grade 300)

6.0600

kg

54.00

327.24

Head Mason

0.0800

day

650.00

52.00

Skilled Labour

0.3500

day

450.00

157.50

Ordinary Labour

0.5200

day

370.00

192.40

H.C. of Lister Engine

0.0180

day

10000.00

180.00 2554.89

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2899.80 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2957.79

10% Profit ( Add 10% on Subtotal-B) :

3253.57

VAT

6% of Total

IT

4% of Total

216.90 144.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

344.91

3615.08

Page: 1824 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.11

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

800mm internal dia, 100mm thick

m

Quantity 5

Unit

Rate

6

7

Amount 8

1st Class Brick Chips (10mm down graded)

0.2471

m3

3049.00

753.41

Sand (FM - 1.5)

0.1235

m3

795.00

98.18

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.7454

bag

430.00

750.52

M.S. Ribbed/ Deformed Bar (Grade 300)

6.0600

kg

54.00

327.24

Head Mason

0.0800

day

650.00

52.00

Skilled Labour

0.3500

day

450.00

157.50

Ordinary Labour

0.5200

day

370.00

192.40

H.C. of Lister Engine

0.0180

day

10000.00

180.00 2511.25

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2850.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2907.28

10% Profit ( Add 10% on Subtotal-B) :

3198.00

VAT

6% of Total

IT

4% of Total

213.20 142.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

339.02

3553.34

Page: 1825 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.12

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

850mm internal dia, 100mm thick

m

Quantity 5

Unit

Rate

6

7

Amount 8

1st Class Brick Chips (10mm down graded)

0.2608

m3

3049.00

795.18

Sand (FM - 1.5)

0.1304

m3

795.00

103.67

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.8423

bag

430.00

792.19

M.S. Ribbed/ Deformed Bar (Grade 300)

6.3200

kg

54.00

341.28

Head Mason

0.0820

day

650.00

53.30

Skilled Labour

0.3600

day

450.00

162.00

Ordinary Labour

0.5400

day

370.00

199.80

H.C. of Lister Engine

0.0190

day

10000.00

190.00 2637.42

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2993.47 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3053.34

10% Profit ( Add 10% on Subtotal-B) :

3358.67

VAT

6% of Total

IT

4% of Total

223.91 149.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

356.05

3731.86

Page: 1826 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.06.13

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

900mm internal dia, 100mm thick

m

Quantity 5

Unit

Rate

6

7

Amount 8

1st Class Brick Chips (10mm down graded)

0.2745

m3

3049.00

836.95

Sand (FM - 1.5)

0.1373

m3

795.00

109.15

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

1.9400

bag

430.00

834.20

M.S. Ribbed/ Deformed Bar (Grade 300)

6.7900

kg

54.00

366.66

Head Mason

0.0850

day

650.00

55.25

Skilled Labour

0.3800

day

450.00

171.00

Ordinary Labour

0.5500

day

370.00

203.50

H.C. of Lister Engine

0.0190

day

10000.00

190.00 2766.71

Subtotal-A: Form work & all other remaining costs

( +13.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3140.22 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3203.02

10% Profit ( Add 10% on Subtotal-B) :

3523.33

VAT

6% of Total

IT

4% of Total

234.89 156.59 Total:

6.09.07

Supplying, fitting fixing and installation of 300mm dia Alfa valve as per drawing, specification and direction the Engineer-in-Charge.

6.09.08

Supplying and Installation of different diameter Gate Valve used in any pipe line system including different dia flange, dresser rubber washer, nut, bolts, gasket, welding, fitting, fixing etc. all complete as per drawing , specification and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

373.51

3914.81

LS

Page: 1827 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.01

2 500mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 500mm dia MS gate valve

1.0000

each

66500.00

66500.00

MS flange for 500mm dia pipe

4.0000

each

3800.00

15200.00

Nails/ Nut bolts/ Screw/ Spikes

5.7000

kg

65.00

370.50

Rubber Washer

4.0000

each

500mm dia drasser

1.0000

no

40.00

160.00

7200.00

7200.00 89430.50

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

100162.16 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102165.40

10% Profit ( Add 10% on Subtotal-B) :

112381.94

VAT

6% of Total

7492.13

IT

4% of Total

4994.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10731.66

124868.83

Page: 1828 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.02

2 450mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 450mm dia MS gate valve

1.0000

each

61600.00

61600.00

MS flange for 450mm dia pipe

4.0000

each

3500.00

14000.00

Nails/ Nut bolts/ Screw/ Spikes

6.7000

kg

65.00

435.50

6800.00

6800.00

40.00

160.00

450mm dia drasser

1.0000

no

Rubber Washer

4.0000

each

82995.50

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

92954.96 94814.06

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

104295.47

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

6953.03

IT

4% of Total

4635.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9959.46

115883.85

Page: 1829 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.03

2 400mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 400mm dia MS gate valve

1.0000

each

56000.00

56000.00

MS flange for 400mm dia pipe

4.0000

each

3200.00

12800.00

Nails/ Nut bolts/ Screw/ Spikes

6.2000

kg

65.00

403.00

Rubber Washer

4.0000

each

400mm dia drasser

1.0000

no

40.00

160.00

6500.00

6500.00 75863.00

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

84966.56 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

86665.89

10% Profit ( Add 10% on Subtotal-B) :

95332.48

VAT

6% of Total

6355.50

IT

4% of Total

4237.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9103.56

105924.98

Page: 1830 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.04

2 355mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 355mm dia MS gate valve

1.0000

each

50400.00

50400.00

MS flange for 355mm dia pipe

4.0000

each

2700.00

10800.00

Nails/ Nut bolts/ Screw/ Spikes

5.7000

kg

65.00

370.50

Rubber Washer

4.0000

each

355mm dia drasser

1.0000

no

40.00

160.00

6000.00

6000.00 67730.50

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

75858.16 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

77375.32

10% Profit ( Add 10% on Subtotal-B) :

85112.86

VAT

6% of Total

5674.19

IT

4% of Total

3782.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8127.66

94569.84

Page: 1831 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.05

2 315mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 315mm dia MS gate valve

1.0000

each

45000.00

45000.00

MS flange for 280mm dia pipe

4.0000

each

2500.00

10000.00

Nails/ Nut bolts/ Screw/ Spikes

5.3000

kg

65.00

344.50

Rubber Washer

4.0000

each

315mm dia drasser

1.0000

no

40.00

160.00

5500.00

5500.00 61004.50

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

68325.04 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

69691.54

10% Profit ( Add 10% on Subtotal-B) :

76660.69

VAT

6% of Total

5110.71

IT

4% of Total

3407.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7320.54

85178.55

Page: 1832 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.06

2 280mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 280mm dia MS gate valve

1.0000

each

38500.00

38500.00

MS flange for 280mm dia pipe

4.0000

each

2500.00

10000.00

Nails/ Nut bolts/ Screw/ Spikes

4.9000

kg

65.00

318.50

Rubber Washer

4.0000

each

280mm dia drasser

1.0000

no

40.00

160.00

5000.00

5000.00 53978.50

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

60455.92 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61665.04

10% Profit ( Add 10% on Subtotal-B) :

67831.54

VAT

6% of Total

4522.10

IT

4% of Total

3014.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6477.42

75368.38

Page: 1833 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.07

2 250mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 250mm dia MS gate valve

1.0000

each

35000.00

35000.00

MS flange for 250mm dia pipe

4.0000

each

2200.00

8800.00

Nails/ Nut bolts/ Screw/ Spikes

4.3000

kg

65.00

279.50

Rubber Washer

4.0000

each

250mm dia drasser

1.0000

no

40.00

160.00

4500.00

4500.00 48739.50

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

54588.24 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55680.00

10% Profit ( Add 10% on Subtotal-B) :

61248.01

VAT

6% of Total

4083.20

IT

4% of Total

2722.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5848.74

68053.34

Page: 1834 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.08

2 225mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 225mm dia MS gate valve

1.0000

each

33600.00

33600.00

MS flange for 225mm dia pipe

4.0000

each

2000.00

8000.00

Nails/ Nut bolts/ Screw/ Spikes

3.8000

kg

65.00

247.00

Rubber Washer

4.0000

each

225mm dia drasser

1.0000

no

40.00

160.00

4300.00

4300.00 46307.00

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

51863.84 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

52901.12

10% Profit ( Add 10% on Subtotal-B) :

58191.23

VAT

6% of Total

3879.42

IT

4% of Total

2586.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5556.84

64656.92

Page: 1835 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.09

2 200mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 200mm dia MS gate valve

1.0000

each

31000.00

31000.00

MS flange for 200mm dia pipe

4.0000

each

1800.00

7200.00

Nails/ Nut bolts/ Screw/ Spikes

3.2000

kg

65.00

208.00

Rubber Washer

4.0000

each

200mm dia drasser

1.0000

no

40.00

160.00

4000.00

4000.00 42568.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

43419.36

10% Profit ( Add 10% on Subtotal-B) :

47761.30

VAT

6% of Total

3184.09

IT

4% of Total

2122.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

53068.11

Page: 1836 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.08.10

2 150mm dia gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Gate Valve (150mm dia.)

1.0000

each

18500.00

18500.00

MS flange (150mm dia.)

4.0000

each

1400.00

5600.00

Nails/ Nut bolts/ Screw/ Spikes

2.8000

kg

65.00

182.00

Rubber Washer

4.0000

each

40.00

160.00

Drasser (150mm dia.)

1.0000

each

3500.00

3500.00 27942.00

Subtotal-A: welding fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

31295.04 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

31920.94

10% Profit ( Add 10% on Subtotal-B) :

35113.03

VAT

6% of Total

2340.87

IT

4% of Total

1560.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3353.04

39014.48

Page: 1837 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.09

Detailed Analysis Brief Description of Item 2 Supplying, fitting, fixing and installation of Air vent pipe (250mm dia, 25mm thick & 3000mm long CC pipe) for Water control structure, mass concrete with pacca nacca as per drawing and direction of Engineer-incharge. Height of the vent pipe should be up to the Hydraulic grade line.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1st Class Brick

282.0000

each

9.00

2538.00

1st Class Brick Chips (10mm down graded)

0.2460

m3

3049.00

750.05

Sand (FM - 1.8)

0.3500

m3

970.00

339.50

Ordinary Portland Cement (CEM I, 52.5N)

2.4930

bag

455.00

1134.32

27.8100

kg

45.00

1251.45

MS Rod (Plain, 40 Grade) Head Mason

0.0462

day

650.00

30.03

Mason

0.7041

day

550.00

387.26

Ordinary Labour

2.3860

day

370.00

882.82

Skilled Labour

0.5250

day

450.00

236.25

Re-bar Fabricator

0.0340

day

570.00

19.38

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0201

day

1200.00

24.12

Hire and running charges of Concrete Vibrator

0.0051

day

400.00

2.04 7595.21

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7747.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8521.83

VAT

6% of Total

568.12

IT

4% of Total

378.75 Total:

6.09.10

Supplying and fitting, fixing of best quality accessories for the steel pipe line.

6.09.10.1

as MS Flap cover Hinge at priming Inlet Top.

Note : Rates of all items should be inclusive of all supply and carriage.

9468.70

LS

Page: 1838 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

6.09.10.2

as Hand wheel along with stem shaft including fitting & fixing at top slab with base plate

6.09.11

Supplying, fitting and fixing of best quality accessories for the steel pipe line as hand wheel along with stem shaft including fitting & fixing at top slab with base plate.

6.09.11.1

Trash screen at inlet/outlet pipes (200-300mm dia)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

LS

set MS Angle, Flat bar, Z bar

9.8000

kg

59.00

578.20

Nails/ Nut bolts/ Screw/ Spikes

3.0900

kg

65.00

200.85

Plastic washer

6.0000

each

1.13

6.78

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.4000

day

370.00

148.00 978.83

Subtotal-A: Subtotal-B: Subtotal-C:

998.41

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1098.25

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

73.22

IT

4% of Total

48.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1220.27

Page: 1839 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.11.2

Detailed Analysis Brief Description of Item 2 Trash screen for top cover of sump well (3000mm dia)

Unit

Sub-Item

3

4

Quantity

Unit

Rate

Amount

5

6

7

213.8700

kg

59.00

12618.33

GI Wire Net (12 BWG) [Rhombus Size 75mm]

9.6200

m2

100.00

962.00

Skilled Labour

0.1300

day

450.00

58.50

Ordinary Labour

0.3300

day

370.00

122.10

8

set MS Angle, Flat bar, Z bar

13760.93

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14036.15

10% Profit ( Add 10% on Subtotal-B) :

15439.76

VAT

6% of Total

IT

4% of Total

1029.32 686.21 Total:

6.09.12

Supplying and laying 12BWG G.I. Wire 75mm rhombus mesh for required size & length of CC Block including placing in position by concrete block including cost of all materials, labour, etc. all complete as per direction of the E-I-C.

sqm

GI Wire Net (12 BWG) [Rhombus Size 75mm]

1.0000

m2

100.00

100.00

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.0292

day

370.00

10.80 119.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

122.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

134.42

VAT

6% of Total

IT

4% of Total

8.96 5.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17155.29

149.36

Page: 1840 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

6.09.13

Supplying and Installation of different diameter MS perforated Foot Valve including painting with anticorrosive paint, laying in position and true to the alignment. Fitting, fixing, joining by continuous welding etc. all completes per specifiations in the drawing and direction of the Engineering-in-Charge.

6.09.13.01

Internal Diameter:150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each MS Perforated Foot Valve (150mm dia)

1.0000

each

4500.00

4500.00

Mason

0.6500

day

550.00

357.50

Ordinary Labour

0.2000

day

370.00

74.00 4931.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5030.13

10% Profit ( Add 10% on Subtotal-B) :

5533.14

VAT

6% of Total

IT

4% of Total

368.88 245.92 Total:

6.09.13.02

Internal Diameter:200mm

each MS Perforated Foot Valve (200mm dia)

1.0000

each

5600.00

5600.00

Mason

0.7000

day

550.00

385.00

Ordinary Labour

0.2500

day

370.00

92.50 6077.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6199.05

10% Profit ( Add 10% on Subtotal-B) :

6818.96

VAT

6% of Total

IT

4% of Total

454.60 303.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6147.94

7576.62

Page: 1841 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

6.09.14

Supplying and Installation of different diameter of 90 degree Mala bend MS pipe including painting with anticorrosive paint, laying in position and true to the alignment. fitting, fixing, joining by continuous welding and/or flange connection etc. all completes per specifiations in the drawing and direction of the Engineering-in-Charge.

6.09.14.01

Internal Diameter:150mm (2.5mm thick)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each MS Mala Bend (150mm dia.)

1.0000

each

2800.00

2800.00

Mason

0.3500

day

550.00

192.50

Ordinary Labour

0.2000

day

370.00

74.00 3066.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3127.83

10% Profit ( Add 10% on Subtotal-B) :

3440.61

VAT

6% of Total

IT

4% of Total

229.37 152.92 Total:

6.09.14.02

Internal Diameter:200mm (3.0mm thick)

each MS Mala Bend (200mm dia.)

1.0000

each

3615.00

3615.00

Mason

0.3500

day

550.00

192.50

Ordinary Labour

0.2500

day

370.00

92.50 3900.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3978.00

10% Profit ( Add 10% on Subtotal-B) :

4375.80

VAT

6% of Total

IT

4% of Total

291.72 194.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3822.90

4862.00

Page: 1842 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.15

Detailed Analysis Brief Description of Item 2 Supplying fitting & fixing of best quality M.S angle(65 kg) Chasis (2100mmx600mm) made of 75mmx75mmx6mm thick etc. all complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS Angle, Flat bar, Z bar

65.0000

kg

59.00

3835.00

Mason

1.2200

day

550.00

671.00

Welder

0.9800

day

680.00

666.40

Ordinary Labour

0.4900

day

370.00

181.30 5353.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5460.77

10% Profit ( Add 10% on Subtotal-B) :

6006.85

VAT

6% of Total

IT

4% of Total

400.46 266.97 Total:

6.09.16

Supply and installation of 450mm width cat ladder prepared with 50mmx50mmx6mm MS Angle, 19mm dia MS rod @300mm c/c welded to MS angle including supply of all materials, labours, tools etc. all complete as per direction of the Engineer-in-Charge.

m

MS Angle, Flat bar, Z bar

9.4300

kg

59.00

556.37

MS Rod (Plain, 40 Grade)

4.0100

kg

45.00

180.45

Welder

0.0670

day

680.00

45.56

Welder Helper

0.1330

day

470.00

62.51 844.89

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

861.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

947.97

VAT

6% of Total

IT

4% of Total

63.20 42.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6674.28

1053.30

Page: 1843 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

6.09.17

Lifting the buried RCC pipes of different diameters from an average depth of 1.0m below ground level using tripod mounted block and tackle. Utmost care will be taken to avoid any damage to the pipes. The pipes must be cleaned of extraneous matter that has accured on the inside surfaces, raking where necessary. The joints must be raked clean to removed all redundant sealant materials. This needs to be carried out carefully to avoid damage to the pipe ends. Re-laying the pipes in a downstream direction .all complete as per design, specifications and direction of the Engineer-in- Charge.

6.09.17.01

Dia 300mm to dia 500mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Ordinary Labour

0.7500

day

370.00

277.50

H.C. of Chain Pulley (1.5 ton)

0.1250

day

500.00

62.50 340.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

346.80

10% Profit ( Add 10% on Subtotal-B) :

381.48

VAT

6% of Total

25.43

IT

4% of Total

16.95 Total:

6.09.17.02

Dia 550mm to dia 750mm

each Ordinary Labour

1.0000

day

370.00

370.00

H.C. of Chain Pulley (1.5 ton)

0.1500

day

500.00

75.00 445.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

453.90

10% Profit ( Add 10% on Subtotal-B) :

499.29

VAT

6% of Total

IT

4% of Total

33.29 22.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

423.87

554.77

Page: 1844 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.09.17.03

2 Dia 750mm to dia 900mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Ordinary Labour

1.2500

day

370.00

462.50

H.C. of Chain Pulley (1.5 ton)

0.2500

day

500.00

125.00 587.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

599.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

659.18

VAT

6% of Total

43.95

IT

4% of Total

29.30 Total:

6.09.18

Supplying of MS T-Joint (600mmX450mmX450mm) including painting with anticorrosive paint, laying in position and true to the alignment. Fitting, fixing, joining by continuous welding etc. all completeas per specifiations in the drawing and direction of the Engineering-in-Charge.

each

MS T-Joint (600mm X 450mm X 450mm)

1.0000

each

15250.00

15250.00

Red Oxide

0.0050

kg

197.00

0.99

Welder Welder Helper

0.3000

day

680.00

204.00

0.1500

day

470.00

70.50

Ordinary Labour

0.2000

day

370.00

74.00

H.C. of Chain Pulley (1.5 ton)

0.0200

day

500.00

10.00 15609.49

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15921.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17513.84

VAT

6% of Total

IT

4% of Total

1167.59 778.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

732.42

19459.82

Page: 1845 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.09.19

Detailed Analysis Brief Description of Item 2 Supplying and Installation of different diameter of 45 degree Mala bend MS pipe including painting with anticorrosive paint, laying in position and true to the alignment. fitting, fixing, joining by continuous welding and/or flange connection etc. all completes per specifiations in the drawing and direction of the Engineering-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS Bend (150mm dia.)

1.0000

each

2500.00

2500.00

Mason

0.3500

day

550.00

192.50

Ordinary Labour

0.2000

day

370.00

74.00 2766.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2821.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3104.01

VAT

6% of Total

IT

4% of Total

206.93 137.96 Total:

6.10.01

Supplying and laying of uPVC pipes of different diameter and wall thickness for at least 3.25 bar (32.00 m head) working pressure in accordance with ISO-4422 and ISO-4065, including placing in position, connecting and leak proof O-ring jointing using best quality elastomeric sealing gaskets, etc. completed including costs of all materials, labors, etc and costs of testing for complete leak proofness and repair and/or replacement of leaking joints , if any but excluding costs of earthworks in trench cutting & filling as per design drawings, specifications and as per Direction of Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

3448.90

m

Page: 1846 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.01.01

Detailed Analysis Brief Description of Item 2 For PVC Pipe: 160mm Dia, Wall Thickness 2.0mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

487.00

487.00

m PVC Pipe: External Dia 160mm & wall thickness 2.00mm

1.0000

487.00

Subtotal-A: Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

38.96

Subtotal-A1: Subtotal-B: Subtotal-C:

525.96 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

536.48

10% Profit ( Add 10% on Subtotal-B) :

590.13

VAT

6% of Total

IT

4% of Total

39.34 26.23 Total:

6.10.01.02

For PVC Pipe:180mm Dia, Wall Thickness 2.3mm

m PVC Pipe: External Dia 180mm & wall thickness 2.30mm

1.0000

m

604.00

Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

48.32

Subtotal-A1: Subtotal-B: Subtotal-C:

604.00 604.00

Subtotal-A:

652.32 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

665.37

10% Profit ( Add 10% on Subtotal-B) :

731.90

VAT

6% of Total

IT

4% of Total

48.79 32.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

655.70

813.23

Page: 1847 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.01.03

Detailed Analysis Brief Description of Item 2 For PVC Pipe: 200mm Dia, Wall Thickness 2.5mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

725.00

725.00

m PVC Pipe: External Dia 200mm & wall thickness 2.50mm

1.0000

725.00

Subtotal-A: Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

58.00

Subtotal-A1: Subtotal-B: Subtotal-C:

6.10.01.04

For PVC Pipe: 225mm Dia, Wall Thickness2.8mm

783.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

798.66

10% Profit ( Add 10% on Subtotal-B) :

878.53

VAT

6% of Total

IT

4% of Total

58.57 39.05 Total:

976.14

1082.00

1082.00

m PVC Pipe: External Dia 225mm & wall thickness 2.80mm

1.0000

m

1082.00

Subtotal-A: Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

86.56

Subtotal-A1: Subtotal-B: Subtotal-C:

1168.56 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1191.93

10% Profit ( Add 10% on Subtotal-B) :

1311.12

VAT

6% of Total

IT

4% of Total

87.41 58.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1456.80

Page: 1848 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.01.05

Detailed Analysis Brief Description of Item 2 For PVC Pipe: 250mm Dia, Wall Thickness 3.1mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m PVC Pipe: External Dia 250mm & wall thickness 3.10mm

1.0000

m

1152.00

1152.00

Subtotal-A: Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

92.16

Subtotal-A1: Subtotal-B: Subtotal-C:

1244.16 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1269.04

10% Profit ( Add 10% on Subtotal-B) :

1395.95

VAT

6% of Total

IT

4% of Total

93.06 62.04 Total:

6.10.01.06

For PVC Pipe: 280mm Dia, Wall Thickness 3.5mm

1551.05

m PVC Pipe: External Dia 280mm & wall thickness 3.50mm

1.0000

m

1420.00

Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

113.60

Subtotal-A1: Subtotal-B: Subtotal-C:

1420.00 1420.00

Subtotal-A:

1533.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1564.27

10% Profit ( Add 10% on Subtotal-B) :

1720.70

VAT

6% of Total

IT

4% of Total

114.71 76.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1152.00

1911.89

Page: 1849 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.01.07

Detailed Analysis Brief Description of Item 2 For PVC Pipe:315mm Dia, Wall Thickness 4.0mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m PVC Pipe: External Dia 315mm & wall thickness 4.0mm

1.0000

m

1844.00

1844.00

Subtotal-A: Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

147.52

Subtotal-A1: Subtotal-B: Subtotal-C:

1991.52 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2031.35

10% Profit ( Add 10% on Subtotal-B) :

2234.49

VAT

6% of Total

IT

4% of Total

148.97 99.31 Total:

6.10.01.08

For PVC Pipe:355mm Dia, Wall Thickness 4.4mm

2482.76

m PVC Pipe: External Dia 355mm & wall thickness 4.4mm

1.0000

m

2325.00

Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

186.00

Subtotal-A1: Subtotal-B: Subtotal-C:

2325.00 2325.00

Subtotal-A:

2511.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2561.22

10% Profit ( Add 10% on Subtotal-B) :

2817.34

VAT

6% of Total

IT

4% of Total

187.82 125.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1844.00

3130.38

Page: 1850 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.01.09

Detailed Analysis Brief Description of Item 2 For PVC Pipe:400mm Dia, Wall Thickness 5.0mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m PVC Pipe: External Dia 400mm & wall thickness 5.0mm

1.0000

m

2875.00

2875.00

Subtotal-A: Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

230.00

Subtotal-A1: Subtotal-B: Subtotal-C:

3105.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3167.10

10% Profit ( Add 10% on Subtotal-B) :

3483.81

VAT

6% of Total

IT

4% of Total

232.25 154.84 Total:

6.10.01.10

For PVC Pipe:450mm Dia, Wall Thickness5.6mm

3870.90

m PVC Pipe: External Dia 450mm & wall thickness 5.6mm

1.0000

m

3520.00

Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

281.60

Subtotal-A1: Subtotal-B: Subtotal-C:

3520.00 3520.00

Subtotal-A:

3801.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3877.63

10% Profit ( Add 10% on Subtotal-B) :

4265.40

VAT

6% of Total

IT

4% of Total

284.36 189.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2875.00

4739.33

Page: 1851 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.01.11

Detailed Analysis Brief Description of Item 2 For PVC Pipe:500mm Dia, Wall Thickness 6.2mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m PVC Pipe: External Dia 500mm & wall thickness 6.2mm

1.0000

m

4257.00

4257.00

Subtotal-A: Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

340.56

Subtotal-A1: Subtotal-B: Subtotal-C:

4597.56 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4689.51

10% Profit ( Add 10% on Subtotal-B) :

5158.46

VAT

6% of Total

IT

4% of Total

343.90 229.26 Total:

6.10.02

Supplying and Installation of uPVC pipe fittings like T-Joints, Bends & End Caps with leak proof O-ring jointing using best quality elastomeric sealing gaskets etc, of different size and wall thickness in accordance with ISO-4422 and ISO-4065, etc. completed including costs of all materials & labors and costs of testing for complete leak proofness and repair and/or replacement of leaking joints, if any, as per design, drawings, specifications and Direction of Engineer-in-Charge.

each

6.10.02.01

For Bend Size:160mm Dia,wall thickness2.5mm&1.52m Length

each 160mm dia PVC Bend,wall thickness2.5mm&1.52m Length

1.0000

each

992.00

5731.62

992.00 992.00

Subtotal-A: Placing,Connecting & Jointing Cost

( +10.00 % on Subtotal-A )

Subtotal-A1:

99.20 1091.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1113.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1224.33

VAT

6% of Total

IT

4% of Total

81.62 54.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4257.00

1360.36

Page: 1852 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.02.02

Detailed Analysis Brief Description of Item 2 For Bend Size:180mm Dia,wall thickness2.8mm&1.52m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 180mm dia PVC Bend,wall thickness2.8mm&1.52m Length

1.0000

each

1211.00

1211.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

For Bend Size:200mm Dia,wall thickness3.2mm&1.52m Length

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1358.74

10% Profit ( Add 10% on Subtotal-B) :

1494.62

VAT

6% of Total

IT

4% of Total

99.64 66.43 1660.68

each 200mm dia PVC Bend,wall thickness3.2mm&1.52m Length

1.0000

each

1476.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1476.00 1476.00

Subtotal-A:

147.60 1623.60

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1656.07

10% Profit ( Add 10% on Subtotal-B) :

1821.68

VAT

6% of Total

IT

4% of Total

121.45 80.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

121.10 1332.10

Total: 6.10.02.03

1211.00

2024.09

Page: 1853 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.02.04

Detailed Analysis Brief Description of Item 2 For Bend Size:225mm Dia,wall thickness3.5mm&1.52m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 225mm dia PVC Bend,wall thickness3.5mm&1.52m Length

1.0000

each

1788.00

1788.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

For Bend Size:250mm Dia,wall thickness3.9mm&1.52m Length

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2006.14

10% Profit ( Add 10% on Subtotal-B) :

2206.75

VAT

6% of Total

IT

4% of Total

147.12 98.08 2451.94

each 250mm dia PVC Bend,wall thickness3.9mm&1.52m Length

1.0000

each

2231.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2231.00 2231.00

Subtotal-A:

223.10 2454.10

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2503.18

10% Profit ( Add 10% on Subtotal-B) :

2753.50

VAT

6% of Total

IT

4% of Total

183.57 122.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

178.80 1966.80

Total: 6.10.02.05

1788.00

3059.44

Page: 1854 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.02.06

Detailed Analysis Brief Description of Item 2 For Bend Size:280mm Dia,wall thickness4.4mm&1.52m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 280mm dia PVC Bend,wall thickness4.4mm&1.52m Length

1.0000

each

2813.00

2813.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

For Bend Size:315mm Dia,wall thickness4.9mm&1.52m Length

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3156.19

10% Profit ( Add 10% on Subtotal-B) :

3471.80

VAT

6% of Total

IT

4% of Total

231.45 154.30 3857.56

each 315mm dia PVC Bend,wall thickness4.9mm&1.52m Length

1.0000

each

3654.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3654.00 3654.00

Subtotal-A:

365.40 4019.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4099.79

10% Profit ( Add 10% on Subtotal-B) :

4509.77

VAT

6% of Total

IT

4% of Total

300.65 200.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

281.30 3094.30

Total: 6.10.02.07

2813.00

5010.85

Page: 1855 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.02.08

Detailed Analysis Brief Description of Item 2 For Bend Size:355mm Dia,wall thickness5.6mm&1.52m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 355mm dia PVC Bend,wall thickness5.6mm&1.52m Length

1.0000

each

4596.00

4596.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

For Bend Size:400mm Dia,wall thickness6.3mm&1.98m Length

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5156.71

10% Profit ( Add 10% on Subtotal-B) :

5672.38

VAT

6% of Total

IT

4% of Total

378.16 252.11 6302.65

each 400mm dia PVC Bend,wall thickness6.3mm&1.98m Length

1.0000

each

6850.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6850.00 6850.00

Subtotal-A:

685.00 7535.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7685.70

10% Profit ( Add 10% on Subtotal-B) :

8454.27

VAT

6% of Total

IT

4% of Total

563.62 375.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

459.60 5055.60

Total: 6.10.02.09

4596.00

9393.63

Page: 1856 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.02.10

Detailed Analysis Brief Description of Item 2 For Bend Size:450mm Dia,wall thickness7.0mm&1.98m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 450mm dia PVC Bend,wall thickness7.0mm&1.98m Length

1.0000

each

8362.00

8362.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

For Bend Size:500mm Dia,wall thickness7.8mm&1.98m Length

9382.16

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10320.38

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

688.03 458.68

1.0000

each

10286.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1028.60 11314.60

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11540.89

10% Profit ( Add 10% on Subtotal-B) :

12694.98

VAT

6% of Total

IT

4% of Total

846.33 564.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10286.00 10286.00

Subtotal-A:

Supplying and Installation of uPVC pipe fittings like T-Joints, Bends & End Caps with leak proof O-ring jointing using best quality elastomeric sealing gaskets etc, of different size and wall thickness in accordance with ISO-4422 and ISO-4065, etc. completed including costs of all materials & labors and costs of testing for complete leak proofness and repair and/or replacement of leaking joints, if any, as per design, drawings, specifications and Direction of Engineer-in-Charge.

11467.09

each 500mm dia PVC Bend,wall thickness7.8mm&1.98m Length

6.10.03

836.20 9198.20

Total: 6.10.02.11

8362.00

14105.53

each

Page: 1857 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

6.10.03.01

For End Cap Size: 160mm dia, wall thickness 2mm &0.56m Length

each

Quantity

160mm dia PVC end Cap, wall thickness 2mm &0.56m Length

5

1.0000

Unit

Rate

6

7

8

476.00

476.00

each

Amount

476.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

523.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

534.07

10% Profit ( Add 10% on Subtotal-B) :

587.48

VAT

6% of Total

IT

4% of Total

39.17 26.11 Total:

6.10.03.02

For End Cap Size:180mm dia, wall thickness 2.3mm &0.56m Length

652.75

each 180mm dia PVC end Cap, wall thickness 2.3mm &0.56m Length

1.0000

each

544.00

544.00 544.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1:

54.40 598.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

610.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

671.40

VAT

6% of Total

44.76

IT

4% of Total

29.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

47.60

746.01

Page: 1858 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.03.03

Detailed Analysis Brief Description of Item 2 For End Cap Size: 200mm dia, wall thickness 2.5mm &0.56m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

608.00

608.00

each 200mm dia PVC end Cap, wall thickness 2.5mm &0.56m Length

1.0000

each

608.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

668.80 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

682.18

10% Profit ( Add 10% on Subtotal-B) :

750.39

VAT

6% of Total

IT

4% of Total

50.03 33.35 Total:

6.10.03.04

For End Cap Size: 225mm dia, wall thickness 2.8mm &0.56m Length

833.77

each 225mm dia PVC end Cap, wall thickness 2.8mm &0.56m Length

1.0000

each

790.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

790.00 790.00

Subtotal-A:

79.00 869.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

886.38

10% Profit ( Add 10% on Subtotal-B) :

975.02

VAT

6% of Total

IT

4% of Total

65.00 43.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

60.80

1083.35

Page: 1859 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.03.05

Detailed Analysis Brief Description of Item 2 For End Cap Size:250mm dia, wall thickness 3.1mm &0.56m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

883.00

883.00

each 250mm dia PVC end Cap, wall thickness 3.1mm &0.56m Length

1.0000

each

883.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

971.30 990.73

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1089.80

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

72.65 48.44 Total:

6.10.03.06

For End Cap Size:280mm dia, wall thickness 3.5mm &0.56m Length

1210.89

each 280mm dia PVC end Cap, wall thickness 3.5mm &0.56m Length

1.0000

each

1071.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1071.00 1071.00

Subtotal-A:

107.10 1178.10

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1201.66

10% Profit ( Add 10% on Subtotal-B) :

1321.83

VAT

6% of Total

IT

4% of Total

88.12 58.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

88.30

1468.70

Page: 1860 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.03.07

Detailed Analysis Brief Description of Item 2 For End Cap Size: 315mm dia, wall thickness 4.0mm &1.42m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 315mm dia PVC end Cap, wall thickness 4.0mm &1.42m Length

1.0000

each

2756.00

2756.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

For End Cap Size:355mm dia, wall thickness 4.4mm &1.42m Length

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3092.23

10% Profit ( Add 10% on Subtotal-B) :

3401.46

VAT

6% of Total

IT

4% of Total

226.76 151.18 3779.39

each 355mm dia PVC end Cap, wall thickness 4.4mm &1.42m Length

1.0000

each

3484.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3484.00 3484.00

Subtotal-A:

348.40 3832.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3909.05

10% Profit ( Add 10% on Subtotal-B) :

4299.95

VAT

6% of Total

IT

4% of Total

286.66 191.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

275.60 3031.60

Total: 6.10.03.08

2756.00

4777.73

Page: 1861 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.03.09

Detailed Analysis Brief Description of Item 2 For End Cap Size:400mm dia, wall thickness 5.0mm &1.42m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 400mm dia PVC end Cap, wall thickness 5.0mm &1.42m Length

1.0000

each

4368.00

4368.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

For End Cap Size:450mm dia, wall thickness 5.6mm &1.42m Length

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4900.90

10% Profit ( Add 10% on Subtotal-B) :

5390.99

VAT

6% of Total

IT

4% of Total

359.40 239.60 5989.98

each 450mm dia PVC end Cap, wall thickness 5.6mm &1.42m Length

1.0000

each

5398.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

5398.00 5398.00

Subtotal-A:

539.80 5937.80

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6056.56

10% Profit ( Add 10% on Subtotal-B) :

6662.21

VAT

6% of Total

IT

4% of Total

444.15 296.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

436.80 4804.80

Total: 6.10.03.10

4368.00

7402.46

Page: 1862 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.03.11

Detailed Analysis Brief Description of Item 2 For End Cap Size: 500mm dia, wall thickness 6.2mm &1.42m Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 500mm dia PVC end Cap, wall thickness 6.2mm &1.42m Length

1.0000

each

6604.00

6604.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Supplying and Installation of uPVC pipe fittings like T-Joints, Bends & End Caps with leak proof O-ring jointing using best quality elastomeric sealing gaskets etc, of different size and wall thickness in accordance with ISO-4422 and ISO-4065, etc. completed including costs of all materials & labors and costs of testing for complete leak proofness and repair and/or replacement of leaking joints, if any, as per design, drawings, specifications and Direction of Engineer-in-Charge.(Same for equal or Unequal)

Note : Rates of all items should be inclusive of all supply and carriage.

660.40 7264.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7409.69

10% Profit ( Add 10% on Subtotal-B) :

8150.66

VAT

6% of Total

IT

4% of Total

543.38 362.25 Total:

6.10.04

6604.00

9056.29

each

Page: 1863 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.04.01

Detailed Analysis Brief Description of Item 2 For T-Joints: 160mmx160mmx160mm, Wall thickness 2.5mm&1.47 Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PVC T-Joints:160mmx160mmx160mm, Wall thickness 2.5mm&1.47 Length

1.0000

each

1311.00

1311.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1:

For T-Joints: 180mmx180mmx180mm, Wall thickness 2.8mm&1.47 Length

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1470.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1618.04

VAT

6% of Total

IT

4% of Total

107.87 71.91 1797.82

each PVC T-Joints:180mmx180mmx180mm, Wall thickness 2.8mm&1.47 Length

1.0000

each

1525.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1525.00 1525.00

Subtotal-A:

152.50 1677.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1711.05

10% Profit ( Add 10% on Subtotal-B) :

1882.16

VAT

6% of Total

IT

4% of Total

125.48 83.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

131.10 1442.10

Total: 6.10.04.02

1311.00

2091.28

Page: 1864 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.04.03

Detailed Analysis Brief Description of Item 2 For T-Joints: 200mmx200mmx200mm, Wall thickness 3.2mm&1.47 Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PVC T-Joints:200mmx200mmx200mm, Wall thickness 3.2mm&1.47 Length

1.0000

each

1772.00

1772.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1:

For T-Joints: 225mmx225mmx225mm, Wall thickness 3.50mm&1.47 Length

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1988.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2187.00

VAT

6% of Total

IT

4% of Total

145.80 97.20 2430.00

each PVC T-Joints:225mmx225mmx225mm, Wall thickness 3.50mm&1.47 Length

1.0000

each

2142.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2142.00 2142.00

Subtotal-A:

214.20 2356.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2403.32

10% Profit ( Add 10% on Subtotal-B) :

2643.66

VAT

6% of Total

IT

4% of Total

176.24 117.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

177.20 1949.20

Total: 6.10.04.04

1772.00

2937.40

Page: 1865 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.04.05

Detailed Analysis Brief Description of Item 2 For T-Joints: 250mmx250mmx250mm, Wall thickness 3.90mm&1.47 Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PVC T-Joints:250mmx250mmx250mm, Wall thickness 3.90mm&1.47 Length

1.0000

each

2624.00

2624.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1:

For T-Joints: 280mmx280mmx280mm, Wall thickness 4.4mm&1.47 Length

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2944.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3238.54

VAT

6% of Total

IT

4% of Total

215.90 143.94 3598.38

each PVC T-Joints:280mmx280mmx280mm, Wall thickness 4.4mm&1.47 Length

1.0000

each

3221.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3221.00 3221.00

Subtotal-A:

322.10 3543.10

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3613.96

10% Profit ( Add 10% on Subtotal-B) :

3975.36

VAT

6% of Total

IT

4% of Total

265.02 176.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

262.40 2886.40

Total: 6.10.04.06

2624.00

4417.06

Page: 1866 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.04.07

Detailed Analysis Brief Description of Item 2 For T-Joints: 315mmx315mmx315mm, Wall thickness 4.90mm&1.47 Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PVC T-Joints:315mmx315mmx315mm, Wall thickness 4.90mm&1.47 Length

1.0000

each

4065.00

4065.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1:

For T-Joints: 355mmx355mmx355mm, Wall thickness 5.6mm&1.98 Length

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4560.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5017.02

VAT

6% of Total

IT

4% of Total

334.47 222.98 5574.47

each PVC T-Joints:355mmx355mmx355mm, Wall thickness 5.6mm&1.98 Length

1.0000

each

6257.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6257.00 6257.00

Subtotal-A:

625.70 6882.70

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7020.35

10% Profit ( Add 10% on Subtotal-B) :

7722.39

VAT

6% of Total

IT

4% of Total

514.83 343.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

406.50 4471.50

Total: 6.10.04.08

4065.00

8580.43

Page: 1867 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.04.09

Detailed Analysis Brief Description of Item 2 For T-Joints: 400mmx400mmx400mm, Wall thickness 6.30mm&2.29Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PVC T-Joints:400mmx400mmx400mm, Wall thickness 6.30mm&2.29Length

1.0000

each

8339.00

8339.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

For T-Joints: 450mmx450mmx450mm, Wall thickness 7.0mm&2.67Length

9356.36

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10291.99

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

686.13 457.42 11435.55

each PVC T-Joints:450mmx450mmx450mm, Wall thickness 7.0mm&2.67Length

1.0000

each

11368.00

Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11368.00 11368.00

Subtotal-A:

1136.80 12504.80

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12754.90

10% Profit ( Add 10% on Subtotal-B) :

14030.39

VAT

6% of Total

IT

4% of Total

935.36 623.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

833.90 9172.90

Total: 6.10.04.10

8339.00

15589.32

Page: 1868 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.04.11

Detailed Analysis Brief Description of Item 2 For T-Joints: 500mmx500mmx500mm, Wall thickness 7.80mm&2.67Length

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PVC T-Joints:500mmx500mmx500mm, Wall thickness 7.80mm&2.67Length

1.0000

each

13957.00

13957.00

Subtotal-A: Placing, connecting & jointing cost

( +10.00 % on Subtotal-A )

Subtotal-A1:

Supply of Fiber reinforced uPVC Lay-Flat hose pipe of different dia, wall thickness and weight/m including cost of carrying and storing in a place as directed by the Engineer-in-Charge etc. all completed as per specifications and direction of the Engineer-in-Charge. Sample to be approved by the Engineer-in-Charge before procurement.

m

6.10.05.01

For 77mm dia pipe,Wall Thickness 1.36mm and weight 0.503 Kg /m

m

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15659.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17225.73

VAT

6% of Total

IT

4% of Total

Fibre reinforced uPVC Lay-Flat hose,77mm dia wall thickness 1.36mm &weight 0.503 kg/m

1148.38 765.59

1.0000

m

125.40

Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

Subtotal-C:

125.40

10.03

Subtotal-A1: Subtotal-B:

19139.70

125.40

Subtotal-A:

135.43 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

138.14

10% Profit ( Add 10% on Subtotal-B) :

151.95

VAT

6% of Total

IT

4% of Total

10.13 6.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1395.70 15352.70

Total: 6.10.05

13957.00

168.84

Page: 1869 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.05.02

Detailed Analysis Brief Description of Item 2 For 103mm dia pipe,Wall Thickness 1.40mm and weight 0.664Kg /m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

171.00

171.00

m Fibre reinforced uPVC Lay-Flat hose,103mm dia wall thickness 1.40mm &weight 0.664 kg/m

1.0000

171.00

Subtotal-A: Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

13.68

Subtotal-A1: Subtotal-B: Subtotal-C:

184.68 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

188.37

10% Profit ( Add 10% on Subtotal-B) :

207.21

VAT

6% of Total

IT

4% of Total

13.81 9.21 Total:

6.10.05.03

For 153mm dia pipe,Wall Thickness 2.0mm and weight 1.06Kg /m

m Fibre reinforced uPVC Lay-Flat hose,153mm dia wall thickness 2.0mm &weight 1.06 kg/m

1.0000

m

296.40

Placing, connecting & jointing cost

( +8.00 % on Subtotal-A )

23.71

Subtotal-A1: Subtotal-B: Subtotal-C:

296.40 296.40

Subtotal-A:

320.11 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

326.51

10% Profit ( Add 10% on Subtotal-B) :

359.17

VAT

6% of Total

IT

4% of Total

23.94 15.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

230.23

399.07

Page: 1870 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.06

Detailed Analysis Brief Description of Item 2 Supply and Placing of joint Sealant(2-part Polysulphide Sealer or Butyl Mastic Sealant or Similar approved) including cleaning and priming of joint surfaces and placement of sealant in accordance with manufacturers instruction for pipes with spigot and socket pipe joint, etc. all complete as per direction of Engineer- in – charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

kg

2-part Polysulphide Sealer or Butyl Mastic Sealant or Similar approved

1.0000

kg

1500.00

1500.00

Subtotal-A: Placing & connecting per joint

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

150.00 1650.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1683.00

10% Profit ( Add 10% on Subtotal-B) :

1851.30

VAT

6% of Total

123.42

IT

4% of Total

82.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1500.00

2057.00

Page: 1871 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.10.07

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing in position of 9mm thick and 230mm wide PVC water stop (3 bulb type) having minimum strength of 13.80 N/mm2 at 225% elongation and of approved grade and quality in contraction and expansion joints with necessary arrangements for modification in shuttering and support arrangements for keeping the water stop in position during casting etc. all complete as per design, specification and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

PVC water stop (3 bulb type)

1.0000

m

620.00

620.00

Skilled Labour

0.5000

day

450.00

225.00 845.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

861.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

948.09

VAT

6% of Total

IT

4% of Total

63.21 42.14 Total:

6.10.08

Supply Puddlow brand of England/German/India

6.10.09

Supplying best quality PVC pipes, fitted and fixed in position with sockets head and shoes, bends, clamps and nails etc. all complete in all floors (Aziz / Lira / National / Polymer or equivalent water grade PVC Pipe) as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

1053.43

LS

Page: 1872 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.10.09.1

2 100mm (Inside dia)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

240.00

240.00

m 100mm dia PVC pipe (3.4mm to 4.0mm thick of Aziz/Lira/National/Polymar)

1.0000

240.00

Subtotal-A: Labour & other costs like head, shoes, bend, clamp

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6.10.09.2

300mm (Inside dia)

288.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

293.76

10% Profit ( Add 10% on Subtotal-B) :

323.14

VAT

6% of Total

IT

4% of Total

21.54 14.36 Total:

359.04

3840.00

3840.00

m 300mm uPVC Pipe -7.8mm wall thickness

1.0000

m

3840.00

Subtotal-A: Labour & other costs like head, shoes, bend, clamp

( +20.00 % on Subtotal-A )

Subtotal-A1:

768.00 4608.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4700.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5170.18

VAT

6% of Total

IT

4% of Total

344.68 229.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

48.00

5744.64

Page: 1873 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.10.09.3

2 600mm (Inside dia)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 600mm uPVC Pipe

1.0000

m

8640.00

8640.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8812.80

10% Profit ( Add 10% on Subtotal-B) :

9694.08

VAT

6% of Total

646.27

IT

4% of Total

430.85 Total:

6.10.09.4

900mm (Inside dia)

10771.20

m 900mm uPVC Pipe

1.0000

m

10800.00

10800.00 10800.00

Subtotal-A: Labour & other costs like head, shoes, bend, clamp

( +20.00 % on Subtotal-A )

Subtotal-A1:

2160.00 12960.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13219.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14541.12

VAT

6% of Total

IT

4% of Total

969.41 646.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8640.00

16156.80

Page: 1874 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.11.01

6.11.01.01

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supply of High Strength Synthetic Rubber Bag of different thickness made of Polymide/Nylone fabric with 3 plies at site including all cost. Rubber bag shall be Transported in a well protected container and labeled stating list of items with width, length and other pertinent information. Before Aging test the tensile strength (warp) should be greater than 560 KN/M following ASTM D-412 testing method or 840 KN/M following GB-5572 (GB:National standard of China) standard, immersion test required should be greater than 6 Kn per m following ASTM D-751- 95 standard or GB-532 standard . Tensile Strength of Rubber bag- After aging test( Air at 100ºc,4days)should be 80%of before ageing test following ASTM D-573-88 WARP(Kn/M)= 80% Tensile strength (warp) before aging test following ASTM D412,Elongation should be greater than 300%, Immersion Standard used: ASTM D-751-95=6Kn/M, Abrasion Resistance sqm cm/1.61 km Measurement Rubber Layer 0.89 maximum Standard used ASTM D- 96397 a Hardness as different point Standard used ASTM D-5963-97 a D240 (water at 70ºc, 4 days) should be greater than 4 KN/M following ASTM D- 51-96 or GB-532 standard used, all manufacture's test reports should be submitted to the purchaser etc. all complete as per design drawing and irection of Engineer-In-Charge. For 13mm Thick Rubber Bag

sqm Main Rubber Bag (13mm Thickness)

1.0000

sqm

18748.00

18748.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19122.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21035.26

VAT

6% of Total

IT

4% of Total

1402.35 934.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18748.00

23372.51

Page: 1875 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.11.01.02

2 For 12mm Thick Rubber Bag

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Main Rubber Bag (12mm Thickness)

1.0000

sqm

18058.00

18058.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18419.16

10% Profit ( Add 10% on Subtotal-B) :

20261.08

VAT

6% of Total

1350.74

IT

4% of Total

900.49 Total:

6.11.01.03

For 11mm Thick Rubber Bag

1.0000

sqm

17483.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17832.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19615.93

VAT

6% of Total

IT

4% of Total

1307.73 871.82 Total:

21795.47

sqm Main Rubber Bag (10mm Thickness)

1.0000

sqm

17022.00

Subtotal-B: Subtotal-C:

17022.00 17022.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17362.44

10% Profit ( Add 10% on Subtotal-B) :

19098.68

VAT

6% of Total

IT

4% of Total

1273.25 848.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17483.00 17483.00

Subtotal-A:

For 10mm Thick Rubbar Bag

22512.31

sqm Main Rubber Bag (11mm Thickness)

6.11.01.04

18058.00

21220.76

Page: 1876 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.02

Detailed Analysis Brief Description of Item 2 Supply of High quality Rubber Base cover sheet (10mm-8mm thickness) in single ply at site etc all complete as per design drawing specification and direction of Engineer-In-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Rubber Base Cover Sheet (8-10mm Thickness)

1.0000

sqm

1785.90

1785.90

Subtotal-A: Cost of test at of Country origin

( +3.00 % on Subtotal-A )

53.58

Subtotal-A1: Subtotal-B: Subtotal-C:

1839.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1876.27

10% Profit ( Add 10% on Subtotal-B) :

2063.89

VAT

6% of Total

IT

4% of Total

137.59 91.73 Total:

6.11.03

Supply of Rubber Foam Sheet (Rubber Filler) at Site etc all complete as per design drawing and direction of Engineer-In-Charge. Thickness: 10mm - 12mm

2293.21

sqm

Rubber Foam Sheet

1.0000

sqm

4531.50

4531.50 4531.50

Subtotal-A: Cost of test at of country origin

( +3.00 % on Subtotal-A )

135.95

Subtotal-A1:

4667.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4760.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5236.87

VAT

6% of Total

IT

4% of Total

349.12 232.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1785.90

5818.75

Page: 1877 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.04

Detailed Analysis Brief Description of Item 2 Supply and Installation of Protect Sheet at Site etc all complete as per design drawing and direction of Engineer-In-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Rubber Protect Sheet

1.0000

sqm

5365.80

5365.80

Subtotal-A: Cost of Test at of Country Origin

( +3.00 % on Subtotal-A )

160.97

Subtotal-A1:

5526.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5637.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6201.04

VAT

6% of Total

413.40

IT

4% of Total

275.60 Total:

6.11.05

Supply of Rubber Glue at Site etc all complete as per direction of Engineer-In-Charge.

6890.04

kg Rubber Glue

1.0000

kg

472.20

472.20 472.20

Subtotal-A: Cost of test at of Country origin

( +3.00 % on Subtotal-A )

14.17

Subtotal-A1:

486.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

496.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

545.70

VAT

6% of Total

36.38

IT

4% of Total

24.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5365.80

606.34

Page: 1878 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.06

Detailed Analysis Brief Description of Item 2 Supplying of 200mm duia PVC pipe, 12mm thick used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials fitting, fixing, providing aica as required etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

200mm PVC pipe 12mm Thickness

1.0000

m

2460.00

2460.00

Subtotal-A: Providing aica & Fitting Fixing

( +12.00 % on Subtotal-A )

Subtotal-A1:

Supplying of flexible hose pipe (100mm dia) used for removing of sand from rubber dam bed including carrying and supplying of all materials fitting, fixing, etc. all complete as per direction of the E-I-C.

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2810.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3091.33

VAT

6% of Total

IT

4% of Total

206.09 137.39 3434.82

m

Hose Pipe 100mm dia

1.0000

m

590.00

590.00 590.00

Subtotal-A: Fitting Fixing

( +12.00 % on Subtotal-A )

Subtotal-A1:

70.80 660.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

674.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

741.42

VAT

6% of Total

IT

4% of Total

49.43 32.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

295.20 2755.20

Total: 6.11.07

2460.00

823.80

Page: 1879 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.08

Detailed Analysis Brief Description of Item 2 Supplying and installation of Water cap structure used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, 16mm thick MS plate, MS rod, nuts, bolts, 200mm flank 10K, rubber washer, welding, fitting, fixing, all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS Plate (16mm)

15.6000

kg

80.00

1248.00

MS Rod (Plain, 40 Grade)

4.6000

kg

45.00

207.00

Nails/ Nut bolts/ Screw/ Spikes

1.2000

kg

65.00

78.00

200mm Flanks 10K

2.0000

each

560.00

1120.00

Rubber Washer

2.0000

each

40.00

80.00 2733.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2787.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3066.43

VAT

6% of Total

204.43

IT

4% of Total

136.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3407.14

Page: 1880 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.09

Detailed Analysis Brief Description of Item 2 Supplying and installation of 200mmX200mm MS pipe Tee joint used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, 200mm MS Tee, nuts, bolts, 200mm flanks 10K, rubber washer, welding, fitting, fixing, all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS Pipe 200mm dia Tee

1.0000

each

5000.00

5000.00

200mm Flanks 10K

3.0000

each

560.00

1680.00

Nails/ Nut bolts/ Screw/ Spikes

3.6000

kg

65.00

234.00

Rubber Washer

6.0000

each

40.00

240.00 7154.00

Subtotal-A: Welding & Fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

8012.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8172.73

10% Profit ( Add 10% on Subtotal-B) :

8990.00

VAT

6% of Total

599.33

IT

4% of Total

399.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

858.48

9988.89

Page: 1881 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.10

Detailed Analysis Brief Description of Item 2 Supplying and installation of 200mm dia 90 degree MS bend used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, 200mm dia. MS bend, nuts, bolts, 200mm flanks 10K, rubber washer, welding, fitting, fixing, all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS Bend (200mm dia.)

1.0000

each

2000.00

2000.00

200mm Flanks 10K

2.0000

each

560.00

1120.00

Nails/ Nut bolts/ Screw/ Spikes

2.4000

kg

65.00

156.00

Rubber Washer

4.0000

each

40.00

160.00 3436.00

Subtotal-A: Welding & fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3848.32 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3925.29

10% Profit ( Add 10% on Subtotal-B) :

4317.82

VAT

6% of Total

287.85

IT

4% of Total

191.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

412.32

4797.57

Page: 1882 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.11

Detailed Analysis Brief Description of Item 2 Supplying and installation of 200mm dia 45 degree MS bend used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, 200mm dia. MS bend, nuts, bolts, 200mm flanks 10K, rubber washer, welding, fitting, fixing, all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS Bend (200mm dia.)

1.0000

each

2000.00

2000.00

Subtotal-A: Welding & fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1:

240.00 2240.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2284.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2513.28

VAT

6% of Total

167.55

IT

4% of Total

111.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2000.00

2792.53

Page: 1883 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.12

Detailed Analysis Brief Description of Item 2 Supplying and installation of 200mm dia Flexible Pipe joint used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, 200mm dia Flexible pipe joint, nuts, bolts, 200mm flanks 10K, rubber washer, welding, fitting, fixing, all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

200mm dia Flexible Pipe joint

1.0000

each

8000.00

8000.00

200mm Flanks 10K

2.0000

each

560.00

1120.00

Nails/ Nut bolts/ Screw/ Spikes

2.4000

kg

65.00

156.00

Rubber Washer

4.0000

each

40.00

160.00 9436.00

Subtotal-A: Welding &fitting Fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

10568.32 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10779.69

10% Profit ( Add 10% on Subtotal-B) :

11857.66

VAT

6% of Total

790.51

IT

4% of Total

527.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1132.32

13175.17

Page: 1884 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.13

Detailed Analysis Brief Description of Item 2 Supplying and installation of 200mm dia Dresser Pipe joint used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, 200mm dia Dresser pipe, welding, fitting, fixing, all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Dresser 200mm dia

1.0000

each

1500.00

1500.00

Subtotal-A: Welding &fitting Fixing

( +12.00 % on Subtotal-A )

Subtotal-A1:

Supplying and installation of 150mm-200mm dia Expansion Pipe joint used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, 150mm-200mm dia Reducer pipe , welding, fitting, fixing, all complete as per direction of the E-I-C.

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1713.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1884.96

VAT

6% of Total

IT

4% of Total

125.66 83.78 2094.40

each

Reducer Pipe 150-200mm dia

1.0000

each

1200.00

Welding &fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1200.00 1200.00

Subtotal-A:

144.00 1344.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1370.88

10% Profit ( Add 10% on Subtotal-B) :

1507.97

VAT

6% of Total

IT

4% of Total

100.53 67.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

180.00 1680.00

Total: 6.11.14

1500.00

1675.52

Page: 1885 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.16

Detailed Analysis Brief Description of Item 2 Supplying and installation of 200mm dia Non return check valve used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, 200mm dia MS check valve , welding, fitting, fixing, all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

MS Check valve 200mm dia

1.0000

each

7000.00

7000.00

200mm Flanks 10K

1.0000

each

560.00

560.00

Nails/ Nut bolts/ Screw/ Spikes

2.4000

kg

65.00

156.00

Rubber Washer

2.0000

each

40.00

80.00 7796.00

Subtotal-A: Welding & fitting fixing

( +12.00 % on Subtotal-A )

Subtotal-A1:

8731.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8906.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9796.77

VAT

6% of Total

653.12

IT

4% of Total

435.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

935.52

10885.29

Page: 1886 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.17

Detailed Analysis Brief Description of Item 2 Supplying and installation of Holding bracket for 200mm dia.MS pipe used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all aterials, 5mm thick flat bar, Royal bolts fitting, fixing, all complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

5mm thick MS flat bar

0.5000

kg

58.00

29.00

Royal bolt

2.0000

each

25.00

50.00 79.00

Subtotal-A: Fitting & Fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

88.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

90.25

10% Profit ( Add 10% on Subtotal-B) :

99.27

VAT

6% of Total

IT

4% of Total

6.62 4.41 Total:

6.11.18

Supplying and installation of Steel fall board at the opening of Sump chamber used in the pipe system of filling and emptying of rubber bag including carrying and supplying of all materials, steel fall board , fitting, fixing, all complete as per direction of the E-I-C.

110.31

each

Steel fall board

1.0000

each

10000.00

Fitting &fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

10000.00 10000.00

Subtotal-A:

1200.00 11200.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11424.00

10% Profit ( Add 10% on Subtotal-B) :

12566.40

VAT

6% of Total

837.76

IT

4% of Total

558.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9.48

13962.67

Page: 1887 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.19

Detailed Analysis Brief Description of Item 2 Supplying and installation of Manhole cover on valve chamber including carrying and supplying of all materials, 500mm dia Manhole cover, fitting, fixing, all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Manhole cover 500mm dia

1.0000

Set

6000.00

6000.00

Subtotal-A: Fitting &Fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Supply of 25mm thick rubber channel cap ( with fitting, fixing etc.--------- Engineer in charge)

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6854.40

10% Profit ( Add 10% on Subtotal-B) :

7539.84

VAT

6% of Total

IT

4% of Total

502.66 335.10 8377.60

m Rubber Chanel cap

1.0000

m

180.00

Fitting &fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

180.00 180.00

Subtotal-A:

21.60 201.60

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

205.63

10% Profit ( Add 10% on Subtotal-B) :

226.20

VAT

6% of Total

15.08

IT

4% of Total

10.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

720.00 6720.00

Total: 6.11.20

6000.00

251.33

Page: 1888 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.21

Detailed Analysis Brief Description of Item 2 Supply of 25mm thick rubber cork at the joining of steel sheet piles ( with fitting, fixing etc.--------- Engineer in charge)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Rubber cork

1.0000

each

25.00

25.00

Subtotal-A: Fitting & Fixing

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Supplying and installing embedded metal in RCC structure including placing, setting and aligning true to line level and position including grinding to smooth edges, corners, welding in place including supplying of all materials, tools, equipments and labour etc. complete as per design drawings, specification of works and direction of the Engineer-inCharge.

6.11.23.01

Rubber bag anchoring platens and pads bolts, double nuts, split washers, etc. in full sets.

Note : Rates of all items should be inclusive of all supply and carriage.

3.00 28.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28.56

10% Profit ( Add 10% on Subtotal-B) :

31.42

VAT

6% of Total

IT

4% of Total

2.09 1.40 Total:

6.11.23

25.00

34.91

Page: 1889 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.11.23.01.1

2 Type A, B & C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set MS Plate (8mm thick)

31.2700

kg

70.00

2188.90

MS Plate (20mm thick)

22.2400

kg

70.00

1556.80

8.9300

kg

54.00

482.22

M.S. Ribbed/ Deformed Bar (Grade 300) Nails/ Nut bolts/ Screw/ Spikes

27.2500

kg

65.00

1771.25

Plastic washer

5.0000

each

1.13

5.65

Skilled Labour

0.5400

day

450.00

243.00

Ordinary Labour

1.3400

day

370.00

495.80 6743.62

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6878.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7566.34

VAT

6% of Total

IT

4% of Total

504.42 336.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8407.05

Page: 1890 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.11.23.01.2

2 Type D & E

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set MS Plate (8mm thick)

21.8900

kg

70.00

1532.30

MS Plate (20mm thick)

10.0000

kg

70.00

700.00

M.S. Ribbed/ Deformed Bar (Grade 300)

12.0200

kg

54.00

649.08

Nails/ Nut bolts/ Screw/ Spikes

20.9400

kg

65.00

1361.10

Plastic washer

5.0000

each

1.13

5.65

Skilled Labour

0.5400

day

450.00

243.00

Ordinary Labour

1.3400

day

370.00

495.80 4986.93

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5086.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5595.34

VAT

6% of Total

IT

4% of Total

373.02 248.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6217.04

Page: 1891 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.11.24

Detailed Analysis Brief Description of Item 2 Fitting and fixing of the rubber bag in position with anchor bolts with pad & platens, washers, nuts etc. under the guidance of experts including local handling and unloading from contractor's vehicles, supply of labours, tools and equipment, chemicals (toluene, rubber glue etc) as required, making adjustments in fitting and fixing, if required after test filling of the dam seating gaps and slots by cement grout/mortar etc. all complete as per drawings, specifications and direction of the experts and E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

Foreman

0.4000

day

800.00

320.00

Skilled Labour

1.6000

day

450.00

720.00

20.0000

day

370.00

7400.00

Ordinary Labour

8440.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8608.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9469.68

VAT

6% of Total

IT

4% of Total

631.31 420.87 Total:

6.11.25

Photograph at various construction stages & maintaining all photographs in Site Order Book etc. all complete as per direction of the Engineer-in-Charge.

6.12.01

Dismantling damaged structural works in bridge/culvert and removing the debris to a safe distance, stacking properly for measurement, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

10521.87

LS

Page: 1892 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.12.01.1

2 CC Work

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

370.00

555.00

cum Ordinary Labour

1.5000

555.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

566.10

10% Profit ( Add 10% on Subtotal-B) :

622.71

VAT

6% of Total

41.51

IT

4% of Total

27.68 Total:

6.12.01.2

RCC Work

cum Ordinary Labour

2.6000

day

370.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

981.24 1079.36 71.96 47.97

Total: Brick Work

1199.29

cum Ordinary Labour

1.0200

day

370.00

Subtotal-B: Subtotal-C:

377.40 377.40

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

384.95

10% Profit ( Add 10% on Subtotal-B) :

423.44

VAT

6% of Total

IT

4% of Total

28.23 18.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

962.00 962.00

Subtotal-A:

6.12.01.3

691.90

470.49

Page: 1893 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.12.02

Detailed Analysis Brief Description of Item 2 Dismantling steel structure bridge for re-use (as far as possible) by any means, removing the debris to a safe distance, carrying the salvaged steel members to the store yard of the department or anywhere as directed, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m.ton

Skilled Labour

3.0300

day

450.00

1363.50

Ordinary Labour

5.0000

day

370.00

1850.00 3213.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3277.77

10% Profit ( Add 10% on Subtotal-B) :

3605.55

VAT

6% of Total

IT

4% of Total

240.37 160.25 Total:

6.12.03

Dismantling timber bridge and timber work including selecting, strong and stacking properly in measurable stacks after carrying those to a safe distance, etc. all complete as per direction of the E-I-C. (Measurement for payment to be made for quantity of salvaged wood).

cum

Carpenter

2.0000

day

680.00

1360.00

Ordinary Labour

5.0000

day

370.00

1850.00 3210.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3274.20

10% Profit ( Add 10% on Subtotal-B) :

3601.62

VAT

6% of Total

IT

4% of Total

240.11 160.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4006.16

4001.80

Page: 1894 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

6.13.01

De-watering of sub-soil water from the working area dry by controlling ground water table by undertaking all necessary measures including installation of shallow tube well, operation and maintenance of adequate number but not less than 2 nos. water pumps of not less than 60 L/S capacity each for pumping out water as required etc. all complete as per direction of the Engineer in charge.

LS

6.13.02

Construction of temporary cross dam in all type of soil, including cutting, carrying throwing & filling with all leads and lifts etc. and removing the cross dam after complete the re-excavation of khal, etc. all complete as per direction of the Engineer-in-Charge.

LS

6.13.03

Making earthen ring/cross bundh of required height and width to prevent water from entering in the working area for any type of foundation with earth arranged and carried by the contractor including bullah/bamboo palisading and double tarja mat/drum sheets walling as and where necessary, maintaining the same throughout the working period, filling by throwing earth in layers, removal of totally on completion of the hydraulic structures etc. all complete as per requirement and instruction of the Engineer-in-Charge.

LS

6.13.04

Bailing out of water from work site including supply, operation and maintenance of requisite numbers of water pumps. It should be carried out in such a manner as to produce possibilities of the movement of water through or alongside any concrete being placed, etc. all complete as per direction of the Engineer-in-Charge.

LS

6.13.05

Providing cork sheet/polythene sheet in expansion joints of concrete works including supply of all materials etc. complete as per direction of Engineer in charge

Note : Rates of all items should be inclusive of all supply and carriage.

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 1895 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 6.13.05.1

2 25mm thick sheet

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm 0.18mm thick polythene sheet

1.0000

m2

12.31

12.31

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.0005

day

370.00

0.19 57.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

64.51

VAT

6% of Total

IT

4% of Total

4.30 2.87 Total:

6.13.05.2

20mm thick sheet

sqm 0.18mm thick polythene sheet

1.0000

m2

12.31

12.31

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.0005

day

370.00

0.19 57.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

64.51

VAT

6% of Total

4.30

IT

4% of Total

2.87 Total:

6.13.06

71.68

71.68

Filling of expansion joints upto a depth of 40mm with bitumen mixed with coarse sand (FM>=2.5) in concrete works including supply of all materials etc. complete as per specification and direction of Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1896 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 6.13.06.1

2 25mm wide

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Sand (FM - 2.5)

0.0010

m3

1500.00

1.50

Bitumen [Grade 80/100]

0.5412

kg

49.00

26.52

Fire wood

0.6560

kg

7.75

5.08

Skilled Labour

0.0246

day

450.00

11.07

Ordinary Labour

0.0492

day

370.00

18.20 62.38

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

63.62

10% Profit ( Add 10% on Subtotal-B) :

69.99

VAT

6% of Total

4.67

IT

4% of Total

3.11 Total:

6.13.06.2

20mm wide

m Sand (FM - 2.5)

0.0008

m3

1500.00

1.20

Bitumen [Grade 80/100]

0.4330

kg

49.00

21.22

Fire wood

0.5248

kg

7.75

4.07

Skilled Labour

0.0197

day

450.00

8.87

Ordinary Labour

0.0394

day

370.00

14.58 49.93

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

50.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

56.02

VAT

6% of Total

IT

4% of Total

3.73 2.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

77.76

62.24

Page: 1897 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.07

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 300mmx300mmx20mm thick marble Name plate at left hand wheel guard on each side, one in English and one in Bengali including cost of materials, labour, form work, engraving neatly the approved Sample given by the engineer etc. complete as per drawings and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

20mm thick gray marble stone

0.0900

m2

4404.00

396.36

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.2000

day

370.00

74.00 1425.36

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1453.87

10% Profit ( Add 10% on Subtotal-B) :

1599.25

VAT

6% of Total

IT

4% of Total

106.62 71.08 Total:

6.13.08

Supplying, fitting and fixing door & door frames (Chowkat) of sections 63mmx150mm made of 18 BWG (1.257mm) galvanized Steel Sheet, fixing, 250mm long 6 nos. of iron clamps of MS angle (38mmx38mmx6mm), one end bifurcated, with vertical members of the frames, fixing the frame in wall after filling the channel with cement concrete (1:2:4), mending good any damage, fixing 4 nos. of 100mm size iron hinge with vertical members of the frame for single leaf shutter, painting all iron faces in 2 coats over a coat of priming with enamel paint of approved colour and quality, including cutting, sizing, welding, etc. all complete, including supply of 38mm thick shutter manufactured with 22-24 BWG (0.794-0.629mm) Japanese coloured rolled/plastic coated iron sheet fitted to stiffener, at two vertical members and 4 bracings in between two sheets, sheets are fitted with requisite numbers of Aluminium repeat not by welding including supply of two handles, two hasbolts, two tower bolts (200mm) and all other materials, laborours, tools etc all complete as per drawing and direction of Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

1776.95

LS

Page: 1898 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.09

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing steel window shutter including frame and Grill having requisite numbers of vertical and horizontal standard MS angles 25mmx25mmx5mm and 19mmx19mmx5mm and MS flat bar 25mmx5mm and 19mmx5mm (Grill) with grill FI clamps 225mmx3mm duly embedded in cement concrete (1:2:4) including making necessary arrangements of fabrications, welding etc. and finishing the intersecting points by filling including supplying and fixing handles, catch hooks 3 nos. hinge for each shutter etc. and 18 gauge MS sheet in position welded to steel shutter with 19mmx3mm MS flat bar stiffener and providing a coat of anticorrosive paint immediately after fabrication and before fixing in position as per drawings and direction of the Engineer-inCharge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

MS Angle, Flat bar, Z bar

15.9400

kg

59.00

940.46

MS Plate (9mm thick)

5.3700

kg

70.00

375.90

Welder

1.7500

day

680.00

1190.00

Skilled Labour

1.5300

day

450.00

688.50 3194.86

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3258.76

10% Profit ( Add 10% on Subtotal-B) :

3584.63

VAT

6% of Total

IT

4% of Total

238.98 159.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3982.93

Page: 1899 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.10

Detailed Analysis Brief Description of Item 2 Construction of sanitary latrine consists of inspection pit, well with CC ring, well cover, soil pipe and air vent pipe including cost of all materials, labours, tools etc., all complete as per drawings, design and direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1st Class Brick Chips (20mm down graded)

0.4770

m3

2940.00

Sand (FM - 1.8)

0.0090

m3

970.00

8.73

Sand (FM - 1.2)

0.1122

m3

584.00

65.52

Sand (FM - 2.5)

0.1173

m3

1500.00

175.95

Ordinary Portland Cement (CEM I, 52.5N)

3.3708

bag

455.00

1533.71

Head Mason

0.0424

day

650.00

27.56

Mason

0.4634

day

550.00

254.87

Skilled Labour

0.3975

day

450.00

178.88

Ordinary Labour

3.9450

day

370.00

1459.65

100mm dia PVC pipe (3.4mm to 4.0mm thick of Aziz/Lira/National/Polymar)

5.0000

m

240.00

1200.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0318

day

1200.00

38.16

Hire and running charges of Concrete Vibrator

0.0318

day

400.00

12.72 6358.13

Subtotal-A: Form Work and other costs

( +5.00 % on Subtotal-A )

317.91

Subtotal-A1: Subtotal-B: Subtotal-C:

6676.04 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6809.56

10% Profit ( Add 10% on Subtotal-B) :

7490.52

VAT

6% of Total

499.37

IT

4% of Total

332.91 Total:

6.13.11

Inscribing the name at O&M Shed with address and date of registration with sand cement mortar (1:4) etc. all complete as per direction of the E/C.

Note : Rates of all items should be inclusive of all supply and carriage.

1402.38

8322.80

LS

Page: 1900 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

6.13.12

Testing of Ground Water collected from the observation well in/c. test for ‘Arsenic’ etc. all complete as per direction of the E-I-C.

6.13.13

Temporary Latrine for LCS Members with bamboo post and jute bag/tarja wall etc. complete as per direction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

LS each Borak Bamboo (75mm dia)

1.3300

m

38.00

50.54

Jute Rope

0.2500

kg

120.00

30.00

Tarza

4.5000

m2

210.00

945.00

White Jute Mat

2.0000

m

64.80

129.60

Ordinary Labour

0.5000

day

370.00

185.00 1340.14

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1366.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1503.64

VAT

6% of Total

100.24

IT

4% of Total

66.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1670.71

Page: 1901 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.14

Detailed Analysis Brief Description of Item 2 Supplying, fitting & fixing wooden gauges with borak bamboo 150mmx38mm of best quality Sundari or Jam/Jarul wood at site marked in meter and decimals including black & white painting and printing with red etc. all complete as per directions of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Jam/Jarul

0.0080

m3

65650.00

Paint

0.0300

litre

260.00

7.80

Carpenter

0.0800

day

680.00

54.40

Plumber/ Electric Mistry/ Painter

0.0800

day

680.00

54.40

Ordinary Labour

0.1400

day

370.00

51.80

Borak Bamboo (75mm dia)

1.5000

m

38.00

57.00 750.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

765.61

10% Profit ( Add 10% on Subtotal-B) :

842.17

VAT

6% of Total

IT

4% of Total

56.14 37.43 Total:

6.13.15

Taking out the gauge from the gauge post including re-fixing to the post by supplying bolts and nuts or nails etc. all complete as per direction of the E-I-C.

935.75

each

Nails/ Nut bolts/ Screw/ Spikes

0.2000

kg

65.00

13.00

Ordinary Labour

0.2000

day

370.00

74.00 87.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

88.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

97.61

VAT

6% of Total

IT

4% of Total

6.51 4.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

525.20

108.46

Page: 1902 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.16

Detailed Analysis Brief Description of Item 2 Supplying bamboo sounding rods 5m long and minimum 50mm external diameter with black and white painting at every alternative meter with decimals in figuring etc. all complete as per direction of the Engineer in - charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Borak Bamboo (50mm dia)

5.0000

m

30.00

Paint

0.0400

litre

260.00

10.40

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00 500.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

510.41

10% Profit ( Add 10% on Subtotal-B) :

561.45

VAT

6% of Total

IT

4% of Total

37.43 24.95 Total:

6.13.17

Shifting of any gauge & de-fixing as per direction of the E-I-C.

623.83

each Ordinary Labour

0.2000

day

370.00

74.00 74.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

75.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

83.03

VAT

6% of Total

IT

4% of Total

5.54 3.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

150.00

92.25

Page: 1903 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.18

Detailed Analysis Brief Description of Item 2 Erection of bamboo fencing around a gauge with full bamboo pieces 3m to 4m long (75mm to 100mm dia) with 1m to 1.5m driven into the ground and 50mm dia bamboo walling fitted and fixed with nails and binding by wire and ropes (enclosure 1.22mx1.22m) etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Borak Bamboo (75mm to 100mm)

22.0000

m

42.00

924.00

Borak Bamboo (50mm dia)

40.0000

m

30.00

1200.00

Nails/ Nut bolts/ Screw/ Spikes

12.0000

kg

65.00

780.00

Skilled Labour

2.9500

day

450.00

1327.50

Ordinary Labour

0.0300

day

370.00

11.10 4242.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4327.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4760.20

VAT

6% of Total

317.35

IT

4% of Total

211.56 Total:

6.13.19

Supplying, fitting and fixing 10mm dia to 12mm dia Polyvinyl / Nylon rope in position as per design drawings specifications and directions of the Engineering-in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

5289.11

LS

Page: 1904 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.20

Detailed Analysis Brief Description of Item 2 Supplying and installation of water pump (10 HP) with 200 Cum/hr. (2 cusec) capacity at maximum working head as per drawing and/or direction of the Engineer-in-Charge including supply with all fittings, fixing complete as per drawings and specifications including testing and commissioning to the satisfaction of the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

3 phase 440V 10hp centrifugal pump motor

1.0000

set

45640.00

45640.00

45.0000

kg

59.00

2655.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Skilled Labour

0.9000

day

450.00

405.00

Ordinary Labour

2.0000

day

370.00

740.00

MS Angle, Flat bar, Z bar

49780.00

Subtotal-A: Commisining, fitting, fixing tools & equipment, welding, grinding etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

54758.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55853.16

10% Profit ( Add 10% on Subtotal-B) :

61438.48

VAT

6% of Total

4095.90

IT

4% of Total

2730.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4978.00

68264.97

Page: 1905 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.21

Detailed Analysis Brief Description of Item 2 Supplying of first aid box for construction site, office, team travel used with emergency medical first aid kit in hand held pp tool box packing. all complete in all respect as per approved specification and direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

First Aid Box

1.0000

each

2800.00

2800.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2856.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3141.60

VAT

6% of Total

209.44

IT

4% of Total

139.63 Total:

6.13.22

Supplying of Best Quality Safety Jacket for construction works made of 100% polyester waterproof fabric, Fluorescent yellow/orange/green/red/blue or Pantone color. all complete in all respect as per approved specification and direction of the Engineer-incharge.

3490.67

each

Safety jacket

1.0000

each

1200.00

Subtotal-B: Subtotal-C:

1200.00 1200.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1224.00

10% Profit ( Add 10% on Subtotal-B) :

1346.40

VAT

6% of Total

89.76

IT

4% of Total

59.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2800.00

1496.00

Page: 1906 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.23

Detailed Analysis Brief Description of Item 2 Supplying of Best Quality Safety hand gloves for construction work of Flexible/durable/excellent puncture resistance working gloves with PVC palm and T/C drill back, pasted cuff ,palm liner . all complete in all respect as per approved specification and direction of the Engineer-incharge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

350.00

350.00

each

Safety hand gloves

1.0000

each

350.00

Subtotal-A:

6.13.24

Supplying of Best Quality Safety Shoe of leather. all complete in all respect as per approved specification and direction of the Engineer-incharge.

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

357.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

392.70

VAT

6% of Total

IT

4% of Total

26.18 17.45 Total:

436.33

1500.00

1500.00

each

Safety Shoe

1.0000

each

1500.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1530.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1683.00

VAT

6% of Total

112.20

IT

4% of Total

74.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1870.00

Page: 1907 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.13.25

Detailed Analysis Brief Description of Item 2 Supplying of Best Quality Safety Helmate of ABS shell, tough, lightweight, durable. Available with four-point or six-point adjustable suspension for shock-absorbing and rain through prevents water from dropping down to the neck, reinforced ribs on top provides the perfect impact protection. Slotted sides to accommodate accessories, such as face shields, ear muffs. Chin Strap not included. all complete in all respect as per approved specification and direction of the Engineer-incharge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

500.00

500.00

each

Safety Helmate

1.0000

each

500.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

510.00

10% Profit ( Add 10% on Subtotal-B) :

561.00

VAT

6% of Total

37.40

IT

4% of Total

24.93 Total:

6.14.01

623.33

Labour charge for unlocking old rubber bag from central floor of rubber dam, including breaking of existing cement concrete, removing bolts and washers carefully without any damage, cleaning rubber bag & floor with appropriate means (by water spraying using hose pipe), taking away the rubber bag and dismantled materials from existing position safely to a suitable and safe distance, carrying, all sorts of handling, stacking smoothly the same properly, preparation and making artificial casing by angles where necessary, including cost of all necessary accessories, their carriages, wages of labour, technicians, incidental charges etc. all complete, approved and accepted by the Engineer-inCharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1908 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.14.01.1

Detailed Analysis Brief Description of Item 2 Placing on the river/khal bank or in the WMCA premises up to 5.0 km

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m H.C. of P & H Mobile Crane (25 ton)

0.0070

day

10000.00

70.00

Artificial Casing Preparation

0.2500

sqm

352.00

88.00

Foreman

0.3000

day

800.00

240.00

Skilled Labour Ordinary Labour

1.3000

day

450.00

585.00

12.0000

day

370.00

4440.00 5423.00

Subtotal-A: Extra for carring (+5.55% on Sub Total-A)

( +5.55 % on Subtotal-A )

300.98

Subtotal-A1: Subtotal-B: Subtotal-C:

5723.98 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5838.46

10% Profit ( Add 10% on Subtotal-B) :

6422.30

VAT

6% of Total

428.15

IT

4% of Total

285.44 Total:

6.14.01.2

Placing other places for additional for each 1 km beyond 5 km

Note : Rates of all items should be inclusive of all supply and carriage.

m

7135.89

Add +5.00% with Item No 6.14.01.1

Page: 1909 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.14.02

Detailed Analysis Brief Description of Item 2 Labour charge for repairing of rubber bag with suitable strong adhesive and 5 mm thick rubber sheet, including cleaning, washing and drying the defective portion of bag, making scaffolding and platform if necessary, clean off and remove waste and debris, including cost of all necessary accessories, their carriages, wages of labour, technicians, incidental charges etc. all complete, approved and accepted by the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Rubber sheet 5.0mm thick

1.0000

sqm

992.17

992.17

Toluine (Chemicals to liquify glue and Cleaning)

0.5000

liter

100.00

50.00

Rubber Glue

0.2500

kg

472.20

118.05

Foreman

0.1250

day

800.00

100.00

Skilled Labour

0.1250

day

450.00

56.25

Ordinary Labour

0.1250

day

370.00

46.25 1362.72

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1389.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1528.97

VAT

6% of Total

101.93

IT

4% of Total

67.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1698.86

Page: 1910 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.14.03

Detailed Analysis Brief Description of Item 2 Supplying, fitting, fixing and setting of 12mm thick rubber felt on steel sheet pile or any other specified location where necessary, including cost of cleaning, washing, drying the surface and all necessary accessories, their carriages, wages of labour, technicians and incidental charges etc. all complete, approved and accepted by the Engineer-inCharge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Rubber sheet (felt) 12 mm thick

1.0000

sqm

2382.00

2382.00

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0100

day

370.00

3.70 2390.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2438.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2681.80

VAT

6% of Total

178.79

IT

4% of Total

119.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2979.78

Page: 1911 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.14.04

Detailed Analysis Brief Description of Item 2 Supplying, fitting, fixing and setting of 25mm thick rubber felt on steel sheet pile or any other specified location where necessary, including cost of cleaning, washing, drying the surface and all necessary accessories, their carriages, wages of labour, technicians and incidental charges etc. all complete, approved and accepted by the Engineer-inCharge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Rubber sheet (felt) 25 mm thick

1.0000

sqm

4800.00

4800.00

Skilled Labour

0.0150

day

450.00

6.75

Ordinary Labour

0.0150

day

370.00

5.55 4812.30

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4908.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5399.40

VAT

6% of Total

359.96

IT

4% of Total

239.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5999.33

Page: 1912 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 6.14.05

Detailed Analysis Brief Description of Item 2 Carrying charge for old Rubber bag from Rubber dam site or from any other places to Upazila HQ or any other specified location by truck or by any other means safely, including loading, unloading, placing, stacking to a suitable place smoothly and shapely without any damage, including hire charge of vehicles, cranes, cost of all necessary accessories, wages of labour, technicians and incidental charges etc. all complete and accepted by the Engineer-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

tonnekm

Skilled Labour

0.0100

day

450.00

4.50

Ordinary Labour

0.0500

day

370.00

18.50 23.00

Subtotal-A: Extra for carring and equipments (+115.5% on Sub Total-A)

( +115.50 % on Subtotal-A )

Subtotal-A1:

26.57 49.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

50.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

55.61

VAT

6% of Total

3.71

IT

4% of Total

2.47 Total:

61.79

Chapter - 7 : Sanitary, Water Supply & Fire Fighting Works 7.01.01

Supplying, fitting and fixing Bangladesh pattern "BISF STANDARD" Long Pan (Model-314E, size 525mmx 295mmx 285mm, Bowl size-410mmx 225mm x 170mm or equivalent) with foot rest of vitreous China and preparing the base of pan with cement concrete (1:2:4) and wire net or rods including making holes wherever required and mending good the damages, etc. all complete as per direction of the E-I-C

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1913 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.01.01.01

2 White [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard simple type white porcelain long pan (Model314E, size-525x295x285mm, Bowl size-410x225x170mm)

1.0000

each

421.00

421.00

Ordinary Portland Cement (CEM I, 52.5N)

0.2500

bag

455.00

113.75

25.0000

each

9.00

225.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

1st Class Brick

1334.75

Subtotal-A: All other remaining costs, like sand, breaking costs of khoa, putty, joining materials etc.

( +4.00 % on Subtotal-A )

53.39

Subtotal-A1: Subtotal-B: Subtotal-C:

1388.14 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1415.90

10% Profit ( Add 10% on Subtotal-B) :

1557.49

VAT

6% of Total

IT

4% of Total

103.83 69.22 Total:

7.01.02

1730.55

Supplying, fitting and fixing Bangladesh pattern "BISF STANDARD" Long Oriental Pan (Model-320, size 540mmx 425mmx 270mm, Bowl size390mmx 210mm x 190mm or equivalent) with foot rest of vitreous China and preparing the base of pan with cement concrete (1:2:4) and with wire net or rods including making holes wherever required and mending good the damages, etc. all complete as per direction of the E-IC.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1914 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.01.02.01

2 White [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard white porcelain long pan (Model-320, size540x425x270mm, Bowl size-390x210x190mm) with foot rest

1.0000

each

790.00

790.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

0.5000

day

680.00

340.00

1st Class Brick Plumber/ Electric Mistry/ Painter Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 1882.50

Subtotal-A: All other remaining costs, like sand, breaking costs of khoa, putty, joining materials etc.

( +4.00 % on Subtotal-A )

75.30

Subtotal-A1:

1957.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1996.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2196.65

VAT

6% of Total

IT

4% of Total

146.44 97.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2440.72

Page: 1915 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.01.02.02

2 Coloured [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard coloured porcelain long pan (Model-320, size540x425x270mm, Bowl size-390x210x190mm) with foot rest

1.0000

each

830.00

830.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

0.5000

day

680.00

340.00

1st Class Brick Plumber/ Electric Mistry/ Painter Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 1922.50

Subtotal-A: All other remaining costs, like sand, breaking costs of khoa, putty, joining materials etc.

( +4.00 % on Subtotal-A )

76.90

Subtotal-A1:

1999.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2039.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2243.33

VAT

6% of Total

IT

4% of Total

149.56 99.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2492.59

Page: 1916 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.01.02.03

Detailed Analysis Brief Description of Item 2 Special Coloured [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard special coloured porcelain long pan (Model320, size-540x425x270mm, Bowl size-390x210x190mm) with foot rest

1.0000

each

872.00

872.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

1st Class Brick

25.0000

each

9.00

225.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 1964.50

Subtotal-A: All other remaining costs, like sand, breaking costs of khoa, putty, joining materials etc.

( +4.00 % on Subtotal-A )

78.58

Subtotal-A1: Subtotal-B: Subtotal-C:

2043.08 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2083.94

10% Profit ( Add 10% on Subtotal-B) :

2292.34

VAT

6% of Total

IT

4% of Total

152.82 101.88 Total:

7.01.03

2547.04

Supplying, fitting and fixing Bangladesh pattern BISF Standard Porcelain Oriental Pan (Model-320, size-540x425x270mm, Bowl size390x210x190mm) or equivalent with foot rest with foot rest of vitreous China and preparing the base of pan with cement concrete (1:2:4) and wire net or rods including making holes wherever required and mending good the damages, supplying minimum 10 liters capacity lowdown wirh master siphon and lowdown cover or equivalent complete set and fitting fixing the same in position with C.I. brackets including supplying best quality 40mm dia PVC flush pipe with brass coupling (not exceeding 1.80m in length), 12mm dia plastic connection pipe with brass coupling, 12mm dia brass stop cock, 12mm dia ball cock and pulling chain etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1917 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.01.03.01

2 White [BISF ASTANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard white porcelain long pan (Model-320, size540x425x270mm, Bowl size-390x210x190mm) with foot rest

1.0000

each

790.00

790.00

20 Mesh 24 BWG GI wire net

0.9300

m2

144.46

134.35

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia PVC flush Pipe with 1.83m long brass coupling

1.0000

each

120.00

120.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia heavy type brass stop cock

1.0000

each

650.00

650.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

0.5000

day

680.00

340.00

1st Class Brick Plumber/ Electric Mistry/ Painter Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 3984.85

Subtotal-A: All other remaining costs like ball cock, brush cock, pulling chain, sand, putty, joining materials, etc.

( +4.00 % on Subtotal-A )

159.39

Subtotal-A1:

4144.24

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4227.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4649.84

VAT

6% of Total

309.99

IT

4% of Total

206.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5166.49

Page: 1918 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.01.03.02

2 Coloured [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard coloured porcelain long pan (Model-320, size540x425x270mm, Bowl size-390x210x190mm) with foot rest

1.0000

each

830.00

830.00

20 Mesh 24 BWG GI wire net

0.9300

m2

144.46

134.35

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

CI Bracket

1.0000

pair

65.00

65.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

40mm dia PVC flush Pipe with 1.83m long brass coupling

1.0000

each

120.00

120.00

12mm dia heavy type brass stop cock

1.0000

each

650.00

650.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

0.5000

day

680.00

340.00

1st Class Brick Plumber/ Electric Mistry/ Painter Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 4024.85

Subtotal-A: All other remaining costs like ball cock, brush cock, pulling chain, sand, putty, joining materials, etc.

( +4.00 % on Subtotal-A )

160.99

Subtotal-A1:

4185.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4269.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4696.51

VAT

6% of Total

313.10

IT

4% of Total

208.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5218.35

Page: 1919 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.01.03.03

Detailed Analysis Brief Description of Item 2 Special coloured [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard special coloured porcelain long pan (Model320, size-540x425x270mm, Bowl size-390x210x190mm) with foot rest

1.0000

each

872.00

872.00

20 Mesh 24 BWG GI wire net

0.9300

m2

144.46

134.35

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

CI Bracket

1.0000

pair

65.00

65.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

40mm dia PVC flush Pipe with 1.83m long brass coupling

1.0000

each

120.00

120.00

12mm dia heavy type brass stop cock

1.0000

each

650.00

650.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

1st Class Brick

4066.85

Subtotal-A: All other remaining costs like ball cock, brush cock, pulling chain, sand, putty, joining materials, etc.

( +4.00 % on Subtotal-A )

162.67

Subtotal-A1: Subtotal-B: Subtotal-C:

4229.52 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4314.11

10% Profit ( Add 10% on Subtotal-B) :

4745.52

VAT

6% of Total

316.37

IT

4% of Total

210.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5272.80

Page: 1920 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.01.04

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, fitting and fixing, Bangladesh pattern BISF Standard simple type Porcelain Long Pan (Model-323, size-520x290x260mm) or equivalent simple type of vitreous China with Siphon and preparing the base of pan with cement concrete and wire net or rods including making holes in walls and floors wherever required and mending good the damages, supplying Porcelain lowdown with master Siphon with Low down cover and all fittings, fitting fixing the same in position with C.I. brackets including supplying best quality 38mm dia PVC flush pipe with brass coupling (not exceeding 1.80m in length), 12mm dia plastic connection pipe with brass coupling, 12mm dia brass stop cock, 12mm dia ball cock and pulling chain etc. all complete as per direction of the EI-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1921 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.01.04.01

2 White [BISF STANDARD] (520mmx290mmx260mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard simple type white porcelain long pan (Model323, size-520x290x260mm)

1.0000

each

581.00

581.00

Porcelain Siphon (Low down)

1.0000

each

1100.00

1100.00

20 Mesh 24 BWG GI wire net

0.9300

m2

144.46

134.35

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

CI Bracket

1.0000

pair

65.00

65.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

40mm dia PVC flush Pipe with 1.83m long brass coupling

1.0000

each

120.00

120.00

12mm dia heavy type brass stop cock

1.0000

each

650.00

650.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

1st Class Brick

4875.85

Subtotal-A: All other remaining costs like ball cock, brush cock, pulling chain, sand, putty, joining materials, etc.

( +4.00 % on Subtotal-A )

195.03

Subtotal-A1:

5070.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5172.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5689.53

VAT

6% of Total

379.30

IT

4% of Total

252.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6321.70

Page: 1922 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.01.04.02

2 Coloured [BISF STANDARD] (520mmx290mmx260mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each BISF Standard simple type coloured porcelain long pan (Model-323, size-520x290x260mm)

1.0000

each

611.00

611.00

Porcelain Siphon (Low down)

1.0000

each

1100.00

1100.00

20 Mesh 24 BWG GI wire net

0.9300

m2

144.46

134.35

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

CI Bracket

1.0000

pair

65.00

65.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

40mm dia PVC flush Pipe with 1.83m long brass coupling

1.0000

each

120.00

120.00

12mm dia heavy type brass stop cock

1.0000

each

650.00

650.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

1st Class Brick

4905.85

Subtotal-A: All other remaining costs like ball cock, brush cock, pulling chain, sand, putty, joining materials, etc.

( +4.00 % on Subtotal-A )

196.23

Subtotal-A1:

5102.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5204.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5724.54

VAT

6% of Total

381.64

IT

4% of Total

254.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6360.60

Page: 1923 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

7.01.04.03

White [BISF STANDARD] Long Pan (Model-314E, size-525x295x285mm, Bowl size-410x225x170mm)

each

Quantity 5

Unit

Rate

Amount

6

7

8

BISF Standard simple type white porcelain long pan (Model314E, size-525x295x285mm, Bowl size-410x225x170mm)

1.0000

each

421.00

421.00

Porcelain Siphon (Low down)

1.0000

each

1100.00

1100.00

20 Mesh 24 BWG GI wire net

0.9300

m2

144.46

134.35

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

CI Bracket

1.0000

pair

65.00

65.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

40mm dia PVC flush Pipe with 1.83m long brass coupling

1.0000

each

120.00

120.00

12mm dia heavy type brass stop cock

1.0000

each

650.00

650.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

1st Class Brick

4715.85

Subtotal-A: All other remaining costs like ball cock, brush cock, pulling chain, sand, putty, joining materials, etc.

( +4.00 % on Subtotal-A )

188.63

Subtotal-A1:

4904.48

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5002.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5502.83

VAT

6% of Total

366.86

IT

4% of Total

244.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6114.25

Page: 1924 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

7.01.05

Supplying "BISF STANDARD" quality glazed porcelain Foot Rest (Model305, size-280mmx140mmx30mm size or equivalent) including fitting fixing in position with cement mortar (1:4) if necessary in all floors including making holes wherever required and mending good the damages and fitting, fixing, finishing with all necessary fittings and connection etc. all complete as per direction of the E-I-C.

7.01.05.01

White "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each BISF standard white porcelain foot rest (Model-305, size280x140x30mm)

1.0000

pair

74.00

74.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 168.00

Subtotal-A: All other remaining costs like cement, sand, etc.

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

191.52 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

195.35

10% Profit ( Add 10% on Subtotal-B) :

214.89

VAT

6% of Total

IT

4% of Total

14.33 9.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23.52

238.76

Page: 1925 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.01.05.02

2 Coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each BISF Standard coloured porcelain foot rest (Model-305, size280x140x30mm)

1.0000

pair

80.00

80.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 174.00

Subtotal-A: All other remaining costs like cement, sand, etc.

( +14.00 % on Subtotal-A )

Subtotal-A1:

198.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

202.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

222.56

VAT

6% of Total

IT

4% of Total

14.84 9.89 Total:

7.01.06

24.36

247.29

Supplying, fitting and fixing superior quality Asian Water Closet (Long Oriental Pan) with foot rest of vitreous China and preparing the base of pan with cement concrete (1:2:4) and with wire net or rods including making holes wherever required and mending good the damages, supplying Asian cistern and fitting fixing the same in position with C.I. brackets including supplying best quality 40mm dia PVC flush pipe with brass coupling (not exceeding 1.80m in length), 12mm dia plastic connection pipe with brass coupling, 12mm dia brass stop cock, 12mm dia ball cock and pulling chain etc. all complete as per direction of the EI-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1926 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

7.01.06.01

Asian Water Closet 29cm (long pan), size: 540x470x290mm, Asian Cistern, size: 385x105x210mm, Brand: RAK or Equivalent

each

Quantity 5

Unit

Rate

6

7

Amount 8

Asian Water Closet 29cm (long pan), size: 540x470x290mm, RAK or Equivalent

1.0000

each

1385.00

1385.00

20 Mesh 24 BWG GI wire net

0.9300

m2

144.46

134.35

Asian Cistern, size: 385x105x210mm, RAK or Equivalent

1.0000

each

2000.00

2000.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia PVC flush Pipe with 1.83m long brass coupling

1.0000

each

120.00

120.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia heavy type brass stop cock

1.0000

each

650.00

650.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

1st Class Brick

5501.85

Subtotal-A: All other remaining costs like ball cock, brush cock, pulling chain, sand, putty, joining materials, etc.

( +4.00 % on Subtotal-A )

220.07

Subtotal-A1:

5721.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5836.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6420.00

VAT

6% of Total

428.00

IT

4% of Total

285.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7133.33

Page: 1927 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.01.06.02

Detailed Analysis Brief Description of Item 2 Asian Water Closet 18 cm (long pan), size: 505x390x200mm, Asian Cistern, size: 385x100x210mm, Brand: RAK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Asian Water Closet 18 cm (long pan), size: 505x390x200mm, RAK or Equivalent

1.0000

each

790.00

790.00

20 Mesh 24 BWG GI wire net

0.9300

m2

144.46

134.35

Asian Cistern, size: 385x100x210mm, RAK or Equivalent

1.0000

each

1970.00

1970.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia PVC flush Pipe with 1.83m long brass coupling

1.0000

each

120.00

120.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia heavy type brass stop cock

1.0000

each

650.00

650.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.2500

bag

430.00

107.50

25.0000

each

9.00

225.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

1st Class Brick

4876.85

Subtotal-A: All other remaining costs like ball cock, brush cock, pulling chain, sand, putty, joining materials, etc.

( +4.00 % on Subtotal-A )

195.07

Subtotal-A1:

5071.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5173.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5690.70

VAT

6% of Total

379.38

IT

4% of Total

252.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6323.00

Page: 1928 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.02.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, fitting and fixing European type glazed porcelain commode "P" or "S" type "BISF STANDARD" (Model-106A, Size475mmx350mmx435mm, Bowl size-350mmx280mmx350mm) with 10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm), (vitress china) including all internal fittings (best quality) with ebonite (heavy type) plastic seat cover, best quality 12mm dia C.P. stop cock, 12mm dia plastic connection pipe with brass coupling and preparing the base with cement concrete and with wire net or rods including making holes wherever required and mending good the damages and fitting, fixing with all necessary fittings and connection, etc. all complete as per direction of the Engineer in Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1929 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.02.01.01

2 White [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each BISF standard white porcelain commode (Model-106A, size475x350x435mm, Bowl size-350x280x350mm)

1.0000

each

1155.00

1155.00

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

Heavy type ebonite plastic seat cover

1.0000

each

650.00

650.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 4348.00

Subtotal-A: All other remaining costs like cost of all internal fittings, blocks, wire net, screws, etc.

( +9.00 % on Subtotal-A )

391.32

Subtotal-A1:

4739.32

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4834.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5317.52

VAT

6% of Total

354.50

IT

4% of Total

236.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5908.35

Page: 1930 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.02.01.02

2 Coloured [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each BISF Standard Coloured porcelain commode (Model-106A, size-475x350x435mm, Bowl size-350x280x350mm)

1.0000

each

1214.00

1214.00

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

Heavy type ebonite plastic seat cover

1.0000

each

650.00

650.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 4407.00

Subtotal-A: All other remaining costs like cost of all internal fittings, blocks, wire net, screws, etc.

( +9.00 % on Subtotal-A )

396.63

Subtotal-A1:

4803.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4899.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5389.67

VAT

6% of Total

359.31

IT

4% of Total

239.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5988.53

Page: 1931 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.02.01.03

Detailed Analysis Brief Description of Item 2 Special Coloured [BISF STANDARD]

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each BISF Standard special coloured Porcelain commode (Model106A, size-475x350x435mm, Bowl size-350x280x350mm)

1.0000

each

1274.00

1274.00

10.00 Liter Capacity low down cistern (Model-403, size530x215x370mm),(white vitress china)

1.0000

each

1078.00

1078.00

Heavy type ebonite plastic seat cover

1.0000

each

650.00

650.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 4467.00

Subtotal-A: All other remaining costs like cost of all internal fittings, blocks, wire net, screws, etc.

( +9.00 % on Subtotal-A )

402.03

Subtotal-A1:

4869.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4966.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5463.05

VAT

6% of Total

364.20

IT

4% of Total

242.80 Total:

7.02.02

6070.06

Supplying, fitting and fixing superior quality Combi-closet glazed porcelain commode with seat cover, water tank with flushing unit, including fitting with fitting nut bolt of same brand in wall or floor with all internal fittings (best quality), best quality 12mm dia heavy type concealed C.P. stop cock for lowdown, 12mm dia plastic connection pipe with coupling including making holes in walls or floor or wherever required and mending good the damages and fitting, fixing with all necessary fittings and connection, etc. all complete as per direction of the E-I-C. (Commode, Lowdown, set with fittings)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1932 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.02.02.01

Detailed Analysis Brief Description of Item 2 Size : 700x370x795 Model: RAK Orient or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Combi-Closet and Seat Cover with Water Tank and Flushing Unit, Size: 700x370x795mm (RAK Orient or Equivalent)

1.0000

each

7340.00

7340.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 8805.00

Subtotal-A: All other remaining costs like cost of all internal fittings, blocks, wire net, screws, etc.

( +9.00 % on Subtotal-A )

792.45

Subtotal-A1: Subtotal-B: Subtotal-C:

9597.45 9789.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10768.34

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

717.89 478.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11964.82

Page: 1933 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

7.02.02.02

Size: 690x360x755mm (S Trap), Model: RAK Karla or Equivalent

each

Quantity 5

Unit

Rate

6

7

Amount 8

Combi-Closet and Seat Cover with Water Tank and Flushing Unit, Size: 690x360x755mm (RAK Karla or Equivalent)

1.0000

each

5566.00

5566.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 7031.00

Subtotal-A: All other remaining costs like cost of all internal fittings, blocks, wire net, screws, etc.

( +9.00 % on Subtotal-A )

632.79

Subtotal-A1:

7663.79

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7817.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8598.77

VAT

6% of Total

IT

4% of Total

573.25 382.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9554.19

Page: 1934 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

7.02.02.03

Size: 725x360x840mm (S Trap), Model: RAK Venice or Equivalent

each

Quantity 5

Unit

Rate

6

7

Amount 8

Combi-Closet and Seat Cover with Water Tank and Flushing Unit, Size: 725x360x840mm (RAK Venice or Equivalent)

1.0000

each

12933.00

12933.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Ordinary Labour

0.5000

day

370.00

185.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 14398.00

Subtotal-A: All other remaining costs like cost of all internal fittings, blocks, wire net, screws, etc.

( +9.00 % on Subtotal-A )

1295.82

Subtotal-A1:

15693.82

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16007.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17608.47

VAT

6% of Total

IT

4% of Total

1173.90 782.60 Total:

7.02.03

19564.96

Commode/WC: Supplying, installation and commissioning of foreign made floor mounted close coupled European type commode/water closet (WC) ‘P’ or ‘S’ Trap with all internal parts of porcelain dual flush cistern (4.8l & 3l), plastic soft closing seat cover with rubber buffer and cap, supplying & fixing 12mm dia two in one bib cock for lowdown, 12mm dia heavy duty hose plus coupling, push shower, including fitting & fixing by specified nuts & bolts, making holes wherever required with preparing the base using cement concrete with wire mesh or rods (if necessary), mending the damages etc., including cost of all necessary accessories, their carriages, wages of labour, plumber and incidental charges etc. all complete, as per direction & approval of the Engineer-inCharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1935 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.02.03.01

Detailed Analysis Brief Description of Item 2 Size: 693x451x763 mm, Model: TOTO - C300 or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreign made close couple Commode, Size: 693x451x763, Model: TOTO - C300 or Equivalent

1.0000

each

28500.00

28500.00

12mm dia metal wire sheathed connection pipe with brass/steel coupling, Model: TOTO - T025005 or Equivalent

1.0000

each

550.00

550.00

12mm dia two in one bib cock, Model: TOTO - TX131L or Equivalent

1.0000

each

5500.00

5500.00

Moving type push shower, Model : THX20MCRB or Equivalent

1.0000

each

3500.00

3500.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 38810.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

39586.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

43544.82

VAT

6% of Total

2902.99

IT

4% of Total

1935.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

48383.13

Page: 1936 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.02.03.02

Detailed Analysis Brief Description of Item 2 Size: 695x368x763 mm, Model: TOTO C300RE#W or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreign made close couple Commode, Size: 695x368x763, Model: TOTO C300RE#W or Equivalent

1.0000

each

29000.00

29000.00

12mm dia metal wire sheathed connection pipe with brass/steel coupling, Model: TOTO - T025005 or Equivalent

1.0000

each

550.00

550.00

12mm dia two in one bib cock, Model: TOTO - TX131L or Equivalent

1.0000

each

5500.00

5500.00

Moving type push shower, Model : THX20MCRB or Equivalent

1.0000

each

3500.00

3500.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 39310.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40096.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

44105.82

VAT

6% of Total

2940.39

IT

4% of Total

1960.26 Total:

7.03.01

49006.47

Supplying, fitting and fixing superior quality Combi-closet glazed porcelain commode with seat cover, water tank with flushing unit, wash hand basin with pedestal including fitting with fitting nut bolt of same brand in wall or floor with all internal fittings (best quality), best quality 12mm dia heavy type concealed C.P. stop cock for lowdown and basin, 12 mm dia heavy type basin pillar cock, 12mm dia basin & lowdown plastic connection pipe with brass coupling, 30mm dia C.P. basin waste with chain plug, 44mm dia PVC waste water pipe with coupling including making holes in walls or floor or wherever required and mending good the damages and fitting, fixing with all necessary fittings and connection, etc. all complete as per direction of the E-I-C. (Commode, Lowdown, Wash Hand Basin with Pedestal complete set with fittings)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1937 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

7.03.01.01

Size: W.C. S trap & cistern : 680x370x800mm (S or P Trap), Wash basin & pedestal : 660x545x850 Model: RAK Orient or Equivalent

each

Quantity 5

Unit

Rate

6

7

Amount 8

Combi-Closet and Seat Cover with Water Tank and Flushing Unit, Size: 700x370x795mm (RAK Orient or Equivalent)

1.0000

each

7340.00

7340.00

Wash Hand Basin, Size: 660x545mm (RAK Orient or Equivalent)

1.0000

each

2035.00

2035.00

Pedestal, Size: 860mm long (RAK Orient or Equivalent)

1.0000

each

1485.00

1485.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 12615.00

Subtotal-A: All other remaining costs like all internal fittings, blocks, screws, wire net etc

( +9.00 % on Subtotal-A )

1135.35

Subtotal-A1: Subtotal-B: Subtotal-C:

13750.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14025.36

10% Profit ( Add 10% on Subtotal-B) :

15427.89

VAT

6% of Total

IT

4% of Total

1028.53 685.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17142.10

Page: 1938 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.03.01.02

Detailed Analysis Brief Description of Item 2 Size: W.C. S trap & cistern: 690x360x755mm (S Trap), Wash basin & pedestal : 605x485x 835 Model: RAK Karla or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Combi-Closet and Seat Cover with Water Tank and Flushing Unit, Size: 690x360x755mm (RAK Karla or Equivalent)

1.0000

each

5566.00

5566.00

Wash Hand Basin, Size: 605x485mm (RAK Karla or Equivalent)

1.0000

each

1610.00

1610.00

Pedestal, Size: 835mm long (RAK Karla or Equivalent)

1.0000

each

1385.00

1385.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 10316.00

Subtotal-A: All other remaining costs like all internal fittings, blocks, screws, wire net etc

( +9.00 % on Subtotal-A )

928.44

Subtotal-A1: Subtotal-B: Subtotal-C:

11244.44 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11469.33

10% Profit ( Add 10% on Subtotal-B) :

12616.26

VAT

6% of Total

IT

4% of Total

841.08 560.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14018.07

Page: 1939 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.03.01.03

Detailed Analysis Brief Description of Item 2 Size: W.C. S trap & cistern : 725x360x840mm S Trap), Wash basin & pedestal : 650x510x855mm Model: RAK Venice or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Combi-Closet and Seat Cover with Water Tank and Flushing Unit, Size: 725x360x840mm (RAK Venice or Equivalent)

1.0000

each

12933.00

12933.00

Wash Hand Basin, Size: 650x510mm (RAK Venice or Equivalent)

1.0000

each

3619.00

3619.00

Pedestal, Size: 855mm long (RAK Venice or Equivalent)

1.0000

each

2200.00

2200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia C.P stop cock

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 20507.00

Subtotal-A: All other remaining costs like all internal fittings, blocks, screws, wire net etc

( +9.00 % on Subtotal-A )

1845.63

Subtotal-A1: Subtotal-B: Subtotal-C:

22352.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22799.68

10% Profit ( Add 10% on Subtotal-B) :

25079.65

VAT

6% of Total

IT

4% of Total

1671.98 1114.65 Total:

7.04.01

27866.28

Supplying, fitting and fixing "BISF STANDARD" glazed vitreous Wash Hand Basin (Model-213, size-450x405x180mm, Bowl size375x275x136mm) including fitting fixing the same in position with heavy type C.I. brackets, 44mm dia PVC waste water pipe with brass coupling (not exceeding 750mm in length), 12mm dia plastic connection pipe with brass coupling, 12mm dia brass stop cock, 12mm dia C.P. pillar cock, 30mm dia C.P. Basin waste with chain plug including making holes in walls and floors and fitting with royal plug, screws and mending good the damages etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1940 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.01.01

2 White "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each White wash hand basin (Model-213, size-450x405x180mm, Bowl size-375x275x136mm)

1.0000

each

578.00

578.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4633.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

138.99

Subtotal-A1:

4771.99

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4867.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5354.17

VAT

6% of Total

356.94

IT

4% of Total

237.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5949.08

Page: 1941 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.01.02

2 Coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coloured wash hand basin (Model-213, size450x405x180mm, Bowl size-375x275x136mm)

1.0000

each

607.00

607.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4662.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

139.86

Subtotal-A1:

4801.86

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4897.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5387.69

VAT

6% of Total

359.18

IT

4% of Total

239.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5986.32

Page: 1942 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.01.03

Detailed Analysis Brief Description of Item 2 Special coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Special coloured wash hand basin (Model-213, size450x405x180mm, Bowl size-375x275x136mm)

1.0000

each

637.00

637.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4692.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

140.76

Subtotal-A1:

4832.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4929.42

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5422.36

VAT

6% of Total

361.49

IT

4% of Total

240.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6024.84

Page: 1943 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, fitting and fixing superior quality glazed vitreous Wash Hand Basin including fitting fixing the same in position with heavy type C.I. Brackets 44mm dia PVC waste water pipe with brass coupling (not exceeding 750mm in length), 12mm dia plastic connection pipe with brass coupling, 12mm dia brass stop cock, 12mm dia C.P. pillar cock, 30mm dia C.P. Basin waste with chain plug including making holes in walls and floors and fitting with wooden blocks screws and mending good the damages etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1944 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.02.01

Detailed Analysis Brief Description of Item 2 Size: 660x545mm (RAK Orient or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wash Hand Basin, Size: 660x545mm (RAK Orient or Equivalent)

1.0000

each

2035.00

2035.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 6090.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

182.70

Subtotal-A1:

6272.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6398.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7037.97

VAT

6% of Total

469.20

IT

4% of Total

312.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7819.97

Page: 1945 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.02.02

Detailed Analysis Brief Description of Item 2 Size: 605x485mm, Model: RAK Karla or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wash Hand Basin, Size: 605x485mm (RAK Karla or Equivalent)

1.0000

each

1610.00

1610.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 5665.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

169.95

Subtotal-A1:

5834.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5951.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6546.81

VAT

6% of Total

436.45

IT

4% of Total

290.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7274.24

Page: 1946 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.02.03

Detailed Analysis Brief Description of Item 2 Size: 650x510mm, Model: RAK Venice or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wash Hand Basin, Size: 650x510mm (RAK Venice or Equivalent)

1.0000

each

3619.00

3619.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 7674.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

230.22

Subtotal-A1:

7904.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8062.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8868.53

VAT

6% of Total

591.24

IT

4% of Total

394.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9853.93

Page: 1947 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.02.04

Detailed Analysis Brief Description of Item 2 Size: 520x445mm (RAK Cynthia or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wash Hand Basin, Size: 520x445mm (RAK Cynthia or Equivalent)

1.0000

each

1375.00

1375.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 5430.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

162.90

Subtotal-A1:

5592.90

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5704.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6275.23

VAT

6% of Total

418.35

IT

4% of Total

278.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6972.48

Page: 1948 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.02.05

Detailed Analysis Brief Description of Item 2 Size: 510x405mm, Model: RAK Lara or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wash Hand Basin, Size: 510x405mm (RAK Lara or Equivalent)

1.0000

each

1375.00

1375.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 5430.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

162.90

Subtotal-A1:

5592.90

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5704.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6275.23

VAT

6% of Total

IT

4% of Total

418.35 278.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6972.48

Page: 1949 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.02.06

Detailed Analysis Brief Description of Item 2 Size: 660x525mm (RAK Windsor or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wash Hand Basin, Size: 660x525mm (RAK Windsor or Equivalent)

1.0000

each

2985.00

2985.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 7040.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

211.20

Subtotal-A1:

7251.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7396.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8135.85

VAT

6% of Total

542.39

IT

4% of Total

361.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9039.83

Page: 1950 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.03

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, fitting and fixing "BISF STANDARD" glazed vitreous wash hand cabinet basin (Model-216, size-500x450x210mm and bowel size 395x315x160mm) including fitting, fixing the same in position with heavy type C.I. brackets, 44mm dia PVC waste water pipe with brass coupling (not exceeding 750mm in length), 12mm plastic connection pipe with brass coupling, 12mm dia brass stop cock, 12mm dia C.P. pillar cock, 30mm dia C.P. Basin waste with chain plug including making holes in walls and floors and fitting with wooden blocks screws and mending good the damages etc. all complete as per direction of the E-IC.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1951 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.03.01

2 White "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each White wash hand cabinet basin (Model-216, size500x450x210mm)

1.0000

each

1158.00

1158.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 5213.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

156.39

Subtotal-A1:

5369.39

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5476.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6024.46

VAT

6% of Total

401.63

IT

4% of Total

267.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6693.84

Page: 1952 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.03.02

2 Coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Coloured wash hand cabinet basin (Model-216, size500x450x210mm)

1.0000

each

1216.00

1216.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 5271.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

158.13

Subtotal-A1:

5429.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5537.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6091.48

VAT

6% of Total

406.10

IT

4% of Total

270.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6768.32

Page: 1953 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.03.03

Detailed Analysis Brief Description of Item 2 Special coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Special coloured wash hand cabinet basin (Model-216, size500x450x210mm)

1.0000

each

1277.00

1277.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waste with brass coupling

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 5332.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

159.96

Subtotal-A1:

5491.96

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5601.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6161.98

VAT

6% of Total

410.80

IT

4% of Total

273.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6846.64

Page: 1954 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.04

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, fitting and fixing "BISF STANDARD" glazed vitreous wash hand cabinet basin (Model-214, size-465x340x180mm and bowel size 350x230x130mm) including fitting, fixing the same in position with heavy type C.I. brackets, 44mm dia PVC waste water pipe with brass coupling (not exceeding 750mm in length), 12mm plastic connection pipe with brass coupling, 12mm dia brass stop cock, 12mm dia C.P. pillar cock, 30mm dia C.P. Basin waste with chain plug including making holes in walls and floors and fitting with wooden blocks screws and mending good the damages etc. all complete as per direction of the Engineering-in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1955 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.04.01

2 White "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each White wash hand cabinet basin (Model-214, size465x340x180mm)

1.0000

each

525.00

525.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waster with chain plug

1.0000

each

395.00

395.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4525.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

135.75

Subtotal-A1:

4660.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4753.97

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5229.36

VAT

6% of Total

348.62

IT

4% of Total

232.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5810.40

Page: 1956 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.04.02

2 Coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coloured wash hand cabinet basin (Model-214, size465x340x180mm)

1.0000

each

552.00

552.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waster with chain plug

1.0000

each

395.00

395.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4552.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

136.56

Subtotal-A1:

4688.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4782.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5260.56

VAT

6% of Total

350.70

IT

4% of Total

233.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5845.07

Page: 1957 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.04.03

Detailed Analysis Brief Description of Item 2 Special coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Special coloured wash hand cabinet basin (Model-214, size465x340x180mm)

1.0000

each

578.00

578.00

12mm dia CP pillar cock

1.0000

each

1200.00

1200.00

CI Bracket

1.0000

pair

65.00

65.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

CP chain with plug

1.0000

each

25.00

25.00

30mm dia CP basin waster with chain plug

1.0000

each

395.00

395.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4578.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

137.34

Subtotal-A1:

4715.34

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4809.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5290.61

VAT

6% of Total

352.71

IT

4% of Total

235.14 Total:

7.04.05

5878.46

Supplying, fitting and fixing "BISF STANDARD" glazed porcelain Pedestal (Model-715A, size-670x186x170mm) or equivalent best quality model etc. all complete as per direction of the Engineering-in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1958 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.05.01

2 White "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each White Pedestal (Model-715A, size-670x186x170mm)

1.0000

each

577.00

577.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 638.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

650.86

10% Profit ( Add 10% on Subtotal-B) :

715.95

VAT

6% of Total

47.73

IT

4% of Total

31.82 Total:

7.04.05.02

Coloured "BISF STANDARD"

each Coloured pedestal (Model-715A, size-670x186x170mm)

1.0000

each

606.00

606.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 667.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

680.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

748.49

VAT

6% of Total

49.90

IT

4% of Total

33.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

795.50

831.65

Page: 1959 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.05.03

Detailed Analysis Brief Description of Item 2 Special coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Special Coloured pedestal (Model-715A, size670x186x170mm)

1.0000

each

637.00

637.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 698.10

Subtotal-A:

7.04.06

Supplying, fitting and fixing superior quality glazed porcelain Pedestal etc. all complete as per direction of the Engineering-in-charge.

7.04.06.01

Size: 860mm long, Model: RAK Orient or Equivalent

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

712.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

783.27

VAT

6% of Total

IT

4% of Total

52.22 34.81 Total:

870.30

each Pedestal, Size: 860mm long (RAK Orient or Equivalent)

1.0000

each

1485.00

1485.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 1546.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1577.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1734.72

VAT

6% of Total

IT

4% of Total

115.65 77.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1927.47

Page: 1960 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.06.02

Detailed Analysis Brief Description of Item 2 Size: 835mm long (RAK Karla or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Pedestal, Size: 835mm long (RAK Karla or Equivalent)

1.0000

each

1385.00

1385.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 1446.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1475.02

10% Profit ( Add 10% on Subtotal-B) :

1622.52

VAT

6% of Total

108.17

IT

4% of Total

72.11 Total:

7.04.06.03

Size: 855mm long (RAK Venice or Equivalent)

each Pedestal, Size: 855mm long (RAK Venice or Equivalent)

1.0000

each

2200.00

2200.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 2261.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2306.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2536.95

VAT

6% of Total

169.13

IT

4% of Total

112.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1802.80

2818.84

Page: 1961 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.06.04

Detailed Analysis Brief Description of Item 2 Size: 795mm long (RAK Cynthia or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Pedestal, Size: 795mm long (RAK Cynthia or Equivalent)

1.0000

each

1176.00

1176.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 1237.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1261.84

10% Profit ( Add 10% on Subtotal-B) :

1388.03

VAT

6% of Total

92.54

IT

4% of Total

61.69 Total:

7.04.06.05

Size: 805mm long, Model: RAK Lara or Equivalent

each Pedestal, Size: 805mm long (RAK Lara or Equivalent)

1.0000

each

1176.00

1176.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 1237.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1261.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1388.03

VAT

6% of Total

92.54

IT

4% of Total

61.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1542.25

1542.25

Page: 1962 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.04.06.06

2 Size: 860mm long, Model: RAK Windsor or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Pedestal, Size: 855mm long (RAK Windsor or Equivalent)

1.0000

each

1925.00

1925.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 1986.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2025.82

10% Profit ( Add 10% on Subtotal-B) :

2228.40

VAT

6% of Total

148.56

IT

4% of Total

99.04 Total:

7.04.07

Supplying, fitting and fixing local best quality glazed porcelain Pedestal ( size-645mmx200mmx190mm or equivalent size and quality) etc. all complete as per direction of the Engineering-in-charge.

7.04.07.01

White

each White pedestal (Model-715, size-670x186x170mm)

1.0000

each

577.00

577.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 638.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

650.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

715.95

VAT

6% of Total

47.73

IT

4% of Total

31.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2476.00

795.50

Page: 1963 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.04.07.02

2 Coloured

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coloured pedestal (Model-715)

1.0000

each

606.00

606.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 667.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

680.44

10% Profit ( Add 10% on Subtotal-B) :

748.49

VAT

6% of Total

49.90

IT

4% of Total

33.27 Total:

7.04.07.03

Special coloured

each Special coloured pedestal (Model-715)

1.0000

each

577.00

577.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1300

day

470.00

61.10 638.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

650.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

715.95

VAT

6% of Total

47.73

IT

4% of Total

31.82 Total:

7.04.08

831.65

795.50

Supplying, fitting and fixing "BISF STANDARD" porcelain Sink (Model502, size-635x480x195mm and bowel size : 555x418x175mm) fitted and fixed with heavy type C.I brackets, 12mm dia C.P. bib cock, 40mm dia C.P. chain plug, 40mm dia C.P. waste, 40mm dia PVC waste pipe with brass coupling (750mm length) including making holes in walls and floors and mending good the damages etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1964 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.08.01

2 White "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each White porcelain Sink (Model-502, size-635x480x195mm)

1.0000

each

1760.00

1760.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia CP waste with brass coupling including CP chain plug

1.0000

set

280.00

280.00

40mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

70.00

70.00

12mm dia CP bib cock

1.0000

each

715.00

715.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 3940.00

Subtotal-A: All other remaining costs like socket, elbow, cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

118.20

Subtotal-A1:

4058.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4139.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4553.30

VAT

6% of Total

IT

4% of Total

303.55 202.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5059.22

Page: 1965 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.04.08.02

2 Coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Coloured porcelain sink (Model-502, size635x480x195mm)with sink tray (595x465x36mm)

1.0000

each

1848.00

1848.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia CP waste with brass coupling including CP chain plug

1.0000

set

280.00

280.00

40mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

70.00

70.00

12mm dia CP bib cock

1.0000

each

715.00

715.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4028.00

Subtotal-A: All other remaining costs like socket, elbow, cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

120.84

Subtotal-A1: Subtotal-B: Subtotal-C:

4148.84 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4231.82

10% Profit ( Add 10% on Subtotal-B) :

4655.00

VAT

6% of Total

IT

4% of Total

310.33 206.89 Total:

7.04.09

5172.22

Supplying, fitting and fixing porcelain Sink (625mmx490mmx224mm size) with sink tray ( 595mmx465mmx36mm) fitted and fixed with heavy type C.I brackets, 12mm dia C.P. bib cock, 40mm dia C.P. chain plug, 40mm dia C.P. waste, 40mm dia PVC waste pipe with brass coupling (750mm length) including making holes in walls and floors and mending good the damages etc. all complete as per direction of the E-IC.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1966 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.04.09.01

2 White

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each White porcelain Sink (Model-502, size-635x480x195mm)

1.0000

each

1760.00

1760.00

White porcelain sink (635x480x195mm) with sink tray (595x465x36mm)

1.0000

each

1760.00

1760.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia CP waste with brass coupling including CP chain plug

1.0000

set

280.00

280.00

40mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

70.00

70.00

12mm dia CP bib cock

1.0000

each

715.00

715.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 5700.00

Subtotal-A: All other remaining costs like socket, elbow, cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

171.00

Subtotal-A1: Subtotal-B: Subtotal-C:

5871.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5988.42

10% Profit ( Add 10% on Subtotal-B) :

6587.26

VAT

6% of Total

439.15

IT

4% of Total

292.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7319.18

Page: 1967 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.04.09.02

2 coloured

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Coloured porcelain sink (Model-502, size635x480x195mm)with sink tray (595x465x36mm)

1.0000

each

1848.00

1848.00

Coloured porcelain sink (Model-502, size635x480x195mm)with sink tray (595x465x36mm)

1.0000

each

1848.00

1848.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia CP waste with brass coupling including CP chain plug

1.0000

set

280.00

280.00

40mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

70.00

70.00

12mm dia CP bib cock

1.0000

each

715.00

715.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 5876.00

Subtotal-A: All other remaining costs like socket, elbow, cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

176.28

Subtotal-A1: Subtotal-B: Subtotal-C:

6052.28 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6173.33

10% Profit ( Add 10% on Subtotal-B) :

6790.66

VAT

6% of Total

IT

4% of Total

452.71 301.81 Total:

7.04.10

7545.18

Supplying, fitting and fixing single bowl Stainless Steel Sink with Sink Tray (Malaysia/ Singapore/Thailand made) fitted and fixed with heavy type C1/Steel brackets, 12mm dia C.P. bib cock, 40mm dia C.P. chain plug, 40mm dia CP waste, 40mm dia PVC waste water pipe with brass coupling (750mm length) including making holes in walls and floors and mending good the damages etc. all complete as per direction of the E-IC.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1968 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.10.01

Detailed Analysis Brief Description of Item 2 Stainless Steel Sink with Sink Tray (Size : 1050mmx450mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Stainless steel sink with sink tray (1050mmx450mm)

1.0000

each

2500.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia CP waste with brass coupling including CP chain plug

1.0000

set

280.00

280.00

40mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

70.00

70.00

12mm dia CP bib cock

1.0000

each

715.00

715.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4680.00

Subtotal-A: Cement, sand and other costs

( +3.00 % on Subtotal-A )

140.40

Subtotal-A1:

4820.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4916.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5408.49

VAT

6% of Total

360.57

IT

4% of Total

240.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2500.00

6009.43

Page: 1969 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.10.02

Detailed Analysis Brief Description of Item 2 Stainless Steel Sink with Sink Tray (Size : 750mmx450mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Stainless steel sink with sink tray (750x460mm)

1.0000

each

2300.00

CI Bracket

1.0000

pair

65.00

65.00

40mm dia CP waste with brass coupling including CP chain plug

1.0000

set

280.00

280.00

40mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

70.00

70.00

12mm dia CP bib cock

1.0000

each

715.00

715.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 4480.00

Subtotal-A: All other remaining costs like socket, elbow, cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

134.40

Subtotal-A1:

4614.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4706.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5177.36

VAT

6% of Total

345.16

IT

4% of Total

230.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2300.00

5752.62

Page: 1970 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.11

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Counter Basin(Above): Supplying, installation and commissioning of foreign made glazed vitreous above counter Lavatories consist of 32mm dia nickel chrome P-Trap (not exceeding 352mm in length), 12mm dia plastic connection pipe with brass coupling, 12mm dia nickel chrome angle stop cock, 12mm dia C.P. pillar cock, 30mm dia one push C.P. Basin waste, including fitting and fixing of commode by specified nuts & bolts, making holes wherever required with preparing the base using cement concrete with wire mesh or rods (if necessary), mending the damages etc., including cost of all necessary accessories, their carriages, wages of labour, plumber and incidental charges etc. all complete, as per direction & approval of the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1971 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.11.01

Detailed Analysis Brief Description of Item 2 Size: 500x450mm, rectangle shape, white (TOTO – LT710CS or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreign made rectangle shape counter basin(Above) with mounting bolt, Size: 500x450mm, White (TOTO – LT710CS or Equivalent)

1.0000

each

15000.00

15000.00

12mm dia metal wire sheathed connection pipe with brass/steel coupling, Model: TOTO - T025005 or Equivalent

1.0000

each

550.00

550.00

12mm dia piller cock, Model: TOTO - TS105B13 or Equivalent

1.0000

each

6900.00

6900.00

12mm dia Angle stop cock, Model: TOTO - TX277SV1 or Equivalent

1.0000

each

2100.00

2100.00

30mm dia P-Trap with SS pipe, Model: TOTO - THX1A3N/5N/6N or Equivalent

1.0000

each

3500.00

3500.00

30mm dia CP basin waste, Model: TOTO - T6JV2N or Equivalent

1.0000

each

4800.00

4800.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 33610.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

34282.20

10% Profit ( Add 10% on Subtotal-B) :

37710.42

VAT

6% of Total

IT

4% of Total

2514.03 1676.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

41900.47

Page: 1972 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.11.02

Detailed Analysis Brief Description of Item 2 Size: 550x446mm, oval shape, white (TOTO – LW861CJ or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreign made oval shape counter basin(Above), Size: 550x446mm, White (TOTO – LW861CJ or Equivalent)

1.0000

each

7500.00

7500.00

12mm dia metal wire sheathed connection pipe with brass/steel coupling, Model: TOTO - T025005 or Equivalent

1.0000

each

550.00

550.00

12mm dia piller cock, Model: TOTO - TS105B13 or Equivalent

1.0000

each

6900.00

6900.00

12mm dia Angle stop cock, Model: TOTO - TX277SV1 or Equivalent

1.0000

each

2100.00

2100.00

30mm dia P-Trap with SS pipe, Model: TOTO - THX1A3N/5N/6N or Equivalent

1.0000

each

3500.00

3500.00

30mm dia CP basin waste, Model: TOTO - T6JV2N or Equivalent

1.0000

each

4800.00

4800.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 26110.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26632.20

10% Profit ( Add 10% on Subtotal-B) :

29295.42

VAT

6% of Total

1953.03

IT

4% of Total

1302.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

32550.47

Page: 1973 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.12

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Pedestal Basin: Supplying, installation and commissioning of foreign made glazed vitreous pedestal Lavatories consist of Basin body, 32mm dia nickel chrome P-Trap (not exceeding 352mm in length), 12mm dia metal wire sheathed connection pipe with brass/steel coupling, 12mm dia nickel chrome angle stop cock, 12mm dia C.P. pillar cock, 30mm dia one push C.P. Basin waste, including fitting, fixing and installation of Basin by specified nut bolt with preparing the base using cement concrete with wire mesh or rods (if necessary), mending the damages etc., including cost of all necessary accessories, their carriages, wages of labour, plumber and incidental charges etc. all complete, as per direction & approval of the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1974 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.04.12.01

Detailed Analysis Brief Description of Item 2 Size: 530x465mm, White (TOTO – LW236CJ / LW239FJ or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreign made pedestal basin, Size: 530x465mm, White (TOTO – LW236CJ / LW239FJ or Equivalent)

1.0000

each

11000.00

11000.00

12mm dia metal wire sheathed connection pipe with brass/steel coupling, Model: TOTO - T025005 or Equivalent

1.0000

each

550.00

550.00

12mm dia piller cock, Model: TOTO - TS105B13 or Equivalent

1.0000

each

6900.00

6900.00

12mm dia Angle stop cock, Model: TOTO - TX277SV1 or Equivalent

1.0000

each

2100.00

2100.00

30mm dia P-Trap with SS pipe, Model: TOTO - THX1A3N/5N/6N or Equivalent

1.0000

each

3500.00

3500.00

30mm dia CP basin waste, Model: TOTO - T6JV2N or Equivalent

1.0000

each

4800.00

4800.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 29610.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30202.20

10% Profit ( Add 10% on Subtotal-B) :

33222.42

VAT

6% of Total

2214.83

IT

4% of Total

1476.55 Total:

7.05.01

36913.80

Supplying, fitting and fixing "BISF STANDARD" European type glazed vitreous porcelain standing urinal (Model-603, size-485x360x290mm, Bowl size-300x255x245mm) including fitting, fixing the same in position after making holes in walls and floors, providing 40mm dia PVC waste water pipe with brass coupling upto grading below, 12mm dia plastic connection pipe with brass coupling, 12mm dia brass stop cock including mending good the damages etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1975 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.05.01.01

2 White "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each White porcelain standing urinal (Model-603, size485x360x290mm, Bowl size-300x255x245mm)

1.0000

each

820.00

820.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 3135.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

94.05

Subtotal-A1:

3229.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3293.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3622.99

VAT

6% of Total

IT

4% of Total

241.53 161.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4025.55

Page: 1976 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.05.01.02

2 Coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coloured porcelain standing urinal (Model-603, size485x360x290mm, Bowl size-300x255x245mm)

1.0000

each

970.00

970.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 3285.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

98.55

Subtotal-A1:

3383.55

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3451.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3796.34

VAT

6% of Total

IT

4% of Total

253.09 168.73 Total:

7.05.02

4218.16

Supplying, fitting and fixing superior quality European type glazed vitreous Standing Urinals including fitting, fixing the same in position after making holes in walls and floors, providing 40mm dia PVC waste water pipe with brass coupling upto grading below, 12mm dia plastic connection pipe with brass coupling, 12mm dia brass stop cock including mending good the damages etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1977 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.05.02.01

Detailed Analysis Brief Description of Item 2 Size: 445x355x330mm, Model: RAK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Urinal Bowl, Size: 355x330x445mm (RAK or Equivalent)

1.0000

each

1650.00

1650.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 3965.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +3.00 % on Subtotal-A )

118.95

Subtotal-A1:

4083.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4165.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4582.19

VAT

6% of Total

IT

4% of Total

305.48 203.65 Total:

7.05.03

5091.32

Supplying, fitting and fixing "BISF STANDARD" glazed vitreous China squatting or porcelain flat urinal (Model-602A, size-510x380x85mm, Bowl size-210x260x46mm) with flushing inlet fitted in cement concrete with 12mm dia brass controlling valve, 44mm dia PVC flush pipe with brass coupling, 12mm dia plastic connection pipe including mending good the damages etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1978 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.05.03.01

2 White "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each White porcelain flat urinal (Model-602A, size-510x380x85mm, Bowl size-210x260x46mm)

1.0000

each

756.00

756.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 3071.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +4.00 % on Subtotal-A )

122.84

Subtotal-A1:

3193.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3257.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3583.49

VAT

6% of Total

IT

4% of Total

238.90 159.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3981.65

Page: 1979 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.05.03.02

2 Coloured "BISF STANDARD"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coloured porcelain flat Urinal (Model-602A, size510x380x85mm, Bowl size-210x260x46mm)

1.0000

each

795.00

795.00

12mm dia CP stop cock with nipple

1.0000

each

1010.00

1010.00

44mm dia PVC waste water pipe with 750mm long brass coupling

1.0000

each

200.00

200.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Ordinary Labour

1.0000

day

370.00

370.00 3110.00

Subtotal-A: All other remaining costs like cement, sand, block, screws, nails, putty, leather, etc.

( +4.00 % on Subtotal-A )

124.40

Subtotal-A1:

3234.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3299.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3629.00

VAT

6% of Total

IT

4% of Total

241.93 161.29 Total:

7.05.04

4032.22

Standing Urinal: Supplying, installation and commissioning of foreign made glazed vitreous Standing/wall hung Urinals consist of Urinal body, 40mm dia PVC waste water pipe with brass coupling up to grading below, inlet spud, wall flange w/seal gasket, hangers & screw, flash valve of 0.07MPa-0.75Mpa, including fitting and fixing of urinals by specified nuts & bolts, making holes wherever required with preparing the wall using cement concrete with wire mesh or rods (if necessary), mending the damages etc., including cost of all necessary accessories, their carriages, wages of labour, plumber and incidental charges etc. all complete, as per direction & approval of the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1980 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.05.04.01

Detailed Analysis Brief Description of Item 2 Size: 330x310x605mm, White & Rectangle Shape (TOTO – U57 / UT57 or Equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreign made Standing Urinal including Flash valve, Size: 330x310x605mm, White & Rectangle Shape (TOTO – U57 / UT57 or Equivalent)

1.0000

each

20500.00

20500.00

12mm dia plastic pipe with nipple

1.0000

each

55.00

55.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00

Ordinary Labour

0.5000

day

370.00

185.00 21315.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21741.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

23915.43

VAT

6% of Total

IT

4% of Total

1594.36 1062.91 Total:

7.06.01

26572.70

Supplying, fitting and fixing best quality and heavy type bib cock, and Two in one Bib cock of brass or cromium plated or special quality plastic materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1981 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.06.01.01

2 12mm dia Brass Bib Cock

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 12mm dia Brass bib cock

1.0000

each

360.00

360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 388.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

395.96

10% Profit ( Add 10% on Subtotal-B) :

435.56

VAT

6% of Total

29.04

IT

4% of Total

19.36 Total:

7.06.01.02

12mm dia C.P. Bib Cock

each 12mm dia CP bib cock

1.0000

each

715.00

715.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 743.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

758.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

833.87

VAT

6% of Total

55.59

IT

4% of Total

37.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

483.96

926.52

Page: 1982 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.01.03

Detailed Analysis Brief Description of Item 2 12mm dia Plastic Bib Cock with heavy iron thread

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 12mm dia plastic bib cock

1.0000

each

90.00

90.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 118.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

120.56

10% Profit ( Add 10% on Subtotal-B) :

132.62

VAT

6% of Total

8.84

IT

4% of Total

5.89 Total:

7.06.01.04

12mm dia C.P. concealed Bib Cock

each 12mm dia CP concealed bib cock

1.0000

each

970.00

970.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 998.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1018.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1119.98

VAT

6% of Total

74.67

IT

4% of Total

49.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

147.36

1244.42

Page: 1983 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.01.05

Detailed Analysis Brief Description of Item 2 20mm dia Plastic Bib Cock with heavy iron thread

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 20mm dia plastic bib cock with heavy iron thread

1.0000

each

140.00

140.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 168.20

Subtotal-A: Subtotal-B: Subtotal-C:

7.06.01.06

12mm dia C.P Two in one Bib Cock

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

171.56

10% Profit ( Add 10% on Subtotal-B) :

188.72

VAT

6% of Total

12.58

IT

4% of Total

8.39 Total:

209.69

each 12mm dia C.P Two in one Bib Cock

1.0000

each

1315.00

1315.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 1355.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1382.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1521.21

VAT

6% of Total

IT

4% of Total

101.41 67.61 Total:

7.06.02

1690.23

Supplying, fitting and fixing best quality Concealed sink cock of fully brass or cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1984 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.02.01

Detailed Analysis Brief Description of Item 2 12 mm CP Concealed fixed sink cock

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 12 mm CP Concealed fixed sink cock

1.0000

each

1210.00

1210.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 1250.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1275.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1403.40

VAT

6% of Total

93.56

IT

4% of Total

62.37 Total:

7.06.02.02

12 mm CP Concealed moving sink cock

each 12 mm CP Concealed moving sink cock

1.0000

each

1550.00

1550.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 1590.80

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1622.62

10% Profit ( Add 10% on Subtotal-B) :

1784.88

VAT

6% of Total

IT

4% of Total

118.99 79.33 Total:

7.06.03

1559.33

1983.20

Supplying, fitting and fixing best quality Stop Cock of fully brass or cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1985 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.03.01

Detailed Analysis Brief Description of Item 2 20mm dia Brass Stop Cock (thread type)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 20mm dia brass stop cock

1.0000

each

650.00

650.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 678.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

691.76

10% Profit ( Add 10% on Subtotal-B) :

760.94

VAT

6% of Total

50.73

IT

4% of Total

33.82 Total:

7.06.03.02

12mm dia Brass Stop Cock (thread type)

each 12mm dia brass stop cock

1.0000

each

450.00

450.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 478.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

487.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

536.54

VAT

6% of Total

35.77

IT

4% of Total

23.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

845.49

596.16

Page: 1986 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.03.03

Detailed Analysis Brief Description of Item 2 20mm dia C.P. Stop Cock (thread type)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 20mm dia CP stop cock

1.0000

each

930.00

930.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 958.20

Subtotal-A: Subtotal-B: Subtotal-C:

977.36

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1075.10

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

71.67

IT

4% of Total

47.78 Total:

7.06.03.04

12mm dia C.P. Stop Cock (thread type)

each 12mm dia C.P stop cock

1.0000

each

650.00

650.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 678.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

691.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

760.94

VAT

6% of Total

50.73

IT

4% of Total

33.82 Total:

7.06.04

1194.56

845.49

Supplying, fitting and fixing special/fancy quality C.P. Concealed Stop Cock etc. all complete as per direction of the E-I-C..

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1987 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.04.01

Detailed Analysis Brief Description of Item 2 12mm dia Stop Cock (Special Quality) (thread type)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 12mm dia special quality CP concealed stop cock

1.0000

each

895.00

895.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 923.20

Subtotal-A: Subtotal-B: Subtotal-C:

941.66

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1035.83

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

69.06

IT

4% of Total

46.04 Total:

7.06.04.02

12mm dia Stop Cock (Fancy best quality) (thread type)

each 12mm dia fancy best quality CP concealed stop cock

1.0000

each

945.00

945.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 973.20

Subtotal-A: Subtotal-B: Subtotal-C:

992.66

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1091.93

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

72.80

IT

4% of Total

48.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1150.92

1213.26

Page: 1988 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.04.03

Detailed Analysis Brief Description of Item 2 12mm dia C.P. Concealed Stop Cock (heavy duty thread type)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 12mm dia CP concealed stop cock

1.0000

each

865.00

865.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 905.80

Subtotal-A: Subtotal-B: Subtotal-C:

923.92

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1016.31

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

67.75

IT

4% of Total

45.17 Total:

7.06.05

Supplying, fitting and fixing Special/Fancy quality C.P. concealed/ Surface Angle stop cock of fully brass or cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

7.06.05.01

12 mm CP surface mounted angle stop cock (general)

each 12 mm CP medium quality surface & heavy type fancy angle stop cock

1.0000

each

590.00

590.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 630.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

643.42

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

707.76

VAT

6% of Total

IT

4% of Total

47.18 31.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1129.23

786.40

Page: 1989 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.05.02

Detailed Analysis Brief Description of Item 2 12 mm CP medium quality surface & heavy type fancy angle stop cock

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 12 mm CP medium quality surface & heavy type fancy angle stop cock

1.0000

each

590.00

590.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 630.80

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

643.42

10% Profit ( Add 10% on Subtotal-B) :

707.76

VAT

6% of Total

47.18

IT

4% of Total

31.46 Total:

7.06.05.03

12 mm surface special heavy type angle stop cock

each 12 mm surface special heavy type angle stop cock

1.0000

each

695.00

695.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 735.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

750.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

825.57

VAT

6% of Total

IT

4% of Total

55.04 36.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

786.40

917.30

Page: 1990 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.05.04

Detailed Analysis Brief Description of Item 2 12 mm CP concealed mount angle stop cock

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 12 mm CP concealed mount angle stop cock

1.0000

each

880.00

880.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 920.80

Subtotal-A: Subtotal-B: Subtotal-C:

939.22

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1033.14

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

68.88

IT

4% of Total

45.92 Total:

7.06.06

7.06.06.01

1147.93

Supplying, fitting and fixing 12mm dia C.P. Pillar Cock of fully brass or cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C. 12mm dia C.P. long Pillar Cock. Best quality

each 12mm dia CP pillar cock (best quality)

1.0000

each

1200.00

1200.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 1228.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1252.76

10% Profit ( Add 10% on Subtotal-B) :

1378.04

VAT

6% of Total

91.87

IT

4% of Total

61.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1531.16

Page: 1991 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.06.02

Detailed Analysis Brief Description of Item 2 12mm dia C.P. long Pillar Cock. Special quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 12mm dia CP pillar cock (special quality)

1.0000

each

1150.00

1150.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 1178.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1201.76

10% Profit ( Add 10% on Subtotal-B) :

1321.94

VAT

6% of Total

88.13

IT

4% of Total

58.75 Total:

7.06.06.03

12mm dia Moving Pillar Cock. Special quality

each 12mm dia Moving Pillar Cock

1.0000

each

1550.00

1550.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 1590.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1622.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1784.88

VAT

6% of Total

IT

4% of Total

118.99 79.33 Total:

7.06.07

1468.82

1983.20

Supplying, fitting and fixing 125mm dia C.P. Shower Rose of cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 1992 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.06.07.01

2 Best quality fixed type

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 125mm dia CP shower rose (best quality)

1.0000

each

1150.00

1150.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 1178.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1201.76

10% Profit ( Add 10% on Subtotal-B) :

1321.94

VAT

6% of Total

88.13

IT

4% of Total

58.75 Total:

7.06.07.02

Special Quality movable

each 125mm dia CP shower rose (special quality)

1.0000

each

875.00

875.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 903.20

Subtotal-A: Subtotal-B: Subtotal-C:

921.26

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1013.39

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

67.56

IT

4% of Total

45.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1468.82

1125.99

Page: 1993 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.06.07.03

2 Special fency type moveable

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 125mm dia CP moveable shower rose (special quality)

1.0000

each

1100.00

1100.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 1128.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1150.76

10% Profit ( Add 10% on Subtotal-B) :

1265.84

VAT

6% of Total

84.39

IT

4% of Total

56.26 Total:

7.06.08

Supplying, fitting and fixing best quality faucets of fully brass or cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

each

faucets

1.0000

each

1200.00

1200.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 1240.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1265.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1392.18

VAT

6% of Total

IT

4% of Total

92.81 61.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1406.49

1546.86

Page: 1994 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.06.09

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing CP Basin Mixture with all necessary hardware and consumables of fully brass or cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

CP Basin Mixture

1.0000

each

2890.00

2890.00

Plumber/ Electric Mistry/ Painter

0.0800

day

680.00

54.40 2944.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3003.29

10% Profit ( Add 10% on Subtotal-B) :

3303.62

VAT

6% of Total

IT

4% of Total

220.24 146.83 Total:

7.06.10

Supplying, fitting and fixing CP Single Handle Basin Mixture with all necessary hardware and consumables of fully brass or cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

each

CP Single Handle Basin Mixture

1.0000

each

2400.00

2400.00

Plumber/ Electric Mistry/ Painter

0.0800

day

680.00

54.40 2454.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2503.49

10% Profit ( Add 10% on Subtotal-B) :

2753.84

VAT

6% of Total

IT

4% of Total

183.59 122.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3670.69

3059.82

Page: 1995 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.06.11

2 Supplying, fitting and fixing CP Shower Mixture including Shower Head only with all necessary hardware and consumables of fully brass or cromium plated materials made with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

CP Shower Mixture

1.0000

each

5000.00

5000.00

Plumber/ Electric Mistry/ Painter

0.0800

day

680.00

54.40 5054.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5155.49

10% Profit ( Add 10% on Subtotal-B) :

5671.04

VAT

6% of Total

IT

4% of Total

378.07 252.05 Total:

7.06.12

Supplying, fitting and fixing hand or push shower for ablution including holder of fully hard foreign plastic (Grohe) or stainless steel body with brass or stainless steel fittings push and SS chain or superior quality tube/pipe of standard length with leak proof and fixing in position with selected tape etc. all complete as per direction of the E-I-C.

7.06.12.01

Moving type hand shower

each Moving type hand shower

1.0000

each

1891.33

1891.33

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 1932.13

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1970.77

10% Profit ( Add 10% on Subtotal-B) :

2167.85

VAT

6% of Total

IT

4% of Total

144.52 96.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6301.15

2408.72

Page: 1996 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.06.12.02

2 Moving type push shower

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Moving type push shower

1.0000

each

514.67

514.67

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80 555.47

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

566.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

623.24

VAT

6% of Total

41.55

IT

4% of Total

27.70 Total:

7.07.01

Supplying, fitting and fixing Standard Size porcelain soap tray fitted with rowel plug and screw including making holes in walls by drill machine and mending good the damages etc. all complete as per direction of the E-I-C.

7.07.01.01

White (150mmx110mmx40mm size)

each White Soap tray (150x110x40mm)

1.0000

each

130.00

130.00

Ordinary Labour

0.2000

day

370.00

74.00 204.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

208.08

10% Profit ( Add 10% on Subtotal-B) :

228.89

VAT

6% of Total

IT

4% of Total

15.26 10.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

692.49

254.32

Page: 1997 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.07.01.02

Detailed Analysis Brief Description of Item 2 Coloured (150mmx110mmx40mm size)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Coloured soap tray (150x110x40mm)

1.0000

each

140.00

140.00

Ordinary Labour

0.2000

day

370.00

74.00 214.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

218.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

240.11

VAT

6% of Total

16.01

IT

4% of Total

10.67 Total:

7.07.01.03

Superior Quality Porcelain soap tray, Size: 225x125mm, Model: RAK or Equivalent

each Soap Holder, Size: 130x125mm (RAK or Equivalent)

1.0000

each

300.00

300.00

Ordinary Labour

0.2000

day

370.00

74.00 374.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

381.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

419.63

VAT

6% of Total

27.98

IT

4% of Total

18.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

266.79

466.25

Page: 1998 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.07.01.04

Detailed Analysis Brief Description of Item 2 Stainless Steel soap tray of standard size

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Stainless Steel soap tray standard size

1.0000

each

325.00

325.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00 461.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

470.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

517.24

VAT

6% of Total

34.48

IT

4% of Total

22.99 Total:

7.07.02

Supplying, fitting and fixing toilet paper holder fitted with rowel plug and screw including making holes in walls by drill machine and mending good the damages etc. all complete as per direction of the E-I-C.

7.07.02.01

White porcelain "BISF STANDARD" (Size: 150mmx150mmx126mm)

each White porcelain toilet paper holder (150x150x126mm)

1.0000

each

450.00

450.00

Ordinary Labour

0.3400

day

370.00

125.80 575.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

587.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

646.05

VAT

6% of Total

IT

4% of Total

43.07 28.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

574.71

717.83

Page: 1999 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.07.02.02

Detailed Analysis Brief Description of Item 2 Special coloured porcelain (Size: 150mmx150mmx126mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Special coloured porcelain toilet paper holder (150x150x126mm)

1.0000

each

290.00

290.00

Ordinary Labour

0.3400

day

370.00

125.80 415.80

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

424.12

10% Profit ( Add 10% on Subtotal-B) :

466.53

VAT

6% of Total

31.10

IT

4% of Total

20.73 Total:

7.07.02.03

Stainless Steel type (Size: 150mmx150mmx126mm)

each Stainless steel toilet paper holder (150x150x126mm)

1.0000

each

400.00

400.00

Ordinary Labour

0.3400

day

370.00

125.80 525.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

536.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

589.95

VAT

6% of Total

IT

4% of Total

39.33 26.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

518.36

655.50

Page: 2000 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.07.02.04

Detailed Analysis Brief Description of Item 2 Plastic type (Size: 150mmx150mmx126mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Plastic toilet paper holder (150x150x126mm)

1.0000

each

160.00

160.00

Ordinary Labour

0.3400

day

370.00

125.80 285.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

291.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

320.67

VAT

6% of Total

21.38

IT

4% of Total

14.25 Total:

7.07.02.05

Porcelain toilet paper holder (Superior Quality), Size: 185x115mm, Model: RAK or Equivalent

each Toilet Paper Holder, Size: 185x115mm (RAK or Equivalent)

1.0000

each

450.00

450.00

Ordinary Labour

0.3400

day

370.00

125.80 575.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

587.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

646.05

VAT

6% of Total

43.07

IT

4% of Total

28.71 Total:

7.07.03

356.30

717.83

Supplying, fitting and fixing Glass plate Shelf (600mmx125mm) of 5mm thick glass with fancy C.P. brackets, screws and frames fitted with rowel plug and screw including making holes in walls by drill machine and mending good the damages etc. all complete as per direction of the E-IC.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2001 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.07.03.01

2 Super quality (white)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 5mm thick glass plate shelf (600x125mm) with CP Brackets (Super quality)

1.0000

each

470.00

470.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 532.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

542.84

10% Profit ( Add 10% on Subtotal-B) :

597.13

VAT

6% of Total

IT

4% of Total

39.81 26.54 Total:

7.07.03.02

Medium quality (white)

each 5mm thick glass plate shelf (600x125mm) with CP brackets (Medium quality)

1.0000

each

380.00

380.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 442.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

451.04

10% Profit ( Add 10% on Subtotal-B) :

496.15

VAT

6% of Total

IT

4% of Total

33.08 22.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

663.48

551.28

Page: 2002 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.07.03.03

2 Super quality (coloured)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 5mm thick glass plate shelf (600x125mm) with CP Brackets (Super quality coloured)

1.0000

each

450.00

450.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 512.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

522.44

10% Profit ( Add 10% on Subtotal-B) :

574.69

VAT

6% of Total

IT

4% of Total

38.31 25.54 Total:

7.07.03.04

Medium quality (coloured)

each 5mm thick glass plate shelf (600x125mm) with CP Brackets (medium quality coloured)

1.0000

each

380.00

380.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 442.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

451.04

10% Profit ( Add 10% on Subtotal-B) :

496.15

VAT

6% of Total

IT

4% of Total

33.08 22.05 Total:

7.07.04

638.54

551.28

Supplying, fitting and fixing Towel rail with holder fitted with rowel plug and screw including making holes in walls by drill machine and mending good the damages etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2003 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.07.04.01

Detailed Analysis Brief Description of Item 2 C.P. Towel rail (Size : 600mmx20mm) with C.P. holder (Super quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each CP Towel rail (600x20mm) with CP holder (super quality)

1.0000

each

625.00

625.00

Skilled Labour

0.6000

day

450.00

270.00 895.00

Subtotal-A: Subtotal-B: Subtotal-C:

912.90

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1004.19

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

66.95

IT

4% of Total

44.63 Total:

7.07.04.02

C.P. Towel rail (Size : 600mmx20mm) with C.P. holder (Medium quality)

each CP Towel rail (600x20mm) with CP holder (Medium quality)

1.0000

each

380.00

380.00

Skilled Labour

0.6000

day

450.00

270.00 650.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

663.00

10% Profit ( Add 10% on Subtotal-B) :

729.30

VAT

6% of Total

IT

4% of Total

48.62 32.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1115.77

810.33

Page: 2004 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.07.04.03

Detailed Analysis Brief Description of Item 2 Superior Quality Towel rail with holder (Size: 95x65mm), Model: RAK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Towel Rail Holder and Rail, Size: 95x65mm (RAK or Equivalent)

1.0000

each

450.00

450.00

Skilled Labour

0.6000

day

450.00

270.00 720.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

734.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

807.84

VAT

6% of Total

53.86

IT

4% of Total

35.90 Total:

7.07.05

Supplying, fitting and fixing super quality unframed 5mm thick Mirror with hard boards at the back with all necessary fittings fitted with rowel plug and screw including making holes in walls by drill machine and mending good the damages etc. all complete as per direction of the E-IC.

7.07.05.01

Japan made Mirror (Size:450mmx350mm)

each Mirror (450x350mm) with hard board back (Japan)

1.0000

each

400.00

400.00

Ordinary Labour

0.4000

day

370.00

148.00 548.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

558.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

614.86

VAT

6% of Total

IT

4% of Total

40.99 27.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

897.60

683.17

Page: 2005 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.07.05.02

Detailed Analysis Brief Description of Item 2 Belgium made Mirror (Size:450mmx300mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Mirror (450x380mm) with hard board back (Belgium)

1.0000

each

380.00

380.00

Ordinary Labour

0.4000

day

370.00

148.00 528.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

538.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

592.42

VAT

6% of Total

39.49

IT

4% of Total

26.33 Total:

7.07.05.03

Belgium made Mirror (Size:450mmx600mm)

each Belgium made Mirror (Size:450mmx600mm)

1.0000

each

600.00

600.00

Ordinary Labour

0.4000

day

370.00

148.00 748.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

762.96

10% Profit ( Add 10% on Subtotal-B) :

839.26

VAT

6% of Total

IT

4% of Total

55.95 37.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

658.24

932.51

Page: 2006 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.07.05.04

2 Belgium made Mirror

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm Belgium made Mirror

1.0000

sqm

2150.00

2150.00

Ordinary Labour

0.5000

day

370.00

185.00 2335.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2381.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2619.87

VAT

6% of Total

174.66

IT

4% of Total

116.44 Total:

7.08.01

Supplying 25mm to 200mm dia (inside) best quality uPVC pipes having specific gravity 1.35-1.45, and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacturer standards or ASTM, BS/ISO/IS standards fitted and fixed in position with sockets head and shoes, bends, clamps and nails etc. all complete in all floors as per direction of the E-I-C.

7.08.01.01

Minimum inner dia 25mm and minimum wall thickness 2.50mm

m uPVC Pipe 25mm dia of 2.2mm to 2.7mm wall thick

1.0000

m

65.32

65.32 65.32

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

13.06 78.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

79.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

87.95

VAT

6% of Total

IT

4% of Total

5.86 3.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2910.97

97.72

Page: 2007 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.01.02

Detailed Analysis Brief Description of Item 2 Minimum inner dia 50mm and minimum wall thickness 2.50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m uuPVC Pipe 50mm dia of 2.5mm to 3.0mm wall thick

1.0000

m

93.00

93.00

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +22.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Minimum inner dia 75mm and minimum wall thickness 2.9mm

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

115.73

10% Profit ( Add 10% on Subtotal-B) :

127.30

VAT

6% of Total

IT

4% of Total

8.49 5.66 141.45

m uPVC Pipe 75mm dia of 2.9mm to 3.4mm wall thick

1.0000

m

165.00

All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

165.00 165.00

Subtotal-A:

41.25 206.25

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

210.38

10% Profit ( Add 10% on Subtotal-B) :

231.41

VAT

6% of Total

15.43

IT

4% of Total

10.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

20.46 113.46

Total: 7.08.01.03

93.00

257.13

Page: 2008 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.01.04

Detailed Analysis Brief Description of Item 2 Minimum inner dia 100mm and minimum wall thickness 3.4mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

240.00

240.00

m uPVC Pipe 100mm dia of 3.4mm to 4.0mm wall thick

1.0000

240.00

Subtotal-A: Labour & other costs like head, shoes, bend, clamp

( +27.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

304.80 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

310.90

10% Profit ( Add 10% on Subtotal-B) :

341.99

VAT

6% of Total

IT

4% of Total

22.80 15.20 Total:

7.08.01.05

Minimum inner dia 150mm and minimum wall thickness 4.5mm

379.98

m uPVC Pipe 150mm dia of 4.5mm to 5.2mm wall thick

1.0000

m

500.00

500.00 500.00

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +30.00 % on Subtotal-A )

Subtotal-A1:

150.00 650.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

663.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

729.30

VAT

6% of Total

IT

4% of Total

48.62 32.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

64.80

810.33

Page: 2009 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.01.06

Detailed Analysis Brief Description of Item 2 Minimum inner dia 200mm and minimum wall thickness 5.3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

999.17

999.17

m uPVC Pipe 200mm dia of 5.3mm to 6.1mm wall thick

1.0000

999.17

Subtotal-A: Labour & other costs like head, shoes, bend, clamp

( +35.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1348.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1375.86

10% Profit ( Add 10% on Subtotal-B) :

1513.44

VAT

6% of Total

IT

4% of Total

100.90 67.26 Total:

7.08.02

349.71

1681.60

Supplying different inside dia best quality uPVC C-grade pipe for water supply having specific gravity 1.35 - 1.45, and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacturer standards or ASTM, BS/ISO/IS standards fitted and fixed in position with sockets, bends, with all accessories such as Round grating/domed roof grating, bends, sockets (length: 6 meter each) etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2010 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.02.01

Detailed Analysis Brief Description of Item 2 12 mm dia wall thickness 2.8 mm - 3.3 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m uPVC Pipe 12mm dia

1.0000

m

28.52

28.52

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

19 mm dia wall thickness 2.9 mm - 3.4 mm

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

36.36

10% Profit ( Add 10% on Subtotal-B) :

40.00

VAT

6% of Total

IT

4% of Total

2.67 1.78 44.44

m uPVC Pipe 19mm dia

1.0000

m

40.67

All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

40.67 40.67

Subtotal-A:

10.17 50.84

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

51.85

10% Profit ( Add 10% on Subtotal-B) :

57.04

VAT

6% of Total

3.80

IT

4% of Total

2.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7.13 35.65

Total: 7.08.02.02

28.52

63.38

Page: 2011 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.02.03

Detailed Analysis Brief Description of Item 2 25 mm dia wall thickness 3.4 mm - 4.0 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m uPVC Pipe 25mm dia of 2.2mm to 2.7mm wall thick

1.0000

m

65.32

65.32

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +27.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

32 mm dia wall thickness 3.6 mm - 4.2 mm

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84.62

10% Profit ( Add 10% on Subtotal-B) :

93.08

VAT

6% of Total

IT

4% of Total

6.21 4.14 103.42

m uPVC Pipe 32mm dia of 2.2mm to 2.7mm wall thick

1.0000

m

70.52

All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +27.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

70.52 70.52

Subtotal-A:

19.04 89.56 91.35

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100.49

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

6.70

IT

4% of Total

4.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17.64 82.96

Total: 7.08.02.04

65.32

111.65

Page: 2012 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.02.05

Detailed Analysis Brief Description of Item 2 40 mm dia wall thickness 3.7 mm - 4.3 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m uPVC Pipe 40mm dia of 2.5mm to 3.0mm wall thick

1.0000

m

78.75

78.75

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +30.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

50 mm dia wall thickness 3.9 mm - 4.5 mm

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

104.42

10% Profit ( Add 10% on Subtotal-B) :

114.86

VAT

6% of Total

IT

4% of Total

7.66 5.11 127.63

m uuPVC Pipe 50mm dia of 2.5mm to 3.0mm wall thick

1.0000

m

93.00

All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +33.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

93.00 93.00

Subtotal-A:

30.69 123.69

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

126.16

10% Profit ( Add 10% on Subtotal-B) :

138.78

VAT

6% of Total

9.25

IT

4% of Total

6.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23.63 102.38

Total: 7.08.02.06

78.75

154.20

Page: 2013 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.02.07

Detailed Analysis Brief Description of Item 2 60 mm dia wall thickness 4.8 mm - 5.5 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m uPVC Pipe 60mm dia of 2.65mm to 3.0mm wall thick

1.0000

m

93.00

93.00

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +33.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

75 mm dia wall thickness 4.8 mm - 5.5 mm

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

126.16

10% Profit ( Add 10% on Subtotal-B) :

138.78

VAT

6% of Total

IT

4% of Total

9.25 6.17 154.20

m uPVC Pipe 75mm dia of 2.9mm to 3.4mm wall thick

1.0000

m

165.00

All remaining cost like Labour,Tee, elbow, bend, socket, plug, solvent cement, clamp etc.

( +35.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

165.00 165.00

Subtotal-A:

57.75 222.75

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

227.21

10% Profit ( Add 10% on Subtotal-B) :

249.93

VAT

6% of Total

16.66

IT

4% of Total

11.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

30.69 123.69

Total: 7.08.02.08

93.00

277.70

Page: 2014 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.08.03

Supplying different inside dia best quality ABS or PPR or prior approval equivalent best quality pipe for water supply having specific gravity 1.35 - 1.45, and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacturer standards or ASTM, BS/ISO/IS standards fitted and fixed in position with sockets, bends, with all accessories such as Round grating/domed roof grating, bends, sockets (length: 6 meter each) etc. all complete as per direction of the E-I-C.

7.08.03.01

12 mm dia wall thickness 2.8 mm - 3.3 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m ABS/PPR or equivalent best quality Pipe 12mm dia

1.0000

m

65.00

65.00

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, Adhesive solution,, clamp etc.

( +60.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

39.00 104.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

106.08

10% Profit ( Add 10% on Subtotal-B) :

116.69

VAT

6% of Total

IT

4% of Total

7.78 5.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

65.00

129.65

Page: 2015 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.03.02

Detailed Analysis Brief Description of Item 2 19 mm dia wall thickness 3.5 mm - 4.1 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m ABS/PPR or equivalent best quality Pipe 19mm dia

1.0000

m

97.00

97.00

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, Adhesive solution,, clamp etc.

( +63.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

25 mm dia wall thickness 4.6 mm - 5.2 mm

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

161.27

10% Profit ( Add 10% on Subtotal-B) :

177.40

VAT

6% of Total

IT

4% of Total

11.83 7.88 197.11

m ABS/PPR or equivalent best quality Pipe 25mm dia

1.0000

m

153.00

All remaining cost like Labour,Tee, elbow, bend, socket, plug, Adhesive solution,, clamp etc.

( +65.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

153.00 153.00

Subtotal-A:

99.45 252.45

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

257.50

10% Profit ( Add 10% on Subtotal-B) :

283.25

VAT

6% of Total

18.88

IT

4% of Total

12.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

61.11 158.11

Total: 7.08.03.03

97.00

314.72

Page: 2016 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.03.04

Detailed Analysis Brief Description of Item 2 32 mm dia wall thickness 5.5 mm - 5.8 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

188.00

188.00

m ABS/PPR or equivalent best quality Pipe 32mm dia

1.0000

188.00

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, Adhesive solution,, clamp etc.

( +68.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

315.84 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

322.16

10% Profit ( Add 10% on Subtotal-B) :

354.37

VAT

6% of Total

IT

4% of Total

23.62 15.75 Total:

7.08.03.05

40 mm dia wall thickness 6.9 mm - 7.2 mm

393.75

m ABS/PPR or equivalent best quality Pipe 40mm dia

1.0000

m

288.00

All remaining cost like Labour,Tee, elbow, bend, socket, plug, Adhesive solution,, clamp etc.

( +70.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

288.00 288.00

Subtotal-A:

201.60 489.60

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

499.39

10% Profit ( Add 10% on Subtotal-B) :

549.33

VAT

6% of Total

36.62

IT

4% of Total

24.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

127.84

610.37

Page: 2017 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.03.06

Detailed Analysis Brief Description of Item 2 50 mm dia wall thickness 8.7 mm - 9.0 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

442.00

442.00

m ABS/PPR or equivalent best quality Pipe 50mm dia

1.0000

442.00

Subtotal-A: All remaining cost like Labour,Tee, elbow, bend, socket, plug, Adhesive solution,, clamp etc.

( +75.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

773.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

788.97

10% Profit ( Add 10% on Subtotal-B) :

867.87

VAT

6% of Total

IT

4% of Total

57.86 38.57 Total:

7.08.04

331.50

964.30

Supplying different inside dia best quality uPVC special fittings having specific gravity 1.35 -1.45, wall thickness 2.7 mm - 3.4 mm, and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacturer standards or ASTM, BS/ISO/IS standards, fitted and fixed in position with sockets, bends, with all accessories such as Round grating/domed roof grating bands, sockets etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2018 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.08.04.01

2 50 mm dia uPVC Y or T - Y Cleanout

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

122.00

122.00

each uPVC Y or T 50mm dia

1.0000

each

122.00

Subtotal-A: All remaining cost like Labour, solvent cement etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

134.20 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

136.88

10% Profit ( Add 10% on Subtotal-B) :

150.57

VAT

6% of Total

IT

4% of Total

10.04 6.69 Total:

7.08.04.02

100 mm dia uPVC ‘P’ or ‘S’ trap

167.30

each uPVC P or S trap 100mm dia

1.0000

each

300.00

All remaining cost like Labour, solvent cement etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

300.00 300.00

Subtotal-A:

30.00 330.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

336.60

10% Profit ( Add 10% on Subtotal-B) :

370.26

VAT

6% of Total

IT

4% of Total

24.68 16.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12.20

411.40

Page: 2019 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.04.03

Detailed Analysis Brief Description of Item 2 100 mm dia uPVC Y or T - Y Cleanout

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

230.00

230.00

each uPVC Y or T 100mm dia

1.0000

each

230.00

Subtotal-A: All remaining cost like Labour, solvent cement etc.

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

253.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

258.06

10% Profit ( Add 10% on Subtotal-B) :

283.87

VAT

6% of Total

IT

4% of Total

18.92 12.62 Total:

7.08.05

23.00

315.41

Supplying, fitting, fixing and laying 150mm/200mm dia PVC "B" class pipe water grade (LIRA / AZIZ / NATIONAL POLYMER BRAND or equivalent) best quality sewerage pipe including necessary fittings and joints with high class solution and at the base and sides filling with best quality local sand all around the pipe (not less than 25mm) upto the required depth etc. complete as per type, plan and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2020 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

7.08.05.01

150mm dia PVC "B" class Pipeand minimum wall thickness 4.5mm

m

Quantity 5

Unit

Rate

Amount

6

7

8

4.5 to 5.2mm thick 150mm dia PVC 'B' Class pipe

1.0000

m

500.00

500.00

Sand (FM - 0.5)

0.2100

m3

420.00

88.20

Ordinary Labour

0.8000

day

370.00

296.00 884.20

Subtotal-A: All other remaining costs like gasket, cement mortar, etc.

( +8.00 % on Subtotal-A )

70.74

Subtotal-A1:

954.94 974.03

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-B:

1071.44

10% Profit ( Add 10% on Subtotal-B) :

Subtotal-C: VAT

6% of Total

71.43

IT

4% of Total

47.62 Total:

7.08.05.02

200mm dia PVC "B" class Pipe and minimum wall thickness 5.30 mm

m 5.3 to 6.1mm thick 200mm dia PVC 'B' Class pipe

1.0000

m

770.00

770.00

Sand (FM - 0.5)

0.2100

m3

420.00

88.20

Ordinary Labour

0.8000

day

370.00

296.00 1154.20

Subtotal-A: All other remaining costs like gasket, cement mortar, etc.

( +8.00 % on Subtotal-A )

92.34

Subtotal-A1: Subtotal-B: Subtotal-C:

1246.54 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1271.47

10% Profit ( Add 10% on Subtotal-B) :

1398.61

VAT

6% of Total

IT

4% of Total

93.24 62.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1190.49

1554.01

Page: 2021 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.05.03

Detailed Analysis Brief Description of Item 2 Supplying 50 mm inside dia best quality uPVC B-grade rain water down pipe having specific gravity 1.35 - 1.45, wall thickness 2.5 - 3.0 mm, and other physical, chemical, thermal, fire resistivity properties etc. as per BSTI approved manufacturer standards or ASTM, BS/ISO/IS standards fitted and fixed in position with sockets, bends, of uPVC Pipe with all accessories such as Round grating /domed roof grating bands, sockets etc. approved and accepted by the Engineer (length: 6000 mm each).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

50mm dia pvc pipe

1.0000

m

103.00

103.00

Plumber/ Electric Mistry/ Painter

0.8000

day

680.00

544.00 647.00

Subtotal-A: All other remaining costs like gasket, cement mortar, etc.

( +8.00 % on Subtotal-A )

51.76

Subtotal-A1: Subtotal-B: Subtotal-C:

698.76 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

712.74

10% Profit ( Add 10% on Subtotal-B) :

784.01

VAT

6% of Total

IT

4% of Total

52.27 34.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

871.12

Page: 2022 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.05.04

Detailed Analysis Brief Description of Item 2 Supplying 100mm dia (inside) best quality PVC rain water down pipes, fitted and fixed in position with sockets head and shoes, bends, clamps and nails etc. all complete in all floors (Aziz / Lira / National / Polymer or equivalent water grade PVC Pipe) as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

240.00

240.00

m

100mm dia PVC pipe (3.4mm to 4.0mm thick of Aziz/Lira/National/Polymar)

1.0000

240.00

Subtotal-A: Labour & other costs like head, shoes, bend, clamp

( +20.00 % on Subtotal-A )

Subtotal-A1:

288.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

293.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

323.14

VAT

6% of Total

IT

4% of Total

21.54 14.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

48.00

359.04

Page: 2023 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.06

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 5.49m long 100mm dia (inner) PVC "B" class pipe water grade (LIRA/AZIZ/ NATIONAL POLYMER brand or equivalent) with all HCI fittings and specials like plain bend, tees, reducing sockets, junctions, door bends, 100mm dia cowls, anti-siphon (MAANCO BRAND) including gasket and cement joints, PVC solution, making holes in walls and mending good the damages etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

3.4 to 4mm thick 100mm dia PVC 'B' class pipe

5.4900

m

307.50

1688.18

100mm dia HCI Junction

1.0000

each

680.00

680.00

10mm dia HCI plain bend

1.0000

each

350.00

350.00

100mm dia HCI cowl

1.0000

each

125.00

125.00

HCI Extra bend

1.0000

each

380.00

380.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.5000

day

470.00

705.00 4608.18

Subtotal-A: All other remaining costs like CC (1:3:6), gasket, cement mortar, bricks, cluamps, scaffolding, etc.

( +5.00 % on Subtotal-A )

230.41

Subtotal-A1:

4838.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4935.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5428.89

VAT

6% of Total

361.93

IT

4% of Total

241.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6032.10

Page: 2024 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.07

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of 5.49m long 100mm dia H.C.I. soil pipe (min. weight 25 Kg. per piece of 1.83 m) with all fittings and specials like plan bend, Tees, reducing sockets, junctions, door bends, 100mm dia cowls, ant siphon including gasket and cement joints making holes in walls and mending good the damages etc. all complete as per direction of the E-I-C. The rate is inclusive of 100mm thick Cement Concrete (1:3.6) all around the soil pipe under ground in/c. necessary earth cutting.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1.83m long 100mm dia HCI soil pipe

3.0000

each

2300.00

6900.00

100mm dia HCI Junction

1.0000

each

680.00

680.00

10mm dia HCI plain bend

1.0000

each

350.00

350.00

100mm dia HCI cowl

1.0000

each

125.00

125.00

HCI Extra bend

1.0000

each

380.00

380.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.5000

day

470.00

705.00 9820.00

Subtotal-A: All other remaining costs like CC (1:3:6), gasket, cement mortar, bricks, cluamps, scaffolding, etc.

( +3.00 % on Subtotal-A )

294.60

Subtotal-A1: Subtotal-B: Subtotal-C:

10114.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10316.89

10% Profit ( Add 10% on Subtotal-B) :

11348.58

VAT

6% of Total

IT

4% of Total

756.57 504.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12609.53

Page: 2025 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.08

Detailed Analysis Brief Description of Item 2 Supplying 100mm dia (inside) cast iron rain water down pipe, fitted and fixed in position with sockets head and shoes, bends, clamps and nails etc. all complete in all floors as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

100mm dia HCI Pipe with socket

1.0000

m

1200.00

1200.00

Subtotal-A: Labour & other costs like head, shoes, bend, clamp

( +33.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

396.00 1596.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1627.92

10% Profit ( Add 10% on Subtotal-B) :

1790.71

VAT

6% of Total

IT

4% of Total

119.38 79.59 Total:

7.08.09

1200.00

1989.68

Supplying, fitting and fixing 3.66m long Ventilation pipe with all fittings and specials like 50mm plain bends, tees, 50mm dia cowls etc. including gasket with cement joints and mending good the damages etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2026 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.09.01

Detailed Analysis Brief Description of Item 2 1.83m long 50mm dia H.C.I. ventilation pipe

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 1.83m long 50mm dia HCI pipe

2.0000

each

365.00

730.00

50mm dia HCI cowl

1.0000

each

60.00

60.00

50mm dia HCI bend

1.0000

each

180.00

180.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 1715.00

Subtotal-A: All other remaining costs like CC (1:3:6), gasket, cement mortar, bricks, cluamps, scaffolding, etc.

( +12.00 % on Subtotal-A )

Subtotal-A1:

1920.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1959.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2155.14

VAT

6% of Total

143.68

IT

4% of Total

95.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

205.80

2394.60

Page: 2027 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.09.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

3.66m long 50mm dia PVC best quality Ventilation Pipe (B.S. 3505)

each

Quantity 5

Unit

Rate

Amount

6

7

8

3.66m long 50mm dia PVC pipe

1.0000

each

456.18

456.18

50mm dia PVC Cowl

1.0000

each

55.00

55.00

50mm dia PVC bend

1.0000

each

30.00

30.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 1286.18

Subtotal-A: All other remaining costs like CC (1:3:6), gasket, cement mortar, bricks, cluamps, scaffolding, etc.

( +22.00 % on Subtotal-A )

Subtotal-A1:

1569.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1600.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1760.57

VAT

6% of Total

117.37

IT

4% of Total

78.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

282.96

1956.19

Page: 2028 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.10

Detailed Analysis Brief Description of Item 2 Painting H.C.I. pipes in 2 coats (100mm to 50mm dia) with approved anti-corrosive paint over a coat of priming including cleaning the rust with sand paper, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Anti- corrosive paint (Epoxy paint)

0.0200

liter

178.85

3.58

Anti-Corrosive paint primer

0.0300

liter

206.00

6.18

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 44.26

Subtotal-A: Add other remaining costs

( +5.00 % on Subtotal-A )

2.21

Subtotal-A1:

46.47

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

47.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

52.14

VAT

6% of Total

3.48

IT

4% of Total

2.32 Total:

7.08.11

57.93

Supplying, fitting, fixing and laying varoius RCC pipe having 1.83 meter in length over 100mm thick Cement Concrete (1:3.6) at base and sides including single layer brick flat soling and gasket with cement mortar joints, cutting and filling trenches up to required depth etc. all complete in all respect as per type plan and direction of the E-I-C. All other remaining costs like gasket, cement mortar, etc.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2029 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.11.01

Detailed Analysis Brief Description of Item 2 R.C.C pipe of 150 mm dia with thickness 40mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m RCC pipe 150mm dia

1.0000

m

299.63

299.63

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.1000

day

370.00

37.00 415.63

Subtotal-A: All other remaining cost for joining materials, cement concrete, cement morter, sand etc

( +20.00 % on Subtotal-A )

Subtotal-A1:

498.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

508.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

559.60

VAT

6% of Total

IT

4% of Total

37.31 24.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

83.13

621.78

Page: 2030 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.11.02

Detailed Analysis Brief Description of Item 2 R.C.C pipe of 225 mm dia with thickness 40mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m RCC pipe 225mm dia

1.0000

m

422.22

422.22

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.2000

day

370.00

74.00 609.22

Subtotal-A: All other remaining cost for joining materials, cement concrete, cement morter, sand etc

( +25.00 % on Subtotal-A )

Subtotal-A1:

761.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

776.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

854.43

VAT

6% of Total

IT

4% of Total

56.96 37.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

152.31

949.37

Page: 2031 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.11.03

Detailed Analysis Brief Description of Item 2 R.C.C pipe of 300 mm dia with thickness 50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m RCC pipe 300mm dia

1.0000

m

587.80

587.80

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.4000

day

370.00

148.00 848.80

Subtotal-A: All other remaining cost for joining materials, cement concrete, cement morter, sand etc

( +30.00 % on Subtotal-A )

Subtotal-A1:

1103.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1125.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1238.06

VAT

6% of Total

IT

4% of Total

82.54 55.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

254.64

1375.62

Page: 2032 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.11.04

Detailed Analysis Brief Description of Item 2 R.C.C pipe of 375 mm dia with thickness 50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m RCC pipe 375mm dia

1.0000

m

703.86

703.86

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Skilled Labour

0.2000

day

450.00

90.00

Ordinary Labour

0.4000

day

370.00

148.00 1009.86

Subtotal-A: All other remaining cost for joining materials, cement concrete, cement morter, sand etc

( +35.00 % on Subtotal-A )

Subtotal-A1:

1363.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1390.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1529.63

VAT

6% of Total

IT

4% of Total

101.98 67.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

353.45

1699.59

Page: 2033 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.12

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 125mm dia Stainless steel floor Gratings on floor drains with cement mortar (1:4) including making holes in walls or floors and mending good the damages etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Floor grating SS 125mm dia

1.0000

each

73.33

73.33

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00 107.33

Subtotal-A: All other remaining costs as solvent cement, cement morter, etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

128.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

131.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

144.51

VAT

6% of Total

9.63

IT

4% of Total

6.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21.47

160.57

Page: 2034 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.13

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 62mm dia Stainless steel floor Gratings on floor drains with cement mortar (1:4) including making holes in walls or floors and mending good the damages etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Floor grating SS 62mm dia

1.0000

each

64.00

64.00

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

0.0100

bag

430.00

4.30

Sand (FM - 1.2)

0.0010

m3

584.00

0.58

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00 136.88

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

6.84

Subtotal-A1:

143.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

146.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

161.26

VAT

6% of Total

10.75

IT

4% of Total

7.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

179.18

Page: 2035 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.14

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing plastic grating with hinged cover size 150 x 150 mm on floor drains including making holes in walls/floors and mending good the damages with cement mortar (1:4) etc. all complete approved and accepted by the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Plastic grating

1.0000

each

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Subtotal-A: All other remaining costs as solvent cement, cement morter, etc.

( +20.00 % on Subtotal-A )

Subtotal-A1:

6.80 40.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

41.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

45.78

VAT

6% of Total

3.05

IT

4% of Total

2.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

34.00

50.86

Page: 2036 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.15

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 100mm dia C.I. gratings at the inlet of rain water down pipes etc. all complete as per specifications and drawings, directions of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

100mm dia CI grating

1.0000

each

90.00

90.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Ordinary Labour

0.0100

day

370.00

3.70 100.50

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.01

Subtotal-A1:

101.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

103.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

113.89

VAT

6% of Total

IT

4% of Total

7.59 5.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

126.54

Page: 2037 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.16

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 125mm dia C.I. Gratings in traps or in drains with cement morter (1:4) including making holes in walls or floors and mending good the damages etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

125mm dia CI Grating

1.0000

each

120.00

120.00

Ordinary Labour

0.0300

day

370.00

11.10 131.10

Subtotal-A: All other remaining costs like cement, sand, etc.

( +25.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

163.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

167.15

10% Profit ( Add 10% on Subtotal-B) :

183.87

VAT

6% of Total

IT

4% of Total

12.26 8.17 Total:

7.08.17

Supplying, fitting and fixing 100mm dia C.I. Trap (Siphon trap or ‘P’ trap) including making holes in walls and floors and mending good the damages etc. all complete as per direction of the E-I-C.

204.30

each

100mm dia CI Trap

1.0000

each

105.00

105.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00 445.00

Subtotal-A: All other remaining costs like cement, sand, gasket, etc.

( +8.00 % on Subtotal-A )

35.60

Subtotal-A1:

480.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

490.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

539.23

VAT

6% of Total

IT

4% of Total

35.95 23.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

32.78

599.15

Page: 2038 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.08.18

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 40mm dia and 600mm long GI spout in floor or wherever required in/c cutting grooves in wall and floors etc. and mending damages properly etc. all complete as per specifications and directions of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

380.48

232.09

each

40mm dia GI pipe of 2.9mm wall thick

0.6100

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Skilled Labour

0.0300

day

450.00

13.50 265.99

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.66

Subtotal-A1:

268.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

274.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

301.43

VAT

6% of Total

IT

4% of Total

20.10 13.40 Total:

7.09.01

334.92

Supplying, fitting and fixing GI pipe confirming to the standard BS-1387 & BDS-1031, having chemical composition (in%) Carbon 0.17-0.25, Manganese 0.95-1.20, Sulphur 0.060 max, Phosphorous 0.060 max, Tensile properties: minimum Yield Strengh 188 MPa, minimum Tensile Strength 313 MPa and marking for a) Manufacturer; b) Materials; c) Wall thickness; d) Nomal outside dia; e) Intended use etc. on the body of the pipe as per British standard BS-729 having 80 micron galvanization and hydrostatic test pressure 50kg/cm2 (710 psi) with all general special fittings such as bends, elbows, sockets, reducing sockets, Tees, unions, jam-nuts etc. including cutting trenches where necessary and fitting the same with earth duly rammed and fixing in walls with holder bats and making holes in floors and walls and mending good the damages etc. all complete in all respects as per direction of the E-I-C. (Pipe manufactured by National Tubes Limited under Steel & Engineering Corporation, Ministry of Industries, Government of Bangladesh shall be given priority)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2039 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.01

Detailed Analysis Brief Description of Item 2 100mm dia GI pipe wall thickness 5mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 100mm dia GI pipe wall thickness 4.50mm

1.0000

m

1912.00

1912.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4000

day

470.00

188.00 2236.00

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +7.00 % on Subtotal-A )

156.52

Subtotal-A1:

2392.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2440.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2684.41

VAT

6% of Total

IT

4% of Total

178.96 119.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2982.67

Page: 2040 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.02

Detailed Analysis Brief Description of Item 2 100mm dia GI pipe wall thickness 4mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 100mm dia GI pipe wall thickness 4.05mm

1.0000

m

1660.00

1660.00

Plumber/ Electric Mistry/ Painter

0.4000

day

680.00

272.00 1932.00

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +7.00 % on Subtotal-A )

135.24

Subtotal-A1:

2067.24

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2108.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2319.44

VAT

6% of Total

154.63

IT

4% of Total

103.09 Total:

7.09.01.03

100mm dia GI pipe wall thickness 3.65mm

m 100mm dia GI pipe wall thickness 3.65mm

1.0000

m

1132.88

1132.88

Plumber/ Electric Mistry/ Painter

0.4000

day

680.00

272.00 1404.88

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +7.00 % on Subtotal-A )

98.34

Subtotal-A1: Subtotal-B: Subtotal-C:

1503.22 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1533.29

10% Profit ( Add 10% on Subtotal-B) :

1686.61

VAT

6% of Total

IT

4% of Total

112.44 74.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2577.16

1874.02

Page: 2041 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.04

Detailed Analysis Brief Description of Item 2 75~80mm dia GI pipe wall thickness 3.65mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 80mm dia GI pipe wall thickness 4.05mm

1.0000

m

1132.00

1132.00

Plumber/ Electric Mistry/ Painter

0.3300

day

680.00

224.40 1356.40

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.80 % on Subtotal-A )

92.24

Subtotal-A1:

1448.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1477.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1625.37

VAT

6% of Total

108.36

IT

4% of Total

72.24 Total:

7.09.01.05

75~80mm dia GI pipe wall thickness 3.25~3.2mm

m 80mm dia GI pipe wall thickness 3.25mm

1.0000

m

784.90

784.90

Plumber/ Electric Mistry/ Painter

0.3300

day

680.00

224.40 1009.30

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.80 % on Subtotal-A )

68.63

Subtotal-A1: Subtotal-B: Subtotal-C:

1077.93 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1099.49

10% Profit ( Add 10% on Subtotal-B) :

1209.44

VAT

6% of Total

IT

4% of Total

80.63 53.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1805.97

1343.82

Page: 2042 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.06

Detailed Analysis Brief Description of Item 2 75~80mm dia GI pipe wall thickness 2.90mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 80mm dia GI pipe wall thickness 2.90mm

1.0000

m

820.00

820.00

Plumber/ Electric Mistry/ Painter

0.3300

day

680.00

224.40 1044.40

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.80 % on Subtotal-A )

71.02

Subtotal-A1:

1115.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1137.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1251.50

VAT

6% of Total

83.43

IT

4% of Total

55.62 Total:

7.09.01.07

62~65mm dia GI pipe wall thickness 4mm

m 65mm dia GI pipe wall thickness 3.65mm

1.0000

m

997.00

997.00

Plumber/ Electric Mistry/ Painter

0.2700

day

680.00

183.60 1180.60

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.40 % on Subtotal-A )

75.56

Subtotal-A1: Subtotal-B: Subtotal-C:

1256.16 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1281.28

10% Profit ( Add 10% on Subtotal-B) :

1409.41

VAT

6% of Total

IT

4% of Total

93.96 62.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1390.56

1566.01

Page: 2043 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.08

Detailed Analysis Brief Description of Item 2 62~65mm dia GI pipe wall thickness 3.25~3.2mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 65mm dia GI pipe wall thickness 3.25mm

1.0000

m

701.10

701.10

Plumber/ Electric Mistry/ Painter

0.2700

day

680.00

183.60 884.70

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.40 % on Subtotal-A )

56.62

Subtotal-A1:

941.32

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

960.15 1056.16

VAT

6% of Total

70.41

IT

4% of Total

46.94 Total:

7.09.01.09

62~65mm dia GI pipe wall thickness 2.90mm

m 65mm dia GI pipe wall thickness 2.90mm

1.0000

m

758.00

758.00

Plumber/ Electric Mistry/ Painter

0.2700

day

680.00

183.60 941.60

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.40 % on Subtotal-A )

60.26

Subtotal-A1: Subtotal-B: Subtotal-C:

1001.86 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1021.90

10% Profit ( Add 10% on Subtotal-B) :

1124.09

VAT

6% of Total

IT

4% of Total

74.94 49.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1173.51

1248.99

Page: 2044 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.10

Detailed Analysis Brief Description of Item 2 50mm dia GI pipe wall thickness 3.65mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 50mm dia GI pipe wall thickness 3.65mm

1.0000

m

670.00

670.00

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 792.40

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.00 % on Subtotal-A )

47.54

Subtotal-A1:

839.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

856.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

942.42

VAT

6% of Total

62.83

IT

4% of Total

41.89 Total:

7.09.01.11

50mm dia GI pipe wall thickness 2.90mm

m 50mm dia GI pipe wall thickness 2.90mm

1.0000

m

457.42

457.42

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 579.82

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.00 % on Subtotal-A )

34.79

Subtotal-A1: Subtotal-B: Subtotal-C:

614.61 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

626.90

10% Profit ( Add 10% on Subtotal-B) :

689.59

VAT

6% of Total

IT

4% of Total

45.97 30.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1047.13

766.21

Page: 2045 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.12

Detailed Analysis Brief Description of Item 2 50mm dia GI pipe wall thickness 2.65mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 50mm dia GI pipe wall thickness 2.65mm

1.0000

m

512.00

512.00

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 634.40

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +6.00 % on Subtotal-A )

38.06

Subtotal-A1:

672.46

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

685.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

754.50

VAT

6% of Total

50.30

IT

4% of Total

33.53 Total:

7.09.01.13

40mm dia GI pipe wall thickness 3.25~3.2mm

m 40mm dia GI pipe wall thickness 3.25mm

1.0000

m

515.00

515.00

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 637.40

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.70 % on Subtotal-A )

36.33

Subtotal-A1: Subtotal-B: Subtotal-C:

673.73 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

687.21

10% Profit ( Add 10% on Subtotal-B) :

755.93

VAT

6% of Total

IT

4% of Total

50.40 33.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

838.34

839.92

Page: 2046 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.14

Detailed Analysis Brief Description of Item 2 40mm dia GI pipe wall thickness 2.90mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 40mm dia GI pipe wall thickness 2.90mm

1.0000

m

380.48

380.48

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 502.88

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.70 % on Subtotal-A )

28.66

Subtotal-A1:

531.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

542.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

596.39

VAT

6% of Total

39.76

IT

4% of Total

26.51 Total:

7.09.01.15

40mm dia GI pipe wall thickness 2.65mm

m 40mm dia GI pipe wall thickness 2.65mm

1.0000

m

410.00

410.00

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 532.40

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.70 % on Subtotal-A )

30.35

Subtotal-A1: Subtotal-B: Subtotal-C:

562.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

574.00

10% Profit ( Add 10% on Subtotal-B) :

631.40

VAT

6% of Total

IT

4% of Total

42.09 28.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

662.66

701.56

Page: 2047 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.16

Detailed Analysis Brief Description of Item 2 32mm dia GI pipe wall thickness 3.25mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 32mm dia GI pipe wall thickness 3.25mm

1.0000

m

380.00

380.00

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 502.40

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.50 % on Subtotal-A )

27.63

Subtotal-A1:

530.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

540.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

594.70

VAT

6% of Total

39.65

IT

4% of Total

26.43 Total:

7.09.01.17

32mm dia GI pipe wall thickness 2.65mm

m 32mm dia GI pipe wall thickness 2.65mm

1.0000

m

303.52

303.52

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 425.92

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.50 % on Subtotal-A )

23.43

Subtotal-A1: Subtotal-B: Subtotal-C:

449.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

458.33

10% Profit ( Add 10% on Subtotal-B) :

504.17

VAT

6% of Total

IT

4% of Total

33.61 22.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

660.77

560.18

Page: 2048 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.18

Detailed Analysis Brief Description of Item 2 32mm dia GI pipe wall thickness 2.35~2.3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 32mm dia GI pipe wall thickness 2.35mm

1.0000

m

308.00

308.00

Plumber/ Electric Mistry/ Painter

0.1800

day

680.00

122.40 430.40

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.50 % on Subtotal-A )

23.67

Subtotal-A1:

454.07

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

463.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

509.47

VAT

6% of Total

33.96

IT

4% of Total

22.64 Total:

7.09.01.19

25mm dia GI pipe wall thickness 2.9mm

m 25mm dia GI pipe wall thickness 3.25mm

1.0000

m

348.00

348.00

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 422.80

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.40 % on Subtotal-A )

22.83

Subtotal-A1: Subtotal-B: Subtotal-C:

445.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

454.54

10% Profit ( Add 10% on Subtotal-B) :

500.00

VAT

6% of Total

IT

4% of Total

33.33 22.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

566.08

555.55

Page: 2049 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.20

Detailed Analysis Brief Description of Item 2 25mm dia GI pipe wall thickness 2.65mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 25mm dia GI pipe wall thickness 2.65mm

1.0000

m

219.40

219.40

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 294.20

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.40 % on Subtotal-A )

15.89

Subtotal-A1:

310.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

316.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

347.92

VAT

6% of Total

23.19

IT

4% of Total

15.46 Total:

7.09.01.21

25mm dia GI pipe wall thickness 2.35~2.3mm

m 25mm dia GI pipe wall thickness 2.35mm

1.0000

m

239.40

239.40

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 314.20

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.40 % on Subtotal-A )

16.97

Subtotal-A1: Subtotal-B: Subtotal-C:

331.17 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

337.79

10% Profit ( Add 10% on Subtotal-B) :

371.57

VAT

6% of Total

IT

4% of Total

24.77 16.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

386.57

412.85

Page: 2050 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.22

Detailed Analysis Brief Description of Item 2 20mm dia GI pipe wall thickness 2.65mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 20mm dia GI pipe wall thickness 2.65mm

1.0000

m

230.00

230.00

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 304.80

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.30 % on Subtotal-A )

16.15

Subtotal-A1:

320.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

327.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

360.11

VAT

6% of Total

24.01

IT

4% of Total

16.00 Total:

7.09.01.23

20mm dia GI pipe wall thickness 2.35~2.3mm

m 20mm dia GI pipe wall thickness 2.35mm

1.0000

m

171.00

171.00

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 245.80

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.30 % on Subtotal-A )

13.03

Subtotal-A1: Subtotal-B: Subtotal-C:

258.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

264.00

10% Profit ( Add 10% on Subtotal-B) :

290.40

VAT

6% of Total

IT

4% of Total

19.36 12.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

400.12

322.67

Page: 2051 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.24

Detailed Analysis Brief Description of Item 2 20mm dia GI pipe wall thickness 2.10~2.2mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 20mm dia GI pipe wall thickness 2.10mm

1.0000

m

174.00

174.00

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 248.80

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.30 % on Subtotal-A )

13.19

Subtotal-A1:

261.99

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

267.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

293.95

VAT

6% of Total

19.60

IT

4% of Total

13.06 Total:

7.09.01.25

12~15mm dia GI pipe wall thickness 2.65mm

m 15mm dia GI pipe wall thickness 2.65mm

1.0000

m

171.00

171.00

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 245.80

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.00 % on Subtotal-A )

12.29

Subtotal-A1: Subtotal-B: Subtotal-C:

258.09 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

263.25

10% Profit ( Add 10% on Subtotal-B) :

289.58

VAT

6% of Total

IT

4% of Total

19.31 12.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

326.61

321.75

Page: 2052 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.01.26

Detailed Analysis Brief Description of Item 2 12~15mm dia GI pipe wall thickness 2.35~2.3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 15mm dia GI pipe wall thickness 2.35mm

1.0000

m

151.00

151.00

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 225.80

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.00 % on Subtotal-A )

11.29

Subtotal-A1:

237.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

241.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

266.01

VAT

6% of Total

17.73

IT

4% of Total

11.82 Total:

7.09.01.27

12~15mm dia GI pipe wall thickness 2.00mm

m 15mm dia GI pipe wall thickness 2.00mm

1.0000

m

115.43

115.43

Plumber/ Electric Mistry/ Painter

0.1100

day

680.00

74.80 190.23

Subtotal-A: All other remaining costs like fittings, joining and fixing materials, mending good the damages of floor, walls etc.

( +5.00 % on Subtotal-A )

9.51

Subtotal-A1: Subtotal-B: Subtotal-C:

199.74 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

203.74

10% Profit ( Add 10% on Subtotal-B) :

224.11

VAT

6% of Total

IT

4% of Total

14.94 9.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

295.57

249.01

Page: 2053 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.02

Detailed Analysis Brief Description of Item 2 Cost for concealing of GI pipe work (12mm and 20mm dia) in brick wall by cutting wall, lintel, beam etc. by any means carefully without damaging the structure and filling the grooves after laying of pipe with Cement Concrete (1:2:4) including cost of scaffolding etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Mass concrete in foundation (1:3:6) with cement, sand and brick chips ……….. (3.11.01)

0.0010

cum

5707.82

5.71

Skilled Labour

0.3300

day

450.00

148.50

Ordinary Labour

0.0700

day

370.00

25.90 180.11

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.80

Subtotal-A1:

181.91

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

204.10

VAT

6% of Total

IT

4% of Total

13.61 9.07 Total:

7.09.03

226.78

Supplying, fitting and fixing best quality G.M. Pit valve of brass fittings with leak proof and fitted selected tape etc. all complete in all respects as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2054 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.03.01

2 50mm dia peet valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50mm dia GM peat valve

1.0000

each

1150.00

1150.00

Ordinary Labour

0.3300

day

370.00

122.10 1272.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1297.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1427.30

VAT

6% of Total

95.15

IT

4% of Total

63.44 Total:

7.09.03.02

40mm dia peet valve

each 40mm dia GM peat valve

1.0000

each

850.00

850.00

Ordinary Labour

0.3300

day

370.00

122.10 972.10

Subtotal-A: Subtotal-B: Subtotal-C:

991.54

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1090.70

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

72.71 48.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1585.88

1211.88

Page: 2055 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.03.03

2 30mm dia peet valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 30mm dia GM peat valve

1.0000

each

660.00

660.00

Ordinary Labour

0.3300

day

370.00

122.10 782.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

797.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

877.52

VAT

6% of Total

58.50

IT

4% of Total

39.00 Total:

7.09.03.04

25mm dia peet valve

each 25mm dia GM peat valve

1.0000

each

390.00

390.00

Ordinary Labour

0.3300

day

370.00

122.10 512.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

522.34

10% Profit ( Add 10% on Subtotal-B) :

574.58

VAT

6% of Total

IT

4% of Total

38.31 25.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

975.02

638.42

Page: 2056 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.03.05

2 20mm dia peet valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 20mm dia GM peat valve

1.0000

each

290.00

290.00

Ordinary Labour

0.3300

day

370.00

122.10 412.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

420.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

462.38

VAT

6% of Total

30.83

IT

4% of Total

20.55 Total:

7.09.03.06

12mm dia peet valve

each 12mm dia GM peat valve

1.0000

each

225.00

225.00

Ordinary Labour

0.3300

day

370.00

122.10 347.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

354.04

10% Profit ( Add 10% on Subtotal-B) :

389.45

VAT

6% of Total

IT

4% of Total

25.96 17.31 Total:

7.09.04

513.75

432.72

Supplying, fitting and fixing best quality G.I. Union of leak proof, fitted with sealant, Teflon tape etc. all complete in all respects as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2057 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.04.01

2 12 mm dia G.I. Union

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each G.I. Union 12 mm dia

1.0000

each

38.80

38.80

Plumber/ Electric Mistry/ Painter

0.0250

day

680.00

17.00

Skilled Labour

0.0750

day

450.00

33.75

Ordinary Labour

0.0500

day

370.00

18.50 108.05

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

110.21

10% Profit ( Add 10% on Subtotal-B) :

121.23

VAT

6% of Total

IT

4% of Total

8.08 5.39 Total:

7.09.04.02

20 mm dia G.I. Union

each G.I. Union 20 mm dia

1.0000

each

58.20

58.20

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.0600

day

370.00

22.20 136.80

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

139.54

10% Profit ( Add 10% on Subtotal-B) :

153.49

VAT

6% of Total

IT

4% of Total

10.23 6.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

134.70

170.54

Page: 2058 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.04.03

2 25 mm dia G.I. Union

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each G.I. Union 25 mm dia

1.0000

each

69.84

69.84

Plumber/ Electric Mistry/ Painter

0.0400

day

680.00

27.20

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.0700

day

370.00

25.90 163.44

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

166.71

10% Profit ( Add 10% on Subtotal-B) :

183.38

VAT

6% of Total

IT

4% of Total

12.23 8.15 Total:

7.09.04.04

32 mm dia G.I. Union

each G.I. Union 32 mm dia

1.0000

each

92.15

92.15

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.1000

day

370.00

37.00 208.15

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

212.31

10% Profit ( Add 10% on Subtotal-B) :

233.54

VAT

6% of Total

IT

4% of Total

15.57 10.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

203.76

259.49

Page: 2059 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.04.05

2 40 mm dia G.I. Union

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each G.I. Union 40 mm dia

1.0000

each

135.80

135.80

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.1200

day

370.00

44.40 270.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

275.91

10% Profit ( Add 10% on Subtotal-B) :

303.50

VAT

6% of Total

IT

4% of Total

20.23 13.49 Total:

7.09.04.06

50 mm dia G.I. Union

each G.I. Union 50 mm dia

1.0000

each

184.30

184.30

Plumber/ Electric Mistry/ Painter

0.0700

day

680.00

47.60

Skilled Labour

0.1200

day

450.00

54.00

Ordinary Labour

0.1500

day

370.00

55.50 341.40

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

348.23

10% Profit ( Add 10% on Subtotal-B) :

383.05

VAT

6% of Total

IT

4% of Total

25.54 17.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

337.22

425.61

Page: 2060 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.04.07

2 62 mm dia G.I. Union

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each G.I. Union 62 mm dia

1.0000

each

407.40

407.40

Plumber/ Electric Mistry/ Painter

0.0900

day

680.00

61.20

Skilled Labour

0.1400

day

450.00

63.00

Ordinary Labour

0.1700

day

370.00

62.90 594.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

606.39

10% Profit ( Add 10% on Subtotal-B) :

667.03

VAT

6% of Total

IT

4% of Total

44.47 29.65 Total:

7.09.04.08

75 mm dia G.I. Union

each G.I. Union 75 mm dia

1.0000

each

543.20

543.20

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Skilled Labour

0.1750

day

450.00

78.75

Ordinary Labour

0.2000

day

370.00

74.00 763.95

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

779.23

10% Profit ( Add 10% on Subtotal-B) :

857.15

VAT

6% of Total

IT

4% of Total

57.14 38.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

741.14

952.39

Page: 2061 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.04.09

2 100 mm dia G.I. Union

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each G.I. Union 100 mm dia

1.0000

each

776.00

776.00

Plumber/ Electric Mistry/ Painter

0.1150

day

680.00

78.20

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.2250

day

370.00

83.25 1022.95

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1043.41

10% Profit ( Add 10% on Subtotal-B) :

1147.75

VAT

6% of Total

IT

4% of Total

76.52 51.01 Total:

7.09.05

Supplying, fitting and fixing best quality G.I. gate valve of brass fittings, leak proof, fitted with sealant, Teflon tape etc. all complete in all respects as per direction of the E-I-C.

7.09.05.01

12 mm dia Brass gate valve

each Brass gate valve 12 mm dia

1.0000

each

213.40

213.40

Plumber/ Electric Mistry/ Painter

0.0250

Skilled Labour

0.0750

day

680.00

17.00

day

450.00

33.75

Ordinary Labour

0.0500

day

370.00

18.50 282.65

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

288.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

317.13

VAT

6% of Total

IT

4% of Total

21.14 14.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1275.28

352.37

Page: 2062 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.05.02

2 20 mm dia Brass gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Brass gate valve 20 mm dia

1.0000

each

368.60

368.60

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.0600

day

370.00

22.20 447.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

456.14

10% Profit ( Add 10% on Subtotal-B) :

501.76

VAT

6% of Total

IT

4% of Total

33.45 22.30 Total:

7.09.05.03

25 mm dia Brass gate valve

each Brass gate valve 25 mm dia

1.0000

each

436.50

436.50

Plumber/ Electric Mistry/ Painter

0.0400

day

680.00

27.20

Skilled Labour

0.0900

day

450.00

40.50

Skilled Labour

0.0700

day

450.00

31.50 535.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

546.41

10% Profit ( Add 10% on Subtotal-B) :

601.06

VAT

6% of Total

IT

4% of Total

40.07 26.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

557.51

667.84

Page: 2063 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.05.04

2 32 mm dia Brass gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Brass gate valve 32 mm dia

1.0000

each

630.50

630.50

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.1000

day

370.00

37.00 746.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

761.43

10% Profit ( Add 10% on Subtotal-B) :

837.57

VAT

6% of Total

IT

4% of Total

55.84 37.23 Total:

7.09.05.05

40 mm dia Brass gate valve

each Brass gate valve 40 mm dia

1.0000

each

679.00

679.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.1200

day

370.00

44.40 813.70

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

829.97

10% Profit ( Add 10% on Subtotal-B) :

912.97

VAT

6% of Total

IT

4% of Total

60.86 40.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

930.64

1014.41

Page: 2064 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.05.06

2 50 mm dia Brass gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Brass gate valve 50 mm dia

1.0000

each

1212.50

1212.50

Plumber/ Electric Mistry/ Painter

0.0700

day

680.00

47.60

Skilled Labour

0.1200

day

450.00

54.00

Ordinary Labour

0.1500

day

370.00

55.50 1369.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1396.99

10% Profit ( Add 10% on Subtotal-B) :

1536.69

VAT

6% of Total

IT

4% of Total

102.45 68.30 Total:

7.09.05.07

62 mm dia Brass gate valve

each Brass gate valve 62 mm dia

1.0000

each

2522.00

2522.00

Plumber/ Electric Mistry/ Painter

0.0900

day

680.00

61.20

Skilled Labour

0.1400

day

450.00

63.00

Ordinary Labour

0.1700

day

370.00

62.90 2709.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2763.28

10% Profit ( Add 10% on Subtotal-B) :

3039.61

VAT

6% of Total

IT

4% of Total

202.64 135.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1707.43

3377.34

Page: 2065 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.05.08

2 75 mm dia Brass gate valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Brass gate valve 75 mm dia

1.0000

each

3395.00

3395.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Skilled Labour

0.1750

day

450.00

78.75

Ordinary Labour

0.2000

day

370.00

74.00 3615.75

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3688.07

10% Profit ( Add 10% on Subtotal-B) :

4056.87

VAT

6% of Total

IT

4% of Total

270.46 180.31 Total:

7.09.05.09

100 mm dia Brass gate valve

each Brass gate valve 100 mm dia

1.0000

each

5625.00

5625.00

Plumber/ Electric Mistry/ Painter

0.1150

day

680.00

78.20

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.2250

day

370.00

83.25 5871.95

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5989.39

10% Profit ( Add 10% on Subtotal-B) :

6588.33

VAT

6% of Total

IT

4% of Total

439.22 292.81 Total:

7.09.06

4507.64

7320.36

Supplying, fitting and fixing best quality G.I. Check valve of brass fittings, threaded joint, leak proof with sealant, Teflon tape etc. all complete in all respects as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2066 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.06.01

2 12 mm brass check valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Brass check valve 12 mm dia

1.0000

each

242.50

242.50

Plumber/ Electric Mistry/ Painter

0.0250

day

680.00

17.00

Skilled Labour

0.0750

day

450.00

33.75

Ordinary Labour

0.0500

day

370.00

18.50 311.75

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

317.99

10% Profit ( Add 10% on Subtotal-B) :

349.78

VAT

6% of Total

IT

4% of Total

23.32 15.55 Total:

7.09.06.02

20 mm brass check valve

each Brass check valve 20 mm dia

1.0000

each

291.00

291.00

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.0600

day

370.00

22.20 369.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

376.99

10% Profit ( Add 10% on Subtotal-B) :

414.69

VAT

6% of Total

IT

4% of Total

27.65 18.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

388.65

460.77

Page: 2067 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.06.03

2 25 mm brass check valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Brass check valve 25 mm dia

1.0000

each

436.50

436.50

Plumber/ Electric Mistry/ Painter

0.0400

day

680.00

27.20

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.0700

day

370.00

25.90 530.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

540.70

10% Profit ( Add 10% on Subtotal-B) :

594.77

VAT

6% of Total

IT

4% of Total

39.65 26.43 Total:

7.09.06.04

32 mm brass check valve

each Brass check valve 32 mm dia

1.0000

each

630.50

630.50

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.1000

day

370.00

37.00 746.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

761.43

10% Profit ( Add 10% on Subtotal-B) :

837.57

VAT

6% of Total

IT

4% of Total

55.84 37.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

660.86

930.64

Page: 2068 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.06.05

2 40 mm brass check valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Brass check valve 40 mm dia

1.0000

each

727.50

727.50

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.1200

day

370.00

44.40 862.20

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

879.44

10% Profit ( Add 10% on Subtotal-B) :

967.39

VAT

6% of Total

IT

4% of Total

64.49 43.00 Total:

7.09.06.06

50 mm brass check valve

each Brass check valve 50 mm dia

1.0000

each

1212.50

1212.50

Plumber/ Electric Mistry/ Painter

0.0700

day

680.00

47.60

Skilled Labour

0.1200

day

450.00

54.00

Ordinary Labour

0.1500

day

370.00

55.50 1369.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1396.99

10% Profit ( Add 10% on Subtotal-B) :

1536.69

VAT

6% of Total

IT

4% of Total

102.45 68.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1074.88

1707.43

Page: 2069 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.06.07

2 62 mm brass check valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Brass check valve 62 mm dia

1.0000

each

2134.00

2134.00

Plumber/ Electric Mistry/ Painter

0.0900

day

680.00

61.20

Skilled Labour

0.1400

day

450.00

63.00

Ordinary Labour

0.1700

day

370.00

62.90 2321.10

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2367.52

10% Profit ( Add 10% on Subtotal-B) :

2604.27

VAT

6% of Total

IT

4% of Total

173.62 115.75 Total:

7.09.06.08

75 mm brass check valve

each Brass check valve 75 mm dia

1.0000

each

2958.50

2958.50

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Skilled Labour

0.1750

day

450.00

78.75

Ordinary Labour

0.2000

day

370.00

74.00 3179.25

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3242.84

10% Profit ( Add 10% on Subtotal-B) :

3567.12

VAT

6% of Total

IT

4% of Total

237.81 158.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2893.64

3963.47

Page: 2070 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.06.09

2 100 mm brass check valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Brass check valve 100 mm dia

1.0000

each

4850.00

4850.00

Plumber/ Electric Mistry/ Painter

0.1150

day

680.00

78.20

Skilled Labour

0.1900

day

450.00

85.50

Ordinary Labour

0.2250

day

370.00

83.25 5096.95

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5198.89

10% Profit ( Add 10% on Subtotal-B) :

5718.78

VAT

6% of Total

IT

4% of Total

381.25 254.17 Total:

7.09.07

Supplying, fitting and fixing best quality G.I. Float valve with brass fittings, threaded joint Pit valve with sealant, Teflon tape, leak proof etc. all complete in all respects as per direction of the E-I-C.

7.09.07.01

12 mm brass Float valve

each Brass Float valve 12 mm dia

1.0000

each

226.98

226.98

Plumber/ Electric Mistry/ Painter

0.0250

Skilled Labour

0.0750

day

680.00

17.00

day

450.00

33.75

Ordinary Labour

0.0500

day

370.00

18.50 296.23

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

302.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

332.37

VAT

6% of Total

IT

4% of Total

22.16 14.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6354.20

369.30

Page: 2071 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.07.02

2 20 mm brass Float valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Brass Float valve 20 mm dia

1.0000

each

307.49

307.49

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.0600

day

370.00

22.20 386.09

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

393.81

10% Profit ( Add 10% on Subtotal-B) :

433.19

VAT

6% of Total

IT

4% of Total

28.88 19.25 Total:

7.09.07.03

25 mm brass Float valve

each Brass Float valve 25 mm dia

1.0000

each

338.53

338.53

Plumber/ Electric Mistry/ Painter

0.0400

day

680.00

27.20

Skilled Labour

0.0900

day

450.00

40.50

Ordinary Labour

0.0700

day

370.00

25.90 432.13

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

440.77

10% Profit ( Add 10% on Subtotal-B) :

484.85

VAT

6% of Total

IT

4% of Total

32.32 21.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

481.33

538.72

Page: 2072 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.07.04

2 32 mm brass Float valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Brass Float valve 32 mm dia

1.0000

each

599.46

599.46

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Skilled Labour

0.1000

day

450.00

45.00

Ordinary Labour

0.1000

day

370.00

37.00 715.46

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

729.77

10% Profit ( Add 10% on Subtotal-B) :

802.75

VAT

6% of Total

IT

4% of Total

53.52 35.68 Total:

7.09.07.05

40 mm brass Float valve

each Brass Float valve 40 mm dia

1.0000

each

792.49

792.49

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

Skilled Labour

0.1100

day

450.00

49.50

Ordinary Labour

0.1200

day

370.00

44.40 927.19

Subtotal-A: Subtotal-B: Subtotal-C:

945.73

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1040.31

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

69.35 46.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

891.94

1155.90

Page: 2073 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.09.08

Supplying, Installation, fitting and fixing MS pipe of different size with necessary wrapping tape and primer confirming to the standard and marking for a) Manufacturer; b) Materials; c) Wall thickness; d) Normal outside dia; e) Intended use etc. on the body of the pipe as per standard with all general special fittings such as bends, elbows, sockets, reducing sockets, Tees, unions, jam-nuts etc. Cutting and cleaning the pipe, applying coal tar. Wrapping the pipes with necessary tape etc. including cutting trenches where necessary and filling the same with sand duly rammed and fixing in walls with holder bats and making holes in floors and walls and mending good the damages etc as per specification of Titas Gas T and D co. ltd. all complete in all respects as per direction of the E-I-C. (Pipe manufactured by National Tubes Limited under Steel & Engineering Corporation, Ministry of Industries, Government of Bangladesh shall be given priority)

7.09.08.01

75mm dia MS pipe weight minimum 8.30 kg/m, standard test pressure 176 kg/m2, wall thickness 4.00mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m 75mm dia. MS pipe and wall thickness 4.00mm

1.0000

m

892.00

892.00

Plumber/ Electric Mistry/ Painter

0.0900

day

680.00

61.20

4"x400' Black Tape

0.0328

Roll

5300.00

173.84

Skilled Labour

0.0800

day

450.00

36.00

Ordinary Labour

0.1500

day

370.00

55.50 1218.54

Subtotal-A: Cost of primer, coal tar, sand, cutting pipe, cleaning and other all excessoreies and charges

( +20.00 % on Subtotal-A )

Subtotal-A1:

1462.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1491.49

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1640.64

VAT

6% of Total

IT

4% of Total

109.38 72.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

243.71

1822.94

Page: 2074 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.08.02

Detailed Analysis Brief Description of Item 2 50mm dia MS pipe weight minimum 5.44 kg/m, standard test pressure 176 kg/m2, wall thickness 4.00mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

534.00

534.00

m 50mm dia. MS pipe and wall thickness 4.00mm

1.0000

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

2"x200' Black Tape

0.0984

Roll

1146.00

112.77

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

0.1500

day

370.00

55.50 770.07

Subtotal-A: Cost of primer, coal tar, sand, cutting pipe, cleaning and other all excessoreies and charges

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

908.68 926.85

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1019.54

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

67.97

IT

4% of Total

45.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

138.61

1132.82

Page: 2075 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.08.03

Detailed Analysis Brief Description of Item 2 25mm dia MS pipe weight minimum 2.50 kg/m, standard test pressure 50 kg/m2, wall thickness 2.90mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

246.00

246.00

m 25mm dia. MS pipe and wall thickness 2.90mm

1.0000

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

2"x200' Black Tape

0.0492

Roll

1146.00

56.38

Skilled Labour

0.0600

day

450.00

27.00

Ordinary Labour

0.1500

day

370.00

55.50 425.68

Subtotal-A: Cost of primer, coal tar, sand, cutting pipe, cleaning and other all excessoreies and charges

( +15.00 % on Subtotal-A )

Subtotal-A1:

489.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

499.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

549.26

VAT

6% of Total

36.62

IT

4% of Total

24.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

63.85

610.29

Page: 2076 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.08.04

Detailed Analysis Brief Description of Item 2 20mm dia MS pipe weight minimum 1.68 kg/m, standard test pressure 50 kg/m2, wall thickness 2.65mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

177.00

177.00

m 20mm dia. MS pipe and wall thickness 2.65mm

1.0000

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

2"x200' Black Tape

0.0410

Roll

1146.00

46.99

Skilled Labour

0.0500

day

450.00

22.50

Ordinary Labour

0.1200

day

370.00

44.40 331.69

Subtotal-A: Cost of primer, coal tar, sand, cutting pipe, cleaning and other all excessoreies and charges

( +12.00 % on Subtotal-A )

Subtotal-A1:

371.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

378.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

416.81

VAT

6% of Total

27.79

IT

4% of Total

18.52 Total:

7.09.09

39.80

463.12

Providing Butt welding joints with pipes to Tees, Elbows, Saddles, end caps etc. above or below ground i/c. cutting and V-leveling in each end of the pipe, grinding by machine etc. as per specification of Titas Gas T and D co. ltd. all complete in all respects as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2077 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.09.01

2 75mm N.D (88.90mm O.D)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Welder

0.1600

day

680.00

108.80

Welder Helper

0.1600

day

470.00

75.20 184.00

Subtotal-A: welding materials and equipments and other requirements

( +2.00 % on Subtotal-A )

3.68

Subtotal-A1: Subtotal-B: Subtotal-C:

187.68 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

191.43

10% Profit ( Add 10% on Subtotal-B) :

210.58

VAT

6% of Total

IT

4% of Total

14.04 9.36 Total:

7.09.09.02

50mm N.D (60.30mm O.D)

each Welder

0.1200

day

680.00

81.60

Welder Helper

0.1200

day

470.00

56.40 138.00

Subtotal-A: welding materials and equipments and other requirements

( +2.00 % on Subtotal-A )

2.76

Subtotal-A1:

140.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

143.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

157.93

VAT

6% of Total

IT

4% of Total

10.53 7.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

233.97

175.48

Page: 2078 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.09.03

2 25mm N.D (33.40mm O.D)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Welder

0.0850

day

680.00

57.80

Welder Helper

0.0850

day

470.00

39.95 97.75

Subtotal-A: welding materials and equipments and other requirements

( +2.00 % on Subtotal-A )

1.96

Subtotal-A1: Subtotal-B: Subtotal-C:

99.71 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

101.70

10% Profit ( Add 10% on Subtotal-B) :

111.87

VAT

6% of Total

IT

4% of Total

7.46 4.97 Total:

7.09.09.04

20mm N.D (26.70mm O.D)

each Welder

0.0800

day

680.00

54.40

Welder Helper

0.0800

day

470.00

37.60 92.00

Subtotal-A: welding materials and equipments and other requirements

( +2.00 % on Subtotal-A )

1.84

Subtotal-A1:

93.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

95.72 105.29 7.02 4.68

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

124.30

116.99

Page: 2079 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.09.10

Supplying, fitting and fixing following materials including carriage to the work site from Titas Gas store etc. as per specification of Titas Gas T and D co. ltd. all complete in all respects as per direction of the E-I-C.

7.09.10.01

50mmx50mmx50mm (N.D) equal Tee

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 50mmx50mmx50mm (N.D) equal Tee

1.0000

each

200.00

200.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 218.30

Subtotal-A: All other materials and charges covered

( +.40 % on Subtotal-A )

0.87

Subtotal-A1:

219.17

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

223.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

245.91

VAT

6% of Total

IT

4% of Total

16.39 10.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

273.24

Page: 2080 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.10.02

Detailed Analysis Brief Description of Item 2 50mmx50mmx25mm (N.D) reducing Tee

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 50mmx50mmx25mm (N.D) reducing Tee

1.0000

each

224.00

224.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 242.30

Subtotal-A: All other materials and charges covered

( +.30 % on Subtotal-A )

0.73

Subtotal-A1: Subtotal-B: Subtotal-C:

243.03 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

247.89

10% Profit ( Add 10% on Subtotal-B) :

272.68

VAT

6% of Total

IT

4% of Total

18.18 12.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

302.97

Page: 2081 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.10.03

Detailed Analysis Brief Description of Item 2 25mmx25mmx25mm (N.D) equal Tee

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 25mmx25mmx25mm (N.D) equal Tee

1.0000

each

127.00

127.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 145.30

Subtotal-A: All other materials and charges covered

( +.30 % on Subtotal-A )

0.44

Subtotal-A1: Subtotal-B: Subtotal-C:

145.74 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

148.65

10% Profit ( Add 10% on Subtotal-B) :

163.52

VAT

6% of Total

IT

4% of Total

10.90 7.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

181.68

Page: 2082 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.10.04

2 50mmx90 degree elbow

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 50mmx90 degree elbow

1.0000

each

164.00

164.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 182.30

Subtotal-A: All other materials and charges covered

( +.20 % on Subtotal-A )

0.36

Subtotal-A1: Subtotal-B: Subtotal-C:

182.66 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

186.32

10% Profit ( Add 10% on Subtotal-B) :

204.95

VAT

6% of Total

IT

4% of Total

13.66 9.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

227.72

Page: 2083 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.10.05

2 25mmx90 degree elbow

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 25mmx90 degree elbow

1.0000

each

48.00

48.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 66.30

Subtotal-A: All other materials and charges covered

( +.20 % on Subtotal-A )

0.13

Subtotal-A1: Subtotal-B: Subtotal-C:

66.43 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

67.76

10% Profit ( Add 10% on Subtotal-B) :

74.54

VAT

6% of Total

IT

4% of Total

4.97 3.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

82.82

Page: 2084 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.10.06

2 50mmx25mm 45 degree elbow

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50mmx25mm 45 degree elbow

1.0000

each

71.00

71.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 89.30

Subtotal-A: All other materials and charges covered

( +.20 % on Subtotal-A )

0.18

Subtotal-A1: Subtotal-B: Subtotal-C:

89.48 91.27

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100.39

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6.69 4.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

111.55

Page: 2085 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.10.07

2 50mmx25mm reducer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50mmx25mm reducer

1.0000

each

79.00

79.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 97.30

Subtotal-A: All other materials and charges covered

( +.20 % on Subtotal-A )

0.19

Subtotal-A1: Subtotal-B: Subtotal-C:

97.49 99.44

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

109.39

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7.29 4.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

121.54

Page: 2086 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.10.08

2 20mm plug, socket

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 20mm plug, socket

1.0000

each

198.00

198.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 216.30

Subtotal-A: All other materials and charges covered

( +.20 % on Subtotal-A )

0.43

Subtotal-A1: Subtotal-B: Subtotal-C:

216.73 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

221.07

10% Profit ( Add 10% on Subtotal-B) :

243.17

VAT

6% of Total

IT

4% of Total

16.21 10.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

270.19

Page: 2087 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.10.09

2 50mmx20mm saddle

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 50mmx20mm saddle

1.0000

each

173.00

173.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 191.30

Subtotal-A: All other materials and charges covered

( +.20 % on Subtotal-A )

0.38

Subtotal-A1: Subtotal-B: Subtotal-C:

191.68 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

195.52

10% Profit ( Add 10% on Subtotal-B) :

215.07

VAT

6% of Total

IT

4% of Total

14.34 9.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

238.96

Page: 2088 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.10.10

2 50mm dia end cap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50mm dia end cap

1.0000

each

74.00

74.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 92.30

Subtotal-A: All other materials and charges covered

( +.20 % on Subtotal-A )

0.18

Subtotal-A1: Subtotal-B: Subtotal-C:

92.48 94.33

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

103.77

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6.92 4.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

115.30

Page: 2089 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.10.11

2 25mm dia end cap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 25mm dia end cap

1.0000

each

64.00

64.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80

Welder

0.0100

day

680.00

6.80

Welder Helper

0.0100

day

470.00

4.70 82.30

Subtotal-A: All other materials and charges covered

( +.20 % on Subtotal-A )

0.16

Subtotal-A1: Subtotal-B: Subtotal-C:

82.46 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84.11

10% Profit ( Add 10% on Subtotal-B) :

92.53

VAT

6% of Total

IT

4% of Total

6.17 4.11 Total:

7.09.11

102.81

Supplying, welding, fitting and fixing of different size Valve Tee/Service Tee to connect the pipe line with the Titas Gas main gas pipe line etc. as per specification of Titas Gas T and D co. ltd. all complete in all respects as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2090 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.11.01

2 50mmx50mm Valve Tee

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50mmx50mm Valve Tee

1.0000

each

14000.00

14000.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Welder

1.0000

day

680.00

680.00

Welder Helper

1.0000

day

470.00

470.00 15830.00

Subtotal-A: All other materials and charges covered

( +5.00 % on Subtotal-A )

791.50

Subtotal-A1: Subtotal-B: Subtotal-C:

16621.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16953.93

10% Profit ( Add 10% on Subtotal-B) :

18649.32

VAT

6% of Total

IT

4% of Total

1243.29 828.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

20721.47

Page: 2091 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.11.02

2 50mmx25mm Valve Tee

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50mmx25mm Valve Tee

1.0000

each

1200.00

1200.00

Plumber/ Electric Mistry/ Painter

0.6000

day

680.00

408.00

Welder

0.6000

day

680.00

408.00

Welder Helper

0.6000

day

470.00

282.00 2298.00

Subtotal-A: All other materials and charges covered

( +3.00 % on Subtotal-A )

68.94

Subtotal-A1: Subtotal-B: Subtotal-C:

2366.94 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2414.28

10% Profit ( Add 10% on Subtotal-B) :

2655.71

VAT

6% of Total

IT

4% of Total

177.05 118.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2950.79

Page: 2092 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.11.03

2 50mmx25mm service Tee

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50mmx25mm service Tee

1.0000

each

2800.00

2800.00

Plumber/ Electric Mistry/ Painter

0.6000

day

680.00

408.00

Welder

0.6000

day

680.00

408.00

Welder Helper

0.6000

day

470.00

282.00 3898.00

Subtotal-A: All other materials and charges covered

( +3.00 % on Subtotal-A )

116.94

Subtotal-A1: Subtotal-B: Subtotal-C:

4014.94 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4095.24

10% Profit ( Add 10% on Subtotal-B) :

4504.76

VAT

6% of Total

IT

4% of Total

300.32 200.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5005.29

Page: 2093 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.09.11.04

2 25mmx25mm service Tee

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 25mmx25mm service Tee

1.0000

each

1500.00

1500.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Welder

0.5000

day

680.00

340.00

Welder Helper

0.5000

day

470.00

235.00 2415.00

Subtotal-A: All other materials and charges covered

( +3.00 % on Subtotal-A )

72.45

Subtotal-A1: Subtotal-B: Subtotal-C:

2487.45 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2537.20

10% Profit ( Add 10% on Subtotal-B) :

2790.92

VAT

6% of Total

IT

4% of Total

186.06 124.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3101.02

Page: 2094 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.09.12

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of Gas burner (double burner) of standard size made with Stainless steel sheet with all other accessories as connection pipe, Key, burner and all other facilities of approved best quality etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Gas Burner (Double)

1.0000

each

3500.00

3500.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00 3568.00

Subtotal-A: All other materials covered as connection pipe, key, burner etc all charges and materials

( +5.00 % on Subtotal-A )

178.40

Subtotal-A1:

3746.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3821.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4203.46

VAT

6% of Total

280.23

IT

4% of Total

186.82 Total:

7.10.01

4670.51

Supply and installation of food-grade plastic internal mini water tank for the use in kitchen, bathroom and toilet for emergency storage and supply of water manufactured from liner low density polyethylene (ILDPE) roto-grade (ultra violet) stabilized which complies FDA (Federal Department of Agriculture, USA) regulations 21 CFR 1277. 152, having food grade quality where no recycled material is used carrying, lifting, fitting, fixing in position including supply of necessary hardware, consumables, fittings etc. all complete in all respects as per direction of the E-I-C..

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2095 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.10.01.01

2 150 liter capacity

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 liter plastic water tank

1.0000

each

1853.00

1853.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Skilled Labour

1.0000

day

450.00

450.00 2983.00

Subtotal-A: All other remaining costs covering 20mm dia ball cock, 20mm dia pipe with jam-nuts, teflon tape, fitting, fixing etc

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3281.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3346.93

10% Profit ( Add 10% on Subtotal-B) :

3681.62

VAT

6% of Total

IT

4% of Total

245.44 163.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

298.30

4090.69

Page: 2096 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.10.01.02

2 300 liter capacity

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 300 liter plastic water tank

1.0000

each

3610.00

3610.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Skilled Labour

1.0000

day

450.00

450.00 4740.00

Subtotal-A: All other remaining costs covering 20mm dia ball cock, 20mm dia pipe with jam-nuts, teflon tape, fitting, fixing etc

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

5214.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5318.28

10% Profit ( Add 10% on Subtotal-B) :

5850.11

VAT

6% of Total

IT

4% of Total

390.01 260.00 Total:

7.10.02

474.00

6500.12

Supplying, fitting and fixing plastic overhead Water Tank of different capacity.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2097 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.02.01

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing plastic overhead Water Tank of 500 litres capacity made with 25mm thick plastic composed sheet with plastic cover on top with locking arrangements, providing inlet and outlet pipe with flanges and plug, jum nuts, 40mm dia ball cock, 12mm dia 1.12m long overflow pipe and with all other necessary fittings etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Overhead water tank made with plastic (Gazi,Padma, etc)

500.0000

litre

8.40

4200.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 5425.00

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

162.75

Subtotal-A1:

5587.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5699.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6269.46

VAT

6% of Total

IT

4% of Total

417.96 278.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6966.06

Page: 2098 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.02.02

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing plastic overhead Water Tank of 1000 litres capacity made with 25mm thick plastic composed sheet with plastic cover on top with locking arrangements, providing inlet and outlet pipe with flanges and plug, jum nuts, 40mm dia ball cock, 12mm dia 1.12m long overflow pipe and with all other necessary fittings etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Overhead water tank made with plastic (Gazi,Padma, etc)

1000.0000

litre

8.40

8400.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 9625.00

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

288.75

Subtotal-A1:

9913.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10112.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11123.23

VAT

6% of Total

IT

4% of Total

741.55 494.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12359.14

Page: 2099 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.02.03

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing plastic overhead Water Tank of 1500 litres capacity made with 25mm thick plastic composed sheet with plastic cover on top with locking arrangements, providing inlet and outlet pipe with flanges and plug, jum nuts, 40mm dia ball cock, 12mm dia 1.12m long overflow pipe and with all other necessary fittings etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Overhead water tank made with plastic (Gazi,Padma, etc)

1500.0000

litre

8.40

12600.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 13825.00

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

414.75

Subtotal-A1:

14239.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14524.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15977.00

VAT

6% of Total

IT

4% of Total

1065.13 710.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17752.22

Page: 2100 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.02.04

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing plastic overhead Water Tank of 2000 litres capacity made with 25mm thick plastic composed sheet with plastic cover on top with locking arrangements, providing inlet and outlet pipe with flanges and plug, jum nuts, 40mm dia ball cock, 12mm dia 1.12m long overflow pipe and with all other necessary fittings etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Overhead water tank made with plastic (Gazi,Padma, etc)

2000.0000

litre

8.40

16800.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 18025.00

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

540.75

Subtotal-A1:

18565.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18937.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20830.77

VAT

6% of Total

IT

4% of Total

1388.72 925.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23145.30

Page: 2101 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.02.05

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing plastic overhead Water Tank of 2500 litres capacity made with 25mm thick plastic composed sheet with plastic cover on top with locking arrangements, providing inlet and outlet pipe with flanges and plug, jum nuts, 40mm dia ball cock, 12mm dia 1.12m long overflow pipe and with all other necessary fittings etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Overhead water tank made with plastic (Gazi,Padma, etc)

2500.0000

litre

8.40

21000.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 22225.00

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

666.75

Subtotal-A1:

22891.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23349.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25684.54

VAT

6% of Total

IT

4% of Total

1712.30 1141.54 Total:

7.10.03

28538.38

Supplying, fitting and fixing overhead Water Tank of different type.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2102 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.03.01

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing overhead Water Tank of 1800 litres capacity (Size : 1200mmx1200mmx1200mm) made with 16 gauge GI sheet including painting the tank with anticorrosive paint of approved colour and quality, providing GI cover on top with locking arrangements, providing inlet and outlet pipe with flanges and plug, jum nuts, 40mm dia ball cock, 12mm dia 1.12m long overflow pipe and with all other necessary fittings etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Overhead water tank made with 16 gauge GI sheet (1200x1200x1200mm)

1.0000

each

8640.00

8640.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00

Painting to door and window frames and shutters in two coats with synthetic enamel paint…(3.12.5.1)

8.9300

sqm

99.43

887.87 10752.87

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

322.59

Subtotal-A1: Subtotal-B: Subtotal-C:

11075.46 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11296.97

10% Profit ( Add 10% on Subtotal-B) :

12426.66

VAT

6% of Total

IT

4% of Total

828.44 552.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13807.40

Page: 2103 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.03.02

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of 1800 litres capacity fibre glass spherical type water tank made of Johannes or other approved company as per specifications and drawings, painting the tank of approved colour and quality if necessary, providing cover (made of same material) on top with locking arrangements, providing inlet and outlet pipe with flanges and plug, jum nuts, 40mm dia ball cock, 12mm dia 1.12m long overflow pipe and with all other necessary fittings etc. all complete in all respects as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Fiber glass spherical type water tank (1800 liters capacity)

1.0000

each

13262.40

13262.40

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 14487.40

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

434.62

Subtotal-A1:

14922.02

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15220.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16742.51

VAT

6% of Total

IT

4% of Total

1116.17 744.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18602.79

Page: 2104 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.03.03

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of 500 litres capacity best quality cylindrical type stainless steel overhead water tank made of 0.50mm thick special brand SUS304# stainless steel including top cover with handle, cap with locking arrangement, inlet and outlet coupling, plastic ventilation system, stainless steel stand with anchoring arrangement with bolts and nuts and with all other necessary fixings etc. all complete and as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

0.5mm thick stainless steel cylindrical type water tank (500 liters capacity)

1.0000

each

7614.00

7614.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 8839.00

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

265.17

Subtotal-A1:

9104.17

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9286.25 10214.88 680.99 453.99

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11349.87

Page: 2105 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.03.04

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of 1500 litres capacity best quality cylindrical type stainless steel overhead water tank made of 0.60mm thick special brand SUS304# stainless steel including top cover with handle, cap with locking arrangement, inlet and outlet coupling, plastic ventilation system, stainless steel stand with anchoring arrangement with bolts and nuts and with all other necessary fixings etc. all complete and as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

0.6mm thick stainless steel cylindrical type water tank (1500 litres capacity)

1.0000

each

21060.00

21060.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 22285.00

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

668.55

Subtotal-A1:

22953.55

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23412.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25753.88

VAT

6% of Total

IT

4% of Total

1716.93 1144.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

28615.43

Page: 2106 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.10.03.05

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of 2000 litres capacity best quality cylindrical type stainless steel overhead water tank made of 0.70mm thick special brand SUS304# stainless steel including top cover with handle, cap with locking arrangement, inlet and outlet coupling, plastic ventilation system, stainless steel stand with anchoring arrangement with bolts and nuts and with all other necessary fixings etc. all complete and as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

0.7mm thick stainless steel cylindrical type water tank (2000 liters capacity)

1.0000

each

27540.00

27540.00

12mm dia ball cock

1.0000

each

160.00

160.00

Plumber/ Electric Mistry/ Painter

0.7500

day

680.00

510.00

Ordinary Labour

1.5000

day

370.00

555.00 28765.00

Subtotal-A: All other remaining costs like overflow pipe, small fittings, etc.

( +3.00 % on Subtotal-A )

862.95

Subtotal-A1:

29627.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30220.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33242.56

VAT

6% of Total

IT

4% of Total

2216.17 1477.45 Total:

7.11.01

36936.18

Construction of masonry inspection pit with 250 mm thick brick work in cement mortar (1:4) including necessary earth work side filling and one layer brick flat soling, 75 mm thick (1:3:6) base concrete for making invert channel and 12 mm thick (1:2) cement plaster with neat finishing up to a depth of 700 mm etc. all complete and as per direction of the EI-C (minimum sand F.M. 1.2).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2107 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.01.01

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Clear 450x450 mm and depth 600 to 675 mm average 525 mm for single 150 mm dia R.C.C pipes and 400 mm PVC pipe

each

Quantity 5

Unit

Rate

6

7

Amount 8

Mass concrete in foundation (1:3:6) with cement, sand and brick chips ……….. (3.11.01)

0.0820

cum

5707.82

468.04

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

0.9330

sqm

308.04

287.40

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

1.1850

sqm

214.86

254.61

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

0.3840

cum

5575.24

2140.89

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.7060

cum

75.80

53.51 3204.46

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3268.55

10% Profit ( Add 10% on Subtotal-B) :

3595.41

VAT

6% of Total

IT

4% of Total

239.69 159.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3994.90

Page: 2108 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.01.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Clear 520x525 mm and depth 675 to 825 mm average 750 mm for single 225 mm dia R.C.C pipes and 400 mm PVC pipe

each

Quantity 5

Unit

Rate

Amount

6

7

8

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

1.9110

sqm

214.86

410.60

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

1.0870

sqm

308.04

334.84

Mass concrete in foundation (1:3:6) with cement, sand and brick chips ……….. (3.11.01)

0.0970

cum

5707.82

553.66

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

1.0890

cum

75.80

82.55

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

0.6080

cum

5575.24

3389.75 4771.39

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4866.82

10% Profit ( Add 10% on Subtotal-B) :

5353.50

VAT

6% of Total

IT

4% of Total

356.90 237.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5948.34

Page: 2109 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.01.03

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Clear 600x600 mm and depth 750 to 900 mm average 825 mm for single 300 mm dia R.C.C pipes and 375 mm and 400 mm PVC pipe

each

Quantity 5

Unit

Rate

Amount

6

7

8

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

2.6250

sqm

214.86

564.02

Mass concrete in foundation (1:3:6) with cement, sand and brick chips ……….. (3.11.01)

0.1140

cum

5707.82

650.69

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

1.4140

cum

75.80

107.18

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

0.8830

cum

5575.24

4922.94

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

1.2520

sqm

308.04

385.67 6630.49

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6763.10

10% Profit ( Add 10% on Subtotal-B) :

7439.41

VAT

6% of Total

IT

4% of Total

495.96 330.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8266.01

Page: 2110 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.01.04

Detailed Analysis Brief Description of Item 2 Master-pit of Size: Clear 600x500 mm and average 750 mm depth for Septic tank.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

0.8530

sqm

308.04

262.76

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

0.3580

cum

5575.24

1995.94

Mass concrete in foundation (1:3:6) with cement, sand and brick chips ……….. (3.11.01)

0.0620

cum

5707.82

353.88

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

2.2300

sqm

214.86

479.14

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.7920

cum

75.80

60.03

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (5.06.01.1)

4.2000

kg

61.59

258.68 3410.43

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3478.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3826.51

VAT

6% of Total

IT

4% of Total

255.10 170.07 Total:

7.11.02

4251.68

Construction and placing of R.C.C inspection pit cover (100 mm thick RCC slab) in (1:2:4) (of item no-5.05.01.01) with 1% reinforcement (of item no-5.06.01.01) excluding M.H cover with locking/ unlocking arrangement including necessary earth work, side filling, shuttering, curing, cement plaster (1:4) (of item no-5.12.01) with neat finishing on edges and top etc. all complete and as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2111 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.02.01

Detailed Analysis Brief Description of Item 2 900 x 900 x 75 mm R.C.C pit cover

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0710

cum

7643.67

542.70

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

1.2290

sqm

214.86

264.07

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (5.06.01.1)

5.5790

kg

61.59

343.61 1150.38

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1173.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1290.72

VAT

6% of Total

86.05

IT

4% of Total

57.37 Total:

7.11.02.02

1025 x 1025 x 75 mm R.C.C pit cover

each 12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

1.4050

sqm

214.86

301.88

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (5.06.01.1)

6.4910

kg

61.59

399.78

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0830

cum

7643.67

634.42 1336.09

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1362.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1499.09

VAT

6% of Total

99.94

IT

4% of Total

66.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1434.14

1665.66

Page: 2112 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.02.03

Detailed Analysis Brief Description of Item 2 1100 x 1100 x 75 mm R.C.C pit cover

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0950

cum

7643.67

726.15

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

1.5930

sqm

214.86

342.28

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (5.06.01.1)

7.4890

kg

61.59

461.25 1529.67

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1560.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1716.29

VAT

6% of Total

114.42

IT

4% of Total

76.28 Total:

7.11.03

1906.99

Construction and placing of R.C.C inspection pit cover (100 mm thick RCC slab) with supplying and provisions for placing, fitting, fixing 450 mm dia C.I Man-hole cover with locking/ unlocking arrangement including concrete (1:2:4)(of item no-5.05.01.01) with approx. 1% reinforcement (of item no-5.05.01.01) necessary earth cutting, or cleaning side filling, curing, etc. with minimum 12 mm cement plaster (1:4)(of item no-5.05.01.01) and neat cement finishing on edges and top etc. all complete and as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2113 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.03.01

Detailed Analysis Brief Description of Item 2 950 x 950 x 75 mm R.C.C pit cover with 450 mm dia C.I manhole cover.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

1.2290

sqm

214.86

264.07

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0590

cum

7643.67

450.98

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (5.06.01.1)

4.6000

kg

61.59

283.31

450mm dia CI Manhole cover

1.0000

each

1040.00

1040.00 2038.36

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2079.12

10% Profit ( Add 10% on Subtotal-B) :

2287.04

VAT

6% of Total

IT

4% of Total

152.47 101.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2541.15

Page: 2114 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.03.02

Detailed Analysis Brief Description of Item 2 1025 x 1025 x 75 mm R.C.C pit cover with 450 mm dia C.I manhole cover.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0700

cum

7643.67

535.06

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

1.2410

sqm

214.86

266.64

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (5.06.01.1)

5.5110

kg

61.59

339.42

450mm dia CI Manhole cover

1.0000

each

1040.00

1040.00 2181.12

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2224.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2447.22

VAT

6% of Total

163.15

IT

4% of Total

108.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2719.14

Page: 2115 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.03.03

Detailed Analysis Brief Description of Item 2 1100 x 1100 x 75 mm R.C.C pit cover with 450 mm dia C.I manhole cover.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0830

cum

7643.67

634.42

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (5.06.01.1)

6.5140

kg

61.59

401.20

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

1.4280

sqm

214.86

306.82

450mm dia CI Manhole cover

1.0000

each

1040.00

1040.00 2382.45

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2430.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2673.10

VAT

6% of Total

178.21

IT

4% of Total

118.80 Total:

7.11.04

2970.12

Construction of Septic Tank with brick masonry works in main and partition walls in cement mortar (1:6) as per standard drawing enumerated in Appendix-6 (Typical soak well design) over a single layer brick flat soling and 150mm thick cement concrete flooring (1:2:4), in/c 20mm thick cement plaster (1:4) to inside of walls with neat cement finishing, 25mm thick patent stone (1:2:4) flooring with neat cement finishing including supplying fitting and fixing of two RCC Tees and providing 450mm dia water sealed heavy type C.I. M.H. cover with necessary locking arrangements, 100mm thick RCC (1:2:4) top slab & 125mm thick RCC (1:2:4) wall around inside of the main wall of septic tank with minimum 1% reinforcement including centering, shuttering, fabricating, casting, curing etc. complete up to required depth. The item is inclusive of necessary earth work in excavation and shoring, bailing out water and side filling including the cost of all materials, operations and incidental charges etc. all complete as per the approved plan and direction of the EI-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2116 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.04.01

Detailed Analysis Brief Description of Item 2 For 200 users with 3 manhole covers.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

55.0000

cum

75.80

4169.00

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

25.0000

sqm

308.04

7701.00

4.0000

cum

6799.07

27196.26

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

16.0000

cum

5575.24

89203.84

125mm brick work with 1st class bricks in cement mortar (1:6) for Ground floor….(5.04.09.01)

8.0000

sqm

816.73

6533.86

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

52.0000

sqm

214.86

11172.88

25mm thick artificial patent stone floor with 10mm down graded stone chips (1:2:4)…..(5.13.03)

12.0000

sqm

312.17

3746.05

1.7000

cum

7643.67

12994.24

kg

61.59

8253.06

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01) M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

134.0000

450mm dia water sealed heavy type CI manhole cover with locking arrangement

3.0000

each

750.00

2250.00

RCC Tees (150mm)

2.0000

each

125.00

250.00 173470.20

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

176939.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

194633.56

VAT

6% of Total

12975.57

IT

4% of Total

8650.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

216259.51

Page: 2117 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.04.02

Detailed Analysis Brief Description of Item 2 For 100 users with 3 manhole covers.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

35.0000

cum

75.80

2653.00

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

16.0000

sqm

308.04

4928.64

2.5000

cum

6799.07

16997.67

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

12.0000

cum

5575.24

66902.88

125mm brick work with 1st class bricks in cement mortar (1:6) for Ground floor….(5.04.09.01)

5.0000

sqm

816.73

4083.66

37.0000

sqm

214.86

7949.93

25mm thick artificial patent stone floor with 10mm down graded stone chips (1:2:4)…..(5.13.03)

6.0000

sqm

312.17

1873.03

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

1.0000

cum

7643.67

7643.67

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

80.0000

kg

61.59

4927.20

450mm dia water sealed heavy type CI manhole cover with locking arrangement

3.0000

each

750.00

2250.00

RCC Tees (150mm)

2.0000

each

125.00

250.00

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

120459.68

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

122868.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

135155.76

VAT

6% of Total

9010.38

IT

4% of Total

6006.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

150173.06

Page: 2118 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.04.03

Detailed Analysis Brief Description of Item 2 For 50 users with 3 manhole covers.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

21.1600

cum

75.80

1603.93

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

11.7600

sqm

308.04

3622.55

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

1.7900

cum

6799.07

12170.33

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

7.9200

cum

5575.24

44155.90

125mm brick work with 1st class bricks in cement mortar (1:6) for Ground floor….(5.04.09.01)

4.7200

sqm

816.73

3854.98

25.7400

sqm

214.86

5530.57

25mm thick artificial patent stone floor with 10mm down graded stone chips (1:2:4)…..(5.13.03)

3.9400

sqm

312.17

1229.95

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.6900

cum

7643.67

5274.13

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

54.7500

kg

61.59

3372.05

450mm dia water sealed heavy type CI manhole cover with locking arrangement

3.0000

each

750.00

2250.00

RCC Tees (150mm)

2.0000

each

125.00

250.00

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

83314.40

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84980.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

93478.75

VAT

6% of Total

6231.92

IT

4% of Total

4154.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

103865.28

Page: 2119 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.04.04

Detailed Analysis Brief Description of Item 2 For 30 users with 2 manhole covers.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

17.2400

cum

75.80

1306.79

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

7.5500

sqm

308.04

2325.70

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

1.1500

cum

6799.07

7818.93

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

5.8100

cum

5575.24

32392.14

125mm brick work with 1st class bricks in cement mortar (1:6) for Ground floor….(5.04.09.01)

1.1200

sqm

816.73

914.74

14.0400

sqm

214.86

3016.68

25mm thick artificial patent stone floor with 10mm down graded stone chips (1:2:4)…..(5.13.03)

1.6000

sqm

312.17

499.47

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.3700

cum

7643.67

2828.16

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

29.0000

kg

61.59

1786.11

450mm dia water sealed heavy type CI manhole cover with locking arrangement

2.0000

each

750.00

1500.00

RCC Tees (150mm)

2.0000

each

125.00

250.00

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

54638.72

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55731.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

61304.65

VAT

6% of Total

4086.98

IT

4% of Total

2724.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

68116.28

Page: 2120 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.04.05

Detailed Analysis Brief Description of Item 2 For 20 users with 2 manhole covers.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

16.0000

cum

75.80

1212.80

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

7.0000

sqm

308.04

2156.28

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

1.0000

cum

6799.07

6799.07

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

5.4000

cum

5575.24

30106.30

125mm brick work with 1st class bricks in cement mortar (1:6) for Ground floor….(5.04.09.01)

1.0000

sqm

816.73

816.73

12.0000

sqm

214.86

2578.36

25mm thick artificial patent stone floor with 10mm down graded brick chips (1:2:4)…..(5.13.01)

1.4000

sqm

282.94

396.11

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.3400

cum

7643.67

2598.85

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

26.0000

kg

61.59

1601.34

450mm dia water sealed heavy type CI manhole cover with locking arrangement

2.0000

each

750.00

1500.00

RCC Tees (150mm)

2.0000

each

125.00

250.00

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

50015.83

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

51016.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

56117.76

VAT

6% of Total

3741.18

IT

4% of Total

2494.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

62353.07

Page: 2121 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.04.06

Detailed Analysis Brief Description of Item 2 For 10 users with 2 manhole covers.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

6.5000

cum

75.80

492.70

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

3.5600

sqm

308.04

1096.62

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.5400

cum

6799.07

3671.50

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

1.9400

cum

5575.24

10815.97

125mm brick work with 1st class bricks in cement mortar (1:6) for Ground floor….(5.04.09.01)

0.5800

sqm

816.73

473.70

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

8.2500

sqm

214.86

1772.62

25mm thick artificial patent stone floor with 10mm down graded stone chips (1:2:4)…..(5.13.03)

1.0400

sqm

312.17

324.66

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.2700

cum

7643.67

2063.79

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

20.6300

kg

61.59

1270.60

450mm dia water sealed heavy type CI manhole cover with locking arrangement

2.0000

each

750.00

1500.00

RCC Tees (150mm)

2.0000

each

125.00

250.00 23732.16

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24206.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26627.48

VAT

6% of Total

1775.17

IT

4% of Total

1183.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

29586.09

Page: 2122 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.05

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Construction of soak well with 250mm thick solid brick work (1:6) and 250mm honey comb brick work (1:6) as per design over RCC (1:2:4) well curb with 1.5% reinforcement upto the depth as per drawing with 100mm dia water sealed heavy type C.I. manhole cover with all locking arrangements, filling the well upto the required depth with graded khoa and sand including supplying and fabricating MS Rod, casting, curing etc. The item is inclusive of necessary earth work in excavation, side filling and bailing out water etc. all complete as per drawing, design and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2123 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.05.01

Detailed Analysis Brief Description of Item 2 For 200 users (Internal dia 1800mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

22.5100

cum

75.80

1706.26

Brick work with 10 holes machine made bricks for ground floor….(5.04.06.01)

3.2300

cum

10240.59

33077.11

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

3.3300

cum

5575.24

18565.55

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.4200

cum

7643.67

3210.34

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.3300

cum

7643.67

2522.41

Providing compacted aggregate sand sub-base course with 38mm down chips……… (3.03.3.1)

8.3500

cum

2435.85

20339.35

78.0000

kg

61.59

4804.02

1.0000

each

750.00

750.00

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1) 450mm dia water sealed heavy type CI manhole cover with locking arrangement

84975.04

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

86674.54

10% Profit ( Add 10% on Subtotal-B) :

95342.00

VAT

6% of Total

IT

4% of Total

6356.13 4237.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

105935.55

Page: 2124 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.05.02

Detailed Analysis Brief Description of Item 2 For 100 users (Internal dia 1500mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

19.7800

cum

75.80

1499.32

Brick work with 10 holes machine made bricks for ground floor….(5.04.06.01)

2.9500

cum

10240.59

30209.75

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

3.0500

cum

5575.24

17004.48

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.3800

cum

7643.67

2904.60

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.2800

cum

7643.67

2140.23

Providing compacted aggregate sand sub-base course with 38mm down chips……… (3.03.3.1)

7.1300

cum

2435.85

17367.61

67.0000

kg

61.59

4126.53

1.0000

each

750.00

750.00

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1) 450mm dia water sealed heavy type CI manhole cover with locking arrangement

76002.52

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

77522.57

10% Profit ( Add 10% on Subtotal-B) :

85274.82

VAT

6% of Total

IT

4% of Total

5684.99 3789.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

94749.80

Page: 2125 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.05.03

Detailed Analysis Brief Description of Item 2 For 50 users (Internal dia 1200mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

17.2000

cum

75.80

1303.76

Brick work with 10 holes machine made bricks for ground floor….(5.04.06.01)

2.6700

cum

10240.59

27342.38

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

2.7600

cum

5575.24

15387.66

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.3500

cum

7643.67

2675.29

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.2400

cum

7643.67

1834.48

Providing compacted aggregate sand sub-base course with 38mm down chips……… (3.03.3.1)

5.3300

cum

2435.85

12983.08

59.0000

kg

61.59

3633.81

1.0000

each

750.00

750.00

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1) 450mm dia water sealed heavy type CI manhole cover with locking arrangement

65910.46

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

67228.67

10% Profit ( Add 10% on Subtotal-B) :

73951.54

VAT

6% of Total

IT

4% of Total

4930.10 3286.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

82168.37

Page: 2126 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.05.04

Detailed Analysis Brief Description of Item 2 For 30 users (Internal dia 1050mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

14.8600

cum

75.80

1126.39

Brick work with 10 holes machine made bricks for ground floor….(5.04.06.01)

2.4000

cum

10240.59

24577.42

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

2.4700

cum

5575.24

13770.84

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.3100

cum

7643.67

2369.54

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.2000

cum

7643.67

1528.73

Providing compacted aggregate sand sub-base course with 38mm down chips……… (3.03.3.1)

4.0800

cum

2435.85

9938.27

52.0000

kg

61.59

3202.68

1.0000

each

750.00

750.00

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1) 450mm dia water sealed heavy type CI manhole cover with locking arrangement

57263.87

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58409.15

10% Profit ( Add 10% on Subtotal-B) :

64250.07

VAT

6% of Total

IT

4% of Total

4283.34 2855.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

71388.96

Page: 2127 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.05.05

Detailed Analysis Brief Description of Item 2 For 20 users (Internal dia 1050mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

14.8600

cum

75.80

1126.39

Brick work with 10 holes machine made bricks for ground floor….(5.04.06.01)

2.4000

cum

10240.59

24577.42

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

2.4700

cum

5575.24

13770.84

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.3100

cum

7643.67

2369.54

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.2000

cum

7643.67

1528.73

Providing compacted aggregate sand sub-base course with 38mm down chips……… (3.03.3.1)

4.0800

cum

2435.85

9938.27

52.0000

kg

61.59

3202.68

1.0000

each

750.00

750.00

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1) 450mm dia water sealed heavy type CI manhole cover with locking arrangement

57263.87

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58409.15

10% Profit ( Add 10% on Subtotal-B) :

64250.07

VAT

6% of Total

IT

4% of Total

4283.34 2855.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

71388.96

Page: 2128 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.05.06

Detailed Analysis Brief Description of Item 2 For 10 users (Internal dia 900mm)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

10.6400

cum

75.80

806.51

Brick work with 10 holes machine made bricks for ground floor….(5.04.06.01)

1.8400

cum

10240.59

18842.69

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

1.9000

cum

5575.24

10592.96

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.2400

cum

7643.67

1834.48

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.1300

cum

7643.67

993.68

Providing compacted aggregate sand sub-base course with 38mm down chips……… (3.03.3.1)

2.0800

cum

2435.85

5066.57

38.0000

kg

61.59

2340.42

1.0000

each

750.00

750.00

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1) 450mm dia water sealed heavy type CI manhole cover with locking arrangement

41227.30

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

42051.85

10% Profit ( Add 10% on Subtotal-B) :

46257.04

VAT

6% of Total

IT

4% of Total

3083.80 2055.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

51396.71

Page: 2129 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.11.06

Detailed Analysis Brief Description of Item 2 Construction of soak or leaching pit including supplying and fitting of 760mm dia 38mm thick 305mm height RCC (1:2:4) ring with 3 layers of No. 10 BWG wire as reinforcement placing in position one above another at equal spacing, placing in position, filling interstices with local sand, placing pit, jointing with 1:6 sand-cement mortar, making hole to RCC ring for inlet pipe and vent pipe including all fittings and jointing including labour, site cleaning, all complete as per drawing and direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

per ring

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0300

cum

M.S. Ribbed bar of steel grade RB 300 with minimum fy=300 Mpa ………. (3.11.05.1)

0.6100

kg

7643.67

229.31

61.59

37.57 266.88

Subtotal-A: All other remaining costs

( +2.50 % on Subtotal-A )

6.67

Subtotal-A1:

273.55

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

279.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

306.93

VAT

6% of Total

20.46

IT

4% of Total

13.64 Total:

7.12.01

341.03

Construction of two-in-pit latrine

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2130 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.12.01.01

Detailed Analysis Brief Description of Item 2 Manufacturing and supplying of RCC ring of 40mm wall thickness and1m internal diameter and 0.3m of height including casting, curing for requisite period, fixing in position etc. all complete as per direction of the E-I-C. (The cost is inclusive of reinforcement and its fabrication)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0390

cum

10 BWG wire reinforcement

0.3000

kg

7643.67

298.10

90.00

27.00 325.10

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

331.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

364.77

VAT

6% of Total

IT

4% of Total

24.32 16.21 Total:

7.12.01.02

Manufacturing, supplying, fitting and fixing white porcelain 450mm long pan (BISF standard) with PVC trap fixed properly to make it fully leak proof, etc. all complete as per direction of the E-I-C.

each

450mm long pan (BISF standard) with trap

1.0000

each

421.00

421.00

Skilled Labour

1.5800

day

450.00

711.00 1132.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1154.64

10% Profit ( Add 10% on Subtotal-B) :

1270.10

VAT

6% of Total

IT

4% of Total

84.67 56.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

405.30

1411.23

Page: 2131 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.12.01.03

Detailed Analysis Brief Description of Item 2 Construction of Y-junction pit mortar for twin pit sanitary latrine, with depth 375mm and octagonal in shape with each arm of 150mm in length with 125mm brick work in cement mortar (1:4), 50mm thick RCC (1:2:4) top slab having reinforcement with 10 BWG wire @125mm c/c both way including necessary earth excavation, side filling, one layer of brick flat soling work, side filling and one layer brick flat soling on a 75mm thick CC (1:3:6) base for making invert channel (shape should be from one inlet to two outlet with one CC separator) including 12mm thick Cement Plaster (1:2) with neat cement finishing, casting, curing, reinforcement fabrication etc. all complete as per drawing and direction of the E-I-C. (The item is inclusive of the cost of reinforcement)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.1900

cum

75.80

14.40

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

0.3100

sqm

308.04

95.49

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.0230

cum

6799.07

156.38

Brick work with 1st class bricks in cement mortar (1:4) in foundation and plinth….(5.04.02)

0.4840

cum

5849.80

2831.30

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0180

cum

7643.67

137.59

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

0.4700

sqm

214.86

100.99

10 BWG wire reinforcement

0.2800

kg

90.00

25.20 3361.35

Subtotal-A: All other remaining costs

( +2.50 % on Subtotal-A )

84.03

Subtotal-A1:

3445.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3514.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3865.72

VAT

6% of Total

IT

4% of Total

257.71 171.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4295.24

Page: 2132 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.12.01.04

Detailed Analysis Brief Description of Item 2 Construction of Y-junction pit mortar for twin pit sanitary latrine, with depth 300mm and octagonal in shape with each arm of 150mm in length with 75mm thick CC (1:2:4) wall and 50mm thick CC (1:2:4) base and with 50mm thick RCC (1:2:4) top slab having reinforcement with 10 BWG wire @125mm c/c both way including necessary earth excavation, side filling and one layer brick flat soling on a 75mm thick CC (1:3:6) base for making invert channel (shape should be from one inlet to two outlet with one CC separator) including 12mm thick Cement Plaster (1:2) with neat cement finishing, casting, curing, reinforcement fabrication etc. all complete as per drawing and direction of the E-I-C. (The item is inclusive of the cost of reinforcement)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.1100

cum

75.80

8.34

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.0500

cum

6799.07

339.95

RCC works (1:2:4) with brick chips for continuous footing of column, raft….(5.05.01.01)

0.0110

cum

7643.67

84.08

10 BWG wire reinforcement

0.2000

kg

90.00

18.00 450.37

Subtotal-A: All other remaining costs

( +2.50 % on Subtotal-A )

11.26

Subtotal-A1:

461.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

470.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

517.95

VAT

6% of Total

IT

4% of Total

34.53 23.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

575.50

Page: 2133 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

7.13.01

Bathtub: Supplying, installation and commissioning of foreign made acrylic bathtub consists of hand grips, head rest, slip resistant surface and pop-up waste including fitting and fixing of bathtub by specified nuts & bolts, making holes wherever required with preparing the base using cement concrete with wire mesh or rods (if necessary), mending good the damages etc., including cost of all necessary accessories, their carriages, wages of labour, plumber and incidental charges etc. all complete, as per direction & approval of the Engineer-in-Charge.

7.13.01.01

Size: 1500x750x580 mm, Model: TOTO- PAY1570D/DB501-2DR or PAY 1570DH/DB501-2DR or Equivalent.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreign made bath tub with pop up waste, Size: 1500x750x580 mm, Model: TOTO- PAY1570D/DB501-2DR or PAY 1570DH/DB501-2DR or Equivalent.

1.0000

each

80500.00

80500.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Ordinary Labour

1.0000

day

370.00

370.00 82020.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

83660.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

92026.44

VAT

6% of Total

IT

4% of Total

6135.10 4090.06 Total:

7.20

Fire Extinguisher

7.20.01

Dry Chemical Powder Type: Supply & fixing the following capacities multi purpose ABC&E dry chemical powder stored pressure type with manometer system Fire Extinguisher suitable for repeated use complete with wall bracket, Cartridge, easy refilling system etc. as per sample accepted/approved by the Engineer.

Note : Rates of all items should be inclusive of all supply and carriage.

102251.60

Page: 2134 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.20.01.01

Detailed Analysis Brief Description of Item 2 1 kg.Dry Chemical Powder type Fire Extinguisher

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 1 kg. DCP type Fire Extinguisher

1.0000

each

1038.00

1038.00

Skilled Labour

0.2500

day

450.00

112.50 1150.50

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

46.02

Subtotal-A1: Subtotal-B: Subtotal-C:

1196.52 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1220.45

10% Profit ( Add 10% on Subtotal-B) :

1342.50

VAT

6% of Total

IT

4% of Total

89.50 59.67 Total:

7.20.01.02

2 kg.Dry Chemical Powder type Fire Extinguisher

each 2 kg. DCP type Fire Extinguisher

1.0000

each

1484.00

1484.00

Skilled Labour

0.2500

day

450.00

112.50 1596.50

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

63.86

Subtotal-A1:

1660.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1693.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1862.92

VAT

6% of Total

IT

4% of Total

124.19 82.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1491.66

2069.92

Page: 2135 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.20.01.03

Detailed Analysis Brief Description of Item 2 3 kg. Dry Chemical Powder type Fire Extinguisher

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 3 kg. DCP type Fire Extinguisher

1.0000

each

1612.00

1612.00

Skilled Labour

0.2500

day

450.00

112.50 1724.50

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

68.98

Subtotal-A1: Subtotal-B: Subtotal-C:

1793.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1829.35

10% Profit ( Add 10% on Subtotal-B) :

2012.28

VAT

6% of Total

IT

4% of Total

134.15 89.43 Total:

7.20.01.04

5 kg. Dry Chemical Powder type Fire Extinguisher

each 5 kg. DCP type Fire Extinguisher

1.0000

each

2473.00

2473.00

Skilled Labour

0.2500

day

450.00

112.50 2585.50

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

103.42

Subtotal-A1:

2688.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2742.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3016.97

VAT

6% of Total

IT

4% of Total

201.13 134.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2235.87

3352.19

Page: 2136 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.20.01.05

Detailed Analysis Brief Description of Item 2 6 kg. Dry Chemical Powder type Fire Extinguisher

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 6 kg. DCP type Fire Extinguisher

1.0000

each

2968.00

2968.00

Skilled Labour

0.2500

day

450.00

112.50 3080.50

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

123.22

Subtotal-A1: Subtotal-B: Subtotal-C:

3203.72 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3267.79

10% Profit ( Add 10% on Subtotal-B) :

3594.57

VAT

6% of Total

IT

4% of Total

239.64 159.76 Total:

7.20.02

3993.97

Carbon-Di-Oxide Type: Supply & fixing the following capacities Carbon-di-Oxide type Fire Extinguisher suitable for repeated use complete with wall bracket, discharge nozzle etc. as per sample accepted/approved by the Engineer.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2137 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.20.02.01

Detailed Analysis Brief Description of Item 2 3 kg. Carbon-di-Oxide type Fire Extinguisher

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 3 kg. CO2 type Fire Extinguisher

1.0000

each

3661.00

3661.00

Skilled Labour

0.2500

day

450.00

112.50 3773.50

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

150.94

Subtotal-A1: Subtotal-B: Subtotal-C:

3924.44 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4002.93

10% Profit ( Add 10% on Subtotal-B) :

4403.22

VAT

6% of Total

IT

4% of Total

293.55 195.70 Total:

7.20.02.02

5 kg. Carbon-di-Oxide type Fire Extinguisher

each 5 kg. CO2 type Fire Extinguisher

1.0000

each

6154.00

6154.00

Skilled Labour

0.2500

day

450.00

112.50 6266.50

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

250.66

Subtotal-A1:

6517.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6647.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7312.25

VAT

6% of Total

IT

4% of Total

487.48 324.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4892.47

8124.73

Page: 2138 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

7.20.03

Accessories of Dry Chemical Powder Type & Carbon-Di-Oxide Type Fire Extinguishers: Providing & fixing the following parts of fire extinguisher as per sample accepted/approved by the Engineer.

7.20.03.01

Trigger

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Trigger

1.0000

each

123.00

123.00

Skilled Labour

0.1000

day

450.00

45.00 168.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

6.72

Subtotal-A1: Subtotal-B: Subtotal-C:

174.72 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

178.21

10% Profit ( Add 10% on Subtotal-B) :

196.04

VAT

6% of Total

13.07

IT

4% of Total

8.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

217.82

Page: 2139 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.20.03.02

2 Hose pipe

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Hose pipe for Fire Extinguisher

1.0000

each

247.00

247.00

Skilled Labour

0.1000

day

450.00

45.00 292.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

11.68

Subtotal-A1: Subtotal-B: Subtotal-C:

303.68 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

309.75

10% Profit ( Add 10% on Subtotal-B) :

340.73

VAT

6% of Total

IT

4% of Total

22.72 15.14 Total:

7.20.03.03

Nipple with nozzle

each Nipple with Nozzle

1.0000

each

98.00

98.00

Skilled Labour

0.1000

day

450.00

45.00 143.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

5.72

Subtotal-A1:

148.72

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

151.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

166.86

VAT

6% of Total

IT

4% of Total

11.12 7.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

378.59

185.40

Page: 2140 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.20.03.04

2 Cartridge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Cartridge up to 6 kg.

1.0000

each

888.00

888.00

Skilled Labour

0.1000

day

450.00

45.00 933.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

37.32

Subtotal-A1: Subtotal-B: Subtotal-C:

970.32 989.73

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1088.70

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

72.58 48.39 Total:

7.20.03.05

ABC & E powder

kg ABC and E Powder

1.0000

kg

148.00

148.00

Skilled Labour

0.1000

day

450.00

45.00 193.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

7.72

Subtotal-A1:

200.72

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

204.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

225.21

VAT

6% of Total

IT

4% of Total

15.01 10.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1209.67

250.23

Page: 2141 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.20.03.06

2 Carbon-Di-Oxide Recharge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

kg Carbon-Di-Oxide Recharge

1.0000

kg

187.00

187.00

Skilled Labour

0.1000

day

450.00

45.00 232.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

9.28

Subtotal-A1: Subtotal-B: Subtotal-C:

241.28 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

246.11

10% Profit ( Add 10% on Subtotal-B) :

270.72

VAT

6% of Total

IT

4% of Total

18.05 12.03 Total:

7.21

300.80

Hydrant System

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2142 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

FIRE WATER PUMP (Engine Driven): Supply & Installation of Disel Engine Driven Fire Pump complete with all related & essential accessores. The pump shall be designed and installed in accordance with globally accepted international standard. Each unit shall be tested and UL listed/FM approved Type: Pumps shall be of the non-overloading, centrifugal, volute type, horizontally split, double suction type with suction and discharge connections in the lower half of the casing, allowing removal of the rotating element without disturbing the pipe connections and operating at not over 3000 rpm. Pumps shall be selected for a total efficientcy of not less than 65%. Pump performance curves shall be submitted for approval together with the pump technical data. Casing: Casing of horizontally split pumps shall be capable of at least withstanding a hydrostatic test pressure of 150% of pump's shut-off head plus 15 kg/cm². Pump casing shall be cast iron / ductile iron, precision making for best performance and long term duty. Impeller: Impellers shall be cast bronze SAE 40 / relavent NEMA and dynamically balanced, accurately keyed to the shaft and fixed in an axial position by shaft sleeves and separate snap rings. Impeller shall be fully protected against damage from reverse rotation. Shaft : Shaft of pump with stuffing box shall be of stainless steel, chrome iron extending through the stuffing boxes. Shaft shall be designed with high safety precautions to easily withstand the torsional loads with other stresses. Shaft sleeves shall be keyed to the shafts and extend through the stuffing box. "O" ring or gaskets shall be provided at sleeve ends to protect the shafts from water corrosion. And will be designed, no dismantling of the pump casing will be required to replace the sleeves. Bearing: Bearings of the pump shall be heavy duty with anti-friction grease lubricated. The bearing shall be self-sealed and housed in malleable iron housing aligned to a bearing bracket, and shall be removable without desmantling any rotating elements or pumps. Diesel Engine: The diesel engine brake horsepower shall be listed by UL / Approved by FM suitable for rated pump capacity.The engine shall rated at standard conditions for 500 ft above sea level at 29.4°C by the testing laboratory. The engine shall be of a reputed manufacturer from which spare parts can be obtained locally. The engine shall be provided with an adjustable governor capable of regulating engine speed with a range of 10% between shut-off and maximum load conditions of the pump. The governor shall be set to maintain the rated pump speed at

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2143 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

maximum pump load. Battery & Charger : The engine shall be provided with two maintenance free storage battery units, each having sufficeint capacity, at 5°C (41°F) to maintain cranking speed recommendaed by the engine manufacturer through a 6 min cycle. Two means for recharging shall be provided. One shall be the generator furnished with the engine. The other shall be an automatically controlled charger taking power from the building power supply. Cooling System & Engine Exhaust Pipe: The engine shall be provided with close circuit cooling water circulation system shall be provided. The exhaust shall be galvanized steel sized in accordance with the manuvaturer's recommendations. The exhaust pipe shall be galvanized steel sized in accordance with the manufacturer's recommendations. The exhaust pipe shall be as short as possible. Fuel Tank: The fuel tank shall be as per manufacturer's recommendation with rigid frame. Fuel tank shall have capacity at least equal to 1 gallon per hosepower plus 5% volume for expansion. Fuel tank shall be quipped with fuel supply line, return line, fill, drain, overflow, air vent and sightglass. Controller: The controller shall be UL listed / FM approved, completely assembled and wired from the factory. The controller shall be 12 volt / 24 volt., and shall be complete with all necessary component and accessories. The controller shall be operable automatically on sensing low pressure in the system and shall be provided with a pressure-actuated switch having independent high & low calobrated adjustments. The switch shall be responsive to water pressure in the fire protectin system. The pressure-sensing element of the switch shall be capable of amomentary surge pressure of 300 psi (min) without loosing its accuracy, suitable provision shall be made for relieving pressure to the pressure actuated switch to allow testing of the operation of the controller and the pumping unit. Country of Origin : USA/ EU Countries/ Japan Or their Liscenced manufacturing units located Globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2144 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.01.01

Detailed Analysis Brief Description of Item 2 EFP Type - I : (up to 6 storied building) 500 US GPM of water against a head of 80 Meter handling capacity pump-motor set with base plate and accessories.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

500 US GPM of water against a head of 262 Feet (80 Meter) handling capacity pump-motor set with base plate and accessories(Engine Driven)

1.0000

set

2000000.00

2000000.00

Skilled Labour

4.0000

day

450.00

1800.00 2001800.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

80072.00

Subtotal-A1:

2081872.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2123509.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2335860.38

VAT

6% of Total

IT

4% of Total

155724.03 103816.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2595400.43

Page: 2145 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.01.02

Detailed Analysis Brief Description of Item 2 EFP Type - II : (7 to 10 storied building) 500 US GPM of water against a head of 90 Meter handling capacity pump-motor set with base plate and accessories.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

500 US GPM of water against a head of296 Feet (90 Meter) handling capacity pump-motor set with base plate and accessories(Engine Driven)

1.0000

set

2500000.00

2500000.00

Skilled Labour

4.0000

day

450.00

1800.00 2501800.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +4.00 % on Subtotal-A )

100072.00

Subtotal-A1:

2601872.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2653909.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2919300.38

VAT

6% of Total

IT

4% of Total

194620.03 129746.68 Total:

7.21.01.03

EFP Type - III : (11 to 15 storied building) 750 US GPM of water against a head of 100 Meter handling capacity pump-motor set with base plate and accessories

set

750 US GPM of water against a head of 328 Feet (100 Meter) handling capacity pump-motor set with base plate and accessories(Engine Driven)

1.0000

set

3000000.00

3000000.00

Skilled Labour

4.0000

day

450.00

1800.00 3001800.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3061836.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3368019.60

VAT

6% of Total

IT

4% of Total

224534.64 149689.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3243667.09

3742244.00

Page: 2146 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.21.02

FIRE WATER PUMP (Motor Driven):

7.21.02.01

MFP Type - I (up to 6 storied building) Supply & installation of electrically driven centrifugal type end suction, vertical discharge Fire Water Pump manufactured according to globally accepted standard shall be complete with skid mounted, coupled with motor, safety cover etc. Motor shall be 420V/3 phase/ 50 HZ/ 2900 rpm / Class F insulation / Encloser IP55 [ as per pump manufacturer's recommendation / performance curve of the pump ]. The pump shall have a capacity to handle 350 US GPM of water against a head of 80 Meter. Country of Origin : Australia / USA / UK / Germany / Japan / Italy / Holland / Malaysia / Singapore / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

350 US GPM of water against a head of 263 Feet (80 Meter) 60HP pump-motor set with base plate and accessories(Motor Driven)

1.0000

set

500000.00

500000.00

Skilled Labour

4.0000

day

450.00

1800.00 501800.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

12545.00

Subtotal-A1: Subtotal-B: Subtotal-C:

514345.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

524631.90

10% Profit ( Add 10% on Subtotal-B) :

577095.09

VAT

6% of Total

IT

4% of Total

38473.01 25648.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

641216.77

Page: 2147 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.02.02

Detailed Analysis Brief Description of Item 2 MFP Type - II (7 to 10 storied building) Supply & installation of electrically driven centrifugal type end suction, vertical discharge Fire Water Pump manufactured according to globally accepted standard shall be complete with skid mounted, coupled with motor, safety cover etc. Motor shall be 420V/3 phase/ 50 HZ/ 2900 rpm / Class F insulation / Encloser IP55 [ as per pump manufacturer's recommendation / performance curve of the pump ]. The pump shall have a capacity to handle 500 US GPM of water against a head of 90 Meter. Country of Origin : Australia / USA / UK / Germany / Japan / Italy / Holland / Malaysia / Singapore / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

500 US GPM of water against a head of 296 Feet (90 Meter) 75HP pump-motor set with base plate and accessories(Motor Driven)

1.0000

set

525000.00

525000.00

Skilled Labour

4.0000

day

450.00

1800.00 526800.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

13170.00

Subtotal-A1:

539970.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

550769.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

605846.34

VAT

6% of Total

IT

4% of Total

40389.76 26926.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

673162.60

Page: 2148 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.02.03

Detailed Analysis Brief Description of Item 2 MFP Type - III (11 to 15 storied building) Supply & installation of electrically driven centrifugal type end suction, vertical discharge Fire Water Pump manufactured according to globally accepted standard shall be complete with skid mounted, coupled with motor, safety cover etc. Motor shall be 420V/3 phase/ 50 HZ/ 2900 rpm / Class F insulation / Encloser IP55 [ as per pump manufacturer's recommendation / performance curve of the pump ]. The pump shall have a capacity to handle 750 US GPM of water against a head of 100 Meter. Country of Origin : Australia / USA / UK / Germany / Japan / Italy / Holland / Malaysia / Singapore / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

750 US GPM of water against a head of 328 Feet (100 Meter) 100HP pump-motor set with base plate and accessories(Motor Driven)

1.0000

set

600000.00

600000.00

Skilled Labour

4.0000

day

450.00

1800.00 601800.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

15045.00

Subtotal-A1:

616845.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

629181.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

692100.09

VAT

6% of Total

IT

4% of Total

46140.01 30760.00 Total:

7.21.03

769000.10

JOCKEY PUMP (Pressure Maintenance Pump):

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2149 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.03.01

Detailed Analysis Brief Description of Item 2 JP Type - I (up to 6 storied building): Supply, installation of multistage jockey pump manufactured according to globally accepted standard or Fire Hydrant system to keep a certain pressure in water distribution system. Capacity of the pump shall be 15 US GPM against a Head of 80 meter of water. Pump shall be complete with motor suitable to meet performance curve of the pump. The Motor shall be 420V/3 phase/ 50 HZ/ 2900 rpm. Country of Origin : Australia / USA / UK / Germany / Japan / Italy / Holland / Malaysia / Singapore / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

15 US GPM of water against a head of 263 Feet (80 Meter) 3HP pump-motor set with base plate and accessories(Pressure Maintenance Pump)

1.0000

set

215000.00

215000.00

Skilled Labour

4.0000

day

450.00

1800.00 216800.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

5420.00

Subtotal-A1:

222220.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

226664.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

249330.84

VAT

6% of Total

16622.06

IT

4% of Total

11081.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

277034.27

Page: 2150 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.03.02

Detailed Analysis Brief Description of Item 2 JP Type - II (for 7 to 10 storied building) Supply, installation of multistage jockey pump manufactured according to globally accepted standard or Fire Hydrant system to keep a certain pressure in water distribution system. Capacity of the pump shall be 15 US GPM against a Head of 90 meter of water. Pump shall be complete with motor suitable to meet performance curve of the pump. The Motor shall be 420V/3 phase/ 50 HZ/ 2900 rpm. Country of Origin : Australia / USA / UK / Germany / Japan / Italy / Holland / Malaysia / Singapore / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

15 US GPM of water against a head of 296 Feet (90Meter) 3HP pump-motor set with base plate and accessories(Pressure Maintenance Pump)

1.0000

set

231500.00

231500.00

Skilled Labour

4.0000

day

450.00

1800.00 233300.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

5832.50

Subtotal-A1:

239132.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

243915.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

268306.67

VAT

6% of Total

17887.11

IT

4% of Total

11924.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

298118.52

Page: 2151 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.03.03

Detailed Analysis Brief Description of Item 2 JP Type - III (for 11 to 15 storied building) Supply, installation of multistage jockey pump manufactured according to globally accepted standard or Fire Hydrant system to keep a certain pressure in water distribution system. Capacity of the pump shall be 20 US GPM against a Head of 100 meter of water. Pump shall be complete with motor suitable to meet performance curve of the pump. The Motor shall be 420V/3 phase/ 50 HZ/ 2900 rpm. Country of Origin : Australia / USA / UK / Germany / Japan / Italy / Holland / Malaysia / Singapore / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

20 US GPM of water against a head of 328Feet (100 Meter) 4HP pump-motor set with base plate and accessories(Pressure Maintenance Pump)

1.0000

set

275000.00

275000.00

Skilled Labour

4.0000

day

450.00

1800.00 276800.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

6920.00

Subtotal-A1:

283720.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

289394.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

318333.84

VAT

6% of Total

21222.26

IT

4% of Total

14148.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

353704.27

Page: 2152 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.04

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Pump Control Panels for Motor Driven Fire & Jockey Pumps: Supply, installation of Fire & Jockey Pump Control Panel complete with MCCB / MCB / Magnetic Contactor / On-Off Push switch / Indication Lamp for phase indication, run, trip mode / Ampere meter / Volt meter / Overload Selector switch / Phase failure protection device / Dry Operation Protection Device / Volt Guard / Connector Block / Bus-bar / CT of rated capacity / Ventilation fan / Buzzer / Cable lugs / and all other accessories. The Panel shall be well dressed in side for safety purpose and for looking good. The Panel shall be suitable for 3-phase 400 ± 5% volt 50Hz Power supply. The Panel shall with Auto-Manual mode to operate the pumps controlled by pressure sensors. For Fire Pump the panel shall have option to start the pump automatically by Stop shall be manual. For Jockey pump the panel shall be suitable to Start-Stop the pump automatically controlled by pressure sensor. Enclosure of the panel shall be made of 16 SWG sheet steel and shall be painted with powder coating of red color approved as Fire code. Door of the panel shall be swing type with locking arrangement. Knob of Main MCCB shall be extended in front screen. The Panel shall be wall mounted type with fixing arrangement properly. The Panel shall be locally assembled in accordance with Standard Code of Practice as NEMA / IEC / VDE / BS standards comprising of required capacity. Country of Origin of Main components (MCCB / MCB / Magnetic Contactor / Overload) : Australia / USA / UK / Germany / Japan / Italy / Holland / Malaysia / Singapore or their Licensed manufacturing units located Globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2153 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.04.01

2 Controller for FP Type - I

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Fire Pump control panel (80 Meter)

1.0000

set

60000.00

60000.00

Starting arrangement of fire pump-motor set (80 Meter)

1.0000

set

20000.00

20000.00

B. Sc. Engineer

0.2000

day

1800.00

360.00

Diploma Engineer (Daily Basis)

0.2000

day

750.00

150.00

Foreman

0.2000

day

800.00

160.00

Fire Mechanics

0.3000

day

700.00

210.00

Electricians

0.3000

day

600.00

180.00 81060.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

2026.50

Subtotal-A1:

83086.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84748.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

93223.05

VAT

6% of Total

IT

4% of Total

6214.87 4143.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

103581.17

Page: 2154 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.04.02

2 Controller for FP Type - II

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Fire Pump control panel (90 Meter)

1.0000

set

75000.00

75000.00

Starting arrangement of Fire pump-motor set (90 Meter)

1.0000

set

20000.00

20000.00

B. Sc. Engineer

0.2000

day

1800.00

360.00

Diploma Engineer (Daily Basis)

0.2000

day

750.00

150.00

Foreman

0.2000

day

800.00

160.00

Fire Mechanics

0.3000

day

700.00

210.00

Electricians

0.3000

day

600.00

180.00 96060.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

2401.50

Subtotal-A1:

98461.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100430.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

110473.80

VAT

6% of Total

IT

4% of Total

7364.92 4909.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

122748.67

Page: 2155 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.04.03

2 Controller for FP Type - III

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Fire Pump control panel (100 Meter)

1.0000

set

100000.00

100000.00

Starting arrangement of fire pump-motor set (100 Meter)

1.0000

set

25000.00

25000.00

B. Sc. Engineer

0.2000

day

1800.00

360.00

Diploma Engineer (Daily Basis)

0.2000

day

750.00

150.00

Foreman

0.2000

day

800.00

160.00

Fire Mechanics

0.3000

day

700.00

210.00

Electricians

0.3000

day

600.00

180.00 126060.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

3151.50

Subtotal-A1:

129211.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

131795.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

144975.30

VAT

6% of Total

IT

4% of Total

9665.02 6443.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

161083.67

Page: 2156 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.04.04

2 Controller for JP Type - I

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Jockey Pump control panel (80 Meter)

1.0000

set

20000.00

20000.00

Starting arrangement of jockey pump-motor set (80 Meter)

1.0000

set

3500.00

3500.00

B. Sc. Engineer

0.2000

day

1800.00

360.00

Diploma Engineer (Daily Basis)

0.2000

day

750.00

150.00

Foreman

0.2000

day

800.00

160.00

Fire Mechanics

0.3000

day

700.00

210.00

Electricians

0.3000

day

600.00

180.00 24560.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

614.00

Subtotal-A1:

25174.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25677.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

28245.23

VAT

6% of Total

IT

4% of Total

1883.02 1255.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

31383.59

Page: 2157 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.04.05

2 Controller for JP Type - II

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Jockey Pump control panel (90 Meter)

1.0000

set

25000.00

25000.00

Starting arrangement of jockey pump-motor set (90 Meter)

1.0000

set

3500.00

3500.00

B. Sc. Engineer

0.2000

day

1800.00

360.00

Diploma Engineer (Daily Basis)

0.2000

day

750.00

150.00

Foreman

0.2000

day

800.00

160.00

Fire Mechanics

0.3000

day

700.00

210.00

Electricians

0.3000

day

600.00

180.00 29560.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

739.00

Subtotal-A1:

30299.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30904.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33995.48

VAT

6% of Total

IT

4% of Total

2266.37 1510.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

37772.75

Page: 2158 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.04.06

2 Controller for JP Type - III

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Jockey Pump control panel (100 Meter)

1.0000

set

30000.00

30000.00

Starting arrangement of jockey pump-motor set (100 Meter)

1.0000

set

3900.00

3900.00

B. Sc. Engineer

0.2000

day

1800.00

360.00

Diploma Engineer (Daily Basis)

0.2000

day

750.00

150.00

Foreman

0.2000

day

800.00

160.00

Fire Mechanics

0.3000

day

700.00

210.00

Electricians

0.3000

day

600.00

180.00 34960.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

874.00

Subtotal-A1:

35834.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

36550.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

40205.75

VAT

6% of Total

IT

4% of Total

2680.38 1786.92 Total:

7.21.05

44673.05

Fire Brigade Connection:

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2159 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.05.01

Detailed Analysis Brief Description of Item 2 Fire Brigade Connection : 2 - Way Supply and installation of 2 - way Fire Brigade Connection complete in all respect with all accessories. The unit shall have two Inlet connections of 63mm male instantaneous with non-return valve and having dia 100mm flanged type outlet directly connected with stand pipe. It will have also one 25mm dia drain valve for drainage of water, rubber blank cap and chain for protection. Outlet 100mm dia shall be as per ANSI-B16B-16.5B. or equivalent and Shall be suitable to withstand pressure of 20kg/cm². It shall be manufactured according to BS standard & suitable for using with fire service & civil defense department of Bangladesh. Country of Origin : Australia / USA / Japan / Malaysia / EU countries / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

100 mm dia 2 way connection complete with non-return valve, chair & cap, purging point etc.

1.0000

set

39000.00

39000.00

Skilled Labour

2.0000

day

450.00

900.00 39900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

997.50

Subtotal-A1:

40897.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

41715.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

45887.00

VAT

6% of Total

IT

4% of Total

3059.13 2039.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

50985.55

Page: 2160 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.05.02

Detailed Analysis Brief Description of Item 2 Fire Brigade Connection : 4 - Way Supply and installation of 4 - way Fire Brigade Connection complete in all respect with all accessories. The unit shall have two Inlet connections of 63mm male instantaneous with non-return valve and having dia 150mm flanged type outlet directly connected with stand pipe. It will have also one 25mm dia drain valve for drainage of water, rubber blank cap and chain for protection. Outlet 100mm dia shall be as per ANSI-B16B-16.5B. Or equivalent and Shall be suitable to withstand pressure of 20kg/cm². It shall be manufactured according to BS standard & suitable for using with fire service & civil defense department of Bangladesh. Country of Origin : Australia / USA / Japan / Malaysia / EU countries / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

100 mm dia 4 way connection complete with non-return valve, chair & cap, purging point etc.

1.0000

set

58400.00

58400.00

Skilled Labour

2.0000

day

450.00

900.00 59300.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

1482.50

Subtotal-A1:

60782.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61998.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

68197.97

VAT

6% of Total

IT

4% of Total

4546.53 3031.02 Total:

7.21.06

75775.52

Fire Hydrant Unit (40mm dia): Each 40mm dia Fire Hydrant Unit shall be complete with the following Components and accessories.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2161 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.06.01

Detailed Analysis Brief Description of Item 2 Hose Angle Valve (Landing valve): 40mm dia Supply and installation of Hose Angle valve / Landing valve of 40mm shall be made with brass / bronze with instantaneous female outlet. The valve shall be UL Listed /FM approved with working pressure not less than 10kg/cm². Inlet must be threaded end type, shall be installed inside the hydrant cabinet.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

40 mm dia hose Angle valve

1.0000

set

14770.00

14770.00

Skilled Labour

2.0000

day

450.00

900.00 15670.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

391.75

Subtotal-A1: Subtotal-B: Subtotal-C:

16061.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16382.99

10% Profit ( Add 10% on Subtotal-B) :

18021.28

VAT

6% of Total

IT

4% of Total

1201.42 800.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

20023.65

Page: 2162 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.06.02

Detailed Analysis Brief Description of Item 2 Fire Hose : 40mm dia Supply & installation of Fire Hose of 40mm dia 30 meter long suitable to install inside the Hydrant cabinet. The hose shall confirming to BS 6391 . The Hose shall be UL Listed /FM approved & Burst Pressure shall be not less that 600 psi and working pressure 200 psi, shall be made with special quality EPDM rubber as internal lining, suitable to withstand heat and polluted water, heat and abrasion resistance, Jacketting shall be made up of 100% polyester for extra sthrength. Hose shall be 30 meter long in a single length and shall be with male coupling in one end, female in the other. Couplings shall be binded with hose with copper wire properly. Instantaneous couplings shall be made with bronze / alluminium alloy, polished / hard anodized to confirm BS 336.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

40 mm dia FIRE HOSE

1.0000

set

20600.00

20600.00

Skilled Labour

2.0000

day

450.00

900.00 21500.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

537.50

Subtotal-A1:

22037.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22478.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24726.08

VAT

6% of Total

IT

4% of Total

1648.41 1098.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

27473.42

Page: 2163 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.06.03

Detailed Analysis Brief Description of Item 2 Jet / Spray Nozzle : 40mm dia Supply & installation of Jet / Spray Nozzle having 40mm dia male instantaneous coupling. The Nozzle shall be operable in three modes: Jet - Spray - Shut off. The Nozzle shall be light weight and easy operable. Construction of the Nozzle shall be of Brass or Alluminium & Nylon. Working pressure shall be not less than 7Kg / Cm². Flow shall be not less than 100 lpm @ 7kg / cm². Nozzle shall be install inside the cabinet.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

40 mm dia Jat/ spray nozzal

1.0000

set

8059.00

8059.00

Skilled Labour

2.0000

day

450.00

900.00 8959.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

223.98

Subtotal-A1: Subtotal-B: Subtotal-C:

9182.98 9366.63

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10303.30

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

686.89 457.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11448.11

Page: 2164 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.06.04

Detailed Analysis Brief Description of Item 2 Steel Cabinet for 40mm Dia Hydrnt Unit: Fabrication, Supply & Installation of Hydrant cabinet of suitble size (as per site measurement and requirement / Rrecommendation of Engineering in Charge) to accommodate Landing valve, Hose, Nozzle and coupling. The cabinet shall be with swing type door with breakable tempered glass. The Cabinet shall be made with 16 SWG sheet steel, Powder coated of red color.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Steel Cabinet for 40 mm dia

1.0000

set

9612.00

9612.00

Skilled Labour

2.0000

day

450.00

900.00 10512.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

262.80

Subtotal-A1:

10774.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10990.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12089.33

VAT

6% of Total

805.96

IT

4% of Total

537.30 Total:

7.21.07

13432.58

Fire Hydrant Unit (63mm dia): Each 63mm dia Fire Hydrant Unit shall be complete with the following Components and accessories.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2165 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.07.01

Detailed Analysis Brief Description of Item 2 Hose Angle Valve (Landing valve): 63mm dia Supply and installation of Hose Angle valve / Landing valve of 40mm shall be made with brass / bronze with instantaneous female outlet. The valve shall be UL Listed /FM approved and working pressure shall not be less than 10kg/cm². Inlet shtall be threaded end type, shall be installed inside the hydrant cabinet.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

63 mm dia hose Angle valve

1.0000

set

18500.00

18500.00

Skilled Labour

2.0000

day

450.00

900.00 19400.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

485.00

Subtotal-A1: Subtotal-B: Subtotal-C:

19885.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20282.70

10% Profit ( Add 10% on Subtotal-B) :

22310.97

VAT

6% of Total

IT

4% of Total

1487.40 991.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

24789.97

Page: 2166 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.07.02

Detailed Analysis Brief Description of Item 2 Fire Hose : 63mm dia Supply & installation of Fire Hose of 40mm dia 30 meter long suitable to install inside the Hydrant cabinet. The hose shall confirming to BS 6391 . The Hose shall be UL Listed /FM approved & Burst Pressure shall be not less that 600 psi and working pressure 200 psi, shall be made with special quality EPDM rubber as internal lining, suitable to withstand heat and polluted water, heat and abrasion resistance, Jacketting shall be made up of 100% polyester for extra sthrength. Hose shall be 30meter long in a single length and shall be with male coupling in one end other end with female coupling. Couplings shall be binded with hose with copper wire properly. Instantaneous couplings shall be made with bronze / alluminium alloy, polished / hard anodized to confirm BS 336.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

63 mm dia FIRE HOSE

1.0000

set

24000.00

24000.00

Skilled Labour

2.0000

day

450.00

900.00 24900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

622.50

Subtotal-A1:

25522.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26032.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

28636.25

VAT

6% of Total

IT

4% of Total

1909.08 1272.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

31818.05

Page: 2167 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.07.03

Detailed Analysis Brief Description of Item 2 Jet / Spray Nozzle : 63mm dia Supply & installation of Jet / Spray Nozzle having 40mm dia male instantaneous coupling. The Nozzle shall be operable in three modes: Jet - Spray - Shut off. The Nozzle shall be light weight and easy operable. Construction of the Nozzle shall be of Brass or Alluminium & Nylon. Working pressure shall be not less than 7Kg / Cm². Flow shall be not less than 100 lpm @ 7kg / cm². Nozzle shall be install inside the cabinet.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

63 mm dia Jat/ spray nozzal

1.0000

set

7000.00

7000.00

Skilled Labour

2.0000

day

450.00

900.00 7900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

197.50

Subtotal-A1: Subtotal-B: Subtotal-C:

8097.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8259.45

10% Profit ( Add 10% on Subtotal-B) :

9085.40

VAT

6% of Total

IT

4% of Total

605.69 403.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10094.88

Page: 2168 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.21.07.04

2 Steel Cabinet for 63mm Dia Hydrnt Unit: Fabrication, Supply & Installation of Hydrant cabinet of suitble size (as per site measurement and requirement / Rrecommendation of Engineering in Charge) to accommodate Landing valve, Hose, Nozzle and coupling. The cabinet shall be with swing type door with breakable tempered glass. The Cabinet shall be made with 16 SWG sheet steel, Powder coated of red color.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Steel Cabinet for 63 mm dia

1.0000

set

11500.00

11500.00

Skilled Labour

2.0000

day

450.00

900.00 12400.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

310.00

Subtotal-A1:

12710.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12964.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14260.62

VAT

6% of Total

950.71

IT

4% of Total

633.81 Total:

7.21.08

15845.13

Pillar Hydrant:

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2169 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.08.01

Detailed Analysis Brief Description of Item 2 Pillar Hydrant : Single Headed Supply and installation of Cast Iron body Single Headed Pillar Hydrant complete with One (01) no. cast brass made controllable outlet of 65mm dia with female instanteneous outlet, Inlet shall be 80mm dia flanged end. The Hydrant shall be suitable to withstand test pressure of 300 psi (min). Color of the unit shall be red / approved by the manufacturer or as per code.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Single Headed Pillar Hydrant

1.0000

set

30000.00

30000.00

Skilled Labour

2.0000

day

450.00

900.00 30900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +.00 % on Subtotal-A )

0.00

( +2.50 % on Subtotal-A )

772.50

Subtotal-A1:

31672.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32305.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

35536.55

VAT

6% of Total

2369.10

IT

4% of Total

1579.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

39485.05

Page: 2170 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.08.02

Detailed Analysis Brief Description of Item 2 Pillar Hydrant : Double Headed Supply and installation of Cast Iron body Double Headed Pillar Hydrant complete with Two (02) nos. cast brass made controllable outlet of 65mm dia with female instanteneous outlet, Inlet shall be 100mm dia flanged end. The Hydrant shall be suitable to withstand test pressure of 300 psi (min). Color of the unit shall be red / approved by the manufacturer or as per code.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Double Headed Pillar Hydrant

1.0000

set

50000.00

50000.00

Skilled Labour

2.0000

day

450.00

900.00 50900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

1272.50

Subtotal-A1:

52172.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

53215.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

58537.55

VAT

6% of Total

3902.50

IT

4% of Total

2601.67 Total:

7.21.09

65041.72

Black Steel Pipe ERW, Schdule 20 Supply and Installation of ERW black steel pipe 20 schedule. The Pipe work shall include welding type Tee, Elbow, Reducer etc., and also hangers / supports etc. complete. Pipe work (over ground) shall be painted with red oxide primer. Underground pipes should be laid after wrapping with pvc tape after using approved primer. Pipe diameter and minimum wall thickness shall be as follows. Country of Origin: Japan / Korea / India /Australia or Equivalent.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2171 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.09.01

Detailed Analysis Brief Description of Item 2 200 mm dia, Wall Thickness: 6.11mm, ERW, Schedule 20

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 200 mm dia, Wall Thickness: 6.11mm, ERW, Schedule 20

1.0000

rm

7495.00

7495.00

Skilled Labour

1.0000

day

450.00

450.00 7945.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

198.63

Subtotal-A1: Subtotal-B: Subtotal-C:

8143.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8306.50

10% Profit ( Add 10% on Subtotal-B) :

9137.15

VAT

6% of Total

IT

4% of Total

609.14 406.10 Total:

7.21.09.02

150 mm dia, Wall Thickness: 4.85mm, ERW, Schedule 20

rm 150 mm dia, Wall Thickness: 4.85mm, ERW, Schedule 20

1.0000

rm

5792.00

5792.00

Skilled Labour

1.0000

day

450.00

450.00 6242.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

156.05

Subtotal-A1:

6398.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6526.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7178.61

VAT

6% of Total

IT

4% of Total

478.57 319.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10152.39

7976.24

Page: 2172 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.09.03

Detailed Analysis Brief Description of Item 2 100 mm dia, Wall Thickness: 4.50mm, ERW, Schedule 20

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 100 mm dia, Wall Thickness: 4.50mm, ERW, Schedule 20

1.0000

rm

3903.00

3903.00

Skilled Labour

1.0000

day

450.00

450.00 4353.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

108.83

Subtotal-A1: Subtotal-B: Subtotal-C:

4461.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4551.06

10% Profit ( Add 10% on Subtotal-B) :

5006.17

VAT

6% of Total

IT

4% of Total

333.74 222.50 Total:

7.21.09.04

80 mm dia, Wall Thickness: 4.05mm, ERW, Schedule 20

rm 80mm dia, Wall Thickness: 4.05mm, ERW, Schedule 20

1.0000

rm

2968.00

2968.00

Skilled Labour

1.0000

day

450.00

450.00 3418.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

85.45

Subtotal-A1:

3503.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3573.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3930.87

VAT

6% of Total

IT

4% of Total

262.06 174.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5562.41

4367.63

Page: 2173 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.09.05

Detailed Analysis Brief Description of Item 2 65 mm dia, Wall Thickness: 3.85mm, ERW, Schedule 20

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 65 mm dia, Wall Thickness: 3.85mm, ERW, Schedule 20

1.0000

rm

2132.00

2132.00

Skilled Labour

1.0000

day

450.00

450.00 2582.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

64.55

Subtotal-A1: Subtotal-B: Subtotal-C:

2646.55 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2699.48

10% Profit ( Add 10% on Subtotal-B) :

2969.43

VAT

6% of Total

IT

4% of Total

197.96 131.97 Total:

7.21.09.06

50 mm dia, Wall Thickness: 3.65mm, ERW, Schedule 20

rm 50 mm dia, Wall Thickness: 3.65mm, ERW, Schedule 20

1.0000

rm

1640.00

1640.00

Skilled Labour

1.0000

day

450.00

450.00 2090.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

52.25

Subtotal-A1:

2142.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2185.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2403.60

VAT

6% of Total

IT

4% of Total

160.24 106.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3299.37

2670.67

Page: 2174 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.09.07

Detailed Analysis Brief Description of Item 2 40 mm dia, Wall Thickness: 3.25mm, ERW, Schedule 20

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 40 mm dia, Wall Thickness: 3.25mm, ERW, Schedule 20

1.0000

rm

1312.00

1312.00

Skilled Labour

1.0000

day

450.00

450.00 1762.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

44.05

Subtotal-A1: Subtotal-B: Subtotal-C:

1806.05 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1842.17

10% Profit ( Add 10% on Subtotal-B) :

2026.39

VAT

6% of Total

IT

4% of Total

135.09 90.06 Total:

7.21.09.08

25 mm dia, Wall Thickness: 3.25mm, ERW, Schedule 20

rm 25 mm dia, Wall Thickness: 3.25mm, ERW, Schedule 20

1.0000

rm

1050.00

1050.00

Skilled Labour

1.0000

day

450.00

450.00 1500.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

37.50

Subtotal-A1:

1537.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1568.25

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1725.08

VAT

6% of Total

IT

4% of Total

115.01 76.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2251.54

1916.75

Page: 2175 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.09.09

Detailed Analysis Brief Description of Item 2 20 mm dia, Wall Thickness: 2.65mm, ERW, Schedule 20

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

rm 20 mm dia, Wall Thickness: 2.65mm, ERW, Schedule 20

1.0000

rm

820.00

820.00

Skilled Labour

1.0000

day

450.00

450.00 1270.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

31.75

Subtotal-A1: Subtotal-B: Subtotal-C:

1301.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1327.79

10% Profit ( Add 10% on Subtotal-B) :

1460.56

VAT

6% of Total

IT

4% of Total

97.37 64.91 Total:

7.21.09.10

12 mm dia, Wall Thickness: 2.65mm, ERW, Schedule 20

rm 12 mm dia, Wall Thickness: 2.65mm, ERW, Schedule 20

1.0000

rm

574.00

574.00

Skilled Labour

1.0000

day

450.00

450.00 1024.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

25.60

Subtotal-A1:

1049.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1070.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1177.65

VAT

6% of Total

IT

4% of Total

78.51 52.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1622.85

1308.50

Page: 2176 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.21.10

Black Steel Pipe ERW, Schdule 40 Supply and Installation of ERW black steel pipe 40 schedule. The Pipe work shall include welding type Tee, Elbow, Reducer etc., and also hangers / supports etc. complete. Pipe work (over ground) shall be painted with red oxide primer. Underground pipes should be laid after wrapping with pvc tape after using approved primer. Pipe diameter and minimum wall thickness shall be as follows. Country of Origin: Japan / Korea / India /Australia or Equivalent.

7.21.10.01

200 mm dia, Wall Thickness: 8.2mm, ERW, Schedule 40

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 200 mm dia, Wall Thickness: 8.2mm, ERW, Schedule 40

1.0000

rm

8036.00

8036.00

Skilled Labour

1.0000

day

450.00

450.00 8486.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

212.15

Subtotal-A1:

8698.15

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8872.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9759.32

VAT

6% of Total

IT

4% of Total

650.62 433.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10843.69

Page: 2177 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.10.02

Detailed Analysis Brief Description of Item 2 150 mm dia, Wall Thickness: 7.1mm, ERW, Schedule 40

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 150 mm dia, Wall Thickness: 7.1mm, ERW, Schedule 40

1.0000

rm

7167.00

7167.00

Skilled Labour

1.0000

day

450.00

450.00 7617.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

190.43

Subtotal-A1: Subtotal-B: Subtotal-C:

7807.43 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7963.57

10% Profit ( Add 10% on Subtotal-B) :

8759.93

VAT

6% of Total

IT

4% of Total

584.00 389.33 Total:

7.21.10.03

100 mm dia, Wall Thickness: 6.0mm, ERW, Schedule 40

rm 100 mm dia, Wall Thickness: 6.0mm, ERW, Schedule 40

1.0000

rm

5714.00

5714.00

Skilled Labour

1.0000

day

450.00

450.00 6164.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

154.10

Subtotal-A1:

6318.10

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6444.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7088.91

VAT

6% of Total

IT

4% of Total

472.59 315.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9733.26

7876.56

Page: 2178 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.10.04

Detailed Analysis Brief Description of Item 2 80 mm dia, Wall Thickness: 5.5mm, ERW, Schedule 40

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 80mm dia, Wall Thickness: 5.5mm, ERW, Schedule 40

1.0000

rm

4369.00

4369.00

Skilled Labour

1.0000

day

450.00

450.00 4819.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

120.48

Subtotal-A1: Subtotal-B: Subtotal-C:

4939.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5038.26

10% Profit ( Add 10% on Subtotal-B) :

5542.09

VAT

6% of Total

IT

4% of Total

369.47 246.32 Total:

7.21.10.05

65 mm dia, Wall Thickness: 5.2mm, ERW, Schedule 40

rm 65 mm dia, Wall Thickness: 5.2mm, ERW, Schedule 40

1.0000

rm

2624.00

2624.00

Skilled Labour

1.0000

day

450.00

450.00 3074.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

76.85

Subtotal-A1:

3150.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3213.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3535.25

VAT

6% of Total

IT

4% of Total

235.68 157.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6157.88

3928.06

Page: 2179 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.10.06

Detailed Analysis Brief Description of Item 2 50 mm dia, Wall Thickness: 3.9mm, ERW, Schedule 40

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 50 mm dia, Wall Thickness: 3.9mm, ERW, Schedule 40

1.0000

rm

1804.00

1804.00

Skilled Labour

1.0000

day

450.00

450.00 2254.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

56.35

Subtotal-A1: Subtotal-B: Subtotal-C:

2310.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2356.56

10% Profit ( Add 10% on Subtotal-B) :

2592.21

VAT

6% of Total

IT

4% of Total

172.81 115.21 Total:

7.21.10.07

40 mm dia, Wall Thickness: 3.7mm, ERW, Schedule 40

rm 40 mm dia, Wall Thickness: 3.7mm, ERW, Schedule 40

1.0000

rm

1476.00

1476.00

Skilled Labour

1.0000

day

450.00

450.00 1926.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

48.15

Subtotal-A1:

1974.15

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2013.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2215.00

VAT

6% of Total

IT

4% of Total

147.67 98.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2880.24

2461.11

Page: 2180 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.10.08

Detailed Analysis Brief Description of Item 2 25 mm dia, Wall Thickness: 3.4mm, ERW, Schedule 40

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

rm 25 mm dia, Wall Thickness: 3.4mm, ERW, Schedule 40

1.0000

rm

1246.00

1246.00

Skilled Labour

1.0000

day

450.00

450.00 1696.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

42.40

Subtotal-A1: Subtotal-B: Subtotal-C:

1738.40 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1773.17

10% Profit ( Add 10% on Subtotal-B) :

1950.48

VAT

6% of Total

IT

4% of Total

130.03 86.69 Total:

7.21.10.09

20 mm dia, Wall Thickness: 2.9mm, ERW, Schedule 40

rm 20 mm dia, Wall Thickness: 2.9mm, ERW, Schedule 40

1.0000

rm

886.00

886.00

Skilled Labour

1.0000

day

450.00

450.00 1336.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

33.40

Subtotal-A1:

1369.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1396.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1536.47

VAT

6% of Total

IT

4% of Total

102.43 68.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2167.21

1707.19

Page: 2181 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.10.10

Detailed Analysis Brief Description of Item 2 12 mm dia, Wall Thickness: 2.8mm, ERW, Schedule 40

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

rm 12 mm dia, Wall Thickness: 2.8mm, ERW, Schedule 40

1.0000

rm

640.00

640.00

Skilled Labour

1.0000

day

450.00

450.00 1090.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

27.25

Subtotal-A1: Subtotal-B: Subtotal-C:

1117.25 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1139.60

10% Profit ( Add 10% on Subtotal-B) :

1253.55

VAT

6% of Total

IT

4% of Total

83.57 55.71 Total:

7.21.11

1392.84

OS & Y Valves: Supply & Installation of Valves & Fittings manufactured to confirm ANSI B16, ISO-9001 starndard. Suitable to withstand a working pressure of 150 psi and complete in all respect with all accessories such as Flanges, Nut – Bolts, Gaskets etc. Valves 80mm dia and above shall be of Cast Iron body flanged end type, smaller than those shall be Brass / Bronze body Screwed end type. Country of Origin: USA / UK / Germany / Italy / Korea / Singapore / OR Licensed Manufacturing units located Globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2182 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.11.01

2 150 mm dia OS & Y Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 mm dia OS & Y Valve

1.0000

each

30046.05

30046.05

Skilled Labour

2.0000

day

450.00

900.00 30946.05

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

773.65

Subtotal-A1: Subtotal-B: Subtotal-C:

31719.70 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32354.10

10% Profit ( Add 10% on Subtotal-B) :

35589.50

VAT

6% of Total

IT

4% of Total

2372.63 1581.76 Total:

7.21.11.02

100 mm dia OS & Y Valve

each 100 mm dia OS & Y Valve

1.0000

each

21689.00

21689.00

Skilled Labour

2.0000

day

450.00

900.00 22589.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

564.73

Subtotal-A1:

23153.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23616.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25978.48

VAT

6% of Total

IT

4% of Total

1731.90 1154.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

39543.89

28864.98

Page: 2183 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.11.03

2 80 mm dia OS & Y Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 80mm dia OS & Y Valve

1.0000

each

16675.00

16675.00

Skilled Labour

2.0000

day

450.00

900.00 17575.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

439.38

Subtotal-A1: Subtotal-B: Subtotal-C:

18014.38 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18374.66

10% Profit ( Add 10% on Subtotal-B) :

20212.13

VAT

6% of Total

IT

4% of Total

1347.48 898.32 Total:

7.21.11.04

65 mm dia OS & Y Valve

each 65 mm dia OS & Y Valve

1.0000

each

11618.45

11618.45

Skilled Labour

2.0000

day

450.00

900.00 12518.45

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

312.96

Subtotal-A1:

12831.41

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13088.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14396.84

VAT

6% of Total

IT

4% of Total

959.79 639.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

22457.92

15996.49

Page: 2184 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.11.05

2 50 mm dia OS & Y Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50 mm dia OS & Y Valve

1.0000

each

9723.25

9723.25

Skilled Labour

2.0000

day

450.00

900.00 10623.25

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

265.58

Subtotal-A1: Subtotal-B: Subtotal-C:

10888.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11106.61

10% Profit ( Add 10% on Subtotal-B) :

12217.27

VAT

6% of Total

IT

4% of Total

814.48 542.99 Total:

7.21.11.06

40 mm dia OS & Y Valve

each 40 mm dia OS & Y Valve

1.0000

each

5968.50

5968.50

Skilled Labour

2.0000

day

450.00

900.00 6868.50

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

171.71

Subtotal-A1:

7040.21

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7181.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7899.12

VAT

6% of Total

IT

4% of Total

526.61 351.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13574.74

8776.80

Page: 2185 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

7.21.12

Gate Valves: Supply & Installation of Valves & Fittings manufactured to confirm ANSI B16, ISO-9001 starndard. Suitable to withstand a working pressure of 150 psi and complete in all respect with all accessories such as Flanges, Nut – Bolts, Gaskets etc. Valves 80mm dia and above shall be of Cast Iron body flanged end type, smaller than those shall be Brass / Bronze body Screwed end type. Country of Origin: USA / UK / Germany / Italy / Korea / Singapore / OR Licensed Manufacturing units located Globally.

7.21.12.01

150 mm dia Gate Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 mm dia Gate Valve

1.0000

each

26127.00

26127.00

Skilled Labour

2.0000

day

450.00

900.00 27027.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

675.68

Subtotal-A1: Subtotal-B: Subtotal-C:

27702.68 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28256.73

10% Profit ( Add 10% on Subtotal-B) :

31082.40

VAT

6% of Total

IT

4% of Total

2072.16 1381.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

34536.00

Page: 2186 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.12.02

2 100 mm dia Gate Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 100 mm dia Gate Valve

1.0000

each

18860.00

18860.00

Skilled Labour

2.0000

day

450.00

900.00 19760.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

494.00

Subtotal-A1: Subtotal-B: Subtotal-C:

20254.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20659.08

10% Profit ( Add 10% on Subtotal-B) :

22724.99

VAT

6% of Total

IT

4% of Total

1515.00 1010.00 Total:

7.21.12.03

80 mm dia Gate Valve

each 80mm dia Gate Valve

1.0000

each

14500.00

14500.00

Skilled Labour

2.0000

day

450.00

900.00 15400.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

385.00

Subtotal-A1:

15785.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16100.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17710.77

VAT

6% of Total

IT

4% of Total

1180.72 787.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25249.99

19678.63

Page: 2187 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.12.04

2 65 mm dia Gate Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 65 mm dia Gate Valve

1.0000

each

10103.00

10103.00

Skilled Labour

2.0000

day

450.00

900.00 11003.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

275.08

Subtotal-A1: Subtotal-B: Subtotal-C:

11278.08 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11503.64

10% Profit ( Add 10% on Subtotal-B) :

12654.00

VAT

6% of Total

IT

4% of Total

843.60 562.40 Total:

7.21.12.05

50 mm dia Gate Valve

each 50 mm dia Gate Valve

1.0000

each

8455.00

8455.00

Skilled Labour

2.0000

day

450.00

900.00 9355.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

233.88

Subtotal-A1:

9588.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9780.65 10758.72 717.25 478.17

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14060.00

11954.13

Page: 2188 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.12.06

2 40 mm dia Gate Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 40 mm dia Gate Valve

1.0000

each

5190.00

5190.00

Skilled Labour

2.0000

day

450.00

900.00 6090.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

152.25

Subtotal-A1: Subtotal-B: Subtotal-C:

6242.25 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6367.10

10% Profit ( Add 10% on Subtotal-B) :

7003.80

VAT

6% of Total

IT

4% of Total

466.92 311.28 Total:

7.21.13

7782.01

Globe Valves: Supply & Installation of Valves & Fittings manufactured to confirm ANSI B16, ISO-9001 starndard. Suitable to withstand a working pressure of 150 psi and complete in all respect with all accessories such as Flanges, Nut – Bolts, Gaskets etc. Valves 80mm dia and above shall be of Cast Iron body flanged end type, smaller than those shall be Brass / Bronze body Screwed end type. Country of Origin: USA / UK / Germany / Italy / Korea / Singapore / OR Licensed Manufacturing units located Globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2189 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.13.01

2 150 mm Globe Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 mm dia Globe Valve

1.0000

each

27832.00

27832.00

Skilled Labour

2.0000

day

450.00

900.00 28732.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

718.30

Subtotal-A1: Subtotal-B: Subtotal-C:

29450.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30039.31

10% Profit ( Add 10% on Subtotal-B) :

33043.24

VAT

6% of Total

IT

4% of Total

2202.88 1468.59 Total:

7.21.13.02

100 mm Globe Valve

each 100 mm dia Globe Valve

1.0000

each

20238.00

20238.00

Skilled Labour

2.0000

day

450.00

900.00 21138.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

528.45

Subtotal-A1:

21666.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22099.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24309.76

VAT

6% of Total

IT

4% of Total

1620.65 1080.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

36714.71

27010.84

Page: 2190 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.13.03

2 80 mm Globe Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 80mm dia Globe Valve

1.0000

each

15559.00

15559.00

Skilled Labour

2.0000

day

450.00

900.00 16459.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

411.48

Subtotal-A1: Subtotal-B: Subtotal-C:

16870.48 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17207.88

10% Profit ( Add 10% on Subtotal-B) :

18928.67

VAT

6% of Total

IT

4% of Total

1261.91 841.27 Total:

7.21.13.04

65 mm Globe Valve

each 65 mm dia Globe Valve

1.0000

each

10808.00

10808.00

Skilled Labour

2.0000

day

450.00

900.00 11708.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

292.70

Subtotal-A1:

12000.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12240.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13464.79

VAT

6% of Total

IT

4% of Total

897.65 598.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21031.86

14960.87

Page: 2191 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.13.05

2 50 mm Globe Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50 mm dia Globe Valve

1.0000

each

10058.00

10058.00

Skilled Labour

2.0000

day

450.00

900.00 10958.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

273.95

Subtotal-A1: Subtotal-B: Subtotal-C:

11231.95 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11456.59

10% Profit ( Add 10% on Subtotal-B) :

12602.25

VAT

6% of Total

IT

4% of Total

840.15 560.10 Total:

7.21.13.06

40 mm Globe Valve

each 40 mm dia Globe Valve

1.0000

each

7533.00

7533.00

Skilled Labour

2.0000

day

450.00

900.00 8433.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

210.83

Subtotal-A1:

8643.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8816.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9698.37

VAT

6% of Total

IT

4% of Total

646.56 431.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14002.50

10775.97

Page: 2192 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.21.14

Non-Return/Check Valves: Supply & Installation of Valves & Fittings manufactured to confirm ANSI B16, ISO-9001 starndard. Suitable to withstand a working pressure of 150 psi and complete in all respect with all accessories such as Flanges, Nut – Bolts, Gaskets etc. Valves 80mm dia and above shall be of Cast Iron body flanged end type, smaller than those shall be Brass / Bronze body Screwed end type. Country of Origin: USA / UK / Germany / Italy / Korea / Singapore / OR Licensed Manufacturing units located Globally.

7.21.14.01

150 mm Non-Return/Check Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 mm dia Non-Return/ Check Valve

1.0000

each

29347.00

29347.00

Skilled Labour

2.0000

day

450.00

900.00 30247.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

756.18

Subtotal-A1: Subtotal-B: Subtotal-C:

31003.18 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

31623.24

10% Profit ( Add 10% on Subtotal-B) :

34785.56

VAT

6% of Total

IT

4% of Total

2319.04 1546.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

38650.62

Page: 2193 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.14.02

Detailed Analysis Brief Description of Item 2 100 mm Non-Return/Check Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 100 mm dia Non-Return/ Check Valve

1.0000

each

23413.00

23413.00

Skilled Labour

2.0000

day

450.00

900.00 24313.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

607.83

Subtotal-A1: Subtotal-B: Subtotal-C:

24920.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25419.24

10% Profit ( Add 10% on Subtotal-B) :

27961.17

VAT

6% of Total

IT

4% of Total

1864.08 1242.72 Total:

7.21.14.03

80 mm Non-Return/Check Valve

each 80mm dia Non-Return/ Check Valve

1.0000

each

16997.00

16997.00

Skilled Labour

2.0000

day

450.00

900.00 17897.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

447.43

Subtotal-A1:

18344.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18711.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20582.44

VAT

6% of Total

IT

4% of Total

1372.16 914.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

31067.96

22869.38

Page: 2194 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.14.04

Detailed Analysis Brief Description of Item 2 65 mm Non-Return/Check Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 65 mm dia Non-Return/ Check Valve

1.0000

each

14190.00

14190.00

Skilled Labour

2.0000

day

450.00

900.00 15090.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

377.25

Subtotal-A1: Subtotal-B: Subtotal-C:

15467.25 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15776.60

10% Profit ( Add 10% on Subtotal-B) :

17354.25

VAT

6% of Total

IT

4% of Total

1156.95 771.30 Total:

7.21.14.05

50 mm Non-Return/Check Valve

each 50 mm dia Non-Return/ Check Valve

1.0000

each

12206.00

12206.00

Skilled Labour

2.0000

day

450.00

900.00 13106.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

327.65

Subtotal-A1:

13433.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13702.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15072.56

VAT

6% of Total

IT

4% of Total

1004.84 669.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

19282.51

16747.28

Page: 2195 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.14.06

Detailed Analysis Brief Description of Item 2 40 mm Non-Return/Check Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 40 mm dia Non-Return/ Check Valve

1.0000

each

7457.00

7457.00

Skilled Labour

2.0000

day

450.00

900.00 8357.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

208.93

Subtotal-A1: Subtotal-B: Subtotal-C:

8565.93 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8737.24

10% Profit ( Add 10% on Subtotal-B) :

9610.97

VAT

6% of Total

IT

4% of Total

640.73 427.15 Total:

7.21.15

10678.85

Y-Strainers: Supply & Installation of Valves & Fittings manufactured to confirm ANSI B16, ISO-9001 starndard. Suitable to withstand a working pressure of 150 psi and complete in all respect with all accessories such as Flanges, Nut – Bolts, Gaskets etc. Valves 80mm dia and above shall be of Cast Iron body flanged end type, smaller than those shall be Brass / Bronze body Screwed end type. Country of Origin: USA / UK / Germany / Italy / Korea / Singapore / OR Licensed Manufacturing units located Globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2196 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.15.01

2 150 mm Y-Strainers

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 mm dia Y - Strainer

1.0000

each

28428.00

28428.00

Skilled Labour

2.0000

day

450.00

900.00 29328.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

733.20

Subtotal-A1: Subtotal-B: Subtotal-C:

30061.20 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30662.42

10% Profit ( Add 10% on Subtotal-B) :

33728.67

VAT

6% of Total

IT

4% of Total

2248.58 1499.05 Total:

7.21.15.02

100 mm Y-Strainers

each 100 mm dia Y - Strainer

1.0000

each

20231.00

20231.00

Skilled Labour

2.0000

day

450.00

900.00 21131.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

528.28

Subtotal-A1:

21659.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22092.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24301.71

VAT

6% of Total

IT

4% of Total

1620.11 1080.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

37476.30

27001.90

Page: 2197 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.15.03

2 80 mm Y-Strainers

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 80mm dia Y - Strainer

1.0000

each

13819.00

13819.00

Skilled Labour

2.0000

day

450.00

900.00 14719.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

367.98

Subtotal-A1: Subtotal-B: Subtotal-C:

15086.98 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15388.71

10% Profit ( Add 10% on Subtotal-B) :

16927.59

VAT

6% of Total

IT

4% of Total

1128.51 752.34 Total:

7.21.15.04

65 mm Y-Strainers

each 65 mm dia Y - Strainer

1.0000

each

13260.00

13260.00

Skilled Labour

2.0000

day

450.00

900.00 14160.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

354.00

Subtotal-A1:

14514.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14804.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16284.71

VAT

6% of Total

IT

4% of Total

1085.65 723.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18808.43

18094.12

Page: 2198 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.15.05

2 50 mm Y-Strainers

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50 mm dia Y - Strainer

1.0000

each

11140.00

11140.00

Skilled Labour

2.0000

day

450.00

900.00 12040.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

301.00

Subtotal-A1: Subtotal-B: Subtotal-C:

12341.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12587.82

10% Profit ( Add 10% on Subtotal-B) :

13846.60

VAT

6% of Total

IT

4% of Total

923.11 615.40 Total:

7.21.15.06

40 mm Y-Strainers

each 40 mm dia Y - Strainer

1.0000

each

7670.00

7670.00

Skilled Labour

2.0000

day

450.00

900.00 8570.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

214.25

Subtotal-A1:

8784.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8959.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9855.93

VAT

6% of Total

IT

4% of Total

657.06 438.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15385.11

10951.03

Page: 2199 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.21.16

Foot Valve with Strainer: Supply & Installation of Valves & Fittings manufactured to confirm ANSI B16, ISO-9001 starndard. Suitable to withstand a working pressure of 150 psi and complete in all respect with all accessories such as Flanges, Nut – Bolts, Gaskets etc. Valves 80mm dia and above shall be of Cast Iron body flanged end type, smaller than those shall be Brass / Bronze body Screwed end type. Country of Origin: USA / UK / Germany / Italy / Korea / Singapore / OR Licensed Manufacturing units located Globally.

7.21.16.01

150 mm Foot Valve with Strainer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 mm dia Foot Valve with Strainer

1.0000

each

19171.00

19171.00

Skilled Labour

2.0000

day

450.00

900.00 20071.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

501.78

Subtotal-A1: Subtotal-B: Subtotal-C:

20572.78 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20984.23

10% Profit ( Add 10% on Subtotal-B) :

23082.65

VAT

6% of Total

IT

4% of Total

1538.84 1025.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25647.39

Page: 2200 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.16.02

2 100 mm Foot Valve with Strainer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 100 mm dia Foot Valve with Strainer

1.0000

each

15590.00

15590.00

Skilled Labour

2.0000

day

450.00

900.00 16490.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

412.25

Subtotal-A1: Subtotal-B: Subtotal-C:

16902.25 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17240.30

10% Profit ( Add 10% on Subtotal-B) :

18964.32

VAT

6% of Total

IT

4% of Total

1264.29 842.86 Total:

7.21.16.03

80 mm Foot Valve with Strainer

each 80mm dia Foot Valve with Strainer

1.0000

each

13157.00

13157.00

Skilled Labour

2.0000

day

450.00

900.00 14057.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

351.43

Subtotal-A1:

14408.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14696.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16166.25

VAT

6% of Total

IT

4% of Total

1077.75 718.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21071.47

17962.50

Page: 2201 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.16.04

2 65 mm Foot Valve with Strainer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 65 mm dia Foot Valve with Strainer

1.0000

each

10335.00

10335.00

Skilled Labour

2.0000

day

450.00

900.00 11235.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

280.88

Subtotal-A1: Subtotal-B: Subtotal-C:

11515.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11746.19

10% Profit ( Add 10% on Subtotal-B) :

12920.81

VAT

6% of Total

IT

4% of Total

861.39 574.26 Total:

7.21.16.05

50 mm Foot Valve with Strainer

each 50 mm dia Foot Valve with Strainer

1.0000

each

8241.00

8241.00

Skilled Labour

2.0000

day

450.00

900.00 9141.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

228.53

Subtotal-A1:

9369.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9556.92 10512.61 700.84 467.23

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14356.46

11680.67

Page: 2202 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.16.06

2 40 mm Foot Valve with Strainer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 40 mm dia Foot Valve with Strainer

1.0000

each

6194.00

6194.00

Skilled Labour

2.0000

day

450.00

900.00 7094.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

177.35

Subtotal-A1: Subtotal-B: Subtotal-C:

7271.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7416.78

10% Profit ( Add 10% on Subtotal-B) :

8158.45

VAT

6% of Total

IT

4% of Total

543.90 362.60 Total:

7.21.17

9064.95

Flexible Joint: Supply & Installation of Valves & Fittings manufactured to confirm ANSI B16, ISO-9001 starndard. Suitable to withstand a working pressure of 150 psi and complete in all respect with all accessories such as Flanges, Nut – Bolts, Gaskets etc. Valves 80mm dia and above shall be of Cast Iron body flanged end type, smaller than those shall be Brass / Bronze body Screwed end type. Country of Origin: USA / UK / Germany / Italy / Korea / Singapore / OR Licensed Manufacturing units located Globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2203 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.17.01

2 150 mm Flexible Joint

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 mm dia Flexible Joint

1.0000

each

17650.00

17650.00

Skilled Labour

2.0000

day

450.00

900.00 18550.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

463.75

Subtotal-A1: Subtotal-B: Subtotal-C:

19013.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19394.03

10% Profit ( Add 10% on Subtotal-B) :

21333.43

VAT

6% of Total

IT

4% of Total

1422.23 948.15 Total:

7.21.17.02

100 mm Flexible Joint

each 100 mm dia Flexible Joint

1.0000

each

13196.00

13196.00

Skilled Labour

2.0000

day

450.00

900.00 14096.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

352.40

Subtotal-A1:

14448.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14737.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16211.10

VAT

6% of Total

IT

4% of Total

1080.74 720.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23703.81

18012.34

Page: 2204 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.17.03

2 80 mm Flexible Joint

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 80mm dia Flexible Joint

1.0000

each

12438.00

12438.00

Skilled Labour

2.0000

day

450.00

900.00 13338.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

333.45

Subtotal-A1: Subtotal-B: Subtotal-C:

13671.45 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13944.88

10% Profit ( Add 10% on Subtotal-B) :

15339.37

VAT

6% of Total

IT

4% of Total

1022.62 681.75 Total:

7.21.17.04

65 mm Flexible Joint

each 65 mm dia Flexible Joint

1.0000

each

11595.00

11595.00

Skilled Labour

2.0000

day

450.00

900.00 12495.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

312.38

Subtotal-A1:

12807.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13063.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14369.87

VAT

6% of Total

IT

4% of Total

957.99 638.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17043.74

15966.53

Page: 2205 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.17.05

2 50 mm Flexible Joint

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50 mm dia Flexible Joint

1.0000

each

9344.00

9344.00

Skilled Labour

2.0000

day

450.00

900.00 10244.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

256.10

Subtotal-A1: Subtotal-B: Subtotal-C:

10500.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10710.10

10% Profit ( Add 10% on Subtotal-B) :

11781.11

VAT

6% of Total

IT

4% of Total

785.41 523.60 Total:

7.21.17.06

40 mm Flexible Joint

each 40 mm dia Flexible Joint

1.0000

each

8161.00

8161.00

Skilled Labour

2.0000

day

450.00

900.00 9061.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

226.53

Subtotal-A1:

9287.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9473.28 10420.60 694.71 463.14

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13090.12

11578.45

Page: 2206 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

7.21.18

Ball Valves, Class: PN20: Supply & Installation of Valves & Fittings manufactured to confirm ANSI B16, ISO-9001 starndard. Suitable to withstand a working pressure of 150 psi and complete in all respect with all accessories such as Flanges, Nut – Bolts, Gaskets etc. Valves 80mm dia and above shall be of Cast Iron body flanged end type, smaller than those shall be Brass / Bronze body Screwed end type. Country of Origin: USA / UK / Germany / Italy / Korea / Singapore / OR Licensed Manufacturing units located Globally.

7.21.18.01

65 mm Ball Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 65 mm dia Ball Valve, Class: PN20

1.0000

each

8031.00

8031.00

Skilled Labour

2.0000

day

450.00

900.00 8931.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

223.28

Subtotal-A1: Subtotal-B: Subtotal-C:

9154.28 9337.36

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10271.10

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

684.74 456.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11412.33

Page: 2207 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.21.18.02

2 50 mm Ball Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 50 mm dia Ball Valve, Class: PN20

1.0000

each

5403.00

5403.00

Skilled Labour

2.0000

day

450.00

900.00 6303.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

157.58

Subtotal-A1: Subtotal-B: Subtotal-C:

6460.58 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6589.79

10% Profit ( Add 10% on Subtotal-B) :

7248.77

VAT

6% of Total

IT

4% of Total

483.25 322.17 Total:

7.21.18.03

40 mm Ball Valve

each 40 mm dia Ball Valve, Class: PN20

1.0000

each

2289.00

2289.00

Skilled Labour

2.0000

day

450.00

900.00 3189.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

79.73

Subtotal-A1:

3268.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3334.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3667.51

VAT

6% of Total

IT

4% of Total

244.50 163.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8054.18

4075.01

Page: 2208 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.21.18.04

2 25 mm Ball Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 25 mm dia Ball Valve, Class: PN20

1.0000

each

1794.00

1794.00

Skilled Labour

2.0000

day

450.00

900.00 2694.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

67.35

Subtotal-A1: Subtotal-B: Subtotal-C:

2761.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2816.58

10% Profit ( Add 10% on Subtotal-B) :

3098.23

VAT

6% of Total

IT

4% of Total

206.55 137.70 Total:

7.21.18.05

20 mm Ball Valve

each 20 mm dia Ball Valve, Class: PN20

1.0000

each

1398.00

1398.00

Skilled Labour

2.0000

day

450.00

900.00 2298.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

57.45

Subtotal-A1:

2355.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2402.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2642.81

VAT

6% of Total

IT

4% of Total

176.19 117.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3442.48

2936.46

Page: 2209 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.21.18.06

2 12 mm Ball Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 12 mm dia Ball Valve, Class: PN20

1.0000

each

765.00

765.00

Skilled Labour

2.0000

day

450.00

900.00 1665.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

41.63

Subtotal-A1: Subtotal-B: Subtotal-C:

1706.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1740.76

10% Profit ( Add 10% on Subtotal-B) :

1914.83

VAT

6% of Total

IT

4% of Total

127.66 85.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2127.59

Page: 2210 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.19

Detailed Analysis Brief Description of Item 2 Pressure Gauge: Supply and installation of 100mm dial type Pressure Gauges including supply of all accessories and consumable. The range shall be 0-250 psi. Country of Origin: Japan / Germany / EU / Korea or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

0-250 psi dial type pressure gauge with necessary accessories and sundry materials

1.0000

each

4000.00

4000.00

Skilled Labour

2.0000

day

450.00

900.00 4900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

122.50

Subtotal-A1: Subtotal-B: Subtotal-C:

5022.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5122.95

10% Profit ( Add 10% on Subtotal-B) :

5635.25

VAT

6% of Total

IT

4% of Total

375.68 250.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6261.38

Page: 2211 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.20

Detailed Analysis Brief Description of Item 2 Pressure Switch: Supply, installation and testing of Pressure Switch complete with sensing element, enclosure material, 15 mm NPT pressure connection, direct mounting electrical connection, other material etc. Accepted/approved by the Engineer Country of Origin: Japan / Germany / EU / Korea or their licensed manufacturing units located globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Electric operated pressure switch complete with sensing element and other standard accessories

1.0000

each

6500.00

6500.00

Skilled Labour

2.0000

day

450.00

900.00 7400.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

185.00

Subtotal-A1: Subtotal-B: Subtotal-C:

7585.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7736.70

10% Profit ( Add 10% on Subtotal-B) :

8510.37

VAT

6% of Total

IT

4% of Total

567.36 378.24 Total:

7.21.21

9455.97

Pressure Release Valve: Supply, installation and testing of Pressure Release valve of 50mm dia of cast iron / brass body with adjustable knob to adjust set pressure for release excess pressure from the system to safe the fire fighting system network to drain. The valve shall be installed at pump house in discharge header. The valve shall be suitable to withstand pressure of 12kg/cm². Inlet / outlet shall be flanged / threaded end type. Country of Origin: Japan / Germany / EU / Korea or their licensed manufacturing units located globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2212 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.21.01

Detailed Analysis Brief Description of Item 2 50 mm dia Pressure Release Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Pressure Release Valve,50 mm dia

1.0000

each

29935.00

29935.00

Skilled Labour

2.0000

day

450.00

900.00 30835.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

770.88

Subtotal-A1: Subtotal-B: Subtotal-C:

31605.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32237.99

10% Profit ( Add 10% on Subtotal-B) :

35461.79

VAT

6% of Total

IT

4% of Total

2364.12 1576.08 Total:

7.21.21.02

80 mm dia Pressure Release Valve

each Pressure Release Valve,80 mm dia

1.0000

each

40000.00

40000.00

Skilled Labour

2.0000

day

450.00

900.00 40900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

1022.50

Subtotal-A1:

41922.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

42760.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

47037.05

VAT

6% of Total

IT

4% of Total

3135.80 2090.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

39401.99

52263.38

Page: 2213 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.22

Detailed Analysis Brief Description of Item 2 Auto Air-Vent Valve: Supply & Installation of Auto Air vent valve of 25mm dia of 25mm dia inlet BSP, bronze made with rubber ball and seat. The valve shall be suitable to release air from the fire hydrant pipes. Shall be suitable to withstand pressure up to 10kg/cm². Country of Origin: Japan / Germany / EU / Korea or their licensed manufacturing units located globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

20 mm dia air-vent valve

1.0000

set

7000.00

7000.00

Skilled Labour

2.0000

day

450.00

900.00 7900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

197.50

Subtotal-A1:

8097.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8259.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9085.40

VAT

6% of Total

605.69

IT

4% of Total

403.80 Total:

7.21.23

10094.88

Flow Switch: Supply & Installation of Flow Switch of leaf type suitable for installation within 65mm and 50mm dia water hydrant pipe. The flow switch shall sense flow of water within pipe and send signal to water flow monitoring panel. Flow switch shall be under control of water flow supervisory Panel to ensure the hydrant operation. Power supply shall be 24V DC. The Flow Switch shall be UL Listed. Country of Origin: Japan / Germany / EU / Korea or their licensed manufacturing units located globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2214 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.23.01

2 100 mm dia Flow-switch

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Flow-switch 100 mm dia

1.0000

set

19000.00

19000.00

Skilled Labour

2.0000

day

450.00

900.00 19900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

497.50

Subtotal-A1: Subtotal-B: Subtotal-C:

20397.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20805.45

10% Profit ( Add 10% on Subtotal-B) :

22886.00

VAT

6% of Total

IT

4% of Total

1525.73 1017.16 Total:

7.21.23.02

80 mm dia Flow-switch

each Flow-switch 80 mm dia

1.0000

set

15000.00

15000.00

Skilled Labour

2.0000

day

450.00

900.00 15900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

397.50

Subtotal-A1:

16297.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16623.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18285.80

VAT

6% of Total

IT

4% of Total

1219.05 812.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25428.88

20317.55

Page: 2215 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.23.03

2 65 mm dia Flow-switch

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Flow-switch 65 mm dia

1.0000

set

12000.00

12000.00

Skilled Labour

2.0000

day

450.00

900.00 12900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

322.50

Subtotal-A1: Subtotal-B: Subtotal-C:

13222.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13486.95

10% Profit ( Add 10% on Subtotal-B) :

14835.65

VAT

6% of Total

IT

4% of Total

989.04 659.36 Total:

7.21.23.04

50 mm dia Flow-switch

each Flow-switch 50 mm dia

1.0000

set

9000.00

9000.00

Skilled Labour

2.0000

day

450.00

900.00 9900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

247.50

Subtotal-A1:

10147.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10350.45

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11385.50

VAT

6% of Total

IT

4% of Total

759.03 506.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

16484.05

12650.55

Page: 2216 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.21.24

Pressure Reducing Valve: Supply & Installation of Pressure Reducing valve of brass body, screwed end type, shall be used with Hydrant system (To reduce high pressure as necessary). Valve body shall be made of hot pressed brass, seat of stainless steel ANSI304 and suitable for 80°C. Initial pressure shall be 15 bar, adjustable final pressure shall be 0.5bar (min) to 7bar (max) Country of Origin: Japan / Germany / EU / Korea or their licensed manufacturing units located globally.

7.21.24.01

80 mm Pressure Reducing Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Pressure Reducing Valve:80mm dia

1.0000

each

30100.00

30100.00

Skilled Labour

2.0000

day

450.00

900.00 31000.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

775.00

Subtotal-A1: Subtotal-B: Subtotal-C:

31775.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32410.50

10% Profit ( Add 10% on Subtotal-B) :

35651.55

VAT

6% of Total

IT

4% of Total

2376.77 1584.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

39612.83

Page: 2217 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.24.02

Detailed Analysis Brief Description of Item 2 65 mm Pressure Reducing Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Pressure Reducing Valve:65mm dia

1.0000

each

27100.00

27100.00

Skilled Labour

2.0000

day

450.00

900.00 28000.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

700.00

Subtotal-A1: Subtotal-B: Subtotal-C:

28700.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

29274.00

10% Profit ( Add 10% on Subtotal-B) :

32201.40

VAT

6% of Total

IT

4% of Total

2146.76 1431.17 Total:

7.21.24.03

50 mm Pressure Reducing Valve

each Pressure Reducing Valve:50mm dia

1.0000

each

24100.00

24100.00

Skilled Labour

2.0000

day

450.00

900.00 25000.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

625.00

Subtotal-A1:

25625.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26137.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

28751.25

VAT

6% of Total

IT

4% of Total

1916.75 1277.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35779.33

31945.83

Page: 2218 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.21.24.04

Detailed Analysis Brief Description of Item 2 40 mm Pressure Reducing Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Pressure Reducing Valve:40mm dia

1.0000

each

21130.00

21130.00

Skilled Labour

2.0000

day

450.00

900.00 22030.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

550.75

Subtotal-A1: Subtotal-B: Subtotal-C:

22580.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23032.37

10% Profit ( Add 10% on Subtotal-B) :

25335.60

VAT

6% of Total

IT

4% of Total

1689.04 1126.03 Total:

7.21.25

28150.67

Sprinklar Head: Supply & Installation of Sprinklar head of 12 mm diameter nominal orifice, K-Factor 5.6 chrome finish glass bulb type. Temparature rating 68°C for general area others area shall be specified as per requirement. Sprinklar head shall be UL Listed / FM Approved.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2219 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.25.01

2 Pendent Type Sprinkler Head

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Pendent Type Sprinkler Head

1.0000

each

1460.00

1460.00

Skilled Labour

2.0000

day

450.00

900.00 2360.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

59.00

Subtotal-A1: Subtotal-B: Subtotal-C:

2419.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2467.38

10% Profit ( Add 10% on Subtotal-B) :

2714.12

VAT

6% of Total

IT

4% of Total

180.94 120.63 Total:

7.21.25.02

Up-Right type Sprinkler Head

each Up-Right type Sprinkler Head

1.0000

each

1397.00

1397.00

Skilled Labour

2.0000

day

450.00

900.00 2297.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

57.43

Subtotal-A1:

2354.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2401.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2641.66

VAT

6% of Total

IT

4% of Total

176.11 117.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3015.69

2935.18

Page: 2220 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.25.03

2 Side wall type Sprinkler Head

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Side wall type Sprinkler Head

1.0000

each

1730.00

1730.00

Skilled Labour

2.0000

day

450.00

900.00 2630.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

65.75

Subtotal-A1: Subtotal-B: Subtotal-C:

2695.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2749.67

10% Profit ( Add 10% on Subtotal-B) :

3024.63

VAT

6% of Total

IT

4% of Total

201.64 134.43 Total:

7.21.26

3360.70

Sprinklar Alarm Check Valve: Supply & Installation of Sprinkler Alarm Check Valve (Wet Riser Type) The valve shall be actuated by breaking of sprinkler glass bulb. The valve shall be UL Listed /FM approved Country of Origin: Japan / Germany / EU / Korea or their licensed manufacturing units located globally.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2221 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.26.01

2 150 mm dia Alarm Check Valve

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 6" Alarm Check Valve

1.0000

each

250000.00

250000.00

Skilled Labour

2.0000

day

450.00

900.00 250900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

6272.50

Subtotal-A1: Subtotal-B: Subtotal-C:

257172.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

262315.95

10% Profit ( Add 10% on Subtotal-B) :

288547.55

VAT

6% of Total

IT

4% of Total

19236.50 12824.34 Total:

7.21.26.02

100 mm dia Alarm Check Valve

each 4" Alarm Check Valve

1.0000

each

200000.00

200000.00

Skilled Labour

2.0000

day

450.00

900.00 200900.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

5022.50

Subtotal-A1:

205922.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

210040.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

231045.05

VAT

6% of Total

IT

4% of Total

15403.00 10268.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

320608.38

256716.72

Page: 2222 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

7.21.27

Water Flow Monitoring Panel: Supply & Installation of Water Flow Monitoring Panel to monitor water flow of Hydrant units. After receiving Close Contact through flow switches Indication will be at Panel and buzzer will be activated. Power supply: 230V AC ± 10%. Network power shall be 24V DC. The panel shall be Conventional type, complete with LED indication, keypad, trickle charger, rechargeable batteries etc. Country of Origin: Japan / Germany / EU / Korea or their licensed manufacturing units located globally.

7.21.27.01

WFMP for 8 nos of Hydrant

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Water Flow Monitoring panel for 8 nos of Hydrant

1.0000

each

80630.00

80630.00

Skilled Labour

2.0000

day

450.00

900.00 81530.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

2038.25

Subtotal-A1: Subtotal-B: Subtotal-C:

83568.25 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

85239.62

10% Profit ( Add 10% on Subtotal-B) :

93763.58

VAT

6% of Total

IT

4% of Total

6250.91 4167.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

104181.75

Page: 2223 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.21.27.02

2 WFMP for 16 nos of Hydrant

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Water Flow Monitoring panel for 16 nos of Hydrant

1.0000

each

100900.00

100900.00

Skilled Labour

2.0000

day

450.00

900.00 101800.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

2545.00

Subtotal-A1: Subtotal-B: Subtotal-C:

104345.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

106431.90

10% Profit ( Add 10% on Subtotal-B) :

117075.09

VAT

6% of Total

IT

4% of Total

7805.01 5203.34 Total:

7.21.27.03

WFMP for 24 nos of Hydrant

each Water Flow Monitoring panel for 24 nos of Hydrant

1.0000

each

150660.00

150660.00

Skilled Labour

2.0000

day

450.00

900.00 151560.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

3789.00

Subtotal-A1:

155349.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

158455.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

174301.58

VAT

6% of Total

IT

4% of Total

11620.11 7746.74 Total:

7.21.28

130083.43

193668.42

Balancing, Testing & Commissioning of Fire Hydrant system.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2224 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.21.28.01

2 For Level: 1 to 5

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

2.0000

day

1800.00

3600.00

Diploma Engineer (Daily Basis)

4.0000

day

750.00

3000.00

Foreman

4.0000

day

800.00

3200.00

Fire Mechanics Electricians Plumber/ Electric Mistry/ Painter

4.0000

day

700.00

2800.00

12.0000

day

600.00

7200.00

8.0000

day

680.00

5440.00 25240.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc. Consumables like jute, cloth, copper brush, thread tap, welding rod, adjustable nuts etc. in/c T & P Charge Hire charge of testing equipment (water pressure testing equipment, earth tester, chain pulley, tripod)

( +2.50 % on Subtotal-A )

631.00

( +5.00 % on Subtotal-A )

1262.00

( +5.00 % on Subtotal-A )

1262.00

Subtotal-A1:

28395.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28962.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

31859.19

VAT

6% of Total

2123.95

IT

4% of Total

1415.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35399.10

Page: 2225 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.21.28.02

2 For next level

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

0.5000

day

1800.00

900.00

Diploma Engineer (Daily Basis)

0.5000

day

750.00

375.00

Foreman

1.0000

day

800.00

800.00

Fire Mechanics

1.0000

day

700.00

700.00

Electricians

1.0000

day

600.00

600.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00 4055.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc. Consumables like jute, cloth, copper brush, thread tap, welding rod, adjustable nuts etc. in/c T & P Charge Hire charge of testing equipment (water pressure testing equipment, earth tester, chain pulley, tripod)

( +.00 % on Subtotal-A )

0.00

( +2.50 % on Subtotal-A ) ( +5.00 % on Subtotal-A )

101.38 202.75

( +5.00 % on Subtotal-A )

202.75

Subtotal-A1:

4561.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4653.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5118.42

VAT

6% of Total

341.23

IT

4% of Total

227.49 Total:

7.22

Conventional Fire Alarm & Detection System

7.22.01

Conventional Fire Alarm Control Panels:

Note : Rates of all items should be inclusive of all supply and carriage.

5687.14

Page: 2226 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.22.01.01

Detailed Analysis Brief Description of Item 2 Fire Alarm Control Panel : 08 Zone Capacity Supply and Installation of 08 Zone Conventional Fire alarm control panel with power supply unit, batteries and other accessories. The panel shall be complete with zone indicating LED, Fault indication and optional telephone Jack etc. The panel shall have input 220V AC and output 24V DC. Panel shall be Confirmed UL Listed or FM Approved.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

08- zone conventional fire-alarm control panel with power supply unit including batteries and other accessories etc. complete

1.0000

set

79142.00

79142.00

Skilled Labour

3.0000

day

450.00

1350.00 80492.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

2012.30

Subtotal-A1: Subtotal-B: Subtotal-C:

82504.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84154.39

10% Profit ( Add 10% on Subtotal-B) :

92569.82

VAT

6% of Total

IT

4% of Total

6171.32 4114.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

102855.36

Page: 2227 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.22.01.02

Detailed Analysis Brief Description of Item 2 Fire Alarm Control Panel : 16 Zone Capacity Supply and Installation of 16 Zone Conventional Fire alarm control panel with power supply unit, batteries and other accessories. The panel shall be complete with zone indicating LED, Fault indication and optional telephone Jack etc. The panel shall have input 220V AC and output 24V DC. Panel shall be Confirmed UL Listed or FM Approved.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

16- zone conventional fire-alarm control panel with power supply unit including batteries and other accessories etc. complete

1.0000

set

98926.00

98926.00

Skilled Labour

3.0000

day

450.00

1350.00 100276.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

2506.90

Subtotal-A1: Subtotal-B: Subtotal-C:

102782.90 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

104838.56

10% Profit ( Add 10% on Subtotal-B) :

115322.41

VAT

6% of Total

IT

4% of Total

7688.16 5125.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

128136.02

Page: 2228 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.22.01.03

Detailed Analysis Brief Description of Item 2 Fire Alarm Control Panel : 24 Zone Capacity Supply and Installation of 24 Zone Conventional Fire alarm control panel with power supply unit, batteries and other accessories. The panel shall be complete with zone indicating LED, Fault indication and optional telephone Jack etc. The panel shall have input 220V AC and output 24V DC. Panel shall be Confirmed UL Listed or FM Approved.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

24- zone conventional fire-alarm control panel with power supply unit including batteries and other accessories etc. complete

1.0000

set

150000.00

150000.00

Skilled Labour

3.0000

day

450.00

1350.00 151350.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

3783.75

Subtotal-A1: Subtotal-B: Subtotal-C:

155133.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

158236.43

10% Profit ( Add 10% on Subtotal-B) :

174060.07

VAT

6% of Total

IT

4% of Total

11604.00 7736.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

193400.08

Page: 2229 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.22.02

2 Manual Call Point: Supply and installation of conventional type manual call point like break glass switch or single action pull station complete with back box and all other accessories and consumables. Power supply shall be 24V DC. According to UL listed or FM approved / NFPA or equivalent standard . Country of Origin : Australia / USA / Japan / Malaysia / EU countries / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Push-button manual call point and accessories

1.0000

set

4946.00

4946.00

Skilled Labour

0.5000

day

450.00

225.00 5171.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

129.28

Subtotal-A1:

5300.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5406.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5946.91

VAT

6% of Total

396.46

IT

4% of Total

264.31 Total:

7.22.03

6607.68

Notification Devices:

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2230 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.22.03.01

Detailed Analysis Brief Description of Item 2 Fire Alarm Bell: Supply and installation of Conventional type Fire Alarm Bell of 150mm dia , red color, shall be UL / ULC listed / CSFM / FM / MEA / BFP / EN54 approved. Power supply shall be 24VDC. Sound level shall be not less than 92 dBA @ 3meter. Color of the Bell shall be red. Country of Origin : Australia / USA / Japan / Malaysia / EU countries / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Fire alarm bell with all accessories

1.0000

set

5113.00

5113.00

Skilled Labour

0.5000

day

450.00

225.00 5338.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

133.45

Subtotal-A1:

5471.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5580.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6138.97

VAT

6% of Total

409.26

IT

4% of Total

272.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6821.07

Page: 2231 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.22.03.02

Detailed Analysis Brief Description of Item 2 Horn: Supply and installation of Conventional type Horn for notification purpose suitable to produce electronic sound level of 87 to 95 dBA @ 3 meter complete with back box. , red color, shall be UL / ULC listed / CSFM / FM / MEA / BFP / EN54 approved. Power supply shall be 24VDC. Color of the device shall be red. Country of Origin : Australia / USA / Japan / Malaysia / EU countries / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Fire Horn with all accessories

1.0000

set

4912.00

4912.00

Skilled Labour

0.5000

day

450.00

225.00 5137.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

128.43

Subtotal-A1: Subtotal-B: Subtotal-C:

5265.43 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5370.73

10% Profit ( Add 10% on Subtotal-B) :

5907.81

VAT

6% of Total

IT

4% of Total

393.85 262.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6564.23

Page: 2232 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.22.03.03

Detailed Analysis Brief Description of Item 2 Strobe / Horn with Strobe: Supply and installation of Conventional type Horn for notification purpose suitable to produce electronic sound level of 87 to 95 dBA @ 3 meter complete with back box. , red color, shall be UL / ULC listed / CSFM / FM / MEA / BFP / EN54 approved. Power supply shall be 24V DC. Color of the device shall be red. Country of Origin : Australia / USA / Japan / Malaysia / EU countries / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Strobe with all accessories

1.0000

set

5144.00

5144.00

Skilled Labour

0.5000

day

450.00

225.00 5369.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

134.23

Subtotal-A1: Subtotal-B: Subtotal-C:

5503.23 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5613.29

10% Profit ( Add 10% on Subtotal-B) :

6174.62

VAT

6% of Total

IT

4% of Total

411.64 274.43 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6860.69

Page: 2233 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.22.04

Detailed Analysis Brief Description of Item 2 Optical / Photoelectric Smoke Detector: Supply and installation of Smoke Detector complete with base. Shall be UL / ULC listed / CSFM / FM / MEA / BFP / EN54 approved. Integrated alarm LED. Remote LED connection. Power supply shall be 24V DC. Country of Origin : Australia / USA / Japan / Malaysia / EU countries / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Photo electric smoke detector

1.0000

set

4947.00

4947.00

Skilled Labour

0.5000

day

450.00

225.00 5172.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

129.30

Subtotal-A1: Subtotal-B: Subtotal-C:

5301.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5407.33

10% Profit ( Add 10% on Subtotal-B) :

5948.06

VAT

6% of Total

IT

4% of Total

396.54 264.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6608.95

Page: 2234 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.22.05

Detailed Analysis Brief Description of Item 2 Heat Detector: Supply and installation of Heat Detector complete with base. Shall be UL / ULC listed/ CSFM / FM / MEA / BFP / EN54 approved. Integrated alarm LED. Remote LED connection. Power supply shall be 24V DC. Country of Origin : Australia / USA / Japan / Malaysia / EU countries / Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Heat Detector

1.0000

set

4947.00

4947.00

Skilled Labour

0.5000

day

450.00

225.00 5172.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

129.30

Subtotal-A1: Subtotal-B: Subtotal-C:

5301.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5407.33

10% Profit ( Add 10% on Subtotal-B) :

5948.06

VAT

6% of Total

IT

4% of Total

396.54 264.36 Total:

7.22.06

6608.95

Balancing, Testing & Commissioning of Fire Detection & Alarm System

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2235 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.22.06.01

2 For 8 Zone

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

1.0000

day

1800.00

1800.00

Diploma Engineer (Daily Basis)

2.0000

day

750.00

1500.00

Foreman

2.0000

day

800.00

1600.00

Fire Mechanics

2.0000

day

700.00

1400.00

Electricians

8.0000

day

600.00

4800.00

Ordinary Labour

8.0000

day

370.00

2960.00 14060.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

351.50

Subtotal-A1: Subtotal-B: Subtotal-C:

14411.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14699.73

10% Profit ( Add 10% on Subtotal-B) :

16169.70

VAT

6% of Total

1077.98

IT

4% of Total

718.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17966.34

Page: 2236 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.22.06.02

2 For 16 Zone

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

2.0000

day

1800.00

3600.00

Diploma Engineer (Daily Basis)

4.0000

day

750.00

3000.00

Foreman

4.0000

day

800.00

3200.00

Fire Mechanics

4.0000

day

700.00

2800.00

Electricians

16.0000

day

600.00

9600.00

Ordinary Labour

16.0000

day

370.00

5920.00 28120.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

703.00

Subtotal-A1: Subtotal-B: Subtotal-C:

28823.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

29399.46

10% Profit ( Add 10% on Subtotal-B) :

32339.41

VAT

6% of Total

2155.96

IT

4% of Total

1437.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35932.67

Page: 2237 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.22.06.03

2 For 24 Zone

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

4.0000

day

1800.00

7200.00

Diploma Engineer (Daily Basis)

8.0000

day

750.00

6000.00

Foreman

8.0000

day

800.00

6400.00

Fire Mechanics

8.0000

day

700.00

5600.00

Electricians

32.0000

day

600.00

19200.00

Ordinary Labour

32.0000

day

370.00

11840.00 56240.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

1406.00

Subtotal-A1: Subtotal-B: Subtotal-C:

57646.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

58798.92

10% Profit ( Add 10% on Subtotal-B) :

64678.81

VAT

6% of Total

4311.92

IT

4% of Total

2874.61 Total:

7.23

71865.35

Fire Detection & Alarm System

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2238 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Addressable Type Fire Alarm Control Panel: Supply & Installation of Addressable type Fire Alarm Control Panel complete with following basic options. Master Controller Assembly / CPU shall be suitable with port to add Voice alarm system / Fire Fighter Telephone system / Printer / Remote Annunciator etc. FACP must be comply with internationally accepted standard. Control units for Fire Protective Signaling Systems". Addressable Fire Alarm Control Panel shall be complete, non-coded, Addressable, microprocessor based with initiating devices, notification appliances, and monitoring and control devices. Annunciation: Operation of alarm and supervisory initiating devices shall be annunciated at the FACP indicating the location and type of device. Monitoring: FACP shall individually monitor sensors for calibration, sensitivity, and alarm condition, and shall individually adjust for sensitivity. The control unit shall determine the condition of each sensor by comparing the sensor value to the stored values. Environmental Compensation: The FACP shall maintain a moving average of the sensor's smoke chamber value to automatically compensate for dust, dirt, and other conditions that could affect detection operations. Programmable Sensitivity : Photoelectric Smoke Sensors shall have various sensitivity levels ranging from (±) 0.2% up to 3.7%, programmed and monitored from the FACP. Sensitivity Testing Reports: The FACP shall provide sensor reports that meet NFPA /internationally accepted standard calibrated test method requirements. The reports shall be viewed on a CRT Display or printed for annual recording and logging of the calibration maintenance schedule. The FACP shall automatically indicate when an individual sensor needs cleaning. The system shall provide a means to indicate that a sensor requires cleaning. When a sensor's average value reaches a predetermined value, (3) progressive levels of reporting are provided. The first level shall indicate that a sensor is close to a trouble reporting condition and will be indicated on the FACP as "ALMOST DIRTY." This condition provides a means to alert maintenance staff of a dirty sensor without creating a trouble in the system. If this indicator is ignored, a second level "DIRTY SENSOR" condition shall be indicated at the FACP and subsequently a system trouble is reported [to the Central Monitoring Station]. The sensor base LED shall

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2239 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

glow steady giving a visible indication at the sensor location. The "DIRTY SENSOR" condition shall not affect the sensitivity level required to alarm the sensor. If a "DIRTY SENSOR" is left unattended, and its average value increases to a third predetermined value, an "EXCESSIVELY DIRTY SENSOR" trouble condition shall be indicated at the control unit. The FACP shall continuously perform an automatic self-test on each sensor which will check sensor electronics and ensure the accuracy of the values being transmitted. Any sensor that fails this test shall indicate a "SELF TEST ABNORMAL" trouble condition. Options at FACP : The control panel operator shall be able to make announcements via the push-to-talk paging microphone over the preselected speakers. Soft touch keypad, LED indications, LCD Display. Facility for total building paging shall be accomplished by the means of an "All Call" switch. Firefighter's phone (Optional) : Provide a supervised, two-way communication system between the Command Center/main fire alarm control panel and emergency phones. The firefighter's phone system shall be capable of handling single or simultaneous conversations with all phones connected into the system. As many as seven (7) phones shall be able to be connected into the active conversation. The phone system circuits shall be designed to prevent static, hum or other interference for clear, intelligible two-way conversation among all phones of the system. The phone system circuits shall be supervised, such that the FACP shall be able to differentiate between whether a handset has been plugged into the emergency phone jack or whether the circuit has a shorted wire. A beeping busy signal shall indicate to the person attempting to use a remote phone that the signal is being received at the control unit and that the lines are intact. The act of plugging a handset into an emergency phone jack or removal of any phone from its normal hook position shall cause an audible and visual indication at the control unit. Picking up the master phone and acknowledgment of the phone circuit shall silence the tone and allow for direct two-way communications. The act of unplugging handsets in use and replacement of remote phones will return the phone circuits to their normal supervisory functions. The FACP shall be provided with sufficient battery capacity to operate Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2240 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

the entire system upon loss of normal AC power in a normal supervisory mode for a period of 24 hours with 5 minutes of alarm operation at the end of this period. The system shall automatically transfer to battery standby upon power failure. All battery charging and recharging operations shall be automatic. Battery: Sealed lead-acid. Provide sufficient capacity to operate the complete alarm system in normal or supervisory (non-alarm) mode for a period of 24 hours. Following this period of operation on battery power, the battery shall have sufficient capacity to operate all components of the system, including all alarm indicating devices in alarm or supervisory mode for a period of 5 minutes. Power Supply (Input Power) shall be 240VAC. All circuits requiring system-operating power shall be 24 VDC and shall be individually fused at the control unit. The incoming power to the system shall be supervised so that any power failure will be indicated at the control unit. A green "power on" LED shall be displayed continuously while incoming power is present. The system batteries shall be supervised so that a low battery or depleted battery condition or disconnection of the battery shall be indicated at the control unit and displayed for the specific fault type. The system shall support 100% of addressable devices in alarm or operated at the same time, under both primary (AC) and secondary (battery) power conditions. Loss of primary power shall sound a trouble signal at the FACP. FACP shall indicate when the system is operating on an alternate power supply. Product data sheets for system components highlighted to indicate the specific products, features, or functions required to meet this specification. Alternate or as-equal products submitted under this contract must provide a detailed line-by-line comparison of how the submitted product meets, exceeds, or does not comply with this specification. Wiring diagrams, Shop drawings showing system details including location of FACP, all devices, circuiting and details of graphic annunciator. System Power and battery charts with performance graphs and voltage drop calculations to assure that the system will operate per the prescribed backup time periods and under all voltage conditions per UL and NFPA standards. System operation description including method of operation and Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2241 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

supervision of each type of circuit and sequence of operations for all manually and automatically initiated system inputs and outputs. A list of all input and output points in the system shall be provided with a label indicating location or use of IDC, NAC, relay, sensor, and auxiliary control circuits. Alphanumeric Display and System Controls: Panel shall be included an 80 character LCD display to indicate alarm, supervisory, and component status messages and shall include a keypad for use in entering and executing control commands. Voice Alarm: Provide an emergency communication system, integral with the FACP, including voice alarm system components, microphones, amplifiers, and tone generators. Features include: Amplifiers comply with UL 1711, "Amplifiers for Fire Protective Signaling Systems." Amplifiers shall provide an onboard local mode temporal coded horn tone as a default backup tone. Test switches on the amplifier shall be provided to test and observe amplifier backup switchover. Each amplifier shall communicate to the host panel amplifier and NAC circuit voltage and current levels for display on the user interface. All announcements shall made over dedicated, supervised communication lines. All risers shall support [Class A][Class B] wiring for each audio channel. Emergency voice communication audio controller module shall provide up to 30 minutes of message memory for digitally stored messages. Provide supervised connections for master microphone and up to 5 remote microphones. Fire fighters' telephone communication system: Arrange system to use dedicated, two-way, supervised voice communication links between the FACP and remote fire fighters' telephone stations throughout the building. Fire Alarm Control Unit shall be capable of operating remote CRT's and/or printers; output shall be ASCII from an RS connection with an adjustable baud rate. Fire Alarm Control Unit shall be capable of operating a PC Annunciator which provides status annunciation and limited system control using a convenient and familiar Microsoft Windows® 2000 operating system based interface. PC Annunciator shall provide the following functions: FACP shall be with Login / Logoutsword protection with time duration selectable automatic logout. Displays: Alarm, Supervisory, Priority 2, and Trouble conditions with numerical tallies for each displays first and last Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2242 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

alarms. Different event types have separate visible indicators with common audible indicator. Event logs can be searched and printed. View and / or print status reports and service reports (printing requires and available local or network printer). Alarm Silence, System Reset and priority to reset global and individual point acknowledge. Set system time and date and clear event log, individual point access for control or parameter revisions. Each RS port shall be capable of supporting and supervising a remote Printer; the FACP shall support as many as remote displays. The Fire Alarm Control Panel shall support five RS ports. Cabinet shall be Lockable steel enclosure. Arrange unit so all operations required for testing or for normal care and maintenance of the system are performed from the front of the enclosure. If more than a single unit is required to form a complete control unit, provide exactly matching modular unit enclosures. Operation and maintenance data for inclusion in Operating and Maintenance Manual. Include data for each type product, including all features and operating sequences, both automatic and manual. Provide the names, addresses, and telephone numbers of service organizations. Operating Temperature Range: 32° to 120°F (0° to 49°C) Operating Humidity Range: Up to 93% RH, non-condensing @ 90° F (32° C) maximum Approvals: UL, ULC Listed/, FM approved/ CSFM approved.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2243 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.01.01

Detailed Analysis Brief Description of Item 2 FACP for up to 250 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Fire Alarm Control Panel for up to 250 Addressable Devices (Max) with all accessories

1.0000

set

450000.00

450000.00

Diploma Engineer (Daily Basis)

1.0000

day

750.00

750.00

Electricians

1.0000

day

600.00

600.00

Skilled Labour

3.0000

day

450.00

1350.00 452700.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

11317.50

Subtotal-A1:

464017.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

473297.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

520627.64

VAT

6% of Total

IT

4% of Total

34708.51 23139.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

578475.15

Page: 2244 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.01.02

Detailed Analysis Brief Description of Item 2 FACP for up to 500 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Fire Alarm Control Panel for up to 500 Addressable Devices (Max) with all accessories

1.0000

set

533000.00

533000.00

Diploma Engineer (Daily Basis)

1.0000

day

750.00

750.00

Electricians

1.0000

day

600.00

600.00

Skilled Labour

3.0000

day

450.00

1350.00 535700.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

13392.50

Subtotal-A1:

549092.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

560074.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

616081.79

VAT

6% of Total

IT

4% of Total

41072.12 27381.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

684535.32

Page: 2245 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.01.03

Detailed Analysis Brief Description of Item 2 FACP for up to 750 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Fire Alarm Control Panel for up to 750 Addressable Devices (Max) with all accessories

1.0000

set

640000.00

640000.00

Diploma Engineer (Daily Basis)

1.0000

day

750.00

750.00

Electricians

1.0000

day

600.00

600.00

Skilled Labour

3.0000

day

450.00

1350.00 642700.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

16067.50

Subtotal-A1:

658767.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

671942.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

739137.14

VAT

6% of Total

IT

4% of Total

49275.81 32850.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

821263.48

Page: 2246 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.01.04

Detailed Analysis Brief Description of Item 2 FACP for up to 1000 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Fire Alarm Control Panel for up to 1000 Addressable Devices (Max) with all accessories

1.0000

set

732000.00

732000.00

Diploma Engineer (Daily Basis)

1.0000

day

750.00

750.00

Electricians

1.0000

day

600.00

600.00

Skilled Labour

3.0000

day

450.00

1350.00 734700.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

18367.50

Subtotal-A1:

753067.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

768128.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

844941.74

VAT

6% of Total

IT

4% of Total

56329.45 37552.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

938824.15

Page: 2247 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.01.05

Detailed Analysis Brief Description of Item 2 FACP for up to 1500 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Fire Alarm Control Panel for up to 1500 Addressable Devices (Max) with all accessories

1.0000

set

881700.00

881700.00

Diploma Engineer (Daily Basis)

1.0000

day

750.00

750.00

Electricians

1.0000

day

600.00

600.00

Skilled Labour

3.0000

day

450.00

1350.00 884400.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

22110.00

Subtotal-A1: Subtotal-B: Subtotal-C:

906510.00 924640.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1017104.22

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

67806.95 45204.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1130115.80

Page: 2248 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.01.06

Detailed Analysis Brief Description of Item 2 FACP for up to 2000 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Fire Alarm Control Panel for up to 2000 Addressable Devices (Max) with all accessories

1.0000

set

1138000.00

1138000.00

Diploma Engineer (Daily Basis)

1.0000

day

750.00

750.00

Electricians

1.0000

day

600.00

600.00

Skilled Labour

3.0000

day

450.00

1350.00 1140700.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

28517.50

Subtotal-A1:

1169217.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1192601.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1311862.04

VAT

6% of Total

IT

4% of Total

87457.47 58304.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1457624.48

Page: 2249 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.02

Detailed Analysis Brief Description of Item 2 Repeater Panel / Remote Annunciator: Supply & Installation of Repeater Panel / Remote LCD Annunciator with the same "look and feel" as the FACP operator interface. The Remote LCD Annunciator shall use the same Primary Acknowledge, Silence, and Reset Keys, Status LEDs and LCD Display as the FACP. Annunciator shall have super-twist LCD display with two lines of 40 characters each. Annunciator shall be provided with programmable control switches and associated LEDs. Under normal conditions the LCD shall display a "SYSTEM IS NORMAL" message and the current time and date. Should an abnormal condition be detected the appropriate LED (Alarm, Supervisory or Trouble) shall flash. The unit audible signal shall pulse for alarm conditions and sound steady for trouble and supervisory conditions. The LCD shall display the following information relative to the abnormal condition of a point in the system: 40 character location label. Type of device (e.g. smoke / pull station / water flow etc.). Point status (e.g. alarm / trouble). Operator keys shall be key switch enabled to prevent unauthorized use. The key shall only be removable in the disabled position. Acknowledge, Silence and Reset operation shall be the same as the FACP Voltage: 20 to 32 VDC, system supplied Operating temperature range shall be : 0° to 40°C Operating Humidity Range: 10% to 90% from 0° to 40°C The Panel shall be fixed on wall with Surface mount box. Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Liscenced manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set

Repeater Panel with all accessories

1.0000

set

163000.00

163000.00

Diploma Engineer (Daily Basis)

1.0000

day

750.00

750.00

Electricians

1.0000

day

600.00

600.00

Skilled Labour

3.0000

day

450.00

1350.00 165700.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4142.50 169842.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

173239.35 Page: 2250 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

Amount 8 190563.29

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

12704.22 8469.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

211736.98

Page: 2251 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.03

Detailed Analysis Brief Description of Item 2 Multi Detector / Multi Sensors: Supply & Installation of Multi-Sensors shall be combined with photoelectric smoke sensing and heat sensing technologies complete with standard base. An alarm shall be determined by either smoke detection, with selectable sensitivity from 0.2 to 3.7 %/ft obscuration; or heat detection, selectable as fixed temperature or fixed with selectable rate-of-rise; or based on an analysis of the combination of smoke and heat activity. The Sensors shall be complete with Programmable standard bases. It shall be possible to program relay and sounder bases to operate independently of their associated sensor. Magnet test activation of smoke sensors shall be distinguished by its label and history log entry as being activated by a magnet. shall be suitable for 360° smoke entry for optimum response, photoelectric light scattering sensing technology. The detector shall be functional and architecturally styled enclosures for ceiling or wall mounting. Smoke sensor louver design that directs air flow to chamber enhancing smoke capture. Shall be designed for EMI compatibility, RFI shielded. UL Listed temperature Range shall be: 0° to 38°C and Operating temperature range shall be : 0° to 50°C Shall be suitable for Humidity range: 10% to 95% RH Housing color shall be Frost White. Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Multy Detector addressable type

1.0000

set

7700.00

7700.00

Skilled Labour

1.0000

day

450.00

450.00 8150.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

203.75

Subtotal-A1: Subtotal-B: Subtotal-C:

8353.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8520.83

10% Profit ( Add 10% on Subtotal-B) :

9372.91

VAT

6% of Total

IT

4% of Total

624.86 416.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10414.34

Page: 2252 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Page: 2253 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.04

Detailed Analysis Brief Description of Item 2 Addressable type Photoelectric Smoke Detector: Supply & Installation of Addressable type Photoelectric Smoke Detector c/w Standard Base. Comply with internationally accepted standard “Smoke Detectors for Fire Protective Signaling Systems." Include the following features: The detector shall be Self-Restoring: Detectors do not require resetting or readjustment after actuation to restore normal operation. Sensors shall be with Plug-In Arrangement and associated electronic components are mounted in a module that connects to a fixed base with a twist-locking plug connection. Base shall provide break-off plastic tab that can be removed to engage the head/base locking mechanism. No special tools shall be required to remove head once it has been locked. Removal of the detector head shall interrupt the supervisory circuit of the fire alarm detection loop and cause a trouble signal at the control unit. Sensors shall be with Quick Connect Arrangement: Photoelectric sensor and electronics in a single piece construction which shall twistlock onto a mounting base that attaches to a standard electrical box. Each sensor base shall contain an LED that will flash each time it is scanned by the Control Unit (once every 4 seconds). In alarm condition, the sensor base LED shall be on steady. Each sensor base shall contain a magnetically actuated test switch to provide for easy alarm testing at the sensor location. Each sensor shall be scanned by the Control Unit for its type identification to prevent inadvertent substitution of another sensor type. Upon detection of a "wrong device", the control unit shall operate with the installed device at the default alarm settings for that sensor; 2.5% obscuration for photoelectric sensor, 135-deg F and 15deg F rate-of-rise for the heat sensor, but shall indicate a "Wrong Device" trouble condition. The sensor's electronics shall be immune from false alarms caused by EMI and RFI. Sensors shall be including a communication transmitter and receiver in the mounting base having a unique identification and capability for status reporting to the FACP. Sensor address shall be located in base to eliminate false addressing when replacing sensors. Removal of the sensor head for cleaning shall not require the setting of addresses. UL Listed temperature Range shall be: 0° to 38°C and Operating temperature range shall be : 0° to 50°C Shall be suitable for Humidity range: 10% to 95% RH Housing color shall be Frost White. Smoke sensor Ambient Ratings: Air Velocity = 0-2000 ft/min (0-

Note : Rates of all items should be inclusive of all supply and carriage.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Page: 2254 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

610m/min) Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally. Photo electric smoke detector addressable type

1.0000

set

7000.00

7000.00

Skilled Labour

1.0000

day

450.00

450.00 7450.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

186.25

Subtotal-A1:

7636.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7788.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8567.87

VAT

6% of Total

571.19

IT

4% of Total

380.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9519.86

Page: 2255 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.05

Detailed Analysis Brief Description of Item 2 Addressable Type Heat Detector: Supply & Installation of Addressable type Heat Detector / Thermal Sensor: Combination fixed-temperature and rate-of-rise unit with plug-in base and alarm indication lamp; 135° F fixed-temperature setting except as indicated. Thermal sensor shall be of the epoxy encapsulated electronic design. It shall be thermostat-based, rate-compensated, selfrestoring and shall not be affected by thermal lag. The Heat Sensors of fixed temperature sensing shall be independent of rate-of-rise sensing and programmable to operate at 135° F or 155° F. Sensor rate-of-rise temperature detection shall be selectable at the FACP for either 15° F or 20° F per minute. The Heat Sensors shall have the capability to be programmed as a utility monitoring device to monitor for temperature extremes in the range from 32-deg F to 155-deg F. UL Listed temperature Range shall be: 0° to 38°C and Operating temperature range shall be : 0° to 50°C Shall be suitable for Humidity range: 10% to 95% RH Housing color shall be Frost White. Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Addressable Type Heat Detector

1.0000

set

6170.00

6170.00

Skilled Labour

1.0000

day

450.00

450.00 6620.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

165.50

Subtotal-A1: Subtotal-B: Subtotal-C:

6785.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6921.21

10% Profit ( Add 10% on Subtotal-B) :

7613.33

VAT

6% of Total

IT

4% of Total

507.56 338.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8459.26

Page: 2256 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

7.23.06

Addressable Manual Pull Station: Supply & Installation of Addressable type Manual Call Station of red LEXAN, with molded, raised-letter operating instructions of contrasting color. Station will mechanically latch upon operation and remain so until manually reset by opening with a key common with the control units. Shall be with compact construction, suitable to Electronics module encloure minimizes dust infiltration. Allows mounting in standard electrical boxes. Screw terminals for wiring connections. Activation of the MCS will required a firm downward pull to activate the alarm switch. The pull lever latches into the alarm position and remains extended out of the housing to provide a visible indication. UL Listed Temperature Range: 32° to 120° F (0° to 49° C) intended for indoor operation. Humidity Range: Up to 93% RH at 100°F (38°C) Housing Colour shall be Red with white raised lettering. Housing and pull lever shall be made with Lexan Polycarbonate or equal. The MCS shall be semi-flash / surface mount type. Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally.

7.23.06.01

Addressable Manual Pull Station : Single action

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Addressable Manual Pull Station : Single action

1.0000

set

7000.00

7000.00

Skilled Labour

0.5000

day

450.00

225.00 7225.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

180.63

Subtotal-A1:

7405.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7553.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8309.11

VAT

6% of Total

553.94

IT

4% of Total

369.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9232.35

Page: 2257 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.06.02

Detailed Analysis Brief Description of Item 2 Addressable Manual Pull Station : Double action

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Addressable Manual Pull Station : Double action

1.0000

set

8600.00

8600.00

Skilled Labour

0.5000

day

450.00

225.00 8825.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

220.63

Subtotal-A1: Subtotal-B: Subtotal-C:

9045.63 9226.54

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10149.19

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

676.61 451.08 Total:

7.23.07

11276.88

Addressable Notification Devices:

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2258 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.07.01

Detailed Analysis Brief Description of Item 2 Addressable Notification Device (Horn Only) Supply & Installation of Addressable type audible horn for notification purpose shall contain an electronic module and a selectable address setting. A visible LED on each appliance shall provide verification of communications. The device shall be suitable to program the High / Low setting of the audible (horn) appliances by channel from the addressable controller. The Horn shall be red color with “FIRE" lettering. Addressable horn shall be listed to UL. The horn shall be suitable to produce sound pressure level of 89 dBA @ 24VDC. The horn shall suitable to mount directly to a standard single gang, double gang or 4" square electrical box, without the use of special adapter or trim rings. Shall be suitable to temperature range : 0° to 50° C Humidity Range: Up to 93% RH at 100°F (38°C) Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Addressable Notification Device (Audible Horn Only) :

1.0000

set

7000.00

7000.00

Skilled Labour

0.5000

day

450.00

225.00 7225.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

180.63

Subtotal-A1:

7405.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7553.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8309.11

VAT

6% of Total

553.94

IT

4% of Total

369.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9232.35

Page: 2259 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.07.02

Detailed Analysis Brief Description of Item 2 Addressable Notification Device (Strobe Only) Supply & Installation of Addressable strobe shall be listed to UL. The V/O shall consist of a xenon flash tube and associated lens/reflector system. The V/O enclosure shall mount directly to standard single gang, double gang or 4" square electrical box, without the use of special adapters or trim rings. Appliances shall be wired with UTP conductors, having a minimum of 3 twists per foot. V/O appliances shall be provided with different minimum flash intensities from 15cd to 110cd and to provide a label inside the strobe lens to indicate the listed candela rating of the specific Visible Only appliance. Shall be suitable to temperature range : 0° to 50° C Humidity Range: Up to 93% RH at 100°F (38°C) Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Addressable Notification Device (Strobe Only) :

1.0000

set

7000.00

7000.00

Skilled Labour

0.5000

day

450.00

225.00 7225.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

180.63

Subtotal-A1: Subtotal-B: Subtotal-C:

7405.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7553.74

10% Profit ( Add 10% on Subtotal-B) :

8309.11

VAT

6% of Total

553.94

IT

4% of Total

369.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9232.35

Page: 2260 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 7.23.07.03

2 Addressable Notification Device (Horn with Strobe) Supply & Installation of Addressable type Horn with Strobe for Audible & Visible application, combination of Audible & Visible (A/V) Notification Appliances shall be listed to UL. The strobe light shall consist of a xenon flash tube and associated lens / reflector system. Provide a label inside the strobe lens to indicate the listed candela rating of the specific strobe. The horn shall have a minimum sound pressure level of 83 to 89 dBA @ 24VDC. The audible / visible enclosure shall mount directly to standard single gang, double gang or 4" square electrical box, without the use of special adapters or trim rings. Shall be suitable to temperature range : 0° to 50° C Humidity Range: Up to 93% RH at 100°F (38°C) Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Addressable Notification Devices(Horn with Strobe)

1.0000

set

8600.00

8600.00

Skilled Labour

0.5000

day

450.00

225.00 8825.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

220.63

Subtotal-A1: Subtotal-B: Subtotal-C:

9045.63 9226.54

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10149.19

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

676.61

IT

4% of Total

451.08 Total:

7.23.08

11276.88

Addressable Modules:

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2261 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.08.01

Detailed Analysis Brief Description of Item 2 Isolator Module / Fault Isolator Module Supply & Installation of Addressable type Isolator / Fault Isolator Module shall be used in the field wiring between the devices (contractor shall propose the quantity and location in the system required) to detect & isolate the devices at the time short cirtuit in SLC. The module shall be suitable to provide communications isolation to improve installation convenience and increase the system integrity. Isolation will be automatically activated when an output short circuit is detected (also be suitable for manual operation for isolation and trouble shooting for wiring problems). The device shall be suitable for indoor use only. Shall be suitable to temperature range : 0° to 50° C Humidity Range: Up to 90% RH at 35°C) Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Isolator Module / Fault Isolator Module

1.0000

set

6200.00

6200.00

Skilled Labour

0.5000

day

450.00

225.00 6425.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

160.63

Subtotal-A1:

6585.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6717.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7389.07

VAT

6% of Total

492.60

IT

4% of Total

328.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8210.08

Page: 2262 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.08.02

Detailed Analysis Brief Description of Item 2 Addressable-Conventional Interface Module Supply & Installation of Addressable - Conventional Interface Module shall be used in the field wiring to connect the conventional Initiating devices with the Addressable FACP interfaces to make the system convenient as when as required (configured by the service provider). The module shall be suitable for single address to the FACP on receiving signal from any conventional initiating device. The device shall be installed with a back box. The device shall be suitable for indoor use only. Shall be suitable to temperature range : 0° to 50° C Humidity Range: Up to 90% RH at 35°C) Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Licensed manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Addressable-Conventional Interface Module

1.0000

set

6200.00

6200.00

Skilled Labour

0.5000

day

450.00

225.00 6425.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

160.63

Subtotal-A1: Subtotal-B: Subtotal-C:

6585.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6717.34

10% Profit ( Add 10% on Subtotal-B) :

7389.07

VAT

6% of Total

IT

4% of Total

492.60 328.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8210.08

Page: 2263 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.08.03

Detailed Analysis Brief Description of Item 2 Addressable Relay / Control Module Supply & Installation of Addressable Relay / Control Module shall be used in the field wiring to connect the conventional Initiating devices with the Addressable FACP interfaces to control / operate dampers, motors or similar appliances on receiving signal from the FACP as when as required (configured by the service provider). The device shall be suitable for indoor use only and shall be with back box. Shall be suitable to temperature range : 0° to 50° C Humidity Range: Up to 90% RH at 35°C) Approvals: UL, ULC Listed/, FM approved/ CSFM approved Country of Origin: Japan / Italy / UK / USA Or their Liscenced manufacturing units located Globally.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Addressable Relay / Control Module

1.0000

set

6200.00

6200.00

Skilled Labour

0.5000

day

450.00

225.00 6425.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

160.63

Subtotal-A1: Subtotal-B: Subtotal-C:

6585.63 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6717.34

10% Profit ( Add 10% on Subtotal-B) :

7389.07

VAT

6% of Total

IT

4% of Total

492.60 328.40 Total:

7.23.09

8210.08

Programming, Testing & Commissioning of Addressable type Fire Alarm

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2264 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.09.01

Detailed Analysis Brief Description of Item 2 FACP for up to 250 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

5.0000

day

1800.00

9000.00

Diploma Engineer (Daily Basis)

10.0000

day

750.00

7500.00

Foreman

12.0000

day

800.00

9600.00

Fire Mechanics

18.0000

day

700.00

12600.00

Electricians

30.0000

day

600.00

18000.00

Ordinary Labour

32.0000

day

370.00

11840.00

Plumber/ Electric Mistry/ Painter

30.0000

day

680.00

20400.00

300.00

75000.00

Programming Charge for first 250

250.0000 per device

163940.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

4098.50

Subtotal-A1:

168038.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

171399.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

188539.20

VAT

6% of Total

12569.28

IT

4% of Total

8379.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

209488.00

Page: 2265 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.09.02

Detailed Analysis Brief Description of Item 2 FACP for up to 500 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

5.0000

day

1800.00

9000.00

Diploma Engineer (Daily Basis)

10.0000

day

750.00

7500.00

Foreman

12.0000

day

800.00

9600.00

Fire Mechanics

18.0000

day

700.00

12600.00

Electricians

30.0000

day

600.00

18000.00

Ordinary Labour

32.0000

day

370.00

11840.00

Plumber/ Electric Mistry/ Painter

30.0000

day

680.00

20400.00

Programming Charge for first 250

250.0000 per device

300.00

75000.00

Programming Charge after 250

250.0000 per device

40.00

10000.00 173940.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

4348.50

Subtotal-A1: Subtotal-B: Subtotal-C:

178288.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

181854.27

10% Profit ( Add 10% on Subtotal-B) :

200039.70

VAT

6% of Total

IT

4% of Total

13335.98 8890.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

222266.33

Page: 2266 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.09.03

Detailed Analysis Brief Description of Item 2 FACP for up to 750 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

5.0000

day

1800.00

9000.00

Diploma Engineer (Daily Basis)

10.0000

day

750.00

7500.00

Foreman

12.0000

day

800.00

9600.00

Fire Mechanics

18.0000

day

700.00

12600.00

Electricians

30.0000

day

600.00

18000.00

Ordinary Labour

32.0000

day

370.00

11840.00

Plumber/ Electric Mistry/ Painter

30.0000

day

680.00

20400.00

Programming Charge for first 250

250.0000 per device

300.00

75000.00

Programming Charge after 250

500.0000 per device

40.00

20000.00 183940.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

4598.50

Subtotal-A1: Subtotal-B: Subtotal-C:

188538.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

192309.27

10% Profit ( Add 10% on Subtotal-B) :

211540.20

VAT

6% of Total

IT

4% of Total

14102.68 9401.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

235044.66

Page: 2267 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.09.04

Detailed Analysis Brief Description of Item 2 FACP for up to 1000 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

5.0000

day

1800.00

9000.00

Diploma Engineer (Daily Basis)

10.0000

day

750.00

7500.00

Foreman

12.0000

day

800.00

9600.00

Fire Mechanics

18.0000

day

700.00

12600.00

Electricians

30.0000

day

600.00

18000.00

Ordinary Labour

32.0000

day

370.00

11840.00

Plumber/ Electric Mistry/ Painter

30.0000

day

680.00

20400.00

Programming Charge for first 250

250.0000 per device

300.00

75000.00

Programming Charge after 250

750.0000 per device

40.00

30000.00 193940.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

4848.50

Subtotal-A1: Subtotal-B: Subtotal-C:

198788.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

202764.27

10% Profit ( Add 10% on Subtotal-B) :

223040.70

VAT

6% of Total

IT

4% of Total

14869.38 9912.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

247823.00

Page: 2268 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.23.09.05

Detailed Analysis Brief Description of Item 2 FACP for up to 1500 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

5.0000

day

1800.00

9000.00

Diploma Engineer (Daily Basis)

10.0000

day

750.00

7500.00

Foreman

12.0000

day

800.00

9600.00

Fire Mechanics

18.0000

day

700.00

12600.00

Electricians

30.0000

day

600.00

18000.00

Ordinary Labour

32.0000

day

370.00

11840.00

Plumber/ Electric Mistry/ Painter

30.0000

day

680.00

20400.00

Programming Charge for first 250 Programming Charge after 250

250.0000 per device

300.00

75000.00

1250.0000 per device

40.00

50000.00 213940.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

5348.50

Subtotal-A1: Subtotal-B: Subtotal-C:

219288.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

223674.27

10% Profit ( Add 10% on Subtotal-B) :

246041.70

VAT

6% of Total

IT

4% of Total

16402.78 10935.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

273379.66

Page: 2269 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 7.23.09.06

2 FACP for up to 2000 Addressable Devices (Max.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Job B. Sc. Engineer

5.0000

day

1800.00

9000.00

Diploma Engineer (Daily Basis)

10.0000

day

750.00

7500.00

Foreman

12.0000

day

800.00

9600.00

Fire Mechanics

18.0000

day

700.00

12600.00

Electricians

30.0000

day

600.00

18000.00

Ordinary Labour

32.0000

day

370.00

11840.00

Plumber/ Electric Mistry/ Painter

30.0000

day

680.00

20400.00

Programming Charge for first 250 Programming Charge after 250

250.0000 per device

300.00

75000.00

1750.0000 per device

40.00

70000.00 233940.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +2.50 % on Subtotal-A )

5848.50

Subtotal-A1: Subtotal-B: Subtotal-C:

239788.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

244584.27

10% Profit ( Add 10% on Subtotal-B) :

269042.70

VAT

6% of Total

IT

4% of Total

17936.18 11957.45 Total:

7.24

298936.33

Fire Rated Door:

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2270 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 7.24.01

Detailed Analysis Brief Description of Item 2 Fire Rated Door: Supply & installation of UL listed /FM approved fire rated door complete with panic bar, electromagnetic door holder & vision panel. The door shall be UL certified made with 1.60mm thick sheet steel, powder coated paint finish and curing in temperature controlled gas oven with approved red colour over a coat of primer. Thickness of the leaf shall be 50mm and filled with fire proof / resisting materials rock wool with density of 100 kg/cum of minimum two hours rated. The panic bar shall be horizontal type, UL listed made of aluminum alloy / steel, chrome plated, c/w with security lock to operate from outside. All MS sheet surface shall be chemically treated before assembling in chemical treatment plant. Vision panel shall be made of minimum 5mm thick glass with a frame of 1.60mm thick imported cold rolled MS sheet & SS pop rivet, anchor bolts, ceramic fiber tape should be used for fixing. Door frame shall be made with sheet steel of 2.30mm thickness. Hinges shall be quite smooth, robust and aligned properly. Peripheral clearance of the shutter should be as per standard code of practice. The opening of the door should be in one direction. A complete door should also include frame header, frame strike jamb, frame hinge jamb, U-channel top, door closer, mortise/handle lock, door leaf bottom, door leaf top, U-channel bottom, etc. size shall be minimum 1100mm (width) x 2100mm (height). Measurement of the door shall be including frame & vision panel of minimum 0.045 sqm all complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

Door with Frame & Shutter single (1100X2100)

1.0000

each

60690.00

60690.00

Vision Panel (Min 0.045 sqm)

1.0000

each

12600.00

12600.00

Electromagnetic Door Holder

1.0000

each

7350.00

7350.00

Ordinary Labour

4.0000

day

370.00

1480.00 82120.00

Subtotal-A: All other remaining costs like cost of all fitting accessories, Handling etc.

( +6.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C: VAT Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4927.20 87047.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

88788.14

10% Profit ( Add 10% on Subtotal-B) :

97666.96

6% of Total

6511.13 Page: 2271 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

4340.75 Total:

108518.84

Chapter - 8 : Electrical Works 8.01

Distribution board (DB/MDB): Supplying, assembling, fitting, fixing & installation (with effective connection) of 415 volt, 50Hz grade Plug in type (concealed/surface) distribution board made of 18 SWG mild steel sheet, complete with hinged type door, built in type locking arrangement, along with approved type handle, 100A - 400A capacity bus-bar (Phase, Neutral & Earthing) , insulators at both ends, necessary arrangement for fixing of TP MCCB (incoming) & SP/TP MCB (outgoing) by keeping main MCCB's knob out on the top cover of the board with with Powder Coated painting etc. all completes (except circuit breakers) as per specification & direction of the Engineer-in-Charge. Brand : Siemens/Hager or equivalent.

8.01.1

12-ways DB Box size-430mmx560mmx125mm; Incoming-TP MCCB Out going-12 nos. SP MCB/4 nos. TP MCB

each 12 way plug in db box

1.0000

each

14500.00

14500.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 14730.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15024.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16527.06

VAT

6% of Total

1101.80

IT

4% of Total

734.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18363.40

Page: 2272 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.01.2

Detailed Analysis Brief Description of Item 2 24-ways DB Box size-430mmx630mmx125mm; Incoming-TP MCCB Out going-24 nos. SP MCB/8 nos. TP MCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 24 way plug in db box

1.0000

each

16500.00

16500.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 16730.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17064.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18771.06

VAT

6% of Total

1251.40

IT

4% of Total

834.27 Total:

8.01.3

36-ways DB Box size-430mmx750mmx125mm; Incoming-TP MCCB Out going-36 nos. SP MCB/12 nos. TP MCB

each 36 way plug in db box

1.0000

each

20000.00

20000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 20230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20634.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22698.06

VAT

6% of Total

IT

4% of Total

1513.20 1008.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

20856.73

25220.07

Page: 2273 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

8.02

Sub-distribution board (SDB): Supplying & fitting 250 volt, 50HZ grade following concealed sub-distribution board made of 18 SWG mild steel sheet, complete with hinged type door, built in type locking arrangement, along with approved type handle 200 A capacity bus-bar with required number of holes there on, insulators at both ends. Copper bar for neutral & earth terminal, necessary arrangement for fixing of SPMCB by keeping its knobs out on the top cover of the board with enamel/hammer painting. All completes as per specification & direction of the Engineer-in-Charge.Manufacturer of SPMCB Dorman smith (UK/ Germany) MEM (UK) SIEMENS (USA/Germany) or Equivalent.

8.02.01

4-ways SDBBoxsize-450mmx350mmx125mmIncoming-1x 32 A SP MCBOut going-4 x 6/10/16 A SP MCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 18 SWG Steel Sheet Metal

2.5000

kg

217.00

542.50

painting both side

0.5000

sqm

130.00

65.00

5-30A SP MCB

5.0000

each

440.00

2200.00

push type lock

1.0000

each

37.00

37.00

Earthing copper block & busbar

1.0000

each

27.00

27.00

1C-1.5mm connecting wire

1.0000

m

40.00

40.00

Plumber/ Electric Mistry/ Painter

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 2978.90

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

187.67

Subtotal-A1:

3166.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3229.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3552.89

VAT

6% of Total

IT

4% of Total

236.86 157.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3947.66

Page: 2274 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.02

Detailed Analysis Brief Description of Item 2 5-ways SP MCBBoxsize-500mmx450mmx125mmIncoming-1 x 40 A SP MCBOut going-5 x 6/10/16 A SPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

kg

217.00

651.00

each 18 SWG Steel Sheet Metal

3.0000

painting both side

0.5000

sqm

130.00

65.00

5-30A SP MCB

5.0000

each

440.00

2200.00

40Amps (6KA) SP MCB

1.0000

each

350.00

350.00

push type lock

1.0000

each

37.00

37.00

Earthing copper block & busbar

1.0000

each

27.00

27.00

1C-1.5mm connecting wire

1.0000

m

40.00

40.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 3474.50

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

218.89

Subtotal-A1:

3693.39

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3767.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4143.99

VAT

6% of Total

IT

4% of Total

276.27 184.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4604.43

Page: 2275 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.03

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

6-ways SDBBoxsize-550mmx500mmx125mmIncoming-1 x 63 A SP MCBOut going- 6 x 6/10/16 A SPMCB

each 18 SWG Steel Sheet Metal

Quantity 5

3.5000

Unit

Rate

Amount

6

7

8

kg

217.00

759.50

painting both side

0.6000

sqm

130.00

78.00

5-30A SP MCB

6.0000

each

440.00

2640.00

40Amps (6KA) SP MCB

1.0000

each

350.00

350.00

push type lock

1.0000

each

37.00

37.00

Earthing copper block & busbar

1.0000

each

27.00

27.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 4002.80

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

252.18

Subtotal-A1: Subtotal-B: Subtotal-C:

4254.98 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4340.08

10% Profit ( Add 10% on Subtotal-B) :

4774.08

VAT

6% of Total

318.27

IT

4% of Total

212.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5304.54

Page: 2276 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.04

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

8-ways SDBBoxsize-550mmx500mmx125mmIncoming-1 x 63 A SP MCBOut going- 8 x 6/10/16 A SPMCB

each 18 SWG Steel Sheet Metal

Quantity 5

3.5000

Unit

Rate

Amount

6

7

8

kg

217.00

759.50

painting both side

0.6000

sqm

130.00

78.00

5-30A SP MCB

8.0000

each

440.00

3520.00

40Amps (6KA) SP MCB

1.0000

each

350.00

350.00

push type lock

1.0000

each

37.00

37.00

Earthing copper block & busbar

1.0000

each

27.00

27.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 4882.80

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4980.46

10% Profit ( Add 10% on Subtotal-B) :

5478.50

VAT

6% of Total

IT

4% of Total

365.23 243.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6087.22

Page: 2277 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.05

Detailed Analysis Brief Description of Item 2 10-ways SDBBoxsize-550mmx500mmx125mmIncoming-1 x 63 A SP MCBOut going- 10 x 6/10/16 A SPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

kg

217.00

759.50

each 18 SWG Steel Sheet Metal painting both side

3.5000 0.6000

sqm

130.00

78.00

10.0000

each

440.00

4400.00

40Amps (6KA) SP MCB

1.0000

each

350.00

350.00

push type lock

1.0000

each

37.00

37.00

Earthing copper block & busbar

1.0000

each

27.00

27.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50

5-30A SP MCB

5762.80

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5878.06

10% Profit ( Add 10% on Subtotal-B) :

6465.86

VAT

6% of Total

IT

4% of Total

431.06 287.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7184.29

Page: 2278 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.06

Detailed Analysis Brief Description of Item 2 12-ways SDBBoxsize-550mmx500mmx125mmIncoming-1 x 63 A SP MCBOut going- 12 x 6/10/16 A SPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

kg

217.00

759.50

each 18 SWG Steel Sheet Metal painting both side

3.5000 0.6000

sqm

130.00

78.00

12.0000

each

440.00

5280.00

40Amps (6KA) SP MCB

1.0000

each

350.00

350.00

push type lock

1.0000

each

37.00

37.00

Earthing copper block & busbar

1.0000

each

27.00

27.00

Plumber/ Electric Mistry/ Painter

0.0600

day

680.00

40.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50

5-30A SP MCB

6642.80

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6775.66

10% Profit ( Add 10% on Subtotal-B) :

7453.22

VAT

6% of Total

IT

4% of Total

496.88 331.25 Total:

8.02.07

8281.36

Sub-distribution board (ENCLOSER): Supplying, assembling, fitting, fixing, installation (with effictive connection), testing & Commissioning of 250 volt, 50HZ grade following concealed sub-distribution board made of 18 SWG mild steel sheet, complete with hinged type door, built in type locking arrangement, along with approved type handle 100 A capacity bus-bar (Only Neutral & Earthing) , insulators at both ends, necessary arrangement for fixing of SPMCB by keeping its knobs out on the top cover of the board with enamel/hammer painting. All completes as per specification & direction of the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2279 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.07.1

Detailed Analysis Brief Description of Item 2 4-ways SDBBoxsize-250mmx150mmx125mm, Provision : Incoming-1x 20 A SP MCB Out going-4 x 6/10/16 A SP MCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

650.00

650.00

each 4-WAY SDB

1.0000

each

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 673.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

686.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

755.11

VAT

6% of Total

50.34

IT

4% of Total

33.56 Total:

8.02.07.2

6-ways SDBBoxsize-250mmx200mmx125mm, Provision : Incoming-1x 32 A SP MCB Out going-6 x 6/10/16 A SP MCB

each 6-WAY SDB

1.0000

each

750.00

750.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 773.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

788.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

867.31

VAT

6% of Total

IT

4% of Total

57.82 38.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

839.01

963.67

Page: 2280 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.07.3

Detailed Analysis Brief Description of Item 2 8-ways SDBBoxsize-250mmx250mmx125mm, Provision : Incoming-1x 32 A SP MCB Out going-8 x 6/10/16 A SP MCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 8-WAY SDB

1.0000

each

1100.00

1100.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 1123.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1145.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1260.01

VAT

6% of Total

84.00

IT

4% of Total

56.00 Total:

8.02.07.4

10-ways SDBBoxsize-50mmx300mmx125mm, Provision : Incoming-1x 40 A SP MCB Out going-10 x 6/10/16 A SP MCB

each 10-WAY SDB

1.0000

each

1600.00

1600.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 1623.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1655.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1821.01

VAT

6% of Total

IT

4% of Total

121.40 80.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1400.01

2023.34

Page: 2281 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.07.5

Detailed Analysis Brief Description of Item 2 12-ways SDBBoxsize-250mmx350mmx125mm, Provision : Incoming-1x 63 A SP MCB Out going-12 x 6/10/16 A SP MCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 12-WAY SDB

1.0000

each

1800.00

1800.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 1823.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1859.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2045.41

VAT

6% of Total

136.36

IT

4% of Total

90.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2272.67

Page: 2282 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.08

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing Distribution/Sub-Distribution board made of 18 SWG steel sheet metal enclosed with double cover, gray hammer painted on outside and enamel paint on inside on rust proof prime coat with hinged front door with lock and key arrangement for half concealed mounted board having knock out for conduit entry and exit for 415/230V TP&N/ SP&N operations. The board shall have solid neutral and earth copper bus bar and also required size off 3 phase copper bus bars covering transperent fiber glass. All bars shall have required number of holes of 5mm for cable connections etc. all complete as per drawing, design and direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

18 SWG Steel Sheet Metal

3.0000

kg

217.00

651.00

Painting to door and window frames and shutters in two coats with synthetic enamel paint…(3.12.5.1)

3.0000

sqm

99.43

298.28

40 amps SPMCB (6 KA)

1.0000

each

350.00

350.00

Copper Bus Bars

0.9300

kg

1400.00

1302.00

5/20 amps SPMCB (6 KA)

6.0000

each

389.00

2334.00

Porcelain Base Insulator with nuts and bolts

8.0000

each

165.00

1320.00

Connecting wire (IC -1.5mm2)

2.1700

m

25.00

54.25 6309.53

Subtotal-A: Lock & Key, cutting wall, earthing copper block, fixing of MCB & other cost

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

7192.86 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7336.72

10% Profit ( Add 10% on Subtotal-B) :

8070.39

VAT

6% of Total

538.03

IT

4% of Total

358.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

883.33

8967.10

Page: 2283 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

8.02.09

"Water heater (Geyser):Supplying, assembling, fitting, fixing, installation (with effictive connection), testing & commissioning of following capacity electrically operated Water Heater containing inner tank made of minimum 14 SWG non magnetic rust proof galvanized steel & outer jacket/body made of minimum 22 SWG mild steel sheet & proper thermal insulation with automatic thermostatic switch with suitable wattage range of immersion heating element, on-off indicating lamp, inlet and outlet water connection pipe including fixing accessories all complete as required with adequate safety measures complete with required accessories and in conformity with codes and specification of international standards, suitable for use in tropicalized country like Bangladesh. Model and sample to be approved by the competent authority."

8.02.09.1

10 gallon/Hr. (1000Watt) Wall mounted type

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 10 Gallon/Hr water heater

1.0000

each

7250.00

7250.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 7480.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

374.00

Subtotal-A1:

7854.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8011.08

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8812.19

VAT

6% of Total

IT

4% of Total

587.48 391.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9791.32

Page: 2284 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.09.2

Detailed Analysis Brief Description of Item 2 15 gallon/Hr. (1250Watt) Wall mounted type

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 15 Gallon/Hr water heater

1.0000

each

8500.00

8500.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 8730.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

436.50

Subtotal-A1: Subtotal-B: Subtotal-C:

9166.50 9349.83

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10284.81

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

685.65 457.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11427.57

Page: 2285 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.02.10

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 300mm depth surface type double based meter board made of 16 SWG sheet metal with gray hammer paint on outside and enamel paint on inside surface over rust proof prime coat. Second base shall be part by part hinged type of required width fixing arrangement, MCCB/MCB’s, bus bars and also to height of connecting cable. Outside sheets shall be fixed on 38mmx38mm M.S angle frame. Front cover shall be of hinged type with lock and key arrangement. The board shall have knockout for cable entry and exit and also to dispose heat produced inside. There shall be transparent plastic in the front door over the meter for meter reading. Copper bus bars for three phase, neutral and earthing shall be supplied by the contractors. The meter board shall be fixed on proper clamping with nuts and bolts etc. all complete as per drawing, design and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

200.00

200.00

sqm

16 SWG Metal Board with MS Angle Frame including painting etc.

1.0000

each

Clamp (250x38x6mm)

4.0000

each

55.00

220.00

Lock and Key

1.0000

set

150.00

150.00 570.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

28.50

Subtotal-A1: Subtotal-B: Subtotal-C:

598.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

610.47

10% Profit ( Add 10% on Subtotal-B) :

671.52

VAT

6% of Total

44.77

IT

4% of Total

29.85 Total:

8.02.11

746.13

Supplying, fitting and fixing 250 volts 15 amps ICDB with fuse on live side and complete as per directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2286 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.02.11.1

2 10- way

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 15 amps 250V 10 way ICDB

1.0000

each

2500.00

2500.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2730.00

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

54.60

Subtotal-A1:

2784.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2840.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3124.32

VAT

6% of Total

IT

4% of Total

208.29 138.86 Total:

8.02.11.2

8-way

each 15 amps 250V 8 way ICDB

1.0000

each

2300.00

2300.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2530.00

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

50.60

Subtotal-A1: Subtotal-B: Subtotal-C:

2580.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2632.21

10% Profit ( Add 10% on Subtotal-B) :

2895.43

VAT

6% of Total

IT

4% of Total

193.03 128.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3471.47

3217.15

Page: 2287 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.02.11.3

2 6-way

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 15 amps 250V 6 way ICDB

1.0000

each

2100.00

2100.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2330.00

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

46.60

Subtotal-A1:

2376.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2424.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2666.55

VAT

6% of Total

IT

4% of Total

177.77 118.51 Total:

8.02.11.4

4-way

each 15 amps 250V 4 way ICDB

1.0000

each

1900.00

1900.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2130.00

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

42.60

Subtotal-A1: Subtotal-B: Subtotal-C:

2172.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2216.05

10% Profit ( Add 10% on Subtotal-B) :

2437.66

VAT

6% of Total

IT

4% of Total

162.51 108.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2962.83

2708.51

Page: 2288 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.02.11.5

2 2-way

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 15 amps 250V 2 way ICDB

1.0000

each

1800.00

1800.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2030.00

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

40.60

Subtotal-A1:

2070.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2112.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2323.21

VAT

6% of Total

IT

4% of Total

154.88 103.25 Total:

8.02.12

2581.35

Supplying, fitting and fixing junctions boxes where necessary as per directions of the E-I-C. The junction boxes should be shock proof.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2289 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.02.12.1

2 2- way

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 2 way junction box

1.0000

each

75.00

75.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 123.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

1.24

Subtotal-A1:

125.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

127.59

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

140.35

VAT

6% of Total

IT

4% of Total

9.36 6.24 Total:

8.02.12.2

4- way

each 4 way junction box

1.0000

each

150.00

150.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 198.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

1.99

Subtotal-A1: Subtotal-B: Subtotal-C:

200.84 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

204.86

10% Profit ( Add 10% on Subtotal-B) :

225.34

VAT

6% of Total

IT

4% of Total

15.02 10.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

155.94

250.38

Page: 2290 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

8.02.13

Taking out old panel board, switch board, ICDB/sub-main switch board etc. and stacking the same to a preselected place as per directions of the E-I-C.

8.03

Supplying, fitting and fixing energy meter with cutout teak wood board etc. all complete as per directions of E-I-C (when the meter is not supplied by PDB).

8.03.1

500 Volts 3 phase

8.03.1.1

200 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

LS

each 200 amps 500V 3 phase Energy Meter

1.0000

each

13500.00

13500.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 13615.00

Subtotal-A: All other remaining costs

( +3.50 % on Subtotal-A )

476.53

Subtotal-A1:

14091.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14373.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15810.69

VAT

6% of Total

IT

4% of Total

1054.05 702.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17567.43

Page: 2291 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.03.1.2

2 150 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150 amps 500V 3 phase Energy Meter

1.0000

each

5500.00

5500.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 5615.00

Subtotal-A: All other remaining costs

( +3.50 % on Subtotal-A )

196.53

Subtotal-A1:

8.03.1.3

100 amps

5811.53

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5927.76

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6520.53

VAT

6% of Total

IT

4% of Total

434.70 289.80 Total:

7245.03

each 100 amps 500V 3 phase Energy Meter

1.0000

each

10000.00

10000.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 10115.00

Subtotal-A: All other remaining costs

( +3.50 % on Subtotal-A )

354.03

Subtotal-A1: Subtotal-B: Subtotal-C:

10469.03 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10678.41

10% Profit ( Add 10% on Subtotal-B) :

11746.25

VAT

6% of Total

IT

4% of Total

783.08 522.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13051.38

Page: 2292 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.03.1.4

2 60 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 60 amps 500V 3 phase Energy Meter

1.0000

each

10000.00

10000.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 10115.00

Subtotal-A: All other remaining costs

( +3.50 % on Subtotal-A )

354.03

Subtotal-A1:

10469.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10678.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11746.25

VAT

6% of Total

IT

4% of Total

783.08 522.06 Total:

8.03.1.5

30 amps

each 30 amps 500V 3 phase Energy Meter

1.0000

each

8500.00

8500.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 8615.00

Subtotal-A: All other remaining costs

( +3.50 % on Subtotal-A )

301.53

Subtotal-A1: Subtotal-B: Subtotal-C:

8916.53 9094.86

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10004.34

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

666.96 444.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13051.38

11115.93

Page: 2293 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

8.03.2

250 Volts single phase

8.03.2.1

10 amps to 60 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 10 amps to 60 amps 250V single phase Energy Meter

1.0000

each

2000.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 2115.00

Subtotal-A: All other remaining costs

( +3.50 % on Subtotal-A )

74.03

Subtotal-A1:

2189.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2232.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2456.09

VAT

6% of Total

IT

4% of Total

163.74 109.16 Total:

8.04

Supplying, assembling, fitting, fixing & installation (with effictive connection) on a prepared board 250/500volt grade following single/triple pole SPMCB/TPMCB/TPMCCB having minimum breaking capacity 6/10/16KA with thermal over current & instantaneous electromagnetic short circuit release provision. Manufacturer of SPMCB/TPMCB/TPMCCB (6/10/16 KA) Dorman smith (UK/ Germany) MEM (UK), ABB (Italy), Legrand (France), Hager (France)/SIEMENS (USA/Germany) or equivalent approved by the Engineer-in-charge.

8.04.1

"SPMCB (6KA) Manufacturer of SPMCB/TPMCB/TPMCCB (6/10/16 KA) Dorman smith (UK/ Germany), MEM (UK), ABB (Italy), Legrand (France), SIEMENS (USA/Germany) or equivalent approved by the Engineer-in-charge."

Note : Rates of all items should be inclusive of all supply and carriage.

2000.00

2728.98

Page: 2294 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.1.1

2 3 amps (6KA) SPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 6 amps (6KA) SP MCB

1.0000

each

350.00

350.00

Asst Electrician

0.0100

day

680.00

6.80 356.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

3.57

Subtotal-A1:

360.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

367.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

404.33

VAT

6% of Total

26.96

IT

4% of Total

17.97 Total:

8.04.1.2

6 amps (6KA) SPMCB

each 6 amps (6KA) SP MCB

1.0000

each

350.00

350.00

Asst Electrician

0.0100

day

680.00

6.80 356.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

363.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

400.33

VAT

6% of Total

26.69

IT

4% of Total

17.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

449.26

444.81

Page: 2295 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.1.3

2 10 amps (6KA) SPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 10 amps (6KA) SP MCB

1.0000

each

350.00

350.00

Asst Electrician

0.0100

day

680.00

6.80 356.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

3.57

Subtotal-A1:

360.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

367.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

404.33

VAT

6% of Total

26.96

IT

4% of Total

17.97 Total:

8.04.1.4

16 amps (6KA) SPMCB

each 16 amps (6KA) SP MCB

1.0000

each

350.00

350.00

Asst Electrician

0.0100

day

680.00

6.80 356.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

3.57

Subtotal-A1:

360.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

367.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

404.33

VAT

6% of Total

IT

4% of Total

26.96 17.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

449.26

449.26

Page: 2296 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.1.5

2 20 amps (6KA) SPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 20 amps (6KA) SP MCB

1.0000

each

350.00

350.00

Asst Electrician

0.0100

day

680.00

6.80 356.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

3.57

Subtotal-A1:

360.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

367.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

404.33

VAT

6% of Total

26.96

IT

4% of Total

17.97 Total:

8.04.1.6

32amps (6KA) SPMCB

each 32 amps (6KA) SP MCB

1.0000

each

350.00

350.00

Asst Electrician

0.0100

day

680.00

6.80 356.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

3.57

Subtotal-A1:

360.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

367.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

404.33

VAT

6% of Total

IT

4% of Total

26.96 17.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

449.26

449.26

Page: 2297 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.1.7

2 40 amps (6KA) SPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 40 amps SPMCB (6 KA)

1.0000

each

350.00

350.00

Asst Electrician

0.0100

day

680.00

6.80 356.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

3.57

Subtotal-A1:

360.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

367.58

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

404.33

VAT

6% of Total

26.96

IT

4% of Total

17.97 Total:

8.04.1.8

63 amps (6KA) SPMCB

each 63Amps (6KA) SP MCB

1.0000

each

490.00

490.00

Asst Electrician

0.0100

day

680.00

6.80 496.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

4.97

Subtotal-A1:

501.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

511.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

562.98

VAT

6% of Total

IT

4% of Total

37.53 25.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

449.26

625.54

Page: 2298 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.1.9

2 32A-63A (10kA) DP MCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 32A-63A (10 kA) DP MCB

1.0000

each

1150.00

1150.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 1163.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1186.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1305.56

VAT

6% of Total

87.04

IT

4% of Total

58.02 Total:

8.04.2

TP MCB (6KA) Manufacturer of SPMCB/TPMCB/TPMCCB (6/10/16 KA) Dorman smith (UK/ Germany) MEM (UK) SIEMENS (USA/Germany) or equivalent approved by the Engineer-in-charge.

8.04.2.1

20 amps (6KA) TPMCB

each 20Amps (6KA) TP MCB

1.0000

each

1550.00

1550.00

Asst Electrician

0.0100

day

680.00

6.80 1556.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

15.57

Subtotal-A1: Subtotal-B: Subtotal-C:

1572.37 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1603.82

10% Profit ( Add 10% on Subtotal-B) :

1764.20

VAT

6% of Total

IT

4% of Total

117.61 78.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1450.62

1960.22

Page: 2299 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.2.2

2 32 amps (6KA) TPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 32Amps (6KA) TP MCB

1.0000

each

2000.00

2000.00

Asst Electrician

0.0100

day

680.00

6.80 2006.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

20.07

Subtotal-A1:

2026.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2067.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2274.15

VAT

6% of Total

151.61

IT

4% of Total

101.07 Total:

8.04.2.3

40 amps (6KA) TPMCB

each 40Amps (6KA) TP MCB

1.0000

each

2000.00

2000.00

Asst Electrician

0.0100

day

680.00

6.80 2006.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

20.07

Subtotal-A1:

2026.87

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2067.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2274.15

VAT

6% of Total

IT

4% of Total

151.61 101.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2526.83

2526.83

Page: 2300 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.2.4

2 63 amps (6KA) TPMCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 63Amps (6KA) TP MCB

1.0000

each

2150.00

2150.00

Asst Electrician

0.0100

day

680.00

6.80 2156.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

21.57

Subtotal-A1:

2178.37

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2221.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2444.13

VAT

6% of Total

162.94

IT

4% of Total

108.63 Total:

8.04.2.5

16 amps (6KA) TPMCB

each 16 Amps (6KA) TP MCB

1.0000

each

2000.00

2000.00

Asst Electrician

0.0100

day

680.00

6.80 2006.80

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2046.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2251.63

VAT

6% of Total

150.11

IT

4% of Total

100.07 Total:

8.04.3

2715.70

2501.81

TP MCCB: Manufacturer of TP MCCB Dorman smith (UK/ Germany) MEM (UK) SIEMENS (USA/Germany) or equivalent approved by the Engineeringcharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2301 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.3.1

2 63 amps (10 KA) TPMCCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 63Amps (10KA) TP MCCB

1.0000

each

7000.00

7000.00

Asst Electrician

0.0200

day

680.00

13.60 7013.60

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

70.14

Subtotal-A1:

7083.74

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7225.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7947.95

VAT

6% of Total

529.86

IT

4% of Total

353.24 Total:

8.04.3.2

80 amps (10 KA) TPMCCB

each 80Amps (10KA) TP MCCB

1.0000

each

8570.00

8570.00

Asst Electrician

0.0200

day

680.00

13.60 8583.60

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

85.84

Subtotal-A1:

8669.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8842.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9727.11

VAT

6% of Total

IT

4% of Total

648.47 432.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8831.06

10807.90

Page: 2302 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.04.3.3

2 100 amps (10 KA) TPMCCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 100Amps (16KA) TP MCCB

1.0000

each

8970.00

8970.00

Asst Electrician

0.0200

day

680.00

13.60 8983.60

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

89.84

Subtotal-A1: Subtotal-B: Subtotal-C:

9073.44 9254.90

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10180.40

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

678.69

IT

4% of Total

452.46 Total:

8.04.3.4

150/160 amps (10 KA) TPMCCB

each 150/160Amps (16KA) TP MCCB

1.0000

each

16849.00

16849.00

Asst Electrician

0.0200

day

680.00

13.60 16862.60

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

168.63

Subtotal-A1:

17031.23

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17371.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19109.04

VAT

6% of Total

IT

4% of Total

1273.94 849.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11311.55

21232.26

Page: 2303 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.04.3.5

2 125 amps (10 KA) TPMCCB

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 125 amps (10 KA) TPMCCB

1.0000

each

9500.00

9500.00

Asst Electrician

0.0200

day

680.00

13.60 9513.60

Subtotal-A: Subtotal-B: Subtotal-C:

9703.87

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10674.26

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

711.62

IT

4% of Total

474.41 Total:

8.04.4

Supplying, fitting and fixing 500V grade re-wearable fuse link porcelain carrier approved quality (foreign made) on prepared board etc. all complete as per directions of the E-I-C.

8.04.4.1

100 amps

each 100 amps cut out

1.0000

each

85.00

85.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60 122.60

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.23

Subtotal-A1: Subtotal-B: Subtotal-C:

123.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

126.30

10% Profit ( Add 10% on Subtotal-B) :

138.93

VAT

6% of Total

9.26

IT

4% of Total

6.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11860.29

154.37

Page: 2304 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.04.4.2

2 60 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 60 amps cut out

1.0000

each

87.00

87.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 110.50

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.11

Subtotal-A1:

111.61

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

113.84

10% Profit ( Add 10% on Subtotal-B) :

125.22

VAT

6% of Total

8.35

IT

4% of Total

5.57 Total:

8.04.4.3

30 amps

each 30 amps cut out

1.0000

each

69.00

69.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 83.10

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.83

Subtotal-A1:

83.93

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

85.61

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

94.17

VAT

6% of Total

6.28

IT

4% of Total

4.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

139.13

104.63

Page: 2305 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.04.4.4

2 15 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 15 amps cut out

1.0000

each

52.00

52.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 66.10

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

0.66

Subtotal-A1:

66.76

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

68.10

10% Profit ( Add 10% on Subtotal-B) :

74.91

VAT

6% of Total

4.99

IT

4% of Total

3.33 Total:

8.04.4.5

10 amps

each 10 amps cut out

1.0000

each

46.00

46.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 60.10

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

0.60

Subtotal-A1:

60.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

68.11

VAT

6% of Total

4.54

IT

4% of Total

3.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

83.23

75.67

Page: 2306 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.04.4.6

2 5 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 5 amps cut out

1.0000

each

34.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 48.10

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

0.48

Subtotal-A1: Subtotal-B: Subtotal-C:

48.58 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

49.55

10% Profit ( Add 10% on Subtotal-B) :

54.51

VAT

6% of Total

3.63

IT

4% of Total

2.42 Total:

8.05

ELECTRICAL WIRING

8.05.01

Batten Wiring: Surface Batten Wiring for the following Points Looping at the Switch board with earth terminal including Circuit wiring with 2c-1.5 sq.mm PVC insulated and sheathed cable (BYFYE) on minimum 12.5 mm thick teak wood batten painted at the bottom complete with 18 SWG GP Sheet switch board with 3mm thick ebonite sheet cover, 5 amps. Piano type switch, brass holder, ceiling rose, wooden round block, fixing materials & all other accessories as required including mending the damages: Manufacturer of cable Eastern/BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the specification & direction of the Engineer- incharge.

Note : Rates of all items should be inclusive of all supply and carriage.

60.56

Page: 2307 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.01.1

Detailed Analysis Brief Description of Item 2 Light point / Exhaust / Wall bracket fan point

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 2c-1.5sq.mm (BYFYE) cable

7.0000

m

1/2"x1/2" thick CTW batten

6.8000

m

GP sheet SB with ebonite cover

1.0000

no

5A Piano switch

1.0000

no

wooden block

1.0000

no

Bake light ceiling rose

1.0000

no

Plumber/ Electric Mistry/ Painter

0.1000

day

35.00

245.00

680.00

68.00

Asst Electrician

0.1250

day

680.00

85.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 492.00

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

31.00

Subtotal-A1: Subtotal-B: Subtotal-C:

523.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

533.46

10% Profit ( Add 10% on Subtotal-B) :

586.80

VAT

6% of Total

IT

4% of Total

39.12 26.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

652.00

Page: 2308 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.05.01.2

2 Ceiling fan point

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 2c-1.5sq.mm (BYFYE) cable

7.0000

m

1/2"x1/2" thick CTW batten

6.8000

m

GP sheet SB with ebonite cover

1.0000

no

5A Piano switch

1.0000

no

wooden block

1.0000

no

Bake light ceiling rose

1.0000

no

Plumber/ Electric Mistry/ Painter

0.1000

day

35.00

245.00

680.00

68.00

Asst Electrician

0.1250

day

680.00

85.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 492.00

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

31.00

Subtotal-A1: Subtotal-B: Subtotal-C:

523.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

533.46

10% Profit ( Add 10% on Subtotal-B) :

586.80

VAT

6% of Total

IT

4% of Total

39.12 26.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

652.00

Page: 2309 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.01.3

2 Call bell point with bell push

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 2c-1.5sq.mm (BYFYE) cable

8.0000

m

1/2"x1/2" thick CTW batten

7.8000

m

GP sheet SB with ebonite cover

1.0000

no

5A Piano switch

1.0000

no

wooden block

1.0000

no

Bake light ceiling rose

1.0000

no

Plumber/ Electric Mistry/ Painter

0.1000

day

35.00

280.00

680.00

68.00

Asst Electrician

0.1250

day

680.00

85.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 527.00

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

33.20

Subtotal-A1: Subtotal-B: Subtotal-C:

560.20 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

571.41

10% Profit ( Add 10% on Subtotal-B) :

628.55

VAT

6% of Total

IT

4% of Total

41.90 27.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

698.38

Page: 2310 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.01.4

2 2-pin 5 amps socket ( outlet )

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point GP sheet board with ebonite cover

1.0000

m

5A Piano switch

1.0000

no

2-Pin 5 amp Piono Socket

1.0000

each

25.00

25.00

30.00

30.00

Asst Electrician

0.0330

day

680.00

22.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50

2c-1.5sq.mm (BYFYE) cable

7.0000

m

35.00

245.00 345.94

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

21.79

Subtotal-A1: Subtotal-B: Subtotal-C:

367.73 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

375.09

10% Profit ( Add 10% on Subtotal-B) :

412.60

VAT

6% of Total

IT

4% of Total

27.51 18.34 Total:

8.05.02

458.44

Channel Wiring: Surface Channel Wiring for the following Points Looping at the Switch board with earth terminal including Circuit wiring with 1C1.5 Sq.mm PVC insulated and sheathed stranded cable (BYM) & 1.5 mm rm (green) PVC insulated ECC wire (BYA) through 01 mm thick PVC Channel complete with 18 SWG GP Sheet concealed/ surface switch board with 3mm thick ebonite sheet cover, circular box, 5 amps. Piano type switch, brass holder, ceiling rose, fixing materials & all other accessories as required including mending the damages: Manufacturer of cable Eastern/BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the specification & direction of the Engineer- incharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2311 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.02.1

Detailed Analysis Brief Description of Item 2 Light point/Exhaust / Wall bracket fan point

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 2c-1.5sq.mm (BYM) cable

7.0000

m

55.50

388.50

1/2" PVC Channel

5.0000

m

18.00

90.00

1C-1.5sq.mm BYA ECC

5.0000

m

13.00

65.00

5A Piano switch

1.0000

no

wooden block

1.0000

no

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Asst Electrician

0.1500

day

680.00

102.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 773.50

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

48.73

Subtotal-A1: Subtotal-B: Subtotal-C:

822.23 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

838.68

10% Profit ( Add 10% on Subtotal-B) :

922.54

VAT

6% of Total

61.50

IT

4% of Total

41.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1025.05

Page: 2312 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.05.02.2

2 Ceiling fan point

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 2c-1.5sq.mm (BYM) cable

7.0000

m

55.50

388.50

1/2" PVC Channel

5.0000

m

18.00

90.00

1C-1.5sq.mm BYA ECC

5.0000

m

13.00

65.00

5A Piano switch

1.0000

no

Regulator board

1.0000

no

80.00

80.00

wooden block

1.0000

no

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Asst Electrician

0.1500

day

680.00

102.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 877.00

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

55.25

Subtotal-A1: Subtotal-B: Subtotal-C:

932.25 950.90

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1045.99

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

69.73 46.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1162.21

Page: 2313 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.02.3

2 Call bell point with bell push

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 2c-1.5sq.mm (BYM) cable

8.0000

m

55.50

444.00

1/2" PVC Channel

6.0000

m

18.00

108.00

1C-1.5sq.mm BYA ECC

6.0000

m

13.00

78.00

5A call bell push with brass copper contact

1.0000

no

35.00

35.00

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Asst Electrician

0.1500

day

680.00

102.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 895.00

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

56.39

Subtotal-A1: Subtotal-B: Subtotal-C:

951.39 970.41

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1067.45

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

71.16 47.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1186.06

Page: 2314 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.02.4

2 2-pin 5 amps socket (outlet)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point GP sheet board with ebonite cover

1.0000

m

5A Piano switch

1.0000

no

2-Pin 5 amp Piono Socket

1.0000

each

25.00

25.00

30.00

30.00

Asst Electrician

0.0330

day

680.00

22.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50

10.0000

m

35.00

350.00

2c-1.5sq.mm (BYFYE) cable

450.94

Subtotal-A: All other remaining costs

( +6.30 % on Subtotal-A )

28.41

Subtotal-A1: Subtotal-B: Subtotal-C:

479.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

488.94

10% Profit ( Add 10% on Subtotal-B) :

537.83

VAT

6% of Total

IT

4% of Total

35.86 23.90 Total:

8.05.03

597.59

Surface Conduit wiring : Conduit wiring on Surface for the following Points Looping at the Switch board with earth terminal including Circuit wiring with 1c-2x1.5 Sq.mm PVC insulated and stranded cable (BYA) & 1.5 mm rm (green) PVC insulated ECC wire (BYA) through PVC conduit (Aziz or equivalent) of 25 mm inner dia , wall thickness 1.5 mm, 18 SWG GP Sheet, switch board & Pull box with 3 mm thick ebonite sheet cover, 5 amps. Piano type switch, brass holder, ceiling rose, wooden round block, fixing materials & all other accessories as required including mending the damages: Manufacturer of cable Eastern/BRB/Citizen/ Paradise/Poly cable/ Super sign/EVANA or equivalent according to the specification & direction of the Engineer- incharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2315 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.03.1

Detailed Analysis Brief Description of Item 2 Light point/Exhaust/Wall bracket fan point

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 1c, 2x1.5sq.mm (BYA) cable

7.0000

m

28.00

196.00

20mm dia PVC pipe

5.0000

m

24.00

120.00

1C-1.5sq.mm BYA ECC

5.0000

m

13.00

65.00

5A Piano switch

1.0000

no

3"x3" PVC Circular Box

1.0000

no

20.00

20.00

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Asst Electrician

0.1250

day

680.00

85.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 648.00

Subtotal-A: all other remaning cost

( +6.30 % on Subtotal-A )

40.82

Subtotal-A1: Subtotal-B: Subtotal-C:

688.82 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

702.60

10% Profit ( Add 10% on Subtotal-B) :

772.86

VAT

6% of Total

51.52

IT

4% of Total

34.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

858.73

Page: 2316 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.05.03.2

2 Ceiling fan point

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 1c, 2x1.5sq.mm (BYA) cable

7.0000

m

28.00

196.00

20mm dia PVC pipe

5.0000

m

24.00

120.00

1C-1.5sq.mm BYA ECC

5.0000

m

13.00

65.00

5A Piano switch

1.0000

no

3"x3" PVC Circular Box

1.0000

no

20.00

20.00

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Regulator board

1.0000

no

80.00

80.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Asst Electrician

0.1250

day

680.00

85.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 751.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

47.34

Subtotal-A1:

798.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

814.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

896.30

VAT

6% of Total

IT

4% of Total

59.75 39.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

995.89

Page: 2317 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.03.3

2 Call bell point with bell push

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 1c, 2x1.5sq.mm (BYA) cable

8.0000

m

28.00

224.00

20mm dia PVC pipe

6.0000

m

24.00

144.00

1C-1.5sq.mm BYA ECC

6.0000

m

13.00

78.00

5A call bell push with brass copper contact

1.0000

no

35.00

35.00

3"x3" PVC Circular Box

1.0000

no

20.00

20.00

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Asst Electrician

0.1250

day

680.00

85.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 748.00

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

47.12

Subtotal-A1: Subtotal-B: Subtotal-C:

795.12 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

811.03

10% Profit ( Add 10% on Subtotal-B) :

892.13

VAT

6% of Total

59.48

IT

4% of Total

39.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

991.25

Page: 2318 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.03.4

2 2-pin 5 amps socket (outlet)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point GP sheet board with ebonite cover

1.0000

m

5A Piano switch

1.0000

no

2-Pin 5 amp Piono Socket

1.0000

each

25.00

25.00

30.00

30.00

Asst Electrician

0.0330

day

680.00

22.44

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50

10.0000

m

35.00

350.00

2c-1.5sq.mm (BYFYE) cable

450.94

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

28.41

Subtotal-A1: Subtotal-B: Subtotal-C:

479.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

488.94

10% Profit ( Add 10% on Subtotal-B) :

537.83

VAT

6% of Total

IT

4% of Total

35.86 23.90 Total:

8.05.04

597.59

Concealed Conduit wiring: Concealed Conduit wiring for the following Points Looping at the Switch board with earth terminal including Circuit wiring with 1c-2x1.5 Sq.mm PVC insulated stranded cable (BYA) & 1.5 Sq.mm (Yellow-green) PVC insulated stranded ECC wire (BYA) through PVC conduit (Aziz or equivalent) of 25 mm inner dia wall thickness 1.5 mm, 18 SWG GP Sheet, switch board & Pull box with 3mm thick ebonite sheet cover, brass contact, ceiling rose, fixing materials & all other accessories as required including mending the damages: Manufacturer of cable Eastern/ BRB/Citizen/Paradise/Poly cable/Super sign/EVANA or equivalent according to the specification & direction of the Engineer- incharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2319 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.04.1

Detailed Analysis Brief Description of Item 2 Light point/Exhaust/Wall bracket fan point

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 1c, 2x1.5sq.mm (BYA) cable

7.0000

m

28.00

196.00

20mm dia PVC pipe

5.0000

m

24.00

120.00

1C-1.5sq.mm BYA ECC

5.0000

m

13.00

65.00

5A Piano switch

1.0000

no

3"x3" PVC Circular Box

1.0000

no

20.00

20.00

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Plumber/ Electric Mistry/ Painter

0.1500

day

680.00

102.00

Asst Electrician

0.3000

day

680.00

204.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4000

day

470.00

188.00 895.00

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

56.39

Subtotal-A1: Subtotal-B: Subtotal-C:

951.39 970.41

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1067.45

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

71.16

IT

4% of Total

47.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1186.06

Page: 2320 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.05.04.2

2 Ceiling fan point

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 1c, 2x1.5sq.mm (BYA) cable

7.0000

m

28.00

196.00

20mm dia PVC pipe

5.0000

m

24.00

120.00

1C-1.5sq.mm BYA ECC

5.0000

m

13.00

65.00

5A Piano switch

1.0000

no

3"x3" PVC Circular Box

1.0000

no

20.00

20.00

GP sheet SB with ebonite cover

1.0000

no

Regulator board

1.0000

no

80.00

80.00

Plumber/ Electric Mistry/ Painter

0.1500

day

680.00

102.00

Asst Electrician

0.3000

day

680.00

204.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4500

day

470.00

211.50 998.50

Subtotal-A: all other reamining cost

( +6.30 % on Subtotal-A )

62.91

Subtotal-A1: Subtotal-B: Subtotal-C:

1061.41 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1082.63

10% Profit ( Add 10% on Subtotal-B) :

1190.90

VAT

6% of Total

79.39

IT

4% of Total

52.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1323.22

Page: 2321 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.04.3

2 Call bell point with bell push

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point 1c, 2x1.5sq.mm (BYA) cable

8.0000

m

28.00

224.00

20mm dia PVC pipe

6.0000

m

24.00

144.00

1C-1.5sq.mm BYA ECC

6.0000

m

13.00

78.00

5A call bell push with brass copper contact

1.0000

no

35.00

35.00

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Plumber/ Electric Mistry/ Painter

0.1500

day

680.00

102.00

Asst Electrician

0.3000

day

680.00

204.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.4000

day

470.00

188.00 975.00

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

61.43

Subtotal-A1: Subtotal-B: Subtotal-C:

1036.43 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1057.15

10% Profit ( Add 10% on Subtotal-B) :

1162.87

VAT

6% of Total

IT

4% of Total

77.52 51.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1292.08

Page: 2322 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.04.4

2 2-pin 5 amps socket (outlet)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

point GP sheet board with ebonite cover

1.0000

m

5A Piano switch

1.0000

no

2-Pin 5 amp Piono Socket

1.0000

each

25.00

25.00

30.00

30.00

Asst Electrician

0.0030

day

680.00

2.04

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50

10.0000

m

35.00

350.00

2c-1.5sq.mm (BYFYE) cable

430.54

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

27.12

Subtotal-A1: Subtotal-B: Subtotal-C:

457.66 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

466.82

10% Profit ( Add 10% on Subtotal-B) :

513.50

VAT

6% of Total

IT

4% of Total

34.23 22.82 Total:

8.05.05

570.55

BYFYE Cable: Supplying & installation of surface batten wiring with the following PVC insulated & sheathed cable (BYFYE) on 12.5 mm thick teak wood batten, painted at the bottom. Complete with all other accessories. Manufacturer of cable Eastern/BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2323 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.05.1

2 2c – 1.5 Sq.mm (BYFYE ) Cable

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2c-1.5sq.mm (BYFYE) cable

1.0000

m

35.00

35.00

1/2"x1/2" thick CTW batten

1.0000

m

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0350

day

470.00

16.45 71.85

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

4.53

Subtotal-A1:

76.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

77.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

85.69

VAT

6% of Total

5.71

IT

4% of Total

3.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

95.22

Page: 2324 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.05.2

2 2c – 2.5 Sq.mm (BYFYE ) Cable

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2c-2.5sq.mm (BYFYE) cable

1.0000

m

55.76

55.76

1/2"x1/2" thick CTW batten

1.0000

m

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0350

day

470.00

16.45 92.61

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

5.83

Subtotal-A1:

98.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

110.45

VAT

6% of Total

7.36

IT

4% of Total

4.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

122.73

Page: 2325 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.05.3

2 2c – 4.0 Sq.mm (BYFYE ) Cable

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2c-4.0sq.mm (BYFYE) cable

1.0000

m

83.40

83.40

1/2"x1/2" thick CTW batten

1.0000

m

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0350

day

470.00

16.45 120.25

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

7.58

Subtotal-A1:

127.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

130.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

143.42

VAT

6% of Total

9.56

IT

4% of Total

6.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

159.36

Page: 2326 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.05.4

2 2c – 6.0 Sq.mm (BYFYE ) Cable

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

119.20

119.20

m 2c-6.0sq.mm (BYFYE) cable

1.0000

m

1/2"x1/2" thick CTW batten

1.0000

m

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0350

day

470.00

16.45 156.05

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

9.83

Subtotal-A1:

165.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

169.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

186.12

VAT

6% of Total

12.41

IT

4% of Total

8.27 Total:

8.05.06

206.80

BYM Cable: Supplying & installation of surface Channel wiring with the following PVC insulated & sheathed stranded cable (BYM) & green Colored PVC insulated ECC wire (BYA) through PVC Channel complete with fixing materials & other accessories as specified. Manufacturer of cable. Eastern/ BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- incharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2327 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.06.1

Detailed Analysis Brief Description of Item 2 1c-2x1.5 Sq.mm (BYM)Cable with 1.5 Sq.mm (BYA) ECC wire through PVC Channel

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2c-1.5sq.mm (BYM) cable

1.0000

m

55.50

1/2" PVC Channel

1.0000

m

18.00

18.00

1C-1.5sq.mm BYA ECC

1.0000

m

13.00

13.00

Asst Electrician

0.0250

day

680.00

17.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0250

day

470.00

11.75 115.25

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

7.26

Subtotal-A1:

122.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

124.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

137.46

VAT

6% of Total

IT

4% of Total

9.16 6.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

55.50

152.73

Page: 2328 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.06.2

Detailed Analysis Brief Description of Item 2 1c-2x2.5 Sq.mm (BYM)Cable with 2.5 Sq.mm (BYA) ECC wire through PVC Channel

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2c-2.5sq.mm (BYM) cable

1.0000

m

78.60

1/2" PVC Channel

1.0000

m

18.00

18.00

1C-2.5sq.mm BYA ECC

1.0000

m

21.00

21.00

Asst Electrician

0.0250

day

680.00

17.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0250

day

470.00

11.75 146.35

Subtotal-A: all other reamining cost

( +6.30 % on Subtotal-A )

9.22

Subtotal-A1:

155.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

158.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

174.55

VAT

6% of Total

IT

4% of Total

11.64 7.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

78.60

193.94

Page: 2329 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.06.3

Detailed Analysis Brief Description of Item 2 1c-2x4.0 Sq.mm (BYM)Cable with 4.0 Sq.mm (BYA) ECC wire through PVC Channel

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2c-4.0sq.mm (BYM) cable

1.0000

m

82.00

1/2" PVC Channel

1.0000

m

18.00

18.00

1C-4.0sq.mm BYA ECC

1.0000

m

34.00

34.00

Asst Electrician

0.2500

day

680.00

170.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0250

day

470.00

11.75 315.75

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

19.89

Subtotal-A1:

335.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

342.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

376.59

VAT

6% of Total

IT

4% of Total

25.11 16.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

82.00

418.43

Page: 2330 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.06.4

Detailed Analysis Brief Description of Item 2 1c-2x6.0 Sq.mm (BYM)Cable with 6.0 Sq.mm (BYA) ECC wire through PVC Channel

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

120.00

120.00

m 2c-6.0sq.mm (BYM) cable

1.0000

1/2" PVC Channel

1.0000

m

18.00

18.00

1C-6.0sq.mm BYA ECC

1.0000

m

50.00

50.00

Asst Electrician

0.2500

day

680.00

170.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 475.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

29.96

Subtotal-A1:

505.46

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

515.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

567.12

VAT

6% of Total

IT

4% of Total

37.81 25.21 Total:

8.05.07

630.14

BYA Cable: Conduit wiring on surface with the following PVC insulated stranded cable (BYA) & green Colored PVC insulated ECC wire (BYA) through PVC Conduit complete with fixing materials & other accessories as specified, Manufacturer of cable Eastern/BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2331 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.07.1

Detailed Analysis Brief Description of Item 2 1c-2x1.5 Sq.mm (BYA ) Cable with 1.5 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 2x1.5sq.mm (BYA) cable

1.0000

m

28.00

28.00

20mm dia PVC pipe

1.0000

m

24.00

24.00

1C-1.5sq.mm BYA ECC

1.0000

m

13.00

13.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 99.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

6.27

Subtotal-A1:

105.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

107.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

118.67

VAT

6% of Total

IT

4% of Total

7.91 5.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

131.86

Page: 2332 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.07.2

Detailed Analysis Brief Description of Item 2 1c-2x2.5 Sq.mm (BYA ) Cable with 2.5 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 2x2.5sq.mm (BYA) cable

1.0000

m

45.00

25mm dia pvc pipe

1.0000

m

32.00

32.00

1C-2.5sq.mm BYA ECC

1.0000

m

21.00

21.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 132.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

8.35

Subtotal-A1:

140.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

143.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

158.03

VAT

6% of Total

IT

4% of Total

10.54 7.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

45.00

175.59

Page: 2333 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.07.3

Detailed Analysis Brief Description of Item 2 1c-2x4.0 Sq.mm (BYA ) Cable with 4.0 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 2x4.0sq.mm (BYA) cable

1.0000

m

70.00

25mm dia pvc pipe

1.0000

m

32.00

32.00

1C-4.0sq.mm BYA ECC

1.0000

m

34.00

34.00

Asst Electrician

0.3000

day

680.00

204.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 354.10

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

22.31

Subtotal-A1:

376.41

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

383.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

422.33

VAT

6% of Total

IT

4% of Total

28.16 18.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

70.00

469.26

Page: 2334 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.07.4

Detailed Analysis Brief Description of Item 2 1c-2x6 Sq.mm (BYA ) Cable with 6.0 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

100.00

100.00

m 1c, 2x6.0sq.mm (BYA) cable

1.0000

25mm dia pvc pipe

1.0000

m

32.00

32.00

1C-6.0sq.mm BYA ECC

1.0000

m

50.00

50.00

Asst Electrician

0.2500

day

680.00

170.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 469.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

29.58

Subtotal-A1:

499.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

509.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

559.97

VAT

6% of Total

IT

4% of Total

37.33 24.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

622.18

Page: 2335 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.07.5

Detailed Analysis Brief Description of Item 2 1c-2x10 Sq.mm (BYA ) Cable with 10 Sq.mm (BYA) ECC wire through PVC Pipe of 31 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

165.00

165.00

m 1c, 2x10.0sq.mm (BYA) cable

1.0000

32mm dia pvc pipe

1.0000

m

56.00

56.00

1C-10.0sq.mm BYA ECC

1.0000

m

83.00

83.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10 338.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

21.33

Subtotal-A1:

359.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

367.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

403.72

VAT

6% of Total

IT

4% of Total

26.91 17.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

448.58

Page: 2336 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.07.6

Detailed Analysis Brief Description of Item 2 1c-2x16 Sq.mm (BYA ) Cable with 16 Sq.mm (BYA) ECC wire through PVC Pipe of 40 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

260.00

260.00

m 1c, 2x16.0sq.mm (BYA) cable

1.0000

40mm dia pvc pipe

1.0000

m

70.00

70.00

1C-16.0sq.mm BYA ECC

1.0000

m

126.00

126.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0400

day

470.00

18.80 495.20

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

31.20

Subtotal-A1:

526.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

536.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

590.62

VAT

6% of Total

IT

4% of Total

39.37 26.25 Total:

8.05.08

656.24

NYY Cable: Surface Conduit wiring with the following PVC insulated stranded cable (NYY) & green Colored PVC insulated ECC wire (BYA) through PVC Conduit complete with fixing materials & other accessories as specified, Manufacturer of cable Eastern/BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2337 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.01

Detailed Analysis Brief Description of Item 2 1c-4x2.5 Sq.mm (NYY ) Cable with 2.5 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

150.00

150.00

m 1c, 4x2.5sq.mm (NYY) cable

1.0000

32mm dia pvc pipe

1.0000

m

56.00

56.00

1C-2.5sq.mm BYA ECC

1.0000

m

21.00

21.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 270.90

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

17.07

Subtotal-A1:

287.97

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

293.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

323.10

VAT

6% of Total

IT

4% of Total

21.54 14.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

359.00

Page: 2338 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.02

Detailed Analysis Brief Description of Item 2 1c-4x4.0 Sq.mm (NYY ) Cable with 4.0 Sq.mm (BYA) ECC wire through PVC Pipe of 30 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

210.00

210.00

m 1c, 4x4.0sq.mm (NYY) cable

1.0000

32mm dia pvc pipe

1.0000

m

56.00

56.00

1C-4.0sq.mm BYA ECC

1.0000

m

34.00

34.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 343.90

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

21.67

Subtotal-A1:

365.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

372.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

410.16

VAT

6% of Total

IT

4% of Total

27.34 18.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

455.74

Page: 2339 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.03

Detailed Analysis Brief Description of Item 2 1c-4x6 Sq.mm (NYY ) Cable with 6.0 Sq.mm (BYA) ECC wire through PVC Pipe of 30 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

285.00

285.00

m 1c, 4x6.0sq.mm (NYY) cable

1.0000

40mm dia pvc pipe

1.0000

m

70.00

70.00

1C-6.0sq.mm BYA ECC

1.0000

m

50.00

50.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 448.90

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

28.28

Subtotal-A1:

477.18

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

486.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

535.40

VAT

6% of Total

IT

4% of Total

35.69 23.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

594.89

Page: 2340 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.04

Detailed Analysis Brief Description of Item 2 1c-4x10 Sq.mm (NYY ) Cable with 10 Sq.mm (BYA) ECC wire through PVC Pipe of 40 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

420.00

420.00

m 1c, 4x10.0sq.mm (NYY) cable

1.0000

40mm dia pvc pipe

1.0000

m

70.00

70.00

1C-10.0sq.mm BYA ECC

1.0000

m

83.00

83.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 621.60

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

39.16

Subtotal-A1:

660.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

673.98

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

741.37

VAT

6% of Total

IT

4% of Total

49.42 32.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

823.75

Page: 2341 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.05

Detailed Analysis Brief Description of Item 2 1c-4x16 Sq.mm (NYY ) Cable with 16 Sq.mm (BYA) ECC wire through PVC Pipe of 40 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

625.00

625.00

m 1c, 4x16.0sq.mm (NYY) cable

1.0000

40mm dia pvc pipe

1.0000

m

70.00

70.00

1C-16.0sq.mm BYA ECC

1.0000

m

126.00

126.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 869.60

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

54.78

Subtotal-A1: Subtotal-B: Subtotal-C:

924.38 942.87

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1037.16

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

69.14 46.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1152.40

Page: 2342 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.06

Detailed Analysis Brief Description of Item 2 1c-4x25 Sq.mm (NYY ) Cable with 16 Sq.mm (BYA) ECC wire through PVC Pipe of 50 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

940.00

940.00

m 1c, 4x25.0sq.mm (NYY) cable

1.0000

50mm dia pvc pipe

1.0000

m

103.00

103.00

1C-16.0sq.mm BYA ECC

1.0000

m

126.00

126.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90 1222.30

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

77.00

Subtotal-A1:

1299.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1325.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1457.82

VAT

6% of Total

IT

4% of Total

97.19 64.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1619.80

Page: 2343 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.07

Detailed Analysis Brief Description of Item 2 1c-4x35 Sq.mm (NYY) Cable with 16 Sq.mm (BYA) ECC wire through PVC Pipe of 50 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x35.0sq.mm (NYY) cable

1.0000

m

1256.00

50mm dia pvc pipe

1.0000

m

103.00

103.00

1C-25.0sq.mm BYA ECC

1.0000

m

202.00

202.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90 1614.30

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

101.70

Subtotal-A1:

1716.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1750.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1925.35

VAT

6% of Total

IT

4% of Total

128.36 85.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1256.00

2139.28

Page: 2344 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.08

Detailed Analysis Brief Description of Item 2 1c-4x50 Sq.mm (NYY) Cable with 25 Sq.mm (BYA) ECC wire through PVC Pipe of 65 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x50.0sq.mm (NYY) cable

1.0000

m

1765.00

50mm dia pvc pipe

1.0000

m

103.00

103.00

1C-35.0sq.mm BYA ECC

1.0000

m

278.00

278.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60 2204.00

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

138.85

Subtotal-A1:

2342.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2389.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2628.68

VAT

6% of Total

IT

4% of Total

175.25 116.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1765.00

2920.76

Page: 2345 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.09

Detailed Analysis Brief Description of Item 2 1c-4x70 Sq.mm (NYY ) Cable with 35 Sq.mm (BYA) ECC wire through PVC Pipe of 65 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x70.0sq.mm (NYY) cable

1.0000

m

2415.00

75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00

1C-50.0sq.mm BYA ECC

1.0000

m

396.00

396.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60 3034.00

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

191.14

Subtotal-A1:

3225.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3289.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3618.61

VAT

6% of Total

IT

4% of Total

241.24 160.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2415.00

4020.68

Page: 2346 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.10

Detailed Analysis Brief Description of Item 2 1c-4x95 Sq.mm (NYY ) Cable with 50 Sq.mm (BYA) ECC wire through PVC Pipe of 75 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x95.0sq.mm (NYY) cable

1.0000

m

3220.00

75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00

1C-70.0sq.mm BYA ECC

1.0000

m

550.00

550.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0900

day

470.00

42.30 3997.70

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

251.86

Subtotal-A1:

4249.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4334.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4768.00

VAT

6% of Total

IT

4% of Total

317.87 211.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3220.00

5297.78

Page: 2347 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.11

Detailed Analysis Brief Description of Item 2 1c-4x120 Sq.mm (NYY ) Cable with 70 Sq.mm (BYA) ECC wire through PVC Pipe of75 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x120.0sq.mm (NYY) cable

1.0000

m

4010.00

75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00

1C-70.0sq.mm BYA ECC

1.0000

m

550.00

550.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 4792.40

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

301.92

Subtotal-A1:

5094.32

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5196.21

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5715.83

VAT

6% of Total

IT

4% of Total

381.06 254.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4010.00

6350.92

Page: 2348 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.12

Detailed Analysis Brief Description of Item 2 1c-4x150 Sq.mm (NYY ) Cable with 70 Sq.mm (BYA) ECC wire through PVC Pipe of 75 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x150.0sq.mm (NYY) cable

1.0000

m

4960.00

4960.00

100mm dia pvc pipe

1.0000

m

244.00

244.00

1C-95.0sq.mm BYA ECC

1.0000

m

740.00

740.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 6011.40

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

378.72

Subtotal-A1:

6390.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6517.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7169.71

VAT

6% of Total

IT

4% of Total

477.98 318.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7966.35

Page: 2349 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.13

Detailed Analysis Brief Description of Item 2 1c-4x185 Sq.mm (NYY) Cable with 95 Sq.mm (BYA) ECC wire through PVC Pipe of 100 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x185.0sq.mm (NYY) cable

1.0000

m

6120.00

6120.00

100mm dia pvc pipe

1.0000

m

244.00

244.00

1C-120.0sq.mm BYA ECC

1.0000

m

928.00

928.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 7359.40

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

463.64

Subtotal-A1:

7823.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7979.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8777.45

VAT

6% of Total

IT

4% of Total

585.16 390.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9752.73

Page: 2350 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.14

Detailed Analysis Brief Description of Item 2 1c-4x240 Sq.mm (NYY ) Cable with 120 Sq.mm (BYA) ECC wire through PVC Pipe of 125 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x240.0sq.mm (NYY) cable

1.0000

m

7920.00

7920.00

125mm dia pvc pipe

1.0000

m

296.00

296.00

1C-120.0sq.mm BYA ECC

1.0000

m

928.00

928.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 9211.40

Subtotal-A: all other remaininig cost

( +6.30 % on Subtotal-A )

580.32

Subtotal-A1: Subtotal-B: Subtotal-C:

9791.72 9987.55

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10986.31

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

732.42 488.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12207.01

Page: 2351 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.08.15

Detailed Analysis Brief Description of Item 2 1c-4x300 Sq.mm (NYY ) Cable with 150 Sq.mm (BYA) ECC wire through PVC Pipe of 125 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x300.0sq.mm (NYY) cable

1.0000

m

9840.00

125mm dia pvc pipe

1.0000

m

296.00

296.00

1C-150.0sq.mm BYA ECC

1.0000

m

1160.00

1160.00

Asst Electrician

0.0300

day

680.00

20.40

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 11386.90

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

717.37

Subtotal-A1:

12104.27

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12346.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13581.00

VAT

6% of Total

IT

4% of Total

905.40 603.60 Total:

8.05.09

9840.00

15090.00

BYA Cable: concealed Conduit wiring with the following PVC insulated stranded cable (BYA) & green Colored PVC insulated ECC wire (BYA) through PVC Conduit (Aziz or equivalent) complete with fixing materials & other accessories as specified, Manufacturer of cable Eastern/BRB/Citizen/Paradise/Poly cable/Super sign/EVANA or equivalent according to the Specification & direction of the Engineer-incharge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2352 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.09.1

Detailed Analysis Brief Description of Item 2 1c-2x1.5 Sq.mm (BYA ) Cable with 1.5 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 2x1.5sq.mm (BYA) cable

1.0000

m

28.00

28.00

20mm dia PVC pipe

1.0000

m

24.00

24.00

1C-1.5sq.mm BYA ECC

1.0000

m

13.00

13.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 122.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

7.72

Subtotal-A1:

130.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

146.10

VAT

6% of Total

IT

4% of Total

9.74 6.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

162.34

Page: 2353 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.09.2

Detailed Analysis Brief Description of Item 2 1c-2x2.5 Sq.mm (BYA ) Cable with 2.5 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 2x2.5sq.mm (BYA) cable

1.0000

m

45.00

25mm dia pvc pipe

1.0000

m

32.00

32.00

1C-2.5sq.mm BYA ECC

1.0000

m

21.00

21.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 155.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

9.80

Subtotal-A1:

165.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

168.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

185.46

VAT

6% of Total

IT

4% of Total

12.36 8.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

45.00

206.07

Page: 2354 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.09.3

Detailed Analysis Brief Description of Item 2 1c-2x4.0 Sq.mm (BYA ) Cable with 4.0 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 2x4.0sq.mm (BYA) cable

1.0000

m

70.00

25mm dia pvc pipe

1.0000

m

32.00

32.00

1C-4.0sq.mm BYA ECC

1.0000

m

34.00

34.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 193.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

12.19

Subtotal-A1:

205.69

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

209.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

230.78

VAT

6% of Total

IT

4% of Total

15.39 10.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

70.00

256.43

Page: 2355 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.09.4

Detailed Analysis Brief Description of Item 2 1c-2x6 Sq.mm (BYA ) Cable with 6.0 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

100.00

100.00

m 1c, 2x6.0sq.mm (BYA) cable

1.0000

25mm dia pvc pipe

1.0000

m

32.00

32.00

1C-6.0sq.mm BYA ECC

1.0000

m

50.00

50.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0500

day

470.00

23.50 239.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

15.09

Subtotal-A1:

254.59

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

259.68

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

285.65

VAT

6% of Total

IT

4% of Total

19.04 12.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

317.39

Page: 2356 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.09.5

Detailed Analysis Brief Description of Item 2 1c-2x10 Sq.mm (BYA ) Cable with 10 Sq.mm (BYA) ECC wire through PVC Pipe of 31 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

165.00

165.00

m 1c, 2x10.0sq.mm (BYA) cable

1.0000

32mm dia pvc pipe

1.0000

m

56.00

56.00

1C-10.0sq.mm BYA ECC

1.0000

m

83.00

83.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 366.20

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

23.07

Subtotal-A1:

389.27

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

397.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

436.76

VAT

6% of Total

IT

4% of Total

29.12 19.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

485.29

Page: 2357 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.09.6

Detailed Analysis Brief Description of Item 2 1c-2x16 Sq.mm (BYA ) Cable with 16 Sq.mm (BYA) ECC wire through PVC Pipe of 40 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

260.00

260.00

m 1c, 2x16.0sq.mm (BYA) cable

1.0000

40mm dia pvc pipe

1.0000

m

70.00

70.00

1C-16.0sq.mm BYA ECC

1.0000

m

126.00

126.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20 518.20

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

32.65

Subtotal-A1:

550.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

561.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

618.05

VAT

6% of Total

IT

4% of Total

41.20 27.47 Total:

8.05.10

686.72

NYY Cable: concealed Conduit wiring with the following PVC insulated stranded cable (NYY) & green Colored PVC insulated stranded ECC wire (BYA) through PVC Conduit complete with fixing materials & other accessories as specified, Manufacturer of cable BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2358 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.01

Detailed Analysis Brief Description of Item 2 1c-4x2.5 Sq.mm (NYY) Cable with 2.5 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

150.00

150.00

m 1c, 4x2.5sq.mm (NYY) cable

1.0000

32mm dia pvc pipe

1.0000

m

56.00

56.00

1C-2.5sq.mm BYA ECC

1.0000

m

21.00

21.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90 293.90

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

18.52

Subtotal-A1:

312.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

318.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

350.53

VAT

6% of Total

IT

4% of Total

23.37 15.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

389.48

Page: 2359 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.02

Detailed Analysis Brief Description of Item 2 1c-4x4.0 Sq.mm (NYY) Cable with 4.0 Sq.mm (BYA) ECC wire through PVC Pipe of 25 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

210.00

210.00

m 1c, 4x4.0sq.mm (NYY) cable

1.0000

32mm dia pvc pipe

1.0000

m

56.00

56.00

1C-4.0sq.mm BYA ECC

1.0000

m

34.00

34.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90 366.90

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

23.11

Subtotal-A1:

390.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

397.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

437.60

VAT

6% of Total

IT

4% of Total

29.17 19.45 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

486.22

Page: 2360 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.03

Detailed Analysis Brief Description of Item 2 1c-4x6 Sq.mm (NYY) Cable with 6.0 Sq.mm (BYA) ECC wire through PVC Pipe of 30 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

285.00

285.00

m 1c, 4x6.0sq.mm (NYY) cable

1.0000

40mm dia pvc pipe

1.0000

m

70.00

70.00

1C-6.0sq.mm BYA ECC

1.0000

m

50.00

50.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90 471.90

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

29.73

Subtotal-A1:

501.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

511.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

562.83

VAT

6% of Total

IT

4% of Total

37.52 25.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

625.37

Page: 2361 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.04

Detailed Analysis Brief Description of Item 2 1c-4x10 Sq.mm (NYY) Cable with 10 Sq.mm (BYA) ECC wire through PVC Pipe of 40 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

420.00

420.00

m 1c, 4x10.0sq.mm (NYY) cable

1.0000

40mm dia pvc pipe

1.0000

m

70.00

70.00

1C-10.0sq.mm BYA ECC

1.0000

m

83.00

83.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60 644.60

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

40.61

Subtotal-A1:

685.21

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

698.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

768.81

VAT

6% of Total

IT

4% of Total

51.25 34.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

854.23

Page: 2362 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.05

Detailed Analysis Brief Description of Item 2 1c-4x16 Sq.mm (NYY) Cable with 16 Sq.mm (BYA) ECC wire through PVC Pipe of 40 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

625.00

625.00

m 1c, 4x16.0sq.mm (NYY) cable

1.0000

40mm dia pvc pipe

1.0000

m

70.00

70.00

1C-16.0sq.mm BYA ECC

1.0000

m

126.00

126.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60 892.60

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

56.23

Subtotal-A1: Subtotal-B: Subtotal-C:

948.83 967.81

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1064.59

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

70.97 47.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1182.88

Page: 2363 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.06

Detailed Analysis Brief Description of Item 2 1c-4x25 Sq.mm (NYY) Cable with 16 Sq.mm (BYA) ECC wire through PVC Pipe of 50 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

940.00

940.00

m 1c, 4x25.0sq.mm (NYY) cable

1.0000

50mm dia pvc pipe

1.0000

m

103.00

103.00

1C-16.0sq.mm BYA ECC

1.0000

m

126.00

126.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0900

day

470.00

42.30 1245.30

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

78.45

Subtotal-A1:

1323.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1350.23

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1485.25

VAT

6% of Total

IT

4% of Total

99.02 66.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1650.28

Page: 2364 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.07

Detailed Analysis Brief Description of Item 2 1c-4x35 Sq.mm (NYY) Cable with 16 Sq.mm (BYA) ECC wire through PVC Pipe of 50 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x35.0sq.mm (NYY) cable

1.0000

m

1256.00

50mm dia pvc pipe

1.0000

m

103.00

103.00

1C-16.0sq.mm BYA ECC

1.0000

m

126.00

126.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0900

day

470.00

42.30 1561.30

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

98.36

Subtotal-A1:

1659.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1692.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1862.14

VAT

6% of Total

IT

4% of Total

124.14 82.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1256.00

2069.05

Page: 2365 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.08

Detailed Analysis Brief Description of Item 2 1c-4x50 Sq.mm (NYY) Cable with 25 Sq.mm (BYA) ECC wire through PVC Pipe of 65 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x50.0sq.mm (NYY) cable

1.0000

m

1765.00

50mm dia pvc pipe

1.0000

m

103.00

103.00

1C-25.0sq.mm BYA ECC

1.0000

m

202.00

202.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0900

day

470.00

42.30 2146.30

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

135.22

Subtotal-A1:

2281.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2327.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2559.86

VAT

6% of Total

IT

4% of Total

170.66 113.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1765.00

2844.29

Page: 2366 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.09

Detailed Analysis Brief Description of Item 2 1c-4x70 Sq.mm (NYY) Cable with 35 Sq.mm (BYA) ECC wire through PVC Pipe of 65 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x70.0sq.mm (NYY) cable

1.0000

m

2415.00

75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00

1C-35.0sq.mm BYA ECC

1.0000

m

278.00

278.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 2939.00

Subtotal-A: all other remaing cost

( +6.30 % on Subtotal-A )

185.16

Subtotal-A1:

3124.16

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3186.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3505.30

VAT

6% of Total

IT

4% of Total

233.69 155.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2415.00

3894.78

Page: 2367 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.10

Detailed Analysis Brief Description of Item 2 1c-4x95 Sq.mm (NYY) Cable with 50 Sq.mm (BYA) ECC wire through PVC Pipe of 75 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x95.0sq.mm (NYY) cable

1.0000

m

3220.00

75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00

1C-50.0sq.mm BYA ECC

1.0000

m

396.00

396.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1250

day

470.00

58.75 3873.75

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

244.05

Subtotal-A1:

4117.80

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4200.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4620.17

VAT

6% of Total

IT

4% of Total

308.01 205.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3220.00

5133.52

Page: 2368 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.11

Detailed Analysis Brief Description of Item 2 1c-4x120 Sq.mm (NYY) Cable with 70 Sq.mm (BYA) ECC wire through PVC Pipe of 75 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x120.0sq.mm (NYY) cable

1.0000

m

4010.00

4010.00

100mm dia pvc pipe

1.0000

m

244.00

244.00

1C-70.0sq.mm BYA ECC

1.0000

m

550.00

550.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1250

day

470.00

58.75 4896.75

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

308.50

Subtotal-A1:

5205.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5309.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5840.29

VAT

6% of Total

IT

4% of Total

389.35 259.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6489.21

Page: 2369 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.12

Detailed Analysis Brief Description of Item 2 1c-4x150 Sq.mm (NYY) Cable with 70 Sq.mm (BYA) ECC wire through PVC Pipe of 100 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x150.0sq.mm (NYY) cable

1.0000

m

4960.00

4960.00

100mm dia pvc pipe

1.0000

m

244.00

244.00

1C-70.0sq.mm BYA ECC

1.0000

m

550.00

550.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 5858.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

369.09

Subtotal-A1:

6227.59

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6352.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6987.35

VAT

6% of Total

IT

4% of Total

465.82 310.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7763.72

Page: 2370 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.13

Detailed Analysis Brief Description of Item 2 1c-4x185 Sq.mm (NYY) Cable with 95 Sq.mm (BYA) ECC wire through PVC Pipe of 100 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x185.0sq.mm (NYY) cable

1.0000

m

6120.00

6120.00

100mm dia pvc pipe

1.0000

m

244.00

244.00

1C-95.0sq.mm BYA ECC

1.0000

m

740.00

740.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 7208.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

454.14

Subtotal-A1:

7662.64

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7815.89

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8597.48

VAT

6% of Total

IT

4% of Total

573.17 382.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9552.75

Page: 2371 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.14

Detailed Analysis Brief Description of Item 2 1c-4x240 Sq.mm (NYY) Cable with 120 Sq.mm (BYA) ECC wire through PVC Pipe of 125 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x240.0sq.mm (NYY) cable

1.0000

m

7920.00

7920.00

125mm dia pvc pipe

1.0000

m

296.00

296.00

1C-120.0sq.mm BYA ECC

1.0000

m

928.00

928.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1750

day

470.00

82.25 9260.25

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

583.40

Subtotal-A1:

9843.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10040.52

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11044.57

VAT

6% of Total

IT

4% of Total

736.30 490.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12271.75

Page: 2372 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.15

Detailed Analysis Brief Description of Item 2 1c-4x300 Sq.mm (NYY) Cable with 150 Sq.mm (BYA) ECC wire through PVC Pipe of 125 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x300.0sq.mm (NYY) cable

1.0000

m

9840.00

125mm dia pvc pipe

1.0000

m

296.00

296.00

1C-150.0sq.mm BYA ECC

1.0000

m

1160.00

1160.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1750

day

470.00

82.25 11412.25

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

718.97

Subtotal-A1:

12131.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12373.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13611.23

VAT

6% of Total

IT

4% of Total

907.42 604.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9840.00

15123.59

Page: 2373 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.10.16

Detailed Analysis Brief Description of Item 2 1c-4x400 Sq.mm (NYY) Cable with 150 Sq.mm (BYA) ECC wire through PVC Pipe of 125 mm inner dia.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c, 4x400.0sq.mm (NYY) cable

1.0000

m

13090.00

125mm dia pvc pipe

1.0000

m

296.00

296.00

1C-150.0sq.mm BYA ECC

1.0000

m

1160.00

1160.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1750

day

470.00

82.25 14662.25

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14955.50

10% Profit ( Add 10% on Subtotal-B) :

16451.04

VAT

6% of Total

IT

4% of Total

1096.74 731.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13090.00

18278.94

Page: 2374 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

8.05.10.20

1c-3X240+120Sq.mm (2xFGY)Armour Cable through PVC Pipe of 150mm inner dia.

m

Quantity 5

Unit

Rate

6

7

Amount 8

1c, 3x240+120sq.mm (2xRGY) cable

1.0000

m

13471.00

125mm dia pvc pipe

1.0000

m

296.00

296.00

1C-150.0sq.mm BYA ECC

1.0000

m

1160.00

1160.00

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1750

day

470.00

82.25 15043.25

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15344.12

10% Profit ( Add 10% on Subtotal-B) :

16878.53

VAT

6% of Total

IT

4% of Total

1125.24 750.16 Total:

8.05.11

13471.00

18753.92

HT Cable: Supplying & Laying of following sizes HT (11KV) PVC insulated & sheathed stranded screened & armoured cable (NYSEYFGbY)/ HT(11KV) armoured XLPE cable in common trench.With HT (11KV) Cables (NYSEYFGby) Manufacturer of cable BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2375 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.11.1

Detailed Analysis Brief Description of Item 2 3Cx25 sq.mm cable in ground/road through 75 mm PVC pipe having wall thickness of 3mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx25sq.mm (NYSEYFGbY) cable

1.0000

m

2212.00

2212.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90

Mason

0.0300

day

550.00

16.50

75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00 2482.40

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

156.39

Subtotal-A1:

2638.79

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2691.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2960.72

VAT

6% of Total

197.38

IT

4% of Total

131.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3289.69

Page: 2376 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.11.2

Detailed Analysis Brief Description of Item 2 3Cx35 sq.mm cable in ground/road through 75 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx35sq.mm (NYSEYFGbY) cable

1.0000

m

2548.00

2548.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90

Mason

0.0300

day

550.00

16.50

75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00 2818.40

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

177.56

Subtotal-A1:

2995.96

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3055.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3361.47

VAT

6% of Total

224.10

IT

4% of Total

149.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3734.96

Page: 2377 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.11.3

Detailed Analysis Brief Description of Item 2 3Cx50 sq.mm cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx50sq.mm (NYSEYFGbY) cable

1.0000

m

3020.00

3020.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60

Mason

0.0300

day

550.00

16.50

100mm dia pvc pipe

1.0000

m

244.00

244.00 3374.10

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

212.57

Subtotal-A1:

3586.67

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3658.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4024.24

VAT

6% of Total

268.28

IT

4% of Total

178.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4471.38

Page: 2378 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.11.4

Detailed Analysis Brief Description of Item 2 3Cx70 sq.mm cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx70sq.mm (NYSEYFGbY) cable

1.0000

m

3700.00

3700.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60

Mason

0.0300

day

550.00

16.50

100mm dia pvc pipe

1.0000

m

244.00

244.00 4054.10

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

255.41

Subtotal-A1:

4309.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4395.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4835.27

VAT

6% of Total

322.35

IT

4% of Total

214.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5372.52

Page: 2379 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.11.5

Detailed Analysis Brief Description of Item 2 3Cx95 sq.mm cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx95sq.mm (NYSEYFGbY) cable

1.0000

m

3700.00

3700.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0900

day

470.00

42.30

Mason

0.0300

day

550.00

16.50

100mm dia pvc pipe

1.0000

m

244.00

244.00 4058.80

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

255.70

Subtotal-A1:

4314.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4400.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4840.87

VAT

6% of Total

322.72

IT

4% of Total

215.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5378.75

Page: 2380 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.11.6

Detailed Analysis Brief Description of Item 2 3Cx120 sq.mm cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx120sq.mm (NYSEYFGbY) cable

1.0000

m

5252.00

5252.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00

Mason

0.0400

day

550.00

22.00

100mm dia pvc pipe

1.0000

m

244.00

244.00 5621.00

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

354.12

Subtotal-A1:

5975.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6094.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6704.09

VAT

6% of Total

446.94

IT

4% of Total

297.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7448.99

Page: 2381 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.11.7

Detailed Analysis Brief Description of Item 2 3Cx150 sq.mm cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx150sq.mm (NYSEYFGbY) cable

1.0000

m

6365.00

6365.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50

Mason

0.0400

day

550.00

22.00

100mm dia pvc pipe

1.0000

m

244.00

244.00 6757.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

425.72

Subtotal-A1:

7183.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7326.89

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8059.58

VAT

6% of Total

537.31

IT

4% of Total

358.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8955.08

Page: 2382 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.11.8

Detailed Analysis Brief Description of Item 2 3Cx185 sq.mm cable in ground/road through 125 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx185sq.mm (NYSEYFGbY) cable

1.0000

m

11688.00

11688.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50

Mason

0.0400

day

550.00

22.00

125mm dia pvc pipe

1.0000

m

296.00

296.00 12132.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

764.35

Subtotal-A1:

12896.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13154.78

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14470.26

VAT

6% of Total

964.68

IT

4% of Total

643.12 Total:

8.05.12

16078.07

With HT (11KV) Cables (XLPE) insulated PVC sheathed armoured cables Manufacturer of cable BRB/Citizen/Paradise/Poly cable/Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2383 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

8.05.12.1

3Cx25 sq.mm XLPE cable in ground/road through 75 mm PVC pipe having wall thickness of 3mm

m

Quantity 5

Unit

Rate

6

7

HT 3cx25sq.mm (XLPE) cable

1.0000

m

bricks for separation

4.0000

Asst Electrician

0.0500

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

Amount 8

1730.00

1730.00

each

5.50

22.00

day

680.00

34.00

0.0600

day

470.00

28.20

Mason

0.0300

day

550.00

16.50

75mm PVC Pipe -2.9mm to 3.4mm wall thick

1.0000

m

165.00

165.00 1995.70

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

125.73

Subtotal-A1:

2121.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2163.86

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2380.24

VAT

6% of Total

158.68

IT

4% of Total

105.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2644.71

Page: 2384 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.12.2

Detailed Analysis Brief Description of Item 2 3Cx35 sq.mm XLPE cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx35sq.mm (XLPE) cable

1.0000

m

2080.00

2080.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0600

day

470.00

28.20

Mason

0.0300

day

550.00

16.50

100mm dia pvc pipe

1.0000

m

244.00

244.00 2424.70

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

152.76

Subtotal-A1:

2577.46

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2629.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2891.91

VAT

6% of Total

192.79

IT

4% of Total

128.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3213.23

Page: 2385 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.12.3

Detailed Analysis Brief Description of Item 2 3Cx50 sq.mm XLPE cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx50sq.mm (XLPE) cable

1.0000

m

2525.00

2525.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0700

day

470.00

32.90

Mason

0.0300

day

550.00

16.50

100mm dia pvc pipe

1.0000

m

244.00

244.00 2874.40

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

181.09

Subtotal-A1:

3055.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3116.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3428.26

VAT

6% of Total

228.55

IT

4% of Total

152.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3809.17

Page: 2386 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.12.4

Detailed Analysis Brief Description of Item 2 3Cx70 sq.mm XLPE cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx70sq.mm (XLPE) cable

1.0000

m

3200.00

3200.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60

Mason

0.0400

day

550.00

22.00

100mm dia pvc pipe

1.0000

m

244.00

244.00 3559.60

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

224.25

Subtotal-A1:

3783.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3859.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4245.49

VAT

6% of Total

283.03

IT

4% of Total

188.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4717.21

Page: 2387 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.12.5

Detailed Analysis Brief Description of Item 2 3Cx95 sq.mm XLPE cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx95sq.mm (XLPE) cable

1.0000

m

4010.00

4010.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0900

day

470.00

42.30

Mason

0.0400

day

550.00

22.00

100mm dia pvc pipe

1.0000

m

244.00

244.00 4374.30

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

275.58

Subtotal-A1:

4649.88

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4742.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5217.17

VAT

6% of Total

347.81

IT

4% of Total

231.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5796.85

Page: 2388 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.12.6

Detailed Analysis Brief Description of Item 2 3Cx120 sq.mm XLPE cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx120sq.mm (XLPE) cable

1.0000

m

4735.00

4735.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00

Mason

0.0400

day

550.00

22.00

100mm dia pvc pipe

1.0000

m

244.00

244.00 5104.00

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

321.55

Subtotal-A1:

5425.55

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5534.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6087.47

VAT

6% of Total

405.83

IT

4% of Total

270.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6763.85

Page: 2389 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.12.7

Detailed Analysis Brief Description of Item 2 3Cx150 sq.mm XLPE cable in ground/road through 100 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx150sq.mm (XLPE) cable

1.0000

m

5600.00

5600.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00

Mason

0.0400

day

550.00

22.00

100mm dia pvc pipe

1.0000

m

244.00

244.00 5969.00

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

376.05

Subtotal-A1:

6345.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6471.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7119.14

VAT

6% of Total

474.61

IT

4% of Total

316.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7910.16

Page: 2390 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.12.8

Detailed Analysis Brief Description of Item 2 3Cx185 sq.mm XLPE cable in ground/road through 125 mm PVC pipe having wall thickness of 3mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m HT 3cx185sq.mm (XLPE) cable

1.0000

m

6630.00

6630.00

bricks for separation

4.0000

Asst Electrician

0.0500

each

5.50

22.00

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50

Mason

0.0400

day

550.00

22.00

125mm dia pvc pipe

1.0000

m

296.00

296.00 7074.50

Subtotal-A: all other remaining cost

( +6.30 % on Subtotal-A )

445.69

Subtotal-A1:

7520.19

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7670.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8437.66

VAT

6% of Total

562.51

IT

4% of Total

375.01 Total:

8.05.13

9375.17

Telecommunication Cable: Providing and drawing of following size PVC insulated & sheathed twisted pair telecommunication cable through prelaid pipes.Manufacturer of cable BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2391 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.13.01

2 1C-2x0.282 sq.mm (1 pair)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m TP cable 1C-2x0282sq.mm (1 pair)

1.0000

m

14.00

14.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

0.14

Subtotal-A1: Subtotal-B: Subtotal-C:

14.14 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14.42

10% Profit ( Add 10% on Subtotal-B) :

15.87

VAT

6% of Total

IT

4% of Total

1.06 0.71 Total:

8.05.13.02

1C-4x0.282 sq.mm (2 pair)

17.63

m TP cable 1C-4x0282sq.mm (2 pair)

1.0000

m

22.00

all other remaining cost

( +1.00 % on Subtotal-A )

0.22

Subtotal-A1: Subtotal-B: Subtotal-C:

22.00 22.00

Subtotal-A:

22.22 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22.66

10% Profit ( Add 10% on Subtotal-B) :

24.93

VAT

6% of Total

IT

4% of Total

1.66 1.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14.00

27.70

Page: 2392 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.13.03

2 1C-6x0.282 sq.mm (3 pair)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m TP cable 1C-6x0282sq.mm (3 pair)

1.0000

m

33.00

33.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

0.33

Subtotal-A1: Subtotal-B: Subtotal-C:

33.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

34.00

10% Profit ( Add 10% on Subtotal-B) :

37.40

VAT

6% of Total

IT

4% of Total

2.49 1.66 Total:

8.05.13.04

1C-8x0.282 sq.mm (4 pair)

41.55

m TP cable 1C-8x0282sq.mm (4 pair)

1.0000

m

46.00

all other reamining cost

( +1.00 % on Subtotal-A )

0.46

Subtotal-A1: Subtotal-B: Subtotal-C:

46.00 46.00

Subtotal-A:

46.46 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

47.39

10% Profit ( Add 10% on Subtotal-B) :

52.13

VAT

6% of Total

IT

4% of Total

3.48 2.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

33.00

57.92

Page: 2393 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.13.05

2 1C-10x0.282 sq.mm ( 5pair)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m TP cable 1C-10x0282sq.mm (5 pair)

1.0000

m

55.00

55.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

0.55

Subtotal-A1: Subtotal-B: Subtotal-C:

55.55 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56.66

10% Profit ( Add 10% on Subtotal-B) :

62.33

VAT

6% of Total

IT

4% of Total

4.16 2.77 Total:

8.05.13.06

1C-12x0.282 sq.mm (6 pair)

69.25

m TP cable 1C-12x0282sq.mm (6 pair)

1.0000

m

66.00

all other remaining cost

( +1.00 % on Subtotal-A )

0.66

Subtotal-A1: Subtotal-B: Subtotal-C:

66.00 66.00

Subtotal-A:

66.66 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

67.99

10% Profit ( Add 10% on Subtotal-B) :

74.79

VAT

6% of Total

IT

4% of Total

4.99 3.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

55.00

83.10

Page: 2394 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.13.07

2 1C-16x0.282 sq.mm (8 pair)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m TP cable 1C-16x0282sq.mm (8 pair)

1.0000

m

84.00

84.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

0.84

Subtotal-A1: Subtotal-B: Subtotal-C:

84.84 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

86.54

10% Profit ( Add 10% on Subtotal-B) :

95.19

VAT

6% of Total

IT

4% of Total

6.35 4.23 Total:

8.05.13.08

1C-20x0.282 sq.mm (10 pair)

105.77

m TP cable 1C-20x0282sq.mm (10 pair)

1.0000

m

106.00

all other remaining cost

( +1.00 % on Subtotal-A )

1.06

Subtotal-A1: Subtotal-B: Subtotal-C:

106.00 106.00

Subtotal-A:

107.06 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

109.20

10% Profit ( Add 10% on Subtotal-B) :

120.12

VAT

6% of Total

IT

4% of Total

8.01 5.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

84.00

133.47

Page: 2395 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.13.09

2 1C-40x0.282 sq.mm (20 pair)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

200.00

200.00

m TP cable 1C-40x0282sq.mm (20 pair)

1.0000

200.00

Subtotal-A: all other remaining cost Incidental Cost

( +1.00 % on Subtotal-A ) ( +2.00 % on Subtotal-A )

2.00 4.00

Subtotal-A1: Subtotal-B: Subtotal-C:

206.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

210.12

10% Profit ( Add 10% on Subtotal-B) :

231.13

VAT

6% of Total

IT

4% of Total

15.41 10.27 Total:

8.05.13.10

1C-100x0.282 sq.mm (50 pair)

m TP cable 1C-100x0.282sq.mm (50 pair)

1.0000

m

511.00

511.00 511.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

521.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

573.34

VAT

6% of Total

IT

4% of Total

38.22 25.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

256.81

637.05

Page: 2396 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.13.11

2 Network Cable, UTP-CAT-6, Brand-Pandit/Systimax/Digi- Link or equivalent.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Network cable

1.0000

m

25.00

25.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

28.05

VAT

6% of Total

1.87

IT

4% of Total

1.25 Total:

8.05.14

CO-axial Cable: Providing and drawing of following size PVC insulated & sheathed 75 ohm impedance co-axial cables through pre-laid pipes.Manufacturer of cable BRB/Citizen/Paradise/Poly cable/ Super sign/EVANA or equivalent according to the Specification & direction of the Engineer- in-charge.

8.05.14.1

4/C CO-axial Cable

31.17

m Co-axial cable 4/C

1.0000

m

23.00

23.00 23.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

0.23

Subtotal-A1:

23.23

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26.06

VAT

6% of Total

1.74

IT

4% of Total

1.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25.00

28.96

Page: 2397 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.14.2

2 5/C CO-axial Cable

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Co-axial cable 5/C

1.0000

m

27.00

27.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

0.27

Subtotal-A1: Subtotal-B: Subtotal-C:

27.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

27.82

10% Profit ( Add 10% on Subtotal-B) :

30.60

VAT

6% of Total

IT

4% of Total

2.04 1.36 Total:

8.05.14.3

6/C CO-axial Cable

1.0000

m

36.00

all other remaining cost

( +1.00 % on Subtotal-A )

0.36

Subtotal-A1: Subtotal-B: Subtotal-C:

36.36 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

37.09

10% Profit ( Add 10% on Subtotal-B) :

40.80

VAT

6% of Total

IT

4% of Total

2.72 1.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

36.00 36.00

Subtotal-A:

Taking out old wiring including batten and stacking to a preselected place as per directions of the E-I-C.

34.00

m Co-axial cable 6/C

8.05.15

27.00

45.33

LS

Page: 2398 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

8.05.16

Concealed conduit wiring with the following PVC insulated and sheathed stranded cable (NYY/)/XLPE insulated and PVC sheathed stranded cable(2xY) & PVC insulated green/white coloured ECC wire (BYA) through PVC conduit of reputed manufacturer complete with fixing materials other accessories etc. as required including mending the damages good. All electrical contacts shall be of brass/copper connected through connector or soldering ( no twisting shall be allowed) and cables shall be manufactured and tested according to relavent IEC/BDS/BS/VDE standards and as per detailed specification mentioned in Annexure-A. The work shall be carried out as per direction/approval/ acceptance of the Engineer

8.05.16.1

1C-2x2.5 sq.mm. (NYY) cable with 2.5 sq.mm (BYA) ECC wire through PVC pipe of minimum inner dia 25 mm having wall thickness of 1.5 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1C-2x2.5 sq.mm (NYY) cable

1.0000

m

25mm dia GI pipe

1.0000

m

75.32

1C-2.5sq.mm BYA ECC

1.0000

m

21.00

21.00

Asst Electrician

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 203.92

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

208.00

10% Profit ( Add 10% on Subtotal-B) :

228.80

VAT

6% of Total

IT

4% of Total

15.25 10.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

75.32

254.22

Page: 2399 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.16.2

Detailed Analysis Brief Description of Item 2 1C-2x4.0 sq.mm. (NYY) cable with 4 sq.mm (BYA) ECC wire through PVC pipe of minimum inner dia 25 mm having wall thickness of 1.5 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

104.46

104.46

m 1C-2x4sq.mm. (NYY) cable

1.0000

m

25mm dia GI pipe

1.0000

m

1C-4.0sq.mm BYA ECC

1.0000

m

34.00

34.00

Asst Electrician

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 246.06

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

250.98

10% Profit ( Add 10% on Subtotal-B) :

276.08

VAT

6% of Total

IT

4% of Total

18.41 12.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

306.75

Page: 2400 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.16.3

Detailed Analysis Brief Description of Item 2 1C-2x6.0 sq.mm. (NYY) cable with 6 sq.mm (BYA) ECC wire through PVC pipe of minimum inner dia 25 mm having wall thickness of 1.5 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

144.28

144.28

m 1C-2x6sq.mm. (NYY) cable

1.0000

m

25mm dia GI pipe

1.0000

m

1C-6.0sq.mm BYA ECC

1.0000

m

50.00

50.00

Asst Electrician

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 301.88

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

307.92

10% Profit ( Add 10% on Subtotal-B) :

338.71

VAT

6% of Total

IT

4% of Total

22.58 15.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

376.34

Page: 2401 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.16.4

Detailed Analysis Brief Description of Item 2 1C-2x10 sq.mm. (NYY) cable with 10 sq.mm (BYA) ECC wire through PVC pipe of minimum inner dia 25 mm having wall thickness of 1.5 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

211.16

211.16

m 1C-2x10sq.mm. (NYY) cable

1.0000

m

25mm dia GI pipe

1.0000

m

1C-6.0sq.mm BYA ECC

1.0000

m

50.00

50.00

Asst Electrician

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 368.76

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

376.14

10% Profit ( Add 10% on Subtotal-B) :

413.75

VAT

6% of Total

IT

4% of Total

27.58 18.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

459.72

Page: 2402 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.16.5

Detailed Analysis Brief Description of Item 2 1C-2x16 sq.mm. (NYY) cable with 16 sq.mm (BYA) ECC wire through PVC pipe of minimum inner dia 32mm having wall thickness of 1.5 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

312.12

312.12

m 1C-2x16sq.mm. (NYY) cable

1.0000

25mm dia GI pipe

1.0000

m

1C-16.0sq.mm BYA ECC

1.0000

m

126.00

126.00

Asst Electrician

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 545.72

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

556.63

10% Profit ( Add 10% on Subtotal-B) :

612.30

VAT

6% of Total

IT

4% of Total

40.82 27.21 Total:

8.05.17

680.33

Overhead Cable AAC/ACSR: Supplying, assembling, fitting, fixing, installation (with effictive connection), testing & Commissioning of following PVC insulated aluminum stranded conductor in overhead line at proper sag all complete with necessary accessories such as G.I binding, insulator, wire as required etc.with conductor manufactured by BRB/Paradise OR equivalent accepted/approved by the Engineer-in-charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2403 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.17.1

2 1C-25 sq.mm(GNAT)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c-25sq.mm(GNAT)

1.0000

m

25.00

25.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10

Asst Electrician

0.0300

day

680.00

20.40 59.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

60.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

66.76

VAT

6% of Total

4.45

IT

4% of Total

2.97 Total:

8.05.17.2

1C-50 sq.mm(ANT)

m 1c-50sq.mm(ANT)

1.0000

m

48.00

48.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10

Asst Electrician

0.0300

day

680.00

20.40 82.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

84.15

10% Profit ( Add 10% on Subtotal-B) :

92.57

VAT

6% of Total

IT

4% of Total

6.17 4.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

74.18

102.85

Page: 2404 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.05.17.3

2 1C-75 sq.mm(EARWIG)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1c-75sq.mm(EARWIG)

1.0000

m

80.00

80.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10

Asst Electrician

0.0300

day

680.00

20.40 114.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

116.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

128.47

VAT

6% of Total

8.56

IT

4% of Total

5.71 Total:

8.05.17.4

1C-100 sq.mm(WASP)

m 1c-100sq.mm(WASP)

1.0000

m

115.00

115.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0300

day

470.00

14.10

Asst Electrician

0.0300

day

680.00

20.40 149.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

152.49

10% Profit ( Add 10% on Subtotal-B) :

167.74

VAT

6% of Total

IT

4% of Total

11.18 7.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

142.74

186.38

Page: 2405 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.05.18

Detailed Analysis Brief Description of Item 2 ELECTRICAL WIRING: Under ground wiring Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Under Ground wiring for the following Points Looping at the Switch board with earth terminal including Circuit wiring with 1c-2x2.5 Sq.mm PVC insulated stranded Sheathed cable (NYY) & 2.5 sq.mm (green) PVC insulated stranded ECC wire (BYA) through PVC conduit (Aziz or equivalent) of 25 mm inner dia wall thickness 2.0 mm, 18 SWG GP Sheet, switch board & Pull box with 3mm thick ebonite sheet cover, brass contact, ceiling rose, fixing materials & all other accessories as required including mending the damages: Manufacturer of cable Eastern/ BRB/Citizen/Paradise/Poly cable/Super sign/EVANA or equivalent according to the specification & direction of the Engineer- incharge.Garden Light /Gate Light/Security Light point

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

10.0000

m

100.00

1000.00

5.0000

m

18.00

90.00

21.00

210.00

5

Amount 8

each

1c, 2x6.0sq.mm (BYA) cable 1/2" PVC Channel 1C-2.5sq.mm BYA ECC

10.0000

m

5A Piano switch

1.0000

no

Bake light ceiling rose

1.0000

no

GP sheet SB with ebonite cover

1.0000

no

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00

Asst Electrician

0.1500

day

680.00

102.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1530.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1560.60

10% Profit ( Add 10% on Subtotal-B) :

1716.66

VAT

6% of Total

114.44

IT

4% of Total

76.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1907.40

Page: 2406 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

8.06.1

Supplying, fitting and fixing 20mm thick switch board for fan regulators, lighting switches two pin and at the three pin socket outlets the switch board to be made of teak wood and varnished on all sides etc. all complete as per directions of the E-I-C.

8.06.1.1

350mmx450mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

360.00

360.00

each Teak Wood Board (350x450x25mm) including varnishing

1.0000

each

360.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

18.00

Subtotal-A1: Subtotal-B: Subtotal-C:

378.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

385.56

10% Profit ( Add 10% on Subtotal-B) :

424.12

VAT

6% of Total

28.27

IT

4% of Total

18.85 Total:

8.06.1.2

250mmx350mm

each Teak Wood Board (250x350x25mm) including varnishing

1.0000

each

275.00

275.00 275.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

13.75

Subtotal-A1:

288.75

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

294.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

323.98

VAT

6% of Total

IT

4% of Total

21.60 14.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

471.24

359.98

Page: 2407 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.1.3

2 200mmx300mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

275.00

275.00

each Teak Wood Board (200x300x25mm) including varnishing

1.0000

each

275.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

13.75

Subtotal-A1: Subtotal-B: Subtotal-C:

288.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

294.53

10% Profit ( Add 10% on Subtotal-B) :

323.98

VAT

6% of Total

IT

4% of Total

21.60 14.40 Total:

8.06.1.4

150mmx200mm

each Teak Wood Board (150x200x 25mm) including varnishing

1.0000

each

240.00

All other remaining costs

( +5.00 % on Subtotal-A )

12.00

Subtotal-A1: Subtotal-B: Subtotal-C:

240.00 240.00

Subtotal-A:

252.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

257.04

10% Profit ( Add 10% on Subtotal-B) :

282.74

VAT

6% of Total

IT

4% of Total

18.85 12.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

359.98

314.16

Page: 2408 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.1.5

2 100mmx150mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

210.00

210.00

each Teak Wood Board (100x150x25mm) including varnishing

1.0000

each

210.00

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

10.50

Subtotal-A1: Subtotal-B: Subtotal-C:

220.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

224.91

10% Profit ( Add 10% on Subtotal-B) :

247.40

VAT

6% of Total

IT

4% of Total

16.49 11.00 Total:

8.06.1.6

100mmx100mm

each Teak Wood Board (100x100x25mm) Including varnishing

1.0000

each

180.00

All other remaining costs

( +5.00 % on Subtotal-A )

9.00

Subtotal-A1: Subtotal-B: Subtotal-C:

180.00 180.00

Subtotal-A:

189.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

192.78

10% Profit ( Add 10% on Subtotal-B) :

212.06

VAT

6% of Total

IT

4% of Total

14.14 9.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

274.89

235.62

Page: 2409 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.06.2

Detailed Analysis Brief Description of Item 2 Supplying and installation of metal board (Switch/Socket/Regulator) with open front made of 18 SWG B.P sheet with corner of 14 SWG B.P sheet with machine screw duly painted inner and outer surface with gray enamel paint with suitable anchoring arrangement with all wall, column and other places (only back surface of the box will be considered for measurement) and all complete as per design, specification and direction of the E-I-C..

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Metal Board made of 18 SWG BP sheet with corner of 14 SWG BP sheet including painting

1.0000

each

90.00

90.00

Subtotal-A: Other costs

( +5.00 % on Subtotal-A )

4.50

Subtotal-A1: Subtotal-B: Subtotal-C:

94.50 96.39

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

106.03

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7.07 4.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

90.00

117.81

Page: 2410 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.06.3

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 5 Amps 2-pin socket with control switch etc. complete as per drawing & directions of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

455.00

455.00

each 5 amps 2 pin socket with control switch

1.0000

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 503.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

5.04

Subtotal-A1:

508.89

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

519.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

570.97

VAT

6% of Total

IT

4% of Total

38.06 25.38 Total:

8.06.4

634.41

Supplying, assembling, fitting, fixing & installation (with effictive connection) of 250 volts single phase 3-pin combined switches and socket outlet (Gang type) foreign made MK/Legrand/Hager (Stylea)/ABB/MEM or equivalent brand, mounted on best quality locally made required size 18 SWG galvanized plain sheet board (75mm depth) etc. all complete as per drawings and directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2411 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.06.4.1

2 13 amps, Flat pin type

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

430.00

430.00

each 13 amps ,Flat pin Type

1.0000

each

430.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

438.60

10% Profit ( Add 10% on Subtotal-B) :

482.46

VAT

6% of Total

32.16

IT

4% of Total

21.44 Total:

8.06.4.2

15 amps, Round pin type

each 15 amps, Round pin type

1.0000

each

520.00

520.00 520.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

530.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

583.44

VAT

6% of Total

IT

4% of Total

38.90 25.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

536.07

648.27

Page: 2412 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.06.4.3

2 16 amps, Multi Switched Socket

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 16 amps, Multi Switched Socket

1.0000

each

615.00

615.00

Asst Electrician

0.0200

day

680.00

13.60 628.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

641.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

705.29

VAT

6% of Total

47.02

IT

4% of Total

31.35 Total:

8.06.5

Gang switch & socket: Supplying, assembling, fitting, fixing & installation (with effictive connection) on prepared board 250 volt 5 amp concealed type switch/socket with switch (foreign made MK/Legrand/ Hager (Stylea)/ABB /MEM or equivalent brand) mounted on 18 SWG galvanized sheet board 75mm depth with other accessories as per drawing, specification & direction of the Engineer-in-charge..

Note : Rates of all items should be inclusive of all supply and carriage.

783.65

each

Page: 2413 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.5.01

2 01-gang switch

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 01-gang switch

1.0000

each

190.00

190.00

18 SWG Steel Sheet Metal

0.2500

kg

217.00

54.25

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 258.10

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

2.58

Subtotal-A1:

260.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

265.89

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

292.48

VAT

6% of Total

19.50

IT

4% of Total

13.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

324.98

Page: 2414 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.5.02

2 02- gang switch

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 02-gang switch

1.0000

each

320.00

320.00

18 SWG Steel Sheet Metal

0.2500

kg

217.00

54.25

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 388.10

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

3.88

Subtotal-A1:

391.98

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

399.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

439.80

VAT

6% of Total

29.32

IT

4% of Total

19.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

488.67

Page: 2415 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.5.03

2 03-gang switch

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 03-gang switch

1.0000

each

420.00

420.00

18 SWG Steel Sheet Metal

0.0250

kg

217.00

5.43

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 439.28

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

4.39

Subtotal-A1:

443.67

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

452.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

497.80

VAT

6% of Total

33.19

IT

4% of Total

22.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

553.11

Page: 2416 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.5.04

2 04-gang switch

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 04-gang switch

1.0000

each

525.00

525.00

18 SWG Steel Sheet Metal

0.0250

kg

217.00

5.43

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 544.28

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

5.44

Subtotal-A1:

549.72

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

560.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

616.78

VAT

6% of Total

41.12

IT

4% of Total

27.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

685.31

Page: 2417 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.06.5.05

Detailed Analysis Brief Description of Item 2 01-gang switch & one 5 amps 2 pin socket

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 2-pin 5A socket

1.0000

each

650.00

650.00

18 SWG Steel Sheet Metal

0.2500

kg

217.00

54.25

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 718.10

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

7.18

Subtotal-A1:

725.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

739.79

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

813.77

VAT

6% of Total

54.25

IT

4% of Total

36.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

904.18

Page: 2418 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.06.5.06

2 Fan regulator( gang type)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each gang type fan regulator

1.0000

each.

450.00

450.00

18 SWG Steel Sheet Metal

0.2500

kg

217.00

54.25

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 518.10

Subtotal-A: all other remaining

( +1.00 % on Subtotal-A )

5.18

Subtotal-A1:

523.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

533.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

587.12

VAT

6% of Total

39.14

IT

4% of Total

26.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

652.36

Page: 2419 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.06.5.07

2 Call bell push( gang type)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each call bell

1.0000

each

700.00

700.00

18 SWG Steel Sheet Metal

0.2500

kg

217.00

54.25

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 768.10

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

7.68

Subtotal-A1:

775.78

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

791.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

870.43

VAT

6% of Total

58.03

IT

4% of Total

38.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

967.14

Page: 2420 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.06.5.08

2 Telephone socket( gang type)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each telephone socket (gang type)

1.0000

each

780.00

780.00

18 SWG Steel Sheet Metal

0.2500

kg

217.00

54.25

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 848.10

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

8.48

Subtotal-A1:

856.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

873.71

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

961.08

VAT

6% of Total

64.07

IT

4% of Total

42.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1067.87

Page: 2421 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.5.09

2 TV socket ( gang type)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each TV socket (gang type)

1.0000

each

600.00

600.00

18 SWG Steel Sheet Metal

0.2500

kg

217.00

54.25

Asst Electrician

0.0100

day

680.00

6.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0150

day

470.00

7.05 668.10

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

6.68

Subtotal-A1:

674.78

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

688.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

757.10

VAT

6% of Total

50.47

IT

4% of Total

33.65 Total:

8.06.5.10

5A piano Switch

each 5A Piano switch

1.0000

no

Asst Electrician

0.0200

day

680.00

13.60 13.60

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

0.14

Subtotal-A1:

13.74

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14.01

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15.41

VAT

6% of Total

IT

4% of Total

1.03 0.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

841.23

17.12

Page: 2422 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.06.5.11

2 2-pin 5A Piano Socket

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 2-Pin 5 amp Piono Socket

1.0000

each

30.00

30.00

Asst Electrician

0.0200

day

680.00

13.60 43.60

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

0.44

Subtotal-A1:

44.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

44.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

49.41

VAT

6% of Total

3.29

IT

4% of Total

2.20 Total:

8.06.5.12

20A, Double Pole Switch with neon indicator

each 20A DP SWITCH

1.0000

each

500.00

500.00

Asst Electrician

0.2000

day

680.00

136.00 636.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

648.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

713.59

VAT

6% of Total

47.57

IT

4% of Total

31.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

54.90

792.88

Page: 2423 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.06.5.13

2 Fan Regulator with switch

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Fan Regulator with switch

1.0000

each

612.00

612.00

Asst Electrician

0.0200

day

680.00

13.60 625.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

638.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

701.92

VAT

6% of Total

46.79

IT

4% of Total

31.20 Total:

8.06.5.14

Data Socket, RJ-45

each Data Socket, RJ-45

1.0000

each

875.00

875.00

Asst Electrician

0.0200

day

680.00

13.60 888.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

906.37

10% Profit ( Add 10% on Subtotal-B) :

997.01

VAT

6% of Total

IT

4% of Total

66.47 44.31 Total:

8.06.6

779.91

1107.79

Supplying, fitting and fixing teak wood battens minimum 12mm thick wooden plug of approved quality etc. for lights, fans and out lets from main switch board to distribution fuse board and from distribution fuse board to individual points in/c varnishing etc. complete as per directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2424 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.6.1

2 63mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 12mm thick 63mm wide teak wood batten

1.0000

m

45.00

45.00

Wood Pegs

3.0000

each

30.00

90.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 183.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

1.84

Subtotal-A1:

185.69

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

189.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

208.34

VAT

6% of Total

13.89

IT

4% of Total

9.26 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

231.49

Page: 2425 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.6.2

2 50mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 12mm thick 50mm wide teak wood batten

1.0000

m

42.00

42.00

Wood Pegs

3.0000

each

30.00

90.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 180.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

1.81

Subtotal-A1:

182.66

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

186.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

204.94

VAT

6% of Total

13.66

IT

4% of Total

9.11 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

227.71

Page: 2426 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.6.3

2 40mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 12mm thick 40mm wide teak wood batten

1.0000

m

37.00

37.00

Wood Pegs

3.0000

each

30.00

90.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 175.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

1.76

Subtotal-A1:

177.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

181.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

199.28

VAT

6% of Total

13.29

IT

4% of Total

8.86 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

221.42

Page: 2427 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.6.4

2 25mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 12mm thick 25mm wide teak wood batten

1.0000

m

24.00

24.00

Wood Pegs

3.0000

each

30.00

90.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 162.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

1.63

Subtotal-A1:

164.48

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

167.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

184.54

VAT

6% of Total

12.30

IT

4% of Total

8.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

205.05

Page: 2428 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.6.5

2 20mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 12mm thick 20mm wide teak wood batten

1.0000

m

20.00

20.00

Wood Pegs

3.0000

each

30.00

90.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 158.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

1.59

Subtotal-A1:

160.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

163.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

180.01

VAT

6% of Total

12.00

IT

4% of Total

8.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

200.01

Page: 2429 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.06.6.6

2 12mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 12mm thick 20mm wide teak wood batten

1.0000

m

20.00

20.00

Wood Pegs

3.0000

each

30.00

90.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 158.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

1.59

Subtotal-A1:

160.44

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

163.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

180.01

VAT

6% of Total

12.00

IT

4% of Total

8.00 Total:

8.07.1

Earthing the electrical installation with 38mm dia GI pipe (earth electrode) having 6mm dia holes across the dia at 1.0m interval securedly bonded with 2 SWG HDBC earth lead with washer, nuts, bolts etc. sunk upto under-mentioned depth and protection of earth lead by 12mm dia GI pipe upto plinth level run at a depth of 6.6m below G.L upto main board to be earthed in/c necessary connecting copper sockets, bolts, nuts, in/c additional vertical run of 12mm dia GI pipe upto G.L. from 6.6m depth with blind socket for water pouring facility etc. all complete for maintaining earth resistance within 1 ohm.

Note : Rates of all items should be inclusive of all supply and carriage.

200.01

each set

Page: 2430 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.07.1.01

Detailed Analysis Brief Description of Item 2 Depth of main electrode at 12.0m and length of the electrode 11.0 m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

12.0000

m

165.00

1980.00

1.0000

each

35.00

35.00

12.0000

each

28.00

336.00

5

Amount 8

set 40mm dia GI pipe with holes around the pipe GI Reducing socket (38x12mm) 12mm GI plug Copper Flat Bar Clamp

7.0000

each

180.00

1260.00

12mm GI Tee

3.0000

each

25.00

75.00

12mm GI bend

1.0000

each

15.00

15.00

SWG HDBC Wire (#2)

7.0000

kg

900.00

6300.00

Plumber/ Electric Mistry/ Painter

3.0000

day

680.00

2040.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

6.0000

day

470.00

2820.00 14861.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15158.22

10% Profit ( Add 10% on Subtotal-B) :

16674.04

VAT

6% of Total

IT

4% of Total

1111.60 741.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18526.71

Page: 2431 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.07.1.02

Detailed Analysis Brief Description of Item 2 Depth of main electrode at 35-40m

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

40.0000

m

165.00

6600.00

1.0000

each

35.00

35.00

15.0000

each

28.00

420.00

5

Amount 8

set 40mm dia GI pipe with holes around the pipe GI Reducing socket (38x12mm) 12mm GI plug Copper Flat Bar Clamp

8.0000

each

180.00

1440.00

12mm GI Tee

1.0000

each

25.00

25.00

12mm GI bend

1.0000

each

15.00

15.00

SWG HDBC Wire (#2)

7.5000

kg

900.00

6750.00

Plumber/ Electric Mistry/ Painter

3.0000

day

680.00

2040.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

7.0000

day

470.00

3290.00 20615.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21027.30

10% Profit ( Add 10% on Subtotal-B) :

23130.03

VAT

6% of Total

IT

4% of Total

1542.00 1028.00 Total:

8.07.2

25700.03

Supply and installation of electrolytic annealed copper/PVC single core green earth continuity conductor along with cable in pre-installed conduit/cable tray including connection to various metallic parts etc. all complete as per drawings, specifications and direction of the Engineer of the following :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2432 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.07.2.1

2 1.5mm2 Green

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 1.5mm2 green earth continuity conductor

1.0000

m

21.00

21.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.21

Subtotal-A1: Subtotal-B: Subtotal-C:

21.21 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21.63

10% Profit ( Add 10% on Subtotal-B) :

23.80

VAT

6% of Total

IT

4% of Total

1.59 1.06 Total:

8.07.2.2

2.5mm2 Green

26.44

m 2.5mm2 green earth continuity conductor

1.0000

m

33.00

All other remaining costs

( +1.00 % on Subtotal-A )

0.33

Subtotal-A1: Subtotal-B: Subtotal-C:

33.00 33.00

Subtotal-A:

33.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

34.00

10% Profit ( Add 10% on Subtotal-B) :

37.40

VAT

6% of Total

IT

4% of Total

2.49 1.66 Total:

8.07.2.3

21.00

41.55

HDBC wire

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2433 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.07.2.3.1

2 18 SWG

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 18 SWG HDBC Wire

1.0000

m

27.00

27.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.27

Subtotal-A1: Subtotal-B: Subtotal-C:

27.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

27.82

10% Profit ( Add 10% on Subtotal-B) :

30.60

VAT

6% of Total

IT

4% of Total

2.04 1.36 Total:

8.07.2.3.2

12 SWG

34.00

m 12 SWG HDBC wire

1.0000

m

44.00

All other remaining costs

( +1.00 % on Subtotal-A )

0.44

Subtotal-A1: Subtotal-B: Subtotal-C:

44.00 44.00

Subtotal-A:

44.44 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

45.33

10% Profit ( Add 10% on Subtotal-B) :

49.86

VAT

6% of Total

IT

4% of Total

3.32 2.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

27.00

55.40

Page: 2434 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.07.2.3.3

2 8 SWG

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

107.00

107.00

m 8 SWG HDBC wire

1.0000

107.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.07

Subtotal-A1: Subtotal-B: Subtotal-C:

108.07 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

110.23

10% Profit ( Add 10% on Subtotal-B) :

121.25

VAT

6% of Total

IT

4% of Total

8.08 5.39 Total:

8.07.2.3.4

6 SWG

m 6 SWG HDBC wire

1.0000

m

155.00

All other remaining costs

( +1.00 % on Subtotal-A )

1.55

Subtotal-A1: Subtotal-B: Subtotal-C:

155.00 155.00

Subtotal-A:

156.55 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

159.68

10% Profit ( Add 10% on Subtotal-B) :

175.65

VAT

6% of Total

IT

4% of Total

11.71 7.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

134.73

195.17

Page: 2435 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.07.2.3.5

2 4 SWG

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

213.00

213.00

m 4 SWG HDBC wire

1.0000

213.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.13

Subtotal-A1: Subtotal-B: Subtotal-C:

215.13 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

219.43

10% Profit ( Add 10% on Subtotal-B) :

241.38

VAT

6% of Total

IT

4% of Total

16.09 10.73 Total:

8.07.2.3.6

2 SWG

m 2 SWG HDBC wire

1.0000

m

347.00

All other remaining costs

( +1.00 % on Subtotal-A )

3.47

Subtotal-A1: Subtotal-B: Subtotal-C:

347.00 347.00

Subtotal-A:

350.47 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

357.48

10% Profit ( Add 10% on Subtotal-B) :

393.23

VAT

6% of Total

IT

4% of Total

26.22 17.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

268.20

436.92

Page: 2436 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.07.3

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing of single lightning arrester on the top of the building 1.22m long 12mm dia GI pipe and clamp with bolts and 3mm mounted air spike. Top of the lightning arrester should be soldered and other fittings required etc. all complete in all respects as per directions of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

12mm dia GI Pipe (2mm thick)

1.2200

m

131.00

159.82

Skilled Labour

0.5000

day

450.00

225.00 384.82

Subtotal-A: All other remaining costs like 12mm dia GI pipe, cluamps, bolts, air spike, soldering, other necessary fittings, etc.

( +150.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

962.05 981.29

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1079.42

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

71.96 47.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

577.23

1199.36

Page: 2437 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.07.4

Detailed Analysis Brief Description of Item 2 Earthing for LPS : Supply & installation (with effictive connection) of 10'-0" Solid Copper Rod (min. 12.7mm dia) under 2'-0" from FGL at 2'-0" from building premises , Connecting the rod with Lightning Arrestor by 7.5mm dia copper wire (#2SWG), Copper bracket etc. (properly soldering with the rod) through 25 mm dia pvc pipe complete with necessary accessories as per direction of Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Materials cost for LPS earthing

1.0000

each

7000.00

7000.00

Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 8830.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9006.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9907.26

VAT

6% of Total

660.48

IT

4% of Total

440.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11008.07

Page: 2438 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.07.5

Detailed Analysis Brief Description of Item 2 Construction of Earthing inspection pit inside measurement 600 mm x 600 mm with 250 mm thick brick in cement morter (1:4) with 100mm thick RCC top slab (1:2:4) with 1% re-inforcement 450 mm dia water sealed CI man-hole cover with locking arrangement including necessary earth works, site filling and one brick flat soling 75 mm thick (1:3:6) base concrete for making inlet channel & 12mm thick (1:2) cement plaster with neat finishing etc.all complete up to a depth of .75 meter.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Materials cost for PIT

1.0000

each

4200.00

4200.00

Mason

2.0000

day

550.00

1100.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 5770.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5885.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6473.94

VAT

6% of Total

431.60

IT

4% of Total

287.73 Total:

8.08.1

7193.27

Laying medium pressure under ground cable of different sizes etc. all complete by cutting trench on the following measurements on a layer of 150mm thick sand cushion. The cable should be protected by a single layer 1st class brick soling etc. all complete as per directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2439 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.08.1.1

2 450mm wide and 900mm depth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.4050

cum

75.80

30.70

Sand (FM 0.50) filling on the road bed in the improved subgrade……. (3.02.1.1)

0.0670

cum

547.49

36.68

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

0.4500

sqm

308.04

138.62 206.00

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

4.12

Subtotal-A1:

210.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

214.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

235.75

VAT

6% of Total

15.72

IT

4% of Total

10.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

261.95

Page: 2440 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.08.1.2

2 450mm wide and 600mm depth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.2700

cum

75.80

20.47

Sand (FM 0.50) filling on the road bed in the improved subgrade……. (3.02.1.1)

0.0670

cum

547.49

36.68

Single layer brick flat soling with 1st class or picked jhama bricks….(3.08.4.1)

0.4500

sqm

308.04

138.62 195.77

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

3.92

Subtotal-A1:

199.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

203.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

224.04

VAT

6% of Total

14.94

IT

4% of Total

9.96 Total:

8.08.2

248.94

Supplying, fitting and fixing PVC pipe for service line and sleeves for electrical wiring when it passes through wall etc. all complete as per directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2441 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.08.2.1

2 40mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2.5 to 3mm thick 40mm dia PVC pipe ('C' Class)

1.0000

m

87.00

87.00

Subtotal-A: Labour & other costs

( +60.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

25mm dia

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

141.98

10% Profit ( Add 10% on Subtotal-B) :

156.18

VAT

6% of Total

IT

4% of Total

10.41 6.94 173.54

m 2.5 to 3mm thick 25mm dia PVC pipe ('C' Class)

1.0000

m

58.00

Labour & other costs

( +60.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

58.00 58.00

Subtotal-A:

34.80 92.80 94.66

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

104.12

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6.94 4.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

52.20 139.20

Total: 8.08.2.2

87.00

115.69

Page: 2442 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.08.2.3

2 20mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2.5 to 3mm thick 20mm dia PVC pipe ('C' Class)

1.0000

m

33.23

33.23

Subtotal-A: Labour & other costs

( +60.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

12mm dia

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

54.23

10% Profit ( Add 10% on Subtotal-B) :

59.65

VAT

6% of Total

IT

4% of Total

3.98 2.65 66.28

m 2.5 to 3mm thick 12mm dia PVC pipe ('C' Class)

1.0000

m

27.33

Labour & other costs

( +60.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

27.33 27.33

Subtotal-A:

16.40 43.73

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

44.60

10% Profit ( Add 10% on Subtotal-B) :

49.06

VAT

6% of Total

IT

4% of Total

3.27 2.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

19.94 53.17

Total: 8.08.2.4

33.23

54.51

Page: 2443 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.08.3

2 Supplying, fitting and fixing 250 volts electric buzzer complete set including push bottom switch, required length of PVC twin flexible cord, 25w bulb, brass batten holder etc. all complete as per directions (Foreign made or prior approved quality) of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

450.00

450.00

set

250V electric buzzer

1.0000

each

25 watt Bulb with brass batten holder

1.0000

each

83.00

83.00

Teak Wood Board (350x450x25mm) including varnishing

1.0000

each

360.00

360.00

PVC flexible cord of size 2x14/0.193mm

4.0000

m

27.00

108.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1400

day

470.00

65.80 1066.80

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

21.34

Subtotal-A1:

1088.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1109.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1220.89

VAT

6% of Total

81.39

IT

4% of Total

54.26 Total:

8.08.4

Supplying all materials as per requirement of power development board for service connection from PDB pole to the desired structure and any other charges (e.g. security deposit, connection fee, meter installation, testing fee) required by the power development board for supply of power to the desired structure through underground cable/overhead line etc. complete as per direction of the E-I-C.

8.08.4.1

For 3-phase

LS

8.08.4.2

For 1-phase

LS

Note : Rates of all items should be inclusive of all supply and carriage.

1356.54

Page: 2444 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

8.09.1

Supplying, fitting and fixing 250V capacitor type ceiling fan complete with concealed condensers, canopies and required length of rods, ceiling roses, wooden round blocks, regulator, switches and required length of flexible wire etc. all complete as per drawings and directions of the E-IC.

8.09.1.1

1.422m sweep (best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 1.422 m sweep ceiling fan (best quality)

1.0000

each

3000.00

Plumber/ Electric Mistry/ Painter

0.1200

day

680.00

81.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1200

day

470.00

56.40 3138.00

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

31.38

Subtotal-A1: Subtotal-B: Subtotal-C:

3169.38 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3232.77

10% Profit ( Add 10% on Subtotal-B) :

3556.04

VAT

6% of Total

IT

4% of Total

237.07 158.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3000.00

3951.16

Page: 2445 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.09.1.2

2 1.22m sweep (best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 1.22 m sweep ceiling fan (best quality)

1.0000

each

2500.00

2500.00

Plumber/ Electric Mistry/ Painter

0.1200

day

680.00

81.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1200

day

470.00

56.40 2638.00

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

26.38

Subtotal-A1:

2664.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2717.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2989.43

VAT

6% of Total

IT

4% of Total

199.30 132.86 Total:

8.09.1.3

.914m sweep (best quality)

each 0.914 m sweep ceiling fan (best quality)

1.0000

each

2000.00

2000.00

Plumber/ Electric Mistry/ Painter

0.1200

day

680.00

81.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1200

day

470.00

56.40 2138.00

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

21.38

Subtotal-A1: Subtotal-B: Subtotal-C:

2159.38 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2202.57

10% Profit ( Add 10% on Subtotal-B) :

2422.82

VAT

6% of Total

IT

4% of Total

161.52 107.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3321.59

2692.03

Page: 2446 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.09.1.4

Detailed Analysis Brief Description of Item 2 wall bracket fan 16” sweep plastic body & blade

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each wall bracket fan 16" sweep plastic body & blade

1.0000

each

2420.00

2420.00

Asst Electrician

0.0600

day

680.00

40.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60 2498.40

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

24.98

Subtotal-A1:

2523.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2573.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2831.24

VAT

6% of Total

IT

4% of Total

188.75 125.83 Total:

8.09.1.5

wall bracket fan 16” sweep steel body & blade

each wall bracket fan 16" sweep steel body & blade

1.0000

each

2970.00

2970.00

Asst Electrician

0.0600

day

680.00

40.80

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0800

day

470.00

37.60 3048.40

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

30.48

Subtotal-A1: Subtotal-B: Subtotal-C:

3078.88 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3140.46

10% Profit ( Add 10% on Subtotal-B) :

3454.51

VAT

6% of Total

IT

4% of Total

230.30 153.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3145.82

3838.34

Page: 2447 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.09.1.6

Detailed Analysis Brief Description of Item 2 Fan clamp box type : Supplying, fitting & fixing of box type fan clamp made of 25 mm x 6.35 mm MS flat bar with 16 mm diameter MS hook including necessary bolts, nuts, etc

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

25mmx6.25mm flat bar

0.6400

kg

50.00

32.00

5/8 inch dia ms rod hook

0.8700

kg

60.15

52.33

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 188.83

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

1.89

Subtotal-A1:

190.72

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

194.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

213.99

VAT

6% of Total

14.27

IT

4% of Total

9.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

237.76

Page: 2448 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.09.1.7

Detailed Analysis Brief Description of Item 2 Fan clamp `U’ type : Supplying, fitting & fixing of `U’ type fan clamp made of 16 mm diameter MS rod or according to the specification

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 5/8 inch dia ms rod hook

1.5600

kg

60.15

Asst Electrician

0.0500

day

680.00

34.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1500

day

470.00

70.50 198.33

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

1.98

Subtotal-A1:

200.32

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

204.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

224.76

VAT

6% of Total

IT

4% of Total

14.98 9.99 Total:

8.09.2

93.83

249.73

Supplying, fitting and fixing axial flow AC capacitor type wall mounted exhaust fan complete with blade, steel frame, standard wall louver shutter, PVC insulated connecting wire etc. complete as required in/c cutting wall and mending good the damages etc. all complete as per directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2449 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.09.2.1

2 600mm sweep (best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 600mm sweep wall mounted Exhaust fan (best quality)

1.0000

each

4500.00

4500.00

Louver Shutter

1.0000

each

165.00

165.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

0.5000

day

450.00

225.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 5282.50

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

52.83

Subtotal-A1: Subtotal-B: Subtotal-C:

5335.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5442.03

10% Profit ( Add 10% on Subtotal-B) :

5986.23

VAT

6% of Total

IT

4% of Total

399.08 266.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6651.37

Page: 2450 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.09.2.2

2 450mm sweep (best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 450mm sweep wall mounted Exhaust fan (best quality)

1.0000

each

2400.00

2400.00

Louver Shutter

1.0000

each

165.00

165.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

0.5000

day

450.00

225.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 3182.50

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

31.83

Subtotal-A1: Subtotal-B: Subtotal-C:

3214.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3278.61

10% Profit ( Add 10% on Subtotal-B) :

3606.47

VAT

6% of Total

IT

4% of Total

240.43 160.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4007.19

Page: 2451 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.09.2.3

2 400mm sweep (best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 400mm sweep wall mounted Exhaust fan (best quality)

1.0000

each

2250.00

2250.00

Louver Shutter

1.0000

each

165.00

165.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

0.5000

day

450.00

225.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 3032.50

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

30.33

Subtotal-A1: Subtotal-B: Subtotal-C:

3062.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3124.08

10% Profit ( Add 10% on Subtotal-B) :

3436.49

VAT

6% of Total

IT

4% of Total

229.10 152.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3818.32

Page: 2452 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.09.2.4

2 300mm sweep (best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 300mm sweep wall mounted Exhaust fan (best quality)

1.0000

each

2000.00

2000.00

Louver Shutter

1.0000

each

165.00

165.00

Mason

0.5000

day

550.00

275.00

Skilled Labour

0.5000

day

450.00

225.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2500

day

470.00

117.50 2782.50

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

27.83

Subtotal-A1: Subtotal-B: Subtotal-C:

2810.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2866.53

10% Profit ( Add 10% on Subtotal-B) :

3153.18

VAT

6% of Total

IT

4% of Total

210.21 140.14 Total:

8.09.3

3503.54

Repairing of ceiling fan and supplying necessary accessories as per directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2453 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.09.3.1

2 Repairing of ceiling fan

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 727.00

Subtotal-A: All other remaining costs like supplying necessary accessories, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

799.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

815.69

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

897.26

VAT

6% of Total

IT

4% of Total

59.82 39.88 Total:

8.09.3.2

Bearing supply

996.96

pair Fan bearing

1.0000

pair

100.00

100.00 100.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.00

Subtotal-A1:

101.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

103.02

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

113.32

VAT

6% of Total

7.55

IT

4% of Total

5.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

72.70

125.91

Page: 2454 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.09.3.3

2 Capacitor supply

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

120.00

120.00

each Fan capacitor

1.0000

each

120.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.20

Subtotal-A1: Subtotal-B: Subtotal-C:

121.20 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

123.62

10% Profit ( Add 10% on Subtotal-B) :

135.99

VAT

6% of Total

IT

4% of Total

9.07 6.04 Total:

8.09.3.4

Old blade bending (three blade) and spray painting including body.

set Plumber/ Electric Mistry/ Painter

0.3000

day

680.00

204.00

Painting to door and window frames and shutters in two coats with synthetic enamel paint…(3.12.5.1)

0.4300

sqm

99.43

42.75 246.75

Subtotal-A: All other remaining costs

( +5.00 % on Subtotal-A )

12.34

Subtotal-A1:

259.09

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

264.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

290.70

VAT

6% of Total

IT

4% of Total

19.38 12.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

151.10

323.00

Page: 2455 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.09.3.5

Detailed Analysis Brief Description of Item 2 Supply of approved quality regulator

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

580.00

580.00

each Fan Dimmer

1.0000

each

580.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

5.80

Subtotal-A1: Subtotal-B: Subtotal-C:

585.80 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

597.52

10% Profit ( Add 10% on Subtotal-B) :

657.27

VAT

6% of Total

IT

4% of Total

43.82 29.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

730.30

Page: 2456 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.01

Detailed Analysis Brief Description of Item 2 Saucer Light : Supplying, assembling, fitting, fixing & installation (with effictive connection) the special type single lamp lock type saucer light fitting of following manufacturers consisting of golden/anodized brass carrier of minimum 250mm dia designed glass of min. height 100mm suitable for carrier, brass holder, earth terminal, necessary wiring with 2x0.4sq.mm stranded PVC insulated flexible FR cable, compatible for 23/26 W CFl etc. complete (except lamp) of the following model & as per sample approved by the Engineer-in-charge Asha cat No. ACSP-2816 or Anyasha cat No.ACCMS-71 or Crescent cat No. CPC-29-CP-29 or Gloria cat No. GCF-689 Ring or Shwash cat No. SCCF-12/28 or equivalent approved by the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

Saucer light

1.0000

set

850.00

850.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 898.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

8.99

Subtotal-A1: Subtotal-B: Subtotal-C:

907.84 926.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1018.59

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

67.91 45.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1131.77

Page: 2457 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.02

Detailed Analysis Brief Description of Item 2 Bracket Light: Supplying, assembling, fitting, fixing & installation (with effictive connection) the fancy Single bracket light fitting of following manufacturers consisting of designed glass shade of breadth 150mm minimum total height of fitting 200mm, oxidized or chromium plated/golden brass bracket with carrier, brass holder, earth terminal, necessary wiring with 2x0.4sq.mm stranded PVC insulated flexible FR cable etc. complete (except lamp) of following model & as per sample approved by the Engineer Asha cat No.ACSBS-3778 G 529 GB or Crescent cat No. CB-431-592 FR or Gloria cat No. GWB-1501-2101 FR or Shwash cat No. SCS-447

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

Metal plated fancy bracket holder and fancy shade

1.0000

set

800.00

800.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 848.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

8.49

Subtotal-A1: Subtotal-B: Subtotal-C:

857.34 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

874.49

10% Profit ( Add 10% on Subtotal-B) :

961.93

VAT

6% of Total

64.13

IT

4% of Total

42.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1068.82

Page: 2458 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.03

Detailed Analysis Brief Description of Item 2 Mirror light: Supplying, assembling, fitting, fixing & installation (with effictive connection) the Bath-room light fitting of following manufacturers consisting of oxidized/chromium plated brass frame with carrier, cylindrical type glass shade of minimum dia 78mm (minimum total length of fitting 325mm), brass holder, earth terminal, necessary wiring with 2x0.4 sq.mm stranded PVC insulated fiexible Frcable etc complete of following model & as per sample accepted by trhe engineer-in charge. Asha cat no. ACSBB-2876 or Crescent cat. No.CB-807/6-t6-DGN or Gloria cat no. GBB-399-1802-CR/BR or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

Mirror light

1.0000

set

500.00

500.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 548.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

5.49

Subtotal-A1:

554.34

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

565.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

621.97

VAT

6% of Total

IT

4% of Total

41.46 27.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

691.08

Page: 2459 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.04

Detailed Analysis Brief Description of Item 2 Pendent Light : Supplying, assembling, fitting, fixing & installation (with effictive connection) of stiff pendent light fitting of the following manufacturers (as per picture No. PWD Sch.-1.9) consisting of anodized reflective body of 550mm dia, 150mm long pipe of 3/4" dia, total length of fitting 440mm, with ceiling base, thread type ceramic holder, earth terminal, necessary wiring with 2x0.4 sq.mm stranded PVC insulated flexible cable etc. complete (except lamp) of the following model and as per sample approved by the Engineer-in-charge. Asha cat no. ASS-C-228 or Crescent cat No.CML-527 or Gloria cat No. GCF-1198/85 or Swash cat No. SCH-218(1) or equivalent approved by the enginer in charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Pendent light fitting (Best Quality)

1.0000

set

2100.00

2100.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 2148.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

21.49

Subtotal-A1:

2170.34

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2213.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2435.12

VAT

6% of Total

IT

4% of Total

162.34 108.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2705.69

Page: 2460 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.05

Detailed Analysis Brief Description of Item 2 Foot Light: Supplying, assembling, fitting, fixing & installation (with effictive connection) the outdoor type foot light fitting of following manufacturers (as per figure no. 11.1, PWD schedule) suitable for mounting recessed wall/step consisting of cast aluminum robust housing of min breadth 250mm and height 100 mm water proof louver type diffuser polished alluminum reflector with fixing materials rubber, gasket, lamp cap (including LED type lamp), necessary wiring with 2x0.4sq.mm stranded PVC insulated flexible FR cable, etc. complete of the following model & as per sample approved by the Engineer in charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

Asha cat No. ACSF-2770 or Crescent cat No.-CML184 or Gloria cat No. GFL-01 Shwash cat no. Shwash Foot light Foot light

1.0000

set

900.00

900.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 948.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

9.49

Subtotal-A1: Subtotal-B: Subtotal-C:

958.34 977.51

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1075.26

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

71.68 47.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1194.73

Page: 2461 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.06

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 1.22m long 40 watt fluorescent tube light with necessary superior quality ballast, starter, condenser, holders, 18 SWG sheet steel stove enamel base, etc. all complete as per drawing and directions of the E-I-C. Each lamp is to be operated by one way switch. (Eastern or prior approved quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

1.22mm long 40 W fluorescent tube set with choke coil starter, condenser holder, 18 SWG sheet steel stove enamel base etc. (Eastern or prior approved quality)

1.0000

set

670.00

670.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0750

day

470.00

35.25 718.85

Subtotal-A: Other costs

( +1.00 % on Subtotal-A )

7.19

Subtotal-A1:

726.04

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

740.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

814.62

VAT

6% of Total

IT

4% of Total

54.31 36.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

905.13

Page: 2462 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.07

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 450mm dia flood light fitting consisting of 20 SWG aluminium sheet body, anodized aluminium reflector, screw type holder, heat proof glass cover, glass ring MS flat bar stand and 500 watt lamp etc. all complete as per direction (Model No. SCFT or prior approved quality) of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

450mm flood light (excluding lamp)

1.0000

set

7875.00

7875.00

MS Angle, Flat bar, Z bar

5.0000

kg

59.00

295.00

500 watt normal lamp

1.0000

each

150.00

150.00

Tumbler switch

1.0000

each

25.00

25.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 8460.00

Subtotal-A: Fabrication of stand & other costs

( +12.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

9475.20 9664.70

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10631.17

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

708.74

IT

4% of Total

472.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1015.20

11812.42

Page: 2463 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.08

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Supplying, fitting and fixing metallic cone shade with brass batten holder as per directions of the E-I-C.

each

Quantity 5

Unit

Rate

Amount

6

7

8

262.00

262.00

Metallic cone shade

1.0000

each

Brass batten holder

1.0000

each

27.00

27.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00 323.00

Subtotal-A: Other costs

( +5.00 % on Subtotal-A )

16.15

Subtotal-A1: Subtotal-B: Subtotal-C:

339.15 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

345.93

10% Profit ( Add 10% on Subtotal-B) :

380.53

VAT

6% of Total

IT

4% of Total

25.37 16.91 Total:

8.10.09

Supplying, fitting and fixing metallic cone shade with brass pendent holder ceiling rose, required length of flexible wire as per directions of the E-I-C.

each

Metallic cone shade

1.0000

each

262.00

262.00

Brass pendent holder

1.0000

Plumber/ Electric Mistry/ Painter

0.0500

each

33.00

33.00

day

680.00

34.00 329.00

Subtotal-A: Other costs

( +5.00 % on Subtotal-A )

16.45

Subtotal-A1: Subtotal-B: Subtotal-C:

345.45 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

352.36

10% Profit ( Add 10% on Subtotal-B) :

387.59

VAT

6% of Total

IT

4% of Total

25.84 17.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

422.81

430.66

Page: 2464 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

8.10.10

Repairing of fluorescent tube light and supplying necessary accessories as per directions of the E-I-C. (Eastern or prior approved quality)

8.10.10.1

1.20m 40 watt. fluorescent tube

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 1.20m 40W fluorescent tube (Eastern or prior approved quality)

1.0000

each

120.00

120.00

Plumber/ Electric Mistry/ Painter

0.0100

day

680.00

6.80 126.80

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.27

Subtotal-A1: Subtotal-B: Subtotal-C:

128.07 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

130.63

10% Profit ( Add 10% on Subtotal-B) :

143.69

VAT

6% of Total

IT

4% of Total

9.58 6.39 Total:

8.10.10.2

Choke

each Choke (Tube Light)

1.0000

each

280.00

280.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00 314.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

3.14

Subtotal-A1:

317.14

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

323.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

355.83

VAT

6% of Total

IT

4% of Total

23.72 15.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

159.66

395.37

Page: 2465 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.10.10.3

2 Holder

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

pair Tube light holder

1.0000

each

30.00

30.00

Wood Pegs

2.0000

each

30.00

60.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00 124.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.24

Subtotal-A1:

125.24

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

127.74

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

140.52

VAT

6% of Total

IT

4% of Total

9.37 6.25 Total:

8.10.10.4

Starter

each Tube light starter

1.0000

each

20.00

20.00

Plumber/ Electric Mistry/ Painter

0.0050

day

680.00

3.40 23.40

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.23

Subtotal-A1:

23.63

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26.52

VAT

6% of Total

IT

4% of Total

1.77 1.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

156.13

29.46

Page: 2466 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.10.10.5

2 Condenser

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Condenser

1.0000

each

260.00

260.00

Plumber/ Electric Mistry/ Painter

0.0500

day

680.00

34.00 294.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.94

Subtotal-A1:

296.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

302.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

333.17

VAT

6% of Total

22.21

IT

4% of Total

14.81 Total:

8.10.11

Supplying, fitting and fixing signal light with brass batten holder in/c coloured bulb, etc. all complete as per direction of the E-I-C.

set Signal light

1.0000

set

280.00

280.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 1430.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

14.30

Subtotal-A1:

1444.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1473.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1620.50

VAT

6% of Total

IT

4% of Total

108.03 72.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

370.19

1800.56

Page: 2467 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.12

Detailed Analysis Brief Description of Item 2 Single Tube Light Set : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1*4'*40 watt Fluorescent tube light fitting of consisting of powder coated 22 SWG sheet steel frame of min. length 1240mm & breadth 104mm,superior qulity electronic ballast with one year guarantee , holder, necessary wiring with 2*0.4 sq mm PVC insulated (stranded) fiexible fr wire, earth terminal etc. complete (except lamp) of following model & as per sample approved by Engineer. Gloria cat no. GTF-899*1*40 watt or equivalent approved by Engineerin-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Single tube light

1.0000

set

1250.00

1250.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 1273.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1298.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1428.31

VAT

6% of Total

95.22

IT

4% of Total

63.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1587.01

Page: 2468 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.13

Detailed Analysis Brief Description of Item 2 "Louver type Double Tube Set : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 2x4'x40 watt Louver type fluorescent tube light fitting (ceiling hanging) of following manufacturers consisting of powder coated 22 SWG sheet steel frame of minimum length of 1340mm & breath 165mm, superior quality electronic ballast holder, earth terminal, necessary wiring with 2x1.5sq.mm insulated and sheathed wire etc. complete (except lamp) of the following model & as per sample approved by the Engineer"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Louver type double tube light

1.0000

set

1375.00

1375.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 1398.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1425.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1568.56

VAT

6% of Total

IT

4% of Total

104.57 69.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1742.84

Page: 2469 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.14

Detailed Analysis Brief Description of Item 2 Flood Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of the following manufaturers having min. total length 460mm, consisting of aluminum sheet body of min. dia 460mm, polished aluminum reflector, screw type holder, earth terminal cast aluminum/iron adjustable stand, heat proof galss cover, necessary wiring with FR cable for use with 500/1000W lamp etc. complete of the following model & as per sample approved by the engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Asha cat No. ACSFL-972 or Crescent cat No. CFLD-11 or Gloria cat No. GFL-730x1x500/1000W or Shwash cat No.-SCFL-21/84 or equivalent Flood light

1.0000

set

6750.00

6750.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 6773.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6908.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7599.31

VAT

6% of Total

IT

4% of Total

506.62 337.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8443.67

Page: 2470 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.15

Detailed Analysis Brief Description of Item 2 EMERGENCY EXIT LIGHT Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 250 volt grade Exit light fitting of die-cast aluminium robust housing with anodized aluminium reflector,heat proof/ toughened glass, silicon rubber gasket, lamp holder, etc. complete with prime coating and best quality powder coated paint suitable to use with Par-38 lamp (with lamp) of following model & as per sample approved by the Engineer-in-charge. Crescent cat. No. CTLS-189 (EXIT) Gloria cat. No. GWT-EXIT Light Shwash cat. No. Exit Light (Both Side) or equivalent approved by the Engineering-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Exit light

1.0000

set

1600.00

1600.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 1623.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1655.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1821.01

VAT

6% of Total

IT

4% of Total

121.40 80.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2023.34

Page: 2471 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.16

Detailed Analysis Brief Description of Item 2 Ceiling Concealed Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of concealed type spot light fitting of following manufacturers consisting of steel sheet base and arm having powder coated paint and inside alluminium reflector of min. 104mm dia 182mm height compatible for 23/26W CFL E-27 holder, earth terminal, necessary wiring with 2x0.4sq.mm stranded PVC insulated flexible FR cable, etc. complete (except lamp) of the following model & as per sample approved by the Engineering-in-Charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

625.00

625.00

set

Celling concealed light

1.0000

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 648.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

660.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

727.06

VAT

6% of Total

IT

4% of Total

48.47 32.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

807.84

Page: 2472 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.17

Detailed Analysis Brief Description of Item 2 Ceiling Light (Surface Type): Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of spot light fitting of following manufacturers consisting of minimum 114mm dia 203mm high cylindrical powder coated aluminium shade, brass holder, earth terminal, necessary wiring with 2x0.4sq.mm stranded PVC insulated flexible FR cable, compatible for 23/26 W CFl etc. complete (except lamp) of the following model & as per sample approved by the Engineer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

Ceiling light

1.0000

set

650.00

650.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 673.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

686.46

10% Profit ( Add 10% on Subtotal-B) :

755.11

VAT

6% of Total

IT

4% of Total

50.34 33.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

839.01

Page: 2473 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.18

Detailed Analysis Brief Description of Item 2 Boundary Security Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Glass/Acrylic Globe boundary light fitting consisting of aluminium sheet cover with cast aluminium base, duly painted with DUCO wrinkle/place paint, design glass globe of min. dia 330mm and height 420mm with brass holder, earth terminal, necessary wiring with 2x0.4sq.mm stranded PVC insulated flexible FR cable etc. complete suitable for use of energy saving lamp of following model and sample approved by the Engineer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Boundary light

1.0000

set

1900.00

1900.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 1923.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1961.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2157.61

VAT

6% of Total

IT

4% of Total

143.84 95.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2397.34

Page: 2474 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.19

Detailed Analysis Brief Description of Item 2 Gate Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Speaker type special bollard light fitting consisting of cast aluminum body duly painted with DUCO wrinkle paint, acrylic luminous cover of min. dia 195mm and height 1050mm with brass holder, earth terminal, necessary wiring with 2x0.4sq.mm stranded PVC insulated flexible FR cable etc. complete suitable for use of energy saving lamp of following brand (Gloria/crescent/asha) and sample approved by the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Gate light

1.0000

set

5000.00

5000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 5023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5123.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5635.81

VAT

6% of Total

IT

4% of Total

375.72 250.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6262.01

Page: 2475 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.20

Detailed Analysis Brief Description of Item 2 Street Light Fitting: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of black die-casting aluminium body of , polisged aluminium reflector, suitable for 50mm dia Bracket for pole mounting, E-40 holder, ballast (Philips/Harmonics/ GE), necessary wiring suitable for use with 65/85 watt enegry saving lamp etc. with earth terminal complete & as per sample approved by the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Street light

1.0000

set

4200.00

4200.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 4223.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4307.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4738.21

VAT

6% of Total

315.88

IT

4% of Total

210.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5264.67

Page: 2476 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.21

Detailed Analysis Brief Description of Item 2 Louverset 2'x2': Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 4x2'x20 watt Fluorescent tube light fitting (concealed type) with v-grid louver of following manufacturers consisting of powder coated 22 SWG sheet steel frame of min. length 600mm & breadth 600mm, symmetrical mirror reflector of anodized, superior quality electronic ballast with one year guarantee, holder necessary wiring with 2x0.4sq.m PVC insulated flexible FR wire earth terminal etc complete of following model & as per sample approved by the engineer. Asha cat No. ACSTLS 356X4X20 watt Crescent cat No. CTLS-96X4X20 watt Gloria cat No. GTF 851X4X20 watt V Grid

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Louver light

1.0000

set

3100.00

3100.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 3123.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3185.46

10% Profit ( Add 10% on Subtotal-B) :

3504.01

VAT

6% of Total

233.60

IT

4% of Total

155.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3893.34

Page: 2477 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.22

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing mushroom type garden light of 350mm dia at top portion, 250mm height and having 20 SWG aluminium casting with green colour. The garden light should be installed on 300mmx300mmx13mm size base plate as per directions of the E-I-C. (Swash model No. SCGL 21 or any equivalent prior approved model). The rate excludes the cost of base plate.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Boundary light

1.0000

set

1900.00

1900.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 1923.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1961.46

10% Profit ( Add 10% on Subtotal-B) :

2157.61

VAT

6% of Total

IT

4% of Total

143.84 95.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2397.34

Page: 2478 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.23

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing 300mmx300mmx13mm size base plate placing on CC foundation in/c required size of nuts, bolts and two coats of red oxide paint complete and as per directions of the E-I-C. The rate excludes the cost of CC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set

Base plate (300x300x12mm)

1.0000

each

525.00

525.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00 593.00

Subtotal-A: All other remaining costs like painting, nuts, bolts, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

652.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

665.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

731.88

VAT

6% of Total

48.79

IT

4% of Total

32.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

59.30

813.20

Page: 2479 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.24

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing gate light fitting of minimum 610mm high consisting of hexagonal conical shaped polished brass made body, frosted fancy glass cover, brass holder, necessary wiring etc. complete (except lamp) of suitable for 38mm dia GI pipe post of following model as per sample approved by the E-I-C. (Model No. CG-14 Crescent or any equivalent prior approved quality).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Light fitting minimum 610mm high consisting of hexagonal conical shaped polished brass made body, frosted fancy glass cover, brass holder, necessary wiring etc.

1.0000

set

1601.00

1601.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 2176.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

21.76

Subtotal-A1:

2197.76

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2241.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2465.89

VAT

6% of Total

IT

4% of Total

164.39 109.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2739.87

Page: 2480 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.25

Detailed Analysis Brief Description of Item 2 GI Pole : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of G.I pole fabricated with G.I pipe completed with G.I sockets, top cover , necessary welding as required: Total 7620mm (25'-0") long having 101.6 mm (4") dia 20'-0" at the bottom and 76.20mm (3") dia 1524 mm (5'-0") at the middle and 75mm (3") dia 5'-0" at the top with 275 mm x275 mm x 16mm size steel bar plate completed as per instruction of E/C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

GI pole 25'

1.0000

each

13000.00

13000.00

Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.0000

day

470.00

940.00 15300.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15606.00

10% Profit ( Add 10% on Subtotal-B) :

17166.60

VAT

6% of Total

IT

4% of Total

1144.44 762.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

19074.00

Page: 2481 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.26

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of total 9.325m long GI pole having 150mm dia and 4mm thickness 5525mm at bottom and 75mm dia & 3mm thickness 3800mm at top with 275mmx275mmx16mm ms steel base plate all complete as per approved drawing, specification & direction of Engineer-In -charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

GI pole 30'

1.0000

each

19000.00

19000.00

Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.0000

day

470.00

940.00 21300.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21726.00

10% Profit ( Add 10% on Subtotal-B) :

23898.60

VAT

6% of Total

IT

4% of Total

1593.24 1062.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

26554.00

Page: 2482 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.27

Detailed Analysis Brief Description of Item 2 Pole Light Fitting: Supply, fitting fixing, testing & Commissioning of Metal halide flood light fitting as of following manufacturers (as per picture No. 10.2) consisting of black die-cast aluminium body of min. length 635mm & breadth 270mm, housing for control gear, polished aluminium reflector, 4 mm toughened heatproof glass, universal mounting for ceiling, wall or surface, hinged front glass for in position lamp replacement,cable entry gland, U-shaped bracket for pole mounting, brass holder, ballast (Phillips/ Harmonics /GE), ignitor, capacitor,necessary wiring with FR cable suitable for use with 250 watt metal halide lamp etc. with earth terminal complete with 250 watt metal halide lamp(Phillips /Harmonics/GE) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSM-3730(Metal) or Harmonics cat No. HPLSTL1003/250 MH or Crescent cat No. CST-1011/250 W MH or Shwash cat No.SCFL-9 MHRL-250 Watt or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Pole Light Fitting

1.0000

each

18000.00

18000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 18230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18594.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20454.06

VAT

6% of Total

IT

4% of Total

1363.60 909.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

22726.73

Page: 2483 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.28

Detailed Analysis Brief Description of Item 2 Saucer Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Saucer light fitting (with round fluorescent tube) of following manufacturers consisting of powder coated aluminium carrier & acrylic circular cover of minimum dia 350mm & height 120mm, holder, electronic ballast with one year guarantee, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable etc.compatible for 18/20 W RT complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Crescent cat No. CML - 42(32W R/T) or Gloria cat No. GCF- 801X1''X36 Watt Opel or Shwash cat No. SCCF (TFR)- 1/84 or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00

saucer Light2

1.0000

each

1520.00

1520.00 1750.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1785.00

10% Profit ( Add 10% on Subtotal-B) :

1963.50

VAT

6% of Total

130.90

IT

4% of Total

87.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2181.67

Page: 2484 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.29

Detailed Analysis Brief Description of Item 2 Saucer Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Fancy Saucer light fitting (suitable for 18/20 W fluorescent round tube) of following manufacturers consisting of powder coated steel carrier of min. dia 264mm, acrylic semicircular shade of height 90mm suitable for the carrier, holder, superior quality electronic ballast with one year guarantee, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Crescent cat No. CPM 56 (22Watt R/T) or Gloria cat No. GCF-884x1x22 watt or Shwash cat No. SCTFR- 4x22 watt or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

saucer Light3

1.0000

each

1780.00

1780.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2010.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2050.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2255.22

VAT

6% of Total

IT

4% of Total

150.35 100.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2505.80

Page: 2485 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.30

Detailed Analysis Brief Description of Item 2 Bracket Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Fancy single bracket light fitting of following manufacturers consisting of half round designed glass shade of minimum breadth 233mm, minimum total height of fitting 194mm, golden oxidized or chromium plated/ brass bracket with carrier, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Crescent cat No. CB-790-906 or Gloria cat No. GWB-2781-2418 FR or Shwash cat No. SCSB- 207 - CF Glass or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Bracket Light2

1.0000

each

800.00

800.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1030.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1050.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1155.66

VAT

6% of Total

IT

4% of Total

77.04 51.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1284.07

Page: 2486 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.31

Detailed Analysis Brief Description of Item 2 Bracket Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Fancy single bracket light fitting of following manufacturers consisting of half round half bowl type white acrylic sheet & lacquered chromium plated steel sheet base of minimium dia 285 mm & height 150 mm, with CFL compatible shade with brass holder, earth terminal, necessary wiring with 2 x 0.4 sq. mm stranded PVC insulated flexible FR cable etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSBS- 64 (H-SON) or Crescent cat No. CB-1199(ACR) CFL or Gloria cat No. GWB-1795-2155 CR(white) or Shwash cat No.SCSB-448 HUF MOON or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Bracket Light3

1.0000

each

880.00

880.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1110.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1132.20

10% Profit ( Add 10% on Subtotal-B) :

1245.42

VAT

6% of Total

83.03

IT

4% of Total

55.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1383.80

Page: 2487 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.32

Detailed Analysis Brief Description of Item 2 Mirror light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Double lamp bath-room light fitting of following manufacturers consisting of powder coated steel base with carrier, brass holder, cylindrical glass shade of minimum dia 100mm ( minimum total length of fitting 330mm), earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSBB 2810 or Crescent cat No. CBB-4/12-T12-P or Gloria cat No. GBB-953-1803 D/CUT or Shwash cat No. SCB- 33-12''PL or Anyasha cat No. ACBF-31-12''T or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Mirror Light2

1.0000

each

800.00

800.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1030.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1050.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1155.66

VAT

6% of Total

IT

4% of Total

77.04 51.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1284.07

Page: 2488 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.33

Detailed Analysis Brief Description of Item 2 Pendent Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Fancy Pendent light fitting of following manufacturers consisting of frosted ornamental designed glass of dia518mm, Golden /oxidized/ chromium plated brass carrier, brass holder, suspended by golden brass chain of required length where total length of fitting 600mm, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ASSCP-209 or Crescent cat No. CML-362 or Gloria cat No.GCF-3115-2422 or Shwash cat. No. SCH-10 (RLM New) orr equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Pendent Light2

1.0000

each

1877.00

1877.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2107.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2149.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2364.05

VAT

6% of Total

IT

4% of Total

157.60 105.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2626.73

Page: 2489 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.34

Detailed Analysis Brief Description of Item 2 Pendent Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of High Bay Light fitting suitable for 1x 85watt energy saving lamp of following manufacturers consisting of 325 mm. dia. inside & outside powder coated aluminium sheet body , height of 820 mm, covered with heat proof glass, E - 27 Porcelain Holder, suspended by oxidized/ chromium / plated golden brass chain/ stick of required length, Earth terminal, necessary wiring with 2 x 0.4 Sq. mm. stranded PVC insulated round FR Cable with ceiling base etc. complete (Except Lamp) of following model & as per sample accepted/approved by the Engineer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Pendent Light3

1.0000

each

2200.00

2200.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2430.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2478.60

10% Profit ( Add 10% on Subtotal-B) :

2726.46

VAT

6% of Total

IT

4% of Total

181.76 121.18 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3029.40

Page: 2490 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.35

Detailed Analysis Brief Description of Item 2 Single Tube Light Set : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1 x 4' x 40 watt Fluorescent tube light fitting of following manufacturers consisting of powder coated 22 SWG sheet steel frame of min. length 1240mm & breadth 60mm, designed acrylic sheet cover, superior quality electronic ballast of one year guarantee, holder, necessary wiring with 2 X 0.4 sq mm PVC insulated (stranded) flexible FR wire, earth terminal etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Ceiling / wall mounted type Crescent cat No. CTLS- 11 x1 x 40 watt Dgn or Gloria cat No. GTF- 755 x 1 x 40 watt Dgn or Asha cat No. ACSTLS 317x 1x 40 watt Shwash cat No. SCTF- 34x 1 x 40 watt or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

single tube set Light3

1.0000

each

1240.00

1240.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1470.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1499.40

10% Profit ( Add 10% on Subtotal-B) :

1649.34

VAT

6% of Total

IT

4% of Total

109.96 73.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1832.60

Page: 2491 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.36

Detailed Analysis Brief Description of Item 2 Single Tube Light Set : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1x 4' x 40 watt Fluorescent tube light fitting of following manufacturers consisting of powder coated 22 SWG sheet steel frame of min. length 1213mm & breadth 175mm, symmetrical mirror reflector of anodized aluminum, superior quality electronic ballast with one year guarantee, holder, necessary wiring cable with 2 x 0.4 sq mm PVC insulated (stranded) flexible FR wire, earth terminal etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Ceiling / wall mounted type : Crescent cat No. CTLS- 101 x1 x 40 watt or Gloria cat No. GTF- 807x 1 x 40 watt or Asha cat No. ACSTLS-339 x 1x 40 watt or Shwash cat No. SCTF- 24/85 x 1 x 40 watt or Anyasha cat No. ACTLS 84 x 1x 40 watt or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

single tube set Light4

1.0000

each

2100.00

2100.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2330.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2376.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2614.26

VAT

6% of Total

IT

4% of Total

174.28 116.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2904.73

Page: 2492 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.37

Detailed Analysis Brief Description of Item 2 Single Tube Light Set : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1 x 4' x 40 watt Fluorescent tube light Louver fitting (ceiling mounted) of following manufacturers consisting of powder coated 22 SWG sheet steel frame of min. length 1240mm & breadth 104mm, superior quality electronic ballast with one year guarantee, holder, necessary wiring with 2 x 0.4 sq mm PVC insulated (stranded) flexible FR wire, earth terminal etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Gloria cat No. GTF- 892 x1 x40 watt or Crescent cat No. CTLS- 225x1x40 (G) or Shwash cat No -CATA (CH) or Asha cat No. ACSTLS 307 x1x 40 watt or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

single tube set Light5

1.0000

each

1380.00

1380.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1610.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1642.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1806.42

VAT

6% of Total

IT

4% of Total

120.43 80.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2007.13

Page: 2493 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.38

Detailed Analysis Brief Description of Item 2 Single Tube Light Set : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1 x 4' x 40 watt Fluorescent tube light fitting (ceiling mounted & with design perspex sheet/cover ) of following manufacturers consisting of powder coated 22 SWG sheet steel frame of min. length 1240mm & breadth 104mm , superior quality electronic ballast with one year guarantee, holder, , necessary wiring with 2 x 0.4 sq mm PVC insulated (stranded) flexible FR wire, earth terminal etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Gloria cat No. GTF- 899 x1 x40 watt or Crescent cat No. CTLS- 225x1x40 (P) or Shwash cat No -SCTF-40 AX1X40 W or Asha cat No. ACSTLS 373 x1 x 40 watt Anyasha cat No. ACTLS 103 x1 x 40 watt or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

single tube set Light6

1.0000

each

1420.00

1420.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1650.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1683.00

10% Profit ( Add 10% on Subtotal-B) :

1851.30

VAT

6% of Total

IT

4% of Total

123.42 82.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2057.00

Page: 2494 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.39

Detailed Analysis Brief Description of Item 2 Double Tube Set: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 4 x 2'x 23 watt Compact Fluorescent light (CFL) fitting (False ceiling mounted concealed type) of following manufacturers consisting of powder coated 22 SWG sheet steel frame of min. length 600mm & breadth 600mm, designed prismatic sheet cover, superior quality E-27 holder, necessary wiring with 2 x 0.4 sq.mm PVC insulated (stranded) flexible FR wire, earth terminal etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Gloria cat No. GTF 924x4x23 watt CFL or Asha cat No. ACSTLS 391 x 4 x 20/23 watt Crescent cat No. CTLS-230x4x23 W (CFL) or Shwash cat No -SCTF-33X4X20 CFL or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

double tube set Light3

1.0000

each

2960.00

2960.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 3190.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3253.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3579.18

VAT

6% of Total

IT

4% of Total

238.61 159.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3976.87

Page: 2495 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.40

Detailed Analysis Brief Description of Item 2 Flood Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Flood light fitting with high pressure sodium lamp of following manufacturers having minimum breadth 410mm & height 300mm, back side cover of 145mm width, total height with stand 510mm, black color housing, consisting of aluminum die-casting body coated with epoxy powder, high purity anodized aluminum reflector, terminal resistant tempered glass cover , 250 W Sodium lamp, ignitor, 25 mfd capacitor, control gear, best quality E-40 holder, earth terminal, cast aluminum /iron adjustable stand, necessary wiring with FR cable suitable for use with 250 watt lamp etc. complete of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSFL-40 (250 W) or Harmonics cat No. HPL-MHL 1027/250HPS or Crescent cat No. CMHLD-02-250 W-HPS Shwash cat No.SCFL-8.5 MH-250 W or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

flood Light2

1.0000

each

16620.00

16620.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 16850.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17187.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18905.70

VAT

6% of Total

IT

4% of Total

1260.38 840.25 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21006.33

Page: 2496 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.41

Detailed Analysis Brief Description of Item 2 Flood Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Flood light fitting with metal halide lamp of following manufacturers having min. total length 460mm, black color housing consisting of aluminum sheet/die-casting body of min. dia 460mm & coated with epoxy powder, high purity anodized aluminum reflector, terminal resistant tempered glass cover , 400W flood light lamp, ignitor, 40mfd capacitor, control gear, best quality E-40 holder, earth terminal, cast aluminum /iron adjustable stand, necessary wiring with FR cable suitable for use with 400 watt lamp etc. complete of following model & as per sample accepted/approved by the Engineer.(suitable for upward high rise long beam glowing) Asha cat No. ACSF-3701 or Gloria cat No. GFL 734 x 1x 400 W MH or Crescent cat No. CFLD-03-400 WM/H or Shwash cat No.SCFL-1001/400 W or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

flood Light3

1.0000

each

18660.00

18660.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 18890.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19267.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21194.58

VAT

6% of Total

IT

4% of Total

1412.97 941.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23549.53

Page: 2497 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.42

Detailed Analysis Brief Description of Item 2 LED Flood: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of LED Flood light fitting with earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable, base foundation etc. complete of following specification & as per sample accepted/approved by the Engineer Power : 50W Driver : Standard, 90V-265V Housing : Aluminium Injection Body IP : IP65, Colour Temp. =6500 Kelvin Beam -120o Brand & Origin: EAE/OSRAM/PHILIPS, EU/USA

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

flood Light4

1.0000

each

5000.00

5000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 5230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5334.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5868.06

VAT

6% of Total

IT

4% of Total

391.20 260.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6520.07

Page: 2498 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.43

Detailed Analysis Brief Description of Item 2 LED Flood: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of LED Flood light fitting with earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable, base foundation etc. complete of following specification & as per sample accepted/approved by the Engineer Power : 100W Driver : Standard, 90V-265V Housing : Aluminium Injection Body IP : IP65, Colour Temp. =6500 Kelvin Beam -120o Brand & Origin: EAE/OSRAM/PHILIPS, EU/USA

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

flood Light5

1.0000

each

10000.00

10000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 10230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10434.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11478.06

VAT

6% of Total

IT

4% of Total

765.20 510.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12753.40

Page: 2499 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.44

Detailed Analysis Brief Description of Item 2 Ceiling Concealed Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Spot light fitting of following manufacturers consisting of powder coated white aluminium body of minimum dia 130mm at bottom (minimum total height of shade 160mm) & cast aluminium bracket, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable etc., compatible for 15/18 watt CFL, complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSS-2887 or Crescent cat No. CML - 149 or Gloria cat No. GSL- 401 or Shwash cat No. SCSL- 20 (B) or Anyasha cat No. ACSL-1012 or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Ceiling ConcealedLight2

1.0000

each

530.00

530.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 760.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

775.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

852.72

VAT

6% of Total

IT

4% of Total

56.85 37.90 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

947.47

Page: 2500 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.45

Detailed Analysis Brief Description of Item 2 Ceiling Concealed Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Concealed type Spot Light fitting of following manufacturers consisting of min. 120 mm. dia & 184mm height Steel Sheet Carrier (body & arms) with Powder coated Paint & inside powder coated white reflector, E – 27 Holder, Earth terminal, necessary wiring with 2 x 0.4 Sq. mm. Stranded PVC insulated flexible FR Cable etc., suitable for 18/20 watt CFL, Complete (Except Lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSP-3670 or Gloria cat No. GDL 377 or Crescent cat No. CML-177 or Shwash cat No -SCCSL-1 Brass or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Ceiling ConcealedLight3

1.0000

each

720.00

720.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 950.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

969.00 1065.90 71.06 47.37

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1184.33

Page: 2501 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.46

Detailed Analysis Brief Description of Item 2 Ceiling Concealed Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Concealed type Spot Light fitting of following manufacturers consisting of min. 152 mm. dia & 114 mm height Cylindrical aluminium shade having Powder coated Paint & inside chromium plated brass reflector, E – 27 Holder, Earth terminal, necessary wiring with 2 x 0.4 Sq. mm. Stranded PVC insulated flexible FR Cable etc., suitable for 15/18 watt CFL, Complete (Except Lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSS-2852 or Gloria cat No. GDL 378(B) AL/CHB or Crescent cat No. CML-58 or Shwash cat No -SCCSL-6 Charuta (M) or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Ceiling ConcealedLight4

1.0000

each

960.00

960.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1190.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1213.80

10% Profit ( Add 10% on Subtotal-B) :

1335.18

VAT

6% of Total

89.01

IT

4% of Total

59.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1483.53

Page: 2502 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.47

Detailed Analysis Brief Description of Item 2 Boundary/Garden Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Special type Bollard light fitting of following manufacturers having minimum total height 455 mm & dia 225 mm, consisting of cast aluminium body, aluminium louver, mounted on 50.8 mm (2") dia G.I. pipe with base duly painted with DUCO hammer/wrinkle paint, acrylic luminous cover, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible FR cable & suitable to be fitted on prepared C.C base, complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Crescent cat No. CG-74 or Gloria cat No. GGL-307 or Shwash cat No. SCGL-37 or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Boundary/Garden Light5

1.0000

each

2850.00

2850.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 3080.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3141.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3455.76

VAT

6% of Total

IT

4% of Total

230.38 153.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3839.73

Page: 2503 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.48

Detailed Analysis Brief Description of Item 2 Boundary/Garden Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Garden light fitting of following manufacturers having minimum total height 1090 mm, consisting of Aluminum cast top cover & cast Aluminum base, Vertical support with Steel Sheet frame (dia 300mm at top) duly Painted with Wrinkle / Powder coated Paint, Clear glass cover, Brass Holder, earth terminal, necessary wiring with 2 x 0.4 Sq. mm. Stranded PVC insulated flexible FR Cable, etc. Complete to be fitted on 740mm GI pipe (38mm dia) (except Lamp, except pipe) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSGL-994 or Crescent cat No. CGL-82 or Gloria cat No. GGDL-268 or Shwash cat No -SCGDL-40 New garden light or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Boundary/Garden Light6

1.0000

each

4200.00

4200.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 4430.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4518.60

10% Profit ( Add 10% on Subtotal-B) :

4970.46

VAT

6% of Total

IT

4% of Total

331.36 220.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5522.73

Page: 2504 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.49

Detailed Analysis Brief Description of Item 2 Boundary/Garden Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Glass/Acrylic Globe gate' light fitting of following manufacturers having minimum total height 420 mm , consisting of cast aluminium base duly painted with DUCO wrinkle/ place paint, plain glass shade of min. dia 330 mm, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible FR cable etc. complete suitable for use of energy savings lamps (except lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACS-GL 978 (16'') or Crescent cat No. CG-100-G-16'' or Shwash cat No -SCGL-12" Globe or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Boundary/Garden Light7

1.0000

each

3040.00

3040.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 3270.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3335.40

10% Profit ( Add 10% on Subtotal-B) :

3668.94

VAT

6% of Total

244.60

IT

4% of Total

163.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4076.60

Page: 2505 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.50

Detailed Analysis Brief Description of Item 2 Boundary/Garden Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Bollard light fitting of following manufacturers having minimum total height 1110 mm & upper part dia 205 mm & made of cast aluminium body , acrylic luminous cover etc. mounted on 50.8 mm (2") dia G.I pipe with base plate duly painted with DUCO hammer/wrinkle paint polished aluminium reflector, acrylic luminous cover, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible FR cable & suitable to be fitted on C.C base, complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Crescent cat No. CGL-27 or Gloria cat No. GBL-253 or Shwash cat No. SCBL-2(ALU) or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Boundary/Garden Light8

1.0000

each

5700.00

5700.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 5930.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6048.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6653.46

VAT

6% of Total

IT

4% of Total

443.56 295.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7392.73

Page: 2506 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.51

Detailed Analysis Brief Description of Item 2 Boundary/Garden Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Special type Bollard light fitting of following manufacturers with minimum total height 900 mm & dia 235 mm , consisting of cast aluminium body, mounted on 50.8 mm (2") dia G.I. pipe with base, duly painted with DUCO hammer/wrinkle paint, acrylic luminous cover, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible FR cable & suitable to be fitted on prepared C.C base, complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Crescent cat No. CGL-36 or Gloria cat No. GBL-263 or Shwash cat No. SCBL-11(Big) or Asha cat No. ACSBL-2954 or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Boundary/Garden Light9

1.0000

each

2436.00

2436.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2666.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2719.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2991.25

VAT

6% of Total

IT

4% of Total

199.42 132.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3323.61

Page: 2507 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.52

Detailed Analysis Brief Description of Item 2 Boundary/Garden Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Fancy Gate light fitting of following manufacturers having minimum height 420 mm, (shade top dia 195mm), consisting of cast aluminium cover with cast aluminium base, duly painted with DUCO paint, design glass, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable etc. complete suitable for use of energy savings lamps (except lamp) of following model & as per sample accepted/approved by the Engineer. Crescent cat No. CGL-67 or Asha cat No. ACSGL- 976 or Gloria cat No. GGL-295(B) or Shwash cat No -New gate light SCGL-40 or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Boundary/Garden Light10

1.0000

each

2085.00

2085.00

Plumber/ Electric Mistry/ Painter

0.3000

day

680.00

204.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 2383.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2430.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2673.73

VAT

6% of Total

IT

4% of Total

178.25 118.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2970.81

Page: 2508 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.53

Detailed Analysis Brief Description of Item 2 Boundary/Garden Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Garden light fitting of following manufacturers having minimum total height 930 mm , consisting of 300mm height & 195mm dia cast aluminium shade (top & bottom cover including louver type middle part) , 630 mm GI pipe of 50mm dia & cast aluminium base duly painted DUCO wrinkle/ place paint, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible FR cable etc. complete suitable to be fitted on prepared C.C. base & for use of energy saving lamps (except lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSWGL-9307 or Gloria cat No. GBL 284 or Shwash cat No.SCBL-12 or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Boundary/Garden Light11

1.0000

each

5730.00

5730.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 5960.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6079.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6687.12

VAT

6% of Total

IT

4% of Total

445.81 297.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7430.13

Page: 2509 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.54

Detailed Analysis Brief Description of Item 2 Security Light (Water Tight): Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Special type Security light fitting of following manufacturers consisting of maroon color powder coated steel sheet body of 205 mm length & 110mm breadth, thickness 100 mm, cover of glass, brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible FR cable etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSBF (WT) 2019 or Gloria cat No. GWT 363 Glass or Crescent cat No. CML- 140 GL or Shwash cat No -BF (WT)-Glass or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

secuirity Light1

1.0000

each

863.00

863.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1093.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1114.86

10% Profit ( Add 10% on Subtotal-B) :

1226.35

VAT

6% of Total

81.76

IT

4% of Total

54.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1362.61

Page: 2510 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.55

Detailed Analysis Brief Description of Item 2 Security Light (Water Tight): Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Special type W.T light fitting of following manufacturers consisting of cast aluminium base of min. length 205mm, splited aluminium cover, (breadth of fitting 135mm) brass holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible FR cable etc. complete (except lamp) of following model & as per sample approved by the Engineer . Crescent cat No. CBH- 20 or Gloria cat No. GWT-711 or Shwash cat No. BF(WT)-7 or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

863.00

863.00

each

secuirity Light2

1.0000

each

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1093.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1114.86

10% Profit ( Add 10% on Subtotal-B) :

1226.35

VAT

6% of Total

IT

4% of Total

81.76 54.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1362.61

Page: 2511 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.56

Detailed Analysis Brief Description of Item 2 Street light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 150 W Road light fitting with high pressure Sodium lamp of following manufacturers of length 530mm, breadth 240mm, height 235 mm, consisting of epoxy powder coated grey colour Aluminium die-casting body, high purity anodized aluminium reflector, terminal resistant tempered frosted glass cover, 150 W high pressure sodium lamp, E-40/E-27 holder, Ignitor, 12 mfd Capacitor, control gear, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable & mountable on 38.1 mm (1.5") dia G.I pipe bracket etc. complete (with lamp) of following model & as per sample accepted/approved by the Engineer. Harmonics cat No. HPL-STL1001 /150 HPS OR Asha cat No. ACS RL- 3747(CFL) or Crescent Cat No-CST-1010-150 watt or Shwash cat No -SCSLR-1006X1X150 W or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

street Light2

1.0000

each

13020.00

13020.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 13250.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13515.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14866.50

VAT

6% of Total

IT

4% of Total

991.10 660.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

16518.33

Page: 2512 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.57

Detailed Analysis Brief Description of Item 2 Street light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1x85 W CFL Street light fitting of following manufacturers consisting of powder coated black/grey painted steel sheet body of breadth 310mm& length 425mm , clear heat proof glass cover, E-27 holder, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable & mountable on 38.1 mm (1.5") dia G.I pipe bracket etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Gloria cat No. GRL 746x1x85W CFL or Asha cat No. ACS RL- 3723(CFL) or Crescent Cat No-CST-1007 or Shwash cat No -SCRL-6 (SM) or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

street Light3

1.0000

each

5235.00

5235.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 5465.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5574.30

10% Profit ( Add 10% on Subtotal-B) :

6131.73

VAT

6% of Total

408.78

IT

4% of Total

272.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6813.03

Page: 2513 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.58

Detailed Analysis Brief Description of Item 2 Street light: LED LIGHT Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of LED Street light fitting with earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible Frcable & mountable on 38.1 mm (1.5") dia G.I pipe bracket etc. complete of following specification & as per sample accepted/approved by the Engineer Power : 36W Driver : Standard, 110V-265V Housing : Aluminium Injection Body IP : IP66, Colour Temp. =4000 Kelvin Optics -1 : narrow beam lense Optics-2 : Tempered Glass

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

street Light4

1.0000

each

20000.00

20000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 20230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20634.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22698.06

VAT

6% of Total

IT

4% of Total

1513.20 1008.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25220.07

Page: 2514 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.59

Detailed Analysis Brief Description of Item 2 Fountain light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 250 volt grade Fountain light fitting of following manufacturers of cast aluminium robust housing with net type arrangement with polished aluminium reflector of min. dia 125mm at top & height 150mm, heat proof/ toughened glass, silicon rubber gasket, necessary wiring with sub marine cable, lamp holder, etc. complete with prime coating and best quality powder coated paint suitable to use with Par-38 lamp, complete (with lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACS-U WL1188 or Crescent Cat No-CUWL-03 (N) or S hwash cat No -SCEPL-1 Net Brass or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

fountain Light1

1.0000

each

6755.00

6755.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 6985.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7124.70

10% Profit ( Add 10% on Subtotal-B) :

7837.17

VAT

6% of Total

522.48

IT

4% of Total

348.32 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8707.97

Page: 2515 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.60

Detailed Analysis Brief Description of Item 2 Tower/aviation light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 250 volt grade Tower/Aviation light fitting of following manufacturers consisting of cast aluminium robust housing of min. dia 210mm & height 300mm with polished aluminium reflector, heat proof/ toughened glass, silicon rubber gasket, metalic net, necessary wiring with FR cable , lamp holder, etc. complete with prime coating and best quality powder coated paint suitable to use with 400W-1000W lamp, complete (without lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACS-L2006 or Crescent cat No. CML x339 (Expansion Proof) or Gloria cat No. GEPL-742 or Shwash cat No -SCAV-1 Sincnac or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Tower/aviation light1

1.0000

each

6820.00

6820.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 7050.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7191.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7910.10

VAT

6% of Total

IT

4% of Total

527.34 351.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8789.00

Page: 2516 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.61

Detailed Analysis Brief Description of Item 2 Lake light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of out door type, recessed wall/step mounted lake light fittings of following manufacturers consisting of cast aluminium robust housing of breadth 300mm & height 110mm (width or depth of housing 100mm) , water proof louver type diffuser, polished aluminium reflector with fixing materials, rubber gasket, lamp cap, earth terminal, necessary wiring & mending the damages good, complete (except Lamp) of following model & as per sample accepted/approved by the Engineer. Asha ACSF-230 casting (lake light) or Crescent cat No. CML-568 or Shwash cat No -SCSL-786X1X30 Watt or equivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Lake light 1

1.0000

each

4872.00

4872.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 5102.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5204.04

10% Profit ( Add 10% on Subtotal-B) :

5724.44

VAT

6% of Total

381.63

IT

4% of Total

254.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6360.49

Page: 2517 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.10.62

Detailed Analysis Brief Description of Item 2 Operation Theatre Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Special type OT Light (Operation Theatre Light) with all necessay accessories complete as per following specification & as per sample accepted/approved by the Engineer. Diameter of Light Head: 650mm Illumination at 1m: 80000-160000 Diameter of Light Sport D10: 180mm Diameter of Light Sport D50:110mm Depth of Illumination: 130mm Color rendering index CRI: =/>90 Optional color Temperature (K): 3500/4000/4500 Number of LED bulbs: 72 Average bulb life: 50000 hours Heat-to-Light Ratio: =/<3.3 Power Supply: 110V/220V Input Power: 240V Ceilling Height for installation: 270-320 cm Country of Origin : USA/EU countries or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

OT Light

1.0000

each

125000.00

125000.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 125575.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

128086.50

10% Profit ( Add 10% on Subtotal-B) :

140895.15

VAT

6% of Total

IT

4% of Total

9393.01 6262.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

156550.17

Page: 2518 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.10.63

2 Foot Light: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Stair light fitting of following manufacturers consisting of pre-treated powder coated steel sheet body of min. breadth 300mm & height 180mm, earth terminal, necessary wiring with 2 x 0.4 sq.mm stranded PVC insulated flexible FR cable etc. complete (except lamp) of following model & as per sample accepted/approved by the Engineer. Asha cat No. ACSF- 216 or Crescent cat No. CML- 568 (I) or Gloria cat No. GFL-02 or Shwash Foot light Dhali+B705 or equiivalent product.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Foot Light2

1.0000

each

720.00

720.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 950.00

Subtotal-A: Subtotal-B: Subtotal-C:

969.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1065.90

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

71.06 47.37 Total:

8.11

Supplying, fitting and fixing the following electric lamp for garden/gate/room light and different places as per directions of the E-IC.

8.11.1

Balandered bulb

Note : Rates of all items should be inclusive of all supply and carriage.

1184.33

Page: 2519 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.11.1.1

2 160 watt

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 160w mercury bulb

1.0000

each

440.00

440.00

Plumber/ Electric Mistry/ Painter

0.0250

day

680.00

17.00 457.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

4.57

Subtotal-A1:

461.57

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

470.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

517.88

VAT

6% of Total

34.53

IT

4% of Total

23.02 Total:

8.11.1.2

200 watt

each 200w mercury bulb

1.0000

each

495.00

495.00

Plumber/ Electric Mistry/ Painter

0.0250

day

680.00

17.00 512.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

5.12

Subtotal-A1:

517.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

527.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

580.21

VAT

6% of Total

IT

4% of Total

38.68 25.79 Total:

8.11.2

575.42

644.68

Normal bulb

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2520 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.11.2.1

2 500 watt

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 500w normal bulb

1.0000

each

165.00

165.00

Plumber/ Electric Mistry/ Painter

0.0250

day

680.00

17.00 182.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.82

Subtotal-A1:

183.82

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

187.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

206.25

VAT

6% of Total

13.75

IT

4% of Total

9.17 Total:

8.11.2.2

200 watt

each 200w normal bulb

1.0000

each

60.00

60.00

Plumber/ Electric Mistry/ Painter

0.0250

day

680.00

17.00 77.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.77

Subtotal-A1:

77.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

79.33

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

87.26

VAT

6% of Total

IT

4% of Total

5.82 3.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

229.16

96.95

Page: 2521 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.11.2.3

2 100 watt

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 100w normal bulb

1.0000

each

37.00

37.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 45.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.46

Subtotal-A1:

46.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

47.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

51.95

VAT

6% of Total

3.46

IT

4% of Total

2.31 Total:

8.11.2.4

60 watt

each 60w normal bulb

1.0000

each

32.00

32.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 40.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.41

Subtotal-A1:

41.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

42.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

46.28

VAT

6% of Total

IT

4% of Total

3.09 2.06 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

57.72

51.42

Page: 2522 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.11.2.5

2 40 watt

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 40w normal bulb

1.0000

each

32.00

32.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 40.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.41

Subtotal-A1:

41.25

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

42.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

46.28

VAT

6% of Total

3.09

IT

4% of Total

2.06 Total:

8.11.2.6

1.20m 40 wall flurorecent lamp

each 1.20m 40W fluorescent tube (Eastern or prior approved quality)

1.0000

each

120.00

120.00

Asst Electrician

0.0100

day

680.00

6.80 126.80

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

1.27

Subtotal-A1: Subtotal-B: Subtotal-C:

128.07 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

130.63

10% Profit ( Add 10% on Subtotal-B) :

143.69

VAT

6% of Total

IT

4% of Total

9.58 6.39 Total:

8.11.3

51.42

159.66

Energy Savings Lamp (CLF)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2523 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.11.3.01

2 5/6/7 watt Pin Type B-22 CDL (Cool Day Light)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 5/6/7 watt Pin Type B-22 CDL (Cool Day Light)

1.0000

each

235.00

235.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 243.84

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

248.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

273.59

VAT

6% of Total

18.24

IT

4% of Total

12.16 Total:

8.11.3.02

11/13/14/15 watt B-22 CDL

each 11/13/14/15 watt B-22 CDL

1.0000

each

267.00

267.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 275.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.76

Subtotal-A1: Subtotal-B: Subtotal-C:

278.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

284.17

10% Profit ( Add 10% on Subtotal-B) :

312.59

VAT

6% of Total

IT

4% of Total

20.84 13.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

303.99

347.32

Page: 2524 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.11.3.03

Detailed Analysis Brief Description of Item 2 8 watt screw Type lamps E-27 CDL/11 watt E22

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 8 watt screw Type lamps E-27 CDL/11 watt E22

1.0000

each

235.00

235.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 243.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.44

Subtotal-A1:

246.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

251.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

276.32

VAT

6% of Total

18.42

IT

4% of Total

12.28 Total:

8.11.3.04

15 watt Spiral Type lamps B22 CD

each 15 watt Spiral Type lamps B22 CDL

1.0000

each

225.00

225.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 233.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.34

Subtotal-A1:

236.18

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

240.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

264.99

VAT

6% of Total

IT

4% of Total

17.67 11.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

307.03

294.44

Page: 2525 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.11.3.05

2 20 watt Spiral Type lamps B22 CD

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 20 watt Spiral Type lamps B22 CDL

1.0000

each

289.00

289.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 297.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.98

Subtotal-A1:

300.82

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

306.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

337.52

VAT

6% of Total

22.50

IT

4% of Total

15.00 Total:

8.11.3.06

23 watt Spiral Type lamps B22

each 23 watt Spiral Type lamps B22

1.0000

each

275.00

275.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 283.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.84

Subtotal-A1:

286.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

292.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

321.65

VAT

6% of Total

IT

4% of Total

21.44 14.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

375.02

357.39

Page: 2526 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.11.3.07

Detailed Analysis Brief Description of Item 2 15 watt Spiral Screw Type lamps E-27

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 15 watt Spiral Screw Type lamps E-27

1.0000

each

267.00

267.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 275.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.76

Subtotal-A1:

278.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

284.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

312.59

VAT

6% of Total

20.84

IT

4% of Total

13.89 Total:

8.11.3.08

20 watt Spiral Screw Type lamps E-27

each 20 watt Spiral Screw Type lamps E-27

1.0000

each

289.00

289.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 297.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.98

Subtotal-A1:

300.82

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

306.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

337.52

VAT

6% of Total

IT

4% of Total

22.50 15.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

347.32

375.02

Page: 2527 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.11.3.09

2 23 watt Spiral Screw Type lamps E-27

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 23 watt Spiral Screw Type lamps E-27

1.0000

each

275.00

275.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 283.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.84

Subtotal-A1:

286.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

292.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

321.65

VAT

6% of Total

21.44

IT

4% of Total

14.30 Total:

8.11.3.10

9 watt lamps B-22/E-27 CDL

each 9 watt lamps B-22/E-27 CDL

1.0000

each

246.00

246.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 254.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.55

Subtotal-A1:

257.39

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

262.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

288.79

VAT

6% of Total

IT

4% of Total

19.25 12.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

357.39

320.88

Page: 2528 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.11.3.11

Detailed Analysis Brief Description of Item 2 14 watt Mini Spiral Type lamps B-22/E-27 Warm White

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 14 watt Mini Spiral Type lamps B-22/E-27 Warm White

1.0000

each

257.00

257.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 265.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.66

Subtotal-A1:

268.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

273.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

301.26

VAT

6% of Total

20.08

IT

4% of Total

13.39 Total:

8.11.3.12

25/26 watt Spiral Type lamps E-27 CDL

each 25/26 watt Spiral Type lamps E-27 CDL

1.0000

each

280.00

280.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 288.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.89

Subtotal-A1:

291.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

297.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

327.32

VAT

6% of Total

IT

4% of Total

21.82 14.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

334.73

363.69

Page: 2529 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.11.3.13

2 8 watt lamps E-14 DL/ W W

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 8 watt lamps E-14 DL/ W W

1.0000

each

235.00

235.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 243.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.44

Subtotal-A1:

246.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

251.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

276.32

VAT

6% of Total

18.42

IT

4% of Total

12.28 Total:

8.11.3.14

11 watt lamps E-14 DL

each 11 watt lamps E-14 DL

1.0000

each

250.00

250.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 258.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.59

Subtotal-A1:

261.43

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

266.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

293.32

VAT

6% of Total

IT

4% of Total

19.55 13.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

307.03

325.91

Page: 2530 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.11.3.15

2 15 watt lamps B-22 DL

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each 15 watt lamps B-22 DL

1.0000

each

267.00

267.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 275.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.76

Subtotal-A1:

278.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

284.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

312.59

VAT

6% of Total

20.84

IT

4% of Total

13.89 Total:

8.11.3.16

20 watt lamps B-22 DL/E-27 DL

each 20 watt lamps B-22 DL/E-27 DL

1.0000

each

289.00

289.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 297.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.98

Subtotal-A1:

300.82

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

306.83

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

337.52

VAT

6% of Total

IT

4% of Total

22.50 15.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

347.32

375.02

Page: 2531 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.11.3.17

2 65 watt lamps E-27 DL/B-27

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 65 watt lamps E-27 DL/B-27

1.0000

each

1284.00

1284.00

Plumber/ Electric Mistry/ Painter

0.0130

day

680.00

8.84 1292.84

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

12.93

Subtotal-A1:

1305.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1331.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1465.07

VAT

6% of Total

97.67

IT

4% of Total

65.11 Total:

8.11.4

"Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of the following electric lamp/bulb for room light/gate light/garden light etc. complete as per requirement.Origin :EU/USA or equivalent."

8.11.4.01

28W, T5 Tube,

each 28w, t5 tube

1.0000

each

165.00

Subtotal-B: Subtotal-C:

165.00 165.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

168.30

10% Profit ( Add 10% on Subtotal-B) :

185.13

VAT

6% of Total

IT

4% of Total

12.34 8.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1627.86

205.70

Page: 2532 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.11.4.02

2 3W LED Bulb (White)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

290.00

290.00

each 3w led

1.0000

each

290.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

295.80

10% Profit ( Add 10% on Subtotal-B) :

325.38

VAT

6% of Total

21.69

IT

4% of Total

14.46 Total:

8.11.4.03

5W LED Bulb (White)

each 5w led

1.0000

each

415.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

423.30

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

465.63

VAT

6% of Total

IT

4% of Total

31.04 20.69 Total:

7W LED Bulb (White)

517.37

each 7w led

1.0000

each

500.00

Subtotal-B: Subtotal-C:

500.00 500.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

510.00

10% Profit ( Add 10% on Subtotal-B) :

561.00

VAT

6% of Total

IT

4% of Total

37.40 24.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

415.00 415.00

Subtotal-A:

8.11.4.04

361.53

623.33

Page: 2533 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.11.4.05

2 9W LED Bulb

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

700.00

700.00

each 9w led

1.0000

each

700.00

Subtotal-A: Subtotal-B: Subtotal-C:

8.11.4.06

12W LED Bulb

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

714.00

10% Profit ( Add 10% on Subtotal-B) :

785.40

VAT

6% of Total

52.36

IT

4% of Total

34.91 Total:

872.67

2000.00

2000.00

each 12w led

1.0000

each

2000.00

Subtotal-A:

8.11.4.07

65W LED Street Bulb

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2040.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2244.00

VAT

6% of Total

IT

4% of Total

149.60 99.73 Total:

2493.33

24000.00

24000.00

each 65w led street

1.0000

each

24000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24480.00

10% Profit ( Add 10% on Subtotal-B) :

26928.00

VAT

6% of Total

IT

4% of Total

1795.20 1196.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

29920.00

Page: 2534 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.11.4.08

2 150W High Pressure Sodium Vapor lamp

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 150w sodium light

1.0000

each

1200.00

1200.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1224.00

10% Profit ( Add 10% on Subtotal-B) :

1346.40

VAT

6% of Total

89.76

IT

4% of Total

59.84 Total:

8.12

Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of single stage 2800-2900 RPM Centrifugal water Pump Motor Set monobloc type manufactured according to DIN/NEMA/IEC/BS/VDE/JIS & ISO 9001 standard of following capacity suitable for operation at single phase, 230V/400V ± 5% 50Hz A.C having insulation: Class F & Protection: IP44 (Minimum) manufactured by CE certified/UL listed countries as per sample accepted/approved by the Engineer.

8.12.1

440 volts 3-phase

Note : Rates of all items should be inclusive of all supply and carriage.

1200.00

1496.00

Page: 2535 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.12.1.1

2 3.00 HP

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 3 phase 440V 3hp centrifugal pump motor

1.0000

set

20500.00

20500.00

Nails/ Nut bolts/ Screw/ Spikes

0.2000

kg

65.00

13.00

Plumber/ Electric Mistry/ Painter

0.2500

day

680.00

170.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 20918.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

209.18

Subtotal-A1:

21127.18

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21549.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

23704.70

VAT

6% of Total

1580.31

IT

4% of Total

1053.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

26338.55

Page: 2536 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.12.1.2

2 5.5 HP

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 3 phase 440V 5hp centrifugal pump motor

1.0000

set

33450.00

33450.00

Nails/ Nut bolts/ Screw/ Spikes

0.2000

kg

65.00

13.00

Plumber/ Electric Mistry/ Painter

0.2500

day

680.00

170.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 33868.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

338.68

Subtotal-A1:

34206.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

34890.81

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

38379.89

VAT

6% of Total

2558.66

IT

4% of Total

1705.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

42644.33

Page: 2537 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.12.1.3

2 7.5 HP

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 3 phase 440V 7hp centrifugal pump motor

1.0000

set

38750.00

38750.00

Nails/ Nut bolts/ Screw/ Spikes

0.2000

kg

65.00

13.00

Plumber/ Electric Mistry/ Painter

0.2500

day

680.00

170.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 39168.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

391.68

Subtotal-A1:

39559.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40350.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

44385.96

VAT

6% of Total

2959.06

IT

4% of Total

1972.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

49317.73

Page: 2538 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.12.1.4

2 10.00 HP

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 3 phase 440V 10hp centrifugal pump motor

1.0000

set

45640.00

45640.00

Nails/ Nut bolts/ Screw/ Spikes

0.2000

kg

65.00

13.00

Plumber/ Electric Mistry/ Painter

0.2500

day

680.00

170.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 46058.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

460.58

Subtotal-A1:

46518.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

47448.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

52193.85

VAT

6% of Total

3479.59

IT

4% of Total

2319.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

57993.16

Page: 2539 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.12.1.5

2 15.00 HP

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 3-phase 440V 15hp centrifugal pump motor

1.0000

set

65000.00

65000.00

Nails/ Nut bolts/ Screw/ Spikes

0.3000

kg

65.00

19.50

Plumber/ Electric Mistry/ Painter

0.6000

day

680.00

408.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.8000

day

470.00

376.00 65803.50

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

658.04

Subtotal-A1:

8.12.1.6

20.00 HP

66461.54

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

67790.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

74569.84

VAT

6% of Total

4971.32

IT

4% of Total

3314.22 Total:

82855.38

172000.00

172000.00

each 3-phase 440V 20hp centrifugal pump motor

1.0000

each

Nails/ Nut bolts/ Screw/ Spikes

0.4500

kg

65.00

29.25

Plumber/ Electric Mistry/ Painter

0.6000

day

680.00

408.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.9000

day

470.00

423.00 172860.25

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

176317.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

193949.20

VAT

6% of Total

IT

4% of Total

12929.95 8619.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

215499.11

Page: 2540 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.12.1.7

2 30.00 HP

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 3-phase 440V 30hp centrifugal pump motor

1.0000

set

192000.00

192000.00

Nails/ Nut bolts/ Screw/ Spikes

0.4500

kg

65.00

29.25

Plumber/ Electric Mistry/ Painter

0.6000

day

680.00

408.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.9000

day

470.00

423.00 192860.25

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

1928.60

Subtotal-A1:

194788.85

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

198684.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

218553.09

VAT

6% of Total

14570.21

IT

4% of Total

9713.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

242836.77

Page: 2541 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.12.1.8

2 40 H.P Pump Motor Set, Discharge: 4650- 833 liter/min , Head: 28-51 metre, Suction & delivery: 100 mm x 80 mm (4"x3" )

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

40hp pump

1.0000

each

490000.00

Nails/ Nut bolts/ Screw/ Spikes

1.0000

kg

65.00

65.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.0000

day

470.00

940.00 491685.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

501518.70

10% Profit ( Add 10% on Subtotal-B) :

551670.57

VAT

6% of Total

IT

4% of Total

36778.04 24518.69 Total:

8.12.2

490000.00

612967.30

220 volts single phase

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2542 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.2.1

Detailed Analysis Brief Description of Item 2 .5 H.P Pump Motor Set. Discharge: 10-80 liter/min, Head: 22-14 metre Suction & delivery : 25 mm x 25 mm (1" x 1" )

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

single phase centrifugal pump1

1.0000

each

12000.00

12000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 12230.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

122.30

Subtotal-A1: Subtotal-B: Subtotal-C:

12352.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12599.35

10% Profit ( Add 10% on Subtotal-B) :

13859.28

VAT

6% of Total

IT

4% of Total

923.95 615.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15399.20

Page: 2543 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.2.2

Detailed Analysis Brief Description of Item 2 1.00 H.P Centrifugal Pump Motor Set Discharge: 10-90 liter/min, Head: 34-25 meter. Suction & delivery : 25 mm x 25 mm (1" x 1" )

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

single phase centrifugal pump2

1.0000

each

14216.00

14216.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 14446.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

144.46

Subtotal-A1: Subtotal-B: Subtotal-C:

14590.46 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14882.27

10% Profit ( Add 10% on Subtotal-B) :

16370.50

VAT

6% of Total

IT

4% of Total

1091.37 727.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18189.44

Page: 2544 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.2.3

Detailed Analysis Brief Description of Item 2 1.5 H.P Centrifugal Pump Motor Set. Discharge: 30- 120 liter/min Head: 38-22 meter. Suction & delivery: 32 mm x 25 mm (1.25" x 1" )

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

single phase centrifugal pump3

1.0000

each

20020.00

20020.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 20250.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20655.00

10% Profit ( Add 10% on Subtotal-B) :

22720.50

VAT

6% of Total

IT

4% of Total

1514.70 1009.80 Total:

8.12.2.4

2.00 H.P Centrifugal Pump Motor Set Discharge: 50 - 220 liter/ min Head: 37-20 meter Suction & Delivery: 40 mm x 25 mm (1.50” x 1”)

each

single phase centrifugal pump4

1.0000

each

30000.00

30000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 30230.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30834.60

10% Profit ( Add 10% on Subtotal-B) :

33918.06

VAT

6% of Total

IT

4% of Total

2261.20 1507.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25245.00

37686.73

Page: 2545 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

8.12.3

Motor starter Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of metal clad surface mounting type three phase 400 ± 5% Volt 50 Hz. automatic direct-on -line (DOL) motor starter complete with contractor, overload relay coil, etc. (Foreign made) of the following range of rated current including supply of required fixing materials assembled by ADEX/SIEMENS/SIGMA PUMP LTD. or equivalent as per direction of the Engineers.

8.12.3.1

4 Amps to 12Amps (up to 3 H.P.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each motor starter1

1.0000

each

9000.00

9000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 9230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9414.60 10356.06

VAT

6% of Total

690.40

IT

4% of Total

460.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11506.73

Page: 2546 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.3.2

Detailed Analysis Brief Description of Item 2 12 Amps to 17Amps (up to 5 H.P.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each motor starter2

1.0000

each

11000.00

11000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 11230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11454.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12600.06

VAT

6% of Total

840.00

IT

4% of Total

560.00 Total:

8.12.3.3

17 Amps to 32Amps (up to 7.5 H.P.)

each motor starter3

1.0000

each

14000.00

14000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 14230.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14514.60

10% Profit ( Add 10% on Subtotal-B) :

15966.06

VAT

6% of Total

IT

4% of Total

1064.40 709.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14000.07

17740.07

Page: 2547 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.3.4

Detailed Analysis Brief Description of Item 2 More than 32 Amps to 50Amps (up to 15 H.P.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each motor starter4

1.0000

each

16000.00

16000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 16230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16554.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18210.06

VAT

6% of Total

1214.00

IT

4% of Total

809.34 Total:

8.12.4

20233.40

Submersible pump: Supplying, assembling, fitting, fixing, installation (with effictive connection), testing & Commissioning of following capacity multistage sub-mersible water pump motor set manufactured according to DIN/NEMA/IEC/BS/VDE/JIS & ISO 9001 standard comprising of single stage 2900 RPM sub-mersible motor having Insulation: Class F & protection : IP68 (minimum) suitable for operation at three/ single phase 400/230V, 50Hz AC Supply with 18.29 meter (60') column pipe (API-5L, grade B) with flange gasket, non-return valve, pressure gauge, 40meter (131'-0") long required marine cable in a single length etc. complete in all respect manufactured by CE certified/ UL listed countries as per sample approved by Engineer in charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2548 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.4.1

Detailed Analysis Brief Description of Item 2 Motor set. 1.0 H.P, Discharge: 10-60 liter/min Head: 88-26 meter. Suction & delivery : 100mmx31.25mm Column Pipe: 32.25 mm, Brand : Pedrollow/Saer, Italy

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1 hp submercibal

1.0000

each

34000.00

34000.00

18.3000

m

457.42

8370.79

Nails/ Nut bolts/ Screw/ Spikes

2.0000

kg

65.00

130.00

Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.0000

day

470.00

940.00

50mm dia GI pipe of 2.9mm wall thick

44800.79

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

45696.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

50266.48

VAT

6% of Total

3351.10

IT

4% of Total

2234.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

55851.65

Page: 2549 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.4.2

Detailed Analysis Brief Description of Item 2 Motor set. 2.0 H.P, Discharge: 40-200 liter/min Head: 58-21 meter. Suction & delivery : 50mmx50mm Column Pipe: 50 mm, Brand : Pedrollow/Saer, Italy

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

2 hp submercibal

1.0000

each

40000.00

40000.00

18.3000

m

457.42

8370.79

Nails/ Nut bolts/ Screw/ Spikes

2.0000

kg

65.00

130.00

Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.0000

day

470.00

940.00

50mm dia GI pipe of 2.9mm wall thick

50800.79

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

51816.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

56998.48

VAT

6% of Total

3799.90

IT

4% of Total

2533.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

63331.65

Page: 2550 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.4.3

Detailed Analysis Brief Description of Item 2 Motor set. 3.0 H.P, Discharge: 40-200 liter/min Head: 85-30 meter. Suction & delivery : 50mmx50mm Column Pipe:50 mm, Brand : Pedrollow/Saer, Italy

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

3 hp submercibal

1.0000

each

45000.00

45000.00

18.3000

m

457.42

8370.79

Nails/ Nut bolts/ Screw/ Spikes

2.0000

kg

65.00

130.00

Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

2.0000

day

470.00

940.00

50mm dia GI pipe of 2.9mm wall thick

55800.79

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56916.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

62608.48

VAT

6% of Total

4173.90

IT

4% of Total

2782.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

69564.98

Page: 2551 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 8.12.4.4

2 Motor: 4 H.P. Discharge: 2200 – 4000 IGPH Head: 40 - 18 meter Column pipe: 50.00 mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

submersible pump4

1.0000

each

152000.00

152000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 152230.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

155274.60

10% Profit ( Add 10% on Subtotal-B) :

170802.06

VAT

6% of Total

IT

4% of Total

11386.80 7591.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

189780.07

Page: 2552 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.4.5

Detailed Analysis Brief Description of Item 2 Motor : 5.5 H.P Suction X Delivery: 50mm X50mm Discharge : 50-375 liter/min. Head :77-19 meter Column pipe : 50 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

submersible pump5

1.0000

each

180000.00

180000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 180230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

183834.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

202218.06

VAT

6% of Total

13481.20

IT

4% of Total

8987.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

224686.73

Page: 2553 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.4.6

Detailed Analysis Brief Description of Item 2 Motor : 6 H.P. Suction X Delivery: 50mm X50mm Discharge : 2200-4500 IGPH Head: 60 - 30 meter Column pipe: 50.00 mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

submersible pump6

1.0000

each

175550.00

175550.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 175780.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

179295.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

197225.16

VAT

6% of Total

13148.34

IT

4% of Total

8765.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

219139.07

Page: 2554 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.4.7

Detailed Analysis Brief Description of Item 2 Motor : 7.5 H.P Suction X Delivery: 50mm X50mm Discharge : 40-200 liter/min. Head : 200-72 meter Column pipe: 50 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

submersible pump7

1.0000

each

193000.00

193000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 193230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

197094.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

216804.06

VAT

6% of Total

14453.60

IT

4% of Total

9635.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

240893.40

Page: 2555 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.4.8

Detailed Analysis Brief Description of Item 2 Motor:7.5 H.P Suction X Delivery: 80mm X80mm Discharge: 2500 - 10000 IGPH Head: 44 - 26 meter column pipe: 80 mm dia

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

submersible pump8

1.0000

each

216000.00

216000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 216230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

220554.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

242610.06

VAT

6% of Total

16174.00

IT

4% of Total

10782.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

269566.73

Page: 2556 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.4.9

Detailed Analysis Brief Description of Item 2 Motor : 10 H.P Suction X Delivery: 80mm X80mm Discharge : 100-600 liter/min. Head : 92-31 meter Column pipe: 80 mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

submersible pump9

1.0000

each

323500.00

323500.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 323730.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

330204.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

363225.06

VAT

6% of Total

24215.00

IT

4% of Total

16143.34 Total:

8.12.5

403583.40

Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of metal clad surface mounting type single phase 220± 5%/400v Volt 50 Hz. ( DOL ) motor (Push switch ON-OFF type) of the following range of rated current including supply of required fixing materials(Foreign made) as per direction of the Engineers

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2557 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.5.1

Detailed Analysis Brief Description of Item 2 4 Amps to 17Amps (up to 5 H.P.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each motor starter5

1.0000

each

1440.00

1440.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 1670.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1703.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1873.74

VAT

6% of Total

124.92

IT

4% of Total

83.28 Total:

8.12.6

2081.93

Supplying fitting and fixing 3 phase starter for Electric motor etc. all complete as per direction, (MEM of England or any equivalent prior approved quality) of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2558 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.12.6.1

2 7 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 7 amps 3 phase starter for motor

1.0000

each

1085.00

1085.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 1200.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

12.00

Subtotal-A1:

1212.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1236.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1359.86

VAT

6% of Total

IT

4% of Total

90.66 60.44 Total:

8.12.6.2

15 amps

each 15amps 3 phase starter for motor

1.0000

each

1160.00

1160.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 1275.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

12.75

Subtotal-A1: Subtotal-B: Subtotal-C:

1287.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1313.51

10% Profit ( Add 10% on Subtotal-B) :

1444.86

VAT

6% of Total

IT

4% of Total

96.32 64.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1510.96

1605.40

Page: 2559 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 8.12.6.3

2 30 amps

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 30amps 3 phase starter for motor

1.0000

each

1230.00

1230.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 1345.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

13.45

Subtotal-A1:

8.12.6.4

50 amps

1358.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1385.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1524.18

VAT

6% of Total

IT

4% of Total

101.61 67.74 Total:

1693.53

each 50amps 3 phase starter for motor

1.0000

each

14500.00

14500.00

Plumber/ Electric Mistry/ Painter

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.1000

day

470.00

47.00 14615.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14907.30

10% Profit ( Add 10% on Subtotal-B) :

16398.03

VAT

6% of Total

IT

4% of Total

1093.20 728.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18220.03

Page: 2560 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 8.12.7

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Surge Protection Device/Surge Arrestor (SPD) for Low voltage distribution system against transient over voltage as per following specificationResponding time (rate of voltage rise 5 kv/µs) <25 ns Voltage protection level at 5 kA :1000V Maximum continuous operating voltage :280V AC Open Circuit Voltage : 10 kV Nominal discharge current : 20 kA Maximum discharge current : 40 kA Brand : ABB/Eaton/Hager/Legrand or equivalent. Origin : EU/USA

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Surge protection device

1.0000

each

45000.00

45000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 45230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

46134.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

50748.06

VAT

6% of Total

IT

4% of Total

3383.20 2255.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

56386.73

Page: 2561 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Chapter - 9 : Termite Treatment Works 9.01

Supplying anti termite chemicals such as Heptachlor-40 WP or equivalent Govt. registered approved chemicals and mixing the same with pure water in required proportion (For-Heptachlor-40 WP-1 Kg. of Heptachlor powder in 79 litres of pure water and for other chemicals, mixed according to manufacturer’s specification) and spraying the emulsified mixture @5 litres per square metre of soil surface by hand spray or by any other means to the sides and bottom of the foundation trench and over plinth filling or floor bed etc. all complete as per direction of the E-I-C.

sqm

Heptachlor - 40 WP

0.0600

kg

116.64

7.00

Termite Technician

0.0030

day

680.00

2.04

Skilled Labour

0.0150

day

450.00

6.75 15.79

Subtotal-A: All other remaining costs

( +.26 % on Subtotal-A )

0.04

Subtotal-A1: Subtotal-B: Subtotal-C:

15.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16.15

10% Profit ( Add 10% on Subtotal-B) :

17.76

VAT

6% of Total

IT

4% of Total

1.18 0.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

19.73

Page: 2562 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.02

Detailed Analysis Brief Description of Item 2 Extra cost for supplying anti termite chemicals and mixing the same with pure water as per specification in item No. 9.1 and using the same emulsified water as mixing water in Cement Sand mortar of 1st class brick works (1:6) in foundation & upto plinth etc. all complete as per direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Heptachlor - 40 WP

0.4400

kg

116.64

51.32

Termite Technician

0.0400

day

680.00

27.20

Skilled Labour

0.1800

day

450.00

81.00 159.52

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.60

Subtotal-A1: Subtotal-B: Subtotal-C:

161.12 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

164.34

10% Profit ( Add 10% on Subtotal-B) :

180.77

VAT

6% of Total

IT

4% of Total

12.05 8.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

200.86

Page: 2563 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.03

Detailed Analysis Brief Description of Item 2 Supplying anti termite chemicals and mixing the same with pure water as per specification in item No. 9.1 and spraying the emulsified mixture over both outside and inside back fill in foundation trenches @15 litres per sq. m. of the vertical surface area of the foundation wall etc. all complete as per direction of the E-I-C. (The maximum depth of the back fill to be treated is 500mm and the measurement for depth should not be given more than 500mm).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Heptachlor - 40 WP

0.1900

kg

116.64

22.16

Termite Technician

0.0025

day

680.00

1.70

Skilled Labour

0.0200

day

450.00

9.00 32.86

Subtotal-A: All other remaining costs

( +.25 % on Subtotal-A )

0.08

Subtotal-A1: Subtotal-B: Subtotal-C:

32.94 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

33.60

10% Profit ( Add 10% on Subtotal-B) :

36.96

VAT

6% of Total

2.46

IT

4% of Total

1.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

41.07

Page: 2564 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.04

Detailed Analysis Brief Description of Item 2 Anti-termite treatment in existing structures by making holes at a required depth of 225mm from the existing finished FL/GL inside and outside the building and applying anti termite chemicals, such as Heptachlor 40 WP or Dursbane 20 EC or Pyrifox 20 EC or equivalent Govt. registered approved chemicals into the holes preparing chemical solution mix with water at the ratio of chemical: water 1:40 maintaining a dosage rate of 25 ml per hole including supplying all materials and making and repairing the holes etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

per hole

Anti-termite chemical (Heptachlor -40WP or Dursbane ZOEC or Pyrifox ZOEC)

0.0125

liter

572.63

7.16

Termite Technician

0.0025

day

680.00

1.70

Skilled Labour

0.0200

day

450.00

9.00

Ordinary Labour

0.0700

day

370.00

25.90 43.76

Subtotal-A: All other remaining costs

( +1.50 % on Subtotal-A )

0.66

Subtotal-A1: Subtotal-B: Subtotal-C:

44.41 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

45.30

10% Profit ( Add 10% on Subtotal-B) :

49.83

VAT

6% of Total

3.32

IT

4% of Total

2.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

55.37

Page: 2565 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.05

Detailed Analysis Brief Description of Item 2 Trench treatment for protection against incoming termites to the establishment through underground by making trench around existing building/structures at a required depth of 0.76m from existing level supplying anti termite chemicals such as Heptachlor 40 WP or Pyrifox 20 EC or Dursbane 20 EC or Dieldrin or equivalent Govt. registered approved chemicals preparing solution mix with water at the ratio of chemical: water 1:40, applying the solution into trench with the help of a chemical sprayer in three layers and phases including earth filling in trench etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Dieldrin

0.1720

ml

0.86

Termite Technician

0.0082

day

680.00

5.58

Skilled Labour

0.0700

day

450.00

31.50

Ordinary Labour

0.1700

day

370.00

62.90 100.12

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.00

Subtotal-A1:

101.13

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

103.15

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

113.46

VAT

6% of Total

7.56

IT

4% of Total

5.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

0.15

126.07

Page: 2566 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.06

Detailed Analysis Brief Description of Item 2 Fumigation treatment (Pest Control) against mosquitoes, flies, bees, cockroaches, spiders, silver fishes, lizards and other common pests and insects in wooden walls, brick walls, floors, doors and windows, furniture fanlight, carpets, records, curtains, electrical conduits etc. with the application of fumigants such as DDVP-100 EC, or DENCAVAPON100 EC, or NEOCIDOL-60 EC or similar chemically equivalent govt. registered pest control products, preparing chemical solution mix with water at the ratio of chemical: water 1:100 applying with the help of electrically operated jet fogging machine, swing fog, Dina fog, pneumatic hand sprayer, knap sak hand sprayer at air tight position etc. all complete as per direction of the E-I-C. After fumigation the surface will remain at air tight position at least for 3 (three) hours (Volume of the room will be considered towards measurement).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Fumigant

7.0700

ml

1.13

7.99

Termite Technician

0.0002

day

680.00

0.14

Skilled Labour

0.0007

day

450.00

0.32 8.44

Subtotal-A: All other remaining costs

( +4.00 % on Subtotal-A )

0.34

Subtotal-A1:

8.78

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9.85

VAT

6% of Total

0.66

IT

4% of Total

0.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10.94

Page: 2567 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.07.01

Detailed Analysis Brief Description of Item 2 Treatment of all wooden door frames, window frames, wood paneling etc. by using TIMBERIN (an oil-based wood treatment formulation suitable for wood, plywood, partex, hard board etc.) on both surfaces by brush-on-method etc. all complete as per direction of the E-I-C..

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

sqm

Timberin (1 bottle of 500 ml)

0.1100

bottle

540.00

Brush

0.0350

each

35.64

1.25

Ordinary Labour

0.0350

day

370.00

12.95 73.60

Subtotal-A: All other remaining costs like scaffolding etc.

( +8.00 % on Subtotal-A )

5.89

Subtotal-A1:

79.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

81.07

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

89.18

VAT

6% of Total

IT

4% of Total

5.95 3.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

59.40

99.09

Page: 2568 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.07.02

Detailed Analysis Brief Description of Item 2 Treatment of wooden fittings irrespective of infestation status, all wooden fittings like door/window frames, wall cabinets etc. to be treated by injecting 100 ml Dursban/pyrifos, 4% solution of ZOEC formulation per drill hole in between walls and frames etc. all complete as per direction of the E-I-C. Each door/window/cabinet will require 10 Nos. drill hole treatment. If the door/window is proportionately larger no drill hole treatment may be required. Drill bit to be used is 5mm dia and hole to be made should have a depth of 75mm to 100mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

per hole

Anti-termite chemical (Heptachlor -40WP or Dursbane ZOEC or Pyrifox ZOEC)

0.2500

liter

572.63

143.16

Ordinary Labour

0.0800

day

370.00

29.60 172.76

Subtotal-A: All other remaining costs

( +.10 % on Subtotal-A )

0.17

Subtotal-A1: Subtotal-B: Subtotal-C:

172.93 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

176.39

10% Profit ( Add 10% on Subtotal-B) :

194.03

VAT

6% of Total

IT

4% of Total

12.94 8.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

215.59

Page: 2569 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.08

Detailed Analysis Brief Description of Item 2 Treatment of electric system by inserting a plucking materials (cotton, foam etc.) soaked in oil based anti-termite chemical TIMDERIN to a electric switch board point for all floors etc. all complete as per direction of the E-I-C..

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

per swch board Timberin (1 bottle of 500 ml)

0.2000

bottle

540.00

108.00

Ordinary Labour

0.6200

day

370.00

229.40 337.40

Subtotal-A: All other remaining costs like plucking materials, etc.

( +9.00 % on Subtotal-A )

30.37

Subtotal-A1:

367.77

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

375.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

412.63

VAT

6% of Total

IT

4% of Total

27.51 18.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

458.48

Page: 2570 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.09

Detailed Analysis Brief Description of Item 2 Treatment of infested walls of old building (generally the thickness of wall 375mm to above) by using chemical (1:40) Dursban ZOEC/pyrifos ZOEC solution, including drilling holes in walls (15mmx150mm) with heavy-duty drilling machine, making and applying the solution to holes as per direction etc. all complete for all floors as per direction of the E-IC.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

sqm

Anti-termite chemical (Heptachlor -40WP or Dursbane ZOEC or Pyrifox ZOEC)

1.0800

liter

572.63

618.44

Ordinary Labour

0.1800

day

370.00

66.60 685.04

Subtotal-A: All other remaining costs like hire charge of drill machine, repair of drill hole, etc.

( +16.00 % on Subtotal-A )

Subtotal-A1:

794.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

810.54

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

891.59

VAT

6% of Total

59.44

IT

4% of Total

39.63 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

109.61

990.66

Page: 2571 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.10

Detailed Analysis Brief Description of Item 2 Destruction of termite nest around an infested building, tree stumps in lawn with the treatment of Heptachlor by excavation soil in affected area upto a depth of 1.5 metre, mixing the Heptachlor with the soil and laying the same in same place etc. all complete as per direction of the EI-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

per nest

Heptachlor - 40 WP

0.7900

kg

116.64

92.15

Termite Technician

0.5000

day

680.00

340.00

Ordinary Labour

1.0700

day

370.00

395.90 828.05

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

8.28

Subtotal-A1: Subtotal-B: Subtotal-C:

836.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

853.05

10% Profit ( Add 10% on Subtotal-B) :

938.36

VAT

6% of Total

IT

4% of Total

62.56 41.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1042.62

Page: 2572 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 9.11

Detailed Analysis Brief Description of Item 2 Chemical for Anti-termite treatment : Supplying and applying specified type of chemicals such as Pestearthy or equivalent best quality, confirming the current chemical specification requirements like physical properties, uniformity & equivalence in composition etc. for treatment of Anti-termite inside (Floor) of building & outside (Barrier) of building : a. Inside (Floor) of building : At first fill the floor with sand and soil. Then spread Pestearthy equally on the surface of the floor. 1 kg Pestearthy spread 300 sft of coverage area. B.Outside (Barrier) of building : Dig the canal in the soil outside and attached to the external wall and make a surrounding canal of 600mm wide and 600mm deep. Spread Pestaerthy equally on the bottom layer of the canal. Fill up half of the canal with soil or sand. Then spread Pestearthy as 2nd layer the half-filled canal by the same way.After that fill up the 3/4 of the canal with soil or sand and spread Pestearthy as 3rd or final layer on the surface and fill the rest part of the canal with sand, soil, cement concrete etc. Pestearthy 1 kg spread surrounding canal of 3 layers by 12.20m or doges mentioned in the manufacturer's brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. All complete as per direction of the E-I-C. A. Inside (Floor) of building : At first fill the floor with sand and soil. Then spread Pestearthy equally on the surface of the floor. 1 kg Pestearthy spread 30 sqm of coverage area. B.Outside (Barrier) of building : Dig the canal in the soil outside and attached to the external wall and make a surrounding canal of 600mm wide and 600mm deep. Spread Pestaerthy equally on the bottom layer of the canal. Fill up half of the canal with soil or sand. Then spread Pestearthy as 2nd layer the half-filled canal by the same way. After that fill up the 3/4 of the canal with soil or sand and spread Pestearthy as 3rd or final layer on the surface and fill the rest part of the canal with sand, soil, cement concrete etc. Pestearthy 1 kg spread surrounding canal of 3 layers by 12.20m or doges mentioned in the manufacturer's brochures and strictly following the recommendation and instruction, providing safety provision in all respect etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

5

Unit

Rate

6

7

Amount 8

sqm

Anti-termite treatment Chemicals Pestearthy

1.0000

kg

1670.00

1670.00

Skilled Labour

0.0100

day

450.00

4.50

Subtotal-A: Note : Rates of all items should be inclusive of all supply and carriage.

Quantity

1674.50 Page: 2573 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1707.99

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1878.79

VAT

6% of Total

IT

4% of Total

125.25 83.50 Total:

2087.54

Chapter - 10 : Tube Well Works 10.01

Mobilization of materials, equipment, tools and plants, boring rig at the work site, assembling of derrick and dismantling the same, cleaning the site on completion of work, etc. all complete as per direction of the E-I-C

10.02

Boring by using 100mm dia cutter and 38mm dia GI Pipe and other equipment capable of drilling up to a depth of 500m by water jet system through all sorts of strata, protection of caving by supplying necessary casing pipe, collection of soil samples at every 3m interval and at every change of strata and preserve them for analysis, withdrawal of boring pipes & casing pipes etc. all complete as per specification and direction of the E-I-C.

10.02.01

From 0.0m to 50m = 50m

LS

m Cost of boring (100mm dia) including all equipment ,accessories, materials, labour etc,

1.0000

m

100.00

100.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102.00

10% Profit ( Add 10% on Subtotal-B) :

112.20

VAT

6% of Total

7.48

IT

4% of Total

4.99 Total:

10.02.02

From 50m to 100m = 50m

m

Add +10.00% with Item No 10.02.01

10.02.03

From 100m to 152m = 52m

m

Add +21.00% with Item No 10.02.01

Note : Rates of all items should be inclusive of all supply and carriage.

100.00

124.67

Page: 2574 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

10.02.04

From 152m to 200m = 48m

m

Add +33.00% with Item No 10.02.01

10.02.05

From 200m to 250m = 50m

m

Add +46.00% with Item No 10.02.01

10.02.06

Beyond 250m

m

Add +60.00% with Item No 10.02.01

10.03

Supplying and lowering 38mm dia water grade PVC pipe having wall thickness 2.5m to 3.0mm (‘D’ Class Aziz pipe/equivalent), PVC sand trap of length 3.0m with cap, PVC strainer of desired slot installing at the middle of the most suitable water bearing strata. 38mm dia GI pipe of best quality of length 1.52m with MS welded flat bar on each side to prevent from rotation up to the desired depth, fitting fixing the hand pump No. 6 etc. including the cost of solvent cement, socket adapter, filling medium sand up to 18.0m above strainer and the remaining portion with available soil from boring etc. all complete as per standard specification and direction of the E-I-C

10.03.01

Hand pump No. 6 complete set (EPL/RFL) (Medium)/equivalent brand)

Quantity 5

Unit

Rate

6

7

Amount 8

each Hand pump (no 6) complete set (best quality)

1.0000

set

2285.00

2285.00

Skilled Labour

0.5700

day

450.00

256.50 2541.50

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2592.33

10% Profit ( Add 10% on Subtotal-B) :

2851.56

VAT

6% of Total

IT

4% of Total

190.10 126.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3168.40

Page: 2575 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.03.02

Detailed Analysis Brief Description of Item 2 38mm dia GI pipe 2.9mm thick (National Tubes/equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

459.20

459.20

m 2.9mm thick 38mm dia GI pipe

1.0000

459.20

Subtotal-A: Labour other remaining costs

( +14.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

523.49 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

533.96

10% Profit ( Add 10% on Subtotal-B) :

587.35

VAT

6% of Total

IT

4% of Total

39.16 26.10 Total:

10.03.03

38mm dia water graded PVC pipe having thickness 2.5-3.00mm (‘D’ class Aziz brand/equivalent) pipe sand trap

652.62

m 2.5- 3mm thick 40mm dia water graded PVC pipe ('D' Class)

1.0000

m

78.72

Labour other remaining costs

( +20.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

78.72 78.72

Subtotal-A:

15.74 94.46 96.35

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

105.99

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

7.07

IT

4% of Total

4.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

64.29

117.77

Page: 2576 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.03.04

2 38mm dia water graded PVC strainer having thickness 2.5 – 3.0mm (‘D’ class Aziz brand/equivalent) of recommended slot size

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2.5 -3mm thick 40mm dia water graded PVC strainer ('D' Class)

1.0000

m

78.72

78.72

Subtotal-A: Labour other remaining costs

( +19.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

38mm dia socket adapter

95.55

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

105.11

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7.01 4.67 116.78

each 40mm dia socket adapter

1.0000

each

11.00

Labour other remaining costs

( +21.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

11.00 11.00

Subtotal-A:

2.31 13.31

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13.58

10% Profit ( Add 10% on Subtotal-B) :

14.93

VAT

6% of Total

IT

4% of Total

1.00 0.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14.96 93.68

Total: 10.03.05

78.72

16.59

Page: 2577 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.03.06

2 Best quality 38mm dia PVC cap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 38mm dia PVC cap (best quality)

1.0000

each

44.00

44.00

Subtotal-A: Labour other remaining costs

( +10.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Filling the top 0.6metre of the bore hole around the top pipe with sanitary seal of concrete (1:2:4), etc. all complete as per specifications and direction of the E-I-C.

10.05

Complete development of the tube well to obtain sand & turbidity free water at a satisfactory yield, etc. all complete as per specifications and direction of the E-I-C.

10.05.01

For wells up to 200m depth

LS

10.05.02

For wells beyond 200m depth

LS

10.06

Furnishing design of the production well by testing of water and soil samples collected from the observation well in/c. test for ‘Arsenic’ etc. all complete as per direction of the E-I-C. (excluding the cost of actual fees for testing which will be paid to the contractor separately by the department).

LS

10.07

Disinfecting the well by using minimum 1kg of bleaching powder or any other disinfectant etc. all complete as per standard specifications and direction of the E-I-C.

LS

Note : Rates of all items should be inclusive of all supply and carriage.

4.40 48.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

49.37

10% Profit ( Add 10% on Subtotal-B) :

54.30

VAT

6% of Total

IT

4% of Total

3.62 2.41 Total:

10.04

44.00

60.34

LS

Page: 2578 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

10.09

Preparation for installation of tube well and transportation of complete boring equipment, labours, materials to the work site and returned the materials on completion of works. Installation of drilling rig and accessories, making arrangements for electricity, water, labour shed, site office and stores, digging mud pit etc. leveling, dressing and clearing of the site as per original condition etc. all complete as per specifications and directions of the E-I-C.

10.09.01

For Tube wells up to 100 m depth

LS

10.09.02

For Tube wells up to 200 m depth

LS

10.09.03

For Tube wells beyond 200 m depth

LS

10.10

Execution of boring through all sorts of strata reserve circulation or any other approved method (Method other than reserve circulation is to be applied only for wells deeper than 152 m) for boring 325mm dia vertical hole up to designed depth and collection of soil samples at every 3m interval and at every change of formation including sinking and withdrawing necessary casing pipe and all necessary arrangements, etc. all complete as per specifications and direction of the E-I-C. (Measurement will be allowed from G.L. to bottom of the blank pipe and the rate is inclusive of the cost of extra depth of boring required for caving and siltation).

10.10.01

From 0.0m to 50m = 50m

Quantity 5

Unit

Rate

Amount

6

7

8

m

450.00

450.00

m Cost of boring (325m dia boring) including all equipment, accessories, materials, labour etc.

1.0000

450.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

459.00

10% Profit ( Add 10% on Subtotal-B) :

504.90

VAT

6% of Total

IT

4% of Total

33.66 22.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

561.00

Page: 2579 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

10.10.02

From 50m to 100m = 50m

m

Add +15.00% with Item No 10.10.01

10.10.03

From 100m to 152m = 52m

m

Add +32.00% with Item No 10.10.01

10.10.04

From 152m to 200m = 48m

m

Add +52.00% with Item No 10.10.01

10.10.05

From 200m to 250m = 50m

m

Add +75.00% with Item No 10.10.01

10.10.06

Beyond 250m

m

Add +101.00% with Item No 10.10.01

10.11

Supplying tube well fixtures at working site as per standard practice etc. all complete as per specifications and direction of the E-I-C.

10.11.01

Best quality 50mm dia PVC cap

Quantity 5

Unit

Rate

Amount

6

7

8

115.00

115.00

each 50mm dia PVC cap (best quality)

1.0000

each

115.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.15

Subtotal-A1: Subtotal-B: Subtotal-C:

116.15 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

118.47

10% Profit ( Add 10% on Subtotal-B) :

130.32

VAT

6% of Total

IT

4% of Total

8.69 5.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

144.80

Page: 2580 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.11.02

Detailed Analysis Brief Description of Item 2 50mm dia water grade PVC blank pipe/ sand trap having wall thickness 2.5mm to 3.0mm (‘C’ class Aziz/ equivalent Brand)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

173.78

173.78

m 2.5 - 3mm thick 50mm dia water graded PVC blank pipe ('C' Class)

1.0000

173.78

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.74

Subtotal-A1:

175.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

179.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

196.93

VAT

6% of Total

IT

4% of Total

13.13 8.75 Total:

10.11.03

50mm dia strainer of any slot as per design made with grade PVC pipe having wall thickness 2.5mm to 3mm (‘C’ class Aziz/equivalent brand).

m 2.5 -3mm thick 50mm dia PVC strainer ('C' Class)

1.0000

m

134.04

134.04 134.04

Subtotal-A: Making slots & other costs

( +39.00 % on Subtotal-A )

Subtotal-A1:

52.28 186.32

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

190.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

209.05

VAT

6% of Total

13.94

IT

4% of Total

9.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

218.81

232.27

Page: 2581 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.11.04

Detailed Analysis Brief Description of Item 2 50mm dia water grade PVC Blind pipe/ well pipe having wall thickness 2.5mm to 3mm (‘C’ class Aziz/ equivalent brand).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

173.78

173.78

m 2.5 -3mm thick 50mm dia PVC blind/well pipe ('C' Class)

1.0000

173.78

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.74

Subtotal-A1:

175.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

179.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

196.93

VAT

6% of Total

13.13

IT

4% of Total

8.75 Total:

10.11.05

Best quality 50mmx125mm PVC Reducer

each 50x125mm PVC reducer (best quality)

1.0000

each

130.00

All other remaining costs

( +2.50 % on Subtotal-A )

3.25

Subtotal-A1: Subtotal-B: Subtotal-C:

130.00 130.00

Subtotal-A:

133.25 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

135.92

10% Profit ( Add 10% on Subtotal-B) :

149.51

VAT

6% of Total

IT

4% of Total

9.97 6.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

218.81

166.12

Page: 2582 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

10.11.06

125mm dia water grade PVC Housing pipe having wall thickness of 5.5mm to 6.4mm (‘C’ class Aziz/equivalent Brand).

m 5.5 - 6.4mm thick 125mm dia PVC pipe ('C' Class)

Quantity 5

1.0000

Unit

Rate

Amount

6

7

8

m

643.33

643.33 643.33

Subtotal-A: All other remaining costs

( +2.50 % on Subtotal-A )

16.08

Subtotal-A1:

659.41

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

672.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

739.86

VAT

6% of Total

49.32

IT

4% of Total

32.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

822.07

Page: 2583 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.12

Detailed Analysis Brief Description of Item 2 Complete installation of 50mm dia PVC tube well fixtures such as expanded top pipes, reducer, tube well pipes, strainer, blind pipe, pipe cap etc. fitting and fixing with best quality PVC solution, iron screws and PVC tape and placing in position with proper size bamboo split centralizer @3m c/c in strainer portion in/c. blank pipe etc. all complete as per standard practice, specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

PVC tape

0.0200

each

15.00

0.30

PVC solution gum

0.0200

each

500.00

10.00

Borak Bamboo (75mm dia)

0.0300

m

38.00

1.14

Foreman

0.0100

day

800.00

8.00

Foreman helper

0.0400

day

350.00

14.00

Skilled Labour

0.0400

day

450.00

18.00 51.44

Subtotal-A: All other remaining costs like bamboo split, iron screws, etc.

( +17.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

60.18 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61.39

10% Profit ( Add 10% on Subtotal-B) :

67.53

VAT

6% of Total

IT

4% of Total

4.50 3.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8.74

75.03

Page: 2584 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.13

2 Preparation and making gravel pack around the tube well fixtures with supply of designed graded pea gravel (passing through 10 mesh and retained on 40 mesh) including screening, washing etc. all complete as per standard specifications and direction of the E-I-C. (The rate is inclusive of the cost of extra amount required for caving and extra depth below the tube well fixtures. Shrouding should not be more than 15m above the strainer and measurement should be allowed from bottom of the tube well fixture to top of the gravel pack).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (6mm down graded) [LAA≤30]

1.2000

m3

3800.00

4560.00

Skilled Labour

0.3600

day

450.00

162.00

Ordinary Labour

0.3600

day

370.00

133.20 4855.20

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

97.10

Subtotal-A1:

4952.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5051.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5556.49

VAT

6% of Total

IT

4% of Total

370.43 246.95 Total:

10.14

Complete development of the tube well by air compressor and pump of suitable capacity by alternate surging and pumping or any specified method until satisfactory yield, sand free water and the turbidity condition is reached using necessary quantity of calgon and conducting step draw down test before and after the development, etc. all complete as per specifications and direction of the E-I-C (Development should be started within 24 hours on completion of shrouding).

10.14.01

Wells up to 200m depth

LS

10.14.02

Wells beyond 200m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

6173.87

Page: 2585 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.15

Detailed Analysis Brief Description of Item 2 Long term pumping test of the well by required capacity of turbine/submersible pump with supply of testing equipment and all materials for 72 hours including yield draw down and recovery test etc. all complete as per specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

104.00

hour

Foreman

0.1300

day

800.00

Skilled Labour

0.0900

day

450.00

40.50

H.C. of Water Pump

0.1250

day

500.00

62.50 207.00

Subtotal-A: Fuel & other costs

( +35.00 % on Subtotal-A )

Subtotal-A1:

279.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

285.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

313.54

VAT

6% of Total

IT

4% of Total

20.90 13.94 Total:

10.16

Disinfecting the well including supply of sufficient quantity of bleaching powder (33% strength), chlorinated water having 150ppm available free chlorine complete as per standard specification, etc. all complete as per specifications and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

72.45

348.38

LS

Page: 2586 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.17

Detailed Analysis Brief Description of Item 2 Filling the bore hole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawal of selected soil or local clay, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0400

day

450.00

18.00 26.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.26

Subtotal-A1: Subtotal-B: Subtotal-C:

26.26 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26.79

10% Profit ( Add 10% on Subtotal-B) :

29.46

VAT

6% of Total

IT

4% of Total

1.96 1.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

32.74

Page: 2587 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.18

Detailed Analysis Brief Description of Item 2 Making a sanitary seal up to a minimum depth of 6m from G.L. or as specified including the supply of approved quality of cement, sand, brick aggregate (10mm down graded) in proportion 1:1.5:3 etc. all complete as per standard specifications and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (10mm down graded)

0.9000

m3

3049.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7700

bag

430.00

3341.10

Head Mason

0.0600

day

650.00

39.00

Mason

0.2400

day

550.00

132.00

Skilled Labour

0.3500

day

450.00

157.50

Ordinary Labour

4.1000

day

370.00

1517.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8463.20

Subtotal-A: All other remaining costs like form work, etc.

( +8.00 % on Subtotal-A )

677.06

Subtotal-A1:

9140.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9323.06 10255.37 683.69 455.79

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2744.10

11394.85

Page: 2588 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.19

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing best quality 150mm dia 4mm thick MS pipe 1.0m long one end blocked with 200mm dia 4mm thick MS plate and other end minimum 300mm embedded in sanitary seal for protection of PVC Housing Pipe, etc. all complete as per standard specification and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

4mm thick 150mm dia MS pipe-5mm thick

1.0000

m

2624.00

2624.00

4mm thick 200mm dia MS plate

1.0000

each

325.00

325.00 2949.00

Subtotal-A: All other remaining costs like welding, etc.

( +8.00 % on Subtotal-A )

235.92

Subtotal-A1:

3184.92

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3248.62

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3573.48

VAT

6% of Total

238.23

IT

4% of Total

158.82 Total:

10.20

Preparation for installation of tube well and transportation of complete boring equipment, labours and materials to the work site and returned the materials on completion of works. Installation of drilling rig and accessories, making arrangements for electricity, water, labour shed, site office and stores, digging mud pit etc. leveling, dressing and clearing the site as to the original condition etc. all complete as per specifications and direction of the E-I-C.

10.20.01

For Tube wells up to 100 m depth

LS

10.20.02

For Tube wells up to 200 m depth

LS

10.20.03

For Tube wells beyond 200 m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

3970.53

Page: 2589 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

10.21

Execution of boring through all sorts of strata reserve circulation or any other approved method (Method other than reserve circulation is to be applied only for wells deeper than 152m) for boring 350mm dia vertical hole up to designed depth and collection of soil samples at every 3m interval and at every change of formation including sinking and withdrawing necessary casing pipe and all necessary arrangements, etc. all complete as per specifications and direction of the E-I-C. (Measurement will be allowed from G.L. to bottom of the blank pipe and the rate is inclusive of the cost of extra depth of boring required for caving and siltation.)

10.21.01

From 0.0m to 50m = 50m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

500.00

500.00

m Cost of boring (350m dia boring) including all equipment, accessories, labour etc.

1.0000

500.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

510.00

10% Profit ( Add 10% on Subtotal-B) :

561.00

VAT

6% of Total

IT

4% of Total

37.40 24.93 Total:

10.21.02

From 50m to 100m = 50m

m

Add +15.00% with Item No 10.21.01

10.21.03

From 100m to 152m = 52m

m

Add +32.00% with Item No 10.21.01

10.21.04

From 152m to 200m = 48m

m

Add +52.00% with Item No 10.21.01

10.21.05

From 200m to 250m = 50m

m

Add +75.00% with Item No 10.21.01

10.21.06

Beyond 250m

m

Add +101.00% with Item No 10.21.01

10.22

Supplying tube well fixtures at working site, etc. all complete as per standard practice, specifications and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

623.33

Page: 2590 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.22.01

2 Best quality 75mm dia PVC cap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

160.00

160.00

each 75mm dia PVC cap (best quality)

1.0000

each

160.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

1.60

Subtotal-A1: Subtotal-B: Subtotal-C:

161.60 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

164.83

10% Profit ( Add 10% on Subtotal-B) :

181.32

VAT

6% of Total

IT

4% of Total

12.09 8.06 Total:

10.22.02

75mm dia water grade PVC blank pipe/sand trap having wall thickness 3.5mm to 4.1mm (‘C’ class Aziz/ equivalent Brand)

m 3.5 - 4.1mm thick 75mm dia water graded PVC blank pipe ('C' Class)

1.0000

m

252.50

All other remaining costs

( +1.00 % on Subtotal-A )

2.53

Subtotal-A1: Subtotal-B: Subtotal-C:

252.50 252.50

Subtotal-A:

255.03 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

260.13

10% Profit ( Add 10% on Subtotal-B) :

286.14

VAT

6% of Total

IT

4% of Total

19.08 12.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

201.46

317.93

Page: 2591 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.22.03

Detailed Analysis Brief Description of Item 2 75mm dia strainer of any slot as per design made with grade PVC pipe having wall thickness 3.5mm to 4.1mm (‘C’ class Aziz/equivalent brand).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

252.50

252.50

m 3.5 - 4.1mm thick 75mm dia PVC strainer ('C' Class)

1.0000

252.50

Subtotal-A: Making slots & other costs

( +6.00 % on Subtotal-A )

15.15

Subtotal-A1:

267.65

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

273.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

300.30

VAT

6% of Total

20.02

IT

4% of Total

13.35 Total:

10.22.04

75mm dia water grade PVC Blind pipe/well pipe having wall thickness 3.5mm to 4.1mm (‘C’ class Aziz/ equivalent brand).

m 3.5 - 4.1mm thick 75mm dia PVC blind/well pipe ('C' Class)

1.0000

m

252.50

252.50 252.50

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.53

Subtotal-A1:

255.03

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

260.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

286.14

VAT

6% of Total

19.08

IT

4% of Total

12.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

333.67

317.93

Page: 2592 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.22.05

Detailed Analysis Brief Description of Item 2 Best quality 75mmx150mm dia PVC Reducer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

140.00

140.00

each 75x150mm PVC reducer (best quality)

1.0000

each

140.00

Subtotal-A: All other remaining costs

( +1.50 % on Subtotal-A )

2.10

Subtotal-A1: Subtotal-B: Subtotal-C:

142.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

144.94

10% Profit ( Add 10% on Subtotal-B) :

159.44

VAT

6% of Total

IT

4% of Total

10.63 7.09 Total:

10.22.06

150mm dia water grade PVC Housing pipe having wall thickness 6.6mm to 7.6mm (‘C’ class Aziz/equivalent Brand).

m 6.6 - 7.6mm thick 150mm dia PVC pipe ('C' Class)

1.0000

m

931.67

All other remaining costs

( +2.00 % on Subtotal-A )

18.63

Subtotal-A1: Subtotal-B: Subtotal-C:

931.67 931.67

Subtotal-A:

950.30 969.31

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1066.24

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

71.08

IT

4% of Total

47.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

177.15

1184.71

Page: 2593 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.23

Detailed Analysis Brief Description of Item 2 Complete installation of 75mm dia PVC tube well fixtures such as expanded top pipes, reducer, tube well pipes, strainer, blind pipe, pipe cap etc. fitting and fixing with best quality PVC solution, iron screws and PVC tape and placing in position with proper size bamboo split centralizer @3m c/c in strainer portion in/c. blank pipe etc. all complete as per standard practice, specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

PVC tape

0.0300

each

15.00

0.45

PVC solution gum

0.0300

each

500.00

15.00

Borak Bamboo (75mm dia)

0.0350

m

38.00

1.33

Foreman

0.0100

day

800.00

8.00

Foreman helper

0.0400

day

350.00

14.00

Skilled Labour

0.0400

day

450.00

18.00 56.78

Subtotal-A: All other remaining costs like bamboo split, screws, fuel etc.

( +18.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

67.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

68.34

10% Profit ( Add 10% on Subtotal-B) :

75.17

VAT

6% of Total

IT

4% of Total

5.01 3.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10.22

83.53

Page: 2594 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.24

2 Preparation and making gravel pack around the tube well fixtures and bore hole with supply of designed graded pea gravel (passing through 10 mesh and retained on 40 mesh) including screening, washing etc. all complete as per standard specifications and direction of the E-I-C. (The rate is inclusive of the cost of extra amount required for caving and extra depth below the well fixtures. Shrouding should not be more than 15m above the strainer and measurement should be allowed from bottom of the tube well fixture to top of the gravel pack).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (6mm down graded) [LAA≤30]

1.2000

m3

3800.00

4560.00

Skilled Labour

0.3600

day

450.00

162.00

Ordinary Labour

0.3600

day

370.00

133.20 4855.20

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

97.10

Subtotal-A1:

4952.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5051.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5556.49

VAT

6% of Total

IT

4% of Total

370.43 246.95 Total:

10.25

Complete development of the well by suitable air compressor and pump of suitable capacity by alternate surging and pumping until satisfactory yield, sand free water and the turbidity condition is reached using necessary quantity of calgon and conducting step draw down test before and after the development, etc. all complete as per specifications and direction of the Engineer-in- charge. (Development should be started within 24 hours of completion of shrouding).

10.25.01

Wells up to 200m depth

LS

10.25.02

Wells beyond 200m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

6173.87

Page: 2595 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.26

Detailed Analysis Brief Description of Item 2 Long term pumping test of the well by required capacity of turbine/submersible pump with supply of testing equipment and all materials for 72 hours including yield draw down and recovery test etc. all complete as per specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

104.00

hour

Foreman

0.1300

day

800.00

Skilled Labour

0.0900

day

450.00

40.50

H.C. of Water Pump

0.1250

day

500.00

62.50 207.00

Subtotal-A: Fuel & other costs

( +35.00 % on Subtotal-A )

Subtotal-A1:

279.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

285.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

313.54

VAT

6% of Total

IT

4% of Total

20.90 13.94 Total:

10.27

Disinfecting the well including supply of sufficient quantity of bleaching powder (33% strength) chlorinated water having 150 ppm available free chlorine, etc. all complete as per standard specifications and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

72.45

348.38

LS

Page: 2596 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.28

Detailed Analysis Brief Description of Item 2 Filling of the bore hole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawal of selected soil or local clay, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0500

day

450.00

22.50 30.50

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.31

Subtotal-A1: Subtotal-B: Subtotal-C:

30.81 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

31.42

10% Profit ( Add 10% on Subtotal-B) :

34.56

VAT

6% of Total

IT

4% of Total

2.30 1.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

38.40

Page: 2597 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.29

Detailed Analysis Brief Description of Item 2 Making a sanitary seal up to a minimum depth of 6m from G.L. or as specified including the supply of approved quality of cement, sand, khoa, (10mm down graded) in proportion 1:1.5:3 as per standard specification, etc. all complete as per direction of E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (10mm down graded)

0.9000

m3

3049.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7700

bag

430.00

3341.10

Head Mason

0.0600

day

650.00

39.00

Mason

0.2400

day

550.00

132.00

Skilled Labour

0.3500

day

450.00

157.50

Ordinary Labour

4.1000

day

370.00

1517.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8463.20

Subtotal-A: All other remaining costs like form work, etc.

( +8.00 % on Subtotal-A )

677.06

Subtotal-A1:

9140.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9323.06 10255.37 683.69 455.79

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2744.10

11394.85

Page: 2598 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.30

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing best quality 200mm dia 4mm thick MS pipe 1.0m long one end blocked with 250mm dia 4mm thick MS plate and other end minimum 300mm embedded in sanitary seal for protection of PVC Housing Pipe, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

5mm thick 200mm dia MS pipe-6.5mm thick

1.0000

m

3608.00

3608.00

5mm thick 250mm dia MS plate

1.0000

each

350.00

350.00 3958.00

Subtotal-A: Welding & other costs

( +9.00 % on Subtotal-A )

356.22

Subtotal-A1:

4314.22

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4400.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4840.55

VAT

6% of Total

322.70

IT

4% of Total

215.14 Total:

10.31

Preparation for installation of tube well and transportation of complete boring equipment, labours and materials to the work site and returned the materials on completion of works. Installation of drilling rig and accessories, making arrangements for electricity, water, labour shed, site office and stores, digging mud pit etc. leveling dressing and clearing the site to original condition etc. all complete as per specifications and directions of the E-I-C.

10.31.01

For Tube wells up to 100 m depth

LS

10.31.02

For Tube wells up to 200 m depth

LS

10.31.03

For Tube wells beyond 200 m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

5378.39

Page: 2599 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

10.32

Execution of boring through all sorts of strata reserve circulation or any other approved method (method other than reserve circulation is to be applied only for wells deeper than 152 m) for boring 400mm dia vertical hole up to designed depth and collection of soil samples at every 3m interval and at every change of formation including sinking and withdrawing necessary casing pipe and all necessary arrangements, etc. all complete as per specifications and direction of the E-I-C. (Measurement will be allowed from G.L. to bottom of the blank pipe and the rate is inclusive of the cost of extra depth of boring required for caving and siltation.

10.32.01

From 0.0m to 50m = 50m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

600.00

600.00

m Cost of boring (400mm dia) including all equipment, accessories, materials, labours etc.

1.0000

600.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

612.00

10% Profit ( Add 10% on Subtotal-B) :

673.20

VAT

6% of Total

IT

4% of Total

44.88 29.92 Total:

10.32.02

From 50m to 100m = 50m

m

Add +15.00% with Item No 10.32.01

10.32.03

From 100m to 152m = 52m

m

Add +32.00% with Item No 10.32.01

10.32.04

From 152m to 200m = 48m

m

Add +52.00% with Item No 10.32.01

10.32.05

From 200m to 250m = 50m

m

Add +75.00% with Item No 10.32.01

10.32.06

Beyond 250m

m

Add +101.00% with Item No 10.32.01

10.33

Supplying tube well fixtures at working site, etc. all complete as per standard practice and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

748.00

Page: 2600 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.33.01

Detailed Analysis Brief Description of Item 2 Best quality 100mm dia PVC cap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

200.00

200.00

each 100mm dia PVC cap (best quality)

1.0000

each

200.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

2.00

Subtotal-A1: Subtotal-B: Subtotal-C:

202.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

206.04

10% Profit ( Add 10% on Subtotal-B) :

226.64

VAT

6% of Total

IT

4% of Total

15.11 10.07 Total:

10.33.02

100mm dia water grade PVC blank pipe/sand trap having wall thickness 4.5mm to 5.2mm (‘C’ class Aziz/equivalent Brand)

m 4.5 -5.2mm thick 100mm dia water graded PVC blank pipe ('C' Class)

1.0000

m

403.33

All other remaining costs

( +1.00 % on Subtotal-A )

4.03

Subtotal-A1: Subtotal-B: Subtotal-C:

403.33 403.33

Subtotal-A:

407.36 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

415.51

10% Profit ( Add 10% on Subtotal-B) :

457.06

VAT

6% of Total

IT

4% of Total

30.47 20.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

251.83

507.85

Page: 2601 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.33.03

Detailed Analysis Brief Description of Item 2 100mm dia strainer of any slot as per design made with grade PVC pipe having wall thickness 4.5mm to 5.2mm (‘C’ class Aziz/equivalent brand).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

445.00

445.00

m 4.5 - 5.2mm thick 100mm dia PVC strainer ('C' Class)

1.0000

445.00

Subtotal-A: Making slots & other costs

( +12.00 % on Subtotal-A )

Subtotal-A1:

498.40

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

508.37

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

559.20

VAT

6% of Total

37.28

IT

4% of Total

24.85 Total:

10.33.04

100mm dia water grade PVC Blind pipe/well pipe having wall thickness 4.5mm to 5.2mm (‘C’ class Aziz/equivalent brand).

621.34

m 4.5 - 5.2mm thick 100mm dia PVC blind/ well pipe ('C' Class)

1.0000

m

403.33

403.33 403.33

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

4.03

Subtotal-A1:

407.36

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

415.51

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

457.06

VAT

6% of Total

30.47

IT

4% of Total

20.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

53.40

507.85

Page: 2602 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.33.05

Detailed Analysis Brief Description of Item 2 Best quality 100mmx200mm dia PVC Reducer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

780.00

780.00

each 100x 200mm PVC reducer (best quality)

1.0000

each

780.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

7.80

Subtotal-A1: Subtotal-B: Subtotal-C:

10.33.06

200mm dia water grade PVC Housing pipe having wall thickness 7.8mm to 9.0mm (‘C’ class Aziz/equivalent Brand).

787.80 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

803.56

10% Profit ( Add 10% on Subtotal-B) :

883.91

VAT

6% of Total

IT

4% of Total

58.93 39.28 Total:

982.12

1432.50

1432.50

m 7.8 - 9.0mm thick 200mm dia PVC pipe ('C' Class)

1.0000

m

1432.50

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

14.33

Subtotal-A1: Subtotal-B: Subtotal-C:

1446.83 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1475.76

10% Profit ( Add 10% on Subtotal-B) :

1623.34

VAT

6% of Total

108.22

IT

4% of Total

72.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1803.71

Page: 2603 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.34

Detailed Analysis Brief Description of Item 2 Complete installation of 100mm dia PVC tube-well fixtures such as expanded top pipes, reducer, tube well pipes, strainer, blind pipe, pipe cap etc. fitting and fixing with best quality PVC solution, iron screws and PVC tape and placing in position with proper size bamboo split centralizer @3m c/c in strainer portion in/c. blank pipe etc. all complete as per standard practice, specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

PVC tape

0.0300

each

15.00

0.45

PVC solution gum

0.0300

each

500.00

15.00

Borak Bamboo (75mm dia)

0.0350

m

38.00

1.33

Foreman

0.0100

day

800.00

8.00

Foreman helper

0.0500

day

350.00

17.50

Skilled Labour

0.0500

day

450.00

22.50 64.78

Subtotal-A: All other remaining costs like bamboo split, screws, fuel etc.

( +16.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

75.14 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

76.65

10% Profit ( Add 10% on Subtotal-B) :

84.31

VAT

6% of Total

IT

4% of Total

5.62 3.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10.36

93.68

Page: 2604 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.35

2 Preparation and making gravel pack around the tube well fixtures and bore hole with supply of designed graded pea gravel (passing through 10 mesh and retained on 40 mesh) including screening, washing etc. all complete as per standard specifications and direction of the E-I-C. (The rate is inclusive of the cost of extra amount required the caving and extra depth below the tube well fixtures. Shrouding should not be more than 15m above the strainer and measurement should be allowed from bottom of the tube well fixture to top of the gravel pack).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (6mm down graded) [LAA≤30]

1.2000

m3

3800.00

4560.00

Skilled Labour

0.3600

day

450.00

162.00

Ordinary Labour

0.3600

day

370.00

133.20 4855.20

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

97.10

Subtotal-A1:

4952.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5051.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5556.49

VAT

6% of Total

IT

4% of Total

370.43 246.95 Total:

10.36

Complete development of the tube well by air compressor and pump of suitable capacity by alternate surging and pumping until satisfactory yield, sand free water and the turbidity condition is reached using necessary quantity of calgon and conducting step draw down test before and after the development, etc. all complete as per specifications and direction of the E-I-C. (Development should be started within 24 hours of completion of shrouding)

10.36.01

Wells up to 200m depth

LS

10.36.02

Wells beyond 200m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

6173.87

Page: 2605 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.37

Detailed Analysis Brief Description of Item 2 Long term pumping test of the well by required capacity of turbine/submersible pump with supply of testing equipment and all materials for 72 hours including draw down and recovery test etc. all complete as per specifications and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

104.00

hour

Foreman

0.1300

day

800.00

Skilled Labour

0.0900

day

450.00

40.50

H.C. of Water Pump

0.1250

day

500.00

62.50 207.00

Subtotal-A: Fuel & other costs

( +43.00 % on Subtotal-A )

Subtotal-A1:

296.01

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

301.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

332.12

VAT

6% of Total

IT

4% of Total

22.14 14.76 Total:

10.38

Disinfecting the well including supply of sufficient quantity of bleaching powder (33% strength) chlorinated water having 150ppm available free chlorine etc. all complete as per standard specifications and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

89.01

369.03

LS

Page: 2606 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.39

Detailed Analysis Brief Description of Item 2 Filling the bore hole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawal of selected soil or local clay, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0600

day

450.00

27.00 35.00

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.35

Subtotal-A1: Subtotal-B: Subtotal-C:

35.35 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

36.06

10% Profit ( Add 10% on Subtotal-B) :

39.66

VAT

6% of Total

IT

4% of Total

2.64 1.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

44.07

Page: 2607 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.40

Detailed Analysis Brief Description of Item 2 Making a sanitary seal up to a minimum depth of 6m from G.L. or as specified including the supply of approved quality of cement, sand and brick aggregate, (10mm down graded) in proportion 1:1.5:3 as per standard specification, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (10mm down graded)

0.9000

m3

3049.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7700

bag

430.00

3341.10

Head Mason

0.0600

day

650.00

39.00

Mason

0.2400

day

550.00

132.00

Skilled Labour

0.3500

day

450.00

157.50

Ordinary Labour

4.1000

day

370.00

1517.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8463.20

Subtotal-A: All other remaining costs like form work, etc.

( +8.00 % on Subtotal-A )

677.06

Subtotal-A1:

9140.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9323.06 10255.37 683.69 455.79

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2744.10

11394.85

Page: 2608 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.41

Detailed Analysis Brief Description of Item 2 Supplying and fitting fixing best quality 250mm dia 4mm thick MS pipe 1.0m long one end blocked with 300mm dia 4mm thick MS plate and other end minimum 300mm embedded in sanitary seal for protection of PVC Housing Pipe, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

5mm thick 250mm dia MS pipe-7mm thick

1.0000

m

4920.00

4920.00

5mm thick 300mm dia MS plate

1.0000

each

410.00

410.00 5330.00

Subtotal-A: Welding & other costs

( +11.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6034.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6638.09

VAT

6% of Total

442.54

IT

4% of Total

295.03 Total:

10.42

Preparation for installation of tube well and transportation of complete boring equipment, labours and materials to the work site and returned the materials on completion of works. Installation of drilling rig and accessories, making arrangements for electricity, water, labour shed, site office and stores, digging mud pit etc. leveling dressing and clearing the site to original condition etc. all complete as per specifications and directions of the E-I-C.

10.42.01

For Tube wells up to 100 m depth

LS

10.42.02

For Tube wells up to 200 m depth

LS

10.42.03

For Tube wells beyond 200 m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

586.30 5916.30

7375.65

Page: 2609 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

10.43

Execution of boring through all sorts of strata reserve circulation or any other approved method (method other than reserve circulation is to be applied only for wells deeper than 152 m) for boring 600mm dia vertical hole up to designed depth and collection of soil samples at every 3m interval and at every change of formation including sinking and withdrawing necessary casing pipe and all necessary arrangements, etc. all complete as per specifications and direction of the E-I-C. (Measurement will be allowed from G.L. to bottom of the blank pipe and the rate is inclusive of the cost of extra depth of boring required for caving and siltation.

10.43.01

From 0.0m to 50m = 50m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

800.00

800.00

m Cost of boring (600m dia boring) including all equipment, accessories, materials, labour etc.

1.0000

800.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

816.00

10% Profit ( Add 10% on Subtotal-B) :

897.60

VAT

6% of Total

IT

4% of Total

59.84 39.89 Total:

10.43.02

From 50m to 100m = 50m

m

Add +15.00% with Item No 10.43.01

10.43.03

From 100m to 152m = 52m

m

Add +32.00% with Item No 10.43.01

10.43.04

From 152m to 200m = 48m

m

Add +52.00% with Item No 10.43.01

10.43.05

From 200m to 250m = 50m

m

Add +75.00% with Item No 10.43.01

10.43.06

Beyond 250m

m

Add +101.00% with Item No 10.43.01

10.44

Supplying tube well fixtures at working site, etc. all complete as per standard practice and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

997.33

Page: 2610 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.44.01

Detailed Analysis Brief Description of Item 2 Best quality 150mm dia PVC cap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

250.00

250.00

each 150mm dia PVC cap (best quality)

1.0000

each

250.00

Subtotal-A: All other remaining costs

( +3.00 % on Subtotal-A )

7.50

Subtotal-A1: Subtotal-B: Subtotal-C:

257.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

262.65

10% Profit ( Add 10% on Subtotal-B) :

288.92

VAT

6% of Total

IT

4% of Total

19.26 12.84 Total:

10.44.02

150mm dia water grade PVC blank pipe/sand trap having wall thickness 6.6mm to 7.6mm (‘C’ class Aziz/ equivalent Brand)

m 6.6 - 7.6mm thick 150mm dia water graded PVC blank pipe ('C' Class)

1.0000

m

931.66

All other remaining costs

( +2.00 % on Subtotal-A )

18.63

Subtotal-A1: Subtotal-B: Subtotal-C:

931.66 931.66

Subtotal-A:

950.29 969.30

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1066.23

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

71.08 47.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

321.02

1184.70

Page: 2611 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.44.03

Detailed Analysis Brief Description of Item 2 150mm dia strainer of any slot as per design made with grade PVC pipe having wall thickness 6.6mm to 7.6mm (‘C’ class Aziz/equivalent brand).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

931.66

931.66

m 6.6 - 7.6mm thick 150mm dia water graded PVC blank pipe ('C' Class)

1.0000

931.66

Subtotal-A: Making slots & other costs

( +6.00 % on Subtotal-A )

55.90

Subtotal-A1:

987.56

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1007.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1108.04

VAT

6% of Total

IT

4% of Total

73.87 49.25 Total:

10.44.04

150mm dia water grade PVC Blind pipe/well pipe having wall thickness 6.6mm to 7.6mm (‘C’ class Aziz/ equivalent brand).

m 6.6 - 7.6mm thick 150mm dia PVC blind/well pipe ('C' Class)

1.0000

m

931.66

All other remaining costs

( +2.00 % on Subtotal-A )

18.63

Subtotal-A1: Subtotal-B: Subtotal-C:

931.66 931.66

Subtotal-A:

950.29 969.30

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1066.23

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

71.08

IT

4% of Total

47.39 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1231.16

1184.70

Page: 2612 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.44.05

Detailed Analysis Brief Description of Item 2 Best quality 150mmx200mm dia PVC Reducer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

780.00

780.00

each 100x 200mm PVC reducer (best quality)

1.0000

each

780.00

Subtotal-A: All other remaining costs

( +1.50 % on Subtotal-A )

11.70

Subtotal-A1: Subtotal-B: Subtotal-C:

10.44.06

200mm dia water grade PVC Housing pipe having wall thickness 7.8mm to 9.0mm (‘C’ class Aziz/equivalent Brand).

791.70 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

807.53

10% Profit ( Add 10% on Subtotal-B) :

888.29

VAT

6% of Total

IT

4% of Total

59.22 39.48 Total:

986.99

1432.50

1432.50

m 7.8 - 9.0mm thick 200mm dia PVC pipe ('C' Class)

1.0000

m

1432.50

Subtotal-A: All other remaining costs

( +1.50 % on Subtotal-A )

21.49

Subtotal-A1: Subtotal-B: Subtotal-C:

1453.99 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1483.07

10% Profit ( Add 10% on Subtotal-B) :

1631.37

VAT

6% of Total

108.76

IT

4% of Total

72.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1812.64

Page: 2613 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.45

Detailed Analysis Brief Description of Item 2 Complete installation of 100mm dia PVC tube-well fixtures such as expanded top pipes, reducer, tube well pipes, strainer, blind pipe, pipe cap etc. fitting and fixing with best quality PVC solution, iron screws and PVC tape and placing in position with proper size bamboo split centralizer @3m c/c in strainer portion in/c. blank pipe etc. all complete as per standard practice, specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

PVC tape

0.0500

each

15.00

0.75

PVC solution gum

0.0400

each

500.00

20.00

Borak Bamboo (75mm dia)

0.0500

m

38.00

1.90

Foreman

0.0100

day

800.00

8.00

Foreman helper

0.0400

day

350.00

14.00

Skilled Labour

0.0400

day

450.00

18.00 62.65

Subtotal-A: All other remaining costs like bamboo split, screws, fuel etc.

( +17.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

73.30 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

74.77

10% Profit ( Add 10% on Subtotal-B) :

82.24

VAT

6% of Total

IT

4% of Total

5.48 3.66 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10.65

91.38

Page: 2614 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.46

2 Preparation and making gravel pack around the tube well fixtures and bore hole with supply of designed graded pea gravel (passing through 10 mesh and retained on 40 mesh) including screening, washing etc. all complete as per standard specifications and direction of the E-I-C. (The rate is inclusive of the cost of extra amount required the caving and extra depth below the tube well fixtures. Shrouding should not be more than 15m above the strainer and measurement should be allowed from bottom of the tube well fixture to top of the gravel pack).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (6mm down graded) [LAA≤30]

1.2000

m3

3800.00

4560.00

Skilled Labour

0.3600

day

450.00

162.00

Ordinary Labour

0.3600

day

370.00

133.20 4855.20

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

97.10

Subtotal-A1:

4952.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5051.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5556.49

VAT

6% of Total

IT

4% of Total

370.43 246.95 Total:

10.47

Complete development of the tube well by air compressor and pump of suitable capacity by alternate surging and pumping until satisfactory yield, sand free water and the turbidity condition is reached using necessary quantity of calgon and conducting step draw down test before and after the development, etc. all complete as per specifications and direction of the E-I-C. (Development should be started within 24 hours of completion of shrouding)

10.47.01

Wells up to 200m depth

LS

10.47.02

Wells beyond 200m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

6173.87

Page: 2615 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.48

Detailed Analysis Brief Description of Item 2 Long term pumping test of the well by required capacity of turbine/submersible pump with supply of testing equipment and all materials for 72 hours including draw down and recovery test etc. all complete as per specifications and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

104.00

hour

Foreman

0.1300

day

800.00

Skilled Labour

0.0900

day

450.00

40.50

H.C. of Water Pump

0.1250

day

500.00

62.50 207.00

Subtotal-A: Fuel & other costs

( +44.00 % on Subtotal-A )

Subtotal-A1:

298.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

304.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

334.45

VAT

6% of Total

IT

4% of Total

22.30 14.86 Total:

10.49

Disinfecting the well including supply of sufficient quantity of bleaching powder (33% strength) chlorinated water having 150ppm available free chlorine etc. all complete as per standard specifications and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

91.08

371.61

LS

Page: 2616 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.50

Detailed Analysis Brief Description of Item 2 Filling the bore hole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawal of selected soil or local clay, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0900

day

450.00

40.50 48.50

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.49

Subtotal-A1: Subtotal-B: Subtotal-C:

48.99 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

49.96

10% Profit ( Add 10% on Subtotal-B) :

54.96

VAT

6% of Total

IT

4% of Total

3.66 2.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

61.07

Page: 2617 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.51

Detailed Analysis Brief Description of Item 2 Making a sanitary seal up to a minimum depth of 6m from G.L. or as specified including the supply of approved quality of cement, sand and brick aggregate, (10mm down graded) in proportion 1:1.5:3 as per standard specification, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (10mm down graded)

0.9000

m3

3049.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7700

bag

430.00

3341.10

Head Mason

0.0600

day

650.00

39.00

Mason

0.2400

day

550.00

132.00

Skilled Labour

0.3500

day

450.00

157.50

Ordinary Labour

4.1000

day

370.00

1517.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8463.20

Subtotal-A: All other remaining costs like form work, etc.

( +8.00 % on Subtotal-A )

677.06

Subtotal-A1:

9140.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9323.06 10255.37 683.69 455.79

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2744.10

11394.85

Page: 2618 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.52

Detailed Analysis Brief Description of Item 2 Supplying and fitting fixing best quality 250mm dia 4mm thick MS pipe 1.0m long one end blocked with 300mm dia 4mm thick MS plate and other end minimum 300mm embedded in sanitary seal for protection of PVC Housing Pipe, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

6mm thick 300mm dia MS pipe-8mmthick

1.0000

m

5740.00

5740.00

6mm thick 300mm dia MS plate

1.0000

each

410.00

410.00 6150.00

Subtotal-A: Welding & other costs

( +11.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6963.03

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7659.33

VAT

6% of Total

510.62

IT

4% of Total

340.41 Total:

10.53

Preparation for installation of tube well and transportation of complete boring equipment, labours and materials to the work site and returned the materials on completion of works. Installation of drilling rig and accessories, making arrangements for electricity, water, labour shed, site office and stores, digging mud pit etc. leveling dressing and clearing the site to original condition etc. all complete as per specifications and directions of the E-I-C.

10.53.01

For Tube wells up to 100 m depth

LS

10.53.02

For Tube wells up to 200 m depth

LS

10.53.03

For Tube wells beyond 200 m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

676.50 6826.50

8510.37

Page: 2619 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

10.54

Execution of boring through all sorts of strata reserve circulation or any other approved method (method other than reserve circulation is to be applied only for wells deeper than 152 m) for boring 600mm dia vertical hole up to designed depth and collection of soil samples at every 3m interval and at every change of formation including sinking and withdrawing necessary casing pipe and all necessary arrangements, etc. all complete as per specifications and direction of the E-I-C. (Measurement will be allowed from G.L. to bottom of the blank pipe and the rate is inclusive of the cost of extra depth of boring required for caving and siltation.

10.54.01

From 0.0m to 50m = 50m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

800.00

800.00

m Cost of boring (600m dia boring) including all equipment, accessories, materials, labour etc.

1.0000

800.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

816.00

10% Profit ( Add 10% on Subtotal-B) :

897.60

VAT

6% of Total

IT

4% of Total

59.84 39.89 Total:

10.54.02

From 50m to 100m = 50m

m

Add +15.00% with Item No 10.54.01

10.54.03

From 100m to 152m = 52m

m

Add +32.00% with Item No 10.54.01

10.54.04

From 152m to 200m = 48m

m

Add +52.00% with Item No 10.54.01

10.54.05

From 200m to 250m = 50m

m

Add +75.00% with Item No 10.54.01

10.54.06

Beyond 250m

m

Add +101.00% with Item No 10.54.01

10.55

Supplying tube well fixtures at working site, etc. all complete as per standard practice and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

997.33

Page: 2620 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.55.01

Detailed Analysis Brief Description of Item 2 150mm dia M.S. cap 6mm thick for blank pipe/sand trap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 6mm thick 150mm dia MS cap (best quality)

1.0000

each

1025.00

1025.00

Subtotal-A: All other remaining costs

( +3.00 % on Subtotal-A )

30.75

Subtotal-A1: Subtotal-B: Subtotal-C:

1055.75 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1076.87

10% Profit ( Add 10% on Subtotal-B) :

1184.55

VAT

6% of Total

IT

4% of Total

78.97 52.65 Total:

10.55.02

150mm dia GI pipe (national Tube or equivalent Brand) having minimum thickness 4.85 for Blank pipe/sand trap.

1316.17

m 4.8mm thick 150mm dia GI pipe blank

1.0000

m

2640.00

All other remaining costs

( +1.20 % on Subtotal-A )

31.68

Subtotal-A1: Subtotal-B: Subtotal-C:

2640.00 2640.00

Subtotal-A:

2671.68 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2725.11

10% Profit ( Add 10% on Subtotal-B) :

2997.62

VAT

6% of Total

199.84

IT

4% of Total

133.23 Total:

10.55.03

1025.00

3330.69

150mm dia strainer of slot opening as per design including tagging 4 Nos. 12mm dia M.S. rod continuously.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2621 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.55.03.01

Detailed Analysis Brief Description of Item 2 Stainless steel strainer of continuous slot (Johnson or equivalent) having weight 28.84kg per m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 150mm dia stainless steel strainer (28.84 kg/m) MS Rod (Plain, 40 Grade)

1.0000

m

5292.00

5292.00

21.8400

kg

45.00

982.80 6274.80

Subtotal-A: All other remaining costs

( +.35 % on Subtotal-A )

21.96

Subtotal-A1: Subtotal-B: Subtotal-C:

6296.76 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6422.70

10% Profit ( Add 10% on Subtotal-B) :

7064.97

VAT

6% of Total

IT

4% of Total

471.00 314.00 Total:

10.55.03.02

2.50mm thick stainless steel Bridge type strainer

m 2.5mm thick 150mm dia stainless steel bridge type strainer MS Rod (Plain, 40 Grade)

1.0000

m

4536.00

4536.00

21.8400

kg

45.00

982.80 5518.80

Subtotal-A: All other remaining costs

( +.35 % on Subtotal-A )

19.32

Subtotal-A1:

5538.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5648.88

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6213.77

VAT

6% of Total

IT

4% of Total

414.25 276.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7849.96

6904.18

Page: 2622 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.55.04

Detailed Analysis Brief Description of Item 2 150mm dia GI blind pipe (National Tube or equivalent) having minimum thickness 4.85mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 4.85mm thick 150mm dia GI pipe

1.0000

m

2640.00

2640.00

Subtotal-A: All other remaining costs

( +1.20 % on Subtotal-A )

31.68

Subtotal-A1:

2671.68

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2725.11

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2997.62

VAT

6% of Total

199.84

IT

4% of Total

133.23 Total:

10.55.05

150mmx300mm dia M.S. reducer having minimum thickness of 6mm.

3330.69

each 150x300mm dia MS reducer

1.0000

each

2900.00

All other remaining costs

( +1.50 % on Subtotal-A )

43.50

Subtotal-A1: Subtotal-B: Subtotal-C:

2900.00 2900.00

Subtotal-A:

2943.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3002.37

10% Profit ( Add 10% on Subtotal-B) :

3302.61

VAT

6% of Total

IT

4% of Total

220.17 146.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2640.00

3669.56

Page: 2623 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.55.06

Detailed Analysis Brief Description of Item 2 300mm dia M.S. Housing pipe having minimum thickness 6mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 6mm thick 300mm dia MS pipe-8mmthick

1.0000

m

5740.00

5740.00

Subtotal-A: All other remaining costs

( +2.20 % on Subtotal-A )

126.28

Subtotal-A1: Subtotal-B: Subtotal-C:

5866.28 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5983.61

10% Profit ( Add 10% on Subtotal-B) :

6581.97

VAT

6% of Total

IT

4% of Total

438.80 292.53 Total:

10.55.07

Centralizer made with 10mm dia M.S. rod of approved design.

7313.30

each MS Rod (Plain, 40 Grade)

7.4400

kg

45.00

334.80 334.80

Subtotal-A: All other remaining costs like welding, fabrication, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

33.48 368.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

375.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

413.21

VAT

6% of Total

IT

4% of Total

27.55 18.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5740.00

459.12

Page: 2624 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

10.55.08

350mm dia M.S. cap having 6mm thick for housing pipe covering.

each

Quantity

6mm thick 300mm dia MS plate

5

1.0000

Unit

Rate

6

7

8

410.00

410.00

each

Amount

410.00

Subtotal-A: All other remaining costs like welding, fabrication, etc.

( +31.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

537.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

547.84

10% Profit ( Add 10% on Subtotal-B) :

602.63

VAT

6% of Total

IT

4% of Total

40.18 26.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

127.10

669.58

Page: 2625 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.56

Detailed Analysis Brief Description of Item 2 Complete installation of 150mm dia deep tube-well fixtures such as expanded top pipes, reducer, tube well pipes, strainer, blind pipe, pipe cap etc. fitting and fixing with best quality PVC solution, iron screws and PVC tape and placing in position with proper size bamboo split centralizer @3m c/c in strainer portion in/c. blank pipe etc. all complete as per standard practice, specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Lowering the bail plug, strainer 150mm dia GI pipe and 300mm dia MS pipe

1.0000

m

46.44

46.44

Stone Chips (6mm down graded) [LAA≤30]

0.2600

m3

3800.00

988.00 1034.44

Subtotal-A: Filling slurry, verticality test, anchoring the tube well in/c supplying joint, concrete, brick work and other costs

( +229.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3403.31 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3471.37

10% Profit ( Add 10% on Subtotal-B) :

3818.51

VAT

6% of Total

IT

4% of Total

254.57 169.71 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2368.87

4242.79

Page: 2626 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.57

2 Preparation and making gravel pack around the tube well fixtures and bore hole with supply of designed graded pea gravel (passing through 10 mesh and retained on 40 mesh) including screening, washing etc. all complete as per standard specifications and direction of the E-I-C. (The rate is inclusive of the cost of extra amount required the caving and extra depth below the tube well fixtures. Shrouding should not be more than 15m above the strainer and measurement should be allowed from bottom of the tube well fixture to top of the gravel pack).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (6mm down graded) [LAA≤30]

1.2000

m3

3800.00

4560.00

Skilled Labour

0.3600

day

450.00

162.00

Ordinary Labour

0.3600

day

370.00

133.20 4855.20

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

97.10

Subtotal-A1:

4952.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5051.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5556.49

VAT

6% of Total

IT

4% of Total

370.43 246.95 Total:

10.58

Complete development of the tube well by air compressor and pump of suitable capacity by alternate surging and pumping until satisfactory yield, sand free water and the turbidity condition is reached using necessary quantity of calgon and conducting step draw down test before and after the development, etc. all complete as per specifications and direction of the E-I-C. (Development should be started within 24 hours of completion of shrouding)

10.58.01

Walls upto 200m depth

LS

10.58.02

Walls beyond 200m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

6173.87

Page: 2627 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.59

Detailed Analysis Brief Description of Item 2 Long term pumping test of the well by required capacity of turbine/submersible pump with supply of testing equipment and all materials for 72 hours including draw down and recovery test etc. all complete as per specifications and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

104.00

hour

Foreman

0.1300

day

800.00

Skilled Labour

0.0900

day

450.00

40.50

H.C. of Water Pump

0.1250

day

500.00

62.50 207.00

Subtotal-A: Fuel & other costs

( +44.00 % on Subtotal-A )

Subtotal-A1:

298.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

304.04

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

334.45

VAT

6% of Total

IT

4% of Total

22.30 14.86 Total:

10.60

Disinfecting the well including supply of sufficient quantity of bleaching powder (33% strength) chlorinated water having 150ppm available free chlorine etc. all complete as per standard specifications and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

91.08

371.61

LS

Page: 2628 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.61

Detailed Analysis Brief Description of Item 2 Filling the bore hole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawal of selected soil or local clay, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0900

day

450.00

40.50 48.50

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.49

Subtotal-A1: Subtotal-B: Subtotal-C:

48.99 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

49.96

10% Profit ( Add 10% on Subtotal-B) :

54.96

VAT

6% of Total

IT

4% of Total

3.66 2.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

61.07

Page: 2629 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.62

Detailed Analysis Brief Description of Item 2 Making a sanitary seal up to a minimum depth of 6m from G.L. or as specified including the supply of approved quality of cement, sand and brick aggregate, (10mm down graded) in proportion 1:1.5:3 as per standard specification, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (10mm down graded)

0.9000

m3

3049.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7700

bag

430.00

3341.10

Head Mason

0.0600

day

650.00

39.00

Mason

0.2400

day

550.00

132.00

Skilled Labour

0.3500

day

450.00

157.50

Ordinary Labour

4.1000

day

370.00

1517.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8463.20

Subtotal-A: All other remaining costs like form work, etc.

( +8.00 % on Subtotal-A )

677.06

Subtotal-A1:

9140.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9323.06 10255.37 683.69 455.79

Total: 10.63

2744.10

11394.85

Preparation for installation of tube well and transportation of complete boring equipment, labours and materials to the work site and returned the materials on completion of works. Installation of drilling rig and accessories, making arrangements for electricity, water, labour shed, site office and stores, digging mud pit etc. leveling dressing and clearing the site to original condition etc. all complete as per specifications and directions of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2630 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

10.63.01

For Tube wells up to 100 m depth

LS

10.63.02

For Tube wells up to 200 m depth

LS

10.63.03

For Tube wells beyond 200 m depth

LS

10.64

Execution of boring through all sorts of strata reserve circulation or any other approved method (method other than reserve circulation is to be applied only for wells deeper than 152 m) for boring 600mm dia vertical hole up to designed depth and collection of soil samples at every 3m interval and at every change of formation including sinking and withdrawing necessary casing pipe and all necessary arrangements, etc. all complete as per specifications and direction of the E-I-C. (Measurement will be allowed from G.L. to bottom of the blank pipe and the rate is inclusive of the cost of extra depth of boring required for caving and siltation.

10.64.01

From 0.0m to 50m = 50m

1

Quantity 5

Unit

Rate

Amount

6

7

8

m

800.00

800.00

m Cost of boring (600m dia boring) including all equipment, accessories, materials, labour etc.

1.0000

800.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

816.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

897.60

VAT

6% of Total

IT

4% of Total

59.84 39.89 Total:

10.64.02

From 50m to 100m = 50m

m

Add +15.00% with Item No 10.64.01

10.64.03

From 100m to 152m = 52m

m

Add +32.00% with Item No 10.64.01

10.64.04

From 152m to 200m = 48m

m

Add +52.00% with Item No 10.64.01

Note : Rates of all items should be inclusive of all supply and carriage.

997.33

Page: 2631 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

10.64.05

From 200m to 250m = 50m

m

Add +75.00% with Item No 10.64.01

10.64.06

Beyond 250m = 50m

m

Add +101.00% with Item No 10.64.01

10.65

Supplying tube well fixtures at working site, etc. all complete as per standard practice and direction of the E-I-C.

10.65.01

200mm dia M.S. cap 6mm thick for blank pipe/sand trap

Quantity 5

Unit

Rate

6

7

Amount 8

each 6mm thick 200mm dia MS cap (best quality)

1.0000

each

1682.00

1682.00

Subtotal-A: All other remaining costs

( +2.50 % on Subtotal-A )

42.05

Subtotal-A1:

1724.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1758.53

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1934.38

VAT

6% of Total

IT

4% of Total

128.96 85.97 Total:

10.65.02

200mm dia GI pipe (national Tube or equivalent Brand) having minimum thickness 6mm for Blank pipe/sand trap

2149.32

m 6mm thick 200mm dia GI pipe

1.0000

m

3936.00

3936.00 3936.00

Subtotal-A: All other remaining costs

( +.80 % on Subtotal-A )

31.49

Subtotal-A1:

3967.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4046.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4451.52

VAT

6% of Total

IT

4% of Total

296.77 197.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1682.00

4946.14

Page: 2632 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

10.65.03

200mm dia strainer of slot opening as per design including tagging 4 Nos. 12mm dia M.S. rod continuously.

10.65.03.01

Stainless steel strainer of continuous slot (Johnson brand or equivalent) having weight 38.36kg per m

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 200mm dia stainless steel strainer (38.36 kg/m) MS Rod (Plain, 40 Grade)

1.0000

m

8640.00

8640.00

21.6900

kg

45.00

976.05 9616.05

Subtotal-A: All other remaining costs

( +.40 % on Subtotal-A )

38.46

Subtotal-A1:

9654.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9847.60 10832.36 722.16 481.44

Total: 10.65.03.02

2.50mm thick stainless steel Bridge type strainer

m 2.5mm thick 200mm dia stainless steel bridge type strainer MS Rod (Plain, 40 Grade)

1.0000

m

6156.00

6156.00

21.8400

kg

45.00

982.80 7138.80

Subtotal-A: All other remaining costs

( +.35 % on Subtotal-A )

24.99

Subtotal-A1:

7163.79

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7307.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8037.77

VAT

6% of Total

IT

4% of Total

535.85 357.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12035.96

8930.85

Page: 2633 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.65.04

Detailed Analysis Brief Description of Item 2 200mm dia GI blind pipe (National Tube or equivalent brand) having minimum thickness 4.85mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 6mm thick 200mm dia GI pipe

1.0000

m

3936.00

3936.00

Subtotal-A: All other remaining costs

( +.80 % on Subtotal-A )

31.49

Subtotal-A1:

3967.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4046.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4451.52

VAT

6% of Total

296.77

IT

4% of Total

197.85 Total:

10.65.05

200mmx300mm dia M.S. reducer having minimum thickness of 6mm.

4946.14

each 200x300mm dia MS reducer

1.0000

each

3000.00

All other remaining costs

( +1.50 % on Subtotal-A )

45.00

Subtotal-A1: Subtotal-B: Subtotal-C:

3000.00 3000.00

Subtotal-A:

3045.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3105.90

10% Profit ( Add 10% on Subtotal-B) :

3416.49

VAT

6% of Total

IT

4% of Total

227.77 151.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3936.00

3796.10

Page: 2634 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.65.06

Detailed Analysis Brief Description of Item 2 300mm dia M.S. Housing pipe having minimum thickness 6mm.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 6mm thick 300mm dia MS pipe-8mmthick

1.0000

m

5740.00

5740.00

Subtotal-A: All other remaining costs

( +2.20 % on Subtotal-A )

126.28

Subtotal-A1: Subtotal-B: Subtotal-C:

5866.28 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5983.61

10% Profit ( Add 10% on Subtotal-B) :

6581.97

VAT

6% of Total

IT

4% of Total

438.80 292.53 Total:

10.65.07

Centralizer made with 10mm dia M.S. rod of approved design.

7313.30

each MS Rod (Plain, 40 Grade)

7.4400

kg

45.00

334.80 334.80

Subtotal-A: All other remaining costs like welding, fabrication, etc.

( +10.00 % on Subtotal-A )

Subtotal-A1:

33.48 368.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

375.65

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

413.21

VAT

6% of Total

IT

4% of Total

27.55 18.36 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5740.00

459.12

Page: 2635 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

10.65.08

350mm dia M.S. cap having 6mm thick for housing pipe covering.

each

Quantity

6mm thick 350mm dia MS cap (best quality)

5

1.0000

Unit

Rate

6

7

each

Amount 8

4320.00

4320.00

Subtotal-A: All other remaining costs like welding, fabrication, etc.

( +31.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

1339.20 5659.20

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5772.38

10% Profit ( Add 10% on Subtotal-B) :

6349.62

VAT

6% of Total

IT

4% of Total

423.31 282.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4320.00

7055.14

Page: 2636 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.66

Detailed Analysis Brief Description of Item 2 Complete installation of 200mm dia deep tube-well fixtures such as expanded top pipes, reducer, tube well pipes, strainer, blind pipe, pipe cap etc. fitting and fixing with best quality PVC solution, iron screws and PVC tape and placing in position with proper size bamboo split centralizer @3m c/c in strainer portion in/c. blank pipe etc. all complete as per standard practice, specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Lowering the bail plug ,strainer 200mm dia GI pipe and 375mm dia MS pipe

1.0000

m

51.84

51.84

Stone Chips (6mm down graded) [LAA≤30]

0.2600

m3

3800.00

988.00 1039.84

Subtotal-A: Filling slurry, verticality test, anchoring the tube well in/c supplying joint, concrete, brick work and other costs

( +214.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3265.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3330.40

10% Profit ( Add 10% on Subtotal-B) :

3663.44

VAT

6% of Total

IT

4% of Total

244.23 162.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2225.26

4070.49

Page: 2637 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 10.67

2 Preparation and making gravel pack around the tube well fixtures and bore hole with supply of designed graded pea gravel (passing through 10 mesh and retained on 40 mesh) including screening, washing etc. all complete as per standard specifications and direction of the E-I-C. (The rate is inclusive of the cost of extra amount required the caving and extra depth below the tube well fixtures. Shrouding should not be more than 15m above the strainer and measurement should be allowed from bottom of the tube well fixture to top of the gravel pack).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

Stone Chips (6mm down graded) [LAA≤30]

1.2000

m3

3800.00

4560.00

Skilled Labour

0.3600

day

450.00

162.00

Ordinary Labour

0.3600

day

370.00

133.20 4855.20

Subtotal-A: All other remaining costs

( +2.00 % on Subtotal-A )

97.10

Subtotal-A1:

4952.30

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5051.35

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5556.49

VAT

6% of Total

IT

4% of Total

370.43 246.95 Total:

10.68

Complete development of the tube well by air compressor and pump of suitable capacity by alternate surging and pumping until satisfactory yield, sand free water and the turbidity condition is reached using necessary quantity of calgon and conducting step draw down test before and after the development, etc. all complete as per specifications and direction of the E-I-C. (Development should be started within 24 hours of completion of shrouding)

10.68.01

Wells upto 200 m depth

LS

10.68.02

Wells beyond 200 m depth

LS

Note : Rates of all items should be inclusive of all supply and carriage.

6173.87

Page: 2638 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.69

Detailed Analysis Brief Description of Item 2 Long term pumping test of the well by required capacity of turbine/submersible pump with supply of testing equipment and all materials for 72 hours including draw down and recovery test etc. all complete as per specifications and direction of the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

104.00

hour

Foreman

0.1300

day

800.00

Skilled Labour

0.0900

day

450.00

40.50

H.C. of Water Pump

0.1250

day

500.00

62.50 207.00

Subtotal-A: Fuel & other costs

( +42.00 % on Subtotal-A )

Subtotal-A1:

293.94

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

299.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

329.80

VAT

6% of Total

IT

4% of Total

21.99 14.66 Total:

10.70

Disinfecting the well including supply of sufficient quantity of bleaching powder (33% strength) chlorinated water having 150ppm available free chlorine etc. all complete as per standard specifications and direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

86.94

366.45

LS

Page: 2639 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.71

Detailed Analysis Brief Description of Item 2 Filling the bore hole around the tube well from top of the shrouding up to the bottom of sanitary seal by withdrawal of selected soil or local clay, etc. all complete as per standard specifications and direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Foreman

0.0100

day

800.00

8.00

Skilled Labour

0.0900

day

450.00

40.50 48.50

Subtotal-A: All other remaining costs

( +1.00 % on Subtotal-A )

0.49

Subtotal-A1: Subtotal-B: Subtotal-C:

48.99 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

49.96

10% Profit ( Add 10% on Subtotal-B) :

54.96

VAT

6% of Total

IT

4% of Total

3.66 2.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

61.07

Page: 2640 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.72

Detailed Analysis Brief Description of Item 2 Making a sanitary seal up to a minimum depth of 6m from G.L. or as specified including the supply of approved quality of cement, sand and brick aggregate, (10mm down graded) in proportion 1:1.5:3 as per standard specification, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

cum

1st Class Brick Chips (10mm down graded)

0.9000

m3

3049.00

Sand (FM - 1.8)

0.4500

m3

970.00

436.50

Portland Composite Cement (CEM-II/A-L/M/V/W 42.5N)

7.7700

bag

430.00

3341.10

Head Mason

0.0600

day

650.00

39.00

Mason

0.2400

day

550.00

132.00

Skilled Labour

0.3500

day

450.00

157.50

Ordinary Labour

4.1000

day

370.00

1517.00

H.C. of Concrete Mixture Machine (Capacity 0.40/ 0.28 cum)

0.0600

day

1200.00

72.00

Hire and running charges of Concrete Vibrator

0.0600

day

400.00

24.00 8463.20

Subtotal-A: All other remaining costs like form work, etc.

( +8.00 % on Subtotal-A )

677.06

Subtotal-A1:

9140.26

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9323.06 10255.37 683.69 455.79

Total: 10.73

2744.10

11394.85

Supplying and sinking 40mm dia Water grade (‘D’ Class Aziz Brand/equivalent) PVC tube well pipe having wall thickness 2.5mm to 3.0mm in/c trial boring and with all necessary fittings as required etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2641 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.73.01

Detailed Analysis Brief Description of Item 2 40mm dia pipe up to 60m depth

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m 2.5- 3mm thick 40mm dia water graded PVC pipe ('D' Class)

1.0000

m

78.72

78.72

Subtotal-A: Labour & other costs

( +57.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

40mm dia pipe beyond 60m depth

10.74

Supplying and sinking Five Star/equivalent brand 40mm dia PVC strainer 3m long including trial boring and with all necessary fittings as required etc. all complete as per direction of the E-I-C.

m

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

126.06

10% Profit ( Add 10% on Subtotal-B) :

138.67

VAT

6% of Total

IT

4% of Total

9.24 6.16 154.08

Add +19.00% with Item No 10.73.01

each

3m long 40mm dia PVC strainer (Five Star/ equivalent brand)

1.0000

each

260.00

Labour & other costs

( +59.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

260.00 260.00

Subtotal-A:

153.40 413.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

421.67

10% Profit ( Add 10% on Subtotal-B) :

463.83

VAT

6% of Total

30.92

IT

4% of Total

20.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

44.87 123.59

Total: 10.73.02

78.72

515.37

Page: 2642 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.75

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing EPI/RFL (Medium) Brand No. 6 pump for 40mm dia tube well with all necessary fittings including 0.61m long 40mm dia GI pipe etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Hand pump (no 6) complete set (best quality)

1.0000

set

2285.00

2285.00

40mm dia GI pipe of 2.9mm wall thick

0.6100

m

380.48

232.09 2517.09

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2567.43

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2824.18

VAT

6% of Total

188.28

IT

4% of Total

125.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3137.98

Page: 2643 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.76

Detailed Analysis Brief Description of Item 2 Construction of platform of size 1.4mx1.0m as per drawing with 75mm thick Cement Concrete (1:2:4) over a layer of brick flat soling and providing 125mmx75mm brick band all around in/c finished with 12mm thick cement plaster (1:4) with neat cement finishing, providing outlet drain up to 1m long, etc. all complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Earthwork in excavation of foundation trenches, including layout, ……. (2.04.1.1)

0.7300

cum

75.80

55.33

Sand (FM - 0.8)

0.2000

m3

480.00

96.00

Brick work with 1st class bricks in cement mortar (1:6) in foundation and plinth….(5.04.01)

0.3500

cum

5575.24

1951.33

Mass concrete (1:2:4) work in foundation with 1st class/picked jhama brick chips…(5.03.05.01)

0.2400

cum

6799.07

1631.78

12mm thick cement plaster (1:4) to dado and plinth wall…..(5.12.01)

2.7000

sqm

214.86

580.13 4314.57

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4400.87

10% Profit ( Add 10% on Subtotal-B) :

4840.95

VAT

6% of Total

IT

4% of Total

322.73 215.15 Total:

10.77

5378.84

Supplying and sinking PVC tube well pipe, PVC strainer including trial boring with all necessary fittings as required etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2644 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.77.01

Detailed Analysis Brief Description of Item 2 50mm dia water grade (‘C’ Class Aziz brand/equivalent) PVC pipe having wall thickness 2.5mm to 3.0mm

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

m

134.04

134.04

m 2.5 - 3mm thick 50mm dia pvc pipe (class C)

1.0000

134.04

Subtotal-A: Labour & other costs

( +59.00 % on Subtotal-A )

Subtotal-A1:

213.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

217.39

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

239.12

VAT

6% of Total

15.94

IT

4% of Total

10.63 Total:

10.77.02

40mm dia water grade (‘D’ Class Aziz brand/equivalent) PVC pipe having wall thickness 2.5mm to 3mm

265.69

m 2.5 -3mm thick 40mm dia water graded PVC strainer ('D' Class)

1.0000

m

78.72

78.72 78.72

Subtotal-A: Labour & other costs

( +57.00 % on Subtotal-A )

Subtotal-A1:

44.87 123.59

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

126.06

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

138.67

VAT

6% of Total

IT

4% of Total

9.24 6.16 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

79.08

154.08

Page: 2645 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 10.77.03

Detailed Analysis Brief Description of Item 2 40mm dia Five Star/equivalent brand PVC strainer 3.0m long

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

260.00

260.00

each 3m long 40mm dia PVC strainer (Five Star/ equivalent brand)

1.0000

each

260.00

Subtotal-A: Labour & other costs

( +59.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

153.40 413.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

421.67

10% Profit ( Add 10% on Subtotal-B) :

463.83

VAT

6% of Total

IT

4% of Total

30.92 20.61 Total:

515.37

Chapter - 11 : Furniture and Fixtures 11.01

Supply of furniture for Primary School

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2646 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.01.01

Detailed Analysis Brief Description of Item 2 Supplying High Bench (Size : 1.125mx0.35mx0.6m) with top made of best quality seasoned wood (well matured and sapless) like Jack wood, Silkarai, Gamari and Chittagong Teak. Legs and structures be made of steel angle in box form, welded (12mm weld length @ 50mm c/c all through angle box), cold bended and formed round corners. Exposed faces of all iron components shall be painted and finished with 2 coats BERGER/equivalent enamel paint over a coat of priming and wood surfaces to be varnished with best quality varnish in 3 coats, fabrication of steel angle box, finishing, assembling of all components, providing best quality PVC stoppers, fixing with requisite numbers and sizes of nuts and bolts and packing, etc all complete as shown in the drawing (if provided) and as per direction of the E-I-C. (Rate is inclusive of delivering the furniture at the selected school).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

High bench of size 1.125x0.35x0.6m of best quality seasoned wood (Jack /Chittagong sil korai / Gamari/ chittagong teak and structures made of steel angle), painting, varnishing etc. all complete

1.0000

each

3000.00

3000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3060.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3366.00

VAT

6% of Total

IT

4% of Total

224.40 149.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3000.00

3740.00

Page: 2647 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.01.02

Detailed Analysis Brief Description of Item 2 Supplying Low Bench (Size : 1.35mx0.25mx0.375m) with top made of best quality seasoned wood (well matured and sapless) like Jack wood, Silkarai, Gamari and Chittagong Teak. Legs and structures be made of steel angle in box form, welded (12mm weld length @ 50mm c/c all through angle box), cold bended and formed round corners. Exposed faces of all iron components shall be painted and finished with 2 coats BERGER/equivalent enamel paint over a coat of priming and wood surfaces to be varnished with best quality varnish in 3 coats, fabrication of steel angle box, finishing, assembling of all components, providing best quality PVC stoppers, fixing with requisite numbers and sizes of nuts and bolts and packing, etc all complete as shown in the drawing (if provided) and as per direction of the E-I-C. (Rate is inclusive of delivering the furniture at the selected school).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Low bench of size 1.35x0.25x0.375m of best quality seasoned wood (Jack/ Chittagong sil korai/Gamari/Chittagong teak and structures made of steel angle), painting, varnishing etc. all complete

1.0000

each

2700.00

2700.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2754.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3029.40

VAT

6% of Total

IT

4% of Total

201.96 134.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2700.00

3366.00

Page: 2648 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.01.03

Detailed Analysis Brief Description of Item 2 Supplying Teacher’s Table (Size : 0.675mx0.375mx0.763m) with top made of best quality seasoned wood (well matured and sapless) like Jack wood, Silkarai, Gamari and Chittagong Teak. Legs and structures be made of steel angle in box form, welded (12mm weld length @ 50mm c/c all through angle box), cold bended and formed round corners. Exposed faces of all iron components shall be painted and finished with 2 coats BERGER/equivalent enamel paint over a coat of priming and wood surfaces to be varnished with best quality varnish in 3 coats, fabrication of steel angle box, finishing, assembling of all components, providing best quality PVC stoppers, fixing with requisite numbers and sizes of nuts and bolts and packing, etc all complete as shown in the drawing (if provided) and as per direction of the E-I-C. (Rate is inclusive of delivering the furniture at the selected school).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Teacher's table of 0.675x0.375x0.763m best quality seasoned wood (Jack/Chittagong Chittagong/Gamari/Chittagong teak and structures made of steel angle), painting, varnishing etc. all complete

1.0000

each

3700.00

3700.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3774.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4151.40

VAT

6% of Total

IT

4% of Total

276.76 184.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3700.00

4612.67

Page: 2649 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.01.04

Detailed Analysis Brief Description of Item 2 Supplying Teacher’s Chair (Size : 0.45mx0.4mx0.425m) with back and seat made of best quality seasoned wood (well matured and sapless) like Jack wood, Silkarai, Gamari and Chittagong Teak. Legs and structures be made of steel angle in box form, welded (12mm weld length @ 50mm c/c all through angle box), cold bended and formed round corners. Exposed faces of all iron components shall be painted and finished with 2 coats BERGER/equivalent enamel paint over a coat of priming and wood surfaces to be varnished with best quality varnish in 3 coats, fabrication of steel angle box, finishing, assembling of all components, providing best quality PVC stoppers, fixing with requisite numbers and sizes of nuts and bolts and packing, etc all complete as shown in the drawing (if provided) and as per direction of the E-I-C. (Rate is inclusive of delivering the furniture at the selected school).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Teacher's chair of 0.45x0.4x0.425m of best quality seasoned wood (Jack/Chittagong Chittagong/Gamari/Chittagong teak and structures made of steel angle), painting, varnishing etc. all complete

1.0000

each

3700.00

3700.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3774.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4151.40

VAT

6% of Total

IT

4% of Total

276.76 184.51 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3700.00

4612.67

Page: 2650 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.01.05

Detailed Analysis Brief Description of Item 2 Supplying Steel Almirah (Size : 1.8mx0.9mx0.675m) with required number of drawers, made of 18 BWG MS sheet at front and two parallel sides and 20 BWG MS sheet at back side as per approved design and specification in/c superior quality painting with synthetic (BERGER/equivalent) enamel paint in/c welding, plane surfacing, denting points, fitting and fixing standard lock with two sets of keys and also lock in drawers etc. all complete as per direction of the E-I-C. (Rate is inclusive of delivering the furniture at the selected school).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Steel Almirah of 1.8x0.9x0.675m size made of 18 BWG MS sheet at front and two parallel sides and 20 BWG MS sheet at back side including painting, varnishing etc. all complete

1.0000

each

19290.00

19290.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19675.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21643.38

VAT

6% of Total

1442.89

IT

4% of Total

961.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

19290.00

24048.20

Page: 2651 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.01.06

Detailed Analysis Brief Description of Item 2 Supply of High, Low combined Bench with Book shelf for Primary School: (A). High Bench with Book shelf: Size : 1.450m-(L) x 0.425m(W)x0.730m(H) with plastic top wall thickness 5mm with side wall 25mm height, wall thickness 5mm, Plastic frame weight 5000 gm, Vertical Ribs 25 nos, Horizontal Ribs 7 nos ,Rib height 12mm and thickness 4mm, Plastic top rib sunk size: 6 to 8mm dia for provided screw 38mm dia @ 180mm c/c long direction and 75mm c/c short direction fitted with steel frame size: 1.435m x0.372m x0.713m made of 25mm MS square box , Steel frame for footing bracing made of 38mm MS Square box with same materials, Book shelf fitted with 150mm below top frame with same materials and 5mm guide Rod 15 nos at back side and 2 nos each at left and right side welded with 25mm x 25mmx 2mm MS Angle as shown in drawing, Stopper should be anchored by raised thread. (B). Low Bench: Size : 1.395m-(L)x0.305m(W)x0.380m(H) with plastic top wall thickness 5mm with side wall 25mm height, wall thickness 5mm, Plastic frame weight 3000 gm, Vertical Ribs 21 nos, Horizontal Ribs 7 nos, Rib height 12mm and thickness 4mm, Plastic top rib sunk size 6 to 8mm dia for provided screw 38mm dia @ 180mm c/c long direction and 75mm c/c short direction fitted with steel frame size: 1.325m x0.270m x0.363m made of 25mm MS square box. Steel frame for footing bracing made of 38mm MS Square box, Stopper should be anchored by raised thread as shown in the drawing (if provided) including cost of fabricating, cutting, welding, painting etc. all Complete as per the drawing and direction of the E-I-C. (Rate is inclusive of delivering the furniture at the selected school). BUET test: Physical strength, Breaking strength of Polypropylene impact co Polymer Plastic frame: i) Hardness, Rock well, ii) Tensile strength High and Low Bench for every 1000 nos set/pair or part there of one test for each type of comprising average of 2 (Two) sample. all complete

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

set

Combined Platic High Bench with Book shelf: Size : 1.450m(L)x0.425m(W)x0.730m(H) and Low Bench: Size : 1.395m(L)x0.305m(W)x0.380m(H)

1.0000

set

8352.00

Subtotal-B: Subtotal-C: VAT

8352.00

8352.00

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8519.04

10% Profit ( Add 10% on Subtotal-B) :

9370.94

6% of Total

624.73 Page: 2652 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 IT

Quantity 5

Unit

Rate

6

7

Amount 8

4% of Total

416.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10412.16

Page: 2653 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.01.07

Detailed Analysis Brief Description of Item 2 Teacher Table: Supply Primary school teachers Table as per below specification Table top Raw materials :-Polypropylene Impact Copolymer Plastic Size : - 838mm(L) x 533mm(W) x 775m Table Top: Dimen 838mm(L) x 533mm(W) x 25mm(T) Colour: Deep blue, Brick Red, Black, Orange Plastic Top Weight : 5000gm Steel tube Specification 25mm x 25mm x1.2mm Steel frame Dimension 785mm(L) x 470mm(W) x 750mm Drawer: Two drawer fixed right side, made by high quality 12mm melamine laminated board with two side covered by 12mm laminated board and Back side covered by 3mm thick ply wood. Size:300mmx300mm Other Manufacturing and Supplying teachers table will be made of non-toxic Polypropylene impact Copolymer Plastic and Legs are structure made of ms Round tube -25mm x 1.2mm(22x1.2mm), welded ( 0.5” weld length @ 2” c/c continuously through the MS tube), cold bended & formed strictly as per drawing. The frame of table must be cleaned in 07(seven) stage tank with phosphate chemical method pure along with polyester powder coating for pre-head at 230ºC for 22 minutes in heat heaven for curing the paint. Finishing including assembling of all components and best quality PVC stoppers necessary number and type of nuts and bolts and packing shall be used as shown in the design. Bottom of legs will be provided with PVC cap/shoe as per drawing. Plastic frame top installation : The Polypropylene Impact Copolymer plastic frame top will be tied with MS steel frame (25mm X 378MM and thick1.2mm ) by 1 micron electroplated (No-16) X 4 and 50mm star head Countersunk screw at a distance 75 and 180mm c/c. BUET test: Physical strength, Breaking strength of Polypropylene impact co Polymer Plastic frame: i) Hardness, Rock well, ii) Tensile strength All complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

Polypropylene Impact Copolymer Plastic Table : Size : 838mm(L) x 533mm(W) x 775m Table Top: Dimen 838mm(L) x 533mm(W) x 25mm(T).

1.0000

each

5750.00

Subtotal-B:

5750.00

5750.00

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5865.00 Page: 2654 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

Amount 8 6451.50

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

430.10 286.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7168.33

Page: 2655 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.01.08

Detailed Analysis Brief Description of Item 2 Teacher Chair: Size 550mm(L)x515mm(W)x850m (H) Chair seat Raw materials :- Polypropylene Impact copolymer Chair top Specific on 465mm(L)x480mm(W)x425m (H) Plastic weight 174 Chair colour Deep blue, Brick red, black, Or Steel tu, Specification Round tube -25mm x 1.2mm, Steel frame Dimension 550mm(L) x 515mm(W) x 47 Manufacturing & Supplying teacher chair made of Polypropylene Impact Copolymer Plastic and Legs are structure made of MS Round tube 25mm x 1.2mm (22x1.2 mm), welded (0.5’’ weld length@2 `` C/C continuously through the MS tube), cold bended & formed strictly as per drawing. The frame of chair must be cleaned in 07 (seven) stage tank with phosphate chemical method pure along with polyester powder coating for pre-head at 230ºc for 22 minutes in heat oven for curing the paint to make the permanent of color of steel frame. Finishing including assembling of all components and best quality PVC stoppers necessary number and type of nuts and bolts and packing shall be used as shown in the same must be supplied and get approval from Upazila Engineer/Executive Engineer before manufacturing of the lot. Bottom of legs will be provided with PVC cap/shoe as per drawing BUET test: Physical strength, Breaking strength of Polypropylene impact co Polymer Plastic frame: i) Hardness, Rock well, ii) Tensile strength All complete as per direction of the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Polypropylene Impact Copolymer Plastic Chair, Size:550mm(L)x515mm(W)x850m (H).

1.0000

each

1547.00

1547.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1577.94

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1735.73

VAT

6% of Total

IT

4% of Total

115.72 77.14 Total:

11.02

1547.00

1928.59

Washing, cleaning and polishing with French polish, in/c small repairs as necessary, etc. all complete as per direction of the E-I-C.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2656 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 11.02.01

2 Armed chair

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Varnish (Matt)

0.0750

litre

280.00

21.00

Skilled Labour

0.5000

day

450.00

225.00 246.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

250.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

276.01

VAT

6% of Total

18.40

IT

4% of Total

12.27 Total:

11.02.02

Armless chair

each Varnish (Matt)

0.0750

litre

280.00

21.00

Skilled Labour

0.4000

day

450.00

180.00 201.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

205.02

10% Profit ( Add 10% on Subtotal-B) :

225.52

VAT

6% of Total

IT

4% of Total

15.03 10.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

306.68

250.58

Page: 2657 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 11.02.03

2 Easy chair (caned)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Varnish (Matt)

0.1000

litre

280.00

28.00

Skilled Labour

0.4000

day

450.00

180.00 208.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

212.16

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

233.38

VAT

6% of Total

15.56

IT

4% of Total

10.37 Total:

11.02.04

Easy chair (canvassed)

each Varnish (Matt)

0.1000

litre

280.00

28.00

Skilled Labour

0.4000

day

450.00

180.00 208.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

212.16

10% Profit ( Add 10% on Subtotal-B) :

233.38

VAT

6% of Total

IT

4% of Total

15.56 10.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

259.31

259.31

Page: 2658 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 11.02.05

2 Table (big)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Varnish (Matt)

0.1250

litre

280.00

35.00

Skilled Labour

0.6000

day

450.00

270.00 305.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

311.10

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

342.21

VAT

6% of Total

22.81

IT

4% of Total

15.21 Total:

11.02.06

Table (small)

each Varnish (Matt)

0.1000

litre

280.00

28.00

Skilled Labour

0.5000

day

450.00

225.00 253.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

258.06

10% Profit ( Add 10% on Subtotal-B) :

283.87

VAT

6% of Total

IT

4% of Total

18.92 12.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

380.23

315.41

Page: 2659 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 11.02.07

2 Dressing Table

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Varnish (Matt)

0.2500

litre

280.00

70.00

Skilled Labour

1.0000

day

450.00

450.00 520.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

530.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

583.44

VAT

6% of Total

38.90

IT

4% of Total

25.93 Total:

11.02.08

Sofa Set

each Varnish (Matt)

0.7500

litre

280.00

210.00

Skilled Labour

1.5000

day

450.00

675.00 885.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

902.70

10% Profit ( Add 10% on Subtotal-B) :

992.97

VAT

6% of Total

IT

4% of Total

66.20 44.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

648.27

1103.30

Page: 2660 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 11.02.09

2 Cot

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Varnish (Matt)

0.7500

litre

280.00

210.00

Skilled Labour

1.2500

day

450.00

562.50 772.50

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

787.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

866.75

VAT

6% of Total

57.78

IT

4% of Total

38.52 Total:

11.02.10

Almirah

each Varnish (Matt)

0.7500

litre

280.00

210.00

Skilled Labour

1.5000

day

450.00

675.00 885.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

902.70

10% Profit ( Add 10% on Subtotal-B) :

992.97

VAT

6% of Total

IT

4% of Total

66.20 44.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

963.05

1103.30

Page: 2661 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 11.02.11

2 Meat Safe

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Varnish (Matt)

0.2500

litre

280.00

70.00

Skilled Labour

1.0000

day

450.00

450.00 520.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

530.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

583.44

VAT

6% of Total

38.90

IT

4% of Total

25.93 Total:

11.02.12

Cupboard

each Varnish (Matt)

0.2500

litre

280.00

70.00

Skilled Labour

1.0000

day

450.00

450.00 520.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

530.40

10% Profit ( Add 10% on Subtotal-B) :

583.44

VAT

6% of Total

IT

4% of Total

38.90 25.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

648.27

648.27

Page: 2662 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.02.13

Detailed Analysis Brief Description of Item 2 Sideboard, whatnot, rack, cloth stand

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Varnish (Matt)

0.1500

litre

280.00

42.00

Skilled Labour

0.5000

day

450.00

225.00 267.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

272.34

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

299.57

VAT

6% of Total

19.97

IT

4% of Total

13.31 Total:

11.03

Supplying best quality Cot (Size:2.13mx1.07m) made of best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

each

Cot (2.13x1.07m) of jack wood including varnishing all finishing etc.

1.0000

each

15500.00

Subtotal-B: Subtotal-C:

15500.00 15500.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15810.00

10% Profit ( Add 10% on Subtotal-B) :

17391.00

VAT

6% of Total

IT

4% of Total

1159.40 772.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

332.86

19323.33

Page: 2663 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.04

Detailed Analysis Brief Description of Item 2 Supplying ordinary Table (Size:1.08mx0.76m) made of best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Table (1.08x0.76m) of jack wood including all varnishing finishing etc.

1.0000

each

9000.00

9000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9180.00 10098.00

VAT

6% of Total

673.20

IT

4% of Total

448.80 Total:

11.05

Supplying best quality Tea Table of standard size made of best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

11220.00

each

Tea table (standard size) of jack wood including all varnishing finishing etc,

1.0000

each

3000.00

3000.00 3000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3060.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3366.00

VAT

6% of Total

224.40

IT

4% of Total

149.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9000.00

3740.00

Page: 2664 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.06

Detailed Analysis Brief Description of Item 2 Supplying best quality Secretariat Table (Size: 1.52m x1.07mx0.76m) made of best quality well matured, fully seasoned Chittagong Teak wood (timber should be sapless) in/c superior quality varnishing/French polishing, best quality rexin topping and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Secretariat Table (1.52x1.07x0.76m) of chittagong teak wood including all varnishing finishing etc.

1.0000

each

20000.00

20000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20400.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22440.00

VAT

6% of Total

1496.00

IT

4% of Total

997.33 Total:

11.07

Supplying official Table made of best quality imported 18mm thick scrach proof and termite proof Laminated Melamine Board (LB) with edge covering. Three side covered in same board in black /beech colour and one side opened i/c table top covered with smooth finishing Laminated Melamine Board (LB) etc. all complete as per direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

11.07.01

Official Table LB (Size : 1600LX850WX 750Hmm) (Navana of FTL0560/ Otobi/Hatil/Akther/ Brothers or equivalent best quality)

24933.33

each Official Table LB (Size : 1600LX850WX750Hmm) of FTL0560

1.0000

each

8890.00

Subtotal-B: Subtotal-C:

8890.00 8890.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9067.80

10% Profit ( Add 10% on Subtotal-B) :

9974.58

VAT

6% of Total

IT

4% of Total

664.97 443.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

20000.00

11082.87

Page: 2665 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.07.02

Detailed Analysis Brief Description of Item 2 Official Table LB (Size : 1600LX800WX 750Hmm) (Navana of FTL0562 /Otobi/Hatil/Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Official Table LB (Size : 1600LX800WX750Hmm) of FTL0562

1.0000

each

8290.00

8290.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8455.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9301.38

VAT

6% of Total

620.09

IT

4% of Total

413.39 Total:

11.07.03

Official Table LB (Size : 1600LX800WX 750Hmm (Navana of FTL0561/ Otobi / Hatil/ Akther/ Brothers or equivalent best quality)

10334.87

each Official Table LB (Size : 1600LX800WX750Hmm) of FTL0561

1.0000

each

8000.00

8000.00 8000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8160.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8976.00

VAT

6% of Total

598.40

IT

4% of Total

398.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8290.00

9973.33

Page: 2666 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.07.04

Official Table LB (Size : 1600LX800WX 750Hmm) (Navana of FTL0563/Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

each Official Table LB (Size : 1600LX800WX750Hmm) of FTL0563

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

7790.00

7790.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7945.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8740.38

VAT

6% of Total

582.69

IT

4% of Total

388.46 Total:

11.07.05

Official Table LB (Size : 1400LX800WX 750Hmm) (Navana of FTM0560/Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

9711.53

each Official Table LB (Size : 1400LX800WX750Hmm) of FTM0560

1.0000

each

7790.00

7790.00 7790.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7945.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8740.38

VAT

6% of Total

582.69

IT

4% of Total

388.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7790.00

9711.53

Page: 2667 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.07.06

Official Table LB (Size : 1400LX750WX 750Hmm) (Navana of FTM0562/Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

each Official Table LB (Size : 1400LX750WX750Hmm) of FTM0562

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

7290.00

7290.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7435.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8179.38

VAT

6% of Total

545.29

IT

4% of Total

363.53 Total:

11.07.07

Official Table LB (Size : 1400LX750W X 750Hmm) (Navana of FTM0561 /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

9088.20

each Official Table LB (Size : 1400LX750WX750Hmm) of FTM0561

1.0000

each

6590.00

6590.00 6590.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6721.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7393.98

VAT

6% of Total

492.93

IT

4% of Total

328.62 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7290.00

8215.53

Page: 2668 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.07.08

Detailed Analysis Brief Description of Item 2 Official Table LB (Size : 1400LX750WX 750Hmm) (Navana of FTM0563 /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Official Table LB (Size : 1400LX750WX750Hmm) of FTM0563

1.0000

each

6290.00

6290.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6415.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7057.38

VAT

6% of Total

470.49

IT

4% of Total

313.66 Total:

11.07.09

Official Table LB (Size : 1200LX750WX 750Hmm) (Navana of FTN0560/Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

7841.53

each Official Table LB (Size : 1200LX750WX750Hmm) of FTN0560

1.0000

each

7090.00

7090.00 7090.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7231.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7954.98

VAT

6% of Total

530.33

IT

4% of Total

353.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6290.00

8838.87

Page: 2669 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.07.10

Official Table LB (Size : 1200lLX750WX 750Hmm) (Navana of FTN0562/Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

each Official Table LB (Size : 1200LX750WX750Hmm) of FTN0562

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

6290.00

6290.00

Subtotal-A:

11.07.11

Official Table LB (Size : 1200LX700WX 750Hmm) (Otobi of TPOP001LB/Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6415.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7057.38

VAT

6% of Total

470.49

IT

4% of Total

313.66 Total:

7841.53

13880.00

13880.00

each Official Table LB (Size : 1200LX700WX750Hmm) of TPOP001LB

1.0000

each

13880.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14157.60

10% Profit ( Add 10% on Subtotal-B) :

15573.36

VAT

6% of Total

IT

4% of Total

1038.22 692.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6290.00

17303.73

Page: 2670 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.07.12

Detailed Analysis Brief Description of Item 2 Official Table LB (Size : 1200LX 700WX 750Hmm) (Navana of FTN0561 /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Official Table LB (Size : 1200LX700WX750Hmm) of FTN0561

1.0000

each

6090.00

6090.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6211.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6832.98

VAT

6% of Total

455.53

IT

4% of Total

303.69 Total:

11.07.13

Official Table LB (Size : 1200lLX700WX 750Hmm) (Navana of FTN0563 /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

7592.20

each Official Table LB (Size : 1200lLX700WX750Hmm) of FTN0563

1.0000

each

5690.00

5690.00 5690.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5803.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6384.18

VAT

6% of Total

425.61

IT

4% of Total

283.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6090.00

7093.53

Page: 2671 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.07.14

Official Table LB (Size : 1000LX600WX 750Hmm) (Navana of FTS0563/Otobi/Hatil/ Akther/ Brothers or equivalent best quality)

each Official Table LB (Size : 1000LX600WX750Hmm) of FTS0563

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

4790.00

4790.00

Subtotal-A:

11.08

Supplying Senior officials Table made of best quality imported 18mm thick scrach proof and termite proof Laminated Melamine Board (LB) with edge covering. Three side covered in same board in black /beech colour and one side opened i/c table top covered with smooth finishing termite proof Laminated Melamine Board (LB) etc. all complete as per direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

11.08.01

Senior Official Table LB (Size :1800LX1800W X 750Hmm) (Otobi of TMOP008LB /Navana/i/Hatil/Akther/Brothers or equivalent best quality)

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4885.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5374.38

VAT

6% of Total

358.29

IT

4% of Total

238.86 Total:

5971.53

33300.00

33300.00

each Senior Official Table LB (Size :1800LX1800WX750Hmm) of TMOP008LB

1.0000

each

33300.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

33966.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

37362.60

VAT

6% of Total

IT

4% of Total

2490.84 1660.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4790.00

41514.00

Page: 2672 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.08.02

Detailed Analysis Brief Description of Item 2 Senior Official Table LB (Size :1800LX1800W X750Hmm) (Otobi of TMOP004LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Senior Official Table LB (Size :1800LX1800WX750Hmm) of TMOP004LB

1.0000

each

30870.00

30870.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

31487.40

10% Profit ( Add 10% on Subtotal-B) :

34636.14

VAT

6% of Total

IT

4% of Total

2309.08 1539.38 Total:

11.08.03

Senior Official Table LB (Size :1800LX1800W X750Hmm) (Otobi of TMOP019LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

38484.60

each Senior Official Table LB (Size :1800LX1800WX750Hmm) of TMOP019LB

1.0000

each

22540.00

22540.00 22540.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22990.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25289.88

VAT

6% of Total

IT

4% of Total

1685.99 1123.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

30870.00

28099.87

Page: 2673 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.08.04

Detailed Analysis Brief Description of Item 2 Senior Official Table LB (Size :1800LX1700W X750Hmm) (Otobi of TMOP006LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Senior Official Table LB (Size :1800LX1700WX750Hmm) of TMOP006LB

1.0000

each

29970.00

29970.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30569.40

10% Profit ( Add 10% on Subtotal-B) :

33626.34

VAT

6% of Total

IT

4% of Total

2241.76 1494.50 Total:

11.08.05

Senior Official Table LB (Size :1800LX1000W X 750Hmm) (Navana of FTM0552 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

37362.60

each Senior Official Table LB (Size :1800LX1000WX750Hmm) of FTM0552

1.0000

each

18590.00

18590.00 18590.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18961.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20857.98

VAT

6% of Total

IT

4% of Total

1390.53 927.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

29970.00

23175.53

Page: 2674 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.08.06

Detailed Analysis Brief Description of Item 2 Senior Official Table LB (Size :1800LX900WX 750Hmm) (Navana of FTM0550LB /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Senior Official Table LB (Size :1800LX900WX750Hmm) of FTM0550LB

1.0000

each

9490.00

9490.00

Subtotal-A: Subtotal-B: Subtotal-C:

9679.80

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10647.78

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

709.85 473.23 Total:

11.08.07

Senior Official Table LB (Size : 1650LX800WX 750Hmm) (Navana of FTM6001 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

11830.87

each Senior Official Table LB (Size : 1650LX800WX750Hmm) of FTM6001

1.0000

each

27990.00

27990.00 27990.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28549.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

31404.78

VAT

6% of Total

IT

4% of Total

2093.65 1395.77 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9490.00

34894.20

Page: 2675 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.08.08

Detailed Analysis Brief Description of Item 2 Senior Official Table LB (Size :1600LX900WX 750Hmm) (Otobi of TEO005LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Senior Official Table LB (Size :1600LX900WX750Hmm) of TEO005LB

1.0000

each

17540.00

17540.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17890.80

10% Profit ( Add 10% on Subtotal-B) :

19679.88

VAT

6% of Total

IT

4% of Total

1311.99 874.66 Total:

11.08.09

Senior Official Table LB(Size :1600LX850WX 750Hmm) (Navana of FTM0553 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

21866.53

each Senior Official Table LB(Size :1600LX850WX750Hmm) of FTM0553

1.0000

each

10890.00

10890.00 10890.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11107.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12218.58

VAT

6% of Total

IT

4% of Total

814.57 543.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17540.00

13576.20

Page: 2676 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.08.10

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Senior Official Table LB (Size :1600LX850W X750Hmm) (Navana of FTM6002 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

each Senior Official Table LB (Size :1600LX850WX750Hmm) of FTM6002

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

23990.00

23990.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24469.80

10% Profit ( Add 10% on Subtotal-B) :

26916.78

VAT

6% of Total

IT

4% of Total

1794.45 1196.30 Total:

11.08.11

Senior Official Table LB (Size : 1600lLX750W X 750Hmm) (Otobi of TEOP022LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

29907.53

each Senior Official Table LB (Size : 1600lLX750WX750Hmm) of TEOP022LB

1.0000

each

12440.00

12440.00 12440.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12688.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13957.68

VAT

6% of Total

IT

4% of Total

930.51 620.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23990.00

15508.53

Page: 2677 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.08.12

Detailed Analysis Brief Description of Item 2 Senior Official Table LB (Size : 1400LX750W X 750Hmm) (Navana of TEOP012LB /Otobi//Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Senior Official Table LB (Size : 1400LX750WX750Hmm) of TEOP012LB

1.0000

each

17990.00

17990.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18349.80

10% Profit ( Add 10% on Subtotal-B) :

20184.78

VAT

6% of Total

IT

4% of Total

1345.65 897.10 Total:

11.08.13

Senior Official Table LB (Size :1400LX750W X 750Hmm) (Otobi of TEOP002LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

22427.53

each Senior Official Table LB (Size :1400LX750WX750Hmm) of TEOP002LB

1.0000

each

13880.00

13880.00 13880.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14157.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15573.36

VAT

6% of Total

IT

4% of Total

1038.22 692.15 Total:

11.09

17990.00

17303.73

Supplying Senior officials Table made of best quality imported Engineering wood/Melamine MDF (Medium Density Fiber) board of black /beech or any other approved colour with edge covering. Three sides covered in same board i/c cross legs fixing with any other means of wood/metal and one side opened. Table top covered with smooth finishing Engineering wood/MDF (Medium Density Fiber) with front side foreign black lather etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2678 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.09.01

Detailed Analysis Brief Description of Item 2 Senior Official Table MDF/EW (Size :2438LX1907WX750Hmm) (Otobi of TMOP016WD /Navana/Hatil/Akther/Brothers or equivalent best quality) with drawer unit

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Senior Official Table MDF/EW (Size :2438LX1907WX750Hmm) of TMOP016WD

1.0000

each

77260.00

77260.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

78805.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

86685.72

VAT

6% of Total

IT

4% of Total

5779.05 3852.70 Total:

11.09.02

Senior Official Table MDF/EW (Size :2386LX1059WX750Hmm) (Otobi of TMOP020WD /Navana/Hatil/Akther/Brothers or equivalent best quality) with drawer unit

96317.47

each

Senior Official Table MDF/EW (Size :2386LX1059WX750Hmm) of TMOP020WD

1.0000

each

94900.00

Subtotal-B: Subtotal-C:

94900.00 94900.00

Subtotal-A:

96798.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

106477.80

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

7098.52 4732.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

77260.00

118308.67

Page: 2679 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.09.03

Detailed Analysis Brief Description of Item 2 Senior officials Table-MDF/EW (Size: 1800Lx2175Wx750H mm) (Hatil of HPL-500-125-2-1-67 /Navana/Otobi/Akther/Brothers or equivalent best quality) with drawer unit

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Senior officials Table-MDF/EW (Size: 1800Lx2175Wx750H mm) of HPL-500-125-2-1-67

1.0000

each

55640.00

55640.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56752.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

62428.08

VAT

6% of Total

IT

4% of Total

4161.87 2774.58 Total:

11.09.04

Senior Official Table MDF/EW (Size :2150LX900WX750Hmm) (Navana of FTM1303 /Otobi/Hatil/Akther/Brothers or equivalent best quality) with drawer unit

69364.53

each

Senior Official Table MDF/EW (Size :2150LX900WX750Hmm) of FTM1303

1.0000

each

41690.00

Subtotal-B: Subtotal-C:

41690.00 41690.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

42523.80

10% Profit ( Add 10% on Subtotal-B) :

46776.18

VAT

6% of Total

IT

4% of Total

3118.41 2078.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

55640.00

51973.53

Page: 2680 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.09.05

Detailed Analysis Brief Description of Item 2 Senior officials Table-MDF/EW (Size: 1800Lx1800Wx750H mm) (Hatil of HPL-500-128-2-1-88 /Navana/Otobi/Akther/Brothers or equivalent best quality) with drawer unit

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Senior officials Table-MDF/EW (Size: 1800Lx1800Wx750H mm) of HPL-500-128-2-1-88

1.0000

each

58814.00

58814.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

59990.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

65989.31

VAT

6% of Total

IT

4% of Total

4399.29 2932.86 Total:

11.09.06

Senior Official Table MDF (Size :1800LX900WX750Hmm) (Navana of FTM1301LB /Otobi/Hatil/Akther/Brothers or equivalent best quality)

73321.45

each Senior Official Table MDF (Size :1800LX900WX750Hmm) of FTM1301LB

1.0000

each

35590.00

35590.00 35590.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

36301.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

39931.98

VAT

6% of Total

2662.13

IT

4% of Total

1774.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

58814.00

44368.87

Page: 2681 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.09.07

Detailed Analysis Brief Description of Item 2 Senior officials Table-MDF/EW (Size: 1800Lx1700Wx750H mm) (Otobi of TMOP018WD /Navana/Hatil/Akther/Brothers or equivalent best quality) with drawer unit

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Senior officials Table-MDF/EW (Size: 1800Lx1700Wx750H mm) of TMOP018WD

1.0000

each

52510.00

52510.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

53560.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

58916.22

VAT

6% of Total

IT

4% of Total

3927.75 2618.50 Total:

11.09.08

Senior Official Table MDF/EW (Size :1650LX800WX750Hmm) (Navana of FTM6001LB /Otobi/Hatil/Akther/Brothers or equivalent best quality)

65462.47

each Senior Official Table MDF/EW (Size :1650LX800WX750Hmm) of FTM6001LB

1.0000

each

28750.00

28750.00 28750.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

29325.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

32257.50

VAT

6% of Total

2150.50

IT

4% of Total

1433.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

52510.00

35841.67

Page: 2682 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.09.09

Detailed Analysis Brief Description of Item 2 Senior Official Table MDF/EW (Size :1400LX800WX750Hmm) (Navana of FTM1304 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Senior Official Table MDF/EW (Size :1400LX800WX750Hmm) of FTM1304

1.0000

each

21990.00

21990.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22429.80

10% Profit ( Add 10% on Subtotal-B) :

24672.78

VAT

6% of Total

IT

4% of Total

1644.85 1096.57 Total:

11.10

Supplying Drawer unit made of best quality imported 18mm thick scrach proof and termite proof Laminated Melamine Board (LB) with edge covering of standard (beech/Black) Colour & size, three drawer in high quality imported PVC handle with Center lock. Inside constructed rollers with bearings for smooth operation of sliding drawer etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

11.10.01

Three Drawer unit with wheel (size : 400Wx470Dx700H) (Otobi of FDZ0610 /Navana/Hatil/ Akther/Brothers or equivalent best quality)

27414.20

each Three Drawer unit with wheel (size : 400Wx470Dx700H) of FDZ0610

1.0000

each

5200.00

5200.00 5200.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5304.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5834.40

VAT

6% of Total

IT

4% of Total

388.96 259.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21990.00

6482.67

Page: 2683 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.10.02

Detailed Analysis Brief Description of Item 2 Three Drawer unit without wheel (size : 400Wx470Dx650H) (Otobi of FDZ0611 /Navana/Hatil/Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Three Drawer unit without wheel (size : 400Wx470Dx650H)FDZ0611

1.0000

each

5500.00

5500.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5610.00

10% Profit ( Add 10% on Subtotal-B) :

6171.00

VAT

6% of Total

IT

4% of Total

411.40 274.27 Total:

11.10.03

Three Drawer unit without wheel (size : 400Wx470Dx650H) (Otobi of FDZ0620 /Navana/ Hatil/Akther/ Brothers or equivalent best quality)

6856.67

each Three Drawer unit without wheel (size : 400Wx470Dx650H)FDZ0620

1.0000

each

5000.00

5000.00 5000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5100.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5610.00

VAT

6% of Total

IT

4% of Total

374.00 249.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5500.00

6233.33

Page: 2684 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.10.04

Three Drawer unit with wheel (size : 400Wx470Dx705H) (Otobi of FDZ0619 /Navana/Hatil/Akther/Brothers or equivalent best quality)

each Three Drawer unit with wheel (size : 400Wx470Dx705H)FDZ0619

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

5200.00

5200.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5304.00

10% Profit ( Add 10% on Subtotal-B) :

5834.40

VAT

6% of Total

IT

4% of Total

388.96 259.31 Total:

11.10.05

Two Drawer unit with wheel (size : 400Wx470Dx705H) (Otobi of FDZ0617 /Navana/ Hatil/Akther/Brothers or equivalent best quality)

6482.67

each Two Drawer unit with wheel (size : 400Wx470Dx705H)FDZ0617

1.0000

each

4000.00

4000.00 4000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4080.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4488.00

VAT

6% of Total

IT

4% of Total

299.20 199.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5200.00

4986.67

Page: 2685 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.10.06

Detailed Analysis Brief Description of Item 2 Two Drawer unit without wheel (size : 400Wx470Dx650H) (Otobi of FDZ0618/ Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Two Drawer unit without wheel (size : 400Wx470Dx650H)FDZ0618

1.0000

each

3800.00

3800.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3876.00

10% Profit ( Add 10% on Subtotal-B) :

4263.60

VAT

6% of Total

IT

4% of Total

284.24 189.49 Total:

11.11

Supplying Conference Table made of best quality imported 18mm thick scrach proof and termite proof Laminated Melamine Board (LB) frame with standard size leg and 25mm thick scrach proof and termite proof Laminated Melamine Board (LB) top i/c edge covering of black /beech colour etc. all complete as per direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

11.11.01

Conference Table- Corner LB (size: 625Lx625Wx750Hmm) (Navana of FCM 0580 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

4737.33

each Conference Table- Corner LB (size: 625Lx625Wx750Hmm) of FCM 0580

1.0000

each

4000.00

4000.00 4000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4080.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4488.00

VAT

6% of Total

IT

4% of Total

299.20 199.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3800.00

4986.67

Page: 2686 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.11.02

Detailed Analysis Brief Description of Item 2 Conference Table- Short Middle LB (size: 600Lx600Wx750Hmm) (Navana of FCM 0581/ Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Conference Table- Short Middle LB (size: 600Lx600Wx750Hmm)- FCM 0581

1.0000

each

4000.00

4000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4080.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4488.00

VAT

6% of Total

IT

4% of Total

299.20 199.47 Total:

11.11.03

Conference Table- Long Middle LB (size: 1200Lx600Wx750Hmm) (Navana of FCM 0582 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

4986.67

each

Conference Table- Long Middle LB (size: 1200Lx600Wx750Hmm) of FCM 0582

1.0000

each

5900.00

Subtotal-B: Subtotal-C:

5900.00 5900.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6018.00

10% Profit ( Add 10% on Subtotal-B) :

6619.80

VAT

6% of Total

IT

4% of Total

441.32 294.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4000.00

7355.33

Page: 2687 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.11.04

Detailed Analysis Brief Description of Item 2 Conference Table- Long Middle LB (size: 1400Lx600Wx750Hmm) (Navana of FCM 0583 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Conference Table- Long Middle LB (size: 1400Lx600Wx750Hmm) of FCM 0583

1.0000

each

6300.00

6300.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6426.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7068.60

VAT

6% of Total

IT

4% of Total

471.24 314.16 Total:

11.11.05

Conference Table- Long Middle LB (size: 1600Lx600Wx750Hmm) (Navana of FCM 0584 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

7854.00

each

Conference Table- Long Middle LB (size: 1600Lx600Wx750Hmm) of FCM 0584

1.0000

each

7000.00

Subtotal-B: Subtotal-C:

7000.00 7000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7140.00

10% Profit ( Add 10% on Subtotal-B) :

7854.00

VAT

6% of Total

IT

4% of Total

523.60 349.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6300.00

8726.67

Page: 2688 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.12

Detailed Analysis Brief Description of Item 2 Supplying best quality Dressing Table as per approved design, made of best quality well matured, fully seasoned Chittagong Teak wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing to all wood surfaces, providing best quality Belgium Mirror (Size:1.08mx0.41m) etc. all complete and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Dressing Table of Chittagong teak wood including Belgium mirror (1.08x0.41m) including all varnishing, finishing etc.

1.0000

each

11500.00

11500.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11730.00

10% Profit ( Add 10% on Subtotal-B) :

12903.00

VAT

6% of Total

IT

4% of Total

860.20 573.47 Total:

11.13

Supplying Dining Table (Size:1.83mx0.96mx0.76m) made of best quality well matured, fully seasoned Chittagong Teak wood (timber should be sapless) in/c superior quality varnishing/ French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

14336.67

each

Dining Table of chittagong teak wood (1.83x0.96x0.76m) in/c all varnishing, finishing etc.

1.0000

each

20000.00

Subtotal-B: Subtotal-C:

20000.00 20000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20400.00

10% Profit ( Add 10% on Subtotal-B) :

22440.00

VAT

6% of Total

IT

4% of Total

1496.00 997.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11500.00

24933.33

Page: 2689 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.14

Detailed Analysis Brief Description of Item 2 Supplying cushioned Chair as per approved design and direction, made of best quality well matured, fully seasoned Chittagong Teak wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, best quality high tempered spring and cushion in sit, back and handle etc. all complete as per direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Cushioned chair of jack wood (standard size) in/c all varnishing, finishing etc.

1.0000

each

6000.00

6000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6120.00

10% Profit ( Add 10% on Subtotal-B) :

6732.00

VAT

6% of Total

IT

4% of Total

448.80 299.20 Total:

11.15

6000.00

7480.00

Supplying Swivel Chair of official standard with handle or without handle of special size of zinc phosphate coated oven backed powder paint finish milds steel structure, Chrome plated polymer cast leg with 5 nos castors (wheels). High quality PVC handles. Fully revolving and back tilt facility of high or medium or low back. Hydraulically height adjustable mechanism. Foam cushioning seat and back pasted on imported ply wood and covered by foreign Fabric or Rexene and all surface are black colour coat finish etc all complete as per design and direction of the E-IC. (This item includes delivering the furniture at the instructed place).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2690 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.15.01

Detailed Analysis Brief Description of Item 2 Swivel Chair without handle (Navana of FCJ 2262 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Swivel Chair without handle of FCJ 2262

1.0000

each

4900.00

4900.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4998.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5497.80

VAT

6% of Total

366.52

IT

4% of Total

244.35 Total:

11.15.02

Swivel Chair without handle (Otobi of CSEP154/CSEP009 /Navana/Hatil/ Akther/ Brothers or equivalent best quality)

6108.67

each Swivel Chair without handle of CSEP154/CSEP009

1.0000

each

6500.00

6500.00 6500.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6630.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7293.00

VAT

6% of Total

486.20

IT

4% of Total

324.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4900.00

8103.33

Page: 2691 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.15.03

Detailed Analysis Brief Description of Item 2 Swivel Chair without handle (Otobi of CSEP009 / Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Swivel Chair without handle of CSEP009

1.0000

each

6110.00

6110.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6232.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6855.42

VAT

6% of Total

457.03

IT

4% of Total

304.69 Total:

11.15.04

Swivel Chair normal back with handle (Otobi of CSEP002 /Navana/Hatil/Akther/Brothers or equivalent best quality)

7617.13

each Swivel Chair normal back with handle of CSEP002

1.0000

each

7550.00

7550.00 7550.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7701.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8471.10

VAT

6% of Total

564.74

IT

4% of Total

376.49 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6110.00

9412.33

Page: 2692 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.15.05

Detailed Analysis Brief Description of Item 2 Swivel Chair normal back with handle (Navana of FCJ 2261 /Otobi/ Hatil/ Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Swivel Chair normal back with handle of FCJ 2261

1.0000

each

5700.00

5700.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5814.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6395.40

VAT

6% of Total

426.36

IT

4% of Total

284.24 Total:

11.15.06

Swivel Chair medium back with handle (Otobi of CSSP001 /Navana/Hatil/Akther/Brothers or equivalent best quality)

7106.00

each Swivel Chair medium back witht handle of CSSP001

1.0000

each

9770.00

Subtotal-B: Subtotal-C:

9770.00 9770.00

Subtotal-A:

9965.40

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10961.94

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

730.80

IT

4% of Total

487.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5700.00

12179.93

Page: 2693 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.15.07

Detailed Analysis Brief Description of Item 2 Swivel Chair medium back with handle (Navana of FCM 2211 /Otobi/Hatil/Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Swivel Chair medium back witht handle of FCM 2211

1.0000

each

8890.00

8890.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9067.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9974.58

VAT

6% of Total

664.97

IT

4% of Total

443.31 Total:

11.15.08

Swivel Chair medium back with handle (Navana of FCN 2209/2210 /Otobi/Hatil/ Akther/Brothers or equivalent best quality)

11082.87

each Swivel Chair medium back with handle of FCN 2209/2210

1.0000

each

9400.00

Subtotal-B: Subtotal-C:

9400.00 9400.00

Subtotal-A:

9588.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10546.80

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

703.12

IT

4% of Total

468.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8890.00

11718.67

Page: 2694 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.15.09

Detailed Analysis Brief Description of Item 2 Swivel Chair medium back with handle (Navana of PCM 2209 /Otobi/Hatil/ Akther /Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Swivel Chair medium back witht handle of PCM 2209

1.0000

each

10000.00

10000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10200.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11220.00

VAT

6% of Total

748.00

IT

4% of Total

498.67 Total:

11.15.10

Swivel Chair high back with handle (Otobi of CSSP002/003 /Navana/Hatil/ Akther/ Brothers or equivalent best quality)

12466.67

each Swivel Chair medium back witht handle of PCM 2209

1.0000

each

10000.00

10000.00 10000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10200.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11220.00

VAT

6% of Total

748.00

IT

4% of Total

498.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10000.00

12466.67

Page: 2695 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.15.11

Detailed Analysis Brief Description of Item 2 Swivel Chair high back with handle (Navana of FCH 2209/2211 /Otobi/Hatil/Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Swivel Chair high back with handle of FCH 2209/2211

1.0000

each

9800.00

9800.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9996.00 10995.60

VAT

6% of Total

733.04

IT

4% of Total

488.69 Total:

11.15.12

Swivel Chair high back with handle (semi-executive type) (Otobi of CSPP004 / Navana /Hatil/Akther/Brothers or equivalent best quality)

12217.33

each Swivel Chair high back witht handle (semi-executive type) of CSPP004

1.0000

each

14770.00

Subtotal-B: Subtotal-C:

14770.00 14770.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15065.40

10% Profit ( Add 10% on Subtotal-B) :

16571.94

VAT

6% of Total

IT

4% of Total

1104.80 736.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9800.00

18413.27

Page: 2696 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.15.13

Detailed Analysis Brief Description of Item 2 Swivel Chair high back with handle (semi-executive type) (Navana of FCM 2215/FCH 2208/FCH 2214 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Swivel Chair high back with handle (semi-executive type) of FCM 2215/FCH 2208/FCH 2214

1.0000

each

11700.00

11700.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11934.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13127.40

VAT

6% of Total

IT

4% of Total

875.16 583.44 Total:

11.15.14

Swivel Chair high back with handle (executive type) (Navana of PCH 2200 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

14586.00

each Swivel Chair high back with handle (executive type) of PCH 2200

1.0000

each

27800.00

27800.00 27800.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28356.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

31191.60

VAT

6% of Total

2079.44

IT

4% of Total

1386.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11700.00

34657.33

Page: 2697 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.15.15

Detailed Analysis Brief Description of Item 2 Swivel Chair high back with handle (executive type) (Otobi of CSPP002 /Navana/ Hatil/Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Swivel Chair high back witht handle (executive type) of CSPP002

1.0000

each

28860.00

28860.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

29437.20

10% Profit ( Add 10% on Subtotal-B) :

32380.92

VAT

6% of Total

IT

4% of Total

2158.73 1439.15 Total:

11.16

Supplying of Easy Chair of standard size with plastic cone of standard size, made of best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing or French polishing and finishing, etc. all complete as per design (if provided) etc. all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

35978.80

each

Easy chair of jack wood (standard size) in/c all varnishing, finishing etc.

1.0000

each

12000.00

Subtotal-B: Subtotal-C:

12000.00 12000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12240.00

10% Profit ( Add 10% on Subtotal-B) :

13464.00

VAT

6% of Total

IT

4% of Total

897.60 598.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

28860.00

14960.00

Page: 2698 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.17

Detailed Analysis Brief Description of Item 2 Supplying best quality armed ChairJack wood (wooden sit and back) of standard size, made of best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing/ French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Armed Chair of jack wood (standard size) in/c all varnishing, finishing etc.

1.0000

each

5500.00

5500.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5610.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6171.00

VAT

6% of Total

411.40

IT

4% of Total

274.27 Total:

11.18

5500.00

6856.67

Supplying best quality armed Visitor Chair of official standard special size of zinc phosphate coated oven backed powder paint finish stainless steel tube body of 4 legs with two arm made by Stainless Steel tube or pre approved materials . Foam cushioning seat and back pasted on imported ply wood and covered by foreign Fabric or Rexene and all surface are black colour coat finish etc all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2699 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.18.01

Armed chair standard normal (Otobi of CFVE003 / Navana/Hatil/ Akther/ Brothers or equivalent best quality)

each Armed chair standard normal of CFVE003

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

3220.00

3220.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3284.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3612.84

VAT

6% of Total

240.86

IT

4% of Total

160.57 Total:

11.18.02

Armed chair standard normal (Navana of FCF 2305 /CFVP011 / Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

4014.27

each Armed chair standard normal of FCF 2305/CFVP011

1.0000

each

4200.00

4200.00 4200.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4284.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4712.40

VAT

6% of Total

314.16

IT

4% of Total

209.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3220.00

5236.00

Page: 2700 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.18.03

Armed chair standard normal (Navana of FCF 2313 / Otobi/ Hatil/ Akther /Brothers or equivalent best quality)

each Armed chair standard normal of FCF 2313

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

4090.00

4090.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4171.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4588.98

VAT

6% of Total

305.93

IT

4% of Total

203.95 Total:

11.18.04

Armed chair standard medium (Navana of FCF 2303/2304 /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

5098.87

each Armed chair standard medium of FCF 2303/2304

1.0000

each

4400.00

4400.00 4400.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4488.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4936.80

VAT

6% of Total

329.12

IT

4% of Total

219.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4090.00

5485.33

Page: 2701 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.18.05

Armed chair standard fancy light (Navana of FCF 2301/ CFVP011 / Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

each Armed chair standard fancy light of FCF 2301//CFVP011

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

4800.00

4800.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4896.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5385.60

VAT

6% of Total

359.04

IT

4% of Total

239.36 Total:

11.18.06

Armed chair standard fancy heavy (Navana of FCF 2302 /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

5984.00

each Armed chair standard fancy heavy of FCF 2302

1.0000

each

5300.00

5300.00 5300.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5406.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5946.60

VAT

6% of Total

396.44

IT

4% of Total

264.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4800.00

6607.33

Page: 2702 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.18.07

Detailed Analysis Brief Description of Item 2 Armed chair standard fancy heavy (Otobiof CFVP006/007 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Armed chair standard fancy heavy of CFVP006/007

1.0000

each

6110.00

6110.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6232.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6855.42

VAT

6% of Total

457.03

IT

4% of Total

304.69 Total:

11.18.08

Armed chair standard fancy heavy (Navana of FCV 2207/CFVP053/ Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

7617.13

each Armed chair standard fancy heavy of FCV 2207/CFVP053

1.0000

each

7790.00

7790.00 7790.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7945.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8740.38

VAT

6% of Total

582.69

IT

4% of Total

388.46 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6110.00

9711.53

Page: 2703 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.18.09

Detailed Analysis Brief Description of Item 2 Armed chair standard fancy heavy (Navana of FCV 2209/2210/CFVP034 / Otobi/Hatil/ Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Armed chair standard fancy heavy of FCV 2209/2210/CFVP034

1.0000

each

8190.00

8190.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8353.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9189.18

VAT

6% of Total

IT

4% of Total

612.61 408.41 Total:

11.18.10

Armed chair standard fancy heavy (Otobi of CFVP053 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

10210.20

each Armed chair standard fancy heavy of CFVP053

1.0000

each

8440.00

8440.00 8440.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8608.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9469.68

VAT

6% of Total

IT

4% of Total

631.31 420.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8190.00

10521.87

Page: 2704 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.18.11

Detailed Analysis Brief Description of Item 2 Armed chair standard fancy heavy (Navana of FCV 2204 /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Armed chair standard fancy heavy of FCV 2204

1.0000

each

8890.00

8890.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9067.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9974.58

VAT

6% of Total

664.97

IT

4% of Total

443.31 Total:

11.18.12

Armed chair standard fancy heavy (Otobi of CFVP012 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

11082.87

each Armed chair standard fancy heavy of CFVP012

1.0000

each

9990.00

9990.00 9990.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10189.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11208.78

VAT

6% of Total

747.25

IT

4% of Total

498.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8890.00

12454.20

Page: 2705 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.19

Detailed Analysis Brief Description of Item 2 Supplying best quality armless Chair (wooden sit and back) of standard size made of best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

500.00

500.00

each

Armed Less Chair of jack wood (standard size) in/c all varnishing, finishing etc.

1.0000

each

500.00

Subtotal-A:

11.20

Supplying best quality armless Visitor Chair of official standard special size of zinc phosphate coated oven backed powder paint finish stainless steel tube body with 4 legs. Foam cushioning seat and back pasted on imported ply wood and covered by foreign Fabric /Rexene and all surface are black colour coat finish etc all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

11.20.01

Armless chair standard normal (Otobi of CFVE002 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

510.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

561.00

VAT

6% of Total

37.40

IT

4% of Total

24.93 Total:

623.33

2000.00

2000.00

each Armless chair standard normal of CFVE002

1.0000

each

2000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2040.00

10% Profit ( Add 10% on Subtotal-B) :

2244.00

VAT

6% of Total

IT

4% of Total

149.60 99.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2493.33

Page: 2706 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.20.02

Detailed Analysis Brief Description of Item 2 Armless chair standard normal (Navana of FCF 2307 LR /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Armless chair standard normal of FCF 2307 LR

1.0000

each

2200.00

2200.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2244.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2468.40

VAT

6% of Total

164.56

IT

4% of Total

109.71 Total:

11.20.03

Armless chair standard normal (Navana of FCF 2307 FF /Otobi/ Hatil/ Akther/Brothers or equivalent best quality)

2742.67

each Armless chair standard normal of FCF 2307 FF

1.0000

each

2400.00

2400.00 2400.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2448.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2692.80

VAT

6% of Total

179.52

IT

4% of Total

119.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2200.00

2992.00

Page: 2707 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.20.04

Detailed Analysis Brief Description of Item 2 Armless chair standard normal (Otobi of CFVE005/006 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Armless chair standard normal of CFVE005/006

1.0000

each

2560.00

2560.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2611.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2872.32

VAT

6% of Total

191.49

IT

4% of Total

127.66 Total:

11.20.05

Armless chair standard medium (Navana of FCF 2307 LR/ Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

3191.47

each Armless chair standard medium of FCF 2307 LR

1.0000

each

3400.00

3400.00 3400.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3468.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3814.80

VAT

6% of Total

254.32

IT

4% of Total

169.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2560.00

4238.67

Page: 2708 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.20.06

Detailed Analysis Brief Description of Item 2 Armless chair standard medium (Navana of FCF 2307 FF /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Armless chair standard medium of FCF 2307 FF

1.0000

each

3800.00

3800.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3876.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4263.60

VAT

6% of Total

284.24

IT

4% of Total

189.49 Total:

11.20.07

Armless chair standard fancy light (Otobi of CFVP001 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

4737.33

each Armless chair standard fancy light of CFVP001

1.0000

each

4000.00

4000.00 4000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4080.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4488.00

VAT

6% of Total

299.20

IT

4% of Total

199.47 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3800.00

4986.67

Page: 2709 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.20.08

Detailed Analysis Brief Description of Item 2 Armless chair standard fancy thick Plastic seat and back (Otobi of CFVP057 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Armless chair standard fancy thick Plastic seat and back of CFVP057

1.0000

each

4500.00

4500.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4590.00

10% Profit ( Add 10% on Subtotal-B) :

5049.00

VAT

6% of Total

IT

4% of Total

336.60 224.40 Total:

11.20.09

Armless chair sytandard fancy light (Otobi of CFVP010 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

5610.00

each Armless chair sytandard fancy light of CFVP010

1.0000

each

4890.00

Subtotal-B: Subtotal-C:

4890.00 4890.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4987.80

10% Profit ( Add 10% on Subtotal-B) :

5486.58

VAT

6% of Total

IT

4% of Total

365.77 243.85 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4500.00

6096.20

Page: 2710 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.20.10

Detailed Analysis Brief Description of Item 2 Armless chair standard fancy light (Otobi of CFVP030 /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Armless chair standard fancy light of CFVP030

1.0000

each

5650.00

5650.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5763.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6339.30

VAT

6% of Total

422.62

IT

4% of Total

281.75 Total:

11.21

Supplying Dress stand of standard size, made of best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

7043.67

each

Dress Stand of jack wood (standard size) in/c all varnishing, finishing etc.

1.0000

each

3000.00

3000.00 3000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3060.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3366.00

VAT

6% of Total

IT

4% of Total

224.40 149.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5650.00

3740.00

Page: 2711 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.22

Detailed Analysis Brief Description of Item 2 Supplying Dress stand of standard size with coat rack on one side, made of best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Dress Stand with coat rack one side of jack wood (standard size) in/c all varnishing, finishing etc.

1.0000

each

3000.00

3000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3060.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3366.00

VAT

6% of Total

224.40

IT

4% of Total

149.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3000.00

3740.00

Page: 2712 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.23

Detailed Analysis Brief Description of Item 2 Supplying, fitting and fixing door and window palmate (150mm wide) in/c wooden frog and 25mm dia wooden rod with best quality well matured, fully seasoned jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

Jack Wood

0.0040

m3

80540.00

322.16

38mm screw

6.0000

each

0.35

2.10

Varnish (Matt)

0.0750

litre

280.00

21.00

Carpenter

0.0400

day

680.00

27.20

Skilled Labour

0.5400

day

450.00

243.00 615.46

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

627.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

690.55

VAT

6% of Total

IT

4% of Total

46.04 30.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

767.27

Page: 2713 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.24

Detailed Analysis Brief Description of Item 2 Supplying Almirah without front glass (Size:1.52mx1.07mx0.46m) with 4 shelves, made of best quality well matured, fully seasoned Chittagong Teak wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Almirah of chittagong teak wood (1.52x1.07x0.46m) with in/c 4 shelves all varnishing, finishing etc.

1.0000

each

22000.00

22000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22440.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24684.00

VAT

6% of Total

1645.60

IT

4% of Total

1097.07 Total:

11.25

Supplying Almirah with front glass (Size:1.52mx1.07mx0.46m) with 4 shelves, made of best quality well matured, fully seasoned Chittagong Teak wood (timber should be sapless) in/c superior quality varnishing/ French polishing and finishing, in/c glass front, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place).

27426.67

each

Almirah of chittagong teak wood (1.52x1.07x 0.46m) in/c glass front ,all varnishing, finishing etc.

1.0000

each

22000.00

22000.00 22000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22440.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24684.00

VAT

6% of Total

1645.60

IT

4% of Total

1097.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

22000.00

27426.67

Page: 2714 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.26

Detailed Analysis Brief Description of Item 2 Supplying Steel Almirah (Size:1.83mx0.91mx0.61m) with required number of drawers, made of 18 BWG MS sheet at front and two parallel sides and 20 BWG MS sheet at back side as per approved design and specification in/c superior quality painting with synthetic (BERGER/equivalent) enamel paint in/c welding, plane surfacing, denting points, fitting and fixing standard lock with two sets of keys and also lock in drawers etc. all complete as per direction of the E-I-C. (Rate is inclusive of delivering the furniture at the selected school).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Steel Almirah of (1.83x0.91x0.61m) size made of BWG MS sheet at front and two parallel sides and 20 BWG MS sheet at back side including all painting, finishing etc.

1.0000

each

19290.00

19290.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19675.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21643.38

VAT

6% of Total

1442.89

IT

4% of Total

961.93 Total:

11.27

19290.00

24048.20

Supply of best quality Steel Almirah made of rivet less fully mig welded 0.7 & 0.8 mm thick imported cold rolled mild steel. All surface of Mild steel (MS) chemically de-rusted, zinc phosphate coated and oven backed powder paint finish with high quality imported S type handle with office lock. Inside constructed with one fixed shelf with two nos. drawer and three nos. height adjustable shelves on MS slot. Almirah to be stands on box type MS leg. All bands are created by automatic banding machine and all surface are black colour coat finish etc all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2715 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.27.01

Detailed Analysis Brief Description of Item 2 Steel Almirah 915Wx483Dx1929H mm size

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Steel Almirah 915Wx483Dx1929H mm size

1.0000

each

24990.00

24990.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25489.80

10% Profit ( Add 10% on Subtotal-B) :

28038.78

VAT

6% of Total

1869.25

IT

4% of Total

1246.17 Total:

11.28

Supplying Steel File Cabinet (Size:1.37m x0.46mx0.61m) with 4 drawers made of 18 BWG MS sheet as per approved design and specification in/c superior quality painting with synthetic (BERGER/equivalent) enamel paint, welding, plain surfacing, denting points all finishing, fitting and fixing standard lock with two sets of keys and also lock in drawers etc. all complete as per direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

31154.20

each

Steel File Cabinet (1.37x0.46x0.61m) with 4 drawers made of 18 BWG steel sheet in/c all painting, finishing etc.

1.0000

each

13190.00

13190.00 13190.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13453.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14799.18

VAT

6% of Total

986.61

IT

4% of Total

657.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

24990.00

16443.53

Page: 2716 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

11.29

Supply of best quality Steel File Cabinet made of rivet less fully mig welded 0.7 & 0.8 mm thick imported cold rolled mild steel. All surface of Mild steel (MS) chemically de-rusted, zinc phosphate coated and oven backed powder paint finish with high quality imported PVC handle with Center lock. Inside constructed rollers with solid steel bearings for smooth operation of sliding drawer. File Cabinet to be stands on same flat bed. All bands are created by automatic banding machine and all surface are black colour coat finish etc all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

11.29.01

Steel File Cabinet 4 drawer 620Wx476Dx1390H mm size

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Steel File Cabinet 4 drawer 620Wx476Dx1390H mm size

1.0000

each

21090.00

21090.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

21511.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

23662.98

VAT

6% of Total

IT

4% of Total

1577.53 1051.69 Total:

11.29.02

Steel File Cabinet 3 drawer 620Wx476Dx1070H mm size

26292.20

each Steel File Cabinet 3 drawer 620Wx476Dx1070H mm size

1.0000

each

18430.00

Subtotal-B: Subtotal-C:

18430.00 18430.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18798.60

10% Profit ( Add 10% on Subtotal-B) :

20678.46

VAT

6% of Total

IT

4% of Total

1378.56 919.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

21090.00

22976.07

Page: 2717 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.29.03

Detailed Analysis Brief Description of Item 2 Steel File Cabinet 2 drawer 620Wx476Dx748H mm size

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Steel File Cabinet 2 drawer 620Wx476Dx748H mm size

1.0000

each

15210.00

15210.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15514.20

10% Profit ( Add 10% on Subtotal-B) :

17065.62

VAT

6% of Total

1137.71

IT

4% of Total

758.47 Total:

11.30

Supplying Steel Chest of Drawer (Size:1.37m x1.22mx0.53m) with 4 shelves, made of 18 BWG MS sheet as per approved design and specification in/c superior quality painting with synthetic (BERGER/equivalent) enamel paint, welding, plain surfacing, denting points all finishing, fitting and fixing standard lock with two sets of keys and also lock in drawers etc. all complete as per direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

18961.80

each

Steel Chest of Drawer (1.37x1.22x0.53m) with 4 shelves made of 18 BWG steel sheet in/c all painting, finishing etc.

1.0000

each

21690.00

21690.00 21690.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22123.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24336.18

VAT

6% of Total

1622.41

IT

4% of Total

1081.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15210.00

27040.20

Page: 2718 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.31

Detailed Analysis Brief Description of Item 2 Supplying Wooden Whatnot (Size:1.22mx0.38mx0.91m) with 3 shelves, made of best quality well matured, fully seasoned Jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, etc. all complete as per design (if provided) and direction of the E-I-C. (This item includes all fittings, fixings and delivering the furniture at the instructed place)..

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Whatnot (1.22x0.38x0.91m) with 3 shelves made of jack wood in/c all varnishing, finishing etc.

1.0000

each

5500.00

5500.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5610.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6171.00

VAT

6% of Total

411.40

IT

4% of Total

274.27 Total:

11.32

Supplying Wooden Box (Size:1.22mx0.91mx0.76m) made of best quality well matured, fully seasoned Jack wood (timber should be sapless) in/c superior quality varnishing/French polishing and finishing, locking arrangement, etc all complete as per design (if provided) and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

6856.67

each

Wood Box (1.22x0.91x0.76m) made of jack wood in/c all varnishing, finishing etc.

1.0000

each

3500.00

3500.00 3500.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3570.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3927.00

VAT

6% of Total

261.80

IT

4% of Total

174.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5500.00

4363.33

Page: 2719 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

11.33

Supplying Multipurpose shelf of standard Colour & size of local best quality, 16mm thick scrach proof and termite proof finished malamine laminated wood particle board with in top, bottom, two short side and shelf PVC edging i/c 4 nos shelvs, 3nos front side are covered by 3mm sliding glass on PVC channel and one no. shelf covered by laminated board shutter with hinge, handle and tower bolt. Back side covered by 5mm thick ply wood. Fully knowed down system by using Housing, Dowels, T-nut, JRN nut, wood pin etc all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

11.33.01

Multipurpose shelf beech colour (size :1200Lx400Dx1800Hmm) (Navana of HSM 0380 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Multipurpose shelf beech colour (size :1200Lx400Dx1800Hmm) of HSM 0380

1.0000

each

15540.00

15540.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15850.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

17435.88

VAT

6% of Total

1162.39

IT

4% of Total

774.93 Total:

11.33.02

Multipurpose shelf beech colour (size 800Lx400Dx1800Hmm) (Navana of HSM 0381 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

19373.20

each Multipurpose shelf beech colour (size 800Lx400Dx1800Hmm) of HSM 0381

1.0000

each

12440.00

Subtotal-B: Subtotal-C:

12440.00 12440.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12688.80

10% Profit ( Add 10% on Subtotal-B) :

13957.68

VAT

6% of Total

IT

4% of Total

930.51 620.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15540.00

15508.53

Page: 2720 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.33.03

Detailed Analysis Brief Description of Item 2 Multipurpose shelf beech colour (size :600Lx300Dx1800Hmm) (Navana of HSM 0387 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Multipurpose shelf beech colour (size :600Lx300Dx1800Hmm) of HSM 0387

1.0000

each

7690.00

7690.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7843.80

10% Profit ( Add 10% on Subtotal-B) :

8628.18

VAT

6% of Total

IT

4% of Total

575.21 383.47 Total:

11.33.04

Multipurpose shelf beech colour (size :800Lx350Dx1800Hmm) (Navana of HSM 0386 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

9586.87

each Multipurpose shelf beech colour (size :800lx350Dx1800Hmm) of HSM 0386

1.0000

each

8190.00

8190.00 8190.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8353.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9189.18

VAT

6% of Total

IT

4% of Total

612.61 408.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7690.00

10210.20

Page: 2721 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.33.05

Detailed Analysis Brief Description of Item 2 Multipurpose shelf beech colour (size : 600Lx350Dx1800Hmm) (Navana of HSM 0382 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Multipurpose shelf beech colour (size : 600lx350Dx1800Hmm) of HSM 0382

1.0000

each

7690.00

7690.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7843.80

10% Profit ( Add 10% on Subtotal-B) :

8628.18

VAT

6% of Total

IT

4% of Total

575.21 383.47 Total:

11.34

Supplying Computer table of standard Colour & size of local best quality, made by 16mm thick scrach proof and termite proof finished malamine laminated wood particle board with PVC edging i/c CPU, UPS, Monitor, Printer & Mouse etc. placing arrangement and attached keyboard tray slided by channel and wheel etc all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

11.34.01

Computer Table (size :1200Lx600Dx7 50Hmm) (Otobi of TEOB002LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

9586.87

each Computer Table (size :1200lx600Dx750Hmm) of TEOB002LB

1.0000

each

9250.00

9250.00 9250.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9435.00 10378.50 691.90 461.27

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7690.00

11531.67

Page: 2722 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.34.02

Detailed Analysis Brief Description of Item 2 Computer Table (size :1100Lx600Dx 750Hmm) (Otobi of TCCP001LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Computer Table (size :1100Lx600Dx750Hmm) of TCCP001LB

1.0000

each

9770.00

9770.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9965.40 10961.94

VAT

6% of Total

730.80

IT

4% of Total

487.20 Total:

11.34.03

Computer Table (size :910Lx450Dx 750Hmm) (Otobi of SROP007LB /Navana/Hatil/ Akther/Brothers or equivalent best quality)

12179.93

each Computer Table (size :910lx450Dx750Hmm) of SROP007LB

1.0000

each

7330.00

7330.00 7330.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7476.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8224.26

VAT

6% of Total

548.28

IT

4% of Total

365.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9770.00

9138.07

Page: 2723 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.34.04

Detailed Analysis Brief Description of Item 2 Computer Table (size 1000Lx500Dx 750Hmm) (Navana of FTC 0661 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Computer Table (size 1000Lx500Dx750Hmm) of FTC 0661

1.0000

each

6190.00

6190.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6313.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6945.18

VAT

6% of Total

463.01

IT

4% of Total

308.67 Total:

11.34.05

Computer Table (size :1050Lx450Dx 700Hmm) (Otobi of TCCP001LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

7716.87

each Computer Table (size :1050lx450Dx700Hmm) of TCCP001LB

1.0000

each

8880.00

8880.00 8880.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

9057.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9963.36

VAT

6% of Total

664.22

IT

4% of Total

442.82 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6190.00

11070.40

Page: 2724 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.34.06

Detailed Analysis Brief Description of Item 2 Computer Table (size :800Lx500Dx 1400Hmm) (Otobi of TCCP007LB /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Computer Table (size :800Lx500Dx1400Hmm) of TCCP007LB

1.0000

each

8000.00

8000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8160.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8976.00

VAT

6% of Total

598.40

IT

4% of Total

398.93 Total:

11.34.07

Computer Table (size 600Lx480Dx750Hmm) (Navana of FTC 0660 /Otobi/Hatil/Akther/ Brothers or equivalent best quality)

9973.33

each Computer Table (size 600Lx480Dx750Hmm) of FTC 0660

1.0000

each

3670.00

3670.00 3670.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3743.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4117.74

VAT

6% of Total

274.52

IT

4% of Total

183.01 Total:

11.35

8000.00

4575.27

Supplying Side Rack of standard Colour & size of local best quality made by 16mm thick scrach proof and termite proof Laminated Melamine Board (LB) with PVC edging i/c interior side 1 no. shelf and front side two nos. sliding shutter of same materials on PVC channel with hinge, handle, lock and tower bolt. Top and two side covered by Laminated Melamine Board (LB) and back side covered by 5mm thick ply wood i/c all body black /beech colour. etc all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2725 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.35.01

Detailed Analysis Brief Description of Item 2 Side Rack : 900Wx400Dx750H mm size

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Side Rack : 900Wx400Dx750H mm size

1.0000

each

5900.00

5900.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6018.00

10% Profit ( Add 10% on Subtotal-B) :

6619.80

VAT

6% of Total

441.32

IT

4% of Total

294.21 Total:

11.35.02

Side Rack : 750Wx400Dx750H mm size

7355.33

each Side Rack : 750Wx400Dx750H mm size

1.0000

each

5300.00

5300.00 5300.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5406.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5946.60

VAT

6% of Total

IT

4% of Total

396.44 264.29 Total:

11.36

5900.00

6607.33

Supplying Slotted Angle Rack. of best quality fully knock down system steel open rack, structure made of 2mm thick mild steel angle. 5 nos. height adjustable shelves are made of 0.7 & 0.8mm thick mild steel. All surface of mild steel zinc phosphate coated and oven backed powder paint of black colour etc all complete as per design and direction of the E-I-C. (This item includes delivering the furniture at the instructed place).

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2726 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.36.01

Detailed Analysis Brief Description of Item 2 Slotted Angle Rack (size : 1200Lx600Dx 1800H mm size) (Otobi of SROP002MS /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Slotted Angle Rack (size : 1200Lx600Dx1800H mm size) of SROP002MS

1.0000

each

22000.00

22000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22440.00

10% Profit ( Add 10% on Subtotal-B) :

24684.00

VAT

6% of Total

IT

4% of Total

1645.60 1097.07 Total:

11.36.02

Slotted Angle Rack (size : 1200Lx300Dx 1830H mm size) (Navana of FRS 4251 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

1.0000

each

13400.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13668.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15034.80

VAT

6% of Total

IT

4% of Total

1002.32 668.21 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13400.00 13400.00

Subtotal-A:

Supplying Class Room Chair made of best quality MS box tube frame of standard thickness and size in black or any other approved colour with right side folding handle for writing purpose made with local best quality malamine board and same MS box tube frame. Seat and back made with same malamine board fitted with MS box tube with smooth finishing etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

27426.67

each Slotted Angle Rack (size : 1200Lx300Dx1830H mm size) of FRS 4251

11.37

22000.00

16705.33

each

Page: 2727 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.37.01

Detailed Analysis Brief Description of Item 2 Class Room Chair with bottom metal netting basket (Navana of FCC 2353 /Otobi/ Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Class Room Chair with bottom metal netting basket of FCC 2353

1.0000

each

7190.00

7190.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7333.80

10% Profit ( Add 10% on Subtotal-B) :

8067.18

VAT

6% of Total

IT

4% of Total

537.81 358.54 Total:

11.37.02

Class Room Chair with bottom metal netting basket (Hatil of HPL-508203-10-1-00 / Navana/ Otobi/ Akther/Brothers or equivalent best quality)

8963.53

each

Class Room Chair with bottom metal netting basket of HPL508-203-10-1-00

1.0000

each

5200.00

5200.00 5200.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5304.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5834.40

VAT

6% of Total

IT

4% of Total

388.96 259.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7190.00

6482.67

Page: 2728 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.37.03

Detailed Analysis Brief Description of Item 2 Class Room Chair seat and back foam covering (Navana of FCC 2351 /Otobi/ Hatil/ Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Class Room Chair seat and back foam covering of FCC 2351

1.0000

each

3890.00

3890.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3967.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4364.58

VAT

6% of Total

290.97

IT

4% of Total

193.98 Total:

11.37.04

Class Room Chair without basket (Navana of FCC 2352 / Otobi/ Hatil/ Akther/Brothers or equivalent best quality)

4849.53

each Class Room Chair without basket of FCC 2352

1.0000

each

3790.00

3790.00 3790.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3865.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4252.38

VAT

6% of Total

283.49

IT

4% of Total

188.99 Total:

11.38.01

3890.00

4724.87

Supplying three seated group chair made by best quality Mild Steel frame of standard size and thickness of smooth painted surface with Stailess steel box handle of standard size and thickness. Seat and back made by Mild Steel sheet with standard colour coating and smooth finishing etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2729 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.38.01.01

Detailed Analysis Brief Description of Item 2 MS three seated group chair (size :1430Lx 700W X890Hmm) (Navana of FCT 4274 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each MS three seated group chair (size :1430Lx700WX890Hmm) of FCT 4274

1.0000

each

15390.00

15390.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15697.80

10% Profit ( Add 10% on Subtotal-B) :

17267.58

VAT

6% of Total

IT

4% of Total

1151.17 767.45 Total:

11.38.02

Supplying three seated group chair made by best quality Mild Steel frame of standard size and thickness of smooth painted surface without handle. Seat and back made by high strength thick plstic sheet with smooth finishing and standard colour etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

11.38.02.01

Plastic three seated group chair (size :1430-1320Lx700-500WX890800Hmm) (Otobi of CFWP007 /Navana/Hatil/Akther/Brothers or equivalent best quality) with drawer unit

19186.20

each

Plastic three seated group chair (size :1430-1320Lx700500WX890-800Hmm) of CFWP007

1.0000

each

13500.00

13500.00 13500.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13770.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15147.00

VAT

6% of Total

IT

4% of Total

1009.80 673.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15390.00

16830.00

Page: 2730 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.38.02.02

Detailed Analysis Brief Description of Item 2 Plastic three seated group chair (size :1430-1320Lx700-500WX890800Hmm) (Otobi of CFWP003 /Navana/Hatil/Akther/Brothers or equivalent best quality) with drawer unit

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Plastic three seated group chair (size :1430-1320Lx700500WX890-800Hmm) of CFWP003

1.0000

each

11220.00

11220.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11444.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12588.84

VAT

6% of Total

IT

4% of Total

839.26 559.50 Total:

11.38.02.03

Plastic three seated group chair with MS box seat and back frame (size :1430-1320Lx700-500WX890-800Hmm) (Otobi of CFWP004 / Navana/ Hatil/ Akther/ Brothers or equivalent best quality) with drawer unit

13987.60

each

Plastic three seated group chair with MS box seat and back frame (size :1430-1320Lx700-500WX890-800Hmm) of CFWP004

1.0000

each

7890.00

7890.00

7890.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8047.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8852.58

VAT

6% of Total

IT

4% of Total

590.17 393.45 Total:

11.38.03

11220.00

9836.20

Supplying three seated group chair made by best quality Mild Steel frame of standard size and thickness of smooth painted surface without handle. Seat and back made by standard thick and size Mehogini wood with smooth finishing and polishing fitted with ms box frame of standard size and thickness of smooth painted surface etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2731 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.38.03.01

Detailed Analysis Brief Description of Item 2 Wooden three seated group chair (size :1320Lx500WX800Hmm) (Navana of FCT 4270 /Otobi/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Wooden three seated group chair (size :1320Lx500WX800Hmm) of FCT 4270

1.0000

each

9490.00

9490.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9679.80 10647.78 709.85 473.23

Total: 11.39

Supplying Laminated board Bed of standard size made of best quality imported 18mm thick scrach proof and termite proof Laminated Melamine Board (LB) with edge covering of standard thickness with head board, leg board and two nos side rail in same standard thick and size fitted in rust proof clamp-screw and bed slats series of wooden batten and wood tex board, with best quality double or single mattress as in requiremenrts (excluding cost of mattress) etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

11.39.01

Single Bed 2036Lx1080Wx7501Hmm size (Otobi of BSDB003LB /Navana/Hatil/Akther /Brothers or equivalent best quality)

11830.87

each Single Bed 2036Lx1080Wx7501Hmm size of BSDB003LB

1.0000

each

13600.00

13600.00 13600.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13872.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15259.20

VAT

6% of Total

IT

4% of Total

1017.28 678.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9490.00

16954.67

Page: 2732 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.39.02

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Double Bed 2042Lx1540Wx8451Hmm size (Otobi of BDDB019LB /Navana/Hatil/ Akther/ Brothers or equivalent best quality)

each Double Bed 2042Lx1540Wx8451Hmm size of BDDB019LB

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

18210.00

18210.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18574.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20431.62

VAT

6% of Total

1362.11

IT

4% of Total

908.07 Total:

11.39.03

Double Bed 2050Lx1668Wx7001Hmm size (Otobi of BDDB007LB /Navana/Hatil/ Akther/ Brothers or equivalent best quality)

22701.80

each Double Bed 2050Lx1668Wx7001Hmm size of BDDB007LB

1.0000

each

19900.00

19900.00 19900.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20298.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22327.80

VAT

6% of Total

1488.52

IT

4% of Total

992.35 Total:

11.40

18210.00

24808.67

Supplying Wooden Bed of standard size made of best quality well mature full seasoned termite proof Chittagong Teak wood of standard thickness with head board, leg board and two nos side rail in same standard thick and size wood of superior quality natural fiber polishing and finishing fitted in rust proof clamp-screw and bed slats series of wooden batten and wood tex board, with best quality double or single mattress as in requiremenrts (excluding cost of mattress) etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2733 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.40.01

Detailed Analysis Brief Description of Item 2 Single Bed 2036Lx1080Wx7501Hmm size (Otobi of BSDP009WD /Navana/Hatil/Akther /Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Single Bed 2036Lx1080Wx7501Hmm size of BSDP009WD

1.0000

each

29420.00

29420.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30008.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33009.24

VAT

6% of Total

2200.62

IT

4% of Total

1467.08 Total:

11.40.02

Double Bed 2050Lx1540Wx8001Hmm size (Otobi of BDDP050WD /Navana/Hatil/Akther /Brothers or equivalent best quality)

36676.93

each Double Bed 2050Lx1540Wx8001Hmm size of BDDP050WD

1.0000

each

32350.00

32350.00 32350.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32997.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

36296.70

VAT

6% of Total

2419.78

IT

4% of Total

1613.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

29420.00

40329.67

Page: 2734 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.40.03

Detailed Analysis Brief Description of Item 2 Double Bed 2084Lx1600Wx10501Hmm size (Otobi of BDDP089WD /Navana/Hatil/ Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Double Bed 2084Lx1600Wx10501Hmm size of BDDP089WD

1.0000

each

46620.00

46620.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

47552.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

52307.64

VAT

6% of Total

3487.18

IT

4% of Total

2324.78 Total:

11.40.04

Double Bed 2084Lx1600Wx10501Hmm size (Akther of AFL-BED-150 /Otobi/Navana/ Hatil/ Brothers or equivalent best quality)

58119.60

each Double Bed 2084Lx1600Wx10501Hmm size of AFL-BED-150

1.0000

each

54132.00

54132.00 54132.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

55214.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

60736.10

VAT

6% of Total

4049.07

IT

4% of Total

2699.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

46620.00

67484.56

Page: 2735 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.40.05

Detailed Analysis Brief Description of Item 2 Double Bed 2084Lx1540Wx10501Hmm size (Akther of AFL-BED-150 /Otobi/Navana/ Hatil/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Double Bed 2084Lx1540Wx10501Hmm size of AFL-BED-150

1.0000

each

48516.00

48516.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

49486.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

54434.95

VAT

6% of Total

3629.00

IT

4% of Total

2419.33 Total:

11.41

Supplying single or double best quality Compressed mattress covered with PVC bag or febric of Foreign colour and size as per requirements with standard thickness etc. all complete as per direction of the E-I-C (This item includes all fittings fixings and delivering the the instructed place).

11.41.01

Single mattress 2000mmx1000mm size with minimum 100mm thick of approved best quality

60483.28

each Single mattress 2000x1000 size with minimum 100mm thick

1.0000

each

10000.00

Subtotal-B: Subtotal-C:

10000.00 10000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10200.00

10% Profit ( Add 10% on Subtotal-B) :

11220.00

VAT

6% of Total

IT

4% of Total

748.00 498.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

48516.00

12466.67

Page: 2736 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.41.02

Detailed Analysis Brief Description of Item 2 Single mattress 2000mmx1000mm size with minimum 200mm thick of approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Single mattress 2000x1000 size with minimum 200mm thick

1.0000

each

15000.00

15000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15300.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16830.00

VAT

6% of Total

1122.00

IT

4% of Total

748.00 Total:

11.41.03

Double mattress 2000mmx1600mm size with minimum 100mm thick of approved best quality

18700.00

each Double mattress 2000x1600 size with minimum 100mm thick

1.0000

each

13880.00

13880.00 13880.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14157.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15573.36

VAT

6% of Total

1038.22

IT

4% of Total

692.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15000.00

17303.73

Page: 2737 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.41.04

Detailed Analysis Brief Description of Item 2 Double mattress 2000mmx1600mm size with minimum 200mm thick of approved best quality

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Double mattress 2000x1600 size with minimum 200mm thick

1.0000

each

18170.00

18170.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18533.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20386.74

VAT

6% of Total

1359.12

IT

4% of Total

906.08 Total:

11.42

Supplying Sofa set of single or double or tripple seated as in requirement of standard size and colour made by wooden body covered with thick compressed foam and foreign rexin or foreign febric of approved colour and design etc. all complete as per direction of the E-IC (This item includes all fittings fixings and delivering at the instructed place).

11.42.01

Single seated Sofa (Otobi of SSCP006FR /Navana/Hatil/Akther/Brothers or equivalent best quality)

22651.93

each Single seated Sofa of SSCP006FR

1.0000

each

8110.00

8110.00 8110.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8272.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9099.42

VAT

6% of Total

IT

4% of Total

606.63 404.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

18170.00

10110.47

Page: 2738 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.42.02

Detailed Analysis Brief Description of Item 2 Single seated Sofa (Otobi of STCP007LR /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Single seated Sofa of STCP007LR

1.0000

each

16540.00

16540.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16870.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

18557.88

VAT

6% of Total

1237.19

IT

4% of Total

824.79 Total:

11.42.03

Single seated Sofa (Otobi of SDCP04FF /Navana/Hatil/Akther/Brothers or equivalent best quality)

20619.87

each Single seated Sofa of SDCP04FF

1.0000

each

24540.00

24540.00 24540.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25030.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

27533.88

VAT

6% of Total

1835.59

IT

4% of Total

1223.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

16540.00

30593.20

Page: 2739 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.42.04

Detailed Analysis Brief Description of Item 2 Double seated Sofa (Otobi of SSCP006FR /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Double seated Sofa of SSCP006FR

1.0000

each

14550.00

14550.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14841.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16325.10

VAT

6% of Total

1088.34

IT

4% of Total

725.56 Total:

11.42.05

Double seated Sofa (Otobi of STCP007LR /Navana/Hatil/Akther/Brothers or equivalent best quality)

18139.00

each Double seated Sofa of STCP007LR

1.0000

each

36470.00

36470.00 36470.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

37199.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

40919.34

VAT

6% of Total

2727.96

IT

4% of Total

1818.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14550.00

45465.93

Page: 2740 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.42.06

Detailed Analysis Brief Description of Item 2 Double seated Sofa (Otobi of SSCP094FF /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Double seated Sofa of SSCP094FF

1.0000

each

38350.00

38350.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

39117.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

43028.70

VAT

6% of Total

2868.58

IT

4% of Total

1912.39 Total:

11.43

Supplying Sofa set of single or double or tripple seated as in requirement of standard size and design made by best quality well mature full seasoned termite proof Chittagong Teak wood of standard thickness and size of superior quality natural fiber polishing and finishing with thick compressed foam and foreign rexene or foreign fabric cover of approved colour and design etc. all complete as per direction of the EI-C (This item includes all fittings fixings and delivering at the instructed place).

11.43.01

Wooden Single seated Sofa (Otobi of SSCE009FF /Navana/ Hatil/ Akther/Brothers or equivalent best quality)

47809.67

each Wooden Single seated Sofa of SSCE009FF

1.0000

each

14440.00

14440.00 14440.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14728.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16201.68

VAT

6% of Total

IT

4% of Total

1080.11 720.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

38350.00

18001.87

Page: 2741 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

11.43.02

Wooden Double seated Sofa (Otobi of SSCE009FF /Navana/ Hatil/ Akther/ Brothers or equivalent best quality)

each Wooden Double seated Sofa of SSCE009FF

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

22760.00

22760.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

23215.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

25536.72

VAT

6% of Total

1702.45

IT

4% of Total

1134.97 Total:

11.44

Supplying Center Table of standard size and design made by best quality well mature full seasoned termite proof Chittagong Teak wood of standard thickness and size with four legs and frames made with same wood of superior quality natural fiber polishing and finishing etc. all complete as per direction of the E-I-C (This item includes all fittings fixings and delivering at the instructed place). .

11.44.01

Wooden Center Table (Otobi of CTCE008WD /Navana/ Hatil/ Akther/Brothers or equivalent best quality)

28374.13

each Wooden Center Table of CTCE008WD

1.0000

each

7000.00

7000.00 7000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7140.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7854.00

VAT

6% of Total

IT

4% of Total

523.60 349.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

22760.00

8726.67

Page: 2742 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.44.02

Detailed Analysis Brief Description of Item 2 Wooden Center Table (Otobi of CTCE009WD /Navana/ Hatil/ Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wooden Center Table of CTCE009WD

1.0000

each

7550.00

7550.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7701.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8471.10

VAT

6% of Total

564.74

IT

4% of Total

376.49 Total:

11.44.03

Wooden Center Table (Otobi of CTCE049WD /Navana/ Hatil/ Akther/Brothers or equivalent best quality)

9412.33

each Wooden Center Table of CTCE049WD

1.0000

each

8220.00

8220.00 8220.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8384.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9222.84

VAT

6% of Total

614.86

IT

4% of Total

409.90 Total:

11.45

7550.00

10247.60

Supplying Wooden Dining Table set of standard size made of best quality well mature full seasoned termite proof Chittagong Teak wood of standard thickness with four legs and frame in same standard thick and size wood of superior quality natural fiber polishing and finishing with 6mm thick glass top finishing smooth and rounded edge of glass etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2743 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.45.01

Detailed Analysis Brief Description of Item 2 Wooden Dining Table (size : 1524Lx915W x 750H) (Otobi of TDDP018WD /Navana/Hatil/ Akther/ Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wooden Dining Table (size : 1524Lx915Wx750H) of TDDP018WD

1.0000

each

25650.00

25650.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26163.00

10% Profit ( Add 10% on Subtotal-B) :

28779.30

VAT

6% of Total

IT

4% of Total

1918.62 1279.08 Total:

11.45.02

Wooden Dining Table (size : 1650Lx950W x 750H) (Otobi of TDDP049WD /Navana/Hatil/ Akther/Brothers or equivalent best quality)

31977.00

each Wooden Dining Table (size : 1650Lx950Wx750H) of TDDP049WD

1.0000

each

28000.00

28000.00 28000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28560.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

31416.00

VAT

6% of Total

IT

4% of Total

2094.40 1396.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25650.00

34906.67

Page: 2744 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.45.03

Detailed Analysis Brief Description of Item 2 Wooden Dining Table (size : 1520Lx912Wx 744H) (Otobi of TDDP012MF /Navana/Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wooden Dining Table (size : 1520Lx912Wx744H) of TDDP012MF

1.0000

each

29860.00

29860.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30457.20

10% Profit ( Add 10% on Subtotal-B) :

33502.92

VAT

6% of Total

IT

4% of Total

2233.53 1489.02 Total:

11.45.04

Wooden Dining Table (size : 1650-1524Lx 950-915Wx750-744H) (Akther of AFL-DNT/DNC-119 /Hatil/Otobi/Navana/i/Brothers or equivalent best quality)

37225.47

each

Wooden Dining Table (size : 1650-1524Lx950-915Wx750744H) of AFL-DNT/DNC-119

1.0000

each

55016.00

55016.00 55016.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

56116.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

61727.95

VAT

6% of Total

IT

4% of Total

4115.20 2743.46 Total:

11.46

29860.00

68586.61

Supplying Laminated board Dining Table of standard size made of best quality imported 18mm thick scrach proof and termite proof Laminated Melamine Board (LB) with edge covering. Of standard thickness and design with four legs and frame in best quality well mature full seasoned termite proof wooden frame of standard thick and size materials etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2745 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.46.01

Detailed Analysis Brief Description of Item 2 Round shaped Dining Table (size : 1600LX910Wx730Hmm) (Otobi of TDDP001LB /Navana/Hatil/ Akther / Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Round shaped Dining Table (size : 1600LX910Wx730Hmm) of TDDP001LB

1.0000

each

12100.00

12100.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12342.00

10% Profit ( Add 10% on Subtotal-B) :

13576.20

VAT

6% of Total

IT

4% of Total

905.08 603.39 Total:

11.47

Supplying wooden Dining Chair of standard size made of best quality well mature full seasoned termite proof Mhogini wood of standard thickness with four legs, frame in same standard thick and size wood of superior quality natural fiber polishing and finishing with minimum thick foam covered by rexene or Fabric finishing smooth all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

11.47.01

Wooden Dining Chair (size : 596LX586W x 1025Hmm) (Otobi of CFDP013LR /Navana/Hatil/Akther/Brothers or equivalent best quality)

15084.67

each Wooden Dining Chair (size : 596LX586Wx1025Hmm) of CFDP013LR

1.0000

each

5330.00

5330.00 5330.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5436.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5980.26

VAT

6% of Total

IT

4% of Total

398.68 265.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12100.00

6644.73

Page: 2746 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.47.02

Detailed Analysis Brief Description of Item 2 Wooden Dining Chair (size : 440LX522W x 950Hmm) (Otobi of CFDP049WD /Navana/Hatil/ Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wooden Dining Chair (size : 440LX522Wx950Hmm) of CFDP049WD

1.0000

each

6500.00

6500.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6630.00

10% Profit ( Add 10% on Subtotal-B) :

7293.00

VAT

6% of Total

IT

4% of Total

486.20 324.13 Total:

11.47.03

Wooden Dining Chair (size : 410LX475W x 895Hmm) (Otobi of FCDB002FR /Navana/Hatil/ Akther /Brothers or equivalent best quality)

8103.33

each Wooden Dining Chair (size : 410LX475Wx895Hmm) of FCDB002FR

1.0000

each

5550.00

5550.00 5550.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5661.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6227.10

VAT

6% of Total

IT

4% of Total

415.14 276.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6500.00

6919.00

Page: 2747 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.47.04

Detailed Analysis Brief Description of Item 2 Wooden Dining Chair (size : 410LX475W x 895Hmm) (Akther of AFLDNT/DNC-119 /Hatil/Otobi/Navana/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Wooden Dining Chair (size : 410LX475Wx895Hmm) of AFLDNT/DNC-119

1.0000

each

13156.00

13156.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13419.12

10% Profit ( Add 10% on Subtotal-B) :

14761.03

VAT

6% of Total

IT

4% of Total

984.07 656.05 Total:

11.48

Supplying Wooden Wardrobe of standard size made of best quality well mature full seasoned termite proof Chittagong Teak wood of standard thickness with drawer and box as per requirements. Drawer run through smoothly of best quality wheel and channel or runner. Three sides, top and bottom covered with same wood and back side covered by 5mm thick ply wood. Furniture should be superior quality natural fiber polishing and finishing and use best quality handle, lock and key etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

11.48.01

4 Drawer Wooden Wardrobe (size: 830Lx515Wx1220Hmm) (Otobi of CDDP018ED /Navana/Hatil/Akther /Brothers or equivalent best quality)

16401.15

each 4 Drawer Wooden Wardrobe (size: 830Lx515Wx1220Hmm) of CDDP018ED

1.0000

each

31530.00

31530.00 31530.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

32160.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

35376.66

VAT

6% of Total

IT

4% of Total

2358.44 1572.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13156.00

39307.40

Page: 2748 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.48.02

Detailed Analysis Brief Description of Item 2 2 Drawer and bottom side box Wooden Wardrobe (size: 830Lx515Wx1220Hmm) (Otobi of WDDP011ED/EDDP010WD /Navana/ Hatil/Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

2 Drawer and bottom side box Wooden Wardrobe (size: 830Lx515Wx1220Hmm) of WDDP011ED/EDDP010WD

1.0000

each

28850.00

28850.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

29427.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

32369.70

VAT

6% of Total

IT

4% of Total

2157.98 1438.65 Total:

11.49

28850.00

35966.33

Supplying Laminated Melamine Board (LB) Wardrobe of standard size made of best quality imported 18mm thick scrach proof and termite proof Laminated Melamine Board (LB) with edge covering with drawer and box as per requirements. Drawer run through smoothly of best quality wheel and channel or runner. Three sides, top and bottom covered with same wood and back side covered by 5mm thick ply wood. Furniture should be use best quality handle, lock and key etc. all complete as per direction of the E-I-C. (This item includes all fittings fixings and delivering the furniture at the instructed place)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2749 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 11.49.01

Detailed Analysis Brief Description of Item 2 4 Drawer and right side box Laminated Melamine Board (LB) Wardrobe (size: 1210L x 525W x 1220Hmm) (Otobi of WDDP005LB / Navana/ Hatil/ Akther/Brothers or equivalent best quality)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

4 Drawer and right side box Laminated Melamine Board (LB) Wardrobe (size: 1210Lx525Wx1220Hmm)

1.0000

each

23750.00

23750.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24225.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26647.50

VAT

6% of Total

IT

4% of Total

1776.50 1184.33 Total:

11.49.02

4 Drawer Laminated Melamine Board (LB) Wardrobe (size: 1210Lx525Wx1220Hmm) (Otobi of CDDB002KLB / Navana/ Hatil/ Akther / Brothers or equivalent best quality)

29608.33

each

4 Drawer Laminated Melamine Board (LB) Wardrobe (size: 1210Lx525Wx1220Hmm) of CDDB002KLB

1.0000

each

14500.00

Subtotal-B: Subtotal-C:

14500.00 14500.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14790.00

10% Profit ( Add 10% on Subtotal-B) :

16269.00

VAT

6% of Total

IT

4% of Total

1084.60 723.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23750.00

18076.67

Page: 2750 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Chapter - 12 : Electro-Mechanical Works 12.01

Providing Window type Air – Cooler of following cooling capacity based on indoor temperature 270 C DB/19.50 C WB and outdoor temperature 350 C at high fan speed condition complete with well balanced propeller type direct driven centrifugal type blower fan for condenser and evaporator with regulator, fancy and adjustable air circular louver removal & washable filter , expansion valve , thermostat control switch, fresh air intake arrangement etc. as required suitable for operation at 230V, single phase 50 Hz. A.C. supply (Major components of the machine shall be inconformity with relevant internationational standards and codes) Boomyang /Carrier/ Daikin/ Dunhumbush / General/Toshiba/ Trane / York / (Assembled in Thailand / Malayasia / Taiwan/ Korea /Japan/ USA/ EU Countries)or equivalent by the Engineering - in- Charge.

12.01.01

17000-18000 BTU/hr with out Remote Control

each Air-Cooler with out Remote Control (17000-18000 BTU/hr)Window Type

1.0000

each

62095.00

62095.00

Subtotal-A: Carrying including loading, unloading

( +1.00 % on Subtotal-A )

620.95

Subtotal-A1:

62715.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

63970.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

70367.30

VAT

6% of Total

IT

4% of Total

4691.15 3127.44 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

62095.00

78185.88

Page: 2751 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.01.02

Detailed Analysis Brief Description of Item 2 17000-18000 BTU/hr with Remote Control

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Air-Cooler with Remote Control (17000-18000 BTU/hr)Window Type

1.0000

each

64310.00

64310.00

Subtotal-A: Carrying including loading, unloading

( +1.00 % on Subtotal-A )

643.10

Subtotal-A1: Subtotal-B: Subtotal-C:

64953.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66252.16

10% Profit ( Add 10% on Subtotal-B) :

72877.38

VAT

6% of Total

IT

4% of Total

4858.49 3238.99 Total:

12.01.03

22500-24000 BTU/hr with out Remote Control

80974.86

each Air-Cooler with out Remote Control (22500-24000 BTU/hr)Window Type

1.0000

each

75210.00

Carrying including loading, unloading

( +1.00 % on Subtotal-A )

752.10

Subtotal-A1: Subtotal-B: Subtotal-C:

75210.00 75210.00

Subtotal-A:

75962.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

77481.34

10% Profit ( Add 10% on Subtotal-B) :

85229.48

VAT

6% of Total

IT

4% of Total

5681.97 3787.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

64310.00

94699.42

Page: 2752 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.01.04

Detailed Analysis Brief Description of Item 2 22500-24000 BTU/hr with Remote Control

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Air-Cooler with Remote Control (22500-24000 BTU/hr)Window Type

1.0000

each

75210.00

75210.00

Subtotal-A: Carrying including loading, unloading

( +1.00 % on Subtotal-A )

752.10

Subtotal-A1: Subtotal-B: Subtotal-C:

75962.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

77481.34

10% Profit ( Add 10% on Subtotal-B) :

85229.48

VAT

6% of Total

IT

4% of Total

5681.97 3787.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

75210.00

94699.42

Page: 2753 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supply , installation , testing and commissioning of split type room air –cooler comprising condensing and evaporating units having following cooling capacity based on indoor temperature 270 C DB/19.50 C WB and outdoor temperature 37 0 C DB in/c providing refrigerant copper pipe with thermal insulation , refrigerant charging ,necessary wiring with required size of PVC insulated and sheathed cable with ECC through water grade PVC pipe from the source of supply available within 10 (ten) meter form the condensing unit location etc. complete suitable for operation at 230 volts single – phase /400V 3- phase, 50 Hz . A.C. supply as per direction of the E/Ch. (Major components of the machine shall be inconformity with relevant international standards and codes.) Compact weather proof out –door type condensing unit copper condensing coil, well balanced in all respect having inter – lock with the fan coil unit propeller type fan / hermitically sealed compressor duly equipped with vibration –isolator, thermostatic and overload controls , magnetic contactors and all other standard accessories complete. Specified Nos . of matching ceiling / wall /floor /mounted direct expansion system fan coil unit (FCU) having well balanced direct driven centrifugal type fan , fancy and adjustable air circulating louver grill, removable and washable type filter ,condensing water tray, condense water drain out PVC flexible pipe / PVC pipe with necessary insulation, thermostatic switch etc. connected by individual refrigerant circuit with individual compressor of the condensing unit. Carrier / Daikin / Dunhumbush / General / Trane / York (Assembled in Thailand / Malayasia / Taiwan / Korea / Japan /USA/ EU Countries or equivalent approved by the Engineering in Charge.)

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2754 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.01

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Wall Mounted (17000-18000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Wall Mounted (17000-18000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

90000.00

90000.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

2.0000

day

450.00

900.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 93190.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

1630.83

Subtotal-A1:

94820.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

96717.24 106388.97

VAT

6% of Total

7092.60

IT

4% of Total

4728.40 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

118209.96

Page: 2755 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.02

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Wall Mounted (22500-24000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Wall Mounted (22500-24000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

106500.00

106500.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

2.0000

day

450.00

900.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 109690.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

1919.58

Subtotal-A1:

111609.58

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

113841.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

125225.94

VAT

6% of Total

8348.40

IT

4% of Total

5565.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

139139.94

Page: 2756 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.03

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Wall Mounted (30000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Wall Mounted (30000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

139500.00

139500.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

2.0000

day

450.00

900.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 142690.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

2497.08

Subtotal-A1:

145187.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

148090.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

162899.90

VAT

6% of Total

10859.99

IT

4% of Total

7240.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

180999.89

Page: 2757 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.04

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Celling Suspended (18000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Celling Suspended (18000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

107000.00

107000.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

3.0000

day

450.00

1350.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 110640.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

1936.20

Subtotal-A1:

112576.20

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

114827.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

126310.50

VAT

6% of Total

8420.70

IT

4% of Total

5613.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

140345.00

Page: 2758 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.05

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Celling Suspended (24000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Celling Suspended (24000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

119500.00

119500.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

3.0000

day

450.00

1350.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 123140.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

2154.95

Subtotal-A1:

125294.95

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

127800.85

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

140580.93

VAT

6% of Total

9372.06

IT

4% of Total

6248.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

156201.04

Page: 2759 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.06

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Celling Suspended (36000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Celling Suspended (36000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

190500.00

190500.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

3.0000

day

450.00

1350.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 194140.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

3397.45

Subtotal-A1:

197537.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

201488.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

221637.02

VAT

6% of Total

14775.80

IT

4% of Total

9850.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

246263.35

Page: 2760 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.07

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Celling Suspended (45000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Celling Suspended (45000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

250500.00

250500.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

3.0000

day

450.00

1350.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 254140.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

4447.45

Subtotal-A1:

258587.45

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

263759.20

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

290135.12

VAT

6% of Total

19342.34

IT

4% of Total

12894.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

322372.35

Page: 2761 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.08

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Celling Suspended (54000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Celling Suspended (54000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

240000.00

240000.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

3.0000

day

450.00

1350.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 243640.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

4263.70

Subtotal-A1:

247903.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

252861.77

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

278147.95

VAT

6% of Total

18543.20

IT

4% of Total

12362.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

309053.28

Page: 2762 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.09

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Cassette Type (17000-18000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Cassette Type (17000-18000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

110000.00

110000.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

3.0000

day

450.00

1350.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 113640.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

1988.70

Subtotal-A1:

115628.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

117941.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

129735.40

VAT

6% of Total

8649.03

IT

4% of Total

5766.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

144150.45

Page: 2763 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.10

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Cassette Type (22500-24000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Cassette Type (22500-24000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

124000.00

124000.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

3.0000

day

450.00

1350.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 127640.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

2233.70

Subtotal-A1:

129873.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132471.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145718.29

VAT

6% of Total

9714.55

IT

4% of Total

6476.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

161909.21

Page: 2764 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.02.11

Detailed Analysis Brief Description of Item 2 Split Air Cooler-Cassette Type (34500-36000 BTU/hr)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Split Air Cooler-Cassette Type (34500-36000 BTU/hr) in/c. all accessories, wires, copper pipes, etc.

1.0000

each

170000.00

170000.00

Air Cooler Technician

1.0000

day

680.00

680.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00

Skilled Labour

3.0000

day

450.00

1350.00

Mason

0.5000

day

550.00

275.00

Ordinary Labour

0.5000

day

370.00

185.00 173640.00

Subtotal-A: Gasket, sand, cement, bolts, nuts, screw, clamps, etc

( +1.75 % on Subtotal-A )

3038.70

Subtotal-A1:

176678.70

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

180212.27

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

198233.50

VAT

6% of Total

13215.57

IT

4% of Total

8810.38 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

220259.45

Page: 2765 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.03

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Operation of all equipment of the Central air-conditioning and ventilation system of the following capacities for eight hours per day. During normal office hours by engaging experienced Engineer and skilled technical staffs/operators as required as per attached operation manual and direction of Engineer-in-charge. List of Equipment: a) Chillers : (Total………. R. ton capacity) b) Compressor & compressor motors (…...…. Nos.) c) Condensing Water Pumps (……. H.P ……Nos.) d) Chilled water pumpss : (………. H.P ……Nos.) e) Air Compressor(…...…. Nos.) f) Air Handling Unit (…...…. Nos.) g) Cooling tower motors (…...…. Nos.) h) Cooling towers (…...…. Nos.) i) Make-up water tanks (…...…. Nos.) j) Condensing water pipe lines k) Chilled water pipe lines l) Air-Conditioning Ducts All other equipment and ancillary accessories and other items which are part and parcel of the above mentioned air-conditioning and ventilation system but not mentioned above in item sl. From a to 1.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2766 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.03.01

2 Upto 300 R. Ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

month Diploma Engineer

1.0000man-month

42000.00

42000.00

Air-Cooler Mechanics

0.5000man-month

12000.00

6000.00

Air-Cooler Plant Operator

1.0000man-month

9000.00

9000.00

Air-Cooler Plant Operator Helper

1.0000man-month

6000.00

6000.00 63000.00

Subtotal-A: Cunsumable materials like jute, cleaning agent etc.

( +1.75 % on Subtotal-A )

1102.50

Subtotal-A1: Subtotal-B: Subtotal-C:

64102.50 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

65384.55

10% Profit ( Add 10% on Subtotal-B) :

71923.01

VAT

6% of Total

IT

4% of Total

4794.87 3196.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

79914.45

Page: 2767 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.04

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Through maintenance, servicing and minor repairing in/c. necessary replacement of defective minor spare parts (Departmentally supplied) if any, as per detailed daily, weekly, monthly, half yearly andy yearly. Basis work schedule attached for smooth functioning of the following capacity air-conditioning & ventilation system as per standard engineering practice and maintenance manual of the manufacturer and direction of the Engineer-in-charge. (including all consumable materials) List of Equipment: a) Chillers : (Total………. R. ton capacity) b) Compressor & compressor motors (…...…. Nos.) c) Condensing Water Pumps (……. H.P ……Nos.) d) Chilled water pumpss : (………. H.P ……Nos.) e) Air Compressor(…...…. Nos.) f) Air Handling Unit (…...…. Nos.) g) Cooling tower motors (…...…. Nos.) h) Cooling towers (…...…. Nos.) i) Make-up water tanks (…...…. Nos.) j) Condensing water pipe lines k) Chilled water pipe lines l) Air-Conditioning Ducts All other equipment and ancillary accessories and other items which are part and parcel of the above mentioned air-conditioning and ventilation system but not mentioned above in item sl. From a to 1.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2768 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.04.01

2 Upto 300 R. Ton

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

month Diploma Engineer

0.2000man-month

Foreman

0.2000

Plumber/ Electric Mistry/ Painter Foreman helper

42000.00

8400.00

day

800.00

160.00

0.2000

day

680.00

136.00

0.2000

day

350.00

70.00 8766.00

Subtotal-A: Cunsumable materials like jute, cleaning agent etc.

( +9.50 % on Subtotal-A )

832.77

Subtotal-A1: Subtotal-B: Subtotal-C:

9598.77 9790.75

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10769.82

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

717.99 478.66 Total:

12.05

Supply of chemical for central Air-cooler (best quality).

12.05.01

Scale & Corrosion Inhibitor

litre Scale and Corrosion Inhibitor

1.0000

liter

650.00

Subtotal-B: Subtotal-C:

650.00 650.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

663.00

10% Profit ( Add 10% on Subtotal-B) :

729.30

VAT

6% of Total

IT

4% of Total

48.62 32.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11966.47

810.33

Page: 2769 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.05.02

2 Micro biocide for Bacterial Control

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

741.00

741.00

litre Micro Biocide for Bacterial Control

1.0000

liter

741.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

755.82

10% Profit ( Add 10% on Subtotal-B) :

831.40

VAT

6% of Total

55.43

IT

4% of Total

36.95 Total:

12.05.03

Alga Cide (Algae Control)

litre Alga Cide (Algae Control)

1.0000

liter

774.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

789.48

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

868.43

VAT

6% of Total

IT

4% of Total

57.90 38.60 Total:

Closed circuit Corrosion Inhibitor

964.92

litre Closed Circuit Corrosion Inhibitor

1.0000

liter

610.00

Subtotal-B: Subtotal-C:

610.00 610.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

622.20

10% Profit ( Add 10% on Subtotal-B) :

684.42

VAT

6% of Total

IT

4% of Total

45.63 30.42 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

774.00 774.00

Subtotal-A:

12.05.04

923.78

760.47

Page: 2770 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

12.06

Supply of spare parts for detail list of spares mentioning parts mumber as per recommendation of the manufacturer in lot.

12.06.01

Mother Board PCB ASILOG 3.Q

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Mother Board PCB ASILOG 3.Q

1.0000

each

111180.00

111180.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

113403.60

10% Profit ( Add 10% on Subtotal-B) :

124743.96

VAT

6% of Total

IT

4% of Total

8316.26 5544.18 Total:

12.06.02

CPU PCB FCID 360 Q

138604.40

each CPU PCB FCID 360 Q

1.0000

each

87200.00

87200.00 87200.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

88944.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

97838.40

VAT

6% of Total

IT

4% of Total

6522.56 4348.37 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

111180.00

108709.33

Page: 2771 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.06.03

2 Brake Module PCB MBB 3 M

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Brake Module PCB MBB 3 M

1.0000

each

92650.00

92650.00

Subtotal-A: Subtotal-B: Subtotal-C:

94503.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

103953.30

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

6930.22

IT

4% of Total

4620.15 Total:

12.06.04

Safety Circuit PCB SKE 1.M

1.0000

each

87418.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

89166.36

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

98083.00

VAT

6% of Total

IT

4% of Total

6538.87 4359.24 Total:

108981.11

each Car interface PCB ICE 1.Q

1.0000

each

109218.00

Subtotal-B: Subtotal-C:

109218.00 109218.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

111402.36

10% Profit ( Add 10% on Subtotal-B) :

122542.60

VAT

6% of Total

IT

4% of Total

8169.51 5446.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

87418.00 87418.00

Subtotal-A:

Car interface PCB ICE 1.Q

115503.67

each Safety Circuit PCB SKE 1.M

12.06.05

92650.00

136158.44

Page: 2772 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.06.06

2 COP Interface PCB TIC

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each COP Interface PCB TIC

1.0000

each

61694.00

61694.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62927.88

10% Profit ( Add 10% on Subtotal-B) :

69220.67

VAT

6% of Total

4614.71

IT

4% of Total

3076.47 Total:

12.06.07

PCB LONIOS 16 Q

1.0000

each

56680.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

57813.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

63594.96

VAT

6% of Total

IT

4% of Total

4239.66 2826.44 Total:

70661.07

each PCB LONBIO 16 Q

1.0000

each

38150.00

Subtotal-B: Subtotal-C:

38150.00 38150.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

38913.00

10% Profit ( Add 10% on Subtotal-B) :

42804.30

VAT

6% of Total

IT

4% of Total

2853.62 1902.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

56680.00 56680.00

Subtotal-A:

PCB LONBIO 16 Q

76911.85

each PCB LONIOS 16 Q

12.06.08

61694.00

47560.33

Page: 2773 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.06.09

2 PCB EBLON 2Q

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PCB EBLON 2Q

1.0000

each

88290.00

88290.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

90055.80

10% Profit ( Add 10% on Subtotal-B) :

99061.38

VAT

6% of Total

6604.09

IT

4% of Total

4402.73 Total:

12.06.10

PCB EBCIM 68 Q

1.0000

each

43600.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

44472.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

48919.20

VAT

6% of Total

IT

4% of Total

3261.28 2174.19 Total:

54354.67

each Encoder Unit (Shaft Encoder)

1.0000

each

89598.00

Subtotal-B: Subtotal-C:

89598.00 89598.00

Subtotal-A:

91389.96

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100528.96

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6701.93 4467.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

43600.00 43600.00

Subtotal-A:

Encoder Unit (Shaft Encoder)

110068.20

each PCB EBCIM 68 Q

12.06.11

88290.00

111698.84

Page: 2774 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.06.12

2 Photo Sensor-24V DC (PHUET)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Photo Sensor-24V DC (PHUET)

1.0000

each

88000.00

88000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

89760.00

10% Profit ( Add 10% on Subtotal-B) :

98736.00

VAT

6% of Total

6582.40

IT

4% of Total

4388.27 Total:

12.06.13

Print PVEC

1.0000

each

316100.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

322422.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

354664.20

VAT

6% of Total

IT

4% of Total

23644.28 15762.85 Total:

394071.33

each Skip Module (85 BR)

1.0000

each

318280.00

Subtotal-B: Subtotal-C:

318280.00 318280.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

324645.60

10% Profit ( Add 10% on Subtotal-B) :

357110.16

VAT

6% of Total

IT

4% of Total

23807.34 15871.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

316100.00 316100.00

Subtotal-A:

Skip Module (85 BR)

109706.67

each Print PVEC

12.06.14

88000.00

396789.07

Page: 2775 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.06.15

2 Ventilaion Assembly

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Ventilaion Assembly

1.0000

each

92650.00

92650.00

Subtotal-A: Subtotal-B: Subtotal-C:

94503.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

103953.30

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

6930.22

IT

4% of Total

4620.15 Total:

12.06.16

Thermostate

1.0000

each

2725.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2779.50

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3057.45

VAT

6% of Total

IT

4% of Total

203.83 135.89 Total:

3397.17

each Assembly Motor

1.0000

each

174400.00

Subtotal-B: Subtotal-C:

174400.00 174400.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

177888.00

10% Profit ( Add 10% on Subtotal-B) :

195676.80

VAT

6% of Total

IT

4% of Total

13045.12 8696.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2725.00 2725.00

Subtotal-A:

Assembly Motor

115503.67

each Thermostate

12.06.17

92650.00

217418.67

Page: 2776 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.06.18

2 Door Contact Switch

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Door Contact Switch

1.0000

each

3815.00

3815.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3891.30

10% Profit ( Add 10% on Subtotal-B) :

4280.43

VAT

6% of Total

285.36

IT

4% of Total

190.24 Total:

12.06.19

Door Contact Bridge

1.0000

each

763.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

778.26

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

856.09

VAT

6% of Total

IT

4% of Total

57.07 38.05 Total:

951.21

5000.00

5000.00

each Assembly Counter Roller

1.0000

each

5000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5100.00

10% Profit ( Add 10% on Subtotal-B) :

5610.00

VAT

6% of Total

IT

4% of Total

374.00 249.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

763.00 763.00

Subtotal-A:

Assembly Counter Roller

4756.03

each Door Contact Bridge

12.06.20

3815.00

6233.33

Page: 2777 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.06.21

2 PCB LONIBV 1.Q

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each PCB LONIBV 1.Q

1.0000

each

109218.00

109218.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

111402.36

10% Profit ( Add 10% on Subtotal-B) :

122542.60

VAT

6% of Total

8169.51

IT

4% of Total

5446.34 Total:

12.06.22

Clutch Roller

1.0000

each

545.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

555.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

611.49

VAT

6% of Total

IT

4% of Total

40.77 27.18 Total:

679.43

1635.00

1635.00

each Rope Guide Roller

1.0000

each

1635.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1667.70

10% Profit ( Add 10% on Subtotal-B) :

1834.47

VAT

6% of Total

IT

4% of Total

122.30 81.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

545.00 545.00

Subtotal-A:

Rope Guide Roller

136158.44

each Clutch Roller

12.06.23

109218.00

2038.30

Page: 2778 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.06.24

2 Main Guide Shoe

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Main Guide Shoe

1.0000

each

3815.00

3815.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3891.30

10% Profit ( Add 10% on Subtotal-B) :

4280.43

VAT

6% of Total

285.36

IT

4% of Total

190.24 Total:

12.06.25

Counter Guide Shoe

1.0000

each

3270.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3335.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3668.94

VAT

6% of Total

IT

4% of Total

244.60 163.06 Total:

4076.60

each Bottom Roller

1.0000

each

1308.00

Subtotal-B: Subtotal-C:

1308.00 1308.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1334.16

10% Profit ( Add 10% on Subtotal-B) :

1467.58

VAT

6% of Total

IT

4% of Total

97.84 65.23 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3270.00 3270.00

Subtotal-A:

Bottom Roller

4756.03

each Counter Guide Shoe

12.06.26

3815.00

1630.64

Page: 2779 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.06.27

2 V-Ribbed Belt

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each V-Ribbed Belt

1.0000

each

2180.00

2180.00

Subtotal-A: Subtotal-B: Subtotal-C:

12.06.28

Car Position Indicator

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2223.60

10% Profit ( Add 10% on Subtotal-B) :

2445.96

VAT

6% of Total

163.06

IT

4% of Total

108.71 Total:

2717.73

21800.00

21800.00

each Car Position Indicator

1.0000

each

21800.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22236.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24459.60

VAT

6% of Total

IT

4% of Total

1630.64 1087.09 Total:

12.06.29

Hall Position Indicator

27177.33

each Hall Position Indicator

1.0000

each

9810.00

Subtotal-B: Subtotal-C:

9810.00 9810.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10006.20

10% Profit ( Add 10% on Subtotal-B) :

11006.82

VAT

6% of Total

IT

4% of Total

733.79 489.19 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2180.00

12229.80

Page: 2780 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.06.30

2 Decoder PCB For Hall position indicator

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Decoder PCB For Hall position indicator

1.0000

each

21800.00

21800.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22236.00

10% Profit ( Add 10% on Subtotal-B) :

24459.60

VAT

6% of Total

1630.64

IT

4% of Total

1087.09 Total:

12.06.31

Gear Oil (Synthetic)

1.0000

each

2071.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2112.42

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2323.66

VAT

6% of Total

IT

4% of Total

154.91 103.27 Total:

2581.85

each Rope Oil

1.0000

each

436.00

Subtotal-B: Subtotal-C:

436.00 436.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

444.72

10% Profit ( Add 10% on Subtotal-B) :

489.19

VAT

6% of Total

IT

4% of Total

32.61 21.74 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2071.00 2071.00

Subtotal-A:

Rope Oil

27177.33

each Gear Oil (Synthetic)

12.06.32

21800.00

543.55

Page: 2781 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.06.33

2 Uain Magnetic Contactor

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Uain Magnetic Contactor

1.0000

each

9265.00

9265.00

Subtotal-A: Subtotal-B: Subtotal-C:

9450.30

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10395.33

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

693.02

IT

4% of Total

462.01 Total:

12.06.34

Relay For Brake

1.0000

each

7085.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7226.70

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7949.37

VAT

6% of Total

IT

4% of Total

529.96 353.31 Total:

8832.63

each Print PIOVECL 3 Q

1.0000

each

114450.00

Subtotal-B: Subtotal-C:

114450.00 114450.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

116739.00

10% Profit ( Add 10% on Subtotal-B) :

128412.90

VAT

6% of Total

IT

4% of Total

8560.86 5707.24 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7085.00 7085.00

Subtotal-A:

Print PIOVECL 3 Q

11550.37

each Relay For Brake

12.06.35

9265.00

142681.00

Page: 2782 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.07.01

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

HT Switch gear :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2783 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.01.1

Detailed Analysis Brief Description of Item 2 HT Switch gear : Supplying of following 11 KV, 3- phase50 HZ, indoor type , high tension switch gear complete with 630/800 Amps hard-drawn electrolytic copper bus-bar,1 no 0- 15 KV range voltmeter, 1 no ammeter of adequate range both with selector switch & OFF push button switch and ON-OFF- TRIP indicators including following components ( components manufactured & tested in EU Countries/USA/Japan) locally factory assembled in 14 SWG sheet steel metal clad, dust& vermin proof free standing , floor mounting, epoxy resin powder coat painted cabinet components must comply VDE/IEC/BS standard) With withdraw able type vacuum circuit breaker i) 1 set of 11 KV,800 Amps (20KA), 3-phase , 50 HZ, trolley mounted fully withdraw able type vacuum circuit breaker complete with motor operated spring charged stored energy mechanism for auto tripping at 12/24/48//110 volts DC( without battery) ii) 2 nos, 11 KV cast resin insulated, dry type , double pole PT having ratio 11/0. 11, burden 50 VA first core of class 0.5M5 for metering & second core of class 10 P 10 for protection. iii) 3nos. 11KV cast resin insulated, dry type , double core CT of adequate current ratio (compatible with the transformer capacity) burden 10-15 VA, first core of class 0.5 MS for metering and second core of class 10P10 for protection. iv) 1 no of triple pole solid- state microprocessor control IDMT relay with 2 elements of over current and short circuit protection and one for earth fault protection. v) 1 no 415V, 6A (10 KA) TP MCB fpr PT secondary protection Assembled by AEG/ Energy pac/ SIEMEN or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1109900.00

1109900.00

each

Withdraw Type VCB CT, PT etc.

1.0000

1109900.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1132098.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1245307.80

VAT

6% of Total

83020.52

IT

4% of Total

55347.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1383675.33

Page: 2784 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.01.2

Detailed Analysis Brief Description of Item 2 With Load Break Switch (LBS) : Supply of 11 KV, 3-phase, 50 Hz, indoor type, high tension switchgear complete with Load Break Switch (LBS), 800 Amps hard-drawn electrolytic copper bus-bars, 1 No. 0-15 KV range voltmeter & 1 no. Ammeter of adequate ranges both with selector switch, 1 no. of panel heater with auto thermostat control switch, manual ON & OFF push button switch and indicators including following components (components such as LBS, HRC fuse. CT, PT shall be manufactured & tested as per NEMA/VDE/IEC/JIS/BS Standards ) assembled locally in 14 SWG sheet steel clad, dust & vermin proof, free standing, floor mounting, epoxy resin powder coat painted cabinet as per relevant IEC standards and as per accepted/approved by the Engineer. 1 Set of 11 KV, 630 A (25KA), 50 Hz, triple pole, manually operated off load isolator interlocked with earth switch. 1 Set of 11 KV, 630A (25KA), 50 Hz, spring charged, stored energy mechanism triple pole load break switch (LBS) complete with 3 no.s of 11 KV HRC fuse of suitable Amps. (20KA) with spring operated striker pin plunger for automatic tripping activated by any of the three fuses blowup. 2 Nos. of 11 KV, double pole, cast resin insulated, dry type Potential transformer (P.T.) having ratio 11/0. 11, 50VA, class 0.5 for metering.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

3 Nos. of 11 KV, cast resin insulated, dry type, single core Current transformer (C.T.) having adequate current ratio (compatible with the transformer capacity) burden 10-15VA of class 0.5 M5 for metering. 1 No of 415V, 6A ( 10 KA), 50 Hz. TPMCB for PT secondary protection. Assembled by Govt. of Bangladesh owned/Shared company or the valid ISO-9001 certified company having type test certificate for whole panel from any internationally accredited independent laboratory. With Load Break Switch (LBS)

1.0000

each

440000.00

440000.00

Subtotal-A: Subtotal-B: Note : Rates of all items should be inclusive of all supply and carriage.

440000.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

448800.00 Page: 2785 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

Amount 8 493680.00

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

32912.00 21941.33 Total:

12.07.02

Transformer oil type; Supplying of the following oil-immersed , natural air cooled , 3- phase, 50 HZ, 11 KV /0 .415 KV & 0.24 KV out door type distribution transformer of DYN11 vector group having percentage impedance 4- 6.5%, basic impulse insulation level 75 KV , HT& LV porcelain bushing, manual 5 position standard top changer, conservator, thermometer, oil inlet & outlet valves, oil level indicator, dehydrating breather, lifting lug, earthing terminals, wheel, data plate etc. in/c painting, suitable for operation at 40◦C ambient temperature with maximum temperature rise 60.C, locally manufactured in Bangladesh as per VDE/ IEC/BS standard.

12.07.02.01

a)Capacity : 150 KVA b)No load loss 350 watts (maximum) c) Full load loss (maximum) Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

each

150 KVA3-phase oil type transformer

1.0000

each

380000.00

All other remaining cost

( +1.00 % on Subtotal-A )

3800.00

Subtotal-A1: Subtotal-B: Subtotal-C:

380000.00 380000.00

Subtotal-A:

383800.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

391476.00

10% Profit ( Add 10% on Subtotal-B) :

430623.60

VAT

6% of Total

IT

4% of Total

28708.24 19138.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

548533.33

478470.67

Page: 2786 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.02.02

Detailed Analysis Brief Description of Item 2 a) Capacity: 200 KVA b)No load loss 500 watts (maximum) c)Full load loss 2800 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

200 KVA3-phase oil type transformer

1.0000

each

425000.00

425000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

4250.00

Subtotal-A1:

429250.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

437835.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

481618.50

VAT

6% of Total

32107.90

IT

4% of Total

21405.27 Total:

12.07.02.03

a) Capacity: 250 KVA b)No load loss750 watts (maximum) c)Full load loss 4900 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge

535131.67

each

250 KVA3-phase oil type transformer

1.0000

each

525000.00

All other remaining cost

( +1.00 % on Subtotal-A )

5250.00

Subtotal-A1: Subtotal-B: Subtotal-C:

525000.00 525000.00

Subtotal-A:

530250.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

540855.00

10% Profit ( Add 10% on Subtotal-B) :

594940.50

VAT

6% of Total

39662.70

IT

4% of Total

26441.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

425000.00

661045.00

Page: 2787 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.02.04

Detailed Analysis Brief Description of Item 2 a) Capacity:300 / 315 KVA b)No load loss 800 watts (maximum) c)Full load loss 5000 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

300/315 KVA3-phase oil type transformer

1.0000

each

620000.00

620000.00

Subtotal-A: all other reamining cost

( +1.00 % on Subtotal-A )

6200.00

Subtotal-A1:

626200.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

638724.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

702596.40

VAT

6% of Total

46839.76

IT

4% of Total

31226.51 Total:

12.07.02.05

a) Capacity:400 KVA b)No load loss850 watts (maximum c)Full load loss 5200 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

780662.67

each

400 KVA 3-phase oil type transformer

1.0000

each

720000.00

All other remaining cost

( +1.00 % on Subtotal-A )

7200.00

Subtotal-A1: Subtotal-B: Subtotal-C:

720000.00 720000.00

Subtotal-A:

727200.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

741744.00

10% Profit ( Add 10% on Subtotal-B) :

815918.40

VAT

6% of Total

54394.56

IT

4% of Total

36263.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

620000.00

906576.00

Page: 2788 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.02.06

Detailed Analysis Brief Description of Item 2 a) Capacity:500 KVA b)No load loss1000 watts (maximum) c)Full load loss 5800 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

500 KVA 3-phase oil type transformer

1.0000

each

820000.00

820000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

8200.00

Subtotal-A1:

828200.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

844764.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

929240.40

VAT

6% of Total

61949.36

IT

4% of Total

41299.57 Total:

12.07.02.07

a) Capacity: 600/630 KVA with buchholz relay b)No load loss1200 watts (maximum) c)Full load loss 7500 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

1032489.33

each

600/630 KVA 3-phase oil type transformer

1.0000

each

1000000.00

All other remaining cost

( +1.00 % on Subtotal-A )

10000.00

Subtotal-A1: Subtotal-B: Subtotal-C:

1000000.00 1000000.00

Subtotal-A:

1010000.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1030200.00

10% Profit ( Add 10% on Subtotal-B) :

1133220.00

VAT

6% of Total

75548.00

IT

4% of Total

50365.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

820000.00

1259133.33

Page: 2789 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.02.08

Detailed Analysis Brief Description of Item 2 a) Capacity:800 KVA with buchholz relay b)No load loss1400 watts (maximum) c)Full load loss 9000 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1150000.00

1150000.00

each

800 KVA 3-phase oil type transformer

1.0000

1150000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

11500.00

Subtotal-A1:

1161500.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1184730.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1303203.00

VAT

6% of Total

86880.20

IT

4% of Total

57920.13 Total:

12.07.02.09

a) Capacity:1000 KVA with buchholz relay b)No load loss1800 watts (maximum) c)Full load loss 12000 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

each

1000 KVA 3-phase oil type transformer

1.0000

each

1450000.00

all other remaining cost

( +1.00 % on Subtotal-A )

14500.00

Subtotal-A1: Subtotal-B: Subtotal-C:

1450000.00 1450000.00

Subtotal-A:

1464500.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1493790.00

10% Profit ( Add 10% on Subtotal-B) :

1643169.00

VAT

6% of Total

109544.60

IT

4% of Total

73029.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1448003.33

1825743.33

Page: 2790 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.02.10

Detailed Analysis Brief Description of Item 2 a) Capacity:1250 KVA with buchholz relay b)No load loss2000watts (maximum) c)Full load loss 15000 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1450000.00

1450000.00

each

1250 KVA 3-phase oil type transformer

1.0000

1450000.00

Subtotal-A: All other remaining cost (on A)

( +1.00 % on Subtotal-A )

14500.00

Subtotal-A1:

1464500.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1493790.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1643169.00

VAT

6% of Total

109544.60

IT

4% of Total

73029.73 Total:

12.07.02.11

a) Capacity:1500/ 1600 KVA with buchholz relay b)No load loss2200 watts (maximum) c)Full load loss 18000 watts (maximum Assembled by AEG/ Energy pac / SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

each

1500/1600 KVA 3-phase oil type transformer

1.0000

each

1850000.00

All other remaining cost (onA)

( +1.00 % on Subtotal-A )

18500.00

Subtotal-A1: Subtotal-B: Subtotal-C:

1850000.00 1850000.00

Subtotal-A:

1868500.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1905870.00

10% Profit ( Add 10% on Subtotal-B) :

2096457.00

VAT

6% of Total

139763.80

IT

4% of Total

93175.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1825743.33

2329396.67

Page: 2791 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.02.12

Detailed Analysis Brief Description of Item 2 a) Capacity: 2000 KVA with buchholz relay b)No load loss2400 watts (maximum) c)Full load loss 20000 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

2150000.00

2150000.00

each

2000 KVA 3-phase oil type transformer

1.0000

2150000.00

Subtotal-A: All other remaining cost (onA)

( +1.00 % on Subtotal-A )

21500.00

Subtotal-A1:

2171500.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2214930.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2436423.00

VAT

6% of Total

162428.20

IT

4% of Total

108285.47 Total:

12.07.03

2707136.67

Transformer dry type; Supplying of the following dry type cast resin, natural air cooled , 3- phase, 50 HZ, 11 KV /0 .415 KV & 0.24 KV indoor type distribution transformer of DYN11 vector group having percentage impedance 4- 6.5%, basic impulse insulation level 75 KV , HV& LV porcelain bushing, manual 5 position standard tap changer, complete with two windings of high conductivity copper, earthing terminals, temperature sensor with thermometer, thermostat controlled blower fan, lifting lugs, data plate etc. complete as required with maximum 60. C temperature rise and suitable for operation at 40.C ambient temperature manufactured & tested by Trafo- union (Germany) / Trihal (France) or equivalent according to the specification & direction of the Engineer- in-charge according to VDE/ IEC/BS standard.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2792 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.03.1

Detailed Analysis Brief Description of Item 2 a) Capacity: 500 KVA b)No load loss1300 watts (maximum) c)Full load loss 5500 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1050000.00

1050000.00

each

500 KVA 3-phase dry type Transforme

1.0000

1050000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

10500.00

Subtotal-A1:

1060500.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1081710.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1189881.00

VAT

6% of Total

79325.40

IT

4% of Total

52883.60 Total:

12.07.03.2

a) Capacity: 630 KVA b)No load loss2400 watts (maximum) c)Full load loss 20000 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

each

630 KVA 3-phase dry type Transforme

1.0000

each

1300000.00

All other remaining cost (on A)

( +1.00 % on Subtotal-A )

13000.00

Subtotal-A1: Subtotal-B: Subtotal-C:

1300000.00 1300000.00

Subtotal-A:

1313000.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1339260.00

10% Profit ( Add 10% on Subtotal-B) :

1473186.00

VAT

6% of Total

98212.40

IT

4% of Total

65474.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1322090.00

1636873.33

Page: 2793 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.03.3

Detailed Analysis Brief Description of Item 2 a) Capacity:800 KVA b)No load loss1700 watts (maximum) c)Full load loss7600 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1500000.00

1500000.00

each

800 KVA 3-phase dry type Transforme

1.0000

1500000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

15000.00

Subtotal-A1:

1515000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1545300.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1699830.00

VAT

6% of Total

113322.00

IT

4% of Total

75548.00 Total:

12.07.03.4

a) Capacity:1000 KVA b)No load loss2000 watts (maximum) c)Full load loss 8700 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

each

1000 KVA 3-phase dry type Transforme

1.0000

each

2300000.00

All other remaining cost

( +1.00 % on Subtotal-A )

23000.00

Subtotal-A1: Subtotal-B: Subtotal-C:

2300000.00 2300000.00

Subtotal-A:

2323000.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2369460.00

10% Profit ( Add 10% on Subtotal-B) :

2606406.00

VAT

6% of Total

173760.40

IT

4% of Total

115840.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1888700.00

2896006.67

Page: 2794 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.03.5

Detailed Analysis Brief Description of Item 2 a) Capacity:1250 KVA b)No load loss2300 watts (maximum) c)Full load loss 10500 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1885000.00

1885000.00

each

1200 KVA 3-phase dry type Transforme

1.0000

1885000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

18850.00

Subtotal-A1:

1903850.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1941927.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2136119.70

VAT

6% of Total

142407.98

IT

4% of Total

94938.65 Total:

12.07.03.6

a) Capacity:1500/1600 KVA b)No load loss 2800 watts (maximum) c)Full load loss 13500 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

each

1500/1600 KVA 3-phase dry type Transforme

1.0000

each

2400000.00

All other remaining cost

( +1.00 % on Subtotal-A )

24000.00

Subtotal-A1: Subtotal-B: Subtotal-C:

2400000.00 2400000.00

Subtotal-A:

2424000.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2472480.00

10% Profit ( Add 10% on Subtotal-B) :

2719728.00

VAT

6% of Total

181315.20

IT

4% of Total

120876.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2373466.33

3021920.00

Page: 2795 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.03.7

Detailed Analysis Brief Description of Item 2 a) Capacity 2000 KVA b)No load loss 3500 watts (maximum) c)Full load loss 16000 watts (maximum Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

2400000.00

2400000.00

each

2000 KVA 3-phase dry type Transforme

1.0000

2400000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

24000.00

Subtotal-A1:

2424000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2472480.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2719728.00

VAT

6% of Total

181315.20

IT

4% of Total

120876.80 Total:

12.07.04

3021920.00

indoor type low tension switch gear of the following specification complete with voltmeter (0-500)& ammeter of adequate rating both with selector switch, indicating lamps for ON – OFF and following components ( except busbars manufactured & tested in EU countries / USA/ Japan) locally factory assembled in 16 SWG sheet steel clad, dust & vermin proof, free standing, floor mounting epoxy resin powder coat painted cabinet ( MCCB in LT panel must comply VDE/IEC/BSS standardindoor type low tension switch gear of the following specification complete with voltmeter (0-500)& ammeter of adequate rating both with selector switch, indicating lamps for ON – OFF and following components ( except busbars manufactured & tested in EU countries / USA/ Japan) locally factory assembled in 16 SWG sheet steel clad, dust & vermin proof, free standing, floor mounting epoxy resin powder coat painted cabinet ( MCCB in LT panel must comply VDE/IEC/BSS standard

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2796 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.01

Detailed Analysis Brief Description of Item 2 For 150 KVA Transformer Incoming:1set- 415V, 300A TP & NE hard drawn electrolytic copper bus bar. 1 no- 415V, 250A (35 KA ), adjustable type TPMCCB for main control with thermal over load & instantaneous electro magnetic short circuit release. 3 no- 415 V, 250/5 ratio current transformer with suitable accuracy& burden. Outgoing; 2 nos. - 415 V, 150/160A (25 KA ), adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 1 no- 415 V, 100A (16 KA ), TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,60/63A (16 KA ), TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ), TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. Assembled by AEG/Energy pac /SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Equipment for 150 KVA 3-Phase Transformer LT Switch gear

1.0000

each

150000.00

150000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

1500.00

Subtotal-A1:

151500.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

154530.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

169983.00

VAT

6% of Total

IT

4% of Total

11332.20 7554.80 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

150000.00

188870.00

Page: 2797 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.02

Detailed Analysis Brief Description of Item 2 For 200 KVA Transformer Incoming:1set- 415V, 400A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 300/320A (35 KA ) , adjustable type TPMCCB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 300/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 200A (25 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 1 no- 415 V, 150/160A (25 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 2 nos- 415 V,100A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,60/63A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Equipment for 200 KVA 3-Phase Transformer LT Switch gear

1.0000

each

180000.00

180000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

1800.00

Subtotal-A1:

181800.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185436.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

203979.60

VAT

6% of Total

13598.64

IT

4% of Total

9065.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

180000.00

226644.00

Page: 2798 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.03

Detailed Analysis Brief Description of Item 2 For 250 KVA Transformer Incoming:1set- 415 V, 500A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 400A (35 KA ) , adjustable type TPMCCB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 400/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 250A (25 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 2 no- 415 V, 150/160A (25 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 2 nos- 415 V,100A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,60/63A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Equipment for 250 KVA 3-Phase Transformer LT Switch gear

1.0000

each

200000.00

200000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

2000.00

Subtotal-A1:

202000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

206040.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

226644.00

VAT

6% of Total

15109.60

IT

4% of Total

10073.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

200000.00

251826.67

Page: 2799 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.04

Detailed Analysis Brief Description of Item 2 For 300/315 KVA Transformer Incoming:1set- 415 V, 600A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 500A (35 KA ) , adjustable type TPMCCB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 500/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 300A (35 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 1 no- 415 V, 250A (35 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 nos- 415 V,200A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,150/160A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,60/63A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Equipment for 300/315 KVA Transformer PFI capacity 187.5 KVAR

1.0000

each

230000.00

230000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

2300.00

Subtotal-A1:

232300.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

236946.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

260640.60

VAT

6% of Total

17376.04

IT

4% of Total

11584.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

230000.00

289600.67

Page: 2800 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.05

Detailed Analysis Brief Description of Item 2 For 400 KVA Transformer Incoming:1set- 415 V, 800A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 600/630A (50 KA ) , adjustable type TPMCCB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 600/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 400A (35 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 1 no- 415 V, 250A (35 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 nos- 415 V,200A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,150/160A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,60/63A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Equipment for 400 KVA 3-Phase Transformer LT Switch gear

1.0000

each

280000.00

280000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

2800.00

Subtotal-A1:

282800.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

288456.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

317301.60

VAT

6% of Total

IT

4% of Total

21153.44 14102.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

280000.00

352557.33

Page: 2801 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.06

Detailed Analysis Brief Description of Item 2 For 500 KVA Transformer Incoming:1set- 415, 1000A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 800A (50 KA ) , adjustable type TPMCCB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 800/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 500A (35 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 2 no- 415 V, 250A (35 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 2 nos- 415 V,200A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,150/160A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,60/63A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Equipment for 500 KVA 3-Phase Transformer LT Switch gear

1.0000

each

320000.00

320000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

3200.00

Subtotal-A1:

323200.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

329664.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

362630.40

VAT

6% of Total

IT

4% of Total

24175.36 16116.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

320000.00

402922.67

Page: 2802 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.07

Detailed Analysis Brief Description of Item 2 For 600/630 KVA Transformer Incoming:1set- 415 V, 1200A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 1000A (65 KA ) , adjustable type TPMCCB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 1000/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 600A (50 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 3 no- 415 V, 250A (35 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 2 nos- 415 V,200A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,150/160A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,100A (16 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Equipment for 750/800 KVA Transformer PFI capacity 480 KVAR

1.0000

each

430000.00

430000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

4300.00

Subtotal-A1:

434300.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

442986.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

487284.60

VAT

6% of Total

32485.64

IT

4% of Total

21657.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

430000.00

541427.33

Page: 2803 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.08

Detailed Analysis Brief Description of Item 2 For 800 KVA Transformer Incoming:1set- 415V, 1500A TP&NE hard drawn electrolytic copper busbar. 1 no- 415V, 1200/1250A(65 KA ) , adjustable type TPMCCB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 1200/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 800A (65 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 2 no- 415 V, 300/320A (35 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 4 nos- 415 V,250A (35 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,150/160A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.2 no- 415 V, 300/320A (35 KA ) adjustable type TPMCCB with thermal over load & instantaneous electromagnetic short circuit release. 4 nos- 415 V,250A (35 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,150/160A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of the Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

Equipment for 600/630 KVA Transformer PFI capacity 375 KVAR

1.0000

each

400000.00

All other remaining cost

( +1.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B:

400000.00 400000.00

Subtotal-A:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

4000.00 404000.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

412080.00 Page: 2804 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4 Subtotal-C:

Quantity 5

Unit

Rate

6

7

Amount 8 453288.00

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

30219.20 20146.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

503653.33

Page: 2805 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.09

Detailed Analysis Brief Description of Item 2 For 1000 KVA Transformer Incoming:1set- 415 V, 1800A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 1600A (80 KA ) , adjustable type TPMCCB/ACB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 1600/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 1000A (65 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 2 no- 415 V, 300/320A (35 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 6 nos- 415 V,250A (35 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,100A (16 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release the Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Equipment for 1000 KVA 3-Phase Transformer LT Switch gear

1.0000

each

760000.00

760000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

7600.00

Subtotal-A1:

767600.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

782952.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

861247.20

VAT

6% of Total

57416.48

IT

4% of Total

38277.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

760000.00

956941.33

Page: 2806 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.10

Detailed Analysis Brief Description of Item 2 For 1250 KVA Transformer Incoming:1set- 415 V, 2500A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 2000A (80 KA ) , adjustable type TPMCCB /ACB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 2000/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 1250A (65 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 1 no- 415 V, 400A (35 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V,300/320A (35 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 4 no- 415 V,250A (35 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 2 no- 415 V,200A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release 1 no- 415 V,80A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic release 1 no- 415 V,30/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic release

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1000000.00

1000000.00

each

Equipment for 1250 KVA 3-Phase Transformer LT Switch gear

1.0000

1000000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

10000.00

Subtotal-A1:

1010000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1030200.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1133220.00

VAT

6% of Total

IT

4% of Total

75548.00 50365.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1259133.33

Page: 2807 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.04.11

Detailed Analysis Brief Description of Item 2 For 1500 KVA Transformer Incoming:1set- 415 V, 3000A TP&NE hard drawn electrolytic copper busbar. 1 no- 415 V, 2200A (80 KA ) , adjustable type TPMCCB /ACB for main control with thermal over load & instantaneous electro-magnetic short circuit release. 3 nos- 415 V, 2500/5 ratio current transformer with suitable accuracy& burden. Outgoing; 1 no. - 415 V, 1600A (80 KA ) , adjustable type TP MCCB with thermal over load & instantaneous electro-magnetic short circuit release.( one for PFI control) 1 no- 415 V, 600A (50 KA ) adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 2 nos- 415 V,400A (35 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 4 no- 415 V,300/320A (35 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release. 1 no- 415 V,250A (35 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic short circuit release 2 no- 415 V,200A (25 KA ) , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic release 1 no- 415 V,100A (16 KA ) , , adjustable type TPMCCB with thermal over load & instantaneous electro-magnetic release 1 no- 415 V,130/32A (16 KA ) , TPMCCB with thermal over load & instantaneous electro-magnetic release Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

8

each

1423500.00

1423500.00

each

Equipment for 1500 KVA 3-Phase Transformer LT Switch gear

1.0000

1423500.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

Note : Rates of all items should be inclusive of all supply and carriage.

Amount

14235.00 1437735.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1466489.70

10% Profit ( Add 10% on Subtotal-B) :

1613138.67

VAT

6% of Total

IT

4% of Total

107542.58 71695.05 Page: 2808 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Total: 12.07.05

Power factor improvement plant: Supplying of following 415volt , 3phase,50HZ power factor improvement plant complete with TP busbars and earth block, micro processor controlled auto power factor correction relay with digital PF reading display, capacitor bank, contactor, fuse, ON indicator for every stage of capacitor bank (except directly connected one)etc. locally factory assembled in 16SWG sheet steelclad dust& vermin proof, free standing ,floor mounting , epoxy resin power coat painted cabinet contactors, capacitor bank relays, discharge resistor, fuse etc. shall comply VDE/IEC/BSS standard and shall be manufactured & tested in USA/ JAPAN/ EU countries

Note : Rates of all items should be inclusive of all supply and carriage.

1792376.30

each

Page: 2809 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.01

Detailed Analysis Brief Description of Item 2 For 150 KVA Transformer PFI capacity 90 KVAR3 no- 415 V, 200A hard drawn electrolytic copper busbar. 1no- 415 V ,5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge coil for connection directly with line through fuse. 2nos- 415 V ,5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 6nos- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 2nos- 415 V ,10A,50 HZ TP magnetic contactor with AC3 duty 6nos- 415 V ,20A,50 HZ TP magnetic contactor with AC3 duty 9nos- 415V,10A,HRC fuse with base. 18nos- 415V,25A,HRC fuse with base. Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 200 KVATransformer PFI capacity 120 KVAR

1.0000

each

180000.00

180000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

1800.00

Subtotal-A1:

181800.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

185436.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

203979.60

VAT

6% of Total

IT

4% of Total

13598.64 9065.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

180000.00

226644.00

Page: 2810 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.02

Detailed Analysis Brief Description of Item 2 For 200 KVA Transformer PFI capacity 120 KVAR 3 no- 415 V, 250A hard drawn electrolytic copper busbar. 1no- 415 V ,5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge coil for connection directly with line through fuse. 1nos- 415 V ,5 KVAR,50 HZ TP power capacitor bank with bult in discharge resistor 3nos- 415 V ,10 KVAR,50 HZ TP power capacitor bank with bult in discharge resistor. 4nos- 415 V ,20A,20 KVAR 50 HZ TP power capacitor bank with built in discharge resistor. 1nos- 415 V ,10A,50 HZ TP magnetic contactor with AC3 duty 3nos- 415 V ,16A,50 HZ TP magnetic contactor with AC3 4nos- 415 V ,32A,50 HZ TP magnetic contactor with AC3 6nos- 415V,10A,HRC fuse with base. 9nos- 415V,20A,HRC fuse with base. 12nos- 415V,40A,HRC fuse with base. 9nos- 415V,50A,HRC fuse with base

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 250 KVA Transformer PFI capacity 150 KVAR

1.0000

each

200000.00

200000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

2000.00

Subtotal-A1:

202000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

206040.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

226644.00

VAT

6% of Total

IT

4% of Total

15109.60 10073.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

200000.00

251826.67

Page: 2811 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.03

Detailed Analysis Brief Description of Item 2 For 250 KVA Transformer PFI capacity 150 KVAR 3 no- 415 V, 300A hard drawn electrolytic copper busbar. 1no- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge coil for connection directly with line through fuse. 5nos- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 3nos- 415 V ,25 KVAR,50 HZ TP power capacitor bank with bult in /separate discharge resistor. 5nos- 415 V ,20A, 50 HZ auto TP magnetic contactor with AC3 duty. 3nos- 415 V ,40A,50 HZ autoTP magnetic contactor with AC3 duty 15nos- 415 V ,25A, HRC fuse with base 9nos- 415V,50A,HRC fuse with base. Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 150 KVA Transformer PFI capacity 90 KVAR

1.0000

each

190867.00

190867.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

1908.67

Subtotal-A1:

192775.67

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

196631.18

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

216294.30

VAT

6% of Total

IT

4% of Total

14419.62 9613.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

190867.00

240327.00

Page: 2812 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.04

Detailed Analysis Brief Description of Item 2 For 300/315 KVA Transformer PFI capacity 187.5 KVAR 3 no- 415 V, 400A hard drawn electrolytic copper busbar. 1no- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge coil for connection directly with line through fuse. 2nos- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 6nos- 415 V ,25 KVAR,50 HZ TP power capacitor bank with built in /separate discharge resistor. 2nos- 415 V ,20A, 50 HZ TP magnetic contactor with AC3 duty. 6nos- 415 V ,40A,50 HZ TP magnetic contactor with AC3 duty 9nos- 415 V ,25A, HRC fuse with base 18nos- 415V,50A,HRC fuse with base. Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 300/315 KVA Transformer PFI capacity 187.5 KVAR

1.0000

each

230000.00

230000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

2300.00

Subtotal-A1: Subtotal-B: Subtotal-C:

232300.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

236946.00

10% Profit ( Add 10% on Subtotal-B) :

260640.60

VAT

6% of Total

IT

4% of Total

17376.04 11584.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

230000.00

289600.67

Page: 2813 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.05

Detailed Analysis Brief Description of Item 2 For 400 KVA Transformer PFI capacity 240 KVAR 3 no- 415 V, 500A hard drawn electrolytic copper busbar. 1no- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge coil for connection directly with line through fuse. 1nos- 415 V ,10 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 2nos- 415 V ,12.5 KVAR,50 HZ Tp power capacitor bank with built in / separate discharge resistor. 4nos- 415 V ,25 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 2nos- 415 V ,50 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 1no- 415 V ,20A, 50 HZ auto TP magnetic contactor with AC3 duty. 2nos- 415 V ,16A,50 HZauto TP magnetic contactor with AC3 duty 4nos- 415 V ,40A,50 HZ auto TP magnetic contactor with AC3 duty 2nos- 415 V 80A,50 HZ auto TP magnetic contactor with AC3 duty 9nos- 415 V ,25A, HRC fuse with base 3nos- 415V,20A,HRC fuse with base. 12nos- 415 V ,50A, HRC fuse with base 6nos- 415V,100A,HRC fuse with base. Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 400 KVA Transformer PFI capacity 240 KVAR

1.0000

each

260000.00

260000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

2600.00

Subtotal-A1: Subtotal-B: Subtotal-C:

262600.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

267852.00

10% Profit ( Add 10% on Subtotal-B) :

294637.20

VAT

6% of Total

19642.48

IT

4% of Total

13094.99 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

260000.00

327374.67

Page: 2814 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.06

Detailed Analysis Brief Description of Item 2 For 500 KVA Transformer PFI capacity 300 KVAR 3 no- 415 V, 600A hard drawn electrolytic copper busbar. 1no- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge coil for connection directly with line through fuse. 1no- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 5nos- 415 V ,25 KVAR,50 HZ TP power capacitor bank with built in / separate discharge resistor. 3nos- 415 V ,50 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 1no- 415 V ,20A, 50 HZ auto TP magnetic contactor with AC3 duty. 5nos- 415 V ,40A,50 HZ auto TP magnetic contactor with AC3 duty 3nos- 415 V ,80A,50 HZ auto TP magnetic contactor with AC3 duty

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

6nos- 415 V ,25A, HRC fuse with base 15nos- 415V,50A,HRC fuse with base. 9nos- 415 V ,100A, HRC fuse with base . Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge. Equipment for 500 KVA Transformer PFI capacity 300 KVAR

1.0000

each

320000.00

320000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

3200.00

Subtotal-A1: Subtotal-B: Subtotal-C:

323200.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

329664.00

10% Profit ( Add 10% on Subtotal-B) :

362630.40

VAT

6% of Total

IT

4% of Total

24175.36 16116.91 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

320000.00

402922.67

Page: 2815 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.07

Detailed Analysis Brief Description of Item 2 For 630 KVA Transformer PFI capacity 300 KVAR 3 no- 415 V, 600A hard drawn electrolytic copper busbar. 1no- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge coil for connection directly with line through fuse. 1no- 415 V ,12.5 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 5nos- 415 V ,25 KVAR,50 HZ TP power capacitor bank with built in / separate discharge resistor. 3nos- 415 V ,50 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 1no- 415 V ,20A, 50 HZ auto TP magnetic contactor with AC3 duty. 5nos- 415 V ,40A,50 HZ auto TP magnetic contactor with AC3 duty 3nos- 415 V ,80A,50 HZ auto TP magnetic contactor with AC3 duty

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

6nos- 415 V ,25A, HRC fuse with base 15nos- 415V,50A,HRC fuse with base. 9nos- 415 V ,100A, HRC fuse with base . Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge. Equipment for 750/800 KVA Transformer PFI capacity 480 KVAR

1.0000

each

430000.00

430000.00

Subtotal-A: all Other remaining cost

( +1.00 % on Subtotal-A )

4300.00

Subtotal-A1:

434300.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

442986.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

487284.60

VAT

6% of Total

32485.64

IT

4% of Total

21657.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

430000.00

541427.33

Page: 2816 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.08

Detailed Analysis Brief Description of Item 2 For 800 KVA Transformer PFI capacity 480 KVAR 3 no- 415 V, 900A hard drawn electrolytic copper busbar. 1no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with built in / separate discharge coil for connection directly with line through fuse. 4no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 1no- 415 V,5 KVAR,50 HZ TP power capacitor bank with built in / separate discharge resistor. 5nos- 415 V ,50 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 1no- 415 V ,100 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 4no- 415 V ,40A,50 HZ auto TP magnetic contactor with AC3 duty 1nos- 415 V ,10A,50 HZ auto TP magnetic contactor with AC3 duty 5nos- 415 V ,80A,50 HZ auto TP magnetic contactor with AC3 duty 1no- 415 V ,160A,50 HZ auto TP magnetic contactor with AC3 duty 15nos- 415V,50A,HRC fuse with base. 3nos- 415 V ,10A, HRC fuse with base 15nos- 415V,100A,HRC fuse with base. 3nos- 415 V ,200A, HRC fuse with base Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 600/630 KVA Transformer PFI capacity 375 KVAR

1.0000

each

400000.00

400000.00

Subtotal-A: All other remaining cost

( +1.00 % on Subtotal-A )

4000.00

Subtotal-A1:

404000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

412080.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

453288.00

VAT

6% of Total

IT

4% of Total

30219.20 20146.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

400000.00

503653.33

Page: 2817 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.09

Detailed Analysis Brief Description of Item 2 For 1000 KVA Transformer PFI capacity 600 KVAR 3 no- 415 V, 1200A hard drawn electrolytic copper busbar. 1no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with built in / separate discharge coil for connection directly with line through fuse. 3no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 4no- 415 V,50 KVAR,50 HZ TP power capacitor bank with built in / separate discharge resistor. 3nos- 415 V ,100 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 3no- 415 V ,40A, 50 HZ TP magnetic contactor with AC3 duty. 4no- 415 V ,80A,50 HZ auto TP magnetic contactor with AC3 duty 3nos- 415 V ,160A,50 HZ auto TP magnetic contactor with AC3 duty 12nos- 415V,50A,HRC fuse with base. 12nos- 415 V ,100A, HRC fuse with base 9nos- 415V,100A,HRC fuse with base. Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 1000 KVA Transformer PFI capacity 600 KVAR

1.0000

each

560000.00

560000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

5600.00

Subtotal-A1: Subtotal-B: Subtotal-C:

565600.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

576912.00

10% Profit ( Add 10% on Subtotal-B) :

634603.20

VAT

6% of Total

IT

4% of Total

42306.88 28204.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

560000.00

705114.67

Page: 2818 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.10

Detailed Analysis Brief Description of Item 2 For 1250 KVA Transformer PFI capacity 750 KVAR 3 no- 415 V, 1500A hard drawn electrolytic copper busbar. 1no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with built in / separate discharge coil for connection directly with line through fuse. 3no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 3no- 415 V,50 KVAR,50 HZ TP power capacitor bank with built in / separate discharge resistor. 5nos- 415 V ,100 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 3no- 415 V ,40A, 50 HZ TP magnetic contactor with AC3 duty. 3no- 415 V ,80A,50 HZ auto TP magnetic contactor with AC3 duty 5nos- 415 V ,160A,50 HZ auto TP magnetic contactor with AC3 duty 12nos- 415V,50A,HRC fuse with base. 9nos- 415 V ,100A, HRC fuse with base 15nos- 415V,200A,HRC fuse with base. Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 1250 KVA Transformer PFI capacity 750 KVAR

1.0000

each

720000.00

720000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

7200.00

Subtotal-A1: Subtotal-B: Subtotal-C:

727200.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

741744.00

10% Profit ( Add 10% on Subtotal-B) :

815918.40

VAT

6% of Total

IT

4% of Total

54394.56 36263.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

720000.00

906576.00

Page: 2819 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.11

Detailed Analysis Brief Description of Item 2 For 1500 KVA Transformer PFI capacity 900 KVAR 3 no- 415 V, 1800A hard drawn electrolytic copper busbar. 1no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with built in / separate discharge coil for connection directly with line through fuse. 3no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 4no- 415 V,50 KVAR,50 HZ TP power capacitor bank with built in / separate discharge resistor. 6nos- 415 V ,100 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 3no- 415 V ,40A, 40 HZ TP magnetic contactor with AC3 duty. 4no- 415 V ,80A,50 HZ auto TP magnetic contactor with AC3 duty 6nos- 415 V ,160A,50 HZ auto TP magnetic contactor with AC3 duty 12nos- 415V,50A,HRC fuse with base. 12nos- 415V,100A,HRC fuse with base. 18nos- 415V,200A,HRC fuse with base Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 1500/1600 KVA Transformer PFI capacity 900 KVAR

1.0000

each

770000.00

770000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

7700.00

Subtotal-A1:

777700.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

793254.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

872579.40

VAT

6% of Total

IT

4% of Total

58171.96 38781.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

770000.00

969532.67

Page: 2820 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.05.12

Detailed Analysis Brief Description of Item 2 For 2000 KVA Transformer PFI capacity 1200 KVAR 3 no- 415 V, 2000A hard drawn electrolytic copper busbar. 1no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with built in / separate discharge coil for connection directly with line through fuse. 2no- 415 V ,25 KVAR,50 HZ TP power capacitor bank with bult in / separate discharge resistor 3no- 415 V,75 KVAR,50 HZ TP power capacitor bank with built in / separate discharge resistor. 6nos- 415 V ,150 KVAR , 50 HZ TP power capacitor bank with built in/ separate discharge resistor. 2no- 415 V ,40A, 40 HZ TP magnetic contactor with AC3 duty. 3no- 415 V ,125A,50 HZ auto TP magnetic contactor with AC3 duty 6nos- 415 V ,250A,50 HZ auto TP magnetic contactor with AC3 duty 9nos- 415V,50A,HRC fuse with base. 9nos- 415V,150A,HRC fuse with base. 18nos- 415V,300A,HRC fuse with base Assembled by AEG/ Energy pac/ SIEMENS or equivalent according to the specification & direction of Engineer- in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Equipment for 2000 KVA Transformer PFI capacity 1200 KVAR

1.0000

each

90000.00

90000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

900.00

Subtotal-A1: Subtotal-B: Subtotal-C:

90900.00 92718.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

101989.80

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6799.32 4532.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

90000.00

113322.00

Page: 2821 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.06

Detailed Analysis Brief Description of Item 2 Lightning arresterSupplying of outdoor type 11 KV . 50 HZ , 100A (10 KA) , 75 KV BIL lightning arrester complete with mounting accessories etc. Manufacturered by SIEMENS Bangladesh Ltd. Energy pac or equivalent . Product of USA ,EU countries (3nos in set

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Lightning arrester

1.0000

set

10000.00

10000.00

Subtotal-A: all other remaing cost

( +1.00 % on Subtotal-A )

100.00

Subtotal-A1:

10100.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10302.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11332.20

VAT

6% of Total

IT

4% of Total

755.48 503.65 Total:

12.07.07

Drop out fuse: Supplying of outdoor type 11 KV . 50 HZ , 5 KA (20 KA) , drop out fuse complete with mounting accessories etc.mufacturered by SIEMENS Bangladesh Ltd. Energy pac or equivalent . Product of USA ,EU countries (3nos in set)countries

12591.33

set

HT dropout fuse

1.0000

set

10000.00

all other remaining cost

( +1.00 % on Subtotal-A )

100.00

Subtotal-A1: Subtotal-B: Subtotal-C:

10000.00 10000.00

Subtotal-A:

10100.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10302.00

10% Profit ( Add 10% on Subtotal-B) :

11332.20

VAT

6% of Total

IT

4% of Total

755.48 503.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10000.00

12591.33

Page: 2822 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.08

Detailed Analysis Brief Description of Item 2 Disconnecting switch: Supplying of 11 KV . 50 HZ , 320A,3- phase outdoor type Disconnecting switch having 75 KV BIL manufactured by drop out fuse complete with mounting accessories etc. mufacturered by SIEMENS Bangladesh Ltd. Energy pac or equivalent . Product of USA ,EU countries

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

HT disconnecting switch

1.0000

set

60000.00

60000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

600.00

Subtotal-A1:

60600.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61812.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

67993.20

VAT

6% of Total

4532.88

IT

4% of Total

3021.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

60000.00

75548.00

Page: 2823 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.09

Detailed Analysis Brief Description of Item 2 U channel Cross arm: Supplying & fixing U- channel iron cross-arm of size 38mmx76mmx38mmx6.35mm on single pole / H- pole with the help of necessary clamps, nuts, bolt etc. including making required no. of holes on the cross- arm for fixing of drop out fuse, lightning arrester including two coats of superior quality aluminum painting over required prime coat of anti corrosive red- oxide painting complete as required & as per instruction of the Engineering- in- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

U-channel HT disconnecting switch

1.0000

m

10000.00

10000.00

Plumber/ Electric Mistry/ Painter

0.4000

day

680.00

272.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 10742.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

107.42

Subtotal-A1:

10849.42

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11066.41

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12173.05

VAT

6% of Total

IT

4% of Total

811.54 541.02 Total:

12.07.10

13525.61

Installation of HTswitch gear : installation, testing & commissioning of following 11 KV , 50 HZ , 3-phase, indoor type HT switch gear on prepared foundation with the help of necessary tools& plants , skilled labour & technician as per direction of the Engineering- in- charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2824 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.10.1

Detailed Analysis Brief Description of Item 2 With fixed type vacuum circuit breaker

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

per job Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Asst Electrician

4.0000

day

680.00

2720.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

8.0000

day

470.00

3760.00 7840.00

Subtotal-A: all other remaining cost

( +70.00 % on Subtotal-A )

Subtotal-A1:

13328.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13594.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14954.02

VAT

6% of Total

IT

4% of Total

996.93 664.62 Total:

12.07.10.2

With withdraw able type vacuum circuit breaker

16615.57

per job Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Asst Electrician

4.0000

day

680.00

2720.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

8.0000

day

470.00

3760.00 7840.00

Subtotal-A: all other remaining cost

( +80.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

6272.00 14112.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14394.24

10% Profit ( Add 10% on Subtotal-B) :

15833.66

VAT

6% of Total

IT

4% of Total

1055.58 703.72 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5488.00

17592.96

Page: 2825 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

12.07.11

Installation of transformer: installation, testing & commissioning of following 11 KV / 0.415 KV, 50 HZ , 3-phase,indoor / outdoor type transformer on a prepared platform on pole /cc foundation with the help of necessary tools & plants skilled labour & technician as per direction of the Engineering- in- charge.

12.07.11.1

150KVA 3- Phase transformer on H-pole

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

day

680.00

680.00

set Plumber/ Electric Mistry/ Painter

1.0000

Asst Electrician

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

8.0000

day

470.00

3760.00 5800.00

Subtotal-A: all other remaining cost

( +75.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

10150.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10353.00

10% Profit ( Add 10% on Subtotal-B) :

11388.30

VAT

6% of Total

IT

4% of Total

759.22 506.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4350.00

12653.67

Page: 2826 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.11.2

Detailed Analysis Brief Description of Item 2 200-250KVA 3- Phase transformer on H-pole

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

8.0000

day

470.00

3760.00 5800.00

Subtotal-A: all other remaining cost

( +80.00 % on Subtotal-A )

Subtotal-A1:

10440.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10648.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11713.68

VAT

6% of Total

IT

4% of Total

780.91 520.61 Total:

12.07.11.3

150KVA 3- Phase transformer on CC pad

13015.20

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

5.0000

day

470.00

2350.00 4390.00

Subtotal-A: all other remaining cost

( +75.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3292.50 7682.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7836.15

10% Profit ( Add 10% on Subtotal-B) :

8619.77

VAT

6% of Total

IT

4% of Total

574.65 383.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4640.00

9577.52

Page: 2827 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.11.4

Detailed Analysis Brief Description of Item 2 200-315KVA 3- Phase transformer on CC pad

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

6.0000

day

470.00

2820.00 4860.00

Subtotal-A: all other remaing cost

( +80.00 % on Subtotal-A )

Subtotal-A1:

8748.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8922.96

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9815.26

VAT

6% of Total

IT

4% of Total

654.35 436.23 Total:

12.07.11.5

400-630KVA 3- Phase transformer on CC pad

10905.84

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

3.0000

day

680.00

2040.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

8.0000

day

470.00

3760.00 6480.00

Subtotal-A: all other remaining cost

( +80.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

5184.00 11664.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11897.28

10% Profit ( Add 10% on Subtotal-B) :

13087.01

VAT

6% of Total

IT

4% of Total

872.47 581.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3888.00

14541.12

Page: 2828 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.11.6

Detailed Analysis Brief Description of Item 2 800-1000 KVA 3- Phase transformer on CC pad

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Asst Electrician

4.0000

day

680.00

2720.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

8.0000

day

470.00

3760.00 7840.00

Subtotal-A: all other remaining cost

( +90.00 % on Subtotal-A )

Subtotal-A1:

14896.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15193.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16713.31

VAT

6% of Total

IT

4% of Total

1114.22 742.81 Total:

12.07.11.7

1250-1600KVA 3- Phase transformer on CC

18570.35

set Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Asst Electrician

4.0000

day

680.00

2720.00

12.0000

day

470.00

5640.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

9720.00

Subtotal-A: all other remaining cost

( +90.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

8748.00 18468.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18837.36

10% Profit ( Add 10% on Subtotal-B) :

20721.10

VAT

6% of Total

IT

4% of Total

1381.41 920.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7056.00

23023.44

Page: 2829 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.11.8

Detailed Analysis Brief Description of Item 2 2000KVA 3- Phase transformer on CC pad

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Asst Electrician

5.0000

day

680.00

3400.00

16.0000

day

470.00

7520.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

12280.00

Subtotal-A: all other remaining cost

( +95.00 % on Subtotal-A )

Subtotal-A1:

23946.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

24424.92

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

26867.41

VAT

6% of Total

IT

4% of Total

1791.16 1194.11 Total:

12.07.12

11666.00

29852.68

Installation of LT switch gear: installation, testing & commissioning of 415V, 3- phase,50 HZ indoor type LT switch gear / PFI plant suitable for following capacity transformer on prepared CC foundation with the help of necessary tools & plants, skilled labour & technician as per direction of the Engineering- in- charge

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2830 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.07.12.1

2 150KVA 3- Phase transformer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

4.0000

day

470.00

1880.00 3920.00

Subtotal-A: all other remaining cost

( +60.00 % on Subtotal-A )

Subtotal-A1:

6272.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6397.44

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7037.18

VAT

6% of Total

IT

4% of Total

469.15 312.76 Total:

12.07.12.2

200-400KVA 3- Phase transformer

7819.09

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

6.0000

day

470.00

2820.00 4860.00

Subtotal-A: all other remaining cost

( +60.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

2916.00 7776.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7931.52

10% Profit ( Add 10% on Subtotal-B) :

8724.67

VAT

6% of Total

IT

4% of Total

581.64 387.76 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2352.00

9694.08

Page: 2831 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.12.3

Detailed Analysis Brief Description of Item 2 500-600KVA 3- Phase transformer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

7.0000

day

470.00

3290.00 5330.00

Subtotal-A: all other remaining cost

( +62.00 % on Subtotal-A )

Subtotal-A1:

8634.60

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8807.29

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9688.02

VAT

6% of Total

IT

4% of Total

645.87 430.58 Total:

12.07.12.4

800-1000KVA 3- Phase transformer

10764.47

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

2.0000

day

680.00

1360.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

7.0000

day

470.00

3290.00 5330.00

Subtotal-A: all other remainig cost

( +65.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

3464.50 8794.50

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8970.39

10% Profit ( Add 10% on Subtotal-B) :

9867.43

VAT

6% of Total

IT

4% of Total

657.83 438.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3304.60

10963.81

Page: 2832 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.07.12.5

2 1250-1600KVA 3- Phase transformer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

3.0000

day

680.00

2040.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

8.0000

day

470.00

3760.00 6480.00

Subtotal-A: all other remaining cost

( +70.00 % on Subtotal-A )

Subtotal-A1:

11016.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11236.32

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12359.95

VAT

6% of Total

IT

4% of Total

824.00 549.33 Total:

12.07.12.6

2000KVA 3- Phase transformer

13733.28

set Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Asst Electrician

3.0000

day

680.00

2040.00

10.0000

day

470.00

4700.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

7420.00

Subtotal-A: all other remaing cost

( +80.00 % on Subtotal-A )

Subtotal-A1: Subtotal-B: Subtotal-C:

5936.00 13356.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13623.12

10% Profit ( Add 10% on Subtotal-B) :

14985.43

VAT

6% of Total

IT

4% of Total

999.03 666.02 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4536.00

16650.48

Page: 2833 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

12.07.13

Installation of HT Drop out fuse: Installation of HT Drop out fuse / lightning arrester/ disconnection switch on prepared U- channel crossarm on single / H – pole with necessary fixing materials complete as per instruction of the Engineer-in-charge.

12.07.13.1

Drop out fuse

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Asst Electrician

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 1490.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

14.90

Subtotal-A1:

1504.90

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1535.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1688.50

VAT

6% of Total

112.57

IT

4% of Total

75.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1876.11

Page: 2834 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.07.13.2

2 Lightning arrester

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

set Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Asst Electrician

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 1490.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

14.90

Subtotal-A1:

1504.90

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1535.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1688.50

VAT

6% of Total

IT

4% of Total

112.57 75.04 Total:

12.07.13.3

Disconnection switch

set Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Asst Electrician

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 1490.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

14.90

Subtotal-A1: Subtotal-B: Subtotal-C:

1504.90 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1535.00

10% Profit ( Add 10% on Subtotal-B) :

1688.50

VAT

6% of Total

IT

4% of Total

112.57 75.04 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1876.11

1876.11

Page: 2835 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

12.07.14

Component of substation equipment: Supplying of the following component / equipments suitable for use at 11/0.415/0.240 KA & powersupply system manufactured and tested in USA / UK / Germany or equivalent approved by the Engineer-in-charge according to IEC / VDE / BS Standard.

12.07.14.01

11 KV ,3-phase, 50 HZ HT VCB circuit breaker , 630A, 20KA

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each component sub-station equipment HT VCB 630A

1.0000

each

750000.00

750000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

7500.00

Subtotal-A1:

757500.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

772650.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

849915.00

VAT

6% of Total

56661.00

IT

4% of Total

37774.00 Total:

12.07.14.02

11 KV , 50 HZ 50 VA 11/0.11 ratio cast rasin insulated potential transformer (PT) class 0.5

944350.00

each component 11 KV 50VA 11/011 ratio cast resin insulated PT class 0.5

1.0000

each

30000.00

all other remaining cost

( +1.00 % on Subtotal-A )

300.00

Subtotal-A1: Subtotal-B: Subtotal-C:

30000.00 30000.00

Subtotal-A:

30300.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30906.00

10% Profit ( Add 10% on Subtotal-B) :

33996.60

VAT

6% of Total

IT

4% of Total

2266.44 1510.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

750000.00

37774.00

Page: 2836 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.03

Detailed Analysis Brief Description of Item 2 11 KV , 50 HZ 10-15VA adequate ratio , double core cast rasin insulated current transformer (CT)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each component 11 KV 10-15VA 11/011 adequate ratio double core cast resin insulated CT class 0.5

1.0000

each

30000.00

30000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

300.00

Subtotal-A1:

30300.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30906.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33996.60

VAT

6% of Total

IT

4% of Total

2266.44 1510.96 Total:

12.07.14.04

11 KV , 50 HZ 15VA adequate ratio , single core cast rasin insulated current transformer (CT)

37774.00

each component 11 KV 15VA 11/011 adequate ratio single core cast resin insulated CT

1.0000

each

30000.00

all other remaining cost

( +1.00 % on Subtotal-A )

300.00

Subtotal-A1: Subtotal-B: Subtotal-C:

30000.00 30000.00

Subtotal-A:

30300.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30906.00

10% Profit ( Add 10% on Subtotal-B) :

33996.60

VAT

6% of Total

IT

4% of Total

2266.44 1510.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

30000.00

37774.00

Page: 2837 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.05

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

Microprocessor controlled three-phase 50 HZ IDMT relay for 11 KV switchgear

each

Quantity

component Microprocessor controlled three-phase 50 HZ IDMT relay for 11 KV switchgear

5

1.0000

Unit

Rate

6

7

each

Amount 8

100000.00

100000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

1000.00

Subtotal-A1:

101000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

103020.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

113322.00

VAT

6% of Total

IT

4% of Total

7554.80 5036.53 Total:

12.07.14.06

11 KV ,potential bushing (for transformer capacity up to 2MVA)

125913.33

each component 11 KV ,potential bushing (for transformer capacity up to 2MVA

1.0000

each

30000.00

30000.00 30000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

300.00

Subtotal-A1:

30300.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30906.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33996.60

VAT

6% of Total

2266.44

IT

4% of Total

1510.96 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

100000.00

37774.00

Page: 2838 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.07

Detailed Analysis Brief Description of Item 2 500V, potential bushing (for transformer capacity up to 2MVA

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each component 500V, potential bushing (for transformer capacity up to 2MVA

1.0000

each

10000.00

10000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

100.00

Subtotal-A1: Subtotal-B: Subtotal-C:

10100.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10302.00

10% Profit ( Add 10% on Subtotal-B) :

11332.20

VAT

6% of Total

IT

4% of Total

755.48 503.65 Total:

12.07.14.08

Thermostat controlled panel heater for 11 KV , 50HZ, switchgear

12591.33

each component Thermostat controlled panel heater for 11 KV , 50HZ, switchgear

1.0000

each

7643.00

all other remaining cost

( +1.00 % on Subtotal-A )

76.43

Subtotal-A1: Subtotal-B: Subtotal-C:

7643.00 7643.00

Subtotal-A:

7719.43 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7873.82

10% Profit ( Add 10% on Subtotal-B) :

8661.20

VAT

6% of Total

IT

4% of Total

577.41 384.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10000.00

9623.56

Page: 2839 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.09

Detailed Analysis Brief Description of Item 2 Buchholz relay for 11/0.415 & 0.24 KA 3-phase, 50 HZ transformer.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each component Buchholz relay for 11/0.415 & 0.24 KA 3-phase, 50 HZ transformer

1.0000

each

25000.00

25000.00

Subtotal-A: all other remaing cost

( +1.00 % on Subtotal-A )

250.00

Subtotal-A1: Subtotal-B: Subtotal-C:

25250.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25755.00

10% Profit ( Add 10% on Subtotal-B) :

28330.50

VAT

6% of Total

IT

4% of Total

1888.70 1259.13 Total:

12.07.14.10

415V50 HZ,3-phase capacitor bank of following capacity 5 KVAR

31478.33

each component capacitor bank 5 KVAR

1.0000

each

5000.00

5000.00 5000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

50.00

Subtotal-A1:

5050.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5151.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5666.10

VAT

6% of Total

IT

4% of Total

377.74 251.83 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25000.00

6295.67

Page: 2840 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.11

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

415V50 HZ,3-phase capacitor bank of following capacity 7.5 KVAR

each component capacitor bank 7.5 KVAR

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

7000.00

7000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

70.00

Subtotal-A1: Subtotal-B: Subtotal-C:

7070.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7211.40

10% Profit ( Add 10% on Subtotal-B) :

7932.54

VAT

6% of Total

IT

4% of Total

528.84 352.56 Total:

12.07.14.12

415V50 HZ,3-phase capacitor bank of following capacity 10 KVAR

8813.93

each component capacitor bank 10 KVAR

1.0000

each

9000.00

all other remaining cost

( +1.00 % on Subtotal-A )

90.00

Subtotal-A1: Subtotal-B: Subtotal-C:

9000.00 9000.00

Subtotal-A:

9090.00 9271.80

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10198.98

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

679.93 453.29 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7000.00

11332.20

Page: 2841 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.13

Detailed Analysis Brief Description of Item 2 415V50 HZ,3-phase capacitor bank of following capacity 12.5 KVAR

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each component capacitor bank 12.5 KVAR

1.0000

each

13000.00

13000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

130.00

Subtotal-A1: Subtotal-B: Subtotal-C:

13130.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13392.60

10% Profit ( Add 10% on Subtotal-B) :

14731.86

VAT

6% of Total

IT

4% of Total

982.12 654.75 Total:

12.07.14.14

415V50 HZ,3-phase capacitor bank of following capacity 20 KVAR

16368.73

each component capacitor bank 20 KVAR

1.0000

each

20000.00

all other remaining cost

( +1.00 % on Subtotal-A )

200.00

Subtotal-A1: Subtotal-B: Subtotal-C:

20000.00 20000.00

Subtotal-A:

20200.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20604.00

10% Profit ( Add 10% on Subtotal-B) :

22664.40

VAT

6% of Total

IT

4% of Total

1510.96 1007.31 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13000.00

25182.67

Page: 2842 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.15

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

415V50 HZ,3-phase capacitor bank of following capacity 25 KVAR

each component capacitor bank 25 KVAR

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

22000.00

22000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

220.00

Subtotal-A1: Subtotal-B: Subtotal-C:

22220.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22664.40

10% Profit ( Add 10% on Subtotal-B) :

24930.84

VAT

6% of Total

IT

4% of Total

1662.06 1108.04 Total:

12.07.14.16

415V50 HZ,3-phase capacitor bank of following capacity 40 KVAR

27700.93

each component capacitor bank 40 KVAR

1.0000

each

26000.00

all other remaing cost

( +1.00 % on Subtotal-A )

260.00

Subtotal-A1: Subtotal-B: Subtotal-C:

26000.00 26000.00

Subtotal-A:

26260.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26785.20

10% Profit ( Add 10% on Subtotal-B) :

29463.72

VAT

6% of Total

IT

4% of Total

1964.25 1309.50 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

22000.00

32737.47

Page: 2843 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.17

Detailed Analysis Brief Description of Item

Unit

Sub-Item

2

3

4

415V50 HZ,3-phase capacitor bank of following capacity 50 KVAR

each component capacitor bank 50 KVAR

Quantity 5

1.0000

Unit

Rate

6

7

each

Amount 8

35000.00

35000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

350.00

Subtotal-A1: Subtotal-B: Subtotal-C:

35350.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

36057.00

10% Profit ( Add 10% on Subtotal-B) :

39662.70

VAT

6% of Total

IT

4% of Total

2644.18 1762.79 Total:

12.07.14.18

415V50 HZ,3-phase capacitor bank of following capacity 100 KVAR

44069.67

each component capacitor bank 100 KVAR

1.0000

each

42000.00

all other remaing cost

( +1.00 % on Subtotal-A )

420.00

Subtotal-A1: Subtotal-B: Subtotal-C:

42000.00 42000.00

Subtotal-A:

42420.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

43268.40

10% Profit ( Add 10% on Subtotal-B) :

47595.24

VAT

6% of Total

IT

4% of Total

3173.02 2115.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35000.00

52883.60

Page: 2844 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.19

Detailed Analysis Brief Description of Item 2 Power factor correction relay 6 stage

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each component PFC relay 6 stage

1.0000

each

15000.00

15000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

150.00

Subtotal-A1: Subtotal-B: Subtotal-C:

15150.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15453.00

10% Profit ( Add 10% on Subtotal-B) :

16998.30

VAT

6% of Total

IT

4% of Total

1133.22 755.48 Total:

12.07.14.20

Power factor correction relay 9 stage

18887.00

each component PFC relay 9 stage

1.0000

each

25000.00

all other remaining cost

( +1.00 % on Subtotal-A )

250.00

Subtotal-A1: Subtotal-B: Subtotal-C:

25000.00 25000.00

Subtotal-A:

25250.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25755.00

10% Profit ( Add 10% on Subtotal-B) :

28330.50

VAT

6% of Total

IT

4% of Total

1888.70 1259.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15000.00

31478.33

Page: 2845 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.14.21

Detailed Analysis Brief Description of Item 2 Oil level indicator for 11/0.415 & 0.24 KV transformer

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each component Oil level indicator for 11/0.415 & 0.24 KV transformer

1.0000

each

5000.00

5000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

50.00

Subtotal-A1: Subtotal-B: Subtotal-C:

12.07.14.22

Silicagel breather container for transformer

5050.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5151.00

10% Profit ( Add 10% on Subtotal-B) :

5666.10

VAT

6% of Total

IT

4% of Total

377.74 251.83 Total:

6295.67

10000.00

10000.00

each component Silcagel breather container for transformer

1.0000

each

10000.00

Subtotal-A: all other component

( +1.00 % on Subtotal-A )

100.00

Subtotal-A1:

10100.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10302.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

11332.20

VAT

6% of Total

IT

4% of Total

755.48 503.65 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5000.00

12591.33

Page: 2846 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.07.14.23

2 Silicagel for transformer breather

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

926.00

926.00

each component Silcagel for transformer breather

1.0000

each

926.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

9.26

Subtotal-A1: Subtotal-B: Subtotal-C:

935.26 953.97

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1049.36

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

69.96 46.64 Total:

12.07.14.24

Transformer oil

each Transformer oil

1.0000

each

208.00

all other remaining cost

( +1.00 % on Subtotal-A )

2.08

Subtotal-A1: Subtotal-B: Subtotal-C:

210.08 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

214.28

10% Profit ( Add 10% on Subtotal-B) :

235.71

VAT

6% of Total

IT

4% of Total

15.71 10.48 Total:

MCCB: Supplying of 415, 3-phase, following capacity control circuit breaker feeder unit with thermal over current & instantaneous electromagnetic short- circuit release and ( adjustable type above 100 A rating) for sub- station LT panel.

Note : Rates of all items should be inclusive of all supply and carriage.

208.00 208.00

Subtotal-A:

12.07.15

1165.96

261.90

each

Page: 2847 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.01

Detailed Analysis Brief Description of Item 2 30/32 A ( 16 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

40 A( 16 KA ) TP MCCB.

1.0000

each

7000.00

7000.00

Subtotal-A: all ther remaining cost

( +1.00 % on Subtotal-A )

70.00

Subtotal-A1:

7070.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7211.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7932.54

VAT

6% of Total

IT

4% of Total

528.84 352.56 Total:

12.07.15.02

40 A( 16 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

8813.93

each

40 A( 16 KA ) TP MCCB.

1.0000

each

7000.00

all other remaining cost

( +1.00 % on Subtotal-A )

70.00

Subtotal-A1: Subtotal-B: Subtotal-C:

7000.00 7000.00

Subtotal-A:

7070.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7211.40

10% Profit ( Add 10% on Subtotal-B) :

7932.54

VAT

6% of Total

IT

4% of Total

528.84 352.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7000.00

8813.93

Page: 2848 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.03

Detailed Analysis Brief Description of Item 2 50 A ( 16 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

50 A( 16 KA ) TP MCCB.

1.0000

each

7000.00

7000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

70.00

Subtotal-A1:

7070.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7211.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

7932.54

VAT

6% of Total

IT

4% of Total

528.84 352.56 Total:

12.07.15.04

60 / 63 A ( 16 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

8813.93

each

60/63 A( 16 KA ) TP MCCB.

1.0000

each

7000.00

all other remaining cost

( +1.00 % on Subtotal-A )

70.00

Subtotal-A1: Subtotal-B: Subtotal-C:

7000.00 7000.00

Subtotal-A:

7070.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7211.40

10% Profit ( Add 10% on Subtotal-B) :

7932.54

VAT

6% of Total

IT

4% of Total

528.84 352.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7000.00

8813.93

Page: 2849 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.05

Detailed Analysis Brief Description of Item 2 80 A ( 16 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

80 A( 16 KA ) TP MCCB.

1.0000

each

7761.00

7761.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

77.61

Subtotal-A1:

7838.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7995.38

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8794.92

VAT

6% of Total

IT

4% of Total

586.33 390.89 Total:

12.07.15.06

100 A ( 16 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

9772.13

each

100 A( 16 KA ) TP MCCB.

1.0000

each

8970.00

all other remaining cost

( +1.00 % on Subtotal-A )

89.70

Subtotal-A1: Subtotal-B: Subtotal-C:

8970.00 8970.00

Subtotal-A:

9059.70 9240.89

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10164.98

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

677.67 451.78 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7761.00

11294.43

Page: 2850 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.07

Detailed Analysis Brief Description of Item 2 150/160 A ( 16 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

150/160 A( 25 KA ) TP MCCB.

1.0000

each

16849.00

16849.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

168.49

Subtotal-A1:

17017.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

17357.84

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

19093.62

VAT

6% of Total

IT

4% of Total

1272.91 848.61 Total:

12.07.15.08

200 A ( 25 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

21215.14

each

200 A( 25 KA ) TP MCCB.

1.0000

each

12500.00

all other remaining cost

( +1.00 % on Subtotal-A )

125.00

Subtotal-A1: Subtotal-B: Subtotal-C:

12500.00 12500.00

Subtotal-A:

12625.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12877.50

10% Profit ( Add 10% on Subtotal-B) :

14165.25

VAT

6% of Total

IT

4% of Total

944.35 629.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

16849.00

15739.17

Page: 2851 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.09

Detailed Analysis Brief Description of Item 2 250A ( 35 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

250 A( 35 KA ) TP MCCB.

1.0000

each

15000.00

15000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

150.00

Subtotal-A1:

15150.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

15453.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

16998.30

VAT

6% of Total

IT

4% of Total

1133.22 755.48 Total:

12.07.15.10

300 / 320 A ( 35 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

18887.00

each

300/320 A( 35 KA ) TP MCCB.

1.0000

each

35000.00

all other remaining cost

( +1.00 % on Subtotal-A )

350.00

Subtotal-A1: Subtotal-B: Subtotal-C:

35000.00 35000.00

Subtotal-A:

35350.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

36057.00

10% Profit ( Add 10% on Subtotal-B) :

39662.70

VAT

6% of Total

IT

4% of Total

2644.18 1762.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15000.00

44069.67

Page: 2852 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.11

Detailed Analysis Brief Description of Item 2 400A ( 35 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

400 A( 35 KA ) TP MCCB.

1.0000

each

39000.00

39000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

390.00

Subtotal-A1:

39390.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40177.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

44195.58

VAT

6% of Total

IT

4% of Total

2946.37 1964.25 Total:

12.07.15.12

500A ( 35 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

49106.20

each

500 A( 35 KA ) TP MCCB.

1.0000

each

40000.00

all other remaining cost

( +1.00 % on Subtotal-A )

400.00

Subtotal-A1: Subtotal-B: Subtotal-C:

40000.00 40000.00

Subtotal-A:

40400.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

41208.00

10% Profit ( Add 10% on Subtotal-B) :

45328.80

VAT

6% of Total

IT

4% of Total

3021.92 2014.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

39000.00

50365.33

Page: 2853 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.13

Detailed Analysis Brief Description of Item 2 600 /630 A ( 35 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

600/630 A( 35 KA ) TP MCCB.

1.0000

each

45000.00

45000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

450.00

Subtotal-A1:

45450.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

46359.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

50994.90

VAT

6% of Total

IT

4% of Total

3399.66 2266.44 Total:

12.07.15.14

800 A ( 50 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

56661.00

each

800 A( 50 KA ) TP MCCB.

1.0000

each

90000.00

all other remaining cost

( +1.00 % on Subtotal-A )

900.00

Subtotal-A1: Subtotal-B: Subtotal-C:

90000.00 90000.00

Subtotal-A:

90900.00 92718.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

101989.80

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

6799.32 4532.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

45000.00

113322.00

Page: 2854 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.15

Detailed Analysis Brief Description of Item 2 1000 A ( 50 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1000 A( 50 KA ) TP MCCB.

1.0000

each

120000.00

120000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

1200.00

Subtotal-A1:

121200.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

123624.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

135986.40

VAT

6% of Total

IT

4% of Total

9065.76 6043.84 Total:

12.07.15.16

1200/1250A ( 50 KA ) TP MCCB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

151096.00

each

1200/1250 A( 50 KA ) TP MCCB.

1.0000

each

126000.00

all other remaining cost

( +1.00 % on Subtotal-A )

1260.00

Subtotal-A1: Subtotal-B: Subtotal-C:

126000.00 126000.00

Subtotal-A:

127260.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

129805.20

10% Profit ( Add 10% on Subtotal-B) :

142785.72

VAT

6% of Total

IT

4% of Total

9519.05 6346.03 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

120000.00

158650.80

Page: 2855 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.17

Detailed Analysis Brief Description of Item 2 1600A ( 65 KA ) TP ACB. Manufacturer- AEG ( Germany)/ Dorman & Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1600 A( 50 KA ) TP MCCB.

1.0000

each

155000.00

155000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

1550.00

Subtotal-A1:

156550.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

159681.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

175649.10

VAT

6% of Total

IT

4% of Total

11709.94 7806.63 Total:

12.07.15.18

2000 A ( 65 KA ) TP ACB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

195165.67

each

2000 A( 65KA ) TP MCCB.

1.0000

each

225000.00

All other remaining cost

( +1.00 % on Subtotal-A )

2250.00

Subtotal-A1: Subtotal-B: Subtotal-C:

225000.00 225000.00

Subtotal-A:

227250.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

231795.00

10% Profit ( Add 10% on Subtotal-B) :

254974.50

VAT

6% of Total

IT

4% of Total

16998.30 11332.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

155000.00

283305.00

Page: 2856 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.15.19

Detailed Analysis Brief Description of Item 2 2500 A ( 65 KA ) TP ACB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

2500 A( 65 KA ) TP MCCB.

1.0000

each

275000.00

275000.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

2750.00

Subtotal-A1:

277750.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

283305.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

311635.50

VAT

6% of Total

IT

4% of Total

20775.70 13850.47 Total:

12.07.15.20

3000 / 3200 A ( 65 KA ) TP ACB. Manufacturer- AEG ( Germany)/ Dorman& Smith ( UK) / MEM ( UK) SIEMENS ( GERMANY / USA )or equivalent approved by the Engineerin- charge.

346261.67

each

3000/3200 A( 65KA ) TP MCCB.

1.0000

each

350000.00

all other remaining cost

( +1.00 % on Subtotal-A )

3500.00

Subtotal-A1: Subtotal-B: Subtotal-C:

350000.00 350000.00

Subtotal-A:

353500.00 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

360570.00

10% Profit ( Add 10% on Subtotal-B) :

396627.00

VAT

6% of Total

IT

4% of Total

26441.80 17627.87 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

275000.00

440696.67

Page: 2857 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.16

Detailed Analysis Brief Description of Item 2 HT automatic voltage regulator ( HTAVR ): Supplying of 150 Amps.6.35 KV , 50 HZ single phase oil immerged automatic voltage regulator ( AVR ) having voltage regulation+ - 10% in 32 steps of 5/8% each , basic insulation level 95KV ,Microprocessor based control, LCD display position indicator in/c all standard accessories manufactured & tasted in USA/Japan/EU countries or equivalent approved by the Engineer- incharge according to VDE/IEC/BSS

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1412841.00

1412841.00

each

HT AVR

1.0000

1412841.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

14128.41

Subtotal-A1:

1426969.41

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1455508.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1601059.68

VAT

6% of Total

106737.31

IT

4% of Total

71158.21 Total:

12.07.17

1778955.20

LT automatic voltage regulator ( LTAVR ): Supplying, ,installation , testing & commissioning of following 415V , 3-phase 50 HZ electronically controlled automatic voltage stabilizer / regulator locally assembled in metallic painted cabinet suitable for input voltage range 300 – 400, output stepless continuous voltage 400 V +-3% correction speed 20V /sec ( minimum) complete with phase failure and spike & surge fluctuation voltage protection auto shunt off at high& low voltage with autoreset system , overload & instantaneous short circuit protection by MCCB & relay , transient suppression circuit, ON-OFF TRIP indicators, voltmeter& ammeter,by pass circuit etc.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2858 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.17.01

Detailed Analysis Brief Description of Item 2 15 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

LT AVR 15KVA

1.0000

each

108004.00

108004.00

Subtotal-A: all other remaining cost

( +2.00 % on Subtotal-A )

2160.08

Subtotal-A1: Subtotal-B: Subtotal-C:

110164.08 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

112367.36

10% Profit ( Add 10% on Subtotal-B) :

123604.10

VAT

6% of Total

IT

4% of Total

8240.27 5493.52 Total:

12.07.17.02

20 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

137337.89

each

LT AVR 20KVA

1.0000

each

137404.00

137404.00 137404.00

Subtotal-A: all other remaining cost

( +2.00 % on Subtotal-A )

2748.08

Subtotal-A1:

140152.08

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

142955.12

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

157250.63

VAT

6% of Total

IT

4% of Total

10483.38 6988.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

108004.00

174722.93

Page: 2859 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.17.03

Detailed Analysis Brief Description of Item 2 30 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

LT AVR 30KVA

1.0000

each

170856.00

170856.00

Subtotal-A: all other remaining cost

( +2.00 % on Subtotal-A )

3417.12

Subtotal-A1: Subtotal-B: Subtotal-C:

174273.12 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

177758.58

10% Profit ( Add 10% on Subtotal-B) :

195534.44

VAT

6% of Total

IT

4% of Total

13035.63 8690.42 Total:

12.07.17.04

40 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

217260.49

each

LT AVR 40KVA

1.0000

each

177176.00

177176.00 177176.00

Subtotal-A: all other remaining cost

( +2.00 % on Subtotal-A )

3543.52

Subtotal-A1:

180719.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

184333.91

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

202767.30

VAT

6% of Total

IT

4% of Total

13517.82 9011.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

170856.00

225297.00

Page: 2860 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.17.05

Detailed Analysis Brief Description of Item 2 50 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

LT AVR 50KVA

1.0000

each

232977.00

232977.00

Subtotal-A: All other remaining cost

( +2.00 % on Subtotal-A )

4659.54

Subtotal-A1: Subtotal-B: Subtotal-C:

237636.54 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

242389.27

10% Profit ( Add 10% on Subtotal-B) :

266628.20

VAT

6% of Total

IT

4% of Total

17775.21 11850.14 Total:

12.07.17.06

60 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

296253.55

each

LT AVR 60KVA

1.0000

each

257169.00

257169.00 257169.00

Subtotal-A: all other remaining cost

( +2.00 % on Subtotal-A )

5143.38

Subtotal-A1:

262312.38

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

267558.63

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

294314.49

VAT

6% of Total

IT

4% of Total

19620.97 13080.64 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

232977.00

327016.10

Page: 2861 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.17.07

Detailed Analysis Brief Description of Item 2 75 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

LT AVR 75KVA

1.0000

each

328812.00

328812.00

Subtotal-A: All Other remaining cost

( +2.00 % on Subtotal-A )

6576.24

Subtotal-A1:

335388.24

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

342096.00

10% Profit ( Add 10% on Subtotal-B) :

376305.61

VAT

6% of Total

IT

4% of Total

25087.04 16724.69 Total:

12.07.17.08

100 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

418117.34

each

LT AVR 100KVA

1.0000

each

444825.00

444825.00 444825.00

Subtotal-A: all other remaining cost

( +2.00 % on Subtotal-A )

8896.50

Subtotal-A1:

453721.50

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

462795.93

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

509075.52

VAT

6% of Total

IT

4% of Total

33938.37 22625.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

328812.00

565639.47

Page: 2862 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.17.09

Detailed Analysis Brief Description of Item 2 150 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

LT AVR 150KVA

1.0000

each

535080.00

535080.00

Subtotal-A: All Other Remaining Cost

( +2.00 % on Subtotal-A )

10701.60

Subtotal-A1:

545781.60

Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

556697.23

10% Profit ( Add 10% on Subtotal-B) :

612366.96

VAT

6% of Total

IT

4% of Total

40824.46 27216.31 Total:

12.07.17.10

200 KVA AVR Assembled by AEG / NAVANA / RAHIMA FROOZ or equivalent approved by the Engineer- in- charge

680407.73

each

LT AVR 200KVA

1.0000

each

649412.00

649412.00 649412.00

Subtotal-A: All remaining cost

( +2.00 % on Subtotal-A )

12988.24

Subtotal-A1:

662400.24

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

675648.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

743213.07

VAT

6% of Total

IT

4% of Total

49547.54 33031.69 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

535080.00

825792.30

Page: 2863 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.18

Detailed Analysis Brief Description of Item 2 By pass switch: Supplying of off- load 11 KV 1-pole 600 Amps. single phase , self sequencing 2 position by pass switch suitable for use with 11 KV AVR maximum design voltage rating 15.5 KV , impulse withstand voltage : 110 KV , continuous current rating : 400 A complete with all standard accessories Made in USA / JAPAN / EU or equivalent approved by the Engineer- in- charge

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

BI-Pass Switch

1.0000

each

197210.00

197210.00

Subtotal-A: all other remaining cost

( +1.00 % on Subtotal-A )

1972.10

Subtotal-A1: Subtotal-B: Subtotal-C:

199182.10 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

203165.74

10% Profit ( Add 10% on Subtotal-B) :

223482.32

VAT

6% of Total

IT

4% of Total

14898.82 9932.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

197210.00

248313.68

Page: 2864 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.07.19

Detailed Analysis Brief Description of Item 2 Installation testing & commissioning of 11- KV by pass switch in pre supplied and installed pole on prepared MS channel including all required materials as per direction of the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Plumber/ Electric Mistry/ Painter

2.0000

day

680.00

1360.00

Asst Electrician

4.0000

day

680.00

2720.00

12.0000

day

470.00

5640.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

9720.00

Subtotal-A: all other remaining cost

( +85.00 % on Subtotal-A )

Subtotal-A1:

17982.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18341.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20175.80

VAT

6% of Total

IT

4% of Total

1345.05 896.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8262.00

22417.56

Page: 2865 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

Unit

Sub-Item 4

1

2

3

12.07.20

Installation testing & commissioning of 11- KV AVR with all other necessary accessories / materials in the following method.

each Plumber/ Electric Mistry/ Painter

Quantity 5

2.0000

Unit

Rate

Amount

6

7

day

680.00

1360.00

8

Asst Electrician

4.0000

day

680.00

2720.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

8.0000

day

470.00

3760.00 7840.00

Subtotal-A: all other remaining cost

( +75.00 % on Subtotal-A )

Subtotal-A1:

13720.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13994.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15393.84

VAT

6% of Total

IT

4% of Total

1026.26 684.17 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5880.00

17104.27

Page: 2866 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.08

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1035500.00

1035500.00

3-Phase Diesel Generator: With ATS panel with sound attenuated acoustically treated canopy(Max sound level 75 dBA at 7m distance): Supply of 400&230v, 3-phase, 4-wire, 50Hz air/water cooled, floor mounted, indoor type following continuous capacity (Prime power) electric generating set suitable for tropocalized country complete with four stroke, 1500 rpm, diesel engine with all standard accessories viz. 12/24 voly DC battery & auto battery charger with ammeter, radiator assembly, oil & fuel pump, auto speed governor, air cleaner, fuel & oil tank, level & oil pressure gauge, RPM & hour meter, start & stop switch, exhaust silencer, vibration device viz. auto sgut off with indicators foroverload, over & under voltage, high temperature, low oil pressure, over speed, low fuel level etc. coupled with brush less, self excited alternator having control panel with auto voltage regulator, voltmeter & ammeter with selector switch, frequency meter. TPMCCB of required rating for overload & instantaneous short circuit release, manual chage over switch, indicator for ON-OFF-TRIP etc. maintenance manual an manufactured, assembled and trsted in accordance with NEMA/IEC/VDE/JIS standards (Subject to satisfy standard test and approved by LGED) All components manufacturerd assembled and tested in USA /Japan/EU countries or Equivalent Approved by engineer in charge.

12.08.01

30 KVA generator

each 30 KVA Generator

1.0000

1035500.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1056210.00

10% Profit ( Add 10% on Subtotal-B) :

1161831.00

VAT

6% of Total

IT

4% of Total

77455.40 51636.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1290923.33

Page: 2867 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.08.02

2 40 KVA Generator

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1144500.00

1144500.00

each 40 KVA Generator

1.0000

1144500.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1167390.00

10% Profit ( Add 10% on Subtotal-B) :

1284129.00

VAT

6% of Total

85608.60

IT

4% of Total

57072.40 Total:

12.08.03

60 KVA Generator

each 60 KVA Generator

1.0000

each

1417000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1445340.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1589874.00

VAT

6% of Total

IT

4% of Total

105991.60 70661.07 Total:

80 KVA Generator

1766526.67

each 80 KVA Generator

1.0000

each

1853000.00

Subtotal-B: Subtotal-C:

1853000.00 1853000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1890060.00

10% Profit ( Add 10% on Subtotal-B) :

2079066.00

VAT

6% of Total

IT

4% of Total

138604.40 92402.93 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1417000.00 1417000.00

Subtotal-A:

12.08.04

1426810.00

2310073.33

Page: 2868 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.08.05

2 100 KVA Generator

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

2049354.00

2049354.00

each 100 KVA Generator

1.0000

2049354.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2090341.08

10% Profit ( Add 10% on Subtotal-B) :

2299375.19

VAT

6% of Total

153291.68

IT

4% of Total

102194.45 Total:

12.08.06

150 KVA Generator

each 150 KVA Generator

1.0000

each

2725000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2779500.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3057450.00

VAT

6% of Total

IT

4% of Total

203830.00 135886.67 Total:

200 KVA Generator

3397166.67

each 200 KVA Generator

1.0000

each

3052000.00

Subtotal-B: Subtotal-C:

3052000.00 3052000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3113040.00

10% Profit ( Add 10% on Subtotal-B) :

3424344.00

VAT

6% of Total

IT

4% of Total

228289.60 152193.07 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2725000.00 2725000.00

Subtotal-A:

12.08.07

2554861.32

3804826.67

Page: 2869 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.08.08

2 250 KVA Generator

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

3488000.00

3488000.00

each 250 KVA Generator

1.0000

3488000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3557760.00

10% Profit ( Add 10% on Subtotal-B) :

3913536.00

VAT

6% of Total

260902.40

IT

4% of Total

173934.93 Total:

12.08.09

300 KVA Generator

each 300 KVA Generator

1.0000

each

4142000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4224840.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4647324.00

VAT

6% of Total

IT

4% of Total

309821.60 206547.73 Total:

400 KVA Generator

5163693.33

each 400 KVA Generator

1.0000

each

5668000.00

Subtotal-B: Subtotal-C:

5668000.00 5668000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5781360.00

10% Profit ( Add 10% on Subtotal-B) :

6359496.00

VAT

6% of Total

IT

4% of Total

423966.40 282644.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4142000.00 4142000.00

Subtotal-A:

12.08.10

4348373.33

7066106.67

Page: 2870 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.08.11

2 500 KVA Generator

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

6758000.00

6758000.00

each 500 KVA Generator

1.0000

6758000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6893160.00

10% Profit ( Add 10% on Subtotal-B) :

7582476.00

VAT

6% of Total

505498.40

IT

4% of Total

336998.93 Total:

12.08.12

Installation, testing & commissoning of following electric generator on prepared cc pad with the help of necessary T&P, skilled labour, technician, Engineer & 2 hrs/ 5 day trial run operation by skilled operator with supply of necessary fuel & lubricant as per manufacturers instruction manual and in accordance with relavent IEC/NEMA/VDE/JIS standards so that vibration transfer rate to foundation shall be almost zero etc. all complete as per direction of the E-I-C.

12.08.12.1

30 KVA -80 KVA manual/ auto with soundproof acoustically treated canopy generating set.

each Foreman

10.0000

day

800.00

8000.00

Labor

10.0000

day

390.00

3900.00

Asst. Technician

10.0000

day

570.00

5700.00

B. Sc. Engineer

7.0000

day

1800.00

12600.00 30200.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30804.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33884.40

VAT

6% of Total

IT

4% of Total

2258.96 1505.97 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8424973.33

37649.33

Page: 2871 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.08.12.2

Detailed Analysis Brief Description of Item 2 100 KVA -150 KVA manual/ auto with soundproof acoustically treated canopy generating set.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreman

12.0000

day

800.00

9600.00

Labor

12.0000

day

390.00

4680.00

Asst. Technician

12.0000

day

570.00

6840.00

B. Sc. Engineer

10.0000

day

1800.00

18000.00 39120.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

39902.40

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

43892.64

VAT

6% of Total

2926.18

IT

4% of Total

1950.78 Total:

12.08.12.3

200 KVA -300 KVA manual/ auto with soundproof acoustically treated canopy generating set.

each Foreman

15.0000

day

800.00

12000.00

3.0000

day

390.00

1170.00

Asst. Technician

15.0000

day

570.00

8550.00

B. Sc. Engineer

12.0000

day

1800.00

21600.00

Labor

43320.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

44186.40

10% Profit ( Add 10% on Subtotal-B) :

48605.04

VAT

6% of Total

IT

4% of Total

3240.34 2160.22 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

48769.60

54005.60

Page: 2872 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.08.12.4

Detailed Analysis Brief Description of Item 2 400 KVA -500 KVA manual/ auto with soundproof acoustically treated canopy generating set.

Unit

Sub-Item

3

4

Quantity

Unit

Rate

6

7

22.0000

day

800.00

5

Amount 8

each Foreman Labor

5.0000

day

390.00

1950.00

Asst. Technician

22.0000

day

570.00

12540.00

B. Sc. Engineer

16.0000

day

1800.00

28800.00 60890.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

62107.80

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

68318.58

VAT

6% of Total

4554.57

IT

4% of Total

3036.38 Total:

12.08.13

17600.00

75909.53

Single-Phase Diesel Generator: With ATS panel, sound attenuated acoustiocally treated canopy (Max sond level 75 dba at 7m distance). Supply of 220v&230v, single-phase, 3-wire, 50Hz air/water cooled, floor mounted, indoor type following continuous capacity (Prime power) electric generating set suitable for tropocalized country complete with 4stroke diesel/pertol engine with all standard accessories. 12v/24v DC battery and auto battery charger with ammeter radiator assemly, oil & fuel pump auto speed governor, air cleaner, fuel and oil tank, level & oil pressure gauge, RPM & hour meter.Start and stop switch, exhaust silencer, vibration device viz. auto sgut off with indicators for over load, over & under voltage high temperature, low oil pressure, over speed low fuel level etc. Couple with brush less, self excited alternator having control panel with auto voltage regulator volt meter and ammeter, selector switch and frequency meter. TPMCCB of required rating for over load and instantaneous short circuit release, manual change over switch, indicator for ON-OFF-TRIP etc. maintenance manual and manufactured, assembled and tested in accordance with NEMA/IEC/VDE/JIS standards ( subject to satisfy standard test and approved by LGED) all components manufactured assembled and tested in USA/Japan/ EU or equivalent Approved by Engineer in Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2873 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.08.13.1

Detailed Analysis Brief Description of Item 2 5KVA Generatir with recoil start petrol Engine

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 5KVA Generatir with recoil start petrol Engine

1.0000

each

161110.00

161110.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

164332.20

10% Profit ( Add 10% on Subtotal-B) :

180765.42

VAT

6% of Total

12051.03

IT

4% of Total

8034.02 Total:

12.08.13.2

6KVA Generatir with Barrtry start Diesel Engine with canopy

200850.47

each 6KVA Generatir with Barrtry start Diesel Engine with canopy

1.0000

each

362000.00

362000.00 362000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

369240.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

406164.00

VAT

6% of Total

IT

4% of Total

27077.60 18051.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

161110.00

451293.33

Page: 2874 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.08.13.3

Detailed Analysis Brief Description of Item 2 7.5 KVA Generatir with Barrtry start Diesel Engine with canopy

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 7.5 KVA Generatir with Barrtry start Diesel Engine with canopy

1.0000

each

415000.00

415000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

423300.00

10% Profit ( Add 10% on Subtotal-B) :

465630.00

VAT

6% of Total

IT

4% of Total

31042.00 20694.67 Total:

12.08.13.4

8 KVA Generatir with Barrtry start Diesel Engine with canopy

517366.67

each 8 KVA Generatir with Barrtry start Diesel Engine with canopy

1.0000

each

427333.00

Subtotal-B: Subtotal-C:

427333.00 427333.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

435879.66

10% Profit ( Add 10% on Subtotal-B) :

479467.63

VAT

6% of Total

IT

4% of Total

31964.51 21309.67 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

415000.00

532741.81

Page: 2875 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.08.13.5

2 10 KVA Generatir with Barrtry start Diesel Engine with canopy

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each 10 KVA Generatir with Barrtry start Diesel Engine with canopy

1.0000

each

447192.00

447192.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

456135.84

10% Profit ( Add 10% on Subtotal-B) :

501749.42

VAT

6% of Total

IT

4% of Total

33449.96 22299.97 Total:

12.09

LIFT/ESCALATOR Supply of passenger/ bed lift complete with car, control panels, driving motor, gearless, steel suspention ropes, safety devices, guide rails, push buttons, architraves (as required) with other necessary accessories etc. complete Country of origin: USA/European countries/Australia/Canada/Japan with certificates issued by internationally recognized authorities like TUV/DNV for the products of the manufacturer as per relavent standard. For speed 1.0 meter/second.

12.09.1

Passanger Lift

Note : Rates of all items should be inclusive of all supply and carriage.

447192.00

557499.36

each

Page: 2876 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.09.1.1

2 Capacity 450kg upto 3-step

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

2912240.00

2912240.00

each Lift capacity 450kg

1.0000

2912240.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2970484.80

10% Profit ( Add 10% on Subtotal-B) :

3267533.28

VAT

6% of Total

217835.55

IT

4% of Total

145223.70 Total:

12.09.1.2

Capacity 550kg upto 3-step

each Lift capacity 550kg

1.0000

each

2997500.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3057450.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3363195.00

VAT

6% of Total

IT

4% of Total

224213.00 149475.33 Total:

Capacity 650kg upto 3-step

3736883.33

each Lift capacity 650kg

1.0000

each

3161000.00

Subtotal-B: Subtotal-C:

3161000.00 3161000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3224220.00

10% Profit ( Add 10% on Subtotal-B) :

3546642.00

VAT

6% of Total

IT

4% of Total

236442.80 157628.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2997500.00 2997500.00

Subtotal-A:

12.09.1.3

3630592.53

3940713.33

Page: 2877 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.09.1.4

2 Capacity 750kg upto 3-step

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

3815000.00

3815000.00

each Lift capacity 750kg

1.0000

3815000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3891300.00

10% Profit ( Add 10% on Subtotal-B) :

4280430.00

VAT

6% of Total

285362.00

IT

4% of Total

190241.33 Total:

12.09.1.5

Capacity 1000kg upto 3-step

each Lift capacity 1000kg

1.0000

each

4687000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4780740.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5258814.00

VAT

6% of Total

IT

4% of Total

350587.60 233725.07 Total:

Bed/Trolly/Service Lift

Note : Rates of all items should be inclusive of all supply and carriage.

4687000.00 4687000.00

Subtotal-A:

12.09.2

4756033.33

5843126.67

each

Page: 2878 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.09.2.1

2 Capacity 1250kg upto 3-step

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

5341000.00

5341000.00

each Lift capacity 1250kg(bed type)

1.0000

5341000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5447820.00

10% Profit ( Add 10% on Subtotal-B) :

5992602.00

VAT

6% of Total

399506.80

IT

4% of Total

266337.87 Total:

12.09.2.2

Capacity 1500kg upto 3-step

each Lift capacity 1500kg(bed type)

1.0000

each

6104000.00

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6226080.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

6848688.00

VAT

6% of Total

IT

4% of Total

456579.20 304386.13 Total:

Cargo Lift

Note : Rates of all items should be inclusive of all supply and carriage.

6104000.00 6104000.00

Subtotal-A:

12.09.3

6658446.67

7609653.33

each

Page: 2879 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.09.3.1

2 Capacity 2000kg upto 3-step

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

6867000.00

6867000.00

each Lift capacity 2000kg(cargo type)

1.0000

6867000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7004340.00

10% Profit ( Add 10% on Subtotal-B) :

7704774.00

VAT

6% of Total

513651.60

IT

4% of Total

342434.40 Total:

12.09.3.2

Lift capacity 2500kg(cargo type)

8560860.00

each Lift capacity 2500kg(cargo type)

1.0000

each

8175000.00

8175000.00 8175000.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8338500.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9172350.00

VAT

6% of Total

IT

4% of Total

611490.00 407660.00 Total: 10191500.00

12.09.4

Next per stoppage

each Next 01 stoppage

1.0000

each

110000.00

110000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

112200.00

10% Profit ( Add 10% on Subtotal-B) :

123420.00

VAT

6% of Total

IT

4% of Total

8228.00 5485.33 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

110000.00

137133.33

Page: 2880 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.09.5

Detailed Analysis Brief Description of Item 2 For speed 1.0 (one) meter / Second

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

(i)Rates of lifts having speed more than 1.0 (one) meter/ Second up to 1.5 meters/ Second shall be 10% more than the corresponding rates of lift of speed 1.0 (one) meter / Second. (ii)Rates of lifts having speed more than 1.5 meter/ Second up to 2.00 meters/ Second shall be 15% more than the corresponding rates of lift of speed 1.0 (one) meter / Second. (iii)Rates of lifts having speed more than 2.0 meter/ Second shall be 17% more than the corresponding rates of lift of speed 1.0 (one) meter / Second. 12.09.6

Lift installation : Installation (with effictive connection), testing & commissioning of the above lift including supplying of necessary fixing materials, shaft lighting with wiring, additional works on base foundation (if necessary) for machineries and painting of all parts and initial lubrication shall be carried our as per BS EN-81/EN-81 (Lift Directive 95/16/EC)/DIN/VDE/ANSI/ASME/A17.1/JIS.The supplier/ Installer shall carry out 16 hours per day trial run operation for 30days before handing over the lift to the competent authority. All electrical and civil works mending goods for damages in connection with installation (with effictive connection) of the lift shall be carried out in accordance with the provision of the Bangladesh National Building code, latest Bangladesh Electricity rules. Regulations & PWD specification. All non-current carrying metallic enclosure of electrical materials/equipment viz. electric motor frames, control button car switch, limit switch junction boxes & similar electric fittings shall be properly connected to the earthing system. All the works in this regard shall conform to general standards, Codes and specifications of LGED

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2881 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.09.6.1

2 For 450Kg-550Kg upto Upto 6 stop

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Foreman

60.0000

day

800.00

48000.00

Labor

60.0000

day

390.00

23400.00

Asst Electrician

60.0000

day

680.00

40800.00

B. Sc. Engineer

25.0000

day

1800.00

45000.00 157200.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

160344.00

10% Profit ( Add 10% on Subtotal-B) :

176378.40

VAT

6% of Total

IT

4% of Total

11758.56 7839.04 Total:

12.09.6.2

For 630Kg-1000Kg upto Upto 6 stop

each Foreman

70.0000

day

800.00

56000.00

Labor

70.0000

day

390.00

27300.00

Asst Electrician

70.0000

day

680.00

47600.00

B. Sc. Engineer

25.0000

day

1800.00

45000.00 175900.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

179418.00

10% Profit ( Add 10% on Subtotal-B) :

197359.80

VAT

6% of Total

IT

4% of Total

13157.32 8771.55 Total:

12.10

195976.00

219288.67

AUCASTIC/SOUND SYSTEM :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2882 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10. 34

Detailed Analysis Brief Description of Item 2 Supplying and fixing of 24 Channel Mixing Console with the features of Premium ultra-low noise, high-headroom analog mixer. 16 state-of-theart XENYX Mic Preamps comparable to stand-alone boutique preamps. Neo-classic "British" 3-band Eqs with semi-parametric mid band for warm and musical sound. 2 independent studio-grade 24-bit stereo FX processors with 99 awesome presets including reverb, chorus, flanger, delay, pitch shifter and various multi-effec. 4 Subgroup outputs and additional Mono output with sweepable Low Pass filter for subwoofer application. 4 Aux sends per channel: 2 pre/post fader switchable for monitoring/FX applications, 2 post fader (for internal FX or as external send). Brand Name: BEHRINGER, Model No.: SX2442FX, Country of Origin: GERMANY or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

24 channel mixing console

1.0000

set

200000.00

200000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 200162.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

204165.24

10% Profit ( Add 10% on Subtotal-B) :

224581.76

VAT

6% of Total

14972.12

IT

4% of Total

9981.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

249535.29

Page: 2883 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.01

Detailed Analysis Brief Description of Item 2 Vocal Microphone: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Unidirectional vocal microphone suitable for super professional vocalist with On-Off switch, frequency response: 40Hz to 16 KHz, Connector XLR.Nominal impedance 350/12600 ohms Complete with required accessories and in conformity to specified codes and specification of international standard & CE/UL/CSA certificate. Model and sample to be approved by the E-I-C.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Unidirectional vocal microphone

1.0000

each

10500.00

10500.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 10513.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10723.87

10% Profit ( Add 10% on Subtotal-B) :

11796.26

VAT

6% of Total

IT

4% of Total

786.42 524.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13106.95

Page: 2884 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.02

Detailed Analysis Brief Description of Item 2 Condenser Microphone: Supply, installation (with effictive connection), testing of condenser microphone: Precise electrets condenser measurement microphone Ultra-liner frequency response Well-balanced, true omni-directional pattern; Optimally suited for room connection applications Phantom powered, +15 V to + 48 V ragged construction and sleek, modern design Microphone stand adapter perfect for use with the ULTRACURVE DSP 8000/ ULTRA-CURVE PRO dsp 8024 or any other real-time analyzer. Type electros condenser,omni-directional. Impedance 6001000 Ohms. Sensitivity 60 dB. Frequency response 15 Hz to 20 KHz. Connector XLR. Phantom power +15V to +48 V etc. Suitable for use in tropical country like Bangladesh. Complete with required accessories and in conformity to specified codes & specification of international standards & CE/UL/CSA certified. Model & Sample to be approved by the competent authority.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Condenser microphone

1.0000

each

24500.00

24500.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 24513.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25003.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

27504.26

VAT

6% of Total

1833.62

IT

4% of Total

1222.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

30560.29

Page: 2885 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.03

Detailed Analysis Brief Description of Item 2 Wireless Microphone: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of high quality wireless Microphone system with receiver set as per following specification :professional electrets microphone with ON status LED indicator , matt black finish, immune to radio frequency interference from mobile telephones, PDAs & other wireless devices operated within a conference room. Complies with international standard IEC 914. Power requirement: AC mains, 230V, Receiving Frequency: 690–865 MHz, Channel Selectable: 16 channels, Frequency Response: 50–18,000 Hz, ±3dB, Sensitivity: 2μV(S/N>12dB 25kHz deviation). Maximum Output Level: (MIC): -14dBV/100Ω, (LINE): 4dBV/5kΩ, Operating Temperature: - 10ºc to + 50ºc, Transducer Principle: Dynamic, Directionality: Unidirectional, Frequency Range: 690–865 MHz, (UHF) , Standard accessory: AC / DC adapter, Suitable for use in tropical country like Bangladesh, Complete with required accessories and in conformity to specified codes & specification of international standards & CE/UL/CSA certified. Model & Sample to be approved by the competent authority.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Wireless microphone

1.0000

each

45000.00

45000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 45013.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

45913.87

10% Profit ( Add 10% on Subtotal-B) :

50505.26

VAT

6% of Total

3367.02

IT

4% of Total

2244.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

56116.95

Page: 2886 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.04

Detailed Analysis Brief Description of Item 2 Mixing Console: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 16 Channel Mixing Console with the features of Total input channel 16, mono/sterio channel 8/4, mix buses 4/2, XENYX mic preamps 12 (XENYX PRO), channel EQ 4-band, aux sebds per channel 6, effect returns 2 sterio, metering 14-LED Brand Name: BEHRINGER, Model No.: XL1600, Country of Origin: GERMANY.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Mixing console

1.0000

set

145000.00

145000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 145013.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

147913.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

162705.26

VAT

6% of Total

10847.02

IT

4% of Total

7231.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

180783.62

Page: 2887 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.05

Detailed Analysis Brief Description of Item 2 "Amplifier (500W-750W) : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of High power dual Channel professional audio power amplifier as per following specification:Output Power: 8ohms/sterio-(500w+500W)(750W+750W)power band with (half power): 10Hz-40Khz ( THD+N=0.5%)THD+N 20Hz-20KHz half power < 0.1%Frequency Response P0=1W RL=8 ohms, 0dB, +5dB-1dB, f=20Hz-50KHzS/N ratio (DIN Audio): 104dBSensitivity 8 ohms at max +8dBVoltage gain att. Max: 32.1 dBImput impedance: 30K ohms (Balance), 15K ohms (sub balance)Idle power consumption: 35WMax power consumption 4ohms, 4000WComplete with required accessories and in comformity to specified codes and specification of international standard & CE/UL/CSA certificate. Model and sample to be approved by the E-I-C"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Amplifire 500-750w

1.0000

set

88000.00

88000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 88013.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

89773.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

98751.26

VAT

6% of Total

6583.42

IT

4% of Total

4388.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

109723.62

Page: 2888 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.06

Detailed Analysis Brief Description of Item 2 Amplifier (175W-300W): Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of high power dual Channel professional audio power amplifier as per following specification: Output Power: 8ohms/sterio-(500w+500W)-(750W+750W) power band with (half power): 10Hz-40Khz ( THD+N=0.5%) THD+N 20Hz-20KHz half power < 0.1% Frequency Response P0=1W RL=8 ohms, 0dB, +5dB-1dB, f=20Hz50KHz S/N ratio (DIN Audio): 104dB Sensitivity 8 ohms at max +8dB Voltage gain att. Max: 32.1 dB Input impedance: 30K ohms (Balance), 15K ohms (sub balance) Idle power consumption: 35W Max power consumption 4ohms, 4000W Complete with required accessories and in conformity to specified codes and specification of international standard & CE/UL/CSA certificate. Model and sample to be approved by the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Amplifire 175-300w

1.0000

set

68000.00

68000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 68013.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

69373.87

10% Profit ( Add 10% on Subtotal-B) :

76311.26

VAT

6% of Total

5087.42

IT

4% of Total

3391.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

84790.29

Page: 2889 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.07

Detailed Analysis Brief Description of Item 2 Ceiling Speaker (6W-12W): Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of ceiling speaker idea for airports, lounges, convention centers, corporate boardrooms, hotels/hospitals, museums, offices, school, theaters and theme parks, superior sound quality, wide dispersion and smooth off-axis coverage with following specification. Line Voltage: 70V/100V Sensitivity: 90dB Freq. response: 150Hz-15KHz Hole Cutting size: 150mm Baffle size: 185 installation (with effictive connection): Ceiling Enclosure Material: Plastic Line Load resistance: 666 ohm Dispersion angle: 100 deg Complete with required accessories and in conformity to specified codes and specification of international standard model and sample to be approved by the E-I-C

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Celling speaker 6-12w

1.0000

set

11500.00

11500.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 11513.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11743.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12918.26

VAT

6% of Total

861.22

IT

4% of Total

574.14 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14353.62

Page: 2890 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.08

Detailed Analysis Brief Description of Item 2 Auditorium Speaker: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of auditorium speaker with the following features:

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Impedance : 8 ohms Components : 2- way, 1x8"-12"+Ti35 RMS Power : 150 W Max Power :300 W Frequency response : 45Hz-20Hz, Sensitivity : (1W/1M) 99 dB etc. Suitable for use in tropical country like Banladesh, Complete with required accessories and in conformity to specified codes & specification of international standards & CE/UL/CSA certified. Model & sample to be approved by the competent authority. i) Capacity : RMS 150W. Auditorium speaker

1.0000

set

40000.00

40000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 40013.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40813.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

44895.26

VAT

6% of Total

2993.02

IT

4% of Total

1995.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

49883.62

Page: 2891 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.09

Detailed Analysis Brief Description of Item 2 Stage Monitor Speaker : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Stage Monitor Speaker with the features of 90°x60° Elliptical Waveguides (Full Range Models), High Output, Low Distortion Transducers, Full Length Powder Coated Steel Grilles, High Frequency Driver Protection, High Voltage Crossovers, Trapezoidal Enclosures, Alloy Pole Mount Receptacles, High Frequency Boost Switch (+3dB), High Pass Output (Subwoofers), Signal And HF Protect LED Indicators. 15" LF, 2 Way FOH, 8 ohms, 45-20kHz, (+/3dB), 98dB (1w@1m), Power Rating: 300W Continuous, 600W Music, 1200W Peak. Brand Name:WHARFEDALE PRO , Model No.:EVPX15M, Country of Origin:UK

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Stage monitor speaker

1.0000

set

48000.00

48000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 48013.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

48973.87

10% Profit ( Add 10% on Subtotal-B) :

53871.26

VAT

6% of Total

IT

4% of Total

3591.42 2394.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

59856.95

Page: 2892 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.10

Detailed Analysis Brief Description of Item 2 Sound Equalizer: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Equalizer with the features of Constant Q filters, Switchable 6dB / 12dB fader range, Switchable bypass with LED indicator, Four LED output level meter plus input clip indicator, Input gain adjustable between -∞ dB and +6dB, Built in soft limit helps prevent overloads that damage speakers, XLR/ 1/4” TRS balanced / unbalanced inputs/outputs, Ground lift switch quickly solves earth loop and external noise issues. Balanced 20k ohm, unbalanced 10k ohm, >+21dBu balanced or unbalanced, >40dB, typically > 5dB at 1kHz, Impedance-balanced / unbalanced, RF fi ltered, Balanced 100 ohm, Unbalanced 50 ohm, >+21dBu balanced/ unbalanced into 2k ohm or greater, 20Hz to 20kHz, +0.5/-1dB, <10Hz to>50kHz, +0.5/-3dB, Signal-to-Noise: 90dB, THD + Noise: <0.004% Brand Name:WHARFEDALE PRO, Model No.:Q230, Country of Origin:UK

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Sound equalizer

1.0000

set

60000.00

60000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 60013.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

61213.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

67335.26

VAT

6% of Total

4489.02

IT

4% of Total

2992.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

74816.95

Page: 2893 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.11

Detailed Analysis Brief Description of Item 2 Microphone Stand (Floor Type) : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of floor Mic stand complete with Arms and Mic holder. FOREIGN MADE Model & Sample to be approved by the competent authority.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Microphone stand (floor type)

1.0000

each

6000.00

6000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 6013.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6133.87

10% Profit ( Add 10% on Subtotal-B) :

6747.26

VAT

6% of Total

449.82

IT

4% of Total

299.88 Total:

12.10.12

Microphone Stand (Table Type): Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of floor Mic stand complete with Arms and Mic holder. FOREIGN MADE Model & Sample to be approved by the competent authority.

set

Microphone stand (table type)

1.0000

each

4500.00

4500.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 4513.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4603.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5064.26

VAT

6% of Total

337.62

IT

4% of Total

225.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7496.95

5626.95

Page: 2894 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.13

Detailed Analysis Brief Description of Item 2 Sound Junction Box : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of sound junction box for stage floor, one box containing of 5 socket outlet for the system with inter connection cables.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Sound junction box

1.0000

each

4800.00

4800.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 4813.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4909.87

10% Profit ( Add 10% on Subtotal-B) :

5400.86

VAT

6% of Total

IT

4% of Total

360.06 240.04 Total:

12.10.14

Microphone cables : Supplying and fixing of best quality foreign made cables suitable for connection of Microphone & speaker Microphone cables (Twin core shilded)

m

Microphone cable

1.0000

m

85.00

85.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 98.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

100.57

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

110.63

VAT

6% of Total

IT

4% of Total

7.38 4.92 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6000.95

122.92

Page: 2895 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.15

Detailed Analysis Brief Description of Item 2 Line Array: Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Line Array necessary accessories with the features of Safe and Secure, Holds up to 12 WLA28 Speakers, Holds up to 8 WLA-28 Speakers with WLA-15B subwoofer, Multiple Hang Points, Tubular Steel Construction, Heavy Duty Welding, For use with the Wharfedale WLA-28 / WLA15-B only, Material-Steel. Brand Name: WHARFEDALE PRO, Model No.: WLA-28 Fly Frame, Country of Origin: UK

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Line array for speaker

1.0000

each

28000.00

28000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 28013.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28573.87

10% Profit ( Add 10% on Subtotal-B) :

31431.26

VAT

6% of Total

IT

4% of Total

2095.42 1396.94 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

34923.62

Page: 2896 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.16

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Instrument Microphones with the features of High tech zinc fi nish, 5 application specifi c models, Unidirectional polar responses, Neodymium magnets, Dent-resistant steel grilles, Rugged cast Zinc alloy body, Gold-plated XLR connector. Small diaphragm overhead / instrument condenser mic. suitable for cymbals, acoustic. guitars, pianos and other stringed instruments. Frequency response 30-20,000Hz, <1000 ohms, 46 dBV/Pa, >18dB, Brand Name:WHARFEDALE PRO, Model No.: KM3, Country of Origin:UK

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Instrumental microphone

1.0000

each

20000.00

20000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 20013.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20413.87

10% Profit ( Add 10% on Subtotal-B) :

22455.26

VAT

6% of Total

IT

4% of Total

1497.02 998.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

24950.29

Page: 2897 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.17

Detailed Analysis Brief Description of Item 2 "Rack/Cabinet : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of standard cabinet suitable for PA equipments, dissabled for easy shipping. Front glass door with lock.Made of 18 SWG MS sheet & MS angle of proper size and painted with plastic paint over anti corrosive rust proof under coat with following specification;Rota table wheels and fixed stands.Steel : 20""x20""x60""No. of rack : 5Fixed foot : 2Rotate wheel : 2"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Rack for pa system

1.0000

each

9500.00

9500.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 9513.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9703.87 10674.26 711.62 474.41

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11860.29

Page: 2898 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.18

Detailed Analysis Brief Description of Item 2 Subwoofer : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Subwoofer Speaker (Line Array System) with the features of System Type-15” Subwoofer, Frequency Response-35Hz - 900Hz, Power (RMS / Programme / Peak)700W / 1400W / 2800W, Nominal Impedance-8Ω, Sensitivity (1m/1w)99dB, Max SPL-133dB, Inputs-2 x Speakon. Brand Name: WHARFEDALE PRO, Model No.: WLA-15B, Country of Origin: UK

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each set

Subwoofer of sound system

1.0000 each set

Plumber/ Electric Mistry/ Painter

0.0200

day

105000.00

105000.00

680.00

13.60 105013.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

107113.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

117825.26

VAT

6% of Total

7855.02

IT

4% of Total

5236.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

130916.95

Page: 2899 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.19

Detailed Analysis Brief Description of Item 2 Supply and fixing of Main Auditorium Speaker (Line Array System) with the features of System Type 2 x 8”/2-Way, Frequency Response-65 Hz20 kHz, HF Waveguide Exit-1.4”/35.5mm, HF Diaphragm MaterialTitanium, Nominal Coverage (H x V)- 100° x 10°, Power (RMS / Programme / Peak)- 400W / 800W / 1600W. Brand Name:WHARFEDALE PRO, Model No.: WLA-28, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Main Auditorium Speaker

1.0000

set

130000.00

130000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 130162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132765.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

146041.76

VAT

6% of Total

9736.12

IT

4% of Total

6490.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

162268.63

Page: 2900 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.20

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Speaker with the features of 15" LF, 2 Way FOH, 8 ohms, 45-20kHz (+/-3dB), 98dB (1w@1m), Power Rating: 300W Continuous, 600W Music, 1200W Peak. Brand Name:WHARFEDALE PRO, Model No.: EVP-X15 Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Speaker

1.0000

set

65000.00

65000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 65162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

66465.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

73111.76

VAT

6% of Total

4874.12

IT

4% of Total

3249.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

81235.29

Page: 2901 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.21

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Speaker (Passive) with the features of 2-Way, 15" High Power Woofer, 50-20kHz Frequency Response (+/-3dB), 8 ohms Impedance, Bi-Amp, 98dB (1w@1m), Power Rating: 500W Continuous, 1000W Music, 2000 Peak. Brand Name: WHARFEDALE PRO, Model No.: DELTA-15, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Speaker(passive)

1.0000

set

85000.00

85000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 85162.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

86865.24

10% Profit ( Add 10% on Subtotal-B) :

95551.76

VAT

6% of Total

IT

4% of Total

6370.12 4246.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

106168.63

Page: 2902 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.22

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Monitor Speaker (Passive) with the features of 2Way, 15" High Power Woofer, 55-20kHz Frequency Response (+/-3dB), 8 ohms Impedance, Bi-Amp, 98dB (1w@1m), Power Rating: 500W Continuous, 1000W Music, 2000 Peak. Brand Name:WHARFEDALE PRO, Model No.: DELTA-15M, Country of Origin:UK (Made in CHINA) or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

165.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

181.76

VAT

6% of Total

IT

4% of Total

12.12 8.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

201.96

Page: 2903 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.23

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Subwoofer Speaker with the features of 15" subwoofer, 4 ohms, 45-250 kHz (+/-3dB), 99dB (1w@1m), Power Rating: 400W Continuous, 800W Music, 1600W Peak. Brand Name:WHARFEDALE PRO, Model No.: EVPX15B, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Subwoofer of sound system

1.0000 each set

105000.00

105000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 105162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

107265.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

117991.76

VAT

6% of Total

7866.12

IT

4% of Total

5244.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

131101.96

Page: 2904 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.24

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Subwoofer Speaker with the features of 18" subwoofer, 4 ohms, 40-200 kHz (+/-3dB), 100dB (1w@1m), Power Rating: 600W Continuous, 1200W Music, 2400W Peak. Brand Name:WHARFEDALE PRO, Model No.: EVPX18B, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Subwoofer of sound system

1.0000 each set

105000.00

105000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 105162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

107265.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

117991.76

VAT

6% of Total

7866.12

IT

4% of Total

5244.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

131101.96

Page: 2905 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.25

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Speaker (Passive) with the features of 15" LF x 2 Quasi 3 Way, 4 ohms, 40-20 kHz (+/-3dB), 100dB (1w@1m), Power Rating: 500W Continuous, 1000W Music, 2000W Peak. Brand Name: WHARFEDALE PRO, Model No.: EVP-X215, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Speaker(passive)

1.0000

set

85000.00

85000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 85162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

86865.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

95551.76

VAT

6% of Total

6370.12

IT

4% of Total

4246.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

106168.63

Page: 2906 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.26

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Column Speaker with the features of Rated Power: 10W, Impedance: 1kΩ/2kΩ, Frequency Response: 220Hz ~ 15kHz, SPL (1W/m): 87dB, Enclosure Material: Aluminum. Brand Name: INTER-M, Model No.: CU-910(V), Country of Origin: KOREA or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

column speaker1

1.0000

set

12000.00

12000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 12162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12405.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13645.76

VAT

6% of Total

909.72

IT

4% of Total

606.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15161.96

Page: 2907 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.27

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Column Speaker with the features of Rated Power: 20W, Impedance: 500Ω/1kΩ, Frequency Response: 220Hz ~ 15kHz, SPL (1W/m): 90dB, Enclosure Material: Aluminum. Brand Name: INTER-M, Model No.: CU-920(V), Country of Origin: KOREA or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

column speaker2

1.0000

set

13500.00

13500.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 13662.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13935.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15328.76

VAT

6% of Total

1021.92

IT

4% of Total

681.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17031.96

Page: 2908 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.28

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Column Speaker with the features of Rated Power: 30W, Impedance: 330Ω/660Ω, Frequency Response: 220Hz ~ 15kHz, SPL (1W/m): 91dB. Brand Name: INTER-M, Model No.: CU-930(V), Country of Origin: KOREA or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

column speaker3

1.0000

set

12000.00

12000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 12162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12405.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13645.76

VAT

6% of Total

909.72

IT

4% of Total

606.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15161.96

Page: 2909 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.29

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Ceiling Speaker with the features of Rated Power : 6W, Impedance COM : 1.7kΩ, 4kΩ, 8kΩ, Frequency Response: 150Hz-15kHz, SPL (1W/1M) : 92dB. Brand Name: INTER-M, Model No.: CS-610, Country of Origin: KOREA or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

ceiling speaker

1.0000

set

9000.00

9000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 9162.00

Subtotal-A: Subtotal-B: Subtotal-C:

9345.24

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10279.76

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

685.32

IT

4% of Total

456.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11421.96

Page: 2910 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.30

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Powered Mixer Amplifier with the features of 2x 250W RMS power output (4Ω), 16-bit 48kHz USB Interface, 6 phantom powered XLR mic inputs, ¼” jack and RCA line level inputs, Peak indicator for each channel, 3 band EQ on every mono channel, 2 band EQ on the stereo channel, 1 Monitor send, Pan/Balance controls, Built in digital FX. Brand Name: WHARFEDALE PRO, Model No.: PMX-710, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

power mixer amplifier

1.0000

set

110000.00

110000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 110162.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

112365.24

10% Profit ( Add 10% on Subtotal-B) :

123601.76

VAT

6% of Total

IT

4% of Total

8240.12 5493.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

137335.29

Page: 2911 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.31

Detailed Analysis Brief Description of Item 2 Supplying of Digital loudspeaker management with the features of Digital Sound Processing, 6-band parametric EQ with low/high shelf Limiter, Crossover / Filter, Independent processing for each output channel, Ultra-fast workflow, 30 Save slots, Factory presets with popular Wharfedale Pro models, USB connection for editing settings, RS485 connection for remote control up to 1500m Brand Name: WHARFEDALE PRO, Model No.: VERSADRIVE SC-26, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Digital loudspeaker management

1.0000

set

115000.00

115000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 115162.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

117465.24

10% Profit ( Add 10% on Subtotal-B) :

129211.76

VAT

6% of Total

IT

4% of Total

8614.12 5742.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

143568.63

Page: 2912 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.32

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Crossovers with the features of Connectors: 1/4" TRS, Input Impedance: Balanced 20KW, unbalanced 10KW, Maxium Input Level: +20dBu, Output Impedance: Balanced/Unbalanced 100 ohms, Maxium Output Level: +20dBu, Subwoofer Output: 1/4" TRS. Brand Name: WHARFEDALE PRO, Model No.: XO-206, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

crossover

1.0000

set

68000.00

68000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 68162.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

69525.24

10% Profit ( Add 10% on Subtotal-B) :

76477.76

VAT

6% of Total

IT

4% of Total

5098.52 3399.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

84975.29

Page: 2913 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.33

Detailed Analysis Brief Description of Item 2 Supply and Fixing of Audio Multi Effect Processor with features of 71 breathtaking new algorithms true RSM (Real Sound Modeling) stereo and 3D effects. Wave-adaptive virtual Room reverb algorithms for natural reverb and delay. Awesome modulation, dynamic, psychoacoustic and EQ algorithms. Authentic amp simulation, distortion and special effects. Model No.: FX2000, Brand Name: BEHRINGER, Country of Origin: GERMANY or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Audio multi effect processor

1.0000

set

62000.00

62000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 62162.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

63405.24

10% Profit ( Add 10% on Subtotal-B) :

69745.76

VAT

6% of Total

IT

4% of Total

4649.72 3099.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

77495.29

Page: 2914 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.35

Detailed Analysis Brief Description of Item 2 Supplying, Fitting and Fixing of Wireless Microphones (Hand Held Type) With the Features of Receiver: RF frequency range 600MHz-960MHz, Ocillation Type: PLL, Channel 16, Frequency Response: 50Hz-18KHz. Transmitter: Microphone with UHF PLL Transmitter, 16 seclectable channels, Frequency band: 782MHz-806MHz. Brand Name: FBT, Model No.: FBTAC 8001D & FBTAC Mh 750, Country of Origin: ITALY or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Wireless Microphones (Hand Held Type)

1.0000

set

43000.00

43000.00

Asst Electrician

0.2000

day

680.00

136.00 43136.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

43998.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

48398.59

VAT

6% of Total

IT

4% of Total

3226.57 2151.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

53776.21

Page: 2915 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.36

Detailed Analysis Brief Description of Item 2 Supplying and Fixing of Wireless microphone (Clip Type) with the features of Receiver: RF frequency range 600MHz-960MHz, Ocillation Type: PLL, Channel 16, Frequency Response: 50Hz-18KHz. Body Pack Transmitter: 16 seclectable channels, Frequency band: 782MHz806MHz. Clip Microphone: Lavaliar unidirectional cardiod condenser microphone, 4p mini XLR connector, frequency response 100-15,000Hz. Brand Name: FBT, Model No.: FBTAC 8001D, FBTAC PT 850B & FBTAC CM 501, Country of Origin: ITALY or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Wireless Microphones (clip Type)

1.0000

set

42500.00

42500.00

Asst Electrician

0.2000

day

680.00

136.00 42636.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

43488.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

47837.59

VAT

6% of Total

3189.17

IT

4% of Total

2126.12 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

53152.88

Page: 2916 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.37

Detailed Analysis Brief Description of Item 2 Supply and Fixing of Control Unit for Conferrence System : Control Unit with Digital Display. Fault protected • Configuration and system monitoring via 2x16 backlit LCD and 5-button menu system. System status "Alert" LED • Front panel monitor loudspeaker and level control. Tri-colour LED for output level indication • One Auxiliary Input XLR balanced and configurable for mic/line level. With level control and tricolour LED level indicator. Optional chairman’s Priority feature. This option and the gain is set via DIL switches on rear panel – no need to open unit to set jumpers • Loudspeaker Input XLR – balanced, line level. Int/Ext switching via rear panel DIL switch. A compressor is incorporated in the input stage, primarily to protect the system from power overload under extreme continuous signal conditions – e.g. feedback • One Auxiliary Output XLR – balanced, line level • PA Output XLR – balanced, line level. With associated level control and tri-colour LED indicator. Unit can accept frequency shifter module (enabled via the menu system) Brand Name: AUDITEL, Model No.: DSC50, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Control Unit for Conference system

1.0000

set

100000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 100162.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102165.24

10% Profit ( Add 10% on Subtotal-B) :

112381.76

VAT

6% of Total

IT

4% of Total

7492.12 4994.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

100000.00

124868.63

Page: 2917 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.38

Detailed Analysis Brief Description of Item 2 Supply and Fixing of Table Top Chairnam Unit: Table Top Chairnam Unit with microphone & built-in loudspeaker.• 3-way (YAN) voting with LED indicators.• Request to speak switch. Status is shown via a bicolour LED. • Voice-Held (Self-Cancelling) option. • Compact unit design using surface mount technology (SMT). • Luminant flashes to advise speaker to "wind up". • Chairman units have additional priority/override facility. • Unit IDs stored in non-volatile memory. • Gain adjusted on an individual basis using the voting buttons to increase/decrease gain. Gain levels are stored in non-volatile memory. Gain can also be "tweaked" on the fly during meetings remotely from the computer. • Flush mounted, remote fixing and seat arm versions of the delegate and chairman units are also available. MICROPHONEType: Uni-Directional, CardioidSensitivity: -63dB ±3dBRear Attenuation: -20dB @ 1kHzConstruction: Semi Flexible CompositeStemHigh Visibility Ring Luminant LOUDSPEAKERFrequency Response: 150Hz-17kHz (-10dB)Power Handling: 3000mWSPL: 82dB/W/m @ 1kHz Brand Name: AUDITEL, Model No.: CDU103P, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Table top chairman unit for Conference system1

1.0000

set

28000.00

28000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 28162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

28725.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

31597.76

VAT

6% of Total

2106.52

IT

4% of Total

1404.35 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

35108.63

Page: 2918 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.10.39

Detailed Analysis Brief Description of Item 2 Supply and Fixing Table Top Delegate Unit: Table Top Delegate Unit with microphone & built-in loudspeaker. Microphone, with ring luminant, and loudspeaker • 3-way (YAN) voting with LED indicators.• Request to speak switch. Status is shown via a bi-colour LED. • Voice-Held (SelfCancelling) option. • Compact unit design using surface mount technology (SMT). • Luminant flashes to advise speaker to "wind up". • Chairman units have additional priority/override facility. • Unit IDs stored in non-volatile memory. • Gain adjusted on an individual basis using the voting buttons to increase/decrease gain. Gain levels are stored in non-volatile memory. Gain can also be "tweaked" on the fly during meetings remotely from the computer. • Flush mounted, remote fixing and seat arm versions of the delegate and chairman units are also available. MICROPHONEType: Uni-Directional, CardioidSensitivity: -63dB ±3dBRear Attenuation: -20dB @ 1kHzConstruction: Semi Flexible CompositeStemHigh Visibility Ring Luminant LOUDSPEAKERFrequency Response: 150Hz-17kHz (-10dB)Power Handling: 3000mWSPL: 82dB/W/m @ 1kHz Brand Name: AUDITEL, Model No.: DDU103P, Country of Origin: UK or Equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Table top delegate unit for Conference system2

1.0000

set

28500.00

28500.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 28662.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

29235.24

10% Profit ( Add 10% on Subtotal-B) :

32158.76

VAT

6% of Total

IT

4% of Total

2143.92 1429.28 Total:

12.11

35731.96

STAGE/AUDITORIUM LIGHTING :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2919 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.01

Detailed Analysis Brief Description of Item 2 Projector : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Multi media Projector. Brand Name: HITACHI/ SONY/JVC etc or Equavalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Projector

1.0000

each

100000.00

100000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 100013.60

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102013.87

10% Profit ( Add 10% on Subtotal-B) :

112215.26

VAT

6% of Total

IT

4% of Total

7481.02 4987.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

124683.62

Page: 2920 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.02

Detailed Analysis Brief Description of Item 2 "Profile Spot Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of of Profile Spot Light 1000w with POWER SUPPLY: LAMP: 230V, 50 / 60Hz. CP70 1000W. Socket Gx 9. 5. Life 400 hours (manufacturers rating). OPTICS: High efficiency aluminium reflector. Plano convex zoom lenses. Typical throw distance form 2.5 to 10m. ZOOM:Beam angle variable between 20° and 40°. BEAM SHAPERS: Steel shutter blades. IRIS: Optional diaphragm diam. 55m to order. COLOR FRAME: With spring clip for easy filter change. COOLING:Construction assisted convection cooling. HOUSING: Metal parts have epoxy powder paint finish. Easy access to lamp and main components. CONTROL: The projector may be mounted titled at +50° / -45° from the horizontal axis. Maximum ambient temperature 35°C.Brand Name: FAL, Model No.: PF1230, Country of Origin: ITALY"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Profile spot light 1000w

1.0000

each

62000.00

62000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 62023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

63263.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

69589.81

VAT

6% of Total

IT

4% of Total

4639.32 3092.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

77322.01

Page: 2921 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.03

Detailed Analysis Brief Description of Item 2 "FR & PC Spot Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of FR & PC Spot Light 1000w with the features of POWER SUPPLY: 230V, 50/60Hz, POWER:CONSUMPTION: 1000W, LAMP: CP70 (Philips). Colour temperature 25000K, Socket GX9.5. Life 400 hours (manufactures rating), COOLING: Natural convection, HOUSING: Extruded aluminium profile and steel plate, Metal parts have epoxy powder paint finish, Easy access to lamp and main components, CONTROL: The projector may be mounted titled at +90°/ -45°from the horizontal axis. Maximum ambient temperature 40OC.Brand Name: FAL, Model No.: PF5045 &PF5047, Country of Origin: ITALY"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Fr & pc spot light 1000w

1.0000

each

42000.00

42000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 42023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

42863.46

10% Profit ( Add 10% on Subtotal-B) :

47149.81

VAT

6% of Total

IT

4% of Total

3143.32 2095.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

52388.67

Page: 2922 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.04

Detailed Analysis Brief Description of Item 2 "FR & PC Spot Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of FR & PC Spot Light 500w with the features of POWER SUPPLY: 230V, 50/60Hz, POWER:CONSUMPTION: 500W, LAMP: T/25 (Philips). Colour temperature 3000K, Socket GY9.5. Life 600 hours (manufactures rating), COOLING: Natural convection, HOUSING: Extruded aluminium profile and steel plate. Metal parts have epoxy powder paint finish, Easy access to lamp and main components, CONTROL: The projector may be mounted titled at +90°/ -45°from the horizontal axis. Maximum ambient temperature 40OC.Brand Name: FAL, Model No.: PF5041 &PF5043, Country of Origin: ITALY"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Fr & pc spot light 500w

1.0000

each

38000.00

38000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 38023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

38783.46

10% Profit ( Add 10% on Subtotal-B) :

42661.81

VAT

6% of Total

IT

4% of Total

2844.12 1896.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

47402.01

Page: 2923 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.05

Detailed Analysis Brief Description of Item 2 Flood Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Flood light with 500W tungsten halogen lamp, symmetric reflector of high purity aluminium halogen electric cable with colour filter frame etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Flood light with 500w

1.0000

each

14000.00

14000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 14023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14303.46

10% Profit ( Add 10% on Subtotal-B) :

15733.81

VAT

6% of Total

IT

4% of Total

1048.92 699.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17482.01

Page: 2924 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.06

Detailed Analysis Brief Description of Item 2 "Cyclorama Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Cyclorama light with 1000W tungsten halogen lamp, symmetric reflector of high purity aluminium halogen electric cable with colour filter frame etc. LOCAL MADE"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Flood light with 1000w

1.0000

each

19000.00

19000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 19023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19403.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21343.81

VAT

6% of Total

1422.92

IT

4% of Total

948.61 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23715.34

Page: 2925 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.07

Detailed Analysis Brief Description of Item 2 "Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of of Par can 64 with the features of long version, suitable for Par 64 lamp, made entirely in aluminium. Supplied with silicon cable, GX 16 ceramic lampholder, Lamp PAR 64 1000W.Brand Name: ARENA LUCI, Model No.:TH2009, Country of Origin: ITALY"

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Par can 64

1.0000

set

14000.00

14000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 14023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14303.46

10% Profit ( Add 10% on Subtotal-B) :

15733.81

VAT

6% of Total

IT

4% of Total

1048.92 699.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

17482.01

Page: 2926 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.08

Detailed Analysis Brief Description of Item 2 Scanner Light : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Scanner light with as per following specification: Bright and compact LED scanner packed with features to enhance any show, Increase design flexibility and effects with 7 gobos plus 7 separate, saturated colors, Minimize programming time using built-in movement macros and move-in-black features, Increase effects with electronic dimming and strobe features, Continuous shows with individual reset of pan/tilt, color and gobos, Achieve flicker-free video operation with high-frequency LED dimming, Increase mounting options with the included double-bracket yoke that doubles as a floor stand, Sound-activated programs dance to the beat of the music, DMX Channels: 5 or 8, DMX Connectors: 3-pin, Pan and Tilt: 180°/90°, Colors: 7 + white, split colors, continuous scroll at variable speeds, Gobos: 7 + open, continuous scroll at variable speeds, Light Source: 1 (white) 15W (1A) LED 50,000hrs, Strobe Rate: 0 - 20Hz, Beam Angle: 15°, Illuminance: 1,577 lux @ 2m, Power Linking: 11 units @ 120V; 21 units @ 230V, Input Voltage: Auto-ranging 100 - 240VAC 50/60Hz, Power and Current: 80W, 0.7A @ 120V 60Hz, Power and Current: 86W, 0.4A @ 230V 50HzModel No.:Intimidator™ Scan LED 200, Brand Name: CHAUVET, Country of Origin: USA.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Scanner light

1.0000

each

72000.00

72000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 72023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

73463.46

10% Profit ( Add 10% on Subtotal-B) :

80809.81

VAT

6% of Total

IT

4% of Total

5387.32 3591.55 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

89788.67

Page: 2927 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.09

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Zoom LED With the features of DMX Channel: 2, Light Source: 1 LED (White) 15W (4 A), 50,000 hourse, Zoom Angle: 180 to 260 , gobo Size: 28.6mm outside, 26mm image, 1mm max thickness, lluminance: 1,027 lux @ 2m, Input voltage: 100 to 240 VAC, 50/60 Hz (auto-ranging).Model No.: Gobo zoom LED 2.0, Brand Name: CHAUVET, Country of Origin: USA.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Zoom led

1.0000

each

71000.00

71000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 71023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

72443.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

79687.81

VAT

6% of Total

5312.52

IT

4% of Total

3541.68 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

88542.01

Page: 2928 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.10

Detailed Analysis Brief Description of Item 2 12 Channel Dimmer Rack : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 12 Channel Dimmer Rack with the features of Simple to set up and use for Theatres or Television studios. It is fitted with an isolated DMX input and a 0-10 volts analogue control input. The wide mains supply voltage and frequency range allows to work in any country. With a wide range of features at an affordable price, the Rackpack is ideal for touring or permanent installation (with effictive connection).Easy to use menu system, Large 4 line LCD display, Isolated DMX input, 1/10th standard RS-485 load, Programmable DMX start address, 0 to 10 volt analogue control, High immunity to mains interference, Load protection by MCBs.Brand Name: THEATRE LIGHT NZ, Model No.: RACK PACK II (TLRP1220), Country of Origin: NEWZELAND

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

12 channel dimmer rack

1.0000

each

200000.00

200000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 200023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

204023.46

10% Profit ( Add 10% on Subtotal-B) :

224425.81

VAT

6% of Total

14961.72

IT

4% of Total

9974.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

249362.01

Page: 2929 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.11

Detailed Analysis Brief Description of Item 2 Light Controller (24 Channel) : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of CONTROL EQUIPMENT with the features of Light Controller (24 Channel) 12/24 chn modelsEasy to learn, simple to useRecordable up and down fade timesMultiple independent chase speedsLarge memory capacity4 pages of scenemasters with page overlayRecord Beat function for synchronizing chase speedsSD Card back up of all cue data VGA output for live monitoring of desk and on-screen Help""Brand Name: THEATRE LIGHT NZ, Model No.:TLSC24/VGA , Country of Origin: NEWZELAND

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Light control equipment

1.0000

set

180000.00

180000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 180023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

183623.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

201985.81

VAT

6% of Total

IT

4% of Total

13465.72 8977.15 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

224428.67

Page: 2930 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.12

Detailed Analysis Brief Description of Item 2 Light Batten:Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of light batten to be suspended from ceiling in/c. supplying and fixing 13A sockets in each batten complete.Box frame : Made of Aluminium sheet 18 SWG box frame size 16"" long, 5"" breadth 2"" depth.Supporting horizontal bars made of 11 dia 16' length G.I pipe on top and bottoms of the box frame to be linked with box frame by 6""x1'x3/20' flat iron bar at 4' interval welding finishing etc. complete.Supplying & fixing 13A (M.K. brand England) 8-10 Nos. socket in each frame.Hanging the light batten with ceiling by 4 Nos. of 1/2"" dia M.S. Rod with 4 Nos. M.S. hook at bottom of the rod at 6"" vertical interval, the rod to be fixed with ceiling by rowel plug and M.S. plate with necessary welding etc. complete i/c. enamel painting.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Light batten

1.0000

set

16000.00

16000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 16023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

16343.46

10% Profit ( Add 10% on Subtotal-B) :

17977.81

VAT

6% of Total

IT

4% of Total

1198.52 799.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

19975.34

Page: 2931 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.13

Detailed Analysis Brief Description of Item 2 Color Gelatin : Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of color gelatin filter of size 24"x20" of various color. Country of origin : USA/UK/Japan/Australia/Italy or equivalent EU countries.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

Color gelatin filter

1.0000

each

700.00

700.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 723.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

737.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

811.21

VAT

6% of Total

54.08

IT

4% of Total

36.05 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

901.34

Page: 2932 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.14

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1,000W Quartz halogen spare lamp (pin type lamp) in conformity to specified codes & specification of International standard.Country of origin : USA/UK/Japan/Australia/Italy or equivalent EU countries.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

1000w quartz halogen

1.0000

each

3100.00

3100.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 3123.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3185.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3504.01

VAT

6% of Total

233.60

IT

4% of Total

155.73 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3893.34

Page: 2933 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.15

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 500W Quartz halogen spare lamp (pin type lamp) in conformity to specified codes & specification of International standard. Country of origin : USA/UK/Japan/Australia/Italy or equivalent EU countries.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

500w quartz halogen

1.0000

each

2700.00

2700.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 2723.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2777.46

10% Profit ( Add 10% on Subtotal-B) :

3055.21

VAT

6% of Total

IT

4% of Total

203.68 135.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3394.67

Page: 2934 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.16

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1000W tungsten halogen spare lamp (halogen lamp) in conformity to specified codes & specification of International standard. Country of origin : USA/UK/Japan/Australia/Italy or equivalent EU countries.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

1000w tungsten halogen

1.0000

each

650.00

650.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 673.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

686.46

10% Profit ( Add 10% on Subtotal-B) :

755.11

VAT

6% of Total

IT

4% of Total

50.34 33.56 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

839.01

Page: 2935 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.17

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of 1000W tungsten halogen spare lamp (halogen lamp) in conformity to specified codes & specification of International standard.Country of origin : USA/UK/Japan/Australia/Italy or equivalent EU countries.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each

500w tungsten halogen

1.0000

each

500.00

500.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 523.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

533.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

586.81

VAT

6% of Total

39.12

IT

4% of Total

26.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

652.01

Page: 2936 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.18

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of three core 3x40/.0076 (Flexible) 250/440v cable complete with all required accessories i/c. plastic channel and PVC pipes etc. all complete.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

m

3 core 3x40/.0076(flexible) cable

1.0000

m

55.00

55.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 78.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

79.56

10% Profit ( Add 10% on Subtotal-B) :

87.52

VAT

6% of Total

IT

4% of Total

5.83 3.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

97.24

Page: 2937 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.19

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Fogger machine With the features of DMX Interface, LCD Dysplay, 3000W Heater, Output40000cuft, Tank Capasity 6ltr, Fuid Consumption 5min/Liter. Model No.: EF1744, Brand Name: Arena Luci, Country of Origin: ITALY

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Fogger machine

1.0000

set

9000.00

9000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 9023.00

Subtotal-A: Subtotal-B: Subtotal-C:

9203.46

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10123.81

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

674.92

IT

4% of Total

449.95 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

11248.67

Page: 2938 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.20

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of Moon Flower Light With the features of Light Source: 57 LEDs (17 red, 24 green, 16 blue) 0.25 W (20ma), 50,000 hourse, Input voltage: 120 to 230 VAC, 50/60 Hz (Switcable). Model No.: LX-10, Brand Name: CHAUVET, Country of Origin: USA.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

Moon flower light

1.0000

set

62000.00

62000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 62023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

63263.46

10% Profit ( Add 10% on Subtotal-B) :

69589.81

VAT

6% of Total

IT

4% of Total

4639.32 3092.88 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

77322.01

Page: 2939 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.11.21

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of projection screen. Foreign Made

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

esch

Projection screen

1.0000

set

100000.00

100000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 100023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

102023.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

112225.81

VAT

6% of Total

IT

4% of Total

7481.72 4987.81 Total:

12.11.22

Supplying, assembling, fitting, fixing, installation (with effictive connection) testing & Commissioning of VOLTAGE STABILIZER with the features of 5 KVA, 220V/230V, High accuracy and ultra fast response, Law integral impedance, uneffected by frequency variations for sound equipment (Manufactured by grameen - betek Ltd/ Navana electronic Ltd). LOCAL MADE

each

Voltage stabilizer

1.0000

each

14000.00

Subtotal-B: Subtotal-C:

14000.00 14000.00

Subtotal-A: Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14280.00

10% Profit ( Add 10% on Subtotal-B) :

15708.00

VAT

6% of Total

IT

4% of Total

1047.20 698.13 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

124695.34

17453.33

Page: 2940 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.11.23

2 Supplying and fixing of LED PAR 64 with the features of Power Range: 100-240 V, 50/60 Hz, Consumption: 30W, Light source: LED. Brand Name: CHAUVET, Model No.: SLIM PAR 64 RGBA, Country of Origin: USA or equivalent

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

LED PAR 64-30W

1.0000

set

50000.00

50000.00

Asst Electrician

0.2000

day

680.00

136.00 50136.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

51138.72

10% Profit ( Add 10% on Subtotal-B) :

56252.59

VAT

6% of Total

IT

4% of Total

3750.17 2500.12 Total:

12.11.24

Supplying and fixing of DMX Controller with the features of POWER SUPPLY 230Vac 50Hz (9Vdc to 12Vdc) DMX512/1990 standard, 192 DMX channels. Brand Name: ARENA LUCI, Model No.: CO690, Country of Origin: ITALY or equivalent

set

DMX Controller 192

1.0000

set

90000.00

90000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 90162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

91965.24 101161.76

VAT

6% of Total

6744.12

IT

4% of Total

4496.08 Total:

12.12

62502.88

112401.96

CCTV SURVAILLANCE SYSTEM :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2941 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.12.01

Detailed Analysis Brief Description of Item 2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Supplying, assembling, fitting, fixing & installation (with effictive connection) of CCTV : DVR 8/16 channel real time Pentaplex Digital video Recorder Operation: Pentaplex Performance (Simultaneous live Display) Video In: connection Bnc, 1.0 Vpp Composite 75 Ohm Balanced Loop Through Bnc , 1.0 Vpp composite 75 Ohm unbalanced, Audio In Channels: 4-Line level Unbalanced Including Accessories Dvd writer, usb mouse, Ir remote. Main Displays: Bnc 1.0 Vpp Composite 75 Oj, Imba; Amcedf (Videp Pm: U) Vga 15 Pin D-sub 1024*768 @ 60 Hz (With Gui) Screen Display Mode!,4,9,16 -user defined channel for sequence adjustable dwell time,user defined sequences. Spots display: channels 4 fully Programmable Connection Bnc, 1.0 Vpp 1.0 Vpp composite 75 Ohm unbalanced, Display mode foll screen sequence, adjustable Dwell Time Output: 16, High (+5v) or low (0v) selectanle, common ground. Recording: Video codec Mpeg-4 Resolution options for each channel Cif (352*288) 2 Cif (704) pre-eventrecording 5 seconds max. Recording Modes Continuous / motion detection/ alam/ schedule configurable recording time limits weekly / daily motion detection 16*16 selectable grid with 10 levels of covert recording yes, selectable by channel camera title english and numeral. Play Back: Search Method calendar / timeline, event log, sequence, split sceen display modes 1,4,16 audio synchronization yes, any framerate. Archiving: storage backup to cd/dvd media via dvd Rw, Usb format water marked avi, jpeg. Dst YES:

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2942 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

RS-485 multi protocol, baud rate and speed control for each. Network: Connection Rj10/100 Ethernet 2 way network audio yes bandwidth management yes remote client software storage 4* Hdd Mix operating temperature o c to 45 c Model & sample to be approved by Engineer-in-charge. 12.12.01.1

For 8-Channel

set CCTV system 8-channel

1.0000

set

200000.00

200000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 200023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

204023.46

10% Profit ( Add 10% on Subtotal-B) :

224425.81

VAT

6% of Total

IT

4% of Total

14961.72 9974.48 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

249362.01

Page: 2943 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.12.01.2

2 For 16-Channel

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set CCTV system 16-channel

1.0000

set

280000.00

280000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 280023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

285623.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

314185.81

VAT

6% of Total

20945.72

IT

4% of Total

13963.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

349095.34

Page: 2944 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.12.02

Detailed Analysis Brief Description of Item 2 IR Camera :Supplying, assembling, fitting, fixing & installation (with effictive connection) of of 1/3""2.8-12mm Fl.3 Varifocal, DC Auto Iris (Cs Mount) Day/ Night IR, Varifocal IR(Infra red) DC auto Iris lenses Are designed for Day/Night cameras. They eliminate focus shift in night mode, especially in the presence of IR lighting. All lenses are Cs-mount, S comprised of all glass optics, come with liking set srews and a durable metal Barrel.Suitable for use in Bangladesh.Complete with required accessories and in confirmity to specified codes and specification of international standards & CE/UL/CSA certified.Origin : USA/EU/Japan or equivalent.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

IR camera

1.0000

each

8500.00

8500.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 8523.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8693.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

9562.81

VAT

6% of Total

637.52

IT

4% of Total

425.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

10625.34

Page: 2945 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.12.03

Detailed Analysis Brief Description of Item 2 21” Color LCD/LED TV Monitor: Supplying, assembling, fitting, fixing & installation (with effictive connection) of 21'' tv monitor, Foreign made Complete with required accessories & in conformity to Model & sample to be approved by the Engineer-in-charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

21" LCD/LED MONITOR

1.0000

each

20000.00

20000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 20013.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20413.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

22455.26

VAT

6% of Total

1497.02

IT

4% of Total

998.01 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

24950.29

Page: 2946 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Detailed Analysis

Item Code

Brief Description of Item

1 12.12.04

2 32” Color LCD/LED TV Monitor:Supplying, assembling, fitting, fixing & installation (with effictive connection) of 32” Color LCD/LED TV Monitor complete with required accessories and in conformity to specified codes & specification of international standards. Model & sample to be approved by the competent authority.Screen size : 32” (inch)Type : LCD/LEDTV System : Analog, B/G, D/K,I,MColor System : NTSC 3.58, NTSC 4.43, PAL, SECAMVideo Signal : 480/60i, 480/60p, 576/50i, 576/50p, 720/50p, 720/60p, 1080/50i, 1080/60i, 1080/24p (HDMITM Only), 1080/50p (HDMITM /Component), 1080/60p (HDMITM /Component)Display Resolution : WXGAHDMITM /Audio in : 2 (2Rear)USB 2.0 : 1 (SIDE)Composite Video Inputs : 2 (1 Rear Hybrid w/Component)RF Connection Inputs : 1 (Rear)Analog Audio Inputs : 1 (Rear Hybrid w/PC)Audio Out : 1 (Rear / Hybrid w HP)Headphone Out : 1 (Rear / Hybrid w /Audio Out)Control for HTMI (HDMI CEC) : YesUSB Play : Yes (Video, Music, Photo) (USB Viewer supports FAT16, FAT32 and exFAT file system)Power Consumption : 55WStandby Power consumption : 0.5W

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

32" LCD/LED MONITOR

1.0000

each

75000.00

75000.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

76500.00

10% Profit ( Add 10% on Subtotal-B) :

84150.00

VAT

6% of Total

IT

4% of Total

5610.00 3740.00 Total:

12.13

75000.00

93500.00

PABX SYSTEM :

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2947 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.13.01

Detailed Analysis Brief Description of Item 2 Supply ,installation (with effictive connection), testing & commissioning of 8+32 line (Extension Capacity 120 line) digital PABXSystem. Basic Unit: 8+32 line PABX system hardware: (CPU Card, TNG Card, power supply unit & casing) Software: system operating software & billing software.Features :Direct inward station access (DISA) built in billing system automatic Fax/ phone switching key telephone interface day/night service , total call report by extension , individual call report by extension, total call report by CO, individual call. Suitable for use in tropical country like Bangladesh.Complete with required accessories and in conformity to specified codes & specification of international standards & CE/UL/CSA.MODEL & sample to be approved by the competent authority.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set

8+32 line digital PABX

1.0000

set

130000.00

130000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60 130013.60

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

132613.87

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

145875.26

VAT

6% of Total

IT

4% of Total

9725.02 6483.34 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

162083.62

Page: 2948 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.13.02

Detailed Analysis Brief Description of Item 2 Supplying, assembling, fitting, fixing & installation (with effictive connection) of Standard Master Telephone Set i/c display, date, time & 16+24 button DSS control. Suitable for use in tropical country like Bangladesh. Complete with required accessories and in conformity to specified codes & specification of international standards & CE/UL/CSA certified. Model & Sample to be approved by the competent authority. A) For use in 8+32 line system

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Standard master telephone

1.0000

set

9500.00

9500.00

Subtotal-A: Subtotal-B: Subtotal-C:

9690.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10659.00

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

710.60

IT

4% of Total

473.73 Total:

12.13.03

Supply installation (with effictive connection) testing & commissioning of Single line Telephone set with provission volume up + down, Redial, Flash Etc. Complete (for normal User). Suitable for use in tropical country like Bangladesh. Complete with required accessories and in conformity to specified codes & specification of international standards & CE/UL/CSA certified. Model & Sample to be approved by the competent authority.

11843.33

each

Single line telephone set

1.0000

each

950.00

950.00 950.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

969.00 1065.90 71.06 47.37

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

9500.00

1184.33

Page: 2949 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.13.04

Detailed Analysis Brief Description of Item 2 Supply installation (with effictive connection) testing & commissioning of Single line Telephone set with provission volume up + down, Redial, Flash Etc. i/c Display with CID system Complete. (for Executives). Suitable for use in tropical country like Bangladesh. Complete with required accessories and in conformity to specified codes & specification of international standards & CE/UL/CSA certified. Model & Sample to be approved by the competent authority.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Single line telephone set for executive

1.0000

each

1700.00

1700.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1734.00

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1907.40

VAT

6% of Total

127.16

IT

4% of Total

84.77 Total:

12.14

1700.00

2119.33

RENEWABLE ENERGY : SOLAR SYSTEM

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2950 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.14.01

Detailed Analysis Brief Description of Item 2 Solar Panel Supply,fitting fixing and testing of 200 - 250 Wp 12V mono-Crystalline Solar panel as approved by Engineer in charge. Solar PV Module/panel shall be inconformity with the requirement of IEC 61215, IEC 61730 standards. Certificate issued by the international recognized authorities such as UL/ULC/VDC/TUV/DNV or equivalent certifying body according to the above requirement shall have to be submitted by the bidder Necessary Catalogue, Operation & maintenance manual will be supplied by the contactor Cell/Panel Brand : BOSCH/Qcell/Solarworld/Sunway/Suntech; Origin : USA/EU Warranty : At least 20 yrs

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Wp

Solar panel

1.0000

Wp

55.00

55.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 78.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

79.56

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

87.52

VAT

6% of Total

IT

4% of Total

5.83 3.89 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

97.24

Page: 2951 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.14.02

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Solar Inverter : Supply, fitting fixing & testing the solar inverter, protected from lighting induced current by surge protective device of adequate rating both in DC and AC side in parallel at the entry and exit terminal of the inverter. The Inverter shall also be protected for overload and over current protection from both DC and AC side. The inverter shall be tested and certified by UL/ULC/VDC/VDE/ETL in accordance with the requirement of relevant IEC standards and shall have authentication to use CE, TUV and UL/ULC logo. Solar Inverter:Of following watt Pure Sine Wave, Efficiency 94% (minimum) Brand : Outback/Extruder/Deutsche Power/Victor (Netharland) Origin : USA/EU Warranty : At least 03 yrs.

12.14.02.01

1000 Watt 24V/48V

each Solar inverter 1000 watt

1.0000

each

22000.00

22000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 22230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22674.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

24942.06

VAT

6% of Total

IT

4% of Total

1662.80 1108.54 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

27713.40

Page: 2952 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.14.02.02

2 1500 Watt 24V/48V

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Solar inverter 1500 watt

1.0000

each

26000.00

26000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 26230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

26754.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

29430.06

VAT

6% of Total

1962.00

IT

4% of Total

1308.00 Total:

12.14.02.03

2000 Watt 24V/48V

each Solar inverter 2000 watt

1.0000

each

39000.00

39000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 39230.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40014.60

10% Profit ( Add 10% on Subtotal-B) :

44016.06

VAT

6% of Total

IT

4% of Total

2934.40 1956.27 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

32700.07

48906.73

Page: 2953 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.14.02.04

2 2500 Watt 24V/48V

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Solar inverter 2500 watt

1.0000

each

44000.00

44000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 44230.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

45114.60

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

49626.06

VAT

6% of Total

3308.40

IT

4% of Total

2205.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

55140.07

Page: 2954 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.14.03

Detailed Analysis Brief Description of Item 2 Solar Battery with casing : Supply, installation (with effictive connection), testing & commissioning of Solar battery with nominal voltage,12V,130AH or above @10HR or equivalent Deep Cycle heavy duty industrial type Lead Acid battery, positive plate : Tubular or solid thicker Plate, negative plate: Pasted float, Electrolyte Dilute Sulfuric Acid, specially suitable for Solar system. The term "Solar" must be engraved at the body of Battery. Battery,12V,130AH Battery rack/cabinet of sufficient size Brand :Hamko/Volvo/Rahim Afrooz or equivalent Made in Bangladesh Warranty : At least 05 yrs.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Solar battery

1.0000

each

18000.00

18000.00

Plumber/ Electric Mistry/ Painter

0.2000

day

680.00

136.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 18145.40

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18508.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

20359.14

VAT

6% of Total

IT

4% of Total

1357.28 904.85 Total:

12.14.04

22621.27

Charge Controller: Supply fitting fixing of MPPT charge controller, high accuracy confirming certification by UL/ULC/VDC/VDE/ETL in accordance with the requirement of relevant IEC standards and shall have authentication to use CE, TUV and UL/ULC logo. Necessary catalogue, operation & maintenance manual will be supplied by the bidder. All complete & sample approved by Engineer-in-charge. Brand : SMA/Morning Star/Outback/apollo Origin : USA/Germany Warranty : At least 03 yrs.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2955 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.14.04.01

2 Solar Charger:24/48v, 30A

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Charge controller 30A

1.0000

each

33000.00

33000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 33023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

33683.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

37051.81

VAT

6% of Total

2470.12

IT

4% of Total

1646.75 Total:

12.14.04.02

Solar Charger:24/48v, 45A

each Charge controller 45A

1.0000

each

44000.00

44000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 44023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

44903.46

10% Profit ( Add 10% on Subtotal-B) :

49393.81

VAT

6% of Total

IT

4% of Total

3292.92 2195.28 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

41168.67

54882.01

Page: 2956 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.14.04.03

2 Solar Charger:24/48v, 60A

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Charge controller 60A

1.0000

each

66000.00

66000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 66023.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

67343.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

74077.81

VAT

6% of Total

4938.52

IT

4% of Total

3292.35 Total:

12.14.04.04

Solar Charger:24/48v, 80A

each Charge controller 80A

1.0000

each

70000.00

70000.00

Plumber/ Electric Mistry/ Painter

0.0200

day

680.00

13.60

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.0200

day

470.00

9.40 70023.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

71423.46

10% Profit ( Add 10% on Subtotal-B) :

78565.81

VAT

6% of Total

IT

4% of Total

5237.72 3491.81 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

82308.67

87295.34

Page: 2957 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.14.05

Detailed Analysis Brief Description of Item 2 Earthing for Solar system : Supply & installation (with effictive connection) of 8'-0" Brass or Copper Rod (10mm dia) under 2'-0" from FGL outside school building, Connecting the rod with SDB's earthing bar by 6mm dia copper wire (properly soldering with the rod) through 25 mm dia pvc pipe complete with necessary accessories as per direction of Engineer in charge.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Earthing for Solar system

1.0000

each

8500.00

8500.00

Plumber/ Electric Mistry/ Painter

1.0000

day

680.00

680.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

1.0000

day

470.00

470.00 9650.00

Subtotal-A: Subtotal-B: Subtotal-C:

9843.00

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10827.30

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

721.82 481.21 Total:

12.14.06

"Solar Frame structure With 3mm X 38mm angle with spacing @ 12"" of galvanized iron. Per Wp"

Wp Solar Frame structure

1.0000

Wp

14.00

14.00 14.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

14.28

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

15.71

VAT

6% of Total

IT

4% of Total

1.05 0.70 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12030.33

17.45

Page: 2958 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.14.07

Detailed Analysis Brief Description of Item 2 Solar installation (with effictive connection): installation (with effictive connection), testing & commissioning of solar system with cables of required sizes (4rm, 10 rm & 16 rm BYM) etc all complete as per instruction Engineer-in-charge. The one year free maintenance service of the total solar system must be given by the concerned contractor.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Wp

Solar installation

1.0000

Wp

8.00

8.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

8.16

10% Profit ( Add 10% on Subtotal-B) :

8.98

VAT

6% of Total

IT

4% of Total

0.60 0.40

Subtotal-C:

Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8.00

9.97

Page: 2959 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 12.14.08

Detailed Analysis Brief Description of Item 2 Solar Pump (D.C.):Supply, fitting fixing, testing & Commissioning of Submersible Solar pump adequate capacity to lifting water from 150 ft under ground to water tank of 25 ft above from the ground (water lifting capacity at least 1000 ltr/day) compete with motor controller, solar module, cables, GI structure (except boring & GI pipe) in conformity with the requirement of IEC/VDE/BS/JIS or equivalent as per following brand/origin of the materials. Certificate issued by the international recognized authorities such as UL/ULC/VDC/TUV/DNV or equivalent certifying body according to the above requirement shall have to be submitted by the supplier.Necessary Catalogue, Operation & maintenance manual will be supplied from manufacturer by the contactor.Pump : Submersible centrifugal pump, adaptable to work best within 40m lift at 50 degree Celsius, Average flow : 1000 ltr/day at sated head; Non Return ValveCertificate :UL 508, CE, ISO certifiedMotor: Asynchronous brushless DC Motor, Water lubricated, 300W (Rated capacity)Speed-600-3300 rpm, efficiency92%, Submersion limitation- 250m, No electronic spares are inside the motor; Certificate :UL1004, Electric Motors CSA C22.2 No.10, CE, ISO certifiedMPPT Motor Controller: -Continuous maximum power point tracking controllers, provide increases PV array output by upto 30%-Float/pressure switch for overflow protection, Remote controlReverse polarity, Overload & high temperature protection-motor power 0.30KW or higher, 18A (max), 50V (max)-solar operationMPPT, efficiency-98%-Enclosure Class-IP54, LED indication for different statusCertificate :UL, CE, ISO certified Solar module/ panel: 150W or higher, voltage-12V/ 24V mono / poly crystalline, certificate: IEC61215, CE, TUV, Rhineland or VDE certified Others : Bore probe- External bore probe connected with the controller through separate submersible cable Float Switch-External float switch with pressure sensor connected to the controller with separate cables Standard L.A. & earthing rod, 1.5" dia delivery pipe etc.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Brand & Origin of pump : Germany/USA/Japan Pump & Solar Panel will be of same brand Energy Saving Light : 04 nos. with holder and gang switch as required. Cable :NYY/NYY-F/6rm-4rm : 4rm BYA-FRLS type as required & 1-2CNote : Rates of all items should be inclusive of all supply and carriage.

Page: 2960 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

1.5 rm BYM for lights Pump with controller warranty : 2 yrs (at least), Solar module : 25 yrs Solar Pump (D.C.)

1.0000

each

155000.00

155000.00

Plumber/ Electric Mistry/ Painter

0.5000

day

680.00

340.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.5000

day

470.00

235.00 155575.00

Subtotal-A: Subtotal-B: Subtotal-C:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

158686.50

10% Profit ( Add 10% on Subtotal-B) :

174555.15

VAT

6% of Total

IT

4% of Total

11637.01 7758.01 Total:

12.14.09

193950.17

Solar Battery Gel Type with casing : Supply, installation (with effictive connection), testing & commissioning of maintenance free Gel type Solar battery with 2V nominal voltage, heavy duty industrial type, positive plate : Tubular, negative plate: Pasted flat, Electrolyte Dilute Sulfuric Acid, specially suitable for Solar system. This item must includes Battery rack/cabinet of sufficient size. The term "Solar" must be engraved at the body of Battery. Battery,12V,130AH Brand & Origin : European/USA or equivalent Warranty : At least 10 yrs.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2961 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.14.09.1

2 Capacty in Ampere Hour : 400 AH

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set 400 ah gel battery

1.0000

set

25000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 25162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25665.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

28231.76

VAT

6% of Total

1882.12

IT

4% of Total

1254.75 Total:

12.14.09.2

Capacty in Ampere Hour : 500 AH

31368.63

set 500 ah gel battery

1.0000

set

30000.00

30000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 30162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

30765.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

33841.76

VAT

6% of Total

IT

4% of Total

2256.12 1504.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

25000.00

37601.96

Page: 2962 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1 12.14.09.3

2 Capacty in Ampere Hour : 800 AH

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set 800 ah gel battery

1.0000

set

34000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 34162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

34845.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

38329.76

VAT

6% of Total

2555.32

IT

4% of Total

1703.55 Total:

12.14.09.4

Capacty in Ampere Hour : 1000 AH

42588.63

set 1000 ah gel battery

1.0000

set

40000.00

40000.00

Asst Electrician

0.1000

day

680.00

68.00

Helper of Plumber/ Electric Mistry/ Painter/ Carpenter/ Operator

0.2000

day

470.00

94.00 40162.00

Subtotal-A: Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

40965.24

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

45061.76

VAT

6% of Total

IT

4% of Total

3004.12 2002.75 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

34000.00

50068.63

Page: 2963 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code

Detailed Analysis Brief Description of Item

1

2

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

Chapter - 13 : Mechanical Works 13.01

Supplying, fitting, fixing and installation of Element, Air Filter at the specified vehicle conforming to the following specifications including cost of all necessary accessories, their carriages, fuel, lubricant, wages of labour, technicians and incidental charges etc. including testing and commissioning all complete, approved and accepted by the Engineer-inCharge. The parts shall be genuine and collected from authorised dealer of the Manufacturer.

13.01.01

For Mitsubishi Double cabin Pick-up, Vehicle model: L200, Engine Model: 4D56.

each Element, Air Filter, Mitsubishi L200

1.0000

each

4000.00

4000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

91.56

Subtotal-A1:

4142.81

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4225.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4648.23

VAT

6% of Total

IT

4% of Total

309.88 206.59 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5164.70

Page: 2964 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.01.02

Detailed Analysis Brief Description of Item 2 For Mitsubishi Jeep, Vehicle model: Pajero Sports, Engine Model: 4D56.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Element, Air Filter, Mitsubishi Pajero Sports

1.0000

each

4000.00

4000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A ) ( % on Subtotal-A )

91.56

Subtotal-A1:

4142.81

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4225.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4648.23

VAT

6% of Total

309.88

IT

4% of Total

206.59 Total:

13.01.03

For Toyota Double cabin Pick-up, Vehicle model: Hilux, Engine Model: 2KD.

each Element, Air Filter, Toyota Hilux

1.0000

each

4200.00

4200.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4251.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

96.08

Subtotal-A1: Subtotal-B: Subtotal-C:

4347.33 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4434.27

10% Profit ( Add 10% on Subtotal-B) :

4877.70

VAT

6% of Total

IT

4% of Total

325.18 216.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5164.70

5419.67

Page: 2965 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.01.04

Detailed Analysis Brief Description of Item 2 For Toyota Jeep, Vehicle model: Landcruiser Prado GX, Engine Model: 5L.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Element, Air Filter, Landcruiser Prado GX

1.0000

each

3200.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 3251.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

73.48

Subtotal-A1: Subtotal-B: Subtotal-C:

3324.73 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3391.22

10% Profit ( Add 10% on Subtotal-B) :

3730.35

VAT

6% of Total

IT

4% of Total

248.69 165.79 Total:

13.01.05

For Toyota Jeep, Vehicle model: Landcruiser Prado TX, Engine Model: 1KD.

4144.83

each Element, Air Filter, Landcruiser Prado TX

1.0000

each

3200.00

3200.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 3251.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

73.48

Subtotal-A1:

3324.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3391.22

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3730.35

VAT

6% of Total

IT

4% of Total

248.69 165.79 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3200.00

4144.83

Page: 2966 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.01.06

Detailed Analysis Brief Description of Item 2 For Toyota Jeep, Vehicle model: Landcruiser Prado VX, Engine Model: 1HD.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Element, Air Filter, Landcruiser Prado VX

1.0000

each

4500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

102.86

Subtotal-A1: Subtotal-B: Subtotal-C:

4654.11 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4747.19

10% Profit ( Add 10% on Subtotal-B) :

5221.91

VAT

6% of Total

IT

4% of Total

348.13 232.08 Total:

13.01.07

For Toyota Microbus, Vehicle model: Hiace, Engine Model: 2TR.

5802.12

each Element, Air Filter, Toyota Hiace

1.0000

each

4500.00

4500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

102.86

Subtotal-A1: Subtotal-B: Subtotal-C:

4654.11 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4747.19

10% Profit ( Add 10% on Subtotal-B) :

5221.91

VAT

6% of Total

348.13

IT

4% of Total

232.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4500.00

5802.12

Page: 2967 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.01.08

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Corolla G, Engine Model: 1NZ.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Element, Air Filter, Toyota Corolla G

1.0000

each

2400.00

2400.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.4100

day

570.00

233.70 2661.58

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

60.15

Subtotal-A1:

2721.73

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2776.17

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

3053.78

VAT

6% of Total

IT

4% of Total

203.59 135.72 Total:

13.01.09

For Toyota Car, Vehicle model: Corolla X, Engine Model: 1NZ.

each Element, Air Filter, Toyota Corolla X

1.0000

each

2400.00

2400.00

Skilled Technician

0.4100

day

680.00

278.80

Semi Skilled Technician

0.4100

day

570.00

233.70 2912.50

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

65.82

Subtotal-A1: Subtotal-B: Subtotal-C:

2978.32 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3037.89

10% Profit ( Add 10% on Subtotal-B) :

3341.68

VAT

6% of Total

IT

4% of Total

222.78 148.52 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3393.09

3712.98

Page: 2968 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.01.10

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Probox DX, Engine Model: 1NZ.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Element, Air Filter, Toyota Probox DX

1.0000

each

2000.00

2000.00

Skilled Technician

0.4100

day

680.00

278.80

Semi Skilled Technician

0.4100

day

570.00

233.70 2512.50

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

56.78

Subtotal-A1:

2569.28

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2620.67

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2882.73

VAT

6% of Total

IT

4% of Total

192.18 128.12 Total:

13.01.11

For Toyota Car, Vehicle model: Premio F, Engine Model: 1NZ.

each Element, Air Filter, Premio F

1.0000

each

2400.00

2400.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 2451.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

55.40

Subtotal-A1: Subtotal-B: Subtotal-C:

2506.65 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2556.78

10% Profit ( Add 10% on Subtotal-B) :

2812.46

VAT

6% of Total

IT

4% of Total

187.50 125.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3203.04

3124.95

Page: 2969 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

13.02

Supplying, fitting, fixing and installation of Oil Filter at the specified vehicle conforming to the following specifications including cost of all necessary accessories, their carriages, fuel, lubricant, wages of labour, technicians and incidental charges etc. including testing and commissioning all complete, approved and accepted by the Engineer-inCharge. The parts shall be genuine and collected from authorised dealer of the Manufacturer.

13.02.01

For Mitsubishi Double cabin Pick-up, Vehicle model: L200, Engine Model: 4D56.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Oil Filter, Mitsubishi L200

1.0000

each

1700.00

1700.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1751.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

39.58

Subtotal-A1:

1790.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1826.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2009.31

VAT

6% of Total

IT

4% of Total

133.95 89.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2232.57

Page: 2970 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.02.02

Detailed Analysis Brief Description of Item 2 For Mitsubishi Jeep, Vehicle model: Pajero Sports, Engine Model: 4D56.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Oil Filter, Mitsubishi Pajero Sports

1.0000

each

1700.00

1700.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1751.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

39.58

Subtotal-A1:

1790.83

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1826.64

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2009.31

VAT

6% of Total

IT

4% of Total

133.95 89.30 Total:

13.02.03

For Toyota Double cabin Pick-up, Vehicle model: Hilux, Engine Model: 2KD.

each Oil Filter, Toyota Hilux

1.0000

each

1400.00

1400.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1451.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

32.80

Subtotal-A1: Subtotal-B: Subtotal-C:

1484.05 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1513.73

10% Profit ( Add 10% on Subtotal-B) :

1665.10

VAT

6% of Total

IT

4% of Total

111.01 74.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

2232.57

1850.11

Page: 2971 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.02.04

Detailed Analysis Brief Description of Item 2 For Toyota Jeep, Vehicle model: Landcruiser Prado GX, Engine Model: 5L.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Oil Filter, Landcruiser Prado GX

1.0000

each

1500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

35.06

Subtotal-A1: Subtotal-B: Subtotal-C:

1586.31 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1618.03

10% Profit ( Add 10% on Subtotal-B) :

1779.84

VAT

6% of Total

IT

4% of Total

118.66 79.10 Total:

13.02.05

For Toyota Jeep, Vehicle model: Landcruiser Prado TX, Engine Model: 1KD.

1977.60

each Oil Filter, Landcruiser Prado TX

1.0000

each

1400.00

1400.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1451.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

32.80

Subtotal-A1:

1484.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1513.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1665.10

VAT

6% of Total

IT

4% of Total

111.01 74.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1500.00

1850.11

Page: 2972 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.02.06

Detailed Analysis Brief Description of Item 2 For Toyota Jeep, Vehicle model: Landcruiser Prado VX, Engine Model: 1HD.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Oil Filter, Landcruiser Prado VX

1.0000

each

3000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 3051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

68.96

Subtotal-A1: Subtotal-B: Subtotal-C:

3120.21 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3182.61

10% Profit ( Add 10% on Subtotal-B) :

3500.87

VAT

6% of Total

IT

4% of Total

233.39 155.59 Total:

13.02.07

For Toyota Microbus, Vehicle model: Hiace, Engine Model: 2TR.

3889.86

each Oil Filter, Toyota Hiace

1.0000

each

1600.00

1600.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1651.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

37.32

Subtotal-A1: Subtotal-B: Subtotal-C:

1688.57 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1722.34

10% Profit ( Add 10% on Subtotal-B) :

1894.57

VAT

6% of Total

126.30

IT

4% of Total

84.20 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3000.00

2105.08

Page: 2973 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.02.08

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Corolla G, Engine Model: 1NZ.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Oil Filter, Toyota Corolla G

1.0000

each

800.00

800.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 851.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

19.24

Subtotal-A1:

870.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

887.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

976.69

VAT

6% of Total

IT

4% of Total

65.11 43.41 Total:

13.02.09

For Toyota Car, Vehicle model: Corolla X, Engine Model: 1NZ.

each Oil Filter, Toyota Corolla X

1.0000

each

800.00

800.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 851.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

19.24

Subtotal-A1: Subtotal-B: Subtotal-C:

870.49 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

887.90

10% Profit ( Add 10% on Subtotal-B) :

976.69

VAT

6% of Total

IT

4% of Total

65.11 43.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1085.21

1085.21

Page: 2974 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.02.10

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Probox DX, Engine Model: 1NZ.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

Amount

6

7

8

each Oil Filter, Toyota Probox DX

1.0000

each

800.00

800.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 851.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

19.24

Subtotal-A1:

870.49

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

887.90

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

976.69

VAT

6% of Total

IT

4% of Total

65.11 43.41 Total:

13.02.11

For Toyota Car, Vehicle model: Premio F, Engine Model: 1NZ.

each Oil Filter, Premio F

1.0000

each

800.00

800.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 851.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

19.24

Subtotal-A1: Subtotal-B: Subtotal-C:

870.49 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

887.90

10% Profit ( Add 10% on Subtotal-B) :

976.69

VAT

6% of Total

IT

4% of Total

65.11 43.41 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1085.21

1085.21

Page: 2975 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

13.03

Supplying, fitting, fixing and installation of Fuel Filter at the specified vehicle conforming to the following specifications including cost of all necessary accessories, their carriages, fuel, lubricant, wages of labour, technicians and incidental charges etc. including testing and commissioning all complete, approved and accepted by the Engineer-inCharge. The parts shall be genuine and collected from authorised dealer of the Manufacturer.

13.03.01

For Mitsubishi Double cabin Pick-up, Vehicle model: L200, Engine Model: 4D56.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Fuel Filter, Mitsubishi L200

1.0000

each

3500.00

3500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 3551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

80.26

Subtotal-A1:

3631.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3704.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4074.55

VAT

6% of Total

IT

4% of Total

271.64 181.09 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

4527.28

Page: 2976 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.03.02

Detailed Analysis Brief Description of Item 2 For Mitsubishi Jeep, Vehicle model: Pajero Sports, Engine Model: 4D56.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Fuel Filter, Mitsubishi Pajero Sports

1.0000

each

3500.00

3500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 3551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

80.26

Subtotal-A1:

3631.51

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

3704.14

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

4074.55

VAT

6% of Total

IT

4% of Total

271.64 181.09 Total:

13.03.03

4527.28

For Toyota Double cabin Pick-up, Vehicle model: Hilux, Engine Model: 2KD.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2977 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.03.03.1

Detailed Analysis Brief Description of Item 2 For Toyota Double cabin Pick-up, Vehicle model: Hilux, Engine Model: 2KD. Fuel Filter

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Fuel Filter, Toyota Hilux

1.0000

each

2500.00

2500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 2551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

57.66

Subtotal-A1:

2608.91

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

2661.09

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

2927.20

VAT

6% of Total

IT

4% of Total

195.15 130.10 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

3252.44

Page: 2978 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.03.03.2

Detailed Analysis Brief Description of Item 2 For Toyota Double cabin Pick-up, Vehicle model: Hilux, Engine Model: 2KD. Fuel Filter with cap

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each

Fuel Filter with cap, Toyota Hilux

1.0000

each

9500.00

9500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 9551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

215.86

Subtotal-A1:

9767.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

VAT

6% of Total

IT

4% of Total

9962.45 10958.70 730.58 487.05

Total: 13.03.04

For Toyota Jeep, Vehicle model: Landcruiser Prado GX, Engine Model: 5L.

each Fuel Filter, Landcruiser Prado GX

1.0000

each

5000.00

5000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 5051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

114.16

Subtotal-A1: Subtotal-B: Subtotal-C:

5165.41 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5268.72

10% Profit ( Add 10% on Subtotal-B) :

5795.59

VAT

6% of Total

IT

4% of Total

386.37 257.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

12176.33

6439.54

Page: 2979 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.03.05

Detailed Analysis Brief Description of Item 2 For Toyota Jeep, Vehicle model: Landcruiser Prado TX, Engine Model: 1KD.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Fuel Filter, Landcruiser Prado TX

1.0000

each

6000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 6051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

136.76

Subtotal-A1: Subtotal-B: Subtotal-C:

6188.01 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

6311.77

10% Profit ( Add 10% on Subtotal-B) :

6942.95

VAT

6% of Total

IT

4% of Total

462.86 308.58 Total:

13.03.06

For Toyota Jeep, Vehicle model: Landcruiser Prado VX, Engine Model: 1HD.

7714.38

each Fuel Filter, Landcruiser Prado VX

1.0000

each

5000.00

5000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 5051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

114.16

Subtotal-A1:

5165.41

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

5268.72

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5795.59

VAT

6% of Total

IT

4% of Total

386.37 257.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

6000.00

6439.54

Page: 2980 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.03.07

Detailed Analysis Brief Description of Item 2 For Toyota Microbus, Vehicle model: Hiace, Engine Model: 2TR.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Fuel Filter, Toyota Hiace

1.0000

each

11500.00

11500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 11551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

261.06

Subtotal-A1:

11812.31

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12048.55

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13253.41

VAT

6% of Total

IT

4% of Total

883.56 589.04 Total:

13.03.08

For Toyota Car, Vehicle model: Corolla G, Engine Model: 1NZ.

each Fuel Filter, Toyota Corolla G

1.0000

each

4500.00

4500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

102.86

Subtotal-A1: Subtotal-B: Subtotal-C:

4654.11 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4747.19

10% Profit ( Add 10% on Subtotal-B) :

5221.91

VAT

6% of Total

IT

4% of Total

348.13 232.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

14726.01

5802.12

Page: 2981 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.03.09

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Corolla X, Engine Model: 1NZ.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Fuel Filter, Toyota Corolla X

1.0000

each

4500.00

4500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

102.86

Subtotal-A1:

4654.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4747.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5221.91

VAT

6% of Total

IT

4% of Total

348.13 232.08 Total:

13.03.10

For Toyota Car, Vehicle model: Probox DX, Engine Model: 1NZ.

each Fuel Filter, Toyota Probox DX

1.0000

each

4500.00

4500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

102.86

Subtotal-A1: Subtotal-B: Subtotal-C:

4654.11 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4747.19

10% Profit ( Add 10% on Subtotal-B) :

5221.91

VAT

6% of Total

IT

4% of Total

348.13 232.08 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

5802.12

5802.12

Page: 2982 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.03.11

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Premio F, Engine Model: 1NZ.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Fuel Filter, Premio F

1.0000

each

4500.00

4500.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 4551.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

102.86

Subtotal-A1:

4654.11

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

4747.19

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

5221.91

VAT

6% of Total

IT

4% of Total

348.13 232.08 Total:

13.04

Supplying, fitting, fixing and installation of Spark Plugs at the specified vehicle conforming to the following specifications including cost of all necessary accessories, their carriages, high tension wires/ coils, wages of labour, technicians and incidental charges etc. including testing and commissioning all complete, approved and accepted by the Engineer-inCharge. The parts shall be genuine and collected from authorised dealer of the Manufacturer.

13.04.01

For Toyota Car, Vehicle model: Corolla G, Engine Model: 1NZ.

Note : Rates of all items should be inclusive of all supply and carriage.

5802.12

Page: 2983 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.04.01.1

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Corolla G, Engine Model: 1NZ. Spark Plugs, Normal

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Spark Plugs, Normal, Toyota Corolla G

1.0000

set

1400.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1451.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

32.80

Subtotal-A1: Subtotal-B: Subtotal-C:

1484.05 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1513.73

10% Profit ( Add 10% on Subtotal-B) :

1665.10

VAT

6% of Total

IT

4% of Total

111.01 74.00 Total:

13.04.01.2

For Toyota Car, Vehicle model: Corolla G, Engine Model: 1NZ. Spark plugs, Iridium

1850.11

set Spark plugs, Iridium, Toyota Corolla G

1.0000

set

7000.00

7000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 7051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

159.36

Subtotal-A1:

7210.61

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7354.82

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

8090.30

VAT

6% of Total

IT

4% of Total

539.35 359.57 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1400.00

8989.22

Page: 2984 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

13.04.02

For Toyota Car, Vehicle model: Corolla X, Engine Model: 1NZ.

13.04.02.1

For Toyota Car, Vehicle model: Corolla X, Engine Model: 1NZ. Spark Plugs, Normal

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Spark Plugs, Normal, Toyota Corolla X

1.0000

set

1400.00

1400.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1451.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

32.80

Subtotal-A1:

1484.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1513.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1665.10

VAT

6% of Total

IT

4% of Total

111.01 74.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

1850.11

Page: 2985 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.04.02.2

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Corolla X, Engine Model: 1NZ. Spark plugs, Iridium

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Spark plugs, Iridium, Toyota Corolla X

1.0000

set

7000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 7051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

159.36

Subtotal-A1: Subtotal-B: Subtotal-C:

7210.61 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7354.82

10% Profit ( Add 10% on Subtotal-B) :

8090.30

VAT

6% of Total

IT

4% of Total

539.35 359.57 Total:

13.04.03

For Toyota Car, Vehicle model: Probox DX, Engine Model: 1NZ.

8989.22

set Spark Plugs, Toyota Probox DX

1.0000

set

1400.00

1400.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1451.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

32.80

Subtotal-A1: Subtotal-B: Subtotal-C:

1484.05 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1513.73

10% Profit ( Add 10% on Subtotal-B) :

1665.10

VAT

6% of Total

111.01

IT

4% of Total

74.00 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

7000.00

1850.11

Page: 2986 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.04.04

Detailed Analysis Brief Description of Item 2 For Toyota Car, Vehicle model: Premio F, Engine Model: 1NZ.

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

set Spark Plugs, Toyota Premio F

1.0000

set

1400.00

1400.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 1451.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

32.80

Subtotal-A1:

1484.05

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

1513.73

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

1665.10

VAT

6% of Total

IT

4% of Total

111.01 74.00 Total:

13.05

1850.11

Supplying standard tyres, country of origin Japan or similar country of Brand: Yokohama/Dunlop/Bridgestone or equivalent, including fitting, fixing and installation at the specified vehicles conforming to the following specifications, including cost of all necessary accessories, their carriages, inflation, wages of labour, technicians and incidental charges etc. including testing and commissioning all complete, approved and accepted by the Engineer-in-Charge.

Note : Rates of all items should be inclusive of all supply and carriage.

Page: 2987 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.05.01

Detailed Analysis Brief Description of Item 2 Tyre Size: 185/65R14 (radial tyre, tubeless or equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Tyre Size: 185/65R14

1.0000

each

10580.00

10580.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 10631.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

240.27

Subtotal-A1:

10871.52

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11088.95

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12197.84

VAT

6% of Total

IT

4% of Total

813.19 542.13 Total:

13.05.02

Tyre Size: 185/70R14 (radial tyre, tubeless or equivalent)

each Tyre Size: 185/70R14

1.0000

each

11300.00

11300.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 11351.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

256.54

Subtotal-A1: Subtotal-B: Subtotal-C:

11607.79 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11839.94

10% Profit ( Add 10% on Subtotal-B) :

13023.94

VAT

6% of Total

IT

4% of Total

868.26 578.84 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13553.16

14471.04

Page: 2988 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.05.03

Detailed Analysis Brief Description of Item 2 Tyre Size: 195/70R15C-6 (radial tyre, tubeless ply rating 6 or equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Tyre Size: 195/70R15C-6

1.0000

each

13000.00

13000.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 13051.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

294.96

Subtotal-A1:

13346.21

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

13613.13

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

14974.45

VAT

6% of Total

IT

4% of Total

998.30 665.53 Total:

13.05.04

Tyre Size: 215/80R15 (radial tyre, tubeless or equivalent)

each Tyre Size: 215/80R15

1.0000

each

17800.00

17800.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 17851.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

403.44

Subtotal-A1: Subtotal-B: Subtotal-C:

18254.69 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

18619.78

10% Profit ( Add 10% on Subtotal-B) :

20481.76

VAT

6% of Total

IT

4% of Total

1365.45 910.30 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

16638.27

22757.51

Page: 2989 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.05.05

Detailed Analysis Brief Description of Item 2 Tyre Size: 215/80R16 (radial tyre, tubeless or equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Tyre Size: 215/80R16

1.0000

each

18350.00

18350.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 18401.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

415.87

Subtotal-A1:

18817.12

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

19193.46

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

21112.81

VAT

6% of Total

IT

4% of Total

1407.52 938.35 Total:

13.05.06

Tyre Size: 205/80R16 (radial tyre, tubeless or equivalent)

each Tyre Size: 205/80R16

1.0000

each

19990.00

19990.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 20041.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

452.93

Subtotal-A1: Subtotal-B: Subtotal-C:

20494.18 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

20904.07

10% Profit ( Add 10% on Subtotal-B) :

22994.47

VAT

6% of Total

IT

4% of Total

1532.96 1021.98 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

23458.67

25549.41

Page: 2990 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.05.07

Detailed Analysis Brief Description of Item 2 Tyre Size: 265/65R17 (radial tyre, tubeless or equivalent)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Tyre Size: 265/65R17

1.0000

each

24200.00

24200.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 24251.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

548.08

Subtotal-A1:

24799.33

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

25295.31

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

27824.85

VAT

6% of Total

IT

4% of Total

1854.99 1236.66 Total:

13.05.08

Tyre Size: 265/70R16 (radial tyre, tubeless or equivalent)

each Tyre Size: 265/70R16

1.0000

each

21100.00

21100.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 21151.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

478.02

Subtotal-A1: Subtotal-B: Subtotal-C:

21629.27 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

22061.85

10% Profit ( Add 10% on Subtotal-B) :

24268.04

VAT

6% of Total

IT

4% of Total

1617.87 1078.58 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

30916.50

26964.49

Page: 2991 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1

Detailed Analysis Brief Description of Item 2

13.06

Supplying standard Battery of brand: Lucas/ Rangs Power/ Hamko or equivalent, including fitting, fixing and installation at specified vehicle conforming to the following specifications, including cost of all necessary accessories, their carriages, terminals, cable and clamps, charging and wages of labour, technicians and incidental charges etc. including testing and commissioning all complete, approved and accepted by the Engineer-in-Charge. Minimum replacement warranty period of Batteries shall be 12 months.

13.06.01

Battery Type: NS60/L/S (Volt: 12, Plate/cell: 13, AHC@20 hr: 45.)

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Battery Type: NS60/L/S

1.0000

each

6960.00

6960.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 7011.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

158.45

Subtotal-A1: Subtotal-B: Subtotal-C:

7169.70 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

7313.10

10% Profit ( Add 10% on Subtotal-B) :

8044.41

VAT

6% of Total

IT

4% of Total

536.29 357.53 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

8938.23

Page: 2992 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.06.02

Detailed Analysis Brief Description of Item 2 Battery Type: NX120-7/L, (Volt: 12, Plate/cell: 17, AHC@20 hr: 80).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Battery Type: NX120-7/L

1.0000

each

11760.00

11760.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 11811.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

266.93

Subtotal-A1:

12078.18

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

12319.75

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

13551.72

VAT

6% of Total

IT

4% of Total

903.45 602.30 Total:

13.06.03

Battery Type: N100, (Volt: 12, Plate/cell: 17, AHC@20 hr:100.)

each Battery Type: N100

1.0000

each

9550.00

9550.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 9601.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

216.99

Subtotal-A1: Subtotal-B: Subtotal-C:

9818.24 Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

10014.60

10% Profit ( Add 10% on Subtotal-B) :

11016.06

VAT

6% of Total

IT

4% of Total

734.40 489.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

15057.47

12240.07

Page: 2993 of 2994

Unit Cost Analysis for Schedule of Rates Schedule of Rates, LGED, July 2017 District : DHAKA, GAZIPUR, NARSHINGDI, NARAYANGANJ, MUNSHIGANJ, MANIKGANJ Item Code 1 13.06.04

Detailed Analysis Brief Description of Item 2 Battery Type: N100Z, (Volt: 12, Plate/cell: 19, AHC@20 hr:105).

Unit

Sub-Item

3

4

Quantity 5

Unit

Rate

6

7

Amount 8

each Battery Type: N100Z

1.0000

each

10550.00

10550.00

Skilled Technician

0.0410

day

680.00

27.88

Semi Skilled Technician

0.0410

day

570.00

23.37 10601.25

Subtotal-A: Extra for VAT (+2.26% on Sub Total-A)

( +2.26 % on Subtotal-A )

239.59

Subtotal-A1:

10840.84

Subtotal-B:

Lab Test Fees, Incidental charges & Overhead ( Add 2% on Subtotal-A/ A1) :

11057.66

Subtotal-C:

10% Profit ( Add 10% on Subtotal-B) :

12163.42

VAT

6% of Total

IT

4% of Total

810.89 540.60 Total:

Note : Rates of all items should be inclusive of all supply and carriage.

13514.91

Page: 2994 of 2994

Related Documents


More Documents from "Syed Haider"