LEPCL 660MW CFPP, Karachi Project Contractor: SEPCOIII ELECTRIC POWER CONSTRUCTION CORPORATION., LTD.
Owner: Lucky Electric Power Company Limited
Consultant: FICHTNER GMBH & CO KG
Tr ans m it t a l F or m Transm ittal No: LEPCL-TR-SEPCO-FICHTNER-BOILER-00009 To
: FICHTNER
E-Mail
:
[email protected]
Attention
: M. Shakil Akhtar
Document No: LEPCL-10-ZZZ-MQA-20001-S01-D Date:
Subject
04-03-2019
: Submission of ITP for boiler steel structure and platform erection. New submittal
√
Re-submittal
MONTHLY REPORTS
CARGO DECLARATION
CONTRACTOR APPROVAL REQUEST
TEST REPORTS
VENDOR APPROVAL REQUEST
√
TECHNICAL SUBMITTAL
OTHERS
Type Of Activity.
ITP
Signature of
Description
FICHTNER/Consultant
Submission of ITP, checklist and report for boiler steel structure and platform erection
Remarks
Resident Engineer Approved / Not approved
Send by:
Department:
Date:
Received by:
Department:
Date: