Work Breakdown Structure (WBS) Farrokh Alemi, Ph.D. Lee Baliton

Why break up? 

Improve work management Understand resource and time constraints  Set milestones for progress 



Course on Project Management

See alternative sequencing of components of work

Definition of WBS 

Breaks the project scope Inter-related  Discrete tasks 



Course on Project Management

Hierarchical tree structure

Definition of WBS 

Breaks the project Clear scopestarts Inter-related task  Discrete tasks 



Course on Project Management

and ends

Hierarchical tree structure

Definition of WBS Four possible  Breaks the project scope relationship  Inter-related s  Discrete tasks 

Course on Project Management

Hierarchical tree structure

Definition of WBS Four possible  Breaks the project scope relationship  Inter-related s  Discrete tasks 

Hierarchical tree structure

1. Finish to Start: Start second task after first one is finished

Course on Project Management

Definition of WBS Four possible  Breaks the project scope relationship  Inter-related s  Discrete tasks 

Hierarchical tree structure

1. Finish to Start 2. Start to Start: Start second task same time as first one

Course on Project Management

Definition of WBS Four possible  Breaks the project scope relationship  Inter-related s  Discrete tasks 

Hierarchical tree structure 1. Finish to Start 2. Start to Start 3. Finish to Finish: Start second task so both finish at same time

Course on Project Management

Definition of WBS Four possible  Breaks the project scope relationship  Inter-related s  Discrete tasks 

Hierarchical tree structure 1. 2. 3. 4.

Course on Project Management

Finish to Start Start to Start Finish to Finish Start to Finish: Second task cannot finish before first one starts

Definition of Lower WBSlevel tasks inherit the relationships  Breaks the project scope among higher  Inter-related task level tasks  Discrete tasks 

Course on Project Management

Hierarchical tree structure

Hierarchy of Activities Level 1: The root of the tree is the project name

Course on Project Management

A

Hierarchy of Activities EHR implementation

A

Course on Project Management

Hierarchy of Activities EHR implementation

A

Level 2: Components of the entire project

Course on Project Management

B

C

D

Hierarchy of Activities EHR implementation

A Purchase system

B

C

Configure system

Course on Project Management

D

Train users

Hierarchy of Activities EHR implementation

A Purchase system

Level 3: Each level 2 tasks is broken into its subcomponents

Course on Project Management

B

C

D

Train users

Configure system E

F

Hierarchy of Activities EHR implementation

A Purchase system

B

C

D

Train users

Configure system E Purchase training material

Course on Project Management

F Detail employees

Hierarchy of Activities EHR implementation

A Purchase system

B

C

D

Train users

Configure system F

Detail employees

E Purchase training material Course on Project Management

Hierarchy of Activities EHR implementation

A Purchase system

B

C

D

Train users

Configure system F

Detail employees

E Purchase training material Course on Project Management

Hierarchy of Activities EHR implementation

A

Train users

Course on Project Management

F

Detail employees

E

Purchase training material

D

Configure system

C

Purchase system

B

Approaches to Developing Work Breakdown 

  

Course on Project Management

Guidelines Analogy Bottom up Mind mapping

Approaches to Developing Work Breakdown 

  

Course on Project Management

Guidelines Analogy Bottom up Mind mapping

Approaches to Developing Work Breakdown 

  

Course on Project Management

Guidelines Analogy Bottom up Mind mapping

Hierarchy of Activities EHR implementation

A

Train users

Course on Project Management

F

Detail employees

E

Purchase training material

D

Configure system

C

Purchase system

B

Hierarchy of Activities EHR implementation

A

Train users

Course on Project Management

D

Configure system

C

Purchase system

B

F

Detail employees

E

Purchase training material

Approaches to Developing Work Breakdown 

  

Course on Project Management

Guidelines Analogy Bottom up Mind mapping

Task 



Course on Project Management

Mutually exclusive Exhaustive

Task 



Mutually exclusive Exhaustive

EHR implementation A

Purchase of systems and organizing training may not be mutually exclusive if the purchase includes training

Course on Project Management

D

Train users

C

Configure system

B

Purchase system

Task 



Course on Project Management

Mutually exclusive Exhaustive

Breadth .vs. Depth 



Focus on breadth Let details emerge Progressive elaboration  Creativity 

Course on Project Management

Breadth .vs. Depth 



Focus on breadth Let details emerge Progressive elaboration  Creativity 

Course on Project Management

Numbering Convention EHR implementation

A Train (detail) users

Course on Project Management

D

Configure system

C

Purchase system

B

E

1.1.2 Purchase training material

Numbering Convention EHR implementation

A Train (detail) users

Course on Project Management

D

Configure system

C

Purchase system

B

E

1.1.2 Purchase training material

Numbering Convention EHR implementation

A Train (detail) users

Course on Project Management

D

Configure system

C

Purchase system

B

E

1.1.2 Purchase training material

Numbering Convention EHR implementation

A Train (detail) users

Course on Project Management

D

Configure system

C

Purchase system

B

E

1.1.2 Purchase training material

Work Breakdown Is Not … 

Course on Project Management

We need to clarify some common mistakes …

A Task Is … 

Course on Project Management

Not a goal

A Task Is … 



Course on Project Management

Not a goal Not a process

Work Breakdown Is … 

Course on Project Management

Not an exhaustive list of work

Work Breakdown Is … 



Course on Project Management

Not an exhaustive list of work Not a chronology

Work Breakdown Is … 

 

Course on Project Management

Not an exhaustive list of work Not a chronology Not an organization structure

Work Breakdown Is … 

  

Course on Project Management

Not an exhaustive list of work Not a chronology Not an organization structure Not to be changed often

Good Work Breakdowns 

  



Course on Project Management

Easy to understand Corresponds to job descriptions Not too detailed Preserve the most important relationships among the tasks Does not add to length of project

Take Home Message Think Carefully through Work Breakdown Structure