IRAQ GATES CONTRACTING COMPANY Method Statement
Rev: A
For Switchgear recommissioning at Um-Qasr
xxxxxxxxxxxxx
Doc. Cat.
EXT
Method Statement for Switchgear recommissioning at Um-Qasr
A REV
11-Nov-2018 DATE
Issued for Review
B.R
W.A
DESCRIPTION
PREPARED BY
REVIEWED BY
APPROVED
1 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement for Switchgear recommissioning at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
TABLE OF CONTENTS 1.
Introduction
2.
Definitions
3.
Abbreviations
4.
Methodology
5.
MTO
6.
HSE Requirements
7.
Attachments
2 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement for Switchgear recommissioning at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
Method Statement for Switchgear recommissioning at Um-Qasr 1. Introduction As part of BGC development plan, Work Order (WO-026) to perform Refrigerated Export (Method Statement for Switchgear recommissioning at Um-Qasr) At Storage Terminal has been issued to IGCC. This Method Statement, aims to provide sufficient definition for Refrigerated Export Project (Method Statement for Switchgear recommissioning at Um-Qasr) Storage Terminal. Its intent is to also facilitate implementation in a safe and efficient manner and for all involved parties to understand the risks, roles and responsibilities associated with the Switchgear recommissioning at Um-Qasr.
2. Definitions COMPANY
BGC (Basra Gaz Company)
PROJECT
Refrigerated Export Project Electrical service &Distribution work at Um-Qasr.
CONTRACTOR
(IGCC) Iraq Gates Contracting Company
WORK
Shall mean all and any of the work andor services andor materials required to be provided by the CONTRACTOR under contract with COMPANY.
SHALL AND MUST
Indicates mandatory requirements.
SHOULD
Indicates that a provision is not mandatory but recommended as good practice.
3.
Abbreviations
Abbreviation
Definition
SOW
Scope of Work
BGC
Basra Gas Company
3 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement for Switchgear recommissioning at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
4. Methodology 4.1 Engineering Phase - Preparation and Submission of Method Statement. - Preparation and Submission of all HSE Deliverables.
4.2 Procurement Phase - N/A
4.3 Mobilization Phase - Transportation to site all Manpower & Equipment.
4.4 Prior to Start the Works - Having valid PTW with approved method statement. - Having TBT before start the work Explain the steps of work. - Area Barricaded with warning signs. - Only qualified team maintain these works. 4.4.2 Switchgear recommissioning: 4.4.2.1 Preparation Works: - Verify that each incoming cable that must have 0 voltage and all main incomers rack out. Using HV tester stick. - Prepare all related documents and approved by BGC. - Be sure that all grounding system tested and connected to main earthing grid. - Using earth stick that connected to trusted earthing system. - Be sure that all testing equipment's are connected to trusted earthing grid before start the test. - Be sure that all control signal that connected to main control room are disconnected avoiding the false operation.
4 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement for Switchgear recommissioning at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
- Test the main earthing grid before start commissioning activities to achieve Trusted grounding risers used during commissioning. - Be sure that all the area is surrounded by caution tape. - Take care of falling objects from height. - Use the right hand tools, Be sure that all tools are connected with Safe robe when we get working at height. - Using temporary indoor lighting near the SWGR.
5 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement for Switchgear recommissioning at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
4.4.2. Commissioning works: - Perform circuit breaker rack out and earthing switch in close position. - Clean all contact in C.B, ES. - Check the circuit breaker closing and opening, charging circuit, manually. - Perform the insulation resistance of circuit breaker according to: * Close position R ------ S, T, G to ground S ------- R, T, G to ground T ------- R, S, G to ground * Open position Ri, Si, Ti, ---------- Ro, So, To - Preform DC contact test for circuit breaker (closed position). Using primary injection current Omicron CPC100. - Perform control circuit cold loop check according to vendor drawing. - Perform the insulation resistance, continuity test for incoming and outgoing Cables. - Check the LCS cables insulation, continuity, functionally check. - Check all protection setting according to original setting document. Using secondary injection current Omicron CMC356. - Check all protection setting on PC1/PC1-1 and PC1-2. according to original setting document. - Perform primary injection test for current transformer located in motor side. 6 OF 7
IRAG GATES CONTRACTING COMPANY
Method Statement for Switchgear recommissioning at Um-Qasr XXXXXXXXXXXXX
Rev: A Doc. Cat.
EXT
- Perform secondary injection test for protection relay located in switchgear side. - Arrange all testing formats and necessary documents as hand over package. - Using inspected and green tag scaffolding.
5. MTO N/A
6. HSE Requirements
Site Induction.
Using LOTO for the Motors & SWGR.
Preparation of first aid kits and fire extinguishers for emergency case.
HITRA, JHA & PTW, including approved Method of Statements.
Ensure to connect a local earth equipment, if practicable. The case earth must remain connected to the system earth in order to maintain an acceptable single earth potential
PPE Requirement:
Use suitable barriers, barricades and warning signs on both sides of man lift to prevent access to the working zone by persons not involved. If there is any danger of exposing the public or staff to energized conductors or equipment a safety observer must be used.
Housekeeping.
7 OF 7