Management of Medium-Size / Revamping Projects Oil & Gas Downstream Projects 10. Completion, Commissioning, Start-up
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
Management of Medium-Size / Revamping Projects: course content I.
Introduction
II.
Preliminary Studies
III. Basic Engineering (or FEED)
IV. EPC Contracting V.
Organization and Engineering
VI. Procurement VII. HSE, Quality and Risk Management
VIII. Project Control (cost/schedule) X.
Completion / Commissioning / Start-up / Closure
RC - PR GES - 08174_A_A - Rev.1 - 18/07/2013
© 2013 - IFP Training
IX. Construction and Fabrication Management
1
Scope and objectives
Scope: • Completion of all construction activities • Transfer to Owner Operating staff (who normally assures start-up) • Remaining activities until dismantling of the project team
Objectives: • Assure complete and satisfactory execution of project scope • Verify that Operations agree to take Ownership, and transfer it • Identify and implement post-completion project activities Technical (punch-list items resolution) Documentary (as built documents) Financial (claim settling, invoice payment) Managerial (feedback lessons)
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
− − − −
2
Completion activities
Provisional Acceptance
Routine operation START-UP COMMISSIONING EXECUTION PRECOMMISSIONING EXECUTION
CONSTRUCTION & PROCUREMENT
DETAILED ENGINEERING BASIC ENGINEERING
Preliminary and conceptual studies
Perf. Tests Ready for StartUp Mechanical Completion
© 2013 - IFP Training
Commissioning activities through Project phases and completion activities
3 RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
Operations
PROJECT Pre-Project
General preparation
Completion activities
PHASE
ACTIVITIES
MILESTONE
CONFORMITY CHECKS PRECOMMISSIONING
STATIC TESTING
MECHANICAL COMPLETION
FLUSHING & CLEANING ENERGIZATION DYNAMIC TESTS COMMISSIONING
EQUIPMENT RUNNING-IN
READY FOR START - UP
START UP OF UTILITIES TESTS OF SAFETY SYSTEMS
START – UP
BRINGING PLANT ON LINE PERFORMANCE TESTS
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
PROVISIONAL ACCEPTANCE
© 2013 - IFP Training
OIL & GAS IN
4
Completion activities Precommissioning - Commissioning
PRECOMMISSIONING or mechanical completion (unit non energized): • • • •
Visual inspection of equipment (Power Generation, motors, cables...). Quality of installation. Compliance with Project drawings and specifications. “Cold testing”: calibration of instruments, machinery alignment, setting of safety valves, pressure testing of piping... (De-energized tests). • Pipes and vessels air or water flushing and cleaning.
Normally, Project Team responsibility stops there (transfer to Ops)
COMMISSIONING: all activities carried-out before start-up (energized systems)
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
• Electrical motors uncoupled runs, instrument loops tests, electrical breakers operation... • Running-in and on-line tests of plant utilities, and main process equipment in closed loop (wherever applicable). • Piping drying out and leak testing, inerting or loading of various chemicals. • Tests of all safety systems (gas detection, fire water…).
5
System approach “From TRADE to SYSTEM approach”
CONSTRUCTION: organized and split by Trades, disciplines (Civil work, structural, piping, electricity, mechanical…).
Commissioning Activities & Start-up: by system function A system is a part of an Installation (built of various trades) that performs a given operational function such as: Safety system Instrument air Fire water Oil separation
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
• • • •
6
System approach Projet without system approach
Project Projet with system approach
TIME BENEFIT
System 1 System 2
System 3
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
Pre-Comm Comm Start-Up
7
System approach
Oil
Utility Water
Fuel Gas
Oil to Utilities
ExchA
ExchB
ExchC Heat A
Heat B
Drain
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
Sub-system break-down
8
System approach
VESSELS & PIPING INSTRUMENTS
ELECTRICAL PUMP
MOTOR
© 2013 - IFP Training
MECHANICAL
Sub-system and discipline RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
9
Precommissioning methodology
TASK
DISCIPLINE
NUMBER - 1 per item of equipment ( Field )
Conformity Checks
SUPPORT DOCUMENT - 1 Check List per type of equipment & subsystem (Field)
All - 1 Check List per package - 1 per package
- 1 List of checks in the Status Index
Static Tests
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
Process
- 1 per subsystem or Network or TestPack
- 1 Test Sheet per test - List of tests in the Status Index - Specific procedure & report
© 2013 - IFP Training
Flushing & Cleaning
All
- 1 test per specified item ( Field ) - 1 test per safety item ( Package )
10
Precommissioning methodology
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
Piping hydrotest sequence
11
Commissioning methodology
TASK
DISCIPLINE
Preliminary Checks
All
NUMBER - 1 per subsystem
- 1 per package
Functional Tests
Operational Tests
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
Test:multi-discipline
Process
- 1 test per Basic Function
- 1 task report form per subsystem + punch list items in Precomm. dossier
- 1 Functional Test Sheet List of tests in Technical Data Base
- 1 per subsystem or Network
- 1 operational Test Procedure by Subsystem, specific to the installation
- 1 per subsystem, or level of pressure, or main circuit
- Leak test, Inerting... reports, specific to the Installation
© 2013 - IFP Training
Pre-Start up Activities
Electrical Instruments Telecommunication
SUPPORT DOCUMENT
12
Commissioning methodology
System component: Basic Function • Item or group of items that performs an elementary function of the plant (ex: a pump) • It is the smallest item which can be submitted to energization in a Commissioning operation (ex: a switch) • e.g.: Switchboards, transformers, heaters, process control loops, loudspeaker loops, pumps, vessels, etc.
System: made of subsystem, themselves made of system component (ex: electrical power distribution) © 2013 - IFP Training
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
13
Commissioning Organization
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
Commissioning organization chart
14
Commissioning Organization EPCC contract
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
Split of Responsibility between Company and Contractor (TOTAL sample)
15
Commissioning Revamping Projects: specific aspects When several S/D: package-wise construction completion, precommissioning and commissioning and acceptance
At ea. main S/D facilities built during pre-shutdown & S/D will be started
Objective: as for construction, pre-commission / commission to largest extent before S/D in order to minimize S/D time
Job Cards system (refer construction section) define “systems” for ea. JC which are part of commissioning sub-systems: a commissioning sub-system includes several JCs.
Very detailed preparation & planning of commissioning together by Company / Contractor/ Sub-Contractors, and together with construction is necessary.
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
16
Commissioning Revamping Projects: specific aspects
Overall commissioning schedule packages-wise according to completion requirements & available S/Ds
Shut-Down commissioning schedule will include broadly 3 sequential stages, detailed by sub-systems: • Step 1 (normally all by Company Operations): decommissioning, emptying, inerting, install blinds, venting (as required) • Step 2 (by Contractor, with work duration guaranteed by him): works detailed by JCs including construction / pre-com (and, in parallel for maintenance works, by Company and /or possibly by S/D or Maintenance Contractor)
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
• Step 3 (normally all by Company Operations): inerting, remove blinds, filling, circulations as required (e.g. adsorbents), commissioning tests
17
Acceptance of Facilities
Construction and precommissioning
Ready for commissioning (mechanical completion)
Start-up and operation tests
commissioning
Ready for start-up
Performance tests
warranty period To Gas Injection Wells
Ready for performance tests
Provisional acceptance Provisional certificate acceptance
Final acceptance
Performance guarantees (capacity, products, utilities, global operability, possibly some packages and/or equipment…)
Performance Tests duration will depend on work scope
Mechanical Guarantee will start as soon as facilities are operated
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
18
Completion, Commissioning, Startup, Closure Key points to keep in mind
Medium-size and Revamp projects: Project Team stops at Completion
Problems at the Mechanical Completion stage may lead to trouble: • • • • •
Inadequate or incomplete scope execution Unknown needs of operational staff Absence of some As Built Documentation Lack of Start-Up spare parts Communication deficiencies
Commissioning and Start-up are normally done by Operations
The project is only complete when all financial matters are solved
Feedback lessons are important for Continuous Improvement
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2011 - IFP Training
• Invoices • Claims
19
Attachments I. Integrated Commissioning
© 2013 - IFP Training
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
20
Commissioning tool sample: ICAPS
© 2013 - IFP Training
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
21
Commissioning tool ICAPS PREPARATION
EXECUTION
PUNCH LIST
OPERCOM
FORMS
PROGRESS
ENGINEERING
REPORTING
Total use ICAPS … but some other software are used like WINPCS, … RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
POPULATION
22
Overall Sequence
© 2013 - IFP Training
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
23
Sequence & dossiers Precommissioning dossier Combined RFC Certificate
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
One Dossier Per Sub-System
24
Sequence & dossiers Commissioning dossier RFSU Dossier Index
RFSU Certificate
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
© 2013 - IFP Training
One Dossier Per Sub-System
25
Sequence & dossiers Hand-over dossier
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013
One Dossier Per Hand Over Unit
© 2013 - IFP Training
SUB SYSTEM ZZ
SUB SYSTEM YY
SUB SYSTEM XX
RFHO Certificate
26
Sequence & dossiers Overall dossiers
308m
273m
206 HOU Dossiers 849 RFSU Dossiers 891 RFC Dossiers 1,946 Dossiers © 2013 - IFP Training
RC - PR GES - 08176_A_A - Rev. 1 - 18/07/2013